Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan: Updated Procurement Plan, M 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Agricultural Growth Project PLAN General Information Country: Ethiopia Banks Approval Date of the Original Procurement Plan: 2017-03-27 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-11-08 Project ID: P148591 GPN Date: Project Name: Second Agricultural Growth Project Loan / Credit No: IDA / 56050 Executing Agency(ies): Ministry of Agriculutre and Natural Resources Development, Amhara Agricultural Growth Program - Regional Program Coordination Unit, Ethiopian Agricultural Research Institute, OAGP RPCU, Tigray AGP Regional Coordination Office WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAGP RPCU-23864-CW- RFB / Construction of fence for Agriculture Marketing and Value Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 65,219.00 0.00 2017-08-15 2017-08-20 2017-10-01 2017-10-31 2017-12-05 2018-06-03 semen collection center at Bahir Chains Envelope Implementation Dar Animal Health Clinic ET-AAGP RPCU-23866-CW- Agriculture Marketing and Value Single Stage - One Pending RFB / Construction of Nitrogen IDA / 56050 Post Request for Bids Open - National 86,956.00 0.00 2017-08-15 2017-08-20 2017-10-01 2017-10-31 2017-12-05 2018-06-03 Chains Envelope Implementation Plant Center at Bahir Dar ET-AAGP RPCU-26109-CW- RFB / Construction of Small Scale Irrigation at (Elen Burie Worda and Leza Jabitehena Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,481,454.00 0.00 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-06-13 Worda) and Debilitation of two Envelope Implementation Existing Small Scale Irrigation at (Enfiranze Bahirdar Zuria and Karmuki South Achefer Worda). ET-AAGP RPCU-26207-CW- RFB / Construction of three Small Scale Irrigation at Est Gojam Zone Muga-3 Revere Single Stage - One Pending Debaytelatgen worda and IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,287,109.00 0.00 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Implementation Minasie Revere Enmay worda and West Gojame Zone Gunagune-2 Revere Jabitehena worda. ET-AAGP RPCU-26214-CW- RFB / Construction of three new Small scale Irrigation ( Sebatwodel ReverE at South Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,304,347.00 0.00 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Gonder Zone Fata worda, Envelope Implementation Terngomeder Revere and Yogofolfoy Revere at North Shoa Zone Moretna Jeru WORDA. ET-AAGP RPCU-26215-CW- RFB / Construction of three New Irrigation Awi Zone Guagusa shekudad worda Sebatayna Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 2,347,826.00 0.00 2017-08-30 2017-09-04 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Revere,Geray-3 Revere and Envelope Implementation Laheshembekuma Revere at West Gojam Zone Jabitehena Worda. ET-AAGP RPCU-26217-CW- RFB / Construction two new Irrigation at Gumara rever Awi Zone Ankesha worda and Lomitule Rever at Weast Gojam Single Stage - One Pending Zone Yelmana Worda and IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,782,607.00 0.00 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Envelope Implementation Rehabilitation of three Existing Small scale Irrigation at Dim Revere Awi Zone Zigem woreda, Adagihoye Revere North Shoa Zone ET-AAGP RPCU-26218-CW- RFB / Construction of Two Small Scale Irrigation- at Zembele River Denbacha woreda and Tentiba Rivere at Denbia worda And Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,826,128.00 0.00 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Rihabilitation Of Four Existing Envelope Implementation Small Scale Irrigation at