PROCUREMENT PLAN Project information: Mozambique, Smallholder Irrigated Agriculture and Market Access Project, Grant Number D3510-MZ. Project Implementation agency: Ministry of Agriculture and Food Security-AIMU-Agriculture Investment Management Unit. Date of the Procurement Plan: April 5, 2019. Period covered by this Procurement Plan:18 (Eighteen months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in The Mozambique Procurement Regulations, Decree 5/2016 of March 8, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable . PROCUREMENT Mozambique : Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2019-04-25 2021-07-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164431 GPN Date: Project Name: Smallholder Irrigated Agriculture and Market Access Project- IRRIGA 1 Loan / Credit No: IDA / D3510 NATIONAL INSTITUTE OF IRRIGATION Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MZ-INIR-174293-CW-RFB / Component 2-Smallholder Five Irrigation System Single Stage - One 2,281,957.9 2021-07- IDA / D3510 Irrigation Development and Post Request for Bids Open - National 2,690,000.00 Signed 2020-09-30 2020-08-26 2020-10-05 2020-09-02 2020-11-16 2020-09-29 2020-12-16 2020-11-16 2021-01-20 2020-12-31 Construction in Manica Envelope 8 19 Management Province MZ-INIR-174295-CW-RFB / Component 2-Smallholder Request for Single Stage - One 2021-05- Rehabilitating IRRIGA Project IDA / D3510 Irrigation Development and Post Limited 170,000.00 179,150.65 Signed 2020-10-05 2020-09-16 2020-11-30 2020-12-31 Quotations Envelope 29 Office in Zambezia Province Management MZ-INIR-174296-CW-RFB / Component 2-Smallholder Request for Single Stage - One 2021-05- Rehabilitating IRRIGA Project IDA / D3510 Irrigation Development and Post Limited 150,000.00 182,597.32 Signed 2020-10-05 2020-09-08 2020-11-30 2020-12-02 Quotations Envelope 29 Office in Manica Province Management MZ-INIR-180509-CW-RFB / Component 2-Smallholder Pending Acaboco Irrigation System 2021-08- IDA / D3510 Irrigation Development and Post Request for Bids 2,500,000.00 0.00 Implementat 2020-10-20 2020-10-25 2020-12-06 2021-01-05 2021-02-09 Construction, 314 Ha, Buzi 08 Management ion District, Sofala Province MZ-INIR-197130-CW-RFB / Component 2-Smallholder M'ziva Irrigation Ssytem Single Stage - One 1,252,617.8 2021-11- IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,300,000.00 Signed 2021-01-18 2021-01-06 2021-01-23 2021-04-29 2021-03-06 2021-02-12 2021-04-05 2021-03-05 2021-05-10 2021-04-26 Construction, 165, Nicoadala Envelope 3 06 Management District, Zambézia MZ-INIR-207153-CW-RFQ / Rehabilitation Works of Component 1-Institutional Request for Single Stage - One 2021-08- IDA / D3510 Post Limited 150,000.00 177,045.29 Signed 2020-12-23 2021-01-06 2021-02-17 2021-03-11 IRRIGA Project Offices in Beira, Capacity Building Quotations Envelope 16 Sofala Provínce MZ-INIR-180508-CW-RFB / M´ziva Irrigation System Component 2-Smallholder Single Stage - One 2021-10- Construction, 165 Ha, IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2020-12-17 2020-12-22 2021-02-02 2021-03-04 2021-04-08 Envelope 05 Nicoadala District, Zambezia Management Province MZ-INIR-227956-CW-RFQ / Rehabilitation Works of IRRIGA Component 1-Institutional Request for Single Stage - One 2021-12- IDA / D3510 Post Limited 100,000.00 64,646.72 Signed 2021-04-28 2021-04-22 2021-06-23 2021-06-30 Project Offices in Nampula Capacity Building Quotations Envelope 20 province. National MZ-INIR-180497-CW-RFB / Component 2-Smallholder Procurement Pending Chiverano Irrigation System Single Stage - One 2022-05- IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 1,000,000.00 0.00 Implementat 2021-07-13 2021-07-18 2021-08-29 2021-09-28 2021-11-02 Construction, 