Nigeria For Women Project PROCUREMENT PLAN (Textual Part) Project information: [Nigeria] [Nigeria For Women Project] P161364] Project Implementation agency: [Federal Ministry of Women Affairs and Social Development] Date of the Procurement Plan: [August 31, 2018] Period covered by this Procurement Plan: [August 31,2018 to December 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works).Not Applicable. Goods: is not applicable Works: is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable Other Relevant Procurement Information. The project will use the CDD procurement under this project. CDD manual will be produced by the project. PROCUREMENT Nigeria : Nigeria For Women Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-09-10 2021-08-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161364 GPN Date: Project Name: Nigeria For Women Project Loan / Credit No: IDA / V1770, IDA / 62710 Federal Ministry of Women Affairs and Social Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-MOSWAD-82940-CW- RFQ / Partitioning of FPIU Project Management, Request for Single Stage - One 2019-01- Nigeria For Women Project IDA / 62710 Monitoring and Evaluation Post Limited 26,230.00 22,614.17 Completed 2018-10-29 2018-11-19 2018-12-24 2018-12-04 Quotations Envelope 07 (NFWP) Office Accommodation and Learning Abuja. NG-MOSWAD-103885-CW- Project Management, Request for Single Stage - One 2019-10- RFQ / Minor Rehabilitation at IDA / 62710 Monitoring and Evaluation Post Limited 25,000.00 11,170.37 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-11 Quotations Envelope 29 the FPIU Office Abuja and Learning NG-MOSWAD-103895-CW- Project Management, Request for Single Stage - One 2019-10- RFQ / Car Ports for the Six (6) IDA / 62710 Monitoring and Evaluation Post Limited 60,000.00 54,964.58 Completed 2019-03-07 2019-04-03 2019-05-02 2019-06-14 Quotations Envelope 29 SPIUs and Learning NG-MOSWAD-103896-CW- Project Management, Request for Single Stage - One 2019-10- RFQ / Car Ports at the FPIU IDA / 62710 Monitoring and Evaluation Post Limited 15,000.00 87,850.95 Completed 2019-03-07 2019-08-02 2019-05-02 2019-08-26 Quotations Envelope 29 Office, Abuja and Learning NG-MOSWAD-111048-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2019-12- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 29,688.91 Completed 2019-05-04 2019-06-10 2019-06-29 2019-07-08 and Partitioning of SPIU Quotations Envelope 26 and Learning Offices in Abia State NG-MOSWAD-110078-CW- RFQ / Partitioning of six (6) SPIUs Offices in Abia, Ogun, Project Management, Request for Single Stage - One 2019-12- Edo, Taraba, Niger and Kebbi IDA / 62710 Monitoring and Evaluation Post Limited 198,000.00 0.00 Canceled 2019-04-20 2019-06-15 Quotations Envelope 12 States. The works are and Learning scattered in the states. NCB will not be a better method. NG-MOSWAD-112236-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2020-01- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 28,389.70 Signed 2019-05-14 2019-05-15 2019-07-09 2019-08-07 and Partitioning of SPIU Quotations Envelope 05 and Learning Offices in Edo State NG-MOSWAD-112237-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2019-12- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 25,851.39 Completed 2019-05-04 2019-07-04 2019-06-29 2019-08-02 and Partitioning of SPIU Quotations Envelope 26 and Learning Offices in Ogun State NG-MOSWAD-112238-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2019-12- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 31,699.19 Signed 2019-05-04 2019-07-08 2019-06-29 2019-08-20 and Partitioning of SPIU Quotations Envelope 26 and Learning Offices in Taraba State NG-MOSWAD-112239-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2019-12- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 20,393.02 Completed 2019-05-04 2019-06-11 2019-06-29 2019-09-20 and Partitioning of SPIU Quotations Envelope 26 and Learning Offices in Niger State NG-MOSWAD-112240-CW- Project Management, RFQ / Minor Rehabilitation Request for Single Stage - One 2019-12- IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 39,306.95 Completed 2019-05-04 2019-07-24 2019-06-29 2019-08-28 and Partitioning of SPIU Quotations Envelope 26 and Learning Offices in Kebbi State NG-MOSWAD-120009-CW- RFQ / Minor landscaping work Project Management, Request for Single Stage - One 2020-02- of the FPIU office premises IDA / 62710 Monitoring and Evaluation Post