Strengthening the National Rural Transport Program (P132750) Since this is an ongoing project, that started in April 2014, submission of a separate summary procurement plan is irrelevant at this stage. PROCUREMENT Nepal : Project for Strengthening the National Rural Transport Program PLAN General Information Country: Nepal Bank’s Approval Date of the Original Procurement Plan: 2017-10-18 2018-12-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132750 GPN Date: Project Name: Project for Strengthening the National Rural Transport Program Loan / Credit No: IDA / 53360, IDA / H8990 Executing Agency(ies): Department of Local Infrastructure Development and Agricultural Roads WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNRTP-KAN-W-NCB-10.04- UG-070-71 / Kanchanpur: Single Stage - One IDA / 53360 Prior Request for Bids Open - National 181,111.90 Signed Rajmarg-Budha- Jhaipura- Envelope Gauji-Bridhasharam Road SNRTP-ARG-W-NCB-1-16- PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 45,793.00 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Amarai Envelope Jukena Road (8 Km) SNRTP-DHA-W-NCB-6-04- PM-074-75 / Periodic Under Single Stage - One Maintenance of IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Bhimdhunga-Lamidanda- on Galchi (11 Km) SNRTP-GUL-W-NCB-8-08 - PM-074-75 / Periodic Single Stage - One Maintenance of Shantipur- IDA / 53360 Post Request for Bids Open - National 90,548.37 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Harrachaur-Olibang- Sindurghanse Road(12 Km) SNRTP-KAN-W-NCB-10-08- PM-073-74 / Periodic Pending Single Stage - One Maintenance of Bansamiti- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Pipalladi-Jonpuri-Ranipur on Road ( 10 KM) SNRTP-KAI-W-NCB-9-08-PM- Under 074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Geta- Envelope on Murkatti Road (12.60 KM) SNRTP-NAW-W-NCB-15-14- Pending PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Manjariya- Envelope on Jamuniya Road (9.00 km) SNRTP-KAP-W-NCB-11-10- PM-074-75 / Periodic Single Stage - One Maintenance of Krishnanagar- IDA / 53360 Post Request for Bids Open - National 253,899.85 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Shisirwa -Gugauli -Shivgadi Road (25Km) SNRTP-NAW-W-NCB-15-15- PM-074-75 / Periodic Under Single Stage - One Maintenance of Arunkhola- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Rakachuli-Mityal Road (11.50 on km) Page 1 SNRTP-PAR-W-NCB-18-09- PM-074-75 / Periodic Single Stage - One Maintenance of Ramghadwa- IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Jagarnathpur-Milanchowk Road (9 Km) SNRTP-PAR-W-NCB-18-13- PM-074-75 / Periodic Maintenance of Mudli -Tulsi barwa-Road (6 Km), Muldi tindubiya-sabithawa road(6 Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 km), bedhihari birta Envelope basantapur road (6 km) padamsadak-bahuwari (6km) and baghi patelchok road (9 km) SNRTP-RAS-W-NCB-20-06- Under PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Sole-Bhimali- Envelope on Hakubesi Road (5 Km) SNRTP-RAS-W-NCB-20-08- PM-074-75 / Periodic Under Single Stage - One Maintenance of Dasmure IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Seti-Devi Ma Vi. Dhuseni on Road (5 Km) SNRTP-RAU-W-NCB-21-14- PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Prempur Envelope Gonahi MHW Road (22Km) SNRTP-RAU-W-NCB-21-15- PM-074-75 / Periodic Single Stage - One Maintenance of Gamhariya IDA / 53360 Post Request for Bids Open - National 61,964.29 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Birta(BHW) Ragnapur Road (12Km) SNRTP-RAU-W-NCB-21-16- PM-074-75 / Periodic Maintenance of Sukdevchowk Single Stage - One IDA / 53360 Post Request for Bids Open - National 49,759.00 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Khesaraiya Shivnagar Road Envelope (9Km) and nahar bridge 30m, Rautahat SNRTP-SAR-W-NCB-25-08- PM-074-75 / Periodic Maintenance of Baghchaur- Single