Procurement Plan for P145861 (PROCEJ) I. General 2. Bank’s approval Date of the procurement Plan: (Original April 2014) Revisions: February 4, 2015; May 6, 2016; January 9, 2017 3. Date of General Procurement Notice: UNDB December 8 2014 4. Period covered by this procurement plan: Year 2017. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Mandatory threshold to Prior Review Procurement Type of procurement use Thresholds in methods Procurement USD method in USD Works (including ≥ All contract ICB turnkey, supply & 15.000.000 with estimated installation of plant NCB < 15.000.000 cost equal or and equipment, Shopping < 200.000 above 10 and PPP) Direct contracting No threshold million ≥ All contract Goods, information ICB 3.000.000 with estimated technology and NCB < 3.000.000 cost equal or non-consulting Shopping < 100.000 above 2 services Direct contracting No threshold million 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P145861issued by PROCEJ 5. Any Other Special Procurement Arrangements: Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: This Project is implementing since 2014. This Procurement plan is only for the year 2017. 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ million Prefere (Prior / Post) nce (yes/no) 1 Summary of 3,220,000 6 No Post the NCB (Works) 2 Summary of 5,080,660 7 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Mandatory threshold to Prior Review Procurement Type of procurement use Thresholds in methods Procurement USD method in USD QCBS; QBS; FBS; All contract No threshold LCS; SSS with estimated Consultants: firms cost equal or CQS < 300.000 above 1million All contract with estimated Consultants: Competitive and No threshold cost equal or individuals SSS above 0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of number of 2,460,500 59 Post INDV. CQS contracts that will be let under other methods PROCUREMENT Mali : MALI - Skills Development and Youth Employment Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-02-27 2019-08-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145861 GPN Date: Project Name: MALI - Skills Development and Youth Employment Project Loan / Credit No: IDA / 55130, IDA / H9710 Executing Agency(ies): Skills Development and Youth Employment Project WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CW-REF-1 / travaux 3. Institutional Single Stage - One En attente rehabilitation des locaux du IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2017-09-04 2017-09-09 2017-10-09 2017-10-23 2017-11-20 2018-05-19 Envelope d'exécution CFP Missabougou Management CW-REF-3 / 3. Institutional Réhabilitation/rénovation Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2017-09-04 2017-09-09 2017-10-09 2017-10-23 2017-11-20 2018-05-19 des locaux du centre de Envelope d'exécution Management Bankass Mopti DNETP CW-REF-4 / travaux rehabilitation amenagement 3. Institutional des locaux du centre de Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2017-09-04 2017-09-09 2017-10-09 2017-10-23 2017-11-20 2018-05-19 formation mines et services Envelope d'exécution Management auxiliaires de Bougouni DNETP CW-REF-5 / travaux de 3. Institutional Single Stage - One En attente réhabilitation des locaux de IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2017-08-04 2017-08-09 2017-09-08 2017-09-22 2017-10-16 2018-04-14 Envelope d'exécution l'IFSAB Management CW-REF-6 / Réhabilitation/rénovation 3. Institutional Single Stage - One En attente des locaux du centre de IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2017-09-04 2017-09-09 2017-10-09 2017-10-23 2017-11-20 2018-05-19 Envelope d'exécution formation Agro-alimentaire Management de Ségou ML-PROCEJ-52801-CW- RFQ / Travaux de 2. Private-Sector led Job Single Stage - One En attente réhabilitation,Aménagement/ IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-04-12 2018-06-07 2018-12-04 Creation for Youth Envelope d'exécution renovation des locaux de l'IFP de Bankass ML-PROCEJ-52571-CW- RFB / Travaux d'Aménagement et 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-04-12 2018-06-07 2018-12-04 installation des forages Creation for Youth Envelope d'exécution solaires pour le compte de l'ESAP-Ségou, l'IAPS dans le cadre du fonds compétitif ML-PROCEJ-53041-CW- RFQ / travaux 2. Private-Sector led Job Single Stage - One En attente d'aménagement technique IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-04-12 2018-06-07 2018-12-04 Creation for Youth Envelope d'exécution au compte de l'IF-FN dans le cadre du fonds compétitif ML-PROCEJ-53568-CW- RFQ / travaux d'installation d'un forage 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-04-12 2018-05-17 2018-06-16 équipé + château d'eau au Creation for Youth Envelope d'exécution compte de EFAP-KOLON dans le cadre du fonds compétitif ML-PROCEJ-52564-CW- RFB / travaux d'aménagement et 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-06-20 2018-08-15 2019-02-11 installation de château Creation for Youth Envelope d'exécution d'eau et chaps solaire au compte de l'ITAS-KADIOLO dans le cadre du fonds compétitif ML-PROCEJ-52855-CW- RFB / travaux d'aménagement technique 2. Private-Sector led Job Single Stage - One En attente (puits grand diamètre + IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-06-22 2018-08-10 2019-02-06 Creation for Youth Envelope d'exécution cloture de champs) au compte de CFM-MTK dans le cadre du fonds compétitif ML-PROCEJ-52567-CW- RFB / travaux 2. Private-Sector led Job Single Stage - One En attente d'aménagement technique IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-06-20 2018-08-15 2019-02-11 Creation for Youth Envelope d'exécution au compte de l'UFTI dans le cadre du fonds compétitif ML-PROCEJ-93975-CW- 3. Institutional RFB / Aménagement des Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2019-04-29 2019-05-04 2019-06-03 2019-06-17 2019-07-04 2019-12-31 locaux du centre de Envelope d'exécution Management Bankass au compte de la DNETP ML-PROCEJ-93976-CW- 3. Institutional RFQ / aménagement d'une Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-03-04 2019-04-08 2019-06-07 station d'épuration de l'IFP Envelope d'exécution Management de Kalaban-coro GOODS Page 1 Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 3. Institutional GO-REF-5 / Acquisition Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Open - National 0.00 2017-09-15 2017-12-03 2018-01-02 des Trousseaux apprenant Envelope d'exécution Management ML-PROCEJ-52029-GO- 3. Institutional Single Stage - One En attente RFQ / Acquisition des IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-03-05 2018-04-30 2018-10-27 Envelope d'exécution outils de gestion Management 3. Institutional ML-PROCEJ-53531-GO- Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-01-16 RFB / Kits d'insertion Envelope d'exécution Management ML-PROCEJ-52031-GO- 3. Institutional Single Stage - One En attente RFQ / Moto (20) au compte IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-05-10 2018-07-05 2019-01-01 Envelope d'exécution de l'UCP Management ML-PROCEJ-51746-GO- 3. Institutional Single Stage - One En attente RFQ / Pièces détachées des IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-02-06 2018-04-03 2018-09-30 Envelope d'exécution véhicules Management ML-PROCEJ-52613-GO- 3. Institutional RFQ / Kits de matière Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-06-15 2018-08-10 2018-09-09 d'œuvre dans le cadre de Envelope d'exécution Management la certification ML-PROCEJ-52811-GO- RFB / Matériels informatiques et bureautiques au compte du 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Appel d'offres Open - National 0.00 2018-04-05 2018-04-10 2018-05-22 2018-06-21 2018-07-26 2018-08-25 CMA-SIK, ESAP-Ségou, Creation for Youth Envelope d'exécution IAPS, ITAS-KADIOLO, IF- FN, CFM-MTK, EFAP- KOLON, UFTI dans le cadre du fonds compétitif ML-PROCEJ-52799-GO- RFB / Minibus et des motocyclettes pour le 2. Private-Sector led Job Single Stage - One En attente compte de l'ESAP-Ségou, IDA / 55130 A posteriori Appel d'offres Open - National 0.00 2018-03-30 2018-04-04 2018-05-16 2018-06-15 2018-07-20 2019-01-16 Creation for Youth Envelope d'exécution l'IAPS, CFM-MTK, EFAP- KOLON dans le cadre du fonds compétitif ML-PROCEJ-52615-GO- RFB / Equipements de 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Appel