PROCUREMENT PLAN (Textual Part) Country: Kyrgyz Republic Full Project Name: Enhancing Resilience in the Kyrgyz Republic Project (ERIK) Project Number: P162635 Project Implementation agency Project Implementation Unit of the Project under MoES Date of the Procurement Plan: December 26, 2017 Period covered by this December 26, 2017 - December 26, 2018 Procurement Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Kyrgyz Republic : Enhancing Resilience in Kyrgyzstan Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2017-12-27 2020-07-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162635 GPN Date: 2017-12-08 Project Name: Enhancing Resilience in Kyrgyzstan Project Loan / Credit No: IDA / V1060, / , IDA / 62380 Executing Agency(ies): Ministry of Emergency Situations WORKS Procureme Bid Evaluation Activity Reference No. / Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Amount Document / Signed Contract No. Approach Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion (US$) Justification Type Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CW/RFB-10 / Improving Safety and Open - Single Stage - One Procurement of civil works IDA / 62380 Functionality of School Prior Request for Bids 0.00 Canceled 2021-11-30 2021-12-17 2022-02-15 2022-03-17 2022-04-28 2023-04-28 International Envelope for schools Infrastructure KG-CW/RFB-09 / Improving Safety and Pending Open - Single Stage - One Procurement of civil works IDA / 62380 Functionality of School Prior Request for Bids 0.00 Implementat 2020-08-25 2020-09-11 2020-11-10 2020-12-10 2021-01-21 2022-01-21 International Envelope for schools Infrastructure ion GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-02 / Equipment Open - Single Stage - One / Post Request for Bids 0.00 Canceled 2018-04-25 2018-05-23 2018-07-07 2018-08-04 2018-09-01 2019-02-28 for '112' Call Center International Envelope KG-G/RFB-02B / Equipment Contingent Emergency Open - Single Stage - One IDA / V1060 Post Request for Bids 229,590.14 Completed 2018-05-28 2018-07-20 2018-06-08 2018-07-20 2018-07-20 2018-09-04 2018-08-19 2018-09-13 2018-09-23 2018-10-02 2019-03-22 2019-02-26 for '112' Call Center Response International Envelope KG-G/RFQ-02/1 / Software Project Management and (1C accounting system for IDA / V1060 Post Direct Selection Direct 7,900.00 Completed 2018-05-29 2018-06-18 2018-06-01 2018-06-18 2018-06-14 2018-06-19 2018-07-14 2018-07-19 Monitoring & Evaluation PIU under the MOES) KG-G/RFQ-01 / Equipment Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 0.00 Canceled 2018-04-27 2018-05-18 2018-06-07 2018-07-17 for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFQ-02 / Software Project Management and Request for Single Stage - One (1C accounting system for IDA / V1060 Post Open - National 0.00 Canceled 2018-05-05 2018-06-15 2018-08-14 Monitoring & Evaluation Quotations Envelope MoES) KG-G/RFB-01 / Equipment Contingent Emergency Open - Single Stage - One IDA / V1060 Post Request for Bids 0.00 Canceled 2018-05-15 2018-05-29 2018-07-13 2018-08-10 2018-09-07 2019-03-06 for rescue team Response International Envelope KG-G/RFB-01A / Equipment for rescue team: Lot #1- Procurement of Contingent Emergency Single Stage - One IDA / V1060 Post Request for Bids Open - National 98,060.00 Completed 2018-06-22 2018-06-28 2018-06-29 2018-06-29 2018-08-03 2018-07-27 2018-09-02 2018-08-06 2018-10-07 2018-10-01 2018-11-21 2018-10-30 rescue tools Response Envelope Lot #2- Procurement of equipment for rescue service KG-G/RFQ-01B / Furniture Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 3,719.77 Completed 2018-06-29 2018-07-20 2018-08-17 2018-09-06 2018-09-16 2018-10-05 for PIU Monitoring & Evaluation Quotations Envelope Page 1 KG-G/RFQ-01A / Computer Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 19,146.94 Completed 2018-06-29 2018-06-29 2018-08-10 2018-07-12 2018-09-09 2018-08-24 equipment for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFB-02A / Software Contingent Emergency IDA / V1060 Post Direct Selection Direct 508,250.80 Completed 2018-07-09 2018-08-06 2018-07-14 2018-08-07 