STRENGTHENING THE SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM IN PERU(P156250) - BIRF 8682 – PE PROCUREMENT PLAN I. General 1. Bank’s approval Date of the procurement Plan: 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: Until Dec 31, 2017 July 9, 2010 PROCUREMENT Peru : Strengthening the Science, Technology and Innovation System in Peru PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2017-09-21 2019-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156250 GPN Date: 2017-09-21 Project Name: Strengthening the Science, Technology and Innovation System in Peru Loan / Credit No: IBRD / 86820 Executing Agency(ies): Fondo Nacional de Desarrollo Cientifico, Tecnologico y de Innovación Tecnológica WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-FONDECYT-57366-GO- RFQ / Adquisición de Project Management and Solicitud de Single Stage - One equipos de computo y IBRD / 86820 Posterior Limited 49,500.00 39,189.82 Finalizado 2018-04-12 2018-04-25 2018-05-25 Monitoring & Evaluation cotizaciones Envelope licencias para la Gestión Administrativa del Proyecto PE-FONDECYT-87591-GO- Improving the Institutional RFQ / Adquisición de Solicitud de Single Stage - One IBRD / 86820 Framework of the National Posterior Limited 48,000.00 0.00 En ejecución 2018-12-01 2018-12-14 2019-01-13 equipos de laptops y PCs cotizaciones Envelope STI System para monitores y la DPP PE-FONDECYT-70409-GO- RFQ / Adquisición de equipos audiovisuales, Project Management and Solicitud de Single Stage - One Ejecución IBRD / 86820 Posterior Limited 20,000.00 0.00 2019-04-08 2019-06-03 2020-03-29 fotográficos y otros Monitoring & Evaluation cotizaciones Envelope pendiente accesorios de cómputo para el proyecto PE-FONDECYT-59689-GO- RFQ / Adquisición de Project Management and Solicitud de Single Stage - One Ejecución Mobiliario para las oficinas IBRD / 86820 Posterior Limited 10,000.00 0.00 2019-04-07 2019-04-19 2019-05-15 Monitoring & Evaluation cotizaciones Envelope pendiente del equipo de Gestión Administrativa del Proyecto PE-FONDECYT-59685-GO- RFQ / Adquisición de Caja Project Management and Solicitud de Single Stage - One Ejecución Fuerte para el equipo de IBRD / 86820 Posterior Limited 2,500.00 0.00 2019-04-08 2019-04-21 2019-05-16 Monitoring & Evaluation cotizaciones Envelope pendiente Tesorería de la Gestión Administrativa del Proyecto PE-FONDECYT-34224-GO- RFB / Adquisición de equipos de cómputo para la Improving the Institutional adecuación de la Solicitud de Single Stage - One Ejecución IBRD / 86820 Framework of the National Posterior Open - National 406,969.00 0.00 2019-04-08 2019-04-13 2019-05-13 2019-05-20 2019-05-25 2019-07-13 infraestructura tecnológica ofertas Envelope pendiente STI System del sistema de Gestión de CONCYTEC y FONDECYT (Componentes 1.2.2 y 4) PE-FONDECYT-88715-GO- Research and Innovation Solicitud de Open - Single Stage - One RFB / Adquisición de IBRD / 86820 Previa 6,700,000.00 0.00 Cancelado 2018-12-21 2018-12-26 2019-02-06 2019-03-08 2019-04-12 2019-10-09 Capacity ofertas International Envelope equipos de laboratorio PE-FONDECYT-120650-GO- RFQ / Adquisición de Project Management and Solicitud de Single Stage - One Ejecución mobiliario para sala de usos IBRD / 86820 Posterior Limited 36,239.00 0.00 2019-06-29 2019-08-24 2020-02-20 Monitoring & Evaluation cotizaciones Envelope pendiente múltiples del local de San Borja. PE-FONDECYT-120679-GO- RFQ / Suministro e instalacion de equipos de Project Management and Solicitud de Single Stage - One Ejecución IBRD / 86820 Posterior Limited 48,000.00 0.00 2019-06-29 2019-08-24 2020-02-20 aire acondicionado para la Monitoring & Evaluation cotizaciones Envelope pendiente sala de usos múltiples del local de San Borja. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strategic Programs: PE-FONDECYT-15888-NC- Productivity & Innovation RFQ / Eventos de Solicitud de Single Stage - One IBRD / 86820 Fund and Competitiveness Posterior Open - National 25,000.00 6,029.63 Finalizado 2018-02-10 2018-03-04 2018-03-19 lanzamiento del Proyecto cotizaciones Envelope Reinforcement Initiatives 2018 for Productive Innova tion PE-FONDECYT-55194-NC- RFQ / Operador logístico Improving the Institutional para la producción y Solicitud de Single Stage - One IBRD / 86820 Framework of the National Posterior Open - National 49,200.00 49,615.60 Finalizado 2018-04-30 2018-05-14 2018-06-30 organización del Congreso cotizaciones Envelope STI System Nacional de Gestión de la Información en CTI PE-FONDECYT-34233-NC- RFB / Agencia Research and Innovation Solicitud de Open - Single Stage - One Administradora de recursos IBRD / 86820 Previa 4,524,800.00 0.00 Cancelado 2018-02-22 2018-02-27 2018-04-10 2018-05-10 2018-06-14 2021-12-31 Capacity ofertas International Envelope de las subvenciones para investigadores PE-FONDECYT-73920-NC- Strategic Programs: RFQ / Servicio de Productivity & Innovation producción para el evento Solicitud de Single Stage - One IBRD / 86820 Fund and Competitiveness Posterior Limited 35,800.00 18,487.97 Finalizado 2018-08-20 2018-09-09 2018-10-09 de lanzamiento de las cotizaciones Envelope Reinforcement Initiatives iniciativas vinculación for Productive Innova tion academia industria PE-FONDECYT-73750-NC- DIR / Acceso a base de Improving the Institutional Adquisición datos bibliográficos de IBRD / 86820 Framework of the National Previa Direct 6,629,238.20 4,479,215.00 Firmado 2018-08-20 2018-10-04 2018-11-08 2022-02-09 directa revistas científicas STI System especializadas Page 1 PE-FONDECYT-63421-NC- RFB / SERVICIOS DE OPERACIÓN LOGÍSTICA PARA EL CUMPLIMIENTO DE LAS ACTIVIDADES Improving the Institutional Solicitud de Single Stage - One QUE SE REALICEN EN IBRD / 86820 Framework of the National Posterior Open - National 490,000.00 0.00 Cancelado 2018-09-10 2018-09-15 2018-10-15 2018-10-22 2018-11-12 2020-12-21 ofertas Envelope EL MARCO DEL STI System PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DEL SINACYT. PE-FONDECYT-77293-NC- RFQ / Organización y ejecución del Taller de Improving the Institutional Solicitud de Single Stage - One Estándares de IBRD / 86820 Framework of the National Posterior Limited 49,500.00 18,563.15 Firmado 2018-09-15 2018-10-20 2018-11-19 cotizaciones Envelope Representación de la STI System Información sobre Investigación PE-FONDECYT-79614-NC- RFQ / SERVICIO PARA LA ORGANIZACIÓN Y EJECUCION DEL TALLER Improving the Institutional Solicitud de Single Stage - One "LÍNEA DE BASE DEL IBRD / 86820 Framework of the National Posterior Limited 49,000.00 16,751.75 Firmado 2018-10-03 2018-10-21 2018-11-15 cotizaciones Envelope GASTO PÚBLICO EN STI System CIENCIA TECNOLOGÍA E INNOVACION (CTI) EN EL PERU" PE-FONDECYT-73752-NC- RFB / Desaarrollo de la Improving the Institutional Solicitud de Open - Single Stage - One plataforma de gestión del IBRD / 86820 Framework of the National Previa 900,000.00 0.00 En ejecución 2019-03-07 2019-03-12 2019-04-23 2019-04-30 2019-05-21 2020-05-20 ofertas International Envelope conocimiento del STI System CONCYTEC PE-FONDECYT-67001-NC- RFQ / Agenciamiento de pasajes aéreos nacionales e Project Management and Solicitud de Single Stage - One Ejecución internacionales para el IBRD / 86820 Posterior Open - National 48,000.00 0.00 2019-03-19 2019-05-07 2020-05-06 Monitoring & Evaluation cotizaciones Envelope pendiente Proyecto Ampliación y Mejoramiento de los Servicios del SINACYT PE-FONDECYT-59697-NC- RFQ / Servicio de adecuación de la red e Project Management and Solicitud de Single Stage - One Ejecución IBRD / 86820 Posterior Limited 20,000.00 0.00 2019-04-15 2019-04-29 2019-05-22 instalaciones informáticas Monitoring & Evaluation cotizaciones Envelope pendiente para la oficina Gestión Administrativa del Proyecto. PE-FONDECYT-59698-NC- RFQ / Servicio de Línea Dedicada para acceso a Project Management and Solicitud de Single Stage - One Ejecución IBRD / 86820 Posterior Limited 20,000.00 0.00 2019-04-23 2019-05-10 2020-05-29 internet para la Oficina de Monitoring & Evaluation cotizaciones Envelope pendiente Gestión Administrativa del Proyecto PE-FONDECYT-34198-NC- RFB / Adecuación de la Improving the Institutional Solicitud de Single Stage - One Ejecución infraestructura tecnológica IBRD / 86820 Framework of the National Posterior Open - National 100,000.00 0.00 2019-04-04 2019-04-07 2019-05-07 2019-05-12 2019-05-16 2019-07-01 ofertas Envelope pendiente del sistema de Gestión del STI System CONCYTEC PE-FONDECYT-55683-NC- RFQ / Alquiler de local Improving the Institutional Solicitud de Single Stage - One Ejecución para el desarrollo software IBRD / 86820 Framework of the National Posterior Open - National 49,000.00 0.00 2019-04-06 2019-04-29 2021-04-28 cotizaciones Envelope pendiente de Línea de Base y gestión STI System administrativa. PE-FONDECYT-34404-NC- Improving the Institutional Solicitud de Single Stage - One Ejecución RFQ / Modelado del proceso IBRD / 86820 Framework of the National Posterior Open - National 14,545.00 0.00 2019-04-30 2019-06-25 2019-09-23 cotizaciones Envelope