d'offres Open - National 0.00 2018-04-04 2018-04-09 2018-05-21 2018-06-20 2018-07-25 2018-08-24 laboratoire au compte de Creation for Youth Envelope d'exécution l'ESAP-Ségou ML-PROCEJ-52551-GO- RFB / Equipement agricole au compte de l'IAPS, 2. Private-Sector led Job Single Stage - One En attente IDA / 55130 A posteriori Appel d'offres Open - National 0.00 2018-03-22 2018-03-27 2018-05-08 2018-06-07 2018-07-12 2019-01-08 l'ESAP-Ségou, CFM-MTK, Creation for Youth Envelope d'exécution EFAP-KOLON dans le cadre du fonds compétitif ML-PROCEJ-52014-GO- RFQ / Matériels agricole 2. Private-Sector led Job Single Stage - One En attente au compte de l'ITAS- IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-03-25 2018-05-20 2018-11-16 Creation for Youth Envelope d'exécution KADIOLO dans le cadre du fonds compétitif ML-PROCEJ-52830-GO- RFB / Matériels de 2. Private-Sector led Job Single Stage - One En attente préparation et entretien de IDA / 55130 A posteriori Appel d'offres Open - National 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2018-08-09 Creation for Youth Envelope d'exécution sol au compte de CFM- MTK dans le cadre du fonds compétitif ML-PROCEJ-53083-GO- RFQ / Equipements 2. Private-Sector led Job Single Stage - One En attente pédagogiques au compte de IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-03-25 2018-05-20 2018-06-19 Creation for Youth Envelope d'exécution CFM-MTK dans le cadre du fonds compétitif ML-PROCEJ-52780-GO- RFQ / Kits dans le cadre 3. Institutional de la mise en œuvre des Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-03-26 2018-05-21 2018-06-20 mesures de sauvegarde Envelope d'exécution Management environnementales et sociales ML-PROCEJ-53569-GO- 3. Institutional Single Stage - One En attente RFQ / Matériels IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-02-10 2018-03-17 2018-04-16 Envelope d'exécution bureautique et Management informatique ML-PROCEJ-53534-GO- RFQ / Mobiliers de bureau 2. Private-Sector led Job Single Stage - One En attente et scolaire au compte du IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-06-19 2018-07-24 2018-08-23 Creation for Youth Envelope d'exécution CMA-SIK, IAPS, DMTK dans le cadre du fonds compétitif ML-PROCEJ-61674-GO- RFQ / Acquisition l'outil 2. Private-Sector led Job Single Stage - One En attente (logiciel) de gestion au IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-06-11 2018-07-16 2018-08-15 Creation for Youth Envelope d'exécution compte de CFM-MTK dans le cadre du fonds compétitif ML-PROCEJ-61691-GO- 3. Institutional Single Stage - One En attente RFQ / Mobilier de bureau IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-06-18 2018-07-23 2018-08-22 Envelope d'exécution au compte de l'UCP Management Page 2 ML-PROCEJ-93599-GO- RFB / Acquisition des 3. Institutional Single Stage - One En attente équipements pédagogiques, IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2019-05-15 2019-05-20 2019-06-19 2019-07-03 2019-07-24 2020-01-20 Envelope d'exécution installation et formation au Management compte du CFP de Bankass GO-REF-7 / Acquisition 3. Institutional Single Stage - One En attente des kits d'insertion au IDA / 55130 Strengthening and Project A posteriori Appel d'offres Open - National 0.00 2019-02-25 2019-03-02 2019-04-01 2019-04-15 2019-05-09 2019-11-05 Envelope d'exécution compte de la DNFP Management ML-PROCEJ-93969-GO- 3. Institutional Single Stage - One En attente RFQ / Acquisition d'un IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-03-01 2019-03-28 2019-04-27 Envelope d'exécution logiciel de statistique STAT Management MANIA ML-PROCEJ-93971-GO- RFQ / Achat de téléphones 3. Institutional cellulaires et 2 tablettes Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-03-03 2019-03-30 2019-04-29 dans le cadre des enquêtes Envelope d'exécution Management du S&E à distance via Kobotoolbox ML-PROCEJ-93974-GO- 3. Institutional Single Stage - One En attente RFQ / Achat de mobiliers IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-03-09 2019-04-05 2019-05-05 Envelope d'exécution de bureau au compte de Management l'UCP ML-PROCEJ-52838-GO- 3. Institutional RFQ / Véhicules de Single Stage - One IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 Annulé 2018-03-15 2018-05-10 2018-06-09 mission: 2 Pick-up au Envelope Management compte de l'UCP ML-PROCEJ-52553-GO- RFB / Equipement pédagogiques et de matériels de laboratoire au 2. Private-Sector led Job Single Stage - One compte de DMTK, IAPS, IDA / 55130 A posteriori Appel d'offres Open - National 0.00 Annulé 2018-05-30 2018-06-04 2018-07-16 2018-08-15 2018-09-19 2019-03-18 Creation for Youth Envelope CMA-SIK, ITAS-KADIOLO, IFFN, CFM-MTK, EFAP- KOLON, UFTI dans le cadre du fonds compétitif ML-PROCEJ-61679-GO- RFQ / Acquisition l'outil 2. Private-Sector led Job Single Stage - One (logiciel) de gestion au IDA / 55130 A posteriori Demande de prix Limited 0.00 Annulé 2018-06-16 2018-08-04 2018-09-03 Creation for Youth Envelope compte du CMA-SIK dans le cadre du fonds compétitif ML-PROCEJ-61668-GO- RFQ / Acquisition l'outil 3. Institutional Single Stage - One (logiciel) de gestion au IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 Annulé 2018-06-17 2018-07-22 2018-08-21 Envelope compte du DMTK dans le Management cadre du fonds compétitif ML-PROCEJ-61669-GO- RFQ / Acquisition l'outil 3. Institutional Single Stage - One (logiciel) de gestion au IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 Annulé 2018-06-17 2018-07-22 2018-08-21 Envelope compte de l'IF-FN dans le Management cadre du fonds compétitif NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-PROCEJ-52013-NC- 3. Institutional Single Stage - One En attente RFQ / production de IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-05-15 2018-07-10 2019-01-06 Envelope d'exécution rapport certification des Management jeunes ML-PROCEJ-52795-NC- RFQ / Impression de support dans le cadre de la 1. Education and Training Single Stage - One En attente IDA / 55130 A posteriori Demande de prix Limited 0.00 2018-04-20 2018-06-15 2018-06-30 promotion de for Employability Envelope d'exécution l'entreprenariat des jeunes diplômés ML-PROCEJ-52562-NC- 3. Institutional Single Stage - One En attente RFQ / production et IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-04-06 2018-06-01 2018-11-28 Envelope d'exécution impression des documents Management du PROCEJ ML-PROCEJ-52770-NC- 3. Institutional Single Stage - One En attente RFQ / Acquisition de IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-04-06 2018-06-01 2018-11-28 Envelope d'exécution logiciel TOM2PRO Management ML-PROCEJ-52773-NC- RFQ / Acquisition l'outil 3. Institutional Single Stage - One En attente (logiciel) de gestion au IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2018-03-17 2018-05-12 2018-06-11 Envelope d'exécution compte de l'ITAS-KADIOLO Management dans le cadre du fonds compétitif ML-PROCEJ-93597-NC- RFQ / Installation et 3. Institutional Single Stage - One En attente formation des équipements IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-22 2019-03-20 2019-04-19 Envelope d'exécution pédagogiques au compte de Management l'ENETP ML-PROCEJ-93598-NC- RFQ / Installation et 3. Institutional Single Stage - One En attente formation des équipements IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-15 2019-03-14 2019-04-13 Envelope d'exécution pédagogiques au compte de Management l'IFSAB de Banankabougou Page 3 ML-PROCEJ-93600-NC- RFQ / Installation et 3. Institutional Single Stage - One En attente formation des équipements IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-17 2019-03-16 2019-04-15 Envelope d'exécution pédagogiques au compte de Management l'IFP de Ségou ML-PROCEJ-93601-NC- RFQ / Installation et 3. Institutional Single Stage - One En attente formation des équipements IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-26 2019-03-25 2019-04-24 Envelope d'exécution pédagogiques au compte de Management l'IFP de Kalaban-coro ML-PROCEJ-93602-NC- RFQ / Installation et 3. Institutional Single Stage - One En attente formation des équipements IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-24 2019-03-23 2019-04-22 Envelope d'exécution pédagogiques au compte de Management l'IFP de Missabougou