2018-08-30 2018-08-28 2019-01-17 2019-01-14 for '112' call center Response KG-G/RFB-01B / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 18,141.96 Completed 2018-08-15 2018-08-17 2018-08-17 2018-08-17 2018-09-14 2018-09-07 2018-10-14 2018-09-20 2018-11-11 2018-10-17 2018-12-26 2018-11-23 Response Envelope Fire equipment, Lot #3 - Diving equipment. KG-G/RFB-01C / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 45,416.74 Completed 2018-10-04 2018-10-05 2018-10-05 2018-10-05 2018-10-26 2018-10-26 2018-11-15 2018-11-13 2018-12-10 2018-12-17 2019-01-24 2019-04-12 Response Envelope Fire equipment Re-advertisement KG-G/RFQ-04 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-23 2019-07-22 Protection Quotations Envelope regional offices SIO KG-G/RFQ-05 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 0.00 Canceled 2019-04-11 2019-05-30 2019-07-29 Protection Quotations Envelope offices SIO KG-G/RFQ-07 / Procurement Enhancing Financial Request for Single Stage - One IDA / 62380 Post Open - National 0.00 Canceled 2019-07-14 2019-09-13 2019-12-12 of mobile devices for SIO Protection Quotations Envelope KG-G/RFB-05 / Establishing Strengthening Disaster Open - Single Stage - One the Platform to Exchange IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-03-28 2019-04-04 2019-05-19 2019-06-16 2019-07-14 2020-07-13 International Envelope the Data Systems KG-G/RFQ-10 / Procurement Strengthening Disaster of Software for development Request for Open - Single Stage - One IDA / 62380 Preparedness and Response Post 55,000.00 Completed 2019-04-05 2019-04-05 2019-05-20 2019-07-09 2019-09-17 2019-09-04 of the Unified Duty- Quotations International Envelope Systems Dispatching Service 112 KG-G/RFB-03 / Development of the Country- Strengthening Disaster Open - Single Stage - One Wide Integrated Public IDA / 62380 Preparedness and Response Prior Request for Bids 1,250,000.00 Signed 2019-04-04 2019-06-26 2019-04-19 2019-08-21 2019-06-03 2019-08-22 2019-07-01 2019-10-30 2019-08-12 2019-11-14 2020-02-08 International Envelope Notification and Warning Systems System - OKSION System KG-G/RFB-04 / Development of Routine Management Body - Crisis Management Center: Lot #1 Strengthening Disaster Open - Single Stage - One purchase of controller for IDA / 62380 Preparedness and Response Post Request for Bids 103,167.69 Completed 2019-03-25 2019-04-05 2019-03-29 2019-04-05 2019-05-13 2019-05-20 2019-06-10 2019-06-19 2019-07-08 2019-07-10 2019-12-15 2019-12-10 International Envelope video wall. Lot# 2 purchase Systems of satellite equipment. Lot #3 purchase of radio station equipment. KG-G/RFB-09 / Disaster Strengthening Disaster Pending Learning Platform for Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Implementati 2020-06-22 2020-06-26 2020-08-07 2020-09-04 2020-10-16 2021-02-13 Professional Training Center International Envelope Systems on MES KG-G/RFB-10 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 47,782.91 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-10-22 Protection Quotations Envelope offices SIO Page 2 KG-G/RFB-12 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 67,943.35 Completed 2019-04-18 2019-05-13 2019-06-17 2019-07-19 2019-08-16 2019-09-17 Protection Quotations Envelope regional offices SIO KG-G/RFQ-11 / Computer Project Management and IDA / V1060 Post Direct Selection Direct 3,924.70 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-06-16 2019-05-22 2019-07-31 2019-06-05 equipment for PIU Monitoring & Evaluation KG-G/RFQ-12 / Additional Project Management and IDA / V1060 Post Direct Selection Direct 909.09 Completed 2019-05-07 2019-05-17 2019-05-12 2019-05-21 2019-05-24 2019-05-22 2019-06-23 2019-05-29 furniture for PIU Monitoring & Evaluation KG-G/RFQ-09 / Procurement of office equipment for Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - National 0.00 Canceled 2019-03-22 2019-05-08 2019-06-24 Unified Duty- Dispatching Response Quotations Envelope Service 112 KG-G/RFQ-09A / Strengthening Disaster Request for Single Stage - One Procurement of computer IDA / 62380 Preparedness