pendiente de software STI System PE-FONDECYT-34407-NC- Improving the Institutional RFQ / Servicio en la nube Solicitud de Single Stage - One Ejecución IBRD / 86820 Framework of the National Posterior Open - National 36,364.00 0.00 2019-04-27 2019-06-22 2020-03-18 para el almacenamiento de cotizaciones Envelope pendiente STI System datos Strategic Programs: PE-FONDECYT-15890-NC- Productivity & Innovation Solicitud de Single Stage - One Ejecución RFQ / Publicaciones de IBRD / 86820 Fund and Competitiveness Posterior Open - National 20,000.00 0.00 2019-04-30 2019-06-06 2020-06-05 cotizaciones Envelope pendiente avisos en los diarios Reinforcement Initiatives for Productive Innova tion PE-FONDECYT-33456-NC- Research and Innovation Solicitud de Single Stage - One Ejecución RFQ / Promoción y difusión IBRD / 86820 Posterior Limited 50,000.00 0.00 2019-05-01 2019-06-26 2019-12-23 Capacity cotizaciones Envelope pendiente para los concursos PE-FONDECYT-109642-NC- RFQ / SERVICIO DE PLANO DE REPLANTEO Project Management and Solicitud de Single Stage - One Ejecución IBRD / 86820 Posterior Limited 2,000.00 0.00 2019-05-01 2019-06-26 2019-12-23 DETALLADO DE SALA DE Monitoring & Evaluation cotizaciones Envelope pendiente USOS MÚLTIPLES DE LOCAL DE SAN BORJA PE-FONDECYT-120675-NC- RFQ / Mejoramiento de Project Management and Solicitud de Single Stage - One Ejecución ambiente para la sala de IBRD / 86820 Posterior Limited 48,326.00 0.00 2019-06-29 2019-08-24 2020-02-20 Monitoring & Evaluation cotizaciones Envelope pendiente usos múltiples del local de San Borja. PE-FONDECYT-125745-NC- RFQ / CONTRATACIÓN Improving the Institutional DE SERVICIO PARA LA Solicitud de Single Stage - One IBRD / 86820 Framework of the National Posterior Limited 50,000.00 0.00 En ejecución 2019-10-21 2020-10-20 PRODUCCIÓN DEL cotizaciones Envelope STI System EVENTO "ENTRE PARES PERÚ 2019" PE-FONDECYT-125786-NC- RFQ / CONTRATACIÓN DE SERVICIO DE Improving the Institutional TRASLADO Y Solicitud de Single Stage - One IBRD / 86820 Framework of the National Posterior Limited 50,000.00 0.00 En ejecución 2019-10-21 2020-10-20 ALOJAMIENTO DE cotizaciones Envelope STI System PONENTES PARA EL EVENTO "ENTRE PARES PERÚ 2019" PE-FONDECYT-124582-NC- RFB / CONTRATACIÓN DEL SERVICIO DE Improving the Institutional Solicitud de Single Stage - One GESTIÓN DE PONENTES IBRD / 86820 Framework of the National Posterior Open - National 50,000.00 0.00 Cancelado 2019-07-30 2019-09-24 2020-03-22 cotizaciones Envelope Y PARTICIPANTES PARA STI System EL EVENTO "ENTRE PARES PERÚ 2019" Page 2 PE-FONDECYT-128063-NC- RFQ / SERVICIO DE COORDINACIÓN Y ACOMPAÑAMIENTO EN MATERIA MIGRATORIA Y Improving the Institutional TRIBUTARIA PARA Solicitud de Single Stage - One Ejecución IBRD / 86820 Framework of the National Posterior Limited 8,000.00 0.00 2019-08-24 2019-10-19 2020-04-16 EXTRANJEROS CUYOS cotizaciones Envelope pendiente STI System PROYECTOS RESULTEN GANADORES DEL CONCURSO DE INCORPORACIÓN DE INVESTIGADORES. PE-FONDECYT-128064-NC- RFQ / SERVICIO DE SOPORTE TÉCNICO EN MATERIA MIGRATORIA Y TRIBUTARIA PARA Research and Innovation Solicitud de Single Stage - One Ejecución EXTRANJEROS CUYOS IBRD / 86820 Posterior Limited 2,700.00 0.00 2019-08-24 2019-10-19 2020-04-16 Capacity cotizaciones Envelope pendiente PROYECTOS RESULTEN GANADORES DEL CONCURSO DE INCORPORACIÓN DE INVESTIGADORES. PE-FONDECYT-128169-NC- RFQ / SERVICIO DE ARRENDAMIENTO DE INMUEBLE PARA EL DESARROLLO DE LAS Project Management and Solicitud de Single Stage - One Ejecución ACTIVIDADES DEL IBRD / 86820 Posterior Limited 10,000.00 0.00 2019-10-19 2019-10-31 2021-10-31 Monitoring & Evaluation cotizaciones Envelope pendiente EQUIPO IMPLEMENTADOR Y OTROS DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strategic Programs: PE-FONDECYT-15886-CS- Productivity & Innovation Selección basada Ejecución LCS / Evaluación de IBRD / 86820 Fund and Competitiveness Posterior en el menor Open - National 151,515.00 0.00 2020-04-23 2020-05-14 2020-06-27 2020-07-25 2020-08-24 2020-09-28 2020-11-02 2021-01-31 pendiente Resultados del Proyecto Reinforcement Initiatives costo for Productive Innova tion PE-FONDECYT-15826-CS- QCBS / Capacitación en metodología de análisis del Improving the Institutional Selección basada gasto público (PER) - IBRD / 86820 Framework of the National Previa en calidad y Open - National 259,500.00 0.00 Cancelado 2017-12-15 2018-01-05 2018-02-18 2018-03-18 2018-04-17 2018-05-22 2018-06-26 2019-03-19 Operador que realizará los STI System costo 3 Talleres de capacitación 2018-2019 PE-FONDECYT-15701-CS- QCBS / Diagnóstico y planificación de definición Improving the Institutional Selección basada Open - de politicas, de la IBRD / 86820 Framework of the National Posterior en calidad y 405,000.00 0.00 Cancelado 2019-01-04 2019-01-25 2019-03-10 2019-04-07 2019-05-07 2019-06-11 2019-07-16 2020-01-15 International coordinación STI System costo interinstitucional y la regulación del sistema I+D+i PE-FONDECYT-15828-CS- Improving the Institutional Selección basada QCBS / Capacitación en IBRD / 86820 Framework of the National Posterior en calidad y Open - National 270,000.00 0.00 Cancelado 2021-02-10 2021-03-03 2021-04-16 2021-05-14 2021-06-13 2021-07-18 2021-08-22 2021-12-23 monitoreo y evaluación STI System costo (incluye certificación) PE-FONDECYT-73861-CS- Strategic Programs: CQS / Servicio de expositor Productivity & Innovation Selección basada para el evento de IBRD / 86820 Fund and Competitiveness Posterior en calificaciones Open - National 22,336.00 26,357.07 Finalizado 2018-08-14 2018-08-28 2018-09-03 2018-09-06 2018-09-12 2018-10-12 lanzamiento de las Reinforcement Initiatives de consultores iniciativas de vinculación for Productive Innova tion academia-industria PE-FONDECYT-75202-CS- QCBS / Servicio de Strategic Programs: capacitación, Productivity & Innovation Selección basada acompañamiento y Open - IBRD / 86820 Fund and Competitiveness Previa en calidad y 2,500,000.00 0.00 Bajo Revision 2018-09-06 2018-09-27 2018-10-11 2018-11-25 2018-12-02 2018-12-16 2019-01-13 2020-09-24 asistencia técnica para la International Reinforcement Initiatives costo formulación e identificación for Productive Innova tion de las iniciativas de vinculación academia industria (IVAI) Strategic Programs: PE-FONDECYT-15884-CS- Productivity & Innovation Selección basada LCS / Línea de Base del IBRD / 86820 Fund and Competitiveness Posterior en el menor Open - National 106,061.00 0.00 Cancelado 2018-02-09 2018-03-02 2018-04-15 2018-05-13 2018-06-12 2018-07-17 2018-08-21 2018-11-19 Proyecto Reinforcement Initiatives costo for Productive Innova tion PE-FONDECYT-88728-CS- QCBS / ESTUDIO DE LINEA DE BASE Y Strategic Programs: SISTEMA DE Productivity & Innovation Selección basada SEGUIMIENTO DE IBRD / 86820 Fund and Competitiveness Posterior en calidad y Open - National 151,600.00 0.00 En ejecución 2018-12-07 2018-12-28 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 INDICADORES PARA EL Reinforcement Initiatives costo PROYECTO for Productive Innova tion MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DEL SINACYT Strategic Programs: PE-FONDECYT-68643-CS- Productivity & Innovation Selección basada LCS / Diseño de la Ejecución IBRD / 86820 Fund and Competitiveness Posterior en el menor Open - National 110,000.00 0.00 2019-04-01 2019-04-15 2019-04-29 2019-05-27 2019-06-03 2019-06-17 2019-07-15 2020-01-11 estrategia comunicacional pendiente Reinforcement Initiatives costo del componente 2 for Productive Innova tion PE-FONDECYT-52154-CS- QCBS / Servicio para el control de calidad del Improving the Institutional Selección basada Ejecución código del software para las IBRD / 86820 Framework of the National Posterior en calidad y Open - National 250,000.00 0.00 2019-04-01 2019-04-15 2019-05-13 2019-06-12 2019-06-26 2019-07-24 2019-08-21 2020-08-20 pendiente Líneas de Bases regionales, STI System costo presupuesto público y de vigilacia de I+D+i PE-FONDECYT-15713-CS- Improving the Institutional Selección basada QCBS / Línea de base para IBRD / 86820 Framework of the National Posterior en calidad y Open - National 270,000.00 0.00 En ejecución 2019-04-18 2019-05-09 2019-06-22 2019-07-20 2019-08-19 2019-09-23 2019-10-28 2020-03-17 seguimiento de gasto STI System costo público PE-FONDECYT-15707-CS- QCBS / Análisis de la Improving the Institutional Selección basada Ejecución Gobernanza de las IBRD / 86820 Framework of the National Posterior en calidad y Open - National 180,000.