Limited 35,000.00 0.00 Canceled 2019-06-29 2019-08-24 Quotations Envelope 20 including the back view with and Learning 40 Ft. container Offices. NG-MOSWAD-228367-CW- Project Management, Pending RFQ / Procurement and Request for Single Stage - One 2021-12- IDA / 62710 Monitoring and Evaluation Post Limited 7,000.00 0.00 Implementat 2021-04-17 2021-06-12 installation of Biometric Quotations Envelope 09 and Learning ion Access control system GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-76402-GO- Project Management, RFQ / Procurement of Request for Single Stage - One IDA / V1770 Monitoring and Evaluation Prior Limited 245,538.00 315,098.37 Completed 2018-09-22 2018-10-30 2018-11-17 2019-01-11 2019-05-16 2019-03-13 Operational Vehicles for the Quotations Envelope and Learning Federal Coordinating Unit NG-MOSWAD-83083-GO- RFQ / Procurement of Project Management, Request for Single Stage - One Computers, Accessories and IDA / 62710 Monitoring and Evaluation Post Limited 34,279.00 82,422.60 Completed 2018-10-30 2018-11-19 2018-12-25 2018-12-19 2019-06-23 2018-12-23 Quotations Envelope related Items for the FPIU, and Learning Nigeria for Women Project. NG-MOSWAD-83354-GO- RFQ / Procurement of Fiber Project Management, Request for Single Stage - One Internet and Server Room IDA / 62710 Monitoring and Evaluation Post Limited 64,793.00 54,726.34 Completed 2018-10-28 2018-11-20 2018-12-23 2018-12-04 2019-06-21 2019-02-13 Quotations Envelope Implementation for the FPIU, and Learning Nigeria For Women Project. Page 1 NG-MOSWAD-83360-GO- Project Management, RFQ / Procurement of Video Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 50,417.00 42,748.76 Completed 2018-10-29 2018-11-20 2018-12-24 2018-12-05 2019-06-22 2018-12-31 Conferencing device for FPIU Quotations Envelope and Learning of NFWP's Office. NG-MOSWAD-83367-GO- Project Management, Request for Single Stage - One RFQ / Procurement of Inverter IDA / 62710 Monitoring and Evaluation Post Limited 9,054.00 7,676.97 Completed 2018-10-30 2018-11-20 2018-12-25 2018-12-05 2019-06-23 2018-12-31 Quotations Envelope for FPIU of NFWP's Office. and Learning NG-MOSWAD-83925-GO- Project Management, DIR / Procurement of IDA / 62710 Monitoring and Evaluation Prior Direct Selection Direct 22,951.00 18,348.00 Completed 2018-10-29 2018-12-18 2018-11-03 2019-02-15 2018-12-08 2019-03-27 2019-06-06 2019-07-08 Accounting Software (Flexible) and Learning NG-MOSWAD-98241-GO- Project Management, Request for Single Stage - One RFQ / Air Conditioners for IDA / 62710 Monitoring and Evaluation Post Limited 5,500.00 12,750.33 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-05 2019-09-30 2019-03-07 Quotations Envelope FPCU, Abuja and Learning NG-MOSWAD-98243-GO- Project Management, Request for Single Stage - One RFQ / Sound Proof Standby IDA / 62710 Monitoring and Evaluation Post Limited 20,500.00 16,897.00 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-05 2019-09-30 2019-03-07 Quotations Envelope Generator and Learning NG-MOSWAD-98249-GO- RFQ / ICT, Security Equipment Project Management, and Installation(Digital Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 14,000.00 25,720.76 Completed 2019-02-06 2019-02-18 2019-04-03 2019-03-07 2019-09-30 2019-04-18 Camera, DSTV, CCTV, Quotations Envelope and Learning INTERCOM Facility and TV sets. NG-MOSWAD-98287-GO- Project Management, RFQ / Computers, Printers, Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 35,000.00 82,762.61 Completed 2019-02-06 2018-11-26 2019-04-03 2018-12-19 2019-09-30 2018-12-23 Photocopiers etc. for FPIU Quotations Envelope and Learning additional Staff NG-MOSWAD-98238-GO- Project Management, Request for Single Stage - One RFQ / Operational Vehicles for IDA / 62710 Monitoring and Evaluation Post Limited 364,312.00 0.00 Canceled 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Quotations Envelope Six (6) SPIU States and Learning NG-MOSWAD-103888-GO- RFQ / Window Blinds and Project Management, Request for Single Stage - One Internal Decorations at SPIUs IDA / 62710 Monitoring and Evaluation Post Limited 60,000.00 40,021.80 Completed 2019-03-07 2019-04-02 2019-05-02 2019-06-28 2019-10-29 2020-01-20 Quotations Envelope Offices in Abia, Ogun, Edo, and Learning Taraba, Niger and Kebbi States NG-MOSWAD-103889-GO- Project Management, RFQ / Window Blinds and Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 15,000.00 5,219.58 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-10 