Western Economic Corridor and Regional Enhancement Program   (WeCARE)    Environmental and Social Impact Assessment (ESIA)  Jashore‐Jhenaidah Road Corridor    Prepared For  Roads & Highways Department (RHD)  Prepared By    Development Research Initiative (dRi)  House ‐8/7, Road no‐01,   Block‐D, Section‐ 15, Kafrul  Dhaka‐1216, Bangladesh  Phone and fax: +88‐02‐9030828   Mob: 01713504255  E‐mail: contact@dri‐int.org, developmentr.initiative@gmail.com  and  Development Solutions Consultant Limited (DSCL) House-734 (5-B), Road-10, Avenue-04, DOHS Mirpur,   Dhaka -1216, Bangladesh, Tel: +8801822758548 Email: dscl@dsclbd.com; Website: www.dsclbd.com    Western Economic Corridor and Regional Enhancement Program (WeCARE)     Table of Contents  ABBREVIATIONS AND ACRONYMS ........................................................................................................ vii  EXECUTIVE SUMMARY ........................................................................................................................... ix  1  INTRODUCTION ............................................................................................................................. 17    Background ........................................................................................................................... 17    Purpose of the Environmental and Social Impact Assessment ............................................. 17    Scope of the ESIA .................................................................................................................. 20    Identification of mitigation measures in the form of an Environmental and Social  Management Plan (ESMP) Approach and Methodology .................................................................. 20  1.4.1  Approach and Methodology ......................................................................................... 20  1.4.2  Baseline Data Collection and Analysis .......................................................................... 24  1.4.3  Impact Assessment Methods ........................................................................................ 25  1.4.4  Geographical Information Systems (GIS) ...................................................................... 26    Methods for Mitigation and Management ........................................................................... 26    DESCRIPTION OF THE PROJECT ............................................................................................. 26  1.6.1  WeCARE Program .......................................................................................................... 26  1.6.2  Descripition of the Jhenaidah‐Jashore(J‐J) Road Corridor ............................................ 27  1.6.3  ...................................................................................................... 29  Need for the Project  1.6.4  Design Features ............................................................................................................. 29  1.6.5  Design of the Project ..................................................................................................... 30  2  LEGAL AND POLICY FRAMEWORK ............................................................................................. 40    Regulatory Requirements for the Project ............................................................................. 40    World Bank Environment and Social Framework and Standards (ESS) ................................ 45    Clearances/Permissions required for the Project Road ........................................................ 53  3  ENVIRONMENTAL AND SOCIAL BASELINE .................................................................................... 54    General .................................................................................................................................. 54    Physical Environment ............................................................................................................ 54  3.2.1  Climate .......................................................................................................................... 54  3.2.2  Topography ................................................................................................................... 57  3.2.3  Physiographic Features ................................................................................................. 58  3.2.4  ............................................................................................................ 58  Geology and Soil  3.2.5  Water Resources and Hydrology .................................................................................. 59  3.2.6  Seismicity ...................................................................................................................... 63  3.2.7  ............................................................................................................. 66  Natural Hazards  3.2.8  ....................................................................................................... 69  Ambient Air Quality  ESIA for Jashore-Jhenaidah Road Corridor i | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) 3.2.9  Noise and Vibration ...................................................................................................... 69    Biological Environment ......................................................................................................... 72  3.3.1  ...................................................................................................... 72  Bio‐ecological Zones  3.3.2  .................................................................................................................... 73  Biodiversity  3.3.3  Environmentally Sensitive Areas ................................................................................... 78    Socio‐Economic Condition .................................................................................................... 80  3.4.1  Background Characteristics ........................................................................................... 80  3.4.2  Household Characteristics ............................................................................................ 81  3.4.3  Education Status of HH ................................................................................................. 82  3.4.4  Participation in NGO and Government Safety Net Programs ....................................... 83  3.4.5  Land and Dwelling ......................................................................................................... 84  3.4.6  Sublease Land/Lease/Mortgage/Rent .......................................................................... 86  3.4.7  House Ownership Status ............................................................................................... 87  3.4.8  Materials Used to support Roof Wall and Floor ........................................................... 87  3.4.9  Household Assets .......................................................................................................... 88  3.4.10  Business Activities, Savings and Loan ........................................................................... 88  3.4.11  Community .................................................................................................................... 