Ministry of Lands and Natural Resources Ghana Forest Investment Program - Enhancing Natural Forest and Agroforest Landscapes (ENFAL) Project Grant No.: P148183 Procurement Plan General 1. Bank’s approval Date of the Procurement Plan January 20, 2015 2. Date of General Procurement Notice: July, 2, 2015 3. Period covered by this Procurement Plan: January to December, 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 All 2. NCB (Goods) Above US$ 2,000,000 All 3. ICB (Works) Not Applicable All 4. NCB (Works) Not Applicable All 5. (Non-Consultant Services) Above US$ 2,000,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Grant Project P148183 20/01/2015 issued by Ministry of Lands and Natural Resources. 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 December 27, 2017 Estimate Domesti Review Ref Description d Packag c by Bank Comments . Cost es Prefere (Prior / No. US$ nce Post) million (yes/no) Summary of the 1 ICB (Goods) None None None None Summary of the Supply of Heavy NCB (Goods) Duty 2a 2.553 2 No Prior Trucks/Tractors and 23 Vehicles Summary of the 2b NCB (Goods) 1.528 8 No Post Summary of the 3 ICB (Non- None None None None Consultant Services) Summary of the 4 NCB (Non- None None None None Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods Above US$ 1,000,000 2 Packages so far (Firms) 2. Single Source (Firms) All 1 so far 3. Individual Above US$ 300,000 None so far 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref Description of Estimated Review . Assignment Cost Packag by Bank Commen No. US$ es (Prior / ts million Post) December 27, 2017 Summary of 1 number of 0.354 1 Post contracts that will be let under QCBS Summary of 2 number of 1.381 35 Post contracts that will be let under other methods December 27, 2017 PROCUREMENT Ghana : Ghana FIP - Enhancing Natural Forest and Agroforest Landscapes Project PLAN General Information Country: Ghana Bank’s Approval Date of the Original Procurement Plan: 2018-03-25 2021-08-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148183 GPN Date: Project Name: Ghana FIP - Enhancing Natural Forest and Agroforest Landscapes Project Loan / Credit No: TF / 18842, TF / A9512, TF / A9474 Ministry of Lands and Natural Resources - FIP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 2. Pilot ENFAL/WKS/NCB/1/19 / Investments for Improved Single Stage - One 2020-04- Construction of 2 No. Model TF / 18842 Forest and Landscape Post Request for Bids Open - National 700,000.00 0.00 Canceled 2019-07-08 2019-07-22 2019-08-19 2019-09-18 2019-10-23 Envelope 20 Nurseries Management with Communities Component 2. Pilot MLNR/AF/WKS/01/2020 / Investments for Improved Pending 2021-05- Reclamation of Selected 5No. TF / 18842 Forest and Landscape Post Request for Bids Open - National 500,000.00 0.00 Implementat 2020-09-08 2020-09-22 2020-10-20 2020-11-10 2020-12-02 31 Degraded Mined out Sites Management with ion Communities Component 2. Pilot MLNR/ENFAL/WKS/01/21 / Investments for Improved Pending Single Stage - One 2022-03- Reclamation of Selected 5No. TF / A9512 Forest and Landscape Post Request for Bids Open - National 500,000.00 0.00 Implementat 2021-06-15 2021-06-20 2021-07-20 2021-08-10 2021-09-14 Envelope 13 Degraded Mined out Sites Management with ion Communities ENFAL/WKS/SH/1/19 / Component 2. Pilot Construction of 20 No. Investments for Improved Request for Single Stage - One 2020-12- Mechanized Boreholes at TF / 18842 Forest and Landscape Post Open - National 100,000.00 0.00 Canceled 2020-05-09 2020-07-04 Quotations Envelope 31 Selected Seed Production Management with Units of Ghana Cocoa Board Communities ENFAL/WKS/ICB/1/20 / Component 2. Pilot Request for Bids - Construction of 1No. Investments for Improved Pending Single Stage - One Small Works SPD 2022-03- Mechanized Forest Tree TF / 18842 Forest and Landscape