SFG3445 V4 REV PEOPLE’S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo--------------- RESETTLEMENT ACTION PLAN (Final Draft) VIET NAM - EMERGENCY NATURAL DISASTER RECONSTRUCTION PROJECT (ENDR) Phu Yen Subproject PEOPLE’S COMMITTEE OF PHU YEN PROVINCE PHU YEN PROJECT MANAGEMENT UNIT OF CONSTRUCTION INVESTMENT WORKS FOR AGRICULTURE AND RURAL DEVELOPMENT ----------------o0oo--------------- RESETTLEMENT ACTION PLAN Phu Yen Subproject VIET NAM EMERGENCY NATURAL DISASTER RECONSTRUCTION PROJECT (ENDR) PROJECT MANAGEMENT UNITS CONSULTANCY FIRM AUGUST, 2017 TABLE OF CONTENTS ABBREVIATIONS ............................................................................................................................ v GLOSSARY ...................................................................................................................................... vi 1. PROJECT DESCRIPTION ............................................................................................................ 1 1.1. General Context ................................................................................................................. 1 1.2. Emergency Natural Disaster Reconstruction – Phu Yen Subproject ................................. 1 2. OBJECTIVES AND PRINCIPLES OF RESETTLEMENT ACTION PLAN .............................. 4 2.1. Objectives of Resettlement Action Plan ............................................................................ 4 2.2. Scope of Resettlement Action Plan.................................................................................... 4 3. POTENTIAL IMPACTS ............................................................................................................... 4 3.1. Mitigation Measures Of Land Acquisition And Resettlement ........................................... 4 3.1.1. Objectives ....................................................................................................................... 4 3.1.2. Measures to Minimize Negative Impacts ....................................................................... 5 3.2. Scope of Land Acquisition And Resettlement ................................................................... 5 3.2.1 Overall on Land Acquisition .......................................................................................... 5 3.3. Linked projects................................................................................................................. 17 4. SOCIO-ECONOMIC INFORMATION ...................................................................................... 17 4.1. Overview of Phu Yen province .................................................................................... 17 4.2. Socio-economic Information of Affected Households in the Project Area .................. 19 4.2.1. Survey Approaches and Methodologies .......................................................................... 19 4.2.2. Results of Socio-Economic Survey of Affected Households in the Project Area............ 20 5. LEGAL FRAMEWORK.............................................................................................................. 31 5.1. Legal Framework of GoV: ........................................................................................... 31 5.2. World Bank Policy on Involuntary Resettlement (OP 4.12) ........................................ 32 5.3. Comparison between GoV’s and WB’s Policies .......................................................... 33 6. PRINCIPLES AND POLICIES FOR COMPENSATION, ASSISTANCE AND RESETTLEMENT ....................................................................................................................... 33 6.2.1. Compensation Policy for Permanent Impacts .............................................................. 34 6.2.1.1. Compensation Policy for Agricultural Land ................................................................ 34 6.2.1.2. Compensation for Loss of Land for non-agricultural production and business .......... 35 6.2.1.3. Compensation for Residential Land ............................................................................. 35 6.2.1.4. Compensation for Structures ........................................................................................ 36 6.2.1.5. For Loss of Crops, Trees and Livestock ....................................................................... 37 6.2.1.6. Compensation for other assets ..................................................................................... 37 6.2.1.7. Compensation for Public Works ................................................................................... 37 6.2.2. Compensation Policy for Temporary Impacts During the Construction...................... 38 6.2.3. Any other Impacts Identified During Implementation .................................................. 38 6.2.4. Livelihood Restoration Assistances .............................................................................. 38 7. ELIGIBILITY CRITERIA AND ENTITLEMENTS .................................................................. 51 7.1. Affected people (AP) ....................................................................................................... 51 7.2. Identification of vulnerable groups or households ........................................................... 51 7.3. Eligibility ......................................................................................................................... 51 7.4. New HHs after the cut-off date ........................................................................................ 52 8. LIVELIHOOD RESTORATION PROGRAM ............................................................................ 52 8.1. Income Restoration and Assistance Policies ................................................................ 52 8.2. Income Restoration Measures ...................................................................................... 53 8.3. Cost estimate for Income Restoration Measures .......................................................... 56 9. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ....................................... 57 9.1. Objectives of Public Consultation and Information Disclosure ................................... 57 9.2. The Process of Consultation and Participation ............................................................. 57 9.3. Public Consultation ...................................................................................................... 58 9.3.1. Public Consultation during the Preparation Phase ....................................................... 58 9.3.2. Consultation during the Project Implementation .......................................................... 63 9.4. Information Disclosure ................................................................................................. 65 10. GRIEVANCES AND REDRESS MECHANISM ................................................................ 65 10.1. Responsibility ............................................................................................................... 65 10.2. Grievance redress mechanism ...................................................................................... 65 11. IMPLEMENTATION ARRANGEMENTS.......................................................................... 67 11.1. Institutional Framework ............................................................................................... 67 11.2. Responsibilities of Relevant Agencies ......................................................................... 67 11.2.1. Phu Yen PPC ................................................................................................................ 67 11.2.2. Phu Yen PMU of Agriculture and Rural Development ................................................ 67 11.2.3. District/City/District People’s Committees .................................................................. 68 11.2.4. The Districts Compensation and Resettlement Committee (CRC) .............................. 69 11.2.5. Town/Commune People’s Committees ......................................................................... 69 11.2.6. Project Affected People (AHs)...................................................................................... 69 11.2.7. Independent Monitoring Agency (IMA)........................................................................ 70 12. IMPLEMENTATION PLAN ................................................................................................ 70 12.1. Main Activities ............................................................................................................. 70 12.2. Implementation Schedule ............................................................................................. 70 13. MONITORING AND EVALUATION ................................................................................. 71 13.1. Monitoring .................................................................................................................... 71 13.2. Internal Monitoring ...................................................................................................... 71 13.3. Independent Monitoring ............................................................................................... 72 14. COST ESTIMATION ........................................................................................................... 74 14.1. Funding sources ............................................................................................................ 74 14.2. Replacement Cost Survey............................................................................................. 74 Page ii 14.3. Cost Estimate................................................................................................................ 74 ANNEXES ................................................................................................................................... 76 Annex 1: Replacement Cost Survey ................................................................................................. 76 Annex 2: Project information leaflet ................................................................................................. 76 Annex 3: Some Minutes of Public Consultation Meetings At the Project Area ............................... 76 Annex 4: Socio-economic Survey Questionnaire for Affected Households in the Project Area ...... 76 Annex 5: Some Pictures of Consultation Meetings .......................................................................... 76 Annex 6: List of Affected Households with Different Types Of Impact .......................................... 76 Annex 7: TOR for Independent Monitoring ..................................................................................... 76 Page iii LIST OF TABLES Table 1: Proposed Investment Work Items in Phu Yen Province ........................................................... 2 Table 2: Number of Affected Households By The Subproject’s Items .................................................. 6 Table 3: Summary of Land Acquisition Impacts in Phu Yen ................................................................. 6 Table 4: Summary of Land Acquisition Impacts of the Subproject........................................................ 7 Table 5: Summary of Impacts on Residential Land ................................................................................ 9 Table 6: Summary of Impacts On Agricultural Land ........................................................................... 10 Table 7: Summary of Affected Volume of Trees and Crops ................................................................ 13 Table 8: Summary of Impacts on Houses and Structures ..................................................................... 16 Table 9: Area, population and population density of Phu Yen province in 2015 ................................. 18 Table 10: Socio-economic information of the communes/wards for implementation of Subproject’s items ...................................................................................................................................................... 19 Table 11: Socio-Economic Survey Scope in the Project area ............................................................... 21 Table 12: Education level of household heads...................................................................................... 22 Table 13: Occupation of household heads divided into each item ........................................................ 23 Table 14: Average Income/Person/Month ............................................................................................ 25 Table 15: Means of living of households .............................................................................................. 27 Table 16: Information on vulnerable households in the project area ................................................... 27 Table 17: Severely affected vulnerable households in the project area ................................................ 29 Table 18: Entitlement Matrix ................................................................................................................ 41 Table 19: Income Restoration Program for AHs .................................................................................. 55 Table 20: Cost estimate for Income Restoration Program for AHs ...................................................... 56 Table 21: Public Consultation on Land Acquisition and Resettlement ................................................ 58 Table 22: Results of public consultation meetings with prioritized work items under the Subproject . 60 Table 23: Implementation Plan ............................................................................................................. 71 Table 24: Cost estimate for each item affected by the Subproject ........................................................ 75 Page iv CURRENCY EQUIPVALENT (As of 05/05/2017) Unit – Dong (VND) $1.00 = VND 22,700 ABBREVIATIONS AHs Affected Households PMU Project Management Unit GoV Government of Vietnam DMS Detailed measurement survey DRC District Compensation and Resettlement Committee RAP Resettlement Action Plan FS Feasibility Study WB Work Bank RAPF Resettlement Policy Resettlement TOR Term of Reference PC People’s Committee Page v GLOSSARY Affected persons (APs) Individuals, organizations or businesses that are directly affected socially and economically by WB-funded projects caused by the involuntary taking of land and other assets that results in (i) relocation or loss of shelter; (ii) loss of assets or access to assets; or (iii) loss of income sources or means of livelihood, whether or not the affected persons must move to another location. In addition, affected person is one for whom involuntary restriction of access to legally designated parks and protected areas that result in adverse impacts on livelihoods also. Cut-off-date Is the date when the PPC issues the Notification of Land acquisition for the relevant project (Article 67.1 of Land Law 2013) before implementation of detailed measurement survey. Affected persons and local communities will be informed of the cut-off date for each project’s component, and that anyone moving into the project component areas after that date will not be entitled to compensation and assistance under the Project. Eligibility The criteria to receive benefits under the resettlement program. Entitlements Include compensation and assistance for APs based on the type and extent of damage. Income (livelihood) A set of activities to be provided to the affected people who lost restoration income sources or means of livelihoods to restore their income and living standard, as equal to or better than pre-project level. Inventory of Losses (IOL) Is process of accounting for physical assets and income affected by project. Livelihood A set of economic activities, involving self-employment, and or wage employment by using one’s endowments (both human and material) to generate adequate resources for meeting the requirements of the self and household on a sustainable basis with dignity. Project impact Any consequence immediately related to the taking of a parcel of land or to restrictions in the use of legally designated parks or protected areas. People directly affected by land acquisition may lose their home, farmland, property, business, or other means of livelihood. In other words, they lose their ownership, occupancy, or use rights, because of land acquisition or restriction of access. Replacement cost The term used to determine the amount sufficient to replace lost assets and cover transaction costs. For losses that cannot easily be valued or compensated for in monetary terms (e.g. access to public services, customers, and supplies; or to fishing, grazing, or forest areas), attempts are made to establish access to equivalent and culturally acceptable resources and earning opportunities. Resettlement In accordance with the World Bank’s Operational Policy on Involuntary Resettlement (OP 4.12), it covers the involuntary taking of land that results in (i) relocation or loss of shelter, (ii) loss of assets or access to assets; or (iii) loss of income sources or means of livelihood, whether or not the affected persons must move to another Page vi location. Severely Displaced Person Means DPs who will (i) lose 20% (10% for vulnerable households) or more of their total productive land and assets and/or more of their total income sources due to the Project, (ii) have to relocate. Stakeholders Any and all individuals, groups, organizations, and institutions interested in and potentially affected by a project or having the ability to influence a project. Vulnerable groups Groups of people who might suffer disproportionately or face the risk of being further marginalized by the effects of resettlement and specifically include: (i) women headed household (single, widow, disabled husband) with dependents, (ii) disabled (loss of working ability), the elderly alone, (iii) poor people according to the criteria issued by the MOLISA, (iv) the landless, and (v) ethnic minority people. Page vii EXECUTIVE SUMMARY Description of the Project 1. The Government of Vietnam receives a loan from the World Bank for Vietnam Emergency Natural Disaster Reconstruction Project. The investment project will be implemented in five provinces of Phu Yen, Quang Ngai, Binh Dinh, Ha Tinh and Ninh Thuan. The Project Development Objective (PDO) is to reconstruct and rehabilitate infrastructure assets in disaster-affected project provinces (85 percent) and strengthen the capacity of the Government to effectively respond to future disaster events (15 percent). The PDO will be achieved by rebuilding key infrastructure assets based on a ‘build back better’ approach emphasizing all stages of infrastructure life cycle including design, construction, and maintenance and strengthening institutional capacities for climate and DRM. The Project consists of four main components: - Component 1: Resilient Reconstruction of Flood-Damaged Infrastructure at the Provincial level - Component 2: Disaster Recovery Capacity Enhancement - Component 3: Project Management Objectives of Resettlement Action Plans (RAPs) 2. With regard to land acquisition, a RAP is prepared for all work items under Phu Yen province. It is prepared based on inventory of losses (IOL) in the project area, replacement cost survey, review and check entitlements set-out in approved RPF in the context of actual impacts by the Phu Yen subproject. This Resettlement Action Plan contains scope of impacts resulting from land acquisition and resettlement, policy principles on entitlements and eligibility for compensation, implementation arrangements; monitoring and evaluation, community’s participation and consultation, grievances and grievance redress mechanism, cost estimate... Scope and Impacts of Land Acquisition 3. The implementation of works items in Phu Yen province will affect 423 households, of which 403 households are directly affected by taking of land and 20 households are indirectly or economically affected by cultivation on land area managed by commune/ward PCs. In addition, the project implementation also affects 12 towns/communes. 4. It is estimated that 375.582 m² of land owned by 403 households will be acquired. Of which, residential land area: 7,726 m²; agricultural land area: 124,854 m²; Public land area: 245,833 m² managed by commune/ward PCs include specialized land, river, stream land and transport land. 5. Out of 423 households affected with land and structures thereon, none of households is affected with houses and have to relocate, but 118 households are severely affected by agricultural land acquisition, of which 111 households lose 20% or more of total agricultural land area and 7 vulnerable households lose from 10% or more of total agricultural land area). Besides, 34 households fall into vulnerable group (including, 17 poor households; 4 policy households; 05 elderly households and 08 households with woman-headed with independents). Mitigation Measures 6. In the process of project designing, Phu Yen Project Management Unit of Construction Investment Works for Agriculture and Rural Development has cooperated closely with the technical design and resettlement consultant to avoid or minimize scope of land acquisition. Measures to minimize the negative impacts of the project were carried out by studying the project design plans in order to not only promote the project investment efficiency but also minimize magnitude of the land acquisition. 7. Simultaneously, the plans to minimize the temporary impacts in the construction phase have been studied and proposed, in order to avoid and/ or minimize these impacts during the implementation of project. Entitlements Page viii 8. The entitlements for affected households of Phu Yen sub-project will be complied with WB’s policy on involuntary resettlement (OP/BP 4.12) and the laws, regulations of the GoV and the Resettlement Policy Framework (RPF) which has been agreed between the Government of Vietnam and the World Bank. 9. The basic principles applied for the preparation of this Resettlement Action Plan is that all AHs of the project (APs) will be compensated at replacement cost and assisted with restoration measures to help them improve or at least maintain the living conditions and the capacity to make income before the project. Livelihood Restoration Program 10. Livelihood restoration program is an important activity of the compensation, assistance and Resettlement Action Plan. In this project, a vocational training and job introduction program will be provided by the Job Introduction Center under the Department of Labor - Invalids and Social Affairs of Phu Yen Province, contributing to restore the AH’s livelihoods and ensure their living standards at least equal to or better than the pre-project level. In addition, if at the AH’s demands, they will also get a loan from the Social Policy Bank of Phu Yen Province for household economy development with preferential policies and specific instructions and/ or free costs of procedures and related papers. Implementation Arrangements 11. The compensation, assistance and resettlement of the project will be subject to the management and supervision of Phu Yen PMU of Construction Investment Works for Agriculture and Rural Development and implemented by the District/City Land Fund Development Center (LFDC)/ the District/City Compensation and Resettlement Committee (CRC). During the implementation process, there should have the close coordination between the members of the Compensation and Resettlement Councils. In the implementation process, these organizations should have close coordination with the relevant authorities, the authorities at wards/ communes level and the communities in the project area to ensure that the compensation, assistance and resettlement activities are performed openly, transparently, at time-bound and in compliance with the approved RAP. Consultation and Participation 12. The RAP is prepared with the close coordination of the local authorities, representative of local community and affected people. Local authorities at the wards, communes and representatives of the affected households were involved in the consultations through the various forms and channels, including meetings and public consultations, questionnaire-based survey for almost of households in the project area. Information collected during the consultation will serve as a basis for preparing resettlement policy of the project, including compensation plan and income restoration program. Monitoring and Evaluation 13. This RAP will be implemented under the supervision of Phu Yen PMU of Construction Investment Works for Agriculture and Rural Development. At the same time, Phu Yen PMU will also recruit an independent monitoring agency/individual for monitoring the implementation of the RAP. 14. Upon completing the project, the independent monitoring agency (IMA) will also evaluate to determine whether or not the objectives of the resettlement policy have achieved. In case it is found that these objectives are not achieved; Phu Yen PMU of Construction Investment Works for Agriculture and Rural Development will propose the follow-up measures as the basis for the World Bank to continue the monitoring until WB finds it suitable. Grievances and Redress Mechanism 15. The Project will establish a Grievance Redress Board to support in resolving and monitoring the processes related to grievances, complaints and inquiries as a result of the project intervention. The mechanism established by the project aims to allow affected persons (APs) to lodge their complaints and receive the resolutions under the project’s resettlement policy framework ( RPF) and the project’s operational guidelines. The Phu Yen PMU’s officers in charge of resettlement will also work directly with AHs as an official first step of resolving complaints prior to coming up with the Grievance Redress Board. The AHs will be fully informed of the information of grievance redress mechanism via the appropriate measures. Page ix Cost Estimate 16. Cost estimate for implementing this RAP is VND 17,679,405,564 (equivalent to US$ 778,828 at exchange rate: VND 22,700=US$1). This budget includes costs of compensation/ assistance for land, structures, assets affected by project, the income restoration program, transitional assistance, cost of monitoring and evaluation, cost of implementation management and contingency. Estimated cost for the site clearance will be updated according to the detailed design and the time of land acquisition based on the results of the independent valuation agency). 17. All costs for implementation of compensation, assistance and resettlement, replacement cost survey, resettlement training (if any), and independent monitoring will come from counterpart fund. Page x 1. PROJECT DESCRIPTION 1.1. General Context 1. The Government of Vietnam received a loan from the World Bank for Vietnam Emergency Natural Disaster Reconstruction Project including Phu Yen, Quang Ngai, Binh Dinh, Ha Tinh and Ninh Thuan provinces (hereafter called the ENDR). The project has been implemented to rebuild priority infrastructure works in some flood-damaged provinces in 2016 and to strengthen capacity to effectively respond to future disasters in five provinces. The project will benefit affected persons by natural disasters, including the poor, women and ethnic minorities, by improving access to essential infrastructure and services and increasing adaptation capacity as well as supporting for agricultural production through improvement of irrigation works. Specific investment items by the project have been currently identified with the objectives without causing serious negative social impacts. 