Hunan Integrated Management of Agricultural Land Pollution (P153115) Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [original: June 27, 2017; 1st Revision: August 17, 2017; 2nd Revision: June 8, 2018; 3rd Revision: Aug. 10, 2018] 2. Date of General Procurement Notice: August 16, 2017 3. Period covered by this procurement plan: March 2019 to December 2019 II. Goods, Works, non-consulting services and Community participation in procurement under Component 1. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Procurement Method Threshold US$ US$ ICB and LIB (Goods and Non- Greater than or equal to US$ 1. Consulting Services ) All 10 million NCB (Goods and Non-Consulting Greater than or equal to US$ Greater than or equal to 2. Services ) 0.5 million 2 million Greater than or equal to US$ 3. ICB (Works) All 40 million Greater than or equal to US$ Greater than or equal to 4. NCB (Works) 0.5 million 10 million Community participation in to be specified in the 5 No Threshold procurement operation manual 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Detailed procedures for community participation are specified in operation manual. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P153115 has been prepared by Hunan PPMO. 5. Any Other Special Procurement Arrangements [including advance procurement and retroactive financing, if applicable]: None 6 Summary of the Procurement Packages planned during March 2019 to December 2019 . 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ (yes/no) (Prior / thousand Post) Summary of the National Competitive 3448.19 4 Post Bidding (Works) Summary of the Shopping 3777.19 13 Post (Works) Summary of the Shopping 360.30 1 Post (Goods) Summary of the Shopping (Non- 2095.47 9 Post Consultant Services) Cancellation (Works) 688.35 4 Post Cancellation (Goods) 492.54 1 Post III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Greater than or equal to US$ 1,000,000 2. Single Source (Firms) Greater than or equal to US$ 1,000,000 3. Individual Greater than or equal to US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements [including advance procurement and retroactive financing, if applicable or delete if not applicable]: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Estimated Review Description of Cost Ref. No. by Bank Assignment Packages Comments US$ (Prior / thousand Post) Summary of number of contracts that 522.39 1 Post will be let under QCBS Summary of number of contracts that 1548.03 17 Post will be let under other methods Cancellation 465.78 3 Post PROCUREMENT China : Hunan Integrated Management of Agricultural Land Pollution Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2017-09-04 2019-04-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153115 GPN Date: 2017-08-16 Project Name: Hunan Integrated Management of Agricultural Land Pollution Project Loan / Credit No: IBRD / 87770, / Executing Agency(ies): Hunan Integrated Management of Agriculture PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNYDG001 / Construction Pending of drainage ditches, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2017-09-15 2017-11-10 2018-05-09 irrigation ditches, sand and Quotations Envelope on gravel traps. HNYXG001 / Construction Request for Single Stage - One of irrigation ditches, sand IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps, field roads. HNYXG002 / Construction Request for Single Stage - One of drainage ditches, sand IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps. HNYXG003 / Construction of irrigation ditches, drainage ditches, sand and Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 gravel traps, ecological Quotations Envelope interception ditches and pumping stations. HNYXG004 / Construction Request for Single Stage - One of irrigation ditches, sand IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope and gravel traps. HNYXG005 / Construction Request for Single Stage - One of irrigation ditches and IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope drainage ditches. HNHYG001 / Construction Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches HNHYG002 / Construction Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches. HNHYG003 / Construction Request for Single Stage - One of irrigation canals and IBRD / 87770 Post Limited 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope ditches. HNHYG004 / Construction Request for Single Stage - One of Sand and gravel traps IBRD / 87770 Post Limited 0.00 Canceled 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope &Field roads. HNHYG001-1 / Construction Pending of irrigation system and Single Stage - One IBRD / 87770 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 gravel or dirt road in Envelope on Hengyang county. Page 1 HNHYG002-1 / Construction Pending of Irrigation system and Request for Single Stage - One IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2020-05-01 gravel or dirt road in Quotations Envelope on Hengyang county. HNHYG003-1 / Construction Pending of Irrigation system and Request for Single Stage - One IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2020-05-01 gravel or dirt road in Quotations Envelope on