PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-10-04 2021-08-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2880, IDA / 62150, IDA / D2860 M Executing Agency(ies): inistry of Environment and Sustainable Development WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Mise en place d'une clôture Single Stage - One 2019-07- 2019- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 36,168.67 Achevé 2018-11-10 2019-11-08 2019-01-05 2019-11-13 grillagée autour de la marre à Envelope 04 11-30 Investments Spartines MR-MEDD-74202-CW-RFQ / Component 3: Strengthening Travaux d'entretien des Single Stage - One 2019-08- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-12-30 2019-02-24 couloirs de pare-feux du Envelope 23 Investments Typha au niveau de Diawling MR-MEDD-74205-CW-RFB / Component 4: National Single Stage - Two 2019-08- Construction des sièges de IDA / D2880 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 Coordination Envelope 05 l'Observatoire et de l'UGP MR-MEDD-75955-CW-RFB / Component 3: Strengthening Single Stage - One 2019-08- Colmatage des brèches du IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 Annulé 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 Envelope 24 littoral de NKTT Investments MR-MEDD-75986-CW-RFQ / Component 3: Strengthening Single Stage - One En attente 2019-05- Travaux pour la fixation des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-06 2018-12-01 Envelope d'exécution 30 dunes au niveau de Chami Investments MR-MEDD-76006-CW-RFQ / Component 3: Strengthening Restauration des éco- Single Stage - One En attente 2019-07- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-20 2019-01-15 systèmes du Parc National Envelope d'exécution 14 Investments d'Awleigatt (PNA) MR-MEDD-115356-CW-RFQ / Réalisation de clôture Component 3: Strengthening grillagée autour du périmètre Single Stage - One 2019-07- 2019- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 36,467.31 Achevé 2019-05-25 2019-06-13 2019-06-10 2019-06-21 de 15 ha de fixation Envelope 20 07-22 Investments mécanique et biologique du cordon dunaire de Nouakchott MR-MEDD-115655-CW-RFQ Component 3: Strengthening Single Stage - One 2019-08- 2019- / Fixation de 15 ha de dunes IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 36,984.27 Achevé 2019-06-01 2019-06-12 2019-06-11 2019-06-28 Envelope 10 09-16 du littoral de Nouakchott Investments MR-MEDD-115657-CW-RFQ / Travaux d'entretien de Component 3: Strengthening Single Stage - One En cours 2019-07- couloirs de pare-feus pour la IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-05-30 2021-05-19 2019-06-12 Envelope d'exécution 12 restauration des mangroves Investments au niveau de Diawling MR-MEDD-115659-CW-RFQ Component 3: Strengthening Single Stage - One 2019-07- 2019- / Réalisation de pépinières de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 34,921.07 Achevé 2019-06-08 2019-07-19 2019-06-21 2019-08-01 Envelope 21 08-29 mangroves au Diawling Investments MR-MEDD-124501-CW-RFQ Component 3: Strengthening / mise en place d'une cloture Single Stage - One 2020-04- 2019- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 8,464.35 Achevé 2019-08-26 2019-07-25 2019-10-21 2019-08-02 de protectionsur les 2 ha de Envelope 18 08-29 Investments dunes fixées au PND MR-MEDD-124500-GO-RFQ Component 3: Strengthening / mise en place de clotures Single Stage - One En attente 2020-04- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-09-07 2019-10-19 pour abriter les pépinières de Envelope d'exécution 16 Investments mangroves au PND MR-MEDD-129309-CW-RFQ / Clôture grillagée pour la Component 3: Strengthening Single Stage - One 2020-04- 2019- protection d'une fixation de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 36,983.98 Achevé 2019-09-07 2019-09-13 2019-11-02 2019-09-17 Envelope 30 10-23 dunes de 15 ha du littoral de Investments Nouakchott MR-MEDD-137084-CW-RFQ / Mise en place de couloirs de Component 1: Strengthening Single Stage - One 2019-11- 2020- IDA / D2880 A posteriori Demande de prix Limited 28,650.24 Achevé 2019-10-06 2020-03-13 2019-10-16 2020-03-06 pare-feux de Typha au niveau Regional Integration Envelope 15 05-13 du Diawling MR-MEDD-137891-CW-DIR / Renforcement de la Component 3: Strengthening Passation de 2020-01- résilience des communautés IDA / D2880 National Physical and Social A posteriori marché de gré à Direct 0.00 Annulé 2019-10-02 2019-10-04 2019-10-04 02 et des écosystèmes de Investments gré Ndiago. MR-MEDD-156359-CW-RFQ / Mise en place d'une clôture Component 3: Strengthening Single Stage - One En attente 2020-04- grillagée autour de la marre à IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-02-10 2020-03-05 Envelope d'exécution 19 Spartine à la Baie de l'Etoile Investments de Nouadhibou (phase II) MR-MEDD-170442-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2020-11- / Construction de Loges des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-05-13 2020-07-08 Envelope d'exécution 05 agents de surveillance Investments MR-MEDD-170443-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2020-11- / Travaux de fixation des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-06-13 2020-08-08 Envelope d'exécution 06 dunes au diawling Investments Page 1 MR-MEDD-170445-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2020-10- / Clôture grillagée fixation IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-05-14 2020-07-09 Envelope d'exécution 17 dunes au Diawling Investments MR-MEDD-170447-CW-RFQ Component 3: Strengthening Single Stage - One 2021-02- 2020- / Travaux de coupe de typha IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 33,708.59 Achevé 2020-06-24 2020-03-05 2020-08-19 2020-03-23 Envelope 15 04-24 au Parc National du Diawling Investments MR-MEDD-170449-CW-RFQ Component 3: Strengthening Single Stage - One 2020-10- 2020- / Mise en place de pépinière IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 29,996.09 Achevé 2020-06-24 2020-03-10 2020-08-19 2020-03-25 Envelope 03 06-08 de mangroves au Diawling Investments MR-MEDD-170453-CW-RFQ Component 3: Strengthening / clôture pour protéger les Single Stage - One 2020-11- 2020- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 24,131.97 Achevé 2020-06-13 2020-06-05 2020-08-08 2020-06-23 plantations de mangroves au Envelope 16 07-20 Investments Diawling Component 3: Strengthening MR-MEDD-170456-CW-RFQ Single Stage - One 2020-11- 2020- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 14,446.54 Achevé 2020-07-16 2020-07-10 2020-09-10 2020-07-24 / Plantation de mangroves Envelope 09 08-10 Investments MR-MEDD-170457-CW-RFQ Component 3: Strengthening / Travaux d’entretien des Single Stage - One En attente 2020-10- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-05-15 2020-07-10 couloirs et de coupe de Typha Envelope d'exécution 08 Investments déjà réalisés MR-MEDD-170572-CW-RFB / Travaux de réhabilitation et Component 3: Strengthening En attente 2021-05- extension de la digue Nord du IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2020-08-10 2020-09-09 2020-10-09 2020-10-29 2020-11-28 d'exécution 27 Parc National du Diawling Investments (PND) MR-MEDD-170567-CW-RFB Component 2: Strengthening Single Stage - One En attente 2022-05- / Travaux de fixation de IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - International 0.00 2021-01-04 2021-01-19 2021-03-02 2021-04-01 2021-05-06 Envelope d'exécution 03 dunes du littoral Framework MR-MEDD-178901-CW-RFQ Component 3: Strengthening / Entretien des claies et du Single Stage - One 2020-07- 2020- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 16,815.78 Achevé 2020-06-15 2020-06-23 2020-06-28 2020-07-10 reboisement (au niveau du Envelope 28 07-23 Investments PND) MR-MEDD-200677-CW-RFQ Component 3: Strengthening Single Stage - One 2021-02- / Construction d’un poste de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 34,654.84 Signé 2020-11-15 2020-10-26 2021-01-10 2020-12-07 Envelope 24 surveillance au PND Investments MR-MEDD-200725-CW-RFQ Component 3: Strengthening Single Stage - One 2021-04- 2020- / Mise en place d’une IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 16,021.62 Achevé 2020-11-22 2020-10-26 2021-01-17 2020-11-11 Envelope 17 12-07 pépinière d’Acacias Investments MR-MEDD-200729-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2021-05- / Entretien des travaux et IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-12-21 2021-02-15 Envelope d'exécution 16 couloirs déjà réalisés Investments MR-MEDD-200730-CW-RFQ Component 3: Strengthening Single Stage - One 2021-04- 2020- / Entretien de 15 ha coupés IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 18,441.49 Achevé 2020-11-25 2020-10-23 2021-01-20 2020-11-11 Envelope 20 12-17 en 2020 Investments MR-MEDD-200733-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2021-05- / Coupe de 50 ha de Typha IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2020-12-26 2021-02-20 Envelope d'exécution 21 dans le bassin de BELL Investments MR-MEDD-225606-CW-RFQ Component 3: Strengthening Single Stage - One En attente 2021-06- / Entretien des sites de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-03-27 2021-05-16 Envelope d'exécution 30 pépinières mangroves Investments MR-MEDD-225608-CW-RFQ Component 3: Strengthening Single Stage - One 2021-06- 2021- / Clôture de plantations de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 57,763.54 Achevé 2021-04-03 2021-03-26 2021-05-09 2021-04-01 Envelope 08 04-13 mangroves Investments MR-MEDD-225609-CW-RFQ Component 3: Strengthening Single Stage - One 2021-06- 2020- / Reboisement des zones de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 15,365.45 Achevé 2021-04-10 2021-06-10 2021-05-30 2020-07-24 Envelope 02 08-10 mangroves Investments MR-MEDD-170569-CW-RFB Component 3: Strengthening Single Stage - One 2022-01- / Travaux pour le colmatage IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - International 0.00 Annulé 2020-10-12 2020-10-17 2020-11-28 2020-12-28 2021-02-01 Envelope 29 des brèches Investments MR-MEDD-170571-CW-RFB / Travaux pour la réalisation Component 3: Strengthening de passages de Single Stage - One 2021-09- IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 Annulé 2020-11-16 2020-11-21 2021-01-02 2021-02-01 2021-03-08 franchissement du cordon Envelope 04 Investments dunaire et équipement des passages piétons MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Mise en place de de bacs à Single Stage - One 2019-08- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-12-17 2019-02-11 fleurs pour la sécurisation du Envelope 10 Investments littoral MR-MEDD-74188-CW-RFQ / Component 3: Strengthening Single Stage - One 2019-07- Aménagement du site de l'éco- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-11-20 2019-01-15 Envelope 14 loge Investments MR-MEDD-75993-CW-RFQ / Travaux de restauration des Component 3: Strengthening paysages des carrières de Single Stage - One 2019-07- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-12-05 2019-01-30 coquillages en frange Envelope 29 Investments continentale du cordon dunaire du littoral MR-MEDD-74189-CW-RFQ / Component 3: Strengthening Single Stage - One 2019-10- Travaux de construction de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2019-02-09 2019-04-06 Envelope 03 l'éco-loge Investments MR-MEDD-82725-CW-RFQ / Component 2: Strengthening mise en place d'une pépinière Single Stage - One 2019-06- IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-10-27 2018-12-22 pour les besoins de la fixation Envelope 20 Framework des dunes du littoral Page 2 MR-MEDD-200772-CW-RFB Component 3: Strengthening / Travaux de construction du Single Stage - One 2022-04- IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 Annulé 2020-12-30 2021-01-04 2021-02-15 2021-03-17 2021-04-21 siège de l'Observatoire Envelope 21 Investments National du Littoral MR-MEDD-170440-CW-RFQ Component 3: Strengthening / Confection et mise en place Single Stage - One 2020-09- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2020-05-26 2020-07-21 de bacs pour la sécurisation Envelope 19 Investments du littoral MR-MEDD-75951-CW-RFQ / Component 3: Strengthening Travaux pour passages de Single Stage - One 2019-09- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2019-01-15 2019-03-12 piétons sur le cordon dunaire Envelope 08 Investments de NKTT MR-MEDD-232482-CW-RFQ Request for Component 3: Strengthening / Entretenir les claies de Single Stage - One Quotations En attente 2021-12- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-07-17 2021-09-11 fixations des dunes et les Envelope (Non Bank- d'exécution 10 Investments bacs de protection SPD) Request for MR-MEDD-232485-CW-RFQ Component 3: Strengthening Single Stage - One Quotations En attente 2021-11- / Réaliser les travaux de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-06-27 2021-08-16 Envelope (Non Bank- d'exécution 14 fixation des dunes Investments SPD) MR-MEDD-232486-CW-RFQ Request for Component 3: Strengthening / Faire une clôture grillagée Single Stage - One Quotations En attente 2021-12- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-07-10 2021-09-04 autour des sites fixés (fixation Envelope (Non Bank- d'exécution 03 Investments biologique) du cordon dunaire SPD) MR-MEDD-232488-CW-RFQ Request for Component 3: Strengthening / Reboisement de 10000 Single Stage - One Quotations En attente 2021-10- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-06-27 2021-08-22 plants d’Acacia tortilles au Envelope (Non Bank- d'exécution 21 Investments PND SPD) Request for MR-MEDD-232508-CW-RFB Component 3: Strengthening Bids - Works / Réaliser les travaux de Single Stage - One En attente 2023-03- IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National (without 0.00 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 colmatage des 3 brèches (9, Envelope d'exécution 07 Investments prequalificati 13 et 16) on) SPD MR-MEDD-232510-CW-RFB Request for / Réaliser les travaux pour le Component 3: Strengthening Bids - Small Single Stage - One En attente 2023-03- passage de franchissement du IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National Works SPD (1 0.00 2021-11-15 2021-11-20 2022-01-01 2022-01-31 2022-03-07 Envelope d'exécution 07 cordon dunaire et équipement Investments envelope pour le passage piéton process) MR-MEDD-232489-CW-RFQ Request for / Entretenir les travaux, les Component 3: Strengthening Single Stage - One Quotations En attente 2021-12- couloirs de pare-feu, les IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-07-19 2021-09-13 Envelope (Non Bank- d'exécution 12 claies et le reboisement Investments SPD) réalisés en 2020 au PND National Procurement MR-MEDD-232506-CW-RFB Component 2: Strengthening Single Stage - One Document - 1 En attente 2023-02- / Construire le siège de IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 2021-10-15 2021-10-20 2021-12-01 2021-12-31 2022-02-04 Envelope Envelope d'exécution 01 l'observatoire du littoral Framework process (Non Bank-SPD) National MR-MEDD-232511-CW-RFB Procurement / Réhabiliter les bacs Component 3: Strengthening Single Stage - One Document - 1 En attente 2023-01- existants et faire l'extension IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2021-09-16 2021-09-21 2021-11-02 2021-12-02 2022-01-06 Envelope Envelope d'exécution 03 pour la sécurisation du Investments process (Non cordon dunaire du littoral Bank-SPD) MR-MEDD-75980-CW-RFQ / Component 3: Strengthening Travaux de fixation de dunes Single Stage - One 2019-06- IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-10-20 2018-12-15 du littoral de NKTT sur un Envelope 13 Investments premier site pilote GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / Component 2: Strengthening Acquisition d'équipements de Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 1,680.00 Achevé 2018-10-06 2019-07-22 2018-12-01 2019-07-25 2019-05-30 2019-08-30 bureaux au profit de l'Autorité Envelope Framework de la Zone franche de NDB MR-MEDD-74201-GO-RFQ / Acquisition de matériel pour Component 3: Strengthening Single Stage - One la surveillance des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-12-01 2019-01-26 2019-07-25 Envelope investissements physiques Investments pour Diawling MR-MEDD-74203-GO-RFQ / Acquisition d'équipement Component 3: Strengthening Single Stage - One En attente pour l'observatoire IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-06 2018-12-01 2019-05-30 Envelope d'exécution ornithologique au niveau de Investments Diawling MR-MEDD-74204-GO-RFB / Component 4: National Single Stage - One IDA / D2880 A posteriori Appel d'offres Open - National 91,573.20 Signé 2018-08-30 2018-12-27 2018-09-04 2018-10-16 2019-02-07 2018-11-15 2019-02-20 2018-12-20 2020-06-20 2019-06-18 Achat de véhicule Coordination Envelope MR-MEDD-75977-GO-RFQ / Acquisition d'équipements de Component 2: Strengthening Single Stage - One surveillance et de secourisme IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-10-30 2018-12-25 2019-06-23 Envelope au profit de la Direction de la Framework Protection Civile MR-MEDD-75990-GO-RFQ / Component 3: Strengthening Single Stage - One Mise en place de pépinières IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-11-10 2019-01-05 2019-07-04 Envelope de mangroves à Nouamghar Investments MR-MEDD-75995-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Single Stage - One En attente pour le réseau des IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-12-10 2019-02-04 2019-08-03 Envelope d'exécution Parlementaires et élus locaux Framework de l'environnement Page 3 MR-MEDD-75997-GO-RFQ / Component 2: Strengthening Acquisition de matériel pour Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-12-04 2019-01-29 2019-07-28 la coordination du Master Envelope d'exécution Framework Gaed MR-MEDD-75998-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-11-04 2018-12-30 2019-06-28 pour l'opérationnalisation de Envelope d'exécution Framework la base de données du MEED MR-MEDD-76001-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Single Stage - One pour le laboratoire des études IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 26,828.15 Achevé 2018-11-04 2020-08-17 2018-12-30 2020-10-01 2019-06-28 2021-01-13 Envelope environnementales et de Framework géographie (LEERG) MR-MEDD-76866-GO-RFQ / Component 3: Strengthening Single Stage - One En attente Acquisition de matériel pour IDA / D2880 National Physical and Social A posteriori Demande de prix Open - National 0.00 2018-10-15 2018-12-10 