Page 1 SAINT LUCIA HIV/AIDS PREVENTION AND CONTROL PROCUREMENT PLAN - WORKS ICB-International Competitive Bidding; NCB-National Competitive Bidding [NCB 2 is without prior review]; SW- small works [<150,000US$]; NS-National Shopping; LIB-Limited International Bidding; DC-Direct Contracting Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award Elapsed weeks ICB 10 10 45 90 15 NCB 10 10 30 60 15 NCB2 0 0 30 30 0 LIB 10 10 45 60 15 SW 0 0 20 20 10 NS 0 0 20 20 0 DC 10 10 30 30 10 Description Bid Number Prior Review of Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award A. Strengthening the health sector response to HIV/AIDS (component 3) SLU/HIV-SW- VCTC Prior review SW Estimated 120,000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 11-Jul-2005 Actual Post review SW Estimated 57,000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 11-Jul-2005 Actual SLU/HIV-SW- STIC Post review SW Estimated 90,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 11-May-2005 Actual TOTAL COMPONENTES 267,000 TABLE 2: WORKS -- Time Table of Procurement Actions Civil works (rehabilitation) (4-yr1) VTC Centers Refurbishment of Central Med. Store (civil works) Refurbishment of STI clinics (2 Year 1, + 1 in 6 months) 18,000 each SLU/HIV-SW- CMS Page 2 Contract Signature Contract End (delivery) Supplier or Contractor Name 15 15 15 15 3 3 3 Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 21-Jul-2005 19-Jul-2006 360.00 21-Jul-2005 19-Jul-2006 360.00 21-May-2005 15-Nov-2006 540.00 Page 3 SAINT LUCIA HIV/AIDS PREVENTION AND CONTROL PROCUREMENT PLAN - CONSULTING SERVICES FOR EIGHTEEN (18) MONTHS IC-Individual Consulting; CQ-Consultants' Qualification; SS-Single Source; QCBS-Quality Cost Based Selection (N= National, I= International); QBS-Quality Based Selection; LCS-Least Cost Selection * Retroactive financing will be used as the FTAL is not expected to be effective until November 2003. Description Bid Number Prior Review or Post Review Method of Selection Estimated Vs. Actual Elapsed weeks Amount in US$ Request for GPN in UNDB Advertise date in UNDB Request for proposals ready No Object. to RFP Closing date for proposals No Object. Technical Evaluation No Object. Final Evaluation QCBS I 10 30 15 45 30 15 20 QCBS N 0 30 15 30 30 15 20 IC 0 10 0 15 0 0 0 SS 0 10 0 15 0 0 0 CQ 0 10 0 20 0 0 0 LCS 0 10 0 20 0 0 0 FBS 0 10 0 20 0 0 0 QBS 10 30 15 45 30 15 20 Description Bid Number Prior Review or Post Review Method of Selection Estimated Vs. Actual Elapsed weeks Amount in US$ Request for GPN in UNDB Advertise date in UNDB Request for proposals ready No Object. to RFP Closing date for proposals No Object. Technical Evaluation No Object. Final Evaluation A. Strengthening the health sector response to HIV/AIDS (component 3) Post review CQ Estimated 6,000 3-Jul-05 3-Jul-2005 13-Jul-2005 13-Jul-2005 2-Aug-2005 2-Aug-2005 2-Aug-2005 Actual Post review IC Estimated 35,000 17-May-05 17-May-2005 27-May-2005 27-May-2005 11-Jun-2005 11-Jun-2005 11-Jun-2005 Actual Post review IC Estimated 35,000 17-May-05 17-May-2005 27-May-2005 27-May-2005 11-Jun-2005 11-Jun-2005 11-Jun-2005 Actual Post review IC Estimated 24,000 17-Apr-05 17-Apr-2005 27-Apr-2005 27-Apr-2005 12-May-2005 12-May-2005 12-May-2005 Actual Prior review IC Estimated 90,000 15-Feb-05 15-Feb-2005 25-Feb-2005 25-Feb-2005 12-Mar-2005 12-Mar-2005 12-Mar-2005 Actual Counselors (Consultants) Grade 13 : (4-yr1+ 3 