SFG2879 V1 Final Report ABBREVIATED RESETTLEMENT ACTION PLAN (ARAP) ENUGU UKWU GULLY EROSION SITE, ENUGU UKWU, Nigeria Erosion and Watershed Management Project ANAMBRA STATE PROJECT MANGEMENT UNIT OCTOBER 2016 Table of Contents List of Figures ................................................................................................................... v List of Tables ................................................................................................................... vi Definitions ..................................................................................................................... vii Abbreviations .................................................................................................................. ix Executive Summary ......................................................................................................... xi 1 CHAPTER ONE OVERVIEW OF NIGERIA EROSION AND WATERSHED MANAGEMENT PROJECT (NEWMAP) ....................................................................................................... 16 1.1 Background ....................................................................................................................... 16 1.1.1 Environmental and Social Safeguard Concerns .................................................................. 17 1.2 Purpose of the Abbreviated Resettlement Action Plan ....................................................... 18 1.3 Justification for the preparation of an ARAP....................................................................... 18 1.4 ARAP Methodology ........................................................................................................... 19 2 CHAPTER TWO DESCRIPTION OF THE PROJECT ENVIRONMENT AND BASELINE STUDIES21 2.1 Anambra State .................................................................................................................. 21 2.2 Overview of Enugwu-Ukwu ............................................................................................... 23 2.3 Overview of the Project Area ............................................................................................. 24 2.4 Baseline Information ......................................................................................................... 25 2.4.1 Physical Environment .......................................................................................................... 25 2.4.2 Biological Environment ....................................................................................................... 29 2.5 Socio-Economic Baseline Conditions of Project Affected Persons (PAPs) ............................. 33 2.5.1 Gender Distribution of PAPs ............................................................................................... 33 2.5.2 Age Distribution of PAPs ..................................................................................................... 33 2.5.3 Marital status of PAPs ......................................................................................................... 34 2.5.4 Religious practice of PAPs ................................................................................................... 35 2.5.5 Education ............................................................................................................................ 35 2.5.6 Average household size of PAPs ......................................................................................... 35 2.5.7 Occupation .......................................................................................................................... 36 2.5.8 Average Income status of PAPs........................................................................................... 37 2.5.9 Respondents legal or title right to property ....................................................................... 37 2.5.10 Choice of assistance ............................................................................................................ 38 2.6 Summary of the Socio-economic Condition of the Project Area .......................................... 39 3 CHAPTER THREE POLICY LEGAL AND REGULATORY FRAMEWORK .............................. 40 3.1 Introduction ...................................................................................................................... 40 3.2 The Resettlement Policy Framework (RPF) for the NEWMAP .............................................. 40 3.3 Relevant Nigeria Acts and Legislations ............................................................................... 41 3.3.1 Land Use Act of 1978 and Resettlement Procedures .......................................................... 41 ii 3.3.2 Forestry Act ......................................................................................................................... 43 3.4 State Legislations .............................................................................................................. 44 3.5 International Guidelines .................................................................................................... 45 3.6 The World Bank Policy on Involuntary Resettlement (OP. 4.12) and the ARAP for Enugwu- Ukwu Gully Erosion site ................................................................................................................ 45 3.6.1 Comparison between Land Use Act and the World Bank’s Policy (OP4.12) on Compensation 45 3.6.2 Conclusion Drawn from the Review of World Bank Policies on Involuntary Resettlement. 46 4 CHAPTER FOUR IDENTIFICATION OF PROJECT IMPACTS AND PROJECT AFFECTED PERSONS 47 4.1 Impact Reduction Measures Undertaken ........................................................................... 48 4.2 Land acquisition along the corridor .................................................................................... 48 4.3 Positive Impacts of the project .......................................................................................... 49 4.4 Negative Impact of the Project .......................................................................................... 49 4.5 Discussion of project Impacts ............................................................................................ 49 4.6 Inventory of affected assets/structures in the project area ................................................. 51 4.7 Census of Project Affected Persons (PAPs) ......................................................................... 51 4.8 Analysis of Impacts and Income Restoration Measures for Vulnerable Group/PAPs ............ 51 4.9 Performance Indicator for Assessing Income Restoration ................................................... 51 4.10 The Valuation methodology .............................................................................................. 52 4.10.1 Valuation Method for Land Property .................................................................................. 54 4.10.2 Replacement Cost Method for Assets/Structures .............................................................. 54 4.10.3 Disturbance and Other Incidental Contingencies ............................................................... 54 4.10.4 PAPs Losing Permanent Structures-for Residential (immoveable structures) ................... 55 4.10.5 PAPs Losing Permanent Structures-for Business (immoveable structures) ....................... 55 4.10.6 PAPs Losing Shrines or Place of Worship ............................................................................ 55 4.10.7 PAPs Losing Burial Site ........................................................................................................ 55 4.11 Proof of Eligibility .............................................................................................................. 55 4.12 Duration for Civil Works .................................................................................................... 56 4.13 Cut-Off Date...................................................................................................................... 56 4.14 Entitlement Matrix for the PAPs ........................................................................................ 56 4.15 Description of Eligibility Criteria for Defining Various Categories of PAPs ............................ 59 5 CHAPTER FIVE GRIEVANCE REDRESS MECHANISMS ................................................... 60 5.1 Introduction ...................................................................................................................... 60 5.2 Grievances and Appeals Procedure .................................................................................... 60 5.3 Grievance Redress Process ................................................................................................ 60 5.3.1 Procedure for Effective Local Resolution of Grievance ...................................................... 61 5.3.2 Court Resolution of Grievance Matters .............................................................................. 61 5.4 Grievance Redress Committee ........................................................................................... 62 5.5 Expectation When Grievances Arise ................................................................................... 63 5.6 Management of Reported Grievances ................................................................................ 63 iii 5.7 Grievance Log and Response Time ..................................................................................... 64 5.8 Monitoring Complaints ...................................................................................................... 65 5.9 World Bank Group (WBG) Grievance Redress Service ......................................................... 65 6 CHAPTER SIX STAKEHOLDERS’/FOCUS GROUP ENGAGEMENT ................................... 66 6.1 Introduction ...................................................................................................................... 66 6.2 Advocacy Visit ................................................................................................................... 67 6.3 Town Hall Meetings........................................................................................................... 68 6.3.1 The General Town Hall Meeting ......................................................................................... 69 6.3.2 Focal Group Meeting .......................................................................................................... 71 6.3.3 Feed Back Meeting .............................................................................................................. 71 7 CHAPTER SEVEN BUDGET AND FINANCING PLAN ...................................................... 72 7.1 Introduction ...................................................................................................................... 72 7.2 Financing plan ................................................................................................................... 73 7.3 Procedure for Delivering of Entitlements ........................................................................... 74 7.3.1 Engagement of Consultant (NGO)....................................................................................... 74 7.4 ARAP Compensation Process ............................................................................................. 74 7.5 Compensation Payment Administration ............................................................................. 74 7.6 Resettlement Implementation Linkage to Civil Works ........................................................ 75 8 CHAPTER EIGHT INSTITUTIONAL ARRANGEMENTS- ROLES AND RESPONSIBILITIES .... 76 8.1 Introduction ...................................................................................................................... 76 8.2 Institutional Arrangement ................................................................................................. 76 8.2.1 The Financier ....................................................................................................................... 76 8.2.2 Federal Level ....................................................................................................................... 76 8.2.3 State Level ........................................................................................................................... 77 8.2.4 Local Level ........................................................................................................................... 80 8.2.5 Community Level ................................................................................................................ 80 8.2.6 Others.................................................................................................................................. 82 9 CHAPTER NINE TIME TABLE OF EVENTS ..................................................................... 83 9.1 Timetable for the Resettlement Action Plan ....................................................................... 83 9.2 Training and Capacity Needs .............................................................................................. 84 10 CHAPTER TEN MONITORING AND EVALUATION ........................................................ 85 10.1 Overview .......................................................................................................................... 85 10.2 Internal Monitoring ........................................................................................................... 85 10.3 Independent Monitoring ................................................................................................... 86 10.4 Monitoring Indicators ........................................................................................................ 86 10.5 Implementation Schedule.................................................................................................. 87 References ..................................................................................................................... 89 ANNEX 1 CENSUS REGISTRATION FOR PAPS ............................ Error! Bookmark not defined. iv ANNEX 2 MONITORING INDICATOR FOR THE PERFORMANCE OF RAP INCOME RESTORATION 90 ANNEX 3 LIST OF INVENTORY OF AFFECTED ASSETS/STRUCTURES AND COMPENSATION FOR PAPS ...................................................................................... Error! Bookmark not defined. ANNEX 4 CENSUS/ SOCIO-ECONOMIC DATA COLLECTION FORM ..................................... 96 ANNEX 5 LIST OF VULNERABLE PAPS ............................................................................. 102 ANNEX 6 BREAKDOWN OF ASSETS VALUED AND COMPENSATIONError! Bookmark not defined. ANNEX 7 SUMMARY OF AGREEMENT WITH LAND OWNERS .......................................... 105 LIST OF FIGURES FIGURE 1 MAP OF NIGERIA SHOWING ANAMBRA STATE AND HIGHLIGHTING THE PROJECT AREA ..........................21 FIGURE 2 A SECTION OF THE GULLY ............................................................................................................................24 FIGURE 3 THE GULLY SHOWING PART OF AN AFFECTED BUILDING ............................................................................25 FIGURE 4 ENTRANCE INTO THE NGENE NNEVOAKA SHRINE .......................................................................................26 FIGURE 5 AMBIENT TEMPERATURE OF PROJECT AREA (NIMET) .................................................................................27 FIGURE 6 RAINFALL PATTERN OF THE PROJECT AREA (NIMET) ...................................................................................27 FIGURE 7 RELATIVE HUMIDITY OF THE PROJECT AREA (NIMET) .................................................................................28 FIGURE 8 EKE MARKET AT URUNNEBO .......................................................................................................................31 FIGURE 9 NGENE-UBE SHRINE .....................................................................................................................................32 FIGURE 10 OBU NGENE-NNEVOAKA SHRINE ...............................................................................................................32 FIGURE 11 GENDER DISTRIBUTION OF PAPS WITHIN THE PROJECT AREA ..................................................................33 FIGURE 12 AGE DISTRIBUTION OF PAPS WITHIN THE PROJECT AREA .........................................................................34 FIGURE 13 MARITAL STATUS OF PAPS WITHIN THE PROJECT AREA............................................................................34 FIGURE 14 EDUCATIONAL QUALIFICATION OF PAPS WITHIN THE PROJECT AREA ......................................................35 FIGURE 15 AVERAGE FAMILY SIZE OF PAPS WITHIN THE PROJECT AREA ....................................................................36 FIGURE 16 OCCUPATION OF PAPS WITHIN THE PROJECT AREA..................................................................................36 FIGURE 17 AVERAGE MONTHLY INCOME OF PAPS WITHIN THE PROJECT AREA ........................................................37 FIGURE 18 ASSET OWNERSHIP TYPES AMONG PAPS IN THE PROJECT AREA ..............................................................38 FIGURE 19 CHOICE OF ASSISTANCE BY PAPS IN THE PROJECT AREA ...........................................................................38 FIGURE 20 EZENWANI SHRINE .....................................................................................................................................48 FIGURE 21 IMPACTED PROPERTY ................................................................................................................................48 FIGURE 22 AVERAGE YEARLY INFLATION RATE (CBN, 2016) .......................................................................................53 FIGURE 23 AVERAGE MONTHLY INFLATION RATE (NBS, 2016) ...................................................................................54 FIGURE 24 GRIEVANCE REDRESS PROCEDURE ............................................................................................................63 FIGURE 25 IGWE ENUGWU UKWU AND CABINET DURING ADVOCACY MEETING ......................................................67 FIGURE 26 CONSULTANT AND SPMU TEAMS DURING THE ADVOCACY VISIT .............................................................67 FIGURE 27 DR OBI ANYADIEGWU ADDRESSING THE IGWE .........................................................................................68 FIGURE 28 THE LIVELIHOOD OFFICER DURING THE ADVOCACY VISIT WITH THE STAKEHOLDERS .............................68 FIGURE 29 A STAKEHOLDER EXPRESSING CONCERN DURING THE TOWN HALL MEETING .........................................69 v FIGURE 30 A CROSS-SECTION OF THE WOMEN GROUP AT THE TOWN HALL MEETING .............................................69 FIGURE 31 SOME OF THE STAKEHOLDERS WITH THE CONSULTANTS DURING THE FOCAL GROUP CONSULTATION 71 FIGURE 32 FOCAL GROUP CONSULTATION AT THE COMMUNITY...............................................................................71 FIGURE 33 A GROUP OF PAPS AT THE FEEDBACK SESSION .........................................................................................72 FIGURE 34 ONE OF THE PAPS DURING THE FEEDBACK SESSION .................................................................................72 LIST OF TABLES TABLE 1 SOME COMMON PLANTS FOUND WITHIN THE PROJECT COMMUNITY ........................................................29 TABLE 2 COMPARISON OF NIGERIAN LAND USE ACT AND WORLD BANK OP4.12 ON COMPENSATION ....................46 TABLE 3 LIST OF PAPS AND AFFECTED STRUCTURES .............................................ERROR! BOOKMARK NOT DEFINED. TABLE 4 MARKET SURVEY FROM ENUGWU-UKWU.....................................................................................................52 TABLE 5 ENTITLEMENT MATRIX TABLE FOR PAPS .......................................................................................................56 TABLE 6 A TYPICAL REPORTING FORMAT FOR GRIEVANCE REDRESS ..........................................................................64 TABLE 7 SUMMARY OF ARAP BUDGET ..................................................................ERROR! BOOKMARK NOT DEFINED. TABLE 8 TIMETABLE FOR COMPLETION OF ARAP IMPLEMENTATION ........................................................................83 TABLE 9 CAPACITY BUILDING SCHEDULE AND COST ...................................................................................................84 TABLE 10 SUMMARY OF IMPLEMENTATION SCHEDULE .............................................................................................87 vi DEFINITIONS Children: all persons under the age of 18 years according to international regulatory standard (Convention on the rights of Child 2002) Community: a group of individuals broader than households, who identify themselves as a common unit due to recognized social, religious, economic and traditional government ties or shared locality. Compensation: payment in cash or in kind for an asset or resource acquired or affected by the project. Cut-off-Date: the date of completion of inventory of losses and census of project affected persons Economic Displacement: a loss of productive assets or usage rights or livelihood capacities because such assets / rights / capacities are located in the project area. Entitlement: the compensation offered by RAP, including: financial compensation; the right to participate in livelihood enhancement programs; housing sites and infrastructure; transport and temporary housing allowance; and, other short term provisions required to move from one site to another. Head of the Household: the eldest member of the core family in the household, for the purpose of the project. Household: a group of persons living together who share the same cooking and eating facilities, and form a basic socio-economic and decision making unit. One or more households often occupy a homestead. Involuntary Resettlement: resettlement without the informed consent of the displaced persons or if they give their consent, it is without having the power to refuse resettlement. Lost Income Opportunities: lost income opportunities refers to compensation to project affected persons for loss of business income, business hours/time due to project Operational Policy 4.12: Describes the basic principles and procedures for resettling, compensating or at least assisting involuntary displace persons to improve or at least restore their standards of living after alternatives for avoiding displacement is not feasible Physical Displacement: a loss of residential structures and related non-residential structures and physical assets because such structures / assets are located in the project area. Private property owners: persons who have legal title to structures, land or other assets and are accordingly entitled to compensation under the Land Act. Project-Affected Community: a community that is adversely affected by the project. Project-Affected Person: any person who, as a result of the project, loses the right to own, use or otherwise benefit from a built structure, land (commercial, residential, agricultural, or pasture), annual or perennial crops and trees, or any other fixed or moveable asset, either in full or in part, permanently or temporarily. Rehabilitation: the restoration of the PAPs resource capacity to continue with productive activities or lifestyles at a level higher or at least equal to that before the project. vii Relocation: a compensation process through which physically displaced households are provided with a one-time lump-sum compensation payment for their existing residential structures and move from the area. Replacement Cost: the amount of cash compensation and/or assistance suffices to replace lost assets and cover transaction costs, without taking into account depreciation or salvage value. Resettlement Action Plan (RAP): documented procedures and the actions a project proponent will take to mitigate adverse effects, compensate losses, and provide development benefits to persons and communities affected by a project. Resettlement Assistance: support provided to people who are physically displaced by a project. This may include transportation, food, shelter, and social services that are provided to affected people during their resettlement. Assistance may also include cash allowances that compensate affected people for the inconvenience associated with resettlement