Tamil Nadu Sustainable Urban Development Program (TNSUDP) PROCUREMENT PLAN I. General 1. Project information: • Project: Tamil Nadu Sustainable Urban Development Program (TNSUDP) • Country: India • Project Code: P150395 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated February 19, 2015 Revision 0 agreed by the Bank on February 19, 2015 3. Implementing Agencies: TNUIFSL, DMA, CMWSSB, TWADB, Chennai Corporation and other ULBs 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Substantial 6. Original Procurement Risk Rating for the Project: Substantial 7. Current Procurement Risk Rating for the Project: Substantial II. Works, Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Category Method of Procurement Threshold (US$ Equivalent) Works International Competitive Bidding (ICB) > 40,000,000 National Competitive Bidding (NCB) Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) for Works As per paragraph 3.14 of Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Goods and International Competitive Bidding (ICB) > 3,000,000 non- Limited International Bidding (LIB) wherever agreed by Bank consultant National Competitive Bidding (NCB) Up to 3,000,000 (with NCB conditions) services Shopping Up to 100,000 (NCS) Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) Services As per paragraph 3.14 of Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations (UN) Agencies As per paragraph 3.10 of Guidelines 1 b) Prior Review Threshold Works: All contracts more than USD 10 million equivalent Goods: All contracts more than USD 2 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 2 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Procurement of goods, works and non-consulting services under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small- scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. • DGS&D rate contracts may be used as framework agreement (FA) provided: i. Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. ii. Before issuing the purchasing order, the implementing agency will carry out a price analysis on the specific good that is intended to be purchased. If after this due diligence the implementing agency concludes (and Bank agrees) that the DGS&D rate contracts are more advantageous, DGS&D rate contracts may be used as FA. iii. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank's right to audit and F&C clauses could be mentioned. 5. Procurement Packages with Methods and Time Schedule – As per plan in STEP III. Selection of Consultants 1 a) Selection Methods and Thresholds Method of Procurement Threshold (US$ Equivalent) Selection Based on Consultants’ Qualifications Up to 300,000 (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ Quality- for all other cases Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 1,000,000 for firms; and > US$ 300,000 for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Selection and employment of consultants under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 5. Consultancy Assignments with Selection Methods and Time Schedule – As per plan in STEP PROCUREMENT India : Tamil Nadu Sustainable Urban Development Program PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-06-10 2019-06-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150395 GPN Date: Project Name: Tamil Nadu Sustainable Urban Development Program Loan / Credit No: IBRD / 84880 Executing Agency(ies): Tamil Nadu Urban Infrastructure Financial Services Limited WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WBR 4 / Construction of Integrated Storm water Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 7,116,554.07 Signed drains in Cooum watershed Envelope of Cooum water basin IN-TNUIFSL-3669-CW-RFB Under / Construction of 45 MLD Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 0.00 Implementati 2016-11-23 2016-11-23 2016-11-24 2016-11-25 2016-12-19 2019-06-30 TTRO Plant in Kodungaiyur Envelope on & its allied works IN-TNUIFSL-11989-CW-RFB / Providing WSIS to Under Nagercoil Municipality in Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 0.00 Implementati 2017-04-07 2017-04-19 2017-05-26 