year 2, ) @ 13000 each SLU/HIV-C-C Post review IC Estimated 143,000 15-Feb-05 15-Feb-2005 25-Feb-2005 25-Feb-2005 12-Mar-2005 12-Mar-2005 12-Mar-2005 Prior review SS Estimated 5,600 17-Apr-05 17-Apr-2005 27-Apr-2005 27-Apr-2005 12-May-2005 12-May-2005 12-May-2005 Actual Prior review SS Estimated 16,500 17-Apr-05 17-Apr-2005 27-Apr-2005 27-Apr-2005 12-May-2005 12-May-2005 12-May-2005 Actual Post review IC Estimated 12,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual B. Civil society initiatives (component 1) Grants (demand driven) First Con Prior Revie SS Estimated 200,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Several contracts / DC with CSOs/ Competitive proced. Above 10,000 per contract (18 months) Actual SLU/HIV-C-SDP- VTC Supply and distribution of protocol for VCT (Consultancy) -40 copies (1 year) Social Worker (Consultants) - Grade 13 SLU/HIV-C-CW 02 SLU/HIV-C-RS Airtime for TV 77 units @ $48/unit. ($3700/yr) (18 months) Radio spots (104* 5 stations/year) (11,000$/year)- 2/week/station (18 months) Clinical Coordinator Consultancy- Grade 17 (2 Years) SLU/HIV-C-CCC SLU/HIV-C-ATV TABLE 1: Consultant Services -- Time Table of Procurement Actions Treatment protocols reviews and updates (consultancy) Int. (2 Years) SLU/HIV-C-CW 01 SLU/HIV-C-CSA SLU/HIV-C-TPR Social Worker (Consultants) - Grade 13 (1 Year) Consultancy services for adherence (international) (1 Year) Page 4 Post review CQ Estimated 24,000 1-Jul-05 1-Jul-2005 11-Jul-2005 11-Jul-2005 31-Jul-2005 31-Jul-2005 31-Jul-2005 Actual Post review CQ Estimated 15,000 1-Jul-05 1-Jul-2005 11-Jul-2005 11-Jul-2005 31-Jul-2005 31-Jul-2005 31-Jul-2005 Actual Post review IC Estimated 8,500 17-Apr-05 17-Apr-2005 27-Apr-2005 27-Apr-2005 12-May-2005 12-May-2005 12-May-2005 Actual D. Strengthening institutional capacity for program management (Component 4) Post review QCBS N Estimated 112,020 1-May-05 1-May-2005 31-May-2005 15-Jun-2005 15-Jul-2005 14-Aug-2005 29-Aug-2005 Actual Post review CQ Estimated 12,000 2-Apr-05 2-Apr-2005 12-Apr-2005 12-Apr-2005 2-May-2005 2-May-2005 2-May-2005 Actual Broad band installation & annual connectivity Post review CQ Estimated 7,600 2-Apr-05 2-Apr-2005 12-Apr-2005 12-Apr-2005 2-May-2005 2-May-2005 2-May-2005 Also SS permitted with Prior Review (1 Year) Actual Post review IC Estimated 40,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Post review IC Estimated 45,000 17-May-05 17-May-2005 27-May-2005 27-May-2005 11-Jun-2005 11-Jun-2005 11-Jun-2005 Actual Prior review QCBS I Estimated 200,000 5-May-05 15-May-2005 14-Jun-2005 29-Jun-2005 13-Aug-2005 12-Sep-2005 27-Sep-2005 Actual Post review IC Estimated 22,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Post review IC Estimated 12,000 18-Jul-05 18-Jul-2005 28-Jul-2005 28-Jul-2005 12-Aug-2005 12-Aug-2005 12-Aug-2005 Actual Post review IC Estimated 12,000 17-Nov-05 17-Nov-2005 27-Nov-2005 27-Nov-2005 12-Dec-2005 12-Dec-2005 12-Dec-2005 Actual Post review IC Estimated 38,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Prior review IC Estimated 54,000 15-Feb-05 15-Feb-2005 25-Feb-2005 25-Feb-2005 12-Mar-2005 12-Mar-2005 12-Mar-2005 Actual Post review IC Estimated 49,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Post review LCS Estimated 20,000 12-Oct-04 12-Oct-2004 22-Oct-2004 22-Oct-2004 11-Nov-2004 11-Nov-2004 11-Nov-2004 Actual Prior review IC Estimated 45,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Prior