and defray the expenses of a transition to a new locale, such as moving expenses and lost work days. Resettlement: a compensation process through which physically displaced households are provided with replacement plots and residential structures at one of two designated resettlement villages in the district. Resettlement includes initiatives to restore and improve the living standards of those being resettled. Squatters: squatters are landless household squatting within the public / private land for residential and business purposes. Vulnerable group: People who by their disadvantage conditions will be economically worse impacted by project activities than others such as female headed households, persons with disability, at-risk children, persons with HIV-AIDS and elderly household heads of 60 years and above. viii ABBREVIATIONS ARAP Abbreviated Resettlement Action Plan BP Bank Policies CBO Community Based Organization CSO Community Support Organizations DaLA Damage and Loss Assessment EA Environmental Assessment EPA Environmental Protection Agency ESIA Environmental and Social Impact Assessment ESMF Environmental and Social Management Framework ESMP Environmental and Social Management Plan FGN Federal Government of Nigeria FMEnv Federal Ministry of Environment FSLC First School Leaving Certificate GDP Gross Domestic Product GRC Grievance Redress Committee IDA International Development Association LGA Local Government Area M&E Monitoring and Evaluation MDAs Ministries, Departments & Agencies NEWMAP Nigeria Erosion and Watershed Management Project NGOs Non-Governmental Organizations OP Operational Policies (of the World Bank) PAD Project Appraisal Document PAP Project Affected Persons PDO Project Development Objectives PID Project Information Document PMU Project Management Unit RAP Resettlement Action Plan RPF Resettlement Policy Framework SMEnv State Ministry of Environment SPMU State Project Implementation Unit ix STDs Sexually Transmitted Diseases ToR Terms of Reference x EXECUTIVE SUMMARY INTRODUCTION The Government of Nigeria is implementing the multi-sectoral Nigeria Erosion and Watershed Management Project (NEWMAP), financed by the World Bank, Global Environment Facility, the Special Climate Change Fund, and the Government of Nigeria. The Project Development Objective (PDO) of the NEWMAP is to improve erosion management and gully rehabilitation; increase incomes for rural households from improved agricultural and forest practices through the use of conservation agriculture, agroforestry, natural regeneration, etc.; and gain efficiency in public administration and public spending through improved knowledge base, analytical tools, multi-sectoral coordination and stakeholder dialogue. Various documents have been prepared in line with NEWMAP, and they include; Environmental and Social Management Framework (ESMF), Resettlement Policy Frameworks (RPF), Project Appraisal Document (PAD) prepared for the Nigerian Erosion and Watershed Management Project. This report focuses on the Abbreviated Resettlement Action Plan (ARAP) developed for the Rehabilitation of the Enugwu-Ukwu Gully Erosion Njikoka LGA of Anambra State Nigeria. The aim of the ARAP is to identify and assess the human impact of the proposed works at the Umuturu- Umuomeji-Ezemazu Gully Erosion Site, and to prepare an Action Plan to be implemented in coordination with the civil works in line with World Bank Policy and Nigeria policies and laws. Experience has shown that involuntary resettlement can cause loss of income, assets, and community ties that, especially among the poor, can be essential for survival and wellbeing. In extreme cases, involuntary resettlement can lead to the dissolution of families, impoverishment and health problems. The ARAP will identify the project-affected persons (PAPs), engage them in participatory discussions regarding the plan and formulate an action plan for compensation. DESCRIPTION OF THE PROPOSED PROJECT The proposed rehabilitation works is part of the intervention programme of the World Bank (NEWMAP sub-project), which is aimed at reclaiming of the already degraded part of the region for subsequent utilization of land for either agricultural purposes or other developmental projects. These will consider the following:  Refilling part of the gully to rehabilitate existing roads by carrying out complete orpartial reclamation on the gully;  Construction of collector drains along the main roads overlooking the intervention area in order to prevent further runoff concentration along secondary roads;  Provision of proper interceptor drains to safely discharge water through chutes and stilling basins;  Provision of concrete channels in infrastructure areas and check dams at suitable intervals (300mm) at gully bed of the main gully; and  Vegetation measures including afforestation to stabilise the eroded areas. The Project Area The project area cuts across two (2) major communities in Enugwu-ukwu. The larger section in Urunnebo community have separated Umuajana and Umunwankwo Villages while the other section falls xi in Umuorji village in Avomimi Community of Enugwu-Ukwu. Land ownership system in the community is based mainly on inheritance. The gully system have continued to expand with the rains. The slope of the gully area, the characteristics of the incipient soil, man-made interferences, unguided run-off flow as well as poorly terminated drainage systems are the combined causes of the problem. This has resulted to destruction of infrastructure and negatively impacted on agricultural activities as well as reduction of land suitability for other applications. Some families have been displaced as a result of the menace. The Main Gully head originate around coordinates N06.16569° E007.01813°. Field investigation revealed that the gully begins from Eziemenike culvert, near the Eke market running downstream. The Left finger gully head originating from around Ufom’s compound and joins the Main gully just behind Chief Tony Okeke’s residence. Both continues to form a confluence at the Ebenebe tree (N06.16179° E007.01788°). The Right Finger gully originates from the Eziegbo culvert (N06.16489° E007.01489°) and runs downstream through the back of St Francis Catholic Church while the Right Finger Gully-1 originates from around Gosiora’s Compound (N06.16294° E007.01716°) running south west to join the Right Finger gully. Both progress downstream meet the Main Gully at the Ebenebe tree (N06.16179° E007.01788°) and then continues as the Main gully downstream towards the FADAMA III area up to Ngene Lake. The project area is populated and residents are mainly farmers. There are also traders and artisans living within the project communities. Within the area consist of schools, Primary Healthcare Centre, at the Obu Ozum Hall and St Francis Catholic Church at the centre of the town. There is also a village market (Eke Market). POLICY, LEGAL AND REGULATORY FRAMEWORK A number of national and international environmental guidelines are applicable to the operation of the NEWMAP. The Bank’s policy on Involuntary Resettlement advocates that where feasible, involuntary resettlement should be avoided or minimized. Resettlement shall be conceived and executed as a sustainable development program, where it is inevitable, providing sufficient investment resources to enable persons displaced by the project share in project benefit. This ARAP will be aligned with the World Bank Operational Policies including Involuntary Resettlement Policy, which indicate best practices for rehabilitation of livelihoods of people affected by the implementation of the project. IDENTIFICATION OF PROJECT IMPACTS AND PROJECT AFFECTED PERSONS The inventory taken showed that land acquisition will occur for 2 (Two) of the PAPs as a result of the project. A Zinc building used for traditional worship will be impacted which falls within the 10 meter setback within the corridor of the Main gully. This happens to be the only Land owned by the PAP. Also a family burial site belonging to the Iwotor Family will also be impacted. Crops planted on farmlands and associated economic trees were observed as important features that would be affected in the event of the proposed work along the corridor of the gullies. It was also observed that crops planted within the ROW of the drainages as well as encroachment of structures and fences are other categories of impacts by the proposed work. xii IMPACT REDUCTION MEASURES The following are technical steps taken in consultation and concurrence of Anambra State NEWMAP PMU and the Design Engineers which have resulted in the reduction of adverse impacts of the project:  The engineering design for the intervention using gabion retaining walls and interlocked blocks over filtered materials at critical areas near the gully corridor (especially close to structures) was employed. This will help retain the existing structure thereby preventing possible demolition of the structure. Also geotextile was also employed in some areas.  The setback for access and buffer on the corridor was made known to the stakeholders to be 10 meters and that in the event of work in such locations all affected properties are to be removed by their owners to give the required right of way for the work. Consulting/communicating with the people of the project area and PAPs in particular on the day and time to expect civil work activities within their respective location. This will give the PAPs opportunity to harvest mature crops before the beginning of civil works. Census of Project Affected Persons (PAPs) The outcome of the census conducted shows that 76 assets will be potentially impacted. Which include persons that will be potentially impacted or suffer socio-economic losses as a result of sub-project activities as well as some (2) Family Owned assets. Analysis of Impacts and Income Restoration Measures for Vulnerable Group/PAPs Among the 76 PAPs, Twenty-two (22) vulnerable persons were enumerated during the ARAP census which included eighteen (18) widows and four (4) elderly poor persons (above 60 years) with dependents. There was no vulnerable PAP in the category of HIV-AIDS persons and child headed households. No mentally disabled persons were identified as part of the PAPs. Performance Indicators for Assessing Income Restoration It is the responsibility of the monitoring and evaluation officer or the Safeguard Officer at the PMU to design a schedule and budget for monitoring the implementation of the RAP which will begin before project implementation and continue through the life cycle of the project. The monitoring indicators, for the ARAP income restoration progress is attached as annex 2 of this report. The Valuation methodology The asset valuation was conducted based on the current market prices in the project area. For some materials, prices vary on the basis of quality, taste and product brand. Therefore, in such cases the average market price plus 2% price flexibility adjustment was used for the valuation. Valuation Method for Land Property In line with OP 4.12 of the World Bank on involuntary resettlement as stated in the entitlement matrix, land for land entitlement is prescribed. Replacement Cost Method for Assets/Structures The Replacement Cost Method, which is used in estimating the value of the property/structure, is based on the assumption that the capital value of an existing development can be equated to the cost of reinstating the development on the same plot at the current labour, material and other incidental costs. The DaLa method was also employed in the assessment of cash crops and economic trees. xiii Disturbance and Other Incidental Contingencies Affected business premises which will have to close shop or be relocated will be given compensation for loss of business time/income and cash or in kind assistance to enable the relocation of affected property. Only one (1) PAP was identified as eligible for this due to relocation of his shop. This has been factored into the full compensation and details are shown in Annex 3 STAKEHOLDERS /FOCUS GROUP ENGAGEMENT The public consultation strategy for the ARAP activities evolved around the provision of a full opportunity for involvement for all stakeholders, especially the PAPs. Concerns raised by the stakeholders are documented and incorporated in this report and used to develop mitigation and/or enhancement measures for the GRM. The stakeholders were informed of the visits through the existing communication line between the SPMU and the communities. The Community leaders through the use of town criers, church announcements and phone calls, informed the rest of the community of the proposed meetings. Consultation Method: A combination of various consultation methods were used to assess knowledge, perception and attitude of the groups consulted concerning the project, and its potential environmental and social impacts. An Advocacy Visit, Focal group meetings, Town hall meeting and Feedback meetings were conducted. The advocacy visit meeting was held on 3rd May 2016 at the palace of His Royal Highness Igwe Raphael Ikpa (Igwe Enugwu-Ukwu na Umunri) who is the apex authority of the community. A second Advocacy visit was held on the same day at the Obu ozom hall with the Association Executives, Youth executives and women group executives. The Town hall meeting was carried out in two (2) stages. The first was a general meeting where all the stakeholders and community members were given a general overview of the project, the component and information regarding the ESMP and ARAP especially the census/inventory and other relevant information in the RPF and TOR . The second stage meeting involved the consultant and the PAPs after the census exercise. The meeting provided feedbacks, clarifications and responses. BUDGET AND FINANCING PLAN Since the Anambra State Ministry of Environment is the one impacting livelihoods, it will be their responsibility to fund the ARAP budget. It will be financed through the projects administrative and financial management rules and manuals like any other sub-activity of the project eligible for payment under this project. ARAP Compensation Process: The compensation process will involve several steps in accordance with the report. Compensation Payment Administration: The resettlement budget details prepared in this ARAP shall be the guide for the Consultant/NGO to be engaged for ARAP payment Resettlement Implementation Linkage to Civil Works Before any project activity is implemented, PAPs will need to be compensated/resettled in accordance with the entitlement matrix/budget plan established in this ARAP Summary of Budget Estimate for ARAP Implementation S/N DESCRIPTION TOTAL xiv 1 ARAP Compensation/Assistance Budget for 76 PAPs (determined) Land N1,780,000.00 Crops and Agricultural Resources N3,856,470.00 Structures and cultural Resources N4,764,600.00 Sub-Total: Compensation N10,401,070.00 2 Capacity Building and Training for ARAP Implementation N4,527,819.00 3 Operating cost including income restoration measures and N1,040,107.00 Monitoring of RAP Implementation (10 % of ARAP compensation Budget) 4 Cost of engagement of consultant/NGOs for compensation N1,500,000.00 payment *TOTAL N17,468,996.00 *Allow time for annual/seasonal crop owners to harvest their crops. Careful management of the site based on 10m setback and aligning chainages (a distance measured along imaginary line used in survey often corresponding to the centre of a straight road ) will reduce compensation amount INSTITUTIONAL MATRIX The major institutions that are involved in this resettlement process are the Anambra State Ministry of Environment (SMEnv) the World Bank, and the Community Resettlement Committee (CRC). TIMETABLE FOR THE RESETTLEMENT ACTION PLAN The RAP has to be completed and PAPs adequately compensated before operation in the designated project area. Training and Capacity Needs It is necessary that the PMU and the Grievance Redress committee be educated on the modus operandi of involuntary resettlement and how to manage grievance cases and also for PAPs to understand optimal measures for livelihood restoration and the opportunities to possibly take advantage of. GRIEVANCE REDRESS MECHANISM The likelihood of dispute is much reduced because the few affected persons due to the erosion control project have been greatly consulted. Nevertheless, the Grievance redress mechanisms designed herewith has the objective of solving disputes at the earliest possible time, which is in the interest of all parties concerned; it thus implicitly discourages referring such matters to the law courts for resolution, which would take a considerably longer time. GRC will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce litigation. MONITORING AND EVALUATION There will be two levels of monitoring; namely internal monitoring and external monitoring. Under internal monitoring the Anambra State Ministry of Environment will hire a monitoring and evaluation officer to work in the PMU while an external monitoring and evaluation officer will be engaged periodically by SMEnv. xv 1 CHAPTER ONE OVERVIEW OF NIGERIA EROSION AND WATERSHED MANAGEMENT PROJECT (NEWMAP) 1.1 Background The Government of Nigeria is implementing the multi-sectoral Nigeria Erosion and Watershed Management Project (NEWMAP), which is financed by the World Bank, Global Environment Facility, the Special Climate Change Fund, and the Government of Nigeria. NEWMAP finances activities implemented by States and activities implemented by the Federal government. The project currently includes 7 states, namely Anambra, Abia, Cross River, Edo, Enugu, Ebonyi, and Imo. The Nigeria Erosion and Watershed Management Project (NEWMAP) aims to reduce vulnerability to soil erosion in targeted sub-catchments. The Project Development Objective (PDO) of the NEWMAP is to improve erosion management and gully rehabilitation; increase incomes for rural households from improved agricultural and forest practices through the use of conservation agriculture, agroforestry, natural regeneration, etc.; and gain efficiency in public administration and public spending through improved knowledge base, analytical tools, multi-sectoral coordination and stakeholder dialogue. NEWMAP investments include a strategic combination of civil engineering, vegetative land management and other catchment protection measures, and community-led adaptive livelihood initiatives. The sustainability of these investments will be reinforced by strengthening institutions and information services across sectors and States, including support to improve governance, regulatory compliance, environmental monitoring, impact evaluation, catchment and land use planning, and to strengthen Nigeria’s capacity to promote and implement climate-resilient, low- carbon development. NEWMAP involves many Federal and State Ministries, Departments and Agencies (MDAs), local governments, communities, and civil society. Effective implementation requires inter- ministerial and inter-state coordination, collaboration, and information sharing. Each component, sub-component and activity will be implemented through relevant Federal and State MDAs. The various MDAs include those responsible for planning, economy and finance, works, agriculture, water resources, forests, transport, power, emergency response, as well as those focused on climate and hydrological information or catchment/ basin regulation. Most of NEWMAP’s investments will be made at the State level, as States have primary responsibility for land management and land allocations. NEWMAP Components (as documented in the PIM) are divided into 4 viz; Component 1: Erosion and Catchment Management investment  Sub-component 1A Gully Rapid Action and Slope Stabilization Sub-component  1B Integrated Catchment Management  Sub-component 1C Adaptive Livelihoods Component 2: Erosion and Catchment Management Institutions and Information Services 16  Sub-component 2A Federal MDA Effectiveness and Services Sub-component  2B State MDA Effectiveness and Services Sub-component  2C Local Government Capacity Sub-component  2D Private Sector Capacity Component 3: Climate Change Agenda Support  Sub-component 3A Policy and Institutional Framework Sub-component  3B Low Carbon Development Component 4: Project Management Various documents have been prepared in line with NEWMAP, and they include an Environmental and Social Management Framework (ESMF), a Resettlement Policy Framework (RPF) and a Project Appraisal Document (PAD) prepared for the Nigerian Erosion and Watershed Management Project. This report focuses on the Abbreviated Resettlement Action Plan (ARAP) developed for the Rehabilitation of the Enugwu-Ukwu gully erosion site in Njikoka LGA of Anambra State, Nigeria. The project area cuts across two (2) major communities in Enugwu-ukwu. The larger section in Urunnebo community have separated Umuajana and Umunwankwo Villages while the other section falls in Umuorji village in Avomimi Community of Enugwu-Ukwu. Land ownership system in the community is based mainly on inheritance. The gully system are very active and have continued to expand with the rains. The slope of the gully area together with the characteristics of the incipient soil, man-made interferences characterised by poor town planning and blockage of natural waterways leading to unguided run-off flow and poor termination of drainage systems are the root causes of the problem. The Anambra State NEWMAP intends to rehabilitate the gully erosion site and reduce longer-term erosion vulnerability in the targeted area. The activities for this sub-project will involve civil works within the small watershed. This includes mainly stabilization and/or rehabilitation of the gullies by means of revegetation and engineering works. The proposed work activities could result in the acquisition of land or displacement of families, business or public infrastructure, thus triggering the World Bank OP/BP 4.12 – Involuntary Resettlement and hence the need for a Resettlement Plan. 1.1.1 Environmental and Social Safeguard Concerns The environmental and social safeguards concerns for NEWMAP are addressed through two national instruments already prepared under the project: an Environmental and Social Management Framework (ESMF) and a Resettlement Policy Framework (RPF). Environmental and Social Management Framework (ESMF): In general, the ESMF specifies the procedures to be used for preparing, approving and implementing  Environmental/Social Assessments (ESAs, or alternately both an SA or an EA) and/or 17  Environmental/Social Management Plans (ESMPs, or alternately both an EMP and SMP) for individual civil works packages developed for each project. ESMPs are essential elements for Category B projects. Resettlement Policy Framework (RPF): The RPF applies when land acquisition leads to the temporary or permanent physical displacement of persons, and/or loss of shelter, and /or loss of livelihoods and/or loss, denial or restriction of access to economic resources due to project activities. It sets out the resettlement and compensation principles, organizational arrangements and design criteria to be applied to meet the needs of project-affected people, and specifies the contents of a Resettlement Action Plan (RAP) for each package of investments. A Resettlement Policy Framework (RPF), which serves as a practical tool during the programme formulation, design, implementation and monitoring, was prepared for NEWMAP, which serves as a guide for the present terms of reference. The activities of Component 1 will involve civil works in specific intervention sites – that is, construction of drainage works and/or rehabilitation of gullies. This could result in the acquisition of land or displacement of families, business or public infrastructure, thus triggering the World Bank OP/BP 4.12 – Involuntary Resettlement. 1.2 Purpose of the Abbreviated Resettlement Action Plan The aim of the ARAP is to identify and assess the human impact of the proposed works at the Enugwu- Ukwu Gully erosion Site, and to prepare an Action Plan to be implemented in coordination with the civil works in line with World Bank Policy and Nigeria policies and laws. Experience has shown that involuntary resettlement can cause loss of assets and source of livelihood as well as community ties which can be essential for survival and wellbeing of the project affected persons, especially among the poor. In extreme cases, involuntary resettlement can lead to the dissolution of families, impoverishment and health problems. The ARAP will identify the project affected persons (PAPs), engage them in participatory discussions regarding the plan and formulating a plan of action to adequately compensate people for their losses. 