2019-10-29 2019-04-30 Internal Decorations at FPIU Quotations Envelope and Learning Abuja NG-MOSWAD-103891-GO- Project Management, Request for Single Stage - One RFQ / 40 Ft. Container for use IDA / 62710 Monitoring and Evaluation Post Limited 30,000.00 20,000.00 Completed 2019-03-07 2019-03-15 2019-05-02 2019-04-09 2019-10-29 2019-06-27 Quotations Envelope at FPIU Abuja and Learning NG-MOSWAD-103897-GO- Project Management, Request for Single Stage - One RFQ / Kitchen Utensils for use IDA / 62710 Monitoring and Evaluation Post Limited 1,500.00 1,797.08 Completed 2019-03-07 2019-04-03 2019-05-02 2019-05-13 2019-10-29 2019-06-10 Quotations Envelope at FPIU Office Abuja and Learning NG-MOSWAD-103986-GO- RFQ / Furnishing of an Office Project Management, Request for Single Stage - One for the Hon. IDA / 62710 Monitoring and Evaluation Post Limited 20,000.00 15,856.38 Completed 2019-03-08 2019-04-03 2019-05-03 2019-04-22 2019-10-30 2019-05-07 Quotations Envelope Minister/Permanent Secretary and Learning at the FPIU Office Abuja NG-MOSWAD-110063-GO- RFB / Office Furniture for Project Management, States Project Implementation Single Stage - One IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 450,000.00 119,367.67 Completed 2019-04-15 2019-05-21 2019-04-20 2019-06-01 2019-06-27 2019-07-01 2019-08-19 2019-08-05 2019-10-11 2020-02-01 2020-01-08 Units (SPIUs) in Abia, Edo, Envelope and Learning Ogun, Taraba, Niger and Kebbi States under NCB2, Lot 1 NG-MOSWAD-76400-GO- Project Management, RFQ / Procurement of Request for Single Stage - One IDA / V1770 Monitoring and Evaluation Post Limited 50,000.00 41,978.38 Completed 2018-09-19 2018-11-19 2018-11-14 2018-12-05 2019-05-13 2019-01-25 Furniture and Equipment for Quotations Envelope and Learning FPMU NG-MOSWAD-110061-GO- RFB / Fed. Support Ministries & SPIUs NCB1 Lot 1 - Computers & Office Rel. Equip. NCB1 Lot 2 - Video Project Management, Single Stage - One Conferencing, Internet IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 1,410,000.00 697,632.71 Signed 2019-04-15 2019-05-21 2019-04-20 2019-06-01 2019-06-27 2019-07-01 2019-08-19 2019-08-05 2019-10-21 2020-02-01 Envelope Servers, Inverters etc and Learning NCB1 Lot 3 - Generating Sets NCB1 Lot 4 - Air Conditioners, Refrigerators etc NCB1 Lot 5 - Seurity/Comm. Equip. NG-MOSWAD-98294-GO- RFQ / Office Computers, Project Management, Request for Single Stage - One Accessories and Related IDA / 62710 Monitoring and Evaluation Post Limited 85,000.00 0.00 Canceled 2019-02-06 2019-04-03 2019-09-30 Quotations Envelope Equipment for Abia State and Learning Project Implementation Unit NG-MOSWAD-112242-GO- RFQ / External Diesel Tank Project Management, Request for Single Stage - One (1500 Liters) and Armored IDA / 62710 Monitoring and Evaluation Post Limited 4,500.00 3,227.59 Completed 2019-05-04 2019-07-09 2019-06-29 2019-09-03 2019-12-26 2020-01-18 Quotations Envelope Cable 4x35mm2 (30mtrs) for and Learning FPIU Office, Abuja NG-MOSWAD-120020-GO- RFQ / Supply and Installation Project Management, of Furniture and fittings for Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 45,000.00 31,774.03 Completed 2019-06-29 2019-08-01 2019-08-24 2019-08-19 2020-02-20 2019-08-26 the 40 Ft. Container Offices Quotations Envelope and Learning along with an adjacent office at the FPIU Page 2 NG-MOSWAD-126199-GO- RFQ / Federal Support Ministries Equipment Project Management, (FMWASD, FMF, OAGF - 10 Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 50,000.00 33,974.41 Completed 2019-08-19 2019-08-15 2019-10-14 2019-09-05 2020-04-11 2019-09-27 Desktops, 2 Laptops, 10 Quotations Envelope and Learning Printers/Photocopiers and Accessories (Power Surge, UPS, Stabilizers etc) plus NG-MOSWAD-127532-GO- Project Management, Request for Single Stage - One RFQ / Camera and Projector IDA / 62710 Monitoring and Evaluation Post Limited 1,500.00 918.21 Completed 2019-08-24 2019-08-22 2019-10-19 2019-09-03 2020-04-16 2019-09-09 Quotations Envelope Accessories and Learning NG-MOSWAD-130318-GO- RFQ / Office Computers and other Equipment and Project Management, Request for Single Stage - One Accessories IDA / 62710 Monitoring and Evaluation Post Limited 45,000.00 33,633.80 Completed 2019-09-14 2019-09-10 2019-11-09 2019-10-07 2020-05-07 2020-01-18 Quotations Envelope (Printers/photocopiers, and Learning Computers etc) for the New Minister New Staff at the FPIU NG-MOSWAD-110072-GO- RFB / Security/Communication Equipment and Accessories Project Management, Single Stage - One for States Project IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 75,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Envelope Implementation Units (SPIUs) and Learning in Abia, Edo, Ogun, Taraba, Niger and Kebbi States under NCB1, Lot 5. NG-MOSWAD-110070-GO- RFB / Air Conditioners and Accessories, Refrigerators and Project Management, Water Dispensers for States Single Stage - One IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 50,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Project Implementation Units Envelope and Learning (SPIUs) in Abia, Ogun, Edo, Taraba, Niger and Kebbi States under NCB1, Lot 4 NG-MOSWAD-110069-GO- RFB / Generating Sets and for Project Management, States Project Implementation Single Stage - One IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 120,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Units (SPIUs) in Abia, Ogun, Envelope and Learning Edo, Taraba, Niger and Kebbi States under NCB1, Lot 3 NG-MOSWAD-110071-GO- RFB / Video Conferencing Device, Fibre Internet & Project Management, Server, Power Inverters for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Request for Bids Open - National 570,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 States Project Implementation Envelope and Learning Units (SPIUs) in Abia, Edu, Ogun, Taraba, Niger and Kebbi States under NCB1, Lot2 NG-MOSWAD-186019-GO- Project Management, RFQ / Procurement of Fibre Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 6,648.00 6,339.97 Signed 2020-07-29 2020-07-29 2020-09-23 2020-08-06 2021-03-22 Internet Subscription & Quotations Envelope and Learning Installation NG-MOSWAD-225501-GO- Project Management, Under Request for Single Stage - One RFQ / PROCUREMENT OF MIS IDA / 62710 Monitoring and Evaluation Post Limited 20,000.00 0.00 Implementati 2021-03-23 2021-03-18 2021-05-18 2021-11-14 Quotations Envelope CLOUD SERVER and Learning on NG-MOSWAD-228365-GO- Project Management, Pending RFQ / Procurement of Laptops Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 15,000.00 0.00 Implementati 2021-04-17 2021-06-12 2021-12-09 and computer accessories for Quotations Envelope and Learning on FPCU personnels NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-98350-NC- RFQ / Insurance cover for Project Management, Under Request for Single Stage - One Project Vehicles (4Nos IDA / 62710 Monitoring and Evaluation Post Limited 50,000.00 19,304.31 Implementati 2019-02-06 2019-04-11 2019-04-03 2019-04-25 2019-09-30 2019-05-03 Quotations Envelope Vehicles at FPIU and 6Nos at and Learning on SPIUs) NG-MOSWAD-98355-NC- Project Management, Request for Single Stage - One RFQ / Security Guards for IDA / 62710 Monitoring and Evaluation Post Limited 20,000.00 15,247.84 Completed 2019-02-06 2019-02-15 2019-04-03 2019-03-06 2019-09-30 2020-03-02 Quotations Envelope NFWP Office, Abuja and Learning NG-MOSWAD-98360-NC- Project Management, Request for Single Stage - One RFQ / Cleaning Services for IDA / 62710 Monitoring and Evaluation Post Limited 18,000.00 15,017.46 Completed 2019-02-09 2019-02-15 2019-04-06 2019-03-04 2019-10-03 2020-03-03 Quotations Envelope NFWP Ofiice, Abuja. and Learning NG-MOSWAD-103985-NC- Project Management, RFQ / Production and Printing Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 75,000.00 46,250.74 Completed 2019-03-08 2019-06-06 2019-05-03 2019-07-05 2019-10-30 2019-07-25 of Thematic Reports plus Quotations Envelope and Learning other project documents NG-MOSWAD-225695-NC- Project Management, Pending RFQ / Procurement of Request for Single Stage - One IDA / 62710 Monitoring and Evaluation Post Limited 13,200.00 0.00 Implementati 2021-03-27 2021-05-22 2021-11-18 insurance policy for project Quotations Envelope and Learning on vehicles NG-MOSWAD-247312-GO- Pending RFQ / PRINTING AND Request for Single Stage - One IDA / 62710 Building Social Capital Post Limited 22,000.00 0.00 Implementati 2021-08-15 2021-10-10 2022-04-08 PRODUCTION OF IEC Quotations Envelope on MATERIALS CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 NG-MOSWAD-95169-CS- CQS / Community Services on Project Management, Consultant Baseline Survey and Risk IDA / 62710 Monitoring and Evaluation Post Qualification Limited 180,000.00 162,462.88 Completed 2019-01-26 2019-02-24 2019-02-09 2019-05-13 2019-03-11 2019-06-10 2019-04-15 2019-06-11 2019-10-12 2019-12-28 