2019-06-08 Envelope d'exécution les AGR Investments MR-MEDD-124789-GO-RFQ / impression de cartes de Component 3: Strengthening distributions des formations Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 16,666.67 Achevé 2019-08-26 2019-12-09 2019-10-21 2019-12-17 2020-04-18 2020-01-13 de mangroves du BAS DELTA Envelope Investments DU FLEUVE SENEGAL rive droite. MR-MEDD-170370-GO-RFQ Component 2: Strengthening / Équipements au profit des Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-05-15 2020-07-10 2020-08-09 Délégations Régionales de Envelope d'exécution Framework l'Environnement (littoral) MR-MEDD-170397-GO-RFQ Component 2: Strengthening / Acquisition d'équipement de Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-08-25 2020-10-20 2020-12-04 bureau au profit de l'autorité Envelope d'exécution Framework de la zone franche MR-MEDD-170462-GO-RFQ Component 2: Strengthening Single Stage - One / Acquisition d'équipements IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 34,879.93 Achevé 2020-08-23 2020-08-24 2020-10-18 2020-09-08 2021-04-16 2020-09-14 Envelope au profit de la DAPL/MEDD Framework MR-MEDD-172830-GO-DIR / Passation de Component 4: National En cours logiciel gestion suivi- IDA / D2880 A posteriori marché de gré à Direct 0.00 2020-08-10 2021-08-06 2020-08-15 2020-09-19 2020-09-28 Coordination d'exécution évaluation (RUCH) gré MR-MEDD-200669-GO-RFQ / Acquisition d’équipements Component 2: Strengthening au profit de la Délégation Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-11-10 2021-01-05 2021-02-19 Générale de la Sécurité Civile Envelope d'exécution Framework et de la Gestion des Crises au MIDEC MR-MEDD-200671-GO-RFQ Component 2: Strengthening Single Stage - One En attente / Acquisition d’équipements IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-11-10 2021-01-05 2021-02-19 Envelope d'exécution au profit de l’ONM Framework MR-MEDD-200683-GO-RFQ Component 2: Strengthening / Acquisition de matériel Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 35,730.93 Achevé 2020-11-28 2020-10-26 2021-01-23 2020-11-11 2021-03-09 2020-12-15 optique pour l’Observatoire Envelope Framework du PND MR-MEDD-200687-GO-RFQ Component 2: Strengthening Single Stage - One En attente / Acquisition d’un Drone IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2020-11-28 2021-01-23 2026-01-01 Envelope d'exécution équipé au profit du PND Framework MR-MEDD-221606-GO-RFQ / Acquisition de deux zodiacs Component 3: Strengthening équipés de tous ses Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 9,675.19 Signé 2021-02-28 2021-03-04 2021-03-21 2021-03-08 2021-04-20 2021-03-16 accessoires, gonflables, avec Envelope Investments moteur à bord capable de transporter 5 personnes MR-MEDD-221613-GO-RFQ Component 3: Strengthening Single Stage - One / Acquisition de deux drones IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 8,016.59 Achevé 2021-02-28 2021-03-04 2021-03-21 2021-03-08 2021-04-11 2021-03-16 Envelope équipés au profit du PND Investments MR-MEDD-225619-GO-RFQ Component 2: Strengthening Single Stage - One En attente / Equipement de la salle de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-04-04 2021-05-24 2021-07-08 Envelope d'exécution réunion du MEDD Framework MR-MEDD-172827-GO-RFB / Acquisition d'équipements Component 2: Strengthening Single Stage - One de surveillance et de IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - International 0.00 Annulé 2020-08-18 2020-08-23 2020-10-04 2020-11-03 2020-12-08 2021-06-06 Envelope secourisme au profit de la Framework Direction de la Protection Civile MR-MEDD-200771-GO-RFB / Acquisition d'une ambulance Component 2: Strengthening équipée au Profit de la Single Stage - One IDA / 62150 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 Annulé 2020-11-30 2020-12-05 2021-01-16 2021-02-15 2021-03-22 2021-03-26 Délégation Générale de la Envelope Framework sécurité Civile et de la Gestion des crises au MIDEC MR-MEDD-200663-GO-RFQ Component 2: Strengthening / Acquisition d’équipements Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-11-04 2020-12-30 2021-02-13 au profit de la Police Envelope Framework Environnementale MR-MEDD-75959-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-12-10 2019-02-04 2019-08-03 pour l'observatoire national Envelope Framework du littoral mauritanien MR-MEDD-170405-GO-RFQ Component 2: Strengthening / Acquisition de matériel pour Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-06-16 2020-08-11 2020-09-25 la coordination du Master Envelope Framework GAED MR-MEDD-75978-GO-RFQ / Component 2: Strengthening Single Stage - One Acquisition d'équipements au IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-10-20 2018-12-15 2019-06-13 Envelope profit de l'ONM Framework Page 4 MR-MEDD-75988-GO-RFQ / Component 3: Strengthening Acquisition d'équipements Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-11-20 2019-01-15 2019-07-14 pour la fixation des dunes au Envelope Investments niveau de Chami MR-MEDD-74196-GO-RFQ / Component 3: Strengthening Achat de plants pour la Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-11-25 2019-01-20 2019-07-19 fixation biologique du cordon Envelope Investments dunaire de Diawling MR-MEDD-200674-GO-RFQ / Acquisition d’équipements Component 2: Strengthening Single Stage - One au profit du Port Autonome de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-11-15 2021-01-10 2021-07-09 Envelope Nouakchott, dit Port de Framework l’Amitié (PAN – PA) MR-MEDD-74193-GO-RFQ / Component 3: Strengthening Acquisition d'équipements et Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-10-13 2018-12-08 2019-06-06 de matériels de protection du Envelope Investments cordon dunaire de Diawling MR-MEDD-75979-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2018-11-20 2019-01-15 2019-07-14 pour l'opérationnalisation du Envelope Framework plan POLMAR MR-MEDD-75952-GO-RFQ / Component 3: Strengthening Equipements pour passages Single Stage - One IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2019-01-20 2019-03-17 2019-09-13 de franchissement du cordon Envelope Investments dunaire de NKTT MR-MEDD-200694-GO-RFQ / Acquisition de stations de Component 2: Strengthening Single Stage - One mesures topographiques et de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-11-28 2021-01-23 2021-03-09 Envelope GPS différentiels au profit de Framework la DPREM MR-MEDD-170352-GO-RFQ Component 2: Strengthening / Équipement du centre de Single Stage - One IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-07-01 2020-08-26 2020-10-10 documentation électronique Envelope Framework de la CNOEZA MR-MEDD-232476-GO-RFQ / Acquisition des équipements pour les Component 2: Strengthening Single Stage - One En attente Délégations Régionales de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-06-20 2021-08-09 2021-08-12 Envelope d'exécution l'Environnement (NDB, Framework INCHIRI, NKTT NORD ET TRARZA) MR-MEDD-238152-CW-RFQ / panneaux de signalisation Component 2: Strengthening sur les principaux sites du Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2021-08-15 2021-10-10 2022-04-08 projet au Envelope d'exécution Framework niveau du littoral de Nouakchott MR-MEDD-232502-GO-RFB / Acquisition de 7 véhicules au profit des Délégations Component 2: Strengthening Single Stage - One Régionales de l'environnement IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 Annulé 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-03-09 Envelope : NDB, INCHIRI, NKTT ET Framework TRARZA, et du Cabinet du MEDD MR-MEDD-249412-GO-RFB Component 2: Strengthening / Acquérir des équipements Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 2021-09-28 2021-10-03 2021-11-14 2021-12-14 2022-01-18 2022-04-18 pour la police Envelope d'exécution Framework environnementale MR-MEDD-249413-GO-RFB / Acquisition d'une station Component 2: Strengthening Single Stage - One En attente météorologique au profit de IDA / D2880 the Policy and Institutional A posteriori Appel d'offres Open - National 0.00 2021-10-12 2021-10-17 2021-11-28 2021-12-28 2022-02-01 2022-06-01 Envelope d'exécution l'Office National de la Framework Météorologie MR-MEDD-249415-GO-RFQ / Acquisition d'un groupe Component 3: Strengthening Single Stage - One En attente électrogène pour la base de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2021-10-23 2021-12-18 2022-03-18 Envelope d'exécution vie du Parc National de Investments Diawling (PND) MR-MEDD-249410-GO-DIR / Acquisition de 7 véhicules au profit des Délégations Component 2: Strengthening Passation de En attente Régionales de l'environnement IDA / D2880 the Policy and Institutional A posteriori marché de gré à Direct 0.00 2021-09-22 2021-09-27 2021-11-01 2021-12-16 d'exécution : NDB, INCHIRI, NKTT ET Framework gré TRARZA, et du Cabinet du MEDD NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / Collecte et transport sur sites Component 3: Strengthening Single Stage - One de matériaux de fixation IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 Annulé 2018-11-13 2019-04-02 2019-01-08 2019-07-07 Envelope mécanique de dunes au Investments niveau de Diawling MR-MEDD-170490-NC-RFQ Component 4: National Single Stage - One / Maintenance et suivi IDA / D2880 A posteriori Demande de prix