1.3 Justification for the preparation of an ARAP The Policy of the World Bank is to ensure that persons involuntarily resettled caused by the taking of land in the context of a project supported by the Bank, have an opportunity to restore or improve their level of living to at least the pre-project level. Project affected people should participate in the benefits of the project and they should be given options regarding how they restore or improve their previous level of living. In the NEWMAP project it is not sufficient for communities to passively accept project works and the impacts of these works. Rather they must be mobilized to contribute actively to project design and implementation and to maintain the woks following implementation. This feature underscores the need for accurate analysis of local social organization. Although majority of the civil works will occur within the ROW for public facilities, involuntary resettlement is triggered according to OP4.12 of the IDA because the impacts of the sub-projects might 18 cause persons and communities to be economically worse off and may fuel crises in the project area, which could render the project unsustainable. The core requirement of the OP 4.12 – Involuntary Resettlement is as follows:  Avoid or minimize involuntary resettlement where feasible, exploring all viable alternative project designs.  Assist project affected persons in improving their former living standards, income earning capacity, and production levels, or at least in restoring them back to the former status  Encourage community participation in planning and implementing resettlement.  Provide assistance to affected people regardless of the legality of land tenure. A Resettlement Action Plan (RAP) is prepared where major impact is anticipated, that is;  if affected people will be physically displaced  More than 10% of their productive assets/total land hold are lost/acquired and  More than 200 people are to be directly adversely affected. However, an ARAP is prepared where minor impacts are envisaged. That is the reverse of the conditions stated above for a RAP. This is envisaged for the Enugwu-Ukwu gully erosion sites. 1.4 ARAP Methodology This ARAP involves a number of coordinated approaches and action plans tailored towards addressing the scope of work and objectives set out in the TOR. The Consultant took the following steps and approaches: a) Initial meetings with Anambra State NEWMAP PMU and Engineering Design Consultants This meeting offered the opportunity to clarify relevant issues in the terms of reference and to agree on deliverables and timelines. The outcome of this meeting culminated in the collection of relevant documents from project proponent, Engineering design team and other relevant bodies. These documents include Engineering Drawings, Resettlement Policy Framework for NEWMAP, Environmental and Social Management Framework for NEWMAP, NEWMAP Project Implementation Manual (PIM), NEWMAP Project Appraisal Document (PAD), Nigeria Land Use Act (1978) and World Bank guidelines and Policies on Involuntary Resettlement. Also the consultant held several meetings with the engineering consultants (SMEC Ltd) to discuss on the design concept. This helped in throwing more light on the approach for the proposed civil works as well as the measures taken to minimize impact. All relevant document were collected. b) Literature Review 19 The team duly reviewed all the relevant documents. The review exercise was helpful in understanding the relationship and gaps in the policy frameworks of the World Bank on one hand and the country laws and policies on involuntary displacement. Also it helped in understanding the actual design for the intervention. From the review of the policy documents stated above, the necessary requirements for this ARAP were ascertained. c) Initial/Reconnaissance Site Visit and Stakeholder Consultation This step was important to determine the magnitude and nature of the anticipated impacts identify the affected communities, community leaderships and associations in which potential PAPs belong. It was also used to consult with the stakeholder whose assistances and cooperation is expected to ensure sustainable project implementation. d) Engagement of field officers/enumerators Enumerators were selected from the consultant’s office and this selection was based on field experience. The field officers were trained on the use of the survey instruments and on the nature of the policy guidelines that underlay the project. This was undertaken with mock exercise carried out to test their understanding and refresh their capabilities before embarking on field survey. e) Identification of PAPS and Affected Assets Identification of project-affected persons (PAPs) was based on the following considerations: Owners of assets/structures within a range of 5-10 meters set back along the corridor of the gullies as well as Owners of assets/structures along the sections where the access road and buffer zones will be located. Details on this are presented in Chapter Five f) Consultation of Affected Communities, PAPs and MDAs Series of consultations were undertaken in the course of the preparation of the ARAP. The consultant engaged the Traditional Ruler (Igwe Enugwu-Ukwu), Chiefs, Nzes, Associations and Community Development Councils leaders in the dissemination of information to the project area. The essence of this was to inform them of the exercise and invite all stakeholders and project affected persons to a public consultation with date, venue and time specified. Focus group consultations were also carried out with the PAPs, Vulnerable groups and Women groups. 20 2 CHAPTER TWO DESCRIPTION OF THE PROJECT ENVIRONMENT AND BASELINE STUDIES 2.1 Anambra State Anambra State is located within the south-eastern zone of Nigeria with a land mass of over 4120 sq. km. The state has a population of 4,055,048 (2006 Census). Anambra state is situated on a low elevation on the eastern side of the River Niger and shares boundaries with Kogi, Enugu, Imo, Abia, Delta, Rivers and Edo states. Local Government Areas The twenty-one (21) Local Government Areas in Anambra State are: Aguata, Anambra East, Anambra West, Aniocha, Awka North, Awka South, Ayamelum, Dunukofia, Ekwusigo, Idemili North, Idemili South, Ihiala, Njikoka, Nnewi North, Nnewi South, Ogbaru, Onitsha North, Onitsha South, Orumba North, Orumba South, Oyi. The project area is situated in Enugu-Ukwu, which is a large town in Njikoka Local Government Area of Anambra state. 21 Geology Anambra State lies in the Anambra Basin and has about 6,000 m of sedimentary rocks. The sedimentary rocks comprise ancient Cretaceous deltas, somewhat similar to the Niger Delta, with the Nkporo Shale, the Mamu Formation, the Ajali sandstone and the Nsukka Formation as the main deposits. On the surface the dominant sedimentary rocks are the Imo Shale a sequence of grey shales, occasional clay ironstones and Sandstone beds. The Imo Shale underlies the eastern part of the state, particularly in Ayamelum, Awka North, and Oruma North LGAs. Next in the geological sequence, is the Ameke Formation, which includes Nanka Sands, laid down in the Eocene. Its rock types are sandstone, calcareous shale, and limestone in thin bands. Outcrops of the sandstone occur at various places on the higher cuesta, such as at Abagana and Nsugbe, where they are quarried for construction purposes. Nanka sands outcrops mainly at Nanka and Oko in Orumba North LGA. Lignite was deposited in the Oligocene to Miocene; and it alternates with gritty clays in places. Outcrops of lignite occur in Onitsha and Nnewi. The latest of the tour geological formations is the Benin Formation or the coastal plain sands deposited from Miocene to pleistocene. The Benin Formation consists of yellow and white sands. The formation underlies much of lhiala LGA. Thick deposits of alluvium were laid down in the western parts of the state, south and north of Onitsha in the Niger and Anambra river floodplains. Landforms and Drainage Anambra State falls into two main landform regions: a highland region of moderate elevation that covers much of the state south of the Anambra River, and low plains to the west, north, and east of the 22 highlands. The highland region is a low asymmetrical ridge or cuesta in the northern portion of the Awka- Orlu Uplands, which trend roughly southeast to North West, in line with the geological formations that underlie it. It is highest in the southeast, about 410m above mean sea-level, and gradually decreases in height to only 33m in the northwest on the banks of the Anambra River and the Niger. The lower cuesta, formed by the more resistar resistant sandstone rocks of the Imo Shale, rises to only 150m above mean sea-level at Umuawulu an decreases in height northwestward to only 100m < Achalla. Its escarpment faces the Mamu River plain and has a local relief of between 80 and 30m west of it. This is the higher cuesta, formed by the sane stones of the Ameke Formation. Its height is above 400m in the south-east at lgbo-ukwu and lsuofii decreasing north-westward to less than 300m at Agbana, and to only 100m at Aguleri. Vegetation and Soils: Three soil types can be recognised in Anambra State. They are: (i) alluvial soils, (ii) hydromorphic soils, and (iii) ferallitic soils. The alluvial soils are pale brown loamy soils. They are found in the tow plain south of Onitsha in Ogbaru and in the Niger Anambra low plain north of Onitsha. They differ from the hydromorphic soils in being relatively immature, having no well-developed horizons. Ecological Issue: Some of the major ecological issues encountered in Anambra mostly includes; flooding and erosion. The erosion issues have exacerbated overtime due to the extensive forest clearing, often by bush burning, and continuous cropping with little or no replenishment of soil nutrients. This further resulted in the disruption of the ecological equilibrium of the natural forest ecosystem. Such a situation in a region of loosely consolidated friable soils is prone to erosion, giving rise to extensive gully formation typical to the one experience in Enugu-Ukwu village and several other communities in Anambra State. 2.2 Overview of Enugwu-Ukwu Enugwu-Ukwu (or Enugu Ukwu) is a larger town in Anambra State, Nigeria. Basically, Enugwu-Ukwu town is geographically situated on a hilly terrain; thus it is named after its geographical topography. Enugwu-Ukwu in Igbo literally means: "on top of a high hill". It is predominantly occupied by the Igbo ethnic group of Anambra State. Most of its inhabitants are Christians (majorly Roman Catholics). It is located in Njikoka Local Government Area of Anambra State. Major villages that make up the town include Uruokwe, Urunebo, Enu-Avomimi, Adagbe-Avomini, Umu-Atulu, Urualor, Akiyi, Avomimi, Awovu, Enuagu, Ire, Orji, Orofia, Osili, Umuakwu, Umuatulu, Umuatuora, Umuokpaleri, Uruekwo, Urukpaleke, and Uruogbo. Enugwu-Ukwu is surrounded by neighbouring towns comprising Nawfia, Nise, Agukwu-Nri, Nimo, Abagana and Enugwu-Agidi. The estimated population as at 2009 is 448,000 (NPC). 23 The traditional authority adopts the kingship title of Eze Enugwu-Ukwu na Igwe Umunri. The immediate past traditional ruler of the town was His Majesty, Igwe Osita Agwuna III. The current traditional ruler is His Majesty, Igwe Ralph Obumnemeh Ekpeh (Okpalanakana-Ukabia Nri IV) Erosion and Watershed Issues: The main ecological hazards in the area are accelerated gully erosion and flooding. Poor drainage and town planning in a region of loosely consolidated and easily eroded soils is prone to serious erosion, giving rise to extensive gully formation. This as well as the topography of the area is the main cause of the erosion menace in Enugwu-Ukwu. The area is located down the slope of the hill and this results in surface run-off from towns uphill flowing through the community. 2.3 Overview of the Project Area The project area cuts across two (2) major communities in Enugwu-ukwu. The larger section in Urunnebo community have separated Umuajana and Umunwankwo Villages while the other section falls in Umuorji village in Avomimi Community of Enugwu-Ukwu. Land ownership system in the community is based mainly on inheritance. The gully system have continued to expand with the rains. The slope of the gully area, the characteristics of the incipient soil, man-made interferences, unguided run-off flow as well as poorly terminated drainage systems are the combined causes of the problem. This has resulted to destruction of infrastructure and negatively impacted on agricultural activities as well as reduction of land suitability for other applications. Some families have been displaced as a result of the menace. The Main Gully head originate around coordinates N06.16569° E007.01813°. Field investigation revealed that the gully begins from Eziemenike culvert, near the Eke market running downstream. The Left finger gully head originating from around Ufom’s compound and joins the Main gully just behind Chief Tony Okeke’s residence. Both continues to form a confluence at the Ebenebe tree (N06.16179° E007.01788°). Figure 2 A Section of the Gully The Right Finger gully originates from the Eziegbo culvert (N06.16489° E007.01489°) and runs downstream through the back of St Francis Catholic Church while the Right Finger Gully-1 originates 24 from around Gosiora’s Compound (N06.16294° E007.01716°) running south west to join the Right Finger gully. Both progress downstream meet the Main Gully at the Ebenebe tree (N06.16179° E007.01788°) and then continues as the Main gully downstream towards the FADAMA III area up to Ngene Lake. Figure 3 The Gully Showing part of an affected building Members of the community are presently carrying out some palliative measure (use of concrete structures and sand bags) to mitigate the impact of the gullies at different sections. This gully-system if not checked will result to a major disaster in the communities. The NEWMAP intends to rehabilitate the erosion gully site and reduce longer-tern erosion vulnerability in the targeted areas. This activity will be employed through some civil works such as construction of infrastructure and stabilization of the gully. A Feasibility study report and an Engineering design report has already been prepared for the erosion gully intervention, which highlights the detailed civil works that will be carried out. The rehabilitation works will trigger some of the World Bank Safeguard Policies including Environmental Assessment OP 4.01; Natural Habitats OP 4.04; Physical and Cultural Resources OP 4.11 and Involuntary Resettlement OP 4.12. 2.4 Baseline Information This section gives a general description of the Physical, biological and socio-economic environment of the project area. 2.4.1 Physical Environment Climate The climate is characteristically of the Equatorial type found in South-Eastern Nigeria, especially warm and humid. This is a resultant effect of its prevailing seasonal wind, nearness to the sea coast and the relatively flat topography of the environment. A humid Tropical Maritime (mT) from across the Atlantic Ocean in the south dominates the region in the longer wet season (April to October). A drier Tropical 25 Continental (cT) air mass blowing from the northeast direction controls the climate and meteorology of the area during the dry season (November to March). Around December, it culminates into a very hungry (i.e. dry) and foggy harmattan wind as it blows right from across the continental region of the West African sub-region. Most of the original Rain forest in the project community has been lost due to clearing for farming and human settlement. A few examples of the original rain forest remains at places like the Ngene Nnevoaka shrine. Figure 4 Entrance into the Ngene nnevoaka shrine Temperature Air temperature has seasonal and diurnal variations. On the average, the ambient maximum air temperature in the area varies from 28.00C to 37.50C while the minimum temperature varies from about 220C to 270C. Lowest values are recorded in the month of July through August. This coincides with the peak of the rainy season. The diurnal range is kept at a low 40C. The temperature of the area is influenced primarily by the apparent movement of the sun, wind direction and speed as well as land configuration (NIMET). 40 35 30 25 20 15 10 5 0 2011 2012 2013 2014 2015 26 Figure 5 Ambient Temperature of Project Area (NIMET) Rainfall The climate is tropical with two distinct seasons, the rainy season and the dry season. The rainy season begins around the first of April and continues into October while the dry season runs from November to March. Rainfall reaches its highest monthly maximum of 300 – 400mm during the month of June through September and drops to 0.0-1.0mm in December and January. During the rainy season, a marked interruption in the rains occurs during August, resulting in a short dry season often referred to as the “August break�, though for years now this has not been consistent in August due to climate change. 2011 2012 2013 2014 2015 600 500 400 300 200 100 0 Figure 6 Rainfall Pattern of the Project Area (NIMET) The dry season is characterized by the cold dry “Harmattan� from the Sahara Desert. During this period, which begins in November and runs through January a dry and dust laden wind blows from the Sahara Desert. This sometimes makes the hills obscure due to the poor visibility. The sun is also obscured during this period by the prevailing dust haze. Relative humidity Relative humidity is high both day and night. It is greater than 85% at night, above 81% in the mornings and between 60% and 75% in the evenings. Generally the drier months (December to February) have lower values. 9 8 7 6 5 4 3 2 27 1 0 Jan Feb March April May June July August Sept Oct Nov Dec Figure 7 Relative Humidity of the Project Area (NIMET) Wind Speed Wind speed is generally low and usually less than 3 m/s under calm conditions most of the year. Relatively higher wind speeds may occur mainly in the afternoons inducing convective activities and creating diffusion characteristics. Incidences of these are often associated with thunder and lightning especially during changing seasons. Atmospheric disturbances such as line squalls and disturbance lines often induce the variability that results in speeds higher than 5 m/s. Such increases characterize the beginning of rainy season (March-April) and end of heavy rains (September-October), during which storms are more frequent. The harmattan season (December to February) can give rise to occasional high wind regimes. Wind Direction Wind directions are quite variable over the region. Data shows that about 60% of the winds are south- westerlies and westerlies during the day in the wet season (NIMET). Southerlies, south easterlies and south westerlies prevail more in the night during the period. This implies that directions are usually more variable in the nights than in the mornings. The winds are mostly northerlies, north easterlies and north westerlies in the dry season particularly in the mornings. They are more of southerlies south easterlies and/or westerlies during the evenings, indicating the fairly strong influences of the adjoining maritime oceanic air masses, contrasting land and sea breezes as well as appreciable degree of differential heating of the two surfaces. Geology Two ridges or cuestas, both lying in a North-South direction, form the major topographical features of the area. It lies on the Middle Eocene sediment of the Tertiary period called the Bende-Ameki Formation. It constitutes the main bulk of the Eocene strata overlaying the Imo shale group. Ameki formation consists of a series of highly fossiliferous greyish green sandy clay with calcareous concretions and white clayey sandstone. Nanka Sand is a lateral equivalent of the Bende-Ameki Formation. The lithology consists of fine to coarse sandstone with abundant intercalations of calcareous shale and thin shaley limestone below, and of loose cross-bedded white or yellow sandstone with bands of fine-grained sandstone and sandy 28 clay above. The Ameki Formation is uncomfortably overlain by the Ogwashi Asaba Formation. The contact between these two formations can be discerned by the occurrence of thin layers of lignite. 2.4.2 Biological Environment Flora The vegetation types encountered within the Study Area are as follows: - Areas of fallow bush of varying ages - Fields used for rotational subsistence farming - Degraded secondary rainforest as well as statutory and communal forests All flora habitats surveyed were found to comprise shrubs, grasses, sedges and a mixture of mature trees and re-growing juvenile trees. Some of the crops sited during the field trip include oranges trees, plantain plants, cassava, yam, cocoyams, mango trees, breadfruit trees, udala trees, ogbono/ugili trees etc. Table 1 Some common Plants found within the project community S/NO COMMON NAME BOTANICAL NAME 1. Maize /corn Zea mays 2. Cassava Manihot esculenta 3. Banana Musa sapientum 4. Water leaf Talinum triangulare 5. Okro Abelmoschus esculentus 6. Pineapple Ananas comosus 7. Guava Psidium guajava 8. Cocoyam Colocasia esculenta 9. Pumpkin Cocurbita pepo 10. Melon Citrullus vulgaris 11. Pepper (small) Capsicum annuum 12. Mango Magnifera indica 13. Pawpaw Carica papaya 29 14. Bitter leaf Vernonia amygdalina 15 Oil Palm Elaeis guineensis 16 Mango Mangifera indica 17 Avocado Pear Persea Americana 18 Plantain Musa paradisiaca 19 Coconut Cocos nucifera Fauna Some wildlife found in the project area include grass cutters, monitor lizard (sighted), etc. The community members also informed the consultant of the presence of wild dogs within the forest areas of the community. Furthermore, goat, sheep, poultry and pig were some of the livestock sighted within the project area. Demographics The study intends to identify and document the demographic data of the project communities such as population, literacy level, occupation, dependency level, housing and social amenities. These data will be useful not only in establishing the importance of the rehabilitation of the Enugwu-Ukwu Erosion site but equally in quantifying the environmental and social impacts of the planned works which will help determine the management plans for the said project. It will also be used in the analysis for provision of livelihood alternative during the ARAP Implementation. More importantly, the baseline data will be useful for monitoring and evaluating the post implementation condition of the community and by implication the success of the project. Anambra State is located within the southeastern zone of Nigeria with Awka as its capital. Onitsha and Nnewi, which are listed amongst the biggest commercial cities in Africa, are in Anambra State. The state has a landmass of over 4120 sq. km. Enugwu-Ukwu is mostly semi-urban with some rural communities. It has an estimated population of 448,000 (NPC 2009). This is one of the oldest settlements in Igboland established at the centre of the Nri civilization and was the cradle of Igbo civilization. Urunnebo, the immediate project community, is one of the 18 villages that make up Enugwu-Ukwu as a whole. Umuorji-Avomim is also another community where the erosion site transverses. Local Economy The people of Urunnebo are predominantly farmers, traders and artisans who engage in various forms of arts and crafts. They also have educated elites in various professions e.g. Doctors, Lawyers, Accountants. Bankers, Mechanical and Electrical Engineers, Musicians, Professional Drivers (including tractor drivers) etc. The diverse vegetation and soil types in the project state encourage the practice of 30 a variety of agricultural activities like crop farming, forestry, fishery and animal husbandry. Some of the crops include maize, cassava, yam, palm produce and vegetables. Some few others are into palm oil and Artisanship. Commercial activities vary and include mainly petty trading which can be found in all nooks and cranny in the project area. There is an Eke market which due to development have been converted to a daily market with several lock up stores/shops within the community. The community also have a Micro-finance Bank and a Business Centre within the community. Figure 8 Eke Market at Urunnebo Land Use/Tenure  While majority of the land use is for agricultural purposes others are for residential settlement, market places and public reserve for future development uses.  