PROCUREMENT PLAN (Textual Part) Project information: [Afghanistan] [Sehatmandi] [P160615] Project Implementation agency: [Ministry of Public Health] Date of the Procurement Plan: [January 1, 2018] Period covered by this Procurement Plan: [July 1, 2018 – June 30, 2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. PROCUREMENT Afghanistan : Afghanistan Sehatmandi Project PLAN General Information Country: Afghanistan Banks Approval Date of the Original Procurement Plan: 2018-01-01 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-13 Project ID: P160615 GPN Date: Project Name: Afghanistan Sehatmandi Project Loan / Credit No: IDA / D2850 Executing Agency(ies): Ministry of Public Health WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AFG/MOPH/GCMU/SEHATMAN DI/05 / Proposed implementation Component 1: Improving Service Single Stage - Two Pending Prior Request for Bids Open - International 13,348,595.94 0.00 2018-01-02 2018-01-07 2018-02-18 2018-05-03 2018-06-20 2021-06-30 of BPHS & EPHS in Khost Delivery. Envelope Implementation Province AFG/MOPH/GCMU/SEHATMAN DI/15 / Proposed implementation Component 1: Improving Service Single Stage - One Pending Prior Request for Bids Open - International 8,719,629.45 0.00 2018-01-02 2018-01-07 2018-02-18 2018-03-20 2018-06-13 2021-06-30 of BPHS & EPHS in Nimroz Delivery. Envelope Implementation Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Single Stage - One Pending DI/22 / Proposed implementation Prior Request for Bids Open - International 22,256,539.75 0.00 2017-12-03 2017-12-08 2018-01-19 2018-02-18 2018-05-23 2021-06-30 Delivery. Envelope Implementation of BPHS in Helmand Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Single Stage - One Pending DI/26 / Proposed implementation Prior Request for Bids Open - International 12,740,954.63 0.00 2018-01-02 2018-01-07 2018-02-18 2018-03-20 2018-06-13 2021-06-30 Delivery. Envelope Implementation of BPHS in Sari Pul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Single Stage - One Pending DI/16 / Proposed implementation Prior Request for Bids Open - International 22,915,150.80 0.00 2018-02-28 2018-03-05 2018-04-16 2018-04-24 2018-05-29 2021-06-30 Delivery. Envelope Implementation of BPHS in Herat Province AFG/MOPH/GCMU/SEHATMAN DI/02 / Proposed implementation Component 1: Improving Service Single Stage - One Pending Prior Request for Bids Open - International 30,073,470.49 0.00 2018-02-28 2018-03-05 2018-04-16 2018-04-26 2018-05-31 2021-06-30 of BPHS & EPHS in Ghazni Delivery. Envelope Implementation Province AFG/MOPH/GCMU/SEHATMAN DI/03 / Proposed implementation Component 1: Improving Service Single Stage - One Pending Prior Request for Bids Open - International 38,243,394.30 0.00 2018-02-28 2018-03-05 2018-04-16 2018-04-24 2018-05-29 2021-06-30 of BPHS & EPHS in Badakhshan Delivery. Envelope Implementation Province AFG/MOPH/GCMU/SEHATMAN DI/01 / Proposed implementation Component 1: Improving Service Single Stage - One Pending Prior Request for Bids Open - International 46,438,429.29 0.00 2018-02-24 2018-03-01 2018-04-12 2018-04-25 2018-05-30 2021-06-30 of BPHS & EPHS in Nangarhar Delivery. Envelope Implementation Province CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AFG/MOPH/GCMU/SEHATMAN DI/04 / Proposed implementation Component 1: Improving Service Quality And Cost- Under Prior Open - International 21,141,074.29 0.00 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Wardak Delivery. Based Selection Implementation Province AFG/MOPH/GCMU/SEHATMAN DI/06 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 14,853,570.56 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Paktia Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/07 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 17,806,174.58 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Farah Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/08 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 12,266,384.99 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Badghis Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/09 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 18,208,062.91 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Kunar Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/10 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 16,429,777.67 0.00 Under Review 2017-12-02 2018-01-09 2017-12-23 2018-01-11 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Laghman Delivery. Based Selection Province Page 1 AFG/MOPH/GCMU/SEHATMAN DI/11 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 13,944,461.74 0.00 Under Review 2017-12-03 2017-12-24 2018-01-20 2018-02-06 2018-03-06 2018-04-05 2018-05-10 2018-05-30 2021-06-30 of BPHS & EPHS in Paktiak Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/12 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 16,937,283.39 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Daikundi Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/13 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 14,868,982.39 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Logar Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/14 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 13,307,316.25 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Urozgan Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/17 / Proposed implementation Prior Open - International 22,949,462.62 0.00 Under Review 2018-01-02 2018-01-23 2018-01-20 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-14 Delivery. Based Selection of BPHS in Balkh Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/18 / Proposed implementation Prior Open - International 17,310,507.44 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2019-06-13 Delivery. Based Selection of BPHS in Kandahar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/19 / Proposed implementation Prior Open - International 14,840,606.33 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Kunduz Province AFG/MOPH/GCMU/SEHATMAN DI/20 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 22,084,909.00 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Faryab Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/21 / Proposed implementation Prior Open - International 20,459,864.95 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Takhar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/23 / Proposed implementation