Limited 18,116.74 Signé 2020-05-15 2020-03-05 2020-07-10 2020-03-11 2021-07-07 Coordination Envelope informatique MR-MEDD-170472-NC-DIR / Component 3: Strengthening Passation de Opérationnalisation du En attente IDA / D2880 National Physical and Social A posteriori marché de gré à Direct 0.00 2020-06-23 2020-07-08 2020-08-12 2021-02-08 mécanisme de gestion de d'exécution Investments gré plaintes (MGP) Page 5 MR-MEDD-200678-NC-RFQ Component 2: Strengthening Single Stage - One / Nettoyage de 35 villages au IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 Annulé 2020-11-28 2021-01-23 2021-03-09 Envelope PND Framework MR-MEDD-232496-NC-RFQ Component 3: Strengthening Single Stage - One En attente / Recruter une ONG IDA / D2880 National Physical and Social A posteriori Demande de prix Open - National 0.00 2021-07-28 2021-10-22 2022-10-19 Envelope d'exécution facilitatrice du MGP Investments CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS / Sélection fondée Component 2: Strengthening Elaboration de la directive sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 d'aménagement du littoral de qualifications des Framework NDB consultants Sélection fondée MR-MEDD-74184-CS-QCBS / Component 2: Strengthening sur les En attente Etude sur le classement de la IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 qualifications des d'exécution Baie de l'Etoile de NDB Framework consultants MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du Sélection fondée Component 2: Strengthening projet Ahmeyin/Guembeul sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 pour la production de gaz qualifications des Framework offshore en Mauritanie et au consultants Sénégal Sélection fondée MR-MEDD-74256-CS-CQS / Component 3: Strengthening sur les En attente Etude pour le franchissement IDA / D2880 National Physical and Social A posteriori Limited 0.00 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 qualifications des d'exécution du cordon dunaire de NKTT Investments consultants MR-MEDD-75957-CS-QCBS / Sélection fondée Component 2: Strengthening Evaluation des risques liés sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 aux inondations de la ville de qualifications des Framework NKTT consultants MR-MEDD-75958-CS-QCBS / Sélection fondée Component 2: Strengthening Elaboration de la directive sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 d'aménagement du littoral de qualifications des Framework NKTT consultants MR-MEDD-75960-CS-QCBS / Sélection fondée Component 2: Strengthening Elaboration d'une stratégie de sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 gestion intégrée du littoral qualifications des Framework mauritanien consultants MR-MEDD-75970-CS-QCBS / Sélection fondée Component 2: Strengthening Evaluation du capital sur les IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 sédimentologique de la ville qualifications des Framework de NKTT consultants MR-MEDD-115364-CS-CQS Sélection fondée / Etude de faisabilité pour la Component 3: Strengthening sur les réhabilitation et l'extension de IDA / D2880 National Physical and Social A posteriori Limited 0.00 Annulé 2019-05-27 2020-04-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 qualifications des la digue de protection au Investments consultants niveau du Diawling MR-MEDD-115676-CS-CQS Sélection fondée Component 3: Strengthening / Etude technique pour le sur les En attente IDA / D2880 National Physical and Social A posteriori Limited 0.00 2018-06-15 2018-06-29 2018-07-13 2018-08-10 2018-09-24 colmatage des brèches du qualifications des d'exécution Investments littoral de Nouakchott consultants MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet Sélection fondée Component 4: National En attente d'audit pour audit extezrne du IDA / D2880 A posteriori sur la qualité et le Open - National 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 Coordination d'exécution projet pour les années coût 2018 2019 2020 et 2021. MR-MEDD-124791-CS-INDV / etude sur la mise en place du système Waves pour le littoral et l'espace maritime : Component 2: Strengthening Sélection fondée evaluation des ecosystèmes IDA / D2880 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-09-12 2019-10-03 2019-11-16 2019-12-14 2020-01-13 2020-02-17 2020-03-23 2021-03-23 physiqueset monetaire pour la Framework coût selection des comptes du capital naturel côtier . MR-MEDD-135519-CS-QCBS / Etude environnementale Component 2: Strengthening Sélection fondée stratégique pour l'exploitation IDA / D2880 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2019-10-04 2019-10-06 2019-10-09 2019-10-14 2019-10-29 2019-11-03 2019-11-13 2019-12-13 du sable noir sur le littoral Framework coût mauritanien MR-MEDD-157694-CS-CQS Sélection fondée / Etude environnementale Component 2: Strengthening sur les En cours stratégique pour l'exploitation IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 2020-02-11 2020-02-06 2020-02-26 2020-04-10 2020-05-10 2020-06-14 2020-12-11 qualifications des d'exécution du sable noir sur le littoral Framework consultants mauritanien MR-MEDD-170561-CS-CQS Sélection fondée Component 2: Strengthening / Élaboration des directives sur les En cours IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 2020-05-11 2020-10-19 2020-06-01 2021-02-03 2020-07-15 2020-08-14 2020-09-18 2020-12-17 d’aménagement du littoral de qualifications des d'exécution Framework Nouakchott de Nouadhibou consultants MR-MEDD-170480-CS-INDV / Action pilote de recherche Sélection fondée Component 3: Strengthening (introduction de plantes sur les En attente IDA / D2880 National Physical and Social A posteriori Open - National 0.00 2020-07-15 2020-08-05 2020-09-18 2020-10-18 2020-11-22 2021-01-21 aquatiques, atténuation du PH qualifications des d'exécution Investments de l’eau,…) de la mare de consultants Riyad MR-MEDD-170427-CS-CQS Sélection fondée Component 2: Strengthening / Etude impact sur les IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 Annulé 2020-10-12 2020-08-03 2020-10-27 2020-12-10 2021-01-09 2021-02-13 2021-05-04 environnemental et social ( qualifications des Framework colmatage de brèches ) consultants Page 6 MR-MEDD-182813-CS-CQS / Réalisation de l'étude sur la Sélection fondée Component 3: Strengthening caractérisation des déchets sur les En attente IDA / D2880 National Physical and Social A posteriori Open - International 0.00 2020-09-23 2020-10-14 2020-11-27 2020-12-27 2021-01-31 2021-03-17 urbains à Nouadhibou et qualifications des d'exécution Investments proposition d'un système de consultants gestion approprié MR-MEDD-200765-CS-CQS / accompagnement de l'UGP et des structures beneficiaires Sélection fondée dans la mise en oeuvre des Component 4: National sur les En cours IDA / D2880 A posteriori Limited 0.00 2020-05-04 2021-05-24 2020-05-18 2020-06-17 2020-07-22 2021-01-18 activitesd Coordination qualifications des d'exécution investissement(identification consultants des sites screening environnemental reporting...) MR-MEDD-182699-CS-CQS / accompagnement de l'UGP et des structures beneficiaires Sélection fondée Component 2: Strengthening dans la mise en oeuvre des sur les IDA / D2880 the Policy and Institutional A posteriori Limited 0.00 Annulé 2020-07-01 2020-07-15 2020-08-14 2020-09-18 2020-12-17 activitesd qualifications des Framework investissement(identification consultants des sites screening environnemental reporting...) MR-MEDD-211477-CS-CQS Sélection fondée Component 3: Strengthening / Recrutement d'un cabinet sur les En attente IDA / D2880 National Physical and Social A posteriori Open - National 0.00 2021-02-05 2021-02-26 2021-04-11 2021-05-11 2021-06-15 2021-08-14 pour le Suivi des travaux de la qualifications des d'exécution Investments Digue Nord consultants MR-MEDD-228916-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour le choix d’un site sur les En cours IDA / D2880 National Physical and Social A posteriori Limited 0.00 2021-04-06 2021-06-17 2021-04-20 2021-05-20 2021-06-24 2021-12-21 d’Enfouissement Technique et qualifications des d'exécution Investments de traitement des ordures consultants ménagères à Nouakchott MR-MEDD-170566-CS-CQS / Étude pour la détermination Sélection fondée du trait de côte du littoral Component 2: Strengthening sur les mauritanien par images IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 qualifications des satellitaires avec quelques Framework consultants relevés du terrain par GNSS de N’Diago au Cap blanc MR-MEDD-170564-CS-CQS Sélection fondée Component 2: Strengthening / Etude pour l’évaluation des sur les IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 Annulé 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-10-20 risques liés aux inondations qualifications des Framework de Nouakchott et Nouadhibou consultants Sélection fondée MR-MEDD-192591-CS-CQS Component 2: Strengthening sur les / Etude de la bathymétrie et IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 Annulé 2020-09-15 2020-09-30 2020-10-15 2020-10-30 2020-12-04 2021-06-02 qualifications des de l'hydrométrie au PNBA Framework consultants MR-MEDD-76863-CS-QBS / élaboration de plans de Component 2: Strengthening Sélection fondée développement communaux IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 sur la qualité pour