review IC Estimated 45,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Prior review IC Estimated 35,000 17-Oct-04 17-Oct-2004 27-Oct-2004 27-Oct-2004 11-Nov-2004 11-Nov-2004 11-Nov-2004 Actual Prior review IC Estimated 40,000 1-Apr-05 1-Apr-2005 11-Apr-2005 11-Apr-2005 26-Apr-2005 26-Apr-2005 26-Apr-2005 Actual Post review SS Estimated 3,200 15-Feb-06 15-Feb-2006 25-Feb-2006 25-Feb-2006 12-Mar-2006 12-Mar-2006 12-Mar-2006 Actual TOTAL COMPONENTS 1,406,420 SLU/HIV-C- FMS SLU/HIV-C-PS Production to be viewed in cinemas & TV ($1,600 each) SLU/HIV-C- PVC&TV SLU/HIV-C-IA SLU/HIV-C-AA Administrative Assistant (2 Years)-PCU SLU/HIV-C-PS- CSC SLU/HIV-C-ITS SLU/HIV-C-CLA SLU/HIV-C-SO SLU/HIV-C-BS SLU/HIV-C-OR- RGS SLU/HIV-C- M&EC SLU/HIV-C-AS SLU/HIV-C-A Audits ($4000/year by 5 years , $20,000) SLU/HIV-C- IEC/BCCS Internal auditor/accountant-NAPS Behavioural surveys (1 Year) Operational research inlcud risk group Surveill. (1 Year) M& E coordinator (Grade 15) (2 Years) - NAPS Assistant/Secretary (Grade 8) (2 Years) NAPS IEC/BCC Specialist/ (Consultant/s) (2 Years) Procurement Specialist Grade 17- PCU Financial Management Specialist Grade 17-PCU Surveillance Officer (1 Year) IT specialist (2 Years) Consultancy on legal aspects Study of economic and social impact of HIV/AIDS (Consultancy) Design and mid-term review of M&E system (Consultancy) (1 year) Public Sector and Civil Society coordinator (Grade 15) (2 Years) Consultant Servies for Line Ministries C. Line Ministries response (Component 2)- (12 Ministries) Sectoral HIV/AIDS policies including workplace policies(2 Consultannts) (1 Year) LAN installation, hubs, UPS communication (for all project activities) also DC with prior review SLU/HIV-C- LANI SLU/HIV-C- BBIAC SLU/HIV-C- WPC SLU/HIV-SESI SLU/HIV-C- CSLM SLU/HIV-C- DMTR-M&E Page 5 No Objection to Contract Contract Signature Contract End, delivery Contract duration Consultant Name 15 10 15 10 20 3 20 3 30 10 40 10 40 10 15 10 No Objection to Contract Contract Signature Contract End, delivery Contract Duration Consultant Name 2-Aug-2005 1-Sep-2005 6-Sep-2006 360.00 11-Jun-2005 1-Jul-2005 29-Jun-2006 360.00 11-Jun-2005 1-Jul-2005 29-Jun-2006 360.00 12-May-2005 1-Jun-2005 25-May-2007 720.00 12-Mar-2005 1-Apr-2005 25-Mar-2007 720.00 12-Mar-2005 1-Apr-2005 25-Mar-2007 720.00 12-May-2005 1-Jun-2005 26-Nov-2006 540.00 12-May-2005 1-Jun-2005 26-Nov-2006 540.00 26-Apr-2005 16-May-2005 31-Aug-2008 1200.00 26-Apr-2005 16-May-2005 10-Nov-2006 540.00 Page 6 31-Jul-2005 30-Aug-2005 4-Sep-2006 360.00 31-Jul-2005 30-Aug-2005 4-Sep-2006 360.00 12-May-2005 1-Jun-2005 21-Jun-2006 382.00 18-Sep-2005 3-Oct-2005 10-Feb-2006 120.00 2-May-2005 1-Jun-2005 6-Jun-2006 360.00 2-May-2005 1-Jun-2005 6-Jun-2006 360.00 26-Apr-2005 16-May-2005 9-May-2007 720.00 11-Jun-2005 1-Jul-2005 24-Jun-2007 720.00 17-Oct-2005 1-Nov-2005 6-Nov-2006 360.00 26-Apr-2005 16-May-2005 31-Aug-2008 1200.00 12-Aug-2005 1-Sep-2005 30-Aug-2006 360.00 12-Dec-2005 1-Jan-2006 30-Dec-2006 360.00 26-Apr-2005 16-May-2005 9-May-2007 720.00 12-Mar-2005 1-Apr-2005 25-Mar-2007 720.00 26-Apr-2005 16-May-2005 9-May-2007 720.00 11-Nov-2004 21-Dec-2004 14-Apr-2008 1200.00 26-Apr-2005 16-May-2005 31-Aug-2008 1200.00 26-Apr-2005 16-May-2005 31-Aug-2008 1200.00 11-Nov-2004 1-Dec-2004 18-Mar-2008 1200.00 26-Apr-2005 16-May-2005 31-Aug-2008 1200.00 12-Mar-2006 1-Apr-2006 17-Jul-2009 1200.00 Page 