110 Ha, Mopeia Envelope 01 Management Envelope process ion District, Zambezia Province (Non Bank-SPD) National MZ-INIR-231415-CW-RFB / Component 2-Smallholder Procurement Pending Single Stage - One 2022-05- Reahabilitation of Tsetsera IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 1,100,000.00 0.00 Implementat 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 Envelope 03 Irrigation Schemes Management Envelope process ion (Non Bank-SPD) National MZ-INIR-207152-CW-RFB / Component 2-Smallholder Procurement Pending ACABOCO IRRIGATION Single Stage - One 2022-12- IDA / D3510 Irrigation Development and Post Request for Bids Open - National Document - 1 2,500,000.00 0.00 Implementat 2021-08-31 2021-09-05 2021-10-17 2021-11-16 2021-12-21 SYSTEM CONSTRUCTION, 314 Envelope 21 Management Envelope process ion Ha, BÚZI DISTRICT, SOFALA (Non Bank-SPD) PROVINCE Request for Bids - MZ-INIR-246033-CW-RFB / Component 2-Smallholder Pending Single Stage - One Small Works SPD 2022-06- Construction of CHEMBA IDA / D3510 Irrigation Development and Post Request for Bids Open - National 2,800,000.00 0.00 Implementat 2021-08-20 2021-08-25 2021-10-06 2021-11-05 2021-12-10 Envelope (1 envelope 08 Irrigation Schemes 330 ha Management ion process) Request for Bids - MZ-INIR-246047-CW-RFB / Component 2-Smallholder Pending Single Stage - One Small Works SPD 2022-06- CHICUMBUA I and II Irrigation IDA / D3510 Irrigation Development and Post Request for Bids Open - National 1,500,000.00 0.00 Implementat 2021-08-20 2021-08-25 2021-10-06 2021-11-05 2021-12-10 Envelope (1 envelope 08 rehabilitation works Management ion process) GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109235-GO-RFQ / Equipamento informático (16 Component 4- Project Under Request for Single Stage - One Computadores tipo Laptop, 6 IDA / D3510 Management and Monitoring Post Limited 78,900.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope Datashow, 6 Impressoras e 5 and Evaluation on Video Conferencias) MZ-INIR-109256-GO-RFQ / Component 4- Project Under Request for Single Stage - One Aquisição de 5 Smart TV IDA / D3510 Management and Monitoring Post Limited 7,500.00 0.00 Implementati 2019-04-16 2019-06-26 2019-06-11 2019-12-08 Quotations Envelope (Televisores) and Evaluation on MZ-INIR-129230-GO-RFQ / Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 950,000.00 393,283.34 Signed 2019-09-14 2019-09-23 2019-11-09 2019-12-03 2020-05-07 Purchase of Production Kits Capacity Building Quotations Envelope MZ-INIR-129114-GO-RFB / Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 300,000.00 236,899.15 Signed 2019-09-09 2019-12-16 2019-09-14 2020-01-08 2019-10-26 2020-02-06 2019-11-25 2020-02-27 2019-12-30 2020-03-06 2020-06-27 Purchase of 55 Motorcycles Capacity Building Envelope MZ-INIR-139505-GO-RFQ / Aquisition of computer Component 1-Institutional Request for Single Stage - One equipment for the elaboration IDA / D3510 Post Limited 100,000.00 112,209.52 Signed 2019-10-21 2019-11-14 2019-12-16 2019-12-17 2020-06-13 Capacity Building Quotations Envelope of the integrated agrarian survey Page 1 MZ-INIR-140873-GO-RFQ / Acquisition of Protective Component 1-Institutional Request for Single Stage - One Material for Extension IDA / D3510 Post Limited 100,000.00 0.00 Canceled 2019-11-02 2019-12-28 2020-06-25 Capacity Building Quotations Envelope Technicians in Manica and Sofala Provinces MZ-INIR-109253-GO-RFB / Component 4- Project Single Stage - One Aquisicao de 6 Viaturas 4X4, IDA / D3510 Management and Monitoring Post Request for Bids Open - National 240,000.00 0.00 Canceled 2019-04-11 2019-06-06 2019-04-16 2019-08-26 2019-05-28 2019-06-27 2019-08-01 2020-01-28 Envelope Dupla Cabine. and Evaluation MZ-INIR-146499-GO-RFB / Acquisition of Protective Material for Extension Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 200,000.00 187,317.36 Signed 2019-11-28 2019-12-16 2019-12-03 2020-01-08 2020-01-14 2020-02-04 2020-02-13 2020-04-03 2020-03-19 2020-06-04 2020-09-15 Technicians in Manica, Sofala, Capacity Building Envelope Zambezia and Nampula Provinces MZ-INIR-146504-GO-RFB / Component 4- Project Purchase of 6 (six) 4x4 double Single Stage - One IDA / D3510 Management and Monitoring Post Request for Bids Open - National 290,000.00 333,854.45 Signed 2019-11-29 2019-12-17 2019-12-04 2020-01-08 2020-01-15 2020-02-05 2020-02-14 2020-02-13 2020-03-20 2020-02-26 2020-09-16 cab vehicles and one (01) Mini Envelope and Evaluation Bus MZ-INIR-166426-GO-RFQ / Supply and installation of integrated sound and video Component 1-Institutional Request for Single Stage - One system for the Consultative IDA / D3510 Post Limited 35,000.00 85,468.54 Signed 2020-04-15 2020-04-08 2020-06-10 2020-06-01 2020-12-07 Capacity Building Quotations Envelope Council of Meeting Room of the Ministry of Agriculture and Rural Development MZ-INIR-109262-GO-RFQ / Component 4- Project Aquisição de Software de Request for Single Stage - One IDA / D3510 Management and Monitoring Post Limited 40,000.00 29,336.14 Signed 2020-07-05 2020-06-10 2020-08-30 2020-09-14 2021-02-26 Gestão Financeira Quotations Envelope and Evaluation (Parametrização) MZ-INIR-180461-GO-RFQ / Acquisition of Information Component 1-Institutional Request for Single Stage - One IDA / D3510 Post Limited 20,000.00 23,903.10 Signed 2020-07-18 2020-07-10 2020-09-12 2020-07-23 2021-03-11 Equipment for the Fund Capacity Building Quotations Envelope Mobilization Unit MZ-INIR-180512-GO-RFB / Acquisition and Installation of Component 2-Smallholder Single Stage - One 6 Pivo Systems for Irrigating IDA / D3510 Irrigation Development and Prior Request for Bids Open - International 2,750,000.00 0.00 Canceled 2020-07-27 2020-08-01 2020-09-12 2020-10-12 2020-11-16 2021-05-15 Envelope 330ha, Chemba District, Management Sofala Province MZ-INIR-206315-GO-RFQ / Pending Component 1-Institutional Request for Single Stage - One Acquisition of various graphic IDA / D3510 Post Limited 100,000.00 0.00 Implementati 2021-07-16 2021-09-10 2021-12-09 Capacity Building Quotations Envelope material on MZ-INIR-216077-GO-RFB / Under Component 1-Institutional Single Stage - One Acquisition of IT Equipment IDA / D3510 Post Request for Bids Open - National 160,000.00 0.00 Implementati 2021-07-14 2021-06-23 2021-07-29 2021-07-26 2021-09-09 2021-10-09 2021-11-28 2022-05-27 Capacity Building Envelope for PIU and PMU on Under MZ-INIR-238725-GO-RFB / Component 1-Institutional Single Stage - One IDA / D3510 Post Request for Bids Open - National 360,000.00 0.00 Implementati 2021-06-30 2021-07-22 2021-07-05 2021-07-22 2021-08-16 2021-09-15 2021-10-20 2022-04-18 Acquisition of 6 vehicles, 4x4 Capacity Building Envelope on NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-185455-NC-RFQ / Contracting of sound, image, printing services for provincial Under Component 1-Institutional Request for Single Stage - One replicas in the ambit of the IDA / D3510 Post Limited 60,000.00 0.00 Implementati 2020-08-01 2020-09-26 2021-03-25 Capacity Building Quotations Envelope launch of the program on SUSTENTA in Manica, Sofala, Zambezia and Nampula. MZ-INIR-217221-NC-RFQ / Component 3-Agriculture Under Services Provider of the IDA / D3510 Intensification and Market Post Direct Selection Direct 35,000.00 0.00 Implementati 2021-02-14 2021-02-18 2021-02-19 2021-02-23 2021-03-26 2021-09-22 Electronic Producer Support Linkages on latform (ONE STOP SOLUTION) MZ-INIR-217227-NC-RFB / Hiring of E-vouchers Service Component 