89  3.4.12  Poverty Status ............................................................................................................... 91  3.4.13  Gender‐based Perception and Violence ....................................................................... 92  4  STAKEHOLDER CONSULTATIONS & INFORMATION DISCLOSURE ................................................. 94    Purpose of Public Participation ............................................................................................. 94    Past Consultation and Participation during Feasibility Stage ............................................... 95    .................................................................. 95  Consultation Meetings at Detailed Design Stage    Consultation at ESIA Preparation Stage ................................................................................ 96  4.4.1  ................... 96  Summary of Consultation Meeting with Jashore & Jhenaidah Officials (I)  4.4.2  Summary of FGD Meeting with Jashore & Jhenaidah Community Members (II) ......... 97  4.4.3  Summary of Consultations with Haibatpur Union Parshad Chairman (III) ................... 98  4.4.4  Summary of Consultations with Community Leader (IV).............................................. 99  4.4.5  Summary of Consultations with Women (V) ................................................................ 99    Stakeholders ....................................................................................................................... 100  5  ANALYSIS OF ALTERNATIVES ....................................................................................................... 102    Widening or By‐pass or Overpass in Commercial and Market Areas ................................. 102    Diversions and By Passes .................................................................................................... 102  6  ENVIRONMENTAL AND SOCIAL RISKS AND IMPACTS AND MITIGATION MEASURES ................. 103    Introduction ........................................................................................................................ 103    Risk Screening ..................................................................................................................... 103  ESIA‐ Jashore‐Jhenaidah Road Corridor ii | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE)   Anticipated Adverse Impacts and Mitigation Measures ..................................................... 108  6.3.1  Related to Assessment and Management of E&S risk and impact (ESS 1) ................. 108  6.3.2  Relating to Labor and Working Conditions (ESS 2) ..................................................... 109  6.3.3  Relating Resource Efficiency and Pollution Prevention and Management (ESS 3)..... 112  6.3.4  E&S risks and impacts relating to Community Health and Safety (ESS 4) .................. 130  6.3.5  Related on land & assets (ESS 5) ................................................................................. 136  6.3.6  Relating to Bio‐diversity & Living Natural Resources (ESS 6) ...................................... 137  6.3.7  Tribal/Indigenous Population (ESS 7) .......................................................................... 140  6.3.8  Related on Impacts on Cultural Heritage (ESS 8) ........................................................ 140  7  ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN ............................................................... 141    Introduction ........................................................................................................................ 141    ............................................................................................................................ 141  Objectives    PRE‐CONSTRUCTION ACTIVITIES ......................................................................................... 141    CONSTRUCTION STAGE ....................................................................................................... 142    Operation Stage .................................................................................................................. 142    ESMP ................................................................................................................................... 143    Institutional Arrangements for ESMP Implementation ...................................................... 180    Environmental and Social Monitoring Cost Estimation ...................................................... 180  8  Institutional Framework ............................................................................................................. 181    Introduction ........................................................................................................................ 181    Institutional Responsibilities ............................................................................................... 182  8.2.1  Ministry of Road Transport and Bridges (MoRTB) ...................................................... 182  8.2.2  Inter‐ministerial Steering Committee ......................................................................... 182  8.2.3  ............................................................................... 182  Roads and Highways Department  8.2.4  Environment and Social Management Unit ................................................................ 182  8.2.5  RHD Environment and Social Circle ............................................................................ 182  8.2.6  Project Implementation Unit ...................................................................................... 183  8.2.7  Construction Supervision Consultant (CSC) ................................................................ 184  8.2.8  Contractor ................................................................................................................... 185    Capacity Assessment ........................................................................................................... 185  8.3.1  Experience of RHD in Managing World Bank’s ESS related Challenges ...................... 185        ESIA‐ Jashore‐Jhenaidah Road Corridor iii | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) List of Annexure  Annex A: Environmental and Social Standard (ESS) of the World Bank  Annex B: Discussion of the Air Pollution Model and Associated Assumptions  Annex C: Details of the Air Pollution Models used to estimate and forecast the data  Annex D: Test Results of Soil Quality  Annex E: Test Results of Surface Water Quality  Annex F: Test Results of Groundwater Quality  Annex G: Important Environmental and Social Features along the ROW  Annex H: Details of Consultation Meetings  Annex I: List of Alignment Diversion and Impacted Bazars  Annex J: Air Pollution (CALINE 4) Modelling Map    ESIA‐ Jashore‐Jhenaidah Road Corridor iv | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) List of Tables  Table 1.1: Type of Structures  ...................................................................................................... 27  Table 1.2: Main Design Element of the J‐J road .......................................................................... 