2017-06-07 2017-07-12 2018-01-08 Kanyakumari District Envelope on including maintenance period of 12 months IN-TNUIFSL-13575-CW-RFB Under / Providing Water Supply Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 0.00 Implementati 2017-05-29 2017-06-03 2017-07-15 2017-08-14 2017-09-18 2018-03-17 Improvement Scheme in Envelope on Namakkal Municipality IN-TNUIFSL-13580-CW-RFB / Providing SCADA Pending arrangements for Water Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Supply Improvement Scheme Envelope on in Theni-Allinagaram Municipality IN-TNUIFSL-16436-CW-RFB / CWSS to Sankarakoil, Puliyankudi Municipalities, Thiruvenkadam Town panchayat in Tirunelveli Under District and Rajapalayam, Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 0.00 Implementati 2017-06-02 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Sivakasi, Thiruthangal Envelope on Municipalities in Virudhunagar District including maintenance for a period of 12 months under Package-1 IN-TNUIFSL-16442-CW-RFB / CWSS to Sankarakoil, Puliyankudi Municipalities, Thiruvenkadam Town panchayat in Tirunelveli Under District and Rajapalayam, Single Stage - One IBRD / 84880 Prior Request for Bids Open - National 0.00 Implementati 2017-06-02 2017-06-07 2017-07-19 2017-08-18 2017-09-22 2018-03-21 Sivakasi, Thiruthangal Envelope on Municipalities in Virudhunagar District including maintenance for a period of 12 months under Package-2 Page 1 IN-TNUIFSL-5574-CW-RFB / Construction of Integrated Storm Water Drain - Improvements in Cooum Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Basin, Nolambur Watershed Envelope in the extended areas of Chennai Corporation - Package - 25 IN-TNUIFSL-5190-CW-RFB / Construction of Integrated Storm Water Drain - Improvement to Ambattur Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 sidco Canal in Cooum basin, Envelope Nolambur watershed in extended areas of Chennai Corporation-Package-24 IN-TNUIFSL-19179-CW-RFB / Construction of Integrated Under Storm Water Drain - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under Package 19 A IN-TNUIFSL-19184-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under package - 19 B IN-TNUIFSL-19186-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under package - 19 C IN-TNUIFSL-19187-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under package - 19 D IN-TNUIFSL-19190-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under package - 19 E IN-TNUIFSL-19191-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Padikuppam Canal under package - 19 F IN-TNUIFSL-19193-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Ambattur Envelope on Sidco Canal under package - 24 A IN-TNUIFSL-19194-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Ambattur Envelope on Sidco Canal under package - 24 B Page 2 IN-TNUIFSL-19195-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 A IN-TNUIFSL-19196-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 B IN-TNUIFSL-19197-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 C IN-TNUIFSL-19198-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 D IN-TNUIFSL-19199-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 E IN-TNUIFSL-19200-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drains - IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Envelope Improvements to Nolambur on Canal under package - 25 F IN-TNUIFSL-19202-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 A IN-TNUIFSL-19203-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 B IN-TNUIFSL-19204-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 C IN-TNUIFSL-19205-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 D IN-TNUIFSL-19206-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 E Page 3 IN-TNUIFSL-19207-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 F IN-TNUIFSL-19208-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 G IN-TNUIFSL-19210-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 H IN-TNUIFSL-19211-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 I IN-TNUIFSL-19212-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 J