3-Agriculture Under Provider for the Irrigations Single Stage - One IDA / D3510 Intensification and Market Post Request for Bids Open - National 220,000.00 0.00 Implementati 2021-02-14 2021-03-17 2021-02-19 2021-03-31 2021-03-21 2021-04-20 2021-05-25 2022-05-25 Schemes of Manica, Sofala, Envelope Linkages on Zambezia and Nampula Provinces MZ-INIR-238777-NC-RFQ / Progress and Results Pending Component 1-Institutional Request for Single Stage - One Information Monitoring IDA / D3510 Post Limited 100,000.00 0.00 Implementati 2021-07-05 2021-08-30 2022-02-26 Capacity Building Quotations Envelope System (SMIPRE) of irriga on project CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-129100-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 300,000.00 275,000.00 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-22 2020-02-07 2020-08-14 2020-03-13 2020-09-30 2020-04-17 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Manica Province Page 2 MZ-INIR-129103-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 132,153.48 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-27 2020-02-07 2020-08-26 2020-03-13 2020-09-16 2020-03-16 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Sofala Province MZ-INIR-129104-CS-QCBS / Impact Assessment and Executive Rehabilitation Component 2-Smallholder Quality And Cost- Project Preparation for some IDA / D3510 Irrigation Development and Post Open - National 150,000.00 121,956.07 Signed 2019-09-02 2019-09-19 2019-09-23 2019-12-19 2019-11-06 2020-03-19 2019-12-04 2020-05-29 2020-01-03 2020-07-27 2020-02-07 2020-08-19 2020-03-13 2020-09-30 2020-04-17 Based Selection Irrigation Systems Affected by Management IDAI Cyclone in Zambezia Province MZ-INIR-129111-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Sofala Management Province. MZ-INIR-129110-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Management Zambezia Province. MZ-INIR-129106-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Nampula Management Province. MZ-INIR-129112-CS-QCBS / Irrigation Infrastructure Component 2-Smallholder Quality And Cost- Investment Pre-Feasibility and IDA / D3510 Irrigation Development and Post Open - National 200,000.00 0.00 Canceled 2019-09-09 2019-09-19 2019-09-30 2019-11-13 2019-12-11 2020-01-10 2020-02-14 2020-03-20 2020-07-18 Based Selection Feasibility Studies in Manica Management Province. MZ-INIR-146515-CS-CQS / Contracting a company to Component 4- Project Consultant recruit technicians for the IDA / D3510 Management and Monitoring Post Qualification Open - National 100,000.00 0.00 Canceled 2019-12-23 2019-12-17 2020-01-13 2020-02-26 2020-03-27 2020-05-01 2020-10-28 IRRIGA Project at central and and Evaluation Selection provincial levels MZ-INIR-146523-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Nampula province and Supervision of the respective works MZ-INIR-146521-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Zambezia province and Supervision of the respective works MZ-INIR-146520-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Manica province and Supervision of the respective works MZ-INIR-146518-CS-QCBS / Irrigation infrastructure investment Pre-feasibility and Feasibility Studies and elaboration of executive Component 2-Smallholder Quality And Cost- projects for IDA / D3510 Irrigation Development and Prior Open - International 750,000.00 0.00 Canceled 2019-12-23 2020-02-11 2020-01-13 2020-02-26 2020-03-25 2020-04-24 2020-05-29 2020-07-03 2021-07-03 Based Selection construction/rehabilitation of Management 750 hectares of irrigation systems in Sofala province and Supervision of the respective works MZ-INIR-183480-CS-CQS / Component 2-Smallholder Consultant Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Qualification