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 pendiente instituciones que participan STI System costo en el sistema de CTI Page 3 PE-FONDECYT-15709-CS- QCBS / Diseño de un Improving the Institutional Selección basada Ejecución sistema de análisis y IBRD / 86820 Framework of the National Posterior en calidad y Open - National 276,061.00 0.00 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-11-04 pendiente seguimiento del gasto STI System costo público en CTI PE-FONDECYT-15712-CS- Improving the Institutional Selección basada Ejecución QCBS / Línea de base de IBRD / 86820 Framework of the National Posterior en calidad y Open - National 256,364.00 0.00 2019-04-26 2019-05-17 2019-06-30 2019-07-28 2019-08-27 2019-10-01 2019-11-05 2020-05-03 pendiente vigilancia de I+D+i STI System costo Strategic Programs: PE-FONDECYT-15885-CS- Productivity & Innovation Selección basada Ejecución LCS / Evaluación de IBRD / 86820 Fund and Competitiveness Posterior en el menor Open - National 90,909.00 0.00 2019-05-02 2019-05-23 2019-07-06 2019-08-03 2019-09-02 2019-10-07 2019-11-11 2020-02-09 pendiente Término del Proyecto Reinforcement Initiatives costo for Productive Innova tion PE-FONDECYT-15820-CS- QCBS / Capacitación en el Improving the Institutional Selección basada uso de la aplicación para el Open - Ejecución IBRD / 86820 Framework of the National Previa en calidad y 373,000.00 0.00 2019-09-02 2019-09-16 2019-10-10 2019-11-07 2019-11-17 2019-12-08 2020-01-12 2020-07-10 seguimiento de gasto International pendiente STI System costo público en CTI (Sectores, GRs, GLs, solo para operarios). PE-FONDECYT-15704-CS- QCBS / Elaboración de 03 Improving the Institutional Selección basada documentos de análisis del Ejecución IBRD / 86820 Framework of the National Posterior en calidad y Open - National 137,000.00 0.00 2019-04-08 2019-04-29 2019-06-12 2019-07-10 2019-08-09 2019-09-13 2019-10-18 2020-10-17 gasto público en CTI pendiente STI System costo (Funcionalidad, Efectividad y Eficiencia). PE-FONDECYT-108596-CS- QCBS / CONSULTORIA Strategic Programs: PARA LA ELABORACIÓN Productivity & Innovation Selección basada E COMPLEMENTACIÓN IBRD / 86820 Fund and Competitiveness Posterior en calificaciones Open - National 90,000.00 0.00 En ejecución 2019-04-26 2019-05-17 2019-06-30 2019-07-30 2019-09-03 2020-03-01 DE UNA ESTRATEGIA DE Reinforcement Initiatives de consultores COMUNICACIÓN PARA EL for Productive Innova tion SUB COMPONENTE 2 PE-FONDECYT-120559-CS- QCBS / CONTRATACIÓN DE UNA FIRMA Strategic Programs: CONSULTORA PARA Productivity & Innovation Selección basada ELABORAR UN Open - IBRD / 86820 Fund and Competitiveness Previa en calidad y 3,220,000.00 0.00 Bajo Revision 2019-06-24 2019-07-15 2019-08-28 2019-09-25 2019-10-25 2019-11-29 2020-01-03 2021-01-02 PROGRAMA DE International Reinforcement Initiatives costo CAPACITACIÓN EN for Productive Innova tion EMPRENDIMIENTO GLOBAL Y EVENTOS DE PITCH Y MENTORING. PE-FONDECYT-128062-CS- LCS / AUDITORIA FINANCIERA DEL PROYECTO MEJORAMIENTO Y Selección basada Project Management and Ejecución AMPLIACIÓN DE LOS IBRD / 86820 Posterior en el menor Open - National 117,000.00 0.00 2019-08-19 2019-09-09 2019-10-23 2019-11-20 2019-12-20 2020-01-24 2020-02-28 2020-08-26 Monitoring & Evaluation pendiente SERVICIOS DEL SISTEMA costo NACIONAL DE CIENCIA, TECNOLOGÍA E INNOVACIÓN TECNOLÓGICA Strategic Programs: Productivity & Innovation Selección basada PE-FONDECYT-15887-CS- IBRD / 86820 Fund and Competitiveness Posterior en el menor Open - National 72,727.00 0.00 Cancelado 2019-04-29 2019-05-20 2019-07-03 2019-07-31 2019-08-30 2019-10-04 2019-11-08 2023-03-01 LCS / Auditoría al Proyecto Reinforcement Initiatives costo for Productive Innova tion INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-FONDECYT-15821-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para la Ejecución IBRD / 86820 Framework of the National Posterior Individual Limited 27,000.00 0.00 2020-07-02 2020-07-09 2020-07-16 2020-07-30 2021-04-21 capacitación de gasto pendiente STI System público en CTI (Asistencia Técnica y acompañamiento) PE-FONDECYT-15878-CS- Strategic Programs: INDV / Especialista Productivity & Innovation Coordinador de área en la IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 163,636.00 33,956.94 Firmado 2018-01-12 2018-01-17 2018-01-24 2018-02-05 2022-02-21 Unidad de Seguimiento y Reinforcement Initiatives Monitoreo for Productive Innova tion Strategic Programs: PE-FONDECYT-15881-CS- Productivity & Innovation INDV / Especialista de IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 65,455.00 33,502.40 Firmado 2017-11-21 2017-11-26 2017-12-03 2017-12-22 2019-12-31 Evaluación y Selección Reinforcement Initiatives for Productive Innova tion PE-FONDECYT-15705-CS- Improving the Institutional INDV / Taller de cierre de IBRD / 86820 Framework of the National Posterior Individual Limited 5,000.00 0.00 Cancelado 2018-08-15 2018-08-22 2018-08-29 2018-09-12 2018-10-02 la consultoría STI System PE-FONDECYT-15877-CS- Strategic Programs: INDV / Esp. Coord. de área Productivity & Innovation en Seguimiento y Monitoreo IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 127,273.00 35,820.90 Firmado 2018-01-30 2018-02-02 2018-02-09 2018-02-16 2021-12-31 responsable del componente Reinforcement Initiatives 1 for Productive Innova tion PE-FONDECYT-15870-CS- Project Management and INDV / Coordinador IBRD / 86820 Posterior Individual Open 237,273.00 53,928.40 Firmado 2018-01-24 2018-02-11 2018-02-18 2018-03-01 2019-03-01 Monitoring & Evaluation Adjunto del Proyecto Strategic Programs: PE-FONDECYT-15871-CS- Productivity & Innovation INDV / Especialista en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 180,000.00 40,947.37 Finalizado 2017-11-21 2017-11-26 2017-12-03 2017-12-22 2022-01-07 Gestión Administrativa Reinforcement Initiatives (Contabilidad) for Productive Innova tion Strategic Programs: PE-FONDECYT-15872-CS- Productivity & Innovation INDV / Especialista en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 180,000.00 40,947.37 Firmado 2017-11-21 2017-11-26 2017-12-03 2017-12-22 2022-01-07 Adquisiciones Reinforcement Initiatives for Productive Innova tion Strategic Programs: PE-FONDECYT-15873-CS- Productivity & Innovation INDV / Analista de IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 114,545.00 26,057.42 Firmado 2018-01-19 2018-01-24 2018-01-31 2018-02-12 2021-12-31 Adquisiciones Reinforcement Initiatives for Productive Innova tion Page 4 PE-FONDECYT-54867-CS- Project Management and INDV / Especialista de IBRD / 86820 Posterior Individual Open 180,000.00 40,236.54 Finalizado 2017-10-13 2018-01-24 2018-01-24 2018-02-01 2019-01-31 Monitoring & Evaluation Planificación y Presupuesto Strategic Programs: PE-FONDECYT-52471-CS- Productivity & Innovation INDV / Especialista para la IBRD / 86820 Fund and Competitiveness Posterior Individual Open 127,273.00 34,886.34 Firmado 2017-10-30 2017-12-18 2018-01-08 2018-02-12 2019-02-12 Unidad Seguimiento y Reinforcement Initiatives Monitoreo for Productive Innova tion PE-FONDECYT-55436-CS- Project Management and INDV / Especialista para la IBRD / 86820 Posterior Individual Open 65,455.00 32,850.71 Firmado 2017-10-09 2018-02-07 2018-02-07 2018-02-12 2019-02-11 Monitoring & Evaluation Unidad de Desarrollo PE-FONDECYT-15876-CS- Project Management and INDV / Especialista en IBRD / 86820 Posterior Individual Limited 122,727.00 27,641.28 Finalizado 2018-01-12 2018-01-17 2018-01-24 2018-02-05 2021-12-31 Monitoring & Evaluation Comunicaciones Strategic Programs: Productivity & Innovation PE-FONDECYT-15875-CS- IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 147,273.00 33,502.40 Rescindido 2018-01-12 2018-01-17 2018-01-24 2018-02-05 2021-12-31 INDV / Especialista Legal Reinforcement Initiatives for Productive Innova tion Strategic Programs: PE-FONDECYT-15880-CS- Productivity & Innovation INDV / Especialista de IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 65,455.00 0.00 Cancelado 2017-11-21 2017-11-26 2017-12-03 2017-12-22 2019-12-31 Desarrollo Reinforcement Initiatives for Productive Innova tion PE-FONDECYT-57479-CS- Project Management and INDV / Especialista en IBRD / 86820 Posterior Individual Limited 41,000.00 40,236.54 Firmado 2018-04-11 2018-04-16 2018-04-23 2018-05-07 2019-05-07 Monitoring & Evaluation Presupuesto y Finanzas Strategic Programs: PE-FONDECYT-15874-CS- Productivity & Innovation INDV / Especialista en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 180,000.00 39,836.72 Firmado 2017-11-21 2017-11-26 2017-12-03 2017-12-22 2022-01-07 Planificación y Monitoreo Reinforcement Initiatives for Productive Innova tion PE-FONDECYT-59533-CS- Project Management and INDV / Especialista en IBRD / 86820 Posterior Individual Limited 102,274.00 27,621.77 Firmado 2018-04-02 2018-04-07 2018-04-14 2018-04-28 2019-04-28 Monitoring & Evaluation Tesoreria PE-FONDECYT-54824-CS- Project Management and INDV / Especialista en IBRD / 86820 Posterior Individual Open 102,274.00 0.00 Cancelado 2018-03-31 2018-04-12 2018-04-17 2018-04-23 2019-04-22 Monitoring & Evaluation Tesorería PE-FONDECYT-34395-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 2 STI System PE-FONDECYT-34396-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 3 STI System PE-FONDECYT-34397-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 4 STI System PE-FONDECYT-34398-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 5 STI System PE-FONDECYT-34400-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 6 STI System PE-FONDECYT-34393-CS- Improving the Institutional INDV / Desarrollador Senior IBRD / 86820 Framework of the National Posterior Individual Open 33,300.