7 St LUCIA HIV/AIDS PREVENTION AND CONTROL PROCUREMENT PLAN - GOODS ICB-International Competitive Bidding; NCB-National Competitive Bidding [NCB 2 is without prior review]; IS-International Shopping for Goods NS-National Shopping; LIB-Limited International Bidding; DC-Direct Contracting Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening Elapsed weeks ICB 10 10 45 90 NCB 10 10 30 60 NCB2 0 0 30 30 LIB 10 10 45 60 IS 0 0 20 20 NS 0 0 20 20 DC 10 10 30 30 Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening A. Strengthening the health sector response to HIV/AIDS (component 3) ARV Various contracts: DC/IS/LIB all SLU/HIV-HG- 01 PriorR of 1st DC Estimated 89,000 1-Apr-06 11-Apr-2006 21-Apr-2006 21-May-2006 permitted by market situation (18 months) contract and Specs afterwards Actual Other phamaceuticals (STI, OIs, PMTCT) Prior R of 1st DC Estimated 34,000 1-Jun-05 11-Jun-2005 21-Jun-2005 21-Jul-2005 Various contracts: DC/IS/LIB as above (18 months) contract and Specs afterwards Actual CD4 Count system (Faxcount) PriorR of 1st IS Estimated 60,000 1-Aug-05 1-Aug-2005 1-Aug-2005 21-Aug-2005 Various contracts: DC/IS/LIB as above Actual TABLE 3: GOODS -- Time Table of Procurement Actions SLU/HIV-HG- OP-01 SLU/HIV-HG- CD4SC-01 Page 8 Post review IS Estimated 70,000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 Actual Post review NS Estimated 3,200 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 Actual Post review NS Estimated 3,000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 Actual Photocopiers - BHE Post review NS Estimated 15000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Fax machine -BHE Post review NS Estimated 500 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Video player systems (2) STI Clinic Post review NS Estimated 3,200 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Post review NS Estimated 1,000 1-Jul-05 1-Jul-2005 1-Jul-2005 21-Jul-2005 Actual Televisions STI Clinic 4 @1,000 each Post review NS Estimated 4,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Post review NS Estimated 800 1-May-05 1-May-2005 1-May-2005 21-May-2005 Actual Male Condoms supply (50,000 Sexually active people) (1 Year) Prior review IS Estimated 135,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Several contracts 1st Contr. Actual Post review DC Estimated 750 1-Aug-05 11-Aug-2005 21-Aug-2005 20-Sep-2005 Actual Vending machine for condoms Post review NS Estimated 10000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 Actual Rapid Test kits (assume 10,000 tests each year) Prior R of 1ST Con. DC Estimated 60,000 1-Jul-05 11-Jul-2005 21-Jul-2005 20-Aug-2005 DC/IS/LIB permitted Actual ELISA machine 2 machines (10,000 each) Post review DC Estimated 20,000 1-Jun-05 11-Jun-2005 21-Jun-2005 21-Jul-2005 DC/IS/LIB permitted Actual Laboratory reagents and supplies IS Estimated 35,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 DC/IS/LIB permitted Actual Fridges (blood storage) Post review NS Estimated 3,000 1-May-06 1-May-2006 1-May-2006 21-May-2006 Actual Back-up vehicle for boold transfer Post review NCB Estimated 30,000 1-Dec-05 11-Dec-2005 21-Dec-2005 20-Jan-2006 Actual Post review NS Estimated 7,500 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Prior Rev of 1ST Con. IEC/BCC materials (posters, leaflets, Televisions 3 in year @ 1,000 each-VTC Center Female condoms (1000yr1,2000yr2,3000Yr3,4000Yr4,5000Yr5) SLU/HIV-HG- FBS