Limited 360,000.00 290,377.40 Signed 2020-07-30 2020-07-15 2020-08-13 2020-07-15 2020-09-12 2020-08-19 2020-10-17 2020-10-07 2021-04-15 System Supervision Management Selection MZ-INIR-180472-CS-QCBS / Component 2-Smallholder Five Irrigation System Quality And Cost- IDA / D3510 Irrigation Development and Post Open - National 270,000.00 244,915.65 Signed 2020-08-31 2020-08-26 2020-09-21 2020-11-25 2020-11-04 2020-12-22 2020-12-02 2021-01-27 2021-01-01 2021-03-24 2021-02-05 2021-03-18 2021-03-12 2021-04-27 2022-03-12 Supervision in Manica Based Selection Management Province MZ-INIR-180481-CS-CQS / Component 2-Smallholder Consultant Environmental Audit of IDA / D3510 Irrigation Development and Post Qualification Limited 90,000.00 94,851.91 Signed 2020-08-31 2020-08-03 2020-09-14 2020-08-03 2020-10-14 2021-03-24 2020-11-18 2021-05-05 2021-05-17 PROIRRI irrigations Management Selection MZ-INIR-180484-CS-CQS / Component 2-Smallholder Consultant Resettlement Action Plan IDA / D3510 Irrigation Development and Post Qualification Limited 50,000.00 126,181.54 Signed 2020-08-31 2020-08-03 2020-09-14 2020-08-03 2020-10-14 2021-02-11 2020-11-18 2021-04-08 2021-05-17 (PAR) for the Chirimonio - Management Selection ACABOCO Irrigation MZ-INIR-180476-CS-QCBS / Component 2-Smallholder Quality And Cost- Munda Munda Irrigation IDA / D3510 Irrigation Development and Post Open - National 360,000.00 0.00 Canceled 2020-07-20 2020-07-15 2020-08-10 2020-09-23 2020-10-21 2020-11-20 2020-12-25 2021-01-29 2022-01-29 Based Selection System Supervision Management Page 3 MZ-INIR-185302-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Manica Province MZ-INIR-185308-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Nampula Province MZ-INIR-185306-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Zambezia Province MZ-INIR-185305-CS-QCBS / 750 ha Irrigation Component 2-Smallholder Quality And Cost- Infrastructure Projection and IDA / D3510 Irrigation Development and Post Open - International 750,000.00 0.00 Canceled 2020-08-31 2020-08-18 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2022-03-12 Based Selection Its Construction Supervision Management in Sofala Province MZ-INIR-189875-CS-CQS / IRRIGA Project Office Component 2-Smallholder Consultant Rehabilitation Works IDA / D3510 Irrigation Development and Post Qualification Limited 35,000.00 84,296.31 Signed 2020-09-15 2020-09-23 2020-09-29 2020-10-01 2020-10-29 2021-04-26 2020-12-03 2021-04-27 2021-06-01 Supervision in Manica and Management Selection Zambezia Provinces MZ-INIR-197081-CS-QCBS / Manica and Sofala 1 500 ha Component 2-Smallholder Quality And Cost- Irrigation Infrastructure IDA / D3510 Irrigation Development and Prior Open - International 1,500,000.00 0.00 Under Review 2020-10-12 2020-10-06 2020-11-02 2020-10-30 2021-01-16 2021-02-15 2021-03-17 2021-04-21 2021-05-26 2022-05-26 Based Selection Projection and Its Management Construction Supervision MZ-INIR-197082-CS-QCBS / Zambézia and Nampula 1 500 Component 2-Smallholder Quality And Cost- ha Irrigation Infrastructure IDA / D3510 Irrigation Development and Prior Open - International 1,500,000.00 0.00 Under Review 2020-10-12 2020-10-01 2020-11-02 2020-10-30 2021-01-16 2021-02-15 2021-03-17 2021-05-07 2021-06-11 2022-06-11 Based Selection Projection and Its Management Construction Supervision MZ-INIR-197084-CS-CQS / Component 4- Project Consultant Supervision Construction Under IDA / D3510 Management and Monitoring Post Qualification Open - National 130,000.00 0.00 2020-12-14 2021-01-04 2021-01-04 2021-02-09 2021-02-17 2021-03-19 2021-04-23 2021-10-20 Works for Mziva Irrigation Implementation and Evaluation Selection System MZ-INIR-197087-CS-CQS / Component 4- Project