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 de Software 1 STI System PE-FONDECYT-35213-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-01-31 2018-05-01 para la recopilación de STI System información de Líneas de Base PE-FONDECYT-35214-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 2 PE-FONDECYT-35215-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 3 PE-FONDECYT-35216-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 4 PE-FONDECYT-35220-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 8 PE-FONDECYT-35218-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 6 PE-FONDECYT-35217-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 5 Page 5 PE-FONDECYT-35219-CS- INDV / Desarrollador para Improving the Institutional la construcción de software IBRD / 86820 Framework of the National Posterior Individual Limited 16,364.00 0.00 Cancelado 2018-01-05 2018-01-10 2018-01-17 2018-02-07 2018-05-08 para la recopilación de STI System información de Líneas de Base 7 PE-FONDECYT-59545-CS- INDV / Analista Funcional Improving the Institutional para el proyecto de IBRD / 86820 Framework of the National Posterior Individual Limited 26,561.00 31,304.67 Firmado 2018-04-02 2018-04-07 2018-04-14 2018-04-28 2019-04-28 implementación de la nueva STI System plataforma de gestión del conocimiento del SINACYT PE-FONDECYT-34402-CS- INDV / Analista Funcional Improving the Institutional para el proyecto de IBRD / 86820 Framework of the National Posterior Individual Open 26,561.00 0.00 Cancelado 2018-04-27 2018-05-14 2018-05-19 2018-05-23 2019-05-22 implementación de la nueva STI System plataforma de gestión del conocimiento del SINACYT PE-FONDECYT-59555-CS- INDV / Analista funcional Improving the Institutional para el módulo de IBRD / 86820 Framework of the National Posterior Individual Limited 34,375.00 38,670.47 Firmado 2018-04-16 2018-04-21 2018-04-28 2018-05-12 2019-05-12 vigilancia de I+D+i de la STI System nueva plataforma de gestión del conocimiento del SINACYT PE-FONDECYT-34403-CS- INDV / Analista funcional Improving the Institutional para el proyecto de IBRD / 86820 Framework of the National Posterior Individual Open 34,375.00 0.00 Cancelado 2018-01-12 2018-02-02 2018-02-09 2018-03-02 2019-03-02 implementación del módulo STI System de vigilancia de I+D+i PE-FONDECYT-61501-CS- Project Management and IBRD / 86820 Posterior Individual Limited 33,000.00 32,303.20 Rescindido 2018-04-23 2018-04-26 2018-05-01 2018-05-08 2019-05-08 INDV / Especialista Legal Monitoring & Evaluation PE-FONDECYT-69987-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA Improving the Institutional LA GESTIÓN DEL SUB IBRD / 86820 Framework of the National Posterior Individual Limited 25,455.00 0.00 Cancelado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 COMPONENTE 1.1 DEL STI System PROYECTO DE MEJORAMIENTO Y AMPLIACIONES DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-69990-CS- INDV / MONITOR TÉCNICO 1 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,213.75 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69992-CS- INDV / MONITOR TÉCNICO 2 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,213.75 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69993-CS- INDV / MONITOR TÉCNICO 3 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,271.46 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69994-CS- INDV / MONITOR TÉCNICO 4 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,271.46 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69996-CS- INDV / MONITOR FINANCIERO 1 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,271.46 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69998-CS- INDV / MONITOR FINANCIERO 2 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,271.46 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-69999-CS- INDV / MONITOR FINANCIERO 3 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,213.75 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-70000-CS- INDV / MONITOR FINANCIERO 4 DE LA Research and Innovation IBRD / 86820 Posterior Individual Limited 25,455.00 6,271.46 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 UNIDAD DE Capacity SEGUIMIENTO Y MONITOREO PE-FONDECYT-70001-CS- INDV / CONSULTORIA PARA DISEÑO Y ELABORACIÓN DE DOCUMENTOS Improving the Institutional NORMATIVOS PARA LA IBRD / 86820 Framework of the National Posterior Individual Limited 40,000.00 39,057.88 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 IMPLEMENTACIÓN DE STI System MEJORAS AL MARCO INSTITUCIONAL Y ORGANIZACIONAL DEL SINACYT PE-FONDECYT-70003-CS- INDV / DISEÑO, ELABORACIÓN Y SEGUIMIENTO DE Improving the Institutional DOCUMENTOS E IBRD / 86820 Framework of the National Posterior Individual Limited 40,000.00 39,057.88 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 INSTRUMENTOS DE STI System GESTIÓN PARA EL DESARROLLO DEL COMPONENTE 1 Y 3 Page 6 PE-FONDECYT-70007-CS- INDV / GESTIÓN DEL PLAN MULTIANUAL DE ACTIVIDADES DE LA DIRECCIÓN DE Research and Innovation POLÍTICAS Y IBRD / 86820 Posterior Individual Limited 40,000.00 38,732.40 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 Capacity PROGRAMAS DEL CONCYTEC EN EL MARCO DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-15879-CS- Strategic Programs: INDV / Esp. Coord. de área Productivity & Innovation en Seguimiento y Monitoreo IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 163,636.00 0.00 Cancelado 2018-01-26 2018-01-29 2018-02-05 2018-02-12 2021-12-31 responsable del componente Reinforcement Initiatives 3 for Productive Innova tion PE-FONDECYT-15703-CS- INDV / Organización y Improving the Institutional ejecución de Taller para IBRD / 86820 Framework of the National Posterior Individual Limited 5,000.00 0.00 Cancelado 2017-06-16 2017-06-23 2017-06-30 2017-07-14 2017-08-14 elaboración de Términos de STI System Referencia PE-FONDECYT-15850-CS- INDV / ) Gestión del fondo Project Management and para la implementación de IBRD / 86820 Posterior Individual Limited 244,000.00 0.00 Cancelado 2018-07-17 2018-07-24 2018-07-31 2018-08-14 2020-07-06 Monitoring & Evaluation las iniciativas vinculación academia - empresa PE-FONDECYT-55423-CS- INDV / Consultor (1) para Improving the Institutional mapeo de diagnostico IBRD / 86820 Framework of the National Posterior Individual Open 12,750.00 0.00 Cancelado 2018-05-07 2018-05-24 2018-05-29 2018-06-02 2018-11-19 institucional y propuestas STI System de mejoras PE-FONDECYT-35395-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para los IBRD / 86820 Framework of the National Posterior Individual Limited 43,636.00 0.00 Cancelado 2018-07-06 2018-07-11 2018-07-18 2018-08-08 2019-02-04 estudios de Línea de Base STI System I+D+i (asistencia técnica y acompañamiento) PE-FONDECYT-55425-CS- Improving the Institutional INDV / Consultor para la IBRD / 86820 Framework of the National Posterior Individual Open 17,000.00 0.00 Cancelado 2018-05-07 2018-05-24 2018-05-29 2018-06-02 2018-11-19 reglamentación de la nueva STI System ley de SINACYT PE-FONDECYT-55426-CS- INDV / Asistencia técnica Improving the Institutional para revisión internacional IBRD / 86820 Framework of the National Posterior Individual Open 10,000.00 0.00 Cancelado 2018-08-03 2018-08-20 2018-08-25 2018-08-29 2018-10-28 de modelos de organización STI System de sistemas similares al SINACYT PE-FONDECYT-15817-CS- INDV / Seguimiento y Improving the Institutional asesoramiento el desarrollo IBRD / 86820 Framework of the National Posterior Individual Limited 45,000.00 0.00 Cancelado 2018-02-16 2018-02-23 2018-03-02 2018-03-16 2019-04-17 del sistema integrado de STI System información (Asistencia Técnica y acompañamiento) PE-FONDECYT-55420-CS- Improving the Institutional INDV / Consultor (2) para IBRD / 86820 Framework of the National Posterior Individual Open 32,750.00 0.00 Cancelado 2018-04-27 2018-05-14 2018-05-19 2018-05-23 2018-11-09 sistematización y diagnóstico STI System rápido del sistema de I+D+i PE-FONDECYT-15836-CS- INDV / Ejecución del curso Profesores internacionales: Selección , reclutamiento y Project Management and IBRD / 86820 Posterior Individual Limited 196,840.00 0.00 Cancelado 2017-09-14 2017-09-21 2017-09-28 2017-10-12 2017-11-22 viajes internacionales de Monitoring & Evaluation profesores internacionales (12 expertos internacionales). PE-FONDECYT-55424-CS- INDV / Consultor (2) para Improving the Institutional mapeo de diagnóstico IBRD / 86820 Framework of the National Posterior Individual Open 12,750.00 0.00 Cancelado 2018-05-07 2018-05-24 2018-05-29 2018-06-02 2018-11-19 institucional y propuestas STI System de mejoras PE-FONDECYT-55418-CS- Improving the Institutional INDV / Consultor (1) para IBRD / 86820 Framework of the National Posterior Individual Open 32,750.00 0.00 Cancelado 2018-04-27 2018-05-14 2018-05-19 2018-05-23 2018-11-09 sistematización y diagnóstico STI System rápido del sistema de I+D+i PE-FONDECYT-15702-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para