IN-TNUIFSL-19213-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 K IN-TNUIFSL-19214-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 L IN-TNUIFSL-19216-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 M IN-TNUIFSL-19217-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 N IN-TNUIFSL-19218-CW-RFB / Construction of Integrated Under Storm Water Drains - Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-05 2017-07-10 2017-08-21 2017-09-20 2017-10-25 2018-10-25 Improvements to Envelope on Nandambakkam Canal under package - 39 O Page 4 IN-TNUIFSL-5192-CW-RFB / Construction of Integrated Single Stage - One Storm water in Cuddalore IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Municipality under Phase-I Package-1 IN-TNUIFSL-5193-CW-RFB / Construction of Integrated Single Stage - One Storm Water Drain in IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Phase-1 Package-2 IN-TNUIFSL-5194-CW-RFB / Construction of Integrated Single Stage - One Storm Water Drain in IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Phase-1 Package-3 IN-TNUIFSL-5196-CW-RFB / Construction of Integrated Single Stage - One Storm Water Drain in IBRD / 84880 Post Request for Bids Open - National 0.00 Canceled 2017-02-15 2017-02-20 2017-04-03 2017-05-03 2017-06-07 2017-12-04 Envelope Cuddalore Municipality under Phase-1 Package-4 IN-TNUIFSL-21867-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drain in IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 Envelope Cuddalore Municipality on Phase-1 Package-1 IN-TNUIFSL-21865-CW-RFB / Construction of Integrated Under Single Stage - One Storm Water Drain in IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 Envelope Cuddalore Municipality on Phase -1 Package-2 IN-TNUIFSL-47449-CW-RFB / Supply Installation and commissioning of 150 nos of Pending street light lamp posts with Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope on areas in Divsions 1,2,3,4,6,11,12, Zone1 under Package-1 IN-TNUIFSL-47451-CW-RFB / Supply, Installation and commissioning of 1377 nos Pending of street light lamp posts Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 with LED fittings in the Envelope on leftover areas in Divisions 15,16,17,18,19,20 Zone-2 under Package-2 IN-TNUIFSL-47454-CW-RFB / Supply, Installation, Commissioning of 747 nos of Pending Street Light lamp posts with Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope on areas in Divisions 22,23,24,25 Zone 3 under Package-3 IN-TNUIFSL-47455-CW-RFB / Supply, Installation, Commissioning of 407 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 33 Zone 3 under Package-4 Page 5 IN-TNUIFSL-47457-CW-RFB / Supply, Installation, Commissioning of 230 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 26,32 Zone 3 under Package-5 IN-TNUIFSL-47459-CW-RFB / Supply, Installation, Commissioning of 196 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 27,30 Zone 3 under Package-6 IN-TNUIFSL-47460-CW-RFB / Supply, Installation, Commissioning of 210nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 28,29 Zone 3 under Package-7 IN-TNUIFSL-47461-CW-RFB / Supply, Installation, Commissioning of 2531 nos Pending of Street Light lamp posts Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 with LED fittings in the Envelope on leftover areas in Divisions 79,83 Zone 7 under Package- 8 IN-TNUIFSL-47465-CW-RFB / Supply, Installation, Commissioning of 2370 nos Pending Single Stage - One of Street Light lamp posts IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope with LED fittings in the on leftover areas in Divisions 82 Zone 7 under Package-9 IN-TNUIFSL-47466-CW-RFB / Supply, Installation, Commissioning of 629 nos of Pending Street Light lamp posts with Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 LED fittings in the leftover Envelope on areas in Divisions 81,84,85,86,87,88,89,91,92 Zone 7 under Package-10 IN-TNUIFSL-47467-CW-RFB / Supply, Installation, Commissioning of 792 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 80,90,93 Zone 7 under Package-11 IN-TNUIFSL-47473-CW-RFB / Supply, Installation, Commissioning of 456 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 