Stage - One Kotmaula-Patihalna Rural IDA / 53360 Post Request for Bids Open - National 79,114.86 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Road( Phulparasi-Simara- India Border Road) Maintenance (8 Km) SNRTP-SAR-W-NCB-25-11- PM-074-75 / Periodic Maintenance of Raniganj Single Stage - One IDA / H8990 Post Request for Bids Open - National 153,128.41 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Parwanipur Road (10 Km) Envelope Parsa Riterchor (13 km) Sarlahi SNRTP-SIR-W-NCB-26-16- PM-074-75 / Periodic Single Stage - One Maintenance of Mirchaiya IDA / 53360 Post Request for Bids Open - National 130,853.73 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Kalyanpur Siraha Road (23 km): Page 2 SNRTP-TAN-W-NCB-29-15- PM-074-75 / Periodic Under Maintenance of Bhagwati Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Rangapath (Chhirken-Maiwal- Envelope on Nabrung-Tanahunsur- Barbhanjyang ) (13 Km) SNRTP-UDA-W-NCB-30-14- PM-074-75 / Periodic Single Stage - One Maintenance of Basaha IDA / 53360 Post Request for Bids Open - National 207,377.59 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Chaudani Ranitar Road (24 Km) SNRTP-BHOJ-W-NCB-31-08- PM-074-75 / Periodic Maintenance of Taksar- Single Stage - One IDA / 53360 Post Request for Bids Open - National 149,210.76 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Gumba -Dalgaun- Okhare - Envelope Dodhalekhani Rd II Pkg (15 Km) SNRTP-BHOJ-W-NCB-31-09- PM-074-75 / Periodic Maintenance of Tiwari- Single Stage - One IDA / 53360 Post Request for Bids Open - National 159,652.90 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Bhanjyang-Chyangre-Bastim Envelope Thulogaon Duma Sano Duma Road Rd II Pkg (16 Km) SNRTP-SANK-W-NCB-32-01- PM-074-75 / Periodic Single Stage - One Maintenance of Khadbari- IDA / 53360 Post Request for Bids Open - National 195,019.99 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Ramche-Lebrang-Dake- Bharabise Rd (16 Km) SNRTP-TER-W-NCB-33-02- PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 208,807.79 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Maintenance of Serma-jaljale- Envelope Isibu Sadak Rd (19 Km) SNRTP-SIND-W-NCB-34-03- PM-074-75 / Periodic Single Stage - One Maintenance of Dauchet- IDA / 53360 Post Request for Bids Open - National 148,968.33 Signed 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Keureni-Banskharka-Jatatn- Baruwa Rd (19 Km) SNRTP-GOR-W-NCB-35-04- PM-074-75 / Periodic Under Single Stage - One Maintenance of Abuwa -B IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope irdi-Pauwatar-Kalamata- on Airport Road (8 Km) SNRTP-UDA-W-NCB-30-15- PM-074-75 / Periodic Single Stage - One Maintenance of Murkuchi IDA / 53360 Post Request for Bids Open - National 188,476.80 Signed 2017-11-26 2017-12-01 2017-12-31 2018-01-30 2018-02-21 2019-02-21 Envelope Puwarebhanjyang Bhutar Road 23 Km SNRTP-BAR-W-NCB-3-07- PM-074-75 / Periodic Maintenance of Bridge along Single Stage - One Kalaiya-Ganjbhabanipur IDA / H8990 Post Request for Bids Open - National 90,724.43 Signed 2017-11-27 2017-12-02 2018-01-01 2018-01-31 2018-02-22 2018-08-21 Envelope (Bridge Maintenance) and Kholbi Maduwa Road 9km, Bara SNRTP-MAK-W-NCB-14-07- PM-074-75 / Pulkomukh- Under Indrayanichaur - Chalti Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-12-01 2017-12-31 2018-01-15 2018-02-06 2019-02-06 (Agrakhola Road) 25 km and Envelope on GAirigaon pakani manahari road (20 km), Makwanpur Page 3 SNRTP-SIR-W-NCB-26-14- PM-074-75 / Periodic Single Stage - One Maintenance of Dhangadi IDA / H8990 Post Request for Bids Open - National 95,679.16 Signed 2017-11-26 2017-12-01 2017-12-31 2018-01-30 2018-02-21 2019-02-21 Envelope Patari-Jijhaul Road (25 KM), Siraha SNRTP-SIND-W-NCB-34-04- PM-074-75 / Periodic Single Stage - One maintenance of Naubise IDA / H8990 Post Request for Bids Open - National 382,179.93 Signed 2017-12-03 2017-12-08 