Post Request for Bids Open - International 500,000.00 0.00 Implementat 2021-05-27 2021-06-01 2021-07-01 2021-07-31 2021-09-04 Envelope (1 envelope 03 Nursery at Nsoatre in the Management with ion process) Bono Region Communities GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ENFAL/MLNR/GDS/SH/09 / Supply and Installation of ICT Equipment, 8 No. Projectors, Component 3. Innovation, 5 No Mobile PA System, 30 No Single Stage - One TF / 18842 Capacity Building, and Post Request for Bids Open - National 120,000.00 0.00 Canceled 2019-06-28 2019-07-03 2019-07-31 2019-08-30 2019-10-04 2020-01-02 Laptop Computers with Envelope Communications Accessories, 15 No Desktop Computers and 10 No Cameras ENFAL/GDS/SH/04/19 / Supply and Delivery of Office Component 2. Pilot Facilities for 5 No. CREMA Investments for Improved Request for Single Stage - One Offices (500 No. Plastic TF / 18842 Forest and Landscape Post Limited 20,000.00 21,214.10 Completed 2020-03-13 2020-06-03 2020-05-01 2020-06-26 2020-06-30 2020-10-21 Quotations Envelope Chairs, 180 No. Wooden Management with Chairs, 5 No. PA System, 10 Communities No. Tables, 10 No. Sign Post) ENFAL/GDS/NCB/1/19 / Component 2. Pilot Procurement of requisite Investments for Improved logistics for operationalization Single Stage - One TF / 18842 Forest and Landscape Post Request for Bids Open - National 800,000.00 862,239.92 Completed 2020-03-30 2020-05-18 2020-04-13 2020-05-18 2020-05-13 2020-06-10 2020-06-03 2020-06-15 2020-07-08 2020-07-12 2020-11-05 2020-12-14 of community corridor Envelope Management with livelihood schemes for the Communities CREMA Blocks ENFAL/GDS/SH/2/19 / Supply and Installation of Lot 1: 32 No. Laptop Computers Component 3. Innovation, with Accessories , 8 No. LCD Request for Single Stage - One TF / 18842 Capacity Building, and Post Open - National 60,000.00 0.00 Canceled 2019-03-18 2019-05-13 2019-11-09 Projectors, Lot 2: 25 No. Quotations Envelope Communications Digital Cameras and Accessories and Lot 3: 3 No. Mobile PA Systems ENFAL/GDS/SH/3/19 / Component 4. Project Request for Single Stage - One Supply and Delivery of TF / 18842 Management, Monitoring, Post Open - National 25,000.00 0.00 Canceled 2019-03-06 2019-05-01 2019-10-28 Quotations Envelope stationery and Coordination MLNR/AF/GD/02/2020 / Supply and Delivery of Lot 1: 10 No. Laptop Computers and Accessories, 10 No. Component 1. Policy Reforms Request for Single Stage - One Monochrome Printers and 10 TF / 18842 and Institutional Post Open - National 80,000.00 72,231.22 Signed 2020-03-20 2020-05-20 2020-05-15 2020-06-04 2020-05-24 2020-11-26 Quotations Envelope No. Digital Scanners, Lot 2: 10 Strengthening No. Digital Cameras and Lot 3: 3 No Heavy Duty Photocopiers, MLNR/AF/GD/01/2020 / Supply and Delivery of Lot 1: 1No. Station Wagon (High Range), Lot 2: 3No Station Component 1. Policy Reforms Pending Single Stage - One Wagon (Mid Range), Lot 3: 3 TF / A9474 and Institutional Post Request for Bids Open - National 800,000.00 0.00 Implementati 2021-03-31 2021-04-05 2021-05-05 2021-06-04 2021-07-09 2021-11-06 Envelope No. Station Wagon (Low Strengthening on Range), Lot 4: 5No. Double Cabin Pick-Ups and Lot 5: 1No. Saloon Car Page 1 ENFAL/GDS/SH/2/20 / Component 2. Pilot Procurement of GIS software Investments for Improved Request for Single Stage - One and hardware for data TF / 18842 Forest and Landscape Post Limited 40,000.00 0.00 Canceled 2020-03-16 2020-05-11 2020-08-09 Quotations Envelope capture, storage, retrieval and Management with display Communities Component 2. Pilot ENFAL/GDS/SH/1/19 / Investments for Improved Request for Single Stage - One Supply and Delivery of 40,000 TF / 18842 Forest and Landscape Post Open - National 50,000.00 0.00 Canceled 2019-03-20 2019-05-15 2019-07-14 Quotations Envelope No. Plantain Suckers Management with