Planning (3) tier States and Learning Selection Northern States NG-MOSWAD-95173-CS- CQS / Community Services on Project Management, Consultant Baseline Survey & Risk IDA / 62710 Monitoring and Evaluation Post Qualification Limited 150,000.00 119,918.39 Completed 2019-01-26 2019-02-24 2019-02-09 2019-05-13 2019-03-11 2019-06-10 2019-04-15 2019-06-11 2019-10-12 2019-10-31 Planning Local/Community/ and Learning Selection Assessment three(3) tier Southern States NG-MOSWAD-110287-CS- CQS / Communication Project Management, Consultant Strategy Consultant - IDA / 62710 Monitoring and Evaluation Post Qualification Limited 250,000.00 281,937.13 Signed 2019-04-15 2019-07-09 2019-04-29 2019-09-03 2019-05-29 2019-09-23 2019-07-03 2019-10-15 2019-12-30 (Preparation of and Learning Selection Communication Strategy) NG-MOSWAD-95144-CS- Project Management, Consultant CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Qualification Open - National 250,000.00 0.00 Canceled 2019-02-18 2019-03-29 2019-03-11 2019-04-24 2019-05-24 2019-06-28 2019-12-25 Contract Recruitment Agency and Learning Selection NG-MOSWAD-110289-CS- CQS / HR Recruitment Project Management, Consultant Agency/Firm for the IDA / 62710 Monitoring and Evaluation Post Qualification Limited 250,000.00 333,455.39 Signed 2019-04-15 2019-08-23 2019-04-29 2019-07-10 2019-05-29 2019-09-23 2019-07-03 2019-10-15 2019-12-30 recruitment of various staff, and Learning Selection Advisers and Young Professionals NG-MOSWAD-120004-CS- Project Management, Consultant CQS / Local Government IDA / 62710 Monitoring and Evaluation Post Qualification Limited 200,000.00 0.00 Under Review 2019-06-24 2019-08-23 2019-07-08 2019-08-07 2019-09-11 2020-03-09 Areas (LGAs) Facilitating and Learning Selection Consultants NG-MOSWAD-172802-CS- CQS / Engagement of Project Management, Consultant Consultant for the Design and IDA / 62710 Monitoring and Evaluation Post Qualification Limited 255,000.00 241,296.67 Signed 2020-05-12 2020-05-19 2020-05-26 2020-06-22 2020-06-25 2020-08-02 2020-07-30 2020-08-18 2021-01-26 Deployment of Management and Learning Selection Information System(MIS) NG-MOSWAD-173091-CS- Consultant CQS / Engagement of GBV IDA / 62710 Building Social Capital Post Qualification Limited 190,850.00 0.00 Canceled 2020-05-12 2020-05-20 2020-05-26 2020-06-25 2020-07-30 2021-01-26 Mapping Consultant Selection NG-MOSWAD-177289-CS- Project Management, Least Cost CQS / Engagement of External IDA / 62710 Monitoring and Evaluation Post Open - National 6,000.00 0.00 Canceled 2020-06-02 2020-06-02 2020-06-23 2020-08-06 2020-09-03 2020-10-03 2020-11-07 2020-12-12 2021-06-10 Selection Auditor for NFWP and Learning NG-MOSWAD-177711-CS- Project Management, Consultant CQS / Engagement of External IDA / 62710 Monitoring and Evaluation Post Qualification Limited 6,000.00 18,533.27 Signed 2020-06-03 2020-06-03 2020-06-17 2020-06-12 2020-07-17 2020-06-14 2020-08-21 2020-06-16 2021-02-17 Auditor for NFWP and Learning Selection NG-MOSWAD-112241-CS- Project Management, Consultant CQS / Web Development, IDA / 62710 Monitoring and Evaluation Post Qualification Limited 50,000.00 0.00 Canceled 2019-04-29 2019-05-13 2019-06-12 2019-07-17 2020-01-13 Hosting and Management and Learning Selection Consultant/Firm NG-MOSWAD-227039-CS- CQS / PROCUREMENT OF Consultant Under VIDEO PRODUCTION AND IDA / 62710 Building Social Capital Post Qualification Limited 53,000.00 0.00 2021-03-31 2021-04-07 2021-04-14 2021-05-14 2021-06-18 2021-12-15 Implementation EDITING FIRM FOR WAGs Selection INSTRUCTIONAL GUIDE NG-MOSWAD-242667-CS- CQS / BUSINESS ADVISORY Consultant Pending SERVICES FOR THE IDA / 62710 Livelihoods Program Post Qualification Open - National 48,800.00 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-11 2021-11-15 2022-05-14 Implementation DEVELOPMENT BUSINESS Selection PLAN. NG-MOSWAD-242672-CS- CQS / ENGAGEMENT OF Consultant Pending BEHAVIOUR CHANGE IDA / 62710 Building Social Capital Post Qualification Open - National 150,000.00 0.00 2021-07-08 2021-07-29 2021-09-11 2021-10-11 2021-11-15 2022-05-14 Implementation COMMUNICATION Selection CONSULTING FIRM NG-MOSWAD-244985-CS- Consultant Pending CQS / BUSINESS ADVISORY IDA / 62710 Livelihoods Program Post Qualification Limited 50,000.00 0.00 2021-07-22 2021-08-04 2021-09-03 2021-10-08 2022-04-06 Implementation SERVICE Selection NG-MOSWAD-245030-CS- CQS / ENGAGEMENT OF Consultant Pending BEHAVIOURAL CHANGE IDA / 62710 Building