143 Zone 11 under Package-12 Page 6 IN-TNUIFSL-47474-CW-RFB / Supply, Installation, Commissioning of 261 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 145 Zone 11 under Package-13 IN-TNUIFSL-47476-CW-RFB / Supply, Installation, Commissioning of 458 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 147 Zone 11 under Package-14 IN-TNUIFSL-47483-CW-RFB / Supply, Installation, Commissioning of 228 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 148, 151 Zone 11 under Package-15 IN-TNUIFSL-47484-CW-RFB / Supply, Installation, Commissioning of 288 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 149 Zone 11 under Package-16 IN-TNUIFSL-47485-CW-RFB / Supply, Installation, Commissioning of 560 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 150 Zone 11 under Package-17 IN-TNUIFSL-47487-CW-RFB / Supply, Installation, Commissioning of 187 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 152 Zone 11 under Package-18 IN-TNUIFSL-47488-CW-RFB / Supply, Installation, Commissioning of 179 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 154 Zone 11 under Package-19 IN-TNUIFSL-47489-CW-RFB / Supply, Installation, Commissioning of 996 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 153,155 Zone 11 under Package-20 Page 7 IN-TNUIFSL-47490-CW-RFB / Supply, Installation, Commissioning of 130 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 157,158 Zone 12 under Package-21 IN-TNUIFSL-47491-CW-RFB / Supply, Installation, Commissioning of 1814 nos Pending of Street Light lamp posts Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 with LED fittings in the Envelope on leftover areas in Divisions 188 Zone 14 under Package- 22 IN-TNUIFSL-47492-CW-RFB / Supply, Installation, Commissioning of 827 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 189 Zone 14 under Package-23 IN-TNUIFSL-47495-CW-RFB / Supply, Installation, Commissioning of 484 nos of Pending Single Stage - One Street Light lamp posts with IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope LED fittings in the leftover on areas in Divisions 190,191 Zone 14 under Package-24 IN-TNUIFSL-47497-CW-RFB / Supply, Installation, Commissioning of 794 nos of Street Light lamp posts with Pending Single Stage - One LED fittings in the leftover IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-05 2018-02-05 2018-03-12 2018-04-11 2018-05-16 2018-11-12 Envelope areas in Divisions on 168,169,183,187 Zone-14 & Division 192-200 Zone 15 under Package-25 IN-TNUIFSL-49154-CW-RFB / Restoration of Zamin Pending Single Stage - One Pallavaram Periya Eri and IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-02-16 2018-02-16 2018-02-16 2018-02-28 2018-04-04 2018-10-01 Envelope Keelkattalai Eri in on Pallavaram Municipality IN-TNUIFSL-62353-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation - Construction Pending Single Stage - One of Storm water drain at IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope Kalangarqai, Kalugupathai on and Kaluthaipathai odai int o S.V.Kulam under Package- II IN-TNUIFSL-62354-CW-RFB / Construction of Storm Water Drainage in Tuticorin Pending Corporation - Rejunvenation Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 of main S.V.Kulam, Envelope on Improvement of Mullikulam tank and related works under Package-III Page 8 IN-TNUIFSL-62356-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation - Construction of Pending Single Stage - One Storm Water Drain from IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope S.V.Kulam along Meelavittan on Road and drain towards railway side and related works under Package-IV IN-TNUIFSL-62358-CW-RFB / Construction of Storm Water Drain in Tuticorin Pending Single Stage - One Corporation - Construction of IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-05-16 2018-05-21 2018-07-02 2018-08-01 2018-09-05 2019-03-04 Envelope Main Storm Water Drain of on Mullakadu Odai and related work under Package-VI IN-TNUIFSL-83343-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation- Construction of Pending Single Stage - One Channnels for diversion of IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-10-24 2018-10-29 2018-12-10 2019-01-09 2019-02-13 2019-08-12 Envelope kalangakari odai to on periapallam odai and related works along NH-45B under Package-1 IN-TNUIFSL-83344-CW-RFB / Construction of Storm Water Drain in Tuticorin Corporation-Construction of Pending Storm Water Drainage for Single Stage - One IBRD / 84880 Post Request for Bids Open - National 0.00 Implementati 2018-10-24 2018-10-29 2018-12-10 2019-01-09 2019-02-13 2019-08-12 diversion of flow of Envelope on Chengulam Odai to Upparu river and related works along NH-7A under Package- 5 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-TNUIFSL-934-NC-DIR / Technology workshop on IBRD / 84880 Post Direct Selection Direct 0.00 Canceled 2016-08-16 2016-08-21 2016-09-12 2016-10-31 Solid Waste Management (Two days) at Chennai CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 WBR 2 / Project Management Consultancy Services for Implementation Quality And Cost- Open - IBRD / 84880 Prior 2,294,591.76 Signed of Integrated Storm water Based Selection International drain in the extended areas of Chennai Corporation WBR 7 / Preparation of Base Map, Property and Utility Mapping and Door to Quality And Cost- Open - IBRD / 84880 Prior 1,099,564.93 Signed Door Survey using Geo- Based Selection International Spatial Techniques for Corporation of Chennai IN-TNUIFSL-915-CS-QCBS / Consultancy Services for preparation of Detailed Project Reports (DPRs) for Quality And Cost- providing Under Ground IBRD / 84880 Post Open - National 266,107.98 Signed 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 Based Selection Sewerage Schemes (UGSS) for eleven added areas of Greater Chennai Corporation for CMWSSB IN-TNUIFSL-928-CS-QCBS / Consultancy services for preparation of comprehensive Quality And Cost- Open - IBRD / 84880 Post 156,127.65 Signed 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 DPR for UGSS in 14 ULBs Based Selection International in Poonamalle cluster A in Chennai Metropolitan Area IN-TNUIFSL-932-CS-QCBS / Consultancy services for preparation of comprehensive Quality And Cost- Open - Under IBRD / 84880 Post 0.00 2016-08-04 2016-08-04 2016-08-04 2016-09-12 2016-09-30 2016-11-04 2016-12-09 2017-12-09 DPR for UGSS in 9 ULBs Based Selection International Implementation in Poonamalle cluster B in Chennai Metropolitan Area IN-TNUIFSL-2618-CS-QCBS / Consulting services for preparation of Feasibility Report, Bid Documents and Quality And Cost- Open - conducting Bid Process IBRD / 84880 Post 31,835.28 Completed 2016-10-17 2016-10-17 2016-10-27 2016-11-28 2016-12-13 2017-01-13 2017-02-17 2018-02-17 Based Selection International Management for Establishing Solar Roof Tops in Buildings maintained by Greater Chennai Corporation IN-TNUIFSL-2619-CS-QCBS / Consulting services for Bid Process Management for Establishing Solar Roof Tops Quality And Cost- Open - IBRD / 84880 Post 24,016.07 Signed 2016-10-17 2016-10-17 2016-10-27 2016-11-28 2016-12-13 2017-01-13 2017-02-17 2018-02-17 in Buildings maintained by Based Selection International ULB's in Tamil Nadu under O/o Commissionerate of Municipal Administration IN-TNUIFSL-933-CS-QCBS / Appointment of Consultant for formation of Asset Quality And Cost- IBRD / 84880 Post Open - National 0.00 Canceled 2016-08-08 2016-08-08 2016-09-01 2016-10-06 2016-10-19 2016-11-23 2016-12-28 2017-12-28 Management Company for Based Selection Greater Chennai Corporation in PDGF under TNSUDP Page 10 IN-TNUIFSL-2783-CS-QCBS / Consultancy services for Proof Checking of Engineering Designs and Costing of the DPR prepared by TWAD Board for Quality And Cost- Providing CWSS to IBRD / 84880 Post Open - National 37,046.57 Signed 2016-10-25 2016-10-25 2016-10-25 2016-11-29 2016-12-09 2017-01-02 2017-01-23 2017-07-22 Based Selection Nattarasankottai Town Panchayat and 1069 Rural Habitations with Bulk Provision to 7 Town Panchayats and 1228 Rural Habitatio IN-TNUIFSL-2831-CS-QCBS / Consulting services for preparation of Detailed Project Report for Plugging of outfalls, Interception & Quality And Cost- Open - IBRD / 84880 Post 0.00 Canceled 2016-11-01 