Communities NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MLNR/ENFAL/NCS/2/19 / Design and Print 1,000 No. Component 1. Policy Reforms Request for Single Stage - One Final Framework for Payment TF / 18842 and Institutional Post Open - National 15,000.00 0.00 Canceled 2019-06-15 2019-07-21 2019-09-19 Quotations Envelope of Compensation for Crop Strengthening Damage Component 2. Pilot MLNR/ENFAL/NCS/6/19 / Investments for Improved Design and Print 1,000 No. Request for Single Stage - One TF / 18842 Forest and Landscape Post Open - National 10,000.00 6,842.54 Signed 2020-03-15 2020-09-05 2020-05-10 2020-10-14 2020-07-09 Forest Extension Training Quotations Envelope Management with Manuals Communities MLNR/ENFAL/NCS/3/19 / Component 1. Policy Reforms Design and Print 1,000 No. Request for Single Stage - One TF / 18842 and Institutional Post Open - National 15,000.00 0.00 Canceled 2019-04-13 2019-06-01 2019-07-31 Stakeholder Analysis/Roles of Quotations Envelope Strengthening Actors Document Component 2. Pilot MLNR/AF/NCS/01/2021 / Investments for Improved Pending NGO/CBO Services for Request for Single Stage - One TF / 18842 Forest and Landscape Post Limited 150,000.00 0.00 Implementati 2020-05-08 2020-05-13 2020-06-24 2020-07-24 2020-08-28 2021-02-24 Communoty Livelihood Proposals Envelope Management with on Activities Communities Component 2. Pilot ENFAL/NCS/SH/5/20 / Investments for Improved Pending Request for Single Stage - One Design and print reviewed TF / 18842 Forest and Landscape Post Limited 10,000.00 0.00 Implementati 2020-06-15 2020-08-10 2020-10-09 Quotations Envelope Plantation MoP/Guidelines Management with on Communities ENFAL/NCS/SH/8/20 / Component 3. Innovation, Pending Production of documentary Request for Single Stage - One TF / 18842 Capacity Building, and Post Limited 10,000.00 0.00 Implementati 2020-06-15 2020-08-10 2021-02-06 on GFIP Interventions and Quotations Envelope Communications on Achievement MLNR/ENFAL/NCS/1/19 / Component 1. Policy Reforms Design and Print of 1,000 No. Request for Single Stage - One TF / 18842 and Institutional Post Open - National 15,000.00 0.00 Canceled 2019-05-15 2019-06-26 2019-08-25 Information Materials on the Quotations Envelope Strengthening Legal Regime for CREMAs MLNR/ENFAL/NCS/4/19 / Component 2. Pilot Design and Print 1,000 No. Investments for Improved Request for Single Stage - One code of conduct/constitution TF / 18842 Forest and Landscape Post Open - National 15,000.00 0.00 Canceled 2019-04-15 2019-06-03 2019-08-02 Quotations Envelope for the established GFIP- Management with CREMAs Communities Component 2. Pilot ENFAL/NCS/SH/6/20 / Investments for Improved Request for Single Stage - One Design and print 1000 No. TF / 18842 Forest and Landscape Post Limited 10,000.00 0.00 Canceled 2020-06-15 2020-08-10 2020-10-09 Quotations Envelope Forest Investor Handbook Management with Communities Component 2. Pilot ENFAL/NCS/SH/7/20 / Investments for Improved Design and print 1000 No. Request for Single Stage - One TF / 18842 Forest and Landscape Post Limited 10,000.00 0.00 Canceled 2020-06-21 2020-08-16 2020-08-22 Manual of Procedures for Quotations Envelope Management with Enrichment Planting Communities MLNR/ENFAL/NCS/5/19 / Component 2. Pilot Design and Print 1,000 No Investments for Improved field guides for Request for Single Stage - One TF / 18842 Forest and Landscape Post Open - National 10,000.00 0.00 Canceled 2020-05-17 2020-07-05 2020-09-03 Implementation of FIP-CREMA Quotations Envelope Management with Activities within Ecological Communities Corridor CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. Pilot MLNR/ENFAL/CS/1/19 / Investments for Improved Consultant Design and Construction TF / 18842 Forest and Landscape Post Qualification Open - National 50,000.00 0.00 Canceled 2019-04-09 2019-05-16 