Procurement Plan COFFEE SECTOR COMPETITIVENESS PROJECT I. General 1. Project information: Country: Burundi Borrower: Government of Burundi Project Name: Coffee Sector Competitiveness Project Grant No: TBC Project ID No: P151869 Project Implementing Agencies: Ministry of Agriculture and Livestock 2. Bank’s approval Date of the procurement Plan [Negotiations Date: TBC] 3. Date of General Procurement Notice: TBC 4. Period covered by this procurement plan: 30-Sep-2015– 31-mars-2017 (18 months) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments 1. ICB and LIB (Goods)  500,000 2. NCB (Goods)  500,000 3. ICB (Works)  5,000,000 4. NCB (Works)  5, 000,000 5. ICB (Non-Consultant Services)  500,000 2. Prequalification. Bidders for _____________ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. N/A 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA La Participation communautaire à la passation de marchés sera utilisée pour les marchés à réaliser au niveau des sous-projets. [To be more elaborated in project implementation manual and community related documents]. The goods, works and services will be procured following simplified procurement procedures as described in the PIM for community-based projects. Under the PIM the main procurement methods to be used would be the following: (i) Shopping for goods and works where quotations are solicited from at least three qualified suppliers or contractors on basis of simplified documents; (ii) Local bidding for goods and works which is an open competition similar to NCB apart from that the invitation for bids is advertised using radio, local (instead of national) newspapers or through posting notices at strategic places in the community, (iii) community force account where the communities implement themselves the subproject using their own resource and (iv) Direct contracting. For services the selection methods to be used are the following: (i) Individual consultants; (ii) consultants qualifications and (iii) single source selection for the selection of individual consultants and firms. All the above mentioned selection method will be applied as spelled out in the Bank's consultant guidelines. The PIM will describe the details in a clear and simple language that be easily understood by the targeted users. 4. Reference to (if any) Project Operational/Procurement Manual: Not yet available 5. Any Other Special Procurement Arrangements: N/A 6. Procurement Packages with Methods and Time Schedule A. PPA 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid- (US$) (yes/no) (Prior / Opening Post) Date 1 Fourniture d'une 40,000 Shopping No No Post July 2015 camionnette 4x4 2 Fourniture et 30,000 Shopping No No Post July 2015 équipements de bureau, ordinateurs, photocopieuse, scanner, etc. B. PROJET CAFÉ 1. Travaux, Fournitures, Systèmes IT et Services non consultant a. Travaux 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid-Opening (US$) (yes/no) (Prior / Date Post) 1 Travaux de réhabilitation 1,200,000 NCB No No Post May 2016 Non inclus de 30 km de routes 300,000 $ rurales d'accès aux SDL US pour études et surveillance 2 Travaux de 160,100 NCB No No Post Feb 2016 Réhabilitation des Bureaux de l’ARFIC (aménagement des bureaux, climatiseurs, etc.) 3 Construction de 50 bacs 107,700 NCB No No Post Nov 2016 Non compris de traitement des eaux la usées contribution des bénéficiaires de 152,600 $ US 4 Travaux de rénovation 61,000 shopping No No Post Feb 2016 bureaux de l’UGP b. Fournitures, Systèmes IT et Services non consultant 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement P-Q Domestic Review Expected Comments No. (Description) Cost Method Preference by Bank Bid-Opening (US$) (yes/no) (Prior / Date Post) 1 Approvisionnement en 2,500,000 ICB No No Prior Feb 2016 insecticides, fongicides et autres produits phytosanitaires pour 2016-2017 2 Approvisionnement en 350,000 NCB No No Prior April 2016 engrais pour le rajeunissement 2016- 2017 3 Acquisition des 300,000 NCB No No Post March 2016 véhicules pour UGP, ARFIC et INTERCAFE et CNAC 4 Acquisition de 13 motos 78,000 NCB No No Post April 2016 pour la CNAC 5 Equipement de bureau 225,000 NCB No No Post Oct 2015 (Ordinateurs, imprimante, Photocopieuses, scanners, etc) pour l’UGP, ARFIC et INTERCAFE et CNAC 6 Mobilier de bureau pour 55,000 NCB No No Post Apr 2016 l’UGP, ARFIC, INTERCAFE et CNAC 7 Acquisition des 185,000 NCB No No Post Aug 2016 Non compris la Equipements de contribution des laboratoire pour ARFIC bénéficiaires de équipements de 228,500 $ US laboratoires de dégustation pour INTERCAFE (SDL) 8 Fourniture d’un groupe 81,200 NCB No No Post Feb 2016 électrogène pour UGP 9 Renforcement capacités 101,500 NCB No No Post July 2016 A déterminer logistiques de l’ISABU plus tard les articles 10 Conception, fourniture et 111,900 NCB No No Post May 2016 maintenance d’un logiciel de vente de café pour ARFIC/Guichet unique 11 Conception d’un logiciel 188,100 NCB No No Post July 2016 en ligne et fourniture et installation des équipements en appui à la production des statistiques fiables sur le café 12 Fourniture et Installation 50,800 ED No No Post Jan 2016 La NO se fera d’un logiciel de gestion par mail au TTL financière et comptable et formation pour l’UGP 13 Fourniture et Installation 50,800 ED No No Post Jan 2016 La NO se fera d’un logiciel de suivi- par mail au TTL évaluation et Formation pour l’UGP 14 Fourniture et Installation 20,300 Shopping No No Post Jan 2016 des Logiciels bureautiques et Formation pour l’UGP 15 Production fiches 10,400 Shopping No No Post Feb 2016 techniques et films documentaires sur nouvelles techniques de conduite de la caféicultures III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms)  200,000 2. Single Source (Firms)  100,000 3. Individual Consultants  100,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule A. PPA 1 2 3 4 5 6 7 Ref. Description of Assignment Estimate Selection Review Expected Comments No. d Cost Method by Bank Proposals (US$) (Prior / Submission Post) Date 1 Enquête sur le verger caféicole et 100,000 QC Post Apr 2015 localisation des SDL 2 Elaboration d’un Système intégré 50,000 QC Post Apr 2015 de Gestion (Management Information System) 3 Renforcement des capacités des 40,000 QC Post May 2015 institutions partenaires du Projet (ARFIC, INTERCAFE, CNAC, ect.) en Gestion, Cpté, PM, SE, etc.) 4 Elaboration des Manuels (manuel 33,000 CI Post Apr 2015 d’exécution et manuels de Gestion Administratives et Financières du Projet, INTERCAFE, ARFIC et CNAC) B. PROJET CAFE 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Cost (US$) Method by Bank Proposals (Prior / Submission Post) Date 1 Etudes technique d’exécution et 300,000 SFQC Post Nov 2015 Surveillance des travaux de réhabilitation de 30 km de pistes+ autres études pour les autres travaux prévus en 2015-2016 2 Rationalisation politique de la 259,400 SFQC Prior Déc 2016 filière et cadre réglementaire en appui à l’ARFIC 3 Mise en place système de 184,700 QC Post Sept 2016 traçabilité en appui à ARFIC 4 Elaboration de la stratégie 83,000 QC Post June 2016 marketing en appui INTERCAFE 5 Formation des acteurs sur la 80,600 QC Post Jan 2016 qualité du café et la démarche qualité + formation préparatoire et qualifiantes des Q graders en appui à ARFIC 6 Elaboration de la stratégie et 78,100 QC Post Dec 2015 situation de base genre dans la filière café en appui à la CNAC 7 Evaluation impact 77,800 QC Post Jan 2016 environnemental et social 8 Evaluation des coûts de 62,200 QC Post Apr 2016 production au niveau des maillons de la filière café en appui à l’ARFIC 9 Audit comptable et financier 52,200 SMC Post March 2017 externe, exercice 2016 et 2017 10 Audit des SDL existants en vue 31,100 SMC Post Dec 2016 de la certification en appui à INTERCAFE 11 Elaboration plan stratégique de 62,200 CI Post March 2016 l’INTERCAFE 12 Conception et production