Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 2021-02-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 N Executing Agency(ies): ational Unit for the Management of Disaster Risk WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8649-002 / Component 2. Water Supply Acueducto Tumaco, Nariño. and Basic Sanitation Solicitud de Single Stage - One 2019-06- Aduccion: suministro e IBRD / 86490 Posterior Open - National 2,973,324.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 Improvements in the ofertas Envelope 04 instalacion de 5.5 km de Municipality of Tumaco tuberia en HD de 20" (1 de 4) PTSP-BIRF8649-003 / Acueducto Tumaco, Nariño. Optimización PTAP Buchelly (incluye: construccion empate Component 2. Water Supply con la nueva aduccion de 20", and Basic Sanitation Solicitud de Single Stage - One 2019-06- construccion 4 modulos de IBRD / 86490 Posterior Open - National 1,547,966.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 Improvements in the ofertas Envelope 04 desarenacion, mejoramiento Municipality of Tumaco sistema dosificacion coagulante, construccion 4 modulos de floculacion. (2 de 4) PTSP-BIRF8649-004 / Acueducto Tumaco, Nariño. Component 2. Water Supply Red matriz continental: and Basic Sanitation Solicitud de Single Stage - One 2019-06- suministro e instalacion de IBRD / 86490 Posterior Open - National 822,003.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 Improvements in the ofertas Envelope 04 2229 metros de tuberia HD y Municipality of Tumaco suministro e instalacion de macromedidores. (3 de 4) PTSP-BIRF8649-005 / Acueducto Tumaco, Nariño. Component 2. Water Supply Suministro e instalacion de and Basic Sanitation Solicitud de Single Stage - One 2019-06- IBRD / 86490 Posterior Open - National 1,519,053.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 12331 metros de redes de Improvements in the ofertas Envelope 04 distribucion de PVC RDE 21 (4 Municipality of Tumaco de 4) PTSP-BIRF8649-055 / CONSTRUCCION DE 7.800 M DE ADUCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMPLIACION DE LA PTAP Component 2. Water Supply BUCHELLI EN 50 LPS, and Basic Sanitation Solicitud de Single Stage - One 2019-01- IBRD / 86490 Posterior Open - International 7,779,897.00 0.00 Cancelado 2017-08-25 2017-10-17 2017-08-30 2017-10-11 2018-03-14 2017-11-10 2018-06-08 2017-12-15 CONSTRUCCION DE 2.231 M Improvements in the ofertas Envelope 09 DE RED MATRIZ EN TUBERIA Municipality of Tumaco HD, CONSTRUCCION DE 15.298 M DE REDES DE DISTRIBUCION EN TUBERIA PVC-POI SEGUNDO Q PTSP-BIRF8649-045 / CONSTRUCCION DE 5.500 M DE ADUCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMPLIACION DE LA PTAP Component 2. Water Supply BUCHELLI EN 50 LPS, and Basic Sanitation Solicitud de Single Stage - One 2018-09- IBRD / 86490 Posterior Open - National 6,862,347.00 0.00 Cancelado 2017-08-25 2017-08-30 2017-10-20 2017-10-11 2017-11-10 2017-12-15 CONSTRUCCION DE 2.231 M Improvements in the ofertas Envelope 11 DE RED MATRIZ EN TUBERIA Municipality of Tumaco HD, CONSTRUCCION DE 15.298 M DE REDES DE DISTRIBUCION EN TUBERIA PVC - POI SEGUNDO QUINQ PTSP-BIRF8649-018 / “Red Component 2. Water Supply Menor de  distribución de la and Basic Sanitation Solicitud de Single Stage - One 2020-05- zona continental fase 2 en el IBRD / 86490 Posterior Open - National 1,724,138.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 Improvements in the ofertas Envelope 13 Municipio de Tumaco, Municipality of Tumaco Departamento de Nariño” PTSP-BIRF8649-017 / “Construcción segunda fase Component 2. Water Supply de 20” en tubería de hierro and Basic Sanitation Solicitud de Single Stage - One 2019-05- dúctil para aducción, IBRD / 86490 Posterior Open - National 1,436,782.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 Improvements in the ofertas Envelope 19 Municipio de San Andrés de Municipality of Tumaco Tumaco, Departamento de Nariño” PTSP-BIRF8649-014 / Component 1. Water Supply Construcción del sistema and Basic Sanitation Solicitud de Single Stage - One 2020-09- IBRD / 86490 Posterior Open - National 1,353,180.00 0.00 Cancelado 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 definitivo de disposición final Improvements in the ofertas Envelope 10 de residuos. Municipality of Guapi PTSP-BIRF8649-013 / Component 1. Water Supply Construccion del Sistema de and Basic Sanitation Solicitud de Single Stage - One 12,865,288.0 2021-07- IBRD / 86490 Posterior Open - National 0.00 Cancelado 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 Manejo de las Aguas Improvements in the ofertas Envelope 0 31 Residuales Casco Urbano Municipality of Guapi PTSP-BIRF8649-019 / Component 2. Water Supply Construcción nuevo relleno and Basic Sanitation Solicitud de Single Stage - One 2019-04- IBRD / 86490 Posterior Open - National 4,281,100.00 0.00 Cancelado 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 sanitario del municipio de Improvements in the ofertas Envelope 19 Tumaco Municipality of Tumaco PTSP-BIRF8649-074 / "OBRAS DE OPTIMIZACION Y AMPLIACION DEL SISTEMA DE ACUEDUCTO DEL Component 2. Water Supply DISTRITO ESPECIAL DE and Basic Sanitation Solicitud de Single Stage - One 13,263,597.0 9,353,680.1 2020-11- IBRD / 86490 Posterior Open - National Firmado 2019-03-04 2019-03-07 2019-03-06 2019-04-03 2019-04-26 2019-05-03 2019-05-24 2019-06-07 2019-09-13 TUMACO FASE II, Improvements in the ofertas Envelope 0 6 28 COMPONENTES PARA EL Municipality of Tumaco ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". Page 1 PTSP-BIRF8649-076 / "OBRAS DE OPTIMIZACION Y Component 2. Water Supply AMPLIACION DEL SISTEMA DE and Basic Sanitation Solicitud de Single Stage - One 5,357,696.2 2020-07- ACUEDUCTO DEL DISTRITO IBRD / 86490 Posterior Open - National 7,700,000.00 Firmado 2019-04-30 