2. The project will be completed from 2017 to 2020 with total fund of US $118 million, of which IDA loan is US $ 118 million, including 03 components: 1) Resilient Reconstruction of Flood Damaged Infrastructure; 2) Disaster Recovery Capacity Enhancement; 3) Project Management. 3. The Project Development Objective is to reconstruct infrastructure assets in the project areas. The PDO will be achieved by rebuilding key infrastructure assets based on a “build back betterâ€? approach emphasizing all stages of infrastructure lifecycle including design, construction and maintenance and strengthening institutional capacities for climate and disaster risk management 4. Specific objectives of the Project include: - Repairing, improving and upgrading of production infrastructure (including irrigation works, dykes, river embankments, sea embankments, irrigation canals, domestic water supply, etc.) in order to restore production, protect lives and property of the local people, reduce risks caused by natural disasters. - Overcoming damages on traffic infrastructure to facilitate travel, business and production development of the people, facilitate transportation of rescue forces, materials and equipment for emergency rescue for local people in flooded and drought areas in case natural resources and floods in the region. - Support for capacity strengthening of the Client in the project implementation. 1.2. Emergency Natural Disaster Reconstruction – Phu Yen Subproject 5. The Emergency Natural Disaster Reconstruction Project – Phu Yen Subproject will be implemented in Phu Yen province, at locations affected by disaster, in which, the project focuses on rehabilitation of essential infrastructure works to ensure life, restore production and ensure smooth transportation. 6. It is estimated that about 651,000 people living the project districts of Phu Yen province will benefit directly from the reconstruction and rehabilitation of works of the Subproject. Besides, agricultural production organizations in the region will also benefited from the Subproject thanks to improved irrigation works; saving time and cost of travelling in the project area thanks to improved traffic works. 7. According to preliminary estimation, total estimated investment capital of the Subproject is US $ 17,916 million. Of which: - Preferential credit loans (IDA) from the World Bank: US $ 16 million - Counterpart fund of Government of Vietnam: US $ 1,916 million 8. Vietnam Emergency Natural Disaster Reconstruction Project – Phu Yen Subproject consists of 03 components as follow: ï?¶ Component 1: Resilient Reconstruction of Flood Damaged Infrastructures and Disaster Prevention in the future a. Subcomponent 1.1: Irrigation (estimated cost of US $ 9.08 million) Page 1 This Subcomponent will fund rehabilitation and reconstruction of 02 km of dyke, river embankment, sea dyke including (i) Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune, L=2km, (ii) Ky Lo river embankment, section across Ngan Son bridge, L=2km. b. Subcomponent 1.2: Transport (estimated cost of US $ 4.89 million) This Subcomponent will finance for (i) repairing, rehabilitation of the provincial roads 643,650,642, with total length of 13km; and (ii) repairing, rehabilitation of the maintenance and operation road of Xuan Binh reservoir with length of 12km, pavement is cement concrete (Details of works under Subcomponents are presented in Table below). ï?¶ Component 2: Capacity Building 9. In order to well manage construction works and improve the effectiveness of disaster prevention activities, the Project will finance a budget from the counterpart fund of the province to carry out some activities including training, capacity building, community communication and initial costs for O & M activities. These activities will support the sustainable operation and management of works in the future. 10. In addition, the World Bank also commits to find a number of non-refundable aids to carry out a number of research, capacity building and training activities to promote the effectiveness of funded works of the Project. The details of this component will be clarified during the preparation phase of feasibility study report. ï?¶ Component 3: Project Management 11. The objective of this component is to provide support for effective project implementation, including project auditing, monitoring, and mid-term and end-term evaluation, supply of equipment and technical assistance to the PMU during the project implementation process and individual consultancy services and PMU operating costs. This component will also provide reports and project management support to other components. It will provide institutional support and capacity building for project management, coordination, review and evaluation of technical, environmental and social safeguards aspects and project evaluation monitoring. This component will provide workshops to enhance the awareness of management officials and community-related to natural disasters. On the other hand, this component will also provide budget support for key project officials, including project managers, construction engineers and specialists in the field of natural disaster risk management, compliance monitoring, finance, bidding and other related fields of the Project. These key staff will be hired under Time and Scheduled Contracts of the Project. Table 1: Proposed Investment Work Items in Phu Yen Province Communes No. Package Works under the works A Component 1: Reconstruction of Damaged Works and Flood Prevention in the future I Irrigation Subcomponent PY-01-XL New construction of embankment by titling roof embankment, L=2.1km, Ba river embankment roof is reinforced by concrete, embankment foot is concreted Hoa Thang embankment, pier, embankment top is reinforced by concrete. commune section across 1 Phong Nien hamlet, Hoa Thang commune Repairing and rehabilitation of irrigation weir system An Hiep commune 2 PY-02-XL Repairing, Repairing and rehabilitation of An Hiep – An Linh road An Hiep, rehabilitation An Linh Page 2 Communes No. Package Works under the works of irrigation communes weir, Suoi Da bank in An Hiep An Hiep stream embankment An Hiep commune commune, repairing and rehabilitation Ky Lo river embankment, section across Ngan Son bridge, Tuy An district An Dinh of An Hiep- commune, An Linh road, Chi Thanh Tuy An district town and Ky Lo river embankment, section across Ngan Son bridge II Transport Repairing, rehabilitation of the provincial road.642 section from Km1 + Xuan Son 607.00 to Km13 + 789.75 Bac, Xuan Tho 2 PY-03-XL communes, Repairing, La Hai rehabilitation town 3 of the provincial Repairing, rehabilitation of the provincial road.650 with length of L = An Xuan roads.643, 650, 99.61m commune 642 Repairing, rehabilitation of the provincial road. 643 section from Km3 + An My 223.62 to Km3 + 302.60 commune PY-04-XL Repairing of the operation and management road of Xuan Binh reservoir Xuan Binh, Repairing of with total length of 9,783.95m Xuan Loc the operation communes, 4 and Song Cau management town road of Xuan Binh reservoir B Component 2: Capacity Building C Component 3: Project Management Page 3 2. OBJECTIVES AND PRINCIPLES OF RESETTLEMENT ACTION PLAN 2.1. Objectives of Resettlement Action Plan 12. Pursuant to Article 51 of Decree No.16/2016/ND-CP dated 16 March 2016 of the Government on management and use of Official Development Assistance (ODA) and concessional loans from donors stating one basic principle in compensation, assistance and resettlement: “Compensation, assistance and resettlement in implementing the program and project will be implemented in accordance with the applicable regulations and international treaty on ODA and preferential loan, of which Vietnam is a member. In case of any differences between GoV’s regulations and provisions of the international treaty, the provisions of the international treaty will prevailâ€?. The Land Law No. 45/2013/QH13, Clause 2, Article 87 states that: “For projects using loans from international or foreign organizations for which Vietnam has committed to a policy framework for compensation, assistance and resettlement, the policy framework will prevailâ€?. 13. Resettlement Policy Framework (RPF) of the project was prepared based on the Resettlement Action Plan approved by the Prime Minister and cleared by the WB before the time of Agreement negotiation to ensure harmony between the World Bank’s OP/BP 4.12 and the Vietnam's laws and regulations on compensation, assistance and resettlement. 14. Basic objectives: (i) Involuntary resettlement should be avoided where feasible or minimized by all viable alternative technical designs; (ii) Wherever involuntary resettlement is unavoidable, resettlement activities should be conceived of and executed as sustainable development programs, providing sufficient investment sources to enable affected persons to share project’s benefits; Directly or indirectly affected persons must be consulted and participated in the process of planning and implementing resettlement programs; (iii) Affected Persons should be assisted in efforts to improve their livelihoods and living standards or at least to restore them, in real terms, to pre-project levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. 15. All projects affected persons (PAPs) who have assets within or reside within the project area before the cut-off date are entitled to compensation for their losses. Those who have lost their income and/or livelihoods will be eligible for livelihood rehabilitation assistance based on the criteria of eligibility defined by the project in consultation with the PAPs. If, by the end of the project, livelihoods have been shown not to be restored to pre-project levels, additional measures will be provided. 16. This RAP will give guidelines for implementing activities related to compensation and land acquisition during the implementation of items that involved in land acquisition, compensation and resettlement regardless of financial sources. 2.2. Scope of Resettlement Action Plan 17. The Emergency Natural Disaster Reconstruction Project – Phu Yen Subproject includes 04 construction contracts covering 09 work items. This Resettlement Action Plan is prepared for all 04 construction contracts with 09 work items in Phu Yen. 3. POTENTIAL IMPACTS 3.1. Mitigation Measures Of Land Acquisition And Resettlement 3.1.1. Objectives 18. The first principle in the WB's OP4.12 requirement is to avoid or minimize impacts of land acquisition and resettlement. Wherever involuntary resettlement is unavoidable, adequate compensation for affected households should be applied. Page 4 3.1.2. Measures to Minimize Negative Impacts 19. During the project design process, the Project Management Unit of Phu Yen Provincial Agriculture and Rural Development (PMU) has worked closely with the project preparation consultant and resettlement specialists to avoid or minimize magnitude of land acquisition and to ensure that the scope of resettlement impact is mitigated in all work items or packages in Phu Yen province. 20. In detail, to mitigate the project impacts of land acquisition and resettlement, to both physically or directly affected households and economically or indirectly affected households, mitigation measures have been implemented as follows: (i) The Phu Yen PMU has coordinated with the technical design consulting firms of the project to carry out survey and study on the position and scope of each works item in order to propose the best design options with the aim of minimizing level of land acquisition impacts on households. Technical options for reducing design scales, width of embankments, route alignments or intersections have been analyzed and selected. Accordingly, works items on roads and bridges will be mainly re-built or rehabilitated based on the existing ones. For embankment routes, the best design options have been selected to minimize the impacts that acquired land will be mainly public uses, i.e transport, irrigation and agricultural land. (ii) During the process of project preparation and the RAP preparation as well, many public consultations have been organized by the Phu Yen PMU and the resettlement consultant firm in the project area to publicize (i) information on the project and (ii) expected impacts, as well as land acquisition and compensation and resettlement measures, etc. This will enable households to get information about and be aware of the location and benefits of the project as well as expected impacts. From there, it is possible to minimize impacts. In the consultations, many issues were raised and discussed: the project assistance and compensation policies, income restoration programs for severely affected households in order to provide corrective measures. All local people are very supportive of the project and expect the project to be implemented soon. (iii) To minimize the impacts on households living on both sides of the road during the construction/rehabilitation phase, resettlement consultants consulted with the local authorities and the households living along the roads to propose appropriate mitigation measures to each locality. Accordingly, a number of mitigation measures during the construction process will be applied, e.g carrying out the rolling construction, finishing the construction of each section. (iv) As agreed during consultation, construction time will be publicly announced according to regulations to local authorities and affected households so that AHs can arrange suitable farming plans. (v) The resettlement consultant firm has also organized the meetings with the design consulting units of the project to discuss about location of the local works, public works and the selection of design solutions in order to avoid / minimize negative impacts on local people, etc. At the same time, develop criteria together to minimize impacts during the construction process such as establishment of occupational safety plans (in case construction is close to residential areas), arrangement of suitable materials and tools (signboards, partitions with residential areas, etc.), time, and construction schedule and so on. To minimize temporary impacts during the construction process as well as when the project puts into operation. 21. Despite application of many mitigation measures as described above, the impacts of land acquisition and site clearance on the project's construction works is inevitable. The scope and impact magnitude of the project in Phu Yen province are shown in section 3.2 below: 3.2. Scope of Land Acquisition And Resettlement 3.2.1 Overall on Land Acquisition 22. A survey, including inventory of losses, observations, consulations … was carried out for the people affected by taking of land/ structure in Phu Yen ENDR project with the purpose of determining the loss of land and fixed assets such as works, trees, livelihoods and access to community resources due to land acquisition for the project implementation. Page 5 23. Result of the survey show that the implementation of the subproject works will affect 423 households. Number of affected households are summarized in the Table as follow: Table 2: Number of Affected Households By The Subproject’s Items No. Work Items Location Total Ba river embankment, section across Phong Nien hamlet, Hoa 1 Hoa Thang commune 38 Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, repairing, rehabilitation of 2 239 An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge a, Repairing, rehabilitation of irrigation weir system An Hiep commune 24 An Hiep commune 4 b, An Hiep stream embankment – An Linh An Linh commune 9 c, An Hiep stream embankment An Hiep commune 91 Chi Thanh town 28 Ky Lo river embankment, section across Ngan Son bridge, Tuy d, An district An Dinh commune 83 3 Repairing, rehabilitation of the provincial roads.643, 650, 642 102 Xuan Tho 2 commune 75 a, Repairing, rehabilitation of the provincial road.642 La Hai town 0 Xuan Son Bac commune 8 b, Repairing, rehabilitation of the provincial road.650 An Xuan commune 10 c, Repairing, rehabilitation of the provincial road.643 An My commune 9 Repairing of the operation and management road of Xuan 4 44 Binh reservoir Xuan Binh commune 25 Repairing of the operation and management road of Xuan Binh reservoir Xuan Loc commune 19 Total 423 Source: IOL Survey, March-April/2017 24. Many AHs will lose more than one type of land and assets/ structures such as residential land, annual and perennial agricultural land, structures, trees and crops. Out of total 423 AHs affected, none of households is totally affected with houses and require physical relocation. The survey results indicated that none of EM household was found that EMDP is not triggered under Phu Yen project. Number of affected households and organizations are summarized in detailed in the Table as follow: Table 3: Summary of Land Acquisition Impacts in Phu Yen Page 6 Affected Contents Unit volume Total number of affected households HHs 423 Household members Person 2024 1. Number of households affected by land acquisition HHs 403 + Households are affected with partially residential land HHs 22 + Households are affected with partially residential and agricultural land HHs 18 + Households are affected with agricultural land HHs 363 2. Number of affected organizations (Communes People’s Committee) 12 3. Number of households are affected with house HHs 2 5. Number of households have to relocate HHs 0 5. Number of households are affected with trees and scops HHs 423 + No. of directly AHs by land acquisition HHs 403 + No. of indirectly AHs by land acquisition (Cultivation on land area HHs 20 managed by CP) 6. Number of vulnerable households HHs 34 + Poor households HHs 17 + Policy households HHs 4 + Elderly households HHs 5 + Households with woman-headed with independents HHs 8 7.Households are affected 20% or more of total agricultural land area HHs 111+7 (Vulnerable HHs affected 10% or more of total agricultural land area) Source: IOL Survey, March -April 2017 25. The project will affect 375,852 m² of land area owned by 403 households, and managed by 12 commune/town PCs. Of which: - Affected partially residential land area: 7,726 m2 - Affected agricultural land area: 124,854 m2 - Affected public land area 245,833 m2 managed by 12 commune/town PCs, including specialized land, stream, river land, transport land and so on. Table 4: Summary of Land Acquisition Impacts of the Subproject Affected Land Area (m2) Total affected No. Work Items Location Residenti Agri.land Public land area al land (m2) (m2) land (m2) (m2) Page 7 I Irrigation Subcomponent Ba river embankment, section across Phong Hoa Thang 1 Nien hamlet, Hoa Thang commune commune 112 3,296 49,900 53,308 Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, repairing, 2 rehabilitation of An Hiep – An Linh 5,054 88,588 139,750 233,391 road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation of irrigation weir An Hiep a, system commune - 1,341 6,468 7,809 An Hiep commune - 2,432 2,669 5,101 b, An Hiep stream embankment – An Linh An Linh commune - 2,475 2,774 5,249 An Hiep c, An Hiep stream embankment commune 4,597 53,067 112,433 170,097 Chi Thanh town 457 3,853 660 4,970 Ky Lo river embankment, section across d, Ngan Son bridge, Tuy An district An Dinh 25,420 14,746 40,165 commune - Repairing, rehabilitation of the 3 provincial roads.643, 650, 642 2,560 26,629 47,809 74,438 Xuan Tho 2 commune 2,560 21,488 37,107 58,595 Repairing, rehabilitation of the provincial a, La Hai town road.642 - - 1,650 1,650 Xuan Son Bac commune 2,511 5,747 8,258 Repairing, rehabilitation of the provincial An Xuan b, 1,030 road.650 commune - 1,700 2,730 Repairing, rehabilitation of the provincial An My c, 1,600 road.643 commune - 1,605 3,205 Repairing of the operation and 4 management road of Xuan Binh - 6,341 8,374 14,715 reservoir Xuan Binh commune - 3,440 2,304 5,744 Repairing of the operation and management road of Xuan Binh reservoir Xuan Loc commune - 2,901 6,070 8,971 Total 7,726 124,854 245,833 375,852 Source: IOL Survey, April 2017 Page 8 26. As survey result, all affected households as above mentioned are entitled to receive compensation, assistance and resettlement (if any) for their land and other affected assets in compliance with approved RPF, details are shown in Section 6 of the report. 3.2.2 Land Acquisition and Other Assets 3.2.2.1 Impacts on Residential Land 27. It is estimated that, only 03 works items might affect residential land currently used by 40 households, with total area of 7,726 m2. All households are partially affected with residential land and structures thereon. Thus, none of households have to be relocated in Phu Yen province. 28. Magnitude of impacts on residential land for each item is presented as follow: Table 5: Summary of Impacts on Residential Land No. of AHs Total area of No. Items Location affected land Partially Totally (m2) I Irrigation Subcomponent Ba river embankment, section 1 across Phong Nien hamlet, Hoa Hoa Thang commune 1 - 112 Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, repairing, 2 19 - 5,054 rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation of a, An Hiep commune - - - irrigation weir system An Hiep commune - - - An Hiep stream embankment – b, An Linh An Linh commune - - - c, An Hiep stream embankment An Hiep commune 17 - 4,597 Ky Lo river embankment, Chi Thanh town 2 - 457 d, section across Ngan Son bridge, Tuy An district An Dinh commune - - Repairing, rehabilitation of the 3 20 - 2,560 provincial roads.643, 650, 642 Xuan Tho 2 commune 20 - 2,560 Repairing, rehabilitation of the La Hai town - - - a, provincial road 642 Xuan Son Bac commune - - - Repairing, rehabilitation of the b, An Xuan commune - - - provincial road 650 Repairing, rehabilitation of the c, An My commune - - - provincial road 643 Page 9 No. of AHs Total area of No. Items Location affected land Partially Totally (m2) Total 40 - 7,726 Source: IOL Survey, April 2017 3.2.2.2 Impacts on Agricultural Land 29. Agricultural land owned by 381 households will be affected with land area of 124,854 m2. The affected agricultural land area is mainly land for rice (paddy); perennial and annual trees. Out of total 381 households affected by loss of agricultural land, 118 households are severely affected (of which, 111 households losing more than 20% of total land holding and 7 vulnerable households losing from 10% their total land holding). Impacts level on agricultural land under each item of the project is presented in Table below: Table 6: Summary of Impacts On Agricultural Land No. of AHs Total area Less than 20% or of affected No. Items Location 20% or more or agricultural 10% for 10% for land (m2) vulnerable vulnerable households households I Irrigation Subcomponent Ba river embankment, section across Phong Nien Hoa Thang 1 35 - 3,296 hamlet, Hoa Thang commune commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep 2 commune, repairing, rehabilitation of An Hiep – 120 100 88,588 An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge An Hiep a, Repairing, rehabilitation of irrigation weir system 21 - 1,341 commune An Hiep - 4 2,432 commune b, An Hiep stream embankment – An Linh An Linh 7 2 2,475 commune An Hiep c, An Hiep stream embankment 14 67 53,067 commune Chi Thanh 18 4 3,853 town Ky Lo river embankment, section across Ngan Son d, bridge, Tuy An district An Dinh 60 23 25,420 commune Repairing, rehabilitation of the provincial 3 73 14 26,629 roads.643, 650, 642 Xuan Tho 2 53 11 21,488 commune a, Repairing, rehabilitation of the provincial road.642 La Hai town - - - Page 10 No. of AHs Total area Less than 20% or of affected No. Items Location 20% or more or agricultural 10% for 10% for land (m2) vulnerable vulnerable households households Xuan Son Bac 5 3 2,511 commune Repairing, rehabilitation of the provincial road.650 An Xuan b, 6 - 1,030 commune Repairing, rehabilitation of the provincial road.643 An My c, 9 - 1,600 commune Repairing of the operation and management road 4 35 4 6,341 of Xuan Binh reservoir Xuan Binh 18 3 3,440 commune Repairing of the operation and management road of a, Xuan Binh reservoir Xuan Loc 17 1 2,901 commune Total 263 118 124,854 Source: IOL Survey, April 2017 Page 11 3.2.2.3 Impacts on Trees and Crops 30. According to the preliminary inventory results, the project will affect trees, crops owned by 423 households. Of which, 403 households are directly affected with trees and crops by physical land acquisition and 20 households are indirectly affected with trees and crops by cultivation on land area managed by communes/wards CP (non-land assets). Total 2,133 fruit trees (longan, grapefruit, banana, etc.); 2,751 timber trees and about 4,740 bamboo trees are affected, in addition, about 27,091 m2 of rice; 741 m2 of other vegetables crops are affected by the project. Table bellowed summarizes volume of trees and crops affected by the project: Page 12 Table 7: Summary of Affected Volume of Trees and Crops No. of AHs Impacts on Trees Impacts on Crops No. of No. Items Location indirectly AHs No. of directly Fruit Other by land Timber Bamboo Vegetables, AHs by land trees crops acquisition trees (trees) Crops (m2) acquisition (trees) (m2) (managed by CP) I Irrigation Ba river embankment, section Hoa 1 across Phong Thang 36 2 348 238 3067 2,228 - Nien hamlet, commune Hoa Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, repairing, 2 rehabilitation 230 9 986 880 850 24,538 - of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation An Hiep a, 21 3 129 401 680 of irrigation commune weir system An Hiep An Hiep 4 0 47 18 340 commune stream b, embankment – An Linh An Linh 9 0 80 32 300 commune An Hiep An Hiep c, stream 89 2 130 367 130 1,302 commune embankment Ky Lo river Chi embankment, Thanh 24 4 480 45 80 section town d, across Ngan Son bridge, Tuy An An Dinh 83 0 120 17 22,556 district commune 3 Repairing, 98 4 751 1,330 823 325 - rehabilitation Page 13 No. of AHs Impacts on Trees Impacts on Crops No. of No. Items Location indirectly AHs No. of directly Fruit Other by land Timber Bamboo Vegetables, AHs by land trees crops acquisition trees (trees) Crops (m2) acquisition (trees) (m2) (managed by CP) of the provincial roads.643, 650, 642 Xuan Tho 2 75 - 560 678 487 325 commune Repairing, rehabilitation La Hai a, of the - - town provincial road.642 Xuan Son Bac 8 - 148 64 180 commune Repairing, rehabilitation An Xuan b, of the 6 4 17 308 156 commune provincial road.650 Repairing, rehabilitation An My c, of the 9 0 26 280 commune provincial road.643 Repairing of the operation and 4 management 39 5 - 203 - - 741 road of Xuan Binh reservoir Repairing of Xuan the operation Binh 21 4 134 420 and commune management road of Xuan Xuan Binh Loc 18 1 69 321 reservoir commune Total 403 20 2,133 2,751 4,740 27,091 741 Source: IOL Survey, March /2017 Page 14 3.2.2.4 Impacts on Houses and Structure Works 31. Thanks to technical design alternatives to avoid and minimize adverse impacts by land acquisition on households, impact on residential land acquisition and structures is marginal. 