SLU/HIV-GG- BVBT SLU/HIV-GG- IEC/BCCM- SLU/HIV-HG- TE-01 SLU/HIV-HG- MC-01 SLU/HIV-HG- FC-01 SLU/HIV-GG- VM-01 SLU/HIV-HG- RTK SLU/HIV-HG- EM SLU/HIV-HG- LRS TBD Equipment & supplies for VCT centers (18 months) Microscope (simple binocular) - STI Clinic 4 @ 200 each SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- 01 Video player systems - VCT Center 4 in 18 months SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-HG- TE-01 Training equipment [Dildos and pelvic models] STI Clinic SLU/HIV-GG- 01 Page 9 Actual Video systems (2) - BHE Post review NS Estimated 1,600 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Televisions (2) - BHE Post review NS Estimated 2,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Photocopier -Epidemiology Post review NS Estimated 800 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Fax machine - Epidemiology Post review NS Estimated 500 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Plotter (for IEC artist) - BHE Post review NS Estimated 5,000 1-Nov-05 1-Nov-2005 1-Nov-2005 21-Nov-2005 Actual C. Line Ministries response (Component 2)- (12 Ministries) Video system for IEC Post review NS Estimated 5,200 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Television for IEC Post review NS Estimated 6,500 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual D. Strengthening institutional capacity for program management (Component 4) Servers, work stations/laptops and software (for all project activities) Prior review ICB Estimated 280,140 1-Jun-05 11-Jun-2005 21-Jun-2005 5-Aug-2005 also DC with prior review - PCU & St. Jude Actual Software licenses for STD/HIV/AIDS case management,training & testing Prior review ICB Estimated 166,000 1-Jun-05 11-Jun-2005 21-Jun-2005 5-Aug-2005 also DC with prior review Actual Post review NCB Estimated 25,500 1-May-05 11-May-2005 21-May-2005 20-Jun-2005 Actual LCD projector - NAPS Post review NS 2,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Fax machine - NAPS Post review NS Estimated 500 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Photocopier - NAPS Post review NS Estimated 800 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Post review NS Estimated 6,000 1-Apr-05 1-Apr-2005 1-Apr-2005 21-Apr-2005 Actual Prior review DC Estimated 20,000 12-Oct-05 22-Oct-2005 1-Nov-2005 1-Dec-2005 Office Furniture (6 officers) $1000/person - NAPS SLU/HIV-GG- OF SLU/HIV-GG- UFMP- Update to FM & procurement IT hardware and Scanners & printers (for all project activities) IEC/BCC materials (posters, leaflets, slides),$5000/year (18 months) SLU/HIV-GG- S&P SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- SWLS SLU/HIV-SL- CMT&T SLU/HIV-GG- PIEC SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- 01 SLU/HIV-GG- 01 01 SLU/HIV-GG- 01 Page 10 Actual TOTAL COMPONENTS 1,107,490 ITH&S Update to FM & procurement IT hardware and software Page 11 No Objection to Contract Award Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 15 15 15 15 0 15 15 15 15 3 0 3 10 3 No Objection to Contract Award Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 20-Jun-2006 30-Jun-2006 25-Dec-2007 540 20-Aug-2005 30-Aug-2005 24-Feb-2007 540 10-Sep-2005 25-Sep-2005 26-Jan-2006 120 Page 12 11-Jul-2005 26-Jul-2005 20-Jan-2007 540 11-Jul-2005 11-Jul-2005 5-Jan-2007 540 11-Jul-2005 11-Jul-2005 12-Sep-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 