Fetam/densra Rever Burie, Sure Revere Ankesha and Robit Revere Tarmaber . ET-AAGP RPCU-26224-CW- RFB / Construction of warehouse for 8 Primary Cooperative at Awi Zone Workmeda, North Soa Agriculture Marketing and Value Single Stage - One Pending Siaseber, and Moret, West IDA / 56050 Post Request for Bids Open - National 536,303.00 0.00 2017-10-23 2017-10-28 2017-12-09 2018-01-08 2018-02-12 2018-08-11 Chains Envelope Implementation Gojam Dembecha, South Gonder Dera, Eest Gojam Basolibe and Deber Alias and North Gonder Alefa worda. ET-AAGP RPCU-26089-CW- CDD / Construction of Agriculture Marketing and Value Community Driven Under Suspended Bridge (Gula Revere IDA / 56050 Prior Direct 84,284.00 84,284.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation Bridge) at West Gojam Zone Denbecha Worda. ET-AAGP RPCU-26091-CW- CDD / Construction of suspended Agriculture Marketing and Value Community Driven Under bridge (Abaye rever Afaye IDA / 56050 Prior Direct 48,707.00 48,707.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation Kebele) at South Gonder Zone Dera Worda. ET-AAGP RPCU-26086-CW- CDD / Construction of Agriculture Marketing and Value Community Driven Under Suspended Bridge (Gizane IDA / 56050 Prior Direct 110,153.00 110,153.00 2017-09-05 2017-08-30 2017-09-10 2017-10-31 2017-10-15 2018-02-12 Chains Development Implementation Revere Bridge) at Awi Zone Dangela Worda. Page 1 ET-AAGP RPCU-26055-CW-DIR / Construction of Suspended Agriculture Marketing and Value Community Driven Under Bridge (Rebe Revere Bridge IDA / 56050 Prior Direct 72,602.00 72,602.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation Limado Kebele) at North Gonder Zone Farta Wrda ET-AAGP RPCU-26092-CW- CDD / Construction of Agriculture Marketing and Value Community Driven Under Suspended Bridge ( Mugara IDA / 56050 Prior Direct 47,622.00 47,622.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation Revere Bridge) at East Gojam Zone Dejen Worda. ET-AAGP RPCU-26050-CW-DIR / Construction of Suspended Agriculture Marketing and Value Community Driven Under Bridge (Gelgel cheye River bridge IDA / 56050 Prior Direct 55,810.00 55,810.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation Yesarbate kebele) at East Gojam Zone Enarje Enawga Woreda ET-AAGP RPCU-26043-CW-DIR / Construction of suspended Agriculture Marketing and Value Community Driven Under Bridge (Abay River Volva Kebele) IDA / 56050 Prior Direct 98,092.00 98,092.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Chains Development Implementation at w/Gojame zone of North Achefer Woreda. ET-AAGP RPCU-26222-CW- RFB / Construction of Three Warehouse for three Agriculture Marketing and Value Single Stage - One Pending Cooperatives at Dejen Worda IDA / 56050 Post Request for Bids Open - National 971,064.00 0.00 2017-10-23 2017-10-28 2017-12-09 2018-01-08 2018-02-12 2018-08-11 Chains Envelope Implementation Gion Union, Tsehay Union North Gonder and Kesem Union North shoa Zone. ET-AAGP RPCU-26038-CW-DIR / Construction of Suspended Agriculture Marketing and Value Community Driven Under IDA / 56050 Prior Direct 73,310.00 0.00 2017-09-05 2017-08-30 2017-09-10 2017-10-15 2018-02-12 Bridge(Dankom River Bridge) at Chains Development Implementation Awi Zone Zigem Woreda. ET-AAGP RPCU-26106-CW- Agriculture Marketing and Value Single Stage - One RFB / Construction of three ware IDA / 56050 Post Request for Bids Open - National 84,284.00 0.00 Canceled 2017-10-25 2017-10-30 2017-12-11 2018-01-10 2018-02-14 2018-08-13 Chains Envelope house for Cooperative Unions OIDA-IWS/AGP-II/NCB/01-2017 Single Stage - One Pending / Constructuon of 12 New Small IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 3,035,187.00 0.00 2017-06-08 2017-06-13 2017-07-26 2017-08-25 2017-09-29 2018-03-28 Envelope Implementation Scale Irrigation Schems OIDA-IWS/AGP-II/NCB/02-2017 Single Stage - One Pending / Construction of 13 New Small IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,914,319.00 0.00 2017-06-08 2017-06-13 2017-07-27 2017-08-26 2017-09-30 2018-03-29 Envelope Implementation Scale Irrigation Sc hems OTMB/AGP-II/NCB/01-2017 / Agriculture Marketing and Value Single Stage - One Pending Constructuon of 3 Primary IDA / 56050 Post Request for Bids Open - National 307,136.00 0.00 2017-02-12 2017-02-17 2017-03-31 2017-04-30 2017-06-21 2017-12-18 Chains Envelope Implementation Market for Livestock TG/AGP/NCB/WORKS-01 / Agriculture Marketing and Value Single Stage - One Pending Primary market center for crops IDA / 56050 Post Request for Bids Open - National 240,000.00 0.00 2017-10-20 2017-10-25 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Chains Envelope Implementation and vegetables(Mekelle) ET-TAGP RPCU-30175-CW- Agriculture Marketing and Value Single Stage - One Pending RFB / Honey collection and IDA / 56050 Post Request for Bids Open - National 43,500.00 0.00 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Chains Envelope Implementation processing center (Shire) ET-TAGP RPCU-30677-CW- Agriculture Marketing and Value Single Stage - One Pending RFB / Milk collection and IDA / 56050 Post Request for Bids Open - National 87,000.00 0.00 2017-10-25 2017-10-30 2017-12-11 2018-01-10 2018-02-14 2018-08-13 Chains Envelope Implementation processing center(shire) ET-TAGP RPCU-30680-CW- Agricultural Public Support Single Stage - One Pending RFB / Lime production IDA / 56050 Post Request for Bids Open - National 34,800.00 0.00 2017-10-18 2017-10-23 2017-12-04 2018-01-03 2018-02-07 2018-08-06 Services Envelope Implementation house(ADUA) ET-TAGP RPCU-30683-CW- RFB / Construction of Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 1,521,800.00 0.00 2017-11-14 2017-11-19 2017-12-31 2018-01-30 2018-03-06 2018-09-02 shekadaero diversion (Laelay Envelope Implementation Adyabo woreda) ET-AAGP RPCU-31636-CW- RFB / Construction of 6 Primary Market Center (4 Milke processing Market at Wogera, Agriculture Marketing and Value Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 832,304.00 0.00 2017-10-30 2017-11-04 2017-12-04 2018-01-03 2018-01-28 2018-05-28 S/Achefer, Dejen, & Chains Envelope Implementation Basoliben worda & two Honey Processing market at Gualgua and D/Telategen worda. ET-AAGP RPCU-31641-CW- RFB / Construction of 6 Road side market center( 4 fruit & vegetates market at Dera, Agriculture Marketing and Value Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 521,340.00 0.00 2017-11-20 2017-11-25 2018-01-09 2018-02-08 2018-03-09 2018-08-06 Basoliben, Burie and Guagusa Chains Envelope Implementation shekudad worda and one banana market at Gonder and one for hony at Dangla worda. ET-AAGP RPCU-31652-CW- RFB / Construction of Fish Agricultural Public Support Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 397,638.00 0.00 2017-11-30 2017-12-05 2018-01-04 2018-02-03 2018-02-28 2018-07-28 Hatchery at Regional live stock Services Envelope Implementation Agency. TARI/AGPII/SH-07/17 / Maintenance service for Request for Single Stage - One Pending IDA / 56050 Agricultural Research Post Limited 199,875.00 0.00 2017-12-12 2018-02-23 2018-08-22 greenhouse, lathouse & tissue Quotations Envelope Implementation culture GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Project Management, Capacity DC/UNOPS / 102 Vechicles and IDA / 56050 