ML-PROCEJ-93603-NC- 3. Institutional RFQ / Impression et Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-11 2019-03-10 2019-04-09 diffusion des programmes Envelope d'exécution Management et supports de formation 2019 ML-PROCEJ-93604-NC- RFQ / couverture 3. Institutional médiatique et confection Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-06-18 2019-07-15 2019-08-14 des supports de Envelope d'exécution Management communication dans le cadre de la cérémonie de remise des fonds de démarrage ML-PROCEJ-93968-NC- 3. Institutional RFQ / Réalisation des Single Stage - One En attente IDA / 55130 Strengthening and Project A posteriori Demande de prix Limited 0.00 2019-02-17 2019-03-17 2019-04-16 sketchs dans le cadre de la Envelope d'exécution Management campagne de communication ML-PROCEJ-93606-NC- RFQ / Mise en place d'une 2. Private-Sector led Job Single Stage - One En attente plateforme numérique pour IDA / 55130 A posteriori Demande de prix Limited 0.00 2019-02-24 2019-03-23 2019-04-22 Creation for Youth Envelope d'exécution la compétition de plans d'affaires (3ème édition) CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-5 / Etudes architecturales Sélection fondée (aménagement et rénovation 3. Institutional sur les En attente des locaux)u Centre de IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-09-20 2017-10-04 2017-10-25 2017-11-01 2017-11-15 2017-12-15 qualifications des d'exécution formation mines et services Management consultants auxilliaires de Bougouni ou Keniéba CS-REF-8 / Etudes Sélection fondée architecturales 1. Education and Training sur les En attente (aménagement et rénovation IDA / 55130 A posteriori Open - National 0.00 2017-01-28 2017-02-18 2017-04-03 2017-05-03 2017-06-07 2017-12-04 for Employability qualifications des d'exécution des locaux) IFP de consultants Bankass CS-REF-12 / Etudes architecturales Sélection fondée (aménagement et rénovation 3. Institutional sur les En attente des locaux) Centre de IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-01-28 2017-02-18 2017-04-03 2017-05-03 2017-06-07 2017-12-04 qualifications des d'exécution Formation Professionnelle Management consultants de Kalaban -coro (IFP Kalabancoro) Sélection fondée CS-REF-20 / Formation 3. Institutional sur les En attente complémentaire des jeunes IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-08-15 2017-08-29 2017-09-12 2017-09-19 2017-10-03 2017-10-03 qualifications des d'exécution dans les centres Management consultants Sélection fondée CS-REF-36 / Formation 3. Institutional sur les En attente pédagogique des artisans et IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-09-18 2017-10-02 2017-10-23 2017-10-30 2017-11-13 2017-12-13 qualifications des d'exécution exploitants Management consultants Sélection fondée CS-REF-40 / Suivi- 1. Education and Training sur les En attente accompagnement des plans IDA / 55130 A posteriori Open - National 0.00 2017-07-25 2017-08-08 2017-08-22 2017-08-29 2017-09-12 2017-10-12 for Employability qualifications des d'exécution d'affaires des jeunes consultants Sélection fondée CS-REF-41 / Formation et 3. Institutional sur les En attente accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-08-30 2017-09-13 2017-09-27 2017-10-04 2017-10-18 2017-11-17 qualifications des d'exécution candidats zone1 Management consultants CS-REF-43 / Evaluation Sélection fondée 3. Institutional de l'offre de formation et sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-09-17 2017-10-01 2017-10-15 2017-10-22 2017-11-05 2017-12-05 des besoins sur l'ensemble qualifications des d'exécution Management du Mali consultants Sélection fondée CS-REF-44 / Audit des 3. Institutional sur les En attente centres de formation agréés IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-08-06 2017-08-20 2017-09-03 2017-09-10 2017-09-24 2017-10-24 qualifications des d'exécution au niveau de l'ETFP Management consultants CS-REF-48 / Formation à Sélection fondée la mise en œuvre locale de 3. Institutional sur les En attente la formation IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-09-12 2017-09-26 2017-10-10 2017-10-17 2017-10-31 2017-11-30 qualifications des d'exécution (autonomisation des centres) Management consultants au compte de la DNETP Page 4 Sélection fondée CS-REF-52 / Elaboration 3. Institutional sur les En attente de la charte des PME au IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-03-24 2017-04-14 2017-05-28 2017-06-27 2017-08-01 2018-01-28 qualifications des d'exécution compte du MPISP Management consultants CS-REF-56 / Evaluation Sélection fondée 3. Institutional de l'offre de formation et sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-09-17 2017-10-01 2017-10-15 2017-10-22 2017-11-05 2017-12-05 des besoins sur qualifications des d'exécution Management l'ensensembre du Mali- consultants DNFP CS-REF-57 / Audit des 3. Institutional Sélection au En attente centres de formation agrées IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2017-08-13 2017-08-27 2017-09-10 2017-10-10 2017-10-17 2017-11-07 2017-11-28 2017-12-28 moindre coût d'exécution par le MEFP Management ML-PROCEJ-52595-CS- CQS / Etudes Sélection fondée 3. Institutional architecturales sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-03-11 2018-04-01 2018-05-15 2018-06-14 2018-07-19 2019-01-15 (aménagement et rénovation qualifications des d'exécution Management des locaux)u Centre de consultants formation mines et services auxilliaires des IFP ML-PROCEJ-53581-CS- 3. Institutional Sélection fondée En cours QCBS / Auditeur externe IDA / 55130 Strengthening and Project A posteriori sur la qualité et Open - National 0.00 2018-02-03 2018-02-24 2018-03-17 2018-03-31 2018-04-07 2018-04-21 2018-04-30 2019-04-30 d'examen pour les exercices 2018, Management le coût 2019 et 2020 ML-PROCEJ-53118-CS- Sélection fondée CQS / recrutement d'une 3. Institutional sur les En attente ONG pour la formation des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2018-09-29 qualifications des d'exécution jeunes déscolarisés dans la Management consultants région de Taoudeni ML-PROCEJ-52798-CS- Sélection fondée CQS / recrutement d'une 3. Institutional sur les En attente ONG pour la formation des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2018-09-29 qualifications des d'exécution jeunes déscolarisés dans la Management consultants région de Ménaka ML-PROCEJ-53529-CS- Sélection fondée CQS / recrutement d'une 2. Private-Sector led Job sur les En attente ONG pour la formation des IDA / 55130 A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2019-02-26 Creation for Youth qualifications des d'exécution jeunes déscolarisés dans le consultants cercle de Douentza ML-PROCEJ-52026-CS- Sélection fondée CQS / recrutement d'une 3. Institutional sur les En attente ONG pour la formation des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2019-02-26 qualifications des d'exécution jeunes déscolarisés dans le Management consultants cercle de Youwarou ML-PROCEJ-52617-CS- Sélection fondée CQS / recrutement d'une 3. Institutional sur les En attente ONG pour la formation des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2018-09-29 qualifications des d'exécution jeunes déscolarisés dans le Management consultants cercle de Ténékou ML-PROCEJ-52775-CS- Sélection fondée CQS / recrutement d'une 3. Institutional sur les En attente ONG pour la formation des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-04-22 2018-05-13 2018-06-26 2018-07-26 2018-08-30 2018-09-29 qualifications des d'exécution jeunes déscolarisés dans le Management consultants cercle de Bourem ML-PROCEJ-52863-CS- Sélection fondée CQS / la mise en œuvre 3. Institutional sur les En attente du volet « formation IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-08-27 qualifications des d'exécution décentralisée de courte Management consultants durée » dans la région de Mopti ML-PROCEJ-52867-CS- Sélection fondée CQS / la mise en œuvre 3. Institutional sur les En attente du volet « formation IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-08-27 qualifications des d'exécution décentralisée de courte Management consultants durée » dans la région de Gao ML-PROCEJ-52006-CS-LCS / Service de contrôle des Sélection fondée 3. Institutional travaux de sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-06-03 