Prior Review Thresholds I. Goods and Works and non-consulting services. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Procurement Method Prior Review Remarks Thresholds (Estimated Cost of the Contract/Package) Works (including turnkey, ICB, NCB, Direct >=US$ 10,000,000 supply & installation of Contract plant and equipment, and RFQ None PPP) Goods, information ICB, NCB, Direct >=US$ 2,000,000 technology and non- Contract consulting services RFQ None II. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of Procurement Procurement Method Prior Review Remarks Thresholds (Estimated Cost of the Contract/Package) Consultants: firms QCBS, QBS, FBS, >=US$ 1,000,000 CQS, Single Source Selection Consultants: Individual IC (Open, 3CV, or SSS) >=US$ 300,000 III. Short list comprising entirely of national consultants Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT Bangladesh : Bangladesh Urban Resilience Project PLAN General Information Country: Bangladesh Banks Approval Date of the Original Procurement Plan: 2017-02-23 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-12-25 Project ID: P149493 GPN Date: Project Name: Bangladesh Urban Resilience Project Loan / Credit No: IDA / 55990 Executing Agency(ies): Rajdhani Unnayan Kartripakhha, Department of Disaster Mangement, Dhaka North City Corporation, Project Coordination and Monitoring Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the URP/DDM/W-1 / Renovation of Countrys Emergency Request for Single Stage - One Pending the facility that would house IDA / 55990 Prior Open - National 701,300.00 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Management Response Proposals Envelope Implementation ERCC Capacity Component A: Reinforcing the URP/DDM/W-2 / Renovation of Countrys Emergency Request for Single Stage - One Pending the facility that would house IDA / 55990 Prior Open - National 467,530.00 0.00 2017-06-07 2017-06-12 2017-07-24 2017-08-23 2017-09-27 2018-03-26 Management Response Proposals Envelope Implementation NDMRTI Capacity Component B: Vulnerability URP/RAJUK/W-1A / Assessment of Critical and Construction of Shed ,Partition Essential Facilities Request for Single Stage - One Pending and supportive Accessories for IDA / 55990 Post Open - National 12,987.00 0.00 2018-01-01 2018-02-22 2018-03-24 Component C: Improved Quotations Envelope Implementation Accommodation of PIU Office Construction, Urban Planning, Security and Development URP-DNCC/W-3-4 / Erection Component A: Reinforcing the and Fabrication of Signboard at Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 8,750.00 0.00 2018-02-16 2018-04-30 2018-06-29 Emergency Warehouses of City Management Response Quotations Envelope Implementation Corporations Capacity URP-DNCC/W-3-5 / Erection Component A: Reinforcing the and Fabrication of Signboard at Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 8,750.00 0.00 2018-04-04 2018-06-16 2018-08-15 Emergency Warehouses of Management Response Quotations Envelope Implementation FSCD Capacity GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the URP/DDM/G-2 / Procurement of Countrys Emergency Request for Single Stage - One Pending 4 units Micro-bus for NDMRTI IDA / 55990 Post Open - National 233,000.00 0.00 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Management Response Proposals Envelope Implementation and ERCC Capacity URP-DNCC/G-1-1 / Procurement Component A: Reinforcing the of Specialized ICT Equipment Countrys Emergency Single Stage - One Under (VHF and HF Radio Terminals IDA / 55990 Prior Request for Bids Open - International 6,025,250.00 0.00 2017-05-14 2017-06-20 2017-05-19 2017-06-22 2017-07-18 2017-11-01 2017-12-13 2018-09-09 Management Response Envelope Implementation and Related Installations) for Capacity FSCD (Lot-1: VHF, Lot-2: HF) URP-DNCC/G-2-2 / Supply