Hengyang county. HNXXHYG001 / Construction of irrigation Pending Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-10-28 Quotations Envelope Sediment desilting and on landfill in Huayuan county. HNXXHYG002 / Construction of irrigation Pending Request for Single Stage - One system, gravel or dirt road, IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-10-28 Quotations Envelope Sediment desilting and on landfill in Huayuan county. HNQYG001 / Construction Pending of irrigation system and a Request for Single Stage - One IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2020-04-30 gravel or dirt road in Quotations Envelope on Qiyang county . HNCLG001 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili on county. HNCLG002 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili on county. HNCLG003 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili on county. HNCLG004 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili on county. HNCLG005 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-10-15 2019-12-10 2020-08-06 Quotations Envelope desilting and landfill in Cili on county. HNHNG001 / Construction of irrigation system, gravel Pending Single Stage - One or dirt road, Sediment IBRD / 87770 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 Envelope desilting and landfill in on Hengnan county. HNZFG001 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope desilting and landfill in on Zhongfang county. Page 2 HNZFG002 / Construction of irrigation system, gravel Pending Request for Single Stage - One or dirt road, Sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope desilting and landfill in on Zhongfang county. HNLSTG001 / Construction of irrigation system, gravel Pending Single Stage - One or dirt road, Sediment IBRD / 87770 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2020-06-21 Envelope desilting and landfill in on Leng Shuitan county. HNBJG001 / Construction of irrigation system ,gravel Pending Single Stage - One or dirt road, sediment IBRD / 87770 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-12-21 Envelope desilting and landfill in on Baojing county . HNYSG001 / Construction of irrigation system ,gravel Pending Request for Single Stage - One or dirt road, sediment IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-11-01 Quotations Envelope desilting and landfill in on Yongshun county . HNHYG004-1 / Pending Request for Single Stage - One Reconstruction of heavy IBRD / 87770 Post Open - National 0.00 Implementati 2019-04-04 2019-05-30 2019-11-26 Quotations Envelope metal detection laboratory. on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNH002 / Procurement of sampling inspection vehicles to facilitate project Request for Single Stage - One / Post Limited 0.00 Canceled 2017-12-13 2018-02-07 2018-08-06 management and supervion Quotations Envelope and sample transpotation in 15 project counties. HNHYH002 / Procurement Pending Request for Single Stage - One of comprehensive pest and IBRD / 87770 Post Open - National 0.00 Implementati 2019-03-06 2019-05-01 2019-12-27 Quotations Envelope disease control equipment. on HNH001 / Procurement of desktop computers , laptops , multi func printers , scanners, digital cameras , Pending DVs , projectors , GPS Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2019-07-30 locators , projection screens Quotations Envelope on and digital recorders , which aims to promote the management efficency and ability of PMO staffs HNHYH001 / Procurement Pending of testing equipment for the Request for Single Stage - One IBRD / 87770 Post Open - National 0.00 Implementati 2019-04-04 2019-05-30 2019-11-26 Agricultural Bureau in Quotations Envelope on Hengyang County. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 HNYDFZ001 / Sampling Request for Single Stage - One from fields and detection of IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 Quotations Envelope the samples. HNYXFZ001 / Detection of agricultural products, irrigation water, underground Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope fertilizer, and pesticides for heavy matal determination. HNHYFZ001 / detection of agricultural products, irrigation water, underground Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope fertilizer, and pesticides for heavy matal determination. HNYDFZ002 / detection of agricultural products, irrigation water, underground Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2017-09-15 2017-11-10 2018-05-09 water, air, sediment, organic Quotations Envelope fertilizer, and pesticides for heavy matal determination HNYDFZ002-2-2 / Sampling of water, soil, crops, Pending sediments, agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2019-06-30 atmosphere deposition, etc. Quotations Envelope on in Yongding District and detection of the samples. HNYXFZ001-2-2 / Sampling of water, soil, crops, sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2018-03-10 2018-05-05 2019-06-30 atmosphere deposition, etc. Quotations Envelope in Yongxing County and detection of the samples. HNJSFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Jishou City and detection of the samples. HNYSFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Yongshun