ASCCDP: Resettlement Action Plan for Flood Mitigation Works Amaravati Sustainable Capital City Development Project (ASCCDP) Revised Final Draft Resettlement Action Plan for Flood Mitigation Works Andhra Pradesh Capital Region Development Authority Amaravati, Andhra Pradesh August 2018 Version 5.0 1 ASCCDP: Resettlement Action Plan for Flood Mitigation Works TABLE OF CONTENTS ACRONYMS ............................................................................................................................................... 3 EXECUTIVE SUMMARY.......................................................................................................................... 5 I. INTRODUCTION ................................................................................................................................... 9 Impacts .................................................................................................................................................. 12 II. SOCIAL IMPACT ASSESSMENT ..................................................................................................... 16 Magnitude of Social Impacts .............................................................................................................. 16 III. CONSULTATIONS / BASELINE SOCIO-ECONOMIC CHARACTERISTICS OF AFFECTED FAMILIES.................................................................................................................................................. 22 Introduction .......................................................................................................................................... 22 Focus Group Discussions.................................................................................................................... 25 IV. INSTITUTIONAL AND IMPLEMENTATION ARRANGEMENTS .......................................... 29 Institutional Arrangements ................................................................................................................ 29 Implementation Mechanism for LPS / LA / Negotiated Settlement Policy ............................... 29 Coordination with District Administration for Land Acquisition................................................ 31 Project Implementation Unit .............................................................................................................. 33 V. MONITORING OF RAP DURING IMPLEMENTATION ............................................................ 46 ANNEXURES ........................................................................................................................................... 52 Annexure – 1 Land Pooling Scheme - Entitlement Matrix................................................................. 52 Annexure – 2 Compensation and R&R Assistance under Land Acquisition Act ........................... 53 Annexure – 3 Negotiated Settlement Policy ........................................................................................ 55 Annexure – 4 Baseline Socio-Economic Data ....................................................................................... 57 Annexure – 5 Details of Public Consultations ..................................................................................... 72 Annexure – 6 Land Guideline Values in the Project Area ................................................................. 97 Annexure – 7 List of PAFs, PDFs – Flood Mitigation Works ............................................................ 98 Annexure – 8 Summary on LPS PAFs – Blue Network .................................................................... 103 Annexure – 9 Village-wise affected Encumbrance Details .............................................................. 106 Annexure - 10 Assistance to Landless Families ................................................................................. 110 2 ASCCDP: Resettlement Action Plan for Flood Mitigation Works ACRONYMS AP Andhra Pradesh APCRDA Andhra Pradesh Capital Region Development Authority APSSDC Andhra Pradesh State Skill Development Corporation ASCCDP Amaravati Sustainable Capital City Development Project CA Competent Authority RAP Resettlement Action Plan LPS Land Pooling Scheme RFCTLARR Right to Fair Compensation and Transparency in Land Acquisition and Resettlement and Rehabilitation LARR Land Acquisition, Resettlement and Rehabilitation SES Socio-Economic Survey RPF Resettlement Policy Framework GIS Geological Information Systems CPR Community Property Resources LPOC Land Pooling Ownership Certificate SIA Social Impact Assessment GP Gram Panchayat LAO Land Acquisition Officer PDF Project Displaced Family PAF Project Affected Family PAP Project Affected Person PWD Public Works Department IAY Indira Awaas Yojana SSR Standard Schedule of Rates FGD Focus Group Discussion CPIAL Consumer Price Index for Agricultural Labourers NGO Non-Government Organization GRM Grievance Redressal Mechanism MA&UD Municipal Administration & Urban Development TDR Transferrable Development Rights NTR Nandamuri Taraka Rama Rao (former Chief Minister of AP) U/s Under Section 3 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4 ASCCDP: Resettlement Action Plan for Flood Mitigation Works EXECUTIVE SUMMARY The Andhra Pradesh Reorganization Act 2014, which came into effect on June 2, 2014 provided for the reorganization of the then existing state of Andhra Pradesh. The development of a new Capital City – critical for administration, economic development, and cultural integration – is a priority for the residuary state of Andhra Pradesh. The State Cabinet meeting of September 1, 2014 passed a resolution ‗to locate the Capital City in a central place of the state, around Vijayawada, and to go for decentralized development of the state with 3 Mega Cities and 14 Smart Cities‘. The State Government identified the Capital City area between Vijayawada and Guntur cities on the Southern bank of River Krishna, upstream of the Prakasam Barrage. The Amaravati Capital City has an area of 217.23 sq.km and is spread across 25 villages in 3 mandals (Thulluru, Mangalagiri and Tadepalli) of Guntur district. The 25 villages in the Capital City area have a population of about 100,000 people. The nearest cities are Vijayawada at a distance of 30 km and Guntur at a distance of 18 km. The nearest railway station is KC Canal railway station near Tadepalli and the nearest airport is Gannavaram which is at a distance of 22 km. Amaravati is envisioned to be a ‗People‘s Capital‘ built around sustainability and livability principles. It aims to be at par with global standards and has developed a masterplan with the assistance of the Government of Singapore. The new capital will be a center of economic activity, will create a range of jobs and will provide affordable and quality housing. Sustainability, efficient management and optimum utilization of resources will form an important pillar of this new capital. The Project Development Objective of the World Bank supported Amaravati Sustainable Capital City Development Project (ASCCDP) is to provide select urban infrastructure in designated locations of Amaravati Capital City, and to support the initial development of its institutional and governance structure. The ASCCDP has five main components, as follows: (i) Basic Urban and Pro-poor Infrastructure Component, which will support the implementation of priority transport corridors and integration of 25 villages into the Amaravati Capital City development, by financing the construction of a priority road network and the upgrading of infrastructure in selected villages (e.g. water supply, sewage, village roads, and drainage); (ii) Green Climate Resilient Infrastructure, which will help build sustainability and climate resilience in Amaravati Capital City by supporting its integration with the natural surroundings, riverfront, and greenery; (iii) Citizen Benefit Sharing component, which will support government‘s efforts to implement benefit sharing measures for the residents of the capital city area, including but not limited to, training programs for farmers, landless families and other stakeholders, skill building programs, which will allow capital city residents to access jobs and new economic opportunities emerging in an urban context; (iv) Institutional and Fiscal Development, which will support government efforts to develop local government institutions and governance systems; and, (v) Project Management and Implementation Support. A Resettlement Policy Framework (RPF) was prepared to describe the principles, objectives and processes for preparation of specific resettlement plans that will be applicable to interventions financed by the World Bank project, once they are identified during project 5 ASCCDP: Resettlement Action Plan for Flood Mitigation Works preparation/implementation1. The RPF describes the principles and approach in avoiding, minimizing and mitigating adverse social impacts that may arise in implementation of proposed interventions financed by the World Bank. The RPF also provides process for consultations, impact assessment, census and socio-economic surveys, as well as for the preparation and implementation of mitigation plans. The RPF was prepared in line with the provisions of National laws, State laws and the World Bank‘s Involuntary Resettlement Policy (OP 4.12). The RPF was consulted and disclosed. It can be accessed at: https://crda.ap.gov.in/apcrdacommuni/media/asccdp/16082017/Amaravati%20RPF- Cleared%20by%20RSA.pdf This Resettlement Action Plan (RAP) has been prepared, consistent with the guidelines included in the RPF, to cover potential impacts and mitigation measures associated with Flood Mitigation works as a part of ASCCDP that include construction of reservoirs at Krishnayapalem, Neerukonda and Sakhamuru, widening and deepening of Pala Vaagu and Kondaveeti Vagu and construction of Storm Water Canal from Nekkallu to Pichikalapalem. The land required for this sub-component covered under this RAP will be assembled using a combination of land management mechanisms, including: (i) Land Pooling Scheme, whereby land owners surrender their land in return for a smaller plot of urban, serviced land (returnable plot) in the Capital City area that is of higher value than the land relinquished, along with a range of livelihood support measures including inter alia an annuity, skill upgrading and support for setting up self-employed enterprises; (ii) Negotiated settlements, applicable only for land and assets within existing villages, whereby the Government and land owners agree on the terms of a compensation package finalized in accordance with Section 124 of APCRDA Act 2014 that is consistent with the provisions of the 2013 Land Acquisition, Rehabilitation and Resettlement Act (LARR Act, 2013): The compensation involves, among other things, a land-for- land rather than in cash relocation assistance; and, if neither of these first two mechanisms is successful, (iii) Land Acquisition via the 2013 LARR Act, by which compensation for land acquired (replacement value and livelihood support) is provided as per the requirements of the Land Acquisition Act. All such land acquisition mechanisms, to the extent they are applied to land within the project, will be subject to the application of OP 4.12. The land assembly requirements for the flood mitigation component, as well as the numbers of land-owning Project Affected Families (PAFs) by construction of this flood mitigation component are summarized in the following table. Number of land-owning families Area required for WB-financed affected by WB-financed flood flood management works management works (acres) LPS 1,754 1,131.3 2013 LARR Act 110 75.5 Negotiated Settlements 27 10.4 Government land* Nil 811.11** Total 1,891 2,028.3 Number of landless families impacted by land assembly processes: 21,374 1 All interventions to be financed under the World Bank project have not been identified by project appraisal, and thus the overall impacts on land requirements and potential involuntary resettlement cannot be determined upfront. 6 ASCCDP: Resettlement Action Plan for Flood Mitigation Works (*) Occupants of Government land are assisted as per(i) LPS guidelines if occupying agricultural land; and (ii) Negotiated Settlement policy, if occupying land in villages. (**) This includes 680 acres of land in reservoirs (Krishnayapalem, Neerukonda and Sakhamauru) and stream flow area and land adjoining the stream per irrigation records (Vagu land). Note: Land owners currently undergoing Land Acquisition procedures may still opt to join LPS. While this will not affect the total number of families affected, it may affect the breakdown of affected people by land assembly mechanisms. Although OP 4.12 applies only to the footprint of the World Bank financed project, it is challenging to differentiate between landless laborers affected by land assembly within and outside the World Bank project boundaries. Therefore, APCRDA has agreed that all landless families registered with APCRDA for pension by July 15, 2018 are considered World Bank project affected people for the purposes of provision of livelihood restoration measures. The payment of pension and other livelihood-related benefits will be monitored for the list of registered landless families, as per the RPF. As of July 15, 2018, the total of number of landless households is 21,374. This RAP focuses on potential involuntary resettlement impacts on land owners in the Capital City area related to the Bank-financed flood mitigation component, and it includes provisions outlined in the RPF for all registered landless families (by July 15, 2018), which will be monitored under the ASCCDP. Two linked activities, specifically: (i) Undavalli Pumping Station; and (ii) works on the Kondaveeti Vagu, which stretches from Krishnayapalem Reservoir to Undavalli Pumping Station, are also included in this RAP. All land required for implementation of the two linked activities was owned by the GoAP, or surrendered by land owners under the LPS. Specifically, land required for the Undavalli Pumping station (in addition to government land) was assembled exclusively out of LPS. In the case of the stretch from Krishnayapalem reservoir to Undavalli pumping station, works will be restricted within the available width and land already assembled through LPS, thereby avoiding additional land assembly through LA or Negotiated Settlement. All land assembled for these linked activities has already been transferred to APCRDA. Because they are linked activities, the impacts of these two activities, in terms of land assembly and impacted people, are covered within this RAP. These activities are at advanced stages of implementation: (i) the Undavalli Pumping Station is expected to be inaugurated in mid-August 2018; and (ii) work on the Undavalli -Kondaveeti Vaagu stretch has initiated within the existing (Government) lands. Three common property resources, including a burial ground in Sakhamuru, a burial ground in Mandadam, and a private temple in Mandadam will be impacted by flood management works financed under the ASCCDP. In consensus with the community, it was agreed that the area of the two burial grounds located outside of the project affected area was sufficient to accommodate the community needs, and that there was no requirement of relocation of either of the burial grounds. The temple will be relocated suitably in consensus with the community. The summary on LPS Project affected families of lands falling under flood mitigation works is captured in Annexure 8 and their socio-economic baseline data from the sample survey of 96 landowners is presented at Annexure 4. This RAP also covers the impacts and mitigation measures related to lands being acquired through LARR and Negotiated Settlement Policy. The socio-economic data for 56 sampled non- LPS land owners is also provided in Annexure 4. 7 ASCCDP: Resettlement Action Plan for Flood Mitigation Works During the preparation of this Resettlement Action Plan (RAP), public consultations were held during January 2018 and August 2017 to seek suggestions on the initial draft safeguards documents (e.g. Resettlement Policy Framework, Environmental and Social Management Framework.) Subsequently, a series of public consultations were held during January 2018 to seek suggestions on the initial draft safeguards documents viz., EIA/EMP and Resettlement Action Plan for flood mitigation works based on prior disclosure of draft documents by APCRDA. These public consultations were held at four villages (Mandadam, Thulluru, Neerukonda and Krishnayapalem) during which opinions were sought on the Environmental Impact Assessment – Environmental Management Plan and Resettlement Action Plan for the flood mitigation component. In addition to the above public consultations, APCRDA conducted 20 Focus Group Final2 with landless pensioners, 2 with LA, 2 with Discussions including 2 exclusively with women, marginal farmers, 10 with LPS landowners and 2 with people depending on the government lands (but not living) were conducted in 14 villages viz., Pichikalapalem, Ainavolu, Mandadam, Krishnayapalem, Nowluru-2 (Yerrabalem), Sakhamuru, Velagapudi, Venkatapalem, Abbarajupalem, Borupalem, Kuragallu, Ananthavaram, Nekkallu and Penumaka. Further APCRDA conducted interviews with 152 landowners in 19 villages which are affected by flood mitigation works. The RAP contains the institutional and implementation arrangements including roles and responsibilities of various key officers, bringing in dedicated Land Acquisition and Social Development officers to manage and coordinate with District Administration. District Administration will manage the land acquisition and resettlement. The payment of differential amount arising out of RPF provisions will be paid by APCRDA through a separate account. The RAP implementation will be monitored through a monitoring agency through a set of indicators. The RAP also includes details of Grievance Redressal Mechanism (GRM) that is available to PAFs, citizen committee, process for consultations during implementation, support to livelihood measures and support to vulnerable groups, coordination with civil works, certification of payment of compensation and R&R assistance, budget, time table and monitoring and evaluation arrangement. This RAP is prepared based on the result of socio- economic surveys, outcomes of consultations and feedback on draft report as well as findings of independent evaluation of Land Pooling Scheme. 8 ASCCDP: Resettlement Action Plan for Flood Mitigation Works I. INTRODUCTION Overview of Amaravati Capital City 1.1 The Andhra Pradesh Reorganization Act 2014, which came into effect on 2 June, 2014, provided for the reorganization of the then existing state of Andhra Pradesh. The formation of a new Capital City – critical for its administration, economic development, and cultural integration – is a priority for the state of Andhra Pradesh. The State Cabinet meeting in early September 2014, passed a resolution ‗to locate the Capital City in a central place of the state, around Vijayawada, and to go for decentralized development of the state with 3 Mega Cities and 14 Smart Cities. The State Government identified the Capital City area between Vijayawada and Guntur cities on the Southern bank of River Krishna upstream of Prakasam Barrage. 1.2 The Amaravati Capital City has an area of 217.23 sq.km and is spread across 25 villages in 3 mandals (Thulluru, Mangalagiri and Tadepalli) of Guntur district. The 25 villages in the Capital City area have a population of about 100,000 people. The nearest cities are Vijayawada at a distance of 30 km and Guntur at a distance of 18 km. The nearest railway station is KC Canal railway station near Tadepalli and the nearest airport is Gannavaram which is at a distance of 22 km. Amaravati is envisioned to be a ‗People‘s Capital‘ built around sustainability and livability principles. It aims to be at par with global standards and has developed a masterplan with the assistance of the Government of Singapore. The new capital will be a center of economic activity, will create a range of jobs and will provide affordable and quality housing. Sustainability, efficient management and optimum utilization of resources will form an important pillar of this new capital. Objective: The project development objectives of the Amaravati Sustainable Capital City Development Project (ASCCDP) are to provide select urban infrastructure in designated locations of Amaravati Capital City, and to support the initial development of its institutional and governance structure.. 1.3 Components: The Amaravati Sustainable Capital City Development Project (ASCCDP) has five main components, as follows: (i) Basic Urban and Pro-poor Infrastructure Component, which will support the implementation of priority transport corridors and integration of 25 villages into the Amaravati Capital City development, by financing the construction of a priority road network and the upgrading of infrastructure in selected villages (e.g. water supply, sewage, village roads, and drainage); (ii) Green Climate Resilient Infrastructure, which will help build sustainability and climate resilience in Amaravati Capital City by supporting its integration with the natural surroundings, riverfront, and greenery; (iii) Citizen Benefit Sharing component, which will support government‘s efforts to implement benefit sharing measures for the residents of the capital city area, including but not limited to, training programs for farmers, landless families and other stakeholders, skill building programs, which will allow capital city residents to access jobs and new economic opportunities emerging in an urban context; (iv) Institutional and Fiscal Development, which will support government efforts to develop local government institutions and governance systems; and, (v) Project Management and Implementation Support. 1.4 The scope of this Resettlement Action Plan (RAP) is limited to impacts associated with Component 2 - Green Climate Resilient Infrastructure of the ASCCDP, as well as two associated 9 ASCCDP: Resettlement Action Plan for Flood Mitigation Works works carried out and financed by APCRDA that are linked activities to the World Bank financed. This RAP was prepared in accordance to the Resettlement Policy Framework (RPF) developed for the ASCCDP. The RPF describes the principles and approaches in avoiding, minimizing and mitigating adverse social impacts that may arise in implementation of proposed interventions financed by the World Bank. The RPF can be accessed at: https://crda.ap.gov.in/apcrdacommuni/media/asccdp/16082017/Amaravati%20RPF- Cleared%20by%20RSA.pdf 1.5 Land assembly mechanisms: To construct Amaravati City according to its Master Plan, the Government of AP needed to acquire and assemble 217 km2 of land. Land acquisition is governed by a legal framework consisting of the 2013 Land Acquisition, Rehabilitation and Resettlement Act (LARR Act 2013), the Andhra Pradesh Capital Region Development Agency (APCRDA) Act of 2014, the Andhra Pradesh Amendment Act of April 2018 (Act 22/2018) and Andhra Pradesh Capital City Land Pooling Scheme (Formulation & Implementation) Rules 2015. Three land assembly mechanisms are being used to assemble the land needed for the development of the Capital City, and more specifically for the flood management works are as follows: (i) Land Pooling Scheme (LPS) - innovative scheme whereby landowners voluntarily contribute their agricultural land (outside of habitations) in return for a smaller plot of urban, serviced land (returnable plot). The value of the returnable plot is expected to be higher than that of the land surrendered and to continue to increase further in value as development of the Capital City progresses. In addition to the returnable plots, LPS participants also receive a package of benefits described in more detail in Annexure 1. (ii) Negotiated Settlements (NS) – Land assembly mechanism applicable only for land and assets located within the village planning boundary. Government and land owners agree on a compensation package finalized in accordance with Section 124 of the APCRDA Act 2014 that is consistent with the provisions of the 2013 LARR Act, in which the compensation involves a land-for-land exchange rather than a cash compensation. The exchanged land is located within the Capital City area, and the exact location is negotiable. The compensation also includes a cash component, intended to cover costs of construction of replacement housing and a rental allowance for relocation pending construction of replacement housing. Though called ―Negotiated Settlement‖, the negotiation is over the terms of a compensation package that has been prepared in accordance with Section 124 of APCRDA Act 2014 and consistent with the Land Acquisition Act (Refer to Annexure 3 for details) Land Acquisition through 2013 LARR Act, by which compensation for lands acquired (replacement value and livelihood support) is provided following the requirements of the LARR Act 2013 (Refer to Annexure 2 for details). 1.6 The applicable entitlement framework for compensation and R&R assistance, as available in the RPF, is also provided here as Annexure 1, 2 and 3 for LPS, LA and Negotiated Settlement Policy, respectively, for ready reference. 1.7 Landless agricultural laborers: Landless laborers working in the capital city area lost their primary source of income as land was assembled for the development of Amaravati. As such, landless agricultural laborers have been directly impacted by the capital city development project, as land was transferred to APCRDA. A key consideration concerning landless laborers is therefore the extent to which alternative sources of income are available locally to replace the loss of income from agricultural jobs. 10 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 1.8 Although OP 4.12 applies only to the footprint of the World Bank financed project, it is challenging to differentiate between landless laborers affected by land assembly within and outside the World Bank project boundaries. Therefore, APCRDA has agreed that all landless families registered with APCRDA for pension by July 15, 2018 will be considered World Bank project affected people for the purposes of provision of livelihood restoration measures. The payment of pension and other livelihood-related benefits will be monitored for the list of registered landless families, as per the RPF. As of July 15, 2018, the total of number of landless households is 21,374. This RAP focuses on potential involuntary resettlement impacts on land owners in the Capital City area related to the Bank-financed flood mitigation component, and it includes provisions outlined in the RPF for all registered landless families (by July 15, 2018), which will be monitored under the ASCCDP. 