2018-06-17 2018-07-01 2018-07-08 2018-07-25 2018-08-24 réhabilitation/aménagement qualifications des d'exécution Management des locaux de l'IFP consultants peaux et cuirs de Kalaban- Coro ML-PROCEJ-61557-CS- Sélection fondée 3. Institutional CQS / Conception et mise sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-05-30 2018-06-13 2018-06-27 2018-07-04 2018-07-15 2019-01-11 en œuvre de logiciel de qualifications des d'exécution Management gestion des flux scolaires consultants ML-PROCEJ-51982-CS- Sélection fondée CQS / Formation et 1. Education and Training sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-16 2018-08-23 2018-09-13 2018-10-13 accompagnement des for Employability qualifications des d'exécution candidats au niveau de consultants Kati ML-PROCEJ-52820-CS- Sélection fondée CQS / Formation et 3. Institutional sur les En attente accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 qualifications des d'exécution candidats au niveau de Management consultants Niono ML-PROCEJ-52823-CS- Sélection fondée CQS / Formation et 3. Institutional sur les En attente accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 qualifications des d'exécution candidats au niveau de Management consultants Sévaré ML-PROCEJ-51983-CS- Sélection fondée CQS / Formation et 1. Education and Training sur les En attente accompagnement des IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-19 2018-08-09 2018-08-16 2018-08-30 2018-09-29 for Employability qualifications des d'exécution candidats au niveau de consultants Kayes Page 5 ML-PROCEJ-53084-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-16 2018-08-23 2018-09-06 2018-10-06 candidats au niveau de la Creation for Youth qualifications des d'exécution commune IV du District de consultants Bamako ML-PROCEJ-52824-CS- Sélection fondée CQS / Formation et 3. Institutional sur les En attente accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 qualifications des d'exécution candidats au niveau de la Management consultants commune I Bamako ML-PROCEJ-53059-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 candidats au niveau de la Creation for Youth qualifications des d'exécution commune II et III du consultants District de Bamako ML-PROCEJ-52601-CS- Sélection fondée CQS / Formation et 3. Institutional sur les En attente accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 qualifications des d'exécution candidats au niveau de Management consultants Ségou ML-PROCEJ-52785-CS- Sélection fondée 3. Institutional CQS / Formation et sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 accompagnement des qualifications des d'exécution Management candidats au niveau de consultants San ML-PROCEJ-53087-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 candidats au niveau de la Creation for Youth qualifications des d'exécution commune V du District de consultants Bamako ML-PROCEJ-52606-CS- Sélection fondée CQS / Formation et 2. Private-Sector led Job sur les En attente accompagnement des IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 Creation for Youth qualifications des d'exécution candidats au niveau de consultants Bougouni ML-PROCEJ-53550-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-19 2018-08-09 2018-08-16 2018-08-28 2018-09-27 candidats au niveau de la Creation for Youth qualifications des d'exécution commune VI du District de consultants Bamako ML-PROCEJ-52633-CS- Sélection fondée CQS / Formation et 2. Private-Sector led Job sur les En attente accompagnement des IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-16 2018-08-23 2018-09-13 2018-10-13 Creation for Youth qualifications des d'exécution candidats au niveau de consultants Koulikoro ML-PROCEJ-51986-CS- Sélection fondée CQS / Formation et 1. Education and Training sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 accompagnement des for Employability qualifications des d'exécution candidats au niveau de consultants Kita ML-PROCEJ-52603-CS- Sélection fondée CQS / Formation et 2. Private-Sector led Job sur les En attente accompagnement des IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-13 2018-10-13 Creation for Youth qualifications des d'exécution candidats au niveau de consultants Koutiala ML-PROCEJ-52605-CS- Sélection fondée CQS / Formation et 2. Private-Sector led Job sur les En attente accompagnement des IDA / 55130 A posteriori Open - National 0.00 2018-07-05 2018-07-26 2018-08-23 2018-08-30 2018-09-20 2018-10-20 Creation for Youth qualifications des d'exécution candidats au niveau de consultants Sikasso ML-PROCEJ-52623-CS-LCS Sélection fondée / Service de contrôle des 3. Institutional sur les En attente travaux de Réhabilitation IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-05-30 2018-06-13 2018-06-27 2018-07-04 2018-07-16 2019-01-12 qualifications des d'exécution des locaux du CFP Management consultants Missabougou ML-PROCEJ-52776-CS-LCS / Service de contrôle des Sélection fondée travaux de 3. Institutional sur les En attente réhabilitation/aménagement IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-06-04 2018-06-25 2018-08-08 2018-09-07 2018-10-12 2019-04-10 qualifications des d'exécution des locaux du centre de Management consultants formation Agro-alimentaire de Ségou ML-PROCEJ-53046-CS- CDS / Assistance en Sélection fondée 3. Institutional matière de communication sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-10-15 2018-10-29 2018-11-19 2018-11-26 2018-12-10 2019-12-05 institutionnelle, interne et qualifications des d'exécution Management opérationnelle (Firme de consultants communication) ML-PROCEJ-78516-CS- Sélection fondée 3. Institutional CQS / formation sur les En attente IDA / H9710 Strengthening and Project A posteriori Open - National 0.00 2018-10-16 2018-10-30 2018-11-20 2018-11-27 2019-01-03 2019-07-02 décentralisée de courte qualifications des d'exécution Management durée dans la région de consultants Kidal ML-PROCEJ-78517-CS- Sélection fondée 3. Institutional CQS / Formation sur les En attente IDA / H9710 Strengthening and Project A posteriori Open - National 0.00 2018-10-28 2018-11-11 2018-12-02 2018-12-09 2018-12-23 2019-01-22 décentralisée de courte qualifications des d'exécution Management durée dans le cercle consultants d'Ansongo Page 6 ML-PROCEJ-87497-CS- CQS / Suivi des projets Sélection fondée financés et garantis par le 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2018-11-25 2018-12-09 2018-12-30 2019-01-06 2019-01-20 2019-02-19 FARE dans le cadre de la Creation for Youth qualifications des d'exécution compétitions des plans consultants d'affaires ML-PROCEJ-87499-CS- CQS / Réalisation d'une Sélection fondée 3. Institutional cartographie des micros, sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2018-12-02 2018-12-16 2018-12-30 2019-01-06 2019-01-20 2019-07-19 petites et moyennes qualifications des d'exécution Management entreprises par type au consultants Mali ML-PROCEJ-93996-CS- Sélection fondée 3. Institutional CQS / Etudes sur les En attente IDA / H9710 Strengthening and Project A posteriori Open - National 0.00 2019-02-28 2019-03-14 2019-04-04 2019-04-11 2019-04-23 2019-10-20 architecturales de l'IFP de qualifications des d'exécution Management Bankass consultants ML-PROCEJ-94203-CS- CQS / Suivi et Sélection fondée accompagnement des jeunes 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-04-02 2019-04-16 2019-04-30 2019-05-04 2019-05-15 2019-11-11 bénéficiaires de financement Creation for Youth qualifications des d'exécution complémentaire dans le consultants cadre de la 3ème vague ML-PROCEJ-94222-CS- Sélection fondée CQS / Formation en 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 élaboration de PA des Creation for Youth qualifications des d'exécution jeunes sélectionnes des consultants CPA . ML-PROCEJ-94229-CS- Sélection fondée CQS / Suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-06-22 accompagnement des jeunes Creation for Youth qualifications des d'exécution primés (CPA 2) consultants ML-PROCEJ-94235-CS- Sélection fondée CQS / Suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-06-22 accompagnement des jeunes Creation for Youth qualifications des d'exécution primés (CPA 3) consultants ML-PROCEJ-94237-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-06-22 