and Response Post Open - National 0.00 Canceled 2019-06-14 2019-07-11 2019-07-24 2019-09-12 Quotations Envelope equipment for 112 system Systems KG-G/RFB-11 / Procurement Enhancing Financial Open - Single Stage - One IDA / 62380 Post Request for Bids 163,420.25 Completed 2019-06-24 2019-07-22 2019-06-28 2019-07-22 2019-08-09 2019-09-02 2019-08-23 2019-10-01 2019-09-20 2019-10-18 2019-11-19 2020-02-28 of server equipment for SIO Protection International Envelope KG-G/RFB-08 / Strengthening the capacity of the newly created 15 cluster interdistrict points (points) of Strengthening Disaster Open - Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-06-17 2019-06-21 2019-08-02 2019-08-16 2019-09-13 2019-12-12 International Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP Strengthening Disaster KG-G/RFQ-13 / Procurement Request for Single Stage - One IDA / V1060 Preparedness and Response Post Open - National 0.00 Canceled 2019-06-16 2019-08-23 2019-07-31 2019-09-29 of compressed air apparatus Quotations Envelope Systems KG-G/RFB-13 / Procurement of hardware for Web portal and newly created 15 cluster interdistrict points (points) of Strengthening Disaster Open - Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-20 2019-11-12 2019-10-21 2019-12-04 2019-11-25 2020-02-24 International Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP. KG-G/RFB-14 / Production Pending Enhancing Financial Single Stage - One of Branded and Promotional IDA / 62380 Post Request for Bids Open - National 0.00 Implementati 2019-08-12 2019-08-15 2019-09-26 2019-10-26 2019-11-26 2020-02-24 Protection Envelope Products for SIO on KG-G/RFB-04A / Development of Routine Strengthening Disaster Management Body - Crisis Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-08-02 2019-08-13 2019-08-05 2019-08-13 2019-09-19 2019-09-25 2019-10-17 2019-12-05 2019-11-14 2020-02-12 Management Center: International Envelope Systems Purchase of satellite equipment KG-G/RFB-15 / Procurement Enhancing Financial Open - Single Stage - One IDA / 62380 Post Request for Bids 68,800.00 Signed 2019-08-07 2019-08-16 2019-08-09 2019-08-16 2019-09-23 2019-09-27 2019-10-23 2019-11-18 2019-11-25 2019-12-25 2020-01-24 of mobile devices for SIO Protection International Envelope Page 3 KG-G/RFB-06A / Goods for operational survey of landslides: Lot #1 - Equipment and car. Lot # Strengthening Disaster Open - Single Stage - One 2 - Mobile meteorological IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-06-03 2019-06-07 2019-06-06 2019-06-06 2019-07-18 2019-07-19 2019-08-01 2019-08-12 2019-08-29 2019-12-17 International Envelope station and measuring Systems equipment. Lot #3 - UAV and land surveying equipment KG-G/RFB-06C / Strengthening Disaster Single Stage - One Procurement of Off-road IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-12-26 2020-01-23 2020-05-22 Envelope Vehicle Systems KG-G/RFB-06D / Strengthening Disaster Single Stage - One Procurement of UAV and IDA / 62380 Preparedness and Response Post Request for Bids Open - National 47,819.01 Completed 2019-10-03 2019-09-16 2019-10-07 2019-09-17 2019-11-18 2019-10-08 2020-01-02 2019-10-31 2020-01-30 2019-11-12 2020-05-29 2020-03-18 Envelope land survey equipment Systems Strengthening Disaster KG-G/RFB-06Е / Procureme Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2019-09-27 2019-09-16 2019-09-30 2019-09-17 2019-11-11 2019-10-09 2019-12-26 2020-01-23 2020-05-22 nt of Measuring Equipment Envelope Systems KG-G/RFB-06F / Strengthening Disaster Procurement of Mobile Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-09-27 2019-10-17 2019-09-30 2019-10-18 2019-11-14 2019-12-03 2019-12-30 2019-12-19 2020-02-03 2020-06-02 Weather Station and International Envelope Systems Forecast Equipment KG-G/RFQ-13A / Strengthening Disaster Request for Single Stage - One Procurement of compressed IDA / V1060 Preparedness and Response Post Open - National 19,574.61 Completed 2019-10-02 2019-09-24 2019-12-30 2019-12-06 2020-02-28 2020-02-06 Quotations Envelope air apparatus Systems KG-G/DC-01 / Procurement of Software for