1.9 The World Bank‘s policy on involuntary resettlement states as an objective that ―displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher.‖ In line with this objective, measures in addition to those already in place by APCRDA and covering all landless laborers are included in this RPF, to identify and to address, specifically, the needs of the most vulnerable subset of landless households, who need extra support to return to their levels prior to the announcement of the Capital City. The following typologies of landless households are recognized as those at the highest risk: (i) families with women head of household; (ii) households where family members have physical disabilities; (iii) families with chronic diseases; (iv) households with aging family member who cannot longer work (over 60 years old); (v) families with no alternative sources of income other than APCRDA pension; and (vi) families of Scheduled Castes/Scheduled Tribes whose sole source of income is APCRDA pensions. The methodology to identify vulnerable landless laborers and to monitor the engagement with landless laborers is described in Annexure 10. Investments covered under this RAP 1.10 The flood mitigation works to be financed by the World Bank under Component 2 of the ASCCDP include: (i) construction of reservoirs at Krishnayapalem, Neerukonda and Sakhamuru; (ii) widening and deepening of Pala Vagu2 and Kondaveeti Vagu; and (iii) construction of storm water canal from Nekkallu to Pichikalapalem. 1.11 Two ‗linked‘3 activities, specifically: (i) Undavalli Pumping Station; and (ii) works on the Kondaveeti Vagu, which stretches from Krishnayapalem Reservoir to Undavalli Pumping Station, are also included in this RAP. 1.12 The location and salient details of all the flood management investments are summarized in Table 1. A map showing the location of flood mitigation works is presented in Fig. 1. Table 1: Proposed Alignment of Flood Mitigation works 2Vagu means stream in Telugu 3 “Linked‖ activities are those associated with a World Bank project, which although not financed by the World Bank, are relevant to achieving the objectives of the World Bank financed project. In this case, two activities are relevant to the successful achievement of the objectives of Component 2 of the ASCCDP, although they are financed by the Government of Andhra Pradesh and implemented by APCRDA. 11 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Investment Approx. Closest villages Area in acres4 length (km) Undavalli Pumping Station - Undavalli 5 Kondaveeti Vagu (23.6 km) Undavalli to 3.8 Undavalli and Krishnayapalem 125 Krishnayapalem Krishnayapalem to 7.2 Krishnayapalem, Nowluru, 244.68 Neerukonda Kuragallu, Mandadam, Ayinavolu, Neerukonda to Sakhamuru 3.6 Sakhamuru, Thulluru, Nekkallu, 143.94 Ananthavaram Sakhamuru to 9.0 190.85 Ananthavaram Pala Vagu (16.7 km) Krishnayapalem to 9.3 Kondamarajupalem, Velagapudi, 235.59 Secretariat Mandadam, Venkatapalem, Krishnayapalem Secretariat to Dondapadu 7.4 Borupalem, Abbarajupalem, 167.1 Rayapudi, Kondamarajupalem Gravity canal (8 km) Gravity canal 8.0 Nekkallu, Thulluru, 235.67 Ananthavaram, Pichikalapalem Krishnayapalem Reservoir 190 Neerukonda Reservoir 440 Sakhamuru Reservoir 50 Total Length 48.3 km 2028.30 Note: Cells shaded in grey correspond to ―linked‖ activities Impacts 1.13 The proposed flood management investments will have overall positive social impacts, since their objective is to reduce the risk of flooding in the area, as well as improving ground water recharge potential, ecological and environmental improvements in the area, and increasing tourism potential around the reservoirs and along the canals. 1.14 Project affected families: Care was taken to ensure least adverse impacts and minimizing physical displacement as per OP 4.12. On the other hand, the project will create limited adverse impacts in the form of land assembly, which are managed and mitigated through safeguards instruments that were prepared in consistence with the Environmental and Social Management Framework, and with the Resettlement Policy Framework. 1.15 Details of the land assembly mechanisms that were used for the flood management investments designed under the ASCCDP are summarized in Table 2. The corresponding entitlement matrices for LPS, 2013 LARR Act, and NS are included in Annexures 1, 2 and 3, respectively. 4 length and area of the stretch of Flood Mitigation works taken up under Bank‘s project 12 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Table 2 – Land assembly instruments used for flood management investments, area requirements and number of families impacted. Land Assembly Number of families Area assembled5 Instrument impacted for flood (in acres) management works LPS 1,754 1,131.3 LARR Act 110 75.5 Negotiated 27 10.4 Settlements Government land* ----- 811.1** Total 1,891 2,028.3 Number of landless families impacted by land assembly processes: 21,374 (*) Occupants of Government land are assisted as per: (i) LPS guidelines if occupying agricultural land; and (ii) Negotiated Settlement policy, if occupying land in villages. (**) This includes 680 acres of land in reservoirs (Krishnayapalem, Neerukonda and Sakhamauru) and stream flow area and land adjoining the stream per irrigation records (Vagu land). Status of linked activities 1.16 The design of flood management infrastructure and works were optimized to reduce as much as possible the amount of land acquisition requirements, i.e. to minimize the area of land needed to be assembled with instruments other than LPS. As such, all land required for implementation of the two linked activities was: (i) owned by the GoAP (i.e. government lands); or (ii) surrendered by land owners under the LPS. Specifically, land required for the Undavalli station (in addition to government land) was assembled exclusively out of LPS. In the case of the stretch from Krishnayapalem reservoir to Undavalli pumping station, works will be restricted within the available width and land already assembled through LPS, thereby avoiding additional land assembly through LA or Negotiated Settlement (i.e. no physical displacement was caused and no land was acquired under LARR Act). 1.17 All land assembled for these linked activities has already been transferred to APCRDA. Because they are linked activities, the impacts of these two activities, in terms of land assembly and impacted people, are covered within this RAP. Specifically, all land owners who surrendered their land for these two linked activities are included in this RAP (as part as those impacted families under LPS). 1.18 These two linked activities (financed by GoAP) were initiated by the government as a priority, before the start of the ASCCDP, to ensure that the Capital City area was equipped to manage high flooding risks during the 2018 monsoon season. As a result, these activities are at advanced stages of implementation, as described below:  The Undavalli Pumping Station is close to completion, and is expected to be inaugurated in mid-August 2018. The World Bank team has been monitoring the implementation of works and ensuring they are consistent with World Bank policies, as per this RAP. 5 This includes the impacts from land assembled for the linked activities. 13 ASCCDP: Resettlement Action Plan for Flood Mitigation Works  Work in Undavalli -Kondaveeti Vaagu stretch has initiated within the existing (Government) lands. Rather than making a wider channel, the design has involved deepening the existing channel and thus avoiding displacement impacts. 1.19 In the event that land acquisition or physical displacement are encountered while executing the works in Undavalli-Krishnayapalem section (not anticipated at the time of preparation of this RAP), mitigation measures will be proposed through a supplementary RAP, as per RPF provisions. These supplementary RAPs will be shared and reviewed by the Bank. Unclaimed lands / unknown owners 1.20 Lands not occupied, not claimed by anyone and no person of interest could be identified based on examination of records are notified under LARR Act 2013... These lands amount to a total area of 0.31 acres. The compensation would be deposited in LARR Authority keeping it open to settle any future claim. . Common Property Resources 1.21 Three common property resources, including a burial ground in Sakhamuru, a burial ground in Mandadam, and a private temple in Mandadam (see Table 3). In consensus with the community, it was agreed that the area of the two burial grounds located outside of the project affected area was sufficient to accommodate the community needs, and that there was no requirement of relocation of either of the burial grounds. The temple will be relocated suitably in consensus with the community. Table 3: List of Common property resources impacted under flood management works Area Action plan Village Type of property (Acres) Consultations will be held 1 Mandadam Temple 0.19 with community for its relocation 2 Mandadam Burial Ground 0.73 In consultation with community it was agreed that area of the two burial grounds located outside of 3 Sakhamuru Burial Ground 0.26 the project affected area was sufficient to accommodate the community needs 1.22 An NGO will be engaged by August 15, 2018 to support APCRDA in the implementation of this RAP. The selected NGO will support in mobilisation of the interested vulnerable people for additional support. The details of Project Affected Families by impact category is summarised in chapter 2 and listed in Annexure 7. This list may undergo change during implementation based on additional impacts encountered during the implementation or any changes required based on the objections received once the list is disclosed. 14 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Figure 1: Map of Capital Area with proposed alignment of Flood Mitigation works Final 15 ASCCDP: Resettlement Action Plan for Flood Mitigation Works II. SOCIAL IMPACT ASSESSMENT Magnitude of Social Impacts 2.1 The breakdown of the land assembly requirements (village-wise) for flood mitigation investments covered under this RAP is summarized in Table 4 below. Table 4: Land requirement for Flood Mitigation works Land Land assembled Land in proposed Govt. / Grand Village Name through LPS Village under LA others Total with APCRDA areas Act Abbarajupalem 10.97 0.11 0.73 11.81 Ayinavolu 221.87 2.82 224.69 Anantavaram 50.59 0.17 2.39 53.15 Borupalem 13.33 0.26 13.59 Kondamarajupalem 27.89 3.15 1.03 32.07 Krishnayapalem 66.82 203.64 270.46 Kuragallu 258.33 0.05 16.86 275.24 Neerukonda 440 440.00 Lingayapalem 2.04 1.35 3.39 Malkapuram 0.03 0.17 0.20 Mandadam 61.88 3.53 10.21 4.22 79.84 Nekkallu 37.59 6.17 4.95 48.71 Nowluru 54.9 0.15 5.61337 60.66 Pichikalapalem 34.11 0.08 2.73 36.92 Rayapudi 79.08 11.92 0.02 3.99 95.01 Sakhamuru 24.87 0.88 66.11 91.86 Thulluru 51.84 6.56 58.40 Velagapudi 17.34 7.64 0.15 0.62 25.75 Venkatapalem 18.12 0.56 2.4 21.08 Undavalli 29.396 29.39 Penumaka 99.73 39.67 16.63 156.03 Grand Total 1131.30 75.46 10.38 811.11 2028.25 2.2 The village wise list of project affected land owners is summarized in Table 5, below: Table 5: Details of affected landowners for flood mitigation works 6 This extent includes 5 acres towards Undavalli Pumping Station. This extent of 29.39 acres pertains to linked activity. 16 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Number of Number of Number of Number of Total families families in families families number Village Name affected by villages, headed by affected by of 2013 LARR affected by women out LPS families Act NS of Total Abbarajupalem 27 1 28 11 Ayinavolu 263 263 98 Ananthavaram 50 1 51 19 Borupalem 37 0 37 12 Krishnayapalem 124 124 Kondamarajupalem 57 2 59 57 Kuragallu 299 1 300 106 Lingayapalem 4 1 5 2 Malkapuram 2 2 1 Mandadam 91 5 24 120 29 Nekkallu 71 9 80 24 Nowluru 94 1 95 31 Pichikalapalem 109 1 110 36 Rayapudi 180 12 2 194 37 Sakhamuru 37 4 41 8 Thulluru 98 98 Velagapudi 67 10 1 78 2 Venkatapalem 30 2 32 0 Penumaka 112 58 170 44 Undavalli 4* Grand Total 1,754 110 27 1,891 517 (27%) *Linked activity impacts 2.3 Village-wise list of people affected by flood mitigation works in private lands is included in Annexure 7. The list of landowners under LPS category impacts as well as the list of Project Affected People in village areas is published at: https://crda.ap.gov.in/apcrda/userinterface/admin/PAFData_Flood.aspx 2.4 The list of project-affected people was published as a handout/brochure along with other details regarding project, resettlement plan, benefits and was also disclosed in the website for easy access and to facilitate the hearing of any objections. A supplementary list will be prepared if new impacts are encountered during the implementation. The entitlement matrices under LPS, 2013 LARR Act, and Negotiated Settlement are provided respectively in Annexure 1, 2 and 3 respectively. 2.5 Impact of isolated structures: Among 1,754 land owners who have joined land pooling within the project foot-prints, there are no landowners who have isolated structures. Structure impacts, if identified during implementation, will be addressed as per the provisions of LPS / Negotiated Settlement Policy. 17 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 2.6 Minimization of land requirement under the project: Detailed modelling studies were conducted to ascertain the quantum of waters required to be handled during peak design flood scenarios, based on which the engineering studies were carried out. Models included study of the existing alignments, requirement of increasing the top width and bottom width of channels, marginal re-alignments, strategically selecting location and extent of reservoirs. These measures are expected to mitigate the impact of flooding in the Capital City area. The extent of the land assembly requirements was kept in mind while finalizing the various options for implementation. Consultations were held during finalization of the Master Plan. Based on the feedback / objections / suggestions, modifications were carried out to ensure that least disturbance / displacement is caused to the existing settlements. An exhaustive process of alignment, re-alignment revising the detailed Project Report, fixing the draft re-alignment on the ground, conducting field study to identify and verify the structures that might potentially come under displacement, a marginal adjustment of the draft final alignment with inputs from field, have all helped in avoiding the structures, common property resources and others Through design modifications and realignments, the initial estimates of land requirements were reduced by roughly 20 percent. Land assembly needs were limited to about 2,000 acres, of which: (i) land to be acquired through LA is 75 acres (3.77 percent); and (ii) land in village areas that needs to be acquired (through NS or LA) is 10 acres (less than 1 percent). Furthermore, impacts of common properties were reduced to three. Land assembly through LPS A total of 1,131.3 acres of agricultural land needed for flood management works were assembled via LPS. That land has already been surrendered to APCRDA by land owners, who have been receiving annuities and benefits packages since they gave up their land. Of the 1,754 land owning families who joined the LPS, Land Pooling Ownership Certificates have been awarded to 1533. Land Acquisition and Negotiated Settlements 2.7 The proposed Flood Mitigation works involve 10.38 acres of private land in habitation areas and will physically displace 27 families at Mandadam, Rayapudi-1 and Velagapudi villages as noted in Table 6, below. The total population to be displaced is 62 people based on average family size of 2.297 in the sample household survey. The impacts to houses as well as buildings and any units will be considered as full and whole unit will be acquired and partial acquisition of units will be avoided. All impacted households within village boundaries will be entitled for compensation to land and structures and resettlement assistance. Table 6: Village-wise Physical Displacement No. Village (Habitation area) No. of PDFs 1. Mandadam 24 2. Velagapudi 01 3. Rayapudi – 1 02 Total 27 7 The family size of 2.29 is extracted from the survey data wherein the response from the PDFs surveyed has been analysed and the average family size is found to be 2.29. Based on a separate Survey of PDFs of Roads Network, the family size is 3.43 18 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Development of Resettlement sites 2.8 PAFs in villages who have been physically displaced by the construction of the project are being relocated by giving resettlement plot for self-construction of replacement home (as per GoAP norms), as well as compensation for the structural loss. The sites for allotment of resettlement plots are being identified nearby existing villages. Resettlement sites are equipped with / have access to roads, power connections, drinking water, drainages, etc.. Soon after the consent for Negotiated Settlement is received, resettlement plots are allocated through a lottery process. The base resettlement assistance amounts are paid and the difference to updated unit costs will be paid immediately after approval of Project. Post resettlement support 2.14 The resettlement areas are identified within the same village and displaced families are expected to move less than 1-2 km. The post resettlement support includes but not limited to assisting people to have access to basic facilities, transfer of ration cards and other documents, assistance in admission to schools, awareness on health and hygiene, management of common amenities, and any other assistance that the people may be required once they shift to new houses. The terms of reference for NGO services will include providing post resettlement support. The resettlement support may be required for a period of one year actively beyond which the support will be provided on requirement basis. The costs for resettlement support for the first year are included in RAP budgets and beyond this period, it will be provided with GoAP / APCRDA funds. Landless Agricultural Laborers 2.9 Landless laborers working in the capital city area lost their primary source of income as land was assembled for the development of Amaravati. As such, landless agricultural laborers have been directly impacted by the capital city development project, as land was transferred to APCRDA. A key consideration concerning landless laborers is therefore the extent to which alternative sources of income are available locally to replace the loss of income from agricultural jobs. 2.10 Although OP 4.12 applies only to the footprint of the World Bank financed project, it is challenging to differentiate between landless laborers affected by land assembly within and outside the World Bank project boundaries. Therefore, APCRDA has agreed that for purposes of this project, all landless families registered with APCRDA for pension by July 15, 2018 will be considered project affected people for the purposes of provision of livelihood restoration measures. The payment of pension and other livelihood-related benefits will be monitored for the list of registered landless families as per the RPF. As of July 15, 2018, the total of number of landless households is 21,374. Landless agricultural laborers working in the Capital City area are eligible to receive a combination of livelihood restoration benefits that includes: (i) payment of pensions @ INR 2,500 per month per family for a period of 10 years, with annual adjustment linked to inflation index; (ii) employment under the Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) for up to 365 days per year; (iii) facilitate access to interest-free loans for setting up enterprises; (vi) access to skill upgrading and training opportunities; (v) provision of subsidized food; and (vi) free access to medical and educational benefits in designated facilities. 19 ASCCDP: Resettlement Action Plan for Flood Mitigation Works When livelihood restoration benefits are fully accessed by landless laborers, landless households are in a financial situation comparable or in some cases better to their status pre- displacement. However, some landless families may have challenges accessing all the livelihood restoration benefits, in which case there would be people in situation that may be worse than their pre-displacement status. 2.11 The World Bank‘s policy on involuntary resettlement states as an objective that ―displaced persons should be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the beginning of project implementation, whichever is higher.‖ In line with this objective, measures in addition to those already in place by APCRDA and covering all landless laborers are included in the RPF and reproduced in Annexure 10 of this RAP, to identify and to address, specifically, the needs of the most vulnerable subset of landless households, who need extra support to return to their levels prior to the announcement of the Capital City. The following typologies of landless households are recognized as those at the highest risk: (i) families with women head of household; (ii) households where family members have physical disabilities; (iii) families with chronic diseases; (iv) households with aging family member who cannot longer work (over 60 years old); (v) families with no alternative sources of income other than APCRDA pension; and (vi) families of Scheduled Castes/Scheduled Tribes whose sole source of income is APCRDA pensions. 2.12 APCRDA has established a methodology to identify the vulnerable landless families, within a total of 21,374 landless households as of cut-off date. Using this methodology an assessment was carried out by APCRDA in June - July 2018. A total of 857 vulnerable landless families were identified, living in the 25 villages of the Capital City area. While they are similar in nature to some of the general initiatives that APCRDA is implementing across the Capital City for all landless laborers, additional measures specifically tailored and targeted to the needs of the identified 857 families have been designed and include: (i) expanding safety nets for targeted; (ii) skill training for those eligible, tailored to supply of jobs; (iii) job dashboard with information on employment opportunities in villages across the Capital City; (iv) safe, public transportation options for women to travel for work to other locations; and (v) creation of more employment opportunities under MGNREGA within and nearby area of Capital City. 2.13 Existing Self Help Groups (SHG) will, in coordination with APCRDA, engage in reaching out to the targeted households and supporting them as these proposed measures are rolled out. Specifically, they will, first, monitor the implementation of measures targeted to the vulnerable landless households to ensure that measures: (i) provide additional opportunities for target vulnerable landless families to improve their livelihood; and (ii) address some of the bottlenecks in accessing existing programs. Second, activate monitoring mechanisms to verify and calibrate the success of proposed measures, aiming at reducing the number of vulnerable landless families with time; and third, engage with communities and identify new potential families that may need additional assistance. It is expected that the original number of vulnerable landless families will reduce gradually, as target support measures bridge existing gaps and allow families to access opportunities to improve their livelihoods. The monitoring mechanism is in place, building on the present and the penetration of SHGs and of NGO/consultants, will provide a channel to identify on a continuous basis, families that may fall into a vulnerable state. 20 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 21 ASCCDP: Resettlement Action Plan for Flood Mitigation Works III. CONSULTATIONS / BASELINE SOCIO-ECONOMIC CHARACTERISTICS OF AFFECTED FAMILIES Introduction 3.1 During February and March 2015, a census socio-economic survey was conducted by APCRDA to collect information related to all households in Amaravati city. The survey was conducted by well qualified and trained field officers/investigators of District Rural Development Agency (DRDA) of Guntur District, on behalf of APCRDA, in all 25 villages of capital city. A unique ID was generated for each household in the capital city. The survey documented all household living in the capital city. Final 3.2 PAFs data corresponding to 1891 families affected by flood mitigation works financed under the World Bank project (under LPS, LA or NS mechanisms) have been obtained from within this socio-economic survey. Subsequently, a sample socio-economic survey was carried out in January 2018 among the project affected people. This sample survey attempted to cover among those residing within capital city area . It is observed that 1106 out of 1891 are absentees. The list of PAFs and physically displaced families is included in Annexure 7 while the survey findings of the socio-economic survey is presented in Annexure 4 of this RAP. 3.3 Information on non-resident landowners‘ is captured from the land registers available with the Competent Authorities (CAs) and Sub-registrar offices. In addition, paper notices and pamphlets were circulated to spread awareness about identifying non-resident land owners. There are 15 parcels (3.49 acres in the project footprint) that had no information on landowner. This is an ongoing effort until all the non-resident land owner details are obtained. 3.4 The methodology and approach followed for this survey is outlined below: a) Lists of PAFs (losing land and / or structures) were collected from the respective Competent Authorities. The survey was carried out among these PAFs. Subsequently, it was confirmed that some of these PAFs have opted for LPS, b) Coordinating with CAs for prior appointment to conduct surveys in the affected villages, c) Information about survey to PAFs by the CAs, d) Visit the villages on the appointed dates and conduct survey, and e) Revisit the villages in case of respondents not present first time. Key baseline socio-economic indicators 3.5 Sample size: The sample size of the socio-economic survey carried out for this RAP is as follows, also as shown in table 7 below.  