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaire des jeunes de consultants Koulikoro. ML-PROCEJ-94241-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-06-22 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaire des jeunes à consultants Sikasso . ML-PROCEJ-94242-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-06-22 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaires des jeunes de consultants Ségou ML-PROCEJ-94244-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaire des jeunes de consultants Mopti ML-PROCEJ-94246-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaires des jeunes à consultants Tombouctou ML-PROCEJ-94247-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaire des jeunes à Kidal consultants (CECI) ML-PROCEJ-94248-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaires des jeunes Kidal consultants (CECI) ML-PROCEJ-94256-CS- Sélection fondée CQS / suivi- 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-02-12 2019-02-26 2019-03-12 2019-03-16 2019-03-24 2019-04-23 accompagnement des plans Creation for Youth qualifications des d'exécution d'affaires des jeunes à consultants Bamako (CECI) ML-PROCEJ-94279-CS- CQS / Recrutement d'une 3. Institutional firme pour la gestion des Sélection fondée Open - En attente IDA / 55130 Strengthening and Project A posteriori 0.00 2019-10-15 2019-10-30 2019-11-27 2019-12-11 2019-12-25 2020-01-01 2020-01-29 2021-01-28 fonds à couts partagés et sur la qualité International d'exécution Management compétition des plans d'affaires . CS-REF-7 / Avenant au contrat pour les études Sélection fondée architecturales 1. Education and Training sur les IDA / 55130 A posteriori Open - National 0.00 Annulé 2017-01-28 2017-02-11 2017-03-04 2017-03-11 2017-04-01 2017-09-28 (aménagement et rénovation for Employability qualifications des des locaux) du CFP de consultants Banankabougou CS-REF-10 / Avenant au contrat pour les Etudes Sélection fondée 3. Institutional architecturales sur les IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 Annulé 2017-01-28 2017-02-18 2017-04-03 2017-05-03 2017-06-07 2017-12-04 (aménagement et rénovation qualifications des Management des locaux) du CFP de consultants Ségou CS-REF-16 / Avenant au Sélection fondée contrat pour l'Etude 1. Education and Training sur les architecturale IDA / 55130 A posteriori Open - National 0.00 Annulé 2017-07-16 2017-07-30 2017-08-13 2017-08-20 2017-09-03 2017-10-03 for Employability qualifications des (aménagement et rénovation consultants des locaux) Missabougou Page 7 ML-PROCEJ-52803-CS- CQS / Assistance technique Sélection fondée 3. Institutional Mise en place d'un cadre sur les IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 Annulé 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2020-01-09 reglementaire pour la qualifications des Management promotion de la formation consultants par alternance ML-PROCEJ-52624-CS- Sélection fondée CQS / Etudes 3. Institutional sur les architecturales IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 Annulé 2018-03-28 2018-04-18 2018-06-01 2018-07-01 2018-08-05 2019-02-01 qualifications des (aménagement et rénovation Management consultants des locaux) IFP de Bankass ML-PROCEJ-53056-CS- Sélection fondée CQS / Suivi- 2. Private-Sector led Job sur les IDA / 55130 A posteriori Open - National 0.00 Annulé 2018-07-05 2018-07-26 2018-09-08 2018-10-08 2018-11-12 2019-05-11 accompagnement des plans Creation for Youth qualifications des d'affaires des jeunes consultants ML-PROCEJ-52608-CS- Sélection fondée 3. Institutional CQS / Evaluation de l'offre sur les IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 Annulé 2019-04-10 2019-04-24 2019-05-22 2019-05-29 2019-06-12 2019-07-12 de formation et des besoins qualifications des Management sur l'ensemble du Mali consultants ML-PROCEJ-52789-CS- CQS / Formation à la mise Sélection fondée 3. Institutional en œuvre locale de la sur les IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 Annulé 2019-05-15 2019-05-30 2019-06-07 2019-06-14 2019-06-28 2019-07-28 formation (autonomisation qualifications des Management des centres) au compte de consultants la DNETP ML-PROCEJ-77207-CS- QCBS / Renforcement des compétences techniques des enseignants et formateur 3. Institutional Sélection fondée des IFP de Kalaban-coro, Open - IDA / 55130 Strengthening and Project A priori sur la qualité et 0.00 Annulé 2018-10-10 2018-10-24 2018-11-07 2018-12-07 2018-12-21 2019-01-11 2019-02-01 2019-07-11 IFSAB, Ségou , Bankass et International Management le coût Missabougou (Les filières de formation concernées sont le BTP, l'agroalimentaire et les peaux/cuir) ML-PROCEJ-94077-CS- CQS / Formation des Sélection fondée agents de la DNFP et des 3. Institutional sur les En attente directeurs régionaux de la IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2019-04-25 2019-05-10 2019-05-24 2019-05-31 2019-06-24 2019-07-24 qualifications des d'exécution formation professionnelle Management consultants sur le thème responsable du dispositif de formation ML-PROCEJ-94295-CS- Sélection fondée INDV / formation et 3. Institutional sur les En attente l'accompagnement des IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2019-06-16 2019-06-30 2019-07-14 2019-07-21 2019-08-04 2019-09-03 qualifications des d'exécution lauréats 3ème vague dans Management consultants la région de Koulikoro ML-PROCEJ-100463-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-06-17 2019-07-01 2019-07-15 2019-07-22 2019-08-05 2019-09-04 lauréats 3ème vague dans Creation for Youth qualifications des d'exécution le cadre de la CPA du consultants District de Bamako ML-PROCEJ-100466-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-06-17 2019-07-01 2019-07-15 2019-07-22 2019-08-05 2019-09-04 lauréats 3ème vague dans Creation for Youth qualifications des d'exécution le cadre de la CPA dans la consultants région de Kayes ML-PROCEJ-100472-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-06-17 2019-07-01 2019-07-15 2019-07-22 2019-08-05 2019-09-04 lauréats 3ème vague dans Creation for Youth qualifications des d'exécution le cadre de la CPA dans la consultants région de Sikasso ML-PROCEJ-100469-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente IDA / 55130 A posteriori Open - National 0.00 2019-06-17 2019-07-01 2019-07-15 2019-07-22 2019-08-05 2019-09-04 lauréats 3ème vague dans Creation for Youth qualifications des d'exécution le cadre de la CPA dans la consultants région de Ségou ML-PROCEJ-93999-CS- CQS / Suivi de l'insertion Sélection fondée 3. Institutional des sortants dans le cadre sur les En attente IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2019-05-02 2019-05-16 2019-06-06 2019-06-13 2019-06-21 2019-07-21 du programme décentralisé qualifications des d'exécution Management dans les zones de Bamako, consultants kayes, Sikasso et Ségou ML-PROCEJ-100473-CS- CQS / Formation et Sélection fondée accompagnement des 2. Private-Sector led Job sur les En attente lauréats 3ème vague dans IDA / 55130 A posteriori Open - National 0.00 2019-06-18 2019-07-02 2019-07-16 2019-07-23 2019-08-06 2019-09-05 Creation for Youth qualifications des d'exécution le cadre de la CPA dans la consultants région de Mopti et tombouctou ML-PROCEJ-111025-CS- Sélection fondée CQS / suivi et insertion 3. Institutional sur les En attente des sortants dans le cadre IDA / 55130 Strengthening and Project A posteriori Open - National 0.00 2019-05-20 2019-06-03 2019-06-17 2019-06-24 2019-07-12 2019-08-11 qualifications des d'exécution du programme Management consultants d'apprentissage alterné INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Page 8 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Formation en 3. Institutional En attente Building Information IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-24 2017-10-22 2017-10-29 2017-11-12 2017-12-12 d'exécution Managment BIM Management 3. Institutional CS-REF-2 / Formation en En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-27 2017-09-22 2017-09-29 2017-10-13 2017-10-27 pédagogie universitaire d'exécution Management CS-REF-3 / Assistance technique Mise en place 3. Institutional En attente d'un cadre reglementaire IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-20 2017-10-23 2017-10-30 2017-11-13 2017-12-13 d'exécution pour la promotion de la Management