Social Capital Post Qualification Limited 155,000.00 0.00 2021-07-22 2021-08-05 2021-09-04 2021-10-09 2022-04-07 Implementation COMMUNICATION Selection CONSULTING FIRM NG-MOSWAD-248962-CS- Consultant Pending CQS / BUSINESS ADVISORY IDA / 62710 Livelihoods Program Post Qualification Limited 95,000.00 0.00 2021-08-19 2021-09-01 2021-10-01 2021-11-05 2022-05-04 Implementation SERVICE Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-MOSWAD-76579-CS- Project Management, Individual INDV / Engagement of IDA / V1770 Monitoring and Evaluation Prior Consultant Limited 60,000.00 90,604.80 Signed 2018-09-17 2018-11-09 2018-09-22 2018-11-27 2018-10-13 2018-12-18 2018-11-17 2018-12-04 2019-05-16 Procurement Consultant and Learning Selection NG-MOSWAD-95162-CS- INDV / Engagement of 1 Executive Assistant, 1 Young Project Management, Individual Nigerian Professional and 1 IDA / 62710 Monitoring and Evaluation Post Consultant Open 80,000.00 0.00 Under Review 2019-01-16 2019-06-24 2019-03-06 2019-03-27 2019-05-01 2019-10-28 Administrative Assistance and Learning Selection under the Federal Project Coordinator's Office Page 4 NG-MOSWAD-95295-CS- Project Management, Individual INDV / Grievance Redress & IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Under Review 2019-01-26 2019-04-19 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Feedback Mechanism and Learning Selection NG-MOSWAD-95298-CS- Project Management, Individual INDV / Community Institution IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Under Review 2019-01-26 2019-02-24 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Building Adviser and Learning Selection NG-MOSWAD-103892-CS- Project Management, Individual INDV / Community IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 9,155.38 Completed 2019-03-02 2019-04-19 2019-03-07 2019-07-08 2019-03-28 2019-07-31 2019-05-02 2019-08-05 2019-10-29 2020-01-28 Procurement Manual and Learning Selection Consultant NG-MOSWAD-103982-CS- INDV / Engagement of 15 Young Nigerian Professionals by the Recruitment Agency - (To support the following Project Management, Individual Advisers - (Livehood, BCC, IDA / 62710 Monitoring and Evaluation Post Consultant Open 225,000.00 0.00 Under Review 2019-03-03 2019-10-30 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Community Institution and Learning Selection Building, Gender, Innovation & Partnership, Project Comm & Public Relations, M&E, Fin Mgt. & Proc. Spec.) NG-MOSWAD-103984-CS- INDV / Engagement of a Web Project Management, Individual Developer for FPIU, Abuja and IDA / 62710 Monitoring and Evaluation Post Consultant Open 50,000.00 0.00 Canceled 2019-03-03 2019-04-21 2019-05-12 2019-06-16 2019-12-13 SPIUs in Abia, Ogun, Edo, and Learning Selection Taraba, Niger and Kebbi States NG-MOSWAD-103987-CS- Project Management, Individual INDV / Engagement of IT Staff IDA / 62710 Monitoring and Evaluation Post Consultant Limited 20,000.00 0.00 Canceled 2019-03-03 2019-06-24 2019-03-08 2019-03-29 2019-05-03 2019-10-30 to handle ICT related and Learning Selection problems in FPIU Office, Abuja NG-MOSWAD-98348-CS- Project Management, Individual INDV / Community Driven IDA / 62710 Monitoring and Evaluation Prior Consultant Limited 10,000.00 0.00 Canceled 2019-02-01 2019-02-06 2019-02-27 2019-04-03 2019-09-30 Manual Consultant and Learning Selection NG-MOSWAD-115087-CS- Project Management, Individual INDV / Community Driven IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 0.00 Canceled 2019-05-20 2019-06-12 2019-05-25 2019-06-15 2019-07-20 2020-01-16 Development Operations and Learning Selection Manual NG-MOSWAD-116137-CS- INDV / Supervision Engineer for the Minor Rehabilitation Project Management, Individual and Partitioning in the Six IDA / 62710 Monitoring and Evaluation Post Consultant Limited 25,000.00 21,502.27 Completed 2019-05-27 2019-06-14 2019-06-01 2019-06-25 2019-06-22 2019-07-24 2019-07-27 2019-07-29 2020-01-23 2020-01-20 States Projects and Learning Selection Implementation Units (SPIUs) Offices NG-MOSWAD-75969-CS- INDV / Engagement of Project Management, Individual Consultant for the IDA / V1770 Monitoring and Evaluation Post Consultant Open 10,000.00 0.00 Canceled 2018-10-24 2019-01-06 2018-12-12 2019-01-02 2019-02-06 2019-08-05 Preparartion of Community- and Learning Selection Driven Developent Manual NG-MOSWAD-126201-CS- Project Management, Individual INDV / Technical Assistant (1 IDA / 62710 Monitoring and