Building and Monitoring and Prior UN Agencies (Direct) Direct 3,000,000.00 4,759,844.78 Signed 2016-07-14 2017-02-22 2017-04-10 2017-04-12 2017-07-13 688 Motor Cycles Evaluation Agricultural Public Support Single Stage - One Under ICB/FAGP/CU-003 / Row planter IDA / 56050 Post Request for Bids Open - International 500,000.00 0.00 2017-03-31 2017-04-06 2017-04-05 2017-04-24 2017-05-17 2017-07-17 2017-06-09 2017-07-14 2018-01-10 Services Envelope Implementation Project Management, Capacity NCB/FAGP/CU-007 / Equiping Single Stage - One Under IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 535,600.00 0.00 2017-04-05 2017-04-03 2017-04-10 2017-05-10 2017-05-01 2017-06-09 2017-05-05 2017-07-14 2018-01-10 Data Center for MoANR Envelope Implementation Evaluation Project Management, Capacity NCB/FAGP/CU-002 / Standby Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 450,000.00 0.00 2017-04-05 2017-04-07 2017-05-06 2017-06-04 2017-07-03 2017-12-30 Diesel Generator Envelope Implementation Evaluation Project Management, Capacity NCB/FAGP/CU-008 / Computer Single Stage - One Under IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 360,000.00 0.00 2017-04-05 2017-04-10 2017-04-06 2017-04-12 2017-05-15 2017-05-15 2017-06-01 2017-07-06 2018-01-02 and IT equipments Envelope Implementation Evaluation Project Management, Capacity NCB/FAGP/CU-009 / Office Single Stage - One Under IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 765,000.00 0.00 2017-04-05 2017-04-07 2017-04-06 2017-04-12 2017-05-05 2017-05-09 2017-05-22 2017-06-26 2017-12-23 equipment Envelope Implementation Evaluation ICB/AGP/CU-005 / Provision of Agriculture Marketing and Value Single Stage - One Under new parent stock for poultry IDA / 56050 Post Request for Bids Open - International 200,000.00 0.00 2017-04-17 2017-04-22 2017-05-19 2017-06-06 2017-07-06 2017-08-10 2018-02-06 Chains Envelope Implementation multiplication centers ICB/FAGP/CU-004 / Nitrogen Agriculture Marketing and Value Single Stage - One Under IDA / 56050 Post Request for Bids Open - International 1,100,000.00 0.00 2017-04-24 2017-05-09 2017-05-09 2017-06-23 2017-07-23 2017-08-27 2018-02-23 plant and spare parts Chains Envelope Implementation ICB/AGP/CU-002 / Seed quality Agricultural Public Support Single Stage - One Pending IDA / 56050 Prior Request for Bids Open - International 1,600,000.00 0.00 2017-06-01 2017-06-06 2017-07-21 2017-08-17 2017-09-21 2018-03-20 control Laboratory equipments Services Envelope Implementation NCB/AGP/CU-07/09 / Ear Tag Agriculture Marketing and Value Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 100,000.00 0.00 2017-05-26 2017-05-31 2017-07-12 2017-08-11 2017-09-15 2018-03-14 (printed and black) for cows Chains Envelope Implementation Project Management, Capacity SH/FAGP/CU-001/17 / Request for Single Stage - One Under IDA / 56050 Building and Monitoring and Post Limited 30,000.00 0.00 2017-05-20 2017-06-11 2017-07-26 Stationery items Quotations Envelope Implementation Evaluation Project Management, Capacity MOANR/AGPII/UNOPS1 / 620 IDA / 56050 Building and Monitoring and Prior UN Agencies (Direct) Direct 2,155,000.00 2,085,429.87 Signed 2016-07-14 2017-02-22 2017-05-16 2017-05-16 2017-08-16 motor cycles Evaluation EIAR/AGPII/NCB-01 / Single Stage - One Under Procurement of farm machinery IDA / 56050 Agricultural Research Post Request for Bids Open - National 200,000.00 0.00 2017-09-01 2017-10-02 2017-09-06 2017-10-09 2017-10-23 2017-11-16 2018-06-14 Envelope Implementation and equipment EIAR/AGPII/SH-01 / Request for Single Stage - One IDA / 56050 Agricultural Research Post Limited 6,700.00 6,351.29 