Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under July 9, 2010 other methods July 9, 2010 PROCUREMENT Senegal : Senegal Tourism and Enterprise Development Project PLAN General Information Country: Senegal Bank’s Approval Date of the Original Procurement Plan: 2017-08-14 2021-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P146469 GPN Date: Project Name: Senegal Tourism and Enterprise Development Project Loan / Credit No: IDA / 60190, IDA / Q9590, IDA / Q9940 WORKS AND INVESTMENTS AGENCY Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T1 / Sélection d'une entreprise pour la réalisation des travaux physiques de Sustainable Tourism Single Stage - One 35,800,000.0 40,265,060. 2021-01- protection, de restauration et IDA / Q9590 A priori Appel d'offres Open - International Signé 2018-09-07 2017-10-16 2018-10-07 2017-11-04 2018-11-27 2018-01-16 2018-12-27 2018-06-20 2019-01-31 2018-08-10 Development Envelope 0 21 20 d'entretien des plages de la station balnéaire de Saly Portudal T10 / sélection d'une entreprise pour la réalisation Sustainable Tourism Single Stage - One 2019-03- des Travaux physiques de IDA / Q9940 A posteriori Appel d'offres Open - International 3,240,000.00 0.00 Annulé 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 Development Envelope 04 protection et entretien des plages de Saly Niakh Niakhal T4 / Travaux de construction et de réhabilitation d'infrastructures dans le cadre Sustainable Tourism Single Stage - One 2021-09- du plan d'accompagnement IDA / 60190 A posteriori Demande de prix Limited 169,985.00 139,515.53 Signé 2021-01-10 2021-02-11 2021-03-07 2021-05-17 Development Envelope 03 social de la protection, restauration et entretien des plages de Saly T5 / Travaux de construction et de réhabilitation des Supporting Enterprise Single Stage - One En attente 2022-02- plateformes d'investissements IDA / 60190 A posteriori Appel d'offres Open - National 380,000.00 0.00 2021-04-15 2021-04-20 2021-06-01 2021-07-01 2021-08-05 Creation and Growth Envelope d'exécution 01 de Saint-Louis, Saly et Ziguinchor T3 / Travaux de construction et de réhabilitation d'infrastructures dans le cadre Sustainable Tourism Single Stage - One 2021-02- du plan d'accompagnement IDA / 60190 A posteriori Demande de prix 169,985.00 0.00 Annulé 2020-06-21 2020-08-16 Development Envelope 12 social de la protection, restauration et entretien des plages de Saly Request for T6 / Travaux d'aménagement Quotations - Small et de pose de cloisons au Single Stage - One En attente 2021-10- IDA / 60190 Project implementation A posteriori Demande de prix Limited Works 22,000.00 0.00 2021-06-30 2021-08-25 deuxième étage de Envelope d'exécution 24 (Emergency) SPD - l'immeuble Clairafrique Competitive National T7 / Sélection d'une Procurement entreprise pour les travaux Sustainable Tourism Single Stage - One En attente 2022-03- IDA / 60190 A posteriori Demande de prix Limited Document - 1 77,600.00 0.00 2021-07-28 2021-09-22 d'assainissement des plages Development Envelope d'exécution 21 Envelope process rechargées de Saly (Non Bank-SPD) Request for Bids - T8 / Réalisation d'une allée Sustainable Tourism Single Stage - One Small Works SPD En attente 2022-02- piétonne sur la station IDA / 60190 A posteriori Appel d'offres Open - National 452,600.00 0.00 2021-08-10 2021-08-15 2021-09-26 2021-10-26 2021-11-30 Development Envelope (1 envelope d'exécution 28 balnéaire process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F5 / Acquisition de goodies, Supporting Enterprise Single Stage - One matériels de communication IDA / 60190 A posteriori Demande de prix Limited 70,000.00 47,054.37 Achevé 2018-02-27 2017-12-13 2018-04-24 2018-07-23 2018-07-23 2018-11-14 Creation and Growth Envelope dans le cadre du BPC F1 / Acquisition de Single Stage - One IDA / Q9590 Project implementation A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2017-12-04 2018-01-30 2018-03-31 fournitures de bureaux Envelope F8 / Acquisition de Matériels Supporting Enterprise Single Stage - One et consommables IDA / 60190 A posteriori Appel d'offres Open - National 210,000.00 0.00 Annulé 2018-01-30 2018-07-31 2018-02-04 2018-03-18 2018-09-25 2018-04-17 2018-05-22 2018-07-21 Creation and Growth Envelope informatiques F20 / Acquisition de Single Stage - One matériels de vidéo-conférence IDA / 60190 Project implementation A posteriori Demande de prix Limited 21,000.00 21,988.62 Signé 2019-03-30 2019-07-22 2019-05-25 2019-09-26 2019-11-21 Envelope au profit de l'UGP F12 / Solution matérielle et équipement complémentaire du Datacenter DGID (Lot1: Fourniture & install. de modules onduleurs, câbles Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 550,000.00 429,630.29 Signé 2018-12-21 2018-12-17 2018-12-26 2019-02-01 2019-02-06 2019-01-29 2019-03-08 2019-03-12 2019-04-12 2019-07-03 2019-10-09 réseau- lot 2: Fourniture & Creation and Growth Envelope install d'une solution dédiée à SIGTAS et ETAX et mise à niveau de la plateforme virtuelle serveurs) F15 / Acquisition d'une ERP Single Stage - One IDA / 60190 Project implementation A posteriori Demande de prix Limited 40,000.00 40,686.06 Signé 2019-06-08 2020-01-06 2019-08-04 2020-06-11 2020-01-31 pour l'UGP Envelope F3 / Acquisition de véhicules Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 154,000.00 0.00 Annulé 2018-12-14 2018-12-19 2019-01-30 2019-03-01 2019-04-05 2019-10-02 en deux (02) lots Creation and Growth Envelope F9 / Acquisition de mobiliers Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 24,500.00 23,323.60 Signé 2019-06-15 2019-08-02 2019-08-10 2019-12-17 2020-02-06 de bureau en trois lots Creation and Growth Envelope Page 1 F4 / Réalisation de supports de communication (support Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 24,200.00 22,947.03 Signé 2019-08-10 2019-09-06 2019-10-05 2019-12-20 2020-04-02 promotionel, plaquettes…) au Development Envelope profit de l'ASPT F17 / Acquisition de Supporting Enterprise Single Stage - One matériels et consommables IDA / 60190 A posteriori Demande de prix Limited 