2019-06-07 2019-05-05 2019-06-04 2019-07-15 2019-06-29 2019-10-21 2019-08-03 2019-12-17 Improvements in the ofertas Envelope 6 28 ESPECIAL DE TUMACO FASE I, Municipality of Tumaco DEPARTAMENTO DE NARIÑO, COLOMBIA" PTSP-BIRF8649-064 / Construcción de 7.800 m de aducción tubería hd 20", optimización y ampliación Component 2. Water Supply PTAP Buchelli 50 lps, and Basic Sanitation Solicitud de Single Stage - One 2020-04- construcción de 2.231 m red IBRD / 86490 Posterior Open - National 7,733,591.00 0.00 Cancelado 2018-12-28 2019-01-02 2019-01-02 2019-02-13 2019-02-26 2019-03-15 2019-03-15 2019-04-19 Improvements in the ofertas Envelope 13 matriz tubería hd, Municipality of Tumaco construccion de 15.298 m redes de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco PTSP-BIRF8649-083 / “OPTIMIZACION Y Component 1. Water Supply AMPLIACION DEL SISTEMA DE and Basic Sanitation Solicitud de Single Stage - One 3,118,398.3 2021-04- ACUEDUCTO DE LA CABECERA IBRD / 86490 Posterior Open - National 4,500,000.00 En ejecución 2019-07-10 2019-08-30 2019-07-12 2019-10-01 2019-08-09 2019-10-28 2019-09-08 2020-03-27 2019-10-13 Improvements in the ofertas Envelope 0 05 MUNICIPAL DE GUAPI, Municipality of Guapi DEPARTAMENTO DEL CAUCA, COLOMBIA – ETAPA I” PTSP-BIRF8649-100 / OBRAS DE OPTIMIZACIÓN Y Component 2. Water Supply AMPLIACIÓN DEL SISTEMA DE and Basic Sanitation Solicitud de Single Stage - One 2020-10- ACUEDUCTO DEL DISTRITO IBRD / 86490 Posterior Open - National 1,262,000.00 0.00 En ejecución 2020-01-10 2020-01-17 2020-01-15 2020-02-14 2020-03-04 2020-03-10 2020-04-07 2020-04-14 Improvements in the ofertas Envelope 13 ESPECIAL DE TUMACO, Municipality of Tumaco DEPARTAMENTO DE NARIÑO, COLOMBIA - FASE III ETAPA I GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-092 / Adquisición de un (1) Vehículo Component 2. Water Supply Compactador Para La and Basic Sanitation Solicitud de Single Stage - One Prestación Del Servicio Público IBRD / 86490 Posterior Open - National 154,000.00 102,817.39 En ejecución 2019-10-28 2019-11-29 2019-11-06 2019-12-18 2020-01-21 2020-01-17 2020-03-30 2020-02-21 2020-08-19 Improvements in the ofertas Envelope De Aseo En El Distrito De San Municipality of Tumaco Andrés De Tumaco Departamento de Nariño PTSP-BIRF8649-094 / Component 3. Capacity CARACTERIZACIÓN DE AGUA Building and Institutional CRUDA Y MEDICIÓN DE NIVEL Strengthening of Service Solicitud de Single Stage - One ESTATICO EN LOS POZOS IBRD / 86490 Posterior Open - National 13,800.00 0.00 En ejecución 2019-11-02 2019-12-28 2020-06-25 Providers in the cotizaciones Envelope Ccgua-01 - Ccgua-02, Municipalities of Guapi and MUNICIPIO GUAPI, Tum aco DEPARTAMENTO CAUCA PTSP-BIRF8649-095 / SONDA Component 3. Capacity DE NIVEL PARA MEDICIÓN DE Building and Institutional NIVEL ESTATICO EN LOS Strengthening of Service Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 5,200.00 0.00 En ejecución 2019-11-02 2019-12-28 2020-06-25 POZOS Ccgua-01 - Ccgua-02, Providers in the cotizaciones Envelope MUNICIPIO GUAPI, Municipalities of Guapi and DEPARTAMENTO CAUCA Tum aco Component 3. Capacity Building and Institutional PTSP-BIRF8649-118 / Strengthening of Service Solicitud de Single Stage - One Adquirir motobombas y IBRD / 86490 Posterior Open - National 81,226.00 44,630.67 En ejecución 2020-07-13 2020-09-07 2020-10-07 Providers in the cotizaciones Envelope accesorios hidráulicos Municipalities of Guapi and Tum aco Component 3. Capacity Building and Institutional PTSP-BIRF8649-119 / Strengthening of Service Solicitud de Single Stage - One Adquirir tanques para IBRD / 86490 Posterior Open - National 90,263.00 140,822.49 Firmado 2020-07-13 2020-09-07 2020-12-09 2020-10-07 Providers in the cotizaciones Envelope almacenamiento de agua Municipalities of Guapi and Tum aco Component 3. Capacity Building and Institutional PTSP-BIRF8649-120 / Strengthening of Service Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 16,197.00 17,599.95 Firmado 2020-07-13 2020-09-07 2020-11-05 2020-10-22 Adquirir moto cargueros Providers in the cotizaciones Envelope Municipalities of Guapi and Tum aco Component 3. Capacity Building and Institutional PTSP-BIRF8649-121 / Strengthening of Service Solicitud de Single Stage - One Adquirir filtros purificadores IBRD / 86490 Posterior Open - National 12,009.00 56,225.83 Firmado 2020-07-13 2020-09-07 2020-11-11 2020-10-22 Providers in the cotizaciones Envelope de agua Municipalities of Guapi and Tum aco Component 3. Capacity Building and Institutional PTSP-BIRF8649-122 / Strengthening of Service Solicitud de Single Stage - One Adquirir estructuras de IBRD / 86490 Posterior Open - National 38,541.00 44,630.67 Firmado 2020-07-13 2020-09-07 2020-11-19 2020-10-07 Providers in the cotizaciones Envelope soporte metálicas Municipalities of Guapi and Tum aco NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-053 / and Basic Sanitation Solicitud de Single Stage - One Programa de monitoreo de IBRD / 86490 Posterior Limited 17,242.00 0.00 Cancelado 2017-12-27 2018-02-21 2018-05-22 Improvements in the cotizaciones Envelope aguas sub-superficiales Municipality of Guapi Page 2 PTSP-BIRF8649-078 / ADQUISICIÓN EN MODALIDAD DE ARRENDAMIENTO DE UN Component 3. Capacity SOFTWARE INTEGRAL QUE Building and Institutional PERMITA A AGUAS DE Strengthening of Service Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 86,210.00 0.00 Cancelado 2019-11-18 2020-01-16 2020-10-30 TUMACO SA ESP, EJECUTAR EN Providers in the cotizaciones Envelope FORMA EFICIENTE EL Municipalities of Guapi and CONTROL DE LOS PROCESOS Tum aco COMERCIALES, CONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / and Basic Sanitation Selección basada Consultoría Restauración IBRD / 86490 Posterior Open - National 112,024.00 101,622.79 