Completed 2017-08-11 2017-07-24 2017-08-25 2017-07-27 2017-08-30 2017-08-01 Procurement of laptop computer Quotations Envelope EIAR/AGPII/DR-01 / Under Procurement of biotechnology IDA / 56050 Agricultural Research Prior Direct Selection Direct 170,000.00 0.00 2017-08-16 2017-08-21 2017-09-04 2017-12-04 Implementation laboratory reagent ET-AAGP RPCU-26058-GO- Project Management, Capacity RFQ / Procurement of stationary Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Limited 4,608.00 0.00 2017-10-07 2017-11-04 2017-11-18 and office supplies for Regional Quotations Envelope Implementation Evaluation Project Coordination Unit ET-AAGP RPCU-26231-GO- Project Management, Capacity RFB / Procurement of two field Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 260,870.00 0.00 2017-08-31 2017-09-05 2017-10-17 2017-11-16 2017-12-21 2018-06-19 Vehicle for Regional Water Envelope Implementation Evaluation Irrigation and Mining Bureou. ET-AAGP RPCU-26232-GO- RFB / Procurement of of 20 Computers. 4 Medium printers,2 Project Management, Capacity Heavy printers, 3 LCD Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 40,873.00 0.00 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-06-05 Projectors.2 LCD Printer, 168 Envelope Implementation Evaluation pico projector, 4 External Hard Disk, 1 photo copier and 4 hand camera ET-AAGP RPCU-26235-GO- Project Management, Capacity RFB / Procurement of Network Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 101,086.00 0.00 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-02-05 2018-08-04 Installation Equipment for New Envelope Implementation Evaluation Program Supported Wordas. DC/EIAR-AGP2/LAB-02/17 / Pending Procurement of laboratory IDA / 56050 Agricultural Research Prior UN Agencies (Direct) Direct 7,404,232.00 0.00 2017-10-17 2017-10-23 2017-12-12 2018-05-08 Implementation equipment and supply Project Management, Capacity SH/FAGP/CU/001 / four station Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Limited 17,500.00 0.00 2017-09-24 2017-11-12 2018-05-11 furniture Quotations Envelope Implementation Evaluation NCB/AGP/CU-10/2010 / Project Management, Capacity Single Stage - One Pending Antivirus soft ware including IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 110,000.00 0.00 2017-09-15 2017-09-18 2017-10-18 2017-11-17 2017-12-22 2018-06-20 Envelope Implementation instalation Evaluation Project Management, Capacity OBANR/AGP-II/SH/01-2017 / Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Open - National 7,708.00 0.00 2017-11-20 2018-01-15 2018-07-14 Procurement of Office Furniture Quotations Envelope Implementation Evaluation OBANR/AGP-II/NCB/02-2017 / Agricultural Public Support Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 796,800.00 0.00 2017-01-26 2017-02-28 2017-04-11 2017-05-11 2017-06-15 2017-12-12 Non-Motorized Cycles Services Envelope Implementation OBANR/AGP-II/SH/02-2017 / Request for Single Stage - One Pending IDA / 56050 Small Scale Irrigation Post Open - National 250,696.00 0.00 2017-05-02 2017-07-26 2018-01-22 Motor Vehicles Quotations Envelope Implementation ICB/FAGP/CU/G-001/10 / Plant Agricultural Public Support Single Stage - One Under protection laboratory equipment IDA / 56050 Prior Request for Bids Open - International 1,700,000.00 0.00 2017-10-09 2017-10-14 2017-11-25 2017-12-25 2018-01-29 2018-07-28 Services Envelope Implementation for regions Page 3 SH/FAGP/CU-001/10 / Project Management, Capacity Audiovisual equipment s for Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Limited 160,000.00 0.00 2017-10-11 2017-12-06 2018-06-04 public relation/communication of Quotations Envelope