The share of non-LPS families covered is 41% of residents (56 of 137 families).  The sample of LPS families covered is about 15% (96 out of 648 families). Table 7 Sampling for socio-economic survey Affected No. of Sample Size Remarks number of residents* (against families column.2) LPS 1754 648 (37%) 96 (15%) 1106 (63%) are 22 ASCCDP: Resettlement Action Plan for Flood Mitigation Works absentees Non-LPS 137 137 56 (41%) (LARR Act & Negotiated Settlement Policy) Total 1891 785 (42%) 152 (19%) 1106 (58%) are absentee landowners *This refers to those who are currently residing in capital city area. The remaining are non-residents who have moved out of capital city area. The non-resident details among Non-LPS families is not available 3.6 The survey attempted to cover the maximum number of total affected families (1,891). However, it was found that 1,106 families (58% of the total) were absentee landowners residing outside of the capital city, and could not be contacted for the survey. Among those residing within the capital city. i.e. 785 families, the household survey was carried out among 152 families (19% of the total). 3.7 The household survey is carried out primarily to assess the living standards that provide basis to evaluate future living standard improvement. The household survey is supplemented by 20 focus group meetings attended by 165 people, and 4 public consultations with 270 participants. Specifically, the participation for LARR is low as families under LARR preferred the channels of focus group or public consultation meetings rather than individual household surveys. However, non-participation in the household survey does not affect the number of beneficiaries or them accessing entitlements, benefits available to PAPs under all 3 land assembly mechanisms. 3.8 The census data related to individual details, land lost and various benefits, etc., are available to all families. The identification details for all LPS farmers would be available upon the annuities/pensions paid and returnable plots allotted. For Negotiated settlement, all details on the affected family would be available upon individual negotiated agreements signed and consent applications submitted. In case of LARR act, the land acquiring notifications, compensation awards will automatically capture all affected people‘s details, which would be available with APCRDA. 3.9 The following are the key findings from the sample socio-economic survey (2017) among the non-LPS families (N=56). The average values for key indicators is summarized below. Refer to Table 8 and Annexure 4 for more details8.  About 29% of the PAFs are Female Headed Households  About 67% of the PAFs are illiterate  About 96% of the PAFs have own houses and among them 64% have pucca houses.  100% of the PAFs have individual latrines, electrified houses, piped water supply and LPG as fuel for cooking.  The average household monthly income of the PAFs stands at INR 52,083.  All PAFs will be moved to resettlement sites within their village or close to their villages. Table 8: Key baseline socio-economic indicators among non-LPS families 8The surveyed data is available in project files for any further reference. 23 ASCCDP: Resettlement Action Plan for Flood Mitigation Works S. No. Indicator Unit Value/Figure a) Income (N9 = 56) 1 Annual family income Average INR 52,083 2 Level of Indebtedness % 64% 3 Below Poverty line10 based on the possession of % 86% white ration cards b) Economic Activity (N = 56) 4 Farmers % 34% 5 Service (Private and Government) % 13% c) Housing (N = 56) 6 Permanent with concrete roof % 20% 7 Owner Houses % 96% 8 Having separate toilet % 100% 9 Houses electrified % 100% 10 Access to piped water supply (HSC11) % 100% 11 LPG as fuel for cooking % 100% d) Demographic Details 12 Family size (N = 56) Average 212 13 Women headed household (N = 56) % 29% 14 % families with Challenged people 0 e) Standard of Living (N = 56) 15 Having Two-wheeler % 1.79% 16 Having Four-Wheeler % 3.57% 17 Having Ration card % 90% Gender Disaggregated Data and Women’s concerns 3.10 The household data collected comprised details about gender disaggregated data of the PAFs surveyed. Out of 56 respondents among non LPS families, 26 were women. In addition, 165 people including 17 women attended in the focus group meetings. Further, among those who received skill training, 788 (52%) out of 1,121 are women (data not separately segregated for project footprint). 3.11 The trainings provided to women include Java in Information Technology, Jute Bags, Automation, Electrical, Logistics, Land Survey, Herbal Making, Maggam Work (weaving), Mechanical, LMV Driving, English Employability skills, Beautician, Accountancy, Horticulture, Mobile technician, 2-Wheeler Technician, AC Technician, Fashion designing and tailoring, etc. As part of LPS benefits, free education for degree, post-graduation and other professional courses, applications have been offered. A total of 49 applications were received by July 2018, of which 25 are from women (51%). Among pensioners, 60% are women. As part of RAP implementation, gender disaggregated data will be recorded and highlighted in the progress reports, exclusive to the project footprint. 9 N = Baseline number of sample who responded to the survey 10 Defined as family with annual income less than INR 60,000 in rural areas and INR 75,000 in urban areas 11 HSC - House Service Connections 12 Demographic details for family members is provided at Annexure 4 24 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 3.12 The gender gaps identified during focus group meetings include: (i) livelihood gaps for women with lack of alternative employment opportunities due to absence of suitable skills; (ii) women receive lower daily wages (50% lower) than men, because they are less organized in groups/committees and thus have lower bargaining power; (iii) women have lower literacy rates (28% against 33% by men); (iv) large proportion of agricultural laborer are women who find it difficult to get job in the changing urban setting; (v) long travel to avail MNEREGA works; (vi) awareness, capacity and financial literacy gaps among women. To address the above gaps, APCRDA is taking measures, including: (i) organizing exposure visits to women to various skill development and women institutions, (ii) engaging a NGO having expertise in women livelihood sector to assess and develop suitable skills training program that match employment opportunities; and (iii) organizing financial literacy awareness sessions among women. Consultations 3.13 As part of RAP preparation, multiple consultations (in different formats) were held, including: individual discussions, focus group discussions, public consultations amongst a variety of stakeholders including women, economically backward communities, vulnerable and marginal population, NGOs, CBOs, etc. APCRDA ensured distribution of Telugu version of the invitation / subject matter for discussion prior to the consultations. The draft RAP was disclosed by APCRDA ahead of consultation meetings and summary in Telugu was also shared in the public consultations. A detailed overview of consultations is provided in Annexure 5. In addition to consultations described in this RAP, on-going consultations will be conducted twice a year during the project implementation period, to share the implementation progress of the RAP as well as project and seek their feedback. Focus Group Discussions 3.14 A total of 20 Focus Group Discussions (FGD) were conducted in 14 villages at different locations. Around 165 people consisting of PAFs and landless pensioners, women‘s groups, Scheduled Castes / Scheduled Tribes community, physically displaced families, families affected on government lands, etc. The summary of these FGDs is given below and the details of the discussions are provided in Annexure 5A13.  Many of the PAFs indicated that they are aware of the project and its impacts. However, they requested for additional inputs on entitlements. They requested that this information be given through community meetings, print and electronic media and other communication materials like pamphlets, FAQ booklets, etc. They would like this material to be in easily understandable terms with examples.  The PAFs want information on the implementation schedule with details such as a) when the acquisition will be done, b) when they would be notified to vacate their residences, c) how much time will be given for them to vacate the houses, d) when the rehabilitation plots will be allotted to them, e) whether they would be relocated as a community as they are now, f) how much time will be given for building houses at the resettlement locations, g) whether they can take the salvageable material from the demolished residences, etc. 13The attendance sheets and the detailed pictures of these FGDs are available in the project files for reference. 25 ASCCDP: Resettlement Action Plan for Flood Mitigation Works  The PAFs requested that annuity be provided to them on par with other assigned LPS land owners. As annuity is not being paid to the occupants who are on government lands.  The PAFs requested for clarity on the eligibility of occupants based on which how they are given residential returnable plots 250 sq. yd. per acre.  The minimum rate of yearly payment of annuity to all landowners losing land (INR 30,000) did not apply to one individual case, as the individual owns multiple government land scattered in four different locations.  Providing infrastructural facility to all LPS returnable plots needs to be planned as soon as possible.  Loss of Agricultural activity presents challenges to the livelihood of farmers.  NTR Sujala Sravanthi scheme is successful in supplying drinking water to Sakhamuru village.  Water for daily use is not guaranteed, with more acute shortage during summer. This calls for exploitation of alternative water source from either the pipe line arranged at VIT or SRM or Sakhamuru park where water pipes are arranged.  Returnable plots registration progress is slow.  Diversion measure needs to be in place to divert the flood water from Vykuntapuram into the Krishna River.  Vaagu digging soil must be used for filling the low-lying areas where plots are in existing village nearer to Vaagu.  The PAFs requested for more information on the Buffer Zone for the flood mitigation Measures (where residential construction cannot take place), which is meant for the purpose of greenery and for strengthening of Bunds of the proposed channels.  Revetment of Channels is necessary due to potential erosion of the loose black soil during floods.  The PAFs requested that the Gramakantham burning issue be solved as soon as possible.  Poles for the plots need to be placed for demarcation purposes. Public Stakeholder Consultations on RAP 3.15 Four Public consultation workshops on this RAP were held on 6th January 2018 at Mandadam, Thulluru, Neerukonda and Krishnayapalem. The dates of the meetings were announced in advance in English and Telugu newspapers, as well as on the APCRDA website. In addition, draft safeguards documents were disclosed by APCRDA prior to the consultations. Around 272 people representing different impact groups from different villages attended the consultations. About 388 written suggestions/objections were also submitted. Out of these, only 13 were received from World Bank PAFs. Comments received from the 13 PAFs during consultations refer to generic issues such as land requirements for capital city; requests for clarifications and additional information, and some related to suggestions on the provisions in RPF/RAP. None of these PAPs have approached the grievance redress committee. The local media widely covered the outcome of the consultations (see Annex 5a for more details), which is summarized below. 3.16 Comments expressed on the Flood Mitigation works are as follows: (i) The people objecting the Flood Mitigation works argued that it was against the judgement of the National Green Tribunal (NGT) and the Environmental Act, WALTA Act and NDMA Act; (ii) people argued that as per the NGT guidelines, the flood banks and vaagu lands should not be taken up for the Flood Mitigation works (ii) people complaint that the compensation being paid is not genuine and also there are a few title related issues. They also expressed the willingness to join 26 ASCCDP: Resettlement Action Plan for Flood Mitigation Works LPS provided the compensation is increase; (iii) there were concerns from some of the landowners about the Gramakantham issues and the insufficient pension paid to the landless considering the land appreciation; (iv) there were complaints from landless for not being able to find any work as the agricultural activities discontinued in capital city region; (v) there were public complaints on the issue of drinking water insufficiency; and (vi) there were concerns on the issue pertaining to lift irrigation to lands in Yerrabalem. 3.17 Comments expressed on the RAP and EMP were mainly focused on the alignment and the water storage capacity of the proposed reservoirs and the area/ extent covered by these reservoirs. There were no major comments/ suggestions on the improvement of RAP and EMP. 3.18 Additional comments. The public expressed that the sub-component of flood mitigation works is a good initiative from the government side to preserve water and as a precautionary measure to avoid flooding in the capital city. They expressed that another reservoir at Ananthavaram will also be helpful in catering to the drinking water needs of the capital city population. The public also mentioned that the R&R colonies are to be provided to PDFs with all the facilities on par with the LPS layouts. They also expressed that the Karakatta bridge has to be strengthened. Additional protection measures and safety measures to avoid disaster has to be taken up and included in the EMP. 3.19 A summary of the response given by APCRDA is presented below, and the detailed actions taken / plan of action initiated from the outcomes of the consultation meetings are provided in Annexure 5:  APCRDA clarified that no direction has been given by NGT to respond to the above views of the participants for not taking up any flood works.  APCRDA also clarified that it has acted in accordance with the applicable stipulations mandates, and regulations, and following business as usual practice of other agencies, i.e. Irrigation Department  In response to impacts due to flood works - APCRDA has avoided physical displacement by restricting the widening in Krishnayapalem to Undavalli stretch to within the available right-of-way of the existing stream, as noted in irrigation records. This is the normal practice followed by the Irrigation Department, who takes up various projects on these channels (capital or no capital scenario) routinely as per irrigation manual.  Regarding Vagu lands that cannot be used for flood works - it was clarified that Vagu lands adjoining the streams and attached to streams are, as per revenue records, vested with the Irrigation Department (now with CRDA), and are meant to be used for ensuring the free flow of water by taking up required improvement works. The plans and designs proposed on these vaagu lands are as per approved Detailed Project Reports (DPRs), which are vetted by committee established for this purpose. NGT has directed that GOAP will constitute a ―Supervisory Committee‖ and ―Implementation Committee‖ to carry out the works as per the conditions stipulated in the Environmental clearances. The GoAP has constituted these committees and periodical reports on the works carried out in capacity city are being submitted to these committees.  Regarding drinking water issue - GoAP initiated a new drinking water scheme to address the drinking water problem. People who participated in consultations were mainly from the villages of Undavalli and Penumaka where the Flood Mitigation works are limited to within available width and thus avoided physical displacements and additional land acquisition. 27 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Some people wrote to APCRDA subsequently on the impacts, which was not resulted from the flood works and are outside of the project impact area. This is outside the purview of the proposed Bank project. 28 ASCCDP: Resettlement Action Plan for Flood Mitigation Works IV. INSTITUTIONAL AND IMPLEMENTATION ARRANGEMENTS Institutional Arrangements 4.1 All impacts associated with the land required for flood mitigation works will be managed by APCRDA and through District Administration as appropriate. The following institutional arrangements are in place: Andhra Pradesh Capital Region Development Authority (APCRDA): CRDA passes resolutions for acquisition of lands and prescribes rules/ regulations for implementation of LPS/ Negotiated Settlement under the Act. The Government has sanctioned staff f o r APCRDA for implementation of AP Capital City Development Project. The Commissioner, APCRDA, Additional Commissioner, Director- Final Strategy, Director-Planning, Director-Estates, Director-Economic Development, Director- Information Technology, Director-Finance, will support the Competent Authorities under Land Pooling and Land Acquisition. The Commissioner, will be the approving authority for sub-project specific RAPs and EIA/EMP for the project. The Competent Authority, Tahsildars, Deputy Inspector of Surveyors, Surveyors, Deputy Tahsildars, Computer Operators formed into one unit and positioned in 25 villages in Capital City Area to work under the administrative and functional control of the District Collector, Guntur the District Collector is the appropriate g o v e r n m e n t for Land Acquisition and the Joint Collector, Guntur who is the Project Administrator for AP Capital city project for implementing RAP. The differential costs to meet RPF provisions will be approved by the Authority. Implementation Mechanism for LPS / LA / Negotiated Settlement Policy 4.2 Implementation Mechanism for LPS. The process includes several steps and various agreements and consultations. The key steps include notification of LP scheme, hold consultations and hear objections/suggestions, invitation to participate in LPS, execution of development agreement, formulation of redevelopment schemes, allotment of re-developed plots and registration of redevelopment plots in favour of land owners and who surrendered land in favour of APCRDA. As per Section 57(4) of the APCRDA Act 2014, the Land Pooling Ownership Certificate (LPOC) shall be the conclusive evidence of the title of the property in respect of the reconstituted plot / land and shall be eligible for transfer of rights of the property in accordance with the provisions of the Registrations Act 1908. The issuance of LPOC is equivalent step of payment of compensation under LARR Act 2013. The entitlement matrix for LPS is included in Annexure 1. 4.4 Implementation Mechanism under LAR&R Act, 2013. Social Impact Assessment (SIA) Study is the first step for Land Acquisition under LARR Act 2013 to document the impacts and assess the land acquisition requirements and conclude that the benefit of project outweigh the social costs and adverse social impacts. Once the SIA report is heard through public hearing, reviewed by an Expert committee and approved by the Government, the Preliminary and Public Notification on LA process process is initiated. The lands required for construction of Capital City Development Project would be provided through LPS / LA / Negotiated Settlement Policy. The key outcomes of SIA, public hearing and Expert committee‘s views and appropriate Government‘s approval of land acquisition inputs will be summarized in RAP. The detailed steps and process to be followed for land acquisition and entitlements matrix is outlined in Annexure 2. 4.5 Implementation Mechanism under Negotiated Settlement Policy. The areas of 29 ASCCDP: Resettlement Action Plan for Flood Mitigation Works requirement of land in the village settlement zone are not covered by Land Pooling Scheme. Any land required for formation of Roads, Metro Lines etc., within the R1 zone is contemplated to have a Negotiated Settlement. Section-124 of APCRDA Act, 2014 enables the Authority to acquire any property by way of negotiated settlement and in cases where the negotiated settlement fails the provisions of LA R&R Act, 2013 would be made applicable as per requirement of development plan.  Once the negotiating committee and displaced family negotiates on package offered by District Collector, the agreed assistance will be reflected in the negotiated agreement.  Negotiated settlement policy is estimated to be not lower than the provision of LA R&R Act as land to land lost in village site/ habitation is being allotted in a developed Rehabilitation Centre and it is optional. 4.6 Interested persons may come forward to opt for negotiated settlement policy instead of LA. The Competent Authority representing the APCRDA will enter into negotiated settlement through process of negotiation by the Committee constituted by District Collector consisting of land administration and technical persons as members. The compensation and assistance under negotiated policy includes:  Land to land for footprint area of houses/ house sites excluding common areas  Non-Agricultural land – land to land with as is use condition  Two times of the estimated value of the house/ structures as per PWD norms without deducting depreciation and allowing salvage to meet the RP cost  Cost of construction of alternative houses /shops as per GoAP norms; and, 4.7 Those who are not having formal legal rights over houses would be rehabilitated under affordable housing schemes of Government of Andhra Pradesh duly paying structure value. The detailed steps in implementation of the Negotiated Settlement policy are provided in Annexure 3. Updated Resettlement unit costs 4.8 The project has adopted the unit costs for R&R assistance as available in the LARR Act, 2013 w.e.f. 1.1.2014, for R&R entitlements compensation under LARR Act. and w.e.f 19.04.2017 for Negotiated Settlement. In case of LA, the revised unit costs notified by GoAP, as per Section 31 of the LARR Act 2013 will be applicable from the date of notification. Proposals are submitted to government in this regard. In case of Negotiated settlement, the project has adopted the unit costs for R&R assistance from negotiated settlement Policy of GoAP, wef from 19.04.2017. Inflation indexation will be made w.e.f 01.04.18. The difference to updated unit costs will be paid immediately after approval of Project for the lands covered under the Project footprint. Flood Mitigation Works Encumbrances 4.9 Village-wise encumbrances from flood mitigation works are identified survey-number wise and recorded in the Field Measurement Book. 4.10 Details of the project-affected encumbrances are presented in Annexure 9. DGPS coordinates of each parcel affected are available in GIS files. The contractors, ADC will undertake joint survey after the contracts are awarded and record the encumbrances on the ground and prepare a time table for their mitigation so as to handover the encumbrance lands to enable APCRDA/ADC to hand over the lands within the time table proposed in the 30 ASCCDP: Resettlement Action Plan for Flood Mitigation Works contracts. Coordination with District Administration for Land Acquisition 4.11 The following officers will have the required administrative powers to deal with the land acquisition and related activities. Table 9: Roles and Responsibilities of various agencies in land acquisition processes Officers Roles and Powers Government  Notify District Collector as appropriate Government.  Designates Special Deputy Collectors as Collector (LAO) under the Act. Commissioner, AP CRDA  Requisition Authority on behalf of AP CRDA / Government. Commissioner, R&R  Selection of SIA Team and Terms of reference  Approval of R&R Scheme. District Collector  Notify 4(1) Notification for commencement of SIA.  Appointment of Expert Group.  Decision on Acquisition of Land.  11(1) PN Notification  Decision on objections against 11(1) Notification  Review of draft R&R Scheme with Project Level R&R Committee  Publication of Declaration u/s 19  Approval of preliminary valuation  Approval of draft Compensation Award Project Administrator  Conduct of Socio Economic Survey  Preparation of R&R Scheme  Approval of draft R&R Award 31 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Officers Roles and Powers Land Acquisition Officer  Conduct of Social Impact Assessment (LAO)  Submission of report u/s 8(2)  Conduct of Gram Sabha u/s 11(2)  Conduct of Survey u/s 12 and 20  Hearing of Objections on 11(1) PN Notification  Assist Project Administrator for conducting SES and preparation of R&R Scheme  Conduct of Award Enquiry u/s 21  Preparation of valuation statements u/s 26 to 30  Passing of LA R&R Award u/s 23 and Individual Compensation Awards u/s 30(2) and Individual R&R Awards u/s 31(1)  Passing consent Awards as per State Level Negotiation Committee  Payment of compensation, R&R benefits and providing rehabilitation entitlements  Taking possession  References to LA R&R Authority and Depositing Amounts in disputed cases. R&B Department  Preparation of estimates for Residential Houses / Structures Horticulture / Forest /  Estimation of trees and tree topping Sericulture Departments Ground Water  Estimation of well value Department Any other  As per requisition of District Collector. Department Coordination with Civil Work Contracts 4.12 RAP implementation will be linked with implementation of civil works to ensure that compensation is paid before land is taken from PAFs. The following coordination mechanisms will be maintained, unless otherwise agreed between the executing agency and APCRDA, and in consultation with the World Bank.  In all instances, the implementation of resettlement activities is linked to the implementation of the contracts to ensure that displacement or restriction of access does not occur before necessary measures for resettlement are in place. For impacts covered under the RAP, these measures include provision of compensation and of other assistance required for relocation, prior to displacement, and preparation and provision of resettlement sites with adequate facilities, where required. Taking of land and related assets will take place only after compensation has been paid, LPS certificates were issued and, where applicable, alternative housing and moving allowances have been provided to the displaced persons.  