A combination of traditional land ownership system and government ownership of land is observed in the area. However, the Urunnebo community practices the traditional land ownership system. Most of the land are inherited while some are either leased or bought for agricultural or developmental purposes. Communal Institutions The community has an organized system of administration which comprises the following: a) Urunnebo Improvement Union made up of male and female wings b) Age grades namely: Imi-Utaba, Ekwegbalu, Ekwutosi, Onweluego, Onweluzo, Abiriba, Udoka, Ekwueme, Oganiru, Igwebuike, Ifeadigo, Ofuobi and other age grades still on formative stages. Historic and Cultural Resources The survey has so far identified some historic and/or cultural resources in the area. This includes the Ngene nnevoaka shrine and the Ngene ube shrine located at Urunnebo and Umuorji respectively. Other sacred resources include Ukolo, Iyiagu Lake, and the four sacred stools of Iddi, Whum, Emenulu and Iyansele. The communities also have village squares where issues are discussed or elders go for relaxation. 31 Figure 9 Ngene-Ube Shrine Figure 10 Obu Ngene-Nnevoaka shrine Ngene nnevoaka shrine is a place of traditional worship which is said to have been in existence before the coming of the Europeans to Nigeria. It is the first place of worship for the people of the community before the advent of Christianity. Ngene nnevoaka shrine is believed to be a source of healing to the sick. People also consult it for divination, good health, prosperity, protection of life and property. It mediates in conflict and ensures that there is equity, peace and justice between disputing parties. Ngene nnevoaka shrine is still very active till date. People from far and near still visit the shrine. The Ngene Ube shrine is also another shrine located at Umuorji-Avomimi. It also mediates in conflict and ensures that there is equity, peace and justice between disputing parties. However, due to the coming of Christianity, the number of people who go here for worship have reduced. In the community, Udala tree is regarded as a sacred tree. It is believed that a woman who finds it difficult to conceive usually goes there with cola-nuts to pray. Libation would be made on her behalf by the Chief Priest. It is a common believe that once this libation is made, the woman would take in. The Udala fruit is and in this community, the fruits of udala tree are not plucked. The fruits are allowed to shed and fall to the ground on its own for people to pick and lick. In Urunnebo community, udala is always associated with children, that’s why most often, you find children clustering around the tree. Educational Institutions: The Community have a Community Primary School as well as a community library (Ozom Library). Health assessment Field observation showed that there is a Primary Health Care Clinic available at the Community Hall. Visit to this healthcare facility and interviews were conducted during the scoping exercise. Observation showed that Malaria is the prevalent disease in the project area. Literature shows that children and pregnant women are more prone to malaria (WHO, 2007). Vaccinations and maternity care are also performed in this health facility. 32 2.5 Socio-Economic Baseline Conditions of Project Affected Persons (PAPs) The socio-economic assessment studies were aimed at examining the socioeconomic conditions of the PAPs. This will be relevant for measuring and monitoring the progress of this RAP implementation. 2.5.1 Gender Distribution of PAPs It was gathered from the field survey that majority of the PAPs (about 72%) are males while females are 28%. This goes to suggest that vulnerability concerns will apply as there are a good number of female PAPs. This implies that livelihood restoration measures should be properly and thoroughly carried out in consulting with PAPs. Gender 28% Female 72% Male Figure 11 Gender Distribution of PAPs within the project area 2.5.2 Age Distribution of PAPs As shown in figure below, PAPs are adults that range from 21 to above 61 years. The graph shows that those between ages 51-60 years and those above 61 years constitute the dominant population of PAPs with a combined proportion of about 74%. The least age group among PAPs belongs to those from 21- 30 and 31-40 years with a population of 3% and 4% respectively. The highest population of PAPS(48%) were within 61years and above. 33 Age [PERCENTAGE] [PERCENTAGE] [PERCENTAGE] [PERCENTAGE] [PERCENTAGE] 21-30 31-40 41-50 51-60 61 and Above Figure 12 Age Distribution of PAPs within the project area 2.5.3 Marital status of PAPs PAPs are predominantly married people (about 73%). Singles and widows/widowers are the other marital status that featured among the PAPs. The significance of this result is that PAPs are majorly men and women who are the breadwinners and help mates in their respective households. Widows/widowers constitute 24% of the PAPs. Marital Status 24% 3% Married Single 73% Widow Figure 13 Marital Status of PAPs within the project area 34 2.5.4 Religious practice of PAPs All the respondents are Christians and are mostly Roman Catholics. No Muslim was among the PAPs. However, less than 1% practice African Traditional Religion. It goes to show that cultural heritage is an integral part of some of the PAPs even though Christianity is practiced in the community. 2.5.5 Education Most people or PAPs have some form of education (99%). The highest number of PAPs (57%) Indicated that their highest level of academic qualification is SSCE. There was no record of PAPs without a form of formal education. The implication of this section to this ARAP is that majority of PAPs have the minimum level of education that might help them in making informed decision, or participate meaningfully in the resettlement plan meetings that is to come. Education 57.2 60 50 40 30 20 14.3 20 1.5 2 5 10 0 Education Figure 14 Educational Qualification of PAPs within the project area 2.5.6 Average household size of PAPs The survey shows that most of the PAPs (57%) run large households (Above 7). 20% of the PAPs have medium sized households while 27% have families of 2-4 members. This goes to show that the level of dependent on the Head of Household will be much and there will be a heavy burden on the family if involuntary displacement occurs. 35 Family Size Small(2-4) 23% Large(Above 7) 57% Medium(5-&) 20% Small(2-4) Medium(5-&) Large(Above 7) Figure 15 Average Family Size of PAPs within the project area 2.5.7 Occupation Project affected persons were classified into different types of occupation. Figure below shows that majority (93%) of the PAPs in this community are self-employed with 77% engaged in trading, while 11% of the affected respondents are farmers. 7% of the PAPs are public servant, then the remaining (5%) are artisans and engage in such businesses as welding, mason, etc. Occupation 7% 5% 11% 77% Trading Farming Artisan Public Servant Figure 16 Occupation of PAPs within the project area 36 2.5.8 Average Income status of PAPs Field survey shows that dominant income groups amongst PAPs lie between ₦6,000- ₦20,000 and ₦21,000 -₦80,000 and ₦81,000-₦120,000 per Month respectively. The trend shows that about 80% of PAPs each belong to one of these three groups. The survey also shows that about 8% fall within the income of ₦1000- ₦5000 per month while about 12% of PAPs earn ₦120,000 or more per month. Monthly Income 8% 12% 12% ₦1000-5000 28% 40% ₦6000-20000 ₦21000-80000 ₦81000-120000 Above ₦120000 Figure 17 Average Monthly Income of PAPs within the project area Average income of PAPs in the project area were measured at two levels; the overall average which indicates an aggregation of middle and low level income earning PAPs and the low income groups with lowest limit of N500 per day. The outcome is that on the overall aggregation, PAPs mean income is ₦4500 or $22.7 per day (for middle and low income combined) and ₦1200 or $6 per day for lower income group. Based on the later statistic, PAPs in the project area earn on the average, about $1818 per annum. This figure puts PAPs in the class of middle-income economy group according to World Bank development indicators (World Bank, 2016) Lower-middle-income and upper-middle-income economies are separated at a GNI per capita of $4,125. Although these results imply that PAPs can maintain reasonably, good standard of living, it is however, not inconceivable that impacts on their sources of livelihood may have adverse impacts on their income sustenance and standard of living, especially with the dependence on trading, farming as well as low rate of saving culture in the less developed countries. 2.5.9 Respondents legal or title right to property Different means of ownership of property/asset was highlighted, in which the majority (90%) are owned by Individual while 3% are on rent and 6% are family shared properties. About (1%) own right to the property by inheritance. None of PAPs recorded have legal right to property through certificate of occupancy (C of O). This may be due to the fact that the site is within a rural settlement. 37 Ownership Type 70 60 50 40 30 20 10 0 Community owned Family owned Owner Tenant Figure 18 Asset Ownership Types among PAPs in the project area 2.5.10 Choice of assistance Majority of the PAPs preferred support for cash grant (67%). About 10% supported Land for Land replacement while 27% chose house in resettlement site if any. CHOICE OF ASSISTANCE 6% 27% Cash assistance House in resettlement site Land for land loss 67% Figure 19 Choice of Assistance by PAPs in the Project Area 38 2.6 Summary of the Socio-economic Condition of the Project Area The project location site area is an agrarian community with most of the PAPs owning their own businesses. The informal sector, mainly petty traders are well represented within the community. Crop- free period seldom exceeds one year. Thus the execution of this ARAP must ensure that the PAPs agricultural resources are not taken for granted. Also some of the PAPs whose structures may be affected reside outside the community and come in during weekends or during occasions. This should also be considered while implementing the ARAP ensuring adequate compensation in all scenarios of PAPs. 39 3 CHAPTER THREE POLICY LEGAL AND REGULATORY FRAMEWORK 3.1 Introduction A number of national and international environmental guidelines are applicable to the operation of the NEWMAP. The policy and regulatory frameworks discussed in this section guided the preparation of this ARAP. 3.2 The Resettlement Policy Framework (RPF) for the NEWMAP The Resettlement Policy Framework (RPF) was prepared as a guide to set out the general terms under which land acquisition/encroachment, and/or any form of involuntary displacement of persons from the land or right of way of the project can take place, to comply with the World Bank Operational Policy (OP 4.12 - Involuntary Resettlement). The RPF specified that during implementation stage and following the identification of sub- projects and sites for the developments, individual resettlement action plans should be prepared that must be consistent with the provisions of the RPF. It also provided a generic process for the preparation of resettlement plans. The RPF specified that in addressing impacts, resettlement plans must include measures to ensure that the displaced persons are:  Informed about their options and rights pertaining to resettlement;  Consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives;  Provided prompt and effective compensation at full replacement cost for losses of assets and access attributable to the project;  Enabled to restore and preferably improve their living standards compared to the pre- project Condition. In the overall, a major objective of the RPF was to ensure that PAPs are meaningfully consulted, participated in the planning process and are adequately compensated to the extent that at least their pre-displacement incomes have been restored and in a fair and transparent process. The RPF specified that occupants who must be displaced will be moved at minimum cost and at short distance as possible. It also states that occupants who must be moved will be assisted physically by inclusion of preparatory site work in the works programme of the contractor and/or by 40 payments to move shops and items of livelihoods to alternative locations. It also recommended the setting up of a dispute resolution mechanism that will address complaints and grievances that may emanate from the resettlement or compensation process. The preparation of this Resettlement plan is consistent with the guidelines and recommendations of the RPF of NEWMAP, which is also found to be in agreement with the guidelines of the World Bank OP 4.12. 3.3 Relevant Nigeria Acts and Legislations 3.3.1 Land Use Act of 1978 and Resettlement Procedures The Land Use Act, Cap 202, 1990 Laws of the Federation of Nigeria is the applicable law regarding ownership, transfer, acquisition and all such dealings on Land. The provisions of the Act vest every Parcel of Land in every State of the Federation in the Executive Governor of the State. He holds such parcel of land in trust for the people and government of the State. The Act categorized the land in a state to urban and non-urban or local areas. The administration of the urban land is vested in the Governor, while the latter is vested in the Local Government Councils. At any rate, all lands irrespective of the category belongs to the State while individuals only enjoy a right of occupancy as contained in the certificate of occupancy, or where the grants are “deemed�. Thus the Land Use Act is the key legislation that has direct relevance to resettlement and compensation in Nigeria. Relevant Sections of these laws with respect to land ownership and property rights, resettlement and compensation are summarized in this section. The Governor administers the land for the common good and benefits of all Nigerians. The law makes it lawful for the Governor to grant statutory rights of occupancy for all purposes; grant easements appurtenant to statutory rights of occupancy and to demand rent. The Statutory rights of Occupancy are for a definite time (the limit is 99 years) and may be granted subject to the terms of any contract made between the state Governor and the Holder. Local governments may grant customary rights of occupancy to land in any non-urban area to any person or organization for agricultural, residential, and other purposes, including grazing and other customary purposes ancillary to agricultural use. But the limit of such grant is 500 hectares for agricultural purpose and 5,000 for grazing except with the consent of the Governor. The local Government, under the Act is allowed to enter, use and occupy for public purposes any land within its jurisdiction that does not fall within an area compulsorily acquired by the Government of the Federation or of relevant State; or subject to any laws relating to minerals or mineral oils. Requirements of the Land Use Act The State is required to establish an administrative system for the revocation of the rights of occupancy, and payment of compensation for the affected parties. So, the Land Use Act provides for the establishment of a Land Use and Allocation Committee in each State that determines disputes as to compensation payable for improvements on the land. (Section 2 (2) (c). In addition, each State is required to set up a Land Allocation Advisory Committee, to advise the Local Government on matters related to the management of land. The holder or occupier of such 41 revoked land is to be entitled to the value of the unexhausted development as at the date of revocation. (Section 6) (5). Where land subject to customary right of Occupancy and used for agricultural purposes is revoked under the Land Use Act, the local government can allocate alternative land for the same purpose (section 6) (6). If local government refuses or neglects within a reasonable time to pay compensation to a holder or occupier, the Governor may proceed to effect assessment under section 29 and direct the Local Government to pay the amount of such compensation to the holder or occupier. (Section 6) (7). Where a right of occupancy is revoked on the ground either that the land is required by the Local, State or Federal Government for public purpose or for the extraction of building materials, the holder and the occupier shall be entitled to compensation for the value at the date of revocation of their unexhausted improvements. Unexhausted improvement has been defined by the Act as: anything of any quality permanently attached to the land directly resulting from the expenditure of capital or labour by any occupier or any person acting on his behalf, and increasing the productive capacity the utility or the amenity thereof and includes buildings plantations of long-lived crops or trees, fencing walls, roads and irrigation or reclamation works, but does not include the result of ordinary cultivation other than growing produce. Developed Land is also defined in the under Section 50 (1) as follows: Land where there exists any physical improvement in the nature of road development services, water, electricity, drainage, building, structure or such improvements that may enhance the value of the land for industrial, agricultural or residential purposes. It follows from the foregoing that compensation is not payable on vacant land on which there exist no physical improvements resulting from the expenditure of capital or labour. The compensation payable is the estimated value of the unexhausted improvements at the date of revocation. Payment of such compensation to the holder and the occupier as suggested by the Act is confusing. Does it refer to holder in physical occupation of the land or two different persons entitled to compensation perhaps in equal shares? The correct view appears to follow from the general tenor of the Act. First, the presumption is more likely to be the owner of such unexhausted improvements. Secondly, the provision of section 6 (5) of the Act, which makes compensation payable to the holder and the occupier according to their respective interests, gives a pre-emptory directive as to who shall be entitled to what. Again the Act provides in section 30 that where there arises any dispute as to the amount of compensation calculated in accordance with the provisions of section 29, such dispute shall be referred to the appropriate Land Use and Allocation Committee. It is clear from section 47 (2) of the Act that no further appeal will lie from the decision of such a committee. If this is so, then the provision is not only retrospective but also conflicts with the fundamental principle of natural justice, which requires that a person shall not be a judge in his own cause. The Act must, in making this provision, have proceeded on the basis that the committee is a distinct body quite different from the Governor or the Local Government. It is submitted, however, that it will be difficult to persuade the public that this is so since the members of the committee are all appointees of the 42 Governor. Where a right of occupancy is revoked for public purposes within the state of the Federation; or on the ground of requirement of the land for the extraction of building materials, the quantum of compensation shall be as follows:  In respect of the land, an amount equal to the rent, if any, paid by the occupier during the year in which the right of occupancy was revoked.  in respect of the building, installation or improvements therein, for the amount of the replacement cost of the building, installation or improvements to be assessed on the basis of prescribed method of assessment as determined by the appropriate officer less any depreciation, together with interest at the bank rate for delayed payment of compensation. With regards to reclamation works, the quantum of compensation is such cost as may be substantiated by documentary evidence and proof to the satisfaction of the appropriate officer.  in respect of crops on land, the quantum of compensation is an amount equal to the value as prescribed and determined by the appropriate officer. Where the right of occupancy revoked is in respect of a part of a larger portion of land, compensation shall be computed in respect of the whole land for an amount equal in rent, if any, paid by the occupier during the year in which the right of occupancy was revoked less a proportionate amount calculated in relation to the area not affected by the revocation; and any interest payable shall be assessed and computed in the like manner. Where there is any building installation or improvement or crops on the portion revoked, the quantum of compensation shall follow as outlined above and any interest payable shall be computed in like manner. 3.3.2 Forestry Act This Act of 1958 provides for the preservation of forests and the setting up of forest reserves. It is an offence, punishable with up to 6 months imprisonment, to cut down trees over 2ft in girth or to set fire to the forest except under special circumstances. Nigeria is at present a wood deficit nation. In order to ameliorate the situation, the policy on forest resources management and sustainable use is aimed at achieving self-sufficiency in all aspects of forest production through the use of sound forest management techniques as well as the mobilization of human and material resources. The overall objectives of forest policy are to prevent further deforestation and to recreate forest cover, either for productive or for protective purposes, on already deforested fragile land. Specifically, the National Agricultural Policy of 1988 in which the Forestry Policy is subsumed, provides for:  Consolidation and expansion of the forest estate in Nigeria and its management for sustained yield.  Regeneration of the forests at rates higher than exploitation.  Conservation and protection of the environment viz: forest, soil, water, flora, fauna and the protection of the forest resources from fires, cattle grazers and illegal encroachment. 43  Development of Forestry industry through the harvesting and utilization of timber, its derivatives and the reduction of wastes.  Wildlife conservation, management and development through the creation and effective management of national parks, game reserves, tourist and recreational facilities, etc. 3.4 State Legislations The relevant state ministry is the Anambra State Ministry of Lands and Urban Planning. Principally the functions of the Ministry are to provide the following services in line with the laws governing its establishment: a. Acquisition of land and layouts on behalf of the Government. b. Land schedules, including processing of Certificates of Occupancy, Mortgages, Assignment, Leases, Subleases, etc. c. Payment of compensation to land owners in cases of land acquisition d. Conduct of layout designs e. Conduct of perimeter survey of layouts after land acquisition f. Identification of land for possible acquisition g. All revision of numbers to plots on State land h. Review and approval of community layouts i. Conduct of surveys with respect to state lands j. Approval of survey plans for non-state lands for purposes of registration with the lands registry k. Carrying out surveys for individuals with respect to non-Government land l. Approving permits for: (i) Buildings (ii) Filing stations (iii) Private/Community layouts; (iv) Erection of telecommunication masts m. Enforcement of Town and Urban Planning Law and regulations made pursuant thereto, including demolition of illegal and unauthorised structures n. Collection of land related fees and charges on behalf of the Government It gives advices to the government on land tenure issues, and also manages government land and properties. The Ministry is also tasked with administrative rights to land use decree, urban development, city and town rejuvenation. 44 3.5 International Guidelines International Development Partners/Agencies such as World Bank and other financial organizations interested in development projects recognize this highly especially in development that result in involuntary resettlement. It is against this background that policies and guidelines have been set for managing such issues. The World Bank’s policy on involuntary resettlement will be applied in any sub-project of the NEWMAP that displaces people from land or productive resources due to land take. Where there is conflict between national legislation and World Bank Operational Policies, the latter policies shall prevail. 