30  Table 2.1: Summary of Applicable Environment Regulation Regulations of GOB ........................ 40  Table 2.2:  Applicability of the ESSs to the Project ...................................................................... 46  Table 3.1: List of Plants in the Project Area ................................................................................ 73  Table 3.2: List of Fauna Identified in and around the Project Area .............................................. 75  Table 3.3: Basic HH features in the Surveyed Regions ................................................................. 80  Table 3.4: Distribution of Family Size ......................................................................................... 81  Table 3.5: Distribution of Age ..................................................................................................... 81  Table 3.6: Marital Status of Individuals Living in HHs  .................................................................. 82  Table 3.7: School Going Status ................................................................................................... 82  Table 3.8: NGO Participation ...................................................................................................... 84  Table 3.9: Government Safety Net Programs  .............................................................................. 84  Table 3.10:  Land and Dwellings Details ...................................................................................... 84  Table 3.11:  Summary Statistics .................................................................................................. 85  Table 3.12:  Process of Ownership .............................................................................................. 85  Table 3.13:  Value of Land .......................................................................................................... 85  Table 3.14:  Type of Contract...................................................................................................... 86  Table 3.15:  Type of Contract...................................................................................................... 86  Table 3.16: House Ownership Status .......................................................................................... 87  Table 3.17: Value of House  ......................................................................................................... 87  Table 3.18: Materials Used (Roof) .............................................................................................. 87  Table 3.19: Materials Used (Wall) .............................................................................................. 87  Table 3.20: Materials Used (Floor) ............................................................................................. 88  Table 3.21:   Value of HH Assets in BDT ...................................................................................... 88  Table 3.22:   HH Members Profession ......................................................................................... 88  Table 3.23: Individuals Monthly Income ..................................................................................... 89  Table 3.24:  Savings Pattern ....................................................................................................... 89  Table 3.25:   Distribution of Loan Amount in BDT ....................................................................... 89  Table 3.26: Types of Financial Institution ................................................................................... 89  Table 3.27:  Type of Individuals most affected by the project ..................................................... 90  Table 3.28:  Type of Individuals Most Benefitted by the Project ................................................. 90  Table 3.29:  Gender Perception Indicators .................................................................................. 92  Table 4.1: Consultation Meeting Held During EIA Preparation .................................................... 95  Table 6.1: Risk Screening Criteria ............................................................................................. 103  Table 6.2: Generic Adverse Impact Assessment Matrix along the J‐J Road ................................ 104  Table 6.3: Estimated Total Pavement Materials ....................................................................... 112  Table 6.4:  Fuel efficiency in km/l ............................................................................................. 117  Table 6.5:  Emission Standards of Fleet (%) .............................................................................. 117  Table 6.6:  Annual Average Daily Traffic (AADT) for Jashore‐Jhenaidah Road (47.2 Km)  ............ 118  Table 6.7:  Normal Traffic Growth Rates for Different Category of Vehicles .............................. 118  Table 6.8:  Input Parameters for TEEMP ................................................................................... 118  Table 6.9:  CO2 Emission Factors for different vehicle types ...................................................... 119  Table 6.10:  Output and Output Intensity of CO2, PM and NOx ................................................. 119  Table 6.11 Predicted noise level by vehicle type ....................................................................... 121  Table 6.12 Predicted noise level with relation to receivers ....................................................... 126  Table 6.13: Results of Barrier analysis and proposed barrier with length and materials ............ 128  Table 6.14: Details of Noise Barrier provided at sensitive receptors ......................................... 129  Table 6.15: Estimated Hazardous waste during Project Construction Phase ............................. 134  Table 6.16: Estimated Solid waste Generation during Project Construction Phase .................... 135  Table 6.17: List of Plants in the Project Area ............................................................................ 137  ESIA‐ Jashore‐Jhenaidah Road Corridor v | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) Table 8.1: Capacity Building ..................................................................................................... 189    List of Figures  Figure ES‐0.1: Project Location Map ............................................................................................. x  Figure 1.1: Project Location Map ................................................................................................ 18  Figure 1.2: Typical Cross Section with Bus Bay at Urban Area ..................................................... 22  Figure 1.3: Cross‐section for rural area (5.0m median, 5.5m SMVT Lane).................................... 22  Figure 1.4: Cross‐section at constraint area (1.2m median) ........................................................ 23  Figure 1.5: Cross‐section at urban area (1.2m median) ............................................................... 23  Figure 1.6: Project Location Map ................................................................................................ 29  Figure 1.7 Drainage Patterns of the Project ................................................................................ 