An account of village-wise encumbered lands needed for flood mitigation works is provided in Annexure 9. Based on this information, the section-wise handing over of the lands to the contractors will be determined and reflected in the bid document. The 32 ASCCDP: Resettlement Action Plan for Flood Mitigation Works payment of compensation and R&R assistance as well as Land Pooling Ownership Certificates (LPOC) for returnable plots in case of those joined land pooling will be certified with details by – the Joint Collector, for LA and Negotiated Settlement Policy prior to handing over of such stretches to the Contractors.  The bid documents will include a provision that the representatives of contractor and Employer shall, on a mutually agreed date and time, will inspect the site and prepare a memorandum containing the inventory of the site including the vacant and unencumbered land, buildings, structures, road works, trees and other immovable proprieties on or attached to the site. The memorandum will be appended to the contract document specifying the details of the parts sections which are not handed over and agree and record a date for subsequent handing such parts free of encumbrances and the contractor will bear all risks arising out of the inadequacy or physical condition of the site that has been identified and recorded as unencumbered in the memorandum. The details of village-wise affected encumbrances are provided in Annexure 9. This will be updated once the joint survey among contractors and Amaravati Development Corporation (ADC) is completed and will become basis for monitoring the identified encumbrance on a timely basis to hand over the 100% lands to contracts with in the contract provisions. Project Implementation Unit 4.13 In order to coordinate with district administration and manage project related impacts, surveys, studies, monitor implementation and interact with World Bank, the following dedicated project level staff have been mobilized in the Project Management Unit of APCRDA for the implementation of the Bank supported project.  Land Acquisition Officer to coordinate with all land acquisition/Negotiated settlement, LPS and related issues related World Bank financed sub-projects  Social Development Officer to coordinate with census, social-economic surveys, consultation, delivery of annuity and pensions, implementation of RAP, support to vulnerable people, etc. The above two officers will be reporting to Project Director of PMU for the World Bank financed project.  These two officers support of all senior staff of APCRDA.  In addition to two dedicated staff in APCRDA for the project, an additional social development specialist will be in place in ADC, who will be implementing the civil works to manage the social impacts in construction activities. Additional unforeseen impacts during implementation 4.14 In the event of additional impacts to private land acquisition, physical displacement of people, or of those living on public lands is encountered due to changes in the design, missed out in identification or otherwise, a supplementary or addendum to RAP prepared and shared with the World Bank for review and endorsement. The revised document will also be approved by the competent authority and re-disclosed. Management Information System 4.15 RPF, RAP, Negotiated Settlement Policy, LARR Matrix, SES data, estimation of 33 ASCCDP: Resettlement Action Plan for Flood Mitigation Works structures, LPS matrix, tender documents, list of affected people, etc., will be disclosed through various project offices, Competent Authority offices, APCRDA as well as Joint Collector Offices. These documents will be made available in the public domain through websites, in brochures and other forms of documentation. A separate site / page will be developed where all project foot print related information and data will be maintained and updated regularly. The progress in payment of annuities, issuance of Land Pooling Certificates, compensation and R&R assistance for land owners affected by the Bank project will be reported to the World Bank as part of quarterly reporting during project implementation. 4.16 A link to a dedicated section in APCRDA‘s webpage14 has been created to disclose all project-related documents including safeguards documents, including Resettlement Policy Framework, Environmental Social Management Framework, Environmental Impact Assessment – Environmental Management Plans as well as Resettlement Action Plans and other information pertaining to the World Bank funded project. People can directly access these documents online. The list of affected people and any updates are also disclosed on this site for easy access. Printed versions of these documents are also available at Project Information Centers (PICs) in every village. Grievance Redressal Mechanism (GRM) 4.17 Multiple channels have been set up in Amaravati to facilitate the reporting of grievances and the monitoring of how those are being addressed. The various GRM channels will be used for the proposed ASCCDP, and can be specifically used by project affected people under the Bank-financed project. A brief description of both the existing as well as (additional) proposed GRMs are as follows. Bank project (ASCCDP) related grievances addressed / redressed by the GRM / GRC will be collated and reported separately on a quarterly basis as part of project progress review. 4.18 To strengthen the existing grievance redressal system and to provide citizens of Amaravati with responsive service, the APCRDA has constituted a Grievance Redressal Committee (GRC) with the Commissioner, APCRDA as Chairman, Special Commissioner, Additional Commissioner and respective HoDs/ Directors as members. Joint Director OM & OSD (meetings) will be the Member Convener for GRC. All officials interfacing with citizens (farmers, landowners, pensioners etc) will address and resolve grievances within a set time limit. Those grievances which require inputs from other departments/HoDs for decision making in respect of resolving should be brought to the notice of GRC, which will meet once a month i.e., every Saturday. It was decided that the GRC Meeting shall be conducted every Saturday till further notice to address grievances expeditiously in respect of project footprint. In addition to resolving the pending Grievances, the GRC will review the status of Grievances pertaining to all divisions. 4.19 The GRM procedure is simple to facilitate access by PAPs. The procedure for handling grievances is as follows: i. The affected person files his/her grievance in writing, to the GRM. The grievance note should be signed and dated by the aggrieved person. Where the affected person is unable to write, s/he will be provided with assistance to write the note and emboss the letter with his/her thumbprint. The Project Information 14 https://crda.ap.gov.in/APCRDA/Userinterface/admin/asccdp.htm 34 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Centre established at each unit office will be facilitating such assistance. ii. The GRM should respond within 14 days during which any meetings and discussions to be held with the aggrieved person should be conducted. If the grievance relates to valuation of assets, experts may need to be requested to revalue the assets, and this may necessitate a longer period of time. In this case, the aggrieved person must be notified by the GRM that his/her complaint is being considered. iii. If the aggrieved person does not receive a response or is not satisfied with the outcome within the agreed time the person may escalate his/her grievances to the relevant Authority. iv. The relevant Authority will then attempt to resolve the problem (through dialogue and negotiation) within 14 days of the complaint being lodged. If no agreement is reached at this stage, then legal recourse is sought. Existing GRM Mechanisms 1. ‘Meekosam’ (‘for you’ in English): 4.20 This is a State-wide single window online framework for receiving grievances, complaints, covering all departments. Apart from reporting complaints, people can also give suggestions to government directly through this web portal. All the reports and suggestions will be accessible to the respective departments and CM. (URL:http://www.meekosam.ap.gov.in). Key features include:  In addition to CRDA, the Urban Development Department, Revenue Department, Social Welfare Department, and others are all part of this GRM framework.  The recording of grievance is based on Aadhar number.  The person who posts grievance or suggestion can track the progress of his/her application.  An acknowledgement will be sent via SMS/ e-mail once a grievance is registered.  The grievance will be registered, tracking ID issued, categorized and forwarded to the department concerned.  The grievance will be escalated to a higher authority, if the grievance is not addressed within a set time-frame.  The status of the grievance can also be tracked through a toll-free number at 1100/1800- 425-4440.  A Call Centre has been set up for citizens to register and retrieve information on status of grievance applications.  Each of the Competent Authority Unit15 is separately registered in the Meekosam portal to ensure that the grievance is expeditiously addressed by the concerned officer. The progress of redressal is monitored by Commissioner APCRDA at the organization level and by Hon‘ble CM at the state level, during regular review meetings held on every Monday and Wednesday, respectively.  Grievances received from Meekosam, pertaining to CRDA mainly include: payment of pensions, issue of health cards, filling up of vacancies in respect of SC/STs, requests for jobs / employment grants, requests for enrolment into household survey, request for allotment of government land and provide loan to build houses etc. 4.21 All grievances received from Meekosam are forwarded to respective departments. In 15 LPS unit, there are 26 units in capital city and the same units are now addressing the LA process as well 35 ASCCDP: Resettlement Action Plan for Flood Mitigation Works cases related to the Capital City Development project or the Bank-financed project, the compliance will be forwarded to APCRDA. A Committee under the Chairmanship of Commissioner has been constituted to review the compliance on a weekly basis and the responses and grievances will be sent to complainants based on the decisions by the grievance committee. Most of the grievances are redressed on daily basis. Screenshots extracted from the Meekosam site are annexed at Annexure 10.1. The grievances related to project are not separately available, but a mechanism is being put in place to segregate complaints related to Bank project and their status will be reported to the World Bank during project implementation. Screenshot of the ‗Meekosam‘ website Final 2. Mana Amaravati App 4.22 A mobile APP – Mana Amaravati aims to bridge the gap between the State government, citizens of Amaravati, investors, buyers and sellers of plots, district administration, CRDA and other stakeholders. The app also provides information on the projects undertaken as part of the Capital City development, including the World Bank funded project. The grievance redressal system has also been built into the app, where citizens can address issues with concerned departments at their convenience as well as to register, inquire about the status, and retrieve responses for their complaints and suggestions. 4.23 There are currently 20 services integrated into the ‗Mana Amaravati‘ app. Through the app, all plot owners who have been allocated lands can log into the app and list their plot(s) for sale, joint development or lease. One of the key features of the app is the ‗know your plot code‘, which allow users to use his/her Aadhaar number to retrieve details of his/her allocated plot of land. The app also has a feedback form through which users can send suggestions on its services. 36 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4.24 In addition to the services mentioned above, users can retrieve information about Amaravati, Andhra Pradesh Capital Region Development Authority, Farmers First, details about one-time loan waiver, annuity, viewing plot on map and download provisional certificate as well as view LPS layouts and access the Development Permissions Management System (DPMS) book appointment for plot registration, Details about various social benefits which include pension, free health, free education, training details and application for the same, Amaravati Housing Scheme, Job opportunities, NTR Canteens, Photos and Videos of Capital City development. This app also incorporates a direct link to a separate dedicated section for the World Bank ASCCDP project. Links to citizen services and information such as zoning regulations, master plans, e-Encumbrance and MeeBhoomi are also included in the app. A few salient applications of the app are illustrated below (screenshots) 37 ASCCDP: Resettlement Action Plan for Flood Mitigation Works World Bank ASCCDP Action Plans by APCRDA can be found here 38 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Citizen Services Tap on Citizen Services button from Home Screen. Grievances ● Tap on Grievance button from Home Screen. ● Type ―Aadhar Number”, “Phone Number”, “E-Mail Id‖. ● Choose if the grievance is Service ―Related‖ or specify if grievance is related to other in the next field. ● Choose the concerned department in Select Department drop down. ● Describe grievance in Description field. ● Attach any documents to support your claim and tap Submit button. 39 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 3. Call Center 4.25 A toll-free complaint number 1100 is provided to the public by the State to serve as a Grievance Redressal Platform which has received strong response. The intention of the Call Center number is to make lodging complaints easy for the citizens by just dialing a number. Upon registering the complaint through the Call Centre, the grievance is forwarded to the respective department (APCRDA) and the grievance redressal status is monitored from the Chief Minister‘s Office through a core dashboard which is part of the real -time governance (RTG initiatives of Government of Andhra Pradesh). The Call Center is staffed by State-level officer, who route grievances to the concerned departments. . 4. Right to Information Act implementation 4.26 Each of the over 20 departments of APCRDA as well as CAs have been assigned with a designated RTI officer responsible for receiving and disposing the RTI applications. In 2018, till date, about 221 applications have been received, of which about 179 have been attended to as per RTI Act. The rest are in process. Applications/grievances received through RTI included wide queries, for example: Population details of capital city; questions on CC cameras; complaints on unauthorized construction; questions on land allotment; details on skill development trainings; SIA meetings; expenditure levels for Capital City, etc. 5. APCRDA Portal for Grievance Redressal 4.27 Effective consultations and grievance redressal mechanisms were the key enablers for the success of the Capital City Land Pooling Scheme, initiation and implementation works. In addition to Meekosam, APCRDA has its own GRM that includes: (i) a 3-stage physical system, that originates with designated officials (―Competent Authority‖) at various zonal offices throughout Amaravati city, where citizens can approach to report grievances (see below); and (ii) an online portal at: (https://crda.ap.gov.in/APCRDA/Userinterface/Admin/GrievanceRedressalSystem.aspx). 4.28 The grievances from the portal are categorized and forwarded to respective CA units and to the Commissioner APCRDA for further action. 4.29 The three-stage system includes: Stage I Grievance Redressal Cell will be at the Competent Authority level at the village itself. About 26 units of Competent Authorities (CAs) were established during the early stages of Amaravati (Jan/Feb 2015), which are headed by Deputy Collector. The Deputy Collector is assisted by a team of officials including revenue, survey. This translates to the fact that each Deputy Collector is attending to the issues of approximately 1,000 -1,500 farmers of the capital city villages, and is always available to public at large. The Stage II Grievance Redressal Cell will be at the Amaravati city / district level, where the Joint Collector will chair the Grievance Redressal Cell. The Stage III Grievance Redressal Cell will be chaired by R&R Commissioner at State (GoAP) Level. 4.30 Every Monday grievance redressal meeting is held at the CRDA office of the Capital City in which officers from all competent authorities make themselves available for attending to public. The office of Commissioner at the CRDA in Vijayawada city receives grievances and addresses them on a daily basis. Early institutional measures taken to address grievances: a) 26 units of Competent Authorities are established during the early stages of Amaravati (Jan/Feb 2015), which are headed by deputy collector, who otherwise is responsible for more than a district. The deputy collector is assisted by a team of officials including revenue, survey. This translates to the fact that each deputy collector is attending to the 40 ASCCDP: Resettlement Action Plan for Flood Mitigation Works issues of approximately 1000 -1500 farmers of the capital city villages and is always available to public at large. b) These officers have sorted out many land-people related issues while taking the farmers into confidence which mainly included: Family disputes, Enjoyment issues, Survey errors, Extent variations, Encroachments, Assignments and Wakf, Endowment land disputes, etc. In addition, Help Desks were opened to enter into agreements and payment of benefits, Personalized and Door Step Services were provided, a dedicated Support Cell was established for NRIs and NRVs. c) The grievance redressal mechanism, in addition to the consultative process has addressed over 25,000 issues. 9.2 objections alone amount to 17096 covering an extent of 6511 acres of which 7,859 objections have been disposed in favor and 9,237 objections rejected on lack of grounds / merits. Of these rejections, 1,052 appeals were received for reconsideration and are under disposal process after due verification on ground. Similarly, around 415 grievances are addressed regarding village settlement zone (R1 issues). Citizens’ Committee: 4.31 A Citizens Committee has been set up with the following objectives: i. Serve as an approachable body and engage with project affected people and other stakeholders on implementation and policy matters; ii. Serve as an advisory Panel to APCRDA on dealing with potential adverse impacts and policy issues that require management attention; iii. Advise APCRDA to ensure that project‘s safeguard polices for land acquisition, resettlement and livelihoods are followed; and, iv. Advise APCRDA on implementation outcomes of Safeguards mitigation plans 4.32 The terms of reference of the Citizens‘ Committee are summarized below: (a) Provide advice and recommendations to various issues that APCRDA approaches to the committee on the issues encountered during RAP implementation; (b) Undertake Independent field visits to the resettlement sites and project sites to hear the views of the project affected people and other concerned stakeholders on the implementation of RAP and related activities and make recommendation as needed to realize the objectives of RAP. (c) Review the status of compliance with legal covenants related to resettlement as described in the project agreement between the World Bank and APCRDA and recommend measures for their compliance throughout the project implementation; (d) Review the implementation status of APCRDA Resettlement Action Plan and recommend measures to improve the resettlement implementation performance. The Committee will receive inputs from the independent monitoring and evaluation consultant/NGO; (e) Review and recommend measures as appropriate for timely implementation of various actions agreed with the World Bank on the implementation of resettlement aspects of the project (as available in the aide memoirs of supervision missions carried out from time to time). (f) Suggest APCRDA on improvements in the policy provisions based on the implementation experience and interactions with stakeholders. (g) The committee undertakes regular field visits, typically once in a quarter to interact with affected people to hear them directly and provide advice to the implementing agency (APCRDA/ADC) regarding RAP improvement measures. 41 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4.33 The Citizens‘ Committee has been constituted with 12 members, chaired by Pro-Vice Chancellor of a University in Amaravati and includes 2 academicians of repute; 5 women members (landowners/residents from villages); one member from agricultural labor and four landowner members of which one member is from SC/ST community. The first meeting of the Citizen‘s Committee took place on July 24, 2018. 4.34 The minutes of Citizen‘s Committee meetings, recording the summary of outcomes of meeting/field visits and their recommendations will be issued by the Chairman of the committee within a week of the meeting. This will be posted in APCRDA‘s website to enable all the concerned stakeholders kept informed about the outcome of the activities of Citizens Committee in the project. The budget for the Citizen‘s Committee will be set up under the Contingency Provisions of the RAP budget. Supporting NGO 4.35 An NGO will be engaged by APCRDA through Competitive Selection process. The NGO will be one which has well established credentials in addressing large scale bank funded projects of similar nature and have local presence, team with communication skills in local language. The NGO is expected to provide assistance to the PAPs especially those who are illiterate in filing their grievances. The NGO will also educate people on how to approach the grievance redressal mechanism. Communications Strategy 4.36 A communication strategy is in place and will be reviewed and updated periodically to ensure that there is sufficient public awareness of the entitlements under the three categories viz., Land Pooling Scheme, Land Acquisition and Negotiated Settlement Policy. In addition, the use of social development initiatives will further help publicize and facilitate public awareness. NGO services will also be enlisted for maximizing the coverage and awareness at individual and community level. 4.37 A series of 45 to 60 seconds-long video clips and animation has been produced for each subject/topic that require the attention of the landowners / project affected and people at large. A special campaign, developed in cooperation with I&PR department was undertaken. The campaign is also supported by special vans equipped with audio and video facilities. 4.38 In addition to the above-mentioned initiatives, APCRDA is disseminating information through social media, such as Facebook, Twitter, SMS-based communication, YouTube, Mana Amaravati app, etc. The statistics below provides an overview of the outreach through social media as of July 15, 2018:  Facebook—No. of Followers: 52,320  YouTube—No. of Subscribers: 9,489  Twitter—No. of Followers: 14,527  CRDA Website Hits: 1,587,781  Mana Amaravati App Downloads – 31,346 (24,767 (Android) + 5,679 (iOS))  Capital City Farmers count accessing SMS based communication is around 25,000 Project Information Centres 42 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4.39 Project Information Centers (PICs) were set up between Oct-Nov 2017 in all the villages and located at the Deputy Collector (Competent Authority) offices. The CA is designated as Project Information Officer to provide required information on the overall Capital City Project in the form of printed documents, and information made available online, etc. Educated youth (boys and girls) from the respective villages will be trained as information assistants so that they can be more accessible by the villages to seeking required information. The PICs will have copies and will provide access to all project related documents and information, brochures, etc. The PAFs and other interested people can visit this center and access all related information and all documents and other project related information can also be accessed through APCRDA website, www.crda.ap.gov.in. The overall coordination of all village level PICs will be done by the Director Communications of APCRDA. This is in support of the World Bank's policy of disclosure about its activities, open access to its Final documents, and to explain its work to the widest possible audience. 4.40 PICs also serve as the central contact point in the affected area for persons seeking to obtain documents and requests for information. PICs are open to the public and no fee is required to use the PIC. Users can also access information through the internet. PIC services include:  online access to project documents, publications, and other developments-related to execution of work;  access to a special collection of CDs and videotapes on development;  access to development sites on the Internet; online access to projects, documents, and reports; 43 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4.41 A training workshop was conducted on November 3 and 4, 2017 for all the facilitators of PICs on their roles and responsibilities. Photos and newspaper clippings of the workshop are provided below: 44 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 4.42. Cut-off dates. The following cut-off dates will be used for eligibility of entitlements and support for the people affected for the works under this RAP.  Land owners under LPS: The date of signing the consent by land owners to join the LPS;  Land owners under LARR Act: The date of first notification under LARR Act,  Family affected under Negotiated Settlement Policy: The date of submitting the consent by the displaced families to join the NSP  Agricultural labourers: All those who are registered with APCRDA for pensions as of July 15, 2018 are treated as project affected people. The number is 21, 374.  