Evaluation Post Consultant Limited 30,000.00 13,601.92 Signed 2019-08-19 2019-08-29 2019-08-24 2019-10-25 2019-09-14 2019-11-05 2019-10-19 2019-11-05 2020-04-16 No.) and Executive Assistant and Learning Selection (1 No.) NG-MOSWAD-126196-CS- Project Management, Individual INDV / Niger State Project IDA / 62710 Monitoring and Evaluation Post Consultant Limited 65,000.00 4,548.59 Signed 2019-08-19 2019-09-03 2019-08-24 2019-09-17 2019-09-14 2019-09-17 2019-10-19 2019-05-09 2020-04-16 Coordinator Engagement and Learning Selection NG-MOSWAD-126193-CS- Project Management, Individual INDV / Edo State Project IDA / 62710 Monitoring and Evaluation Post Consultant Limited 65,000.00 54,583.06 Signed 2019-08-19 2019-09-03 2019-08-24 2019-09-17 2019-09-14 2019-09-17 2019-10-19 2019-05-09 2020-04-16 Coordinator Engagement and Learning Selection NG-MOSWAD-127527-CS- Project Management, Individual INDV / Community Institution IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Under Review 2019-08-26 2019-10-30 2019-10-14 2019-10-29 2019-12-03 2020-05-31 Building Adviser and Learning Selection NG-MOSWAD-130316-CS- INDV / Engagement of Local Government Area Coordinators by the HR Firm for the six SPCUs as follows: Project Management, Individual 1. Abia State - 3No IDA / 62710 Monitoring and Evaluation Prior Consultant Open 500,000.00 0.00 Under Review 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 2. Edo State - 3 No and Learning Selection 3 Ogun State - 3No 4. Taraba State - 3No 5. Kebbi State - 3 No 6. Niger State - 3 No Total for the six States is 18 NG-MOSWAD-174588-CS- CDS / Engagement of GBV IDA / 62710 Building Social Capital Prior Direct Selection Direct 460,000.00 0.00 Under Review 2020-05-21 2020-06-03 2020-05-31 2020-06-19 2020-08-04 2021-01-31 Mapping Consultant Firm Project Management, Individual NG-MOSWAD-127353-CS- IDA / 62710 Monitoring and Evaluation Post Consultant Limited 10,000.00 0.00 Canceled 2019-08-19 2019-08-24 2019-09-14 2019-10-19 2020-04-16 INDV / Front Desk Officer and Learning Selection NG-MOSWAD-95299-CS- Project Management, Individual INDV / Innovation and IDA / 62710 Monitoring and Evaluation Post Consultant Open 75,000.00 0.00 Canceled 2019-01-26 2019-02-21 2019-03-16 2019-04-06 2019-05-11 2019-11-07 Partnership Adviser and Learning Selection NG-MOSWAD-95164-CS- Project Management, Individual INDV / Project IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Canceled 2019-02-25 2019-02-25 2019-04-15 2019-05-06 2019-06-10 2019-08-09 Communication / Public and Learning Selection relation Adviser NG-MOSWAD-94721-CS- Project Management, Individual CQS / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Open 70,000.00 0.00 Canceled 2019-02-04 2019-02-24 2019-03-09 2019-03-30 2019-05-04 2019-10-31 Monitoring & Evaluation and Learning Selection Specialist by FPCU, NFWP Page 5 NG-MOSWAD-76026-CS- Individual INDV / Engagement Livelihood IDA / V1770 Livelihoods Program Post Consultant Limited 90,000.00 0.00 Canceled 2018-10-02 2019-01-02 2018-10-07 2018-10-28 2018-12-02 2019-05-31 Support Technical Expert Selection NG-MOSWAD-130317-CS- INDV / Engagement of Facilitators for LGAs and Wards by HR Firm for the Six SPCUs as follows: Project Management, Individual 1. Abia State - 9No IDA / 62710 Monitoring and Evaluation Prior Consultant Open 600,000.00 0.00 Canceled 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 2. Edo State - 9No and Learning Selection 3. Ogun State - 9No 4. Taraba State - 9No 5. Kebbi State - 9No 6. Niger State - 9No Total for the six States is 54 NG-MOSWAD-76015-CS- Project Management, Individual INDV / Engagement of Gender IDA / V1770 Monitoring and Evaluation Post Consultant Limited 40,000.00 0.00 Canceled 2018-10-02 2019-01-02 2018-10-12 2018-11-02 2018-12-07 2019-06-05 Specialist and Learning Selection NG-MOSWAD-103983-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Open 80,000.00 0.00 Canceled 2019-03-03 2019-04-19 2019-04-21 2019-05-12 2019-06-16 2019-12-13 Behavioral Change and Learning Selection Communication Adviser NG-MOSWAD-114531-CS- Project Management, Individual INDV / Procurement IDA / 62710 Monitoring and Evaluation Prior Consultant Open 300,000.00 0.00 Canceled 2019-05-13 2019-09-12 2019-07-01 2019-07-22 2019-08-26 2020-02-22 Consultants (6Nos) to support and Learning Selection the Six (6) SPIUs NG-MOSWAD-76030-CS- Project Management, Individual INDV / Engagement of Social IDA / V1770 Monitoring and Evaluation Post