2019-04-23 2019-06-28 2019-05-21 2019-06-20 2019-07-25 2020-01-21 Supervision of 20 No. Management with Selection Mechanized Boreholes Communities MLNR/ENFAL/CS/8/19 / Engagement of Five (5) Component 2. Pilot NGO/CBO to support Investments for Improved operationalization of Non-Profit Under TF / 18842 Forest and Landscape Post Open - National 500,000.00 0.00 2019-05-10 2019-07-08 2019-05-31 2019-07-14 2019-08-13 2019-09-17 2020-03-15 identified livelihood for the Organizations Implementation Management with five (5) CREMA Groups as Communities means of generating income to sustain the groups Component 2. Pilot MLNR/ENFAL/CS/18/19 / Investments for Improved Consultant Design and Construction TF / 18842 Forest and Landscape Post Qualification Open - National 100,000.00 87,270.69 Signed 2019-06-19 2019-07-08 2019-07-03 2019-07-26 2019-08-16 2019-11-08 2019-09-15 2020-04-19 2019-10-20 2020-04-29 2020-04-17 supervision of 2 No. Nurseries Management with Selection Communities Page 2 MLNR/ENFAL/CS/37 / Review Component 1. Policy Reforms Consultant and Finalize the Benefit TF / 18842 and Institutional Post Qualification Open - National 50,000.00 0.00 Canceled 2019-05-15 2019-06-05 2019-07-19 2019-08-18 2019-09-22 2020-03-20 Sharing Framework and Strengthening Selection Guidelines MLNR/ENFAL/CS/2/19 / Component 2. Pilot Development of training Investments for Improved Consultant manuals and information Pending TF / 18842 Forest and Landscape Post Qualification Open - National 10,000.00 0.00 2020-04-12 2020-04-26 2020-05-24 2020-06-07 2020-07-05 2020-11-02 package on fire prevention, Implementation Management with Selection pre-suppression and Communities suppression strategies MLNR/AF/CS/01/20 / collate and assess the viability of all legislations, policies, Component 1. Policy Reforms Consultant guidelines, administrative Pending TF / 18842 and Institutional Post Qualification Open - National 20,000.00 0.00 2020-04-16 2020-04-30 2020-06-04 2020-06-25 2020-07-30 2020-10-28 directives on rehabilitation of Implementation Strengthening Selection mined-out areas and make recommnedations for further policy reforms MLNR/AF/CS/02/20 / Design Component 2. Pilot of appropriate Investments for Improved Consultant Under reclamation/rehabilitation TF / 18842 Forest and Landscape Post Qualification 50,000.00 0.00 2020-04-12 2020-12-21 2020-04-19 2021-06-16 2020-05-24 2020-06-14 2020-07-12 2021-01-08 Implementation method for selected Management with Selection degraded mined-out sites Communities Component 2. Pilot MLNR/AF/CS/03/2020 / Investments for Improved Consultant Prepare a draft legal Pending TF / 18842 Forest and Landscape Post Qualification Open - National 25,000.00 0.00 2020-05-07 2020-05-21 2020-06-06 2020-06-27 2020-08-01 2020-10-30 framework for plantation Implementation Management with Selection development loan scheme. Communities MLNR/AF/CS/04/2020 / Component 2. Pilot Consultancy to support Investments for Improved Consultant Under capacity in business TF / 18842 Forest and Landscape Post Qualification 25,000.00 0.00 2020-05-08 2020-09-02 2020-05-13 2020-09-11 2020-06-10 2021-01-18 2020-07-01 2020-08-05 2020-11-03 Implementation development for beneficiary Management with Selection plantation loan scheme Communities MLNR/ENFAL/CS/01/2020 / Component 3. Innovation, Consultant Conduct Safeguard audit of TF / 18842 Capacity Building, and Post Qualification Open - National 20,000.00 33,600.00 Signed 2020-03-09 2020-03-20 2020-03-23 2020-04-30 2020-04-20 2020-04-30 2020-05-20 2020-06-08 2020-06-24 2020-06-19 2020-08-23 the GFIP Communications Selection MLNR/ENFAL/CS/6/19 / Component 3. Innovation, Consultant Design, Development and Under TF / 18842 Capacity Building, and Post Qualification Open - National 20,000.00 0.00 2020-03-24 2020-09-03 2020-04-14 2020-10-26 2020-05-12 