Prior Open - International 19,228,548.15 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Baghlan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/25 / Proposed implementation Prior Open - International 13,839,755.11 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Kabul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/27 / Proposed implementation Prior Open - International 12,399,720.86 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Jawzjan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/28 / Proposed implementation Prior Open - International 18,945,301.44 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Bamyan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/29 / Proposed implementation Prior Open - International 11,741,569.58 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Samangan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/30 / Proposed implementation Prior Open - National 8,406,533.43 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Zabul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/31 / Proposed implementation Prior Open - International 14,177,686.57 0.00 Under Review 2017-12-02 2017-12-23 2018-01-20 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Nooristan Province AFG/MOPH/GCMU/SEHATMAN DI/33 / Proposed implementation Component 1: Improving Service Quality And Cost- Under Prior Open - International 19,246,830.81 0.00 2017-12-02 2017-12-23 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of Contract Management in three Delivery. Based Selection Implementation SM provinces AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Quality And Cost- DI/24 / Proposed implementation Prior Open - International 17,435,539.85 0.00 Under Review 2017-12-06 2017-12-27 2018-02-09 2018-03-09 2018-04-08 2018-05-13 2018-06-13 2021-06-30 Delivery. Based Selection of BPHS in Ghor Province AFG/MOPH/GCMU/SEHATMAN DI/01 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 46,438,429.29 0.00 Canceled 2017-12-02 2017-12-23 2018-02-05 2018-03-05 2018-04-04 2018-05-09 2018-06-13 2021-06-30 of BPHS & EPHS in Nangarhar Delivery. Based Selection Province AFG/MOPH/GCMU/SEHATMAN DI/107 / Third Party monitoring Component 2: Strengthening the Quality And Cost- Pending and evaluation for Afghanistan IDA / D2850 Health System and its Prior Open - International 4,620,000.00 0.00 2018-05-23 2018-06-13 2018-07-27 2018-08-24 2018-09-23 2018-10-28 2018-12-15 2021-06-30 Based Selection Implementation household survey and sample Performance. registration system AFG/MOPH/GCMU/SEHATMAN DI/35_1 / Proposed Component 2: Strengthening the Quality And Cost- Pending implementation of third party IDA / D2850 Health System and its Prior Open - International 6,465,867.00 0.00 2018-05-29 2018-06-19 2018-08-02 2018-08-30 2018-09-29 2018-11-03 2018-12-01 2021-11-30 Based Selection Implementation monitoring and evaluation for Performance. BSC, HMIS verification and DQA AFG/MOPH/GCMU/SEHATMAN DI/35 / Proposed implementation Component 1: Improving Service Quality And Cost- Prior Open - International 8,461,136.00 0.00 Canceled 2018-01-07 2018-01-28 2018-03-13 2018-04-10 2018-05-10 2018-06-14 2018-07-19 2021-06-30 of Third party Monitoring and Delivery. Based Selection Evalutation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/36 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,055,923.00 0.00 2018-05-09 2018-05-19 2018-07-01 2018-12-31 Delivery. Implementation in C1 Badakhshan AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/37 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,269,220.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in C2 Badakhshan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/38 / Implementationof BPHS IDA / D2850 Prior Direct Selection Direct 2,751,424.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Baghalan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/39 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,196,070.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in C1 Bamyan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/43 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,199,814.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in C2 Bamayn Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/42 / Implementationof BPHS IDA / D2850 Prior Direct Selection Direct 1,660,417.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in C1 Ghazni Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/45 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,435,327.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Jawzjan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/44 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,278,251.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Faryab Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/46 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,855,054.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Kabul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/48 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,344,123.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Khost Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/49 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,041,679.00 0.00 2018-05-12 2018-05-22 2018-07-01 2018-12-31 Delivery. Implementation in Paktika Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/47 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,222,869.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Kandahar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/51 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,506,651.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Takhar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/50 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,669,966.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Paktya Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/52 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 565,681.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Badakhshan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/53 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 542,341.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Ghazni Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/54 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 400,829.