of Component A: Reinforcing the Specialized Search and Rescue Countrys Emergency Single Stage - One Under IDA / 55990 Prior Request for Bids Open - International 647,658.00 0.00 2017-05-14 2017-06-20 2017-05-19 2017-07-13 2017-08-02 2017-11-16 2017-11-20 2017-12-28 2018-09-24 Equipment (Water Rescue) for Management Response Envelope Implementation FSCD Capacity URP-DNCC/G-2-6 / Supply of Component A: Reinforcing the Specialized Search and Rescue Countrys Emergency Single Stage - One Under IDA / 55990 Prior Request for Bids Open - International 1,741,366.00 0.00 2017-05-30 2017-06-15 2017-06-04 2017-06-20 2017-08-18 2017-12-02 2018-01-13 2018-10-10 Equipment (Lot-1: Ambulance, Management Response Envelope Implementation Lot-2: Mortuary Van) Capacity Component A: Reinforcing the BD-DDM-15188-GO-RFP / Countrys Emergency Request for Single Stage - One Pending Procurement of Office Equipment IDA / 55990 Post Open - National 60,000.00 0.00 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Management Response Proposals Envelope Implementation for PIU, DDM Capacity BD-DDM-15189-GO-RFP / Component A: Reinforcing the Procurement of Computer and Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Open - National 26,000.00 0.00 2017-06-22 2017-06-27 2017-08-08 2017-09-07 2017-10-12 2018-04-10 related Equipment's for PIU, Management Response Proposals Envelope Implementation DDM Capacity Component A: Reinforcing the BD-DDM-15190-GO-RFP / Countrys Emergency Request for Single Stage - One Pending Procurement of Mobile Phone IDA / 55990 Post Limited 2,500.00 0.00 2017-06-08 2017-06-13 2017-07-25 2017-08-24 2017-09-28 2018-03-27 Management Response Proposals Envelope Implementation etc. for PIU, DDM Capacity Component A: Reinforcing the BD-DDM-15191-GO-RFP / Countrys Emergency Request for Single Stage - One Pending Procurement of Office Furniture IDA / 55990 Post Open - National 20,000.00 0.00 2017-06-29 2017-07-04 2017-08-15 2017-09-14 2017-10-19 2018-04-17 Management Response Proposals Envelope Implementation for PIU, DDM Capacity BD-DDM-15192-GO-RFP / Component A: Reinforcing the Procurement of Telecom Countrys Emergency Request for Single Stage - One Pending IDA / 55990 Post Limited 6,500.00 0.00 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 Equipment's (Land Telephone, Management Response Proposals Envelope Implementation PABX system etc) for PIU, DDM. Capacity Component D: Project URP-PCMU/G-7 / Procurement Single Stage - One Pending IDA / 55990 Coordination, Monitoring, and Post Request for Bids Open - National 116,000.00 0.00 2017-05-21 2017-05-21 2017-06-12 2017-06-26 2017-07-25 2017-08-27 of Vehicles Envelope Implementation Evaluation Component A: Reinforcing the URP-DNCC/G-4-3 / Procurement Countrys Emergency Single Stage - One Under IDA / 55990 Post Request for Bids Open - National 12,500.00 0.00 2017-09-10 2017-09-25 2017-10-25 2017-12-09 2018-01-20 2018-04-20 of Motor Cycle Management Response Envelope Implementation Capacity Page 1 Component A: Reinforcing the URP-DNCC/G-2-7 / Procurement Countrys Emergency Single Stage - One Pending of Search and Rescue IDA / 55990 Post Request for Bids Open - National 148,600.00 0.00 2017-09-20 2017-10-05 2017-11-19 2018-01-18 2018-03-08 2018-09-04 Management Response Envelope Implementation Equipment for City Corporations Capacity Component A: Reinforcing the URP-DNCC/G-2-3 / Specialized Countrys Emergency Single Stage - One Under Search and Rescue Equipment IDA / 55990 Prior Request for Bids Open - International 2,053,488.00 0.00 2017-09-20 2017-09-20 2017-10-05 2017-11-28 2017-12-04 2018-04-03 2018-05-15 2019-01-10 Management Response Envelope Implementation (Breathing Apparatus Tenders) Capacity URP-DNCC/G-1-2 / Procurement of Specialized ICT Equipment Component A: Reinforcing the (VHF and HF Radio