Procurement Plan I. General 1. Project Information Country : India Borrower : Department of Finance, GoR Project Name : Strengthening Public Financial Management in Rajasthan (P156869) Bank’s Approval Date of the Procurement Plan: October 06, 2016 [as updated regularly on STEP] 2. Date of General Procurement Notice: March 22, 2016 3. Period covered by this Procurement plan: 18 months 4. Risk Rating for the Implementing Agencies: Substantial II. Goods, Works and Non-Consulting Services 1. (a) Procurement Methods Procurement Method Threshold (US$ Equivalent) 1 Open International (Goods) Above 3 million 2 Open National (Goods) Above 100,000 and up to 3 million (with NCB conditions) – as per para 3.3 and 3.4 of the Guidelines 3 Open International (Works) Above 40 million Open National (Works) Above 100,000 3 Shopping (Goods/Works) Up to 100,000 and up to 40 million 4. Open International (Non- Above 3 million consulting Services) 5 Open National (Non-consulting Up to 3 million Services) 6 Direct Contract As per para 3.7 of Guidelines (b) Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Sl. Category Prior Review Threshold Comments No. (US$ Equivalent) 1 Works Above US$ 10.0 million All Contracts 1 Goods Above US$ 2.0 million All Contracts 2 Non-consulting Services Above US$ 2.0 million All Contracts 1 2. Pre-qualification: Bidders shall be pre-qualified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines): Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Under preparation 5. NCB Provisions: a) Only the model bidding documents for NCB agreed with the Bank (and as amended for time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small- scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) To improve efficiency and transparency of small value purchases in Bank financed projects, the Bank has agreed to allow use of Government e-Market place (GeM) as follows: (i) Use of GeM is allowed in lieu of shopping up to US$ 30,000 in catalogue mode; (ii) Use of GeM is allowed in lieu of shopping up to US$ 100,000, provided there are at least 3 suppliers for the item on GeM and the Purchaser uses RFQ (mini competition or bidding among suppliers) feature on GeM to discover the final price; (iii) In both above cases Borrowers will record their assessment on reasonableness of price; and (iv) GeM is not to be used in lieu of NCB. h) Two or three envelope system will not be used (except when using e-procurement system assessed and agreed by the Bank). 6. Summary of the Procurement Packages planned during the first 18 months after 2 project effectiveness (including those that are subject to retroactive financing and advanced procurement) Available on STEP 3 III. Selection of Consultants 1. (a) Procurement Methods Sl. Procurement Method Threshold (US$ Equivalent) No . 1 Selection based on Consultants’ Up to 300,000 Qualifications / Least Cost Selection 2 Single-source Selection of consulting firms As per para 3.9 – 3.11 of Guidelines 3 Selection of Individual Consultants/ Sole As per Section V of Guidelines Source Procedures for the Selection of Individual Consultants 4 Quality- and Cost-based Selection/ For all other cases Quality-based Selection/ Selection under a Fixed Budget 5 i. International Shortlist Above US$ 800,000 ii. Shortlist may comprise national Up to US$ 800,000 consultants only (b) Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above USD 1.0 million All Contracts 2. Individual Up to US$ 300,000 All Contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost up to US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA IV. Other Requirements / Information (applicable for all procurements) a) Even for Post Review cases, the inputs of Bank on TORs will be obtained by project. b) The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. c) The prior review thresholds will also be indicated in the procurement plan. The procurement plan will be subsequently updated annually (or at any other time, if required), and will reflect any change in prior review thresholds. d) The World Bank will carry out an annual ex-post procurement review falling below the prior review thresholds indicated above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the grant. 