newly created 15 cluster interdistrict points (points) of Strengthening Disaster monitoring of hazardous IDA / 62380 Preparedness and Response Post Direct Selection Direct 176,305.00 Completed 2019-09-30 2019-09-20 2019-10-11 2019-09-26 2019-11-08 2019-10-18 2020-03-07 2019-12-03 natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP KG-G/RFQ-09A-2 / Strengthening Disaster Procurement of office Request for Single Stage - One IDA / 62380 Preparedness and Response Post Open - National 9,694.14 Completed 2019-10-05 2019-09-27 2019-11-19 2019-11-14 2020-01-08 2019-12-26 equipment for Unified Duty- Quotations Envelope Systems Dispatching Service 112 KG-G/RFB-06C-2 / Strengthening Disaster Open - Single Stage - One Procurement of Special IDA / 62380 Preparedness and Response Post Request for Bids 49,820.00 Signed 2020-02-06 2020-01-24 2020-02-12 2020-01-23 2020-04-02 2020-03-16 2020-05-12 2020-05-18 2020-06-16 2020-06-05 2020-10-14 International Envelope Vehicles Systems KG-G/RFB-13-2 / Procurement of hardware for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Canceled 2020-02-13 2020-03-11 2020-02-18 2020-03-11 2020-03-16 2020-04-01 2020-04-30 2020-06-04 2020-09-02 Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP KG-G/RFB-04A-2 / Development of Routine Strengthening Disaster Management Body - Crisis Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2020-02-18 2020-02-07 2020-02-21 2020-02-07 2020-04-06 2020-05-11 2020-06-08 2020-10-06 Management Center: International Envelope Systems Purchase of satellite equipment Strengthening Disaster Under KG-G/RFB-06Е-2 / Procurem Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Implementati 2020-03-10 2020-03-13 2020-03-13 2020-03-13 2020-04-30 2020-06-30 2020-06-19 2020-07-17 2020-11-14 ent of measuring equipment International Envelope Systems on Page 4 KG-G/RFB-06F-2 / Strengthening Disaster Under Procurement of a mobile Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Implementati 2020-03-23 2020-06-04 2020-03-25 2020-06-05 2020-05-14 2020-07-03 2020-07-31 2020-11-28 weather station and forecast International Envelope Systems on equipment Strengthening Disaster Pending KG-G/RFB-07 / Scaling-up Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Implementati 2021-01-25 2021-02-01 2021-03-18 2021-04-15 2021-05-13 2021-11-09 of the operational monitoring International Envelope Systems on KG/ERIK-CERC/G/RFQ/2020- 01 / Personal Protective Equipment for RRTs, 24 Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 designated quarantine Response Quotations International Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 02 / Disinfectants for RRTs, Contingent Emergency Request for Open - Single Stage - One 24 designated quarantine IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 Response Quotations International Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 03 / Laboratory reagents needed for diagnosis for Contingent Emergency Request for Open - Single Stage - One RRTs, 24 designated IDA / 62380 Post 71,415.39 Signed 2020-04-07 2020-04-06 2020-05-19 2020-04-29 2020-11-15 Response Quotations International Envelope quarantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 04 / Lifesaving essential drugs for diagnosis for Contingent Emergency Request for Open - Single Stage - One RRTs, 24 designated IDA / 62380 Post 749,828.10 Signed 2020-04-07 2020-04-06 2020-05-19 2020-04-23 2020-11-15 Response Quotations International Envelope quarantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 05 / Medical devices for diagnosis for RRTs, 24 Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 2,510.00 Signed 2020-04-07 2020-04-06 2020-04-19 2020-04-23 2020-05-19 designated quarantine Response Quotations International Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 09 / Procurement of 13 fully Contingent Emergency Request for Open - Single Stage - One equipped ambulances - IDA / 62380 Post 764,900.00 Signed 2020-04-07 2020-04-06 2020-04-19 2020-04-22 2020-06-18 Response Quotations International Envelope Advanced Life Support (ALS) vehicles