Terminals Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 2,401,700.00 0.00 Under Review 2017-07-16 2017-08-10 2017-07-31 2017-09-29 2018-01-27 2018-03-26 2018-09-22 and Related Installations) for City Management Response Envelope Corporation Capacity (Lot-1: VHF, Lot-2: HF) URP-DNCC/G-1-3 / Procurement Component A: Reinforcing the of Specialized ICT Equipment Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - International 653,000.00 0.00 2017-12-24 2018-01-08 2018-03-19 2018-07-03 2018-08-14 2019-02-10 (UHF Radio Terminals and Management Response Envelope Implementation Related Installations) for DSCC Capacity URP-DNCC/G-3 / Procurement Component A: Reinforcing the of Heavy Equipment (Lot-1: Countrys Emergency Single Stage - One Crane, Lot-2: Wheel Type IDA / 55990 Prior Request for Bids Open - International 5,250,000.00 2,552,248.05 Signed 2017-08-24 2017-08-27 2017-10-08 2017-02-27 2017-12-07 2017-09-13 2018-02-03 2017-10-29 2018-10-01 Management Response Envelope Excavator, Lot-3: Chain Type Capacity Excavator, Lot-4: Dozer) URP-DNCC/G-2-1 / Procurement Component A: Reinforcing the of Specialized Search and Countrys Emergency Single Stage - One IDA / 55990 Prior Request for Bids Open - International 12,000,000.00 6,856,362.37 Signed 2017-08-22 2017-08-25 2017-08-17 2017-10-06 2017-08-17 2017-10-09 2017-08-20 2017-10-15 2017-07-11 2018-12-09 Rescue Equipment (Emergency Management Response Envelope Tenders) for FSCD. Capacity Component A: Reinforcing the URP-DNCC/G-2-4 / Specialized Countrys Emergency Single Stage - One Under Search and Rescue Equipment IDA / 55990 Prior Request for Bids Open - International 2,818,100.00 0.00 2017-09-25 2017-10-09 2017-10-10 2017-12-21 2017-12-09 2018-04-08 2018-05-20 2019-01-15 Management Response Envelope Implementation (Personal Protective Equipment) Capacity Component A: Reinforcing the URP-DNCC/G-2-8 / Rescuer Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 611,220.00 0.00 2017-10-01 2017-10-16 2017-11-27 2018-03-27 2018-05-08 2018-11-04 Carrying Vehicle (7.5 Ton Truck) Management Response Envelope Implementation Capacity Component B: Vulnerability URP/RAJUK/G-1A / Mail domain Assessment of Critical and and its accessories purhase & Essential Facilities Request for Single Stage - One Pending IDA / 55990 Post Open - National 6,490.00 0.00 2017-09-21 2017-09-21 2017-09-21 installation for Emergecy Office Component C: Improved Quotations Envelope Implementation use of PIU, Construction, Urban Planning, and Development Component A: Reinforcing the URP-DNCC/G-2-5 / Specialized Countrys Emergency Single Stage - One Pending Search and Rescue Equipment IDA / 55990 Post Request for Bids Open - National 27,450.00 0.00 2018-01-21 2018-02-05 2018-03-19 2018-06-02 2018-07-08 2019-01-04 Management Response Envelope Implementation (Rescuer Tools- Drone) for FSCD Capacity NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the URP-DNCC/NS-2 / Selection of Countrys Emergency Single Stage - One Pending Clearing and Forwarding Agent IDA / 55990 Post Request for Bids Open - National 468,750.00 0.00 2017-09-17 2017-10-02 2017-11-16 2017-12-31 2018-02-11 2020-12-27 Management Response Envelope Implementation (Firm) Capacity Component A: Reinforcing the URP-DNCC/NS-1 / Selection of Countrys Emergency Single Stage - One Pending IDA / 55990 Post Request for Bids Open - National 81,250.00 0.00 2017-08-20 2017-09-04 2017-10-19 2017-12-03 2018-01-14 2020-12-29 Pre-Shipment Inspection Firm Management Response Envelope Implementation Capacity CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual URP/RAJUK/S-6 / Consultancy Component C: Improved Quality And Cost- Under Services for Operationalizing the IDA / 55990 Construction, Urban Planning, Prior Open - International 3,522,730.