Himachal Pradesh Horticulture Development Project Project ID : P151744 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 22, 2016 2. Date of General Procurement Notice: May 19, 2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Procurement Methods Category Method of Procurement Threshold (US$ Equivalent) Goods and non- ICB >3,000,000 consulting services LIB Wherever agreed by the World Bank (including IT NCB Up to 3,000,000 (with NCB contracts) conditions) Shopping Up to 100,000 From UN Agencies As per para 3.10 of Guidelines DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines Framework Agreements As per para 3.6 of Guidelines Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines  Prior Review by the Bank : The World Bank will prior review all Terms of Reference and the following contracts: • Works: All contracts more than US$15.0 million equivalent; • Goods: All contracts more than US$3.0 million equivalent; • Non-Consulting Services: All contracts more than US$3.0 million equivalent;  The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct March 22, 2015 prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on Limited International Bidding (LIB), direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements:  International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services using the World Bank’s standard bidding document. In addition, the following methods may be adopted depending upon size and complexity of subprojects in accordance with Procurement Guidelines, and as agreed in the Procurement Plan: (a) Limited International Bidding (LIB), (b) National Competitive Bidding (NCB), (c) Shopping, (d) Framework Agreements, (e) Direct Contracting, (f) Force Account, and (g) Procurement of UN agencies. Limited International Bidding is essentially ICB by direct invitation, is used only under exceptional circumstances, and will be adopted only for packages that are specifically agreed by the World Bank to be procured following LIB.  National Competitive Bidding (NCB) for procurement of goods and works will be conducted in accordance with paragraphs 3.3 and 3.4 of the Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), will be used for bidding. (ii) Invitation to bid will be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily giving the website/electronic portal March 22, 2015 details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, government-owned enterprises, small-scale enterprises or enterprise from any given regional government; (iv) Except with the prior concurrence of the World Bank, there will be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) For prior review contracts, extension of bid validity will not be allowed without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); (vi) For prior review contracts, re-bidding will not be carried out without the prior concurrence of the World Bank; (vii) The system of rejecting bids outside a pre-determined margin or “bracket” of prices will not be used in the Project; (viii) Rates contracts entered into by the Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the World Bank on a case-by-case basis. Such contracts will be acceptable however, for any procurement under the shopping procedure; (ix) The two or three envelop system will not be used (expect when using the e- procurement system assessed and agreed by the World Bank).  Shopping. Procurement of goods, works and non-consulting services may be carried out using the shopping method (paragraph 3.5 of the Procurement Guidelines) for readily available, off-the-shelf products, or simple civil works valued at less than US$100,000 and which do not require tailor made designs as agreed with the World Bank or concerned expert agencies. Such method, if any, will be agreed in the Procurement Plan. The implementing agency and entities will solicit at least three price quotations for the purchase of goods, materials, small works, or services (non-consulting), to formulate a cost comparison report. If agreed by the World Bank, under exceptional circumstances, (such as design sensitivity due to location near a monument or appropriate technology), International Shopping may be used wherein quotations will be solicited from at least three suppliers in two different countries. Goods that otherwise qualify for shopping could be procured directly from UN agencies. In specific cases agreed with the World Bank, procurement may be made from UN agencies as per paragraph 3.10 of the Procurement Guidelines.  