3.6 The World Bank Policy on Involuntary Resettlement (OP. 4.12) and the ARAP for Enugwu-Ukwu Gully Erosion site The Bank’s policy on Involuntary Resettlement advocates that where feasible, involuntary resettlement should be avoided or minimized. Resettlement shall be conceived and executed as a sustainable development program, where it is inevitable, providing sufficient investment resources to enable persons displaced by the project share in project benefit. Persons displaced shall be: i. Duly consulted and should have opportunity to participate in the planning and execution of the resettlement; ii. Compensated for their losses at full replacement cost prior to civil works; iii. Assisted with the move and supported during the transitional period in the resettlement site; iv. Assisted in their effort to improve their former living standards, income earning capacity and production levels or at least to restore them For the Enugwu-Ukwu gully erosion site rehabilitation, which will also involve civil works, the World Bank required the preparation of an Abbreviated Resettlement Action Plan, which will guide in the execution of a sustainable resettlement or compensation process for all the PAPs. An ARAP is deemed best fit because it is envisaged that the Project Affected Persons (PAPs) will be less than 200 persons and/or level of income loss will be less than 10%. 3.6.1 Comparison between Land Use Act and the World Bank’s Policy (OP4.12) on Compensation In this section a comparison is made between the World Bank policies (OP4.12) and the Nigerian Land Use Act. Whereas the law relating to land administration in Nigeria is wide and varied, entitlements for payment of compensation are essentially based on right of ownership. The Bank’s OP4.12 is fundamentally different from this and states that affected persons are entitled to some form of compensation whether or not they have legal title if they occupy the land by an announced cut -off date. The Nigeria Land Use Act and World Bank Safeguards Policy OP/BP 4.12 agree that compensation should be given to PAPs in the event of land acquisition and displacement of persons prior to the 45 commencement of works. Thus all land to be acquired by the government for this project will be so acquired subject to the Laws of Nigeria and the Bank OP4.12. Table 2 Comparison of Nigerian land Use Act and World Bank OP4.12 on compensation S/N Category of PAPS Nigerian Law World Bank OP/4.12 1 Land Owners- statutory Cash compensation based upon Recommends land-for-land compensation. Other rights market value. compensation is at replacement cost. 2 Land Owner- customary Cash compensation for land full Equivalent value. If not, cash at replacement value, rights improvements; compensation including kind transfer costs with other village/district land 3 Land Tenants Entitled to compensation based Are entitled to some form of compensation whatever upon the amount of rights they the legal recognition of their occupancy. hold upon land. 4 Land Users Not entitled to compensation Entitled to compensation for crops, may be entitled to for land, entitled to replacement of land and income shall be restored to compensation for crops. pre-project levels at least. 5 Owners of “Non- Cash compensation based on Entitled to in-kind compensation or cash compensation permanent� Buildings market value. at full replacement cost including labor and relocation expenses, prior to displacement. 6 Owners of “Permanent� Cash Compensation is based Entitled to in-kind compensation or cash compensation buildings on market value. at full replacement cost including labour and relocation expenses, prior to displacement. This ARAP will be aligned with the World Bank Operational Policies including Involuntary Resettlement Policy which indicate best practices for rehabilitation of livelihoods of people affected by the implementation of the project. This is so because they are involved in the funding of the project and also because their respective policies most fulfil the pro-poor objectives of the project, ensuring that the conditions of PAPs are preferably improved and at least restored to pre displacement levels as well as offers special considerations for vulnerable and landless PAP. 3.6.2 Conclusion Drawn from the Review of World Bank Policies on Involuntary Resettlement Review of the different policy guidelines of the World Bank (OP/BP 4.12) shows that primarily, the World Bank agree that PAPs be compensated or assisted irrespective of legal status of PAPs to the land/or place they occupy. The key concern articulated in this policy is to ensure that PAPs are compensated or assisted including income restoration measures to ensure that they are not economically worse off relative to pre-project period. However, in the event of divergence between the two, the World Bank safeguard policy shall take precedence over Nigeria Land Use Act. 46 4 CHAPTER FOUR IDENTIFICATION OF PROJECT IMPACTS AND PROJECT AFFECTED PERSONS Chapter 1 of this report provides the methodology employed for impacts and PAPs identification, which included census/inventory survey and consultation with the PAPs. Consultation with the project community and PAPs started during the preliminary visit in April 2016. The inventory taken showed that land acquisition will occur for 2 (Two) of the PAPs as a result of the project. A Zinc building used for traditional worship will be impacted which falls within the 10 meter setback within the corridor of the Main gully. This happens to be the only Land owned by the PAP. Also a family burial site belonging to the Iwotor Family will also be impacted. Crops planted on farmlands and associated economic trees were observed as important features that would be affected in the event of the proposed work along the corridor of the gullies. It was also observed that crops planted within the ROW of the drainages as well as encroachment of structures and fences are other categories of impacts by the proposed work. 47 Figure 21 Impacted Property Figure 20 Ezenwani Shrine 4.1 Impact Reduction Measures Undertaken The following are technical steps taken by the Anambra State NEWMAP PMU which have resulted in the reduction of adverse impacts of the project:  The engineering design for the intervention using gabion retaining walls and interlocked blocks over filtered materials at critical areas near the gully corridor (especially close to structures) was employed. This will help retain the existing structure thereby preventing possible demolition of the structure. Also geotextile was also employed in some areas.  The setback for access and buffer on the corridor was made known to the stakeholders to be 10 meters and that in the event of work in such locations all affected properties are to be removed by their owners to give the required right of way for the work.  Consulting/communicating with the people of the project area and PAPs in particular on the day and time to expect civil work activities within their respective location. This will give the PAPs opportunity to harvest mature crops before the beginning of civil works. In spite of the outlined impact reduction measures above, mitigation measures have also been clearly prepared in this document, which is in line with the World Bank policy (OP 4.12) on involuntary resettlement to ensure that those who must suffer economic impact are restored to the pre-project state. 4.2 Land acquisition along the corridor As already established above, two PAPs will be displaced as a result of the rehabilitation project, therefore Land acquisition will be required for these project affected person. Also space may be required in the set back that will serve as camp, where equipment and materials will be stored and used. This will be minimal and restricted to the 10m set back from the edges of the gully. Also entry points have been provided in the design to allow access to work areas. This was discussed with the community and owners provided suitable locations for these. Although there are some assets within these setbacks which are mostly farm crops and economic trees, the proposed rehabilitation will be managed to avoid or at least reduce interference with any of the structures such as concrete fence or buildings. 48 4.3 Positive Impacts of the project The Enugwu-Ukwu Gully Erosion Rehabilitation project will have a lot of beneficial impacts on the community. This include but not limited to termination/control of the gully erosions, reduced loss of infrastructure (e.g. houses), reduced loss of agricultural land and productivity from soil loss caused by surface erosion, provision of good drainage, improved sanitation. The project will also progressively restore vegetative cover, improve environmental conditions and more humid local microclimates resulting in increased vegetation cover for wildlife and carbon sequestration thereby improving the environment through land stabilization measures which preserve the landscape and biodiversity. In spite of these significant positive impacts, there are concerns for negative socio-economic impacts to the PAPs and communities because project activities will cause loss of assets, loss of income, physical displacement, restriction to access to source of livelihood, involuntary displacement/relocation and impact on cultural heritage. 4.4 Negative Impact of the Project Assets shall be displaced by the proposed intervention work. Depending on the amount of land space needed for the work at the given locations along the corridor between 5-10m, the potential assets that could be affected have been identified and an inventory of the assets as well as the PAPs taken and are summarized. 4.5 Discussion of project Impacts The affected assets include economic trees and farmlands, essentially. However some structures may also be affected in the cause of the civil works. These have been identified as shown below; Loss of Land: There will be Loss of land as a result of the project. This affects only 2 (two) PAPs. One of the land (Owned by an individual) was housing a shrine and its accessory structures as well as cash crops belonging to the same owner. The second is a family burial site located along the buffer zone near the Main Gully. Loss of Buildings or Structure: Due to rapid activity of the gullies, some area of land has been taken by the erosion thereby encroaching into kiosks, extension of fences and pavements on the gully corridor. There may be significant adverse economic impacts on PAPs in such conditions. This group of persons might lose part of their structures and possibly income earned from them. About 76 (PAPs) were identified in overall. This comprise of Individual, Community and Family owned crops/structures. Loss of other Means of Livelihood (Shops/Kiosks): It was observed that one (1) person who owns a shop within the project area near the Eke Market culvert might lose her major source of livelihood as this structure may be removed during the civil works. This category of PAPs will be allowed to remove materials from the structures for reuse and cash assistance given. Loss of Economic Trees: The gully erosion cuts across the major farm lands and fallow areas of the project communities. Farming activities have been suspended in some of these areas due to the 49 emergence of the erosion. Palm trees are the dominant trees in this area with most of them within the 10 meters setback on both sides of the gully edge. Other trees include bread fruit, oil bean, oha tree, nturukpa tree, soft wood, cocoa nut, kola nut, Udara, Avocado pear, local pear, Bamboo, ugiri, etc. Types and quantity of these economic trees as well as the owners are outlined in the appendix. Loss of Agricultural Resources (Crops): The major crop affected within the area is mainly Cassava. Other crops identified include yam, spinach, pumpkin etc. Impact on Utilities: There are no major public utilities identified within the setback along the Gully corridor that could be affected in the course of work or that will constitute hindrance to project activities. Loss of access to common (community) property: Though the project transvers through community land, no community owned assets were impacted. Loss of Cultural Property: 2 shrines (Place of worship) were identified along the corridor namely ‘Ezenwanyi’, (care of Mrs Patricia Nwana) and ‘Obu mmuo umuajana’ (care of Chief Anthony Okeke) which the worshippers/priests owned up to. It is worthy of note, at this point, that the World Bank OP 4.11 is triggered. These may be impacted and compensation was discussed and analysed with the PAPs. The OP 4.11 provides for physical cultural resources management plan that measures to avoid or mitigate any adverse impacts on physical cultural resources management of chance finds, any necessary measures for strengthening institutional capacity for the management of physical cultural resources a monitoring system to track the progress of these activities. This will be addressed by the ESMP prepared for this project. Continuous consultation with traditional authorities and local communities will be employed as part of mitigation. Impact on Vulnerable Group: People who by their disadvantage conditions will be economically worse impacted by project activities than others such as female headed households, persons with disability, persons with HIV-AIDS and elderly household heads of above 60 years with dependents were considered vulnerable. Those within this group and may be impacted are Twenty two (22) which included eighteen (18) widows and four (4) elderly poor persons (above 60) with dependents. Potential Relocation Areas: Two (2) buildings were identified to be directly affected during the implementation of this project based on the established setback and design suggestions. One of the affected persons (Mrs Patricia Nwana) requested for land for land replacement and also cash assistance to conduct the traditional rights for relocation of the shrine (Ezenwanyi) that is domiciled in the zinc building. The request for land is due to the fact that it was the only land owned by the PAP. The second affected person (Mrs Josephine Nwana) requested for cash assistance as form of compensation. 50 4.6 Inventory of affected assets/structures in the project area About 76 Assets/structures will be negatively impacted due to the sub-project activities. Some of the PAPs have one or more of their assets/structures affected. These include fences, buildings, and agricultural products. (See Annex 1 for Complete Inventory and Census Registration of PAPs) 4.7 Census of Project Affected Persons (PAPs) Census of PAPs was carried out based on the methodology described in Chapter 1. The outcome shows that 76 persons will be potentially impacted/suffer socio-economic losses as a result of sub-project activities. The census register for the ARAP describes the names of PAPs, means of identification/contact and affected items. (Annex 1). 4.8 Analysis of Impacts and Income Restoration Measures for Vulnerable Group/PAPs Twenty two (22) vulnerable persons were enumerated during the ARAP census consist of widows (18 Nos) and the elderly poor persons (above 60) with dependents (4 Nos). There was no identified vulnerable PAP in the category of HIV-AIDS persons and child headed households. No mentally disabled persons were identified as part of the PAPs. The objective of income restoration measures for the vulnerable persons is to ensure that they are reasonably assisted to overcome potential economic shock from the project, and maintain the quality of life not less than their pre-project state because; they are at higher risk than others based on their vulnerability disadvantage. The kind/cash assistance for vulnerable group and PAPs in general shall be administered by the proponent through the resettlement committee or through NGOs in consultation with the PAPs. To ensure that income restoration measures are effective all the articulated resettlement measures will be carried out prior to the project implementation. The income restoration plan (skill acquisition, assistance) to vulnerable PAPs shall be funded through the amount to be set aside for administration within the resettlement budget. This fund will be set aside by the SMEnv through its counterpart responsibility to project’s due diligence and shall preferably be operated/administered by the resettlement committee to be appointed and supervised by the SPMU during ARAP implementation. 4.9 Performance Indicator for Assessing Income Restoration Performance indicators and monitoring are important in evaluating the progress and effectiveness of the resettlement plan as well as the income restoration measures. It is the responsibility of the monitoring and evaluation officer and/or the Safeguard Officer at the PMU to design a schedule and budget for monitoring the implementation of the ARAP which will begin before project implementation and continue through the life cycle of the project. The monitoring indicators, which provide the basics for requirement of ARAP income restoration progress is discussed in details in Chapter eleven and in annex 2. 51 Positive results or improvement over the baseline conditions will be indicative of track record consistent with the objective of resettlement plan while performances below the baseline conditions indicate failure of the resettlement plan from meeting the desired objectives. In this case, the safeguard officer/monitoring officer is expected to report to the SPMU early and offer ways for improvement/modification of the restoration measures. For successful implementation of the resettlement plan, PAPs must be given prior orientation, perhaps during the training and enlightenment workshop and must be informed that there will be periodic monitoring of their activities. 4.10 The Valuation methodology Valuation of assets to be affected by the implementation of the project was conducted using a general principle adopted in the formulation of the compensation valuation, which follows the World Bank policy that lost income and asset will be valued at their full replacement cost such that the PAPs should experience no net loss. The asset valuation was conducted based on the current market prices in the project area. For some materials, prices vary on the basis of quality, taste and product brand. Therefore, in such cases the average market price plus 2% price flexibility adjustment was used for the valuation. Below is the outcome of the market survey carried out in April 2016 in Enugwu-Ukwu, Anambra State Nigeria. Table 3 Market Survey from Enugwu-Ukwu Category Materials Unit Amount (Naira) Structures (Building, balcony, Wooden Windows 1 No N 2500 Fence, Wall, Pavement) Cement 1 bag N 2000 Wooden Doors 1 No N 5000 Corrugated iron sheet 1 m2 N 2000 Zinc 1 Bundle N 10000 Block (6�) 1 m2 N 120 Block (9�) 1 m2 N 150 Wood/plank 1 piece N 400 Iron rod 1 piece N 1450 Truck Hire within the city N 10,000 Labour cost: Mason, Carpenter, etc 1 artisan Per N 3,500/ N 2,000 day 52 Consumer prices in Nigeria increased 12.8 percent year-on-year in March of 2016, following an 11.4 percent jump in the previous month. It was the highest figure since July 2012, mainly boosted by food prices. On a monthly basis, consumer prices went up 2.2 percent, slowing from a 1.8 percent rise in February to a peg at 15.6% in May (Figure 21). Based on prevailing macroeconomic variables in Nigeria which is demonstrated by an unstable exchange rate between N200 and N400 to the Dollar in the last 12 months and the inflation situation described above, it can be predicted that the exchange rate used in this valuation and the 2% inflation correction item (pegging inflation at not more than 12%) assumption will be realistic over the next 12 to 15 months considering the government’s effort in stabilizing the economy. Average Inflation rate 16 14 13.9 12 12.1 10.8 11.3 10 9.1 9.01 Rate 8 8.05 6 4 2 0 2010 2011 2012 2013 2014 2015 2016 Year Figure 22 Average yearly inflation rate (CBN, 2016) 53 Figure 23 Average monthly inflation rate (NBS, 2016) The method of valuations has been communicated to and dialogued with the PAPs during consultations as presented in the section below. 4.10.1 Valuation Method for Land Property In line with OP4.12 of the World Bank on involuntary resettlement as stated in the entitlement matrix, land for land entitlement is prescribed. In so doing, it is also important to take into cognizance the size of the land and location since these two variables are determinants of value of land property. 4.10.2 Replacement Cost Method for Assets/Structures The Traditional Replacement Cost Method, was used in estimating the value of the property/structure and is based on the assumption that the capital value of an existing development can be equated to the cost of reinstating the development on the same plot at the current labour, material and other incidental costs. The estimated value represents the cost of the property as if new. The Damage Loss Assessment Method is used in this study to determine compensation for economic trees and agricultural products. This method states that market value of yield per tree for the current season (agricultural season) and cost of re-planting and nursery should be used to determine the compensation rate for the economic tree. 4.10.3 Disturbance and Other Incidental Contingencies Affected business premises which will have to close shop or be relocated will be given compensation for loss of business time/income and cash or in kind assistance to enable the relocation of affected property. Only one (1) PAP was identified as eligible for this due to relocation of his shop. This has been factored into the full compensation and details are shown in Annex 3 PAPs will be allowed to dismantle their structures and reuse them at relocated locations. In addition, SPMU will provide supplementary assistance to affected PAPs. Rates of cost of labour and 54 transportation allowances have also been built in where applicable. The current rates in the market have been used. 4.10.4 PAPs Losing Permanent Structures-for Residential (immoveable structures) Structures and other assets including fences, walls and pavements on the ROW of project corridor are categorized as immoveable/permanent structures. Contractors are advised to try and avoid demolition if possible. Where demolition of these structures cannot be avoided, census of PAPs has been taken for resettlement/compensation. PAPs under this category will be resettled or compensated for the value of the structure to be displaced based on the prevailing market value of the structure in Enugwu-Ukwu. Demolition/clearing of structures to secure the ROW will take place at least two (2) weeks to the period of implementation after PAPs would have been compensated. 4.10.5 PAPs Losing Permanent Structures-for Business (immoveable structures) PAPs covered in this category will be resettled or compensated for the value of the structure to be displaced based on the prevailing market value of the structure in Enugwu-Ukwu. In addition, PAPs will be compensated for loss of livelihood income due to loss of business income. Only One (1) PAP was identified in this category. For PAPs relocating to alternative sites, they shall be provided with in kind/cash assistance. Demolition/clearing of structures to secure the ROW will take place at least two (2) weeks to the period of implementation after PAPs would have been compensated. 4.10.6 PAPs Losing Shrines or Place of Worship PAPs covered in this category will be resettled or compensated for the value of the structure to be displaced based on the prevailing market value of the structure in Enugwu-Ukwu. In addition, PAPs will be compensated for loss of livelihood income due to loss of business income. For PAPs relocating to alternative sites, they shall be provided with in kind/cash assistance. Two (2) PAPs were identified in this category. Demolition/clearing of structures to secure the ROW will take place at least two (2) weeks to the period of implementation after PAPs would have been compensated. 4.10.7 PAPs Losing Burial Site PAPs covered in this category will be resettled or compensated for the value of the structure to be displaced based on the prevailing market value of the structure in Enugwu-Ukwu. In addition, PAPs will be compensated for loss of livelihood income due to loss of business income. For PAPs relocating to alternative sites, they shall be provided with in kind/cash assistance. One (1) Family Burial Site belonging to Iwotor Family was identified in this category. This has been documented in the annex. Demolition/clearing of structures to secure the ROW will take place at least two (2) weeks to the period of implementation after PAPs would have been compensated. 