30,900.00 11,344.06 Signé 2019-09-15 2019-09-27 2019-11-10 2020-01-08 2020-05-08 Creation and Growth Envelope informatiques en 4 lots F30 / Réalisation et Sustainable Tourism Single Stage - One installation de panneaux IDA / 60190 A posteriori Demande de prix Limited 80,800.00 82,773.78 Signé 2019-10-27 2019-11-07 2019-12-22 2020-05-15 2020-06-19 Development Envelope signalétiques F10 / Acquisition de Sustainable Tourism Single Stage - One matériels audiovisuels pour le IDA / 60190 A posteriori Demande de prix Limited 78,000.00 0.00 Annulé 2018-11-20 2018-12-28 2019-01-15 2019-07-14 Development Envelope Ministère du Tourisme S27 / Conception et installation de panneaux Sustainable Tourism Single Stage - One signalétiques dans les sites et IDA / 60190 A posteriori Demande de prix Limited 80,000.00 0.00 Annulé 2019-11-05 2019-12-31 2020-06-28 Development Envelope circuits touristiques au profit du MTTA F6 / Acquisition d'équipements frigorifiques Sustainable Tourism Single Stage - One dans le cadre du plan IDA / 60190 A posteriori Demande de prix Limited 25,330.00 45,626.68 Signé 2020-05-10 2021-01-22 2020-07-05 2021-03-25 2021-01-01 Development Envelope d'accompagnement social des travaux de Saly F16 / Acquisition de matériels de pêche, de transformation de produits Sustainable Tourism Single Stage - One halieutiques et de nettoiement IDA / 60190 A posteriori Demande de prix Limited 37,965.00 96,287.44 Achevé 2020-05-31 2020-10-20 2020-07-26 2021-01-06 2021-01-22 2021-04-15 Development Envelope dans le cadre du plan d'accompagnement social des travaux de Saly ( en 3 lots) F11 / Acquisition d'un Single Stage - One logiciel de gestion de projet IDA / 60190 Project implementation A posteriori Demande de prix Limited 64,000.00 0.00 Annulé 2019-01-01 2019-02-26 2019-08-25 Envelope pour l'UGP F2 / Acquisition de produits d'entretien pour les locaux Single Stage - One IDA / 60190 Project implementation A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-11-27 2018-01-19 2018-03-20 devant abriter l'Unité de Envelope Gestion du Projet F18 / Acquisition de kits de protection pour la mise en conformité des Plateformes de Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 5,350.00 6,259.48 Achevé 2020-09-06 2020-09-17 2020-11-01 2020-12-11 2020-12-11 2021-01-27 l’Investissement et pour l’UGP Creation and Growth Envelope : gestes barrières contre la Covid-19 F19 / Acquisition de mobiliers de bureau pour les Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 28,750.00 20,792.94 Signé 2020-11-07 2020-11-09 2021-01-02 2021-03-30 2021-04-02 plateformes (Nord Sud et Creation and Growth Envelope Centre) et l'UGP en deux (02) F24 / Acquisition de matériels informatiques pour l'UGP, les Plateformes d'investissement, le Tribunal Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 105,067.00 78,392.95 Signé 2020-10-29 2020-11-09 2020-11-03 2021-02-02 2020-12-15 2020-12-15 2021-01-14 2020-12-31 2021-02-18 2021-04-12 2021-04-19 Commercial hors classe de Creation and Growth Envelope Dakar et le renforcement du dispositif d'alimentation électrique de secours F22 / Acquisition de matériels lourds (camions) dans le cadre du programme Sustainable Tourism Single Stage - One En cours IDA / 60190 A posteriori Appel d'offres Open - National 404,105.00 447,083.45 2021-01-12 2021-01-15 2021-01-17 2021-01-21 2021-02-28 2021-02-23 2021-03-30 2021-03-30 2021-05-04 2021-10-31 d’urgence d’attractivité et Development Envelope d'exécution d’assainissement de la station de Saly F26 / Acquisition de Supporting Enterprise Single Stage - One En attente mobiliers de bureau en trois IDA / 60190 A posteriori Demande de prix Limited 80,000.00 0.00 2021-04-10 2021-06-05 2021-09-03 Creation and Growth Envelope d'exécution (03) lots F23 / Acquisition de matériels informatiques et Supporting Enterprise Single Stage - One électroniques pour IDA / 60190 A posteriori Demande de prix Limited 95,000.00 0.00 Annulé 2020-05-19 2020-07-14 2021-01-10 Creation and Growth Envelope l'UGP/PDTE et le Tribunal de Commerce de Dakar (3 lots) F27 / Sélection d'un prestataire pour la mise en place d'un système de vidéo surveillance d'autonomie Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Demande de prix Limited 34,000.00 0.00 2021-05-05 2021-06-30 2021-12-27 solaire et climatisation en 2 Creation and Growth Envelope d'exécution lots au profit du Tribunal de Commerce Hors classe de Dakar F25 / Acquisition de Fournitures de bureaux, de Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 146,000.00 0.00 2021-04-30 2021-05-05 2021-06-16 2021-07-16 2021-08-20 2021-11-18 matériels et de consommables Creation and Growth Envelope d'exécution informatiques en six (06) lots. F7 / Acquisition de cinq (05) véhicules répartis en deux Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 252,487.00 0.00 2021-09-23 2021-09-28 2021-11-09 2021-12-09 2022-01-13 2022-04-13 (02) lots pour APIX (DEA) et Creation and Growth Envelope d'exécution l'ADEPME (FFP/BPC) F28 / Acquisition de matériels pour l'entretien et la Sustainable Tourism Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 404,105.00 0.00 2021-08-17 2021-08-22 2021-10-03 2021-11-02 2021-12-07 2022-03-07 maintenance des ouvrages et Development Envelope d'exécution des plages de Saly NON CONSULTING SERVICES Page 2 Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S1 / Sélection d'une agence de communication pour la Single Stage - One Cérémonie de lancement du IDA / Q9590 Project implementation A posteriori Demande de prix Limited 40,000.00 64,846.82 Achevé 2017-11-20 2018-09-28 2018-01-15 2018-10-15 2018-03-16 2018-11-23 Envelope projet de protection et restauration des plages S4 / Sélection d'une agence chargée de de la communication Fonds à Frais Partagé (LOT1) et de la Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 445,000.00 182,891.18 Signé 2017-11-03 2017-12-12 2017-11-08 2017-12-20 2018-01-17 2018-01-19 2018-02-08 2018-02-23 2018-06-21 2020-02-13 communication du concours Creation and Growth Envelope de business plans et de cérémonie de remise des prix (LOT2) S7 / Sélection d'une agence chargée de de la Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 225,000.00 0.00 Annulé 2017-09-15 2017-09-20 2017-11-02 2017-12-02 2018-01-06 2019-06-30 communication Fonds à Frais Creation and Growth Envelope Partagés S20 / Campagne d'affichage pour la deuxième édition du Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 90,000.00 90,790.62 Signé 2018-02-28 2018-10-22 2018-04-25 2019-03-06 2018-10-22 concours national de business Creation and Growth Envelope plan S21 / Acquisition de supports Single Stage - One En attente IDA / 60190 Project implementation A posteriori Demande de prix Limited 33,000.00 0.00 2018-02-20 2018-04-17 2018-06-16 de promotion pour le Projet Envelope d'exécution S30 / SÉLECTION D'UNE AGENCE CHARGÉE DE LA COMMUNICATION DU Supporting Enterprise Single Stage - One CONCOURS DE BUSINESS IDA / 60190 A posteriori Appel d'offres Open - National 225,000.00 218,045.10 Signé 2018-07-02 2018-08-15 2018-07-07 2018-08-18 2018-09-25 2018-09-17 2018-10-04 2018-10-22 2019-04-24 2020-04-14 Creation and Growth Envelope PLANS ET DE L'ORGANISATION DE LA CÉRÉMONIE DE REMISE DES PRIX ( RELANCE) S28 / Sélection d'une agence de Voyage et de Tourisme Sustainable Tourism Single Stage - One pour l'organisation IDA / 60190 A posteriori Demande de prix Limited 80,000.00 32,501.43 Achevé 2018-10-31 2019-02-11 2018-12-26 2019-05-31 2019-06-24 2019-10-30 Development Envelope d'Eductours combinés à un voyage de presse S25 / Création de banque d'images et Conception de films et vidéos promotionnels Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 241,000.00 163,702.35 Signé 2019-01-30 2019-08-20 2019-02-04 2019-03-18 2019-09-24 2019-04-17 2019-11-26 2019-05-22 2020-05-26 2019-11-18 au profit de la destination en Development Envelope deux (02) lots pour le Ministère du Tourisme S13 / Sélection d'une agence de communication pour Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 73,000.00 74,810.00 Achevé 2018-11-03 2018-10-26 2018-12-29 2018-12-20 2019-06-27 2019-02-11 l'organisation du forum de la Creation and Growth Envelope PME S14 / Renouvellement du Supporting Enterprise Single Stage - One système de sécurité réseau du IDA / 60190 A posteriori Demande de prix Limited 97,000.00 172,564.79 Signé 2019-01-01 2019-08-20 2019-02-26 2020-02-27 2019-08-25 Creation and Growth Envelope Datacenter de la DGID S29 / Sélection d'une agence chargée d'accompagner le Sustainable Tourism Single Stage - One Ministère du Tourisme pour IDA / 60190 A posteriori Appel d'offres Open - International 323,283.00 0.00 Annulé 2018-10-17 2018-10-22 2018-12-03 2019-01-02 2019-02-06 2019-08-05 Development Envelope l'organisation de TERANGA DAYS (workshop) S10 / Conception et Sustainable Tourism Single Stage - One installation des signalétiques IDA / 60190 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2017-10-12 2017-10-17 2017-11-28 2017-12-28 2018-02-01 2018-04-02 Development Envelope dans les sites touristiques S9 / Conception et impression de manuels de Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 90,000.00 0.00 Annulé 2018-01-12 2018-01-17 2018-02-28 2018-03-30 2018-05-04 2018-09-01 vente à destination des Development Envelope professionnels du Tourisme F21 / CAMPAGNE DE COMMUNICATION POUR LA Sustainable Tourism Single Stage - One DESTINATION SENEGAL SUR IDA / 60190 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2018-02-23 2018-02-28 2018-04-11 2018-05-11 2018-06-15 2018-12-12 Development Envelope SES MARCHES PRIORITAIRES EN EUROPE S11 / Sélection d'un cabinet pour l'organisation d'ateliers Supporting Enterprise Single Stage - One d'informations et de IDA / 60190 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2018-01-10 2018-03-07 2019-03-03 Creation and Growth Envelope communication sur l'entreprenariat S5 / Location de panneaux Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 180,000.00 0.00 Annulé 2017-12-20 2017-12-25 2018-02-05 2018-03-07 2018-04-11 2020-03-31 numériques et traditionnels Creation and Growth Envelope S32 / Sélection d'une agence chargée d'accompagner le Ministère du Tourisme pour Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 78,400.00 0.00 Annulé 2019-06-22 2019-07-26 2019-08-17 2019-10-16 l'organisation de TERANGA Development Envelope DAYS en France, Belgique et Espagne S33 / Sélection de prestataires pour l’animation Supporting Enterprise Single Stage - One d’une série d’ateliers sur les IDA / 60190 A posteriori Appel d'offres Open - National 113,000.00 0.00 Annulé 2019-10-15 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 Creation and Growth Envelope techniques du commerce international S18 / Sélection d'un prestataire en charge de la Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 48,500.00 44,158.80 Signé 2019-05-05 2020-04-09 2020-04-23 2020-08-19 2020-10-20 notation des candidats du Creation and Growth Envelope Concours Business plan Page 3 S12 / Sélection d'une agence pour la réalisation de Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 96,000.00 0.00 Annulé 2018-10-30 2018-12-25 2019-06-23 supports de communication Development Envelope pour le Ministère du Tourisme S31 / Sélection d'une agence de Communication pour la Supporting Enterprise mise en place des procédures IDA / 60190 A posteriori Demande de prix 8,080.00 0.00 Annulé 2020-05-05 2020-05-05 2020-05-05 Creation and Growth du Tribunal de Commerce hors classe de Dakar S22 / Sélection d'une agence chargée d'accompagner le Ministère du Tourisme pour Sustainable Tourism Single Stage - One IDA / 60190 A posteriori Appel d'offres Open - National 162,000.00 0.00 Annulé 2019-10-24 2019-10-29 2019-12-10 2020-01-09 2020-02-13 2020-08-11 l'organisation de TERANGA Development Envelope DAYS en France, Belgique et Espagne S26 / Élaboration de supports audio-visuels pour Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 16,000.00 0.00 Annulé 2018-11-12 2019-01-07 2019-07-06 les projets des éditions Creation and Growth Envelope précédentes du Concours Business plan S3 / Création et production des