Implementation Evaluation project ET-TAGP RPCU-30673-GO-RFQ Agriculture Marketing and Value Request for Single Stage - One Pending / Improved Horticultural seeds IDA / 56050 Post Open - National 73,000.00 0.00 2017-10-15 2017-12-10 2018-06-08 Chains Quotations Envelope Implementation (potato,onion & paper) Project Management, Capacity ET-TAGP RPCU-30169-GO-RFB Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Open - National 3,000.00 0.00 2017-10-30 2017-12-25 2018-06-23 / Office Furniture Quotations Envelope Implementation Evaluation Project Management, Capacity ET-TAGP RPCU-30178-GO-RFB Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Open - National 3,500.00 0.00 2017-10-30 2017-12-25 2018-06-23 / Stationary matterials Quotations Envelope Implementation Evaluation Agriculture Marketing and Value Pending MOF-REF-9 / Modern Fertilizer IDA / 56050 Post Direct Selection Direct 29,000.00 0.00 2017-10-12 2017-10-17 2017-10-30 2017-11-14 Chains Implementation Project Management, Capacity TG/AGP/SHOP-02 / IT Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Open - National 5,000.00 0.00 2017-10-30 2017-12-25 2018-06-23 Equipment Quotations Envelope Implementation Evaluation TARI/AGP2/SH/2-2017 / Request for Single Stage - One Pending IDA / 56050 Agricultural Research Post Limited 35,745.00 0.00 2017-11-01 2017-12-27 2018-02-21 procurement of furniture Quotations Envelope Implementation TARI/AGPII/SH-1/17 / Procurement of feed mill and Request for Single Stage - One Pending IDA / 56050 Agricultural Research Post Limited 36,809.00 0.00 2017-11-13 2018-01-01 2018-03-30 laboratory equipment for poultry Quotations Envelope Implementation multiplication TARI/AGP2/SH-04/17 / Request for Single Stage - One Pending Procurement of Carpet and IDA / 56050 Agricultural Research Post Limited 20,397.00 0.00 2017-12-04 2018-01-22 2018-02-21 Quotations Envelope Implementation window shatters for meeting hall TARI/AGP2/SH-5/17 / Procurement of electrical and Request for Single Stage - One Pending IDA / 56050 Agricultural Research Post Limited 15,558.00 0.00 2017-12-04 2018-01-16 2018-03-05 audiovisual equipment for Quotations Envelope Implementation meeting halls ET-AAGP RPCU-31499-GO- Project Management, Capacity RFB / Procurement of Total Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Limited 17,391.00 0.00 2017-10-30 2017-11-30 2018-02-28 Station for Bureau of Land Use Quotations Envelope Implementation Evaluation and Administration ET-AAGP RPCU-31501-GO- RFB / Equipping Regional Seed Agricultural Public Support Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 285,714.00 0.00 2017-11-27 2017-12-02 2018-01-01 2018-01-31 2018-02-28 2018-05-29 Quality Analysis Laboratory Services Envelope Implementation Center ET-AAGP RPCU-31511-GO- RFB / Equipping Fish Hatchery Agricultural Public Support Single Stage - One Pending IDA / 56050 Post Request for Bids Open - National 95,652.00 0.00 2017-12-04 2017-12-09 2018-01-08 2018-02-07 2018-03-04 2018-06-02 Center with Hormone, Services Envelope Implementation glove,sheath... ET-AAGP RPCU-31513-GO- Single Stage - One Pending RFB / Procurement of 43 IDA / 56050 Small Scale Irrigation Post Request for Bids Open - National 65,217.00 0.00 2017-10-16 2017-10-21 2017-12-02 2018-01-01 2018-01-30 2018-03-31 Envelope Implementation Leveling Instrument for Irrigation. ET-AAGP RPCU-31540-GO-DIR / Procurement of Cion Equipment Pending IDA / 56050 Agricultural Research Prior Direct Selection Direct 200,000.00 0.00 2017-10-31 2017-11-05 2017-12-04 2018-03-04 for Seed Implementation Germination/Reproduction. ET-AAGP RPCU-31545-GO- RFQ / Procurement of Office Project