4 PROCUREMENT India : Strengthening Public Financial Management in Rajasthan PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-10-06 2021-03-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156869 GPN Date: Project Name: Strengthening Public Financial Management in Rajasthan Loan / Credit No: IBRD / 88550, / Department of Finance, Government of Rajasthan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DOF-5924-GO-RFQ / Procurement of Office Furniture Items ( Modular Request for Single Stage - One office furniture, computer / Post Open - National 24,220.00 25,256.86 Signed 2017-01-28 2017-03-08 2017-02-22 2017-04-07 Quotations Envelope furniture, and storage furniture etc.) for SPFM-PMU office establishments. IN-DOF-5925-GO-RFQ / Procurement of computers , peripherals , software licenses Request for Single Stage - One / Post Open - National 18,713.00 15,501.03 Signed 2017-01-28 2017-03-07 2017-02-14 2017-04-01 (MS Office & Anti-Virus) ,UPS Quotations Envelope etc. for SPFM-PMU Office Establishments. IN-DOF-5927-GO-RFQ / Air Request for Single Stage - One Conditioners for SPFM-PMU / Post Open - National 4,550.00 4,013.90 Signed 2017-02-01 2017-03-29 2017-02-14 2017-09-25 Quotations Envelope Office establishments. IN-DOF-5932-GO-RFB / Procurement of Hardware for Single Stage - One / Post Request for Bids Open - National 1,492,537.00 1,220,694.27 Signed 2017-02-23 2017-04-06 2017-03-02 2017-05-15 2017-05-29 2017-05-30 2017-06-20 2017-07-08 2017-07-05 2018-01-04 Commercial Taxes Envelope Department, GOR. IN-DOF-14298-GO-DIR / Procurement of IT Hardware- "OEM -IT Hardware" for Data Center of the Commercial IBRD / 88550 Post Direct Selection Direct 140,328.99 148,311.12 Signed 2017-05-05 2017-04-09 2017-05-12 2017-06-06 2017-06-23 2017-07-14 2017-08-22 Taxes Department (CTD), Government of Rajasthan on single source basis. IN-DOF-46457-GO-RFB / Supply and Installation of End User Computing IT Hardware- All In One (AIO) Desktops with UPS and Printers Strengthening Expenditure Single Stage - One including computer related / Post Request for Bids Open - National 916,570.00 0.00 Canceled 2018-02-12 2018-02-19 2018-03-21 2018-04-05 2018-05-10 2018-11-06 and Revenue Systems Envelope training for the Excise Department , Finance(Ways&Means-Debt management)) Division, and SPFC in Finance Department.) IN-DOF-5928-GO-RFQ / Printers (including multi- Project Management and Request for Single Stage - One / Post Open - National 6,825.00 5,518.77 Signed 2017-02-01 2018-04-01 2017-02-16 2018-05-01 functional printers) for SPFM- Capacity Building Quotations Envelope PMU Office Establishments. IN-DOF-53470-GO-RFQ / Procurement of Photo Copier Project Management and Request for Single Stage - One / Post Limited 5,538.00 4,207.63 Signed 2018-03-18 2018-03-15 2018-04-05 2018-03-27 2018-05-05 Machine for Office Purpose Capacity Building Quotations Envelope under SPFM Project IN-DOF-53779-GO-RFQ / Project Management and Request for Single Stage - One Supply of Laptops for SPFM / Post Limited 3,846.00 3,891.16 Terminated 2018-03-19 2018-03-13 2018-04-02 2018-03-23 2018-05-02 Capacity Building Quotations Envelope Project IN-DOF-53780-GO-RFQ / Supply and Installation of MS Project Management and Request for Single Stage - One / Post Limited 3,957.00 3,539.07 Signed 2018-03-18 2018-02-21 2018-04-02 2018-03-27 2018-05-02 Office and Renewal of Capacity Building Quotations