los IBRD / 86820 Framework of the National Posterior Individual Limited 51,066.00 0.00 Cancelado 2018-03-30 2018-04-06 2018-04-13 2018-04-27 2018-10-24 estudios del sub componente STI System 1.1.1 (Asistencia Técnica y acompañamiento) PE-FONDECYT-15706-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para los 03 IBRD / 86820 Framework of the National Posterior Individual Limited 43,636.00 0.00 Cancelado 2018-03-16 2018-03-23 2018-03-30 2018-04-13 2019-02-07 estudios de análisis del STI System gasto público. (Asistencia Técnica y acompañamiento) PE-FONDECYT-15708-CS- INDV / Seguimiento y Improving the Institutional asesoramiento a la IBRD / 86820 Framework of the National Posterior Individual Limited 20,606.00 0.00 Cancelado 2017-12-01 2017-12-08 2017-12-15 2017-12-29 2018-12-29 consultoría de Análisis de STI System la Gobernanza PE-FONDECYT-15710-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para el IBRD / 86820 Framework of the National Posterior Individual Limited 10,500.00 0.00 Cancelado 2018-08-15 2018-08-22 2018-08-29 2018-09-12 2019-08-07 estudio del sistema gasto STI System público en CTI. (Asistencia Técnica y acompañamiento) PE-FONDECYT-15714-CS- INDV / Seguimiento y Improving the Institutional asesoramiento para los IBRD / 86820 Framework of the National Posterior Individual Limited 30,000.00 0.00 Cancelado 2018-01-31 2018-02-07 2018-02-14 2018-02-28 2019-01-31 estudios de Línea de Base STI System (Asistencia Técnica y acompañamiento) PE-FONDECYT-15819-CS- INDV / Seguimiento y asesoramiento consultoria de Improving the Institutional de Desarrollo de la IBRD / 86820 Framework of the National Posterior Individual Limited 45,000.00 0.00 Cancelado 2019-06-20 2019-06-27 2019-07-04 2019-07-18 2020-08-18 aplicación para el STI System seguimiento del Gasto Público (Asistencia Técnica y acompañamiento) Page 7 PE-FONDECYT-15827-CS- Improving the Institutional INDV / Coordinador del IBRD / 86820 Framework of the National Posterior Individual Limited 40,500.00 0.00 Cancelado 2018-05-11 2018-05-18 2018-05-25 2018-06-08 2019-03-19 Programa de Capacitación STI System de análisis del gasto público PE-FONDECYT-15829-CS- Improving the Institutional INDV / Coordinador del IBRD / 86820 Framework of the National Posterior Individual Limited 30,000.00 0.00 Cancelado 2021-06-15 2021-06-22 2021-06-29 2021-07-13 2021-12-23 Programa de Capacitación STI System de M & E PE-FONDECYT-15831-CS- Improving the Institutional INDV / Coordinador del IBRD / 86820 Framework of the National Posterior Individual Limited 33,000.00 0.00 Cancelado 2018-01-26 2018-02-02 2018-02-09 2018-02-23 2018-12-13 programa de capacitación de STI System gestión de CTI PE-FONDECYT-15832-CS- INDV / Evaluación de Improving the Institutional currícula de entidad IBRD / 86820 Framework of the National Posterior Individual Limited 7,000.00 0.00 Cancelado 2018-01-26 2018-02-02 2018-02-09 2018-02-23 2018-03-22 capacitadora (por entidad x STI System curso) y dimensionar el costo. PE-FONDECYT-15833-CS- INDV / Contratación de Project Management and expertos para identificación IBRD / 86820 Posterior Individual Limited 7,000.00 0.00 Cancelado 2018-01-26 2018-02-02 2018-02-09 2018-02-23 2018-03-27 Monitoring & Evaluation de las oportunidades tecnológicas PE-FONDECYT-15834-CS- INDV / Diseño y Project Management and IBRD / 86820 Posterior Individual Limited 14,020.00 0.00 Cancelado 2018-05-24 2018-05-31 2018-06-07 2018-06-21 2018-07-21 preparación de los Monitoring & Evaluation materiales de enseñanza PE-FONDECYT-15838-CS- INDV / Elaboración de la Project Management and IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 Cancelado 2018-01-19 2018-01-26 2018-02-02 2018-02-16 2018-06-16 matriz de evaluación de Monitoring & Evaluation sectores PE-FONDECYT-15844-CS- INDV / Consultorías especializadas Project Management and IBRD / 86820 Posterior Individual Limited 60,000.00 0.00 Cancelado 2018-06-15 2018-06-22 2018-06-29 2018-07-13 2019-01-09 internacionales de alto nivel Monitoring & Evaluation para el fortalecer las iniciativas para la competitividad PE-FONDECYT-15845-CS- INDV / Servicio de consultoría para reforma de política: Asesor senior de política para consolidar los Project Management and IBRD / 86820 Posterior Individual Limited 278,400.00 0.00 Cancelado 2018-03-08 2018-03-15 2018-03-22 2018-04-05 2018-08-20 insumos para las iniciativas Monitoring & Evaluation para la competitividad a través de reformas de política (24 días y dos viajes por año) PE-FONDECYT-15848-CS- INDV / Estudio de Project Management and dimensionamiento del fondo IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 Cancelado 2018-04-20 2018-04-27 2018-05-04 2018-05-18 2018-08-31 Monitoring & Evaluation a otorgar , iniciativas de vinculación académica PE-FONDECYT-15852-CS- INDV / Estudio de Research and Innovation dimensionamiento de IBRD / 86820 Posterior Individual Limited 30,000.00 0.00 Cancelado 2018-01-26 2018-02-02 2018-02-09 2018-02-23 2018-05-24 Capacity instrumentos del componente 3 PE-FONDECYT-70254-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA LA GESTIÓN DEL SUB Research and Innovation COMPONENTE 3, SUB IBRD / 86820 Posterior Individual Limited 25,455.00 24,855.01 Firmado 2018-07-30 2018-08-04 2018-08-25 2018-09-29 2019-09-24 Capacity COMPONENTES 3.1, 3.2, 3.3 DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-70387-CS- INDV / SOPORTE ADMINISTRATIVO PARA LA GESTION DEL SUB Improving the Institutional COMPONENTE 1.2 DEL IBRD / 86820 Framework of the National Posterior Individual Limited 25,455.00 0.00 Cancelado 2018-07-31 2018-08-05 2018-08-26 2018-09-30 2019-09-25 PROYECTO DE STI System MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-73712-CS- Improving the Institutional CDS / Capacitación al Selección directa IBRD / 86820 Framework of the National Posterior Direct 68,000.00 67,808.70 Finalizado 2018-08-16 2018-08-26 2018-09-10 2018-10-10 personal de CONCYTEC y de consultores STI System Monitores del FONDECYT PE-FONDECYT-76770-CS- INDV / Elaboración de una guía metodológica de negociación con los subproyectos para capacitar a los monitores de Research and Innovation IBRD / 86820 Posterior Individual Limited 7,000.00 6,805.54 Firmado 2018-09-04 2018-09-09 2018-09-23 2018-10-14 2018-10-29 seguimiento del Proyecto Capacity Mejoramiento y Ampliación del Sistema Nacional de Ciencia, Tecnología e Innovación Tecnológica- SINACYT. PE-FONDECYT-70006-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA LA GESTIÓN DEL SUB Improving the Institutional COMPONENTE 1.1 DE IBRD / 86820 Framework of the National Posterior Individual Limited 25,455.00 24,855.01 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 LAS ACTIVIDADES 1.1.1 STI System DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-70005-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA LA GESTIÓN DEL SUB Project Management and IBRD / 86820 Posterior Individual Limited 25,455.00 24,855.01 Firmado 2018-07-17 2018-07-22 2018-08-12 2018-09-16 2019-03-15 COMPONENTE 2.2 DEL Monitoring & Evaluation PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT Page 8 PE-FONDECYT-77285-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA Improving the Institutional LA GESTIÓN DEL SUB IBRD / 86820 Framework of the National Posterior Individual Open 25,455.00 24,855.01 Firmado 2018-09-07 2018-10-03 2018-10-10 2018-10-24 2019-10-24 COMPONENTE 1.1 DEL STI System PROYECTO DE MEJORAMIENTO Y AMPLIACIONES DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-77290-CS- INDV / Analista de Adquisiciones para el Project Management and IBRD / 86820 Posterior Individual Open 32,800.00 31,956.45 Firmado 2018-09-10 2018-10-06 2018-10-13 2018-10-27 2019-10-27 Proyecto Mejoramiento y Monitoring & Evaluation Ampliación de los Servicios del SINACYT PE-FONDECYT-77295-CS- INDV / Especialista en gestión de metadatos y clasificación temática para Improving the Institutional el proyecto de IBRD / 86820 Framework of the National Posterior Individual Limited 25,455.00 24,855.01 Firmado 2018-09-10 2018-09-15 2018-09-29 2018-10-20 2019-10-20 implementación de la nueva STI System plataforma de Gestión del Conocimiento del Sistema Nacional de Ciencia, Tecnología e Innovación (SINACYT) PE-FONDECYT-77306-CS- INDV / Especialista en control de autoridades y calidad de metadatos para el proyecto de Improving the Institutional implementación de la nueva IBRD / 86820 Framework of the National Posterior Individual Limited 25,455.00 21,304.30 Firmado 2018-09-10 2018-09-15 2018-09-29 2018-10-20 2019-10-20 plataforma de Gestión del STI System Conocimiento del Sistema Nacional de Ciencia, Tecnología e Innovación (SINACYT) PE-FONDECYT-79616-CS- INDV / CONSULTOR ESPECIALIZADO PARA CAPACITACION EN EL Improving the Institutional TALLER "LÍNEA DE BASE IBRD / 86820 Framework of the National Posterior Individual Limited 8,000.00 6,921.05 Finalizado 2018-10-03 2018-10-08 2018-10-15 2018-10-25 2018-11-14 DEL GASTO PÚBLICO EN STI System CIENCIA, TECNOLOGIA E INNOVACION (CTI) EN EL PERU PE-FONDECYT-79618-CS- INDV / CONSULTORIA PARA LA REALIZACIÓN DE LA PRIMERA FASE Improving the Institutional DEL ESTUDIO DE IBRD / 86820 Framework of the National Posterior Individual Limited 15,000.00 14,646.70 Firmado 2018-10-03 2018-10-08 2018-10-15 2018-10-29 2019-01-27 "LÍNEA DE BASE DEL STI System GASTO PÚBLICO EN CIENCIA TECNOLOGIA E INNOVACION (CTI) EN EL PERÚ PE-FONDECYT-87590-CS- INDV / SERVICIO PARA IDENTIFICAR INVESTIGADORES Research and Innovation EXTRANJEROS PARA LAS IBRD / 86820 Posterior Individual Limited 8,500.00 0.00 En ejecución 2019-02-15 2019-02-20 2019-02-27 2019-03-13 2019-07-11 Capacity CONVOCATORIAS DE INCORPORACION DE INVESTIGADORES Y PROYECTOS INTEGRALES PE-FONDECYT-77282-CS- INDV / SOPORTE ADMINISTRATIVO PARA LA GESTION DEL SUB Improving the Institutional Ejecución COMPONENTE 1.2 DEL IBRD / 86820 Framework of the National Posterior Individual Open 25,455.00 0.00 2019-03-08 2019-04-03 2019-04-10 2019-04-24 2020-04-23 pendiente PROYECTO DE STI System MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-70002-CS- INDV / COORDINADOR DE ACTIVIDADES RELACIONADAS A LA Improving the Institutional Ejecución IMPLEMENTACIÓN DE IBRD / 86820 Framework of the National Posterior Individual Limited 40,000.00 0.00 2019-03-06 2019-03-11 2019-04-01 2019-05-06 2019-11-02 pendiente MEJORAS AL MARCO STI System INSTITUCIONAL Y ORGANIZACIONAL DEL SINACYT PE-FONDECYT-59677-CS- INDV / Analista Programador Senior para la implementación de Project Management and Ejecución adecuaciones al módulo de IBRD / 86820 Posterior Individual Limited 14,545.00 0.00 2019-03-29 2019-04-03 2019-04-10 2019-04-24 2019-10-21 Monitoring & Evaluation pendiente seguimiento y monitoreo de subproyectos del Sistema Integrado de Gestión del FONDECYT. PE-FONDECYT-54531-CS- INDV / Especialista en Project Management and Ejecución IBRD / 86820 Posterior Individual Open 180,000.00 0.00 2019-03-26 2019-07-08 2019-07-08 2019-07-19 2020-07-17 Gestión Administrativa Monitoring & Evaluation pendiente (Contabilidad) PE-FONDECYT-55432-CS- Improving the Institutional INDV / Consultor para la Ejecución IBRD / 86820 Framework of the National Posterior Individual Open 22,000.00 0.00 2019-04-04 2019-04-21 2019-04-26 2019-04-30 2019-10-17 elaboración del Plan pendiente STI System Estratégico de CTI PE-FONDECYT-55414-CS- Improving the Institutional INDV / Consultor para Ejecución IBRD / 86820 Framework of the National Posterior Individual Open 38,000.00 0.00 2019-04-01 2019-04-18 2019-04-23 2019-04-27 2019-10-14 Supervisión y Enlace con pendiente STI System DPP PE-FONDECYT-55422-CS- INDV / Consultor senior para consolidar los insumos Improving the Institutional Ejecución para revisión de propuestas IBRD / 86820 Framework of the National Posterior Individual Open 20,100.00 0.00 2019-03-19 2019-04-05 2019-04-10 2019-04-14 2019-06-28 pendiente de iniciativas de política, en STI System el marco del Diagnóstico del sistema de I+D+i PE-FONDECYT-55429-CS- INDV / Consultor para Improving the Institutional Ejecución dinamización y validación IBRD / 86820 Framework of the National Posterior Individual Open 18,200.00 0.00 2019-03-26 2019-04-12 2019-04-17 2019-04-21 2019-06-20 pendiente de propuesta del reglamento STI System del SINACYT Page 9 PE-FONDECYT-55430-CS- INDV / Consultor para Improving the Institutional elaboración de propuesta de Ejecución IBRD / 86820 Framework of the National Posterior Individual Open 22,000.00 0.00 2019-04-01 2019-04-18 2019-04-23 2019-04-27 2019-10-14 nuevo programa pendiente STI System presupuestal del CONCYTEC PE-FONDECYT-45382-CS- INDV / Servicio para el Improving the Institutional modelado de los procesos de Ejecución IBRD / 86820 Framework of the National Posterior Individual Open 29,091.00 0.00 2019-04-19 2019-05-22 2019-05-29 2019-06-12 2020-06-11 software, relacionados al pendiente STI System sistema de M & E y a las líneas de Base regionales Strategic Programs: PE-FONDECYT-33435-CS- Productivity & Innovation Ejecución INDV / Monitor en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 109,090.00 0.00 2019-04-09 2019-04-16 2019-04-23 2019-05-07 2023-03-28 pendiente Seguimiento y Monitoreo 3 Reinforcement Initiatives for Productive Innova tion Strategic Programs: PE-FONDECYT-33433-CS- Productivity & Innovation Ejecución INDV / Monitor en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 109,090.00 0.00 2019-04-24 2019-05-01 2019-05-08 2019-05-22 2023-04-12 pendiente Seguimiento y Monitoreo 2 Reinforcement Initiatives for Productive Innova tion Strategic Programs: PE-FONDECYT-15882-CS- Productivity & Innovation Ejecución INDV / Monitor en IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 109,091.00 0.00 2019-03-21 2019-03-28 2019-04-04 2019-04-18 2023-04-16 pendiente Seguimiento y Monitoreo 1 Reinforcement Initiatives for Productive Innova tion PE-FONDECYT-35221-CS- Improving the Institutional INDV / Recopilación de Ejecución IBRD / 86820 Framework of the National Posterior Individual Limited 15,545.00 0.00 2019-04-19 2019-04-24 2019-05-01 2019-05-15 2019-08-13 información de las Lineas pendiente STI System de Base regionales PE-FONDECYT-35222-CS- Improving the Institutional INDV / Modelado de los Ejecución IBRD / 86820 Framework of the National Posterior Individual Limited 14,545.00 0.00 2019-04-17 2019-04-22 2019-04-29 2019-05-20 2019-08-18 procesos relacionados a las pendiente STI System Líneas de Base regionales PE-FONDECYT-15863-CS- INDV / Evaluación externa, primera convocatoria para Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 25,000.00 0.00 2019-04-18 2019-04-25 2019-05-02 2019-05-16 2019-06-15 modernizar y fortalecer la Capacity pendiente infraestructura de investigación (3.2) PE-FONDECYT-15857-CS- INDV / Calificación de Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 7,500.00 0.00 2019-04-16 2019-04-23 2019-04-30 2019-05-14 2019-06-13 investigadores postulantes Capacity pendiente (Baremo) PE-FONDECYT-15856-CS- INDV / Evaluación externa Research and Innovation Ejecución de instituciones postulantes, IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 2019-04-24 2019-05-01 2019-05-08 2019-05-22 2019-06-25 Capacity pendiente subvenciones para investigadores PE-FONDECYT-15867-CS- INDV / Evaluación externa, Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 25,000.00 0.00 2019-03-28 2019-04-04 2019-04-11 2019-04-25 2019-05-22 primera convocatoria para Capacity pendiente proyectos integrales (3.4) PE-FONDECYT-15865-CS- INDV / Evaluación externa, Research and Innovation Ejecución primera convocatoria para IBRD / 86820 Posterior Individual Limited 60,000.00 0.00 2019-04-18 2019-04-25 2019-05-02 2019-05-16 2019-06-15 Capacity pendiente producción de proyectos de calidad I+D+i (3.3) PE-FONDECYT-15847-CS- INDV / Evaluación externa de planes de inversión Project Management and Ejecución IBRD / 86820 Posterior Individual Limited 116,308.00 0.00 2019-03-20 2019-03-27 2019-04-03 2019-04-17 2019-05-07 (evaluadores externos) para Monitoring & Evaluation pendiente implementar iniciativas de vinculación académica PE-FONDECYT-15858-CS- INDV / Evaluación externa Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 2019-03-29 2019-04-05 2019-04-12 2019-04-26 2019-05-23 segunda etapa, subvenciones Capacity pendiente para investigadores PE-FONDECYT-15859-CS- INDV / Evaluación externa de instituciones postulantes, Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 2019-04-09 2019-04-16 2019-04-23 2019-05-07 2019-06-03 2da convocatoria, Capacity pendiente subvenciones para investigadores (3.1.1) PE-FONDECYT-15860-CS- INDV / Calificación de investigadores postulantes Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 7,500.00 0.00 2019-04-26 2019-05-03 2019-05-10 2019-05-24 2019-06-20 (Baremo), 2da convocatoria Capacity pendiente subvenciones para investigadores PE-FONDECYT-15861-CS- INDV / Evaluación externa Research and Innovation Ejecución segunda etapa, subvenciones IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 2019-05-02 2019-05-09 2019-05-16 2019-05-30 2019-06-26 Capacity pendiente para investigadores, 2da convocatoria PE-FONDECYT-15862-CS- INDV / Evaluación externa Research and Innovation Ejecución de instituciones postulantes, IBRD / 86820 Posterior Individual Limited 24,000.00 0.00 2019-05-03 2019-05-10 2019-05-17 2019-05-31 2019-06-27 Capacity pendiente programas de doctorados (3.1.2) PE-FONDECYT-15864-CS- INDV / Evaluación externa, segunda convocatoria para Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 25,000.00 0.00 2019-05-02 2019-05-09 2019-05-16 2019-05-30 2019-06-26 modernizar y fortalecer la Capacity pendiente infraestructura de investigación (3.2) PE-FONDECYT-15866-CS- INDV / Evaluación externa, Research and Innovation Ejecución segunda convocatoria para IBRD / 86820 Posterior Individual Limited 45,000.00 0.00 2019-04-30 2019-05-07 2019-05-14 2019-05-28 2019-06-24 Capacity pendiente producción de proyectos de calidad I+D+i (3.3) PE-FONDECYT-15868-CS- INDV / Evaluación externa, Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 31,000.00 0.00 2019-04-29 2019-05-06 2019-05-13 