supports de Single Stage - One IDA / 60190 Project implementation A posteriori Demande de prix Limited 23,500.00 10,685.54 Signé 2019-03-03 2019-10-22 2019-04-28 2020-01-08 2019-10-25 communication pour l'Unité Envelope de Gestion du Projet S3L2 / Réalisation et production de film institutionnel sur les travaux de protection, d’entretien et Single Stage - One IDA / 60190 Project implementation A posteriori Demande de prix Limited 43,500.00 21,313.40 Signé 2020-06-27 2020-04-28 2020-08-22 2020-08-19 2021-02-18 de restauration des plages de Envelope Saly dans le cadre du Projet de Développement Touristique et des Entreprises S16 / Organisation atelier sur l'entrepreneuriat et Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 37,500.00 0.00 Annulé 2019-04-20 2019-05-29 2019-06-15 2019-12-12 organisation des CRD (Pré- Creation and Growth Envelope campagne) S17 / Sélection d'un prestataire pour la formation Supporting Enterprise Single Stage - One IDA / 60190 A posteriori Demande de prix Limited 89,000.00 0.00 Annulé 2019-07-15 2019-09-09 2020-03-07 des candidats du concours Creation and Growth Envelope national de plan d'affaires S35 / Sélection d'une agence de communication pour la Single Stage - One IDA / 60190 Project implementation A posteriori Demande de prix Limited 80,000.00 109,431.38 Signé 2020-12-26 2020-12-18 2021-02-04 2021-01-11 2021-02-14 cérémonie de réception des Envelope travaux de Saly S15 / Selection d'une agence de communication pour la Supporting Enterprise Single Stage - One En attente vulgarisation des activités du IDA / 60190 A posteriori Demande de prix Limited 73,000.00 0.00 2021-04-06 2021-06-01 2021-11-28 Creation and Growth Envelope d'exécution Tribunal de Commerce de Dakar S6 / Réalisation de Supporting Enterprise Single Stage - One En attente reportages vidéo sur les IDA / 60190 A posteriori Demande de prix Limited 60,000.00 0.00 2021-05-26 2021-07-21 2023-07-11 Creation and Growth Envelope d'exécution projets et le concours de business plans S36 / Sélection d'une agence de communication, pour la campagne, la création et Supporting Enterprise Single Stage - One En attente IDA / 60190 A posteriori Appel d'offres Open - National 113,000.00 0.00 2021-05-14 2021-05-19 2021-06-30 2021-07-30 2021-09-03 2022-03-02 production de supports de Creation and Growth Envelope d'exécution communication en deux (02) lots S38 / Sélection de prestataires pour le nettoyage Single Stage - One En attente et le gardiennage du IDA / 60190 Project implementation A posteriori Demande de prix Limited 10,000.00 0.00 2021-04-25 2021-06-20 2022-06-20 Envelope d'exécution deuxième Etage de l'Immeuble Clairafrique en 2 lots S39 / Sélection d'un Sustainable Tourism Single Stage - One En attente prestataire pour le nettoyage IDA / 60190 A posteriori Demande de prix Limited 5,800.00 0.00 2021-07-28 2021-09-22 2021-10-22 Development Envelope d'exécution des plages de Saly CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1 / Recrutement d'un Sélection fondée cabinet en charge de la IDA / 60190 Project implementation A posteriori sur la qualité et le Open - National 240,000.00 130,608.46 Signé 2017-06-22 2017-01-30 2017-07-12 2017-08-25 2017-09-07 2017-09-22 2017-11-14 2017-10-22 2018-01-02 2017-11-26 2018-02-08 2017-12-31 2018-06-06 2020-09-16 facilitation et de la coût communication sociales Sélection fondée C8 / Sélection d'un cabinet IDA / 60190 Project implementation A priori sur la qualité et le Open - National 60,000.00 0.00 Annulé 2017-10-12 2017-11-02 2017-12-16 2018-01-13 2018-02-12 2018-03-19 2018-04-23 2021-04-07 chargé de l'Audit financier coût F13 / Recrutement d'un Sélection fondée Supporting Enterprise assistant technique (firme) IDA / 60190 A posteriori sur la qualité et le Open - International 200,000.00 0.00 Annulé 2017-10-31 2017-11-21 2018-01-01 2018-01-29 2018-02-28 2018-04-04 2018-05-09 2019-05-09 Creation and Growth internationale : télépaiement coût C32 / Mise à jour du logiciel Supporting Enterprise Sélection au de gestion des projets et du IDA / 60190 A posteriori Open - National 40,000.00 40,040.65 Achevé 2017-09-27 2017-11-06 2017-10-18 2017-12-01 2018-09-27 2017-12-29 2018-10-26 2018-01-28 2019-02-07 2018-03-04 2019-03-12 2018-04-08 2019-07-22 2018-10-05 2020-01-16 Creation and Growth moindre coût système de suivi évaluation C25 / Sélection d'une entité Sélection fondée Supporting Enterprise en charge de la formation et IDA / 60190 A posteriori sur la qualité et le Open - National 350,000.00 0.00 Annulé 2017-11-07 2017-11-28 2018-01-11 2018-02-08 2018-03-10 2018-04-14 2018-05-19 2020-05-08 Creation and Growth de la notation des candidats coût Page 4 C46 / SELECTION D'UN CABINET CHARGE DE L'ETUDE Sélection fondée D'IMPACT ENVIRONNEMENTAL Sustainable Tourism IDA / Q9940 A posteriori sur la qualité et le Open - National 162,000.00 179,667.89 Signé 2017-09-20 2017-07-11 2017-10-11 2017-11-24 2017-12-22 2018-02-15 2018-01-21 2018-04-23 2018-02-25 2018-05-31 2018-04-01 2018-09-21 2018-06-30 ET SOCIAL DU DRAGAGE POUR Development coût LA RESTAURATION DES PLAGES DE SALY C45 / Sélection d'un cabinet Sélection fondée pour une mission d'assistance Sustainable Tourism IDA / Q9940 A posteriori sur la qualité et le Open - International 325,000.00 0.00 Annulé 2017-10-04 2017-10-23 2017-10-25 2017-12-08 2018-01-05 2018-02-04 2018-03-11 2018-04-15 2019-04-15 technique des travaux de Saly Development coût Niakh Niakhal C35 / Etudes de faisabilité Sélection fondée Sustainable Tourism des projets de Kafountine- IDA / 60190 A posteriori sur la qualité et le Open - International 400,000.00 299,574.58 Signé 2017-11-23 2017-11-06 2017-12-14 2018-08-24 2018-01-27 2018-11-08 2018-02-24 2019-02-19 2018-03-26 2019-02-07 2018-04-30 2019-03-12 2018-06-04 2019-07-16 2018-09-02 Development Abéné coût Sélection fondée C63 / Sélection d'un cabinet En attente IDA / 60190 Project implementation A posteriori sur la qualité et le Open - National 60,000.00 0.00 2018-10-09 2018-10-30 2018-12-13 2019-01-10 2019-02-09 2019-03-16 2019-04-20 2020-04-19 chargé de