d'un 51,900 CI Post July 2016 guide de gestion durable de l'exploitation caféicole du Burundi pour la CNAC 13 Audit organisationnel, technique 51,900 CI Post Feb 2016 et financier de l’INTERCAFE 14 Elaboration de la stratégie de 46,700 CI Post April 2016 communication de l’INTERCAFE 15 Évaluation de la capacité 41,500 CI Post Apr 2016 existante pour le dialogue secteur public / secteur privé (y compris l’étude sur le cadre de concertation des acteurs de la filière) an appui à ARFIC 16 Formation des Cadres de l’ARFIC 38,200 CI Post May 2016 sur la Gouvernance, partenariat public-privé, suivi&évaluation, etc. 17 Formation des Cadres ARFIC sur 38,200 CI Post March 2016 Norme / grade standard de qualité 18 Formation du personnel des 31,100 CI Post June 2016 laboratoires (Appui ARFIC) 19 Formation Suivi et Evaluation et 29,000 CI Post Janv 2016 planification stratégique axée sur les résultats pour INTERCAFE 20 Conception des documents sur les 27,100 CI Post June 2016 procedures d’accréditation des laboratoires en appui à l’ARFIC 21 Amélioration capacité technique, 22,100 CI Post May 2016 opérationnelle et managériale des SDL (Conception et production de guide) en appui à ARFIC 22 Formation des formateurs à 13,300 CI Post March 2016 l'accréditation (Appui à ARFIC) 23 Renforcement des capacités des 10,400 CI Post Aug 2016 organisations de la filière sur le plaidoyer en faveur de l’interprofession du café 24 Recrutement du Staff d de l’UGP Sur une période de 2 Projet ans 24.1  Coordonnateur 80,000 CI Prior July 2015 24.2 75,000 CI Prior July 2015  Responsable de gestion administrative et financière 24.3 72,000 CI Prior July 2015  Spécialiste de la passation des marchés 24.4 72,000 CI Prior July 2015  Spécialiste de S&E 24.5 72,000 CI Prior July 2015  Responsable technique 24.6 66,000 CI Prior July 2015  Auditeur interne 24.7 66,000 CI Prior July 2015  Spécialiste de genre et inclusion sociale 24.8 66,000 CI Prior July 2015  Spécialiste de l'environnement 24.9 44,000 CI Prior July 2015  Comptable (*): FMS and PS staff supporting INTERCAFE and CNAC will be also selected using WB procedures, including prior review requirements. PROCUREMENT Burundi : Burundi Coffee Sector Competitiveness Project PLAN General Information Country: Burundi Bank’s Approval Date of the Original Procurement Plan: 2017-08-31 2019-08-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151869 GPN Date: Project Name: Burundi Coffee Sector Competitiveness Project Loan / Credit No: IDA / D0570 Executing Agency(ies): Ministry of Agriculture and Livestock WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 4 ? Coordination, BI-MINAGRIE-20599-CW- Single Stage - One En cours IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 29,000.00 16,606.90 2017-08-14 2017-10-09 2018-04-07 RFQ / office renovation Envelope d'exécution management Component 4 ? Coordination, MOF -REF-2 / Rénovation Single Stage - One IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 29,000.00 16,354.85 Achevé 2017-06-30 2017-08-25 2018-02-21 des bureaux UCP Envelope management BI-MINAGRIE-45472-CW- Component 3 ? Coffee RFB / Travaux de Single Stage - One En cours IDA / D0570 quality improvement and A posteriori Appel d'offres Open - National 3,060,000.00 0.00 2018-06-17 2018-06-22 2018-08-03 2018-09-02 2018-10-07 2019-04-05 réhabilitation des pistes Envelope d'exécution market access d'accès aux SDLs 60 km BI-MINAGRIE-45486-CW- Component 3 ? Coffee RFB / Construction des bacs Single Stage - One En attente IDA / D0570 quality improvement and A posteriori Appel d'offres Open - National 771,578.00 0.00 2018-09-13 2018-09-18 2018-10-30 2018-11-29 2019-01-03 2019-07-02 de traitement des eaux usées Envelope d'exécution market access aux SDLs BI-MINAGRIE-45489-CW- Component 3 ? Coffee RFB / Mise en place des Single Stage - One En attente IDA / D0570 quality improvement and A posteriori Appel d'offres Open - National 266,800.00 0.00 2018-09-06 2018-09-11 2018-10-23 2018-11-22 2018-12-27 2019-06-25 bâtiments de stockage du Envelope d'exécution market access café MOF -REF-1 / Rénovation Component 1 ? Institutional Single Stage - One des bureaux et laboratoire IDA / D0570 strengthening and value A posteriori Appel d'offres Open - National 128,000.00 118,609.66 Achevé 2017-09-13 2017-09-18 2017-10-30 2017-11-29 2018-01-03 2018-07-02 Envelope principal (ARFIC) chain governance BI-MINAGRIE-104119-CW- Component 1 ? Institutional RFQ / Achèvement des Single Stage - One En attente IDA / D0570 strengthening and value A posteriori Demande de prix Limited 64,000.00 0.00 2019-03-09 2019-05-04 2019-10-31 travaux de rénovation des Envelope d'exécution chain governance bureau de l'ARFIC GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-3 / Fourniture Component 2 ? Coffee Open - Single Stage - One des engrais (500 tonnes - IDA / D0570 growers productive capacity A posteriori Appel d'offres 500,000.00 362,000.00 Signé 2017-06-12 2017-06-17 2017-07-29 2017-08-28 2017-10-02 2018-03-31 International Envelope 2017) NPK enhancement MOF -REF-4 / Component 2 ? Coffee Open - Single Stage - One En cours Approvisionnement en IDA / D0570 growers productive capacity A priori Appel d'offres 1,505,085.00 0.00 2017-05-02 2017-05-07 2017-06-18 2017-07-18 2017-08-22 2018-02-18 International Envelope d'exécution fongicide et insecticide enhancement Component 1 ? Institutional Single Stage - One MOF -REF-7 / Motos (9) IDA / D0570 strengthening and value A posteriori Appel d'offres Open - National 76,500.00 58,069.85 Achevé 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 Envelope chain governance Page 1 MOF -REF-9 / Achat de 2 Ordinateurs centraux dans le Component 3 ? Coffee cadre de l'Appui à la Single Stage - One En attente IDA / D0570 quality improvement and A posteriori Demande de prix Limited 30,000.00 0.00 2017-06-30 2017-08-25 2018-02-21 production des statistiques / Envelope d'exécution market access Département des statistiques ARFIC MOF -REF-12 / Fourniture Component 1 ? Institutional et installation des Open - Single Stage - One En cours IDA / D0570 strengthening and value A posteriori Appel d'offres 370,000.00 0.00 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 équipement de contrôle de International Envelope d'exécution chain governance qualité café MOF -REF-13 / Kits matériels moniteurs Component 2 ? Coffee Single Stage - One En cours (salopettes, bottes, IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 90,120.00 45,370.71 2017-07-02 2017-07-07 2017-08-18 2017-09-17 2017-10-22 2018-04-20 Envelope d'exécution imperméables, triangles à enhancement pentes) MOF -REF-16 / Equipements informatiques et de reprographie pour l'UCP Component 4 ? Coordination, (Ordinateur fixe, Ordinateur Single Stage - One En cours IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 42,500.00 0.00 2017-02-13 2017-04-10 2017-10-07 portable docking station, Envelope d'exécution management Imprimante grande capacité, Imprimante moyenne capacité) MOF -REF-17 / Mobilier de bureau à la CNAC au Component 1 ? Institutional Single Stage - One En cours niveau national et régional IDA / D0570 strengthening and value A posteriori Demande de prix Limited 13,650.00 0.00 2017-04-18 2017-06-13 2017-12-10 Envelope d'exécution (tables, chaises, étagères, chain governance armoires, etc.) Component 4 ? Coordination, MOF -REF-18 / Mobilier de Single Stage - One En cours IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 36,000.00 0.00 2017-02-15 2017-04-12 2017-10-09 burau pour l'UNCP Envelope d'exécution management MOF -REF-19 / Achat de matériel pour les formations Component 3 ? Coffee des Q graders en 2018 (5 Single Stage - One En cours IDA / D0570 quality improvement and A posteriori Demande de prix Limited 30,300.00 0.00 2017-07-20 2017-09-14 2018-03-13 coffee Taster's flavor Wheel Envelope d'exécution market access etc.) et Equipement