Consultant Supervision Construction IDA / D3510 Management and Monitoring Post Qualification Open - National 100,000.00 0.00 Canceled 2020-10-19 2020-11-09 2020-12-23 2021-01-22 2021-02-26 2021-08-25 Works for CRIDF Irrigation and Evaluation Selection System MZ-INIR-206197-CS-QCBS / Service provider for training Component 3-Agriculture and coordination of farmer Quality And Cost- Under IDA / D3510 Intensification and Market Post Open - National 350,000.00 0.00 2020-12-15 2021-01-07 2021-01-14 2021-03-17 2021-03-15 2021-04-12 2021-05-12 2021-06-16 2021-07-21 2022-07-21 associations with acess to the Based Selection Implementation Linkages market in Intabo irrigation scheme in Zambézia province MZ-INIR-206312-CS-LCS / Development and Installation of an Electronic Platform Component 4- Project (online) for the Least Cost Under IDA / D3510 Management and Monitoring Post Open - National 60,000.00 0.00 2020-12-21 2021-01-07 2021-01-11 2021-06-08 2021-02-24 2021-03-24 2021-04-23 2021-05-28 2021-07-02 2021-07-05 implementation of the and Selection Implementation and Evaluation Complaints Management Mechanism of the IRRIGA Project. MZ-INIR-206919-CS-CQS / Risk Analysis of Gender-Based Component 3-Agriculture Consultant Violence (VBG) at Project Under IDA / D3510 Intensification and Market Post Qualification Limited 70,000.00 0.00 2021-01-14 2021-01-18 2021-01-28 2021-02-27 2021-04-03 2021-09-30 Implementation Sites: Implementation Linkages Selection Development of intervention strategy and action plan MZ-INIR-215845-CS-CQS / Consultant Component 1-Institutional Irrigation Speciaslist IDA / D3510 Post Qualification Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-14 2021-04-13 2021-05-18 2022-05-18 Capacity Building (Zambézia) Selection MZ-INIR-222388-CS-CQS / Supervision Services for Consultant Component 1-Institutional Under Rehabilitation Works of IDA / D3510 Post Qualification Limited 70,000.00 0.00 2021-04-16 2021-04-14 2021-04-30 2021-05-30 2021-07-04 2021-12-31 Capacity Building Implementation Nampula and Sofala IRRIGA Selection Offices Project MZ-INIR-222378-CS-QCBS / Organization and Training of Component 3-Agriculture Producers and Establishiment Quality And Cost- Pending IDA / D3510 Intensification and Market Post Open - National 200,000.00 0.00 2021-07-02 2021-07-23 2021-09-05 2021-10-03 2021-11-02 2021-12-07 2022-01-11 2023-01-11 of Market Link in the Based Selection Implementation Linkages Irrigations Schemes in Sofala Provínce MZ-INIR-197085-CS-CQS / Component 4- Project Supervision Construction Quality And Cost- Pending IDA / D3510 Management and Monitoring Post Open - National 250,000.00 0.00 2021-08-31 2021-09-21 2021-11-04 2021-12-02 2022-01-01 2022-02-05 2022-03-12 2023-03-12 Works for ACABOCO Irrigation Based Selection Implementation and Evaluation System INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-INIR-109288-CS-INDV / Individual Component 1-Institutional Especialista em Procurement IDA / D3510 Prior Consultant Open 90,000.00 0.00 Canceled 2019-04-05 2019-05-24 2019-06-14 2019-07-19 2020-01-15 Capacity Building (baseado em Maputo) Selection Page 4 MZ-INIR-129523-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Acaboco IDA / D3510 Irrigation Development and Post Direct Selection Direct 45,000.00 50,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-30 2019-12-16 Irrigation System Works Management Completion Project, 316 ha, Buzi District, Sofala Province MZ-INIR-129528-CS-CDS / Surveying damage caused by IDAI Cyclone and preparing Component 2-Smallholder the Executive Mziva and IDA / D3510 Irrigation Development and Post Direct Selection Direct 90,000.00 90,000.00 Signed 2019-09-02 2019-09-19 2019-09-12 2019-09-30 2019-11-16 2019-12-18 