Firmado 2017-07-01 2017-10-02 2017-07-22 2017-10-02 2017-09-04 2017-11-07 2017-10-02 2018-01-19 2017-11-01 2018-02-07 2017-12-06 2018-02-15 2018-01-10 2018-02-23 2018-08-08 Improvements in the en calidad y costo Urbana Municipality of Guapi Component 3. Capacity PTSP-BIRF8649-021 / Building and Institutional Selección basada Asistencia fortalecimiento Strengthening of Service IBRD / 86490 Posterior en calificaciones Open - National 235,000.00 78,605.00 Firmado 2018-06-01 2018-05-17 2018-06-22 2018-08-05 2018-08-31 2018-09-04 2018-12-03 2018-10-09 2018-12-03 2020-09-28 institucional Aguas de Providers in the de consultores Tumaco en el area urbana Municipalities of Guapi and Tum aco Component 4. Project PTSP-BIRF8649-043 / Management and Selección basada IBRD / 86490 Posterior Open - National 450,000.00 0.00 Cancelado 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 Auditoria Externa Environmental and Social en calidad y costo Management PTSP-BIRF8649-001 / Interventoría integral para Component 2. Water Supply obras de acueducto, and Basic Sanitation Selección basada IBRD / 86490 Previa Open - International 6,266,775.00 0.00 Cancelado 2016-12-14 2017-01-28 2016-12-16 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 alcantarillado y residuos Improvements in the en calidad y costo sólidos en el Municipio de Municipality of Tumaco Tumaco. PTSP-BIRF8649-049 / Interventoria integral para Component 2. Water Supply obras de acueducto y and Basic Sanitation Selección basada IBRD / 86490 Previa Open - International 5,762,334.24 4,364,033.42 Firmado 2017-12-20 2017-12-21 2018-01-12 2017-12-21 2018-02-25 2018-05-28 2018-03-25 2018-09-11 2018-04-24 2019-03-27 2018-05-29 2019-08-10 2018-07-03 2019-09-13 2022-07-02 alcantarillado y residuos Improvements in the en calidad y costo sòlidos en el Municipio de Municipality of Tumaco Tumaco PTSP-BIRF8649-062 / REALIZAR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAMIENTO AGUAS Component 1. Water Supply RESIDUALES DEL MUNICIPIO and Basic Sanitation Selección basada IBRD / 86490 Posterior Open - National 259,310.00 0.00 Cancelado 2018-06-15 2018-09-04 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 DE GUAPI, DEPARTAMENTO Improvements in the en calidad y costo DEL CAUCA, EN EL MARCO Municipality of Guapi DEL FONDO PARA EL DESARROLLO DEL PLAN TODOS SOMOS PAZCÍFICO Component 3. Capacity PTSP-BIRF8649-041 / Building and Institutional Asistencia fortalecimiento Selección basada Strengthening of Service institucional Aguas de IBRD / 86490 Posterior en calificaciones Open - National 235,000.00 0.00 Cancelado 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 Providers in the Tumaco (para el piloto de la de consultores Municipalities of Guapi and politica en el area rural) Tum aco PTSP-BIRF8649-022 / Component 4. Project Implementacion del Plan de Management and Selección basada IBRD / 86490 Posterior Open - National 400,000.00 0.00 Cancelado 2017-11-01 2018-09-13 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 Informacion, Comunicacion y Environmental and Social en el menor costo Participacion Management PTSP-BIRF8649-016 / Component 1. Water Supply Interventoria Obras and Basic Sanitation Selección basada Alcantarillado, Acueducto y IBRD / 86490 Previa Open - National 2,333,451.00 0.00 Cancelado 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 Improvements in the en calidad y costo Residuos Solidos en Municipio Municipality of Guapi de Guapi PTSP-BIRF8649-082 / Interventoría técnica, administrativa, financiera, Component 1. Water Supply legal, ambiental y social para and Basic Sanitation Selección basada los estudios, diseños y obras IBRD / 86490 Previa Open - International 2,900,000.00 0.00 En ejecución 2019-07-10 2019-07-17 2019-08-02 2019-08-12 2019-09-15 2020-02-17 2019-10-13 2020-05-21 2019-11-12 2020-07-22 2019-12-17 2020-09-29 2020-01-21 2024-01-20 Improvements in the en calidad y costo de los sistemas de acueducto Municipality of Guapi y alcantarillado y proyectos de residuos sólidos del municipio de Guapi. PTSP-BIRF8649-096 / ACOMPAÑAR A EMGUAPI Component 3. Capacity S.A.S. ESP EN LA OPERACIÓN Building and Institutional DE LOS SERVICIOS PÚBLICOS Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 662,000.00 0.00 En ejecución 2019-10-31 2020-05-28 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2021-04-06 DE ACUEDUCTO, Providers in the en calidad y costo ALCANTARILLADO Y ASEO Y Municipalities of Guapi and ESTRUCTURACIÓN DEL Tum aco SERVICIO PUBICOS DE ASEO. PTSP-BIRF8649-097 / Desarrollar la Interventoría técnica, operativa, Component 3. Capacity administrativa, comercial, Building and Institutional financiera, contable, Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 215,000.00 0.00 En ejecución 2019-10-31 2020-01-28 2019-11-21 2020-01-04 2020-02-01 2020-03-02 2020-04-06 2020-05-11 2021-05-11 ambiental, social y jurídica al Providers in the en calidad y costo proyecto de acompañamiento Municipalities of Guapi and a la empresa E guapi S.A. ESP. Tum aco En el municipio de Guapi – Cauca. Page 3 PTSP-BIRF8649-077 / INTERVENTORÍA TÉCNICA, ADMINISTRATIVA, FINANCIERA, CONTABLE, Component 3. Capacity AMBIENTAL, SOCIAL Y Building and Institutional JURÍDICA PARA LA Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 211,800.00 0.00 Cancelado 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 "CONSULTORÍA DE Providers in the en calidad y costo ACOMPAÑAMIENTO EN LA Municipalities of Guapi and OPERACIÓN DE LOS SERVICIOS Tum aco PÚBLICOS DE ACUEDUCTO, ALCANTARILLADO Y ASEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTALECIMIENTO Y Component 3. Capacity ACOMPAÑAMIENTO EN LA Building and Institutional OPERACIÓN DE LOS SERVICIOS Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 1,380,000.00 0.00 