Envelope Antivirus for SPFM Project. IN-DOF-79949-GO-RFQ / Procurement of office Project Management and Request for Single Stage - One IBRD / 88550 Post Open - National 4,062.24 0.00 Canceled 2018-10-08 2018-11-29 2019-05-28 furnitures for SPFC under Capacity Building Quotations Envelope SPFM Project IN-DOF-79941-GO-RFQ / Procurement of IT Hardware including Desktop (AIO), Project Management and Request for Single Stage - One IBRD / 88550 Post Open - National 41,554.67 6,615.87 Signed 2018-10-20 2018-12-15 2019-03-05 2019-12-15 Laptops, UPS, Multi Functional Capacity Building Quotations Envelope Printer with scanner & Color Printer under SPFM Project. IN-DOF-80991-GO-RFQ / Project Management and Request for Single Stage - One Procurement of Photocopier IBRD / 88550 Post Open - National 7,312.04 79,401.00 Signed 2018-10-20 2018-12-21 2019-03-07 2019-12-21 Capacity Building Quotations Envelope Machine under SPFM Project IN-DOF-134493-GO-RFQ / Project Management and Request for Single Stage - One Procurement of Furniture for IBRD / 88550 Post Open - National 1,860.00 1,768.11 Signed 2019-11-09 2019-12-31 2020-01-13 2020-06-28 Capacity Building Quotations Envelope SPFM Project Page 1 IN-DOF-143752-GO-RFB / Procurement of All in One Strengthening Expenditure Single Stage - One IBRD / 88550 Post Request for Bids Open - National 422,654.00 0.00 Canceled 2020-01-15 2020-08-10 2020-01-20 2020-08-25 2020-03-02 2020-04-01 2020-05-06 2024-08-30 Desktops with UPS and and Revenue Systems Envelope Printers for Excise Department IN-DOF-150689-GO-RFQ / Project Management and Request for Single Stage - One Supply of Paper Shredding IBRD / 88550 Post Limited 357.00 289.56 Signed 2019-12-23 2019-12-18 2020-01-23 2019-12-24 2021-01-22 Capacity Building Quotations Envelope Machine for SPFM Project. IN-DOF-180236-GO-RFQ / Procurement of Air Purifier Project Management and Request for Single Stage - One IBRD / 88550 Post Open - National 1,581.00 0.00 Canceled 2020-07-05 2020-08-30 2021-08-30 (Qty. 3 to 6 nos.) for SPFM Capacity Building Quotations Envelope Project IN-DOF-184523-GO-RFQ / Pending Project Management and Request for Single Stage - One Procurement of Air Purifier (8 IBRD / 88550 Post Limited 1,939.00 0.00 Implementati 2020-07-30 2020-09-24 2021-09-24 Capacity Building Quotations Envelope Qty.) for SPFM Project on IN-DOF-210539-GO-RFQ / Project Management and Request for Single Stage - One Procurement of Laptops for IBRD / 88550 Post Limited 4,901.29 1,473.37 Signed 2021-01-10 2021-01-29 2021-03-07 2021-02-18 2021-04-12 Capacity Building Quotations Envelope SPFM Project IN-DOF-203703-GO-RFB / Supply and Installation of End User Computing IT Hardware- Strengthening Expenditure Single Stage - One IBRD / 88550 Post Request for Bids Open - National 399,837.79 0.00 Canceled 2020-11-11 2020-11-16 2020-12-07 2021-01-06 2021-02-10 2026-02-09 All in One (AIO) Desktops with and Revenue Systems Envelope UPS and Printers for Excise Department. IN-DOF-213663-GO-RFB / Supply and Installation for IT Hardware - All in One Strengthening Public Desktop with UPS and Printers Single Stage - One IBRD / 88550 Financial Management Post Request for Bids Open - National 680,735.19 0.00 Canceled 2021-01-25 2021-02-01 2021-03-15 2021-04-14 2021-05-19 2026-05-18 for Excise Department and Envelope Framework LFAD Department under National Competitive Bidding (NCB). IN-DOF-218071-GO-RFB / Under Strengthening Expenditure Single Stage - One Supply and Installation of End IBRD / 88550 Post Request for Bids Open - National 1,361,470.39 0.00 Implementati 2021-02-11 2021-02-11 2021-02-16 2021-02-16 2021-03-30 2021-04-29 2021-06-03 2021-10-01 and Revenue Systems Envelope User Computing IT Hardware. on IN-DOF-210543-GO-RFQ / Procurement of Multi- Project Management and Request for Single Stage - One IBRD / 88550 