Non-Title holders. The census survey (March 2015) has been used for identifying those living on Government lands 45 ASCCDP: Resettlement Action Plan for Flood Mitigation Works V. MONITORING OF RAP DURING IMPLEMENTATION 5.1 The implementation of this RAP will be monitored using the framework and processes outlined below. The implementation time table for key activities to be taken up under this RAP are listed below: Table 10: Time Table for Key Activities No Key activities Time Frame Responsibility Remarks Land Acquisition District 1 Issue of section 11 Completed Collector, Guntur District 2 Issue of Section 19 Completed Collector, Guntur LA Award Passed and ordered to deposit the amount U/s.77(2) In progress will Land of LARR Act, 30 of 3 LA Awards be completed by Acquisition 2013 before LARR September 2018 officers Authority in respect of 3 landowners corresponding to 0.69 acres Supplementary plan Differential for affected JC, Guntur / updated unit cost 4 dependants of lands to October 2018 APCRDA would be paid by be acquired under LA APCRDA Act Land R&R Award 5 December 2018 Acquisition announcement Officer Land Compensation 6 November 2018 Acquisition payment Officer Private Negotiations Valuation of affected 1 September 2018 R&B Dept. house/assets Completion of Negotiations 2 October 2018 Negotiations Committee Land Payment of Negotiated 3 October 2018 Acquisition Package Officer 4 Completion of October 2018 JC Guntur 46 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Resettlement site development JC Guntur / Plot allotments to Land 5 November 2018 displaced families Acquisition Officer Land Acquisition Land awards in case of 6 December 2018 Acquisition unsuccessful Officer Negotiation cases Other Key actions Dedicated Land Acquisition/Social 1 Completed APCRDA Development Officers in place. Constitution and notification of 2 Completed APCRDA Grievance Redressal Committee Constitution of Citizen 3 Completed APCRDA Committee 4 Establishment of PICs Completed APCRDA Appointment of NGO to support RAP 5 August 2018 APCRDA implementation support Appointment of APCRDA / 6 Concurrent September 2018 ADC Monitoring Agency Relocation of affected 7 November 2018 APCRDA In progress Community assets Vulnerable people Target group 8 Action plan for needy August 2018 APCRDA identified. Plans in people progress. Family Livelihood NGO to prepare 9 December 2018 APCRDA Action Plan the plan 5.2 The Government of Andhra Pradesh / APCRDA, the requisitioning Authority for acquiring lands required for the project, shall make arrangements for funds:  Required for establishment of land acquisition / land pooling units.  Required for payment of annuity towards net crop loss  Required for payment of pensions through Capital Region Social Security fund.  Required for payment of Compensation, R&R Cash benefits  Required for depositing the LA R&R Cash Benefits for the cases referred to LA R&R Authority under section 64(1) of the LA R&R Act, 2013.  Required for depositing proved non-title holders – benefits under LA R&R Act and RPF 5.3All payments shall be through bank transfers into the accounts of Awardees/ beneficiaries. 47 ASCCDP: Resettlement Action Plan for Flood Mitigation Works In case of land owners refusing to receive compensation or not available to receive compensation, the amounts would be deposited in escrow with the LA R&R Authority.16 The RAP budget will be placed with district administration who is the deemed appropriate government as per LA R&R Act 2013. The funds would be deposited in the P.D. Account of the District Collector which would be operated through Treasury. The Collector / Joint Collector would be sending Utilization Certificates to that effect. APCRDA will have a separate account for payment of difference cost between RPF provisions and LARR Act and this will be paid as a special assistance / RP Cost. 5.4 NGO support for RAP Implementation. APCRDA will engage a NGO by August 15, 2018 with experience in resettlement and community development activities, consultations to support APCRDA, in the implementation of RAP. The key tasks include but not limited to: to engage with farmers and villagers on continuous basis to educate the people on their entitlement, grieve mechanisms, opportunities available for their document and serve a liaison between local villagers and APCRDA. They will also assist the villagers and affected people to access their compensation, entitlements, annuity/pensions and help them in filling their grievances as needed. They will also carry out consultations with all categories of impacts to seek their views and concerns and those will be discussed with APCRDA for suitably addressing them. The NGO will also assist the people in identifying the vulnerable people and preparing vulnerable peoples action plan and support the displaced families in their post resettlement activities for their smooth transition. 5.5 Monitoring and Evaluation: The implementation of this RAP will be monitored through set of indicators outlined in Table 11 below. To support monitoring of RAP implementation, APCRDA will commission external monitoring agency to report on the implementation of RAP. APCRDA plans to initiate the process for commissioning the consultants in August 2018. The agency will review the progress reports prepared by APCRDA and NGOs, and use rapid assessments, sample checks, consultations, discussions, meetings, interviews, etc. to prepare their quarterly reports This will be supplemented by Bank-appointed NGO who is already in place, and will also report on implementation outcomes to the Bank. The M&E Agency / Consultant scope will also include to carry out annual surveys with regard to satisfaction with payment of annuities, access to benefits, etc. The recommendations arising out of the monitoring reports and annul surveys will be considered to adapt the measures being provided during implementation as needed. The final impact evaluation will be carried out at the end of the project by another agency not associated with implementation to assess the realization of RAP objectives. Gender disaggregated data and information will be captured in the reporting. Table 11: Key indicators for monitoring of RAP implementation No Indicators Target values Progress Remarks (project (as of July, footprint) 2018) Land Pooling Scheme* capital city 16 as per G.O.Ms.No.91, Revenue (Land Acquisition) Department, dt. 03-03-2017. 48 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 1 No of landowners received 1754 1533 Land Pooling certificates 2 Proportion of Grievances 100% 85% resolved within 30 days 3 No of families receiving 1754 1754 annuities 4 No. of families receiving 21374 21374 pensions as on date Land Acquisition 1 Land Acquisition award (in 75.46 0.69 acres) 2 No. of farmers paid LA 110 NA compensation 3 No of Farmers paid R&R 110 3 award amounts Negotiated Settlement Acreage – 10.38 acres 1 Number of Negotiated 27 0.00 settlements signed 2 Number of people paid 27 0.00 Negotiated settlement packages 3 Number of Families moved 27 0.00 to new houses 4 Expenditure of RAP INR 240 million NA implementation (INR. In millions) Note: The indicators will be updated from time to time during implementation; * For latest values ref. dashboard of CRDA website. 5.6 Impact Evaluation: Towards the end of ASCCDP implementation, an independent agency not associated with the implementation of the Project will be engaged to undertake impact evaluation to assess the changes in the living standards and impact of compensation and R&R assistance provided to the PAPs/PDFs. The impact evaluation will be based on the key baseline socio economic indicators and additional information will be collected on recall basis and the perceptions of the people on the changes in their living conditions. Further, the outcome LPS will be evaluated based on proportion of first sale of returnable plots and proportion of building permissions obtained out of those not sold and whether LPS beneficiaries expectations on price is realised or not. As needed remedial measures will be designed to address the outcome of impact evaluation including the expectations of LPS beneficiaries on sale of returnable plots. The key baseline social-economic conditions to be used are provided below: Table 12: Key Baseline socio-economic conditions for Impact Evaluation No Indicators Baseline values based on survey (January 2018) PAFs17 17 Both LPS beneficiaries and those given lands under LA. 49 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 1 Average annual family income 52,083 2 Education level / literacy level 72% 3 Poverty line (less than 5,000 PM) 89%18 4 Electricity connections 100% 5 Living standards like vehicle ownership 44% 6 Water facilities 100% 7 Sanitation facilities 100% 8 Housing 96% 9 Indebtedness 27% 10 Occupation (agriculture) 59% 5.7 Final Disclosures: Once cleared by the Bank, this RAP will be re-disclosed on the APCRDA website along with Executive Summary translated into Telugu version and subsequently will be disclosed on the Bank‘s external website. Hard copies of this RAP will be made available to interested parties at CRDA, Joint Collector‘s office. These will also be made available at the PICs. A brochure in the local language will be again circulated by providing key provisions and contact details of grievance redress mechanism. The implementation progress will be disclosed on an on-going basis. In order to keep the community engaged the scope of NGO services will include on-going consultations on regular basis (twice a year) with the project affected people to appraise the progress in project implementation including RAP implementation, provide clarifications and seek suggestions in the implementation to the stakeholders. Feedback received in these meetings will be suitably incorporated in the implementation process. 5.8 Compensation Payment and R&R Support Mechanisms: Payment of all compensation and R&R entitlements will be certified by the concerned Joint Collector/ Land Acquisition Officer. The PIC will also serve as platform for the people to register their complaints and seek information or refer the project related documents. 5.10 Costs and Budget: The budget estimates provided below include compensation for land acquisition and assets, Annuity/Pension, civil works related to resettlement sites, community properties, livelihood support, consultancies and differential costs arising out of RPF provisions compared to LARR Act/Negotiation settlement. All the costs related to implementation of RAP will be born out of counterpart funds, except costs related to consultancies and civil works, if required will be used from the World Bank loan. All costs to be met out of World Bank loan will be based on World Bank‘s procurement guidelines and eligible criteria applicable to the project. The source of budget is APCRDA funds / AP Government budget. The following budget is indicative and any additional requirement will be put up in a supplementary note for approval of the Bank. The budget excludes the land acquisition costs to be met by GoAP separately as part of land acquisition for Capital City development project and includes those costs to be borne directly by APCRDA for implementation of RAP. The cost of maintaining GRM is part of APCRDA‘s overall budget and hence no separate provision is required / stated. If required, cost of GRM will be out of contingency funds provided under the budget. 18 The percentage of population below poverty line is ascertained from the status of possession of white ration cards. The complete statistics of the white ration card holders village-wise is available for access at APCRDA office. 50 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Table 13: Proposed Budget19 Budget No provision Item REMARKS . (Rupees in Millions) Depreciated costs Will be met with APCRDA 1 including salvaged 10.00 funds material for structures Transitional support to As per Annexure 2 and 3 2 10.00 displaced families provisions Resettlement site development and relocation of CPRs including 3 Civil works 100.0020 Layout and proportionate trunk infrastructure NGO support M&E 4 Consultancy services 20.00 Independent monitoring and evaluation Including Citizen committee and 5 Contingency fund 30.00 GRM costs TOTAL 170.00 19 The budgets pertaining to compensation under LA and R&R are met with funds deposited with administration by the requiring body. 20 This is estimated budget specific to 27 displaced families. May vary per actuals 51 ASCCDP: Resettlement Action Plan for Flood Mitigation Works ANNEXURES Annexure – 1 Land Pooling Scheme - Entitlement Matrix Land Pooling Scheme: Returnable Plots and Annuity Category (in Sq. Yards) / Acre Land Categories Dry lands Jareebu lands/Semi-urban Residential Commercial Residential Commercial A) Private lands 1,000 250 1,000 450 B) Assigned lands Ex-Serviceman / Political Sufferer 1,000 250 1,000 450 Assignments before June 18, 1954 1,000 250 1,000 450 Assignments After June 18, -1954 800 100 800 200 Resumed lands – eligible Sivoijamadar occupation ** 500 50 500 100 Un-Objection able Gouvernement lands – Eligible Sivoijamadar ** 500 50 500 100 Objection able Govt. Lands – Eligible Sivoijamadar ** 250 0 250 0 C) Yearly payment of annuity to all INR 30,000/acre INR 50,000/acre landowners losing land* D) Yearly increase INR 3000/acre INR 5,000/acre E) One-time additional payment for gardens (INR) 100,000 (d) Agricultural labourer/ INR 2,500 /Per month/10 years with annual Agricultural Tenants (residing in LPS adjustment linked to inflation index***. villages as on December 8, 2014) *In case of those losing less than one acre of land will receive the annuity equivalent to one acre. ** These three categories of people are paid monthly pensions instead of annuity Other Benefits. In addition to above entitlements, the landowners who have joined or those registered for pensions can access to the following additional benefits: a) Loan Waiver: One-time agricultural loan waiver of up to INR 150,000 is available to all farmers who have outstanding agricultural loans. b) Loans for self-employment: Interest free loan of up to INR 2,500,000 is available to all poor families for setting up any self-employment avenues (below INR 60,000 and 75,000 annual income in rural or urban areas respectively). c) Education and Health: Free education and health facilities are available to all those residing as on December 8, 2014 d) Old age homes will be established to take care of aged of above 65 years; e) Subsidized canteens: To provide food at very subsidized rates f) Wage Employment. APCRDA is assiting to access wage employment under MGNREGA Establishment of skill development institution to provide training with stipend to enhance the skills of cultivating tenants, agricultural labourers and other needy persons. 52 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure – 2 Compensation and R&R Assistance under Land Acquisition Act Sl. Impact Eligibility Entitlement Remarks No Category a) Loss of land Patta/ Temple Higher of basic value or Land/ three-year average sale Assigned/residential price calculating on higher /commercial/indust 50% transactions. rial Land in Rural Steps would be and Urban areas Add value of multiplier (1.0 taken to update times in urban area or 1.25 basic values prior to times in rural areas) first notification and adopt updated values prior to Add Solatium 100% on passing award. final compensation amount Add 12% additional market value from preliminary notification to award. b) Loss of Trees Affected area Estimated value as per GoAP rates will be / Tree Horticulture / Forest adopted as on Toppings Department plus 100% Preliminary solatium. Notification U/s. 11(1). c) Loss of Affected area Value as per R&B SSR rates as on 11(1) structure Department plus 100% Notification are solatium adopted. Depreciation will not be made. Salvage would be allowed to Awardee. d) Resident Displacement in Constructed house not less Prevailing Unit House owner Rural area than IAY specifications or values as per AP irrespective equivalent cost if opted by Housing of legal status displaced family. Department Displacement in House with not less than 50 Transportation cost Urban area sq. m. in plinth area or not of INR 50, 000/- for less than INR 1.50 Lakhs if DPs. opted by displaced family. Subsistence grant 12 months × INR 3,000/- One-time Resettlement grant of INR 50,000. 53 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Affected Constructed house with not Prevailing Unit family less than IAY specifications values as per AP without Housing homestead Department land residing in the area as on the date of census survey. e) Cattle shed / Shifting from reconstruction grant INR 25000/- Petty shop affected area to rehabilitation centre f) Artisan/ Non-agri/ Financial assistance. INR 25,000/- Small trader/ commercial/ Self- industrial/ employed institutional structure in affected area. g) All Affected Loss of livelihood One time resettlement grant INR 500,000 or INR families / / annuity 2,000 X 12 M X 20 Y tenants irrespective of legal status h) Crop Crop Cut down Damages Gross income during survey calculated on Standing Crop Standing crop allowed. average yield Damages if required. multiplied by minimum support price. Net crop loss shall be 50% of the gross income. i) Unidentified R&R assistance as impacts per the principles of this RPF Other Benefits Twelve months construction time allowed from allotment of developed plot or transit accommodation in consultation with the PAFs 1. Updated Resettlement unit costs: 54 ASCCDP: Resettlement Action Plan for Flood Mitigation Works The project has adopted the unit costs for R&R assistance as available in LARR Act, 2013 for impacts under LARR Act. The revised costs notified by GoAP, as per Section 31 of the LARR Act 2013 will be applicable from the date of notification. Proposals are submitted to government in this regard. The difference to updated unit costs will be paid immediately after approval of Project for the lands covered under the Project footprint. Annexure – 3 Negotiated Settlement Policy SL Property Type Description Proposed Compensation No 1 Residential use in R1 House / Residential Plot Two times of compensation of Zone Excluding Common area the structure value. Nearest standard plot in RH colony equal to plinth area of structure / house site with annexure-II of zoning regulations (ref. CRDA website) 2 Non-Agriculture /other As is land use i.e., barons, Two times of compensation of use in R1 Zone hayricks etc., the structure value. Land to land for same land use 3 Commercial/ Industrial Existing structures like Two times of the structure use in R1 Zone or shops or Commercial / value. Scattered commercial/ Industrial Structures Nearest standard plot in RH Industrial Structures excluding common area center equal to plinth area of outside R1 Zone structure, without any amalgamation of plots. The FSI shall be as per Zoning Regulations. 4 Scattered residential Residential Houses that are Two times of the structure Houses in LPS area other constructed and the owner value. than R1 Zone / Lanka is living in the agricultural Allotment of residential Lands fields. entitled standard plot subject to maximum of 500 square yards in RH Colony. The FSI shall be as per Zoning Regulations. 5 Displaced families Constructed house with IAY living on Government specifications lands Transitional and shifting allowance. 6 Tenants House-less tenant will be provided IAY housing Transitional and shifting allowance to all tenants. 7 Unidentified impacts R&R assistance as per the principles of this RPF 55 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Other Benefits a) Housing Unit for Residential House. Construction Grant as per GoAP norms or Housing Department norms as applicable b) Transportation cost for displaced family INR 50,000 /- c) Re-construction of cattle shed/ petty shop INR 25,000 /- d) Resettlement Grant INR 50,000 e) One-time grant for artisan/ small traders / certain INR 25,000/- others f) Subsistence allowance to artisan/ small traders INR 2,500/-* per month for a period of 10 years if not receiving pension under LPS. g) Construction Time 6 months from allotment of developed plot or Transit accommodation in consultation with the PAP. *This allowance is also extended to PDFs under the Negotiated Settlement category if they are not receiving pension already. Negotiated Settlement Documents are available in project files for reference. Updated Resettlement unit costs: The project has adopted the unit costs for R&R assistance for negotiated settlement Policy of GoAP, w.e.f from 19.04.2017. Inflation indexation will be made w. e. f. 01.04.18. The difference to updated unit costs will be paid immediately after approval of Project for the lands covered under the Project footprint. 56 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure – 4 Baseline Socio-Economic Data This annexure provides baseline socio-economic details of LPS and Non LPS fmailies 4.1 Baseline Socio-Economic Survey Data – Non LPS Families (N = 56) Household Head Number Percent Male 25 (49) 49.0 Female 26 (51) Final 51.0 Total 51 100.0% Household Head - Education Qualification Education level Number Percent Illiterate 12 21.0 Informal Education 1 2.0 Class 1 -4 5 9.0 Class 5 7 6 11.0 Class 9 – 10 12 21.0 Class 10 16 29.0 Intermediate 1 2.0 Graduate 2 4.0 Post Graduate 1 2.0 Professional -- -- Total 56 100.0% Household Head –Occupation Occupation Number Percent Housewife 4 7.0 Retired/Old age 4 7.0 Farmer 19 34.0 Ag Labour 14 25.0 Skilled Labour 5 9.0 Unskilled Labour 0 Services 2 4.0 Business(Shop owner) 3 5.0 Government Service 2 4.0 Private Service 3 5.0 Total 56 100 Family Size Size Number Percent 1-3 44 79.0 3-5 8 14.0 57 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 5-7 3 35.0 More than 7 1 2.0 Total 56 100.0% Religion Details Number Percent Hindu 81 79.4% Muslim 15 14.7% Christian 1 1.0% Others 5 4.9% Total 102 100.0% Caste Composition Number Percent General 17 53% BC 3 9% Others 12 38% Total 32 100% Possession of Ration Card Number Percent Yes 27 90% No 3 10% Total 30 100% Ownership of House Number Percent Own 96 96.0% Rented 4 4.0% Others 0 0.0% Total 100 100.0% Type of Structure Number Percent Hut 5 33% Asbestos/tiled roof 7 47% Concrete 3 20% Total 15 100% HH having Electricity Number Percent Yes 51 91.07% No 5 8.93% Total 56 100.00% 58 ASCCDP: Resettlement Action Plan for Flood Mitigation Works HH Drinking water source Number Percent Water tap in HH premises 5 36% Handpump 5 36% Others 4 29% Total 14 100% HH Source for other purposes Number Percent Water tap in HH premises 14 93% Handpump 1 7% Total 15 100% Source of Water for animals Number Percent Water tap in HH premises 7 50% Public Stand post 1 7% Handpump 6 43% Total 14 100% HH having individual latrine Number Percent Yes 11 73% No 1 7% Using Community toilet 3 20% Total 15 100% HH members using Latrines Number Percent Yes 13 87% No 2 13% Total 15 100% HH members wash hands with soap after defecation Number Percent Yes (regular) 12 75% Yes (Some of us, irregular) 4 25% Total 16 100% HH members go for medical treatment to Number Percent Clinic in village 6 40% Clinic in town 1 7% General Hospital 3 20% A traditional healer 5 33% 59 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Total 15 100% HH members hospitalized during last 6 months Number Percent Yes 1 2 No 55 98 Total 56 100.0% Members taken for treatment when fall sick in last six months Number Percent Local hospital 5 63% District hospital 3 38% Total 8 100.0% Fuel used Number Percent Firewood 8 8% Coal 7 7% Natural Gas 6 6% LPG 7 7% Electric Stove 1 1% Others 1 1% Total 56 Assets Owned Number Percent Cycle 2 3.57% Two wheeler 1 1.79% Three wheeler 1 1.79% Four Wheeler 2 3.57% Tiller 3 5.36% Television 51 91.07% Cable/ Dish 51 91.07% Refrigerator 12 21.43% Grinder 4 7.14% Landline 2 3.57% Cell phone 48 85.71% LPG connection 54 96.43% HH members migrated Number Percent Yes 9 16.07% No 51 91.07% Total 56 100.00% Type of Migration Number Percent Seasonal 1 11.11% 60 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Regular 8 88.89% Total 9 100.00% Average HH Monthly Income In INR Number Percent Less than INR 3,000 2 16.67% INR 3,000 – 5,000 8 66.67% INR 5,000 – 10,000 2 16.67% Total 12 100.00% HH Average Monthly Expenditure In INR Number Percent Less than INR 3,000 14 100.00% Total 14 100.00% Indebtedness Number Percent Yes 1 2% No 55 98% Total 56 100 Total loan amount taken In INR Number Percent Less than INR 75,000 1 100% Total 1 100.0% HH willingness to relocate due to proposed flood mitigation works Number Percent Self-Managed (cash) 1 2% Project construction 0 0% Undecided 9 16% Can't Say/ not aware 46 82% Total 56 100% HH opinion about unviable land/building also to be acquired Number Percent Yes 1 2% No 9 16% Can't Say 46 82% Total 56 100% HH preference location if project construct Number Percent Same settlement 9 2% Any other place 1 16% Can't say 46 82% 61 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Total 56 100% HH opinion about should project create or improve basic amenities in village Number Percent Yes 3 5% No 51 91% Can't Say 2 4% Total 56 100% HH willingness to work in the proposed flood mitigation works Number Percent Yes 8 14% No 2 4% Can't say 46 82% Total 56 100% 4.2 Data Analysis of socio-economic conditions of surveyed LPS landowners (N=96) Income & Indebtedness status S. No Indicator Unit Value/Figure a) Income (N = 102) 1 Annual family income Average INR 50, 286/- 2 Level of Indebtedness % 3.0 Assets comparison – before and after LPS Asset Before After Percent LPS Percent LPS Two-Wheeler 0 76 79 Three-Wheeler 78 81 8 8 Four-Wheeler 10 10 38 40 Tractor 28 29 9 9 Tiller 0 0 Television 6 6 73 76 Refrigerator 75 78 58 60 Grinder 60 63 40 42 Land Phone 42 44 37 39 Cell Phone 39 41 81 84 LPG Connection 82 85 88 92 Demographic details Household Head Number Percent Female 24 25.0 Male 72 75.0 Total 96 100.0 62 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Household Head - Education Qualification Education level Number Percent Illiterate 20 40 Up to SSC 7 14 SSC 9 18 HSC 3 6 Graduation 7 14 PG 1 2 Others 3 6 Total 50 100 Household Head –Occupation Cultivation 17 47 Service 2 6 Business 1 3 Wage Earning 1 3 Others 15 42 Total 36 100 . Family Size Size Number Percent 1-3 82 85.42 3-5 14 14.58 Total 96 100.00 Religion Details Number Percent Hindu 73 76.0 Not Reported 23 24.0 Total 96 100.0 Caste Composition Number Percent General 66 68.8 BC 2 2.1 SC 3 3.1 Total 71 74.0 System 25 26.0 Possession of Ration Card Number Percent No 4 5.88 Yes 64 94.12 Total 68 100.00 Housing and Amenities Ownership of House Number Percent Own 96 100.0 63 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Rented 0 0.0 Total 96 100.0 Type of House Type of House Number Percent Kachcha 11 11.4 Pucca 72 75.0 Semi Pucca 13 13.5 Total 96 100.0 HH having Electricity Number Percent Yes 94 97.9 No Final 2 2.1 Total 96 100.0% Water and Sanitation Practices HH having Piped water supply Number Percent Yes 94 97.9 No 2 2.1 Total 96 100.0% HH having individual latrine Number Percent Yes 94 97.9 No 2 2.1 Total 96 100.0% Land Related Number Percent Land Ownership is Patta 86 90 Land given under LPS 96 100.00 Land affected under LA 2 2.08 Possess land other than LPS 1 1.04 Any disputes on the land (not parted in LPS) 0 0 Agricultural income before joining LPS Agricultural Income Number Percent Less than 75,000 22 85 75,000 to 100,000 4 15 100,000 to 200,000 0 0 More than 200,000 0 0 Total 26 100 Cultivating by self or leased out 64 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Self/ leased Number Percent Self 18.00 69.23 Leased 8.00 30.77 Both 0.00 0.00 Total 26.00 100.00 Income earned on leased land Income earned under lease Number Percent Less than 75,000 1 100 Average 15,000 Returnable Plot S. Item Commercial Residential No. (Yes ) (Yes) 1 Received returnable plot? (Yes / No) 86 90 86 90 1A If yes, have you registered (Yes/No 23 12 22 12 1B Received your returnable plot individually 78 81 0 1C Joint 0 0 0 0 1D Identified the plot on the ground (Yes / No) 19 22 19 22 1E Distance from plot to road 0 0 1F Returnable plot is as per plot options (Yes / 60 63 58 60 No) 1G Do you plan to sale (Yes / No) 11 11 11 11 1H Did you get the plot in the same village 58 60 57 59 1I Have you mortgaged / sold your returnable 22 23 21 22 plot (Yes / No). 