38  Figure 3.1: Temperature and Rainfall in Project Area ................................................................. 55  Figure 3.2: Number of Sunny, Rainfall and Cloud Coverage Days in Project Area ........................ 56  Figure 3.3: Wind rose Diagram in Project Area ........................................................................... 57  Figure 3.4: General Topography of the Project Road Area .......................................................... 58  Figure 3.5: Soil Sampling from the Project Area .......................................................................... 59  Figure 3.6: Surface Water Bodies along the Project Road ........................................................... 60  Figure 3.7: Sampling and Onsite Test of Surface Water Quality in the Project Area .................... 61  Figure 3.8: Hydrological Network of the Project Area ................................................................. 62  Figure 3.9: Sampling and Onsite Test of Groundwater Quality in the Project Area ...................... 63  Figure 3.10: Seismic Zone and Activity of the Project Road ......................................................... 65  Figure 3.11: Cyclone Risk Zone of the Project Road .................................................................... 67  Figure 3.12: Flood Zone of the Project Road ............................................................................... 68  Figure 3.13: Ambient Air Quality Sampling in the Project Area ................................................... 69  Figure 3.14: Noise Level Measurement in the Project Area ......................................................... 70  Figure 3.15: Vibration Level Measurement in the Project Area ................................................... 71  Figure 6.1: Result Output of TNM ............................................................................................. 126  Figure 6.2: Noise Barrier Analysis ............................................................................................. 128  Figure 6.3: Traffic Calming measures at Blind Curves/Hair Pin Bends  ........................................ 131  Figure 6.4: Traffic Calming measures at School zones ............................................................... 131  Figure 6.5: Traffic Calming measures at School zones ............................................................... 132  Figure 8.1: Institutional Framework ......................................................................................... 181  ESIA‐ Jashore‐Jhenaidah Road Corridor vi | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) ABBREVIATIONS AND ACRONYMS  ADB  Asian Development Bank  BBS   Bangladesh Bureau of Statistics   BCAS   Bangladesh Centre for Advance Studies   BCR   Building Construction Rules   BECA   Bangladesh Environmental Conservation Act   BRTA   Bangladesh Road Transport Authority   BECR   Bangladesh Environmental Conservation Rules   BOD  Biological Oxygen Demand  BOQ  Bill of Quantity  BWDB  Bangladesh Water Development Board  CITES  Convention on International Trade of Endangered Species  COD  Chemical Oxygen Demand  CPR  Community Property Resources  DCs   Deputy Commissioners   DGWT  Deep Ground Water Table  DO  Dissolve Oxygen   DoE   Department of Environment   EA   Environmental Assessment   EC   Executive Committee   ECC   Environmental Clearance Certificate   EIA   Environmental Impact Assessment   EMP  Environmental Management Plan  ESCP  Environmental and Social Commitment Plan  ESMP  Environmental and Social Management Plan  ESF  Environmental and Social Framework  ESSs  Environmental and Social Standards  FAO   Food and Agriculture Organization   FD  Forest Department  GHG  Greenhouse Gas  GIS  Geographical Information System  GOB  Government of Bangladesh  ESIA‐ Jashore‐Jhenaidah Road Corridor 7 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) GRC  Grievance Redress Committee  GRM  Grievance redress mechanism  GW  Groundwater  HFL  Highest Flood Level  IEE   Initial Environmental Examination   IECs   Important Environment Components   LGED   Local Government Engineering Department   LGRD &C   Local Government Rural Development and Cooperative   MOA   Ministry of Agriculture   MoRTB  Ministry of Road Transport & Bridges  MOEFCC  Ministry of Environment, Forest and Climate Change  NCS   National Conservation Strategy   NEC   National Environmental Council   NEP   National Environmental Policy   NEMAP   National Environmental Management Action Plan   NGO  Non‐Governmental Organization  NOX  Oxides of Nitogen  PAPs   Project Affected Persons   PIU  Project Implementation Unit  PM  Prime Minister  PM  Particulate Matter  PMMU  Project Monitoring and Implementation Unit  PPEs   Personal Protection Equipment   RHD   Roads and Highways Department   RoW  Right of Way  SAFTA  South Asian Free Trade Area  SCR   South Central Region   SWR   South‐ West Region  SGWT  Shallow Ground Water T able  SOX  Oxides of Sulphur  SPM  Suspended Particulate Matter  TA  Technical Assistant  TDS  Total Dissolve Solids  ESIA‐ Jashore‐Jhenaidah Road Corridor 8 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) TSS  Terms of Reference  ToR  Total Suspended Solids  USDA   United States Department of Agriculture   WARPO  Water Resources Planning Organization  WB  World Bank  WMP  Waste Management Plan        ESIA‐ Jashore‐Jhenaidah Road Corridor 9 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) EXECUTIVE SUMMARY  1.0 Project Description    1. Road transport accounts for 70 percent for passenger and 60 percent for freight traffic in Bangladesh.  The total road network size of the country is roughly 375,000 km (road density of roughly 250 km per  100 km2), reflecting the progress in improving connectivity access. The rural road network makes up  94 percent of the network, and Bangladesh has one of the highest scores on the Rural Access Index.  Yet, despite improvements in access, the overall quality of the road network remains poor. Only 27  percent of the rural roads  and  40 percent of the main roads  are paved, half  of which are  in good  condition. Currently, most inter‐district roads and highways do not conform to the standards of the  Asian Highway norms. To improve the condition of the Jhenaidah to Jashore road, the Government of  Bangladesh (GoB) has requested the World Bank to finance the upgradation of the existing 2‐lane  highway to a 4‐lane road through the WeCARE project. The total length of the road is approximately  48.7 km. This road connects Natore, Pabna, Kushtia districts to Jashore, Khulna and Satkhira districts.     2.0 Description of the Jhenaidah‐Jashore Route    2. The  Jhenaidah  –  Jashore  road  begins  at  Al‐Hera  Mor  in  Jhenaidah  and  continues  till  Murali  Mor,  Jashore  (48.7km  approx.).  The  route  connects  with  the  existing  N7  national  highway  heading  in  a  westerly direction through Magura and on to Jhenaidah before turning south to Jashore and finally  south‐east to Khulna. These districts are connected by roads, railway, and river launches (passenger  and cargo). The nearest airport is situated at Jashore (within 5 km distance from the starting point).  