Direct Contracting. Direct contracting for the procurement of civil works and goods (paragraph 3.7 of the Procurement Guidelines) may be used to extend an existing contract or award a new contract. For such contracting to be justified, the World Bank must agree that the price is reasonable and that no advantage could be obtained by further competition. Direct contracting can be used to procure from the private sector, UN agencies/programs March 22, 2015 (for goods), or contractors or NGOs that are already mobilized and working in the target areas.  Force Account. When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the subproject or a certain government agency has exclusive rights to a certain type of works/supply, the borrower may use its own department’s personnel and equipment or government owned construction units, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the World Bank on expenditure, as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements. Directorate General of Supplies and Disposal rate contracts will be acceptable as framework agreements for the procurement of goods. Regional government level rate contracts will be examined by the World Bank and if agreed upon, may also be used as framework agreements. Implementing entities also have the option to set up new framework agreements as per paragraph 3.6 of the Procurement Guidelines.  Use of government institutions and enterprise. Government owned enterprise or institutions in India may be hired based on their unique and exceptional nature if their participation is considered critical to the Project implementation. In such cases, the conditions given in clauses 1.13 of the Consultant Guidelines will be satisfied and each case will be subject to prior review by the World Bank. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Procurement Methods Category Method of Procurement Threshold (US$ Equivalent) Consultants’ services QCBS As per Section II of Guidelines CQS Up to 300,000 SSS As per para 3.8-3.11 of Guidelines Individuals As per Section V of Guidelines LCS As per para 3.6 of Guidelines QBS As per para 3.2 of Guidelines FBS As per para 3.5 of Guidelines (i) International shortlist >800,000 (ii) Shortlist may comprise Up to 800,000 national consultants only March 22, 2015  The World Bank will prior review all Terms of Reference and the following contracts: • All contracts more than US$1.0 million equivalent for firm; and • All contracts more US$300,000 equivalent for individuals. The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements:  Selection of Consultants—Quality and Cost Based Selection: Consultant Services may be procured under contracts awarded on the basis of Quality- and Cost-based Selection in accordance with the provisions of Section II of Consultant Guidelines using the World Bank’s Standard RFP. In addition, the following selection methods may be adopted depending upon size and complexity of tasks and as agreed in the Procurement Plan: • Quality Based Selection (QBS) • Selection under Fixed Budget (FBS) • Least Cost Selection (LCS) • Single Source Selection (SSS) • Individual Consultant (IC) Single-Source Selection of consulting firms or individual experts may be used only if it presents a clear advantage over competition for the required consulting services in accordance with paragraph 3.8 of the World Bank’s Consultant Guidelines. Selection of consulting firms based on Consultants’ Qualifications (CQS) may be appropriate for assignments estimated to cost up to US$300,000 or equivalent in accordance with paragraph 3.7 of the Consultant Guidelines. Advertisement for expression of interest may be limited to the regional level for assignments estimated to cost less than US$100,000. March 22, 2015 For assignments that are estimated to cost less than US$50,000, advertisement is not mandatory as long as a shortlist of at least three proven qualified firms is established. Shortlists of consultants for services estimated to cost less than US$800,000 or the equivalent per contract may be composed entirely of national consultants (paragraph 2.7 of Consultant Guidelines). Services for assignments that meet the requirements set forth in paragraph 5.1 of the Consultant Guidelines may be procured under contracts awarded to individual consultants in accordance with the provisions of paragraphs 5.2 to 5.5 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of the Consultant Guidelines, such contracts may be awarded to individual consultants on a sole source basis. 