2020-05-26 2020-06-30 2020-09-28 Maintenance of Website for Implementation Communications Selection GFIP. MLNR/ENFAL/CS/01/2021 / Preparation of ESIA and Component 3. Innovation, Consultant Under Management Plans for the TF / A9474 Capacity Building, and Post Qualification Open - National 300,000.00 0.00 2021-02-26 2021-05-26 2021-03-12 2021-06-16 2021-04-09 2021-05-09 2021-06-13 2021-12-10 Implementation Rehabilitation of Mined-Out Communications Selection Sites Component 2. Pilot MLNR/ENFAL/CS/02/2020 / Investments for Improved Consultant Prepare Management Plans for TF / 18842 Forest and Landscape Post Qualification Open - National 40,000.00 0.00 Canceled 2020-04-04 2020-04-18 2020-05-23 2020-06-13 2020-07-18 2020-10-16 the five (5) established Management with Selection CREMAs Communities INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ENFAL/MLNR/CS/36 / Review the three Safeguards Instruments currently being used under the ENFAL Project Component 1. Policy Reforms to cover the new areas Pending TF / 18842 and Institutional Post Direct Selection Direct 62,000.00 0.00 2017-12-19 2017-12-21 2017-12-28 2018-02-26 targeted under the Additional Implementation Strengthening Financing (RDDMFL) and also improve the current instruments with lessons learned from the Project. Component 2. Pilot MLNR/ENFAL/CS/4/19 / Investments for Improved Individual Identification of suitable lands TF / 18842 Forest and Landscape Post Consultant Open 10,000.00 0.00 Canceled 2019-05-07 2019-06-09 2019-06-16 2019-07-14 2019-10-12 for commercial plantation Management with Selection establishment Communities ENFAL/CS/9/19 / Component 4. Project Individual Development of Credit Line TF / 18842 Management, Monitoring, Post Consultant Limited 8,000.00 9,224.98 Completed 2019-07-15 2019-09-02 2019-07-20 2019-10-08 2019-08-10 2019-10-14 2019-09-14 2019-10-18 2020-03-12 2020-08-20 Operating Manual (CLOM) for and Coordination Selection the ENFAL Project ENFAL/MLNR/CS/41 / Carbon Assessment report detailing carbon enhancement, and Component 3. Innovation, Individual avoided emission or otherwise TF / 18842 Capacity Building, and Post Consultant Open 70,000.00 0.00 Canceled 2018-03-23 2018-05-11 2018-06-01 2018-07-06 2019-01-02 in the GFIP areas, procedures Communications Selection for replication and capacity needs report, final carbon accounting report MLNR/ENFAL/CS/5/19 / Component 2. Pilot Development of Investments for Improved Individual proposal/blueprint for TF / 18842 Forest and Landscape Post Consultant Open 30,000.00 0.00 Canceled 2019-05-02 2019-06-04 2019-06-18 2019-07-09 2019-10-07 establishment of specialised Management with Selection clearinghouse Communities Component 2. Pilot MLNR/ENFAL/CS/IDV/01/202 Investments for Improved Individual Under 0 / Recruitment of TF / A9512 Forest and Landscape Prior Consultant Limited 15,000.00 0.00 2020-09-04 2020-10-16 2020-09-09 2020-10-23 2020-09-30 2021-02-11 2020-11-04 2021-10-30 Implementation Coordinator for the CFI Management with Selection Communities MLNR/ENFAL/CS/INDV/02/20 Component 4. Project 20 / Recruitment of TF / A9512 Management, Monitoring, Prior Direct Selection Direct 15,000.00 43,200.00 Signed 2020-12-18 2020-12-18 2020-12-28 2021-01-15 2021-03-03 2021-01-26 2021-08-30 Procurement Officer and Coordination Page 3 ENFAL/CS/DC/01/2020 / Component 4. Project Recruitment of Project TF / A9512 Management, Monitoring, Prior Direct Selection Direct 36,000.00 108,000.00 Signed 2020-12-18 2020-12-18 2020-12-28 2021-01-15 2021-03-03 2021-01-26 2021-08-30 Coordinator and Coordination ENFAL/CS/DC/02/2020 / Component 4. Project Recruitment of Project TF / A9512 Management, Monitoring, Prior Direct Selection Direct 30,000.00 90,000.00 Signed 2020-11-30 2020-12-18 2020-12-10 2021-01-15 2021-02-13 2021-01-26 2021-08-12 Manager and Coordination Page 4