2018-01-07 2018-02-06 2018-02-28 2019-02-28 Envelope Chautara Melamchi, Sindhupalchok SNRTP-SAP-W-NCB-24-14- PM-074-75 / Periodic Under Single Stage - One Maintenance of kalyanpur- IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2017-11-27 2017-12-02 2018-01-01 2018-01-31 2018-02-21 2019-02-21 Envelope Phulbariya-Banaula Banauli on Kushaha Road, Saptari SNRTP-NCB-W-25-12-PM- 074-75 / Periodic Maintenance of Dangrakhola Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-12-01 2017-12-31 2018-01-30 2018-02-21 2019-02-21 Bridge and causeway along Envelope salanpurhirapur Road (30 m bridge, 10 m causeway) SNRTP-LAM-W-NCB-36-02- UG-074-75 / Karputar- Single Stage - One Daduwa-Gilung- IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-12-25 2017-12-30 2018-01-29 2018-02-28 2018-03-22 2019-06-25 Envelope Salmebhanjyang (23.4km), Lamjung SNRTP-UDA-W-NCB-30-07- BRI-074-75 / Babiya Khola Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-22 2019-04-22 Bridge at gaighat fattepur Envelope Road 28 Km (50 m) SNRTP-SAP-W-NCB-24-08- Pending BRI-074-75 / Jita Khola-I Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-22 2019-04-22 Bridge at ch23+000 (Jandaul- Envelope on Kushaha Road, 24.55 km) SNRTP-BHOJ-W-NCB-31-06- BRI-074-75 / Pikhuwa Single Stage - One Khola Bridge at Bhojpur- IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2018-01-15 2018-02-04 2018-03-06 2018-04-05 2018-04-27 2019-05-02 Envelope Manebhanjyang-Ranibas- Ghoretar Road, (77.6 m) SNRTP-BAN-W-NCB-2-06- BRI-074-75 / Duduwa Nala Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2018-01-15 2018-02-09 2018-03-11 2018-04-10 2018-05-02 2019-05-02 Bridge at ch 0+500 Envelope (Betahani road),(51 m) SNRTP-GUL-W-NCB-8-13- Single Stage - One BRI-074-75 / Tribeni Khola IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-22 2019-04-22 Envelope Bridge,26 m Gulmi SNRTP-GUL-W-NCB-8-14- Single Stage - One BRI-074-75 / Lung Khola IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-22 2019-04-22 Envelope Bridge, 16 m, Gulmi SNRTP-TER-W-NCB-33-03- PM-074-75 / Periodic Pending Maintenance of Fakchamara- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-01-15 2018-02-19 2018-03-21 2018-04-20 2018-05-12 2019-05-12 Panchkanya-Pokari Road and Envelope on Chaparichowk Angdim Sadak,9 km , Terathum Page 4 SNRTP-DHAN-W-NCB-7-18- Under PM-074-75 / Periodic Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2017-11-26 2017-12-01 2017-12-31 2018-01-30 2018-02-20 2019-02-20 maintenance of Nunapatti Envelope on Barfi Duhabi Road (13.5) km SNRTP-DHAN-W-NCB-7-20- PM-074-75 / Periodic Under Single Stage - One Maintenance of Bisharbohar IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-15 2019-05-15 Envelope Durbakot thadi road (13 on Km) SNRTP-RUP-W-NCB-22-12- BRI-074-75 / Ghamaha Pending Single Stage - One Khola Bridge (Buddhanagar- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-05-09 2018-05-31 2019-05-31 Envelope Serawa-Kisauli-Suryapura on Road)(51m), Rupandehi SNRTP-PAL-W-NCB-17-05- BRI-074-75 / Amlihan Bridge Pending Single Stage - One at 5+560 (Bastari-Jhadewa- IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-15 2018-04-14 2018-04-29 2018-05-21 2019-05-21 Envelope Gothadi Road, 24.940 km) on (32 m) SNRTP-GOR-W-NCB-35-05- BRI-074-75 / Ludi Khola Pending Bridge at 3+00 (Laxmibazar- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-20 2018-04-19 2018-05-19 2018-06-10 2019-06-10 Tinmane-Jumlichautara- Envelope on Rainas-Butar Road, (22 m) Gorkha SNRTP-SYA-W-NCB-28-09- BRI-074-75 / Jugle Khola Pending Bridge at 9+100 of Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-05-11 2018-06-10 2018-07-02 2019-07-02 Naudanda-Bicharichautara- Envelope on Karkineta Rural Road, (23m), Syangja SNRTP-PYU-W-NCB-19-07- Pending Single Stage - One BRI-074-75 / Hariya Khola IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-22 2019-04-22 Envelope Bridge,26 m, Pyuthan on