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in separate Excel file. March 22, 2015 PROCUREMENT India : Himachal Pradesh Horticulture Development Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2018-11-26 2020-08-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151744 GPN Date: 2017-04-03 Project Name: Himachal Pradesh Horticulture Development Project Loan / Credit No: IDA / 58380 Executing Agency(ies): Department of Horticulture, HP, Project Implementing Unit WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-PIU HORTICULTURE- 87358-CW-RFQ / Execution of renovation work of Departmental Office Component A: Horticulture Request for Single Stage - One Building(Double IDA / 58380 Production and Post Open - National 20,777.69 18,158.70 Completed 2018-11-21 2019-01-16 2017-10-17 2019-07-15 Quotations Envelope Story)including water supply Diversification and sanitary fittings at Directorate of Horticulture Complex Navbahar Shimla-2. IN-PIU HORTICULTURE- 87359-CW-RFQ / Invitation for quotations for Component A: Horticulture Request for Single Stage - One construction of retaining wall IDA / 58380 Production and Post Open - National 4,740.14 4,558.60 Completed 2018-11-21 2019-01-16 2018-01-17 2019-07-15 Quotations Envelope and breast wall at Diversification Directorate of Horticulture Complex Shimla-2 IN-PIU HORTICULTURE- 184907-CW-RFQ / Component A: Horticulture Pending Construction of Desilting Request for Single Stage - One IDA / 58380 Production and Post Limited 11,813.00 0.00 Implementat 2020-08-03 2020-09-26 2021-03-25 Tank at Majhewali cluster Quotations Envelope Diversification ion Distt. Shimla WUA (Community Procurement) IN-PIU HORTICULTURE- 184909-CW-RFQ / Laying, Jointing and Commissioning Component A: Horticulture Pending Request for Single Stage - One of HDPE pipes- Source to IDA / 58380 Production and Post Limited 13,423.00 0.00 Implementat 2020-09-07 2020-11-01 2021-04-30 Quotations Envelope Tank-01 at Majhewali Diversification ion cluster Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 184911-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 50,000 Ltr Capacity- (2 No) IDA / 58380 Production and Post Limited 10,273.00 0.00 Implementat 2020-09-07 2020-11-01 2021-04-30 Quotations Envelope at Majhewali cluster Distt. Diversification ion Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 184923-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 50,000 Ltr Capacity- (2 No) IDA / 58380 Production and Post Limited 10,273.00 0.00 Implementat 2020-09-25 2020-11-28 2021-05-27 Quotations Envelope at Majhewali cluster Distt. Diversification ion Shimla (WUA - Community Procurement) Page 1 IN-PIU HORTICULTURE- 184924-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 50,000 Ltr Capacity- (2 No) IDA / 58380 Production and Post Limited 10,273.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Quotations Envelope at Majhewali cluster Distt. Diversification ion Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 184925-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 50,000 Ltr Capacity- (2 No) IDA / 58380 Production and Post Limited 10,273.00 0.00 Implementat 2020-12-18 2021-02-20 2021-08-19 Quotations Envelope at Majhewali cluster Distt. Diversification ion Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185014-CW-RFQ / Construction Of Check Dam- Component A: Horticulture Pending Request for Single Stage - One 01 and Intake Chamber at IDA / 58380 Production and Post Limited 16,522.00 0.00 Implementat 2020-08-11 2020-10-13 2021-04-11 Quotations Envelope Peja cluster Distt. Shimla Diversification ion (WUA - Community Procurement) IN-PIU HORTICULTURE- 185017-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 141500Litres-01 Nos at IDA / 58380 Production and Post Limited 11,528.00 0.00 Implementat 2020-08-11 2020-10-13 2021-04-11 Quotations Envelope Peja cluster Distt. Shimla Diversification ion (WUA - Community Procurement) IN-PIU HORTICULTURE- 185018-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres- tank (2,3) IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-09-25 2020-11-28 2021-05-27 Quotations Envelope at Peja cluster Distt. Shimla Diversification ion (WUA - Community Procurement) IN-PIU HORTICULTURE- 185019-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres- tank IDA / 58380 Production and Post Limited 15,589.