Tevragh Zeine ,sebkha et Framework Elmina MR-MEDD-76873-CS-QCBS / Component 2: Strengthening Sélection fondée Etude sur les pressions et IDA / D2880 the Policy and Institutional A posteriori sur la qualité et le Open - International 0.00 Annulé 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 enjeux exercés sur l'espace Framework coût vital du PNBA MR-MEDD-170392-CS-INDV Sélection fondée Component 2: Strengthening / Etude de faisabilité sur la sur les IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 Annulé 2020-05-20 2020-05-20 2020-06-10 2020-07-24 2020-08-23 2020-09-27 2020-12-26 délocalisation du site qualifications des Framework d'orpaillage de Chami consultants MR-MEDD-170573-CS-CQS Sélection fondée Component 3: Strengthening / Activités de renforcement de sur les IDA / D2880 National Physical and Social A posteriori Open - International 0.00 Annulé 2020-05-11 2020-07-06 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-09-15 la résilience des populations qualifications des Investments de N’Diago consultants MR-MEDD-232480-CS-CQS / Recrutement d’un Cabinet Sélection fondée Component 2: Strengthening pour réaliser un état des sur les En attente IDA / D2880 the Policy and Institutional A posteriori Limited 0.00 2021-06-14 2021-06-28 2021-07-13 2021-08-17 2021-11-15 connaissances et des données qualifications des d'exécution Framework disponibles sur le système consultants côtier (situation de référence MR-MEDD-232491-CS-CQS Sélection fondée Component 3: Strengthening / Recruter un bureau pour sur les En attente IDA / D2880 National Physical and Social A posteriori Open - National 0.00 2021-07-13 2021-08-03 2021-09-16 2021-10-16 2021-11-14 2022-02-12 assurer le contrôle et le suivi qualifications des d'exécution Investments des travaux de la digue consultants MR-MEDD-232494-CS-CQS / Élaborer une enquête statistique sur le nombre de Sélection fondée ménages situés sur le littoral Component 4: National sur les En attente ayant accès à des activités de IDA / D2880 A posteriori Open - National 0.00 2021-08-10 2021-08-31 2021-10-14 2021-11-13 2021-12-12 2022-03-12 Coordination qualifications des d'exécution substances améliorées et sur consultants le score du niveau de satisfaction des populations du littoral MR-MEDD-232505-CS-CQS / Recrutement d’un Cabinet pour Faire une modélisation Sélection fondée de la dynamique du littoral au Component 2: Strengthening sur les niveau du Port de N'Diago IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 En cours d'examen 2021-10-14 2021-08-13 2021-11-04 2021-12-18 2022-01-17 2022-02-21 2022-08-20 qualifications des pour mieux comprendre la Framework consultants problématique actuelle de l’érosion constatée et les mesures à prendre MR-MEDD-232513-CS-CQS / Recrutement d’un bureau Sélection fondée pour Elaborer une EIES pour la Component 2: Strengthening sur les En attente construction d'un Centre IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 qualifications des d'exécution d'Enfouissement Technique Framework consultants des déchets de la ville de Nouakchott Page 7 MR-MEDD-232504-CS-CQS / Recrutement d’un cabinet Sélection fondée Component 2: Strengthening pour réaliser un audit sur les IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 En cours d'examen 2021-09-15 2021-08-11 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-07-22 environnemental des usines qualifications des Framework de farine de poisson le long consultants du littoral MR-MEDD-232481-CS-CQS Sélection fondée / Recrutement d’un bureau de Component 3: Strengthening sur les En cours contrôle et de suivi des IDA / D2880 National Physical and Social A posteriori Open - National 0.00 2021-06-21 2021-06-21 2021-07-12 2021-08-25 2021-09-24 2021-10-29 2022-04-27 qualifications des d'exécution travaux de colmatage des 3 Investments consultants brèches (9, 13 et 16) MR-MEDD-232512-CS-CQS / Élaborer une étude de faisabilité (technique et Sélection fondée Component 2: Strengthening financière) pour la sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 2021-07-20 2021-08-10 2021-09-23 2021-10-23 2021-11-27 2022-05-26 construction d'un Centre qualifications des d'exécution Framework d'Enfouissement Technique consultants des déchets solides urbains de Nouakchott MR-MEDD-232514-CS-CQS / Recrutement d’un bureau pour Mener les études prioritaires nécessaires pour Sélection fondée (i) suivre l’impact du Component 2: Strengthening sur les En attente changement climatique sur le IDA / D2880 the Policy and Institutional A posteriori Open - International 0.00 2021-06-15 2021-07-06 2021-08-19 2021-09-18 2021-10-23 2022-01-21 qualifications des d'exécution littoral, (ii) faire une analyse Framework consultants historique de l’évolution du trait de côte et (iii) fournir les données essentielles aux évalu MR-MEDD-200679-CS-INDV Sélection fondée / Recrutement d'un formateur Component 2: Strengthening sur les pour la formation des IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 Annulé 2020-12-17 2021-01-07 2021-02-20 2021-03-22 2021-04-26 2021-05-26 qualifications des instituteurs en éducation Framework consultants environnementale au PND MR-MEDD-239559-CS-CQS Sélection fondée / Recrutement d'un consultent Component 3: Strengthening sur les En attente pour élaborer le dossier IDA / D2880 National Physical and Social A posteriori Open - National 0.00 2021-08-05 2021-08-26 2021-10-09 2021-11-08 2021-12-13 2022-06-11 qualifications des d'exécution technique pour la fixation de Investments consultants dune de littoral. MR-MEDD-246147-CS-CQS / Recrutement d’ ONGs pour assurer la formation des ONG Sélection fondée Component 3: Strengthening porteuses de Projet et le suivi sur les IDA / D2880 National Physical and Social A posteriori Limited 0.00 En cours d'examen 2021-08-09 2021-08-11 2021-08-23 2021-09-07 2021-10-06 2021-12-05 des Projets qualifications des Investments dans les communes littorales consultants de Nktt: Sebkha ,ElMina et TevraghZeine. MR-MEDD-249750-CS-CQS / Recrutement d'une ONG chargée de la mise en œuvre Sélection fondée du programme de Component 2: Strengthening sur les En attente sensibilisation sur les risques IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2021-09-15 2021-10-06 2021-11-19 2021-12-19 2022-01-23 2022-04-23 qualifications des d'exécution liés à l’utilisation des produits Framework consultants chimiques dans l’extraction artisanale de l’or pour le Wilaya Nouadhibou MR-MEDD-249823-CS-CQS / Recrutement d'un Bureau Sélection fondée d'étude pour le contrôle et le Component 4: National sur les En attente suivi des travaux de la IDA / D2880 A posteriori Open - National 0.00 2021-09-27 2021-10-18 2021-12-01 2021-12-31 2022-02-04 2023-02-01 Coordination qualifications des d'exécution construction du siège de consultants l'Observatoire du Littoral Mauritanien MR-MEDD-249756-CS-CQS / Recrutement d'un bureau Sélection fondée Component 2: Strengthening d'étude pour l'élaboration sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2021-10-13 2021-11-03 2021-12-17 2022-01-16 2022-02-20 2022-04-21 d'un cahier des charges qualifications des d'exécution Framework environnementales des usines consultants d'orpaillages INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de la Component 2: Strengthening capacité de tous les En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-17 2019-03-28 2018-08-22 2018-09-12 2018-10-17 2019-04-15 organismes concernés avec d'exécution Framework l'OLM (inclus consultations, séminaires, ateliers) MR-MEDD-74130-CS-INDV / Component 2: Strengthening En attente Elaboration des plans de IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-20 2018-08-25 2018-09-15 2018-10-20 2019-04-18 d'exécution résilience de N'Diago Framework MR-MEDD-74133-CS-INDV / Identification des actions Component 2: Strengthening prioritaires de l'antenne En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 nationale de la MOLOA (inclus d'exécution Framework consultations, ateliers, séminaires) MR-MEDD-74135-CS-INDV / Component 3: Strengthening Elaboration de textes IDA / D2880 National Physical and Social A posteriori Individuel Limited 14,000.00 Achevé 2018-11-02 2019-02-05 2018-11-07 2019-02-02 2018-11-28 2019-01-02 2019-02-25 2019-07-01 2020-02-10 juridiques relatifs aux Investments principes pollueur-payeurs Page 8 MR-MEDD-74137-CS-INDV / Conception et mise en place d'une plateforme de gestion Component 2: Strengthening environnementale relative à IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 l'évaluation des activités et le Framework suivi de leurs impacts environnementaux sur le littoral mauritanien MR-MEDD-74141-CS-INDV / Analyse du cadre foncier Component 2: Strengthening En cours relatif au littoral (inclus IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-15 2020-12-16 2018-10-20 2018-11-10 2018-12-15 2019-06-13 d'exécution consultations, séminaires, Framework ateliers) MR-MEDD-74152-CS-INDV / Component 2: Strengthening Elaboration de guide des En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 acteurs et des métiers du d'exécution Framework littoral mauritanien MR-MEDD-74153-CS-INDV / Revue et amendement du Component 2: Strengthening système des études d'impact IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 36,000.00 Signé 2018-10-01 2020-02-11 