KG/ERIK-CERC/G/RFQ/2020- 06 / Medical equipment for diagnosis for RRTs, 24 Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 571,333.53 Signed 2020-04-07 2020-04-06 2020-04-19 2020-04-28 2020-06-18 designated quarantine Response Quotations International Envelope hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 08 / Other products (paper Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 0.00 Canceled 2020-04-07 2020-04-06 2020-04-19 2020-05-19 towels, shipping containers, Response Quotations International Envelope etc.) KG/ERIK-CERC/G/RFQ/2020- Contingent Emergency Request for Open - Single Stage - One 07 / Respiratory Support IDA / 62380 Post 1,452,714.24 Signed 2020-04-07 2020-04-06 2020-04-19 2020-05-07 2020-06-18 Response Quotations International Envelope Equipment Page 5 KG/ERIK-CERC/G/RFQ/2020- 01B / PPEs for RRTs, 24 Contingent Emergency Request for Open - Single Stage - One designated quarantine IDA / 62380 Post 441,663.01 Signed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 Response Quotations International Envelope hospitals, PHC, ICUs and designated hospitals - 2 lots KG/ERIK-CERC/G/RFQ/2020- 02B / Disinfectants for RRTs, 24 designated Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 33,803.70 Signed 2020-04-17 2020-04-17 2020-04-29 2020-04-30 2020-05-29 quarantine hospitals, PHC, Response Quotations International Envelope ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 08B / Other products (paper Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 20,369.94 Signed 2020-04-17 2020-04-17 2020-04-29 2020-05-08 2020-05-29 towels, liquid soap, shipping Response Quotations International Envelope containers, etc.) G/ERIK-CERC/G/RFQ/2020- 05B / Medical devices for diagnosis for RRTs, 24 designated quarantine Contingent Emergency Request for Open - Single Stage - One IDA / 62380 Post 21,614.87 Signed 2020-04-20 2020-04-20 2020-05-02 2020-05-04 2020-06-01 hospitals, PHC, ICUs and Response Quotations International Envelope designated hospitals - Lot No 2 - Consumables for medicament injection KG/ERIK-CERC/G/RFQ/2020- 04B / Procurement of lifesaving essential drugs for Contingent Emergency Request for Open - Single Stage - One diagnosis for RRTs, 24 IDA / 62380 Post 152,657.78 Signed 2020-04-23 2020-04-23 2020-05-05 2020-05-04 2020-06-04 Response Quotations International Envelope designated quarantine hospitals, PHC, ICUs and designated hospitals KG/ERIK-CERC/G/RFQ/2020- 03B / Laboratory reagents needed for diagnosis for Contingent Emergency Request for Open - Single Stage - One RRTs, 24 designated IDA / 62380 Post 0.00 Canceled 2020-05-11 2020-05-11 2020-06-24 2020-07-24 Response Quotations International Envelope quarantine hospitals, PHC, ICUs and designated hospitals -Lot No 1 KG-G/DC-02 / Procurement Under Enhancing Financial of database of residential IDA / 62380 Post Direct Selection Direct 0.00 Implementati 2020-05-10 2020-05-27 2020-05-15 2020-05-28 2020-05-25 2020-07-24 Protection properties for SIO on KG/ERIK-CERC/G/RFQ/2020- 06B / Medical equipment for Under diagnosis for RRTs, 24 Contingent Emergency Request for IDA / 62380 Post 0.00 Implementati 2020-05-18 2020-05-19 2020-06-09 2020-08-08 designated quarantine Response Quotations on hospitals, PHC, ICUs and designated hospitals. KG/ERIK-CERC/G/RFQ/2020- 10 / Procurement of Under Contingent Emergency Request for Open - Single Stage - One equipment for disinfection IDA / 62380 Post 0.00 Implementati 2020-05-26 2020-05-28 2020-06-22 2020-08-21 Response Quotations International Envelope and reduction of medical on waste KG-G/RFB-13-2B / Procurement of hardware for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Under Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids Open - National 0.00 Implementati 2020-06-22 2020-06-22 2020-06-25 2020-06-22 2020-07-25 2020-08-29 2020-09-08 2020-12-07 Envelope natural processes within the Systems on framework of the creation of mobile monitoring points of the ESCMP Page 6 KG/ERIK- CERC/G/UNA/2020/1 / Contingent Emergency UN Agencies Procurement of Personel IDA / 62380 Post Direct 679,275.58 Signed 