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Quotations Envelope (4,5,6) at Peja cluster Distt. Diversification ion Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185020-CW-RFQ / Construction of Retaining Component A: Horticulture Pending Request for Single Stage - One Walls ( around tank no IDA / 58380 Production and Post Limited 16,082.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Quotations Envelope 2,3,4,5,6) at Peja cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185023-CW-RFQ / Construction of Tank No. 1 Component A: Horticulture Pending Request for Single Stage - One & 2 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope EACH) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185026-CW-RFQ / Construction of Tank No. Component A: Horticulture Pending Request for Single Stage - One 3&10 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-09-07 2020-11-10 2021-05-09 Quotations Envelope EACH) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) Page 2 IN-PIU HORTICULTURE- 185027-CW-RFQ / Construction Of Retaining Component A: Horticulture Pending Request for Single Stage - One Walls around tank IDA / 58380 Production and Post Limited 12,868.00 0.00 Implementat 2020-09-07 2020-11-10 2021-05-09 Quotations Envelope (1,2,3,10) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185028-CW-RFQ / Construction of Tank No. 4& Component A: Horticulture Pending Request for Single Stage - One 5 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-09-25 2020-11-28 2021-05-27 Quotations Envelope EACH) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185029-CW-RFQ / Construction of Tank No. 6& Component A: Horticulture Pending Request for Single Stage - One 7 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-09-25 2020-11-28 2021-05-27 Quotations Envelope EACH) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185030-CW-RFQ / Construction of Tank No. 8 Component A: Horticulture Pending Request for Single Stage - One & 9 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 10,393.00 0.00 Implementat 2020-10-21 2020-12-24 2021-06-22 Quotations Envelope EACH) at Seema cluster Diversification ion Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185041-CW-RFQ / Construction Of Water Component A: Horticulture Pending Tank 50000Litres-3Nos( Request for Single Stage - One IDA / 58380 Production and Post Limited 16,342.00 0.00 Implementat 2020-08-14 2020-10-17 2021-04-15 Barech , Bahli & Khari) at Quotations Envelope Diversification ion Barech cluster Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185042-CW-RFQ / Construction Of three Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres- Barech- IDA / 58380 Production and Post Limited 16,342.00 0.00 Implementat 2020-10-21 2020-12-24 2021-06-22 Quotations Envelope 2no ,loha- 1no at Barech Diversification ion cluster Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185044-CW-RFQ / Construction of Tank No-1 Component A: Horticulture Pending Request for Single Stage - One (141000 ltr capacity) at IDA / 58380 Production and Post Limited 13,706.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope Ghanduri Cluster Distt. Diversification ion Sirmour (WUA- Community Procurement) IN-PIU HORTICULTURE- 185047-CW-RFQ / Construction of Tank No-2 Component A: Horticulture Pending Request for Single Stage - One and tank 3 (50000 ltr IDA / 58380 Production and Post Limited 11,925.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope capacity) at Ghanduri Diversification ion Cluster Distt. Sirmour (WUA- Community Procurement) Page 3 IN-PIU HORTICULTURE- 185048-CW-RFQ / Construction of Tank No-4 Component A: Horticulture Pending Request for Single Stage - One and tank5 (50000 ltr IDA / 58380 Production and Post Limited 11,925.00 0.00 Implementat 2020-10-28 2020-12-31 2021-06-29 Quotations Envelope capacity) at Ghanduri Diversification ion Cluster Distt. Sirmour (WUA- Community Procurement) IN-PIU HORTICULTURE- 185050-CW-RFQ / Construction of Tank No-6 Component A: Horticulture Pending Request for Single Stage - One and tank 7 (50000 ltr IDA / 58380 Production and Post Limited 11,925.00 0.00 Implementat 2020-10-28 2020-12-31 2021-06-29 Quotations Envelope capacity) at Ghanduri Diversification ion Cluster Distt. Sirmour (WUA- Community Procurement) IN-PIU HORTICULTURE- 185061-CW-RFQ / Component A: Horticulture Pending Construction Of Check Dam Request for Single Stage - One IDA / 58380 Production and Post Limited 19,011.00 0.00 Implementat 2020-08-15 2020-10-18 2021-04-16 at Sanohat Kotali Cluster Quotations Envelope Diversification