The  horizontal  alignment  of  the  existing  road  is  open  and  free‐flowing;  however,  there  are  constrictions  to the alignment  in  a number of areas. During the field visit, several  structures were  observed on both sides of the highway corridor. Examples of the observed structure include but not  limited to schools, colleges, medical facilities, mills and factories, a portion of the Jashore cantonment,  bazaars, cell phone towers, business and government‐owned structures.    3. The road is situated close to the railway track, and this feature presents a number of challenges. The  road and railway track run parallel to each other (in some locations) and the J‐J road bypasses the  railway line at a number of locations. Agricultural lands and trees were observed on both sides of the  roads. Moreover, the J‐J road is joined by various small and semi‐paved road originating from nearby  villages, and unions. While the road is mostly smooth, however, there are a number of locations (8‐ 10) where the state of the road can be considered risky. This road is usually frequented by bus, trucks,  cars and motorcycles, and locally improvised four and three wheelers (nasimun and karimun). The  presence of smaller vehicles often leads to accidents on this route. Shalabhara part of the J‐J road is  infamous for the number of accidents observed per year. Temporary markets are set up on a regular  basis in different places of the roadside that exacerbate the risks of accidents.     4. Currently,  the  width  of  the  existing  road  is  approximately  7.5  to  8  meters.  Upgrading  the  2‐lane  highway into a four‐lane highway may require an increase in the RoW to approximately 50 to 60 meter  in rural areas and 30 to 40 meter in urban areas.  In some sections, the present RoW and its adjacent  RHD lands in shoulders are sufficient for widening the road; however, this is not the case for the entire  road, and hence land acquisition will be required. Land acquisition and civil works are likely to trigger  involuntary  physical  (loss  of  agricultural  and  homestead  land)  and  economic  displacement  (loss  of  income, business structures) and may cause environmental degradation through loss of trees along  ESIA‐ Jashore‐Jhenaidah Road Corridor 10 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) the ROW, including very old trees, changes to local drainage patterns and health and safety of workers  and communities.         Figure ES‐0.1: Project Location Map  5. The total number of bridges and culverts in the nearby area is 220, of which 2 (two) road bridges, 1  rail over bridge and 8 (eight) rail overpasses, and 187 are culverts are over 100 meters long. Roadside  drainage shall also be required at a number of locations where the road passes through markets and  local markets (bazaars).     3.0 Purpose and Scope of ESIA    6. An  Environmental  and  Social  Impact  Assessment  (ESIA)  of  the  project  is  required  to  assess  the  environmental and social risks and impacts of the upgradation of Jashore‐Jhenaidah Road from 2‐lane  to 4‐lane road and to develop measures based on mitigation hierarchy to manage environmental and  social risks and impacts. RHD prepared an EIA in 2015 for the same road section. The EIA has been  updated  through  this  ESIA  to  ensure  that  the  present  ground  reality  is  accounted  for  and  the  ESIA‐ Jashore‐Jhenaidah Road Corridor 11 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) requirements  of  the  World  Bank’s  ESF  are  met.  Thus.  This  ESIA  is  based  on  a  preliminary  design  prepared  for  Jashore‐Jhenaidah  Road  by  ADB  and  is  prepared  in  accordance  with  the  World  Bank  Environmental and Social Framework (ESF) and its relevant Environmental and Social Standards (ESSs)  as  well  as  with  the  Government  of  Bangladesh’s  Environmental  Conservation  Rules  1997,  EIA  Guidelines 1997 and other relevant laws and policies. This ESIA will be updated and finalized based  on the detailed engineering design of Jashore‐Jhenaidah Road, which will be undertaken after World  Bank Board approval of the project.      7. The scope of the updated ESIA report describes the following most important features:  i. A  general  description  of  the  project  and  existing  physical,  biological  and  socio‐economic  conditions;   ii. Analysis  of  different  alternatives  to  the  project  in  terms  of  environmental  and  social  perspectives; identification and assessment of the potential risks and impacts on the natural  and human environment in the project area, from the construction of the project;   iii. Consultation with the locals/stakeholder involving concerned people in order to identify and  act on any undocumented or perceived environmental issues and;   iv. Identification of mitigation measures in the form of an Environmental and Social Management  Plan (ESMP).    4.0 Legal and Institutional Framework    8. The ESIA presents a review of the existing laws and policies related to the environmental and social  dimensions of the Jashore‐Jhenaidah road corridor project. Along with providing a summary of the  relevant GoB laws and policies, it presents the World Bank’s Environmental and Social Standards (ESS).  Gaps  between  the  relevant  government  laws  and  World  bank  ESS  are  also  presented  along  with  remedial measures to address the gaps.     5.0 Environment and Social Baseline    9. The baseline conditions of environmental quality at the project site  and the preliminary road design  serve as the basis for identifying, predicting and assessing impacts. The Baseline environmental quality  is assessed through field studies within the RoW for the different components of the environment,  viz. Air, noise, water, land, socio‐economic, etc. along with the project activities.    10. The project area (Jashore to Jhenaidah road) corridor is located in the south‐western region of the  country.  Though  far  less  than  half  of  Bangladesh  is  in  the  tropics,  the  influence  of  the  Himalayan  Mountain Range has created a tropical macroclimate over most of East Bengal's landmass.    11. In Jashore, the average wind speed ranges from 5 to 19 km/h during most of the months in a given  year. In the project location, the extremes of the zones to the north are somewhat tempered in the  south‐west zone. Rainfall varies from 1,500 mm to 1,800 mm. The mean highest possible summer  temperature is less than 35 ° C. The general topography of the project area comprises of floodplains  in the majority of the road and terraces. The topography of the project area slopes from north to  south with elevation ranged from 15 m a.m.s.l to 11 m a.m.s.l. The project road alignment area lies  mostly in the north‐western and south‐western part of the country and depends on the Ganges River  for freshwater supply. The entire road alignment runs through Ganges Floodplain physiographic unit.  ESIA‐ Jashore‐Jhenaidah Road Corridor 12 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) The general soil types of the project road area predominantly include the Calcareous Alluvium, and  Calcareous Dark Grey Floodplain soils and Calcareous Brown Floodplain soils. The quality of the local  soil was identified to characterize the baseline status. During the survey period, soil samples were  collected from the possible 2 locations. The samples were sent to the laboratory of Dhaka University.    