17-Feb-2022 Her Excellency Ms. Silveria E. Jacobs Prime Minister Ministry of General Affairs Soualuiga Road 1 Pond Island, Great Bay Sint Maarten RE: Sint Maarten: Hurricane Irma Reconstruction, Recovery and Resilience Trust Fund Grant Agreement Sint Maarten Airport Terminal Reconstruction Project (Grant No. TF0B0760) Amendment to the Grant Agreement (“Amendment Letter”) Dear Excellency: We refer to the Grant Agreement between SINT MAARTEN (“Recipient”) and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT (“World Bank”), acting as administrator of Sint Maarten: Hurricane Irma Reconstruction, Recovery and Resilience Trust Fund, dated December 9, 2019, for the above-captioned project (“Project”), Grant Number TF0B0760, (“Grant Agreement”). Reference is also made to the Borrower’s request for additional financing for the Project (“Additional Financing”). In view of the Additional Financing, as discussed and confirmed between the Recipient and the Bank, certain related updates will be incorporated into the Project with respect to the Project Closing Date and results indicators. Accordingly, we are pleased to inform you that the Grant Agreement is hereby amended as set forth below: 1. Section III.B.2 of Schedule 2 to the Grant Agreement is hereby amended to read in its entirety as follows: “The Closing Date is December 31, 2023.” 2. With reference to Section 2.06(a) of the Standard Conditions, the indicators set forth in the “Results Framework” in the Annex to this Amendment Letter shall serve as a basis for the Borrower to monitor and evaluate the progress of the Project and the achievement of the objectives thereof. Please confirm your agreement to the foregoing amendments to the Grant Agreement on behalf of the Recipient, by signing and dating the confirmation on the enclosed copy of this Amendment Letter and returning it to us. Upon receipt by the World Bank of a countersigned original Amendment Letter, this Amendment Letter will become effective as of the date of countersignature by the Recipient. -1- All other provisions of the Grant Agreement except as amended through this Amendment Letter shall remain in full force and effect. This Amendment Letter shall be executed in three (3) counterparts each of which shall be an original. Sincerely INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT ______________________ Lilia Burunciuc Country Director for Caribbean Countries The World Bank AGREED: SINT MAARTEN By: ____________________ Authorized Representative Ms. Silveria E. Jacobs Name: ____________________ Prime Minister of St. Maarten Title: ____________________ 15-Apr-2022 Date: ____________________ -2- Copy: Cc with copies: E. Mr. Ardwell M.R. Irion, Minister of Finance Dr. Abel S. Knottnerus, Legal Officer and Deputy Director, National Recovery Program Bureau (NRPB) Mr. Brian Mingo, Chief Executive Officer, Prince Juliana Airport Operating Company -3- Annex 1 RESULTS Results Framework COUNTRY: St Maarten RESULT_NO_PDO Additional Financing for the Sint Maarten Airport Terminal Reconstruction Project Project Development Objective(s) The development objective to restore the passenger capacity of Princess Juliana International Airport to pre-Hurricane Irma levels with improved resilience towards hurricanes. Project Development Objective Indicators by Objectives/ Outcomes RESULT_FRAME_T BL_ PD O Indicator Name PBC Baseline End Target Restore to pre-Irma levels the passenger capacity of Princess Juliana International Airport Passenger handling capacity of the terminal (Number) 1,000,000.00 2,500,000.00 Action: This indicator has been Revised Improve resilience of the terminal against hurricanes Resistance of terminal building to Irma-level hurricanes (Yes/No) No Yes Action: This indicator has been Revised PDO Table SPACE Intermediate Results Indicators by Components RESULT_FRAME_T BL_ IO Indicator Name PBC Baseline Intermediate Targets End Target 1 Reconstruction of the PJIA passenger terminal -3- Completion of package 2 terminal reconstruction works (Percentage) 0.00 100.00 Action: This indicator has been Revised Replacement of Passenger Boarding Bridges with Supplier for Passenger Boarding Bridges Passenger Boarding Bridges with improved Passenger Boarding Bridges not installed improved corrosion resistance (Text) contracted corrosion resistance installed Rationale: The name of this indicator has been changed from "jet bridges" to reflect the specific name of the equipment package "Passenger Action: This indicator has been Revised Boarding Bridges", which will replace the boarding bridges which were damaged during the hurricane and will have improved corrosion resistance. Installation of structurally improved entrance Structurally improved entrance doors not Supplier for structurally improved entrance Structurally improved entrance doors doors (Text) installed doors contracted installed Rationale: Action: This indicator has been Revised Resilient wording replaced with "structurally improved" to better explain the technical upgrade to the doors. Supplier of Baggage Handling System Replacement of Baggage Handling System (Text) Baggage Handling System not replaced Baggage Handling System replaced contracted Rationale: This indicator has been reworded from "restoration" to "replacement" to reflect the new and improved equipment being procured as part Action: This indicator has been Revised of the project. Replacement of exterior glazing panels (Yes/No) No Yes Rationale: Added new indicator “Replacement of exterior glazing panels” as these were broken and missing following the hurricane and are Action: This indicator is New considered vulnerable elements of the facade and will be replaced during the Package 2 works. Capacity Building of and Project Management by PJIAE (Action: This Component is New) PJIAE submits quarterly reports describing claims received through GRM and how issues were No Yes Yes resolved (Yes/No) Action: This indicator has been Revised -4- Capacity Building of and Project Management by the Govt of Sint Maarten (Action: This Component is New) PJIAE and Government officials trained (Number) 0.00 50.00 Rationale: Action: This indicator is New Adding an indicator for Component 3. IO Table SPACE Monitoring & Evaluation Plan: PDO Indicators Mapped Methodology for Data Responsibility for Data Indicator Name Definition/Description Frequency Datasource Collection Collection Project Semi- Passenger handling capacity of the Annual Annual Contractor's Reports PJIAE terminal Report Based on the intermediate indicators Project Semi- on replacement of Resistance of terminal building to Irma- Annual Annual PJIAE doors, BHS, glazing, and level hurricanes Report passenger boarding bridges. ME PDO Table SPACE Monitoring & Evaluation Plan: Intermediate Results Indicators Mapped Methodology for Data Responsibility for Data Indicator Name Definition/Description Frequency Datasource Collection Collection Project Semi- Physical progress of the Completion of package 2 terminal Annual Annual Package 2 works based PJIAE reconstruction works Report on Contractor's Reports. -5- Project Semi- Replacement of Passenger Boarding Based on Contractor's Annual Annual PJIAE Bridges with improved corrosion Report Report resistance Project Semi- Based on Contractor's Installation of structurally improved Annual Annual PJIAE Report entrance doors Report Project Semi- Based on Contractor's Annual Annual PJIAE Replacement of Baggage Handling System Report Report Project Semi- Based on Contractor's Annual Annual PJIAE Replacement of exterior glazing panels Report Report PJIAE submits quarterly reports describing Semi Project Semi- Data from Quarterly PJIAE claims received through GRM and how Annual Annual Report ESMRs issues were resolved Number of persons from Project Semi- PJIAE and Government who Semi- Annual Participation sheets NRPB PJIAE and Government officials trained participated in training Annual Report sessions financed by the Project. ME IO Table SPACE ME IO Table SPACE -6-