32. According to the preliminary inventory results, out of total 403 affected households, 29 households are affected with structures, of which 02 households are affected with houses, 27 other households are affected with auxilariy structures such as: yard, fencing wall, shed and so on. Table below summarizes type of affected houses and structures under the project. : Page 15 Table 8: Summary of Impacts on Houses and Structures Affecte No. of AHs No. Items Location on structures Fen Houses (m2) I Irrigation Subcomponent Ba river embankment, section across Phong Nien 1 Hoa Thang commune 1 - hamlet, Hoa Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, 2 repairing, rehabilitation of An Hiep – An Linh 20 62 road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge a, Repairing, rehabilitation of irrigation weir system An Hiep commune - - An Hiep commune - - b, An Hiep stream embankment – An Linh An Linh commune - - c, An Hiep stream embankment An Hiep commune 17 35 Chi Thanh town 2 - Ky Lo river embankment, section across Ngan d, Son bridge, Tuy An district An Dinh commune 1 27 Repairing, rehabilitation of the provincial 3 8 - roads.643, 650, 642 Xuan Tho 2 8 - commune Repairing, rehabilitation of the provincial a, La Hai town - - road.642 Xuan Son Bac - - commune Repairing, rehabilitation of the provincial b, An Xuan commune - - road.650 Repairing, rehabilitation of the provincial c, An My commune - - road.643 Total 29 62 Source: IOL Survey, March /2017 Page 16 3.2.3 Impacts on Public Land 33. In addition to impacted land and structures owned by households, the project also has affects with 245,833 m2 of public land managed by 12 commune/town CPs, including specialized land, stream, river land, and transport road. This public land managed by communes/towns will be assisted at 80% of agricultural land area at the same type in land price as current regulations of Phu Yen PPC. 3.2.4 Impacts on Income and Business 34. The preliminary survey results showed that out of 423 affected households, there is none of households with business activities lost resulted by land acquisition. 35. However, out of 381 households are affected with agricultural land, 118 households are severely affected by losing agricultural land area (of which 111 households lose from more than 20% of total agricultural production land area and 07 vulnerable households lose from 10% of total existing cultivation land area. For households affected with income and business, in addition compensation, assistance, these households will be participated in income restoration progam (IR). Details of IR are presented in the next chapter of the RAP. 3.3. Temporary Impacts during the Construction Process 36. The preliminary survey results showed that the project will also temporarily affect agricultural land owned by 60 households and public land managed by 12 communes/towns with total temporarily affected land area of 31,810 m2, of which affected agricultural land area is 8,500m2, public land area is 23,310m2 including special used land, stream, river land, transport land, without any assets and crops and trees. 37. During the construction process. temporarily affected land area is used mainly as gathering site of materials, bypass, and transport roads. Compensation, assistance for temporarily affected land area will be paid based on affected level and detailed time of construction of the Project by Contractor. In case if any structures, crops and trees found affected by the construction activities, it will be compensated in accordance with project policies (see Section 6.2.2). 3.4. Linked projects 38. Screening results showed that there is no project linked or associated with the Emergency Natural Disaster Reconstruction Project – Phu Yen Subproject. 4. SOCIO-ECONOMIC INFORMATION 4.1. Overview of Phu Yen province ï?¶ Natural conditions 39. Phu Yen province is located in South Central Coast with geographical coordinates: Northernmost point: 13041'28"; Southernmost point: 12042'36"; Westernmost point: 108040'40" and Easternmost point: 109027'47". - It borders Binh Dinh province to the North; - It borders Gia Lai and Dak Lak provinces to the West; - It borders Khanh Hoa province to the South; - It borders East Sea to the East. Phu Yen province has favorable location on geography and transport for socio-economic development. 40. Phu Yen province has natural area of 5,152.49 km2, coastline is 189km long, Phu Yen has 01 city, 01 town and 07 districts. Page 17 ï?¶ Socio-economic conditions Characteristics of population, labor: 41. By 2015, Phu Yen province’s average population is 1,247,644 people with population density of 242 people/km2. Total population working in national economy in Phu Yen province is 498,710 people. Of which rate of population in agricultural, forestry, fishery sector is 295,236 people, accounting for 59.2%; 81,789 people, representing 16.4% in industry – construction; 121,685 people, in service sector, making up 24.4% out of total population in national economy. Table 9: Area, population and population density of Phu Yen province in 2015 Administrative map - Phu Yen province Administrative Av. population Pop. density No. District/City Area (km2) unit (People) (people/km2) 1 Tuy Hoa city 6 107 202,030 1900 2 Dong Xuan district 11 1,063 63,715 60 3 Dong Hoa district 10 26,959 115,246 - 4 Song Hinh district 11 887 48,000 5 Phu Hoa district 9 263 105,068 6 Son Hoa district 14 950.33 57,835 7 Tuy An district 15 435 133,000 8 Tay Hoa district 12 61,043 125,617 9 Song Cau township 14 489,284 101,521 188,139 Total 184 5,152.49 1,247.644 242 (Source: Statistical Yearbook of Phu Yen Province, 2015) 42. Phu Yen province is located in Central key economic zone with average growth rate by 2010 of 13.6%/year; this rate reached 15.2% in the period 2011 – 2015 and 15.3% in 2016 – 2020. Income per capita is US $ 750/person/year in 2010; 1,600 US $/person/year in 2015, income per capita is estimated at US $ 3,000/person/year by 2020. 43. Economic restructuring: Economic restructuring follows the direction of gradually increasing the proportion of industries and services. Economic structure: in 2010: agriculture 24.5%, industry 38.5%, services 37%; By 2015: agriculture is only 16%, industry 44% and service is 40%; It is expected that by 2020, agriculture will fall to 10%, industry will increase to 47% and services will be Page 18 43%. Budget revenue growth rate: The ratio of budget revenue compared to GDP in 2010: 11.5%; 2015: 15% and 20% by 2020. 44. Growth rate for value of export and import turnover: Export turnover and services of foreign exchange reached 150 million USD in 2010, reached 1,000 million USD in 2015, it is estimated to reach 1,500 million USD by 2020. 4.2. Socio-economic Information of Affected Households in the Project Area 45. VietNam Emergency Natural Disaster Reconstruction Project– Phu Yen subproject consists of 04 components with 9 works items. The Subproject’s works items to be implemented in 12 communes/towns of Dong Xuan, Phu Hoa, Tuy An, Dong Xuan districts and Song Cau township. Socio-economic information of the project communes/wards is presented in the Table as follow: Table 10: Socio-economic information of the communes/wards for implementation of Subproject’s items Rate of Rate of Rate of natural near poor No Communes/ poor Districts Population No. Of HHs pop. households . Towns households increase (%) (%) (%) 1 An My Tuy An 3,399 - 0.9 9.53 17.18 2 An Hiep Tuy An 6538 - 0.88 9.05 11.46 3 An Linh Tuy An 4,467 1,294 - 13.83 8.96 4 An Xuan Tuy An - - 0.4 13.06 16.76 5 An Dinh Tuy An - 1660 0.35 10.13 - 6 Chi Thanh town Tuy An - 3300 0.85 11.99 13.06 7 La Hai town Dong Xuan 10,150 2534 0.2 7.14 - 8 Xuan Son Bac Dong Xuan 3280 - - 31.62 17.80 9 Xuan Tho 2 Song Cau township 3,687 914 0.93 13.35 10.71 10 Xuan Binh Song Cau township 10,000 2570 - 15.14 10.33 11 Xuan Loc Song Cau township - - 0.95 2.7 - 12 Hoa Thang Phu Hoa 21,049 5,411 0.97 10.05 4.81 (Source: Socio-economic development situation of communes/towns, 2016) 4.2.1. Survey Approaches and Methodologies ï?¶ Approaches 46. The participatory approach is used in preparing the Resettlement Action Plan. Accordingly, affected people were engaged in preparatory phase of this Resettlement Action Plan by mean of in- depth interviews, focus group discussions, and observation. The representatives of Phu Yen PMU and Ward/Commune PCs were also invited to participate. ï?¶ Methodologies 47. The methodologies applied in the process of preparing the RAP in Phu Yen province include: Desk review Page 19 48. The Consultant collected, reviewed, studied and analyzed/assessed the documents relating to compensation, assistance and resettlement of the Project. Those documents were collected at Phu Yen PMU, the PCs of project wards/communes, including: (i) Project documents (Statement and Design Drawings of project work items; Resettlement Policy Framework, etc.); (ii) Cadastral maps, copies of maps and Socio-economic reports provided by commune/ward PCs; (iii) relevant policies of the World Bank, the Government of Vietnam and Phu Yen PPC with aim to (1) find out procedures, regulations proposed and approved from the project documents, (2) find out technical methods proposed for each Project component; (3) review socio – economic reports of localities, (4) propose mitigation measures and guidelines for follow-up actions. Qualitative research method • Consulting agencies carried out 09 focus-group discussions with representatives of local authorities and affected households in affected communes/towns (including severely affected households and vulnerable households) on issues related to land acquistion, compensation and assistance. • Consulting agencies implemented 23 in-depth interviews with key informants, including 04 village leaders, 04 leaders of CPCs and 15 households with more acquired land area than other households ( of which 06 households are affected by losing from 20% or more of total agricultural land area, 05 vulnerable households and 04 households are affected with residential land). Out of total 89 participants in group discussion and in-depth interview, 47 people are male and 42 people are female. List of participation and minutes of working is attached to this report in Annex 02. • Field survey to the project area to determine the potential impacts on local residents during the project implementation. Quantitative research method. • During the period from 03/04/2017 to 10/04/2017, resettlement consultants carried out socio- economic survey1 and survey for affected land/assets in 12 communes/towns of Phu Hoa, Tuy An districts, Song Cau township, Dong Xuan district. • Socio-Economic Survey (SES) by questionnaire: 40% of total affected households whose land is acquired by the project implementation were surveyed. Including: (i) severely affected households (by losing 20% or more of total agricultural land holding and households affected with income); (ii) households are affected with residential land and (iii) vulnerable households (woman-headed households, poor households, households with the elderly and so on) and some households are indirectly affected by the Subproject. As result, total 116 households are socio-economic surveyed by questionnaire in the project area. SES sample for affected households are attached in Annex 3 of this report. • The Inventory of Losses (IOL) is carried out with 100% affected households. 49. Entering and processing data. Information collected from the field visit will be processed by specialized software such as SPSS (Quantitative) and NVIVO (Qualitative). 4.2.2. Results of Socio-Economic Survey of Affected Households in the Project Area 4.2.2.1. Survey Scope 50. Regarding to impacts by land acquisition for implementation of the Subproject’s works, results of survey showed that the project might affect 423 households, of which 403households are directly affected by land acquisition and 20 households are indirectly affected by cultivation on land area managed by communes/wards CP (non-land assets). 51. Thus, from 03 to 10, April 2017, SES was carried out for 116 households out of total 423 affected households (accounting for 27% out of total affected households). Detailed data on surveyed scope for each works item of the project are shown in the Table as follow: 1 Use SES questionnaire for the ENDR project- Ha Tinh Subproject Page 20 Table 11: Socio-Economic Survey Scope in the Project area No. of surveyed households Household Marginall Items Communes/ s are y affected No. Household Wards Vulnerabl affected HHs s with e 20% or affected household more of residential s agricultur land al land area I Irrigation Subcomponent 1 Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune Ba river embankment, section across a, Phong Nien hamlet, Hoa Thang Hoa Thang 3 1 0 3 commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, repairing, 2 rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation of irrigation An Hiep a, 0 0 0 0 weir system commune An Hiep 4 0 2 0 commune Repairing, rehabilitation of An Hiep – b, An Linh road An Linh 2 0 2 0 commune An Hiep c, An Hiep stream embankment 4 14 12 0 commune Chi Thanh 0 0 4 0 township Ky Lo river embankment, section across d, Ngan Son bridge An Dinh 2 0 14 0 commune II Transport 3 Repairing, rehabilitation of the provincial road 643, 650, 642 Xuan Tho 2 2 15 6 0 commune Repairing, rehabilitation of the Xuan Son Bac a, 4 0 2 2 provincial road 642 commune La Hai town 0 0 0 0 Repairing, rehabilitation of the An Xuan c, 3 0 0 0 provincial road.650 commune Repairing, rehabilitation of the An My 3 0 0 0 provincial road.643 commune Page 21 No. of surveyed households Household Marginall Items Communes/ s are y affected No. Household Wards Vulnerabl affected HHs s with e 20% or affected household more of residential s agricultur land al land area 4 Repairing of the operation and management road of Xuan Binh reservoir Xuan Binh 3 0 2 0 Repairing of the operation and commune a, management road of Xuan Binh reservoir Xuan Loc 4 0 1 0 commune Total 34 32 45 5 Source: SES, April/2017 (Note: A household will have more than one type of impacts including business loss, requirement of relocation and be vulnerable household. 52. Out of 116 surveyed households, 32 households are affected with residential land; 45 households lose more than 20% of total agricultural land area (more than 10% for vulnerable households); 34 households fall into vulnerable households, 05 marginally affected HHs. The selected households are typical households/groups for selected samples in the project area. 53. Selection of households for SES is based on principle of land acquisition impacts scope, including losing agricultural land, residential land and permanently affected households by business production. Besides SES with about 27% affected households, public consultation meetings with local authorities and affected households were implemented by consultants during the Subproject’s wo rks items implementation. 4.2.2.2. Characteristics of Household Members 54. According to survey data from 116 households directly affected by subproject’s works, the majority of households consists of from 3 to 5 members (accounting for 61.5%), followed by households with 6 - 9 members, accounting for 30% and households with 1 to 2 members, accounting for only 9.1%. On average, each AH household in the project area has 4.3 persons / household and the average main number of laborers per household is 2 persons. Out of 12 communes/towns, none of ethnic minorities households could be found. 4.2.2.3. Education level 55. According to survey data from 116 affected households, education level of local people in the project area remains low, percentage of household heads with primary school accounts for 14.7%, in which rate of female is higher than rate of male, male accounts for 5.6% meanwhile female makes up 9.8%, 20.7% of households heads graduated from high school, in which male represents 33.3%, female accounts for 8.8%; mostly 52.5% of household heads graduated from secondary school, in which male accounts for 38.9% and female represents 65.6%, 4.3% of household heads graduated from college/university. Meanwhile, the rate of uneducated/illiteracy is 7.8% due to difficult economic situation, lack of local infrastructure, it is impossible for them to attend school. Table 12: Education level of household heads Male Female Numbers No. Education level Rate (%) No. % No. % (persons) Page 22 Male Female Numbers No. Education level Rate (%) No. % No. % (persons) 1 Illiteracy 3 5.6 6 9.8 9 7.8 2 Primary school 9 16.7 8 13.1 17 14.7 3 Secondary school 21 38.9 40 65.6 61 52.5 4 High school 18 33.3 6 9.8 24 20.7 5 College/University 3 5.6 2 1.6 5 4.3 Total 54 100.0 62 100.0 116 100 Source: SES, April/2017 4.2.2.4. Occupation of Household Heads 56. The survey results showed that the main source of income for affected households in the affected communes is mainly based on agricultural production activities, including afforestation, growing rice and livestock and so on. Agricultural production is a great determinant of the stability and well-being of the household. Out of 116 surveyed AHs, 108 household heads (accounting for 93.1%) are farmers; 7 affected household with household heads are workers, free labors, representing 6.0 % and 0.9 % of household heads do other business. Table 13: Occupation of house hold heads by gender Male Female Numbers Occupation Rate (%) Male % Female % (perons) Agriculture 49 90.7 59 95.1 108 93.1 Workers 4 7.4 3 4.9 7 6.0 Service Business 0 - 0 - 0 - Civil servant 1 1.9 0 - 1 0.9 Total 54 100.0 62 100.0 116 100.0 Source: SES, April 2017 57. Details of occupation of household heads by gender are presented in the Table as follow: Table 14: Occupation of household heads divided into each item Occupation No. Items Location Public Agricultur Workers servants/ Trade/ e, fishery officials Service I Irrigation subcomponent 1 Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune Ba river embankment, section across Phong Nien a, Hoa Thang 7 1 0 0 hamlet, Hoa Thang commune Page 23 Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, 2 repairing, rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation a, An Hiep commune 0 0 of irrigation weir system Repairing, rehabilitation An Hiep commune 6 b, of An Hiep – An Linh road An Lanh commune 4 An Hiep stream c, An Hiep commune 28 2 embankment Ky Lo river embankment, Chi Thanh town 6 d, section across Ngan Son bridge An Dinh commune 14 2 II Transport Subcomponent 3 Repairing, rehabilitation of the provincial road 643, 650, 642 Xuan Tho 2 19 2 1 commune Repairing, rehabilitation a, Xuan Son Bac of the provincial road.642 8 commune La Hai town 0 0 0 Repairing, rehabilitation b, An Xuan commune 3 of the provincial road.650 Repairing, rehabilitation An My commune c, 3 of the provincial road.643 4 Repairing of the operation and management road of Xuan Binh reservoir Xuan Binh 5 0 Repairing of the operation commune a, and management road of Xuan Binh reservoir Xuan Loc 5 0 commune Total 108 7 1 0 Source: SES, April/2017 4.2.2.5. Income and Expenditure 58. Income level of affected households falls into group with income below 1 million VND/person/month (accounting for 25 %). Followed by rate of household with income level from 1.1 - 3 million VND/person/month (accounting for 65.5%); rate of household with income more 3 million VND/person/month accounts for 9.5%. In which, income level is below 1 million dong, income of male accounts for 22.2% and income of female represents 27.4%. Income level from 1.1 – 3 million dong, in which income of male accounts for 63% and income of female makes up 67.7% and income is more than 3 million dong, income level of male accounts for 14.8% and income level of female represents 4.8%. Page 24 Table 15: Average Income/person/month by gender Male Female Income Number Rate (%) Male % Female % Below 1 million 12 22.2 17 27.4 29 25 VND/month From 1.1 million – 3 millionVND/ 34 63.0 42 67.7 76 65,5 month Morre than 3 8 14.8 3 4.8 11 9,5 million Total 54 100.0 62 100.0 116 100 Source: SES, April 2017 59. Specific data on average income/person/month of surveyed AHs are shown by items and impact magnitude in the Table as follow: Table 16: Average Income/Person/Month Income level (%) Commune/tow N Below 1 From 1.1 Over 3 Items ns o. million – 3 million million VND/mon VND/ VND/ month th month I Irrigation Subcomponent 1 Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune Ba river embankment, section across a, Hoa Thang 3 3 1 Phong Nien hamlet, Hoa Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, 2 repairing, rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation of irrigation weir An Hiep a, 0 0 system commune An Hiep 4 2 commune Repairing, rehabilitation of An Hiep – An b, Linh road An Linh 4 commune An Hiep c, An Hiep stream embankment 3 23 4 commune Chi Thanh 2 4 Ky Lo river embankment, section across township d, Ngan Son bridge An Dinh 2 14 Page 25 commune II Transport 3 Repairing, rehabilitation of the provincial road.643, 650, 642 Xuan Tho 2 2 17 4 commune Repairing, rehabilitation of the provincial a, Xuan Son Bac road.642 4 4 0 commune La Hai town Repairing, rehabilitation of the provincial An Xuan b, 3 0 road.650 commune Repairing, rehabilitation of the provincial An My c, 3 0 road.643 commune 4 Repairing of the operation and management road of Xuan Binh reservoir Xuan Binh 3 2 0 commune Repairing of the operation and a, management road of Xuan Binh reservoir Xuan Loc 4 1 commune Total 29 76 11 Source: SES, April/2017 60. According to results from SES reports of communes/towns in the project area in 2016, average income level of AHs in the project area is approximately 18.6 million VND/person/year. In which, Thi Thanh town has the highest average income level per capita with 28.8 million VND/person/year, 2 communes of Xuan Tho 2 and An Dinh of Tuy An district have the lowest average income level per capita with 5.5 million VND/person/year. 61. Out of 7 vulnerable households losing 10% or more of total agricultural land area, there are 4 poor households have their income below 700,000 VND/person/month., 3 policy households have their income from over 1,000,000 – 1,500,000 VND/person/month. 62. For 08 AHs with women headedhouseholds, survey results showed that these households have their averageincome level from 800,000 – 1,000,000 VND/ month, economic activities of households totally depend on agricultural production activities, thus, their lives get many difficulties, majority of women headed households in the project area falls into poor near households at locality. 63. Income level of households is decisive factor on their expenditure, with such income level, majority of surveyed households answered that they do not have enough money to cover their living expenses (including: eating, investment for their children education, medical treatment and so on). Their main source of income mainly depends on agriculture. Thus, during the project implementation process, poor households, ethnic minorities, policy households, etc. should be paid special attention in the case of resettlement, they have to relocate to new places, and their opportunities for restoring income and maintaining lives for these households are so difficult. 4.2.2.6. Households Ownership of Commodities 64. Value of assets in each household depends much on their economic condition. In the surveyed communes/towns areas, rate of poor households and medium-income households is majority, thus, means of living of households are mainly essential, common and low value. Specifically, 68.5% of households own bicycles, 86% of households own mobile phone, 91.6% of households own Page 26 motorbikes, 95.8% of households own colored television and so on. Furniture ownership situation of households are presented in detailed in the Table as follow: Table 17: Means of living of households No. Furniture No. of HHs Rate 1 High quality wooden furniture 87 75% 2 Motorbike 101 87% 3 Bicycles 98 84% 4 Radio 79 68% 5 Colored television 109 94% 6 Fridge 92 79% 7 Washing machine 39 34% 8 Telephone 113 97% Source: SES, April /2017 4.2.2.7. Vulnerable households 65. Consultation results with local authorities and survey by questionnaire in the project area showed that, out of 384 households affected by works under the Subproject, 34 AHs are vulnerable groups, of which: - 17 poor households. - 4 policy households. - 5 households with the elderly. - 8 women headed households. 66. Information of affected vulnerable households for each works under Subproject is shown in the Table as follow: Table 18: Information on vulnerable households in the project area No. of vulnerable households Communes/to No. Items Househo wns Poor Policy Household ld with househol househ with women the ds old headed elderly I Irrigation Subcomponent 1 Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune Ba river embankment, section a, across Phong Nien hamlet, Hoa Hoa Thang 3 2 1 1 Thang commune Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, 2 repairing, rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Page 27 No. of vulnerable households Communes/to No. Items Househo wns Poor Policy Household ld with househol househ with women the ds old headed elderly Repairing, rehabilitation of An Hiep a, irrigation weir system commune An Hiep commune Repairing, rehabilitation of An b, Hiep – An Linh road An Lanh commune An Hiep c, An Hiep stream embankment 1 commune Chi Thanh 1 township Ky Lo river embankment, d, section across Ngan Son bridge An Dinh 3 2 3 commune II Transport 3 Repairing, rehabilitation of the provincial roads.643, 650, 642 Xuan Tho 2 3 1 commune Repairing, rehabilitation of the a, provincial road.642 La Hai town Xuan Son 3 1 commune Repairing, rehabilitation of the An Xuan c, 2 provincial road.650 commune Repairing, rehabilitation of the An My commune 2 provincial road.643 4 Repairing of the operation and management road of Xuan Binh reservoir Xuan Binh 1 1 2 Repairing of the operation and commune a, management road of Xuan Binh reservoir Xuan Loc 1 commune Total 17 4 5 8 Page 28 No. of vulnerable households Communes/to No. Items Househo wns Poor Policy Household ld with househol househ with women the ds old headed elderly Source: SES, April /2017 67. Out of total 34 affected households falling into vulnerable group, none of severely affected households has to relocate, 7 households lost 10% or more of total agricultural land area, 27 remaining households are marginally affected. Information of severely affected vulnerable households in the project area is shown in the Table as follow: Table 19: Severely affected vulnerable households in the project area Severely affected vulnerable households Households losing No. Items Location from more than Relocated 10% total households agricultural land area I Irrigation Subcomponent 1 Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune River embankment for PhongNien a, HoaThang commune 1 - section Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep 2 commune, repairing, rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge Repairing, rehabilitation of An Hiep commune a, - - irrigation weir system Repairing, rehabilitation of An An Hiep commune - - b, Hiep – An Linh road An Linh commune - - c, An Hiep stream embankment An Hiep commune - - Ky Lo river embankment, section Chi Thanh township - - d, across Ngan Son bridge An Dinh commune 3 - II Transport 3 Repairing, rehabilitation of the provincial road.643, 650, 642 Repairing, rehabilitation of the Xuan Tho 2 - a, 1 provincial road.642 commune Page 29 Severely affected vulnerable households Households losing No. Items Location from more than Relocated 10% total households agricultural land area Xuan Son Bac - 1 commune La Hai town - - Repairing, rehabilitation of the - - b, An Xuan commune provincial road.650 Repairing, rehabilitation of the c, An My commune - - provincial road.643 4 Repairing of the operation and management road of Xuan Binh reservoir Repairing of the operation and Xuan Binh commune - a, management road of Xuan Binh reservoir Xuan Loc commune 1 - Total 7 - Source: SES, April /2017 4.2.2.8. Land Use Right Certificates (LURCs) 68. Through survey of LURCs, 89.4% of households have LURCs; 10.6% of households have leased land contracts for agricultural cultivation. They are all entitled to receive compensation and assistances from the project. Out of 89.4% of households with LỦRCs, 58% of households with LURCs named by husbands and wives, 31% of households with LURCs named by husbands and 11% of households with LURCs named by wives. 