SNRTP-SIR-W-NCB-26-09- BRI-074-75 / Mainawati Pending Single Stage - One Khola Bridge at ch 2+700 IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Envelope Siraha-Sukhipur Road,18.96 on km (35 m) SNRTP-GUL-W-NCB-8-12- BRI-074-75 / Harewa Khola Pending Single Stage - One Bridge at 13+500 ( Chorkate- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Envelope Shantipur Road) (26 m), on Gulmi SNRTP-RAU-W-NCB-21-09- BRI-074-75 / Aduwa (Aruwa) Khola Bridge,Malahi ghat at Pending Single Stage - One 7+530 (Gaur-Kathariya- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Envelope Santapur-Dostiya- on Petbharwa(bara border) Road 25 m, Rautahat SNRTP-KAN-W-NCB-10-05- BRI-074-75 / Construction of Pending Malaria Khola Bridge.( 25 m Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-01-15 2018-02-14 2018-03-16 2018-04-15 2018-05-07 2019-05-07 span) across Dadthan- Envelope on Baliban Road, KANCHANPUR Page 5 SNRTP-SANK-W-NCB-32-06- BRI-074-75 / Pangma Khola Pending Bridge at 7+120 (Khandbari- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Kalchebesi-Pangtha-Dake- Envelope on Sabhapokhar Road) (26m), Sankhuwasabha SNRTP-ARG-W-NCB-01-11- BRI-074-75 / Samne Khola Pending Single Stage - One Bridge at Sandhikhark- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-01-15 2018-01-30 2018-03-01 2018-03-31 2018-04-21 2019-04-21 Envelope Pakale-Dharapani-Chujathanti on Road,(11 m),Argakhachi SNRTP-SANK-W-NCB-32-07- Pending BRI-074-75 / Malta Khola Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Bridge, 26 m , Envelope on Sankhuwasabha, SNRTP-MAK-W-NCB-14-08- BRI-074-075 / Dubu Khola, Pending Single Stage - One Ch 9+800 along Chuniya- IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Envelope Namtar-Bharta-Khairang on Road, 20 m Makwanpur SNRTP-PAR-W-NCB-18-08- BRI-074-075 / Dharar Khola Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Bridge,CH 13+130 along Envelope Janata Road, 20 m , Parsa SNRTP-SAR-W-NCB-25-09- BRI-074-075 / Gadauli(Godar) Pending Single Stage - One Bridge,Ch 2+190 along IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Envelope Karmaiya-Hathiyol Road, 25 on m Sarlahi SNRTP-SAR-W-NCB-25-12- PM-074-75 / Periodic Maintenance of Dangrakhola Single Stage - One IDA / H8990 Post Request for Bids Open - National 30,930.46 Signed 2018-03-05 2018-03-10 2018-04-09 2018-04-26 2018-05-18 2019-05-18 Bridge and causeway along Envelope salanpurhirapur Road (30 m bridge, 10 m causeway) SNRTP-BRD-W-NCB-4-08- PM-074-75 / Periodic Single Stage - One Maintenance of Ghorpitta - IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Baniyabhar - MRM Road (9 km) SNRTP-KAS-W-NCB-12-19- PM-074-75 / Periodic Under Maintenance of Rakhi- Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Mijauri - Gahate -Toshi Envelope on Road (27.1 Km.) including causeway, Kaski SNRTP-BAR-W-NCB-3-08- PM-074-75 / Periodic Under Maintenance of Kuduwa- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Langada Chowk-Bazar Envelope on (Bargadhi), Bara ( 0+000 to 13+326, Length- 13.326 km) SNRTP-KAP-W-NCB-11-11- PM-074-75 / Periodic Pending Maintenance of Jahadi-Bikuli- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Bugchi Road, Kapilvastu ( Envelope on 0+000 to 9+500, Lenght 9.5km) Page 6 SNRTP-KAP-W-NCB-11-13- PM-074-75 / Periodic Under Maintenance of Jhanda- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Bangai-Motipur-Dohate Road, Envelope on Kapilvastu (0+000 to 14+400, Length 11.05 km) SNRTP-DHAN-W-NCB-7-21- PM-074-75 / Periodic Maintenance of Under Dhanushadham-Sarsa- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Laxmipur-Kesharpatti- Envelope on Bhimanchowk- Road, Dhanusha(0+000 to 7+500, Length-7.50 km) SNRTP-KAP-W-NCB-11-14- PM-074-75 / Periodic Maintenance of Mahendrakot Under Bhelai-Kapasi-Purena- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Gorusinghe-Bakadariya- Envelope on Chetradehi-Tilaurakot Road, Kapilvastu (0+000 to 20+000, Length 13.9 km) SNRTP-SYA-W-NCB-28-01- Under PM-074-75 / Periodic Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Maintenance of PUtalikhet- Envelope on Pachamul-Aruchour Road SNRTP-BRD-W-NCB-4-09- PM-074-75 / Periodic Maintenance of PCO Chouk Pending Single Stage - One (Kakoura)-Damouli-Juraina- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Pachasa Road, Bardiya on (0+000 to 11+1000, Length 11.1 km) SNRTP-DHAN-W-NCB-7-22- PM-074-75 / Periodic Maintenance of Laxmipur- Under Bagewa-Gopalpur-Baniniya- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Ramdaiya-Bhabadi-Tarapati- Envelope on Sirsiya-Road, Dhanusha (0+000 to 13+440, Length 13.44 km) SNRTP-BRD-W-NCB-4-10- PM-074-75 / Periodic Pending Maintenance of Puspachouk- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Bholagoudi-Danfe Raod, Envelope on Bardiya (0+000 to 22+851, Length 22.85km) SNRTP-DHAN-W-NCB-7-23- PM-074-75 / Periodic Maintenance of Hariharpur- Under Single Stage - One Bateshwar-Bhuchakrapur- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Laxminibas-Road, Dhanusha on (0+000 to 10+030, Length- 10.03) SNRTP-GOR-W-NCB-35-05- PM-074-75 / Periodic Pending Maintenance of Nayapul- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Biruwarat-Pauwatar Road, Envelope on Gorkha (0+000 to 8+790, Length 8.79km) Page 7 SNRTP-SAR-W-NCB-25-13- PM-074-75 / Periodic Single Stage - One Maintenance of Salempur- IDA / 53360 Post Request for Bids Open - National 95,238.76 Signed 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Hirapur-Road, Sarlahi (0+000 to 15+000, Length-15 km) SNRTP-KAS-W-NCB-12-21- PM-074-75 / Periodic Maintenance of Baidam Pending Single Stage - One Pame Raod including IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope crossing structures, Kaski on (3+000 to 12+064, Length 9.06km and 100m) SNRTP-SIR-W-NCB-26-17- PM-074-75 / Periodic Maintenance of Lahan- Single Stage - One IDA / 53360 Post Request for Bids Open - National 40,912.81 Signed 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Tarengana Road, Siraha Envelope (1+500 to 0+100, Length-7.6 km) SNRTP-KAS-W-NCB-12-22- PM-074-75 / Periodic Maintenance of Kaure- Under Single Stage - One Jyamdung-Tanting Road IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope along with causeway, Kaski on (0+000 to 17+320, Length 17.32 km and 40m) SNRTP-SIR-W-NCB-26-18- PM-074-75 / Periodic Maintenance of Lahan- Single Stage - One IDA / 53360 Post Request for Bids Open - National 125,049.63 Signed 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Rameshchowk-Jhajpatti-Road, Envelope Siraha (0+000 to 19+000, Length-19km) SNRTP-KAS-W-NCB-12-23- PM-074-75 / Periodic Under Maintenance of Ghattekhola Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Dhampush Khanigaun Raod, Envelope on Kaski (0+000 to 7+500), Length 7.5km SNRTP-SAP-W-NCB-24-15- PM-074-75 / Periodic Under Maintenance of Chapin-Khola Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Bridge (Kharchuiya Kachan Envelope on Road), Saptari (3+450 to 3+477, Length- 27.35m) SNRTP-DAN-W-NCB-5-14- PM-074-75 / Periodic Under Maintenance of Simthana- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Khaireni Jumlekula Road, Envelope on Dang (0+000 to 8+5000, Length 8.5km) SNRTP-SAP-W-NCB-24-16- PM-074-75 / Periodic Under Maintenance of Hariharpur- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Pakari-Bishahariya-Tilanthi- Envelope on Road, Saptari (0+000 to 10+000, Length-10 km) SNRTP-DAN-W-NCB-5-15- PM-074-75 / Periodic Under Maintenance of Tarigaun- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Bhojpur-Khausapur Rural Envelope on Road, Dang (0+000 to 5+000, Length 5km) Page 8 SNRTP-DAN-W-NCB-5-16- PM-074-75 / Periodic Under Maintenance of Sarra- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Saudiyar-Dharna-Duruwa Envelope on Raod, Dang (0+000 to 15+5000),Length 15.5km SNRTP-BAR-W-NCB-3-09- PM-074-75 / Periodic Under Maintenance of Kolbi- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Baragadhi-Lautan- Road , Envelope on Bara (0+000 to 11+571, Length-11.571 km) SNRTP-ARG-W-NCB-1-17- PM-074-75 / Periodic Maintenance of Chutrabesi- Pending Single Stage - One Pakle-DharapanipRajame- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Pyutha Road, Arghakhanchi on (0+250 to 25+500, Length 25.25km) SNRTP-DHA-W-NCB-6-06- UG-074-75 / Upgrading of Pending Single Stage - One Dhadingbeshi-Sankosh-Tipling IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Road, Dhading (Length 2 on km) SNRTP-SUR-W-NCB-27-16- PM-074-75 / Periodic Maintenance of Baddichaur- Guthu-Bijaura-Benighat-Doti- Pending Single Stage - One Road (Babiyachaur-Guthu- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Section), Surkhet (17+600 to on 29+657, Length-12.057km, Crossing Structure-1+100 to 9+900, Length-69 m) SNRTP-BAN-W-NCB-2-09- PM-074-75 / Periodic Maintenance of Chaulika Single Stage - One Chowk (RRM)- IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Mahendranagar-Hirminiya- Holiya (Nayabasti Border) Road (6km) SNRTP-BAN-W-NCB-2-09- PM-074-75-2 / Periodic Maintenance of Chaulika Under Single Stage - One Chowk (RRM)- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-05 2018-06-09 2018-07-09 2018-08-08 2018-08-22 2019-06-18 Envelope Mahendranagar-Hirminiya- on Holiya (Nayabasti Border) Road (6km) SNRTP-BAN-W-NCB-2-10- PM-074-75 / Periodic Maintenance of Chandani Chowk(MRM)-Titihiriya- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Simalghari(Sonpur)- Envelope Udharapur-Gaughat Road (12km) SNRTP-BAN-W-NCB- 2-10-PM-074-75 SNRTP-BAN-W-NCB-2-10- PM-074-75-2 / Periodic Maintenance of Chandani Under Single Stage - One Chowk(MRM)-Titihiriya- IDA / 53360 Post Request for Bids Open - National 114,532.98 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Envelope Simalghari(Sonpur)- on Udharapur-Gaughat Road (12km) Page 9 SNRTP-PYU-W-NCB-19-09- PM-074-75 / Periodic Single Stage - One Maintenance of Kumaltar- IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Kondrachaur-Ratapani Road(10 Km) SNRTP-PYU-W-NCB-19-09- PM-074-75-2 / Periodic Under Single Stage - One Maintenance of Kumaltar- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Envelope Kondrachaur-Ratapani on Road(10 Km) SNRTP-RUP-W-NCB-22-13- PM-074-75 / Periodic Maintenance of Patkhouli- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Lothpura-Gauri- Envelope S shaniya-PartitoIe- Ramnagar Road (12 km) SNRTP-RUP-W-NCB-22-13- PM-074-75-2 / Periodic Under Maintenance of Patkhouli- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Lothpura-Gauri- Envelope on Sisaniya-PartitoIe-Ramnagar Road (12 km) SNRTP-RUP-W-NCB-22-14- PM-074-75 / Periodic Single Stage - One Maintenance of Bansghadi- IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Gaj edi- Suryapura Road (11 km), Rupendehi SNRTP-RUP-W-NCB-22-14- PM-074-75-2 / Maintenance Under Single Stage - One of Bansghadi-Gajedi- IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Envelope Suryapura Road (11 km), on Rupendehi SNRTP-RUP-W-NCB-22-15- PM-074-75 / Periodic Single Stage - One Maintenance of Bhangaiya IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Envelope Thu. Piprahawa Karauta Semara Road (20km) SNRTP-RUP-W-NCB-22-15- PM-074-75-2 / Periodic Under Single Stage - One Maintenance of Bhangaiya IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Envelope Thu- Piprahawa Karauta on Semara Road (20km) SNRTP-RUP-W-NCB-22-16- PM-074-75 / Periodic Maintenance of Tunihawa Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2017-11-26 2017-11-30 2017-12-30 2018-01-29 2018-02-20 2019-02-20 Mukundagadh Envelope Rayapur(semara) Road (19km) SNRTP-RUP-W-NCB-22-16- PM-074-75-2 / Periodic Under Maintenance of Tunihawa Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-10 2018-07-10 2018-08-09 2018-08-23 2019-06-19 Mukundagadh