l'Audit financier d'exécution coût C66 / Sélection d'un bureau de contrôle technique pour les Sélection fondée ouvrages fixes des travaux Sustainable Tourism sur les IDA / 60190 A posteriori Open - International 242,000.00 243,740.83 Signé 2018-09-12 2018-08-27 2018-10-03 2018-09-28 2018-11-16 2018-12-16 2018-12-18 2019-01-20 2019-03-04 2019-07-19 physiques de protection Development qualifications des restauration et entretien des consultants plages de Saly Sélection fondée C10 / Elaboration du Plan de sur les IDA / 60190 Project implementation A posteriori Open - National 20,000.00 0.00 Annulé 2018-01-17 2018-02-07 2018-04-29 2018-05-29 2018-07-03 2018-10-01 formation du projet qualifications des consultants Sélection fondée C5 / Sélection d'un cabinet sur les pour l'Audit technique pour IDA / 60190 Project implementation A posteriori Open - National 90,000.00 0.00 Annulé 2017-11-20 2017-12-12 2018-01-25 2018-02-24 2018-03-31 2018-06-29 qualifications des les ouvrages consultants C50 / Etude sur le mode de Sélection fondée gestion, entretien et Sustainable Tourism sur les maintenance des ouvrages IDA / 60190 A posteriori Open - National 24,200.00 206,245.06 Signé 2019-06-03 2019-05-08 2019-06-24 2019-08-21 2019-08-07 2019-11-08 2019-09-06 2019-12-10 2019-10-11 2020-06-02 2020-04-08 Development qualifications des réalisés à Saly dans le cadre consultants du PDTE C69 / Etudes de faisabilité et Sélection fondée d'exécution et mise à niveau Sustainable Tourism IDA / 60190 A posteriori sur la qualité et le Open - International 484,000.00 0.00 Annulé 2018-12-20 2018-11-26 2019-01-10 2019-02-23 2019-03-23 2019-04-22 2019-05-27 2019-07-01 2020-06-30 du pôle touristique du Lac Development coût Rose C34 / Elaboration d'un Sélection fondée master plan d'aménagement Sustainable Tourism IDA / 60190 A posteriori sur la qualité et le Open - International 500,000.00 0.00 Annulé 2017-09-11 2017-11-06 2017-10-02 2017-11-15 2017-12-13 2018-01-12 2018-02-16 2018-03-23 2018-09-19 touristique de la petite côte et Development coût du littoral sud C33 / Sélection d'un cabinet Sélection fondée pour le renforcement de Supporting Enterprise sur les IDA / 60190 A posteriori Open - National 46,500.00 0.00 Annulé 2017-11-17 2017-12-12 2018-02-15 2018-02-25 2018-03-28 2020-03-17 capacités des PME en matière Creation and Growth qualifications des d'exportation. consultants C40 / Etude diagnostic et de Sélection fondée mise à niveau Sustainable Tourism sur les IDA / 60190 A posteriori Open - National 70,000.00 0.00 Annulé 2018-01-19 2018-01-19 2018-01-19 2018-01-19 2018-02-09 2018-05-10 environnemental au profit de Development qualifications des la SAPCO consultants S19 / Sélection d'un Consultant pour l'animation Sélection fondée d'une série d'ateliers de Supporting Enterprise sur les IDA / 60190 A posteriori Open - National 115,000.00 135,306.13 Achevé 2019-11-20 2019-10-21 2019-12-11 2020-10-27 2020-01-24 2020-02-07 2020-02-23 2020-07-20 2020-03-29 2020-10-19 2020-09-25 2020-12-11 formation sur les techniques Creation and Growth qualifications des du Commerce international consultants pour le FFP. F14 / Services de consultant pour l'étude filières et Sélection fondée investissement, et Supporting Enterprise sur les élaboration du profil IDA / 60190 A posteriori Open - National 180,000.00 0.00 Annulé 2017-11-23 2017-12-14 2018-01-29 2018-02-28 2018-04-04 2020-04-03 Creation and Growth qualifications des d'attractivité des régions et de consultants la cartographie des produits exports C81 / Recrutement d’un cabinet pour l’élaboration et la mise en œuvre d’une Sélection fondée stratégie de marketing Sustainable Tourism IDA / 60190 A posteriori sur la qualité et le Open - National 323,000.00 0.00 Annulé 2020-03-10 2020-04-16 2020-03-31 2020-04-21 2020-05-14 2020-06-11 2020-07-11 2020-08-15 2020-09-19 2021-09-19 territorial appliquée au Development coût tourisme au profit de l'Agence sénégalaise de Promotion touristique (ASPT). C82 / Sélection d’un cabinet chargé de l’élaboration de la politique, des procédures et des outils de gestion Sélection fondée Sustainable Tourism environnementale et sociale IDA / 60190 A posteriori sur la qualité et le Open - National 80,820.00 113,176.12 Signé 2020-03-13 2020-03-27 2020-04-03 2020-10-28 2020-05-17 2020-07-21 2020-06-14 2020-10-05 2020-07-14 2020-10-08 2020-08-18 2020-11-12 2020-09-22 2021-03-23 2021-09-22 Development de la Société d’Aménagement coût et de Promotion des Côtes et zones touristiques du Sénégal (SAPCO) C9 / Etat des lieux sur l'environnement ces affaires Sélection fondée locales (cartographie sur les IDA / 60190 Project implementation A posteriori Open - National 60,000.00 0.00 Annulé 2017-10-18 2017-11-08 2017-12-22 2018-01-21 2018-02-25 2018-05-26 investissements privés qualifications des tourisme...) à Saly, Ziguinchor consultants et Saint Louis C2 / Sélection d'un cabinet Sélection fondée pour l'Etude d'impact Sustainable Tourism sur les IDA / 60190 A posteriori Open - National 120,000.00 0.00 Annulé 2018-01-16 2018-02-06 2018-03-22 2018-04-21 2018-05-26 2018-08-24 environnemental et social Development qualifications des pour le dragage consultants C47 / Sélection d'un cabinet Sélection fondée pour la réalisation de l'étude Sustainable Tourism sur les d'impact environnemental et IDA / Q9940 A posteriori Open - National 48,500.00 0.00 Annulé 2017-10-27 2017-07-31 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-06-04 Development qualifications des social pour les travaux de Saly consultants Niakh Niakhal Page 5 C76 / Coaching des lauréats Sélection fondée Supporting Enterprise du Concours national de Plan IDA / 60190 A posteriori sur la qualité et le Open - National 197,000.00 0.00 Annulé 2019-11-04 2019-11-25 2020-01-08 2020-02-05 2020-03-06 2020-04-10 2020-05-15 2021-05-15 Creation and Growth d'affaires - Seconde édition coût C87 / Sélection d'un cabinet pour la mise en place d'un Sélection fondée Sustainable Tourism En cours système d'information IDA / 60190 A posteriori sur la qualité et le Open - National 161,645.00 