1J Expected price for sale (average) -- -- -- -- 1K Planned time of sale 1L Do you want to construct? (Yes / No) 13 14 14 15 1M If yes, did you apply for building 2 15 2 14 permissions 1N Are you satisfied with conduct of lottery 67 78 67 78 process (Yes / No) 1P Do you have any objections in plot 4 5 0 allotment 1Q Details of Objections -- -- -- -- 1R Have they been resolved -- -- -- -- LPS Benefits Sl. No. Item Number Percent 2 Are you receiving annuity regularly (Yes / No) 160 166.67 4 Self-employment/ employment, details 76 79.17 65 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 5 Are you availing free health cards 21 21.88 6 Are you availing fee reimbursement 59 61.46 7 Did you get loan waiver, if yes, amount -- -- Participation in Consultations Participation in Consultations Number Percent LPS consultations 80 83.33 Master Plan Consultation 62 64.58 Environmental Impact Assessment 63 65.63 Safeguards Documents 80 83.33 LPS Layout 63 65.63 LPS Plot Development (peg marking/ infra) 78 81.25 Information & Communication Avenues to access information Number Percent Mana Amaravati App 65 67.71 WhatsApp 79 82.29 Physical visit to APCRDA Unit office 87 90.63 Mike announcement 81 84.38 SMS based communication 42 43.75 APCRDA website 65 65.21 Grievance Redressal Item Number Percent Do you have any grievances in LPS process / compliance 6 100 Have you submitted your grievances 6 100 Have your grievances been resolved 6 100 Are there any pending grievances with APCRDA 0 0 Indebtedness Particulars Number Percent Have you taken any loan? 1- Yes/ 2- No 3 3 If Yes, what is the purpose Source of Loan 1 – Bank 1 33 2- Pvt. Money Lender 1 33 3- Relatives 0 0 4 – Neighbor 0 0 5 – Others (specify) 1 33 What is the total amount taken? In INR (Average) 75,000 Rate your annuity amount with your earlier incomes from the lands given to LPS Rate annuity with earlier income Number Percent Less 14 18 66 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Same 18 23 More 48 60 80 100 Annuity amount is being supplemented Annuity amount is being supplemented Number Percent Family purpose utilized 36 78 Fair 8 17 Sufficient 1 2 Not sufficient 1 2 46 100 Annuity amount is supplemented to lead same living standard as before Number Percent Insufficient 11 16.18 sufficient 57 83.82 68 100.00 Expected land prices for returnable plots/Sq. Expected Average Price 2017 (current) 2020 2025 Residential 4935 6241 10358 Commercial 4160 7124 9771 4.3 Data Analysis of socio-economic conditions of vulnerable families under surveyed LPS landowners category (N = 25) Gender of HH No. of people Percent Not reported 14 56.0 Female 4 16.0 Male 7 28.0 Total 25 100.0 Religion No. of people Percent Hindu 14 56.0 Not reported 11 44.0 Total 25 100.0 Caste No. of people Percent General 10 40.0 SC 3 12.0 Total 13 52.0 Not reported 12 48.0 Total 25 100.0 Possession of Ration Card No. of people Percent Not reported 5 20.0 67 ASCCDP: Resettlement Action Plan for Flood Mitigation Works No 1 4.0 Yes 19 76.0 Total 25 100.0 Type of ration Card No. of people Percent Not reported 10 40.0 White 15 60.0 Total 25 100.0 Size of Family No. of families Percent 1-2 17 68.0 3-4 6 24.0 5 -6 2 8.0 Type of Family No. of families Percent Individual 16 64.0 Joint 2 8.0 Nuclear 7 28.0 Total 25 100.0 Age of HH No. of people Percent Below 50 4 16 Above 50 8 32.0 Not reported 13 52.0 Total 25 100.0 Education of HH No. of people Percent Not reported 17 68.0 10th 1 4.0 7th 1 4.0 Degree 1st Year 1 4.0 Illiterate 1 4.0 Nil 4 16.0 Total 25 100.0 Assets Owned Before LPS After LPS No. of people Percent No. of people Percent Two wheeler 16 64.0 19 76.0 Three Wheeler 2 8.0 2 8.0 Four wheeler 6 24.0 7 28.0 Tractor 2 8.0 3 12.0 Tiller 1 4.0 1 4.0 Television 17 68.0 19 76.0 68 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Refrigerator 14 56.0 15 60.0 Grinder 11 44.0 12 48.0 Landline 9 36.0 10 40.0 LPG 19 76.0 20 80.0 Cell phone 22 88.0 22 88.0 Type of House No. of people Percent Kutcha 2 8.0 pucca 16 64.0 Semi pucca 7 28.0 Total 25 100.0 Ownership of house No. of people Percent Own 25 100.0 Total 25 100.0 Other facilities to the house owned No. of people Percent Percent Cumulative Percent Separate Toilet 25 100.0 100.0 100.0 Electricity 25 100.0 100.0 100.0 Pipe water supply 25 100.0 100.0 100.0 Land Ownership No. of people Percent Not reported 2 8.0 Patta 25 92.0 Total 25 100.0 Loss of structures under LPS No. of people Percent Not reported 4 16.0 No 19 76.0 Yes 2 8.0 Total 25 100.0 Any disputes on the land (not parted in LPS) No. of people Percent Not reported 6 24.0 No 19 76.0 Total 25 100.0 Agricultural Income before joining LPS No. of people Percent 69 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Not reported 17 68.0 Less than 75,000 8 28.0 Above 75,000 1 4.0 Total 25 100.0 Cultivation by Self / leased out No. of people Percent Not reported 20 80.0 self 5 20.0 Total 25 100.0 Returnable plots, annuity and other returnable benefits: S. No. Item Commerci Percent Resident Percent al (Yes ) ial (Yes) 1 Received returnable plot? (Yes / No) 23 92.0 23 92.0 1A If yes, have you registered (Yes/No 9 39.1 9 39.1 1B Received your returnable plot 22 88.0 22 88.0 individually 1C Identified the plot on the ground (Yes / 4 16.0 4 16.0 No) 1D Returnable plot is as per plot options 18 72.0 18 72.0 (Yes / No) 1E Do you plan to sale (Yes / No) 4 16.0 4 16.0 1F Did you get the plot in the same village 18 72.0 18 72.0 1G Have you mortgaged / sold your 4 16.0 4 16.0 returnable plot (Yes / No). 1H Do you want to construct? (Yes / No) 3 12.0 3 12.0 1I Are you satisfied with conduct of lottery 18 78.3 18 78.3 process (Yes / No) 1J Do you have any objections in plot 1 4.3 1 4.3 allotment Sl. Item Frequency Percent No. 2 Are you receiving annuity regularly (Yes / No) 25 100.0 4 Self-employment/ employment, details 2 8.0 5 Are you availing free health cards 20 80.0 6 Are you availing fee reimbursement 5 20.0 7 Did you get loan waiver, if yes, amount 17 68.0 Average Amount of Loan Waived 79412 Indebtedness No. of people Percent Not reported 1 4.0 No 21 84.0 Yes 3 12.0 Total 25 100.0 70 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Amount of loan No. of people Percent 100,000 1 33.3 125,000 1 33.3 Not reported 1 33.3 Total 3 100.0 Rate annuity with earlier income No. of people Percent Not reported 2 8.0 Less 4 16.0 more Final 11 44.0 same 8 32.0 Total 25 100.0 Annuity amount is being supplemented No. of people Percent Not reported 11 44.0 Fair 6 24.0 Family purpose 8 16.0 Total 25 100.0 Annuity is sufficient to lead same living standard as before No. of people Percent Not reported 5 20.0 No 3 12.0 Sufficient 17 68.0 Total 25 100.0 71 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure – 5 Details of Public Consultations Summary of Public Consultations held at Mandadam, Thulluru, Neerukonda and Krishnayapalem on 6th January 2018 on World Bank Draft Safeguards The draft RAP and EMP were disclosed in the APCRDA website and about 400 written suggestions were received which are made available in the project files for easy access. Draft Safeguards documents namely - Resettlement Action Plan (RAP) and Environmental Management Plan (EMP) were prepared and disclosed during December 2017 on the website of CRDA and the general public is notified through public notice. Comments and suggestions on the draft documents were invited. A Public Notice in both Telugu and English was published well before the public consultations‘ dates and wide publicity within the capital city was undertaken about the public consultation by CRDA. Minutes of the public consultation workshops held on January 6, 2018: Venue: Mandadam APCRDA Office – 11.30 am to 2.15 pm - Participants – Around 127 out of which 20 are women but very few of them agreed to sign the attendance sheet. More than 215 people gave representations and the data analysis of the type of complaints / comments / suggestions is in progress. Profile of the participants – Most of the participants are landowners of Undavalli and Penumaka villages while the remaining participants comprise of landowners whose lands are being acquired under RFCTLARR Act 2013 and the project displaced families and landless poor. Proceedings: The meeting started at 11.30 am and went on till 2.15 pm with a presentation of the alignment of the Flood Mitigation Works (Blue Network) through a map and explaining about how the project will be taken up to take a precautionary measure from the happening of flood in the capital city. The participants objected the Flood Mitigation works‘ project as a whole saying that this is against the judgement of Hon‘ble National Green Tribunal and the Environmental Act, WALTA Act and NDMA Act. The participants also expressed that the compensation being paid is not genuine and also there are a few title related issues. They also mentioned that they are ready to join Land Pooling Scheme provided that the compensation is increased up to their expectations. Some of the landowners expressed their concerns about the Gramakantham issues and also said that the pensions being paid to landless is insufficient when compared at the rising prices. They also mentioned that they are not finding any work as all the agricultural activities are stopped in the capital city region in the lands given for Land pooling. The public expressed that as per the NGT guidelines, the flood banks should not be touched to take up the Flood Mitigation works. 72 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Public consultation at Mandadam on January 6, 2018 – Representation from APCRDA, ADC, VMM and public The public mentioned that the LPS layouts that are being developed are not up to the mark. They expressed that the proposed alignment is not feasible. They said that there is no drinking water for the last five decades. Krishna water has been discharged to villages of capital city to cater to the drinking water needs. From the above discussions, it is observed that there are no comments specific to the draft RAP. However, the public who have actively participated are mainly from the villages of Undavalli and Penumaka where the sub-project of Flood Mitigation works is not covered at all. Emails were received with identical attachment from 13 persons using 15 mail ids (13 people sent from their own mail ids while two of them sent from different mail ids) email ids. Out of these, no persons are project affected persons under flood component. Venue: Thulluru from 3.00 pm to 4.00 pm – Participants – 17 out of which two were women comprising of landowners and landless poor. The presentation on draft documents of EMP as well as RAP was made by the Director, Strategy. The public expressed their doubts about the alignment and the water storage capacity of the proposed reservoirs and the area / extent covered by these reservoirs. The workshop went on smoothly without any major comments / suggestions for improvement of RAP and EMP. 73 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Public consultation at Thulluru on January 6, 2018 – representation from ADC, APCRDA, VMM and local public Venue: Neerukonda – 5.00 pm to 6.45 pm – Participants – 120 out of which 28 were women but no one signed the attendance sheet. The participants included landowners of Undavalli and Penumaka villages who have participated in Mandadam consultation also. Around 200 representations were received including farmers federations with identical text in the documents. The public expressed that they are not ready to give their lands. They also expressed that they are against the capital city construction and development. They said that the vagu lands are not to be used for Flood Mitigation works. They enquired whether ASCCDP is a registered body and ADC has a right to develop infrastructure facilities. Some of the public expressed title related issues and Gramakantham issues. They expressed that the burial ground in Mandadam is getting affected for which it is made clear that the works are re-aligned to avoid displacement of the burial ground. They said that the development works are not being done as per the applicable Acts and policies. They mentioned that the records in government are misleading and hence requested for reinitiating the study about the lands, agriculture, Jareebu-dry classification, type of land use, etc., and then prepare the RAP for payment of compensation. An issue pertaining to lift irrigation to lands in Yerrabalem has been raised. The public opposed the storage capacity and extent of reservoir coverage in Neerukonda saying that the base estimates are incorrect. They expressed that the capital city should be built in an alternative area instead of present proposed locality. Public consultation at Neerukonda on January 6, 2018 74 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Venue: Krishnayapalem – 7.00 pm to 7.35 pm – Participants – 25 out of which six are women. The public here expressed that the sub-project is a good initiative from the government side to preserve water and as a precautionary measure to avoid flooding in the capital city. They expressed that another reservoir at Ananthavaram will also be helpful in catering to the needs of the capital city population. The public also mentioned that the R&R colonies are to be provided to PDFs with all the facilities on par with the LPS layouts. They also expressed that the Karakatta bridge has to be strengthened. Additional protection measures and safety measures to avoid disaster has to be taken up and included in the EMP. Public Consultation at Krishnayapalem on January 6, 2018 with officials from ADC, APCRDA,VMM and local public With this, the workshops concluded at all the four locations. The photographs as well as available attendance sheets are accessible in the project files at APCRDA, Vijayawada office. The following matrix presents the details of the issues discussed and the clarifications provided by the Authority: 75 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority 1. Mandada Jan 6, 2018  More  Participants objected that APCRDA m (11.30 am than 215 CRDA gave two messages received requests to 2.15 pm) participan about the meetings; it from the public to ts caused ambiguity to conduct meetings  Landown attend the meetings. in their villages ers from also. Accordingly Undavalli two more & meetings were Penumak announced in a Thulluru and  PAPs Krishnayapalem  Landless which are poor convenient for people flood PAFs to participate. It is appraised to all that the participants are welcome in any / all of the meetings.  Participants said that APCRDA CRDA taking signatures clarified that the from the attendees and participants are not mention any minutes required to on the paper, so they record their objected, mainly they participation as it suspected that the is an important attendance sheet is used evidence of their as confirmation paper of participation the meeting. which will be kept in project files throughout the project period. It is further clarified that minutes will be included in the revised version of RAP and uploaded onto website of APCRDA for access by the public.  Farmers objected that The works CRDA did not follow the undertaken by 76 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority NGT guidelines, as per APCRDA are in NGT flood ways are not to accordance with disturb existing ones, but the NGT in some areas Rayapudi, directions. If any Lingayapalem it was deviations filled. observed due to miscommunicatio n will be quickly addressed appropriately.  The public also expressed No pending that the compensation issues related to being paid is not to project footprint. genuine and also there are Statements raised a few title related issues. on adhoc basis are forwarded to concerned authorities for initiating necessary action.  Farmers expressed It is clarified that whether reservoir‘s bunds the bunds will be are prepared pucca made to withstand overflows, breaches, etc., and will be as per the relevant engineering / construction codes prescribed by IS. Also the designs are vetted by professional agencies and technical committees.  People expressed the It is clarified in concern that pensions are RPF and also in paid to landless is RAP that pension insufficient looking at the is an allowance rising prices. and is not a replacement of livelihood income. Pension paid to landless is equivalent to the 77 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority annuity of the landowner with an acre or less of land.  They also mentioned that The skill they are not finding any development and work as all the livelihood agricultural activities are development stopped in the capital city initiatives for Final region promoting alternate livelihoods are explained. It is further clarified that targeted skill development programs will be conducted as desired by them.  People expressed concern The inundation about the flooding mitigation problem in the rainy measures through season & Public enquired the project are about the immediate explained in mitigation measures: detail. The reservoirs, canals and the pumping systems are designed to fully mitigate 1 in 100 year flows. On an immediate basis, the existing channels are being cleaned and pumping systems at Undavalli are being completed.  The public expressed that The EMP has the earth material would already put in be generated from place mitigation widening and deepening measures of the canals: Mitigation regarding dug measures has to be taken earth. up and included in the EMP.  People expressed that as The proposed 78 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority per the NGT guidelines, works will be as the flood banks should not per the directions be touched to take up the of Hon‘ble NGT. Flood Mitigation Works.  They expressed that the Alignments are proposed alignment is not finalized only feasible after conducting required studies and after approval of the Competent Authorities.  People expressed that they The Capital City faced the drinking water Infrastructure problem from the last 5 Master Plan has decades. addressed the water supply scheme for the entire capital city. 2. Thulluru Jan 6, 2018  Total 17  The public expressed their It is clarified that (3.00 pm to participan doubts about the the alignments 4.00 pm) ts alignment and the water are finalized after  2 women storage capacity of the conducting  Landless proposed reservoirs and required poor & the area/ extent covered gravitational landowne by these reservoirs. They studies and with rs and also expressed that it the approval of becomes difficult for them the Competent to attend the frequent Authorities. meetings, surveys, FGDs, Similarly, new etc.. in view of their reservoirs are current work and proposed with a requested not to create storage capacity any disturbance unless the of 0.4 TMC at meeting/ issue is really Neerukonda, 0.1 urgent. TMC at Krishnayapalem and 0.03 TMC at Sakhamuru. The public are informed that unless and until there is a great need, meetings and surveys will not be scheduled as suggested. 79 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority 3. Neeruko Jan 6, 2018  Total 120  The public expressed that It is clarified that nda (5.00 pm to participan they are not ready to give required technical 6.45 pm) ts their lands. They also studies have been  28 expressed that they are carried out as women against the capital city required to  No one construction and finalize the signed development. designs and the  Vagu lands are not to be drawings and attendanc used for Flood Mitigation there is no e sheet. Works. necessity for any  landowne  They enquired whether apprehension as rs of ASCCDP is a registered to the storage Undavalli body and ADC has a right capacity of the & to develop infrastructure reservoirs. Penumak facilities. Further, it is a  Some of the public clarified that  Landless expressed title related ASCCDP is a labours issues and Gramakantham project designed issues. by APCRDA  They said that the which is development works are constituted under not being done as per the the Act and the applicable Acts and ADC is the policies executing agency of the works.  They mentioned that the Other issues as records in government are raised by the misleading and hence requested for reinitiating public as to the study about the lands, Gramakantham, agriculture, Jareebu-dry development classification, type of land works, etc., have use, etc, and then prepare been explained in the RAP for payment of a transparent compensation. manner. With regard to  The public opposed the construction of storage capacity and Amaravati at extent of reservoir alternative coverage in Neerukonda location is a saying that the base policy matter to estimates are incorrect. be decided by the  They expressed that the Government. capital city should be built in an alternative location instead of Amravati. 4. Krishnay Jan 6, 2018  Total – 25  The public expressed / The public are apalem (7.00 pm to  Women: 6 enquired about the green clarified that 7.35 pm) belt development along sufficient green 80 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Sr. Name of Date Major issues discussed Clarification No the /time Participa by the . village nts authority the vaagus (canals) and belt development reservoirs: included in the is being taken up EMP along the Vaagus (canals) and reservoirs as per the assurance given to NGT by APCRDA. Suggestions from the local people in the area  The public here expressed that the sub-project is a good initiative from the government side to preserve water and as a precautionary measure to avoid flooding in the capital city.  The public also mentioned that the R&R colonies are to be provided to PDFs with all the facilities on par with the LPS layouts.  They also expressed that the Karakatta bridge has to be strengthened. Additional protection measures and safety measures to avoid disaster has to be taken up and included in the EMP. Website clipping of invitation for Public Consultation Workshops held on January 6, 2018 81 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Public Notice in Newspapers about the public consultations held Andhra Prabha dt. 3-1-2018 Deccan Chronicle Dt. 6-1-2018 82 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Andhra Jyothi Dt. 29-12-2017 Print Media Coverage: The public consultations were widely covered by the regional media which are as under: Andhra Jyothi Dt. 07-01-2018 83 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Deccan Chronicle Dt. 07-01-2018 Eenadu dt. 07-01-2018 84 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Final Eenadu Dt. 07-01-2018 Sakshi Dt. 07-01-2018 85 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annex 5A: Summary of Focus Group Discussions Out of the 20 affected villages21, 20 Focus Group Discussions were conducted in 14 villages at different locations. Around 165 people consisting of PAFs and landless pensioners, women‘s groups, SC/ST community, structure affected PDFs, PDFs affected on government lands, etc. The attendance sheets and the detailed pictures of these FGDs are available in the project files for reference. A detailed description of the key issues raised and how those issues are addressed is presented below. No Key issues raised How those addressed Mandadam: 25-07-2017: FGD with marginal farmers, landless pensioners and PDFs due to structure loss - 15 attended Entitlements to the LA and LPS The entitlements under LA, LPS and Negotiated Settlement Policy have been explained in detail. Ayinavolu: 25-07-2017: FGD with women pensioners and marginal farmers - 23 including seven women Requested for extending Health cards Government of Andhra Pradesh as part coverage and acceptability in more of the NTR Vaidya Seva issues Health number of hospitals for all kinds of cards to only BPL families / holders of ailments. white ration cards. In Amaravati, the Health cards are issued to all the residents of Capital City as on 8-12-2014. These health cards enable treatments to 1044 ailments at designated hospitals across Andhra Pradesh. Pichikalapalem: 25-07-2017 : FGD with Marginal Farmers, pensioners and occupants in Government lands - 35 including 9 women Loans for small business, fees The policy is being prepared for issue of reimbursement loans to initiate entrepreneurial activities. Krishnayapalem: 19-03-2018 : FGD with occupants in Government lands: 8 participants including 1 woman  Annuity is not being paid to the  The compensation to occupants of occupants who are on Govt. Government lands was covered lands. It is requested to provide under G.O.Ms.No.153 dated 19-04- annuity to them on par with other 2017 and the compensation is being assigned LPS land owners. They paid accordingly. also knowingly or unknowingly  With reference to payment of depending upon Government pensions to non-residents it is lands for the past three clarified that all the persons who are generations and getting their in Household survey will be livelihood. provided with pensions as per their eligibility. If those eligible are missed  Pension amount of INR 2500 is out, they can apply to receive the 21 Total 20 revenue villages affected by the flood mitigation works but impacts are only in 15 villages. 