2018-10-06 2020-05-30 2018-10-27 2020-06-02 2018-12-01 2020-06-30 2019-05-30 environnemental en Framework Mauritanie MR-MEDD-74164-CS-INDV / Recrutement d'un assistant Component 2: Strengthening En attente technique au profit de IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 d'exécution l'Autorité de la Zone franche Framework de NDB MR-MEDD-74175-CS-INDV / Component 2: Strengthening Etat des lieux de En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-01 2018-12-20 2018-11-06 2018-11-27 2019-01-01 2019-06-30 l'environnement au niveau de d'exécution Framework la Zone franche de NDB MR-MEDD-74194-CS-INDV / Component 3: Strengthening Etudes de faisabilité des En cours IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-10-01 2018-11-24 2018-10-06 2018-10-27 2018-12-01 2019-05-30 travaux de fixation du cordon d'exécution Investments dunaire de Diawling MR-MEDD-74199-CS-INDV / Recrutement d'un consultant Component 3: Strengthening pour le suivi et le contrôle des IDA / D2880 National Physical and Social A posteriori Individuel Limited 9,240.00 Achevé 2018-11-05 2019-03-28 2018-11-10 2019-03-28 2018-12-01 2019-01-05 2019-03-28 2019-07-04 2019-04-02 travaux du cordon dunaire de Investments Diawling MR-MEDD-74200-CS-INDV / Component 3: Strengthening Elaboration d'une carte IDA / D2880 National Physical and Social A posteriori Individuel Limited 17,280.00 Achevé 2018-11-15 2019-03-28 2018-11-20 2019-03-28 2018-12-11 2019-01-15 2019-03-28 2019-07-14 2019-05-15 d'occupation des éco- Investments systèmes de mangroves MR-MEDD-75945-CS-INDV / Component 3: Strengthening En cours Etude pour le franchissement IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-10-01 2019-02-12 2018-10-06 2018-10-27 2018-12-01 2019-05-30 d'exécution du cordon dunaire de NKTT Investments MR-MEDD-75972-CS-INDV / Component 2: Strengthening En attente Conception et mise en place IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-05 2018-11-10 2018-12-01 2019-01-05 2019-07-04 d'exécution d'un site web pour l'OLM Framework MR-MEDD-76164-CS-INDV / Component 2: Strengthening En attente Recrutement d'un Comptable IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 d'exécution pour le Projet Framework MR-MEDD-76422-CS-INDV / Component 4: National En cours Recrutement d'un auditeur IDA / D2880 A posteriori Individuel Limited 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Coordination d'exécution interne MR-MEDD-76867-CS-INDV / Component 3: Strengthening Mise à jour du SIG de la IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 Région de Nouakchott Investments MR-MEDD-76868-CS-INDV / Component 3: Strengthening Adaptation du fonds IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 d'Investissement communal Investments (région de NKTT) MR-MEDD-82701-CS-INDV / recrutement d'un consultant Component 2: Strengthening national pour l'appui à l'étude En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 de faisabilité du projet WACA- d'exécution Framework CCA en Mauritanie MR-MEDD-82704-CS-INDV / Component 2: Strengthening En attente réalisation d'un documentaire IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 d'exécution sur la baie de l'étoile Framework MR-MEDD-82731-CS-INDV / Component 4: National En attente Maintenance et suivi IDA / D2880 A posteriori Individuel Limited 0.00 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Coordination d'exécution informatique MR-MEDD-82737-CS-INDV / accompagnement de l'UGP et des structures beneficiaires Component 3: Strengthening dans la mise en oeuvre des IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 activitesd Investments investissement(identification des sites screening environnemental reporting...) MR-MEDD-76859-CS-NPO / Component 3: Strengthening En attente Mise en place d'un système de IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 d'exécution Gestion de plaintes Investments MR-MEDD-76166-CS-INDV / Component 2: Strengthening Recrutement d'un IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 9,600.00 Signé 2018-09-05 2019-03-18 2018-09-10 2018-07-26 2018-10-01 2018-11-05 2019-07-31 2019-05-04 Responsable de Suivi- Framework Evaluation Page 9 MR-MEDD-76167-CS-INDV / Component 2: Strengthening En attente Recrutement d'un Spécialiste IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 d'exécution en communication Framework MR-MEDD-76173-CS-INDV / Component 2: Strengthening Recrutement en IDA / D2880 the Policy and Institutional A posteriori Individuel Open 9,600.00 Signé 2018-09-05 2019-07-25 2018-10-24 2019-07-25 2018-11-14 2018-12-19 2019-08-01 2019-06-17 Développement Institutionnel Framework MR-MEDD-76168-CS-INDV / Component 2: Strengthening Recrutement d'un Spécialiste En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 en Développement Social, d'exécution Framework sauvegarde sociale et genre MR-MEDD-76158-CS-INDV / Component 2: Strengthening Recrutement Coordinateur du IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 4,320.00 Signé 2018-08-29 2017-09-28 2018-09-03 2017-09-28 2018-09-24 2017-09-28 2018-10-29 2020-01-02 2019-04-27 Projet WACA Framework MR-MEDD-76160-CS-INDV / Component 2: Strengthening Recrutement d'un IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 3,520.00 Signé 2018-08-29 2018-02-01 2018-09-03 2018-02-01 2018-09-24 2018-10-29 2018-05-02 2019-04-27 Coordinateur-Adjoint juriste Framework pour le Projet WACA MR-MEDD-76162-CS-INDV / Component 2: Strengthening Recrutement d'un IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 1,600.00 Signé 2018-08-29 2018-06-28 2018-09-03 2018-06-28 2018-09-24 2018-10-29 2018-08-02 2019-04-27 Responsable de Passation des Framework Marchés MR-MEDD-115334-CS-INDV / Elaboration des TDR de Component 2: Strengthening l'étude de détermination du En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2019-05-30 2019-10-01 2019-06-12 2019-06-14 2019-06-18 2019-07-08 trait de côte du Littoral d'exécution Framework mauritanien par GNSS de N'Diago au Cap blanc MR-MEDD-115272-CS-INDV Component 2: Strengthening / Etude pour l'élaboration IDA / D2880 the Policy and Institutional A posteriori Individuel Open 23,826.67 Achevé 2019-05-30 2019-06-07 2019-06-13 2019-06-13 2019-06-15 2019-06-18 2019-06-21 2019-06-27 2019-08-05 2019-09-05 d'une stratégie et d'un plan de Framework communication pour le Projet MR-MEDD-115327-CS-INDV / L'élaboration d'une étude Component 3: Strengthening d'identification de sous- IDA / D2880 National Physical and Social A posteriori Individuel Open 21,493.34 Achevé 2019-05-30 2019-06-12 2019-06-11 2019-06-13 2019-06-13 2019-06-17 2019-06-27 2019-07-27 2019-09-05 projets dans les communes Investments littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de Component 3: Strengthening prescriptions techniques pour IDA / D2880 National Physical and Social A posteriori Individuel Open 7,466.67 Signé 2019-05-30 2019-10-02 2019-06-12 2019-06-13 2019-06-17 2019-06-18 2019-06-20 2019-06-27 2019-07-16 le colmatage des brèches du Investments cordon dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Etat des lieux du foncier du IDA / D2880 the Policy and Institutional A posteriori Individuel Open 24,773.34 Achevé 2019-05-30 2019-10-01 2019-06-11 2019-09-05 2019-06-13 2019-09-05 2019-06-17 2019-09-09 2019-08-16 2019-11-21 littoral de N'Diago et de la Framework Zone Franche de Nouadhibou MR-MEDD-124792-CS-INDV / Inventaire des textes Component 2: Strengthening juridiques relatifs à la gestion IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 des zones côtières et marines Framework et ratifications des protocoles de la convention d'Abidjan. MR-MEDD-129310-CS-CQS / Opérationalisation et Mise Component 3: Strengthening Sélection de En cours en place d'un système de IDA / D2880 National Physical and Social A posteriori consultants par Direct 0.00 2019-09-24 2019-10-01 2019-09-27 2019-10-02 2020-03-30 d'exécution gestion de plaintes pour le Investments entente directe Projet WACA MR-MEDD-74150-CS-INDV / Analyse et révision de Component 2: Strengthening l'ordonnance relative au IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2019-10-22 2019-11-15 2019-11-20 2019-11-30 2020-01-09 littoral et élaboration des Framework textes d'application MR-MEDD-149021-CS-INDV / Recrutement d'un consultant pour une mission d'assistance pour la saisie, sur le STEP, de Component 1: Strengthening En attente IDA / D2880 A posteriori Individuel Limited 0.00 2019-12-09 2019-12-11 2019-12-13 2019-12-17 2020-01-01 l’ensemble des marchés Regional Integration d'exécution passés par les Projets PGDP et WACA/Mauritanie au cours de l’exercice 2019. MR-MEDD-170446-CS-INDV Component 3: Strengthening En cours / suivi des travaux de fixation IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2020-05-29 2020-06-24 2020-06-13 2020-07-04 2020-08-08 2020-09-22 d'exécution des dunes au Diawling Investments MR-MEDD-170469-CS-INDV / Elaboration de l’étude d’impact environnemental ou Component 3: Strengthening En cours de notice d’impact IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-07-06 2020-11-11 2020-08-24 2021-05-26 2020-09-14 2021-05-26 2020-10-19 2021-04-17 d'exécution environnemental pour Investments l’extension de la digue Nord du PND MR-MEDD-170484-CS-INDV Component 3: Strengthening En cours / Expert