County and detection of the samples. HNBJFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Baojing County and detection of the samples. HNXXHYFZ001-2 / Sampling of water, soil, crops, sediments,agriculture Pending Request for Single Stage - One inputs, atmosphere IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 Quotations Envelope deposition, etc. in Huayuan on County and detection of the samples. Page 4 HNQYFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Qiyang County and detection of the samples. HNCLFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Cili County and detection of the samples. HNYZFZ001-2 / Sampling of water, soil, crops, sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope in Yizhang County and detection of the samples. HNZFFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Zhongfang County and detection of the samples. HNAHFZ001-2 / Sampling of water, soil, crops, sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Canceled 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope in Anhua County and detection of the samples. HNLSTFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2018-03-10 2018-05-05 2018-12-31 atmosphere deposition, etc. Quotations Envelope on in Lengshuitan District and detection of the samples. HNHYFZ001-2-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Hengyang County and detection of the samples. HNYDFZ003 / Sampling of water, soil, crops, sediments, Pending agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Yongding District and detection of the samples. HNQYFZ002 / Sampling of water, soil, crops, sediments, Pending agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Qiyang county and detection of the samples. HNLWFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Linwu County and detection of the samples. Page 5 HNZFFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Zhongfang County and detection of the samples. HNLSTFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Leng Shuitan District and detection of the samples. HNXXHYFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Huayuan County and detection of the samples. HNBJFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Baojing County and detection of the samples. HNYSFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Yongshun County and detection of the samples. HNHYFZ002 / Publicize the measures and effects of the project in Hengyang, so as to enhance the visibility of Pending the project and the value of Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2024-03-31 agricultural products in the Quotations Envelope on project area, and popularize the knowledge of heavy metal pollution control at the same time. HNHNFZ001-2 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Hengnan County and detection of the samples. HNCLFZ002 / Sampling of water, soil, crops, Pending sediments,agriculture inputs, Request for Single Stage - One IBRD / 87770 Post Limited 0.00 Implementati 2019-03-06 2019-05-01 2023-12-31 atmosphere deposition, etc. Quotations Envelope on in Cili County and detection of the samples. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HNYXZ001 / Screening of Consultant low metal-accumulating IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2021-01-28 variety. Selection Page 6 HNYDZ005 / Comparing the differences of heavy Consultant metal uptaking between the IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 "with project"and"without Selection project" situations HNYDZ006 / Disseminate knowledge gained from Consultant demonstrations for increasing IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 awareness and building Selection ability to make informed choices among alternatives. Consultant HNYXZ002 / Project IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. Selection Consultant HNYXZ003 / Supervision of IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 agronomic measures. Selection HNZ005 / Screening experiment on simultaneous Consultant Pending passivation agents for IBRD / 87770 Post Qualification Open - National 0.00 2018-06-10 2018-07-01 2018-08-14 2018-09-13 2018-10-18 2019-12-31 Implementation combined pollution of Selection cadmium and arsenic. HNZ008 / Conduction of annual environmental Consultant assessment (produce one IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 environmental assessment Selection report every six months) HNHYZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Hengyang county. HNHYZ002 / Experiment on the effect of harvesting Consultant at different maturity on Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2021-07-09 cadmium accumulation in Implementation Selection rice, to be conducted in Hengyang county. HNHYZ003 / Comparison of effects of agronomic Consultant measures in different regions Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2023-12-31 and monitoring experiment Implementation Selection of soil cadmium balance in Hengyang county. HNHYZ006 / Local policies Consultant Pending and standards development IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2023-12-31 Implementation in Hengyang county. Selection