Labo de dégustation MOF -REF-20 / Achat des engrais pour cultures Component 2 ? Coffee Single Stage - One En cours intercalires, pépinères,caféiers IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 376,670.00 0.00 2017-06-26 2017-07-01 2017-08-12 2017-09-11 2017-10-16 2018-04-14 Envelope d'exécution regénérés et recépés enhancement (DAP+Urée) MOF -REF-21 / Achat du Component 2 ? Coffee Single Stage - One En cours matériel pour pépinères 2017 IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 64,705.00 0.00 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-04-23 Envelope d'exécution et pour plants 2018 enhancement MOF -REF-22 / Achat de Component 2 ? Coffee produits phytosanitaires pour Single Stage - One En cours IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 25,162.00 0.00 2017-07-03 2017-08-28 2018-02-24 les cultures intercalaires et Envelope d'exécution enhancement les pépinières MOF -REF-26 / Component 2 ? Coffee Single Stage - One En cours Etablissement des cahiers IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 60,000.00 0.00 2017-06-25 2017-06-30 2017-08-11 2017-09-10 2017-10-15 2018-04-13 Envelope d'exécution des caféiculteurs enhancement MOF -REF-8 / Fournitures pour Appui logistique et matériel informatique et de reprographie pour l'ARFIC, INTERCAFE, CNAC & Component 1 ? Institutional Single Stage - One En cours ISABU (imprimantes, IDA / D0570 strengthening and value A posteriori Appel d'offres Open - National 156,050.00 0.00 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 Envelope d'exécution ordinateurs, Appareil photo chain governance numérique, etc.) + Achat de 6 ordinateurs portables, de 2 ordinateurs de bureaux et de 5 impr Page 2 MOF -REF-10 / Achat Component 2 ? Coffee Open - Single Stage - One matériel de traitement et de IDA / D0570 growers productive capacity A posteriori Appel d'offres 401,310.00 208,500.00 Signé 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 International Envelope protection enhancement Component 2 ? Coffee MOF -REF-11 / Matériel de Single Stage - One En cours IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 55,000.00 0.00 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 taille (scie et sécateur) Envelope d'exécution enhancement MOF -REF-14 / Fourniture d'un logiciel gestion Component 4 ? Coordination, Passation de financière et comptable y En cours IDA / D0570 monitoring and knowledge A posteriori marché de gré à Direct 60,000.00 0.00 2017-02-16 2017-02-21 2017-03-28 2017-09-24 compris la formation pour d'exécution management gré équipe fiduciaire UCP, Intercafé, CNAC et ARFIC Component 2 ? Coffee Passation de MOF -REF-15 / Fourniture En cours IDA / D0570 growers productive capacity A posteriori marché de gré à Direct 500,000.00 344,315.00 2016-12-08 2016-12-13 2017-01-17 2017-07-16 des engrais d'exécution enhancement gré Component 2 ? Coffee Passation de MOF -REF-23 / Achat En cours IDA / D0570 growers productive capacity A posteriori marché de gré à Direct 25,849.00 0.00 2017-07-03 2017-07-08 2017-08-12 2018-02-08 semences intercalaires d'exécution enhancement gré BI-MINAGRIE-27545-GO- Component 3 ? Coffee Single Stage - One En attente RFQ / Acquisition d'une IDA / D0570 quality improvement and A posteriori Demande de prix Limited 24,000.00 0.00 2017-10-07 2017-12-02 2018-05-31 Envelope d'exécution flotte téléphonique market access BI-MINAGRIE-27547-GO- Component 3 ? Coffee RFQ / Acquisition des Single Stage - One En attente IDA / D0570 quality improvement and A posteriori Demande de prix Limited 15,000.00 0.00 2017-10-07 2017-12-02 2018-05-31 modems pour connexion Envelope d'exécution market access internet ARFIC BI-MINAGRIE-27641-GO- RFQ / Conception, hébergement et maintenance Component 3 ? Coffee Single Stage - One En cours du site web du PACSC et IDA / D0570 quality improvement and A posteriori Demande de prix Limited 21,600.00 2,812.88 2017-09-16 2017-11-11 2018-05-10 Envelope d'exécution redesign, hébergement et market access maintenance du site web de l'intercafé BI-MINAGRIE-34505-GO- Component 2 ? Coffee Single Stage - One En cours RFQ / Acquisition fumure IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 154,117.00 0.00 2017-11-03 2017-12-29 2018-06-27 Envelope d'exécution organique enhancement MOF -REF-24 / Fumure Component 2 ? Coffee organique pour caféiers à Single Stage - One IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 154,117.00 0.00 Annulé 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 renouveler + caféier à Envelope enhancement recéper BI-MINAGRIE-37482-GO- RFQ / Acquisition d'un Component 4 ? Coordination, serveur et de 50 Single Stage - One IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 29,000.00 24,056.30 Signé 2017-12-02 2018-01-27 2018-07-26 smartphones pour Envelope management l'opérationnalité du service Suivi-Evaluation BI-MINAGRIE-37484-GO- RFB / Informatisation et Component 1 ? Institutional acquisition des logiciels de Single Stage - One En attente IDA / D0570 strengthening and value A posteriori Appel d'offres Open - National 76,500.00 0.00 2017-11-26 2017-12-01 2018-01-12 2018-02-11 2018-03-18 2018-09-14 vente café et formation des Envelope d'exécution chain governance utilisateurs ainsi que la maintenance du matériel Passation de Component 1 ? Institutional marchés auprès MOF -REF-6 / Véhicules (6) IDA / D0570 strengthening and value A priori Direct 290,000.00 406,465.38 Résilié 2017-11-21 2017-11-21 2017-11-21 2017-11-21 des agences de chain governance l'ONU BI-MINAGRIE-46105-GO- Component 2 ? Coffee Single Stage - One RFB / Achat matériel de IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 617,700.00 165,288.70 Signé 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Envelope taille enhancement Page 3 BI-MINAGRIE-46106-GO- Component 2 ? Coffee Single Stage - One RFB / Achat du matériel de IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 478,941.00 350,779.06 Signé 2018-02-19 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Envelope protection enhancement BI-MINAGRIE-46107-GO- Component 2 ? Coffee Single Stage - One RFB / Approvisionnement en IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 242,420.00 168,348.50 Signé 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope produits phytosanitaires enhancement BI-MINAGRIE-46111-GO- Component 1 ? Institutional RFB / Achat matériel de Single Stage - One IDA / D0570 strengthening and value A posteriori Appel d'offres Open - National 101,400.00 98,080.43 Achevé 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2018-11-20 déplacement pour moniteurs Envelope chain governance (vélos) BI-MINAGRIE-46305-GO- Component 2 ? Coffee Single Stage - One RFQ / Établissements de IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 68,440.00 42,235.89 Achevé 2018-02-11 2018-04-08 2018-10-05 Envelope cahiers des caféiculteurs enhancement BI-MINAGRIE-46307-GO- Component 2 ? Coffee Single Stage - One En attente RFQ / Achat d'engrais et du IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 12,619.00 0.00 2018-04-07 2018-06-02 2018-11-29 Envelope d'exécution matériel pour l'ISABU enhancement BI-MINAGRIE-46320-GO- RFB / Achat d'engrais DAP Component 2 ? Coffee et Urée pour pépinières, Open - Single Stage - One IDA / D0570 growers productive capacity A posteriori Appel d'offres 1,093,822.00 1,103,789.50 Signé 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 cultures intercalaires saison International Envelope enhancement A 2018-2019, caféiers remplacés et caféiers recépés BI-MINAGRIE-47559-GO- Component 4 ? Coordination, Single Stage - One En attente RFQ / Achat d'équipement IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 36,000.00 0.00 2018-03-10 2018-05-05 2018-11-01 Envelope d'exécution informatique et bureautique management BI-MINAGRIE-47904-GO- Component 1 ? Institutional RFQ / Achat véhicule pick Single