Post Limited 2,042.21 0.00 Canceled 2021-01-06 2021-03-03 2022-03-03 Functional Colour Printer and Capacity Building Quotations Envelope Laser Printer for SPFM Project IN-DOF-184292-GO-RFQ / Procurement of Multi Project Management and Request for Single Stage - One IBRD / 88550 Post Limited 1,726.00 0.00 Canceled 2020-07-31 2020-09-25 2021-09-25 functional Colour Printer (2 Capacity Building Quotations Envelope Qty.) for SPFM Project NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DOF-2276-CS-QCBS / Selection of Consultant for carry out an Institutional Quality And Cost- IBRD / 88550 Post Open - International 540,000.00 1,047,716.20 Signed 2016-10-07 2016-10-19 2016-10-12 2016-11-10 2016-10-25 2016-12-08 2016-12-28 2017-01-07 2017-04-04 2017-02-11 2017-04-21 2017-03-18 2017-04-26 2018-03-18 Assessment including GST Based Selection Readiness Assessment and training. IN-DOF-5930-CS-QCBS / Enhancing Effectiveness of Quality And Cost- IBRD / 88550 Post Open - National 671,641.00 845,562.76 Signed 2017-02-05 2016-04-12 2017-02-08 2017-02-20 2017-04-21 2017-03-23 2017-06-12 2017-04-22 2017-10-09 2017-05-21 2017-10-30 2017-06-18 2017-11-06 2019-06-18 Public Audit Institutions in the Based Selection Government of Rajasthan IN-DOF-5931-CS-QCBS / Strengthening Public Strengthening Decentralized Quality And Cost- IBRD / 88550 Financial Management Post Open - National 373,134.00 1,023,014.58 Signed 2017-02-05 2016-04-17 2017-02-10 2017-02-24 2017-04-18 2017-03-26 2017-06-05 2017-04-05 2017-10-16 2017-04-22 2018-01-25 2017-05-20 2018-04-24 2019-05-20 Participative Planning in Based Selection Framework Government of Rajasthan IN-DOF-4591-CS-QCBS / Consultancy for Training Quality And Cost- Needs Assessment (TNA) and IBRD / 88550 Post Open - National 221,000.00 237,697.82 Signed 2016-12-15 2016-04-17 2016-12-16 2017-02-18 2017-02-21 2017-03-20 2017-04-12 2017-04-04 2017-07-10 2017-04-24 2017-07-17 2017-05-06 2017-07-31 2017-11-02 Based Selection Development of Training Strategy IN-DOF-4592-CS-QCBS / Consultancy for Developing and Establishing a Quality And Cost- / Post Open - National 220,000.00 713,912.79 Signed 2016-12-16 2016-04-17 2016-12-26 2017-02-26 2017-03-03 2017-04-17 2017-04-27 2017-05-25 2017-07-10 2017-06-04 2017-07-18 2017-06-18 2017-07-31 2019-06-18 Commitment Control System Based Selection and Information System in Government of Rajasthan IN-DOF-18473-CS-QCBS / Strengthening Public Consulting Services for Data Quality And Cost- / Financial Management Post Open - National 935,701.93 915,937.73 Signed 2017-09-22 2017-05-04 2017-09-24 2017-10-03 2017-06-19 2017-10-31 2017-08-16 2017-11-15 2017-10-16 2017-11-24 2018-02-27 2017-12-11 2018-04-25 2020-12-10 for Policy Action in Based Selection Framework Government of Rajasthan IN-DOF-18552-CS-QCBS / Consultancy for Business Process Re-Engineering (BPR) Quality And Cost- / Post Open - National 507,024.09 410,618.44 Signed 2017-06-19 2017-04-17 2017-06-19 2017-06-19 2017-06-19 2017-07-21 2017-08-16 2017-08-16 2017-10-09 2017-08-30 2017-10-30 2017-09-07 2017-11-06 2018-09-07 Study of Transport Based Selection Department in Rajasthan, India Page 2 IN-DOF-78202-CS-QCBS / Consultancy for Independent Project Management and Quality And Cost- IBRD / 88550 Post Open - National 181,380.16 0.00 Canceled 2018-09-14 2018-09-18 2018-09-18 2018-10-09 2018-12-01 2019-01-03 2018-12-11 2019-02-15 2019-01-10 2019-02-26 2019-02-01 2019-03-05 2019-02-21 2024-07-31 Verification Agency (IVA) for Capacity Building Based Selection SPFM Project IN-DOF-79935-CS-CQS / Consultancy for Public Expenditure Management -- Strengthening Public Consultant Study on Rationalization and IBRD / 88550 Financial Management Post Qualification Open - National 117,334.00 130,766.83 Signed 2018-10-15 2018-09-17 2018-10-29 2018-10-15 2018-12-12 2019-01-31 