Envelope on Rayapur(semara) Road (19km) SNRTP-BAN-W-NCB-2-07- BRI-074-75 / Gandhiyanala Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2018-03-05 2018-03-10 2018-04-09 2018-04-24 2018-05-16 2019-05-16 Bridge at puraina,11 m Envelope Banke Page 10 SNRTP-BAN-W-NCB-2-07- Pending BRI-074-75-2 / Gandhaila Single Stage - One IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-06-06 2018-06-11 2018-07-11 2018-08-10 2018-08-24 2019-07-15 Nala Bridge at Puraina,11 Envelope on m Banke SNRTP-PYU-W-NCB-19-07- UG-074-75 / Upgrading of Single Stage - One Cherneta-Puranthanti-Jogitari IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2018-05-08 2018-05-13 2018-06-12 2018-06-27 2018-07-11 2019-07-11 Envelope Road,Pyuthan ( Length 2.45km ) SNRTP-PYU-W-NCB-19-08- UG-074-75 / Upgrading of Pending Single Stage - One Chujathati- Argakhachi IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-25 2018-06-30 2018-07-30 2018-08-14 2018-08-28 2019-07-09 Envelope Road,Pyuthan ( Length on 2.45km ) SNRTP-KAP-W-NCB-11-12- PM-074-75 / Periodic Maintenence of Pending Single Stage - One Chakarchauda-Siswa- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-25 2018-06-30 2018-07-30 2018-08-14 2018-08-28 2019-07-09 Envelope Autkoniya-Dohani Road on (0+000 to 10+500, Length 10.5km) SNRTP-UDA-W-NCB-30-16- PM-074-75 / Periodic Pending Maintenance of Nepaltar- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-25 2018-06-30 2018-07-30 2018-08-14 2018-08-28 2019-07-09 Udayapur-Gadhi- Road , Envelope on Udayapur (0+000 to 15+000, Length- 15 km) SNRTP-KAS-W-NCB-12-20- PM-074-75 / Periodic Pending Maintenance of Lamachaur- Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-25 2018-06-30 2018-07-30 2018-08-14 2018-08-28 2019-07-09 Machhapuchhre Road, Kaski Envelope on (8+5000 to 18+000, Length 9.5km) SNRTP-TER-W-NCB-33-02- UG-074-75 / Upgrading of Pending Single Stage - One Myanglung-Okhre-Sukrabare- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-06-25 2018-06-30 2018-07-30 2018-08-14 2018-08-28 2019-07-09 Envelope Chaparichowk-Dagappa Road on , Length 12 km SNRTP-PAR-W-NCB-18-09- PM-074-75-2 / Periodic Pending Single Stage - One Maintenance of Ramghadwa- IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-12-05 2018-12-09 2019-01-08 2019-01-23 2019-02-14 2019-07-14 Envelope Jagarnathpur-Milanchowk on Road (9 Km) SNRTP-PAR-W-NCB-18-13- PM-074-75-2 / Periodic Maintenance of Mudli -Tulsi barwa-Road (6 Km), Muldi Pending tindubiya-sabithawa road(6 Single Stage - One IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-12-05 2018-12-09 2019-01-08 2019-01-23 2019-02-14 2019-07-14 km), bedhihari birta Envelope on basantapur road (6 km) padamsadak-bahuwari (6km) and baghi patelchok road (9 km) SNRTP-PAR-W-NCB-18-08- BRI-074-075-2 / Dharar Pending Single Stage - One Khola Bridge,CH 13+130 IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-12-05 2018-12-10 2019-01-09 2019-01-24 2019-02-15 2019-07-15 Envelope along Janata Road, 20 m , on Parsa GOODS Page 11 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNRTP-CPCU-G-DP-17-074- Pending 75 / Purchase of Laptop, IDA / H8990 Post Direct Selection Direct 0.00 Implementati 2018-01-15 2018-01-30 2018-02-02 2018-03-04 Tablet and Desktop set (one on nos Each) SNRTP-CPCU-G-DP-18-074- 75 / Purchase of Smart TV IDA / H8990 Post Direct Selection Direct 1,678.17 Completed 2018-01-15 2018-01-20 2018-01-23 2018-02-22 for meeting HAll SNRTP-CPCU-U-DP-16-074- IDA / H8990 Post Direct Selection Direct 4,362.08 Completed 2018-01-15 2018-01-20 2018-02-10 2018-04-11 75 / Purchase of AC 4 Nos NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNRTP-CPCU-S-SSS-45-072- 073 / NOL to Minutes of Negotiations and Draft Negotiated Contract with IDA / H8990 Prior Direct Selection Direct 2,572,163.00 Signed ILO for three(03) new districts( Lamjung, Gorkha and Sindhupalchowk), Single Source Selection SNRTP-CPCU-S-SSS-25-070- 