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Khost Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/55 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 406,426.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Paktika Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/105 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 1,019,407.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Paktya Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/57 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,198,084.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Badghis Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/58 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 3,292,291.00 0.00 2018-06-10 2018-06-20 2018-07-01 2018-12-31 Delivery. Implementation in Balkh Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/59 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,924,537.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Daikundi Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/61 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,537,287.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Ghor Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/62 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 3,252,507.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Helmand Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/63 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,080,242.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Kunar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/64 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,156,843.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Kunduz Province Page 3 AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/65 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,875,857.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Laghman Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/66 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,730,003.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Logar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/67 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 4,793,207.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Nangarhar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/68 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 818,339.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Nimruz Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/69 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,769,855.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Nuristan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/70 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,715,259.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Samangan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/71 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,862,948.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Sarepul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/72 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,527,109.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Urozga n Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/73 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,635,869.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Wardak Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/74 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,231,134.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Zabul Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/75 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 542,149.00 0.00 2018-05-13 2018-05-23 2018-07-01 2018-12-31 Delivery. Implementation in Daikundi Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/76 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 513,717.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Farah Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/77 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 591,490.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Kunar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/78 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 508,056.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Laghman Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/79 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 435,730.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Logar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/80 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 1,996,576.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Nangarhar Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/81 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 439,254.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Nimruz Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/82 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 404,762.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Urozgan Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/83 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 433,577.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Wardak Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/84 / Implementation of EPHS IDA / D2850 Prior Direct Selection Direct 473,139.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation in Badghis Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/85 / Implement of Kabul Urban IDA / D2850 Prior Direct Selection Direct 1,200,000.00 0.00 2018-06-11 2018-06-21 2018-07-01 2018-12-31 Delivery. Implementation Health Project AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/60 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 2,075,612.57 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Farah Province AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/92 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 1,720,391.69 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Ghazni C2 AFG/MOPH/GCMU/SEHATMAN Component 1: Improving Service Pending DI/93 / Implementation of BPHS IDA / D2850 Prior Direct Selection Direct 3,321,102.65 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 Delivery. Implementation in Herat Province AFG/MOPH/GCMU/SEHATMAN DI/56 / Proposed implementation Component 1: Improving Service Pending IDA / D2850 Prior Direct Selection Direct 2,128,482.00 0.00 2018-05-14 2018-05-24 2018-07-01 2018-12-31 of Third party Monitoring and Delivery. Implementation Evalutation Page 4