10-Aug-2005 10-Aug-2005 11-Nov-2005 90 11-May-2005 11-May-2005 13-Jul-2005 60 10-Jun-2005 10-Jun-2005 11-Sep-2005 90 11-May-2005 26-May-2005 24-May-2006 360 20-Oct-2005 30-Oct-2005 28-Oct-2006 360 11-Jul-2005 11-Jul-2005 12-Oct-2005 90 19-Sep-2005 29-Sep-2005 26-Mar-2007 540 20-Aug-2005 30-Aug-2005 1-Dec-2005 90 11-May-2005 26-May-2005 20-Nov-2006 540 10-Jun-2006 10-Jun-2006 12-Aug-2006 60 21-Mar-2006 5-Apr-2006 19-Jul-2006 90 11-May-2005 11-May-2005 5-Nov-2006 540 Page 13 11-May-2005 11-May-2005 12-Aug-2005 90 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-Dec-2005 11-Dec-2005 14-Mar-2006 90 11-May-2005 11-May-2005 12-Aug-2005 90 11-May-2005 11-May-2005 12-Aug-2005 90 3-Nov-2005 18-Nov-2005 3-Mar-2006 90 3-Nov-2005 18-Nov-2005 2-Apr-2006 120 19-Aug-2005 3-Sep-2005 17-Dec-2005 90 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 11-May-2005 11-May-2005 13-Jul-2005 60 31-Dec-2005 10-Jan-2006 29-Dec-2006 350 Page 14 Page 15 SAINT LUCIA HIV/AIDS PREVENTION AND CONTROL PROCUREMENT PLAN - TRAINING ICB-International Competitive Bidding; NCB-National Competitive Bidding [NCB 2 is without prior review]; IS-International Shopping for Goods NS-National Shopping; LIB-Limited International Bidding; IC-Individual Consulting; DC-Direct Contracting; Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award Elapsed weeks ICB 10 10 45 90 15 NCB 10 10 30 60 15 NCB2 0 0 30 30 0 LIB 10 10 45 60 15 IS 0 0 20 20 15 NS 0 0 20 20 0 DC 10 10 30 30 10 Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award A. Strengthening the health sector response to HIV/AIDS (component 3) Post review NS Estimated 7,000 1-Dec-05 1-Dec-2005 1-Dec-2005 21-Dec-2005 10-Jan-2006 Actual Training (STI) Post review NS Estimated 7,000 1-Sep-05 1-Sep-2005 1-Sep-2005 21-Sep-2005 11-Oct-2005 Actual Post review NS Estimated 7,000 3-Jul-05 3-Jul-2005 3-Jul-2005 23-Jul-2005 12-Aug-2005 Actual Training including CD4 Post review NS Estimated 4,000 5-May-05 5-May-2005 5-May-2005 25-May-2005 14-Jun-2005 Actual Training on ARVs, OIs, STI, PMTCT (80 people trained yearly) SLU/HIV-T- CD4 TABLE 4: Training -- Time Table of Procurement Actions SLU/HIV-T- ARV SLU/HIV-T-STI- 01 SLU/HIV-T- PMTCT Training - PMTCT (hospital and district) Page 16 Post review NS Estimated 1,000 7-Apr-05 7-Apr-2005 7-Apr-2005 27-Apr-2005 17-May-2005 Actual Post review NS Estimated 1,500 9-Jun-05 9-Jun-2005 9-Jun-2005 29-Jun-2005 19-Jul-2005 Actual Training - IEC/BCC (workshops) Post review NS Estimated 4,000 11-Jun-05 11-Jun-2005 11-Jun-2005 1-Jul-2005 21-Jul-2005 Actual B. Civil society initiatives (component 1) Training [20 people each year] Post review NS Estimated 1,500 15-Aug-05 15-Aug-2005 15-Aug-2005 4-Sep-2005 24-Sep-2005 Actual C. Line Ministries response (Component 2)- (12 Ministries) Training (Average 50 people - ministry with clients /ministry /year) SLU/HIV-T- MWC Post review NS Actual 22,000 18-Jul-05 18-Jul-2005 18-Jul-2005 7-Aug-2005 27-Aug-2005 Several workshops Estimated D. Strengthening institutional capacity for program management (Component 4) IT training Post review NS Estimated 4,500 1-Oct-05 1-Oct-2005 1-Oct-2005 21-Oct-2005 10-Nov-2005 Actual M& E Training Post review NS Estimated 6,000 1-Jun-05 1-Jun-2005 1-Jun-2005 21-Jun-2005 11-Jul-2005 Actual Post review NS Estimated 4,000 1-Oct-05 1-Oct-2005 1-Oct-2005 21-Oct-2005 10-Nov-2005 Actual TOTAL COMPONENTS 69,500 SLU/HIV-T- M&E Training equipment (Dildos 