2019-12-16 Chiverano Irrigation System Management Works Completion Project, Zambeze Province MZ-INIR-139499-CS-INDV / Component 3-Agriculture Individual Hire a consultant to boost the IDA / D3510 Intensification and Market Post Consultant Limited 30,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 2019/2020 agricultural Linkages Selection company in Manica Province MZ-INIR-139496-CS-INDV / Hire a consultant to boost the Component 3-Agriculture Individual 2019/2020 agricultural IDA / D3510 Intensification and Market Post Consultant Limited 35,000.00 0.00 Canceled 2019-10-14 2019-10-19 2019-11-09 2019-12-14 2020-06-11 company in Sofala and Linkages Selection Zambezia Provinces MZ-INIR-140872-CS-CDS / Service provider for the preparation of PEDSA II and Component 2-Smallholder PNISA II as part of the IDA / D3510 Irrigation Development and Post Direct Selection Direct 300,000.00 0.00 Canceled 2019-12-10 2019-12-20 2020-02-23 2020-08-21 institutional support to DPCI. Management Services performed via UN system. Individual MZ-INIR-150739-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Limited 72,000.00 0.00 Canceled 2019-12-22 2020-02-11 2019-12-27 2020-02-13 2020-01-17 2020-02-21 2020-08-19 Procurement Specialist Capacity Building Selection MZ-INIR-153140-CS-CDS / Component 3-Agriculture Service Provider for Operation IDA / D3510 Intensification and Market Post Direct Selection Direct 180,000.00 199,447.47 Signed 2020-01-26 2020-01-17 2020-02-05 2020-01-22 2020-04-10 2020-03-30 2020-10-07 of da Paz Irrigation in Linkages Zambezia Province Individual MZ-INIR-167041-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Open 72,000.00 52,500.00 Signed 2020-05-18 2020-05-05 2020-07-06 2020-07-22 2020-07-27 2020-08-18 2020-08-31 2020-09-15 2021-02-27 Procurement Specialist Capacity Building Selection MZ-INIR-175070-CS-CDS / Organising and Building Component 3-Agriculture Capacity of Producers and IDA / D3510 Intensification and Market Post Direct Selection Direct 100,000.00 130,950.00 Signed 2020-06-30 2020-06-30 2020-07-10 2020-06-10 2020-09-13 2020-08-05 2021-03-12 Establishing Market Linkages Linkages in Manica Province MZ-INIR-178882-CS-INDV / Individual Component 1-Institutional Monitoring and Evaluation IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-30 2020-09-12 2020-07-01 2021-03-11 Capacity Building Specialist Selection MZ-INIR-178865-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 144,000.00 144,000.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-29 2020-09-12 2020-07-01 2021-03-11 Capacity Building Coordinator Selection MZ-INIR-178878-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-08-05 2020-08-08 2020-08-20 2020-09-12 2020-08-20 2021-03-11 Capacity Building Environment Management Selection MZ-INIR-178874-CS-INDV / Individual Component 1-Institutional Funds Mobilization Unit IDA / D3510 Post Consultant Limited 57,600.00 57,600.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-30 2020-09-12 2020-07-01 2021-03-11 Capacity Building Finance Management Selection Individual MZ-INIR-178872-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 72,000.00 72,000.00 Signed 2020-07-13 2020-06-24 2020-07-18 2020-06-24 2020-08-08 2020-06-29 2020-09-12 2020-07-01 2021-03-11 P4R Unit Coordinator Capacity Building Selection Individual MZ-INIR-109291-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Direct 36,000.00 0.00 Canceled 2019-05-23 2019-06-02 2019-06-23 2019-07-28 2020-01-24 Procurement Assistant Capacity Building Selection MZ-INIR-197120-CS-INDV / Individual Consultant for Component 2-Smallholder Individual project design and IDA / D3510 Irrigation Development and Post Consultant Limited 180,000.00 0.00 Canceled 2020-12-10 2020-12-30 