2016-11-01 2016-11-01 2016-12-12 2016-12-22 2017-01-08 2017-02-08 2017-11-10 Diversion of Sewerage, Solid Based Selection International Waste Management, Flood carrying capacity, structural adequacy and R&R in Major drains in Cooum Basin IN-TNUIFSL-2832-CS-QCBS / Consulting services for preparation of Detailed Project Report for Plugging of outfalls, Interception & Quality And Cost- Open - IBRD / 84880 Post 0.00 Canceled 2016-11-01 2016-11-01 2016-11-01 2016-12-12 2016-12-22 2017-01-08 2017-02-08 2017-11-10 Diversion of Sewerage, Solid Based Selection International Waste Management, Flood carrying capacity, structural adequacy and R&R in Major drains in Adyar Basin IN-TNUIFSL-5533-CS-QBS / Consulting services for preparation of Feasibility Report and Detailed Project Report (DPR) for Quality And Cost- IBRD / 84880 Post Open - National 107,245.11 Completed 2017-01-12 2017-01-12 2017-01-19 2017-02-27 2017-03-15 2017-03-29 2017-04-26 2017-11-22 construction of bridges Based Selection connecting Nesapakkam to Nandampakkam over Adyar River at two locations for Greater Chennai Corporation IN-TNUIFSL-5534-CS-QCBS / Consulting services for preparation of Feasibility Report and Detailed Project Report (DPR) for construction of New bridge Quality And Cost- IBRD / 84880 Post Open - National 67,651.46 Completed 2017-01-12 2017-01-12 2017-01-19 2017-02-27 2017-03-06 2017-03-29 2017-04-26 2017-11-22 at Stephenson road across Based Selection Otteri Nullah and Widening of existing bridge across Cooum at Arunachala road for Greater Chennai Corporat IN-TNUIFSL-5540-CS-QCBS / Consulting Services for preparation of Revised Detailed Project Report Quality And Cost- (DPR) for providing IBRD / 84880 Post Open - National 264,583.65 Signed 2017-01-20 2017-01-20 2017-01-30 2017-03-13 2017-03-20 2017-04-03 2017-05-08 2018-05-08 Based Selection Integrated Storm Water Drains (SWD) for Kosasthalaiyar basin in Greater Chennai Corporation Page 11 IN-TNUIFSL-5544-CS-QCBS / Consultancy Services for Proof Checking of Engineering Designs and Quality And Cost- IBRD / 84880 Post Open - National 11,653.46 Signed 2017-01-30 2017-01-30 2017-02-09 2017-03-23 2017-03-30 2017-04-13 2017-05-18 2018-05-18 Costing of DPR for providing Based Selection Water Supply Improvement Scheme to Bodinayakkanur Municipality IN-TNUIFSL-10422-CS- QCBS / Consulting Services for preparation of Feasibility Report and Transaction Advisory Services for setting Quality And Cost- IBRD / 84880 Post Open - National 25,155.56 Signed 2017-03-22 2017-03-22 2017-04-03 2017-05-01 2017-05-31 2017-07-05 2017-08-09 2018-08-09 up a Multi Level Parking Based Selection (MLP) at Uthamar Gandhi Salai in Chennai under PPP mode for Greater Chennai Corporation IN-TNUIFSL-9650-CS-QCBS / Consulting Services for Quality And Cost- assessment of Industrial IBRD / 84880 Post Open - National 0.00 Canceled 2017-03-10 2017-03-27 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2018-03-15 Based Selection Water Supply Scenario in Tamil Nadu IN-TNUIFSL-11080-CS- QCBS / Consulting services for preparation of a Quality And Cost- Feasibility Report and IBRD / 84880 Post Open - National 20,238.14 Completed 2017-03-31 2017-03-31 2017-04-03 2017-05-05 2017-05-12 2017-06-16 2017-07-21 2018-04-30 Based Selection Detailed Project Report (DPR) for construction of Bus Stand for Namakkal Municipality IN-TNUIFSL-10923-CS- QCBS / Planning, Setting up and Operationalizing a Real Time Flood Forecasting & Spatial DSS for Adyar, Cooum, Kosasthalayar & Quality And Cost- Open - IBRD / 84880 Prior 0.00 Under Review 2017-03-24 2017-03-24 2017-03-24 2017-05-03 2017-06-02 2017-07-07 2017-08-11 2022-03-31 Kovalam Basins & setting Based Selection International up of a Hydro Modelling cum Flood Monitoring Control Room at SEOC, Chennai, setting up of Flood Monitoring Co IN-TNUIFSL-11644-CS- QCBS / Consulting Services for Preparation of Feasibility Report and conducting Transaction Advisory Quality And Cost- Open - IBRD / 84880 Post 0.00 Canceled 2017-04-05 2017-04-06 2017-05-15 2017-06-20 2017-07-05 2017-08-09 2017-09-13 2018-09-13 Services for Establishing Based Selection