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2017-10-20 2017-12-01 2018-02-16 2018-03-23 2020-06-30 Based Selection Implementation URU in RAJUK and Development URP/RAJUK/S-7 / Assessing the Current State and Deploying Component C: Improved a Web-based Integrated Quality And Cost- Under IDA / 55990 Construction, Urban Planning, Prior Open - International 1,998,260.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2017-10-20 2017-12-01 2018-02-16 2018-03-23 2020-06-30 Information Management System Based Selection Implementation and Development for the Construction Permit System of RAJUK URP/RAJUK/S-8 / Consultancy Component C: Improved Quality And Cost- Under Services for Professional IDA / 55990 Construction, Urban Planning, Prior Open - International 3,542,210.00 0.00 2017-05-15 2017-06-05 2017-07-20 2017-08-25 2017-10-20 2017-11-19 2018-03-04 2018-04-08 2020-06-30 Based Selection Implementation Accreditation Program in RAJUK and Development URP/DDM/S-3 / Procurement of Consultancy Services for Training Exercises and Drills (TED) Program for the MoDMR, FSCD , Component E: Contingent Quality Based Under DNCC, DSCC & SCC and related IDA / 55990 Prior Open - International 10,000,000.00 0.00 2017-05-14 2017-05-14 2017-06-28 2017-07-12 2017-07-26 2017-08-02 2017-09-06 2020-02-23 Emergency Response Selection Implementation institutions of the Government of Bangladesh involved in the Disaster Risk Management of Dhaka and Sylhet URP-PCMU/S-1 / Monitoring Component D: Project Quality And Cost- Pending and Evaluation Consultancy IDA / 55990 Coordination, Monitoring, and Prior Open - International 2,160,493.00 0.00 2017-05-21 2017-05-21 2017-05-21 2017-06-04 2017-07-15 2017-09-01 2017-10-15 2020-06-30 Based Selection Implementation through a Firm Evaluation Page 2 Component D: Project URP-PGMU/S-2 / Internal Audit Quality And Cost- Pending IDA / 55990 Coordination, Monitoring, and Prior Open - National 121,950.00 0.00 2017-05-21 2017-05-21 2017-07-15 2017-08-14 2017-08-30 2017-10-07 2017-11-11 2018-11-11 through a Firm Based Selection Implementation Evaluation URP/RAJUK/S-5 / Consultancy Component B: Vulnerability Services for Development of a Quality And Cost- Pending IDA / 55990 Assessment of Critical and Prior Open - International 6,296,550.00 0.00 2017-10-04 2017-10-04 2017-10-18 2017-11-15 2018-02-13 2018-03-27 2018-05-01 2020-06-30 Risk-sensitive Land Use Planning Based Selection Implementation Essential Facilities Practice for URU URP/RAJUK/S-11 / Consultancy Services for Design and Supervision of Urban Resilience Component B: Vulnerability Quality And Cost- Pending Unit (URU) Building including IDA / 55990 Assessment of Critical and Prior Open - International 2,425,950.00 0.00 2017-10-04 2017-10-04 2017-10-18 2017-11-15 2018-02-13 2018-03-27 2018-05-01 2020-06-30 Based Selection Implementation Research, Training, and Testing Essential Facilities Laboratory facilities under RAJUK in Dhaka, Bangladesh BD-DDM-28928-CS-QBS / Selection of Consulting Services Component A: Reinforcing the Consultant on "Design and Supervision Countrys Emergency Under IDA / 55990 Post Qualification Open - National 37,500.00 0.00 2017-09-21 2017-10-04 2017-10-12 2017-11-25 2017-12-25 2018-01-29 2018-07-28 consultancy" for outfit NDMRTI & Management Response Implementation Selection ERCC Facilities in Dhaka and Capacity Sylhet URP/RAJUK/S-9 / Consultancy Component C: Improved Quality And Cost- Pending Services for Building Code IDA / 55990 Construction, Urban Planning, Prior Open - International 3,240,260.00 0.00 2017-09-21 2017-09-21 2017-11-09 2017-12-21 2018-03-21 2018-05-09 2018-06-13 2020-06-30 Based Selection Implementation Enforcement and Development URP/RAJUK/S-4 / Consultancy Services for Vulnerability Component B: Vulnerability Quality And Cost- Under Assessment and Prioritized IDA / 55990 