2021-01-19 2021-02-23 2022-03-20 supervision for supply and Management Selection installation of the Chemba irrigation system Individual MZ-INIR-206913-CS-INDV / Component 1-Institutional IDA / D3510 Prior Consultant Direct 36,000.00 36,000.00 Signed 2020-12-07 2021-01-12 2020-12-17 2021-03-15 2021-01-07 2021-04-11 2021-02-11 2021-04-16 2022-02-11 Procurement Assistant Capacity Building Selection Individual MZ-INIR-215703-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Open 50,000.00 0.00 2021-02-10 2021-01-28 2021-03-31 2021-04-21 2021-05-26 2021-11-22 Irrigation Specialist (UGISA) Capacity Building Implementation Selection Individual MZ-INIR-215704-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Limited 100.00 0.00 2021-02-10 2021-01-28 2021-02-15 2021-03-08 2021-04-12 2021-10-09 Civil Engineer Capacity Building Implementation Selection Individual MZ-INIR-215833-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Manica) Capacity Building Selection Individual MZ-INIR-215836-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Sofala) Capacity Building Selection Individual MZ-INIR-215841-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 36,000.00 0.00 Canceled 2021-02-28 2021-01-28 2021-03-05 2021-03-26 2021-04-30 2022-04-30 Irrigation Specialist (Nampula) Capacity Building Selection Page 5 MZ-INIR-215847-CS-INDV / Individual Component 1-Institutional Safeguards Specislist IDA / D3510 Post Consultant Limited 30,000.00 30,000.00 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Capacity Building (Zambézia) Selection MZ-INIR-215851-CS-INDV / Individual Component 1-Institutional Safeguards Specialist IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Capacity Building (Nampula) Selection Individual MZ-INIR-215857-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-24 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Safeguards Specialist (Manica) Capacity Building Selection Individual MZ-INIR-215859-CS-INDV / Component 1-Institutional IDA / D3510 Post Consultant Limited 30,000.00 516.57 Signed 2021-02-28 2021-02-22 2021-03-05 2021-03-25 2021-03-26 2021-04-09 2021-04-30 2021-04-26 2022-04-30 Safeguards Specialist (Sofala) Capacity Building Selection Individual MZ-INIR-238711-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Open 36,000.00 0.00 2021-06-25 2021-07-13 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Irrigation Technician (Sofala) Capacity Building Implementation Selection Individual MZ-INIR-238715-CS-INDV / Component 1-Institutional Under IDA / D3510 Post Consultant Open 36,000.00 0.00 2021-06-25 2021-07-12 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Irrigation Technician (Manica) Capacity Building Implementation Selection MZ-INIR-238717-CS-INDV / Individual Component 1-Institutional Under Irrigation Technician IDA / D3510 Post Consultant Open 36,000.00 0.00 2021-06-25 2021-07-12 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Capacity Building Implementation (Zambézia) Selection MZ-INIR-238720-CS-INDV / Individual Component 1-Institutional Under Irrigation Technician IDA / D3510 Post Consultant Open 36,000.00 0.00 2021-06-25 2021-07-12 2021-08-13 2021-09-03 2021-10-08 2022-04-06 Capacity Building Implementation (Nampula) Selection Individual MZ-INIR-246063-CS-INDV / Component 1-Institutional Pending IDA / D3510 Post Consultant Open 54,000.00 0.00 2021-08-20 2021-10-08 2021-10-29 2021-12-03 2022-06-01 Agriculture Specialist Capacity Building Implementation Selection MZ-INIR-246066-CS-INDV / Individual Component 1-Institutional Pending Communication and Image IDA / D3510 Post Consultant Open 42,000.00 0.00 2021-08-20 2021-10-08 2021-10-29 2021-12-03 2022-06-01 Capacity Building Implementation Specialist Selection Page 6