0.00 2020-07-21 2020-08-25 2020-08-11 2021-01-13 2020-09-24 2020-12-24 2020-10-22 2021-01-26 2020-11-21 2021-02-23 2020-12-26 2021-04-08 2021-01-30 2022-01-30 Development d'exécution géographique (SIG) au profit coût de la SAPCO-Sénégal C89 / Recrutement d'un cabinet pour la mission d'assistance technique pour la mise en oeuvre d'un Sélection fondée Sustainable Tourism En cours programme IDA / 60190 A posteriori sur la qualité et le Open - National 161,645.00 0.00 2020-08-17 2020-03-27 2020-09-07 2020-11-02 2020-10-21 2020-12-24 2020-11-18 2021-01-26 2020-12-18 2021-02-23 2021-01-22 2021-04-01 2021-02-26 2022-02-26 Development d'exécution d'accompagnement de l'unité coût de gestion environnementale et sociale de la SAPCO- Sénégal C84 / Sélection d'un cabinet pour la création de la marque Sélection fondée touristique de la destination Sustainable Tourism En cours IDA / 60190 A posteriori sur la qualité et le Open - International 750,000.00 0.00 2020-09-04 2020-08-05 2020-09-25 2020-11-04 2020-11-08 2021-04-06 2020-12-06 2021-05-06 2021-01-05 2021-02-09 2021-03-16 2022-03-16 Sénégal et élaboration et mise Development d'exécution coût en oeuvre de stratégies de marketing touristique C83 / Recrutement d’un cabinet chargé de l’élaboration de Business Model, de manuel de Sélection fondée Supporting Enterprise En cours procédures et une proposition IDA / 60190 A posteriori sur la qualité et le Open - National 113,150.00 0.00 2020-08-18 2020-07-23 2020-09-08 2021-03-10 2020-10-22 2021-03-09 2020-11-19 2021-04-13 2020-12-19 2021-01-23 2021-02-27 2022-02-27 Creation and Growth d'exécution de textes normatifs ou coût réglementaires pour les Plateformes de l’Investissement C16 / Sélection d'un bureau d'études pour le diagnostic sur l'état des locaux, les études architecturales et d'aménagement et Supporting Enterprise Sélection au IDA / 60190 A posteriori Open - National 135,000.00 220,053.83 Signé 2019-05-28 2019-05-14 2019-06-18 2019-07-31 2019-10-28 2019-08-28 2019-11-13 2019-09-27 2019-11-13 2019-11-01 2019-11-13 2019-12-06 2020-04-21 2020-06-03 supervision des travaux de Creation and Growth moindre coût réhabilitation des locaux abritant les plateformes de Saly et Ziguinchor et Saint- Louis C15 / Sélection d'un bureau d'études pour le diagnostic sur l'état des locaux, les Sélection fondée études architecturales et Supporting Enterprise sur les d'aménagement et IDA / 60190 A posteriori Open - National 35,500.00 0.00 Annulé 2019-07-25 2019-05-14 2019-08-15 2019-09-28 2019-10-28 2019-12-02 2020-05-30 Creation and Growth qualifications des supervision des travaux de consultants réhabilitation des locaux abritant la plateforme de Saint Louis C85 / Sélection d'un cabinet pour le développement de produits touristiques et la Sélection fondée mise en ouvre s'un Sustainable Tourism En cours IDA / 60190 A posteriori sur la qualité et le Open - International 350,000.00 0.00 2020-08-20 2020-07-17 2020-09-10 2020-11-13 2020-10-24 2020-12-24 2020-11-21 2021-01-28 2020-12-21 2021-03-18 2021-01-25 2021-03-01 2022-03-01 programme de promotion des Development d'exécution coût investissements des poles Dakar, Saly - Petite Côte, Delta du Saloum C88 / Sélection d'un cabinet Sélection fondée pour l'assistance technique du Sustainable Tourism En cours IDA / 60190 A posteriori sur la qualité et le Open - International 525,400.00 0.00 2020-10-19 2020-07-17 2020-11-09 2020-11-02 2020-12-23 2021-02-01 2021-01-20 2021-03-02 2021-02-19 2021-03-26 2021-04-30 2022-04-30 Ministère du Tourisme et des Development d'exécution coût Transports aériens (MTTA) C90 / Sélection d'un cabinet pour le Diagnostic du Sélection fondée dispositif électronique de la Supporting Enterprise En cours IDA / 60190 A posteriori sur la qualité et le Open - National 210,135.00 0.00 2021-01-11 2020-12-30 2021-02-01 2021-03-25 2021-03-17 2021-04-14 2021-05-14 2021-06-18 2021-07-23 2022-07-23 plateforme de création Creation and Growth d'exécution coût d’entreprises pour la zone centre-ouest S34 / Encadrement des entreprises issues des Sélection fondée Supporting Enterprise lauréats de la première édition IDA / 60190 A posteriori sur la qualité et le Open - National 177,810.00 0.00 Annulé 2020-11-27 2020-12-18 2021-01-31 2021-02-28 2021-03-30 2021-05-04 2021-06-08 2022-06-08 Creation and Growth du concours national de coût business plans. C13 / Recrutement d'un cabinet pour l'élaboration et la Sélection fondée mise en œuvre d'une stratégie Sustainable Tourism En cours IDA / 60190 A posteriori sur la qualité et le Open - International 323,500.00 0.00 2020-12-28 2021-02-11 2021-01-18 2021-04-15 2021-03-03 2021-03-31 2021-04-30 2021-06-04 2021-07-09 2022-07-09 de marketing territorial Development d'exécution coût appliquée au tourisme (relance) C92 / Recrutement d'un Sélection fondée cabinet pour l'élaboration Sustainable Tourism IDA / 60190 A posteriori sur la qualité et le Open - National 485,000.00 0.00 En cours d'examen 2021-02-26 2021-07-14 2021-03-19 2021-04-15 2021-05-02 2021-05-30 2021-06-29 2021-08-03 2021-09-07 2022-09-07 d'un plan de développement Development coût intégré de la Petite-Côte. C80 / Sélection d'un cabinet pour l'encadrement des Sélection fondée entreprises issues des Supporting Enterprise En cours IDA / 60190 A posteriori sur la qualité et le Open - National 501,000.00 0.00 2021-04-23 2021-02-05 2021-05-14 2021-04-19 2021-06-27 2021-07-25 2021-08-24 2021-09-28 2021-11-02 2022-11-02 lauréats du concours national Creation and Growth d'exécution coût de business Plan réparti en deux (02) missions C97 / Sélection d'un cabinet Sélection fondée chargé de l'Étude portant sur Supporting Enterprise IDA / 60190 A posteriori sur la qualité et le Open - National 130,000.00 0.00 En cours d'examen 2021-03-01 2021-05-18 2021-03-22 2021-05-05 2021-06-02 2021-07-02 2021-08-06 2021-09-10 2022-09-10 le business plan du projet de Creation and Growth coût Scoring universel C96 / Sélection d'un cabinet pour l'appui à la mutualisation Sélection fondée des services de la CCIA de Supporting Enterprise sur les En