4.2.2.9. Access to Utilities and Services 69. Use of electricity: According to consultation results, 99.7% of surveyed households use the national power grid with their own electricity meters and the average electricity consumption of a household is about 114,000 VND / household / month. 70. Use of water for eating, living and production: Out of total 116 surveyed households, 40.7% of households use river and stream water for living and eating; 43.2% of households use drill well water; 17.9% of households use storm water and only 17.2% of households use tap water for living and eating. 71. Use of toilets: Out of total 116 surveyed AHs, 84.1% of households have their own toilets; 15.9% of households do not have toilets. In the project area, majority of households use two compartment toilet and ash toilet, the septic tank only accounts for a small rate. 72. Waste collection: Currently, in the project area, Chi Thanh and La Hai towns have waste collection system; this activity is implemented quite effectively with waste collection frequency of 1 time/1 day. In other communes, without waste collection system, households often throw rubbish into the stream or into their garden. Page 30 5. LEGAL FRAMEWORK 73. In order to guide the implementation of involuntary resettlement, this section provides principles, objectives, and eligibility for AHs as well as benefits, institutional and legal frameworks for compensation and restoration measures based on the World Bank’s OP/BP 4.12 Policy on Involuntary Resettlement (amended in May 2011) and Legal Framework of the GoV. 74. The Resettlement Action Plan was prepared on the basis of the Resettlement Policy Framework of the project which has been approved by the Prime Minister and obtained No-objection from the Bank. Simultaneously, the Resettlement Action Plan will comply with the laws, circulars, decrees stipulating the land acquisition, compensation and resettlement in Vietnam, and the WB’s policy on Involuntary Resettlement. 5.1. Legal Framework of GoV 75. The Laws and Decrees with respect to land acquisition, compensation and resettlement in Vietnam are based on the regulations of the city/province at time of preparing RAPF and RAP, including: - Constitution of the Socialist Republic of Vietnam adopted in 2013. - Land Law No.45/2013/QH13 dated in 2013, effective on July 1, 2014. - Decree No. 43/2014/ND-CP dated May 15, 2014 of the GoV on detailing a number of articles of the Land Law No.45/2013/QH13. - Decree No. 44/2014/ND-CP dated May 15, 2014 of the GoV on land prices; - Decree No. 45/2014/ND-CP dated May 15, 2014 of the GoV on collection of land use levies. - Decree No. 46/2014/ND-CP dated May 15, 2014 of the GoV on collection of land rent and water surface rental. - Decree No. 47/2014/ND-CP dated May 15, 2014 of the GoV on compensation, support and resettlement upon land recovery by the State. - Decree No. 84/2013/ND-CP dated July 25, 2013 of the GoV on development and management of resettlement housing. - Decree No. 16/2016/ND-CP dated March 16, 2016 of the GoV on management and use of official development assistance (ODA) and concessional loans of foreign donors. - Circulars No. 36/2014/TT-BTNMT dated June 30, 2014 of Ministry of Natural Resources and Environment on land pricing method; compilation of and adjustment to land price lists; determination of specific land prices and consultancy on land pricing. - Circular No.37/2014/TT-BTNMT of the MONRE dated June 30, 2014 on compensation, support and resettlement upon land recovery by the State. - Decision No/63/2015/QD-TTg of the Governmental Prime Minister dated December 10, 2015 on policy on assistance in vocational training and job search for workers whose land is withdrawn by the state. - Decision No.1956/2009/QD-TTg of the Governmental Prime Minister dated November 17, 2009 on vocational training for rural. 76. Other relevant laws, decrees and regulations:: the Construction Law No.50/2014/QH13 dated June 18, 2014 on construction activities, rights and obligations of organization and individual investing in civil works construction and construction activities; Decree No.102/2014/ND-CP on sanctioning of administrative violations in the field of land; Decree No.15/2013/ND-CP dated February 6, 2013 on quality management of constructions; Decree No. 12/2009/ND-CP dated February 12, 2009 on the management of construction investment projects; Decree No.126/2014/ND- CP on marriage and family Law implementation, stipulating that all documents registering family assets and land use rights must be in the names of both husband and wife. Page 31 77. Decrees relevant to protection and preservation of cultural property include Decree No. 98/2010/ND-CP. Detailed regulations for implementation of some articles of the Law on Cultural Heritage and the Law on editing and supplementing some articles of the Law on Cultural Heritage requiring that sites currently recognized as cultural and historical vestiges, should be kept intact according to current legal regulations. 78. Documents relating to complaints and resolve complaints mechanisms: Complaints Law 02/2011/QH13 dated November 11, 2011; Decree No. 75/2012/ND-CP dated March 10, 2012 on specific provisions a number of articles of the Law on Complaints. 79. Decisions issued by Phu Yen province related to compensation, assistance and resettlement policies to be applied include:  Decision No.57/2014/QD-UBND dated December 30th 2014 by Phu Yen PPC on detailed regulations on compensation, assistance and resettlement when the State acquires land in Phu Yen province.  Decision No. 44/2016/QD-UBND on procedures of detailed price implementation in Phu Yen province.  Decision No.55/2014/QD-UBND dated December 29th 2014 by Phu Yen PPC on compensation rate on houses, structures when the State acquires land in Phu Yen province.  Decision No.01/2015/QD-UBND dated January 06th 2015 by Phu Yen PPC on compensation rate on trees, crops when the State acquires land in Phu Yen province.  Decision No.56/2014/QD-UBND dated December 30th 2014 on land price in 2015 in Phu Yen province, applied in the 05 – year period (2015 – 2019). 5.2. World Bank Policy on Involuntary Resettlement (OP 4.12) 80. The World Bank recognizes that involuntary resettlement may cause severe long-term hardship, impoverishment, and environmental damage unless appropriate measures are carefully planned and carried out. The Bank’s Resettlement Policy OP 4.12, includes safeguards to address and mitigate the economic, social, and environmental risks arising from involuntary resettlement. 81. Objectives of the WB’s policy on involuntary resettlement are the following: (i) Involuntary resettlement should be avoided where feasible or minimized by all viable alternative project designs and selection of location where land acquisition is unavoidable but impacts are minimized; (ii) Wherever involuntary resettlement is unavoidable, resettlement activities should be conceived of and executed as sustainable development programs, providing sufficient investment sources to enable affected persons to share project’s benefits; (iii) Directly or indirectly affected persons must be consulted and participated in the process of planning and implementing resettlement programs; (iv) Affected Persons should be assisted in efforts to improve their livelihoods and living standards or at least to restore them, in real terms, to pre-project levels or to levels prevailing prior to the beginning of project implementation, whichever is higher. 82. Required measures: To resolve project impacts, the Project Owner prepared a Resettlement Action Plan that includes measures to ensure that affected persons are: (a) Informed of their options and entitlements to resettlement; (b) Consulted on the offered choices and provided with technically and economically feasible resettlement alternatives; and (c) Provided with prompt and effective compensation at replacement cost for lost assets attributable directly to the project. Page 32 5.3. Comparison between GoV’s and WB’s Policies 83. There are still some differences between the Government of Vietnam’s Laws, policies, regulations related to land acquisition/resettlement, and the World Bank’s OP 4.12 on Involuntary Resettlement. Comparison of GoV’s and WB’s policies on compensation, assistance and resettlement and proposed policies under the ENDR project is presented in the approved RAPF. 84. Vietnam is a country member of the World Bank, the Government of Vietnam has committed that should the international agreements signed or acceded to by Vietnam and the World Bank contains provisions different from those in the existing resettlement legal framework in Vietnam, the provisions of the international agreements with World Bank shall prevail. According to Clause 2, Article 87 of the Land Law 2013: "For projects using loans from international or foreign organizations for which Vietnam has committed to a policy framework for compensation, assistance and resettlement that framework policy shall prevail.â€? 85. The project Resettlement policy framework confirms that in approving this instrument, the Government of Vietnam and Phu Yen Provincial People's Committee grant the waivers to the relevant provisions of the Vietnam law that contradict or are not consistent with the objectives set forth in the Resettlement Policy Framework. The measures taken to resolve these differences and compliance with the WB’s policy on involuntary resettlement are addressed under RPF and applied to this RAP. 6. PRINCIPLES AND POLICIES FOR COMPENSATION, ASSISTANCE AND RESETTLEMENT 6.1. General Principles 86. All projects affected persons (AHs) who have assets within or reside within the area of project land-take before the cut-off date are entitled to compensation for their losses. Those who have lost their income and/or livelihood will be eligible for livelihood rehabilitation assistance based on the criteria of eligibility defined by the project in consultation with the AHs. If, by the end of the project, livelihoods have been shown not to be restored to pre-project levels, additional assistance measures will be provided. (a) The compensation rates will be determined timely and in consultation based on independent land valuation results of the Independent Valuation Unit hired by Phu Yen PMU. Compensation rates for trees/crops/non-land assets will be applied as those issued annually by Phu Yen PPC based on market price survey results of Phu Yen Department of Construction. The independent monitoring agency (IMA) will assess relevance of these compensation rates. (b) All fees and taxes related to transferring land and/or housing and fee for receiving land use right certificate will be exempted for the relocated HHs who already paid fee before for receiving land use right certificate. The local authorities will ensure that AHs who will be arranged relocation on their own, will also be exempted from transaction fees like the ones who will move to the project resettlement sites. (c) Land will be compensated “land for landâ€?, or in cash, according to PAP’s choice whenever possible. The choice of land for land must be offered to those loosing 20% or more of their productive land. If land is not available, the borrower must assure itself to meet the Ban’s requirements that this is indeed the case. Those loosing 20% or more of their land will have to be assisted to restore their livelihood. The same principles apply for the poor and vulnerable people losing 10% or more of their productive landholding. (d) PAPs who prefer “land for landâ€? for residential land will be provided with land plots with the equivalent quality for lost lands or a combination of land (a standard land plot) in a new residential area nearby for residential land, and cash adjustment for difference between their lost land and the land plots provided. The resettlement area will be planned properly and implemented in consultation with the PAPs. All basic infrastructures, such as paved roads, sidewalks, drainage, water supply, and electricity and telephone lines, will be provided. Page 33 (e) PAPs who prefer “cash for landâ€? will be compensated in cash at the full replacement cost. These PAPs will be assisted in rehabilitating their livelihoods and making their own arrangements for relocation. (f) Compensation for all residential, commercial, or other structures will be offered at the replacement cost, without any depreciation of the structure and without deduction for salvageable materials. Structures shall be evaluated individually. Any rates set by category of structure must use the highest value structure in that group (not the lowest). (g) As for the displaced households affected with shelter (displaced from existing residential land because the remaining land area is not feasible for building house or entire land acquisition), the local resettlement board needs to conduct consultations and makes agreed solutions to assist for new shelter for affected households. (h) The displaced households affected with shelter that are capable of building a house on the remaining land (not subject to displacement) will have general policies of the project applied in accordance with the agreed entitlement matrix. (i) The PAPs will be provided with full assistance (including a transportation allowance) for transportation of personal belongings and assets, in addition to the compensation at replacement cost of their houses, lands and other properties. (j) Compensation and rehabilitation assistance must be provided to each PAP at least 30 days prior to the taking of the assets for those who are not to be relocated and 60 days for those who will have to be relocated. Exceptions should be made in the case of vulnerable groups who may need more time. (k) If, by the end of the project, livelihoods have been shown not to be restored to pre- project levels, additional measures will be provided. (l) Additional efforts, such as economic rehabilitation assistance, training and other forms of assistance, should be provided to PAPs losing income sources, especially to vulnerable groups, to enhance their future prospects toward livelihood restoration and improvement. 6.2. Entitlements 87. AHs will be entitled to the compensation, assistance and resettlement policy (if any) in accordance with the regulations of Vietnam and the World Bank OP 4.12. AHs will not be considered for compensation or support from the project for the area to be occupied after the cut-off date announcement. Compensation policies of project are as below: 6.2.1. Compensation Policy for Permanent Impacts 6.2.1.1. Compensation Policy for Agricultural Land 88. For legal land users or legalizable land use rights: (i) The local agricultural land fund of wards/commune in Phu Yen province is not available, therefore the cash compensation will be applied instead of the “land for landâ€? compensation to affected agricultural land area and assets on acquired land at 100% replacement cost; (ii) If area of remaining land after acquisition is not enough to continue cultivation, the project will acquire the entire piece of land and compensation would be implemented in cash for the affected agricultural land area and assets on the acquired land at 100% replacement cost. (iii) In addition to cash compensation for acquired land area as stipulated above, AHs will be entitled to livelihood restoration assistances as mentioned in the RPF. (iv) In the case of acquired land exceeding the limit of local land allocation quota (except for land by inheritance, donation or receive transfer of land use rights) this land is not entitled to compensation for land but supported remaining values invested in such lands. Page 34 89. Users with temporary or leased rights to use communal/public land: (i) For AHs currently using land assigned by State-owned agricultural or forestry farms on a contractual basis for agricultural, forestry, or aquaculture purposes (excluding land under special use forests and protected forests), compensation shall be provided for the remaining value of investments made on the land, and for all assets attached to the land at replacement cost, and these AHs will also receive additional support for income rehabilitation if they are directly involved in agricultural activities as per Government’s regulations. (ii) Where AHs receive land on a contractual basis but are other than the individuals specified as point (i) above, they shall only receive compensation for the remaining value of investments made on the land and structures created on land at full replacement cost. 90. Land Users who do not have formal or customary rights to the affected land (i) For agricultural land which was used before July 1, 2004, of which land users are households and individuals directly engaged in agricultural production will be compensated at 100% as per Clause 2, Article 77 of the Land Law. (ii) For other cases, instead of compensation, the AHs will receive financial assistance of an amount corresponding to the remained value of investment made for the land improvement. (iii) In case of a physical impediment caused by the project, AHs will receive additional compensation or supports if required to offset. 6.2.1.2. Compensation for Loss of Land for non-agricultural production and business 91. Organizations, individuals whose land for non-agricultural production and business is acquired will be compensated according to the following cases: (i) All affected households, individuals with LURC or legalizable: i) if local land fund is available and AHs choice, Compensation “land for landâ€? is priority; ii) If land is not available or the AHs prefers to receive cash compensation, they will receive compensation in cash for loss of land and assets on the land acquisition at 100% replacement cost. (ii) Households and individuals who use leased land acquisition with annual rent payment or lump-sum rent payment but were exempted from rent will not be compensated for land but compensated equivalent to remaining values invested in such lands and assets on the land at 100% replacement cost . (iii) Valid organizations (economic organizations, public organizations in accordance with financial autonomy) using land for non-agricultural production and business with lump-sum rent payment (rent unused the state budget) with LURs or legalizable LURs will be compensated “land for landâ€? if local land fund is available, if not, will be compensated in cash at 100% of replacement cost. (iv) Valid organizations (economic organizations, public organizations in accordance with financial autonomy) using land for non-agricultural production and business with annual rent payment or lump-sum rent payment but were exempted from rent will not be compensated for land but compensated equivalent to remaining values invested in such lands and assets on the land at 100% replacement cost. 92. In addition to the compensation mentioned above, the project will provide removal allowances of manufacturing and business facilities for affected organizations/Individuals. 6.2.1.3. Compensation for Residential Land 93. Users whose residential land is acquired will be compensated as follows: 94. Loss of residential land without structures: (i) For legal and/or legalizable land users, all compensation for loss of land will be made in cash at 100% replacement cost. Page 35 (ii) For land users who have no recognizable land use right, financial assistance will be provided corresponding to the remained investment put on the land. The amount will be determined by Provincial People’s Committee. 95. Loss of residential land with structures built thereon, where the remaining (non-acquired) land is adequate to rebuild the structure (reorganizing AHs): (i) Compensation for loss of land will be made in cash at 100% replacement cost for legal and legalizable land users; (ii) Financial assistance of an agreed amount will be provided to land users who do not have recognizable land use rights. The amount will be determined by Provincial People’s Committee. (iii) Regardless of legal status of land use, compensation for affected structures at 100% replacement cost. (iv) If AHs have to rebuild the main house (not necessary to relocate to new area), they will also receive repair allowance as mentioned in the RAPF. 96. Loss of residential land with structures built thereon, and the remaining land is not adequate to rebuild the structure in accordance with regulations of PPC (AHs have to relocate): (i) AHs with legal and/or legalizable rights to the affected land, can choose one of the following options: ï‚· If AHs choice is compensation “land for landâ€?: AHs will be compensated land plot/apartment in the project’s resettlement site where infrastructure is fully invested and allocation of resettlement land plot/apartment land will be made according to the provisions of Provincial People’s Committee, depending on local land fund. AHs will be provided with a certificate of land/ apartment use without paying any fees. ï‚· In case that the compensation amount to be paid is more than the cost of land plot/apartment compensation in the project’s resettlement site, the difference amount will be paid in cash to AHs. ï‚· In case the compensation amount to be paid is less than the cost of a minimum land plot /apartment in the project’s resettlement site, AHs will be provided the differences. ï‚· If AHs choice is not compensation “land for landâ€?, all compensation for loss of land will be made in cash at 100% replacement cost, plus relocation allowance prescribed by the province for self-relocation. ï‚· In case the remaining land is not large enough to rebuild a house, but in the same plot of land there is a pond/ garden/ agricultural land, households may propose converting part of the pond/ garden/agricultural land into residential use according to the provisions of the PPC to be able to rebuild house on site. (ii) The AHs, who do not have legal or legalizable rights to the affected land, are entitled to the following: ï‚· Amount of financial assistance will be reviewed and decided by Provincial People’s Committee. ï‚· If the AHs have no place to move, a land plot or an apartment satisfactory to them will be provided in the resettlement site and they can either pay in installments or rent it for living. 97. In case the relocated AHs belong to poor or vulnerable groups or households, additional assistance (in cash and kind) will be provided to ensure that they are able to fully relocate to a new site. Phu Yen PPC will consider making decision on assistance level for AHs. 6.2.1.4. Compensation for Structures 98. Compensation policy for structures are as follows: 99. For Loss of Structures: Page 36 (i) Owners of affected structures shall be compensated as follows: ï‚· Compensation in cash will be made for all affected private-owned houses/structures, at 100% the replacement costs, regardless of whether or not they have title to the affected land or a construction permit for the affected structure. The compensation amount will be sufficient to rebuild the affected house/structure of the same quality. ï‚· If the house/structure is partially affected, a financial assistance will be provided to enable AHs to repair the affected house/structures to restore it to the former condition, or better, at no additional cost to them. ï‚· Cash compensation will be at full replacement cost. No deductions will be made for depreciation or salvageable materials. ï‚· The calculation of rates will be based on the actual affected area and not the useable area. (ii) Tenants of state-owned or state organization-owned houses will be entitled to rent or buy a new apartment of an area at least equal to their affected ones; or provided a financial assistance equivalent to 60% of replacement cost of the affected land and houses. The affected structures, crops, trees created by the AHs before cut-off date will be compensated for at full replacement costs. (iii) Tenants who are leasing a private house for living purposes will be provided with transportation allowance for moving assets, and will be assisted in identifying alternative accommodation. 100. For Graves: (i) Compensation for the removal of graves/ tombs will include the cost of excavation, relocation, reburial and other related costs which are necessary to satisfy customary requirements. The compensation amount will be determined by Provincial People’s Committee. (ii) For ownerless affected graves, Phu Yen PMU will sign a contract with an independent unit for compensation and relocation of them to a new site. (iii) Household and individual graves are considered physical cultural resources (PCR) and even though the costs associated with their relocation will be covered in the Resettlement Action Plan, the WB OP 4.11 on Physical Cultural Resources should be triggered and relevant cross references should be made to the Environmental and Social Management Plan or Project Operation Manual (POM). 6.2.1.5. For Loss of Crops, Trees and Livestock 101. For annual and perennial standing crops, regardless of the legal status of the land, compensation will be paid to households who cultivate the land at full replacement cost. For trees which have not been harvested yet but can be brought to another location, the transportation cost and the actual damage due to the transportation and re-planting must be compensated. 102. For livestock (including aquatic livestock), AHs will be compensated in cash at replacement cost at the time of land acquisition. In case the aquatic livestock can be brought to another location, the transportation cost and the damage caused by the transportation must be compensated. 6.2.1.6. Compensation for other assets 103. In the case that the AHs are equipped with telephone system, water meter, electric meter, cable TV, internet access (subscription), the AHs shall be compensated according to the unit price of installing new units, are offered service announcement or relocation costs due to service provider’s regulations. 6.2.1.7. Compensation for Public Works 104. In cases where public works such as schools, factories, water sources, roads, sewage systems, medical centers, distribution/transmission, communication and fiber cables are damaged and the community wishes to reuse them, the project will ensure that these are restored or repaired as the case may be, at no cost to the community. Page 37 105. Public infrastructure directly related to people’s livelihoods and developmental needs, such as irrigation canals, schools, clinics, transportation road, electricity, telecommunication, cable lines (except for the structures with construction permit requiring relocation when needed) etc. will be restored/rebuilt to pre-project or higher quality levels or compensated at replacement cost. 6.2.2. Compensation Policy for Temporary Impacts During the Construction 106. In case the land is needed for temporary construction site, it will be rented following regulations stipulated by the Civil Law. 107. Compensation Policy for loss of private or public structures occurring during construction phase: (i) Damaged property will be restored to its former condition by contractors, immediately upon completion of civil works. (ii) Under their contract specifications, the contractors will be required to take extreme care to avoid damaging property during their construction activities. Where damages do occur, the contractor will be required to repair the damages and may also be required to pay compensation to the affected families, groups, communities, or government agencies at the same compensation rates that are applied to all other assets affected by the Project. 