Management, Capacity Equipment and Electronics Request for Single Stage - One Pending IDA / 56050 Building and Monitoring and Post Limited 17,652.00 0.00 2017-11-04 2017-12-12 2018-02-10 (Computer, photocopier, printer, Quotations Envelope Implementation Evaluation LCD...) for Regional Water Irrigation and Energy bureau. ET-AAGP RPCU-31550-GO- RFB / Procurement of Field Project Management, Capacity Single Stage - One Pending Equipment(Woki Toki) for IDA / 56050 Building and Monitoring and Post Request for Bids Open - National 174,565.00 0.00 2017-12-31 2018-01-05 2018-02-16 2018-03-18 2018-04-11 2018-07-10 Envelope Implementation Regional Water Irrigation and Evaluation Energy bureau ET-AAGP RPCU-31556-GO-DIR Pending / Procurement of Lime for Soil IDA / 56050 Agricultural Research Prior Direct Selection Direct 37,010.00 0.00 2017-12-11 2017-12-16 2018-01-19 2018-03-20 Implementation Treatment Demonstration SH/FAGP/CU-002/10 / Self Agricultural Public Support Request for Single Stage - One Pending propelled reaper binder harvesting IDA / 56050 Post Limited 100,000.00 0.00 2017-10-23 2017-12-06 2018-06-04 Services Quotations Envelope Implementation machine EIAR/AGP2/SH-03/17 / Request for Single Stage - One Pending Procurement of green house and IDA / 56050 Agricultural Research Post Limited 48,706.00 0.00 2017-12-04 2018-01-29 2018-04-11 Quotations Envelope Implementation lathouse equipment OBANR/AGP-II/SH/05-2017 / Project Management, Capacity Request for Single Stage - One Pending Procurement office Equipment IDA / 56050 Building and Monitoring and Post Open - National 21,188.00 0.00 2017-11-27 2018-01-22 2018-07-21 Quotations Envelope Implementation and Office machine Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Page 4 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FAGP/CU/CON-003/09 / Project Management, Capacity Quality And Cost- Program Implemntation IDA / 56050 Building and Monitoring and Prior Open - National 245,000.00 246,075.00 Signed 2016-04-08 2016-04-27 2016-07-11 2016-08-12 2016-10-14 2017-03-23 2017-05-26 2017-04-18 2017-03-27 2017-09-18 Based Selection Pefrormance Review Evaluation AGP/CU/CONS-002/09 / Project Management, Capacity Quality And Cost- Pending Independent procurement Audit IDA / 56050 Building and Monitoring and Prior Open - International 150,000.00 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-20 2017-09-19 2017-10-24 2017-11-28 2018-11-28 Based Selection Implementation of AGP Evaluation FAGP/CU/CON-006/09 / Quality And Cost- Under Training on SSI Feasibility Study IDA / 56050 Small Scale Irrigation Post Open - National 250,000.00 0.00 2017-05-12 2017-05-16 2017-06-02 2017-07-16 2017-08-13 2017-09-12 2017-10-17 2017-11-21 2018-11-21 Based Selection Implementation and Design INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FAGP/CU/CON-012/09 / Project Management, Capacity Under External Financial Audit for AGP IDA / 56050 Building and Monitoring and Prior Direct Selection Direct 100,000.00 0.00 2017-04-24 2017-08-09 2017-05-04 2017-06-10 2017-07-25 Implementation 1 closing and AGp 2 2009 EFY Evaluation AGP/CU/CONS-012/09 / Direct Agriculture Marketing and Value Under contract of government owned IDA / 56050 Prior Direct Selection Direct 25,000.00 0.00 2017-05-15 2017-05-25 2017-07-29 2018-01-25 Chains Implementation Alage ATVET to provide training DC/FAGP/CU/CON-28/10 / documentary film content Agricultural Public Support Pending production and broadcasting by IDA / 56050 Prior Direct Selection Direct 15,000.00 0.00 2017-11-03 2017-11-13 2018-01-17 2018-07-16 Services Implementation Ethiopian broad casting corporation Page 5