Cancelado 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 PÚBLICOS DE ACUEDUCTO, Providers in the en calidad y costo ALCANTARILLADO Y ASEO DEL Municipalities of Guapi and OPERADOR DE GUAPI - FASE I, Tum aco II Y III PTSP-BIRF8649-056 / Consultoría de Diseño de la Component 1. Water Supply Planta de Tratamiento de and Basic Sanitation Selección basada IBRD / 86490 Posterior Open - National 141,300.00 0.00 Cancelado 2018-05-02 2019-09-27 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 Aguas de Residuales para el Improvements in the en calidad y costo Sistema de Alcantarillado del Municipality of Guapi Municipio de Guapi Component 3. Capacity PTSP-BIRF8649-020 / Building and Institutional Aseguramiento en la Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 1,800,000.00 0.00 Cancelado 2018-06-01 2019-09-27 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 prestación de los servicios Providers in the en calidad y costo públicos Guapi. Municipalities of Guapi and Tum aco PTSP-BIRF8649-112 / Auditoría a los Estados Component 4. Project Financieros de Propósito Management and Selección basada IBRD / 86490 Posterior Open - National 31,050.00 0.00 Cancelado 2020-05-15 2020-05-14 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-04-23 Especial de Proyectos Environmental and Social en el menor costo Financiados por el Banco Management Mundial a través de préstamos INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el Departamento del Cauca en la Component 4. Project implementaciòn y ejecuciòn Management and IBRD / 86490 Posterior Individual Open 21,450.78 16,386.55 Finalizado 2017-05-11 2017-08-16 2017-06-05 2017-06-15 2017-09-06 2017-07-05 2017-09-18 2018-07-05 2018-09-17 del FDPTSP que adelanta Environmental and Social como entidad ejecutora la Management Unidad Nacional para la Gestiòn del Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la implementación y ejecución Component 4. Project del Fondo para el Desarrollo Management and del Plan Todos Somos IBRD / 86490 Posterior Individual Open 82,299.37 62,869.64 Finalizado 2017-05-11 2017-08-28 2017-06-11 2017-06-21 2017-09-18 2018-07-01 2017-09-18 2018-12-28 2018-09-18 Environmental and Social Pazcífico que adelanta como Management entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta como entidad ejecutora la Unidad Nacional para la Component 4. Project Gestión del Riesgo de Management and Desastres, en la viabilización IBRD / 86490 Posterior Individual Open 48,873.76 36,452.16 Firmado 2017-06-01 2017-05-22 2017-06-16 2017-07-01 2017-06-19 2017-07-21 2017-06-27 2018-07-21 Environmental and Social de proyectos del componente Management de Agua y Saneamiento Básico, ante el Ministerio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordinación de las acciones y Component 4. Project actividades al interior del Management and MVCT relacionadas con el IBRD / 86490 Posterior Individual Open 56,033.61 40,456.30 Firmado 2017-06-01 2018-04-18 2017-06-16 2017-06-21 2018-05-03 2017-07-02 2018-05-18 2018-07-02 Environmental and Social crédito para dar respuesta a Management los requerimientos de la Banca Multilateral y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el Departamento de Nariño en la implementación y ejecución Component 4. Project del Fondo para el Desarrollo Management and IBRD / 86490 Posterior Individual Open 21,450.78 1,660.60 Firmado 2017-05-18 2017-08-22 2017-06-11 2017-06-26 2017-09-12 2017-07-16 2018-04-03 2018-07-16 del Plan Todos Somos Environmental and Social Pazcífico que adelanta como Management entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-024 / Apoyo Management and IBRD / 86490 Posterior Individual Open 17,908.97 12,960.77 Finalizado 2017-05-16 2017-03-22 2017-07-04 2017-07-25 2017-05-19 2017-08-29 2017-05-19 2018-02-25 2018-05-18 Administrativo (nivel técnico) Environmental and Social Management Component 4. Project PTSP-BIRF8649-028 / Lider Management and IBRD / 86490 Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-03-01 2017-03-11 2017-04-01 2017-03-06 2017-05-06 2017-03-16 2017-11-02 2018-03-15 de Adquisiciones Environmental and Social Management Component 4. Project PTSP-BIRF8649-029 / Management and IBRD / 86490 Posterior Individual Open 70,938.36 48,197.86 Finalizado 2017-04-01 2017-03-20 2017-05-20 2017-03-22 2017-06-10 2017-04-03 2017-07-15 2017-04-04 2018-01-11 2018-04-03 Especialista Adquisiciones Environmental and Social Management Page 4 Component 4. Project PTSP-BIRF8649-033 / Lider Management and IBRD / 86490 Posterior Individual Direct 93,771.65 61,167.00 Firmado 2017-04-01 2017-03-22 2017-04-11 2017-03-24 2017-05-02 2017-03-28 2017-06-06 2017-04-04 2017-12-03 Ambiental Environmental and Social Management Component 4. Project PTSP-BIRF8649-034 / Management and IBRD / 86490 Posterior Individual Open 56,458.32 36,452.16 Finalizado 2017-06-01 2017-08-01 2017-07-20 2017-08-08 2017-08-10 2017-08-15 2017-09-14 2017-04-04 2018-03-13 2018-04-03 Especialista ambiental Environmental and Social Management Component 4. Project PTSP-BIRF8649-035 / Lider Management and IBRD / 86490 Posterior Individual Direct 99,507.79 61,167.00 Firmado 2017-03-01 2017-03-02 2017-03-11 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 Componente Agua Environmental and Social Management Component 4. Project PTSP-BIRF8649-036 / Management and IBRD / 86490 Posterior Individual Direct 63,844.53 41,645.62 Firmado 2017-04-01 2017-03-17 2017-04-11 2017-05-02 2017-03-22 2017-06-06 2018-04-05 2017-12-03 Especialista Proyectos Agua Environmental and Social Management Component 4. Project PTSP-BIRF8649-037 / Management and IBRD / 86490 Posterior Individual Open 56,033.61 36,452.16 Firmado 2017-06-01 2017-11-01 2017-07-20 2017-08-10 2017-11-20 2017-09-14 2017-11-20 2018-03-13 