6 & pelvic models 3) Workshops/training (5 per year of 20 people) $ 2700/year SLU/HIV-T- CSO SLU/HIV-T-IT SLU/HIV-TE- D&PM SLU/HIV-T- SWM SLU/HIV-T- IEC/BCC Training (Solid Waste Management) Page 17 Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 15 15 15 15 3 3 3 Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 10-Jan-2006 13-Apr-2006 90 11-Oct-2005 13-Nov-2005 30 12-Aug-2005 14-Oct-2005 60 14-Jun-2005 17-Jul-2005 30 Page 18 17-May-2005 19-Jul-2005 60 19-Jul-2005 21-Aug-2005 30 21-Jul-2005 23-Aug-2005 30 24-Sep-2005 26-Dec-2005 90 27-Aug-2005 28-Nov-2005 90 10-Nov-2005 11-Feb-2006 90 11-Jul-2005 12-Sep-2005 60 10-Nov-2005 12-May-2006 180 Page 19 SAINT LUCIA HIV/AIDS PREVENTION AND CONTROL PROCUREMENT PLAN - OPERATING COSTS ICB-International Competitive Bidding; NCB-National Competitive Bidding [NCB 2 is without prior review]; IS-International Shopping for Goods NS-National Shopping; LIB-Limited International Bidding;DC-Direct Contracting; Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award Elapsed weeks ICB 10 10 45 90 15 NCB 10 10 30 60 15 NCB2 0 0 30 30 0 LIB 10 10 45 60 15 IS 0 0 20 20 15 NS 0 0 20 20 0 DC 10 10 30 30 10 Description Bid Number Prior Review or Post Review Procurement Method Estimated Vs. Actual Amount in US$ Bidding Documents No Objection Bid Docs Call for Bids Bid Opening No Objection to Contract Award D. Strengthening institutional capacity for program management (Component 4) TBD Post review DC Estimated 60,000 1-Apr-05 11-Apr-2005 21-Apr-2005 21-May-2005 20-Jun-2005 Actual TBD Post review DC Estimated 11,500 1-Jun-05 11-Jun-2005 21-Jun-2005 21-Jul-2005 20-Aug-2005 Actual TBD Post review DC Estimated 10,000 4-Jun-05 14-Jun-2005 24-Jun-2005 24-Jul-2005 23-Aug-2005 Actual TBD Post review NS Estimated 24,000 6-Mar-05 6-Mar-2005 6-Mar-2005 26-Mar-2005 15-Apr-2005 Actual Office supplies and stationery( $4800/year) TABLE 5: Operating costs -- Time Table of Procurement Actions Local travel expenses(12,000 US$/year for 5 people) Council meetings ($2300/year, 4 meetings a year) Technical meetings ( ($2000/year, 9 meetings a year) Page 20 TBD Post review DC Estimated 18,000 8-Mar-05 18-Mar-2005 28-Mar-2005 27-Apr-2005 27-May-2005 Actual TBD Post review DC Estimated 30,000 10-May-05 20-May-2005 30-May-2005 29-Jun-2005 29-Jul-2005 Actual TBD Prior review DC Estimated 501,500 10-Mar-05 20-Mar-2005 30-Mar-2005 29-Apr-2005 29-May-2005 Actual TBD Post review NS Estimated 30,000 10-Mar-05 10-Mar-2005 10-Mar-2005 30-Mar-2005 19-Apr-2005 Actual Post review NS Estimated 24,000 10-Apr-05 10-Apr-2005 10-Apr-2005 30-Apr-2005 20-May-2005 Actual Post review DC Estimated 250,000 10-Apr-05 20-Apr-2005 30-Apr-2005 30-May-2005 29-Jun-2005 Actual TOTAL COMPONENTS 959,000 PCR service cost Social support for people affected by HIV/AIDS Operat. Costs for FM and PROCUR Telecommunications (internet, phone, etc, $3600/year) International travel (3/year: $6,000) Operating expenses For Line Ministries Page 21 Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 15 15 15 15 3 3 3 Contract Signature Contract End (delivery) Contract Duration Supplier or Contractor Name 30-Jun-2005 15-Oct-2008 1200 30-Aug-2005 15-Dec-2008 1200 2-Sep-2005 18-Dec-2008 1200 15-Apr-2005 31-Jul-2008 1200 Page 22 6-Jun-2005 21-Sep-2008 1200 8-Aug-2005 23-Nov-2008 1200 8-Jun-2005 23-Sep-2008 1200 19-Apr-2005 4-Aug-2008 1200 20-May-2005 23-May-2005 9-Jul-2005 12-Jul-2005