Consultant HNYDZ003 / Project IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 monitoring and evaluation. Selection Consultant HNYDZ007 / Supervision of IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2022-12-31 agronomic measures. Selection HNQYZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Qiyang county. Page 7 HNCLZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Cili county. HNHNZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Hengnan county. HNZFZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Zhongfang county. HNLSTZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Lengshuitan district. HNXXHYZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Huayuan county. HNYSZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 accumulation varieties in Implementation Selection Yongshun county. HNZ001 / Development of a risk-based land management tool and use the tool to map all farmland sat the county and provincial levels Quality Based Pending IBRD / 87770 Post Open - National 0.00 2019-03-10 2019-03-31 2019-05-14 2019-06-11 2019-07-11 2019-08-10 2019-09-14 2022-09-14 to classify areas with Selection Implementation different risk levels, crops for different soil types and conditions, and identify risk management options. HNZ002 / Studies on sustainable financing models Consultant and eco-compensation Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-17 2019-03-27 2019-05-10 2019-06-09 2019-07-14 2022-07-14 mechanisms for long-term Implementation Selection agricultural land management. HNZ003 / Establish a database of all relevant Consultant information, and give early Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-17 2019-04-07 2019-05-21 2019-06-20 2019-07-25 2021-07-25 warning of possible risks to Implementation Selection farmland and crops according to data changes. HNZ004 / Monitoring the progress of project, finance, procurement and training.And summarize the situation of social tracking Consultant monitoring, environmental IBRD / 87770 Post Qualification Open - National 0.00 Canceled 2018-11-10 2018-12-01 2019-01-14 2019-02-13 2019-03-20 2024-06-30 tracking monitoring and Selection project implementation effectiveness assessment (a report is produced every six months). Page 8 HNZ004-2 / The overall monitoring and evaluation of the project (includes the Quality And Cost- Pending IBRD / 87770 Post Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-02 2019-07-02 2019-08-06 2019-09-10 2023-12-31 evaluation of the Based Selection Implementation implementation effect of the project) . HNZ006 / Monitoring the Consultant whole process of sampling Pending IBRD / 87770 Post Qualification Open - National 0.00 2018-08-13 2018-09-03 2018-10-17 2018-11-16 2018-12-21 2023-12-31 and detection of the samples Implementation Selection for quality control HNZ007 / Conduction of Social evaluation annually (tracking monitoring one Consultant natural village per county Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-02 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2023-12-31 and produce a social Implementation Selection evaluation report each year) and dam safety assessment annually. HNZ009 / Screening experiment on simultaneous Consultant passivation agents for Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2021-07-13 combined pollution of Implementation Selection cadmium and arsenic for the second time. HNHYZ005 / Analysis and Consultant evaluation of heavy metal Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2023-12-31 pollution data in Hengyang Implementation Selection county. HNYDZ004 / Screening of Consultant Pending low metal-accumulating IBRD / 87770 Post Qualification Open - National 0.00 2019-03-01 2019-03-22 2019-05-05 2019-06-04 2019-07-09 2022-07-09 Implementation variety in Yongding district. Selection HNBJZ001 / Screening Consultant experiment of low cadmium Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-02 2019-03-23 2019-05-06 2019-06-05 2019-07-10 2022-07-10 accumulation varieties in Implementation Selection Baojing county. HNZ008-2 / Conduction of annual environmental Quality And Cost- Open - Pending assessment (produce one IBRD / 87770 Post 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2023-12-31 Based Selection International Implementation environmental assessment report every six months) HNLSTZ002 / Hire a third party to supervise the Consultant Pending implementation of agronomic IBRD / 87770 Post Qualification Open - National 0.00 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2023-12-31 Implementation measures in Leng Shuitan Selection District. HNQYZ003 / Hire a third Consultant party to supervise the Pending IBRD / 87770 Post Qualification Open - National 0.00 2019-03-25 2019-04-15 2019-05-29 2019-06-28 2019-08-02 2023-12-31 implementation of agronomic Implementation Selection measures in Qi Yang county. HNHNZ002 / Hire a third party to supervise the Consultant Pending implementation of agronomic IBRD / 87770 Post Qualification Open - National 0.00 2019-04-06 2019-04-27 2019-06-10 2019-07-10 2019-08-14 2023-12-31 Implementation measures in Heng Nan Selection county. INDIVIDUAL CONSULTANTS Page 9