6.2.3. Any other Impacts Identified During Implementation 108. Any other impacts that may be identified during implementation will be compensated in accordance with the principles of this RAPF and World Bank OP 4.12. Any disruption of business will be compensated in accordance with the principles of the RAPF 6.2.4. Livelihood Restoration Assistances 109. Besides the compensation for affected assets, AHs will be provided with financial assistance to cover their expenses during the transition period. The assistance levels will be adjusted, taking into account inflation factor and price increase to be appropriate to the payment time. They include, but are not limited to: ï?¶ For Loss of Residential Land 110. Transportation Allowance to relocating households: Relocating households who move to a new location will be provided financial assistance in cash. The amount will be determined by Provincial People’s Committee. 111. House Renting Allowance will be provided to AHs who may be forced to relocate from their original homes and are still awaiting the replacement land plots or apartments. In the case of replacement land plots, the rental allowance will extend to the period during which the new house is being built. The allowance amount will be determined by Provincial People’s Committee. 112. Self-relocated households which are eligible for resettlement, but self-accommodation: an amount supported for investment in infrastructure for a minimum land plot /apartment in the projec t’s resettlement site. The specific level of support will be determined by Provincial People’s Committee. 113. Reparation Allowance: If house/structure is partially affected and the remaining structure is viable for continued use, the project will provide a repair allowance to enable AHs to restore it to former or better conditions. The level of specific support will be determined by Phu Yen PPC. 114. For households/individuals relocated by residential land acquisition that combines business: the project will provide an allowance for vocational training and job creation according to the provisions of the PPCs for demographic in the working age. 115. Subsistence allowance: AHs who is relocated or rebuilt house on the remaining land area will receive subsistence allowance in the transition period. The amount will be determined by Phu Yen PPC. ï?¶ For Impacts on Agricultural Land Page 38 116. Allowance for Subsistence allowance (during transition period): AHs impacted with agricultural land will be provided with an assistance in cash equal 30kg rice/person/month, specifically: (i) AHs losing 20 - 70% of their agricultural landholding (or 10 - 70% for the poor and vulnerable groups) will be provided with compensation of 6 months if they do not have to relocate, and 12 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided for a maximum of 24 months; (ii) AHs losing more than 70% of their agricultural landholding will be assisted at the above rate for a period of 12 months if they do not have to relocate, and 24 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided up to a maximum of 36 months; (iii) Households affected by loss of less than 20% of land, where the remaining land is rendered unviable for continued use, will be assisted with the above support plus any additional support as determined, for a period of 12 months. 117. Allowance for production stabilization: Households, individuals who are compensated by agricultural land will be supported for production rehabilitation, including: Support for plant varieties and animal breeds for agricultural production, services such as agricultural/forestry extension, plant protection, animal health, cultivation techniques, animal husbandry and professional techniques for manufacturing, business and commercial services. Form and level of specific support according to the provisions of Phu Yen PPC. 118. Allowance for Vocational Training and Job Creation: The maximum support will be 3 (three) times of price of agricultural land for acquired agricultural land area. 119. Assistance for agricultural, garden and pond land adjacent to, but not included in the category of residential land will be made according to the provisions of Phu Yen PPC. ï?¶ Support for Loss of Income and/or Business 120. Production and business stabilization assistance: (i) Businesses / households with business registration will be compensated or supported. The maximum compensation/support is 30% of after-tax income of 01 years based on their average annual of the last three years which have been declared to the tax authorities; (ii) Households without business license but who have met their tax obligations will be entitled to compensation equivalent to 50% of support level for businesses/households with business registration. 121. Removal Support: Organizations and AHs that are leased land by the state or are lawfully using land and have to relocate their productive and/or business establishments are entitled to financial support for dismantling, relocating and re-installation of the establishment. Support levels will be determined by actual costs at the time of removal, based on self-declaration of the organizations and verification by the agency in charge of compensation. This will then be submitted to the relevant authorities for approval. 122. Allowance for interrupted employment: Employees who work in affected manufacturing facilities or businesses with labor contract will receive allowance equivalent to the minimum salary as per the regulations to affected employees during the transition period which can be for a maximum of 6 months as well as assistance in seeking job opportunity if needed. ï?¶ For Loss of Public Land funds of communes, wards or townships: 123. If land belonging to public land funds of communes, wards or townships is acquired, it will be provided with an assistance of 80% of price of same-type agricultural land in accordance with the land price list issued by the PPC. The assistance amount will be paid into the state budget and allocated in annual budget estimates of communes, wards or townships people’s committee. The assistance amount should be used to invest construction of infrastructure projects used for public interest purposes of communes, wards and townships as stipulated in Article 24 of Decree 47/2014/ND-CP. ï?¶ Allowances/Assistances for Vulnerable Households Page 39 (i) For landless households: Assistance through provision of an apartment with either payment by installment to buy it or rent it for living (at AHs’ choice). Additional assistance will be considered if needed to ensure the AHs have a place to live. (ii) Social policy Households: Relocated Households which included heroic mothers, heroic armed force, heroic labor, war veterans, wounded or dead soldiers will be provided with support as regulated by Provincial People’s Committee (to be certified by local authority). (iii) For poor households: apart from received allowanced as regulated for the affected ones, further allowance for vulnerable groups shall be also received as follows: ï‚· Poor AHs who have to relocate or lose more than 10% of their agricultural landholding, poor AHs who lose less than 10% of their land but such land area is not enough to continue cultivation: will be assisted in cash equal to 30kg rice/person/month for a period of 24 months or in accordance with provincial policy; whichever is higher. ï‚· Other poor AHs: will be assisted in cash equal to 30kg rice/person/month for a period of 6 months or in accordance with provincial policy; whichever is higher. (iv) Other vulnerable groups: Female headed households with dependents, household with disabled persons, elderly without any source of support, poor households and ethnic minority households will get the same support given to poor households in accordance with the provincial policy or assisted in cash equal to 30 kg of rice per person per month for 6 months; ; whichever is higher. ï?¶ Other Allowances/Assistances 124. Incentive Bonus: All AHs who vacate the affected land immediately after receiving compensation and allowances will be given an incentive allowance consistent with each province. 125. AHs who will lose income sources will be entitled to take part in Income Restoration Programs. Rehabilitation measures like agricultural extension services, job training and creation, credit access and/or other measures as appropriate will be given to AHs losing income sources to ensure their livelihood could be restored to the pre-project level. 126. Apart from the assistances mentioned above, based on the actual situation, the Project may consider other assistances to secure life stabilization, culture, production and livelihoods of AHs. 127. Entitlement Matrix Table below presents details on impacts levels and compensation, assistance level for AHs by the Subproject’s works. Page 40 Table 20: Entitlement Matrix Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons I - Impacts due to permanent land acquisition 1.1. Agricultural land 1.1.1. Marginal impact 1.1.1.1. All AHs with For affected agricultural land:  Affected households to be 2 (<20% of landholding or LURC, or legalizable notified at least 90 days <10% for vulnerable group) (i) The Agricultural land fund of wards/commune in before land recovery by the (381 HHs) Phu Yen province is in available, therefore the Project. The remaining area of cash compensation will be applied instead of the affected plot is still “land for landâ€? compensation to affected  The owner of land will hand economically viable for use agricultural land area and assets on acquired land over the land within 20 days or meets the expected at 100% replacement cost; from the date District personal yield. Compensation Board fully (ii) If area of remaining land after acquisition is not pays compensation for land. enough to continue cultivation, the project will acquire the entire piece of land and  In the case that compensation would be implemented in cash for compensation “land for the affected agricultural land area and assets on landâ€? is applied, the project the acquired land at 100% replacement cost. will approval land compensation in the order (iii) Besides cash compensation for acquired land of priority from severely area as stipulated above, AHs will be entitled to affected households to livelihood restoration assistances as mentioned marginal affected in the RAPF. households. (iv) In the case of acquired land exceeding the limit  Land compensation must of local (except for land by inheritance, donation meet the following or receive transfer of land use rights) are not principles: a) equivalent to entitled to compensation for land but supported the affected land area but remaining values invested in such lands. The not exceeding the limit of Provincial People's Committee may consider local; b) same type of soil providing supports suitable to the local realities. (or equal productive Compensation for assets on the land acquisition, please capacity); c) satisfactory to 2 Classification of agricultural land is stipulated in Article 10, Land Law Page 41 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons refer to section 1.4, 1.5, 1.6, 1.7, 1.8 of this entitlement the AP; d) there is land use matrix. rights for the head of household and his/her Livelihood restoration assistance will be provided, wife/husband (if any); and including: allowance for production stabilization; e) non-payment of taxes, allowance for vocational training and job creation charges and fees for In addition to above, for agricultural, garden and pond land registration of land use adjacent to, but not included in the category of residential rights. If land compensation land, AHs will receive assistance according to the size is smaller or lower provisions of the PPC. quality, AHs will be entitled to compensation on cash equivalent the differences.  If area of land acquisition is different between actual measured and recorded on Land Use Rights Certificate (LURC), land acquisition will be compensated according to actual measured area unless otherwise occupied. 1.1.1.2. Land Users with (i) For the affected families are using land allocated temporary or leased rights by the State for purposes of agriculture, forestry to use land. or aquaculture (excluding special-use forest, protection forest) of Enterprises (SFEs), AHs are (20 HHs) not compensated for land. Cash compensation at full replacement cost for remaining values invested in such lands and affected assets attached to land. (ii) Users who are leased rights to use land on the basis of contracts with individuals, families, or organizations, other than the cases specified in Page 42 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons point (i) of this section shall be compensated compensation for remaining values invested in such lands and affected assets created on such land at full replacement cost. 1.1.2. Severe Loss ≥20% All AHs with LURC, or  Compensation and assistances as applicable for sub-item  Rehabilitation assistance or ≥10% for vulnerable legalizable 1.1.1.1 of this matrix, priority for compensation "land will be applied in case if the groups for land" if local land fund is available and AHs choice. option "land for land" (118 HHs) cannot be available. The  In addition, they will receive assistance in cash for forms of assistance should living rehabilitation as specified in item 3.1.2 of this be consulted closely with matrix. appropriate and effective measures of agricultural encouragement to assist the poor to restore their income generating capacity and income levels. 1.2. Residential land 1.2.1. Marginal loss 1.2.1.1. Legal and/or (i) All compensation for loss of land will be made  Affected legalizable land users in cash at 100% replacement cost persons/organizations to be  Loss of residential land notified at least 180 days without structures (40 HHs) (ii) Compensation for assets on the land acquisition, before land recovery by the please refer to section 1.4, 1.5, 1.6, 1.7, 1.8 of Or Project. this entitlement matrix.  Loss of residential land  The owner of land will hand with structures built 1.2.1.2. Land users who (i) AHs will not be compensated for land but will over the land within 20 days thereon, where the have temporary land use be compensated for assets on the land which from the date District remaining (non-acquired) right or leased rights to use they created at 100% replacement cost according Compensation Board fully land is adequate to land to sections 1.4, 1.5, 1.6, 1.7, 1.8 of this pays compensation for land. rebuild the structure entitlement matrix (reorganizing AHs)  If area of land acquisition is different between actual 1.2.1.3. AHs who have no (i) Compensation in cash for the remaining amount measured and recorded on right of land use or of leasing contract. Land Use Rights Certificate unlegalizable (ii) Compensation for assets on the land acquisition, (LURC), land acquisition Page 43 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons please refer to section 1.4, 1.5, 1.6, 1.7, 1.8 of will be compensated this entitlement matrix. according to actual measured area unless otherwise occupied. 1.2.1.4. Land users who (i) AHs will not be compensated for land but will have temporary land use be compensated for assets on the land which right or leased rights to use they created at 100% replacement cost according land to sections 1.4, 1.5, 1.6, 1.7, 1.8 of this entitlement matrix (ii) Compensation in cash for the remaining amount of leasing contract. (iii) Assistance in transportation allowance for the AHs in accordance with section 3.2.2 of this entitlement matrix 1.2.1.5. AHs who have no (i) AHs will not be compensated for land but will be  In case AHs falling into right of land use or assisted in cash by PPC. poor or vulnerable unlegalizable households, they will be (ii) Compensation for affected assets on land, refer to assisted (in cash or objects) section 1.4, 1.5, 1.6, 1.7, 1.8 of this Entitlement to ensure that AHs can Matrix remove to new location. (iii) AHs without any locations for living will be arranged PPC will make a decision of a minimum resettlement plot or an apartment in RS assistance level for these with form of installment or renting for living. households. 1.3. Houses, Partial impact Owners of affected (i) Compensation in cash for affected structures at structures structures created before 100% replacement cost. If house/structure is Unaffected portion of the the cut-off date regardless partially affected and the remaining structure is house is still viable for use of whether or not they have viable for continued use, the project will provide and could be remained from title to the affected land or Repair Allowance (please refer item 3.2.1 of this the technical viewpoints, permit to build the affected entitlement matrix). therefore, require no Page 44 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons relocation. structure (ii) Compensation and assistance will be paid in cash, without any depreciation of the structure (29 HHs) and without deduction for salvageable materials. (iii) The compensation is calculated according to the actual area affected. 1.4. Crops and Trees, 1.4.1. Loss of, or damage Owners of affected crops For annual and perennial standing crops, regardless of the  AHs to be notified at least livestock crops and/or trees and trees created before the legal status of the land, compensation will be paid to 90 days before land cut-off date regardless of households who cultivate the land, according to full recovery by the Project. The the legal status of the land replacement cost will be paid to the affected persons who crops which have been cultivate the land. For plants which have not been cultivated after cut-off date (423 HHs) harvested yet but can be brought to another location, the will not be entitled any transportation cost and the actual damage due to the allowances. transportation and re-planting must be compensated. 1.5. Loss of, or  Loss of, or damage to Owners/ users affected In the case of the affected households is equipped with damage other assets assets Such as telephone assets created before the telephone system, water meter, electric meter, cable TV, system, water meter, cut-off date regardless of internet access (subscription), well shall be compensated electric meter, cable TV, the legal status of the land according to unit price of installing new units offer service internet access… announcement or relocation costs due to service providers regulations 1.6. Public structures Loss of, or damage to Owners/ users affected  In cases where community infrastructure such as  For public structures assets assets created before the schools, factories, water sources, roads, sewage systems, directly related to people’s cut-off date regardless of medical centers, distribution/transmission, livelihoods and the legal status of the land communication and fiber cable are damaged and the developmental needs will community wishes to reuse them, the PPC, PMU will be carried out by the owners ensure that these are restored or repaired as the case may prior to the start of works. be, at no cost to the community.  Public infrastructure directly related to people’s livelihoods and developmental needs, such as irrigation canals, school, clinic, etc. will be (i) compensated at replacement cost, as determined through consultation Page 45 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons with the affected community; or (ii) restored/rebuilt with quality equal to or higher than the pre-project levels. II. ALLOWANCES AND REHABILITATION ASSISTANCE 2.1. For Impacts Marginal loss (<20% of Land users: i) have LURC  Allowance for Vocational Training, Job changing and on Agricultural Land land holding or <10% for or legalizable; and ii) Job Creation: The maximum support will be 05 times of vulnerable group) contracted by the State and agricultural land price of the same kind in the local land directly engaged in price list for the whole acquired area but not exceeding The remaining area of agricultural production the limit of local allocation. The level of specific affected plot is still support will be determined by Provincial People’s economically viable for use (381 HHs) Committee. or meets the expected personal yield.  Allowance for production rehabilitation: Households, individuals who are compensated by agricultural land will be, supported production rehabilitation, include: Support for plant varieties and animal breeds for agricultural production, services such as agricultural/forestry extension, plant protection, animal health, cultivation techniques, animal husbandry and professional techniques for manufacturing, business and commercial services. Form and level of specific support according to the provisions of Provincial People’s Committee. 2.1.1. Loss ≥20% or ≥10% Land users: i) have LURC Compensation and assistances as applicable for item 3.1.1  Price of rice is the market for vulnerable groups or legalizable; and ii) of this matrix. price at time of contracted by the State and compensation In addition, they also receive the following allowances: directly engaged in agricultural production Subsistence allowance (during transition period): in cash  PPC based on the actual equal 30kg of rice per person per month, in particular: situation will determine the (118 HHs) level of support. (i) AHs losing 20 - 70% of their agricultural landholding (or 10 - 70% for the poor and Page 46 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons vulnerable groups) will be provided with compensation of 6 months if they do not have to relocate, and 12 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided for a maximum of 24 months; (ii) AHs losing more than 70% of their agricultural landholding will be assisted at the above rate for a period of 12 months if they do not have to relocate, and 24 months in case of relocation. In some special cases, in extremely difficult areas, the compensation may be provided up to a maximum of 36 months; (iii) Households affected by loss of less than 20% of land, where the remaining land is rendered unviable for continued use, will be assisted with the above support plus any additional support as determined, for a period of 12 months. 2.2. For Impacts on Marginal impact Owners of affected  Reparation Allowance: If house/structure is partially Residential Land house/structure created affected and the remaining structure is viable for  House/structure is before the cut-off date continued use, the project will provide a repair partially affected, the regardless of the legal allowance to enable AHs to restore it to former or better remaining can continue to status of the land (2 conditions. The level of specific support will be use HHs) determined by Provincial People’s Committee. 2.3. For public land Land acquisition of public Communes, and towns For land acquisition of public land funds of communes or  Financial assistance will be land funds of communes, manage acquired land townships: assistance level is 80% price of same-type included in the annual or townships agricultural land in the price list issued by the PPC. budget estimates of the (12 commune/town PCs) CPC. It is used to invest construction of infrastructure projects, used for public interest purposes Page 47 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons of communes, wards and townships as stipulated in Article 24 of Decree 47/2014/ND-CP. 2.4. Other 2.4.1. Allowance / Affected vulnerable groups  For landless households: assistance through provision of  The vulnerable groups were Allowances/ Assistance targeted to regardless level of impact an apartment that AHs can either pay in installment to identified in the “Glossaryâ€? Assistances Vulnerable Households buy or rent it for living (depending on the choice of the part. (34 HHs) AHs). Additional assistance will be considered if necessary to ensure the affected people have inhabited.  Price of rice is the market price at time of  Social Policy Relocated Households that include heroic compensation mothers, heroic armed force, heroic labor, war veterans, wounded or dead soldiers families will be provided with support as regulated by the (to be certified by local authority)  For poor households: apart from received allowanced as regulated for the affected ones, further allowance for vulnerable groups shall be also received as follows: a) Poor AHs who have to relocate or lose more than 10% of their agricultural landholding, poor AHs who lose less than 10% of their land but such land area is not enough to continue cultivation: will be assisted in cash equal to 30kg rice/person/month for a period of 24 months or in accordance with provincial policy; whichever is higher. b) Other poor AHs: will be assisted in cash equal to 30kg rice/person/month for a period of 6 months or in accordance with provincial policy; whichever is higher.  Other vulnerable groups: Female headed households with dependents, household with disabled persons, elderly without any source of support, poor households and ethnic minority households will get the Page 48 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons same support given to poor households in accordance with the provincial policy or assisted in cash equal to 30 kg of rice per person per month for 6 months; whichever is higher. 2.4.2. Incentive Bonus AHs move out of the Incentive Bonus: All AHs who vacate the affected land affected areas on time immediately after receiving compensation and allowances will be given an incentive allowance depending on capacity (423 HHs) of each locality. 2.4.3. Additional  AHs who will lose income sources will be entitled to  Income and Livelihood allowances/supports (if take part in Income Restoration Programs. Restoration Programs will necessary) Rehabilitation measures like agricultural extension be designed in combination services, job training and creation, credit access and/or with current programs of other measures as appropriate will be given to AHs the locality and with the losing income sources to ensure their livelihood could assistance of livelihoods be restored to the pre-project level. experts.  Apart from the assistances mentioned above, based on  The programs will target the actual situation, the Project may consider other the needs of both men and assistances to secure life stabilization, culture, women production and livelihoods of AHs. III. TEMPORARY IMPACTS DURING CONSTRUCTION 3.1. For temporary Temporary loss of Owners/ users affected  In case the project need temporary construction plan, the loss of land/assets land/assets on affected land and/or assets created PMU rents the land of the owners complying with on affected land land where to be used as regulations stipulated by the Civil Law. temporary construction plan (60 HHs) 3.2. For impact Damages caused by Owners/ users affected  Damaged property will be restored to its former  In case of impacts on arising from the contractors to private or land and/or assets created condition by contractors, immediately upon completion livelihoods of AHs, the Page 49 Application Implementation Type of Loss/Impacts Entitlements Arrangements Level of Impact Eligible Persons construction public structures on affected land of civil works contractors, construction units have to agree with the  Under their contract terms and conditions, the households on payment for contractors will be required to take extreme care to disruption of business. avoid damaging property during their construction activities. Where damages do occur, the contractor will be required to repair the damage and may also be required to pay compensation to the affected families, groups, communities, or government agencies at the same compensation rates that are applied to all other assets affected by the Project IV. OTHER IMPACTS 3.3 Other impacts Any other impacts that Individuals, organizations  In case the Project causes restriction of access to may be identified during in the project area resources or residents’ establishments, such households implementation will be received necessary additional compensation amount or allowances.  