071 / Contract variation - Consultancy Services for Providing Technical Support IDA / H8990 Prior Direct Selection Direct 7,400,265.00 Canceled to Routine Maintenance System of Rural Roads and Bridges SNRTP-CPCU-S-DS-60-074- Pending 75 / Financial Management IDA / H8990 Post Direct Selection Direct 0.00 Implementati 2017-11-26 2017-12-01 2017-12-12 2019-12-12 Assistant for 2 years: on SNRTP-CPCU-NC-DP-13-074- 75 / Safeguard Training for Pending Safeguard team(Logistic,Meal IDA / H8990 Post Direct Selection Direct 0.00 Implementati 2018-01-15 2018-02-14 2018-03-17 2018-04-16 and Residency), one training on to be organized in at each PMU cluster. SNRTP-CPCU-NC-RFQ-12- Request for Single Stage - One 074-75 / Bio- engineering IDA / 53360 Post Limited 20,938.54 Completed 2018-05-14 2018-06-19 2018-08-18 Quotations Envelope Training to District Team SNRTP-CPCU-NC-DP-12-074- 75 / Soil/bio Engineering IDA / H8990 Post Direct Selection Direct 0.00 Canceled 2018-01-15 2018-02-14 2018-04-01 2018-05-31 Training to District Team SNRTP-CPCU-NCS-RFB-70- Single Stage - One 07 / VCDP and GAP IDA / H8990 Post Request for Bids Open - National 0.00 Canceled 2018-05-11 2018-05-18 2018-06-17 2018-07-02 2018-07-16 2019-03-18 Envelope training for Eastern Cluster Page 12 SNRTP-CPCU-NCS-IFB-71- Single Stage - One 074-75 / VCDP and GAP IDA / 53360 Post Request for Bids Open - National 0.00 Canceled 2018-05-11 2018-05-18 2018-06-17 2018-07-02 2018-07-16 2019-03-18 Envelope Training for western Cluster SNRTP-CPCU-NCS-RFB-70- Pending Single Stage - One 07-2 / VCDP and GAP IDA / H8990 Post Request for Bids Open - National 0.00 Implementati 2018-10-12 2018-10-19 2018-11-18 2018-12-03 2018-12-17 2019-07-15 Envelope training for Eastern Cluster on SNRTP-CPCU-NCS-IFB-71- Pending Single Stage - One 074-75-2 / VCDP and GAP IDA / 53360 Post Request for Bids Open - National 0.00 Implementati 2018-10-12 2018-10-19 2018-11-18 2018-12-03 2018-12-17 2019-07-15 Envelope Training for western Cluster on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SNRTP-CPCU-CS-CQS-36- 074-75 / Procurement of Consultant Pending Consulting Firm for Market IDA / H8990 Post Qualification Open - National 0.00 2018-06-28 2018-07-13 2018-08-27 2018-09-11 2018-10-03 2019-04-01 Implementation infrastructure investment Selection study SNRTP-CPCU-CS-QCBS-47- 074-75 / Procurement of Quality And Cost- IDA / H8990 Prior Open - National 0.00 Canceled 2017-12-03 2017-12-18 2018-02-01 2018-03-03 2018-03-18 2018-04-16 2018-05-08 2019-11-09 NGO for Beneficiary Based Selection Monitoring for PMU West SNRTP-CPCU-CS-QCBS-46- 074-75 / Procurement of Quality And Cost- IDA / H8990 Prior Open - National 0.00 Canceled 2017-12-03 2017-12-18 2018-02-01 2018-03-03 2018-03-18 2018-04-17 2018-05-09 2019-11-10 NGO for Beneficiary Based Selection Monitoring for PMU East SNRTP-CPCU-CS-QCBS-48- 074-75 / Procurement of Quality And Cost- Under IDA / H8990 Post Open - National 0.00 2018-08-24 2018-08-27 2018-09-20 2018-10-21 2018-11-04 2018-11-14 2018-12-06 2019-07-14 NGO for Beneficiary Based Selection Implementation Monitoring for PMU West SNRTP-CPCU-CS-QCBS-49- 074-75 / Procurement of Quality And Cost- Under IDA / H8990 Post Open - National 0.00 2018-08-24 2018-08-27 2018-09-20 2018-10-21 2018-11-04 2018-11-14 2018-12-06 2019-07-14 NGO for Beneficiary Based Selection Implementation Monitoring for PMU East SNRTP-CPCU-CS-CQS-35- Consultant 074-75 / Procurement of IDA / H8990 Post Qualification Open - National 0.00 Canceled 2017-11-30 2017-12-15 2018-01-29 2018-02-13 2018-03-07 2018-09-03 Consulting Firm for Baseline Selection Study SNRTP-CPCU-CS-QCBS-50- 075/76 / Pocurement of Quality And Cost- Under IDA / 53360 Post Open - National 0.00 2018-09-17 2018-09-21 2018-10-15 2018-11-15 2018-11-29 2018-12-11 2019-01-02 2019-07-16 Consulting firm for Impact Based Selection Implementation Study INDIVIDUAL CONSULTANTS Page 13