4.11 Proof of Eligibility The resettlement committee will consider the presentation of eligibility certificate (Identification Card) as a means of identifying eligible PAPs for entitlements. In case of lose or misplacement, other forms of evidence as proof of eligibility will also be acceptable but limited to one or more of the following: • Identification based on phone number and name and passport photograph supplied during the census stage 55 • PAPs with no phone numbers will be identified by their Township or community leader so long as the name being used for claim is one recognized in the census register. 4.12 Duration for Civil Works Estimation of the duration for civil works/rehabilitation completion is six (6) months. PAPs will not be disrupted in anyway by the project until resettlement program is implemented. 4.13 Cut-Off Date The cut-off date for being eligible for compensation and/ or resettlement assistance is May 16th 2016 which is the day the final field consultation with the PAPs was conducted. PAPs and project community were duly informed about the significance of the cut-off date in the implementation of this ARAP through the Local authorities. 4.14 Entitlement Matrix for the PAPs The matrix shows specific and applicable categories of PAPs under this project and types of losses as well as entitlement plan for PAPs. The Entitlement matrix therefore, is the basis for compensation budget, resettlement and income restoration measures to be administered by the proponent. The subsequent section further provides explanation of the entitlement matrix under eligibility criteria for entitlements. Table 4 Entitlement Matrix Table for PAPs Type of Loss Entitled Person Description of Entitlement 1. Permanent loss of land 1.1 (a)Legal owners of 1.1 (a) Land for land compensation is land preferred priority, or Cash compensation at 1.1 Cultivable/residential replacement value based on market rate plus (b)Occupancy/Hereditar /commercial land 10% compulsory acquisition surcharge as y second option (c)Tenant (b) & (c) Compensation will be paid as plus a one- time lump sum grant for restoration of livelihood and assistance for relocation. . 2. Damage to land (such as 2.1. (a)Legal owner/s 2. 1 (a) & (b) Restoration of land to pre- abutting sub-project site) construction condition or cash compensation (b) Village/s or clan/s at prevailing rates for necessary bulldozer/ 2.1. By excavation etc. from with customary tractor hours to restoring level and/or borrows for earth for ownership truckloads of earth for fill construction. 2.2. (a)Legal owner/s 2.2 Provision of water course to connect 2.2 By severance of (b) Village/s or clan/s severed segment with source of water agricultural holding with customary 56 Type of Loss Entitled Person Description of Entitlement ownership 3. Loss of income and 3.1.Cultivator occupying 3.1. Estimated net income for each lost livelihood land cropping season, based on land record averages of crops and area planted in the 3.1. Temporary loss of previous four years access to land for cultivation 3.2. Loss of agricultural 3.2. (a) Owner/s of crops 3.2. (a) Cash compensation for loss of crops, and fruit and wood or trees. Includes crops agricultural crops at current market value of trees. trees owned by mature crops, based on average production. encroachers/squatters 3.3 Loss of income by Compensation for loss of fruit trees for agricultural tenants because (b) /tenant average fruit production years to be of loss of land they were computed at current market value. 3.3 Persons working on cultivating the affected lands Compensation for loss of wood-trees at current market value of wood (timber or firewood, as the case may be). 3.2. (b) Partial compensation to tenants for loss of their crops/trees as per due share or agreement (verbal or written) 3.3 One-time lump sum grant to agricultural tenants (permanent, short-term or long- term agricultural labor (this will be in addition to their shares in crop/tree compensation) a) Tree/perennial crops: Harvesting of the crops will be given a first priority but where harvesting is not possible, counting of the affected crops will be done in the presence of the owner. Computation of the costs will be done according to market rates b) Annual crops: Crops will be harvested by the owner and therefore no compensation will be paid for crops. Where crops cannot be harvested, compensation at the market rate will be paid 4. Permanent loss of 4.1. (a)Owners of the 4.1. (a) Cash compensation for loss of built- structures whether or 57 Type of Loss Entitled Person Description of Entitlement Structures not the land on which up structures at full replacement costs the structure stands is 4.1 Residential and Owners of affected structures will be allowed legally occupied commercial structures to take/reuse their salvageable materials for rebuilding/rehabilitation of structure. (b) Renters In case of relocation, transfer allowance to cover cost of Shifting (transport plus loading/unloading) the effects and materials will be paid on actual cost basis or on current market rates. (b) One-time cash assistance equivalent to 4 months’ rent moving to alternate premise. Transfer allowance to cover cost of shifting (transport plus loading/unloading) personal effects paid on actual cost basis or on current market rates. 4.2. Cultural, Religious, and 4.2. 4.2. Complete rehabilitation/restoration by community structures the Project; or, Cash compensation for Community /facilities School, church, restoring affected cultural/community water channels, pathways, structures and installations, to the and other community recognized patron/custodian. structures/installations 5. Special provision for 5.1 Women headed 5. Needs based special assistance to be vulnerable PAPs households, disabled or provided either in cash or in kind. elderly persons and the 5.1.Restablishing and/or landless enhancing livelihood 5.2 Change in Livelihood for 5.2. (a) Vulnerable 5.2 (a) &(b).Restoration of livelihood women and other PAPs, particularly (vocational training) and subsistence vulnerable PAPs that need Women enrolled in a allowance at agreed rate per day for a total of to substitute their income vocational training 6 months while enrolled in a vocational because of adverse impact facility training facility 5.2. (b) owner/s whose landholding has been reduced to less than 5 acres Unanticipated adverse The Project team will deal with any unanticipated consequences of the 58 Type of Loss Entitled Person Description of Entitlement impact due to project Project during and after project implementation in the light and spirit of intervention or associated the principle of the entitlement matrix. activity 4.15 Description of Eligibility Criteria for Defining Various Categories of PAPs Based on the World Bank’s OP4.12, the following three criteria are recognized: a) Those who have formal rights to land (including customary, traditional and religious rights recognized under the Federal and/or State Laws of Nigeria). b) Those who do not have formal legal rights to land at the time of the census begins but have a claim to such land or assets provided that such claims are recognized through a process identified in this resettlement plan c) Those who have no recognizable legal right or claim to the land they are occupying, using or getting their livelihood. Those covered under (a) and (b) above according to the guiding policy are to be provided compensation for the land they lose, and other assistances in accordance with the policy. PAPs covered under (c) above are to be provided resettlement assistance in lieu of compensation for the land they occupy and other assistance, as necessary to achieve the objective of them not being economically worse off because of the development. Under The World Bank Policy, cash compensation is only appropriate when there is an active market in land or housing and where such assets are actually available for purchase. Communal rights to land and other assets are recognized. Clans, lineages and other community property have been subjected to the same procedures as for privately held land. In such case, the traditional law of the affected community may be taken into account. Although all PAPs irrespective of their legal rights or not, squatters or otherwise encroaching on land are eligible for some kind of assistance under the policies of the WB, such PAPs must be those captured in the census. In other words, persons that encroach on land/ROW after the cut-off date will not be entitled to any form of assistance or compensation. 59 5 CHAPTER FIVE GRIEVANCE REDRESS MECHANISMS 5.1 Introduction The likelihood of dispute is much reduced because the few affected persons due to the erosion control project have been greatly consulted. Nevertheless, in the event that grievances arise this redress mechanism has been prepared. Already, the affected persons have been helped to appreciate that there are provisions for addressing any complaints or grievances. The grievance procedure will further be made available to the affected person through project implementation. The major grievances that might require mitigation include:  PAPs not listed;  Losses not identified correctly;  Inadequate assistance;  Dispute about ownership;  Delay in disbursement of assistance and improper distribution of assistance. 5.2 Grievances and Appeals Procedure This grievance procedure is prepared in line with the provision of the RPF of NEWMAP. The need to provide a forum locally to receive, hear and resolve disputes is in the best interest of all parties to forestall the lengthy process of litigation, which could affect the progress of project. Therefore, the setting of grievance redress committee early during RAP implementation is desirable. 5.3 Grievance Redress Process There is no ideal model or one-size-fits-all approach to grievance resolution. The best solutions to conflicts are generally achieved through localized mechanisms that take account of the specific issues, cultural context, local customs, and project conditions and scale. In its simplest form, grievance mechanisms can be broken down into the following primary components: • Receiving and registering a complaint. • Screening and assessing the complaint. • Formulating a response. 60 • Selecting a resolution approach. • Implementing the approach. • Announcing the result. • Tracking and evaluating the results. • Learning from the experience and communicate back to all parties involved. • Preparing a timely report to management on the nature and resolution of grievances. 5.3.1 Procedure for Effective Local Resolution of Grievance The following steps and procedures will apply in this project to ensure that grievances are settled within PMU and /or at the level of the Grievance Redress Committee as much as possible:  An accessible and affordable complaints mechanism will be in place as soon as RAP report is disclosed, and will enable people with claims against the process to make their complaints  At the first stage, PAPs will register their complaints and grievances to the Safeguard Officer in PIU (contact address to be provided to PAPs).The Safeguard Officer is required to in consultation with the Project Coordinator provide a written response to the PAP within fourteen (14) calendar days of receiving the complaint.  If the PAP is not satisfied with the decision of the PIU, the PAP should present the case to the independent Grievance Redress Committee (GRC). The GRC upon receiving the complaint should write to acknowledge the receipt within one week.  A record should be kept for hearing concerning the complaint, as well as of the reasons for filing the complaint  The matter so complained should be verified with the PIU  Mediation efforts at the discretion of the GRC should be embarked upon within three weeks of receiving the complaint Where a matter is not satisfactorily resolved at this level, the GRC should assist PAPs to seek redress through the court of justice. 5.3.2 Court Resolution of Grievance Matters The possibility of seeking for grievance resolution in the court may be a last resort and should be expected, especially, where the complainant felt dissatisfied with resolution of the GRC. The provision of the RPF of NEWMAP on this matter is that grievances concerning non-fulfilment of contracts, levels of compensation, or seizure of assets without compensation shall be addressed to the state local courts system of administration of justice. The court hierarchy would in ascending order therefore, be land dispute tribunals/chiefs, followed by magistrate courts and then finally the high courts. The high court of the state is being designated as the highest appellate court to settle grievances. This, admittedly, is a costly and time-consuming procedure. Nevertheless, affected persons will be exempted from administrative and legal fees incurred pursuant to this grievance redress procedure. 61 5.4 Grievance Redress Committee The project will establish a Grievance Redress Committee (GRC). The GRC will hear complaints and facilitate solutions; and the process, as a whole, will promote dispute settlement through mediation to reduce litigation. This committee will be coordinated by a local NGO and shall be made up of the following parties:  NGOs  Community Development Councils (CDCs)  Representative of the community  Representatives of associations/interest groups and,  PAPs representative It is expected that an independent body such as NGO should head the Grievance Redress Committee (GRC) so as to give the committee credibility and trust of protecting the interest of PAPs. SMEnv, NEWMAP or its staff would not be heading the committee since it is a party to the anticipated grievance cases. The NGO to be chosen must have experience in dispute resolution and must have a lawyer in its team that will serve as the secretary of the body. The PMU will provide the GRC with the guideline based on the provisions of this ARAP and also make available to it contact details/register of PAPs which details their names, addresses and phone numbers for contacting them when necessary. PAPs shall also have the option of contacting the GRC directly or indirectly to register their grievance by themselves or through their local chief or leader There will be no fees or charges required of those wishing to have a grievance or complaint heard. The timeline for implementation of the grievance resolutions shall be at most 15 days from the last day allowable for grievance and complaints submission following the end of RAP disclosure. The functions of the Grievance Redress Committee include:  Provide support to PAPs on problems arising from loss of private properties and business area.  Record the grievance of the PAPs, categorize and prioritize the grievances that need to be resolved by the committee; and  Report to the aggrieved parties about the developments regarding their grievances and the decision of the project authorities The committee will suggest corrective measures at the field level itself and fix responsibilities for implementation of its decisions. In terms of implementation, all efforts will be made to first resolve the issue faced by PAPs at the field level. The grievance procedure should be simple, administered as far as possible at the local and state levels to facilitate access, flexible and open to various proofs taking into consideration the fact that many people are illiterate requiring a speedy, just and fair resolution of their grievances. However, when matters could not be resolved at this level, there is need for the grieved to seek redress in the court 62 5.5 Expectation When Grievances Arise When local people present a grievance, they expect to be heard and taken seriously. Therefore, the SPMU and others such as the engineers involved in one aspect of the project or other must convince people that they can voice grievances and work to resolve them without retaliation. It should be understood that all or any of the following is or are expected from the project management/channel of grievance resolution by the local people: • acknowledgement of their problem, • an honest response to questions/issues brought forward, • an apology, adequate compensation, • modification of the conduct that caused the grievance and some other fair remedies 5.6 Management of Reported Grievances a) The procedure for managing grievances should be as follows: b) The affected person file his/ her grievance, relating to any issue associated with the resettlement process or compensation, in writing or phone to the project Resettlement and Compensation committee (Phone numbers will be provided by the SPMU). Where it is written, the grievance note should be signed and dated by the aggrieved person. And where it is phone, the receiver should document every details. c) A selected member of the Site Committee will act as the Project Liaison Officer who will be the direct liaison with PAPs in collaboration with an independent agency/SFNGO person ensure to objectivity in the grievance process. d) Where the affected person is unable to write, the local Project Liaison Officer will write the note on the aggrieved person’s behalf. e) Any informal grievances will also be documented 63 5.7 Grievance Log and Response Time The process of grievance redress will start with registration of the grievance/s to be addressed, for reference purposes and to enable progress updates of the cases. Thus the person affected by the project will file a Grievance Form with the Grievance Redress Committee. The Form (See table 5) should contain a record of the person responsible for an individual complaint, and records dates for the date the complaint was reported; date the Grievance Log was uploaded onto the project database; date information on proposed corrective action sent to complainant (if appropriate), the date the complaint was closed out and the date response was sent to complainant. The Project Liaison officer working with the local Government Desk Officer in recording all grievances will ensure that each complaint has an individual reference number, and is appropriately tracked and recorded actions are completed. The response time will depend on the issue to be addressed but it should be addressed with efficiency. The Grievance committee will act on it within 10 working days of receipt of grievances. If no amicable solution is reached, or the affected person does not receive a response within 15 working days, the affected person can appeal to a designated office in the SPMU, which should act on the grievance within 15 working days of its filing. Table 5 A typical Reporting format for Grievance Redress Community Type of Grievance Grievance Resolution project & Name awarded are not Case referred to of Complainant not paid before Compensation Compensation about impacts Date received Resettlement not informed Affected, but and options inadequate acquisition awarded is complaint the Court provided Pending benefits Date of assets other Community Project 1 Complainant A Complainant B Complainant C Community Project 2 Complainant D 64 Complainant E TOTAL 5.8 Monitoring Complaints The Project Liaison Officer will be responsible for:  providing the grievance Committee with a weekly report detailing the number and status of complaints  any outstanding issues to be addressed  monthly reports, including analysis of the type of complaints, levels of complaints, actions to reduce complaints and initiator of such action. 5.9 World Bank Group (WBG) Grievance Redress Service The Grievance Redress Service (GRS) ensures that complaints are being promptly reviewed and addressed by the responsible units in the World Bank. The objective is to make the Bank more accessible for project affected communities and to help ensure faster and better resolution of project-related complaints. The GRS accepts complaints that are:  Related to an active World Bank-supported project (IBRD or IDA)  Filed by a person or community who believes they have been or may be adversely affected by a World Bank-Financed project  Filed by a bidder or potential bidder about the procurement process on a World Bank-financed contract. These complaints will be processed in line with Bank Procedure (BP) 11.00 (Annex D) and will not follow the GRS procedures. The identity of the complainant will be kept confidential if requested, but anonymous complaints will not be accepted. How to file a complaint?  Complaints must be in writing and addressed to the World Bank Grievance Redress Service (GRS).  Complaints will be accepted by email, fax, letter, and by hand delivery to the GRS at the World Bank Headquarters in Washington or World Bank Country Offices Program affected community/ individuals may also submit their complaint to the WBG‘s independent Inspection Panel which determines whether harm occurred, or could occur, as a result of WBG non- compliance with its policies and procedures. Complaints may be submitted at any time after concerns have been brought directly to the WBG‘s attention, and WBG Management has been given an opportunity to respond. 65 6 CHAPTER SIX STAKEHOLDERS’/FOCUS GROUP ENGAGEMENT 6.1 Introduction Public consultation and participation are essential because they afford PAPs the opportunity to contribute to both the design and implementation of the project activities and reduce the likelihood for conflicts. The consultation process will ensure that all those identified as stakeholders are consulted. Information about the project was shared with the stakeholders, to enable meaningful contribution, and enhance the success of the project The public consultation strategy for the ARAP activities evolved around the provision of a full opportunity for involvement for all stakeholders, especially the PAPs. Concerns raised by the stakeholders are documented and incorporated in this report and used to develop mitigation and/or enhancement measures for the GRM. The stakeholders were informed of the visits through the existing communication line between the SPMU and the communities. The Community leaders through the use of town criers, church announcements and phone calls, informed the rest of the community of the proposed meetings. The identified groups includes:  Anambra State NEWMAP SPMU  Traditional Leader of Enugwu-Ukwu  Title holders (Chiefs, Nze and Ozos) Elders  President General of Urunnebo Community  Youth group Executives of Urunnebo and Avomimi  Women group Executives of Urunnebo and Avomimi  Town Union Executives of the communities  Project Affected Persons  People living or owning assets along the corridors of the gullies 66 6.2 Advocacy Visit The advocacy visit meeting was held on 3rd May 2016 at the palace of His Royal Highness Igwe Raphael Ikpa (Igwe Enugwu-Ukwu na Umunri) who is the apex authority of the community. A second Advocacy visit was held on the same day at the Obu ozom hall with the Association Executives, Youth executives and women group executives. The advocacy visit was held to introduce the ESMP and ARAP sub-projects to the stakeholders and seek their consent and opinion on the exercise. The visit was also scheduled to gain a better understanding of the project environment, social structure and existing livelihood activities of the area. This meeting was also scheduled to allow the authorities select a suitable date for a larger stakeholder’s consultation including venue and time for the town hall meeting. This will give the community well enough time to disseminate the information to all relevant stakeholders. The Traditional Ruler, HRH Igwe Raphael Ikpa expressed happiness over the visit and assured the consultant and the SPMU that the community will give them the needed support to ensure a successful study. He further buttressed the need for the project to be commenced on time so as to arrest the erosion menace. CONCERNS 1. How can the people be informed about the project as it is important for the community to be aware of the project? Ans: A Focal NGO has been engaged to create awareness and community sensitization. 2. How feasible and soon is the rehabilitation work as the community have witnessed many politicians that came with similar promises and are yet to commence work? Ans: The NEWMAP project undergoes stage by stage implementation so as to satisfy the World Bank safeguards policies. The ESMP and ARAP are critical part of the process that needs to be completed before civil work. Hospitalia Consultaire is already on ground to start the study. This is the stage preceding commencement of the actual work. So the people should be rest assured that the work will soon commence. 