Stage - One IDA / D0570 strengthening and value A posteriori Demande de prix Limited 45,000.00 46,449.10 Achevé 2018-03-03 2018-04-28 2018-10-25 up pour la CNAC - Envelope chain governance Fédération Gitega- Karusi BI-MINAGRIE-47958-GO- Component 2 ? Coffee Single Stage - One En attente RFQ / Achat fumure IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 528,600.00 0.00 2018-04-30 2018-06-25 2018-12-22 Envelope d'exécution organique enhancement BI-MINAGRIE-47991-GO- Component 2 ? Coffee Open - Single Stage - One RFB / Achat d'insecticides et IDA / D0570 growers productive capacity A posteriori Appel d'offres 970,320.00 25,391,159.11 Signé 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2019-01-05 International Envelope de fongicides enhancement BI-MINAGRIE-48357-GO- Component 2 ? Coffee Single Stage - One RFB / Achat matériel de IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 615,000.00 410,770.80 Signé 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Envelope traitement enhancement BI-MINAGRIE-46108-GO- Component 2 ? Coffee Single Stage - One En attente RFQ / Approvisionnement en IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 217,005.00 0.00 2018-02-11 2018-04-08 2018-10-05 Envelope d'exécution semences enhancement Component 4 ? Coordination, BI-MINAGRIE-46114-GO- Single Stage - One En cours IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 25,000.00 0.00 2018-02-17 2018-04-14 2018-10-11 RFQ / Achat climatiseurs Envelope d'exécution management BI-MINAGRIE-46093-GO- Component 2 ? Coffee Open - Single Stage - One En cours RFB / Achat de 4000 tonnes IDA / D0570 growers productive capacity A priori Appel d'offres 4,233,933.00 2,796,000.00 2018-03-29 2018-04-03 2018-05-15 2018-06-14 2018-07-19 2019-01-15 International Envelope d'exécution d'engrais NPK enhancement BI-MINAGRIE-56617-GO- Component 2 ? Coffee Open - Single Stage - One RFB / Achat de 12.300 IDA / D0570 growers productive capacity A posteriori Appel d'offres 615,000.00 0.00 Annulé 2018-04-09 2018-04-14 2018-05-26 2018-06-25 2018-07-30 2019-01-26 International Envelope pulvérisateurs à dos enhancement BI-MINAGRIE-47957-GO- RFB / Achat d'engrais DAP Component 2 ? Coffee Single Stage - One et urée pour cultures IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 406,274.00 0.00 Annulé 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope intercalaires caféiers enhancement remplacés et caféiers recépés. Page 4 BI-MINAGRIE-67785-GO- Component 2 ? Coffee RFQ / Approvisinnement in Single Stage - One IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 99,000.00 59,788.27 Signé 2018-06-30 2018-08-25 2019-02-21 intrants pour production des Envelope enhancement plants (Sachets et arrosoirs) BI-MINAGRIE-83181-GO- RFQ / Achat de 600 smrtphones pour le Component 1 ? Institutional Single Stage - One recensement général des IDA / D0570 strengthening and value A posteriori Demande de prix Limited 98,900.00 85,177.52 Achevé 2018-10-26 2018-12-21 2019-06-19 Envelope caféiers et des caféiculteurs chain governance y compris l'aspect socioé- conomique. BI-MINAGRIE-48230-GO- Component 2 ? Coffee Open - Single Stage - One RFB / Achat de 2000 tonnes IDA / D0570 growers productive capacity A priori Appel d'offres 2,116,967.00 0.00 Annulé 2018-07-05 2018-07-10 2018-08-21 2018-09-20 2018-10-25 2019-04-23 International Envelope d'engrais NPK enhancement Passation de Component 1 ? Institutional MOF -REF-5 / Vehicules marchés auprès IDA / D0570 strengthening and value A priori Direct 450,000.00 0.00 Annulé 2017-02-07 2017-02-07 2017-02-07 2017-02-07 (10) des agences de chain governance l'ONU BI-MINAGRIE-101928-GO- Component 1 ? Institutional Single Stage - One En attente RFQ / Appui en matériel IDA / D0570 strengthening and value A posteriori Demande de prix Limited 20,048.00 0.00 2019-02-24 2019-04-21 2019-10-18 Envelope d'exécution aratoire à l'UNIPROBA chain governance BI-MINAGRIE-102119-GO- Passation de Component 3 ? Coffee UN / Acquisition du matériel marchés auprès IDA / D0570 quality improvement and A posteriori Direct 60,000.00 32,928.18 Signé 2019-02-20 2019-02-25 2019-04-01 2019-09-28 roulant (1 véhicule pick up des agences de market access pour la CNAC l'ONU BI-MINAGRIE-102127-GO- Component 2 ? Coffee RFQ / Approvisionnement en Single Stage - One En attente IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 171,536.00 0.00 2019-02-25 2019-04-22 2019-10-19 semences de cultures Envelope d'exécution enhancement intercalaires BI-MINAGRIE-102132-GO- Component 2 ? Coffee RFB / Acquisition de 385 Open - Single Stage - One En cours IDA / D0570 growers productive capacity A priori Appel d'offres 2,625,000.00 0.00 2019-02-20 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 tonnes de fongicides contre International Envelope d'examen enhancement l'Anthracnose et et la rouille BI-MINAGRIE-102380-GO- RFQ / Acquisition des Component 1 ? Institutional Single Stage - One En attente semences de cultures IDA / D0570 strengthening and value A posteriori Demande de prix Limited 35,000.00 0.00 2019-02-26 2019-04-23 2019-10-20 Envelope d'exécution maraîchères pour le compte chain governance de l'UNIPROBA BI-MINAGRIE-101918-GO- Component 1 ? Institutional RFQ / Achat d'un Single Stage - One En attente IDA / D0570 strengthening and value A posteriori Demande de prix Limited 2,300.00 0.00 2019-03-01 2019-04-26 2019-10-23 rétroprojecteur + Envelope d'exécution chain governance Stabilisateur BI-MINAGRIE-106372-GO- Component 3 ? Coffee Passation de DIR / Acquisition d'une En cours IDA / D0570 quality improvement and A posteriori marché de gré à Direct 35,000.00 0.00 2019-04-01 2019-04-06 2019-05-11 2019-11-07 Machine torréfacteur d'exécution market access gré PROBATINO NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-27 / Sélection d'un prestataire de services pour l'élaboration d'un devis Component 4 ? Coordination, Single Stage - One En cours quantitatif suivi et contrôle IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 1,000.00 0.00 2017-06-24 2017-08-19 2018-02-15 Envelope d'exécution des travaux relatifs au management réaménagement des bureaux de l'UC-PACSC Page 5 BI-MINAGRIE-37486-NC- Component 3 ? Coffee Single Stage - One En cours RFQ / Impression des outils IDA / D0570 quality improvement and A posteriori Demande de prix Limited 23,733.00 0.00 2017-12-01 2018-01-26 2018-07-25 Envelope d'exécution promotionnels market access BI-MINAGRIE-46313-NC- Component 2 ? Coffee Single Stage - One En attente RFQ / Élaboration des IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 20,000.00 0.00 2018-04-21 2018-06-16 2018-12-13 Envelope d'exécution modules et leur impression enhancement BI-MINAGRIE-47258-NC- RFB / Transport de la Component 2 ? Coffee Single Stage - One fumure minérale des IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 195,000.00 0.00 Annulé 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope provinces vers les communes enhancement par la CNAC BI-MINAGRIE-47262-NC- Component 2 ? Coffee RFQ / Transport des intrants Single Stage - One IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 71,200.00 0.00 Annulé 2018-02-20 2018-04-17 2018-10-14 et matériels caféicoles des Envelope enhancement provinces vers les communes BI-MINAGRIE-47267-NC- RFB / Transport des engrais Component 2 ? Coffee Single Stage - One minéraux , des pesticides et IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 319,090.00 0.00 Annulé 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope du matériel de Bujumbura enhancement vers les provinces BI-MINAGRIE-47550-NC- Component 4 ? Coordination, RFQ / Conception et Single Stage - One IDA / D0570 monitoring and knowledge A posteriori Demande de prix Limited 20,000.00 13,182.01 Achevé 2018-03-05 2018-04-30 2018-10-27 production des outil de Envelope management visibilité pour le PACSC BI-MINAGRIE-47986-NC- Component 