Page 1 Rural Water Supply and Sanitation Project Procurement Plan I. General 1. Project Information Project Name: Rural Water Supply and Sanitation Project Country: Yemen Project ID: P005906 Loan/Credit Numbers: IDA 3450 ,IDA H- 3510 2. Bank's approval date of Procurement Plan Original: GRANT H3510 15/02/2008,and CREDIT 3450 Nov 2001 Revision 1: 14, June 2009 Add new revisions 3. Date of General Procurement Notice 11-Aug-08 II. Goods, Work and Non-Consulting Services Thresholds 1. 1a. Procurement Category Prior Review Threshold (USD) Comments Goods >=200000 Works >=250000 Non-Consultant Services NA Include all categories authorized by the loan agreement 1b. Procurement Method Procurement Method Threshold (USD) Comments ICB and LIB (Goods) NA NCB (Goods) 200000 Shopping (Goods) IS <= 50000 Shopping (GoodsNS <=5000 ICB (Works) NA NCB (Works) 250000 ICB (Non-Consultant Services) NA Include all methods authorized by the loan agreement 2. 3. 4. 5. 6. III. Selection of Consultants 1. 1a. Procurement Category Prior Review Threshold (USD) Comments Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Reference to (if any) Project Operational/Procurement Manual: Project Operational Manual dated Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet Any Other Special Procurement Arrangements: NA Prequalification. Bidders for __/////____ shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. Proposed Procedures for CDD Components (as per paragraph 3.17 of the Guidelines): Refer to the relevant CDD project implementation document approved by the Bank NA Page 2 Consulting Firms (Competitive) >= 100,000 Consulting Firms (Sole Source) ALL Individual Consultants (Competitive) >50,000 Individual Consultants (Sole Source) ALL Include all categories authorized by the loan agreement 1b. Procurement Method Procurement Method Threshold (USD) Comments QCBS > = 100,000 QCB NA FCS NA LCS NA CQS < = 100,000 Consulting Firms (Competitive) < = 100,000 Consulting Firms (Sole Source) NA Individual Consultants (Competitive) < 50,000 Individual Consultants (Sole Source) < 50,000 ICB (Non-Consultant Services) NA Include all methods authorized by the loan agreement 2. Note: OPCPR list of ceilings can be found here: http://go.worldbank.org/MKXO98RY40 3. 4. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 200,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Any Other Special Selection Arrangements: NA Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity Building" sheet Page 3 GRANT H3510 15/02/2008,and CREDIT 3450 Nov 2001 Page 4