12. The project road alignment crosses Bhairab River, Chitra River, Begobati River at several locations.  There are also significant numbers of beels (stagnant water body) and canals in and around the project  locations. Besides, there are numerous ponds and ditches available in the project area. The surface  water  quality  assessment  in  the  project  influence  area  has  been  carried  out  for  the  most  critical  parameters. The sampling was undertaken from the rivers of the proposed bridge locations (Bhairab  River, Begobati river, Bishkhali River, Chitra River) during the field survey. From quality test report, it  has been anticipated that the maximum parameter is complied with the national standard except for  a  few  parameters.  The  deep  groundwater  table  (DGWT)  in  terrace  land  (Project  area)  fluctuates  between 15.0m and 20.0m during the dry season and reaches to the surface during the rainy season.  Groundwater in terrace lands is over exploited due to domestic, industrial and agricultural uses and  the draw down is near to 7.0m during the dry season.    13. As per the seismic zone classifications, project road falls in zone III means low seismic intensity. The  project area does not fall under the risk zone of the cyclone. The drainage of the surrounding areas is  mostly dependent on the water levels of the peripheral rivers. Therefore, the project area is risk free  from cyclone and flood hazard.    14. Air  pollution  is  localized  and  comparatively  moderate  in  the  project  corridor.  Air  pollution  in  the  project area is from road dust, black smoke from diesel engines, construction dust, windblown dust  from agricultural lands, domestic heating and cooking, and transportations.    15. According  to  World  Health  Organization’s  Guidelines  for  Community  Noise  (1999),  daily  sound  pressure levels of 50 decibels (dB) or above can create discomfort amongst humans, while ongoing  exposure to sound pressure levels over 85 dB is usually considered the critical level for temporary  hearing damage. The vibration level of the surroundings of the project area is insignificant. However,  there is a negligible vibration level from the traffic movement on the nearby road.    16. The project is located on flat land with mixed vegetation and has a low chance of being inundated.  Crops, vegetables are cultivated at the surrounding mainly include rice, wheat, tobacco, corn, nut,  rabi (winter) crops and variety of homestead vegetables. Different types of aquatic flora species were  recorded along the project roadside. The ponds and burrow pits within RoW are presently used for  fish culture or fish stocking. There is no natural stream or wetland within the RoW, so upgrading the  4‐lane will  not impact local or regional hydrology.  There  are  hardly  any physical structures and/or  cultural heritage sites along the highway or within 5.0 km of the route. Marjat Baor is an ecologically  critical area situated in the Kaliganj Upazila of Jhenaidah, which is more than 5 km away from the  project  site.  So,  there  is  no  environmental  sensitive  location  within  a  5  km  radius  of  the  project  influenced area.    17. A  Social  Survey  was  carried  out  in  the  project  intervention  areas  to  create  a  profile  of  the  socio‐ economic features of the communities. The survey team interviewed 200 households (HHs) across  Jashore and Jhenaidah. Out of the 200 surveyed HHs, 55 HHs are located in Jashore while 145 HHs are  located in Jhenaidah. The average age of each HH is approximately 31.17. Education status indicates  ESIA‐ Jashore‐Jhenaidah Road Corridor 13 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) that 22 percent of individuals are regularly attending school. Around 10.14 percent of the surveyed  individuals  are  currently  involved  in  NGO  run  microcredit  programs.  Fourteen  percent  of  HH  are  sharecropper. About, 67.35 percent report that then the land they own is in the same district and  near  their  house.  The  average  value  of  land  owned  by  HH  is  BDT1284793  (USD15,000),  and  393  individuals residing in the surveyed HH owns land. About 60.5 percent of HH live in homestead owned  by  themselves.  The  current  mean  value  of  HH  assets  is  BDT  16,902  (USD  200).  The  respondents  strongly  suggested  that  there  is  no  restriction  in  the  project  area  related  to  land  use.  Only  2.5  of  respondents have reported restrictions, and this restriction is linked to people owning land.  Close to  80  percent  of  the  surveyed  HH  expected  that  the  project  would  benefit  the  entire  community,  followed by transport related entrepreneurs.     18. The respondents expect no negative impact as a result of labor influx since migrant labor will live in  separate  camps  and  their  movement  will  be  restricted.  Around  65  percent  of  HH  reports  that  the  market  will  be  affected  and  another  13.5  percent  of  HH  expect  schools  and  madrasas  might  be  impacted as a result of the project. The HH perception of women’s status and rights are captured by  16 questions in the survey. Broadly the results indicate that women are discriminated against in the  surveyed regions.    6.0 Vulnerable Groups    19. The  social  analysis  carried  out  thus  far  has  indicated  the  presence  of  a  number  of  vulnerable  HHs  based on age, income, disability and self‐reported food status. The approximate Bangladesh poverty  line is Tk5000 / month (equivalent to US$2/person/day). Keeping in mind the challenges faced by the  poverty line measure, the ESIA finds that there 34 HH who earn less than or equal to BDT5000 and  hence can be categorized as vulnerable. Income data also shows that there are 210 individuals in the  surveyed  HH  who  earn  less  than  or  equal  to  BDT  5000  a  month    may  become  vulnerable  due  the  project  depending on the transaction cost that might be incurred during the various phases of the  project  .(e.g.  of  transaction  cost  may  include:  additional  travelling  cost,  opportunity  cost  of  lost  income, inability to find similar jobs in the local labor market etc.). Close to 16 percent of the HH faced  some degree of food shortage. The survey has identified 68 individuals whose age is higher than 60  years and the project may impact them disproportionately. Moreover, 12 individuals suffering from a  disability  has  also  been  identified.  Acquisition  of  land  may  also  cause  some  individuals  to  lose  a  significant proportion of land (10 percent) and make these individuals or HH vulnerable as a result of  the project. However, “vulnerability” as a result of land acquisition will become apparent closer to  census survey before the RAP is designed.       7.0 Analysis of Alternatives     20. A  major  infrastructure  project  has  the  potential  to  transform  regions  and  their  economic  outlook.  However, it also has the potential to impart negative externalities on the locality. In accordance with  the principle of avoid, minimize or mitigate this ESIA considered a number of alternatives in project  design along with carrying out analysis on the no project scenario. The three options that have been  considered in the preliminary design are as follows:     Widening  of  RoW  to  allow  4  lanes  and  any  necessary  junctions  with  the  demolition  of  commercial areas: during construction this would impose a negative impact on the economic  ESIA‐ Jashore‐Jhenaidah Road Corridor 14 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) health of the area and may cause significant physical displacement. It would also worsen the  road safety for pedestrians, and other road users.   