2019-05-27 2019-07-05 segunda convocatoria para Capacity pendiente proyectos integrales (3.4) Page 10 PE-FONDECYT-15869-CS- INDV / Evaluación Research and Innovation Ejecución externa,tercera convocatoria IBRD / 86820 Posterior Individual Limited 15,000.00 0.00 2019-04-29 2019-05-06 2019-05-13 2019-05-27 2019-06-23 Capacity pendiente para proyectos integrales (3.4) PE-FONDECYT-77327-CS- Project Management and INDV / Especialista de IBRD / 86820 Posterior Individual Limited 32,800.00 0.00 En ejecución 2019-02-14 2019-02-19 2019-02-26 2019-03-10 2020-03-09 Monitoring & Evaluation Comunicaciones del Proyecto Strategic Programs: PE-FONDECYT-15837-CS- Productivity & Innovation INDV / Coordinador del Ejecución IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 45,000.00 0.00 2019-04-11 2019-04-18 2019-04-25 2019-05-09 2020-04-09 componente 2 asignado al pendiente Reinforcement Initiatives CONCYTEC for Productive Innova tion PE-FONDECYT-59676-CS- INDV / Analista Programador Senior para la implementación de Project Management and IBRD / 86820 Posterior Individual Limited 14,545.00 0.00 Cancelado 2019-03-28 2019-04-02 2019-04-09 2019-04-23 2019-10-20 adecuaciones al módulo de Monitoring & Evaluation evaluación y selección del Sistema Integrado de Gestión del FONDECYT. PE-FONDECYT-59563-CS- INDV / Analista Programador Junior para la implementación de Project Management and IBRD / 86820 Posterior Individual Limited 10,909.00 0.00 Cancelado 2019-04-15 2019-04-20 2019-04-27 2019-05-11 2019-11-07 adecuaciones al módulo de Monitoring & Evaluation gestión de convocatorias del Sistema Integrado de Gestión del FONDECYT. PE-FONDECYT-59674-CS- INDV / Analista Programador Junior para la implementación de Project Management and IBRD / 86820 Posterior Individual Limited 10,909.00 0.00 Cancelado 2019-04-03 2019-04-08 2019-04-15 2019-04-29 2019-10-26 adecuaciones al módulo de Monitoring & Evaluation seguimiento y monitoreo del Sistema Integrado de Gestión del FONDECYT. PE-FONDECYT-59558-CS- INDV / Arquitecto de Project Management and Software para el desarrollo IBRD / 86820 Posterior Individual Limited 14,545.00 0.00 Cancelado 2019-04-09 2019-04-14 2019-04-21 2019-05-05 2019-11-01 Monitoring & Evaluation de mejoras en el SIG de FONDECYT PE-FONDECYT-59561-CS- INDV / Analista Programador Junior para la implementación de Project Management and IBRD / 86820 Posterior Individual Limited 10,909.00 0.00 Cancelado 2019-04-11 2019-04-16 2019-04-23 2019-05-07 2019-11-03 adecuaciones al módulo de Monitoring & Evaluation evaluación y selección del Sistema Integrado de Gestión del FONDECYT. PE-FONDECYT-95709-CS- INDV / Monitor Técnico 5 Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-95712-CS- INDV / Monitor Técnico 6 Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-95713-CS- INDV / Monitor Técnico 7 Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-95714-CS- INDV / Monitor Financiero Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 5 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-95717-CS- INDV / Monitor Financiero Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 6 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-95719-CS- INDV / Monitor Financiero Research and Innovation IBRD / 86820 Posterior Individual Open 24,706.00 0.00 En ejecución 2019-01-21 2019-03-11 2019-04-01 2019-05-06 2019-11-02 7 de la Unidad de Capacity Seguimiento y Monitoreo PE-FONDECYT-92307-CS- INDV / ESPECIALISTA EN Project Management and IBRD / 86820 Posterior Individual Direct 40,000.00 0.00 Cancelado 2018-12-28 2019-01-07 2019-01-14 2019-01-19 2020-01-19 GESTION Monitoring & Evaluation ADMINISTRATIVA PE-FONDECYT-96584-CS- INDV / ESPECIALISTA EN Project Management and IBRD / 86820 Posterior Individual Limited 40,000.00 0.00 En ejecución 2019-02-06 2019-02-11 2019-02-26 2019-03-08 2020-03-07 GESTION Monitoring & Evaluation ADMINISTRATIVA PE-FONDECYT-96585-CS- Project Management and INDV / ESPECIALISTA EN IBRD / 86820 Posterior Individual Limited 40,000.00 0.00 En ejecución 2019-02-06 2019-02-11 2019-02-26 2019-03-08 2020-03-07 Monitoring & Evaluation ADQUISICIONES PE-FONDECYT-101184-CS- INDV / Contratar los Project Management and Servicios de un consultor IBRD / 86820 Posterior Individual Limited 29,412.00 0.00 En ejecución 2019-02-15 2019-02-20 2019-03-13 2019-04-17 2019-10-14 Monitoring & Evaluation individual especializado para la selección de gerentes PE-FONDECYT-101189-CS- INDV / Profesional para gestionar el proceso de Research and Innovation evaluación y selección del IBRD / 86820 Posterior Individual Limited 14,850.00 0.00 En ejecución 2019-02-15 2019-02-20 2019-03-13 2019-04-17 2019-10-14 Capacity subcomponente 3.1 y 3.4 del SINACYT para propuestas de Lima y Centro del Perú PE-FONDECYT-101190-CS- INDV / Profesional para gestionar el proceso de evaluación y selección del Research and Innovation IBRD / 86820 Posterior Individual Limited 14,850.00 0.00 En ejecución 2019-02-15 2019-02-20 2019-03-13 2019-04-17 2019-10-14 subcomponente 3.1 y 3.4 del Capacity SINACYT para las propuestas del Sur y Norte del Perú Page 11 PE-FONDECYT-101191-CS- INDV / Analista desarrollador de una nueva Research and Innovation plataforma para las IBRD / 86820 Posterior Individual Limited 24,243.00 0.00 En ejecución 2019-02-15 2019-02-20 2019-03-13 2019-04-17 2019-10-14 Capacity Unidades de Desarrollo y Evaluación y Selección del FONDECYT PE-FONDECYT-101192-CS- INDV / Consultoría para el seguimiento de las Project Management and actividades y formulación de IBRD / 86820 Posterior Individual Open 35,295.00 0.00 En ejecución 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Monitoring & Evaluation documentos de las iniciativas de vinculación academia-industria 1 PE-FONDECYT-101193-CS- INDV / Consultoría para el seguimiento de las Project Management and actividades y formulación de IBRD / 86820 Posterior Individual Open 35,295.00 0.00 En ejecución 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Monitoring & Evaluation documentos de las iniciativas de vinculación academia-industria 2 PE-FONDECYT-101194-CS- INDV / Consultoría para el seguimiento de las Project Management and actividades y formulación de IBRD / 86820 Posterior Individual Open 35,295.00 0.00 En ejecución 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Monitoring & Evaluation documentos de las iniciativas de vinculación academia-industria 3 PE-FONDECYT-101195-CS- INDV / Consultoría para el seguimiento de las Project Management and actividades y formulación de IBRD / 86820 Posterior Individual Open 35,295.00 0.00 En ejecución 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Monitoring & Evaluation documentos de las iniciativas de vinculación academia-industria 4 PE-FONDECYT-101196-CS- INDV / Consultoría para el seguimiento de las Project Management and actividades y formulación de IBRD / 86820 Posterior Individual Open 35,295.00 0.00 En ejecución 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 Monitoring & Evaluation documentos de las iniciativas de vinculación academia-industria 5 PE-FONDECYT-101197-CS- INDV / Consultor para la gestión y cumplimiento del Plan Multianual de Project Management and Ejecución IBRD / 86820 Posterior Individual Open 52,942.00 0.00 2019-02-15 2019-04-05 2019-04-26 2019-05-31 2019-11-27 actividades de la Monitoring & Evaluation pendiente Subdirección de Innovación y Transferencia Tecnológica del CONCYTEC PE-FONDECYT-54546-CS- Project Management and Ejecución INDV / Especialista en IBRD / 86820 Posterior Individual Open 180,000.00 0.00 2019-04-08 2019-07-20 2019-07-20 2019-07-28 2020-07-26 Monitoring & Evaluation pendiente Adquisiciones PE-FONDECYT-105977-CS- Project Management and Ejecución IBRD / 86820 Posterior Individual Open 32,000.00 0.00 2019-03-13 2019-05-01 2019-05-22 2019-06-26 2019-12-23 INDV / Especialista Legal Monitoring & Evaluation pendiente PE-FONDECYT-107014-CS- INDV / Sensibilización de potenciales postulantes a las Research and Innovation Ejecución convocatorias de IBRD / 86820 Posterior Individual Limited 5,648.00 0.00 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-12-05 Capacity pendiente incorporación de investigadores y Proyectos integrales PE-FONDECYT-108341-CS- INDV / SERVICIO PARA LA ELABORACIÓN DE Strategic Programs: LINEAMIENTOS Productivity & Innovation TECNICOS Y OPERATIVOS Ejecución IBRD / 86820 Fund and Competitiveness Posterior Individual Open 6,500.00 0.00 2019-03-29 2019-05-03 2019-05-24 2019-06-28 2019-12-25 PARA EL LANZAMIENTO pendiente Reinforcement Initiatives Y GESTIÓN DEL for Productive Innova tion CONCURSO DE INICIATIVAS PARA LA COMPETITIVIDAD - VENTANILLA 1 PE-FONDECYT-108593-CS- INDV / SERVICIO DE SOPORTE ADMINISTRATIVO PARA LA GESTIÓN DEL SUB Improving the Institutional Ejecución COMPONENTE 1.1 DE IBRD / 86820 Framework of the National Posterior Individual Limited 4,120.00 0.00 2019-04-04 2019-04-09 2019-04-30 2019-06-04 2019-12-01 pendiente LAS ACTIVIDADES 1.1.1 STI System DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT PE-FONDECYT-108594-CS- INDV / CONSULTORIA