International large Solar Parks in various places in Tamil Nadu under Public Private Partnership mode IN-TNUIFSL-11651-CS- QCBS / Consulting Services Quality And Cost- Open - for Preparation of Detailed IBRD / 84880 Post 209,679.19 Signed 2017-04-05 2017-04-06 2017-05-10 2017-06-12 2017-07-03 2017-08-07 2017-09-11 2018-06-25 Based Selection International Project Report for Restoration of Ennore Creek IN-TNUIFSL-11654-CS- QCBS / Consulting Services for Preparation of Detailed Quality And Cost- Open - Project Report for IBRD / 84880 Post 126,578.45 Signed 2017-04-05 2017-04-06 2017-05-10 2017-06-12 2017-07-03 2017-08-07 2017-09-11 2018-06-25 Based Selection International Restoration of Kovalam Creek (Muttukadu Back waters) Page 12 IN-TNUIFSL-15977-CS- QCBS / Planning, Setting up and Operationalizing a Real Time Flood Forecasting & Spatial DSS for Adyar, Cooum, Kosasthalayar & Quality And Cost- Open - IBRD / 84880 Prior 4,216,934.12 Signed 2017-05-23 2017-05-23 2017-05-23 2017-06-30 2017-07-30 2017-09-03 2017-11-01 2022-03-31 Kovalam Basins & setting Based Selection International up of a Hydro Modelling cum Flood Monitoring Control Room at SEOC, GCC, Tiruvallur & Kancheepuram Collectorate IN-TNUIFSL-5543-CS-QCBS / Consulting Services for preparation of Detailed Project Report (DPR) for providing Storm Water Quality And Cost- Drains(SWD)for missing links IBRD / 84880 Post Open - National 0.00 Canceled 2017-01-20 2017-01-20 2017-01-27 2017-03-08 2017-03-15 2017-03-29 2017-04-26 2017-10-23 Based Selection and for draining the flooded water in the subways to integrate with the existing Storm Water Drains in various locations for GCC IN-TNUIFSL-9520-CS-QCBS / Consulting Services for preparation of Feasibility Quality And Cost- Report for assessing the IBRD / 84880 Post Open - National 0.00 Canceled 2017-03-09 2017-03-27 2017-05-10 2017-06-07 2017-07-07 2017-08-11 2017-09-15 2018-09-15 Based Selection potential of Neyveli mines as water storage reservoirs for CMWSSB IN-TNUIFSL-21924-CS- QCBS / Consulting Services Quality And Cost- for Environmental and Social IBRD / 84880 Post Open - National 14,250.50 Completed 2017-07-26 2017-07-26 2017-07-26 2017-08-28 2017-09-04 2017-09-18 2017-11-06 2018-03-31 Based Selection Audit for projects under TNSUDP (2017) IN-TNUIFSL-21927-CS- QCBS / Consulting Services to prepare detailed study report for providing Equitable Water Supply to Quality And Cost- all ULBS based on the IBRD / 84880 Post Open - National 0.00 Canceled 2017-08-21 2017-08-21 2017-08-21 2017-09-25 2017-10-16 2017-11-06 2017-12-18 2018-07-31 Based Selection study of existing Water Supply Schemes in Karaikudi, Thiruvannamalai, Gobichettipalayam & Chengalpattu Municipalities IN-TNUIFSL-34932-CS- QCBS / Consulting Services for preparation of a Detailed Project Report for Optimising Quality And Cost- IBRD / 84880 Post Open - National 134,433.01 Signed 2017-11-02 2017-11-06 2017-12-01 2017-12-29 2018-01-12 2018-02-16 2018-03-23 2019-03-23 and Revamping of the Based Selection existing Distribution Network and SCADA for Salem Corporation IN-TNUIFSL-37743-CS- QCBS / Consultancy Services for preparation of Feasibility Quality And Cost- cum Detailed Project Report IBRD / 84880 Post Open - National 0.00 Canceled 2017-11-22 2017-12-06 2017-12-16 2018-01-18 2018-01-22 2018-02-20 2018-03-27 2018-08-31 Based Selection (DPR) for reconstruction of VOC Market for Salem City Municipal Corporation Page 13 IN-TNUIFSL-37747-CS- QCBS / Consulting Services for preparation of Feasibility Report cum Detailed Project Quality And Cost- IBRD / 84880 Post Open - National 0.00 Canceled 2017-11-22 2017-12-06 2017-12-20 2018-01-22 2018-01-29 2018-02-19 2018-03-26 2018-12-20 Report for Rehabilitation of Based Selection Defunct Dumping site at Erumapalayam in Salem City Municipal Corporation IN-TNUIFSL-118513-CS- QCBS / Consulting Services Quality And Cost- Pending IBRD / 84880 Post Open - National 0.00 2019-06-30 2019-07-21 2019-09-03 2019-10-01 2019-10-31 2019-12-05 2020-01-09 2021-01-08 for Environmental and Social Based Selection Implementation Audit (2019) INDIVIDUAL CONSULTANTS Page 14