Consultant Limited 40,000.00 0.00 Canceled 2018-10-02 2019-02-21 2018-10-07 2018-10-28 2018-12-02 2019-05-31 Environmental Safeguards and Learning Selection Specialist NG-MOSWAD-140893-CS- Project Management, Individual INDV / Project Implementation IDA / 62710 Monitoring and Evaluation Post Consultant Limited 20,000.00 0.00 Canceled 2019-10-17 2019-10-22 2019-11-12 2019-12-17 2020-06-14 Manual (PIM) Review and Learning Selection Consultant NG-MOSWAD-76033-CS- INDV / Engagement of Consultant for the Project Management, Individual Preparartion of Project IDA / V1770 Monitoring and Evaluation Post Consultant Limited 30,000.00 0.00 Canceled 2018-10-24 2018-10-23 2018-10-29 2018-12-07 2018-11-19 2018-12-24 2019-06-22 Implementation and Learning Selection Manual(Federal Coordinating Office and States PIUs NG-MOSWAD-186884-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 19,738.94 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-08-31 2021-04-03 Behavior Change and Learning Selection Communication Adviser NG-MOSWAD-186885-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 28,486.57 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-08-20 2021-04-03 Community Mobilization & and Learning Selection Capacity Building Adviser NG-MOSWAD-186888-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 23,145.34 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-09-08 2021-04-03 Livelihood Adviser and Learning Selection NG-MOSWAD-186889-CS- INDV / Engagement of Project Management, Individual Monitoring, Evaluation & IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 32,047.39 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-10-08 2021-04-03 Knowledge Management and Learning Selection Adviser NG-MOSWAD-186887-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 0.00 Under Review 2020-08-05 2020-08-04 2020-08-10 2020-08-31 2020-10-05 2021-04-03 Environmental Adviser and Learning Selection NG-MOSWAD-186886-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 28,486.57 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-08-20 2021-04-03 Gender & Gender Based and Learning Selection Violence Adviser NG-MOSWAD-186890-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 31,579.00 23,145.34 Signed 2020-08-05 2020-08-04 2020-08-10 2020-08-09 2020-08-31 2020-08-12 2020-10-05 2020-08-31 2021-04-03 Innovation & Partnership and Learning Selection Adviser NG-MOSWAD-200905-CS- Project Management, Individual INDV / Engagement of Under IDA / 62710 Monitoring and Evaluation Post Consultant Limited 50,000.00 0.00 2020-10-21 2020-10-22 2020-10-26 2020-11-16 2020-12-21 2021-06-19 Management Information Implementation and Learning Selection System Specialist NG-MOSWAD-204871-CS- INDV / Engagement of Project Management, Individual Consultant for Capacity Under IDA / 62710 Monitoring and Evaluation Post Consultant Limited 19,000.00 0.00 2020-11-15 2020-12-11 2020-11-20 2020-12-11 2021-01-15 2021-07-14 Building (Community Implementation and Learning Selection Operating Manual-Training of Trainers) NG-MOSWAD-209261-CS- Project Management, Individual Under INDV / engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 50,000.00 0.00 2020-12-16 2021-01-27 2020-12-21 2021-01-11 2021-02-15 2021-08-14 Implementation Procurement Consultant and Learning Selection NG-MOSWAD-217809-CS- INDV / Engagement of an Project Management, Individual Under Individual Consultant for the IDA / 62710 Monitoring and Evaluation Post Consultant Limited 18,000.00 0.00 2021-02-04 2021-02-08 2021-02-09 2021-03-02 2021-04-06 2021-10-03 Implementation training on Financial and Learning Selection Management NG-MOSWAD-228363-CS- CDS / Consulting services for Mapping of Services for IDA / 62710 Building Social Capital Post Direct Selection Direct 460,000.00 0.00 Under Review 2021-04-08 2021-04-29 2021-04-14 2021-05-17 2021-11-13 Survivors of Gender Based Violence (GBV) Page 6 NG-MOSWAD-230427-CS- Project Management, Individual Pending CDS / Engagement of External IDA / 62710 Monitoring and Evaluation Post Consultant Direct 7,900.00 0.00 2021-04-21 2021-05-01 2021-05-22 2021-06-26 2021-12-23 Implementation Auditors and Learning Selection NG-MOSWAD-230431-CS- Project Management, Individual INDV / Engagement of IDA / 62710 Monitoring and Evaluation Post Consultant Limited 4,800.00 0.00 Under Review 2021-04-26 2021-04-26 2021-05-01 2021-05-22 2021-06-26 2021-12-23 Assistant Project Accountant and Learning Selection Page 7