PARA EL DESARROLLO DE ESTRATEGIAS PARA LA IMPLEMENTACION EFECTIVA DE UN PROGRAMA DE Research and Innovation REPATRIACIÓN, IBRD / 86820 Posterior Individual Limited 12,350.00 0.00 En ejecución 2019-04-04 2019-04-09 2019-04-30 2019-06-04 2019-12-01 Capacity INCORPORACIÓN Y RETENCIÓN DE INVESTIGADORES EN CIENCIAS Y TECNOLOGÍA PARA LAS UNIVERSIDADES PERUANAS PE-FONDECYT-108726-CS- INDV / Consultores para integrar el PANEL DE EVALUACIÓN TÉCNICA del Concurso E038-2019-01- Research and Innovation Ejecución IBRD / 86820 Posterior Individual Open 98,802.00 0.00 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 BM "Incorporación de Capacity pendiente Investigadores", del Subcomponente "Incremento de la disponibilidad de capital humano en I+D+i" Page 12 PE-FONDECYT-109640-CS- INDV / CONTRATACIÓN DE SERVICIO ESPECIALIZADO PARA LA REVISIÓN Y ADAPTACIÓN DEL CUESTIONARIO DE LA Improving the Institutional ENCUESTA Y LA IBRD / 86820 Framework of the National Posterior Individual Limited 8,000.00 0.00 Bajo Revision 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-12-05 ELABORACIÓN DEL STI System MANUAL DEL ENCUESTADOR PARA LA PRIMERA ENCUESTA DE PERCEPCIÓN SOCIAL DE LA CIENCIA Y TECNOLOGÍA EN EL PERÚ 2019. PE-FONDECYT-109641-CS- INDV / CONTRATACIÓN DE SERVICIO ESPECIALIZADO PARA LA REVISIÓN Y ADAPTACIÓN DEL CUESTIONARIO DE LA Improving the Institutional ENCUESTA Y LA IBRD / 86820 Framework of the National Posterior Individual Limited 14,000.00 0.00 Bajo Revision 2019-04-08 2019-04-13 2019-05-04 2019-06-08 2019-12-05 ELABORACIÓN DEL STI System MANUAL DEL ENCUESTADOR PARA LA PRIMERA ENCUESTA DE PERCEPCIÓN SOCIAL DE LA CIENCIA Y TECNOLOGÍA EN EL PERÚ 2019. PE-FONDECYT-108342-CS- CDS / SERVICIO ESPECIALIZADO PARA EL ANÁLISIS E INTERPRETACIÓN DE RESULTADOS DEL Improving the Institutional ANEXO N° 1 FORMATO Selección directa IBRD / 86820 Framework of the National Previa Direct 9,000.00 0.00 Cancelado 2019-03-29 2019-04-08 2019-06-12 2019-12-09 DE RECOLECCIÓN DE de consultores STI System DATOS , COMO PARTE DEL ESTUDIO DE LINEA BASE DEL GASTO PUBLICO EN CIENCIA, TECNOLOGÍA E INNOVACIÓN EN EL PERÚ PE-FONDECYT-111845-CS- CDS / SERVICIO ESPECIALIZADO PARA EL ANÁLISIS E INTERPRETACIÓN DE RESULTADOS DEL Improving the Institutional ANEXO N° 1 FORMATO Selección directa IBRD / 86820 Framework of the National Posterior Direct 9,000.00 0.00 En ejecución 2019-04-24 2019-05-04 2019-07-08 2020-01-04 DE RECOLECCIÓN DE de consultores STI System DATOS , COMO PARTE DEL ESTUDIO DE LINEA BASE DEL GASTO PUBLICO EN CIENCIA, TECNOLOGÍA E INNOVACIÓN EN EL PERÚ PE-FONDECYT-111857-CS- INDV / CONTRATACIÓN DE SERVICIO ESPECIALIZADO PARA LA ELABORACIÓN DEL PERFIL DE LA EMPRESA QUE SE ENCARGUE DE Improving the Institutional LA REALIZACIÓN Y IBRD / 86820 Framework of the National Posterior Individual Limited 8,000.00 0.00 En ejecución 2019-04-24 2019-04-29 2019-05-20 2019-06-24 2019-12-21 SUPERVISION DE LA STI System EJECUCIÓN DE LA ENCUESTA DE PERCEPCIÓN SOCIAL DE LA CIENCIA Y TECNOLOGÍA EN EL PERU 2019 PE-FONDECYT-116770-CS- INDV / Especialista en SIGA-MEF para el Proyecto Mejoramiento y ampliación Project Management and Ejecución IBRD / 86820 Posterior Individual Limited 28,700.00 0.00 2019-05-27 2019-06-01 2019-06-22 2019-07-27 2020-01-23 de los servicios del Sistema Monitoring & Evaluation pendiente Nacional de Ciencia, Tecnología e Innovación Tecnológica (SINACYT) PE-FONDECYT-116779-CS- CDS / Analista de Adquisiciones 1 para el Proyecto Mejoramiento y Project Management and Selección directa ampliación de los servicios IBRD / 86820 Posterior Direct 32,300.00 0.00 En ejecución 2019-05-27 2019-06-01 2019-08-05 2020-02-01 Monitoring & Evaluation de consultores del Sistema Nacional de Ciencia, Tecnología e Innovación Tecnológica (SINACYT) PE-FONDECYT-116791-CS- CDS / Analista de Adquisiciones 2 para el Proyecto Mejoramiento y Project Management and Selección directa Ejecución ampliación de los servicios IBRD / 86820 Posterior Direct 32,300.00 0.00 2019-05-28 2019-06-02 2019-08-06 2020-02-02 Monitoring & Evaluation de consultores pendiente del Sistema Nacional de Ciencia, Tecnología e Innovación Tecnológica (SINACYT) PE-FONDECYT-116992-CS- INDV / Supervisor Financiero de la Unidad de Seguimiento y Monitoreo en el Marco del Proyecto Research and Innovation Ejecución IBRD / 86820 Posterior Individual Limited 35,900.00 0.00 2019-05-28 2019-06-02 2019-06-23 2019-07-28 2020-01-24 Mejoramiento y Ampliación Capacity pendiente del Sistema Nacional de Ciencia, Tecnología e Innovación Tecnológica - SINACYT PE-FONDECYT-121561-CS- INDV / Consultoría para el seguimiento de las Project Management and Ejecución actividades y la formulación IBRD / 86820 Posterior Individual Open 20,600.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 Monitoring & Evaluation pendiente de documentos de las iniciativas de vinculación academia-industria 6 PE-FONDECYT-121562-CS- INDV / Consultoría para el seguimiento de las Project Management and Ejecución actividades y la formulación IBRD / 86820 Posterior Individual Open 20,600.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 Monitoring & Evaluation pendiente de documentos de las iniciativas de vinculación academia-industria 7 Page 13 PE-FONDECYT-121563-CS- INDV / Consultoría para el seguimiento de las Project Management and Ejecución actividades y la formulación IBRD / 86820 Posterior Individual Open 20,600.00 0.00 2019-06-28 2019-08-16 2019-09-06 2019-10-11 2020-04-08 Monitoring & Evaluation pendiente de documentos de las iniciativas de vinculación academia-industria 8 PE-FONDECYT-124589-CS- INDV / ESPECIALISTA EN DESARROLLO DE SOFTWARE DE LA Research and Innovation PLATAFORMA PARA LOS IBRD / 86820 Posterior Individual Limited 29,000.00 0.00 En ejecución 2019-07-24 2019-07-29 2019-08-19 2019-09-23 2020-03-21 Capacity PROCESOS OPERATIVOS DE LAS UNIDADES ORGÁNICAS DEL FONDECYT PE-FONDECYT-124590-CS- INDV / ESPECIALISTA EN ANÁLISIS Y DISEÑO DE SOFTWARE DE LA Research and Innovation PLATAFORMA PARA LOS IBRD / 86820 Posterior Individual Limited 29,000.00 0.00 En ejecución 2019-07-24 2019-07-29 2019-08-19 2019-09-23 2020-03-21 Capacity PROCESOS OPERATIVOS DE LAS UNIDADES ORGÁNICAS DEL FONDECYT PE-FONDECYT-126726-CS- INDV / Consultor Individual Especialista Ambiental para el Proyecto Mejoramiento y Project Management and Ejecución ampliación de los servicios IBRD / 86820 Posterior Individual Limited 36,000.00 0.00 2019-08-08 2019-08-13 2019-09-03 2019-10-08 2020-04-05 Monitoring & Evaluation pendiente del Sistema Nacional de Ciencia, Tecnología e innovación Tecnológica (SINACYT) PE-FONDECYT-128047-CS- INDV / SOPORTE ADMINISTRATIVO PARA Strategic Programs: LA MEJORA DE LA Productivity & Innovation GESTIONES DEL SUB Ejecución IBRD / 86820 Fund and Competitiveness Posterior Individual Limited 21,800.00 0.00 2019-08-16 2019-08-21 2019-09-11 2019-10-16 2020-04-13 COMPONENTE 2.2 DEL pendiente Reinforcement Initiatives PROYECTO DE for Productive Innova tion MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DEL SINACYT. PE-FONDECYT-127623-CS- INDV / CONSULTORÍA PARA LA COORDINACIÓN, SUPERVISIÓN Y CONSOLIDACIÓN DE Improving the Institutional PRODUCTOS DE LA Ejecución IBRD / 86820 Framework of the National Posterior Individual Limited 34,200.00 0.00 2019-08-16 2019-08-21 2019-09-11 2019-10-16 2020-04-13 ACTIVIDAD 1.1.1 PARA LA pendiente STI System IMPLEMENTACIÓN DE MEJORAS AL MARCO INSTITUCIONAL Y ORGANIZACIONAL DEL SINACYT. PE-FONDECYT-128032-CS- INDV / ESPECIALISTA EN CONTABILIDAD PARA EL PROYECTO MEJORAMIENTO Y Project Management and Ejecución AMPLIACIÓN DE LOS IBRD / 86820 Posterior Individual Limited 24,900.00 0.00 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 Monitoring & Evaluation pendiente SERVICIOS DEL SISTEMA NACIONAL DE CIENCIA, TECNOLOGÍA E INNOVACIÓN TECNOLÓGICA . PE-FONDECYT-128038-CS- INDV / CONSULTORIA INDIVIDUAL PARA LA GESTIÓN DEL PLAN MULTIANUAL DE ACTIVIDADES DE LA Research and Innovation Ejecución DIRECCIÓN DE IBRD / 86820 Posterior Individual Limited 34,200.00 0.00 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 Capacity pendiente POLITICAS Y PROGRAMAS DEL CONCYTEC EN EL MARCO DEL PROYECTO DE MEJORAMIENTO Y AMPLIACIÓN DE LOS SERVICIOS DEL SINACYT. PE-FONDECYT-128041-CS- INDV / CONTRATAR CONSULTOR DE SOPORTE Improving the Institutional ADMINISTRATIVO PARA Ejecución IBRD / 86820 Framework of the National Posterior Individual Limited 21,800.00 0.00 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 LA GESTION DEL SUB pendiente STI System COMPONENTE 1.1 DEL PROYECTO DE MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DEL SINACYT. PE-FONDECYT-128059-CS- INDV / PROFESIONAL PARA GESTIONAR EL PROCESO DE EVALUACIÓN Y SELECCIÓN RESPECTO A LOS SUBCOMPONENTES: Research and Innovation Ejecución INCREMENTO DE LA IBRD / 86820 Posterior Individual Limited 22,000.00 0.00 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 Capacity pendiente DISPONIBILIDAD DE CAPITAL HUMANO PARA CIENCIA, TECNOLOGÍA E INNOVACIÓN Y ASIGNACIÓN INTEGRAL DE RECURSOS PARA LOS SUBPROYECTOS DE I+D+i Page 14