Côtier (gestion IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-05-15 2020-07-09 2020-07-03 2020-07-24 2020-08-28 2021-08-25 d'exécution intégrée des zones costières ) Investments MR-MEDD-170486-CS-INDV / Expert en système de Component 3: Strengthening gestion de l'information En cours IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-06-15 2020-08-18 2020-08-04 2020-08-25 2020-09-29 2020-12-28 environnementale pour le d'exécution Investments littoral (Système de données et d'information) MR-MEDD-170488-CS-INDV Component 4: National En cours / Spécialiste en sauvegarde IDA / D2880 A posteriori Individuel Open 0.00 2020-06-22 2020-05-20 2020-08-10 2020-08-31 2020-10-05 2021-01-03 Coordination d'exécution environnementalement Page 10 MR-MEDD-170410-CS-INDV Component 2: Strengthening En cours / Révision de l'ordonnance du IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2020-08-17 2021-08-05 2020-10-05 2020-10-26 2020-11-30 2021-01-29 d'exécution littoral Framework MR-MEDD-170431-CS-INDV / Élaboration APS, APD et DAO Component 3: Strengthening En cours pour passage de IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-10-13 2020-09-10 2020-12-01 2021-06-01 2020-12-22 2021-06-02 2021-01-26 2021-04-26 d'exécution franchissement du cordon Investments dunaire MR-MEDD-170466-CS-INDV Component 3: Strengthening / Elaboration des études (APS, IDA / D2880 National Physical and Social A posteriori Individuel Open 26,669.01 Signé 2020-07-20 2020-05-08 2020-09-07 2020-06-02 2020-09-28 2020-06-02 2020-11-02 2020-06-24 2021-05-01 APD, DAO) de l’extension de Investments la digue Nord du PND MR-MEDD-170420-CS-INDV Component 2: Strengthening En attente / Révision du décret portant IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2020-06-08 2020-07-27 2020-08-17 2020-09-21 2020-11-05 d'exécution création du FIE Framework MR-MEDD-170408-CS-INDV Component 2: Strengthening / Analyse de l'ordonnance du IDA / D2880 the Policy and Institutional A posteriori Individuel Open 31,898.11 Signé 2020-05-11 2020-06-23 2020-06-29 2020-08-24 2020-07-20 2020-09-02 2020-08-24 2020-09-17 2020-10-08 littoral Framework MR-MEDD-170478-CS-INDV Component 3: Strengthening / Elaboration du Plan de En cours IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-08-17 2021-05-24 2020-10-05 2021-05-17 2020-10-26 2021-05-24 2020-11-30 2021-05-29 gestion et d’exploitation de la d'exécution Investments mare de Riyad MR-MEDD-170430-CS-INDV Component 3: Strengthening / Etude pour la préparation du En attente IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2020-06-22 2020-08-10 2020-08-31 2020-10-05 2021-01-03 dossier technique pour la d'exécution Investments fixation des dunes MR-MEDD-170476-CS-INDV / Réalisation de l’étude sur la Component 3: Strengthening caractérisation des déchets IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2020-08-10 2020-06-03 2020-09-28 2020-10-19 2020-11-23 2021-01-22 urbains à NDB et proposition Investments d’un système de gestion approprié MR-MEDD-183319-CS-CDS / Complément à l'étude relative Component 3: Strengthening Sélection de En attente à l'identification de sous- IDA / D2880 National Physical and Social A posteriori consultants par Direct 0.00 2020-07-08 2020-07-18 2020-07-28 2020-08-04 d'exécution projets sociaux dans les Investments entente directe communes littorales MR-MEDD-192575-CS-INDV Component 3: Strengthening / Etude impact En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2020-09-21 2020-09-26 2020-10-11 2020-11-15 2020-12-30 environnemental et social d'exécution Investments (colmatage de brèches) MR-MEDD-170422-CS-INDV Component 2: Strengthening / Etude de la bathymétrie et IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-08-18 2020-09-05 2020-10-06 2020-10-27 2020-12-01 2021-03-01 de l'hydrométrie au PNBA Framework MR-MEDD-200735-CS-INDV / Recrutement d’un Expert Component 2: Strengthening En attente d’appui pour la restauration et IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-10 d'exécution la valorisation des Mangroves Framework et du Sporobolus MR-MEDD-200747-CS-INDV / Recrutement d'un Expert Component 2: Strengthening En cours International en gestion du IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2020-12-15 2020-11-24 2021-02-02 2021-02-23 2021-03-30 2021-07-28 d'exécution Littoral pour un appui à la Framework DPREM MR-MEDD-200770-CS-CDS / Sélection de Recrutement d’un Consultant Component 4: National En attente IDA / D2880 A posteriori consultants par Direct 0.00 2020-09-15 2020-09-25 2020-10-20 2020-12-04 pour la formation sur STEP Coordination d'exécution entente directe avec une assistance pour STEP MR-MEDD-203246-CS-INDV Component 4: National En cours / Recrutement d’un IDA / D2880 A posteriori Individuel Limited 0.00 2020-09-10 2020-04-23 2020-09-15 2020-10-06 2020-11-10 2021-05-09 Coordination d'exécution Coordinateur Adjoint MR-MEDD-207334-CS-INDV / Etude de faisabilité de la Component 3: Strengthening En cours restauration et de la IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2020-12-04 2020-12-14 2020-12-09 2020-12-19 2021-01-14 2021-02-13 d'exécution valorisation de mangroves au Investments PND MR-MEDD-209747-CS-INDV / Recrutement de consultant (e) individuel (le) pour la réalisation d’une Notice Component 2: Strengthening En cours d’Impact Environnemental et IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2020-12-22 2020-12-23 2020-12-27 2020-01-20 2021-01-17 2021-01-29 2021-02-21 2021-04-22 d'exécution Social (NIES) pour la Framework construction du bâtiment devant abriter l’Observatoire du Littoral mauritanien (OLM). MR-MEDD-211476-CS-INDV / Recrutement d'un Chef Component 4: National IDA / D2880 A posteriori Individuel Open 0.00 Annulé 2021-01-15 2021-03-05 2021-03-26 2021-04-30 2022-04-27 comptable pour le Projet Coordination WACA -Mauritanie Component 3: Strengthening MR-MEDD-217842-CS-INDV En cours IDA / D2880 National Physical and Social A posteriori Individuel Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-16 2021-02-20 2021-05-21 / Comptable du PGDP d'exécution Investments MR-MEDD-217844-CS-INDV Component 3: Strengthening En cours / Conseiller technique du IDA / D2880 National Physical and Social A posteriori Individuel Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-13 2021-02-16 2021-05-17 d'exécution Coordinateur du PGDP Investments Component 3: Strengthening MR-MEDD-217850-CS-INDV En cours IDA / D2880 National Physical and Social A posteriori Individuel Direct 0.00 2021-02-09 2021-02-15 2021-02-11 2021-02-14 2021-02-19 2021-05-20 / Expert SIG du PGDP d'exécution Investments Page 11 MR-MEDD-218369-CS-INDV Component 4: National En cours / Recrutement de l'Expert en IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-05-23 2021-02-17 2021-02-20 2021-02-24 2022-02-24 Coordination d'exécution suivi/évaluation MR-MEDD-218371-CS-INDV Component 4: National En cours / Recrutement de l'Auditeur IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-05-23 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination d'exécution Interne MR-MEDD-218374-CS-INDV Component 4: National / Recrutement du Spécialiste IDA / D2880 A posteriori Individuel Direct 0.00 Annulé 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination de Passation des Marchés MR-MEDD-218375-CS-INDV Component 4: National En cours / Recrutement de l'assistant IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination d'exécution en passation de marchés MR-MEDD-218377-CS-INDV / Recrutement du spécialiste Component 4: National En cours IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 en Sauvegarde Sociale, Société Coordination d'exécution Civile et Genre MR-MEDD-218381-CS-INDV Component 4: National En cours / Recrutement d'un Spécialiste IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-05-24 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination d'exécution en Communication MR-MEDD-218382-CS-INDV Component 4: National En cours / Recrutement de IDA / D2880 A posteriori Individuel Direct 0.00 2021-02-15 2021-02-15 2021-02-17 2021-02-19 2021-02-23 2022-02-23 Coordination d'exécution Coordinateur (ce) du Projet MR-MEDD-219143-CS-INDV Component 4: National En cours / Recrutement d'un comptable IDA / D2880 A posteriori Individuel Limited 20,016.68 2021-02-11 2021-03-19 2021-02-16 2021-02-25 2021-03-09 2021-02-01 2021-04-13 2021-10-10 Coordination d'exécution en chef pour l'UGP MR-MEDD-225611-CS-INDV / Recrutement d'un Consultant Individuel pour le Component 4: National En cours déroulement sur STEP des IDA / D2880 A posteriori Individuel Direct 0.00 2021-03-22 2021-03-23 2021-04-01 2021-04-22 2021-05-21 2021-06-20 Coordination d'exécution activités du Projet PGDP pour les exercices 2019,2018 et 2017. MR-MEDD-200742-CS-INDV Component 2: Strengthening / Recrutement d’un IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-12-25 2020-12-30 2021-01-20 2021-02-24 2021-04-25 consultant pour compléter Framework l’étude sur la Baie de l’Etoile MR-MEDD-74185-CS-INDV / Component 2: Strengthening Actualisation du plan IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 d'aménagement et de gestion Framework de la Baie de l'Etoile de NDB MR-MEDD-200710-CS-INDV / Recrutement d’un Component 2: Strengthening Consultant pour compléter le IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-11-23 2020-11-28 2020-12-19 2021-01-23 2021-03-24 guide des acteurs et métiers Framework du littoral MR-MEDD-170414-CS-INDV / Élaboration du décret Component 2: Strengthening portant modalités du IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-05-11 2020-05-16 2020-06-06 2020-07-11 2020-10-09 fonctionnement de Framework l'observatoire du littoral MR-MEDD-170415-CS-INDV Component 2: Strengthening / Révision du décret portant IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-05-18 2020-05-23 2020-06-13 2020-07-18 2020-09-01 création du conseil consultatif Framework du littoral MR-MEDD-74187-CS-INDV / Component 3: Strengthening Etude relative à la mise en IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 place de l'éco-loge Investments MR-MEDD-170403-CS-INDV / Élaboration du Plan de Component 2: Strengthening Gestion Environnementale et IDA / D2860 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-05-25 2020-07-13 2020-08-03 2020-09-07 2020-11-06 Sociale de la Zone Franche de Framework Nouadhibou MR-MEDD-74191-CS-INDV / Component 2: Strengthening Elaboration d'une carte de IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 potentialités de la Zone Framework franche de NDB MR-MEDD-170401-CS-INDV Component 2: Strengthening / Élaboration d'une carte de IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-08-25 2020-10-13 2020-11-03 2020-12-08 2021-06-06 potentialités pour la zone Framework Franche de NDB MR-MEDD-170174-CS-INDV / Recrutement d'une assistance technique pour Component 2: Strengthening l'intégration de la dimension IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2020-12-27 résilience climatique dans Framework l'ensemble des stratégies du littoral MR-MEDD-74190-CS-INDV / Component 3: Strengthening Elaboration d'un plan de IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 Annulé 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 gestion environnementale et Investments sociale du site de l'éco-loge MR-MEDD-170425-CS-INDV / Etude sur l'état des lieux et Component 2: Strengthening le mapping des bases de IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-07-20 2020-09-07 2020-09-28 2020-11-02 2021-05-01 données et systèmes Framework géographiques des zones côtières de la Mauritanie Page 12 MR-MEDD-74174-CS-INDV / Component 2: Strengthening Actualisation du schéma IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 opérationnel de la Zone Framework franche de NDB MR-MEDD-200714-CS-INDV / Recrutement d’un Consultant pour l’élaboration du décret portant modalités Component 3: Strengthening du fonctionnement de IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2020-11-30 2020-12-05 2020-12-26 2021-01-30 2021-02-05 l’Observatoire du Littoral et la Investments révision du décret portant création du Conseil Consultatif du Littoral MR-MEDD-124785-CS-INDV / etude sur l'état des lieux et Component 2: Strengthening le mapping des bases de IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 donnees et SIG des zones Framework côtières et arides de la mauritanie. MR-MEDD-74154-CS-INDV / Rédaction des termes de Component 2: Strengthening référence de l'étude relative IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 aux plans de résilience de Framework N'Diago (inclus consultations, ateliers, séminaires) MR-MEDD-137101-CS-INDV / sélection d'un consultant Component 3: Strengthening pour préparer le dossier IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2019-10-08 2019-10-13 2019-10-20 2019-10-23 2019-12-22 relatif aux fixations des dunes Investments du littoral MR-MEDD-200737-CS-INDV / Recrutement d’un Component 2: Strengthening consultant pour adapter le IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-12-24 2020-12-29 2021-01-19 2021-02-23 2021-04-24 guide de bonnes pratiques Framework /pestes et pesticides MR-MEDD-74192-CS-INDV / Component 3: Strengthening Evaluation des risques IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 d'inondations pour la ville de Investments NBD MR-MEDD-170396-CS-INDV Component 2: Strengthening / Etat de lieu de la pollution IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 métallique dans le milieu Framework littoral de la baie du Lévrier MR-MEDD-158682-CS-INDV Component 2: Strengthening / étude de faisabilité de la IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-02-13 2020-04-02 2020-04-23 2020-05-28 2020-11-24 délocalisation du Centre de Framework traitement de l'or de Chami MR-MEDD-74172-CS-INDV / Component 2: Strengthening Analyse du schéma IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-01-29 2020-02-10 2020-03-18 2020-04-08 2020-05-13 2020-07-12 opérationnel de la Zone Framework franche de NDB MR-MEDD-82696-CS-INDV / Component 2: Strengthening recrutement d'un consultant IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2018-10-31 2018-11-20 2018-11-05 2018-11-26 2018-12-31 2019-06-29 pour appuyer la cellule Framework Changement Climatique MR-MEDD-170400-CS-INDV / Etude pour réaliser un état des lieux des capacités des Component 2: Strengthening usines de production de farine IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 Annulé 2020-07-15 2020-08-18 2020-09-02 2020-09-23 2020-10-28 2021-01-26 de poisson d'Elbountiya en Framework matière de gestion environnementale MR-MEDD-157985-CS-INDV Component 2: Strengthening / Etude de faisabilité de la IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 Annulé 2020-02-10 2020-02-19 2020-02-15 2020-02-26 2020-03-11 2020-04-10 délocalisation du centre de Framework traitement de l'or à Chami MR-MEDD-232477-CS-INDV / Recrutement d’un Component 4: National En attente IDA / D2880 A posteriori Individuel Open 0.00 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-09-04 spécialiste en développement Coordination d'exécution institutionnel MR-MEDD-232478-CS-INDV Component 2: Strengthening En cours / Recrutement d’un juriste en IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2021-06-15 2021-07-19 2021-06-20 2021-07-11 2021-08-15 2022-02-11 d'exécution appui au MEDD Framework MR-MEDD-232483-CS-INDV / Recrutement d’un Component 3: Strengthening consultant Individuel pour En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2021-12-12 Faire le contrôle et le suivi des d'exécution Investments travaux de fixation des dunes du littoral MR-MEDD-232484-CS-INDV / Un Consultant Individuel Component 3: Strengthening En attente pour assurer le suivi des IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2021-06-28 2021-07-03 2021-07-24 2021-08-28 2022-02-24 d'exécution travaux de franchissement et Investments de construction de bacs MR-MEDD-232492-CS-INDV Component 3: Strengthening En attente / Élaborer un plan genre pour IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2021-07-20 2021-09-07 2021-09-28 2021-10-27 2022-01-25 d'exécution le projet Investments MR-MEDD-232493-CS-INDV Component 3: Strengthening / faire une évaluation En attente IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2021-07-19 2021-09-06 2021-09-27 2021-11-01 2022-01-30 environnementale et sociale d'exécution Investments des sous projets sociaux Page 13 MR-MEDD-232495-CS-INDV / Recrutement d’un Component 4: National En cours IDA / D2880 A posteriori Individuel Open 0.00 2021-08-10 2021-06-21 2021-09-28 2021-10-19 2021-11-17 2022-02-15 Consultant pour l’évaluation à Coordination d'exécution mi-parcours MR-MEDD-232497-CS-INDV / Evaluer les besoins (études, Component 3: Strengthening données à acquérir) et définir En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-01-13 les indicateurs de suivi pour d'exécution Investments une meilleure compréhension de l’évolution du littoral MR-MEDD-232498-CS-INDV / Un Consultant Individuel Component 2: Strengthening En attente pour Définir les objectifs, le IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2021-07-20 2021-09-07 2021-09-28 2021-11-02 2022-01-31 d'exécution cadre et le contenu de Framework l’Observatoire du Littoral MR-MEDD-236658-CS-INDV / Recrutement du Spécialiste Component 4: National En cours IDA / D2880 A posteriori Individuel Open 0.00 2021-06-04 2021-06-02 2021-07-23 2021-08-11 2021-08-13 2021-09-17 2022-09-14 de Passation des Marchés du Coordination d'exécution Projet WACA-Mauritanie MR-MEDD-200718-CS-INDV / Recrutement d’un Component 3: Strengthening Consultant pour l’élaboration IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 Annulé 2020-11-30 2021-06-10 2020-12-05 2020-12-26 2021-01-30 2021-03-31 du dossier technique pour la Investments fixation des dunes du Littoral MR-MEDD-249821-CS-INDV / RECRUTEMENT D’UN CONSULTANT Component 2: Strengthening INTERNATIONAL INDIVIDUEL En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Direct 0.00 2021-09-15 2021-09-25 2021-10-16 2021-11-20 2022-01-04 POUR L’ELABORATIOND’UNE d'exécution Framework LOI SUR L’EVALUATION D’IMPACT ENVIRONNEMENTAL EN MAURITANIE MR-MEDD-249825-CS-INDV / Recrutement d'un Consultant Individuel pour Component 2: Strengthening l'élaboration d'une Notice En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2021-09-15 2021-11-03 2021-11-24 2021-12-29 2022-03-29 d'Impact et Environnementale d'exécution Framework Sociale pour l'addiction de l'eau potable du Parc National de Diawling (PND) Page 14