86 ASCCDP: Resettlement Action Plan for Flood Mitigation Works also not given to some of the pension amount. It is clarified that occupants who are not now living about 200 new pensions are in that village. sanctioned in the preceding weeks.  Indexation of pension amount is  10% increase of Pension amount considered. is proposed.  The eligibility or ineligibility of  The allotment of residential plots to occupants needs clarity to know occupants is as per the guidelines how they are given residential under land pooling scheme. Specific returnable plots 250 sq. yd. per grievances, if any, may be applied to Acre. Majority of the occupant‘s concerned CA for examination. demand to provide at least 500 sq.  It is clarified that an individual can yd. as their family size is receive annuity equivalent to 1 acre increased. even if he / she possesses combined extent of less than 1 acre. The request  Minimum of INR 30,000/- not is not admissible as per the policy. applied to one individual as he has his government land about 0.60 acres at four different places. Nowluru-2 (Yerrabalem): 19-03-2018 : FGD with LPS Landowners: 6 participants  Drainage in existing village will  The flood mitigation plan including be a problem for them. Before, storm water discharge is explained. this capital city project, there are The plan will ensure that there are no vaagus and Donkas through issues arising out of discharge of which the sewage water flows. storm water. But now all the vagus, vankas  Indexation of pension amount is and Donkas were taken away by considered. CRDA and developing them as  With reference to development of returnable plots. Now they may Infrastructure, it is clarified that all face drainage problem. steps are being taken in a phased manner to develop the infrastructure  An individual who is Dumb and as per master plan. local eligible person is not getting pension from CRDA or handicap pension under Social security scheme.  Providing infrastructural facility to all LPS returnable plots to be planned as soon as possible.  Loss of Agricultural activity is a problem for the farmers. Sakhamuru : 20-03-2018 : FGD with LPS landowners: 4 participants  Boundary stones at some  Boundary stones as per standards returnable plots to be fixed. are fixed for all the returnable plots with GPS coordinates. Any specific  Health Cards issue brought to the issue will be addressed by the CA. 87 ASCCDP: Resettlement Action Plan for Flood Mitigation Works notice of the Commissioner. The Commissioner assured that  Project information centre is there will be some particular designated to provide additional individual on this job of health support regarding health cards. A cards, and his Phone number will qualified medical doctor is placed as be written on the walls of every coordinator to facilitate health care CRDA office to facilitate the and treatment related issues for Health card holders to contact the Amaravati health card holders. A person at need times. sticker containing essential information will be affixed to each  Seasonal employment to be health cardholder‘s residence and provided to local labour or communication material is handed vehicles. over regarding treated ailments and designated hospitals. A common toll  NTR Sujala Sravanthi Scheme is free number 104 will attend to excellent in supplying drinking resolving any queries water to Sakhamuru village.  Steps are being taken to position a  Water for daily use is not person to look after health cards available. Hence there will be issues and specific instructions have much water trouble for daily use been issued to all contractors by the during ensuing summer and it is ADC to engage local people in requested to plan for alternative construction work. source of water either from the pipe line arranged at VIT or from  Suitable steps will be taken to SRM or from Sakhamuru park redress water problems. where water pipes arranged. Velagapudi : 20-03-2018; FGD with LPS landowners: 9 participants  Discrimination in LPS package for  It is clarified that compensation is the same individual for an extent being paid as per the approved of 0.19 acres of Jareebu it is INR guidelines and there is no 30,000 offered but for other parcel discrimination in payment of of land with the same extent of annuity to any person. Specific cases 0.19 under assignment is offered may be brought to the notice of the only INR 10,000. But the concerned CA for redressal. Steps are individual expects that a being taken to relocate the plots in minimum of INR 30,000 for the the undisputed area. Flood assigned land also. Mitigation Works will be done as per the drawings approved to avoid  Returnable Plots registration is inundation. pending as their plots are located on the land of a person who is willing to give land to CRDA either under LPS or under LA or NSP. Requested to take steps for reallocation of plots.  Panchayat Secretary told that if Vaagu is properly levelled to 88 ASCCDP: Resettlement Action Plan for Flood Mitigation Works ensure free flow of rain water into Krishna River, it a good solution for inundation problems and requested to take steps accordingly as all land now is under the control of CRDA. Abbarajupalem: 21-03-2018: FGD with LPS landowners: 3 participants  Returnable plots for LPS land  Utmost care has been taken to allot owners allotted on the land not plots in lands under possession of surrendered by the private APCRDA. Specific grievances as to individual. And also there are plot allotment may be brought to the only two boundary poles for the notice of the concerned CA for commercial plots which require redressal. planning for erection of another  A technical committee constituted by two poles. the District Administration has reviewed all cases regarding land  It is complained that the classification and annuity is paid authorities have denied payment based on the decision of the of annuity to them treating their Committee. lands as non Jareebu now, though they were classified as Jareebu lands in the past and paid annuity accordingly for three years. It is further complained that notices were issued to 11 land owners and the individuals went to the court also. But two individual have not yet received either notice or annuity but orally informed. Thus the farmers are not willing to get their lands registered. Borupalem: 21-03-2018 : FGD with LPS landowners: 11 participants  Returnable plots registration is  New registration offices are set up in somewhat slow. centralized places to ensure speedy registration of plots. It is informed  Flood water from Vykuntapuram that about 10,000 registrations are must be diverted into the Krishna already complete. Channelization of River. flood water will be attended as per the approved drawings to ensure  Vaagu digging soil must be used safety of property and lives. for filling the low-lying areas Consultations are in its way for the where plots are in existing village transfer of PWD lands to APCRDA. nearer to Vaagu.  One individual who has gone to Singapore told that there is no private land which all the land resources are in the government control and also all individuals 89 ASCCDP: Resettlement Action Plan for Flood Mitigation Works work hard and give more importance to cleanliness.  It is informed that Lands under PWD control are not yet transferred to and all those types of land must come to CRDA custody and then all the land owners of Borupalem who surrendered their land under LPS will go to Registration.  Jareebu lands are now treated as non-Jareebu which is a major problem related to 14 acres of Lemon Gardens.  Infrastructure as promised to be provided at the LPS layouts at the earliest. Venkatapalem: 21-03-2018 : FGD with LPS landowners and Marginal farmers: 15 participants  It is opined that it will take 20  The matter of extending annuity to years or so for getting the area LPS landowners beyond 10 years, developed as promised. So all the Kalyana Lakshmi, Medical facilities LPS land owners request for are noted and passed on to enhancement of annuity period appropriate authorities. from 10 years to 15 years annuity.  1325 health cards were issued at Venkatapalem village and all of them shall be provided with medical aid without any ceiling and without any charges for Medical tests.  Kalyana Lakshmi scheme shall be extended to poor people in upper castes also.  LA farmers land under valued as INR 22 lakhs. But the land owners request to fix the value basing on the market value at INR 4 crore per acre.  Health card Desk is to be situated at Thulluru. 90 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Kuragallu: 22-03-2018 : FGD with LPS landowners: 18 participants  It is enquired about the Buffer  Buffer zone as provided under Flood Zone under flood mitigation Mitigation Works and as per the Measures (where no residential drawings will be adopted. Similarly construction cannot take place) revetment of channels will be taken which is meant for the purpose of up as per drawings and designs. greenery and for strengthening of  The issue relating to Bunds of the proposed channels. Gramakanthams‘ is considerably resolved already.  Revetment of Channels is  The payment of annuity is being necessary as it is the loose black made to all the eligible LPS soil which may be eroded during landowners. The third year annuity floods. has already been released. Compensation to LPS farmers  In survey no. 577 an extent of 0.51 including jasmine gardens is being acres which was surrendered to paid as per the provisions of LPS CRDA under LPS. Annuity of Rules. Specific demarcation of plots INR 15,000/ for one year was is being carried out by putting paid and it was delayed the next boundary stones. two annuities.  People demanded to solve the Gramakantham burning issue as soon as possible.  The Land owners of Jasmine gardens demands for higher compensation.  10 cents exemption is a demand from the people of Kuragallu.  Poles for the plots to be placed to identify where one‘s own plot is. There are no poles to some plots. Ananthavaram & Nekkallu: 22-03-2018 : FGD with LPS landowners: 8 participants  There is some delay in payment  With regard to the partial loan of annuity waiver, the beneficiary is advised to submit representation for taking  Gramakantham issue suitable steps.  Partial loan waiver. Penumaka : 25-04-2018 FGD with LPS landowners: 4 participants including 1 woman  Allotment of returnable plots not  The request for extending unlimited yet done. The farmers requested medical facilities, capital gains tax is to give the returnable plots as passed on to appropriate authorities. soon as possible.  Health cards were issued to everyone but in some hospitals 91 ASCCDP: Resettlement Action Plan for Flood Mitigation Works these were not accepted, saying that, that particular hospital/disease is not listed on the health card.  The farmers who attended to the FGD felt happy for the rise in Land prices due to capital announcement / formation only.  People request capital gain tax exemption until the allotted plot(s) is sold.  Peg-marking is not yet done. Final Brief Photo Report of Focussed Group Discussions22 FGD at Krishnayapalem with people dependent on government lands on 19-03-2018 FGD at Yerrabalem (Nowluru-2) with LPS landowners on 19-03-2018 22 Full set of photographs are made available in project files at APCRDA, a few visuals only are presented for ready reference. 92 ASCCDP: Resettlement Action Plan for Flood Mitigation Works FGD at Sakhamuru with LPS landowners on FGD at Velagapudi with LPS landowners on 20-03-2018 20-03-2018 FGD at Abbarajupalem with LPS landowners FGD at Venkatapalem with LPS landowners on 21-03- on 21-03-2018 2018 FGD at Kuragallu with LPS landowners on 22- FGD at Borupalem with LPS landowners on 21-03-2018 03-2018 93 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Mandadam – FGD with pensioners on Mandadam – FGD with Structure loss on 25-07-2017 25-07-2017 Ayinavolu– FGD with women pensioners on Ayinavolu – FGD with Marginal farmers on 25-07-2017 25-07-2017 Pichikalapalem – FGD with Pensioners on Pichikalapalem – Marginal Farmers on 25-07-2017 25-07-2017 Pichikalapalem – occupants in Govt. Land on Mandadam –FGD with marginal Farmers on 25-07-2017 94 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 25-07-2017 FGD with LPS landowners at Penumaka on FGD with marginal farmers at Undavalli on 25-04-2018 25-04-2018 95 ASCCDP: Resettlement Action Plan for flood mitigation works 96 ASCCDP: Resettlement Action Plan for flood mitigation works Annexure – 6 Land Guideline Values in the Project Area23 MARKET VALUES OF LANDS IN CAPITAL CITY VILLAGES - RATES AS PER THE REGISTERS / RECORDS Revision as on 01-08-2018 Revision as on 29-04-2017 Agricultural Agricultural land put to Agricultural land fit for House Name of the village Agricultural land per non- land INR house sites sites INR acre agricultural Per Acre INR per per Sq.Yd use per sq. acre Yard Wetlands / Wetlands Dry (1) Residential Jareebu & / Jareebu / Dry (2) Commercial Krishnayapalem 577000 3049200 630 10,00,000 500 579,1100 & Nowlur-1 1039000 3234000 1450 18,00,000 2000 Nowlur-2 1039000 3234000 1450 18,00,000 1100 Kuragallu 462000 3146000 650 8,00,000 500 Neerukonda 462000 3146000 650 4,00,000 500 Nidamarru 693000 4065600 840 12,00,000 600 Undavalli 2079000 4042000 1650 36,00,000 2200 Penumaka 924000 5082000 1050 16,00,000 800 Abbarajupalem 462000 2541000 525 8,00,000 400 Borupalem 462000 2541000 525 8,00,000 400 Dondapadu 346500 2541000 525 6,00,000 400 Pitchakalapalem 346500 2541000 525 6,00,000 400 Inavolu 346000 2541000 525 6,00,000 400 Rayapudi 924000 3303300 682.5 16,00,000 500 Kondamarajupalem 577000 2541000 525 10,00,000 500 Lingayapalem 577000 2541000 525 10,00,000 400 Uddandarayunipalem 577000 2541000 525 10,00,000 400 Malkapuram 462000 2541000 525 8,00,000 400 Nekkallu 346000 2541000 525 6,00,000 400 Nelapadu 346500 2541000 525 6,00,000 400 Sakhamuru 346000 2541000 525 6,00,000 400 Thullur 462000 5082000 1050 8,00,000 800 Velagapudi 462000 2541000 525 8,00,000 400 23 These are guideline values captured from Sub-Registrar Office. 97 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Venkatapalem 1155000 2310000 1050 20,00,000 800 Mandadam 693000 2887000 1155 12,00,000 1859.5 Ananthavaram 346000 2541000 6,00,000 400 Under LPS or under Negotiated Settlement Policy, the revision of Market Values will not have any bearing. However, as per the Section 26 of LARR Act of 2013, there is a need for revision of the Market Value for the lands covered by acquisition under LARR Act of 2013. Accordingly, Anomalies Committee have revised the Market Values under the Chairmanship of the District Collector, Guntur during the year 2017. Hence, steps have been taken to revise the Market Values as per the procedure. The landowners will get the compensation as per LARR Act 2013 taking the revised basic value / the average sale price whichever is high for such category of lands as per the provisions of the Section 26 of the LARR Act of 2013. Annexure – 7 List of PAFs, PDFs – Flood Mitigation Works List of PAFs under Land Acquisition for Flood Mitigation works S.no. Village Survey Number Name of the landowner 1 Sakhamuru 45 Marri Sivaiah 2 Sakhamuru 45 Marri Saraswathi 3 Sakhamuru 45 Marri koteswara Rao 4 Sakhamuru 45 Marri Srinivasa Rao 5 Abbarajupalem 32 Yadlapalli Ganesh 6 Ananthavaram 117 Bandla Seshagiri Rao 7 KURAGALLU-1 530 MURUGUDU MADHUSUDHAN RAO 8 Lingayapalem 184 Anumolu Venkata Tiruchand Gandhhi 9 Malkapuram 3 Nuthakki Ramadevi 10 Malkapuram 3 Nuthakki Suryaprakasarao 11 MANDADAM-1 94 BORRA HANUMANTARAO MANDADAM-1 94 12 MANDADAM-1 121 CHINTALA SIVA DURGA VARAPRASAD 13 MANDADAM-1 GADDIPATI BHARATHI 14 MANDADAM-1 126 Nuthakki Narasimha Naidu 15 MANDADAM-1 278 PRATHURI SAMBASIVA RAO MANDADAM-1 280 MANDADAM-1 280 16 NEKKALLU 59 RAVELA RAMACHANDRA RAO 17 NEKKALLU 59 RAVELA SREENIVASA RAO 18 NEKKALLU 59 RAVELA RAMBABU 19 NEKKALLU 59 RAMINENI RAMARAO 20 NEKKALLU 59 RAMANENI STHANAKA BABU 21 NEKKALLU 59 RAMANENI MALLESWARI 22 NEKKALLU 59 ABBURI RAJANI 23 NEKKALLU 120 VINAY CHOWDARY JONNALAGADDA NEKKALLU 120 98 ASCCDP: Resettlement Action Plan for Flood Mitigation Works NEKKALLU 120 NEKKALLU 122 24 NEKKALLU 122 JONNALAGADDA MADUSUDHANA RAO 25 Nowlur-2 586 AKULA SIVA SANKAR RAO 26 Pichchikalapalem 93 KAKUMANU MADHAVARAO 27 Rayapudi-1 93 MADALA BHUVANESWARA RAO 28 Rayapudi-1 93 MALISETTY ANKARAJU 29 Rayapudi-1 93 MALISETTY SRINIVASA RAO 30 Rayapudi-1 93 PENUMUCHU SHESHU KUMARI 31 Rayapudi-1 93 YAMPARALA RAMARAO 32 Rayapudi-1 152 RAYAPUDI EDUKONDALU 33 Rayapudi-1 162 KONURU HANUMANTHARAO 34 Rayapudi-1 188 MANDALI ANUSHA 35 Rayapudi-1 Final MALISETTI VENKATARATNA KUMARI 36 Rayapudi-1 MALISETTI SRINIVASA RAO 37 Rayapudi-1 337 ADUSUMILLI TRIPURASUNDARI 38 Rayapudi-1 KONURU RANGANAYAKAMMA 39 Kondamarajupalem 28 KONDAVEETI SRINIVASA RAO 40 Kondamarajupalem 28 KONDAVEETI SIVA KUMARI Kondamarajupalem 34 Kondamarajupalem 35 41 Velagapudi 23 GUDURI SIVA RAMA KRISHNA Velagapudi 4 Velagapudi 23 Velagapudi 24 42 Velagapudi 41 GARIKAPATI RAMA KRISHNA Velagapudi 43 Velagapudi 3 GADDE VENKATESWARA RAO 44 Velagapudi 3 GADDE CHANDRA SEKHAR 45 Velagapudi 42 NEERUKONDA JAYA SIVA RAMA KRISHNA 46 Velagapudi JASTY RAM PRASAD 47 Velagapudi GAGGARA SURYA NARAYANA 48 Velagapudi TALLAM MANIKANTA ANANTHA SAI VISWANADH 49 Velagapudi Manne krishna kishore 50 Velagapudi DAGGUMATI MARUDVATHI DEVI 51 Venkatapalem 196 Pasupuleti Parvathi Devi 52 Venkatapalem 231 Lanka Venkata Lakshmi 53 Penumaka 84 Chappidi Latha, W/o Suresh 54 Penumaka 84 Chappidi Sree Ramulu, S/o Venkaiah 84 55 Penumaka 84 Meka malliswari, W/o Sambi reddy 56 Penumaka 84 Meka Sambireddy, S/o Koti reddy 57 Penumaka 84 Reddybattula Nagireddy 58 Penumaka 85 Arekuti Sivareddy, S/o Pitchi reddy 59 Penumaka 87 Meka Bharghivi, W/o Sridhar reddy 60 Penumaka 87 Doddipati Pitchaiah & Meka Punan Reddty 61 Penumaka 88 Kaza . Jyothi Babu, Mallavarapu Nageswararao 62 Penumaka 88 Meka Obul Reddy 63 Penumaka 88 Meka Punna Reddy, Doddipati Pitchaiah 88 64 Penumaka 88 Mallavarapu Syamala, W/o Koteswara rao 99 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 65 Penumaka 88 Meka Ramiredy, S/o Obul reddy 66 Penumaka 88 Jonnala Venkata Sivamma, W/o Rami reddy 67 Penumaka 88 Meka Seshamma, 68 Penumaka 88 Meka Venkareddy, S/o Anji reddy 69 Penumaka 89 Meka Chandrashekhar reddy, S/o Venkata 89 reddy 70 Penumaka 89 Meka Subba reddy, S/o Siva reddy Katikala Narasimhareddy, S/o Ramakrishna 71 89 Penumaka reddy 72 Penumaka 89 Meka Seethamahalakshmi, W/o Subba reddy 73 Penumaka 89 Meka Guravauiah 74 Penumaka 90 Meka sivareddy & lakshmareddy 75 Penumaka 90 Kallam Vijayashekhar reddy, S/o Siva reddy 76 Penumaka Doddipati Rambabu, S/o Ramachandra rao 93 77 Penumaka Neelapu Ramya, W/o Manoj 78 Penumaka 229 Tamma Sudharani W/o Naga Muni Reddy 79 Penumaka 230 Kallam Sivareddy S/o Koti Reddy 80 Penumaka 232 Dandamudi Krishnarao S/o Ramalakshmaiah 81 Penumaka 232 Dandamudi Sadasivarao S/o Ramalakshmaiah 232 82 Penumaka 232 Polisetty Sivayya S/o Ankamaiah 83 Penumaka 232 Polisetty Krishnakumari W/o Hanumantha Rao 233 84 Penumaka 233 Polisetty Sivayya S/o Ankamaiah 85 Penumaka 233 Chekka Seshamma 86 Penumaka 233 Polisetty Rama mohanarao S/o Ankamma 235 87 Penumaka 234 Kallam Naveen Kumar Reddy S/o. Siva Reddy 88 Penumaka 235 Polisetty Ramamohanrao S/o Ankamma 89 Penumaka Mannava Appaji S/o Krishnaiah 90 Penumaka Mannava Lakshmanna & 3 Others 91 Penumaka Mannava Krishna Rao S/o Kotaiah 236 92 Penumaka Mannava Narasimharao S/o Goapaiah 93 Penumaka Mannava China Seshaiah 94 Penumaka Polisetty Venkateswararao S/o Ankamaiah 95 Penumaka Meka Sambireddy S/o Gopi Reddy 96 Penumaka 239 Meka Anjireddy S/o Bapi Reddy 97 Penumaka Bandi Veerareddy S/o Subba Reddy 98 Penumaka Meka Renuka W/o Srinivasa Reddy 99 Penumaka Meka Jayarami reddy S/o Lakshma Reddy 100 Penumaka Meka Sesha ratnam W/o Sambi Reddy 101 Penumaka 240 Meka padma W/o Sambi Reddy 102 Penumaka Meka venkayamma W/o Peddi Reddy 103 Penumaka Chirasani Bitchhireddy S/o Siva Nagi Reddy 104 Penumaka Meka Srinivasareddy S/o Sambi Reddy 105 Penumaka 242 Mannava Veeraiah 106 Penumaka 245 Muppiri Venkanna 107 Penumaka 247 Paritala Kotaiah Singamsetty Markandeya Babu S/o 108 Penumaka Venkateswara Rao 249 Dandu Manikumar S/o Anantha padmanabha 109 Penumaka sasthry Penumaka Repala Nageswararao S/o Hanumantha Rao 100 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 110 101 ASCCDP: Resettlement Action Plan for Flood Mitigation Works List of PDFs under Land Acquisition or Negotiated Settlement Policy S.no Village Survey number Name of the PDF 1 Mandadam-1 106 Aluri venu gopala rao Mandadam-1 Mandadam-1 107 2 Nuthakki satyanarayana Mandadam-1 3 Mandadam-1 107 Bejawada hanumantha rao 4 Mandadam-1 107 Bejawada satyanarayana Mandadam-1 107 5 Mandadam-1 Aluri sarveswararao Mandadam-1 6 Mandadam-1 107 Yarramaneni punnarao Mandadam-1 7 Mandadam-1 110 Aluri suryanarayana 8 Mandadam-1 110 Aluri venkata rao 9 Mandadam-1 110 Madala venu gopala rao 10 Mandadam-1 111 Gudapati havish 11 Mandadam-1 Gudapati siva naga mani 12 Mandadam-1 Gudapati venkateswara rao 13 Mandadam-1 Gudapati sambasiva rao Mandadam-1 107 14 Mandadam-1 Muppa nageswara rao 15 Mandadam-1 Peddu swarupa rani 16 Mandadam-1 Gudapati harshavardhana rao 17 Mandadam-1 Lavu sudha rani 18 Mandadam-1 117 Idupulapati koteswara rao 19 Mandadam-1 117 Idupulapati nageswara rao 20 Mandadam-1 117 Idupulapati rambabu 21 Mandadam-1 284 Gaddam gloryt rambabu 22 Mandadam-1 284 Bellam naga archana 23 Mandadam-1 284 Saggurthi ramya keerthana 24 Mandadam-1 284 Pathuri lakshmi narayana 25 Velagapudi 41 Garikapati ramakrishna 26 Rayapudi-1 152 Shaik mohiddin babu 27 Rayapudi-1 155 Jani begum 102 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure – 8 Summary on LPS PAFs – Blue Network Extent and Count: The total land requirement for the Flood Mitigation works is 1,998.86 acres of which 1131.30 acres is already available with APCRDA through Land Pooling Scheme, while 781.72 acres is government land. Therefore, the total land already available with APCRDA is 95.6%. The total count of parcels under LPS category is 500 corresponding to 2,041 landowners. However some landowners owned more than 1 parcel and based on ownership details, Aadhaar details, unique ownership details are arrived at which resulted in a total number of 1754 landowners including 4 landowners as part of linked activities – Undavalli Pumping Station (not using Bank funds). The list of landowners is available at the following link: https://crda.ap.gov.in/apcrda/userinterface/admin/PAFData_Flood.aspx Dry and Jareebu Classification: Analysis of the number of landowners and extent indicates that 77% of the landowners had dry lands corresponding to 81% extent, 22% had Jareebu lands corresponding to 18% extent and 1% had both dry and Jareebu lands corresponding to 1% extent, respectively. Marginal landowners: An analysis based on base annuity indicates that 84% of the landowners belong to Marginal landowner Category (less than 2.5 acres total extent) and possess 48% of total extent. Similarly, 14% of the landowners own between 2.5 to 5.00 acres and own 38% of the total extent. 2% possess more than 5.00 acres and own 14% of total extent. However, it may be noted that this analysis is based on the total extent owned and not based on the actual affected extent under flood mitigation works. Annuity: Total annuity paid for the 1,754 landowners is approx. ₹53 crores till date (including 3rd year annuity). Residents & non-resident landowners: Out of these 1,754 landowners around 648 (forming 37%) landowners are currently residing in the capital city while the remaining 63% of the landowners are non-resident. Out of these 648 resident landowners, 96 resident landowners were surveyed forming a sample size of 12%, during December 2017 to assess their existing socio-economic condition and prepare baseline data for monitoring the progress as well as performance with respect to indicators. The survey details in the form of tables are provided in Annexure 4 while the survey findings are summarized as under: Out of the 96 landowners who were surveyed, it is found that there are 24 women-headed households forming 25% of the total surveyed LPS landowners. 60% of the landowners are found to be literate at least till SSC education and 6% of them do possess professional 103 ASCCDP: Resettlement Action Plan for Flood Mitigation Works qualification while 14% are graduates and 2% are post graduates. As regards the occupation 47% of the landowners‘ occupation was cultivation while the remaining 53% depended on alternatives like working in service sector, daily wage earning, self-employment (business), etc. Most of the families among the 96 households surveyed are with a family size of 1 to 3 forming 85% while the remaining 15% family size is between 3-5. 76% of the households surveyed are Hindus by religion. Of the 96 landowners surveyed, 69% are general category, 2.1% belong to Backward Communities, 3.1% belong to Scheduled Castes. 94% have ration cards. 96% of the families reside in own houses while 4% constitutes to families residing in rental accommodation. 75% of families reside in pucca houses while 13.5% live in semi-pucca houses and 11.5% live in Kachcha houses. 98% of the households have electric connection; 98% of the families have piped water supply and 98% have individual household latrines. Out of 96, 90% of families possess patta land. About 2.9% informed that they hold some more lands which are not under LPS and likely to participate in land acquisition. 1.4% possesses land outside capital city area. Before joining LPS 85% of the families earned agricultural income of less than INR 75,000. 69% of the families cultivated the land by their own before joining LPS while 31% leased it out and earned income of less than INR 75,000. The average annual family income of the LPS landowners who were surveyed is INR 50,286. The average income earned from the land leased out is INR 15,000. 90% of the families have received the returnable plots. 12% have registered their commercial plots and 12% registered their residential plots. 60% of the people received plots in the same village and around 23% have mortgaged / sold their returnable plots. 