Especialista Proyectos RSU Environmental and Social Management Component 4. Project PTSP-BIRF8649-038 / Management and Ingeniero de apoyo (Agua IBRD / 86490 Posterior Individual Open 35,053.71 16,386.55 Finalizado 2017-06-01 2017-07-19 2017-07-20 2017-08-10 2017-08-15 2017-09-14 2017-08-31 2018-03-13 2018-08-30 Environmental and Social Tumaco) Management Component 4. Project PTSP-BIRF8649-039 / Management and Ingeniero de apoyo ( Agua IBRD / 86490 Posterior Individual Open 35,053.71 19,500.00 Finalizado 2017-06-01 2017-12-12 2017-07-20 2017-08-10 2018-01-03 2017-09-14 2017-09-25 2018-03-13 2018-09-24 Environmental and Social Guapi) Management Component 4. Project PTSP-BIRF8649-040 / Apoyo Management and IBRD / 86490 Posterior Individual Open 16,742.07 12,960.77 Finalizado 2017-06-01 2017-06-28 2017-07-20 2017-09-12 2017-08-10 2017-09-18 2017-09-14 2017-09-22 2018-03-13 2018-09-21 Administrativo (lideres) Environmental and Social Management Component 4. Project PTSP-BIRF8649-023 / Management and Coordinación General - LUZ IBRD / 86490 Posterior Individual Direct 116,664.30 71,591.30 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-10 2017-05-06 2017-03-16 2017-11-02 Environmental and Social AMANDA PULIDO Management PTSP-BIRF8649-026 / Lider Component 4. Project Financiero - CLAUDIA Management and IBRD / 86490 Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-02-15 2017-03-11 2017-04-01 2017-03-08 2017-05-06 2017-03-16 2017-11-02 2018-03-15 AGUDELO SEDANO - Por Environmental and Social continuidad de Servicios Management PTSP-BIRF8649-031 / Lider Component 4. Project de Planeación y Seguimiento - Management and IBRD / 86490 Posterior Individual Direct 99,507.79 61,063.18 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-10 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 JUAN DE DIOS CISNEROS - - Environmental and Social Por continuidad de Servicios Management PTSP-BIRF8649-032 / Component 4. Project Especialista Planeación y Management and Seguimiento - JULIAN ANDRES IBRD / 86490 Posterior Individual Direct 67,749.98 41,574.93 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-22 2017-05-06 2017-03-31 2017-11-02 Environmental and Social VALBUENA - Por continuidad Management de Servicios PTSP-BIRF8649-025 / Component 4. Project Asistente Financiero y Management and Administrativo - BEATRIZ IBRD / 86490 Posterior Individual Direct 37,173.93 0.00 Cancelado 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 Environmental and Social PARRA - Continuidad de Management Servicios Component 4. Project PTSP-BIRF8649-048 / Tulio Management and fuentes Especialista en IBRD / 86490 Posterior Individual Direct 49,242.00 46,194.37 Firmado 2017-11-02 2017-10-23 2017-11-07 2017-10-12 2017-11-08 2017-10-20 2017-11-10 2017-11-10 2018-11-09 Environmental and Social Adquisiciones 2 Management Component 4. Project PTSP-BIRF8649-046 / Management and IBRD / 86490 Posterior Individual Open 49,242.00 0.00 Cancelado 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 Especialista Adquisiciones 2 Environmental and Social Management Component 3. Capacity Building and Institutional PTSP-BIRF8649-044 / Strengthening of Service Especialista Fortalecimiento IBRD / 86490 Posterior Individual Open 49,242.00 47,560.97 Firmado 2017-08-18 2017-10-12 2017-09-01 2017-11-10 2017-09-03 2017-12-20 2017-09-17 2017-12-28 2018-09-12 Providers in the Institucional Municipalities of Guapi and Tum aco PTSP-BIRF8649-51 / IEH GRUCON-Realizar los estudios y diseños de los proyectos priorizados para la Component 2. Water Supply optimización y ampliación del and Basic Sanitation Selección directa sistema de acueducto del IBRD / 86490 Posterior Direct 792,345.00 708,875.23 Firmado 2017-12-18 2018-02-20 2017-12-31 2018-02-21 2018-01-15 2018-02-23 2019-01-10 Improvements in the de consultores municipio de Tumaco, Municipality of Tumaco departamento de Nariño, en el marco del Fondo para el Desarrollo del Plan Todos Somos PAZcífico Component 4. Project PTSP-BIRF8649-054 / KPMG- Management and Selección directa IBRD / 86490 Posterior Direct 35,000.00 69,291.56 Firmado 2017-12-29 2018-04-04 2018-01-08 2018-04-05 2018-03-14 2018-04-13 2018-09-10 AUDITORIA EXTERNA Environmental and Social de consultores Management Component 1. Water Supply PTSP-BIRF8649-057 / and Basic Sanitation Antonio Nieto - Director de IBRD / 86490 Posterior Individual Direct 26,897.00 25,232.22 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-15 2018-11-03 Improvements in the Interventorìa Municipality of Guapi Component 1. Water Supply PTSP-BIRF8649-058 / Ramiro and Basic Sanitation Gutierrez. Especialista Electro- IBRD / 86490 Posterior Individual Direct 6,771.00 6,351.73 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 Improvements in the mecànico de Interventorìa Municipality of Guapi Page 5 Component 1. Water Supply PTSP-BIRF8649-060 / Alvaro and Basic Sanitation Bravo - Especialista IBRD / 86490 Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 Improvements in the Geotecnista de Interventorìa Municipality of Guapi Component 1. Water Supply PTSP-BIRF8649-059 / and Basic Sanitation Eduardo Gòmez - Especialista IBRD / 86490 Posterior Individual Direct 9,233.00 0.00 Cancelado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 Improvements in the Estructural de Interventorìa Municipality of Guapi PTSP-BIRF8649-061 / Component 1. Water Supply FERNANDO VARGAS and Basic Sanitation IBRD / 86490 Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-05-07 2018-05-04 2018-05-08 2018-05-11 2018-05-13 2018-06-08 2018-06-12 2018-06-08 2018-12-09 RODRÍGUEZ. Especialista Improvements in the Estructural de Interventoria. Municipality of Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el Departamento del Chocò, en Component 