Bypass: This alternative will negatively affect agricultural land and farmers. It should only be  considered for larger centers. The health of the existing commercial area may be adversely  affected by the loss of trade due to the establishment of the bypass;   Flyover (elevated road): This may have advantages over widening the RoW, which will require  extensive  land  acquisition  and  resettlement.  However,  it  would  reduce  the  environmental  quality of the land and building below the flyover and may still require some land acquisition  and resettlement.  21. The  present  alignment  between  Jashore  and  Jhenaidah  will  require  numerous  short  distance  realignments to be straightened in order to ensure that the designed alignment is in accordance with  the  RHD  standards.  The  selection  of  these  minor  realignments  has  ensured  a  minimum  negative  impact  on  the  local  environment  and  built  environment;  and  reduced  the  need  for  more  land  acquisition and resettlement. There are a total of 10 diversions or minor diversions to straighten the  alignment or to improve approaches to new or existing bridges.    7.1 No Project Scenario    22. Given  the  transformative  implications  of  the  project,  the  no  build  alternative  is  perhaps  not  an  acceptable option. An infrastructure project in terms of the scale of the proposed project is likely to  have some negative impact, however, installing robust environmental and social measures will ensure  that the negative impacts of the project are minimized and affected HHs can be at least at the same  level  in  socio‐economic terms  if  not in  a  better position.  Therefore, at the margin, the cumulative  benefits of the project significantly outweigh the costs.      8.0 Anticipated Environmental and Social Impacts and Mitigation Measures     23. The project’s likely environmental and social risks and impacts by each relevant standard have been  assessed based on the current design and measures to mitigate them have been proposed.     8.1 E&S risks and impacts on Disadvantaged and Vulnerable persons     24. Project  shall  define  a  vulnerable  person  in  terms  of  various  criteria  including  female  headed  HH,  physically  challenged  individual,  income  of  less  than  BDT5000  per  month,  widows,  and  individuals  above  the  age  of  60  years  irrespective  of  whether  they  are  titled  land  owners.  Vulnerable  groups  would also include those farmers who (after the acquisition of land) become small/marginal farmers  and also qualify for inclusion due to income equal to or less than BDT 5000. Needs and concerns of  the  local  people  including  the  disadvantaged  groups  like  physically  challenged  people  were  considered. As mentioned earlier, the social survey has identified a number of vulnerable people in  the  area.  The  project  will  ensure  individual  and  HH  level  special  economic  package  for  vulnerable  groups and individuals as additional assistances as part of R&R measures. In addition, provision of  public amenities like toilets, drinking water provision of streetlight in settlement areas, road safety  during  construction  particularly  at  socially  sensitive  locations  such  as  hospitals,  schools,  etc.  will  consider access of differently able people.  ESIA‐ Jashore‐Jhenaidah Road Corridor 15 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE)   25. Positive cumulative impacts of the project are expected to outweigh any negative cumulative impacts.  With no new capital investment in the road, the Jashore‐Jhenaidah road would have to undergo the  challenges  of  all  future  traffic  flows,  which  are  expected  to  increase  given  the  envisaged  future  development in the area. This would create a significant environmental and social disturbance on the  existing communities residing along the present alignment. There would be sharp increases in noise  and vibration and air pollution. Not implementing the project will also have social implications.  Road  users, local communities and pedestrians would have to contend with an increased level of health  and safety risks as a result of higher traffic flow. Crossing the road would become more hazardous  and  the  roadside  communities  would  be  physically  segregated  between  the  different  sides  of  the  road. Traffic congestion would increase, and the economic cost of traffic jams is likely to impose a  negative  externality  on  the  local  economy.  Overall  the  quality  of  the  environment  and  social  conditions would deteriorate along the road corridor in the no project scenario. With the project, road  conditions will improve, health and safety will also improve with separation of Slow‐Moving Vehicle  Traffic  (SMVT)  from  fast  moving  vehicles  and  the  implementation  of  safety  design  features  of  the  road, including imposition of traffic speed limits and signages. There will also be reduction in travel  time  and  trading  of  goods  is  expected  to  increase  and  be  made  more  efficient.  A  Regional  Environmental and Social Assessment that includes a detailed Cumulative Impact Assessment will be  carried out in the Western Corridor of Bangladesh during the implementation of the project.       8.2 E&S risks on labor and working conditions      26. RHD  shall  contract  agencies  to  undertake  civil  works,  agencies/firms  to  support  core‐functions;  primary  suppliers  of  material/equipment  and  other  implementation  support  partners.  The  various  categories  of  project  workers  include:   Direct  workers,  Contracted  workers  (including  Migrant  Workers)  Primary  supplier  workers  (those  providing  goods  and  materials,  e.g.  IT  services,  security  services  outsourced  through  by  the  contractor);  Risks  include:  employment  of  child  labor,  non‐ payment of wages by employer; non‐payment of benefits (compensation, bonus, maternity benefits  etc.)  by  employer;  discrimination  in  employment  (e.g.  abrupt  termination  of  the  employment,  working  conditions,  wages  or  benefits  etc.);  possibility  of  gender  based  violence  as  the  road  shall  traverse through sensitive locations such as hospitals, schools, etc. that are near to habitations; health  risks of labor relating to HIV/AIDS and other sexually transmitted diseases.    8.3 E&S risks relating to resource efficiency and pollution prevention    27. The assessment of impacts and risks due to road constructions has considered a settlement, nearby  infrastructure, drainage pattern of the area, water bodies, roadside trees/plantation, erosion prone  locations, sensitive receptors of air, water, noise and soil quality etc. In addition, natural calamity like  landslide, earthquake and flooding were also considered during  assessment due to the location of  road in such sensitive geography. The main impacts include air pollution due to dust emission and  noise pollution along with potential water pollution if remedial measures are not ensured.    