2 ? Coffee RFB / Transport des intrants Single Stage - One IDA / D0570 growers productive capacity A posteriori Appel d'offres Open - National 319,090.00 0.00 Annulé 2018-07-09 2018-07-14 2018-08-25 2018-09-24 2018-10-29 2019-04-27 et matériel caféicoles de Envelope enhancement Bujumbura vers les provinces BI-MINAGRIE-48017-NC- Component 3 ? Coffee Single Stage - One RFQ / Impression des outils IDA / D0570 quality improvement and A posteriori Demande de prix Limited 11,866.00 11,543.56 Signé 2018-05-11 2018-07-06 2019-01-02 Envelope à messages promotionnels market access BI-MINAGRIE-46115-NC- DIR / Contrat avec IMF Component 2 ? Coffee Passation de En cours pour la collecte des IDA / D0570 growers productive capacity A posteriori marché de gré à Direct 23,529.00 0.00 2018-02-12 2018-02-17 2018-03-24 2018-09-20 d'exécution contributions des enhancement gré caféiculteurs BI-MINAGRIE-46119-NC- DIR / Identifications des foyers d'antrachnose et de la Component 2 ? Coffee Passation de En cours rouille ainsi que la IDA / D0570 growers productive capacity A posteriori marché de gré à Direct 58,000.00 0.00 2018-02-16 2018-02-21 2018-03-28 2018-09-24 d'exécution réalisation des tests avec le enhancement gré Département de Protection des Végétaux BI-MINAGRIE-47977-NC- RFQ / Location de magasins Component 2 ? Coffee Single Stage - One En attente des intrants et matériels IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 15,000.00 0.00 2018-02-27 2018-04-24 2018-10-21 Envelope d'exécution caféicoles dans les provinces enhancement de destination BI-MINAGRIE-67727-NC- Component 2 ? Coffee RFQ / Transport de la Single Stage - One IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 195,000.00 0.00 Annulé 2018-07-16 2018-09-10 2019-03-09 fumure minérale des Envelope enhancement provinces vers les communes BI-MINAGRIE-67726-NC- DIR / location des magasins Component 2 ? Coffee provinciaux pour le stockage Single Stage - One En attente IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 15,000.00 0.00 2018-07-17 2018-09-11 2019-03-10 des intrants et matériels Envelope d'exécution enhancement caféicoles pour le compte de la CNAC Page 6 BI-MINAGRIE-73931-NC- Component 3 ? Coffee Open - Single Stage - One En attente RFQ / Accès à l'information IDA / D0570 quality improvement and A posteriori Demande de prix 16,000.00 0.00 2018-09-19 2018-11-14 2019-05-13 International Envelope d'exécution des marchés internationaux market access BI-MINAGRIE-47922-NC- Component 1 ? Institutional Passation de DIR / Recensement général IDA / D0570 strengthening and value A priori marché de gré à Direct 240,000.00 0.00 Annulé 2018-02-28 2018-03-05 2018-04-09 2018-10-06 des caféiers y compris chain governance gré l'aspect socio-éconique MOF -REF-25 / Achat de prestations de services (Régie Nationale des Postes: RNP) Component 2 ? Coffee Passation de pour la collecte des fonds IDA / D0570 growers productive capacity A priori marché de gré à Direct 23,000.00 0.00 Annulé 2017-06-25 2017-06-30 2017-08-04 2018-01-31 des caféiculteurs (partie non enhancement gré subventionnée de du coûts des engrais) BI-MINAGRIE-92352-NC- DIR / Convention avec l'ISTEEBU pour le Component 1 ? Institutional Passation de recensement général des IDA / D0570 strengthening and value A posteriori marché de gré à Direct 608,000.00 584,596.91 Signé 2019-02-01 2019-02-06 2019-03-13 2019-09-09 cafeiers et des cafeiculteurs chain governance gré y compris l'enquête socio economique et l'inclusion financière BI-MINAGRIE-102138-NC- DIR / Convention avec Département de Protection Component 2 ? Coffee Passation de En attente des Végétaux pour IDA / D0570 growers productive capacity A posteriori marché de gré à Direct 58,900.00 0.00 2019-02-20 2019-02-25 2019-04-01 2019-09-28 d'exécution l'identification des foyers enhancement gré d'anthracnose et les tests antestiopsis BI-MINAGRIE-47970-NC- Component 2 ? Coffee RFQ / Transport des intrants Single Stage - One IDA / D0570 growers productive capacity A posteriori Demande de prix Limited 150,000.00 0.00 Annulé 2018-07-21 2018-09-15 2019-03-14 et matériel caféicoles des Envelope enhancement provinces vers les communes CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-28 / Etudes techniques et surveillance Component 3 ? Coffee Sélection fondée En cours des travaux de Réhabilitation IDA / D0570 quality improvement and A posteriori sur la qualité et Open - National 104,000.00 0.00 2017-06-23 2017-07-14 2017-08-27 2017-09-24 2017-10-24 2017-11-28 2018-01-02 2018-03-03 d'exécution des pistes rurales d'accès market access le coût aux SDL: 60 km MOF -REF-30 / Audit Component 4 ? Coordination, comptable et financier Sélection au En cours IDA / D0570 monitoring and knowledge A posteriori Open - National 50,000.00 0.00 2017-07-11 2017-08-01 2017-09-14 2017-10-12 2017-11-11 2017-12-16 2018-01-20 2018-07-19 externe, exercice 2017 et moindre coût d'exécution management 2018 MOF -REF-31 / Audit Sélection fondée organisationnel, technique et Component 1 ? Institutional sur les Open - En cours financier de l'INTERCAFE + IDA / D0570 strengthening and value A posteriori 114,125.00 0.00 2017-06-21 2017-07-12 2017-08-25 2017-09-24 2017-10-29 2018-04-27 qualifications des International d'exécution Elaboration d'un plan chain governance consultants stratégique de l'INTERCAFE MOF -REF-32 / Elaboration Sélection fondée Component 3 ? Coffee de la stratégie marketing ( sur les Open - En cours IDA / D0570 quality improvement and A posteriori 83,000.00 0.00 2017-07-04 2017-07-25 2017-09-07 2017-10-07 2017-11-11 2018-05-10 AT internationale et AT qualifications des International d'exécution market access nationale) consultants Sélection fondée Component 3 ? Coffee MOF -REF-34 / Audit des sur les En cours IDA / D0570 quality improvement and A posteriori Open - National 31,100.00 0.00 2017-06-08 2017-06-29 2017-08-12 2017-09-11 2017-10-16 2018-04-14 SDL existantes qualifications des d'exécution market access consultants Page 7 MOF -REF-41 / Etudes techniques pour la Sélection fondée Component 2 ? Coffee conception, plans et DAO sur les En attente IDA / D0570 growers productive capacity A posteriori Open - National 20,000.00 0.00 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-05-16 pour la construction et qualifications des d'exécution enhancement équipement laboratoire de consultants biotechnologie ISABU MOF -REF-42 / Etudes techniques pour conception, plans et DAO pour la Sélection fondée construire d'un laboratoire de Component 2 ? Coffee sur les défense de la culture du café IDA / D0570 growers productive capacity A posteriori Open - National 10,000.00 0.00 Annulé 2017-07-10 2017-07-31 2017-09-13 2017-10-13 2017-11-17 2018-05-16 qualifications des contre les principales enhancement consultants maladies et ravageurs du café (Labo phytopathologie, entomologie, etc.) MOF -REF-56 / Sélection fondée Recrutement d'un consultant Component 4 ? Coordination, sur les En cours pour l'évaluation de l'impact IDA / D0570 monitoring and knowledge A posteriori Open - National 45,000.00 0.00 2017-05-18 2017-06-08 2017-07-22 2017-08-21 2017-09-25 2018-03-24 qualifications des d'exécution environnemental et social du management consultants projet MOF -REF-57 / Recrutement d'un consultant Sélection fondée pour l'élaboration des études Component 1 ? Institutional sur les En cours techniques d'exécution des IDA / D0570 strengthening and value A posteriori Open - National 22,000.00 0.00 2017-07-11 2017-08-01 2017-09-14 2017-10-14 2017-11-18 2018-05-17 qualifications des d'exécution travaux de rénovation des chain governance consultants bureaux et laboratoire principal (ARFIC) Sélection fondée MOF -REF-33 / Logiciel de Component 1 ? Institutional sur les En cours suivi-évaluation et formation IDA / D0570 strengthening and value A posteriori Open - National 50,000.00 0.00 2017-05-15 2017-06-05 2017-07-19 