4. Project la implementaciòn y ejecuciòn Management and IBRD / 86490 Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-08-22 2017-05-02 2017-05-12 2017-09-12 2017-06-01 2018-06-01 del FDPTSP que adelanta Environmental and Social como entidad ejecutora la Management Unidad Nacional para la Gestiòn del Riesgo de Desastres. PTSP-BIRF8649-012 / Apoyar el componente social, en el Departamento del Valle en la Component 4. Project implementaciòn y ejecuciòn Management and IBRD / 86490 Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 del FDPTSP que adelanta Environmental and Social como entidad ejecutora la Management Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-030 / Apoyo Management and IBRD / 86490 Posterior Individual Open 26,159.48 0.00 Cancelado 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones Environmental and Social Management Component 4. Project PTSP-BIRF8649-042 / Management and Asistente Financiero y IBRD / 86490 Posterior Individual Open 37,173.93 0.00 Cancelado 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 Environmental and Social Administrativo Management CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la gestión predial y catastral de los bienes inmuebles que Component 1. Water Supply sean necesarios para la and Basic Sanitation viabilización de los proyectos IBRD / 86490 Posterior Individual Open 7,763.00 7,763.00 Firmado 2018-11-30 2018-11-28 2019-01-18 2019-02-08 2019-02-05 2019-03-15 2019-02-05 2019-09-11 Improvements in the que se ejecutan en el marco Municipality of Guapi del Fondo para el Desarrollo del Plan Todos Somos Pazcífico, que adelanta como entidad PTSP-BIRF8649-063 / Liderar el componente de Agua y Saneamiento Básico, en la implementación y ejecución Component 4. Project del Fondo para el Desarrollo Management and IBRD / 86490 Posterior Individual Open 34,200.00 34,200.00 Firmado 2018-12-26 2019-02-18 2019-02-13 2019-03-06 2019-04-04 2019-04-10 2019-04-08 2019-10-07 del Plan Todos Somos Environmental and Social Pazcífico que adelanta como Management entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-072 / Management and Especialista de Adquisiciones IBRD / 86490 Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 Environmental and Social - Recontratación Pilar Valero Management PTSP-BIRF8649-073 / Component 4. Project Especialista de Adquisiciones Management and IBRD / 86490 Posterior Individual Direct 53,560.00 53,560.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-15 2019-03-15 2020-03-09 - Recontratación Tulio Environmental and Social Fuentes Management PTSP-BIRF8649-075 / Component 4. Project Especialista Financiera - Management and IBRD / 86490 Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 Recontratación Sandra Lorena Environmental and Social Peña Management PTSP-BIRF8649-069 / Líder Component 4. Project de Adquisiciones - Management and IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2020-03-12 Recontratación Elkin Adolfo Environmental and Social Pinilla Cañón Management PTSP-BIRF8649-065 / Component 4. Project Directora Ejecutiva / Management and Coordinadora del Proyecto IBRD / 86490 Posterior Individual Direct 83,000.00 41,500.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 Environmental and Social FTSP - Recontratación Luz Management Amanda Pulido Component 4. Project PTSP-BIRF8649-067 / Líder Management and Ambiental - Recontratación IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 Environmental and Social Alejandra Catacoli Management Component 4. Project PTSP-BIRF8649-068 / Líder Management and Financiera - Recontratación IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-02-25 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 Environmental and Social Claudia Agudelo Management Component 4. Project PTSP-BIRF8649-066 / Líder Management and de Planeación y Seguimiento - IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-15 2020-03-12 Environmental and Social Luis Ignacio Alfonso Management Component 4. Project PTSP-BIRF8649-070 / Líder Management and Social - Recontratación Kelly IBRD / 86490 Posterior Individual Direct 23,600.00 11,800.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2019-07-17 Environmental and Social Ruiz Management Page 6 PTSP-BIRF8649-080 / Component 4. Project Especialista Social para la Management and Evaluación Social de los IBRD / 86490 Posterior Individual Open 13,140.00 0.00 Cancelado 2019-04-12 2019-07-16 2019-04-29 2019-05-10 2019-05-20 2019-07-30 Environmental and Social municipios de Tumaco Management (Nariño) y Guapi (Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a la Interventoría Integral de los contratos de Estudios y Component 1. Water Supply Diseños como interventor en and Basic Sanitation IBRD / 86490 Posterior Individual Open 16,000.00 9,050.40 Firmado 2019-07-10 2019-06-21 2019-08-28 2019-09-27 2019-09-18 2019-09-25 2019-10-23 2019-10-01 2020-04-20 los aspectos eléctricos y Improvements in the mecánicos de los proyectos Municipality of Guapi de preinversión priorizados en el componente de Agua y Saneamiento Básico. PTSP-BIRF8649-081 / Dirección de Interventoría Integral de Estudios y Diseños Component 1. Water Supply de los proyectos de and Basic Sanitation IBRD / 86490 Posterior Individual Open 27,000.00 12,926.59 Firmado 2019-06-25 2019-07-26 2019-08-13 2019-09-10 2019-09-03 2019-10-01 2019-10-08 2019-10-11 2020-04-05 preinversión priorizados en el Improvements in the componente de Agua y Municipality of Guapi Saneamiento Básico en el marco del préstamo BIRF. Component 4. Project PTSP-BIRF8649-085 / Líder Management and IBRD / 86490 Posterior Individual Open 20,000.00 25,517.85 Firmado 2019-06-21 2019-07-29 2019-08-09 2019-09-24 2019-08-30 2019-09-02 2019-10-04 2019-09-06 2020-04-01 de Seguridad