formation par alternance CS-REF-4 / Etude de dimensionnement du Centre 3. Institutional En attente de formation mines et IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-03 2017-10-01 2017-10-08 2017-10-22 2017-11-21 d'exécution services auxilliaires de Management Bougouni ou Keniéba CS-REF-6 / Elaboration des curricula et modules de formation (Centre de 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-02-11 2017-04-01 2017-04-22 2017-05-27 2017-11-23 formation mines et services for Employability d'exécution auxilliaires de Bougouni ou Keniéba) CS-REF-9 / Elaboration 3. Institutional des curricula et modules de En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-17 2017-10-15 2017-10-22 2017-11-05 2017-12-05 formation pour l'IFP de d'exécution Management Bankass CS-REF-11 / Elaboration 3. Institutional En cours des curricula et modules de IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-22 2017-09-17 2017-09-24 2017-10-08 2017-11-07 d'examen formation (Ségou) Management CS-REF-13 / Elaboration des curricula et modules de 3. Institutional formation pour le Centre En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-20 2017-10-19 2017-10-26 2017-11-09 2017-12-09 de Formation d'exécution Management Professionnelle de Kalaban -coro (IFP Kalabancoro) CS-REF-15 / Formation 3. Institutional En attente technique des enseignants IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-10 2017-10-06 2017-10-13 2017-10-27 2017-11-03 d'exécution et formateur Management CS-REF-17 / formation des 1. Education and Training En attente formateurs et gestionnaires IDA / 55130 A posteriori Individuel Open 0.00 2017-06-11 2017-07-09 2017-07-16 2017-07-30 2017-08-29 for Employability d'exécution du centre 3. Institutional CS-REF-21 / Elaboration En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-10 2017-10-06 2017-10-13 2017-10-27 2017-11-26 des supports de formation d'exécution Management CS-REF-22 / Formation en 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-09-03 2017-09-29 2017-10-06 2017-10-20 2017-11-19 entreprenariat for Employability d'exécution CS-REF-23 / Formation de 1. Education and Training En attente perfectionnement en IDA / 55130 A posteriori Individuel Open 0.00 2017-08-28 2017-09-23 2017-09-30 2017-10-14 2017-11-13 for Employability d'exécution ménuiserie aluminium CS-REF-24 / Formation de perfectionnement en 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-08-27 2017-09-22 2017-09-29 2017-10-13 2017-11-12 mécanique des engins à for Employability d'exécution deux roues CS-REF-25 / Formation de 3. Institutional En attente perfectionnement en froid IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-28 2017-09-25 2017-10-02 2017-10-16 2017-11-15 d'exécution climatisation Management CS-REF-26 / Formation de 3. Institutional perfectionnement en En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-12 2017-10-08 2017-10-15 2017-10-29 2017-11-28 réparation des équipements d'exécution Management électroniques numériques CS-REF-27 / Foramtion de 3. Institutional En attente perfectionnement en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-06-14 2017-07-12 2017-07-19 2017-08-02 2017-09-01 d'exécution ménuiserie ébénisterie Management CS-REF-28 / Formation de perfectionnement en diagnostic et réparation de 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-06-14 2017-07-12 2017-07-19 2017-08-02 2017-09-01 système d'allumage et for Employability d'exécution d'alimentation électroniques des véhicules CS-REF-29 / Formation de perfectionnment en 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-08-27 2017-09-22 2017-09-29 2017-10-13 2017-11-12 équipement électronique for Employability d'exécution numeriques CS-REF-30 / Formation de 3. Institutional perfectionnment en En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-07-23 2017-08-20 2017-08-27 2017-09-10 2017-10-10 transformation d'exécution Management agroalimentaire CS-REF-31 / Formation de 1. Education and Training En attente perfectionnment en staff- IDA / 55130 A posteriori Individuel Open 0.00 2017-09-03 2017-09-29 2017-10-06 2017-10-20 2017-11-19 for Employability d'exécution platrerie Page 9 CS-REF-32 / Formation de 3. Institutional En attente perfectionnment en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-17 2017-10-13 2017-10-20 2017-11-03 2017-12-03 d'exécution ferronnerie Management CS-REF-33 / Formation de 3. Institutional perfectionnment en En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-19 2017-10-17 2017-10-24 2017-11-07 2017-12-07 fabrication de materiel d'exécution Management agricole CS-REF-34 / Elaboration 3. Institutional En attente des curricula et modules de IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-11-17 2017-12-20 2017-12-27 2018-01-10 2018-02-09 d'exécution formation Management CS-REF-35 / Elaboration 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-05-04 2017-06-01 2017-06-08 2017-06-22 2017-07-22 des supports de formation for Employability d'exécution CS-REF-37 / Formation 1. Education and Training En attente des animateurs et chargés IDA / 55130 A posteriori Individuel Open 0.00 2017-07-31 2017-08-28 2017-09-04 2017-09-16 2017-10-16 for Employability d'exécution de projet (Alphabétisation) CS-REF-38 / Formation 3. Institutional En attente technique complémentaire IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-30 2017-09-27 2017-10-04 2017-10-18 2017-11-17 d'exécution des jeunes Management CS-REF-39 / Recrutement 2. Private-Sector led Job En attente facilitateur pour formation IDA / 55130 A posteriori Individuel Open 0.00 2017-04-23 2017-06-11 2017-07-02 2017-08-06 2018-02-02 Creation for Youth d'exécution des formateurs CS-REF-42 / Formation Réaliser l'audit technique 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-07-30 2017-08-27 2017-09-03 2017-09-17 2017-10-17 d'un organisme de for Employability d'exécution formation professionnelle CS-REF-45 / Formation 3. Institutional En attente des points focaux et équipe IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-15 2017-09-12 2017-09-17 2017-09-29 2017-10-06 d'exécution UCP sur Excel Management CS-REF-46 / Etude sur l'identifcation des filières 3. Institutional En attente porteuses d'emplois et leurs IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-07-20 2017-09-07 2017-09-28 2017-11-02 2018-05-01 d'exécution chaines de Management valeurs/document méthodologique (ONEF) CS-REF-49 / Formation 3. Institutional sur informatique (ACCES, En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-03 2017-10-01 2017-10-08 2017-10-22 2017-11-21 ORACLE, MS Project) pour d'exécution Management le compte de la DNETP CS-REF-50 / Formation en accompagnement des agents 1. Education and Training En attente chargés du suivi-évaluation IDA / 55130 A posteriori Individuel Open 0.00 2017-08-06 2017-09-03 2017-09-10 2017-09-24 2017-10-24 for Employability d'exécution de l'insertion des sortants 1 au compte de la DNETP CS-REF-51 / Elaboration 3. Institutional des outils de suivi des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-08-24 2017-09-19 2017-09-26 2017-10-10 2017-11-09 sortants au compte de la d'exécution Management DNETP CS-REF-54 / Formateur pour la formation des agents de la Direction Nationale de la Formation 1. Education and Training En attente Professionnelle sur le IDA / 55130 A posteriori Individuel Open 0.00 2017-07-10 2017-08-05 2017-08-12 2017-08-26 2017-09-25 for Employability d'exécution module élaboration et construction des outils dans le cadre de la démarche qualité et d’évaluation CS-REF-55 / Formation sur réaliser l'audit 3. Institutional En attente technique d'un organisme IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-07-11 2017-08-08 2017-08-15 2017-08-29 2017-09-28 d'exécution de formation professionnelle Management au compte de la DNFP CS-REF-58 / Recrutement 3. Institutional En attente d'un assistant en passation IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-09-03 2017-10-01 2017-10-08 2017-10-22 2017-11-21 d'exécution des marchés Management CS-REF-59 / Evaluation 3. Institutional En attente d'impact du Programme IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2017-07-15 2017-09-02 2017-09-23 2017-10-28 2018-04-26 d'exécution d'Insertion Management CS-REF-53 / Formation en Gestion Axée sur les