Entitlements to compensation and other assistance could be provided in accordance with the compensation policy.  Secondary impacts on production and business or AHs isolated from access to resources temporarily have to be compensated and supported in accordance with OP4.12 of WB. Page 50 7. ELIGIBILITY CRITERIA AND ENTITLEMENTS 7.1. Affected people (AP) 128. Project affected people are those who are directly affected by the Project through the loss of land, residences, other structures, business, assets, or access to resources, specifically: ï‚· Persons whose agricultural land will be affected (permanently or temporarily) by the Project; ï‚· Persons whose residential land/houses will be affected (permanently or temporarily) by the Project; ï‚· Persons whose leased houses will be affected (permanently or temporarily) by the Project; ï‚· Persons whose businesses, agricultural activities, occupations, or places of work will be affected (permanently or temporarily) by the Project; ï‚· Persons whose crops/ trees (annual and perennial) will be affected in part or in total by the Project; ï‚· Persons whose other assets or access to those assets will be affected in part or in total by the Project; and ï‚· Persons whose livelihoods will be impacted (permanently or temporarily) due to restriction of access to protected areas by the Project. 7.2. Identification of vulnerable groups or households 129. According to the definition of vulnerable group/household in the Project’s Resettlement Policy Framework and the definition of beneficiaries of social sponsorship in Decree No. 67/2007/NÄ?-CP dated 13th April 2007 and the Decree No. 13/2010/NÄ?-CP dated 27th February 2010 by the Government on support policies for beneficiaries under social sponsorship, the Project’s vulnerable HHs/groups shall include: ï‚· Poor and near poor households as identified by MOLISA and according to local regulations; ï‚· Poor landholders that have limited productive land (this will be determined by the minimum amount of farm land needed to be a viable farmer in the project area); ï‚· Ethnic minority Households (if any); ï‚· Mentally and physically handicapped people or people in poor physical health; infants, children and women without assistance; ï‚· Poorest women-headed households or women-headed households with no other support; ï‚· Other PAP identified by the project management unit and who may not be protected through national land compensation or land titling; or ï‚· Any additional groups identified by the socio - economic surveys and by meaningful public consultation. 130. These are special groups that may suffer from inappropriate impacts or are exposed to the risks of further impoverishment from resettlement. Hence, the Compensation Board and the Project Management Unit, during the process of devising compensation, assistance and resettlement methods, must co-operate with the People's Committees of ward/communes to survey and update the list of vulnerable groups or HHs in order to provide timely and proper assistance. 7.3. Eligibility 131. The eligibility for entitlement to compensation is determined by asset ownership criteria as follows: (i) Those who have formal legal rights to land (including customary and traditional rights recognized under the laws of the country. In the consideration of such cases, it is also useful to document how long AHs have been using the land or the assets associated with it); Page 51 (ii) Those who do not have formal legal rights to land at the time the census begins but have a claim to such land or assets provided that such claims are recognized under the laws of the country or become recognized through a process identified in the RAP; (iii) Those who cannot legalize the right to land use in accordance with Vietnamese laws or have no recognizable legal right or claim to the land they are occupying. 132. Persons covered under item (i) and (ii) are provided compensation for the land they lose, and other assistance as regulated in the Resettlement Policy Framework. Persons covered under (iii) are provided resettlement assistance in lieu of compensation for the land they occupy, and other assistance, as necessary, to achieve the objectives set out in this policy, if they occupy the project area prior to a cut-off date established by the borrower and acceptable to the World Bank. Persons who encroach on the area after the cut-off date are not entitled to compensation or any other form of resettlement assistance. All persons included in (i), (ii), or (iii) are provided compensation for loss of owned or used assets other than land. 133. As defined, a cut-off-date is the date that a State competent agency issues the announcement of land acquisition before detailed measurements (Point 1, Article 67 of 2013 Land Law). However, to build a basis for designing this RAP, 30th March 2017 (completion date of IOL) is defined as the temporary cut-off-date to identify the extent of impact due to land acquisition. AHs and local communities have been informed about this cut-off date and information related to the Project so that they can work out their own production/investment/construction plans, avoiding damages or losses otherwise caused by a lack of information on the Project. 7.4. New HHs after the cut-off date 134. Those households splitting from larger families after the cut-off-date who meet the following conditions shall be recognized as eligible AHs:  Households with multiple generations or many couples living together on a plot of acquired land who are eligible to separate households;  Endorsement by the District authority with verification of commune People’s Committee that the household has split;  Newly born children, spouses of persons named in the household registration books, people who have completed military service, and people who have just returned from schools to live with the AHs from the cut-off date to the date of compensation payment will be entitled to compensation and support outlined in the Resettlement Policy Framework 135. In case the Gov regulations will be changed and there will be some entitlements, which are better than the ones described in the RPF, these better entitlements will be applied for the affected people (if possible). 8. LIVELIHOOD RESTORATION PROGRAM 8.1. Income Restoration and Assistance Policies 136. When implementing the project, apart from the construction of works bearing significant socio-economic meaning, the concern about how project-AHs could have normal life is the ensured project sustainability. The objective of income restoration program is to aid subjects-households incurring income damages due to project implementation: (i) changed occupations as a result of loss of agricultural land and (ii) terminated/affected production and business as a result of loss of premises, means of production et. Incomes shall be recovered the same as those before project implementation, or incomes shall be increased further and make sure that AHs will adapt themselves to new conditions at the soonest. 137. The project ensures full compensation and assistance policies at replacement cost for the affected land, buildings and assets. Besides, policies to support income restoration for those AHs are guaranteed and stated fully in the Resettlement Policy Framework of the Project. Page 52 8.2. Income Restoration Measures 138. From experiences, if the vulnerability due to resettlement is not mitigated, the outcomes of development projects regularly lead to severe environmental and socio-economic problems: As for affected households in consequence of agricultural land acquisition (particularly affected households that lose 20% of total agricultural area and vulnerable households), production systems are destroyed; people must face the loss of production tools, for their production assets are affected or they have no alternative income sources. As for displaced or resettled households, their income sources are affected in several first months after displacement if their income is based on land or business site. 139. From the characteristics of the Project, the livelihood restoration measures for affected households are being developed through coordination by the PMU of Phu Yen province's agricultural and rural development works, consulting units, local authorities and relevant agencies such as the Department of Labor, War Invalids and Social Affairs, Vocational Training Center and Job Center of the province, Local Policies Bank Appropriate by support programs and income restoration based community participatory approach. 140. Thus, a livelihood restoration program with policies and restoration measures will focus on the following directions: vocational training and job creation; Support for vulnerable groups; Financial support (financial support for households’ self-business; self-employment), etc. Below are specific income restoration measures: 8.2.1. Assistance for job changing and employment service 141. Phu Yen project will cause land acquisition, including agricultural land, affecting lives of households, especially farmers. Thus, in addition full compensation policies for land, affected works and assets as replacement cost, supports are also provided: 142. Assistance for domestic vocational training: Vocational consultancy, free job introduction at Employment Services Center under Phu Yen Department of Labor, Invalids and Social Affairs; 143. Support for contractual abroad working: - Support 100% tuition fee of vocational training and learning foreign languages and fostering necessary knowledge; - Support 100% of costs for heath examination, passport, visa and judicial records before going to work abroad; - Support for daily meals during the studying time; - Support for round-trip tickets from residence to the studying place in a distance of over 15km; - Also, support loans with preferential interest rates from the Bank for Social Policies to cover the necessary expenses for fixed-term abroad working. - In addition, trainees will be able to borrow loan at preferential interest rates from the Social Policy Bank to cover necessary expenses for working abroad for a definite period of time. 144. For households affected by agricultural land acquisition, these households will be assisted 4 times (400%) of agricultural land cost for the entire acquired agricultural land area. The Project will give priorities for capable people, including men and women, during the project construction and operation: The Project will consider and give priorities to members of relocated households to work as construction workers for the work items under the project. 145. In addition, Phu Yen province also has Employment Services Centersdirectly under Phu Yen Department of Labor, Invalids and Social Affairs which are operating very effectively in training and job introduction for workers in the province. Namely, Phu YenEmployment Services Center (No. 118, PhanDinhPhung road, Phu Yen city. Tel. 055.3713357). 146. Implementation arrangements: Along with the information disclosure on projects information relating to compensation and assistance and resettlement (if any) and site clearance, the Project will also incorporate to disseminate information on training programs to affected persons. 8.2.2. Training on development of agricultural, livestock programs Page 53 147. Through consultations with the commune authorities in the project area, currently, the project communes/wards have organizing training courses on agricultural development programs co- organized to be developed by Agricultural Extension Center, the cooperatives and the Divisions of Labor, Invalids and Social Affairs of the districts. Hence, the income restoration program for affected households due to the loss of agriculture in the project area will be proposed in combination with the local vocational training programs for rural workers. Training courses include: (i) Training in veterinary: care and prevention techniques for cattle and poultry; (ii) Technology transfer: growing chili, planting industrial trees and participating in some integrated programs with theme “Promotionof the role of women in cooperative economic development, the core is cooperative in the period 2017- 2021â€?; and (iii) Positively expanding some prestigious programs for women in the affected households such as: Supporting vocational training including tailoring, knitting, cooking and improving skills for some traditional crafts at locality. 148. In addition, the program will be applied to those who in the working age are directly affected on agricultural production and have the demands for vocational training, job changing, job introduction, job creation loans under Decision 52/2012/QD-TTg of the Prime Minister, especially: 149. Vocational training assistance: Vocational training allowance includes cost of taking the course: (i) short-term vocational courses (elementary level or vocational training time less than 3 months) under the GoV’s Project on Vocational Training for Rural Workers until 2020; (ii) Vocational training at intermediate and college levels. Vocational training schools in Phu Yen province include: + Vocational School in Phu Yen Province Address: Lien Hiep 1 hamlet, Son Tinh town, Son Tinh district, Phu Yen province + Vietnam - Korea – Phu Yen Vocational Training College Address: 236 Hoang Hoa Tham – Quang Phu town –Phu Yen city + Phu Yen Technical – Industrial Vocational Training Center Address: 74 Le Loi, Chanh Lo, Phu Yen city, Phu Yen 150. Support credit loans for pupils and students in accordance with the current regulations. As Decision no. 157/2007/QD-Ttg dated 27/09/2007 by the Prime Minister on maximum loan for a pupil, student of 800,000 Vnd/month (8,000,000 VND/ year). Specific loan level for each pupil, student is determined based on tuition, domestic cost and loan demand of borrower, however, maximum loan is or less than 800,000 VND/ month. In addition, pupils, students included in policy households or difficult households can be exempted from tuition. Domestic job creation support: Consulting services on apprenticeship, Employment Services will be provided free of charge at the Job Introduction Center directly under Phu Yen Department of Labour - Invalids and Social Affairs. 8.2.3. Credit Loan Support 151. In the recent years, the Vietnam Bank for Social Policy (VBSP) – Phu Yen provincial branch regularly coordinated with other agencies, political and social organizations implementation of credit programs to provide preferential loans to poor households and other policy objects. So, many households have escaped from poverty, appearance of hamlets in Phu Yen is changing and prosper. 152. Currently, Phu Yen social policy bank has been implementing 05 credit programs including: loan for poor households, employment solutions, labor export, pupil-student, clean water- rural sanitation. In addition, there are loan programs for production development, program 135, loan as the program 22 of GoV, loan for maintenance, repairing of irrigation works and so on. 153. Thus, the livelihood restoration program, after receiving straight feedbacks and comments for demands and expectations of households, will basically meet the desires/demands of the households. To maximize the effectiveness of the program, the communication of the project to the people will be continued to provide information about the project as well as the income restoration programs during the project implementation and later resettlement phases. Page 54 154. In addition to the above-mentioned measures, Phu Yen PPC will take additional support measures (if necessary) to assist households affected by land acquisition for the project to restore their life. 8.2.4. Support for Vulnerable Groups 155. These are special groups that might suffer disproportionately impacts or might suffer risks of impoverishment due to impacts of resettlement. The group includes poor households, policy families, families deserving for the revolutions, the single elder and woman-headed households with dependents. They may be people who can hardly be competitive on the labor market when their livelihoods depend on the land area acquired/affected by the project. Therefore, the special support programs for these groups should be carried out. These programs may coincide with the general assistance programs to all households affected by the project but there are certain priorities for vulnerable households. 156. Specific support policies include: - Giving priority to vocational training or job creation. - Food or material assistance for extremely disadvantageous households without labor capacity (combined with the social welfare policies of locality) + For poor households: in addition assistance as regulations, households affected with land will be assisted in cash, equivalent to 30kg of rice/person/month within 24 months or as policies of the province, higher assistance level will be applied. + Other vulnerable groups: Women headed households, households with the disable, policy households, households with members benefited regularly from social allowanceswill be additionally assisted from 3 – 5 million VND/household. 157. Table below summarizes IRAPs for AH by EFRD project- Phu Yen subproject Table 21: Income Restoration Program for AHs Proposed Income Implementation Cost Implementation No. Participants Restoration Agencies Estimate Plan Measures 1 Support for Households are affected with Site clearance TBA Quarter III/2017 vocational agricultural land and forestry Compensation training and land Committee or districts vocational LFDC guidance by cash 2 Training on All affected households Agricultural Extension 10.000 From Quarter development of Center, the cooperatives USD III/2017 – agricultural, and the Divisions of Quarter III/2018 livestock Labor, Invalids and programs Social Affairs of the districts 3 Job introduction All affected households Employment Service TBA From Quarter Center of Phu Yen III/2017 – province Quarter III/2018 4 Support for - Poor households Site clearance TBA Quarter III/2017 vulnerable Compensation - Policy households households Committee or districts - Ethnic minorities LFDC - Households with the disable - Households with the elderly Page 55 Proposed Income Implementation Cost Implementation No. Participants Restoration Agencies Estimate Plan Measures - Households with women- headed with independents 5 Loan support All affected households Social Policy Bank of TBA From Quarter Phu Yen province III/2017 – Quarter III/2018 8.3. Cost estimate for Income Restoration Measures 158. Results of consultations with affected households showed that households will continue to produce on the remaining land area and shared the opinion that the Project should: (i) support households to maintain their lives; and (ii) study compensation plan, provide reasonable support to the people satisfactorily. For 118 severely affected households who lost 20% of their agricultural land area for the subproject’s items (or 10% for vulnerable group), when being asked about their needs/desires/ job options after land acquisition, results are as follow: i) there are 49 households requested to be supported capital and farming techniques to continue their farm work on their remaining land area; 31 householdsrequested to be supportedcapital and farming techniques by women. ii) 29 households wished to be supported by the project in vocational training and job introduction for members at population age without stable employment, in which 19 households requested to be supported job finding appropriately; iii) 40 households wished to be training on development of agricultural, livestock programs, in which 21 households wised their women to be involved in these programs. 159. The total cost estimate of income restoration program for Ahs in subproject Phu Yen province about VND 475,200,000 equivalent to 20,934USD. This budget will be provided by Phu Yen PPC through counterpart fund. Table 22: Cost estimate for Income Restoration Program for AHs Time USD (1 USD = No Action Unit Qty Unit cost VND (Month) 22.700 VNÄ?) 1 Agriculture component 153,600,000 6,767 Training classes. 03 classes - givespecial priority in Class 12 3,000,000 3 108,000,000 4,758 training for women Support from Agriculture - Staff 1 7,600,000 3 22,800,000 1,004 center Support from Farmer's - Staff 1 7,600,000 3 22,800,000 1,004 Union 2 Training component 261,600,000 11,524 Short term training 6 months, in which, 03 classes - Class 12 3,000,000 6 216,000,000 9,515 give special priority in training for women Support from Vocational - Staff 1 7,600,000 6 45,600,000 2,009 Training Center 3 Meeting Session 12 5,000,000 60,000,000 2,643 Page 56 Time USD (1 USD = No Action Unit Qty Unit cost VND (Month) 22.700 VNÄ?) 4 Total IRP 475,200,000 20,934 9. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 9.1. Objectives of Public Consultation and Information Disclosure 160. Disseminating information to people affected by the project and the involved agencies is an important part in the work of project preparation and implementation. The consultation with affected persons and their active participation will reduce the potential conflict and risk of slowing the project. This allows the project to design a resettlement and rehabilitation program as a general development program, in accordance with the needs and priorities of affected people and therefore, maximizes economic and social efficiency of investment. Objectives of the information disclosure and public consultation include: a) To ensure that all affected persons and stakeholders will be involved in the planning and making decisions on involuntary resettlement related to them; b) Minimize the adverse impacts caused by involuntary resettlement; c) Avoid possible conflicts during project implementation. 161. The AHs need to be fully informed and consulted closely on selected areas for resettlement and compensation and assistance plans. Consulting affected persons is the starting point for all activities related to resettlement. People affected by resettlement may fear that they might lose their livelihoods and communities, or fear they do not prepare well for the complex negotiations on entitlements. AHs will be involved in the Resettlement Action Planning and management to help decrease fears and give opportunities for them to participate in making decisions on what will effect on their lives. The implementation of resettlement without consultation may lead to an inappropriate strategy and ultimately ineffective. If the affected person is consulted promptly, all conflicts related to the project can be resolved timely. 162. The following points should be focused on encouraging the relevant agencies involved in the consultation process of the Project: a. Identify and encourage all relevant agencies, and especially the affected persons participate in the consultation and participation; b. Develop strategies for relevant agencies to participate in the planning, monitoring, implementation and evaluation; c. Explain the strategy and details for the dissemination of information, and establish procedures to allow the affected persons to negotiate their entitlements; d. Attractive relevant agencies to participate in making decisions at different stages of project implementation (e.g. compensation mechanism, consulting the affected persons is consult about the compensation progress and implementation, etc.); e. Set up a schedule for activities such as providing information, compensation level and the method and establish interests, location and relocation plan; f. Establish grievance redress procedures 9.2. The Process of Consultation and Participation 163. Responsible agencies: AHs will be notified by Phu Yen PMU on the responsibility of organizations/ agencies and local authorities in charge of resettlement and the names and functions of the local government staff along with numbers telephone, address and working time. Page 57 164. Implementation process: The AHs will be notified of the process estimated important resettlement activities and building can only begin when the relocation is implemented and finished and the affected persons have to get out of the project area. It is necessary to emphasize that after receiving compensation for their lost property, AHs will soon relocate as stipulated. The CRCs at all levels will be provided with maps, diagrams and statistics concerning the extent of impacts and the implementation plan. 165. Disclosure of information: The RPF will be posted for affected persons and community in public places such as Phu Yen PMU, District/City/Ward/Commune People's Committees and even at the community household of the residential area. 166. After RAP approved by the PPC, RAP will be disseminated in public places such as Phu Yen PMU, the District/City/Ward/Commune People's Committees, and on the website of the World Bank in Hanoi and Washington D.C. 9.3. Public Consultation 167. During the project preparation, information disclosure and public consultation aims to collect information to evaluate resettlement impacts by the project and give out recommendations of optimal options. This will minimize or eliminate potential negative impacts on the residents and cope with problems arising during the implementation process. 168. The methods of information disclosure and public consultation include participatory rural appraisal (PRA) and consultation with stakeholders through visits to affected households, public meetings, group discussions, focus group discussion and socio-economic survey. 9.3.1. Public Consultation during the Preparation Phase 169. During project’s preparation stage, information disclosure and public consultation aim to gather information for assessing project resettlement impacts and clarify recommendations on possible alternative technical options. This will reduce and/or mitigate potential negative resettlement impacts on local population and to proactively address issues or problems that may emerge during the implementation. AHs have been consulted on the impacts and measures taken to minimize the negative impacts and enhance the entitlements to the community. Local authorities have also been advised of agreements and commitments to implementing the resettlement policy. 170. Phu Yen PMU, with the assistance of resettlement consultants, conducted consultations on compensation and resettlement with relevant stakeholders, including officials from the ward/ commune People's Committees, the leaders of the hamlets and the local population in the affected area. 171. Early March 2017, Phu Yen PMU sent the Dispatch and Public Consultation Plan to the project wards/communes to request the local authorities to coordinate and invite affected households to attend the public consultation meetings to ensure their full and effective participation. 