15% have applied for building permissions for their commercial plots while 14% of people applied for building permissions for their residential plots. From the survey response, it is clear that 78% of people are satisfied with the conduct of lottery process. 100% of people surveyed are receiving annuity regularly and 22% have availed free health cards. 61% were found eligible and covered under fee reimbursement and 42% were found eligible and availed loan waiver. 83% of people participated in LPS consultations, 65% in Master Plan consultations, 66% participated in EIA consultations, 83% in consultations on Safeguards documents, 66% attended LPS layout consultations and 81% attended consultations on LPS Plot development by the teams of peg-marking and infrastructure. With regards to the Information and access to communication, 68% are using Mana Amaravati App, 82% are accessing information through WhatsApp, 90% are physically visiting the APCRDA unit offices, 84% are getting information through mike announcements and SMS based communication. 65% of people are visiting the APCRDA website for information. As regards the grievance Redressal, 100% grievances are addressed by APCRDA. The indebtedness percentage is 3% out of which 83% of people availed loans from Banks while 17% availed loans from private money lender. 104 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Around 60% of the people surveyed rated that the annuity being paid is more than the income earned by them earlier (before joining LPS) while 23% opined that it is the same and 17% expressed that the annuity is less. In response to questions to elicit perceptional view of the sample interviewed a few questions in respect of consideration of LPS over other options, annuity vis-à-vis the earlier incomes from agriculture, benefits / improvements on account of the Flood Mitigation Works, etc., were asked. Majority responses for each of the above are summarized below:  Land owners chose LPS over other options as the area is getting developed as Capital City.  Around 60% of the people surveyed rated that the annuity being paid is more than the income earned by them earlier (before joining LPS) while 23% opined that it is the same and 17% expressed that the annuity is less.  The landowners‘ expectation of increase in price is very optimistic ranging from a minimum increase of INR 5,000 per sq. yd. in residential areas to INR 10,000 per sq. yd. in commercial areas over the next 6 – 7 years over and above the current values. For the purpose of arriving at project affected families, unique landowner details are extracted from the full count. The unique landowners count is found to be 175424. The current progress of LPS for the project footprint is presented below: S. No. Particulars Current Progress in Numbers 1 Land Pooling Scheme Farmers affected by 1,754 Flood Mitigation Works 2 Number of farmers provided with 153325 returnable plots 3 Number of farmers who were paid 1,754 annuity for 3 years 4 Skill Development Trainings and Job trained more than 1,133 people to date; more than placements 770 got placed and 863 got directly recruited; (not separately segregated for project footprint yet) 5 Number of farmers who received loan 19,709 (not segregated for project footprint yet) waiver 6 Job cards and person days of employment 16,676 job cards were issued and 44,392-person days of employment generated during the current financial year (not segregated for project footprint yet) 7 Free Education Scheme Total 49 Students applied for Reimbursement of Tuition Fee. 21 students were found eligible for availing fee Reimbursement (not segregated for project footprint yet) 8 Free Medical facilities Three Phases Mega health camps were conducted by Network hospitals for 4,011 beneficiaries (not segregated for project footprint yet) Note: Above details will be segregated for project footprint during project monitoring 24 This number includes all categories of landowners including encroachers, those who purchased assigned lands. 25 Remaining 221 will be allotted returnable plots in the subsequent lotteries 105 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure – 9 Village-wise affected Encumbrance Details List of village-wise Encumbrances under Land acquisition S.no. Village Survey Sub division Project number affected extent (in acres) 1 Sakhamuru 45 45-b 0.22 2 Sakhamuru 45 45-b 0.22 3 Sakhamuru 45 45-b 0.22 4 Sakhamuru 45 45-b 0.22 5 Abbarajupalem Final 32 A 0.11 6 Ananthavaram 117 2 0.17 7 Kuragallu-1 530 0.05 8 Lingayapalem 184 - 1.35 9 Malkapuram 3 1 0.015 10 Malkapuram 3 2 0.015 11 Mandadam-1 94 A 0.930 Mandadam-1 94 B 12 Mandadam-1 121 2.0000 13 Mandadam-1 14 Mandadam-1 126 0.05 15 Mandadam-1 278 B Mandadam-1 280 2 0.5500 Mandadam-1 280 3 16 Nekkallu 3.93 17 Nekkallu 18 Nekkallu 19 Nekkallu 20 Nekkallu 59 21 Nekkallu 22 Nekkallu 23 Nekkallu A 0.65 Nekkallu 120 B 0.7 Nekkallu C 0.33 Nekkallu 0.28 24 Nekkallu 122 A 0.28 25 Nowlur-2 586 D 0.15 26 Pichchikalapalem 93 93/2a 0.08 27 Rayapudi-1 93 A3 0.5000 28 Rayapudi-1 93 A3 0.2500 29 Rayapudi-1 93 A3 0.2500 30 Rayapudi-1 93 A3 0.8100 31 Rayapudi-1 93 C 0.4000 32 Rayapudi-1 152 0.5700 33 Rayapudi-1 162 0.0900 34 Rayapudi-1 188 A 0.3500 35 Rayapudi-1 A 0.3100 106 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 36 Rayapudi-1 A 0.2000 37 Rayapudi-1 337 1 3.9900 2 3.7000 38 Rayapudi-1 2 0.5000 39 Kondamarajupalem 28 2.5900 40 Kondamarajupalem 28 41 Kondamarajupalem 34 2 0.0600 Kondamarajupalem 35 B 0.5000 42 Velagapudi 23 2 0.01 Velagapudi 4 - 0.32 Velagapudi 23 1 0.99 Velagapudi 24 A 2.02 43 Velagapudi 41 F 0.06 Velagapudi D 0.22 44 Velagapudi 3 A 0.07 45 Velagapudi 3 B 0.67 46 Velagapudi 42 - 3.28 47 Velagapudi 48 Velagapudi 49 Velagapudi Velagapudi 50 Velagapudi 51 Venkatapalem 196 0.02 52 Venkatapalem 231 0.54 53 Penumaka 84 0.5 54 Penumaka 84 0.8 84 0.445 55 Penumaka 84 0.4 56 Penumaka 84 0.6 57 Penumaka 84 0.03 58 Penumaka 85 0.35 59 Penumaka 87 A2 0.29 60 Penumaka 87 B 0.0075 61 Penumaka 88 A1 0.77 62 Penumaka 88 A1 0.06 63 Penumaka 88 B1 0.5 88 B3 0.05 64 Penumaka 88 B3 0.36 65 Penumaka 88 B3 0.36 66 Penumaka 88 B3 0.36 67 Penumaka 88 B3 0.24 68 Penumaka 88 C 1.57 69 Penumaka 89 A1 1.81 89 A2 1.02 70 Penumaka 89 A2 0.515 71 Penumaka 89 A2 0.95 72 Penumaka 89 A2 0.515 73 Penumaka 89 B 0.0075 107 ASCCDP: Resettlement Action Plan for Flood Mitigation Works 74 Penumaka 90 1.98 75 Penumaka 90 1.34 76 Penumaka 93 0.55 77 Penumaka 0.28 78 Penumaka 229 0.1628 79 Penumaka 230 1.36 80 Penumaka 232 0.3665 81 Penumaka 232 0.0425 232 1.035 82 Penumaka 232 1.145 83 Penumaka 232 1.145 233 0.38 84 Penumaka 233 0.4 85 Penumaka 233 0.03 86 Penumaka 233 0.905 235 0.06 87 Penumaka 234 0.045 88 Penumaka 235 0.06 89 Penumaka 236 2.40 90 Penumaka 91 Penumaka 92 Penumaka 93 Penumaka 94 Penumaka 95 Penumaka 239 2.22 96 Penumaka 97 Penumaka 98 Penumaka 240 0.38 99 Penumaka 0.2 100 Penumaka 1.05 101 Penumaka 0.82 102 Penumaka 0.22 103 Penumaka 2.34 104 Penumaka 1.9 105 Penumaka 242 0.185 106 Penumaka 245 0.1075 107 Penumaka 247 0.094 108 Penumaka 249 0.93 109 Penumaka 0.74 110 Penumaka 0.65 108 ASCCDP: Resettlement Action Plan for Flood Mitigation Works List of village-wise Encumbrances under Negotiated Settlement Policy Project affected S. No Village Sy. No. extent 1 MANDADAM-1 0.11 106 MANDADAM-1 0.56 MANDADAM-1 0.14 2 107 MANDADAM-1 0.40 3 MANDADAM-1 107 0.20 4 MANDADAM-1 107 0.20 MANDADAM-1 0.20 5 MANDADAM-1 107 0.92 MANDADAM-1 0.54 6 MANDADAM-1 107 0.17 MANDADAM-1 0.80 7 MANDADAM-1 110 0.33 8 MANDADAM-1 110 0.33 9 MANDADAM-1 110 0.10 10 MANDADAM-1 111 0.07 11 MANDADAM-1 0.10 12 MANDADAM-1 0.10 13 MANDADAM-1 0.10 MANDADAM-1 107 0.80 14 MANDADAM-1 0.06 15 MANDADAM-1 0.05 16 MANDADAM-1 0.10 17 MANDADAM-1 0.10 18 MANDADAM-1 117 0.59 19 MANDADAM-1 117 0.67 20 MANDADAM-1 117 0.54 21 MANDADAM-1 284 1.52 22 MANDADAM-1 284 0.10 23 MANDADAM-1 284 0.10 24 MANDADAM-1 284 0.21 25 Velagapudi 41 0.15 26 Rayapudi-1 152 0.01 27 Rayapudi-1 155 0.01 109 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Annexure - 10 Assistance to Landless Families 1. Landless laborers working in the Capital City area lost their primary source of income as land was assembled by APCRDA for the development of Amaravati. Irrespective of the land assembly instrument used, i.e. LPS or Land Acquisition, the majority of agricultural day-laborer jobs no longer exists, except from those working for landowners who have not joined the LPS and/or whose land still not has been acquired under the LARR Act. Landless laborers may still continue to farm on this land. As such, the majority of landless agricultural laborers have been directly impacted by the capital city development project. A key consideration concerning landless laborers is therefore the extent to which alternative sources of income are available locally to replace the loss of income from agricultural jobs. 2. Although OP 4.12 applies only to the footprint of the World Bank financed project, it is challenging to differentiate between landless laborers affected by land assembly mechanisms within and outside the World Bank project boundaries. Therefore, APCRDA has agreed that for purposes of this RPF, all landless families registered with APCRDA for pension by July 15, 2018 will be considered project affected people, for the purposes of provision of livelihood restoration measures. This goes beyond the APCRDA requirements related to landless families under the World Bank policies, and it illustrates the commitment of the agency to ensure that all those impacted by the Capital City development are provided opportunities to restore their livelihoods in a reasonable amount of time. The payment of pension and other livelihood related benefits will be monitored for the list of registered landless families as per this RPF and subsequent RAPs. As of July 15, 2018, the total of number of landless agricultural laborers is 21,374. 3. Landless laborers are not tied to any particular land parcel, and they work depending on availability of opportunities as and when they arise. Livelihood restoration packages have been uniformly extended to all the identified and registered landless laborers within Amaravati City since May 2015. As of May 2015, approximately 15,000 landless families were registered with APCRDA as residents of the Capital City area (families who resided in the area by December 2014). Subsequently, the number of landless families registered has increased, as APCRDA has allowed registration of additional laborers including, for example, cases of family members of original residents getting married and establishing a separate family. Unregistered landless families who wish to enroll in livelihood restoration programs need to demonstrate that they lived in the Capital City before December 2014. Proof of residence for registration includes Ration Cards, Aadhar Cards, and Voter Id Cards. 4. Landless laborers working in the Capital City area are eligible to receive a combination of livelihood restoration benefits that includes: (i) payment of pensions @ INR 2,500 per month per family for a period of 10 years, with annual adjustment linked to inflation index. The period of 10 years was estimated as the time needed for the Capital City to fully develop, transitioning to an urban area with predominantly non-agricultural income generating activities; (ii) employment under Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA) for up to 365 days per year; (iii) facilitate access to interest-free loans for setting up enterprises; (iv) access to skill upgrading and training opportunities; (v) provision of subsidized food; and (vi) free access to medical and educational benefits in designated facilities. 5. Measures are in place to ensure consistency with the World Bank policy on involuntary 110 ASCCDP: Resettlement Action Plan for Flood Mitigation Works resettlement, in order to assist landless agricultural laborers to improve or at least restore their living standards and livelihoods to levels prior to their displacement. There is substantial variability26 in records of income levels of landless agricultural laborers pre- and post- the announcement of the capital city, hence an accurate estimate of the average income of landless laborers is challenging to obtain. A review of all available data suggests that the average income level of landless households pre-capital city announcement was roughly INR 5,000 per household per month (actual - INR 4,694). In 2017, average incomes for landless laborers ranged from INR 8,500 to INR 13,500 per household per month, with data from the most recent survey (2018) suggesting an average income level of approximately INR 10,000 per household per month (actual - INR 9,636)16,27. 6. Data show that if accessed as designed, the livelihood restoration package designed by APCRDA, would result in an estimated household monthly income of INR12,350 (assuming full access to all benefits and assuming two family members working). This level of earnings is substantially higher than average pre-Capital City announcement levels. This is, however, a high bound estimate. Some landless laborers may have challenges accessing, or taking advantage of all the benefits in the livelihood restoration package, which may leave them in a situation that is inferior to their pre-Capital City status. Estimates suggest, for instance, that women constitute more than 70% of agricultural worker population. Women typically make half of the income of men laborers, suggesting that the income level in some households (headed by women, for instance) may be significantly lower than the estimated maximum. This problem could be particularly acute for large or extended families where more than one family member may have lost their income28. 7. Figure A11.1 compares income levels of households from the various data sources available, including: (i) full access to livelihood restoration package, including MGNREGA benefit and the APCRDA pension (INR 12,350); (ii) average household income in 2015 (INR 8,476); (iii) average household income in 2017 (INR 9,636). This indicates that if access to the benefit package as designed by APCRDA is effective, and if MGNREGA benefits are available, landless laborers would have access to earning levels that are comparable or even higher than those that existed prior to the initiation of the LPS. 26 Baseline data on income of landless laborers (pre- and post-announcement of capital city project) collected by several sources were analyzed. Data differ substantially across sources. This variability is not surprising given the different dates for data collection, as well as the different methodologies, including sample as well as sample sizes, geographical coverage, etc. 27 Vasavya Mahila Mandali (2018) ‗Assessment on Agricultural Laboure rs and Implementation of Benefits in Amaravati Capital City Villages‘ 28 Payne, G. (2018), Assessment of Land Assembly Instruments and their Implementation 111 ASCCDP: Resettlement Action Plan for Flood Mitigation Works Yerrabalem Venkatapalem Velagapudi Undavalli Uddandarayunipalem Thullur Sekhamuru Rayapudi Penumaka Nowlur Nidamarru Nelapadu Nekkallu Neerukonda Mandadam Malkapuram Lingayapalem Kuragallu Krishnayapalem Inavolu Dondapadu Borupalem Bethapudi Ananthavaram Abbarajupalem 0 2000 4000 6000 8000 10000 12000 14000 Figure A.11.1 – Monthly earning of agricultural laborers (in INR) in Capital City villages. Data include monthly household pension of INR2500. Yellow line indicates average household income from 2015 (INR8,476). Red line indicates average household income from 2018 (INR 9,636). Green line indicates monthly income of a household receiving benefit package including full MGNREGA benefits and APCRDA pension43. 8. Data from consultations and field surveys also showed that a share of the landless laborers may be in a situation of high vulnerability. Therefore, measures in addition to those already in place by APCRDA and covering all landless laborers are included in this RPF, to identify and to address, specifically, the needs of the most vulnerable subset of landless laborers, who need extra support to return to their levels prior to the announcement of the capital city. The following typologies of landless households are recognized as those at the highest risk: (i) families with woman as head of household including inter alia single women, widows; (ii) households where family members have physical disabilities; (iii) families with chronic diseases; (iv) households with aging family member who can no longer work (over 60 years old); (v) families with no alternative sources of income other than APCRDA pension; and (vi) families of Scheduled Castes/Scheduled Tribes whose sole source of income is APCRDA pensions. 9. APCRDA has established a methodology to identify the most vulnerable of the landless, i.e. households for whom the package of livelihood restoration benefits – either by design or by nature of benefits – are not sufficient to help them restore their livelihoods to pre-Capital City standards, and who may need additional assistance. The methodology for identification of vulnerable families, within a total universe of 21,374 landless households, includes the following steps: i. Identification of subset of landless laborers in 25 villages, consistent with the six typologies of highest risk/vulnerability; 112 ASCCDP: Resettlement Action Plan for Flood Mitigation Works ii. Deployment of network of 1,920 Self Help Groups29 (SHG) that exist in the Capital City area, which include 19,200 women members, actively engaged and well connected in their communities. SHG, in collaboration with NGO/consultants, reach out to families pre-identified according to typology (e.g. single women/head of household, with physical disabilities and chronic diseases, elderly, with no source of income other than pension, ST/SC). Common Interest Groups consisting of 10 members from SHGs are formed in each village and assigned to contact landless laborer households and to identify vulnerable landless families iii. One Village Facilitator from APCRDA‘s Competent Authority Office acts as nodal person to oversee outcomes of identification exercise. iv. Orientation sessions are held with Common Interest Groups to explain the purpose and approach to be followed for Final identifying the vulnerable families. Common Interest Group Leaders contact landless families to understand their needs and requirements for employment and livelihood, and single out most vulnerable families, in need of additional support. v. APCRDA organizes focus groups with identified vulnerable landless households and develops specific livelihood measures aimed at improving the living conditions of most vulnerable group. vi. Specific Action Plans will be prepared for different typologies of households30, where targeted measures will be identified and expected results will be outlined vii. Monitoring mechanisms for implementation of measures targeted to vulnerable landless families, including methodology and frequency of monitoring are established 10. Using this methodology for identification of vulnerable landless families, an assessment was carried out by APCRDA in June - July 2018. A total of 857 vulnerable landless families were identified, living in the 25 villages of the Capital City area. APCRDA has a complete listing of families and their contact information. The economic and employment profile in the communities, and that of the landless families, varies from village to village, confirming the need for more targeted measures to resolve the needs of the most vulnerable families. The list of vulnerable landless families will likely change with time, and the number of families may increase or decrease reflecting the economic conditions of very poor households at the bottom of the income ladder. Monitoring the impact of the proposed measures on these target households, as well as the overall trend of living and economic conditions in the Capital City area will be critical, to ensure that opportunities are provided to all vulnerable landless households to restore their livelihood, and in the longer term, that the economic transformation of the area from rural to urban is lifting living standards of the poorest. The methodology to identify vulnerable landless families will be repeated within six (6) months, in order to assess impacts and new potential needs. Vulnerable landless families that may have not been identified in the June-July 2018 survey will have recourses to reach out to APCRDA and request 29 Self Help Groups support members in finding solutions to common problems. SHGs in AP serve as a vital agent of social change and catalyst for the empowerment and development process in a community, through providing a cost-effective credit delivery system, enabling participation in identifying, planning, budgeting, and implementing village development programs, generating a forum for collective learning, promoting democratic culture, fostering entrepreneurial culture, providing a firm base for dialogue and cooperation in programs with other institutions. 30 Households of similar characteristics will be grouped together and, when possible, measures will be targeted to multiple households 113 ASCCDP: Resettlement Action Plan for Flood Mitigation Works to be included in the program of additional assistance (e.g. through GRM, by contacting project NGOs). 11. The information obtained from these 857 families includes: (i) characteristics of household; (ii) amount and source of current household income; (iii) skill set and interests; and (iv) challenges in accessing and/or benefitting from livelihood support packages already being offered by APCRDA. Focus group discussions were held with the families to discuss the rationale for the additional lively restoration measures and the importance of their participation in the identification measures to address their specific circumstances. Next steps include: first, by August 31, 2018, preparation of Action Plans for individual households or for typology of households, which present the set of measures to: (i) provide new opportunities for target vulnerable landless families to improve their livelihood; and (ii) address some of the bottlenecks in accessing existing programs. Second, activate monitoring mechanisms to verify and calibrate the success of proposed measures, aiming at reducing the number of vulnerable families with time. These involve the engagement of SHGs and NGO/consultants (both APCRDA and World Bank‘s) in reaching out to the households and following up periodically on the progress. And third, engage with communities and identify new potential families that may need additional assistance. It is expected that the original number of vulnerable landless families will reduce gradually, as target support measures bridge existing gaps and allow families to access opportunities to improve their livelihoods. At the same time and as the transformation of the Capital City area advances, it is likely that additional landless households become vulnerable and need to be the focus of additional livelihood support measures. The monitoring mechanism in place, building on the present and the penetration of SHGs and of NGO/consultants, will provide a channel to identify on a continuous basis, families that may fall into a vulnerable state. 12. An initial set of measures have been identified in focus groups discussions with members of vulnerable landless families. Participants suggested measures that would be suitable and applicable to their situation. The active participation of households in the identification and implementation of these additional measures is essential. This was strongly emphasized during the focus groups. The roles and expected engagement of the families in these new activities will continue to be stressed as implementation of the measures is rolled out, and as additional initiatives are identified. A list of new targeted measures that is being rolled out as of end of July 2018 is presented below. While they are similar in nature to some of the general initiatives that APCRDA is implementing across the Capital City for all landless laborers, these additional measures are specifically tailored and targeted to the needs of the identified 857 families. Specifically: i. Expanding safety nets for targeted beneficiaries – roughly 4 percent of the households include a family member with a disability, or elderly, who may not be getting all the government assistance that is available and they are entitled to receive. APCRDA will ensure the family receives all the available support to which they are entitled; ii. Skill training for those eligible – roughly 65 percent of the households are either surviving on the APCRDA pension alone, or they are only engaging in very low paying jobs. There are untapped employment opportunities around the Capital City area (e.g. construction, masonry, government and university complexes), which these households are not benefitting from, as was determined during the focus group discussions, primarily because of lack of skills. A program will focus on providing tailored skill trainings and matching employment opportunities in the Capital City area, and focusing on those family members who are able to work. The current skill 114 ASCCDP: Resettlement Action Plan for Flood Mitigation Works training offered by APCRDA targets individuals in the age range of 18-35 years old. This targeted training program will be made available for reskilling landless laborers of up to 50 years of age; iii. Provision of (i) information on employment opportunities in villages across the Capital City- i.e. jobs dashboard for people to be aware of available opportunities outside of their village; of (ii) safe, public transportation options for women to travel for work to other locations/villages; and (iii) general training to households on transformation to urban livelihoods and how to live in urban settings. iv. Creation of more employment opportunities under MGNREGA – a number of possible expansion to the menu of employment opportunities under MGNREGA may be feasible for APCRDA and would be appealing to some of the households within and in adjoining area of capital city. 13. SHGs, under coordination from APCRDA, will continue to be engaged in reaching out to the targeted households and supporting them as these proposed measures are rolled out. NGOs engaged by APCRDA and by the World Bank will closely assist in the implementation of measures targeted to the vulnerable landless families. 115