Assessment of Critical and Prior Open - International 6,781,520.00 0.00 2017-09-21 2017-09-21 2017-10-05 2017-11-02 2018-01-31 2018-03-14 2018-04-18 2020-06-30 Based Selection Implementation Investment Plan for Critical Essential Facilities Assets in Dhaka for URU BD-DDM-29946-CS-QBS / Component A: Reinforcing the Consultancy Services for Training Countrys Emergency Quality And Cost- Under IDA / 55990 Prior Open - International 10,000,000.00 0.00 2017-09-25 2017-10-02 2017-10-16 2017-10-09 2017-11-29 2017-12-27 2018-01-26 2018-03-02 2018-04-06 2019-04-06 Exercises and Drills (TED) Management Response Based Selection Implementation Program Capacity INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project Individual Consultant S1 / Procurement Specialist IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response S2 / Senior Financial Component D: Project Individual Consultant Management & Planning IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 285,867.35 Signed 2016-04-28 2016-05-05 Selection Specialist Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project URP-DDM-1/ S1 / Procurement Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 56,452.65 Signed 2016-05-24 2016-05-26 Specialist (Individual) Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP-DDM-1/ S2 / Financial Component D: Project Individual Consultant Management Specialist IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 54,164.03 Signed 2016-05-24 2016-05-26 Selection (Individual) Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Page 3 Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP-DNCC/S-4 / International Component D: Project Consultant: Information & Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 304,430.00 304,430.00 Signed 2016-05-05 2016-06-01 Communication Technology (ICT) Selection Evaluation Specialist Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response URP- DNCC/ S-1 / Individual Component D: Project Individual Consultant Consultant as Procurement IDA / 55990 Coordination, Monitoring, and Prior Open N 0.00 226,765.77 Signed 2016-08-01 2016-04-20 Selection Specialist (National) Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities Component A: Reinforcing the Countrys Emergency Management Response Capacity Component E: Contingent Emergency Response Component D: Project URP-DNCC/S-3 / International Individual Consultant IDA / 55990 Coordination, Monitoring, and Prior Open N 383,300.00 383,300.00 Signed 2016-05-10 2016-06-01 Search and Rescue Expert Selection Evaluation Component C: Improved Construction, Urban Planning, and Development Component B: Vulnerability Assessment of Critical and Essential Facilities URP-DNCC/S-2 / Individual Component A: Reinforcing the Consultant as Financial Countrys Emergency Individual Consultant Under IDA / 55990 Prior Open 210,000.00 0.00 2017-08-15 2017-06-20 2017-11-28 2017-12-13 2018-01-18 2020-12-31 Management and Planning Management Response Selection Implementation Specialist (National) Capacity Component A: Reinforcing the URP-DNCC/S-5-3 / Procurement Countrys Emergency Individual Consultant Under IDA / 55990 Post Open 14,100.00 0.00 2017-05-14 2017-07-27 2017-08-17 2017-09-21 2018-03-20 of Junior Procurement Consultant Management Response Selection Implementation Capacity Component D: Project URP-PCMU/S-5 / Financial Individual Consultant Pending IDA / 55990 Coordination, Monitoring, and Prior Open 219,500.00 0.00 2017-05-21 2017-05-21 2017-05-28 2017-07-16 2018-07-15 Management Specialist Selection Implementation Evaluation Component D: Project URP-PCMU/S-10 / Procurement Individual Consultant Pending IDA / 55990 Coordination, Monitoring, and Prior Open 65,850.00 0.00 2017-05-21 2017-05-21 2017-05-21 2017-05-21 2017-10-29 Consultant (National) Selection Implementation Evaluation Page 4