172. In the Mid-2017, public consultation meetings were carried out at the project wards/communes to notify and consult local people and community on the project’s policies and their entitlements. The specific programs are summarized below: Table 23: Public Consultation on Land Acquisition and Resettlement N No. of No. of o Place Time participan female Participants Contents . ts Representatives of Head Office of PC of Hoa local authorities and 13h – 10 4 1. Introduction about 1 Thang commune, Phu unions: Farmer April 3 the project Hoa district association, Women’s (objectives, locations, Union, Fatherland scale and plan of the Page 58 N No. of No. of o Place Time participan female Participants Contents . ts Front, Youth’s project, etc.); Head Office of PC of An 7 - 2 8h – April Union, etc. 2 My commune, Tuy An - Technical proposal 4 district Representatives of of the project; work affected households items to be 3 Head Office of PC of An 22 12 of project implemented in 9h– April wards/communes. Hiep commune, Tuy An Representatives of 4 district Phu Yen PMU - Policies related to compensation, Head Office of PC of An 18 7 Representatives of 11h– April support and site 4 Linh commune, Tuy An Consultant 4 clearance/resettlemen district t of GoV, WB and the Project. Head Office of PC of An 8 6 13h – 2. Public consultation 5 Xuan commune, Tuy An about resettlement April 4 district issues and options to arrange resettlement Head Office of PC of An 14 5 for displaced HHs; 15h – 6 Dinh commune, Tuy An April 4 district Head Office of Chi Thanh 17h – 17 8 7 town PC April 4 Head Office of La Hai 6 2 7h30 – 8 town PC, Dong Xuan April 5 district Head Office of Xuan Son 18 7 9h – April 9 Ba CPC, Song Cau 5 township Head Office of PC of 6 2 11h – 10 Xuan Tho 2 commune, April 5 Song Cau township Head Office of PC of 10 4 13h – 11 Xuan Binh commune, April 5 Song Cau township Head Office of PC of 7 3 15h – 12 Xuan Loc commune, April 5 Song Cau township (Source: Resettlement Survey, March 2017) 173. Results of the public consultation meetings with the local people showed that in the project area, people actively expressed their opinions on implementation of the project items. Consultation results are shown in the table below: Page 59 Table 24: Results of public consultation meetings with prioritized work items under the Subproject No. Components/Works Public opinions Feedback from the Project Agreed Actions I Irrigation Subcomponent 1 PY-01-XL: Ba river embankment, section across Phong Nien hamlet, Hoa Thang commune - Local authorities and - The project partner will people agree with the receive comments from the project and expect the villagers and make the plans project to be which affect the households at implemented soon. lowest level as possible. - It is recommended - Prior to conducting work that the project team at locality, the project implement closely to implementation unit will ensure the quality receive a notification as well progress of the project, as a detailed work plan to send promptly implement the to the locality. project before the flood All participants in Ba river embankment, season. - The compensation policy consultation in the section across Phong for AHs will be implemented project wards a - In addition, there in accordance with the policies Nien hamlet, Hoa agreed to support should be a clear plan for of the Government of Vietnam Thang commune the implementation prior notification to local and donors. In addition to of the project. authorities before compensation for land and implementation. assets on land, AHs will - It is necessary to receive additional support publicize early the such as subsistence, job compensation and change and so on. assistance policy to - The project unit would households so that they like the local authorities and get the compensation people to cooperate and plans and have the support for the project so that opportunity to choose. the project can be completed on schedule. Repairing, rehabilitation of irrigation weir system, Da stream embankment in An Hiep commune, 2 repairing, rehabilitation of An Hiep – An Linh road, Tuy An district and Ky Lo river embankment, section across Ngan Son bridge - Prior to conducting work - People expect the at locality, the project project to be implementation unit will send 100% of delegates implemented soon. a notification as well as a participating in the detailed work implementation project consultation - AHs completely plan to localities. meetings in agreed to participate in localities agreed to site clearance, site - The compensation policy Repairing, support the project clearance areas are for AHs will be implemented a, rehabilitation of implementation. mainly riverbank land in accordance with the policies irrigation weir system AHs are willing to of the Government of Vietnam - It is necessary to participate in site and donors. In addition to inform the plan and the clearance for the compensation for land and progress of the project project assets on land, AHs will implementation so that implementation. receive additional support AHs are informed and such as subsistence, job arrange suitable crops change and so on. - The project unit would Page 60 No. Components/Works Public opinions Feedback from the Project Agreed Actions like the local authorities and people to cooperate and support for the project so that the project can be completed on schedule. - People expect the project to be - Prior to conducting work 100% of delegates implemented soon; there at locality, the project participating in the is about 1.2 ha of land implementation unit will send project consultation area of landslide in An a notification as well as a meetings in Hiep commune each detailed work implementation localities agreed to Repairing, year. plan to localities. support the project b, rehabilitation of An - AHs completely - The project unit would implementation. Hiep – An Linh road agreed to participate in like the local authorities and AHs are willing to site clearance, site participate in site people to cooperate and clearance areas are clearance for the support for the project so that mainly riverbank land, project the project can be completed there is a section of implementation. on schedule. affected agricultural land, and - Prior to conducting work 100% of delegates at locality, the project participating in the - Limit effects as well as implementation unit will send project consultation impacts on environment, a notification as well as a meetings in especially in residential detailed work implementation localities agreed to An Hiep stream sites plan to localities. support the project c, embankment - Ensure traveling - The project unit would implementation. roads for local people, in like the local authorities and AHs are willing to harvesting and people to cooperate and participate in site agricultural production support for the project so that clearance for the the project can be completed project on schedule. implementation. - Prior to conducting work 100% of delegates at locality, the project participating in the - There should be a implementation unit will send project consultation temporary bridge for a notification as well as a meetings in local people during the Ky Lo river detailed work implementation localities agreed to construction period embankment, section plan to localities. support the project d, - Ensure environment across Ngan Son - The project unit would implementation. bridge, Tuy An district and limit impacts during AHs are willing to like the local authorities and the process of material participate in site people to cooperate and transportation to clearance for the support for the project so that construction site. project the project can be completed on schedule. implementation. II Transport Subcomponent 3 PY-03-XL: Repairing, rehabilitation of the provincial roads.643, 650, 642 Repairing, - Local authorities and - Prior to conducting work - 100% of rehabilitation of the people support the at locality, the project delegates a, provincial roads.642 project implementation implementation unit will send participating in the section from Km1 + a notification as well as a project consultation 607.00 to Km13 + detailed work implementation meetings in Page 61 No. Components/Works Public opinions Feedback from the Project Agreed Actions 789.75 plan to localities. localities agreed to support the project - The project unit would implementation like the local authorities and people to cooperate and support for the project so that the project can be completed on schedule. - Prior to conducting work 100% of delegates at locality, the project participating in the - Ensure water supply implementation unit will send project consultation and drainage for local a notification as well as a meetings in Repairing, people detailed work implementation localities agreed to rehabilitation of the - In case workers plan to localities. support the project b, provincial roads.650 living in long-term and - The project unit would implementation. with length of L = they need like the local authorities and AHs are willing to 99.61m accommodation people to cooperate and participate in site conditions to ensure clearance for the support for the project so that security for local people project the project can be completed on schedule. implementation. - During the - Prior to conducting work 100% of delegates construction period, at locality, the project participating in the roads as well as safety implementation unit will send project consultation should be ensured for Repairing, a notification as well as a meetings in local people. rehabilitation of the detailed work implementation localities agreed to provincial roads. 643 - During the plan to localities. support the project c, transportation process, section from Km3 + - The project unit would implementation. 223.62 to Km3 + environment should be AHs are willing to like the local authorities and 302.60 ensured, especially participate in site people to cooperate and residential site should be clearance for the support for the project so that covered and ensured project the project can be completed impacts on roads of other implementation. on schedule. roads 4 PY-04-XL: Repairing of the operation and management road of Xuan Binh reservoir - Control flow for local people, especially water from stream, forests 100% of delegates - Prior to conducting work participating in the - Assist compensation at locality, the project project consultation for local people (some implementation unit will send meetings in Repairing of the poor households and a notification as well as a localities agreed to operation and households with the detailed work implementation support the project management road of elderly, disables should plan to localities. implementation. Xuan Binh reservoir be assisted additional - The project unit would AHs are willing to with total length of L = allowances. like the local authorities and participate in site 9,783.95m - Limit impacts of people to cooperate and clearance for the environment during the support for the project so that project materials transportation the project can be completed implementation. process on schedule. - Transportation vehicles should be covered fully. Page 62 174. After the survey, the meeting with the local authorities for reporting on all survey/consultation results were organized. At the same time, other related information, advantages and disadvantages, experience lessons and proposed measures were discussed and addressed in the Resettlement Action Plan and established monitoring index and continue implementing at next steps. 9.3.2. Consultation during the Project Implementation 175. During the project implementation, the PMU, with the support from the Consultant, shall undertake following tasks: (i) Providing information to relevant agencies at all levels throughout training workshops. Provide detail information on the project policies and implementation procedures. (ii) Organizing information dissemination and consultation to all affected persons during the project implementation. (iii) The CRC carries out DMS, updates the compensation rates in the updated RAP and reconfirms the scale of land acquisition and impacts on properties based on the results, consultation to affected persons, develop and complete the compensation plan for each affected household. (iv) The compensation plan finalizes affected assets and compensation entitlements of households, which must be signed by affected persons to demonstrate their concurrence with the evaluated results. Any questions of affected persons on the content of the compensation plan must be recorded at this time. (v) A letter/questionnaire about resettlement options will be given to all PAPs entitled to relocation (a) to inform them about resettlement options (a clear explanation of the consequences of choosing each option will be given), (b) to request that PAPs confirm their choice of resettlement option and their preliminary confirmation of resettlement site location, and (c) to propose the PAPs to clarify services that they are using such as education/health/market and distance of access to those services to ensure development of the future infrastructure services. (vi) Consulting affected people about their desires for the rehabilitation plan. This will be applied for severely affected and vulnerable people. The DCRC will notify affected persons the plan and their entitlement to receive technical assistance before requesting them to make clear their desire on the rehabilitation support. 176. Public Consultation: During the preparation of the detailed compensation plan/training and job changing plans, Phu Yen PMU or City/District CRC will organize community meetings at each affected commune to provide the PAPs with additional information and give them an opportunity to participate in the open discussions on resettlement policy and procedures. Invitations will be conveyed to all affected persons before the meeting is held in such place. The purpose of this meeting is to clarify the information updated at the meeting time and create opportunities for affected people to discuss the concerned issues and clarify information. In addition to notification letters addressed to affected people, other measures of information dissemination to them and the public in general like posters in prominent places in the headquarter of communes/districts where the affected people are living by means of local radio and newspapers. Both men and women of affected households as well as community members who are interested in the Project are encouraged to participate. In the meeting, there will be explanations about the Project, rights and entitlements of households, and the meeting will be an opportunity to raise related questions. Similar meetings will be organized periodically throughout the project cycle. The consulting organization must be established record of certified CPC committee representing Vietnam Fatherland Front and communal representatives who have acquired land. 177. Public meetings: Prior to the beginning of the detailed design, a public meeting will be held in each ward/commune to provide PAPs with additional information and an opportunity for open discussion about resettlement policies and procedures in each affected commune. A letter of invitation will be sent to all PAPs before the meeting in their area. This meeting is intended to clarify information that has been given to date and to provide PAP with the opportunity to discuss issues of concern and obtain clarification. In addition to a letter informing the PAP, other means will be used to Page 63 inform PAP and the general public such as posters in prominent locations in the communes and wards where PAP are currently residing. Radio and newspapers will also be used to convey information and elicit response. These announcements and notices will advise the time and location of the meeting, and who can attend. Both men and women from affected households will be encouraged to attend, as well as other interested community members. The meeting will explain the Project, and households’ rights and entitlements. There will be opportunities to ask questions. Such meetings will be conducted periodically during the Project implementation. 178. Relevant information will be given to the PAP at the meetings (verbally, graphically, and/or on printed leaflets). Leaflets will be available at offices of the project district/city/commune/wards. The meetings are proposed to be implemented according to the following forms: (i) Explanations given verbally and in visual format, including written information and drawings of the proposed design for the different works supported by the Project. (ii) Adequate opportunities will be provided for PAPs to respond with questions and comments. PAPs will be encouraged to contribute their ideas for PAP rehabilitation options. (iii) District/City CRCs will establish a complete list of all PAPs present at the meetings. (iv) District/City CRCs will make a complete record of all questions, comments, opinions and decisions that arise during the information/consultation meetings, and present a report of all the meetings to Phu Yen PMU. 179. The following information will be given to PAPs: (i) Project components and sub-projects. This includes the places where they can obtain more detailed information about the Project. (ii) Project impacts. Impacts on the people living and working in the affected areas of the project, including explanations about the need for land acquisition for each project. (iii) PAPs rights and entitlements. These will be defined for PAPs. A cut-off date will be announced to establish eligibility. The rights and entitlements for different impact on PAPs, including the entitlements for those losing businesses, jobs and income will be explained. Available options include for land-for-land and cash compensation, options regarding reorganizing and individual resettlement, provisions and entitlements to be provided for each PAP, entitlement to rehabilitation assistance and opportunities for project-related employment will all be discussed and explained. (iv) Grievance redress mechanism. PAPs will be informed that the project policies and procedures are designed to ensure their pre-project living standards are restored. PAPs will also be informed that if there is any confusion or misunderstanding about any aspect of the Project, the resettlement committee can help resolve problems. If they have complaints about any aspect of the land acquisition, compensation, resettlement, and rehabilitation process, including the compensation rates being offered for their losses, they have the right to make complaints and to have their complaints heard. PAPs will receive an explanation about how to access grievance redress procedures. They will be given information with details of which office to contact and local contact points for grievance redress. (v) Right to participate and be consulted. The PAPs will be informed about their right to participate in the planning and implementation of the resettlement process. The PAPs will be represented in District’s resettlement committees, and the repr esentative for the PAP will be present whenever commune/district/provincial committees meet so that their participation in all aspects of the project is assured. (vi) Resettlement activities. PAPs will be given an explanation regarding compensation calculations and compensation payments; monitoring procedures which will include interviews with a sample of PAPs; relocation to an individual location/self-relocation; and preliminary information about physical works procedures. Page 64 (vii) Organizational responsibilities PAPs will be informed about the organizations and levels of Government involved in resettlement and the responsibilities of each, as well as the names and positions of the government officials with phone numbers, office locations, and office hours if available. (viii) Implementation schedule. PAPs will receive the proposed schedule for the main resettlement activities and informed that physical works will start only after the completion of all resettlement activities and clearance. It will be clarified that they will be expected to move only after receiving full payment of compensation for their lost assets. Implementation schedules and charts will be provided to resettlement committees at all levels. 180. Project Leaflet. A Project Leaflet providing project information will be prepared and handed out to the PAPs in the project preparation and implementation stages to ensure that the people are well aware of the project benefits. The project leaflet will provide detail of the compensation and assistance policies mentioned in this RPF so as to propose social impact mitigation measures in case of land acquisition and site clearance by the sub-project. 9.4. Information Disclosure 181. As requested by WB, the Resettlement Action Plan was disclosed in Vietnamese at local level, especially in the office of Phu Yen PMU of Agriculture and Rural Development, the district/city/ward/commune people’s committees, Phu Yen province’s portal on June 20, 2017 and on the Bank’s website on June 22, 2017. 10. GRIEVANCES AND REDRESS MECHANISM 10.1. Responsibility 182. The agencies are responsible for carrying out the process for settling complaints, questions during the implementation of site clearance compensation including the CPC, the Department of relevant departments, the site clearance compensation council all levels, the local People's Committee which was affected by the project and the organization in charge of compensation and ground clearance for the construction project as well as Phu Yen PMU. Depending on the functions and responsibilities of each level, the mechanism for settling complaints and queries of the affected households will be defined according to the legal documents issued by the State. 183. To ensure the affected households have the opportunity to present complaints related to compensation, support and resettlement, detailed complaint procedures will be established for the project. The objective is to address the complaints of affected households rapidly and right process. The mechanism will be designed to be simple, straightforward, fast, open and fair. By resolving complaints at each project level, project implementation schedule will certainly be more effective. Those who have land recovered if not agree with the decision on compensation, assistance and resettlement can present complaint in accordance with the law. 184. The grievance redress with the decision of compensation and assistance, clearance and resettlement with responsibility for redressing grievances, validity and procedures for settling complaints shall comply with the provisions of Article 204 of the Land Law 2013, articles 89 and 90 of Decree No. 43/2004/ND-CP dated 15May 2014 of the Government of Vietnam on the implementation of the Land Law. 185. Cases related to administrative decisions on land management will comply with procedures to address grievances, complaints, recommendations on civil enforcements set forth in 2011 Law on Complaints and Circular No. 02/2016/TT-BTP dated 01 February 2016 of the Ministry of Justice. 10.2. Grievance redress mechanism 186. All inquiries and complaints from complainants on the right of compensation, compensation policies, compensation rate, land acquisition, resettlement and the related entitlements related to restoration programs will be recorded and processed by the competent authorities. Local social organizations such as the Fatherland Front, Farmers' Association, Women’s Union, Reconciliation Page 65 Council, etc. are mobilized to participate actively in the process of reconciliation and resolution of complaints and inquiries from complainants. 187. The grievance procedures consists of four steps as follows: Step 1: The aggrieved affected household can bring his/her complaint in writing or verbally to any member of the Commune People’s Committee, either through the Village Chief or directly to the CPC. It is incumbent upon said member of CPC or the village chief to notify the CPC of the complaint. The CPC will meet personally with the aggrieved affected household and will have 30 days and maximum of 45 days following the lodging of the complaint, depending on complicated case or distance, to resolve it. The CPC secretariat is responsible for documenting and keeping file of all complaints that it handles. Land fund development center and/or ward/commune People’s Committees shall be responsible for settling these complaints within 30 days from receipt of the complaints from complainants. For complicated cases, the redressing time may be longer but must not exceed 45 days from the date of receipt of the complaints. Step 2: If complainants are unsatisfied with judgment of the LFDC and/or Ward People’s Committee, they can send their grievances to the District People’s Committee Deputy Chairman of the city council chairman clearance organizations responsible for consideration and settlement of complaints of people affected with the participation of relevant agencies are participating menu board. Time to settle complaints by the Board of clearance is within 45 days of receiving the complaint. For complicated cases, the processing time may be longer but must not exceed 60 days from the date of receipt of the complaints and complaints. In the case of complaints by complainants beyond the competence of the Council of clearance, the Council will report to the city People's Committee for resolving; simultaneously notify the complainants to know. City Resettlement Council (CRC) is responsible for working with the agencies of the City/District People’s Committees to resolve complaints by people affected within 15 days. Upon receipt of the settlement of the city People's Committee, the commune/ward PCs are responsible for the fulfillment of its notification to the complainants. In the case of complaints by people affected beyond the competence of the Council of clearance, the Council will report to the city People's Committee resolved, simultaneously notify the affected know. City Resettlement Council (CRC) is responsible to work with the agencies of the City/District People’s Committees to resolve complaints by people affected within 15 days. Upon receiving the opinion of the Committee resolved to Commune/Ward PCs are responsible to notify the complainants of settlement results. Step 3: If the AHs still do not satisfy with the decisions of the PPC on their appeals they can submit their cases to the district courts for review within 15 days since they received decisions from Phu Yen province. PPC is responsible for directing City Resettlement Council (CRC) and the relevant agencies of the city resolved within 45 days of receiving the complaint PPC. PPC shall notify the complainants of settlement results. Step 4: If the complainant is still dissatisfied with the decisions of the PPC, the complainant can bring to the provincial People's Council or to the Court to be resolved according to law In fact, according to the Law on Complaints 2011, complainants may submit to the court at any given time if they want. Where the complainants send a complaint to the City People's Council, the People's Council will direct the City/District People’s Committees to consider and settle the complaint. Duration resolve complaints within 45 days from the date of the City People's Council received a complaint. Pending the settlement of complaints, including the resolution of disputes in court, the people affected must hand over the site to the project on schedule. Compensation, support amount will be deposited in a commercial bank account Page 66 188. The agencies responsible for complaints and resolve complaints during site clearance and compensation are City/District People’s Committees, relevant departments. CRC at all levels and communes/ wards PCs affected by the project. All records of complaints and resolving complaints related agencies are stored at the LFDC and Phu Yen PMU. Phu Yen PMU is responsible for updating the list of complainants and status of complaints expressed in the internal monitoring reports. 