FTSP Environmental and Social Management Component 4. Project PTSP-BIRF8649-086 / Líder Management and Social - Recontratación Kelly IBRD / 86490 Posterior Individual Direct 47,200.00 39,330.50 Firmado 2019-07-11 2019-07-15 2019-07-12 2019-07-23 2019-07-12 2019-08-22 2019-07-18 2019-08-23 2020-03-17 Environmental and Social Ruiz Management PTSP-BIRF8649-089 / Topografo - Prestación de servicios profesionales para la realización de levantamientos Component 1. Water Supply topográficos requeridos para and Basic Sanitation IBRD / 86490 Posterior Individual Open 13,800.00 9,943.53 Firmado 2019-08-26 2019-08-22 2019-10-14 2019-09-19 2019-11-04 2019-10-18 2019-12-09 2019-10-23 2020-03-08 el saneamiento de los predios Improvements in the requeridos para la ejecución Municipality of Guapi de los proyectos del Fondo para el Desarrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-090 / Catastral - Brindar apoyo técnico catastral y de avalúos en la gestión predial de los Component 1. Water Supply bienes inmuebles que sean and Basic Sanitation necesarios para la IBRD / 86490 Posterior Individual Open 27,600.00 8,438.74 Firmado 2019-08-26 2019-08-30 2019-10-14 2019-10-01 2019-11-04 2019-10-25 2019-12-09 2019-11-05 2020-06-08 Improvements in the viabilización de los proyectos Municipality of Guapi que se ejecutan en el marco del Fondo para el Desarrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones jurídicas y administrativas que Component 1. Water Supply se requiera adelantar dentro and Basic Sanitation del proceso de saneamiento, IBRD / 86490 Posterior Individual Open 16,000.00 12,098.26 Firmado 2019-08-26 2020-04-08 2019-10-14 2020-04-10 2019-11-04 2020-04-16 2019-12-09 2020-04-23 2020-06-08 Improvements in the adquisición predial y Municipality of Guapi reasentamiento de población, a través de las modalidades de enajenación PTSP-BIRF8649-088 / Component 1. Water Supply Gestora Predial - and Basic Sanitation IBRD / 86490 Posterior Individual Direct 27,600.00 10,207.20 Firmado 2019-08-30 2019-09-02 2019-09-06 2019-12-09 2019-09-06 2020-01-31 2019-09-13 2020-01-31 2020-03-12 Recontratación NINFA LUCIA Improvements in the SANTANA ESCOBAR. Municipality of Guapi Component 4. Project PTSP-BIRF8649-027 / Management and IBRD / 86490 Posterior Individual Open 63,844.53 0.00 Cancelado 2017-04-01 2017-04-11 2017-05-20 2017-06-10 2017-07-15 2018-01-11 Especialista Financiero Environmental and Social Management Component 4. Project PTSP-BIRF8649-093 / JOHN Management and OTALVARO CORTES - IBRD / 86490 Posterior Individual Direct 18,000.00 11,102.00 Firmado 2019-11-15 2019-11-25 2019-11-22 2020-01-02 2019-11-22 2020-01-02 2019-11-26 2020-01-02 2020-05-24 Environmental and Social Especialista de Adquisiciones Management Component 4. Project PTSP-BIRF8649-099 / Líder Management and de Planeación - JOAN NATALIE IBRD / 86490 Posterior Individual Direct 17,700.00 25,806.54 Firmado 2019-11-15 2019-11-25 2019-11-22 2019-12-05 2019-11-22 2019-12-19 2019-11-26 2019-12-27 2020-05-24 Environmental and Social GARZON Management PTSP-BIRF8649-101 / Component 4. Project Directora Ejecutiva / Management and Coordinadora del Proyecto IBRD / 86490 Posterior Individual Direct 26,400.00 64,142.90 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-12 2020-03-18 2020-03-18 2021-03-17 Environmental and Social FTSP - Recontratación Luz Management Amanda Pulido Component 4. Project PTSP-BIRF8649-102 / Líder Management and Ambiental - Recontratación IBRD / 86490 Posterior Individual Direct 22,520.00 54,713.29 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-16 2020-03-18 2020-03-18 2021-03-17 Environmental and Social Alejandra Catacoli Management Component 4. Project PTSP-BIRF8649-103 / Líder Management and Financiera - Recontratación IBRD / 86490 Posterior Individual Direct 22,520.00 54,127.85 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-12 2020-03-18 2020-03-18 2021-03-17 Environmental and Social Claudia Agudelo Management PTSP-BIRF8649-104 / Líder Component 4. Project de Adquisiciones - Management and IBRD / 86490 Posterior Individual Direct 22,520.00 54,713.29 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-16 2020-03-18 2020-03-18 2021-03-17 Recontratación Elkin Adolfo Environmental and Social Pinilla Cañón Management Component 4. Project PTSP-BIRF8649-105 / Líder Management and de Seguridad FTSP - WILSON IBRD / 86490 Posterior Individual Direct 22,520.00 16,685.59 Firmado 2020-02-24 2020-03-02 2020-03-02 2020-03-04 2020-03-02 2020-03-11 2020-03-06 2020-03-20 2021-03-05 Environmental and Social LAVERDE FLÓREZ Management Page 7 PTSP-BIRF8649-106 / Component 4. Project Especialista Financiera - Management and IBRD / 86490 Posterior Individual Direct 17,050.00 41,402.62 Firmado 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-16 2020-03-18 2020-03-18 2021-03-17 Recontratación Sandra Lorena Environmental and Social Peña Management PTSP-BIRF8649-107 / Component 4. Project Especialista de Adquisiciones Management and IBRD / 86490 Posterior Individual Direct 56,800.00 41,391.10 Firmado 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-12 2020-03-16 2020-03-16 2021-03-15 - Recontratación Tulio Jose Environmental and Social Fuentes Management PTSP-BIRF8649-108 / Líder Component 4. Project Componente Agua y Management and Saneamiento Básico - IBRD / 86490 Posterior Individual Direct 37,523.00 53,829.69 Firmado 2020-03-24 2020-03-24 2020-03-28 2020-03-30 2020-04-01 2020-03-31 2020-04-07 2020-04-08 2021-04-07 Environmental and Social Recontratación FABIOLA Management IGUARAN ARAUJO PTSP-BIRF8649-110 / Liderar el componente social, en la implementación y ejecución de los proyectos de agua, Component 4. Project saneamiento y energía del Management and Fondo para el Desarrollo del