2020-07-01 2020-06-25 2020-07-03 2020-06-24 2020-07-10 2020-06-25 2020-08-29 Response (Direct) Protective Equipment and medical drugs KG/ERIK-CERC/G/DC/2020- 02 / Procurement of Pending Contingent Emergency lifesaving essential drugs for IDA / 62380 Post Direct Selection Direct 0.00 Implementati 2020-07-01 2020-07-01 2020-07-04 2020-07-29 Response RRTs of health care on organizations KG/ERIK-CERC/G/DC/2020- 03 / Procurement of Pending Contingent Emergency lifesaving essential drugs for IDA / 62380 Post Direct Selection Direct 0.00 Implementati 2020-07-01 2020-07-01 2020-07-04 2020-07-29 Response RRTs of health care on organizations KG/ERIK-CERC/G/DC/2020- 04 / Procurement of Pending Contingent Emergency lifesaving essential drugs for IDA / 62380 Post Direct Selection 0.00 Implementati 2020-07-01 2020-07-01 2020-07-04 2020-07-06 Response RRTs of health care on organizations KG/ERIK-CERC/G/DC/2020- 05 / Procurement of Pending Contingent Emergency lifesaving essential drugs for IDA / 62380 Post Direct Selection Direct 0.00 Implementati 2020-07-01 2020-07-01 2020-07-04 2020-07-29 Response RRTs of health care on organizations KG/ERIK-CERC/G/RFQ/2020- 03B-2 / Purchase of Pending Contingent Emergency Request for Open - Single Stage - One consumables for polymerase IDA / 62380 Post 0.00 Implementati 2020-07-13 2020-08-08 2020-09-07 Response Quotations International Envelope chain reaction (PCR) on analysis NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-06B / Strengthening Disaster Procurement of Digital Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 0.00 Canceled 2019-04-05 2019-04-12 2019-05-24 2019-06-21 2019-08-02 2019-12-20 terrain model (DTM) and International Envelope Systems orthophotographs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CS/QCBS-02 / Business process review for Enhancing Financial Quality And Cost- Open - catastrophe insurance and IDA / V1060 Prior 1,333,333.33 Signed 2018-03-15 2018-03-25 2018-04-14 2018-05-11 2018-05-12 2018-06-25 2018-06-09 2018-07-25 2018-06-29 2018-09-12 2018-08-03 2018-11-26 2018-09-18 2018-12-26 2020-09-17 Protection Based Selection International supporting IT customization services KG-CS/LCS-01 / Financial Least Cost Open - audit (annual) of project for / Post 0.00 Canceled 2018-02-25 2018-03-03 2018-03-27 2018-04-24 2018-05-22 2018-06-11 2018-07-09 2018-07-23 2019-12-31 Selection International 2018-2020 Page 7 KG-CS/QCBS-01 / Preparation of Feasibility Studies and Designs for Quality And Cost- Open - Improved Seismic Safety and / Prior 0.00 Canceled 2018-04-25 2018-05-25 2018-06-22 2018-07-20 2018-08-09 2018-09-13 2018-10-29 2020-10-28 Based Selection International Energy Efficiency of Schools and Technical Supervision of construction. KG-CS/QCBS-01/2 / Preparation of Feasibility Studies and Designs for Improving Safety and Quality And Cost- Open - Improved Seismic Safety and IDA / V1060 Functionality of School Post 0.00 Canceled 2020-03-02 2020-03-23 2020-04-27 2020-06-08 2020-06-28 2020-08-02 2020-09-11 2021-04-09 Based Selection International Energy Efficiency of Schools Infrastructure and Technical Supervision of construction. KG-CS/LCS-01/A / Financial Project Management and Least Cost Open - IDA / 62380 Post 76,832.00 Signed 2019-01-18 2019-02-05 2019-02-03 2019-02-08 2019-02-24 2019-03-06 2019-03-24 2019-04-03 2019-04-07 2019-04-10 2019-04-22 2019-04-19 2019-05-13 2019-05-17 2024-01-31 audit of project (annual) Monitoring & Evaluation Selection International KG-CS/QCBS-01/1 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- Open - Under IDA / V1060 Functionality of School Prior 0.00 2019-06-28 2020-01-16 2019-07-12 2020-02-03 2019-08-12 2019-09-11 2019-10-09 2019-11-13 2019-12-18 2020-12-17 Improved Seismic Safety and Based Selection International Implementation Infrastructure Energy Efficiency of Schools and Author supervision KG-CS/QCBS-01/3 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- Open - IDA / V1060 Functionality of School Prior 0.00 Canceled 2020-07-28 2020-08-27 2020-09-27 2020-10-27 2020-11-24 2020-12-29 2021-02-02 2022-10-25 