2017-08-18 2017-09-22 2018-03-21 qualifications des d'exécution du personnel utilisateur chain governance consultants Sélection fondée MOF -REF-40 / Conception, Component 3 ? Coffee sur les Open - En attente hébergement et maintenance IDA / D0570 quality improvement and A posteriori 180,500.00 0.00 2017-09-18 2017-10-09 2017-11-22 2017-12-22 2018-01-26 2018-07-25 qualifications des International d'exécution de logiciels en ligne market access consultants BI-MINAGRIE-46798-CS- Sélection fondée Component 1 ? Institutional CQS / Recrutement d'un sur les Open - En attente IDA / D0570 strengthening and value A posteriori 100,000.00 0.00 2018-04-18 2018-05-09 2018-06-22 2018-07-22 2018-08-26 2019-02-22 consultant pour l'élaboration qualifications des International d'exécution chain governance du Coffee Act consultants BI-MINAGRIE-108524-CS- CQS / Etude d'évaluation Sélection fondée Component 4 ? Coordination, indépendante à mi-parcours sur les En cours IDA / D0570 monitoring and knowledge A posteriori Open - National 100,000.00 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 des Réalisations, des qualifications des d'exécution management Résultats et d'impact du consultants projet PACSC MOF -REF-29 / Recrutement d'un consultant Sélection fondée Component 1 ? Institutional pour préparer les TDRs en sur les Open - En attente IDA / D0570 strengthening and value A posteriori 20,000.00 0.00 2017-06-26 2017-07-17 2017-08-30 2017-09-29 2017-11-03 2018-05-02 vue de chercher un cabinet qualifications des International d'exécution chain governance de consultant pour élaborer consultants le Coffee- Act INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF -REF-37 / Formation des utilisateurs du marché de café sur la gestion des Component 3 ? Coffee En attente risques et techniques IDA / D0570 quality improvement and A posteriori Individuel Limited 36,250.00 0.00 2017-07-24 2017-07-29 2017-08-19 2017-09-23 2018-03-22 d'exécution commerciales du café: 65 market access sociétées, 15 staff Intercafé, CNAC et ARFIC Page 8 MOF -REF-38 / Suivi- Component 1 ? Institutional évaluation et planification En cours IDA / D0570 strengthening and value A posteriori Individuel Limited 29,000.00 0.00 2017-07-03 2017-07-08 2017-07-29 2017-09-02 2018-03-01 stratégique axée sur les d'exécution chain governance résultats MOF -REF-39 / Evaluation Component 1 ? Institutional des coûts de production au IDA / D0570 strengthening and value A posteriori Individuel Limited 62,250.00 46,716.40 Signé 2017-07-14 2017-07-19 2017-08-09 2017-09-13 2018-03-12 niveau des maillons de la chain governance filère café MOF -REF-43 / Etudes techniques pour conception, plans et DAO pour la Component 2 ? Coffee En attente construction et équipement IDA / D0570 growers productive capacity A posteriori Individuel Limited 10,000.00 0.00 2017-07-17 2017-07-22 2017-08-12 2017-09-16 2018-03-15 d'exécution d'un centre de documentation enhancement sur le café et formation des caféiculteurs MOF -REF-44 / Recrutement d'un assistant Component 2 ? Coffee En attente technique d'appui à la IDA / D0570 growers productive capacity A posteriori Individuel Limited 12,000.00 0.00 2017-06-26 2017-07-01 2017-07-22 2017-08-26 2018-02-22 d'exécution Recherche à l'ISABU (cadre enhancement permanent) MOF -REF-46 / Elaboration Component 1 ? Institutional En cours de la stratégie genre dans la IDA / D0570 strengthening and value A posteriori Individuel Limited 30,000.00 0.00 2017-05-16 2017-05-21 2017-06-11 2017-07-16 2018-01-12 d'exécution filière café chain governance MOF -REF-48 / Consultant pour mobiliser les acteurs Component 3 ? Coffee Sélection de En cours dans le cadre de la IDA / D0570 quality improvement and A posteriori consultants par Direct 10,000.00 0.00 2017-04-22 2017-05-02 2017-07-06 2018-01-02 d'exécution participation des acteurs de market access entente directe la filière café à la SCAA MOF -REF-49 / Consultant pour mobiliser les acheteurs Component 3 ? Coffee Sélection de dans le cadre de la En cours IDA / D0570 quality improvement and A posteriori consultants par Direct 10,000.00 0.00 2017-07-06 2017-07-16 2017-09-19 2018-03-18 participation des acteurs de d'exécution market access entente directe la filière café aux Café Show Séoul/afrique MOF -REF-50 / Consultant pour mobiliser les acteurs Component 3 ? Coffee Sélection de En attente dans le cadre de la IDA / D0570 quality improvement and A posteriori consultants par Direct 10,000.00 0.00 2017-07-10 2017-07-20 2017-09-23 2018-03-22 d'exécution participation des acteurs de market access entente directe la filière aux SCAJ MOF -REF-51 / Consultant pour mobiliser les acteurs Component 3 ? Coffee Sélection de En attente dans le cadre de la IDA / D0570 quality improvement and A posteriori consultants par Direct 10,000.00 0.00 2017-07-15 2017-07-25 2017-09-28 2018-03-27 d'exécution participation des acteurs de market access entente directe la filière aux SCAE MOF -REF-52 / Component 3 ? Coffee Recrutement d'un consulant En cours IDA / D0570 quality improvement and A posteriori Individuel Direct 15,000.00 0.00 2017-08-01 2017-08-11 2017-09-01 2017-10-06 2018-04-04 pour aider à sensibiliser les d'exécution market access acheteurs internationaux MOF -REF-54 / Recrutement d'un consultant Component 3 ? Coffee Sélection de En cours chargé d'auditer et de gérer IDA / D0570 quality improvement and A posteriori consultants par Direct 18,000.00 0.00 2017-05-15 2017-05-25 2017-07-29 2018-01-25 d'exécution la base des données de la market access entente directe COE 2017 MOF -REF-55 / Recrutement d'un consultant Component 1 ? Institutional En cours pour l'élaboration d'un IDA / D0570 strengthening and value A posteriori Individuel Limited 12,000.00 0.00 2017-05-18 2017-05-23 2017-06-13 2017-07-18 2018-01-14 d'exécution manuel de suivi-évaluation chain governance de la CNAC MOF -REF-47 / Conception et production d'un guide de Component 2 ? Coffee Sélection de En cours conduite de la caféiculture IDA / D0570 growers productive capacity A posteriori consultants par Direct 40,000.00 0.00 2017-05-17 2017-05-27 2017-07-31 2018-01-27 d'exécution du Burundi +formation enhancement entente directe (Kahawatu) Page 9 MOF -REF-53 / Component 3 ? Coffee Sélection de Recrutement d'un consultant En cours IDA / D0570 quality improvement and A posteriori consultants par Direct 55,000.00 0.00 2017-05-15 2017-05-25 2017-07-29 2018-01-25 pour l'organisation de la Cup d'exécution market access entente directe of Excellence Edition 2017 BI-MINAGRIE-27548-CS- Component 3 ? Coffee INDV / Etude technique IDA / D0570 quality improvement and A posteriori Individuel Limited 20,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-10-21 2017-11-25 2018-05-24 pour le diagnostic des market access besoins de l'ARFIC BI-MINAGRIE-27656-CS- INDV / Adaptation du guide Component 1 ? Institutional de gestion des sous projets IDA / D0570 strengthening and value A posteriori Individuel Open 10,000.00 26,500.00 Achevé 2017-10-01 2017-11-19 2017-12-10 2018-01-14 2018-07-13 du PRODEMA et du chain governance PADZOC au contexte du PACSC BI-MINAGRIE-37483-CS- Component 1 ? Institutional INDV / Assistance technique En cours IDA / D0570 strengthening and value A posteriori Individuel Limited 25,000.00 0.00 2017-11-22 2017-11-27 2017-12-18 2018-01-22 2018-07-21 internationale pour la mise d'exécution chain governance en place d'un guichet unique BI-MINAGRIE-37487-CS- Component 4 ? Coordination, INDV / Mise en place d'un En attente IDA / D0570 monitoring and knowledge A posteriori Individuel Limited 10,000.00 0.00 2017-11-22 2017-11-27 2017-12-18 2018-01-22 2018-07-21 site web d'information en d'exécution management ligne BI-MINAGRIE-37485-CS- Component 1 ? Institutional INDV / Etude d'une stratégie En cours IDA / D0570 strengthening and value A posteriori Individuel Limited 45,000.00 0.00 2017-12-05 