Résultants des assistants et de l'informaticien du STP- 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2017-07-10 2017-08-05 2017-08-12 2017-08-26 2017-09-25 CSSP, des conseiller for Employability d'exécution technques, chargés de mission et de la DFM du MPISP CS-REF-47 / Assistance 1. Education and Training En attente technique pour le compte IDA / 55130 A posteriori Individuel Open 0.00 2018-03-20 2018-04-15 2018-04-22 2018-05-06 2018-06-05 for Employability d'exécution du FAFPA ML-PROCEJ-53565-CS- 3. Institutional En attente INDV / Formation du IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-04-10 2018-05-06 2018-05-13 2018-05-17 2018-06-16 d'exécution personnel administratif des Management CFP ML-PROCEJ-53097-CS- 3. Institutional INDV / Réalisation des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-02-15 2018-04-05 2018-04-26 2018-05-31 2018-06-30 notices et études d'impact d'exécution Management Environemental et social Page 10 ML-PROCEJ-52857-CS- INDV / Recrutement d'un 1. Education and Training En attente assistant en Gestion IDA / 55130 A posteriori Individuel Open 0.00 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 for Employability d'exécution Financière au compte du FAFPA ML-PROCEJ-53094-CS- INDV / Assistance en Suivi 1. Education and Training En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 Evaluation au compte du for Employability d'exécution FAFPA ML-PROCEJ-52639-CS- INDV / Recrutement d'un 1. Education and Training En attente assistant en passation de IDA / 55130 A posteriori Individuel Open 0.00 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2019-02-09 for Employability d'exécution marchés au compte du FAFPA ML-PROCEJ-52793-CS- INDV / Formation des agents de la Direction Nationale de la Formation 3. Institutional En attente Professionnelle sur le IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-07-10 2018-08-28 2018-09-18 2018-10-23 2018-11-22 d'exécution module élaboration et Management construction des outils dans le cadre de la démarche qualité et d’évaluation des projets ML-PROCEJ-52778-CS- INDV / Formation sur la 3. Institutional En attente conception et la IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-03-10 2018-04-28 2018-05-19 2018-06-23 2018-07-23 d'exécution planification stratégique des Management programmes des cadres de la CPS ML-PROCEJ-53114-CS- 3. Institutional INDV / Formation sur la En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-05-15 2018-07-03 2018-07-24 2018-08-28 2018-09-27 gestion des risques des d'exécution Management projets pour les cadres ML-PROCEJ-53110-CS- 3. Institutional INDV / Formation des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-02-03 2018-03-01 2018-03-08 2018-03-22 2018-04-21 agents sur le Logiciel d'exécution Management TOMPRO en Tom Monitoring ML-PROCEJ-52825-CS- INDV / Formation de 3. Institutional perfectionnement des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-05-16 2018-07-04 2018-07-25 2018-08-15 2018-09-14 formateurs au compte du d'exécution Management CMA-SIK dans le cadre du fonds compétitif ML-PROCEJ-52829-CS- INDV / Formation de perfectionnement des 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-07-04 2018-07-25 2018-08-22 2018-09-21 formateurs au compte du Creation for Youth d'exécution DMTK dans le cadre du fonds compétitif ML-PROCEJ-53563-CS- INDV / Formation en 2. Private-Sector led Job En attente gestion de l'APC au compte IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-06-11 2018-06-16 2018-06-20 2018-07-20 Creation for Youth d'exécution de l'ITAS-KADIOLO dans le cadre du fonds compétitif ML-PROCEJ-52611-CS- INDV / Formation en APC 2. Private-Sector led Job En attente au compte de l'ITAS- IDA / 55130 A posteriori Individuel Open 0.00 2018-06-11 2018-07-30 2018-08-20 2018-09-24 2018-10-24 Creation for Youth d'exécution KADIOLO dans le cadre du fonds compétitif ML-PROCEJ-53125-CS- INDV / Formation en gestion des outils 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-06-18 2018-06-25 2018-07-16 2018-08-15 pédagogiques au compte de Creation for Youth d'exécution l'ITAS-KADIOLO dans le cadre du fonds compétitif ML-PROCEJ-51992-CS- INDV / Formation de perfectionnement des 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-07-04 2018-07-25 2018-08-29 2019-02-25 formateurs au compte de Creation for Youth d'exécution l'IF-FN dans le cadre du fonds compétitif ML-PROCEJ-52001-CS- INDV / Formation de perfectionnement des 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-07-04 2018-07-25 2018-08-29 2019-02-25 formateurs au compte de Creation for Youth d'exécution CFM-MTK dans le cadre du fonds compétitif ML-PROCEJ-53584-CS- INDV / Formation du 1. Education and Training En attente personnel en APC au IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-06-11 2018-06-18 2018-06-25 2018-07-25 for Employability d'exécution compte de EFAP-KOLON dans le cadre du fonds compétitif ML-PROCEJ-52874-CS- INDV / Formation de perfectionnement des 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2018-05-16 2018-06-18 2018-06-25 2018-07-09 2018-08-08 formateurs au compte de Creation for Youth d'exécution l'UFTI dans le cadre du fonds compétitif ML-PROCEJ-52581-CS- CDS / Etude de 3. Institutional En attente dimensionnement du Centre IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-05-29 2018-06-24 2018-07-01 2018-07-12 2018-08-11 d'exécution de formation mines et Management services auxilliaires des IFP Page 11 ML-PROCEJ-61697-CS- INDV / Réalisation d'une étude d'impact 3. Institutional En attente environnemental et social IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-06-30 2018-07-26 2018-08-02 2018-08-16 2018-09-15 d'exécution du projet d'implantation de Management filière cuirs et peaux à l'IFP de Kalaban-coro ML-PROCEJ-61702-CS- 3. Institutional En cours INDV / Audit IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-06-29 2018-08-01 2018-08-08 2018-08-22 2018-09-21 d'examen environnemental et social Management du PROCEJ ML-PROCEJ-52818-CS- 3. Institutional En attente CDS / Elaboration des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-08-20 2018-09-15 2018-09-22 2018-10-03 2019-01-01 d'exécution curricula et modules de Management formation ML-PROCEJ-67044-CS- 3. Institutional INDV / Elaboration des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-07-16 2018-08-11 2018-08-15 2018-08-29 2018-09-28 documents législatifs de la d'exécution Management charte des PME ML-PROCEJ-87502-CS- 3. Institutional INDV / Recrutement d'un En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-12-03 2018-12-29 2019-01-02 2019-01-10 2020-01-10 assistant technique du d'exécution Management coordinateur ML-PROCEJ-87506-CS- INDV / Formation en 3. Institutional En attente gestion administrative et IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2018-12-09 2019-01-04 2019-01-11 2019-01-19 2019-02-03 d'exécution financière selon la Management procédure de la Banque mondiale ML-PROCEJ-89931-CS- INDV / Formation en passation des marchés des 3. Institutional En attente agents des structures IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-01-20 2019-02-11 2019-02-14 2019-02-21 2019-03-08 d'exécution d'exécution et les points Management focaux sur les procédures de la Banque mondiale CS-REF-18 / Formation 1. Education and Training En attente pédagogique des artisans et IDA / 55130 A posteriori Individuel Open 0.00 2019-08-29 2019-09-24 2019-10-01 2019-10-15 2019-11-14 for Employability d'exécution exploitants ML-PROCEJ-93993-CS- INDV / Evaluation des coûts des équipements et 1. Education and Training En attente des réaménagements des IDA / 55130 A posteriori Individuel Open 0.00 2019-03-27 2019-05-01 2019-05-05 2019-05-13 2019-06-12 for Employability d'exécution bâtiments du CFP de Bankass au compte de la DNETP CS-REF-14 / Formation 1. Education and Training En attente des formateurs et IDA / 55130 A posteriori Individuel Open 0.00 2019-03-20 2019-04-17 2019-04-24 2019-05-11 2019-06-10 for Employability d'exécution gestionnaires des centres ML-PROCEJ-94085-CS- 3. Institutional INDV / Formation sur En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-05-20 2019-06-15 2019-06-20 2019-06-30 2019-07-07 (Réaliser l'Audit d'un d'exécution Management organisme de formation professionnelle) ML-PROCEJ-94196-CS- INDV / Formation de 3. Institutional En attente perfectionnement des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-02-15 2019-03-15 2019-03-19 2019-03-27 2019-06-25 d'exécution Maitres d'apprentissage au Management compte du FAFPA ML-PROCEJ-94199-CS- 3. Institutional En attente INDV / Evaluation des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-02-21 2019-03-21 2019-03-25 2019-04-02 2019-05-02 d'exécution sortants du secteur formel Management ML-PROCEJ-94273-CS- 3. Institutional INDV / Elaboration des En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-02-25 2019-03-25 2019-03-29 2019-04-06 2019-05-06 notices d'impact d'exécution Management environnemental et social ML-PROCEJ-94289-CS- 3. Institutional INDV / formation en En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-03-05 2019-04-02 2019-04-06 2019-04-14 2019-05-14 gestion des projets et d'exécution Management programmes de développement . ML-PROCEJ-94292-CS- 3. Institutional INDV / Etude En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-02-20 2019-03-20 2019-03-24 2019-04-01 2019-05-01 d'indentification des PME d'exécution Management par type (MPME) au Mali/cartographie . ML-PROCEJ-94297-CS- 3. Institutional INDV / formation sur les En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-02-15 2019-03-15 2019-03-19 2019-03-27 2019-04-26 outils de suivi et de d'exécution Management mesure de la performance des projets ML-PROCEJ-53538-CS- 3. Institutional INDV / Formation en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-04-18 2018-05-14 2018-05-21 2018-05-25 2018-06-24 Building Information Management Managment BIM ML-PROCEJ-52580-CS- 3. Institutional INDV / Formation en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-05-16 2018-07-04 2018-07-25 2018-08-29 2019-02-25 pédagogie universitaire Management ML-PROCEJ-53540-CS- 3. Institutional INDV / Formation IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-04-10 2018-05-06 2018-05-08 2018-05-12 2018-06-11 technique des enseignants Management et formateur Page 12 ML-PROCEJ-52568-CS- 3. Institutional INDV / formation des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-06-11 2018-07-30 2018-08-20 2018-09-24 2019-03-23 formateurs et gestionnaires Management du centre ML-PROCEJ-52584-CS- 3. Institutional INDV / Formation IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2019-03-13 2019-04-08 2019-04-15 2019-04-29 2019-05-29 pédagogique des Management enseignants (utilisation des PE) ML-PROCEJ-52850-CS- 3. Institutional INDV / Formation des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-05-30 2018-07-18 2018-08-08 2018-09-12 2018-10-12 animateurs et chargés de Management projet ML-PROCEJ-52781-CS- 3. Institutional INDV / Elaboration des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-04-02 2018-05-21 2018-06-11 2018-07-16 2019-01-12 supports de formation Management ML-PROCEJ-51976-CS- INDV / Formation en 1. Education and Training IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2019-02-05 2019-03-10 2019-03-17 2019-03-31 2019-04-30 entreprenariat au compte for Employability de l'APEJ ML-PROCEJ-53113-CS- INDV / Formation de 1. Education and Training IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2018-10-27 perfectionnement en for Employability ménuiserie aluminium ML-PROCEJ-53098-CS- INDV / Formation de 2. Private-Sector led Job perfectionnement en IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2018-10-27 Creation for Youth mécanique des engins à deux roues ML-PROCEJ-52594-CS- INDV / Formation de 1. Education and Training IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2019-03-26 perfectionnement en froid for Employability climatisation ML-PROCEJ-53556-CS- INDV / Formation de 3. Institutional perfectionnement en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-07-10 2018-07-15 2018-07-19 2018-08-18 réparation des équipements Management électroniques numériques ML-PROCEJ-52600-CS- INDV / Foramtion de 1. Education and Training IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2019-03-26 perfectionnement en for Employability ménuiserie ébénisterie ML-PROCEJ-51881-CS- INDV / Formation de perfectionnement en 1. Education and Training diagnostic et réparation de IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2019-03-26 for Employability système d'allumage et d'alimentation électroniques des véhicules ML-PROCEJ-53091-CS- INDV / Formation de 3. Institutional perfectionnment en IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2018-10-27 équipement électronique Management numeriques ML-PROCEJ-52630-CS- INDV / Formation de 2. Private-Sector led Job perfectionnment en IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2018-10-12 Creation for Youth transformation agroalimentaire ML-PROCEJ-53052-CS- 3. Institutional INDV / Formation de IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2018-10-27 perfectionnment en staff- Management platrerie ML-PROCEJ-53580-CS- INDV / Formation de 1. Education and Training IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-07-10 2018-07-17 2018-07-24 2018-08-23 perfectionnment en for Employability ferronnerie ML-PROCEJ-53560-CS- INDV / Formation de 2. Private-Sector led Job perfectionnment en IDA / 55130 A posteriori Individuel Open 0.00 Annulé 2018-06-14 2018-07-10 2018-07-17 2018-07-21 2018-08-20 Creation for Youth fabrication de materiel agricole ML-PROCEJ-52787-CS- 3. Institutional INDV / Formation des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-03-20 2018-05-08 2018-05-29 2018-07-03 2018-08-02 points focaux et équipe Management UCP sur Excel ML-PROCEJ-51988-CS- INDV / Formation sur 3. Institutional informatique (ACCES, IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2019-02-28 2019-03-26 2019-04-02 2019-04-16 2019-05-16 ORACLE, MS Project) pour Management le compte de la DNETP ML-PROCEJ-53105-CS- INDV / Formation en 3. Institutional accompagnement des agents IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-03-21 2018-05-09 2018-05-30 2018-07-04 2018-08-03 chargés du suivi-évaluation Management de l'insertion des sortants 1 au compte de la DNETP Page 13 ML-PROCEJ-53544-CS- 3. Institutional INDV / Elaboration des IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-05-03 2018-05-29 2018-05-31 2018-06-04 2018-07-04 outils de suivi des sortants Management au compte de la DNETP ML-PROCEJ-52835-CS- INDV / Formation en Gestion Axée sur les 3. Institutional Résultants des assistants et IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 Annulé 2018-03-10 2018-04-28 2018-05-19 2018-06-23 2018-07-23 de l'informaticien du STP- Management CSSP, des conseiller techniques, chargés de mission et de la DFM du MPISP ML-PROCEJ-93992-CS- INDV / Assistance pour la mise en place d'un nouveau 2. Private-Sector led Job En attente IDA / 55130 A posteriori Individuel Open 0.00 2019-02-20 2019-03-27 2019-04-03 2019-04-14 2019-05-14 modèle de gestion dans les Creation for Youth d'exécution 5 IFP-CFP public appuyés par le PROCEJ ML-PROCEJ-94218-CS- CQS / Recrutement d'un 2. Private-Sector led Job En attente Facilitateur pour la IDA / 55130 A posteriori Individuel Open 0.00 2019-03-17 2019-04-12 2019-04-19 2019-04-30 2019-05-30 Creation for Youth d'exécution formation des formateurs CECI . ML-PROCEJ-111029-CS- 3. Institutional INDV / recrutement d'un En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-05-30 2019-06-27 2019-07-04 2019-07-18 2019-08-17 auditeur interne au compte d'exécution Management de l'UCP ML-PROCEJ-111161-CS- CDS / Recrutement d'un Sélection de cabinet pour la gestion des 2. Private-Sector led Job En attente IDA / 55130 A posteriori consultants par Direct 0.00 2019-05-02 2019-05-12 2019-06-10 2020-06-09 fonds à coûts partagés et Creation for Youth d'exécution entente directe compétition des plans d'affaires . ML-PROCEJ-113882-CS- 3. Institutional INDV / Recrutement d'un En attente IDA / 55130 Strengthening and Project A posteriori Individuel Open 0.00 2019-05-12 2019-06-07 2019-06-12 2019-06-23 2020-06-22 comptable au compte de d'exécution Management l'UCP ML-PROCEJ-126140-CS- 2. Private-Sector led Job En attente INDV / Formation en IDA / 55130 A posteriori Individuel Open 0.00 2019-09-02 2019-09-28 2019-10-05 2019-10-14 2019-11-13 Creation for Youth d'exécution boucherie et charcuterie Page 14