8.4 E&S risks and impacts relating to Community Health and Safety    28. The road will act as a haul road for transporting construction materials will cause a nuisance to local  road users (road users and pedestrians). Risks include: i)  road excavation, use of vibratory equipment,  ESIA‐ Jashore‐Jhenaidah Road Corridor 16 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) construction  debris  handling  and  disposal  etc.  during  construction;  ii)  high  likelihood  of  direct  exposure  to  increased  construction  related  traffic  related  accident  especially  at  road  sections  traversing settlement area with limited carriageway/roadway width, and sensitive receptors such as  schools, religious place, health center/hospitals; iii) high dust levels from earthworks, high noise and  emission  level  from  traffic  congestion  and  idling  of  vehicles;  iv)  )  influx  of  migrant  workers  could  potentially cause local unease or potential conflicts with local people v) possibility of involving child  labor.    8.5 E&S risks and impacts on land & assets      29. The  nature  of  the  intervention  is  linear  and  will  require  land  acquisition.  In  total  106.29  and  148  hectares of land will need to be acquired respectively from Jhenaidah and Jashore for the Jashore‐ Jhenaidah part of the  project. Land  acquisition will  lead to loss of  land  for both title  and non‐title  holders and cause disruption in income and livelihood streams for individual and groups of people.  During the construction stage, land acquisition is anticipated to be required to establish construction  camps,  material  stock  yards,  hot  mix  plants  and  machinery  for  road  expansion.  These  land  requirements will be fulfilled through using the encumbrance free government land adjacent to the  road  or  by  taking  the  land  on  lease  from  the  willing  parties  or  purchasing  private  lands.  With  the  development of the road, avenues for economic activities and opportunities will be created. The RAP  and  entitlement  matrix  will  be  prepared.  In  managing  lack  acquisitions  and  involuntary  land  resettlement, relevant stakeholders will be consulted and engaged as proposed in the Stakeholder  Engagement Plan.  In addition, in cases of impacts on livelihood, rehabilitation through appropriate  skill training/financial counselling would be required. Finally, concerns and needs of vulnerable groups  will  be  addressed  through  a  mix  of  measures  that  includes  additional  assistances  as  part  of  R&R  measures.    8.6 E&S risks linked to Cultural Heritage     30. The  alignment  of  the  project  road  does  not  have  any  cultural  heritage;  thus,  the  project  is  not  expected  to  affect  cultural  heritage.  There  will  some  madrasah  and  graves  that  will  be  physically  affected  and  they  will  be  relocated  and  included  in  the  RAP.  A  chance  find  procedures  will  be  incorporated  in  the  ESMP,  and  a  chance  find  clause  will  be  incorporated  in  work  contracts  with  contractors.    8.7 E & S risks linked to Biodiversity    31. Impact on Flora: The site clearance activities for road construction will involve the removal of roadside  vegetation and felling of trees. The results of the baseline survey indicate that the project corridor is  relatively  less  diverse  due  to  human  intervention.    Ecological  investigations  have  indicated  the  absence of any environmentally‐sensitive habitats or ecosystems; there are also no rare, endangered  and threatened species within the corridor.    32. Impacts  on  Fauna:  There  is  no  National  Park  or  wildlife  sanctuary  with  in  10km  from  the  project  corridor. The biodiversity investigation along the project corridor has not indicated the presence of  Monitor Lizard (Varanus bengalensis) and common peafowl (Pavo cristatus) comes under Schedule‐I  (part‐II) category of Wildlife Protection Act, 1972. The habitats and ecosystems in the project area  support various types of animals as given in Table 6.19.  ESIA‐ Jashore‐Jhenaidah Road Corridor 17 | P a g e   Western Economic Corridor and Regional Enhancement Program (WeCARE) 9.0 Information Disclosure, Consultation and Participation    33. It  will  be  essential  to  continue  the  consultation  process  to  ensure  that  the  community  remains  supportive  and  that  they  are  fully  informed  of  progress,  particularly  before  and  during  the  construction period. During the ESIA stage, household survey and FGDs were conducted to collect  relevant data and inform the communities about the project. Environmental consultations were held  at  (eight  locations  along  the  proposed  alignment  of  the  project.  All  attendants  at  the  meetings  welcomed the improvement of the road and hoped that implementation would proceed as early as  possible    10.0 Environmental and Social Management Plan (ESMP)    34. An ESMP has been designed to mitigate the Project’s environmental and social risks and impacts. It  includes mitigation measures, capacity building, responsibilities and reporting system and budget. In  addition,  the  ESMP  provide  measures  to  address  GBV  issue  at  the  project  level.  A  separate  Resettlement Action Plan will be prepared during the detailed design phase when the final alignment  and  detailed  design  are  completed  to  address  any  land  acquisition  and  physical  and  economic  displacement  related  to  involuntary  land  take.  The  ESMP  obligates  the  contractor,  prior  to  mobilization,  to  prepare  the  C‐ESMP,  which  shall  be  approved  prior  to  the  commencement  of  construction  activities.    The  Contractor’s  CESMP  shall  include  OHS  plan,  Water  and  Waste  Management  Plan,  Influx  management  Plan,  Workers  camp  management  plan,  CHS  Plan,  Traffic  management and road safety management Plan, borrow area management plan, and Site restoration  Plan among others in accordance with the GoB and WBs standards and guidelines. All such plans will  be reviewed and approved by the PIU and RHD prior to commencement of construction works. The  approved C‐ESMP shall be reviewed periodically (but not less than every six (6) months) and updated  in a timely manner. The executing agency for the project is the Roads and Highways Division (RHD). A  project  implementation  unit  (PIU)  will  be  established  which  will  be  headed  by  a  full‐time  project  manager with support from Environmental Specialist, Social Development Specialist and Health and  Safety Specialist. The Environmental and Social Circle of RHD will also be supported and strengthened  under the project. Environmental and social specialists will be a part of the CSC to monitor the ESMP  implementation and ensure compliance with both WB and Government of Bangladesh requirements.     11.0 Grievance Redress Mechanism    35. A  GRM  will  be  established  to  receive,  evaluate  and  facilitate  the  resolution  of  affected  people’s  concerns,  complaints,  and  grievances.  The  GRM  aims  to  provide  a  time  bound  and  transparent  mechanism to voice out and resolve social and environmental concerns linked to the project.      ESIA‐ Jashore‐Jhenaidah Road Corridor 18 | P a g e