2017-12-10 2017-12-31 2018-02-04 2018-08-03 globale de communication de d'exécution chain governance la filière MOF -REF-35 / Assistance Technique de l'IITA à l'ISABU (Assistance technique pour la formation Component 2 ? Coffee Sélection de des chercheurs techniciens en IDA / D0570 growers productive capacity A priori consultants par Direct 308,833.00 0.00 Annulé 2017-06-30 2017-07-10 2017-09-13 2018-03-12 production des hybrides café, enhancement entente directe Gestion intégrée des maladies et ravageurs café, etc.) BI-MINAGRIE-39900-CS- CDS / Assistance technique de l'IITA à l'ISABU pour la Component 2 ? Coffee Sélection de En cours mise en oeuvre des activités IDA / D0570 growers productive capacity A priori consultants par Direct 1,500,000.00 0.00 2017-12-18 2017-12-23 2018-02-26 2018-08-25 d'exécution de la composante B, sous - enhancement entente directe composante B4 Appui à la recherche action. BI-MINAGRIE-46803-CS- Component 3 ? Coffee INDV / Recrutement d'un En cours IDA / D0570 quality improvement and A posteriori Individuel Limited 20,000.00 0.00 2018-03-26 2018-03-31 2018-04-21 2018-05-26 2018-11-22 consultant pour le diagnostic d'exécution market access des besoins de l'ARFIC BI-MINAGRIE-47512-CS- INDV / Recrutement d'un Component 4 ? Coordination, En attente consultant chargé de IDA / D0570 monitoring and knowledge A posteriori Individuel Limited 30,000.00 0.00 2018-02-12 2018-02-17 2018-03-10 2018-04-14 2018-10-11 d'exécution l'élaboration de la stratégie management environnemental BI-MINAGRIE-47548-CS- INDV / Elaboration d'un Component 4 ? Coordination, module sur les politiques En attente IDA / D0570 monitoring and knowledge A posteriori Individuel Limited 15,000.00 0.00 2018-02-19 2018-02-24 2018-03-17 2018-04-21 2018-10-18 environnementales et d'exécution management sociales de la Banque Mondiale BI-MINAGRIE-47917-CS- Component 1 ? Institutional INDV / Elaboration d'une En cours IDA / D0570 strengthening and value A posteriori Individuel Limited 26,000.00 0.00 2018-02-20 2018-02-25 2018-03-18 2018-04-22 2018-10-19 situation de référence d'exécution chain governance (Stratégie genre) Page 10 BI-MINAGRIE-47999-CS- INDV / Recrutement d'un Component 3 ? Coffee consultant chargé de la En attente IDA / D0570 quality improvement and A posteriori Individuel Limited 35,600.00 0.00 2018-03-23 2018-03-28 2018-04-18 2018-05-23 2018-11-19 conception et élaboration d'exécution market access d'un guide de gestion des SDLs BI-MINAGRIE-48004-CS- INDV / Recrutement d'un Component 3 ? Coffee En cours consultant pour la conception IDA / D0570 quality improvement and A posteriori Individuel Limited 25,000.00 0.00 2018-03-27 2018-04-01 2018-04-22 2018-05-27 2018-11-23 d'exécution d'un système de traçabilité à market access l'Intercafé BI-MINAGRIE-48015-CS- INDV / Recrutement d'un Component 3 ? Coffee consultant pour conception et IDA / D0570 quality improvement and A posteriori Individuel Limited 26,190.00 18,928.27 Signé 2018-04-02 2018-04-07 2018-04-28 2018-06-02 2018-11-29 la production des messages market access promotionnels et des outils appropriés. BI-MINAGRIE-48024-CS- INDV / Recrutement d'un Component 3 ? Coffee En attente consultant pour l'organisation IDA / D0570 quality improvement and A posteriori Individuel Limited 10,000.00 0.00 2018-03-29 2018-04-03 2018-04-24 2018-05-29 2018-11-25 d'exécution du tour des acheteurs market access internationaux BI-MINAGRIE-48352-CS- INDV / Recrutement d'un Component 1 ? Institutional consultant pour l'élaboration IDA / D0570 strengthening and value A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-02-21 2018-02-26 2018-03-19 2018-04-23 2018-10-20 des TDRs pour la mise en chain governance place des textes de référence et des textes d'application BI-MINAGRIE-61337-CS- CDS / Recrutement d'un consultant chargé d'auditer Component 3 ? Coffee En cours et de gérer la base des IDA / D0570 quality improvement and A posteriori Individuel Open 18,000.00 0.00 2018-05-17 2018-07-05 2018-07-26 2018-08-30 2019-02-26 d'exécution données de la Cup of market access Excellence (COE), Edition 2018 BI-MINAGRIE-74750-CS- INDV / Elaboration des Component 1 ? Institutional TDRs pour la mise en place IDA / D0570 strengthening and value A posteriori Individuel Limited 20,000.00 8,165.69 Signé 2018-08-21 2018-08-26 2018-09-16 2018-10-21 2019-04-19 d'un texte de référence et chain governance des textes d'application BI-MINAGRIE-76728-CS- INDV / Recrutement d'un Component 4 ? Coordination, consultant chargé de IDA / D0570 monitoring and knowledge A posteriori Individuel Open 30,000.00 22,557.54 Signé 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 l'élaboration de la stratégie management environnement BI-MINAGRIE-76729-CS- INDV / Enquête sur indicateur relatif à la Component 4 ? Coordination, satisfaction des bénéficiaires IDA / D0570 monitoring and knowledge A posteriori Individuel Open 15,000.00 43,406.44 Signé 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 des services apportés par le management projet y compris la CNAC et l'intercafé BI-MINAGRIE-77329-CS- INDV / Recrutement d'un consultant pour Component 1 ? Institutional l'identification des besoins en IDA / D0570 strengthening and value A posteriori Individuel Open 20,000.00 23,401.49 Signé 2018-09-09 2018-10-28 2018-11-18 2018-12-23 2019-06-21 formation et l'élaboration chain governance d'un plan de renforcement des capacités des coopératives BI-MINAGRIE-77330-CS- INDV / Recrutement d'un Component 2 ? Coffee expert pour l'assistance IDA / D0570 growers productive capacity A posteriori Individuel Open 20,000.00 21,124.91 Signé 2018-09-09 2018-10-28 2018-11-18 2018-12-23 2019-06-21 technique dans la gestion enhancement durable d'une exploitation caféicole Page 11 BI-MINAGRIE -80295-CS- CDS / Recrutement « par entente directe » d'un consultant individuel chargé Component 3 ? Coffee Sélection de de la mobilisation des IDA / D0570 quality improvement and A posteriori consultants par Direct 9,000.00 9,000.00 Signé 2018-10-01 2018-10-11 2018-12-15 2019-06-13 acheteurs du café du market access entente directe Burundi lors de la SEOUL CAFE SHOW 2018 en Corée du Sud BI-MINAGRIE-47994-CS- INDV / Recrutement d'un Component 2 ? Coffee expert pour pour l'assistance IDA / D0570 growers productive capacity A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-06-01 2018-06-06 2018-06-27 2018-08-01 2019-01-28 technique dans la gestion enhancement durable d'une exploitation caféicole BI-MINAGRIE-46800-CS- INDV / Recrutement d'un consultant pour Component 1 ? Institutional l'identification des besoins en IDA / D0570 strengthening and value A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 formation et l'élaboration chain governance d'un plan de renforcement des capacités de coopératives BI-MINAGRIE-47511-CS- INDV / Enquête sur Component 4 ? Coordination, indicateur relatif à la IDA / D0570 monitoring and knowledge A posteriori Individuel Limited 15,000.00 0.00 Annulé 2018-02-12 2018-02-17 2018-03-10 2018-04-14 2018-10-11 satisfaction des bénéficiaires management apportés par le projet y compris la CNAC BI-MINAGRIE-85624-CS- Component 3 ? Coffee Sélection de En cours CDS / SCAA country portrait IDA / D0570 quality improvement and A posteriori consultants par Direct 190,000.00 0.00 2018-11-02 2018-11-12 2019-01-16 2019-07-15 d'exécution 2019 market access entente directe BI-MINAGRIE-85628-CS- INDV / Etude d'identification Component 2 ? Coffee des caunaux d'amélioration En cours IDA / D0570 growers productive capacity A posteriori Individuel Open 30,000.00 0.00 2018-11-02 2018-12-21 2019-01-11 2019-02-15 2019-08-14 de l'accès des caféiculteurs d'exécution enhancement aux engrais subventionés par le projet BI-MINAGRIE-87304-CS- INDV / Recrutement d'un Component 1 ? Institutional consultant pour la formation IDA / D0570 strengthening and value A posteriori Individuel