IBRD / 86490 Posterior Individual Direct 22,520.00 16,685.59 Firmado 2020-04-14 2020-04-15 2020-04-15 2020-04-03 2020-04-15 2020-04-20 2020-04-23 2020-04-23 2021-04-22 Environmental and Social Plan Todos Somos PAZcífico Management financiados por la Banca Multilateral que adelanta como entidad ejecutora la Unidad PTSP-BIRF8649-087 / Component 4. Project Especialista Social para la Management and Evaluación Social de los IBRD / 86490 Posterior Individual Open 13,140.00 0.00 Cancelado 2019-08-23 2019-08-30 2019-09-09 2019-09-27 2019-09-20 2019-09-30 2019-12-29 Environmental and Social municipios de Tumaco Management (Nariño) y Guapi (Cauca) Component 4. Project PTSP-BIRF8649-098 / KPMG- Management and Selección directa IBRD / 86490 Posterior Direct 34,500.00 0.00 Cancelado 2019-11-25 2019-12-02 2019-11-30 2020-02-03 2020-08-01 AUDITORIA EXTERNA Environmental and Social de consultores Management PTSP-BIRF8649-111 / “Realizar Los Estudios Y Diseños Para La Construcción, Component 1. Water Supply Operación, Clausura Y Post and Basic Sanitation Selección directa Clausura Del Centro De IBRD / 86490 Posterior Direct 7,350.00 0.00 En ejecución 2020-05-15 2020-05-14 2020-05-20 2020-08-02 2021-01-02 Improvements in the de consultores Restauración Ambiental Municipality of Guapi Urbano – CRAU Del Municipio De Guapi, Departamento Del Cauca” PTSP-BIRF8649-113 / Especialista de Planeación y Seguimiento. - Brindar apoyo Component 4. Project profesional en la gestión de Management and planificación, monitoreo y IBRD / 86490 Posterior Individual Open 17,050.00 0.00 En ejecución 2020-05-14 2020-05-22 2020-06-03 2020-06-18 2020-08-01 2021-08-01 Environmental and Social seguimiento a las actividades Management del Fondo para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-114 / Realizar la evaluación de medio término del PROYECTO DE INFRAESTRUCTURA PARA Component 4. Project EL SUMINISTRO DE AGUA Y Management and SANEAMIENTO BÁSICO & IBRD / 86490 Posterior Individual Open 15,870.00 0.00 En ejecución 2020-05-20 2020-05-20 2020-06-14 2020-06-29 2020-07-10 2020-11-07 Environmental and Social PROVISIÓN DE SERVICIOS, en Management cumplimiento de las condiciones establecidas en el Contrato de Préstamo N° 8649-CO. PTSP-BIRF8649-115 / Liderar la planificación, gestión, monitoreo y seguimiento de las diferentes herramientas de gestión Component 4. Project establecidas para el Management and IBRD / 86490 Posterior Individual Open 22,520.00 0.00 Cancelado 2020-06-24 2020-06-22 2020-07-05 2020-07-25 2020-08-10 2021-08-10 cumplimiento de las metas y Environmental and Social objetivos del Fondo para el Management Desarrollo del Plan Todos Somos PAZcífico que adelanta como entidad ejecutora PTSP-BIRF8649-116 / Auditoría a los Estados Component 4. Project Financieros de Propósito Management and Selección directa Especial de Proyectos IBRD / 86490 Posterior Direct 31,050.00 0.00 En ejecución 2020-06-26 2020-06-22 2020-07-06 2020-07-01 2020-08-20 2020-11-18 Environmental and Social de consultores Financiados por el Banco Management Mundial a través de préstamos. PTSP-BIRF8649-117 / Liderar la planificación, gestión, monitoreo y seguimiento de las diferentes herramientas de Component 4. Project gestión establecidas para el Management and IBRD / 86490 Posterior Individual Limited 22,520.00 0.00 En ejecución 2020-06-23 2020-06-22 2020-06-28 2020-07-08 2020-07-28 2021-07-28 cumplimiento de las metas y Environmental and Social objetivos del Fondo para el Management Desarrollo del Plan Todos Somos PAZcífico que adelanta como entidad ejecutora PTSP-BIRF8649-123 / AUDITORÍA DE LOS ESTADOS FINANCIEROS DE PROPÓSITO ESPECIAL Y ASEGURAMIENTO Component 4. Project RAZONABLE SOBRE LOS Management and Selección directa IBRD / 86490 Posterior Direct 26,600.00 0.00 En ejecución 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-07 2021-07-06 PROCESOS DE ADQUISICIONES Environmental and Social de consultores DEL PROYECTO/PROGRAMA Management FINANCIADO POR EL BID Y EL BANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-124 / Líder Component 4. Project Componente Agua y Management and Ejecución Saneamiento Básico - IBRD / 86490 Posterior Individual Direct 27,500.00 0.00 2021-02-23 2021-02-27 2021-03-03 2021-04-08 2022-04-08 Environmental and Social pendiente Recontratación FABIOLA Management IGUARAN ARAUJO Page 8 PTSP-BIRF8649-125 / Component 4. Project Directora Ejecutiva / Management and Ejecución Coordinadora del Proyecto IBRD / 86490 Posterior Individual Direct 19,330.00 0.00 2021-02-24 2021-03-03 2021-03-03 2021-03-18 2022-03-18 Environmental and Social pendiente FTSP - Recontratación Luz Management Amanda Pulido PTSP-BIRF8649-126 / Líder Component 4. Project de Adquisiciones - Management and Ejecución IBRD / 86490 Posterior Individual Direct 16,500.00 0.00 2021-02-24 2021-03-03 2021-03-03 2021-03-18 2022-03-17 Recontratación Elkin Adolfo Environmental and Social pendiente Pinilla Cañón Management Component 4. Project PTSP-BIRF8649-127 / Líder Management and Ejecución Financiera - Recontratación IBRD / 86490 Posterior Individual Direct 16,500.00 0.00 2021-02-24 2021-03-03 2021-03-03 2021-03-18 2022-03-17 Environmental and Social pendiente Claudia Agudelo Management Component 4. Project PTSP-BIRF8649-128 / Líder Management and Ejecución Social - Recontratación Kelly IBRD / 86490 Posterior Individual Direct 16,500.00 0.00 2021-02-24 2021-02-25 2021-02-25 2021-04-23 2022-04-22 Environmental and Social pendiente Ruiz Management PTSP-BIRF8649-129 / Líder Component 4. Project de Seguridad FTSP - Management and Ejecución IBRD / 86490 Posterior Individual Direct 16,500.00 0.00 2021-02-24 2021-03-03 2021-03-03 2021-03-22 2022-03-21 Recontratación WILSON Environmental and Social pendiente LAVERDE FLÓREZ Management Page 9