11. IMPLEMENTATION ARRANGEMENTS 11.1. Institutional Framework 189. The implementation of resettlement activities requires the involvement of agencies and organizations at national, provincial, district and commune levels. The PC of each Province engaged in the Project will take overall responsibility for the implementation of the general resettlement policy framework and specific Resettlement Action Plan of the sub-project of the province. DCRCs will be established at provincial/district levels in compliance with provisions of Decree No. 47/2014/CP. The provisions and policies of the RAPF and the RAP will form the legal basis for the implementation of compensation and resettlement activities of the subproject. Agencies in charge of land acquisition and resettlement include: o Phu Yen PPC o District/City PCs o Phu Yen PMU of Agriculture and Rural Development o District/City LFDC o People’s Committees of project wards/communes; o Representatives of community and AHs; o Independent Monitoring Agency/Unit/Individual 11.2. Responsibilities of Relevant Agencies 11.2.1. Phu Yen PPC 190. Phu Yen PPC is responsible to or authorizes the District/City PCs to establish and direct the Appraisal Board in accordance with the Project’s demands. Phu Yen PPC or the District/City PCs (if authorized) shall be responsible for: (i) Approving the Resettlement Policy Framework (if authorized by the Government); (ii) Issuing announcements or authorizing the district/city PCs to announce information on land acquisition when the Sub-Project location has been selected; (iii) Appraising and approving RAP after their final draft is approved by the Bank; (iv) Approving land acquisition and allocation in the Project; (v) Making final decision and releasing unit prices of compensation and assistance rates, and support policies towards AHs and vulnerable groups on the basis of the Resettlement Policy Framework and the approved RAP; (vi) Directing the coordination among concerned agencies and provincial departments to implement compensation, assistance and resettlement in accordance with the approved RAP; (vii) Fully funding resettlement activities; (viii) Ensuring that the resettlement activities of the Sub-Project comply with the Policy Framework and the approved RAP; (ix) Considering resettlement locations for AHs, if requested. 11.2.2. Phu Yen PMU of Agriculture and Rural Development 191. Phu Yen PMU is responsible for implementation of RAP of the Subproject. Accordingly, the project staff who are qualified and experienced will be appointed or assigned to take responsibility for Page 67 environmental and social safeguards under the Subproject. They will be involved in training courses in relevant policies and procedures since the first stage of implementation. The list of personnel and their CVs as well as the above-mentioned training programs should be agreed and approved by the WB. In detail, responsibilities of Phu Yen PMU include: (i) On behalf of the Client or city to assign the specialized officials in charge of implementing and monitoring resettlement activities in line with the Subproject under the management of the PPC or DPC to prepare plans, coordinate and monitor the RAP; (ii) To prepare and/or update RAP in accordance with the approved Resettlement Policy Framework and submit it to the PPC/City PC and WB for approval before deploying the approved RAP; (iii) To guide all resettlement activities in the project city/wards/communes in conformity with the policies and guidelines of the RAP; (iv) To establish model procedures/processes regarding information disclosure and relevant consultation organization such as sending a monthly notification to the communities on the Project activities; to coordinate other agencies involved in the RAP, implementing and monitoring resettlement activities; (v) To check and advise the PPC on the compensation rates of land and other assets in coordination with other related government departments and agencies of the Province, on the basis of the principles of the approved Resettlement Policy Framework; (vi) To coordinate, supervise, and monitor the implementation of resettlement activities in the Project; (vii) To establish a contact mechanism to ensure suitable technical assistance and logistics for the implementation of compensation and resettlement; (viii) To set up database criteria on AHs for each component as well as for the entire Project; (ix) To establish procedures on internal monitoring to supervise the compliance with the project policies; (x) To establish procedures on monitoring coordination between contractors and local communities, ensuring timely and prompt identification and compensation for impacts on public and private properties during construction; (xi) To select, monitor, and implement recommendations from the independent monitoring agency and independent valuation agency; (xii) To set procedures on promptly implementing necessary measures of adjustments and advising the project owner in handling complaints; (xiii) To coordinate with related agencies to provide employment related to the Project for AHs; (xiv) To take over acquired land from HHs and hand it over to construction units; (xv) To select and mobilize the independent valuation agency to conduct land price survey as a basis for Phu Yen PPC to make decision on land prices applied to the project and ensure the closeness to the market price. (xvi) To cooperate closely with the independent monitoring agency; and (xvii) To report periodically on resettlement activities to the WB. (xviii) Phu Yen PMU of Agriculture and Rural Development need a staff who is in charge of directly working with AHs as a first step in redressing grievances. He/She will support vulnerable groups in appealing grievances. AHs will be free of administrative and legal fees arising during the grievance redressing. Further information about his/her responsibilities are mentioned in Term of Reference for key social safeguard personnel. 11.2.3. District/City/District People’s Committees 192. District/City/District People’s Committees shall be responsible for: Page 68 a) Making announcements on land acquisition if authorized by Phu Yen PPC; b) Approving compensation plans prepared by the CRC and submitting them to the PPC for endorsement; c) Issuing decisions on land acquisition from individuals and HHs; d) Handling complaints and grievances of the AHs within jurisdiction. 11.2.4. The Districts Compensation and Resettlement Committee (CRC) The District Compensation and Resettlement Committee (CRC) shall take responsibility for compensation and site clearance for the works in the city/districts, including: (i) Planning and implementing all daily resettlement activities within the city; (ii) Making inventories of acquired land, completing compensation lists and tables, and preparing sum-up tables to be submitted to competent authorities for approval and paying compensation directly to each affected person after receiving compensation funds; (iii) Preparing allocated land and relevant procedures for the resettlement of relocated HHs; (iv) Appointing staff for conciliation and handling of complaints by AHs on compensation policy and entitlements; (v) If necessary, establishing commune/ward CRCs and directing them in implementing resettlement activities; (vi) Paying special attention to the needs and aspirations of special groups of people (ethnic minorities) and vulnerable people (children, the elderly, female/single household heads); and (vii) Coordinating closely with independent monitoring agencies. 11.2.5. Town/Commune People’s Committees 193. Town/Commune People’s Committees shall be responsible for: (i) Establishing ward-level working groups and manage their operations; assigning ward/commune staff to assist the CRC and Phu Yen PMU in preparing DMS for the Project, preparing documents on land acquisition, preparing RAP and implementing resettlement activities; (ii) Verifying AHs’ legal titles or certifying their land use or transfer to meet the requirements of compensation; (iii) Assisting other units and agencies, including Phu Yen PMU, in posting or disseminating information; holding community meetings; and consulting AHs for comments; (iv) Assisting other units and agencies, including Phu Yen PMU, in carrying out demographic surveys, replacement cost surveys, detailed measurement and inventory surveys, and other resettlement activities; (v) Participating in all operations of land acquisition and allocation, resettlement, recovery support, and social development support; (vi) Supporting AHs in all resettlement activities and living standard restoration; (vii) Notifying AHs on compensation schedule, monitoring compensation implementation; and signing in documents on compensation with AHs; and (viii) Ensuring full implementation of the mechanism of redressing grievances from AHs; recording all grievances and filing all documents on grievances; supporting and advising AHs; and promptly resolve grievances. 11.2.6. Project Affected People (AHs) 194. AHs shall be responsible for: (i) Coordinating with survey teams in carefully checking and certifying affected land and other assets as well as their entitlements; Page 69 (ii) Participating in all phases of the RAP preparation and implementation and giving feedback to improve the quality of the RAP and devise solutions for implementing the RAP smoothly; and (iii) Moving to new sites in a timely manner after receiving full compensation and entitlements. 11.2.7. Independent Monitoring Agency (IMA) 195. Independent monitoring agency (IMA): It is required to identify and hire an agency/ organization or research institute specializing in social sciences, to conduct socio-economic surveys, monitor and evaluate the implementation of the RAP. Phu Yen PMU will sign a contract with Independent monitoring Agency. Cost for hiring IMA to carry out independent monitoring of resettlement for the subproject will come from the CF. Independent Monitoring Agency (IMA) will report periodically on progress made and to make recommendations concerning resolving the problems detected in the monitoring process. 12. IMPLEMENTATION PLAN 12.1. Main Activities 196. To ensure the project is successfully implemented and highly efficient, the main activities should be established through an implementation schedule with timelines. Thereby, the implementation progress of work items at certain times can be evaluated. The plan should be mapped out from the start of the project and prolong throughout the implementation process and continuously to the completion phase of the project. In the Resettlement Action Plan, the main contents needed to be done from commencement to completion phase include: a. Announcement of the cut-off-date and compensation plan: all project affected households are fully informed of the entitlements, and policies in RAP, including the eligibility, entitlements, methods and compensation rate, schedules, grievances and redress. Project Information Booklet (PIB) will be prepared by PMU and then it will be distributed to affected households or announced at the meeting in population groups, ward, district, or in the public consultation. Besides, leaflets, posters were also distributed to each household, posted at public places like Ward People's Committee/ social, cultural houses, clinics, schools, etc. Announced land acquisition policy of the project, decide the investment project approval, approval of the project design… b. Socio-economic survey in affected area c. Development of the plan on development of resettlement sites. d. Development of the livelihood restoration measures. e. Compensation, support, resettlement and livelihood restoration. f. Assessment of the project’s impacts on affected households: One year after the project ended, a social- economic survey in project area will be conducted to assess the impacts of the project on the benefited community and the project affected households. The results of this survey will be served as basis for assessment of the project’s impacts on the community and the lessons learnt for the later project operations and design and implementation. 12.2. Implementation Schedule 197. Implementation schedule for land acquisition of the ENDR – Phu Yen province is shown in the table below: Page 70 Table 25: Implementation Plan Main activities Time Resettlement Action plan Determine tentative project location and scope of the project’s impacts Quarter I – 2017 Socio-economic survey, preliminary inventory of losses (IOL), public Quarter I – 2017 consultation with affected persons and preparing RAP Submit RAP to Phu Yen PMU for reviewing Quarter II – 2017 Submit RAP to World Bank Quarter II – 2017 Implementation of Resettlement Action Plan Preparing cadastral dossiers and land acquisition demarcation Quarter III – 2017 Implement public consultation and information disclosure, detailed measurement survey (DMS), replacement cost survey, prepare detailed Quarter III – 2017 compensation plan Compensation payment Quarter III/2017 – Quarter II/2018 Quarter III/2017 – Site clearance, relocation and restoration measures (if any) Quarter II/2018 Post-resettlement evaluation Quarter III – Quarter IV/2018 13. MONITORING AND EVALUATION 13.1. Monitoring 198. Monitoring and evaluation activities during the implementation period and after the resettlement stage are to ensure the land acquisition and resettlement activities are to be carried out in accordance with the regulations, guidelines specified in the Resettlement Action Plan. Monitoring provides all stakeholders with continuous reflections on the implementation of land acquisition and resettlement. This activity helps assess the actual successful ability and arising difficulties as soon as possible, to facilitate remedying timely in the project operation phase. 199. Monitoring includes 2 following purposes: (i) Verify whether the project activities are completed efficiently or not, including quantity, quality and time. (ii) Assess whether these activities reach the objectives and purpose of the Project or not, and if not how much do they reach. 200. Phu Yen PMU will hire/recruit an Independent Monitoring Agency (IMA) to regularly monitor and supervise the implementation of RAP. 13.2. Internal Monitoring 201. Internal monitoring of the RAP implementation of the Sub-project is the main responsibility of the implementation agency with the support of the project consultants. The implementation Page 71 agencies will monitor the progress of RAP preparation and implementation throughout the regular progress reports. 202. Internal monitoring aims to: (i) Ensure that compensation payment for affected households for the different types of damage is implemented according to the compensation policy agreed in the RAPF and RAP. (ii) Ensure that resettlement activities are implemented according to the compensation policy agreed in the RAPF and RAP. (iii) Determine whether the conversion process, income restoration measures and resettlement assistance are provided on time or not. (iv) Evaluate whether the income restoration supports have been provided or not yet and propose corrective measures if targets of income restoration for households are not achieved. (v) Disseminate public information and consultation procedures. (vi) Determine whether the complaint procedures have been followed or not and there is any outstanding issue needed the attention by the management level or not. (vii) Prioritize for interests and needs of affected people, especially poor and vulnerable households. (viii) Ensure transition between relocation, clearance and start of construction of civil works proceeds smoothly and that construction area will not be handed over until affected households have been compensated, supported and resettled satisfactorily. 203. The implementation agencies will collect information every month from the different resettlement committees. A database tracking the resettlement implementation of the Project will be maintained and updated monthly, including redressing of grievances (if any). 204. The implementation agencies will submit internal monitoring reports on the RAP implementation as a part of the quarterly report to be submitted to the WB. The internal monitoring reports should contain the following information: (i) Number of affected persons according to types of effect and project component and the status of compensation, relocation and income recovery for each item. (ii) The distributed costs for the activities or for compensation payment and disbursed cost for each activity. (iii) List of outstanding Complaints (iv) Final results on solving complaints and any outstanding issues that demand management agencies at all levels to solve. (v) Arisen issues in the implementation process. (vi) Updated actual schedule of resettlement activities. 13.3. Independent Monitoring 205. Independent monitoring will be conducted by the consulting organization/ non-governmental organization (NGO) experienced in monitoring and evaluation of the implementation of the socio- economic survey. The Project Management Unit will sign a contract with the independent monitoring organization. The implementation of project independent monitoring will be funded by the official development assistance (ODA) for project. The Independent monitoring organization will report every 6 months on the progress and give relevant recommendations to solve any issues arising in the process of monitoring. 206. Objectives: The general objectives of independent monitoring are to periodically supply independent monitoring and assessing results on the implementation of the resettlement objectives, on the changes of living standard and jobs, AHs’ income and social foundation restoration, effectiveness, impacts and sustainability of APs’ entitlements, and on the necessity of mitigation measures (if any) to bring about strategic lessons for making policy and planning in the future. Page 72 207. Responsible agencies: In accordance with the World Bank’s requirements for consultant employment, Phu Yen PMU will hire an IMA to carry out the independent monitoring and evaluation of RAP implementation. This organization is called the Independent Monitoring Agency (IMA) which specializes in social sciences and has experience in independent monitoring of RAP. The IMA should start its work as soon as the project implementation commences. 208. Monitoring indicators include: a. Compensation payment and assistance for affected households are implemented according to the entitlements agreed in the RAP. b. Technical assistance, relocation and allowance c. Income restoration and entitlements to restoration allowances. d. Information disclosure and public consultation. e. Grievance redress procedures, results of resolving complaints. f. Progress of land acquisition Methodology and Approach: Survey Sample 209. A socio-economic survey will be required before, during and after resettlement implementation to provide a clear comparison of success/failure of the Resettlement Action Plan. Monitoring will be on a sample basis. Scale of the survey sample may cover 50% relocated households and severely affected households, and at least 10% of the remaining households. Sample survey is implemented twice a year. 210. The sample surveys should include women, elderly, and other vulnerable groups. It should balance representation of male and female respondents. 211. Post-resettlement evaluation is implemented every 6 months, after completion of the resettlement activities. Independent monitoring agency will be responsible for: (i) reviewing the documents on compensation, assistance and (ii) work with the CRC and local authorities to collect necessary information and data, (iii) interviews with the people; and (iv) group discussions. Database storage 212. The IMA will store information on monitoring of resettlement, include the results of independent monitoring, collect and update basic information about the affected households. All the collected and updated data will be submitted to Phu Yen PMU, the managing agency and the World Bank. Monitoring report 213. The monitoring report will be presented during the meeting between the independent monitoring agency (IMA) and PMU immediately after submitting the report. Solutions will be implemented based on the arising problems are outlined in the report and discussions 214. Independent monitoring reports are made before, during and after resettlement. This report should reflect contents: - Verify the internal monitoring results - Assess whether the resettlement objectives have been achieved or not; how income resources and living standards of the project affected households are restored and improved. - Considering whether the entitlements of resettlement are appropriate with conditions of project affected households and meet the resettlement objectives or not. - Evaluate the effectiveness, impacts and sustainability of the resettlement; lessons learnt for the planning and developing the future resettlement policy Ex-post evaluation Page 73 215. In fact, this is the evaluation at a given point of time on the impact of resettlement and the achieved objectives. The independent monitoring will conduct an evaluation of the resettlement process and impacts from 6 to 12 months after the completion of all resettlement activities. The survey questionnaires for evaluation are used based on the database in the project database system and the questions used in the monitoring activities. 216. If this evaluation determines that livelihoods of severely affected households have not been restored appropriately with the objectives of the project, an additional fund will be provided to continue support for households above. The Independent Monitoring Report will be not only sent to Phu Yen PMU, but also sent directly to the World Bank for following/supervising the progress and effectiveness of the compensation. Or in other words, when a project is not finished, the World Bank will continue monitoring until resettlement activities as mentioned in the RAP have been implemented. When project is completed, the implementation completion report (ICR) will assess the achievements of the resettlement and the lessons learnt and will be incorporated in the evaluation of PMU. This requirement is stated in OP/ BP 4.12, paragraph 12.24. If this evaluation determines the objectives of the resettlement have not been achieved as expected, the ICR will assess the appropriateness of resettlement measures that could be proposed with measures in next time, include follow-up monitoring by the World Bank. The contents of the ICR for next part will be made based on the socio-economic survey of affected households, this survey was conducted at the end of the project (or completion of sub-project), and given the impacts of land acquisition and the impacts on livelihoods for affected households. 14. COST ESTIMATION 14.1. Funding sources 217. The budget for the implementation of the Resettlement Action Plan will be part of the counteRAPart fund of Government (budget from Phu Yen PPC). Phu Yen PPC will provide counteRAPart funds for the implementation of compensation and resettlement, and will be included in the total investment cost of the project. 218. Phu Yen PMU will disburse funds for land acquisition, support and resettlement of the project through the City/District LFDC (District/City CRC). These agencies will be responsible for making compensation payment directly to affected households of the Project. 14.2. Replacement Cost Survey 219. As required by the World Bank’s OP 4.12 on Involuntary Resettlement, Replacement Costs Survey (RCS) will need to be done to establish basis for calculation of replacement costs for all the lands/crops/structures/assets that will be affected by the Project. 220. An independent price appraisal consultant is specialized in assessing costs of land/assets/structures to be affected under the Project, will be engaged by Phu Yen PMU to conduct replacement costs survey. 221. During the RAP preparation, basis for calculating compensation payment proposed to affected households is at the replacement costs (for land and structures), and at market prices (for crops/trees and aquatic livestock), based on household’s perceptions, local land transactions (for resi dential land), capacity of agricultural production (for agricultural land), local quotations for construction material and other assets; and referred to other current replacement cost surveys which have been carried out nearby. 14.3. Cost Estimate 222. Cost estimate for RAP implementation includes: a. Cost for the compensation, assistance and resettlement: includes of the items which were described in the entitlement matrix. b. Cost for independent monitoring: Page 74 - Cost of independent monitoring of RAP implementation is estimated at 1% of total cost of stage of DMS, compensation and restoration support. - The independent monitoring consultant will prepare the technical and financial proposals for bidding. Actual cost will be decided through contract value for independent monitoring consultant. c. Cost for compensation, assistance and resettlement included costs of detailed measurement survey, land acquisition documentation, independent valuation cost, etc. It is estimated at 2% in maximum of total cost of compensation and restoration support. d. Contingency: The rate for contingency should be at about 10% of total cost of compensation and RAP preparation. The contingency will be used in cases of adjusted compensation rates due to inflation, or any adjustments during implementation of the approved RAP. 223. Cost estimate for implementation of RAP for the works under the Subproject is VND 17,679,405,564 (equivalent to US$ 778,828). Cost estimate for each item of the Subproject is presented in Table below. Detailed cost estimate is showed in Annex 1 of this report. Table 26: Cost estimate for each item affected by the Subproject Total amount: exchange rate: US$ 1 = VND 22,700 No Items VNÄ? USD 1 Compensation for land 5,885,712,500 259,282 2 Compensation for structures 398,963,000 17,575 3 Compensation for trees and crops 118,915,000 5,239 4 Assistances 10,033,636,500 442,010 5 Cost estimate for IRP 475,200,000 20,934 6 Total (1+2+3+4+5) 16,912,427,000 745,041 7 Independent monitoring = 1% (6) 169,124,270 7,450 8 Cost estimate for RCS = 0.5% (6) 84,562,135 3,725 9 Management cost = 2% (6) 338,248,540 14,901 Total (6+7+8+9) 17,504,361,945 771,117 Contingency (10% of total amount) 175,043,619 7,711 GRAND TOTAL 17,679,405,564 778,828 Page 75 ANNEXES Annex 1: Replacement Cost Survey Annex 2: Project information leaflet Annex 3: Some Minutes of Public Consultation Meetings At the Project Area Annex 4: Socio-economic Survey Questionnaire for Affected Households in the Project Area Annex 5: Some Pictures of Consultation Meetings Annex 6: List of Affected Households with Different Types Of Impact Annex 7: TOR for Independent Monitoring Page 76 Page 77