Limited 26,080.00 6,532.01 Signé 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 en gestion des stocks et chain governance l'organisation des sessions de formation BI-MINAGRIE-94481-CS- INDV / Recrutement d'un consultant international et national pour l'évaluation des Component 4 ? Coordination, En cours effets et impacts du PACSC IDA / D0570 monitoring and knowledge A posteriori Individuel Open 50,000.00 0.00 2019-01-10 2019-02-28 2019-03-21 2019-04-25 2019-10-22 d'exécution sur la production, la qualité, management le volmume exporté, prix et accès au marchés haut de gamme. BI-MINAGRIE-95477-CS- INDV / Recrutement d'un Component 4 ? Coordination, En cours assistant en passation des IDA / D0570 monitoring and knowledge A posteriori Individuel Open 21,000.00 0.00 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 d'exécution marchés pour le compte du management PACSC BI-MINAGRIE-94479-CS- Component 4 ? Coordination, En cours INDV / Recrutement d'un IDA / D0570 monitoring and knowledge A posteriori Individuel Open 21,000.00 0.00 2019-02-01 2019-03-22 2019-04-12 2019-05-17 2019-11-13 d'exécution comptable du PACSC management MOF -REF-36 / Assistance Component 1 ? Institutional Sélection de Technique de l'ONUDI à IDA / D0570 strengthening and value A priori consultants par Direct 144,000.00 0.00 Annulé 2017-06-26 2017-07-06 2017-09-09 2018-03-08 ARFIC chain governance entente directe Page 12 BI-MINAGRIE-59477-CS- CDS / Recrutement d'un consultant pour la Component 3 ? Coffee Sélection de mobilisation des acheteurs du IDA / D0570 quality improvement and A priori consultants par Direct 12,000.00 0.00 Annulé 2018-04-16 2018-04-26 2018-06-30 2018-12-27 café du Burundi lors de la market access entente directe SCAA, Edition 2018 aux USA BI-MINAGRIE-48022-CS- Component 3 ? Coffee Sélection de CDS / Entente directe avec IDA / D0570 quality improvement and A priori consultants par Direct 50,000.00 0.00 Annulé 2018-03-15 2018-03-25 2018-05-29 2018-11-25 ACE pour l'organisation de market access entente directe la COE 2018 BI-MINAGRIE-99371-CS- Component 4 ? Coordination, INDV / Recrutement d'un En cours IDA / D0570 monitoring and knowledge A posteriori Individuel Open 21,000.00 0.00 2019-02-06 2019-03-27 2019-04-17 2019-05-22 2019-11-18 consultant junior chargé des d'exécution management Infrastructures BI-MINAGRIE-100854-CS- Component 4 ? Coordination, INDV / Recrutement d'un En cours IDA / D0570 monitoring and knowledge A posteriori Individuel Open 21,000.00 0.00 2019-02-14 2019-04-04 2019-04-25 2019-05-30 2019-11-26 assistant du Responsable du d'exécution management Suivi Evaluation BI-MINAGRIE-101917-CS- INDV / Recrutement d'un consultant international pour Component 1 ? Institutional En attente l'identification des types des IDA / D0570 strengthening and value A posteriori Individuel Open 15,400.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 d'exécution déchets, production des chain governance modules de leur gestion et formation des formateurs BI-MINAGRIE-101919-CS- INDV / Recrutement d'un consultant pour l'adaptation Component 1 ? Institutional En attente des outils réglementaires de IDA / D0570 strengthening and value A posteriori Individuel Open 20,000.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 d'exécution l'INTERCAFE (Statuts, chain governance Règlement d'ordre intérieur, manuel des procédures) BI-MINAGRIE-101921-CS- INDV / Recrutement d'un Component 1 ? Institutional consultant pour la formation En attente IDA / D0570 strengthening and value A posteriori Individuel Open 15,640.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 en Suivi et Evaluation et d'exécution chain governance planification stratégique axée sur les résultats BI-MINAGRIE-101924-CS- CQS / Recrutement Component 3 ? Coffee En attente consultant international pour IDA / D0570 quality improvement and A posteriori Individuel Open 21,000.00 0.00 2019-02-21 2019-04-11 2019-05-02 2019-06-06 2019-12-03 d'exécution élaboration du plan market access d'amélioration de la qualité BI-MINAGRIE-101925-CS- Component 3 ? Coffee Sélection de CDS / Recrutement de l'ACE En cours IDA / D0570 quality improvement and A posteriori consultants par Direct 50,000.00 0.00 2019-02-19 2019-03-01 2019-05-05 2019-11-01 pour pour l'organisation de d'exécution market access entente directe la COE 2019 BI-MINAGRIE-101927-CS- INDV / Recrutement d'un consultant international pour Component 3 ? Coffee la formation des formateurs En attente IDA / D0570 quality improvement and A posteriori Individuel Open 17,500.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 et des utilisateurs du d'exécution market access marché de café (90 sociétés+15 staff Intercafé, Cnac et ARFIC ) BI-MINAGRIE-101915-CS- INDV / Recrutement d'un Component 1 ? Institutional En attente consultant international pour IDA / D0570 strengthening and value A posteriori Individuel Open 8,250.00 0.00 2019-02-21 2019-04-11 2019-05-02 2019-06-06 2019-12-03 d'exécution la formation sur le Suivi chain governance environnemental et social Page 13 BI-MINAGRIE-104096-CS- CDS / Recrutement d'un Component 3 ? Coffee Sélection de consultant pour la En cours IDA / D0570 quality improvement and A posteriori consultants par Direct 11,000.00 0.00 2019-03-04 2019-03-14 2019-05-18 2019-11-14 mobilisation des acheteurs du d'exécution market access entente directe café à la SCAA, Edition 2019 BI-MINAGRIE-104101-CS- CDS / Recrutement d'un consultant pour le Component 1 ? Institutional Sélection de parachèvement des études IDA / D0570 strengthening and value A posteriori consultants par Direct 6,000.00 5,659.90 Signé 2019-03-04 2019-03-14 2019-05-18 2019-11-14 techniques et a surveillance chain governance entente directe des travaux de réhabilitation des bureaux de l'ARFIC BI-MINAGRIE-101916-CS- INDV / Recrutement d'un Component 1 ? Institutional En attente consultant international pour IDA / D0570 strengthening and value A posteriori Individuel Open 14,640.00 0.00 2019-02-19 2019-04-09 2019-04-30 2019-06-04 2019-12-01 d'exécution la formation sur Norme / chain governance grade standard de qualité MOF -REF-45 / Component 4 ? Coordination, Recrutement des experts de IDA / D0570 monitoring and knowledge A posteriori Individuel Direct 280,000.00 0.00 Annulé 2016-11-16 2016-11-26 2016-12-17 2017-01-21 2017-07-20 l'UNCP du PACSC management BI-MINAGRIE-108557-CS- Component 3 ? Coffee Sélection de CDS / Recrutement d'un En cours IDA / D0570 quality improvement and A posteriori consultants par Direct 55,000.00 0.00 2019-04-01 2019-04-11 2019-06-15 2019-12-12 consultant pour l'organisation d'exécution market access entente directe de la COE 2019 BI-MINAGRIE-109833-CS- INDV / Recrutement d'un consultant individuel chargé de la réalisation des études Component 2 ? Coffee techniqueset la surveillance IDA / D0570 growers productive capacity A posteriori Individuel Open 15,000.00 0.00 Annulé 2019-04-09 2019-05-28 2019-06-18 2019-07-23 2020-01-19 des travaux de construction enhancement d'un Centre de documentation de l'ISABU à Kayanza BI-MINAGRIE-117672-CS- CDS / Recrutement de Component 1 ? Institutional Sélection de En cours l'ONUDI par entente directe IDA / D0570 strengthening and value A posteriori consultants par Direct 162,720.00 0.00 2019-05-31 2019-06-10 2019-08-14 2020-02-10 d'exécution pour une assistance chain governance entente directe technique à l'ARFIC. BI-MINAGRIE-124532-CS- CDS / Recrutement de consultants individuels en charge de l’élaboration des mémoires explicatives et des Component 2 ? Coffee Sélection de En attente notes techniques - IDA / D0570 growers productive capacity A posteriori consultants par Direct 35,000.00 0.00 2019-07-24 2019-08-03 2019-10-07 2020-04-04 d'exécution construction d’un labo de enhancement entente directe biotechnologie d’un centre de documentation et de formation- Station ISABU Kayanza Page 14