2018-12-26 2019-02-07 2019-01-26 2019-02-15 2019-07-25 Prioritization of Programs / Framework Selection Projects / Schemes in the Government of Rajasthan IN-DOF-79940-CS-QCBS / Consultancy for Providing Strengthening Expenditure Quality And Cost- Technical Support to the State IBRD / 88550 Post Open - International 880,076.89 1,550,414.61 Signed 2018-10-15 2018-09-25 2018-11-18 2018-10-16 2018-12-08 2019-01-04 2019-01-07 2019-02-18 2019-03-08 2019-05-24 2019-03-30 2019-06-13 2019-04-30 2020-09-15 2020-04-29 and Revenue Systems Based Selection Procurement Facilitation Cell (SPFC), GoR IN-DOF-93495-CS-QCBS / Consultancy for Strengthening Strengthening Expenditure Quality And Cost- Cash and Debt Management IBRD / 88550 Prior Open - International 922,394.37 1,090,941.30 Signed 2019-03-08 2019-03-07 2019-03-18 2019-03-11 2019-04-29 2019-07-02 2019-05-29 2019-08-21 2019-06-12 2020-08-14 2019-07-22 2020-09-10 2019-08-26 2020-09-15 2021-11-24 and Revenue Systems Based Selection System for Government of Rajasthan IN-DOF-180224-CS-QCBS / Consultancy for Business Process Re-Engineering (BPR) Strengthening Expenditure Quality And Cost- Under IBRD / 88550 Post Open - National 382,757.35 0.00 2020-06-21 2020-07-02 2020-06-25 2020-07-16 2020-08-08 2020-09-07 2020-11-06 2020-12-20 2021-01-24 2022-01-24 and Institutional Assessment and Revenue Systems Based Selection Implementation for Excise Department in Rajasthan, India IN-DOF-210522-CS-QCBS / Consultancy for Capacities Development on Rajasthan Strengthening Expenditure Quality And Cost- Under IBRD / 88550 Prior Open - International 6,972,884.28 0.00 2021-01-15 2021-02-12 2021-01-30 2021-02-18 2021-03-15 2021-04-12 2021-05-12 2021-06-16 2021-07-21 2024-09-18 Transparency in Public and Revenue Systems Based Selection Implementation Procurement Act [RTPP Act] and Rules under SPFM Project IN-DOF-210528-CS-QCBS / Consultancy for Capacities Strengthening Expenditure Quality And Cost- Pending Development in Contract IBRD / 88550 Prior Open - National 1,089,176.31 0.00 2021-01-29 2021-02-15 2021-04-04 2021-05-02 2021-06-01 2021-07-06 2021-08-10 2022-08-10 and Revenue Systems Based Selection Implementation Management under SPFM Project IN-DOF-210521-CS-QCBS / Consultancy for Public Strengthening Public Quality And Cost- Under Investment Management IBRD / 88550 Financial Management Post Open - International 993,272.97 0.00 2021-02-01 2021-02-11 2021-02-11 2021-02-26 2021-03-27 2021-04-24 2021-05-24 2021-06-28 2021-08-02 2022-09-01 Based Selection Implementation System (PIM) under SPFM Framework Project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DOF-150704-CS-CDS / Consultancy Services for Strengthening Expenditure IBRD / 88550 Post Direct Selection Direct 92,714.00 88,357.65 Signed 2020-01-05 2020-01-19 2020-01-15 2020-01-24 2020-02-08 2020-03-20 2024-07-23 Independent Verification and Revenue Systems Agency (IVA) for SPFM Project IN-DOF-210525-CS-CDS / Consultancy for Procurement Strengthening Expenditure Under IBRD / 88550 Post Direct Selection Direct 102,110.28 0.00 2021-01-27 2021-02-04 2021-02-04 2021-02-18 2021-04-10 2021-10-07 Perception Study under SPFM and Revenue Systems Implementation Project IN-DOF-218066-CS-CDS / Consultancy for Technical Strengthening Public Under Support for Modernizing Front IBRD / 88550 Financial Management Post Direct Selection Direct 198,527.03 0.00 2021-02-11 2021-02-17 2021-02-21 2021-02-23 2021-04-27 2022-01-22 Implementation Transport Offices for Citizen Framework Services Delivery in GoR IN-DOF-225924-CS-INDV / Individual Hiring of Public Finance Project Management and Pending IBRD / 88550 Post Consultant Limited 20,547.94 0.00 2021-03-30 2021-04-04 2021-04-25 2021-05-30 2021-11-26 Expert (Individual Consultant) Capacity Building Implementation Selection for SPFM-PMU. Page 3