3. Does the scope of work cover all the erosion site in Enugu-Ukwu and have they all been identified? Ans: Before now, AN-NEWMAP PMU engaged an Engineering consultant to conduct feasibility studies. The Erosion sites have been identified however, the scope covers the ones selected and approved by the Bank. More work is still on going to identify other sites and hopeful approval by the Bank. Figure 25 Igwe Enugwu Ukwu and Cabinet 67 Figure 26 Consultant and SPMU Teams during during Advocacy meeting the Advocacy visit Figure 27 Dr Obi Anyadiegwu addressing the Figure 28 The Livelihood Officer during the Igwe Advocacy visit with the Stakeholders The traditional Prime Minister (Onowo) assured the stakeholders that the community will play her part for effective project implementation. HRH expressed worries over the watershed problems ravaging across the communities and pleaded that the work should cover all the erosion sites within the community. The consultant requested the community to come out enmass during the public consultation so as to express their concerns and ideas. He also stated that the Project Affected Persons (PAPs) should be on ground during census exercise to enable the consultant carry out an effective study. 6.3 Town Hall Meetings The meeting was carried out in two (2) stages. The first was a general meeting where all the stakeholders and community members were given a general overview of the project, the component and information regarding the ESMP and ARAP especially the census/inventory and other relevant information in the RPF and TOR . The second stage meeting involved the consultant and the PAPs after the census exercise. The meeting provided feedbacks, clarifications and responses. During the visits, the consultant and NEWMAP representatives further explained to the stakeholders that the proposed development would involve construction which may impact on the livelihood of people living along the project areas. However, plan has been set up to ameliorate the envisaged environmental and social risks. The consultant explained that the World Bank OP 4.12 is a safeguard instruments or document that will address the envisaged impact and also provide a guidelines for the compensation and grievance redress. They further specified the need for the community to have a buy- in of the project as it will be their duty to sustain the intervention. 68 6.3.1 The General Town Hall Meeting This meeting was held on the 3rd of May, 2016 at the Obu Ozom hall. The essence was to enable interested and affected parties to air their concerns (views and opinions on the proposed development) which might have been overlooked during the scoping exercise. It also gave room for more enlightenment on the need for the people’s collective effort in protecting the environment, A synopsis of the views of the project affected people as well as representatives of groups (Men, Women and Youth) in the communities through which the project traverses were incorporated in modalities on carrying out the ARAP exercise. Figure 29 A Stakeholder expressing Concern Figure 30 A Cross-section of the Women Group during the Town hall meeting at the Town Hall meeting The meeting commenced at 10:15am at the Obu Ozom hall. The Traditional prime minister blessed and presented the kola-nut welcoming the team of Consultant and SPMU. He on behalf of the community expressed joy that the World Bank and the Government have remembered the plight of the people due to the erosion problem and exude confidence on the community’s readiness to comply with consultants engaged to execute the different components of the project. ANS-NEWMAP Communications Officer explained the synergy between the World Bank and federal government of Nigeria and rationale for the NEWMAP establishment. He stated that the NEWMAP is saddled with responsibility of providing mitigation measures to areas vulnerable to erosion and watershed challenges. He stated that the consultant is employed by NEWMAP to satisfy World Bank safeguard requirement, which will enable it to implement the project without hitches. He stated that the Enugwu-Ukwu Gully site have gotten approval from the World Bank but maintained that the ESMP and ARAP remain a vital instrument before project implementation. He stressed that agreement among the stakeholder is a critical measure for a successful project implementation. He also said that the main aim is for the consultant to carry out census and valuation exercise for the PAP’s property. He therefore explored the stakeholders to work in harmony with the consultant so as to avoid crisis during/after project implementation. The livelihood officer explained the need for the Women to be carried along in the different phases of the project. She also listed out the livelihood services that would be considered during the ARAP 69 implementation process and pleaded with the community to be truthful in their claims as crisis resulting from false claims may slow down the project. The Consultant in his statement, explained the World Bank safeguard policies, emphasising on O.P 4.01 and O.P 4.12. He stressed the importance of stakeholder engagement while challenging the stakeholders to take ownership of the project. He also said that the stakeholders will help in project security and monitoring. He further explained the importance of project design and the setback identified by the Engineering consultant. He then called on the PAPs to identify their affected property through evidence or witness for proper documentation. The modalities involved in the survey, census and inventory activities was also discussed as well as the cut- off date that will be announced in due cause and its importance. He concluded by stating the importance of constituting a site committee and the need for the community commitment towards the sustenance of the project as well as security of equipment and project monitoring to enable effective project implementation. The Focal NGO consultant, buttressed further on the rationale for the site committee and modalities involved. He further moved on to assist the community in constituting the site committee and also the community association committee for the community. He also stated that the project monitoring consultant will work in line with these committees. Concerns Raised by stakeholders a) If the client has engaged contractor? If yes, is it a local or foreign contractor firm? Response: The stakeholders were made to understand that there is a selection process for the contractor which will follow the World Bank guidelines, however, the contractor may choose to work with some of the community members as the bank encourage the use of community members during the civil works to improve their livelihoods. b) How soon will the work commence as most of the affected people are afraid to sleep for fear of their houses falling into the gully during the next rain. Response: As soon as the ESMP and ARAP documents are concluded, the next stage will be to advertise for the contractor that will perform the civil works after which work will start. However, the community should keep up with the palliative measures that they have been employing pending when the main work will commence. c) Is the cooperative association to be formed for all interested members of the community Response: The Association is mainly for the Project Affected Persons as part of Livelihood restoration program. d) The women leader asked if there is any special provision for the women in the project. Response: The Women will be fully involved in all the associations stated as the bank is highly gender sensitive. 70 Closing Remarks: The Communications Officer implored the stakeholders to give all the necessary assistance to the consultant so as to achieve the desired objectives. The town hall meeting was brought to an end at 4:07pm after a closing prayer. 6.3.2 Focal Group Meeting This meeting was held with members of the existing erosion site committee constituted by the community to help control the menace. Also part of the meeting were the project affected persons, community youths, hunters and representative of the community union. The purpose for this meeting was for the consultant to get a deeper understanding of the history surrounding the erosion. Also the consultant sought to find out the measures the community have been engaged in to help prevent or reduce the progress of the erosion. As part of the information sought, the consultant was given a history of the community, cultural heritage as well as leadership hierarchy. The consultant were also assigned community members that will assist them in identifying the project affected persons as well as locating the different fingers of the gull. Figure 31 Some of the stakeholders with the Figure 32 Focal Group Consultation at the consultants during the Focal Group community Consultation The women group who were also members of the Urunnebo Improvement Union, were consulted and they expressed their joy on the intervention. However, they expressed concern that the rehabilitation work needs to commence before rains so as to prevent further loose of their farmlands and properties. The consultant explained to them that the document which was Members of the youth wing of the Urunnebo Improvement Union expressed their joy towards the development. They were 6.3.3 Feed Back Meeting A follow up meeting was conducted on 16th of May, 2016. This marked the end of the census and inventory exercise. The key reason of the meeting was for the consultant and PAPs to thoroughly examine the data filled during the field work and complete the unfilled ones. The meeting was also necessitated by the need to ensure that the communities are still in tune with the project. During this meeting, the cut-of date was formally announced to the PAPs as well. 71 The outcome of this follow-up showed that the communities have a good understanding of the project. Passports and other necessary document were collected from the PAPs for the processing of their Identification Cards. The PAPs were delighted and thanked the consultants for the thoroughness in execution of their assignment and promised to be of assistance to ensure the success of the project. Figure 33 A Group of PAPs at the Feedback Figure 34 One of the PAPs During the Feedback session session 7 CHAPTER SEVEN BUDGET AND FINANCING PLAN 7.1 Introduction A detailed inventory of all affected assets provides the basis for estimating the compensation and assistance costs. This Section provides information on the estimated budget for the overall implementation of this RAP and source of funds. 72 7.2 Financing plan SPMU is the source of this fund for the payment of the necessary compensations and mitigation measures and overall implementation of the ARAP. Since the Anambra State Ministry of Environment (SMEnv) are the ones impacting livelihoods, it will be their responsibility to fund the RAP budget. It will be financed through the projects administrative and financial management rules and manuals like any other sub-activity of the project eligible for payment under this project. It is expected that implementation function will rest on the SPMU, but the budget will however be subject to the finalization of disclosure and clearance/approval by the World Bank before disbursement or implementation can commence. The SMEnv being responsible for funding the compensation entitlement, final approval for payments above the limit for the Project Coordinator must be approved by the Chief Accounting Officer of the Ministry (Commissioner). Table 6 Summary of ARAP Budget S/N DESCRIPTION TOTAL 1 ARAP Compensation/Assistance Budget for 76 PAPs (determined) Land N1,780,000.00 Crops and Agricultural Resources N3,856,470.00 Structures and cultural Resources N4,764,600.00 Sub-Total: Compensation N10,401,070.00 2 Capacity Building and Training for ARAP Implementation N4,527,819.00 3 Operating cost including income restoration measures and N1,040,107.00 Monitoring of RAP Implementation (10 % of ARAP compensation Budget) 4 Cost of engagement of consultant/NGOs for compensation N1,500,000.00 payment *TOTAL N17,468,996.00 The total budget for administering/implementing the ARAP for Rehabilitation of Enugwu-Ukwu Gully Erosion project is Seventeen Million, Four Hundred and Sixty-Eight Thousand, Nine Hundred and Ninety-Six Naira, (N17, 468,996.00). This sum is expected to cover compensation of assets affected and additional mitigations for livelihood restoration measures, coordination of additional mitigations, grievance redress and compensation commission. In addition, 10% of this total budget has been provided for Operation cost and contingencies such as inflation that shall be allowed and added to the current budget. 73 7.3 Procedure for Delivering of Entitlements 7.3.1 Engagement of Consultant (NGO) The SMEnv shall engage the services of a Consultant (in this case an NGO) for preparation and management of entitlement to the PAPs. The Consultant will be responsible for facilitating the ARAP compensation process described below. 7.4 ARAP Compensation Process The compensation process will involve several steps in accordance with this resettlement and compensation plan and shall include the following:  Public participation: Public participation with the PAPs which had been part of the process of this RAP would continue even at the RAP implementation phase. Using the entire identified medium, PAPs would be contacted, consulted and made to participate in enlightenment workshop in which alternatives for income restoration and compensation will be discussed and agreed. During this meeting, eligible PAPs without clearance certificate for entitlement will be issued with certificates. This assignment will be facilitated by the Consultant that will oversee the RAP compensation  The Consultant shall identify and work closely with Township liaison, CDCs, etc. within the project area to ensure that PAPs are all contacted/consulted, and necessary dossiers are documented from PAPs  Type of choice (cash and/or in-kind) made by PAPs shall be documented. This shall be done by issuing PAPs with an order form to be completed and signed by PAPs. PAPs who cannot read or write will be assisted to do so  PAPs will specify clearly within the provision in the order form their transfer instruction (for those receiving cash), stating their Bank Account Name, Name of Bank, Account Number and Sort Code.  Non-Bank Account holders shall be assisted to open bank accounts. This is important due to;  Government of Nigeria is moving towards a cashless economy which may pose difficult for PAPs receiving their entitlements.  Operating a bank account will be a plausible option to manage PAPs income restoration program  Carrying cash to the house by PAPs poses a security treat to PAP and may also lead to increase poverty scenario of PAPs  Notification - Dates of various activities for the resettlement program will be communicated to PAPs for inclusive participation. 7.5 Compensation Payment Administration The resettlement budget details prepared in this RAP shall be the guide for the Consultant to be engaged for RAP payment. After the processes elaborated above has been exhausted, the consultant will prepare the payment documentation stating the Name of PAP, address, Phone number, Bank account details and amount entitled. The submission will be made to the Project Coordinator at The PMU. 74 The Project Coordinator will verify the submission by the consultant using the RAP Budget document as a reference. If there are errors, omissions or ambiguities, the attention of the Consultant will be drawn for reconciliation. When fully verified, the payment mandate/report shall be sent to the Commissioner for approval of fund and payment. The Commissioner/chief accounting officer shall approve the payment and minute to the Project Coordinator at the PMU who shall ensure that the payments are carried out by the accountant/finance officer to the various PAPs banks 7.6 Resettlement Implementation Linkage to Civil Works Before any project activity is implemented, PAPs will need to be compensated/resettled in accordance with the entitlement matrix/budget plan established in this RAP. Alternative structures and relocation sites where applicable should have been prepared and witnessed by State Ministry of Environment and the community leaders/CDCs. PAPs that would not need to relocate, especially those that their Fence/balcony/ relaxation outdoors will be impacted must be informed/given the civil work schedule which at least provides a two weeks prior notice to PAPs before actual civil works in the area or site. Resettlement monitoring of income restoration measures shall however be continuous throughout the project cycle together with other project activity implementations. 75 8 CHAPTER EIGHT INSTITUTIONAL ARRANGEMENTS- ROLES AND RESPONSIBILITIES 8.1 Introduction This ARAP recognizes the cross-ministerial and cross-state coordination and collaboration of the many Federal and State Ministries, Departments and Agencies (MDAs) as well as local governments and communities involved in the NEWMAP. This brought about the development of institutional arrangements amongst public agencies with local communities and PAPs with a view to ensuring good project management. The implementation of this ARAP shall require close collaboration among all the stakeholders with a properly constituted structure for administration which shall be agreed by all parties from the onset. The roles and responsibilities of the participating parties in collaborative efforts are well outlined. The major institutions that are involved in this resettlement process are the Anambra State Ministry of Environment, the World Bank, and the Community Resettlement Committee (CRC). 8.2 Institutional Arrangement The roles and responsibilities of the institutions regarding Resettlement Implementation and Grievance redress is summarized below. 8.2.1 The Financier World Bank • Maintains an oversight role to ensure compliance with the safeguards policies, review and provide clearance and approval for the ARAP. • Conduct regular supervision for satisfactory ARAP implementation, fulfilment of community liaison and provide support role throughout the project implementation, and monitor the progress of the project construction. • Recommend additional measures for strengthening the management framework and implementation performance. • In case the WB considers the implementation to be not acceptable and no improvements can be expected, it will require that institutional capacity building measures be taken to strengthen the SPMU 8.2.2 Federal Level Federal Ministry of Environment (FMEnv) • Lead coordinating agency and hosts the Federal Project Management Unit (FPMU). • FPMU 76 Individual MDAs (State and Federal Levels) • Participate deeply in the annual joint work programming process facilitated by the Federal/State PMU. Federal Steering Committee • Direct the FPMU in overall project coordination, alignment of project content and approach, and oversight of activities taking place across participating State. Federal Project Management Unit (FPMU) • Provides an oversight and advisory role in overall project management including resettlement planning and implementation • Establishes and maintains the project management systems • reinforce the State level structures • Supervises through missions 8.2.3 State Level State Steering Committees (SSCs) • Apex decision-making bodies for the operation in the State. State Technical Committees (STCs) • Reviewing and updating the Joint Annual Work Program for State NEWMAP activities (each activity identifies a lead MDA as provided for in the work plan). • Developing inter-sectoral MOUs if needed. State Project Management Unit (SPMU) The SPMU, as the implementing authority, headed by Project Coordinator (PC) & Authorized to take decision on financial matters within the provided budget, has the mandate to: • Develop and implement RAPs and other safeguard instruments. • Drives activities of procurement, capacity building, service-provider mobilization, and monitoring • and coordinating the many participating MDAs at State and Local Government levels. • Study in detail the RAP, and based on the review of the RAP prepare a detailed action plan and time table for the day to day RAP implementation; • Organize the necessary training and capacity building measures for the unit itself and for other partner organizations and committees; • Establish all local level institutions and committees which will participate in the implementation of the RAP and provide them with the necessary training and capacity building measures; • Coordinates and undertake compensation activities in accordance with the principles and procedures specified in the RAP • Implement the income restoration and social development programs and project in accordance with the principles and procedures specified in the RAP; 77 • Ensure the systematic undertaking of monitoring, review and evaluation of the RAP in accordance with the framework and guidelines provided in the RAP and store the data and information collected in a data base; • Based on the findings of the monitoring and review take corrective actions and submit monitoring and review reports to the relevant higher bodies for timely corrective measure. • Facilitate the discussion between PAPs and communities regarding compensation for land acquired for the projects; • Implement the RAP including their involvement to redress complaints and internal monitoring. • Cooperate through a Steering Committee that provides guidance to the technical aspects of all project activities; • Maintain and manage all funds effectively and efficiently for the projects • Organize the necessary orientation and training for SPMU officials so that they can carry out consultations with communities, support communities in carrying out RAPs and implement the payment of compensation and other measures (relocation and rehabilitation entitlement) to PAPs in a timely manner; • Ensure that progress reports are submitted to the World Bank regularly SPMU Livelihood Safeguard Officer • Initiate Resettlement Action Plan (whenever the project involves displacement of homes or businesses) or land acquisition of any kind). • Review and approve Contractor’s Implementation Plan for the social impact measures as per the RAP • Liaise with the Contractors and the SPMU on implementation of the RAP • Coordinate on behalf of SPMU day to day activities with the relevant line departments and oversee the implementation of RAP instrument, prepare compliance reports with statutory requirements, etc. • Monitor and supervise regularly the implementation of RAP • Observe payment of Compensation to PAPs. • Identify and liaise with all relevant Stakeholders pre and post Project implementation. • Sensitization of and Consultations with relevant Stakeholders during and after (where necessary) Project Implementation. • Charged with the responsibility of safeguard requirements and ensuring the sustainability of project. SPMU Engineer • Provide technical support Monitoring & Evaluation Officer/Consultant • Develop the monitoring and evaluation protocol • Conduct monitoring of RAP implementation activities. • Provide early alert to redress any potential problems. • Monitor target achievements and slippages. 