Improved Seismic Safety and Based Selection International Infrastructure Energy Efficiency of Schools and Author supervision Improving Safety and Consultant KG-CS/CQS-02 / IDA / V1060 Functionality of School Post Qualification Open - National 0.00 Canceled 2021-04-01 2021-04-15 2021-05-13 2021-05-27 2021-07-03 2022-06-28 Supervision and monitoring Infrastructure Selection Improving Safety and KG-CS/QCBS-05 / Quality And Cost- Open - Pending IDA / V1060 Functionality of School Prior 0.00 2021-02-02 2021-02-23 2021-04-08 2021-05-06 2021-06-05 2021-07-10 2021-08-14 2022-12-27 Supervision and monitoring Based Selection International Implementation Infrastructure KG-CS/CQS-03 / Strengthening Disaster Consultant Open - Establishing a Platform to IDA / 62380 Preparedness and Response Post Qualification 137,970.00 Signed 2019-08-05 2019-08-27 2019-08-26 2019-09-06 2019-10-09 2019-12-02 2019-10-16 2020-02-25 2019-11-13 2020-03-17 2020-02-11 International Exchange the Data Systems Selection KG-CS/QCBS-03 / Enhancing Financial Quality And Cost- Open - Pending Optimisation of SIO core IDA / 62380 Prior 0.00 2020-10-01 2020-10-15 2020-12-10 2021-01-07 2021-02-06 2021-03-03 2021-04-18 2022-04-18 Protection Based Selection International Implementation business processes KG-CS/CQS-04 / Risk Consultant Enhancing Financial Open - Pending management and regulatory IDA / 62380 Post Qualification 0.00 2020-10-15 2020-10-29 2020-12-14 2021-01-25 2021-03-01 2021-03-13 Protection International Implementation compliance Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IOC/IC-07 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 12,731.86 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-17 2018-04-16 2020-04-06 2019-04-30 Monitoring & Evaluation Component 1 Selection KG-IOC/IC-08 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 11,086.74 Completed 2018-02-15 2018-02-19 2018-03-29 2018-04-25 2018-03-30 2018-04-28 2018-04-17 2018-05-14 2020-04-06 2019-04-30 Monitoring & Evaluation Component 2 Selection Page 8 KG-IOC/IC-09 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 13,404.13 Completed 2018-02-15 2018-02-15 2018-03-29 2018-04-04 2018-03-30 2018-04-06 2018-04-17 2018-04-23 2020-04-06 2019-04-30 Monitoring & Evaluation Component 3 Selection Individual KG-IOC/IC-03 / Local Project Management and IDA / V1060 Prior Consultant Direct 20,923.36 Completed 2018-02-15 2018-03-02 2018-03-08 2018-03-19 2018-03-22 2018-04-04 2018-03-29 2018-04-01 2019-11-19 2019-04-30 Financial Manager Monitoring & Evaluation Selection Individual KG-IOC/IC-04 / Local Project Management and IDA / V1060 Post Consultant Open 11,986.87 Completed 2018-02-15 2018-02-19 2018-03-20 2018-04-03 2018-03-22 2018-04-03 2018-04-08 2018-04-18 2019-04-03 2019-04-30 Disbursment Specialist Monitoring & Evaluation Selection KG-IOC/IC-05 / Local Individual Project Management and assistant of Procurement IDA / V1060 Post Consultant Open 4,791.60 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-03 2018-03-30 2018-04-05 2018-04-19 2018-04-16 2019-04-14 Monitoring & Evaluation Specialist Selection Individual KG-IOC/IC-06 / Local Project Management and IDA / V1060 Post Consultant Open 8,286.74 Terminated 2018-02-15 2018-02-19 2018-03-29 2018-04-02 2018-03-30 2018-04-02 2018-04-19 2018-04-16 2019-04-14 Translator-office-manager Monitoring & Evaluation Selection Individual KG-CS/IC-02 / Selection of Project Management and / Post Consultant Limited 3,235.30 Terminated 2017-12-29 2018-01-09 2017-12-30 2018-01-17 2018-01-05 2018-01-23 2018-01-17 2018-02-28 Local Social Consultant Monitoring & Evaluation Selection KG-CS/IC-01 / Selection of Individual Local Environmental / Post Consultant Limited 3,970.59 Completed 2017-12-29 2018-01-30 2017-12-31 2018-01-17 2018-01-05 2018-01-22 2018-01-17 2018-02-04 2018-02-28 2018-04-06 Consultant Selection KG-IOC/IC-02 / Local Individual Project Management and Senior Procurement IDA / V1060 Prior Consultant Direct 13,575.10 Terminated 2018-02-22 2018-03-02 2018-02-22 2018-03-19 2018-02-22 2018-04-04 2018-04-01 2018-04-01 2019-11-22 Monitoring & Evaluation Specialist Selection Individual KG-MES-54500-CS-INDV / Project Management and IDA / V1060 Prior Consultant Limited 14,390.21 Completed 2018-03-19 2018-03-22 2018-03-19 2018-04-06 2018-04-02 2018-04-24 2018-04-26 2018-05-16 2019-04-21 2019-04-30 Local Director PIU Monitoring & Evaluation Selection Individual KG-IOC/IC-01 / Local / Prior Consultant Open 0.00 Canceled 2018-02-15 2018-02-19 2018-03-29 2018-04-12 2018-05-17 2020-05-06 Director PIU Selection KG-CS/IC-03 / Selection of Local Consultant for Individual preparation of bidding / Post Consultant Open 0.00 Canceled 2018-04-15 2018-05-27 2018-06-10 2018-06-24 2019-06-19 documents for goods for Selection MoES KG-CS/IC-03-2 / Local IT Consultant for preparation of Individual Project Management and bidding documents for IDA / V1060 Post Consultant Limited 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-03 2019-07-03 Monitoring & Evaluation Component #1 and Selection Component #3 KG-CS/IC-03/1 / Local Individual Consultant for Business Project Management and IDA / V1060 Post Consultant Open 12,778.57 Completed 2018-06-21 2018-06-21 2018-07-30 2018-08-06 2018-08-02 2018-08-06 2018-08-21 2018-08-22 2019-08-21 2019-08-21 Processes and Information Monitoring & Evaluation Selection Technologies Improving Safety and Individual KG-CS/IC-04 / International IDA / V1060 Functionality of School Post Consultant Open 0.00 Canceled 2018-10-26 2018-12-05 2018-12-21 2019-01-09 2020-12-29 Сivil engineer Infrastructure Selection Improving Safety and Individual KG-CS/IC-04/A / Local civil IDA / 62380 Functionality of School Post Consultant Open 41,715.83 Signed 2019-02-17 2019-03-01 2019-03-14 2019-04-10 2019-03-21 2019-04-24 2019-04-11 2019-04-25 2020-04-10 engineer Infrastructure Selection Page 9 Improving Safety and Individual KG-CS/IC-05 / Local Social IDA / 62380 Functionality of School Post Consultant Open 0.00 Canceled 2019-02-27 2019-02-25 2019-04-04 2019-04-10 2019-04-11 2019-05-02 2020-05-01 & Environment Consultant Infrastructure Selection Strengthening Disaster Individual KG-CS/IC-07 / Local IT IDA / V1060 Preparedness and Response Post Consultant Open 5,213.26 Terminated 2019-03-25 2019-04-10 2019-04-19 2019-06-04 2019-04-22 2019-05-31 2019-05-10 2019-06-19 2020-05-09 Consultant for MES KR Systems Selection KG-CS/IC-09 / Local Improving Safety and Individual Translator Consultant for IDA / 62380 Functionality of School Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-06-28 2019-04-12 2019-04-29 2020-04-28 Component #2 Infrastructure Selection KG-CS/IC-10 / Local Individual Enhancing Financial Translator Consultant for IDA / 62380 Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-02 2019-04-12 2019-04-29 2020-04-28 Protection Component #3 Selection KG-CS/IC-05-2 / Local Improving Safety and Individual Social&Enviroment IDA / 62380 Functionality of School Post Consultant Limited 12,936.22 Signed 2019-05-03 2019-05-15 2019-05-10 2019-05-21 2019-05-24 2019-05-31 2019-06-14 2019-07-04 2020-06-13 Consultant Infrastructure Selection KG-CS/IC-08 / Local Strengthening Disaster Individual Translator Consultant for IDA / 62380 Preparedness and Response Post Consultant Open 0.00 Canceled 2019-03-25 2019-04-02 2019-04-11 2019-07-17 2019-04-12 2019-04-29 2020-04-28 Component #1 Systems Selection KG-CS/IC-03/2 / Local Individual Consultant for Business Enhancing Financial IDA / 62380 Post Consultant Direct 12,808.23 Signed 2019-08-21 2019-09-06 2019-08-21 2019-08-20 2019-08-21 2019-08-20 2019-08-22 2019-08-20 2020-08-31 Processes and Information Protection Selection Technologies KG/CS/SSS-01/SDC / Improving Safety and Under Development of special IDA / 62380 Functionality of School Post Direct Selection Direct 0.00 2020-07-01 2020-06-24 2020-07-15 2020-09-09 2020-11-08 Implementation design criteria Infrastructure Strengthening Disaster Individual KG-CS/IC-07/B / Local IT Under IDA / 62380 Preparedness and Response Post Consultant Open 0.00 2020-05-22 2020-06-12 2020-06-20 2020-07-04 2020-07-07 2021-07-07 Consultant for MES Implementation Systems Selection Page 10