cours IDA / 60190 A posteriori Open - National 80,820.00 0.00 2021-03-22 2021-03-15 2021-04-12 2021-05-26 2021-06-25 2021-07-30 2022-01-26 Ziguinchor et des Creation and Growth qualifications des d'exécution organisations professionnelles consultants avec la PLI Sud Page 6 C67 / Sélection d’un établissement de formation professionnelle pour le Sélection fondée renforcement de capacité des Supporting Enterprise sur les En attente acteurs des plateformes de IDA / 60190 A posteriori Open - National 70,980.00 0.00 2021-07-05 2021-07-26 2021-09-08 2021-10-08 2021-11-12 2022-01-11 Creation and Growth qualifications des d'exécution l’investissement et du service consultants informatique de la Direction générale des Impôts et des Domaines (DGID) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C4 / Recrutement en En cours Spécialiste en passation de IDA / 60190 Project implementation A priori Individuel Open 108,000.00 0.00 2017-06-27 2017-11-14 2017-08-15 2017-08-10 2017-09-05 2017-10-10 2018-04-08 d'exécution marchés C7 / Recrutement d'un spécialiste en ingénierie IDA / 60190 Project implementation A priori Individuel Limited 72,000.00 0.00 En cours d'examen 2017-07-13 2017-10-12 2017-07-18 2017-11-03 2017-08-08 2017-09-12 2020-08-27 sociale C11 / Audit technique des IDA / 60190 Project implementation A priori Individuel Limited 20,000.00 0.00 Annulé 2018-04-30 2018-05-05 2018-05-26 2018-06-30 2018-09-28 bénéficiaires du FFP et BPC C37 / Recrutement d'un PMO Sustainable Tourism IDA / 60190 A priori Individuel Open 180,000.00 0.00 Annulé 2017-06-22 2017-08-10 2017-08-31 2017-10-05 2022-09-09 (Project Mgmt Offcer). Development C6 / Sélection d'un Chargé de mission Environnement pour IDA / 60190 Project implementation A priori Individuel Limited 72,000.00 0.00 Annulé 2017-10-28 2017-11-02 2017-11-23 2017-12-28 2020-12-12 le fonds à frais partagés et l'ADEPME C27 / Sélection d'un cabinet Sélection de pour la mise à niveau et Supporting Enterprise IDA / 60190 A priori consultants par Direct 190,000.00 0.00 Annulé 2017-11-23 2017-12-03 2018-02-06 2020-01-27 maintenance de la plateforme Creation and Growth entente directe IT C39 / Recrutement d'un Sustainable Tourism expert environnementaliste au IDA / 60190 A priori Individuel Open 108,000.00 0.00 Annulé 2017-12-20 2018-02-07 2018-02-28 2018-04-04 2023-03-09 Development profit de la SAPCO C30 / Recrutement d'un Supporting Enterprise expert international pour le IDA / 60190 A priori Individuel Open 120,000.00 0.00 Annulé 2017-10-16 2017-11-10 2017-12-15 2017-12-25 2018-01-25 2019-01-25 Creation and Growth FFP C3 / Recrutement Ingénieur IDA / 60190 Project implementation A priori Individuel Open 216,000.00 0.00 Annulé 2017-10-03 2017-10-22 2017-11-21 2017-12-12 2018-01-16 2020-12-31 côtier Senior C48 / RECRUTEMENT D'UN COORDONNATEUR POUR LE Sélection de PROJET DE DÉVELOPPEMENT IDA / Q9940 Project implementation A priori consultants par Direct 312,000.00 0.00 Annulé 2017-09-15 2017-09-25 2017-11-29 2022-11-03 DU TOURISME ET DES entente directe ENTREPRISES REGC1 / MISSION D'ASSISTANCE A MAITRISE D'OEUVRE DANS LE CADRE DE Sélection de LA REALISATION DES Sustainable Tourism IDA / Q9940 A priori consultants par Direct 1,800,000.00 0.00 Annulé 2015-01-19 2017-10-12 2015-01-27 2015-01-27 2016-05-07 2018-04-27 TRAVAUX PHYSIQUES DE Development entente directe RESTAURATION, PROTECTION ET ENTRETIEN DES PLAGES DE SALY C55 / QUANTIFICATION ET CARACTERISATION PHYSICO CHIMIQUE ET BACTERIOLOGIQUE DES SEDIMENTS, DES HABITATS ET Sélection de Sustainable Tourism DES ESPECES MARINES AU IDA / 60190 A posteriori consultants par Direct 65,000.00 103,041.93 Signé 2017-12-27 2018-03-05 2018-03-12 2018-05-16 2018-10-31 2018-05-25 Development NIVEAU DES ZONES DE entente directe DRAGAGE ET D'AMENAGEMENT DES OUVRAGES DE LA ZONE DE SALY C57 / Recrutement d'un expert national en Supporting Enterprise IDA / 60190 A posteriori Individuel Open 54,000.00 137,262.16 Signé 2018-01-30 2018-06-14 2018-03-20 2020-02-27 2018-04-10 2020-02-27 2018-05-15 2020-10-19 2019-05-10 développement des Creation and Growth exportations C56 / Recrutement d'un Sustainable Tourism assistant technique en génie IDA / 60190 A posteriori Individuel Open 216,000.00 181,273.19 Signé 2018-01-30 2018-03-20 2018-02-22 2018-04-10 2018-06-10 2018-05-15 2018-08-23 2018-11-11 Development côtier C58 / Recrutement d'un PMO IDA / 60190 Project implementation A posteriori Individuel Open 180,000.00 0.00 Annulé 2018-01-31 2019-06-25 2018-03-21 2018-04-11 2018-05-16 2018-11-12 (Project Mgmt Officer) C60 / RECRUTEMENT D'UN COORDONNATEUR POUR LE Sélection de En attente PROJET DE DÉVELOPPEMENT IDA / 60190 Project implementation A posteriori consultants par Direct 312,000.00 0.00 2018-02-15 2018-02-25 2018-05-01 2018-10-28 d'exécution DU TOURISME ET DES entente directe ENTREPRISES C61 / Sélection d'un cabinet Sélection de pour la mise à niveau et Supporting Enterprise IDA / 60190 A posteriori consultants par Direct 190,000.00 81,417.20 Signé 2018-03-30 2018-09-17 2018-04-09 2018-11-07 2018-06-13 2019-07-09 2018-12-10 maintenance de la plateforme Creation and Growth entente directe IT C64 / Sélection d'un Expert Sustainable Tourism Environnementaliste au profit IDA / 60190 A posteriori Individuel Open 108,000.00 50,709.80 Signé 2018-03-20 2018-01-14 2018-05-08 2018-12-09 2018-05-29 2018-12-05 2018-07-03 2019-06-11 2018-12-30 Development de la SAPCO C65 / Recrutement d'un Supporting Enterprise expert international pour le IDA / 60190 A posteriori Individuel Open 120,000.00 173,640.00 Signé 2018-02-28 2017-10-24 2018-04-18 2019-02-05 2018-05-09 2019-02-25 2018-06-13 2019-03-26 2018-12-10 Creation and Growth FFP Page 7 C70 / Sélection d'un Project Sustainable Tourism Manager Office (PMO) pour le IDA / 60190 A posteriori Individuel Limited 192,000.00 61,261.35 Signé 2018-04-20 2017-06-01 2018-04-25 2017-09-08 2018-05-05 2018-03-13 2018-05-15 2018-06-12 2019-05-15 Development Ministère du Tourisme C71 / Sélection d'un expert Sustainable Tourism en tourisme pour le Ministère IDA / 60190 A