78 NEWMAP Technical Officer • Acts as a link between the SPMU and the LGA; • Sits at the LGA where the site intervention is taking place. Resettlement Implementation Committee (RIC) To ensure a broad representation with the intent of minimizing any conflict, it is recommended that a Resettlement Implementation Committee (RIC) be set up and members be drawn from amongst the following: • Affected Local government Chairman as Chairman • Physical Planning /land officer and forester • Representative of affected Communities, • PAPs represented by local trade /Union leaders • Coordinated by the Safeguard Unit of SPMU. • Rep of the Site Committees Their roles shall include; • Carry out meeting with each PAPs. • Provide all necessary information to the PAPs regarding guidance value and basis for calculation of prices offered. • Negotiate and firm up the final consent price. • Intimate the decision for payment of compensation to the PAPs • Ensure the Implementation of the RAP without any conflict • Ensure that the project design and specifications adequately reflect the recommendations of the RAP • Establish dialogue with the affected persons and ensure that the concerns and suggestions are referred to SPMU for appropriate response and management • All members of RIC must be people who are knowledgeable in the use of local mechanism to settle grievances and who can ensure equity across cases and also be in position to know and eliminate nuisance claims and satisfy legitimate claimants at low cost Grievance Redress Committee The grievance redress mechanism describes the procedure as well as a number of multi-layered mechanisms to settle grievances and complaints resulting from resettlement and compensation in- house, at local level (See chapter 6 for full details). The objective is to respond to the complaints of the PAPs in a timely and transparent manner and to provide a mechanism to mediate conflict and cut down on lengthy litigation, which often delays such infrastructural projects. It will also provide people who might have objections or concerns about their assistance, a public forum to raise their objections and through conflict resolution, address these issues adequately. The committee will provide ample opportunity to redress complaints informally, in addition to the existing formal administrative and legal procedures. The major grievances that might require mitigation include: 79 • PAPs not listed; • Losses not identified correctly; • Inadequate assistance; • Dispute about ownership; • Delay in disbursement of assistance and improper distribution of assistance. 8.2.4 Local Level Local Government • Coordinates activities at local level during the preparation and implementation of RAPs such as activities for determining the cut-off date and for actually implementing the resettlement, and for handling any grievances and complaints. • Responsible for the appraisal of properties affected by the project. • Provide additional resettlement area and amenities if the designated locations are not adequate. • Engage and encourage carrying out comprehensive and practical awareness campaign for the proposed project, amongst the various relevant grass roots interest groups. • Appoint a suitable Desk Officer for ARAP information management • Participating in sensitization of all communities • Participate in resolving grievances ; • Monitor implementation of projects and activities of Operational Officers; • Liaises with State PMU • Convenes and helps mobilise affected communities within and across targeted sub-catchments • Oversees community facilitators • O&M oversight of works • SPMU Participates in site-committees Technical Officer in Local Government Areas • Act as liaison to SPMU, MDAs and other organisations working with communities. • Provide senior technical skill-set and advisory services to communities and LGAs. • Convene affected and directly participating communities (liaising with neighbouring LGAs as needed). • Closely interact with community stakeholders and the community facilitators. • Support site monitoring. 8.2.5 Community Level Community Liaison and Support Professional • A liaison between the watershed community/communities and the SPMU • in close contact with community members on a frequent and continuous basis, • Assist in the formulation of community plans for livelihoods. • Community sensitization and social mobilization. • Assisting communities to form a representative Community Association. • Helps the community to identify, select and implement livelihood sub-projects. 80 • Mobilizes cooperative labour for physical works. • Provides support to the community for participatory monitoring. Site Committees/ Community Associations • Project site oversight. • Identifies erosion problems and helps select and monitor solutions. • Selects livelihood opportunities. • Oversee physical works. • Participate in site monitoring. • Cooperate with neighbouring communities and LGAs as needed for trans-boundary sub- catchments. Community Interest Groups • Coordinate community inputs to sub-catchment planning, implementation and monitoring, with guidance from support professionals and technical providers such as extension agents. • Participating in site monitoring. • Mobilise Youth and Women’s groups. Traditional Authority • Support in the identification of the right PAPs • Assist in resolving grievances of PAPs • Ensures that social values are not interfered with. Project Affected Persons • Receive compensation and move away from impact areas promptly • Coordinate with the survey team/Resettlement Committee in carefully checking and signing off their affected lands and other assets as well as their entitlements; • Make themselves available during census and participation in implementation; • Provide feedback on improving the quality of the RAP and suggesting solutions for • its effective implementation and • Submit concerns through the right grievance redress channel CBOs/CSOs • Assist in resolving grievances of PAPs • Support and assist in the mobilization of the various relevant grass roots interest groups. • May have complaints that need to be resolved in the execution of the project with a view to avoiding conflicts and grievances. • Serve as witness in compensation process and Monitoring and Evaluation 81 8.2.6 Others Contractors • Comply with relevant contract clauses on resettlement issues • Establish good community relations; • Train the workforce, and avoid any form of discrimination in terms of gender, religion or tribe; • As much as possible employ the workforce from the project catchment area, and also make procurement therein; • Try to provide local infrastructure and services in the course of executing the project; • Ensure that workers and site staff are sensitive to the customs and way of life of the communities. • Promptly repair any damage to utility services or infrastructure of the community in implementation of the project; Ministry of Lands, Survey and Urban Planning • Ensure compliance on matters of Land Acquisition and compensation and other resettlement issues, • Verification of selected sites for resettlement and ensuring that such sites are ideally suitable for affected people. • Invoke the physical planning and urban development law along the roads. • Ensuring that the project meets with the requirements of resettlement as specified in the report • Make appropriate recommendation and input in the resettlement process • Ensuring that affected people are adequately compensated as stated in this report 82 9 CHAPTER NINE TIME TABLE OF EVENTS 9.1 Timetable for the Resettlement Action Plan The ARAP has to be completed and PAPs adequately compensated before operation in the designated project area. The timeline is only indicative since the external factors not envisaged at this period such as delay in reviewing and addressing comments and other administrative and operational matters may cause a delay in the project time line. Table 7 Timetable for Completion of ARAP Implementation S/N Activities Completion Time MAY NOVEMBER DECEMBER JANUARYT 1 Submission of Draft ARAP Report 2 Field Verification and comments 3 Update of comments 4 Submission of final ARAP Document 5 Advertisement in two Local Newspaper in the Country 6 Published in the World Bank Info Shop 7 Commencement of ARAP Implementation 8 Completion of ARAP Implementation 9 Commencement of Civil work 83 9.2 Training and Capacity Needs Based on the assessment of the institutional capacities of the SMEnv in the understanding and implementation of an ARAP, it is recommended that they Contract technical assistance to provide training and operational support to SPMU and other agencies involved in the ARAP implementation. It is necessary that the SPMU and the Grievance Redress Committee be educated on the modus operandi of involuntary resettlement and how to manage grievance cases and also for PAPs to understand optimal measures for livelihood restoration and the opportunities to possibly take advantage of. Table 8 Capacity Building schedule and cost Duration Item Module Who to Train Resources Estimated Amount 2 Days Involuntary Principles of Resettlement SPMU, LG, Contractors, Full text of OP 4.12 for N2,110,839 Resettlement and Action Plan Engineers, & relevant each participant Rehabilitation MDAs, Community Monitoring & Evaluation of PowerPoint Protocol leaders/CBOs/NGOs/PAPs Presentation RAP/RAP Implementation Associated Handouts Public Involvement and Consultation in RAP 1 Day Grievance Conflict Management and SPMU, members of PowerPoint N1,370,520 Redress Resolution in RAP Resettlement and Presentation Mechanism Grievance Redress Associated Handouts Committees 1 Day Basics of Cash Management and SPMU, All the PAPs PowerPoint N1,046,520 Livelihood Monitoring Presentation Restoration Book keeping and Record Associated Handouts Management Investment Decision making TOTAL: N4,527,819 84 10 CHAPTER TEN MONITORING AND EVALUATION 10.1 Overview Monitoring and Evaluation are integral components of the programme/project management cycle used at all stages of the cycle, monitoring and evaluation can help to strengthen project design, enrich quality of interventions, improve decision-making, and enhance learning. The key objectives of monitoring the ARAP implementation would be as follows;  Transparency and accountability in terms of use of project resources  Providing constant feedback on the extent to which the RAP implementation are achieving their goals  Identifying potential problems at an early stage and proposing possible solutions  Providing guidelines for the planning of future projects and,  Improving project design There will be two levels of monitoring; namely internal monitoring and external monitoring. Under internal monitoring the Anambra State Ministry of Environment will hire a monitoring and evaluation officer to work in the PMU while an external monitoring and evaluation officer will be engaged periodically by SMEnv. 10.2 Internal Monitoring The internal monitoring and evaluation officer will report to the Project Coordinator at the PMU. Implementation of the RAP will be regularly supervised and monitored by the Monitoring and Evaluation/ Social Officer in coordination with staff of the NEWMAP- PMU. The findings will be recorded in quarterly reports to be furnished to the NEWMAP- PMU, and the World Bank. Lessons learnt during implementation will be documented and disseminated so that gaps identified can serve as valuable information for subsequent projects. 85 Tasks of the Monitoring and Evaluation Officer  Verify that the baseline information of all PAPs have been carried out and that the valuation of assets, lost or damaged, and the provision of compensation, resettlement and other rehabilitation entitlements has been carried out in accordance with the provisions of this policy framework and the respective inventory and RAP.  Oversee that the RAPs are implemented as designed and approved.  Verify that funds for implementing the RAPs are provided to the respective local level (district) in a timely manner in amounts sufficient for their purposes and that such funds are used by the SMEnv in accordance with the provisions of the RAP.  Ensure the identification and signature/thumb print of PAPs before and during receipt of compensation entitlements.  Record all grievances and their resolution and ensure that complaints are dealt with in a timely manner. 10.3 Independent Monitoring An independent agency will be retained by the SMEnv to periodically carry out external monitoring and evaluation of the implementation of the RAP. The independent agency will be either an academic or research institutions, non- governmental organizations (NGO) or an independent consulting firm. They should have qualified and experienced staff and their terms of reference acceptable to the funding partners In addition to verifying the information furnished in the internal supervision and monitoring reports, the independent monitoring agency will visit a sample of 10% of the Project affected Population in the project area, six months after the RAP has been implemented to:  Determine whether the procedures for PAPs participation and delivery of compensation and other rehabilitation entitlements have been done in accordance with the Policy Framework and the respective RAP.  Assess if the RAP objective or enhancement or at least restoration of living standards and income levels of PAPs have been met.  Gather qualitative indications of the social and economic impact of project implementation on the PAPs.  Suggest modification in the implementation procedures of the RAP, as the case may be, to achieve the principles and objectives of this policy framework. The terms of reference for this task and selection of qualified agency will be prepared by the NEWMAP- PMU in collaboration with the World Bank at the beginning of project implementation stage. 10.4 Monitoring Indicators They include:  Delivery and usage of compensation and resettlement entitlements;  Allocation of replacement land and residential plots, where applicable; 86  Reconstruction of new houses and other infrastructure, where applicable;  Compensation measures applied to compensate for damage during construction activities;  Reported grievances and action taken;  Problems encountered and action taken;  General issues related to the success of compensation and resettlement measures.  Implementation progress;  Compensation and resettlement policies;  Changes in livelihoods and incomes among PAPs; and,  Consultation with and participation of PAPs and other Stakeholders. 10.5 Implementation Schedule Table 10 summarizes the implementation schedule of the Resettlement Action Plan by phase, responsibilities and completion time for the construction and rehabilitation project. Table 9 Summary of Implementation Schedule PROJECT CYCLE PHASE ACTIVITIES RESPONSIBILITIES PLANNING Scoping and Initial site visit & consultations. Consultant; Supervision by Screening Identification of Resettlement SMEnv and Social issues Application of safeguard policies Categorization Action plan Screening Report WB No-Objection DESIGN Preparation of Draft ARAP Consultations Consultant; ARAP and Supervision by WB No-Objection consultations SMEnv Disclosure Disclosure of ARAP locally to WB SMEnv, World Bank Info Shop. Finalization and Final version of ARAP Consultant; Supervision by Incorporation ARAP into contract documents SMEnv WB No-Objection EXECUTION Implementation Implementation Monitoring Contractors 87 and monitoring & reporting on environmental and Supervision by social mitigation measures SMEnv and the Monitoring and reporting of community Resettlement and livelihood issues OPERATIONS Maintenance Monitoring and Contractors (POST- reporting of Resettlement and Supervision by IMPEMENTATIION) social livelihood issues SMEnv and the Community 88 REFERENCES Compulsory Acquisition of Land and Compensation in Infrastructure Projects, World Bank (2012) Environmental and Social Management Framework for the Nigeria Erosion and Watershed Management Project, World Bank (2013) Handbook for Preparing a Resettlement Action Plan, World Bank (2002) Ibe, K.M, and Njemanze, G.M., (1998) The Impact of Urbanization and Protection of Water Resources Owerri, Nigeria [online] Available from IFC performance Standards on Environmental and Social Sustainability, World Bank (2012) Involuntary Resettlement Sourcebook, World Bank (2004) Operational Manual (Safeguards on Involuntary Resettlement), World Bank (2001) Project Appraisal Document for Nigeria Erosion and Watershed Management Project, World Bank (2012) Project Implementation Manual for Nigeria Erosion and Watershed Management Project, World Bank, (2013) Resettlement Policy Framework for Nigeria Erosion and Watershed Management Project, World Bank (2012) Reyment R. A.; 1976. Stratigraphy of Niger Delta. Ibadan University Press, Nigeria. SMEC Group (2015) Detailed Engineering Design Report enugwu Ukwu Erosion Site SMEC Group (2016) Feasibility Study Report For Erosion Control Sites Strategic Framework for Mainstreaming Citizen Engagement in World Bank Group, World Bank (2004) Valuation Reporting Requirements in a Resettlement Action Planning (RAP) Process, Adamu (2013) 89 ANNEX 2 MONITORING INDICATOR FOR THE PERFORMANCE OF RAP INCOME RESTORATION NAME OF MONITORING OFFICER: NAME OF PAP: TYPE OF IMPACT CAUSED TO PAP BY PROJECT: Choice made by PAP between cash and in-kind compensation: Proposed Use of Payments: Date of Monitoring: Indicators Baseline Status New Status Comment (Date) (Date) Income of PAP Occupation of PAP Number of grievances and time and quality of resolution Skill acquisition/training Assistance received from Project Number of Children Number of children in school Type of place of dwelling Ownership of shop/structure? Value of Stock Turnover Condition of affected structure/Asset 90 91 92 93 94 95 ANNEX 4 CENSUS/ SOCIO-ECONOMIC DATA COLLECTION FORM IDENTIFICATION Community: _________________ Date___________________ Name of the Respondent: _______________________________________________ Affix Passport Here Phone No___________________________ Relationship to Household head_________________________ Age___ Sex___ Address: __________________________________________________ Nationality____________ Nativity ___________ Length of stay within the community____________ GENERAL INFORMATION Religious Group: Christians____Muslim___ATR___Others (specify) ___ Social Group: Vulnerable___General___ Family Pattern: Joint___Nuclear___Individual______ Size of Family: Small (2-4) ____Medium (5-7) ____Large (Above7) ____ FAMILYPARTICULARS(Startfrom head of the household) Name of Member Sex Age Marital Relationship Educational Occupation Status to HH-head level Primary Secondary Household’s Main Occupation________________and Monthly income (N)___________Secondary Source_________and Monthly Income (N)________No. of Adult earning members:________ No. of dependents:___ Family annual expenditure: (N)_________ 96 COMMERCIAL/SELF EMPLOYMENT ACTIVITIES Type of Shop/Business Enterprises (SBEs) Hotel____Provision store____Repair & Workshop____ Other Shops (Specify) ___________Other Enterprise (Specify) _____________No. of Partners: ___ Employment Pattern Owner/Operator____Employed 1 to 5 persons___Employed above 5____ VULNERABILITY HH below poverty line___ HH becoming BPL as a result of loss of livelihood/asset___ Female headed household___ PUBLIC UTILITIES How would you describe the condition of the following amenities in town you live/community? Amenities Very Good Good Fair Poor Roads to the community Roads within the community Schools in the community Public Health Institutions Potable Water Public Electricity Communication facilities (Postal Service, Telephone) Public recreation facilities What is the major source of water available to your household? (i)River____ (ii)Borehole (commercial)____ (iii)Borehole (private)___ (iv)Public pipe-borne water___(v)Pond___ (vi)Water Vendor___ (vii)Well water___ How long does it take you in minutes/hours to get to your water source___? What is your primary source of electricity? 97 (i)Hurricane Lamp___(ii) Private Generators___ (iii)Community Generators___ (iv)State Government Utilities Board___ (v)Company Operating in your community___ (vi) PHCN (National Grid)___ What is your secondary source of electricity? (i)Hurricane Lamp___ (ii) Private Generators___ (iii)Community Generators___ (iv)Company Operating in your community___ What is the main fuel you use for cooking? (i)Firewood___(ii)Charcoal___ (iii)Kerosene___ (iv)Gas___ (v)Electricity___(vi)Crop residue/ Saw dust___(vii) Animal Wastes___(viii)Others___ HEALTH AND SANITATION What type of toilet facility do you use? (i)Pit___(ii) Bush___(iii)Bucket___(iv) Water Closet___(v)Others (Specify)…… How do you dispose of your household refuse? (i)Private Open Dump___(ii) Public Open Dump___(iii) Organized Collection___(iv)Burning___(v) Bush___(vi)Burying___ Which of the following diseases/condition is most common in your area (i)Malaria___(ii)Typhoid___(iii)Diarrhoea___(iv)Cough___(v) Respiratory Disturbance___(vi)Others__ PROJECT PERCEPTION Are you aware of the proposed Erosion Rehabilitation Project? Yes___No__ If Yes, Source of information_______________ What is your opinion about the project? Good____ Bad____ Can’t say____ If good, what positive impacts do you perceive? ____________________________ If bad, what negative impacts do you perceive? _____________________________ INFORMATION ON AFFECTED PROPERTY GPS Coordinates: ____________________ Name of PAP______________________________________________________ Phone No______________________________ 98 Category of PAP: Titleholder___ Encroacher___ Tenant___ Squatter____ others (specify) __________ Type of document possessed to certify ownership type_________________________________ If not owned, state name and Address of owner_______________________________________ ______________________________________________________________________________ If informal use right, state type of agreement__________________________________________ Number of years used_____ Rent paid/month (N) ___________ Details of the structure Type of Use: Residential____Commercial___Residential/Commercial___Other (Specify) __ Construction Type: Mud___Brick; Mud/Thatched roof__Brick/Thatched roof____ No. of Rooms/Storey___Impacted Area (m2) _____Total Impacted Area (m2) ____ Utility Connection: Electricity____Water___Phone__ (P-Partially F-Fully) Other Affected Assets Compound wall/fence___ Tree___ Farmland____ Borehole/well___ Others (Specify) ____ Replacement Value (N) _________ Assets distance to the wall edge_____________ Agricultural Products Type of Crop Owner of Crop Total yearly production Average yield Average value of crop Number of labor used for production Crop products sold at market (%) Average yearly household income from agriculture (N) __________ Trees Type of Tree 99 Number of affected Tree Average yield of fruit bearing trees Average yearly income from fruit tree RESETTLEMENT AND REHABILITATION In case you are displaced (residentially) where and how far do you prefer to be located? Within the area___ Outside the area____ Place name_______________ Distance___ (km) Which is your preferred replacement Option? Land for land lost ___Cash Assistance ___House in Resettlement Site ___Shop in Resettlement Site __Other (Specify) ___ Factors to be considered in providing alternate place Access to family/friends ____Income from friends___ Income from Business activity___ Daily Job___ Close to Market___ Other (Specify) ____ 100 101 ANNEX 5 LIST OF VULNERABLE PAPS S/N NAME OF PAPS SEX AGE MARITAL STAUS PHONE NO OF PAPs 1 Female 55 Widow 2 Female 57 Widow 3 Female 70 Widow 4 Female 62 Widow 5 Female 70 Widow 6 Female 70 Widow 7 Female 40 Widow 8 Female 45 Widow 9 Female 75 Widow 10 Female 55 Widow 11 Female 45 Widow 12 Female 75 Widow 13 Female 60 Widow 14 Female 60 Widow 15 Female 55 Widow 16 Female 57 Widow 17 Female 60 Married 18 Male 70 Married 19 Male 84 Married 20 Female 57 Widow 21 Male 73 Married 22 Male 94 Married 102 103 104 ANNEX 7 SUMMARY OF AGREEMENT WITH LAND OWNERS The client held a consultation session with the site committee members, town union president, the 2 PAPs whose land will be acquired (Mr. Emmanuel Iwotor Ezeanya and Mrs. Nwana Patricia). The purpose of this consultation was to delineate the boundaries of the land to be acquired as well as determine the form of compensation for each of the PAPs. After delineation following the engineering designs, the Mrs. Nwana Patricia was made to understand that she will be allowed to harvest all crops planted prior to the commencement of work as well as removal of materials from the shrine on the land. This she accepted and agreed to. However, stated that she does not have another land anywhere. The Town Union president and the Site committee agreed unanimously to assign her a permanent portion of the community land where she can use for her farming and other activities. This she agreed to as well and thanked the union president. However, the consultant stated to the town union president and the site committee members that this must be concluded before the commencement of the civil works in the project site. This they acknowledged and promised to abide with. Furthermore, Mr Emmanuel Iwotor Ezeanya a representative of the Iwortor family that will be losing some portion of their land was consulted and informed of the implication of the project on their land. This he stated their understanding and explained that it has been discussed among his family members and they agreed to accept cash compensation to enable them acquire a new portion. The consultant then distributed a census inventory form for the PAPs to capture their information as well as size of land. The PAPs thanked the consultant for his patience and promised to ensure that the project will not be delayed by them in any way. 105