posteriori Individuel Limited 96,000.00 43,093.88 Signé 2018-07-16 2017-12-21 2018-07-21 2018-11-30 2018-08-11 2019-02-08 2018-09-15 2019-05-22 2020-09-14 Development du Tourisme C72 / Recrutement d'un cabinet de consultant pour le Sélection de coaching et le suivi de Supporting Enterprise IDA / 60190 A posteriori consultants par Direct 180,000.00 235,635.74 Signé 2018-05-25 2018-04-23 2018-06-04 2018-08-08 2018-07-16 2019-02-04 manière personnalisée des Creation and Growth entente directe lauréats du Concours National de Business édition 2016 C29 / Recrutement d'un Supporting Enterprise juriste (huissier ou avocat) IDA / 60190 A priori Individuel Limited 36,000.00 0.00 Annulé 2017-06-15 2017-06-20 2017-07-11 2017-08-15 2018-02-11 Creation and Growth pour les prix C77 / Mise à jour des Sélection de Sustainable Tourism statistiques 2016-2017 du IDA / 60190 A posteriori consultants par Direct 64,000.00 67,973.60 Achevé 2018-11-30 2018-10-15 2018-12-10 2019-02-13 2019-06-03 2019-08-12 2019-12-18 Development Ministère du Tourisme entente directe C73 / Sélection d'un expert pour l'élaboration d'un plan IDA / 60190 Project implementation A posteriori Individuel Limited 8,080.00 0.00 Annulé 2019-05-30 2019-06-04 2019-06-25 2019-07-30 2020-01-26 de formation pour l'ensemble du personnel du Projet C59 / Sélection d'un Chargé de mission Environnement Supporting Enterprise IDA / 60190 A posteriori Individuel Open 72,000.00 0.00 Annulé 2018-02-15 2018-04-05 2018-04-26 2018-05-31 2018-11-27 pour le fonds à frais partagés Creation and Growth et l'ADEPME C42 / Sélection d'un cabinet Sélection de pour la formation des guides Sustainable Tourism IDA / 60190 A posteriori consultants par Direct 120,000.00 0.00 Annulé 2018-01-01 2018-01-11 2018-03-17 2018-06-15 et acteurs touristiques au Development entente directe Sénégal C78 / Sélection d'un cabinet pour la Préparation du Plan de Gestion Environnemental et Sélection de Sustainable Tourism Social (PGES) des travaux de IDA / 60190 A posteriori consultants par 34,000.00 37,831.02 Achevé 2019-10-17 2019-05-17 2019-10-17 2019-08-02 2019-10-17 2020-11-20 2019-10-17 2021-01-27 Development restauration protection et entente directe entretien des plages du village de Saly Niakh-Niakhal C79 / Elaboration du plan de Sustainable Tourism IDA / 60190 A posteriori Individuel Limited 40,410.00 61,490.92 Signé 2020-04-06 2019-09-25 2020-04-11 2020-05-09 2020-05-02 2020-08-04 2020-06-06 2020-10-02 2020-12-03 gestion intégrée de Saly Development C43 / Enquêtes statistiques Sélection de Sustainable Tourism sur l'offre et la demande IDA / 60190 A posteriori consultants par Direct 34,000.00 0.00 Annulé 2017-10-27 2017-11-08 2017-11-04 2018-01-08 2018-02-07 Development touristiques 2016 et 2017 entente directe C62 / Audit technique des IDA / 60190 Project implementation A posteriori Individuel Limited 20,000.00 0.00 Annulé 2018-06-22 2018-06-27 2018-07-18 2018-08-22 2019-02-18 bénéficiaires du FFP et BPC C12 / Recrutement d’un expert individuel pour le suivi environnemental des travaux Sustainable Tourism IDA / 60190 A posteriori Individuel Limited 43,600.00 88,774.25 Signé 2020-07-10 2020-04-06 2020-07-15 2020-08-10 2020-08-05 2020-10-20 2020-09-09 2020-12-23 2021-03-08 physiques de protection, Development restauration et entretien des plages de Saly. C91 / Etude portant sur l’accompagnement de l’ASTP Sélection de pour la définition Sustainable Tourism En cours IDA / 60190 A posteriori consultants par Direct 148,930.00 284,391.08 2020-11-10 2020-08-03 2020-11-20 2021-01-04 2021-01-24 2021-07-23 d’un programme de formation Development d'exécution entente directe post- Covid des acteurs touristiques au Sénégal. C68 / Recrutement d'un agent pour le suivi-évaluation Supporting Enterprise En attente IDA / 60190 A posteriori Individuel Limited 16,000.00 0.00 2021-01-15 2021-01-20 2021-02-10 2021-03-17 2021-09-13 du Concours national de Plan Creation and Growth d'exécution d'affaires C93 / Recrutement d'un prestataire pour le traitement En cours IDA / 60190 Project implementation A posteriori Individuel Limited 14,000.00 0.00 2021-03-05 2021-03-10 2021-03-31 2021-05-05 2022-05-05 exclusif des dossiers de d'exécution paiement du FFP et BPC C94 / Recrutement d’un Supporting Enterprise En cours expert environnemental pour IDA / 60190 A posteriori Individuel Direct 43,500.00 0.00 2021-03-10 2021-03-18 2021-03-20 2021-04-10 2021-05-15 2022-05-15 Creation and Growth d'exécution le concours de plans d’affaires C95 / Sélection d'un cabinet chargé de l'élaboration de la Sélection de Supporting Enterprise En cours stratégie nationale IDA / 60190 A posteriori consultants par 194,000.00 0.00 2021-03-26 2021-03-15 2021-04-05 2021-06-09 2022-06-09 Creation and Growth d'exécution d’exportation (SN export entente directe 2023) C101 / Recrutement d'un facilitateur superviseur dans Sustainable Tourism En attente le cadre de la réalisation des IDA / 60190 A posteriori Individuel Direct 16,722.00 0.00 2021-08-05 2021-08-15 2021-09-05 2021-10-10 2022-04-08 Development d'exécution projets d'intérêt communautaires à Saly C102 / Recrutement d'un animateur (animateur 1) dans le cadre de la facilitation Sustainable Tourism En attente IDA / 60190 A posteriori Individuel Direct 7,700.00 0.00 2021-08-05 2021-08-15 2021-09-05 2021-10-10 2022-04-08 sociale pour la réalisation des Development d'exécution projets d'intérêt communautaire à Saly C103 / Recrutement d'un animateur (animateur 2) dans le cadre de la facilitation Sustainable Tourism En attente IDA / 60190 A posteriori Individuel Direct 7,700.00 0.00 2021-08-05 2021-08-15 2021-09-05 2021-10-10 2022-04-08 sociale pour la réalisation des Development d'exécution projets d'intérêt communautaire à Saly Page 8 C100 / Sélection d'une agence web pour la mise en Sélection de Supporting Enterprise En attente place d'un projet west Africa E- IDA / 60190 A posteriori consultants par Direct 54,480.00 0.00 2021-07-30 2021-08-09 2021-10-13 2022-04-11 Creation and Growth d'exécution Commerce au profit de entente directe l'ADEPME Page 9