ion Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185063-CW-RFQ / Construction of Tank No-1 Component A: Horticulture Pending Request for Single Stage - One & Tank No 2 (50000 ltr IDA / 58380 Production and Post Limited 10,234.00 0.00 Implementat 2020-08-15 2020-10-18 2021-04-16 Quotations Envelope capacity) at Sanohat Kotali Diversification ion Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185064-CW-RFQ / Construction of Tank No-3 Component A: Horticulture Pending Request for Single Stage - One and tank 4 (50000 ltr IDA / 58380 Production and Post Limited 10,234.00 0.00 Implementat 2020-10-13 2020-12-16 2021-06-14 Quotations Envelope capacity) at Sanohat Kotali Diversification ion Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185065-CW-RFQ / Construction of Main Water Component A: Horticulture Pending Request for Single Stage - One Tank ( 141000 Lts ) at IDA / 58380 Production and Post Limited 12,543.00 0.00 Implementat 2020-08-15 2020-10-18 2021-04-16 Quotations Envelope Nawna Batwar Cluster Distt. Diversification ion Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185067-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 1 &2 (50000 Lts ) at IDA / 58380 Production and Post Limited 10,436.00 0.00 Implementat 2020-09-24 2020-11-27 2021-05-26 Quotations Envelope Nawna Batwar Cluster Distt. Diversification ion Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185068-CW-RFQ / Construction of water tank 4 Component A: Horticulture Pending Request for Single Stage - One & 5 (50000 lts) at Nawna IDA / 58380 Production and Post Limited 10,436.00 0.00 Implementat 2020-11-23 2021-01-26 2021-07-25 Quotations Envelope Batwar Cluster Distt. Diversification ion Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185070-CW-RFQ / Construction of water tank 6 Component A: Horticulture Pending Request for Single Stage - One & 7 (50000 lts) at Nawna IDA / 58380 Production and Post Limited 10,436.00 0.00 Implementat 2020-11-23 2021-01-26 2021-07-25 Quotations Envelope Batwar Cluster Distt. Diversification ion Sirmour (WUA Community Procurement) Page 4 IN-PIU HORTICULTURE- 185073-CW-RFQ / Excavation for laying & Jointing of Component A: Horticulture Pending HDPE Pipe in gravity main Request for Single Stage - One IDA / 58380 Production and Post Limited 13,970.00 0.00 Implementat 2020-08-15 2020-10-18 2021-04-16 and distribution at Leh Quotations Envelope Diversification ion Naktera Cluster Distt. Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 185083-CW-RFQ / Excavation for laying & Jointing of Component A: Horticulture Pending Request for Single Stage - One HDPE Pipe in gravity main IDA / 58380 Production and Post Limited 10,336.00 0.00 Implementat 2020-08-19 2020-10-22 2021-04-20 Quotations Envelope and distribution at Kheldhar Diversification ion Cluster Distt. Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 185092-CW-RFQ / Construction of Water Component A: Horticulture Pending Request for Single Stage - One Tanks (2,3,4 & 8) ( 50000 IDA / 58380 Production and Post Limited 20,747.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope Lts ) at Kurgal Cluster Diversification ion Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185093-CW-RFQ / Component A: Horticulture Pending Construction of water tank 5 Request for Single Stage - One IDA / 58380 Production and Post Limited 10,373.00 0.00 Implementat 2020-12-07 2021-02-09 2021-08-08 & 9 (50000 lts) at Kurgal Quotations Envelope Diversification ion Cluster Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185095-CW-RFQ / Construction of Main Water Component A: Horticulture Pending Request for Single Stage - One Tank 1 ( 141000 Lts ) IDA / 58380 Production and Post Limited 11,650.00 0.00 Implementat 2020-08-19 2020-10-22 2021-04-20 Quotations Envelope at Dharon ki Dhar Cluster Diversification ion Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185097-CW-RFQ / Construction of Submain water tank 1 ,Submain Component A: Horticulture Pending Request for Single Stage - One Water Tank 2 & Submain IDA / 58380 Production and Post Limited 15,156.00 0.00 Implementat 2020-12-16 2021-02-18 2021-08-17 Quotations Envelope water Tank 3 (50000 lts) at Diversification ion Dharon ki Dhar Cluster Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185109-CW-RFQ / Construction of Tank No. Component A: Horticulture Pending Request for Single Stage - One 1&2 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 11,111.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope each) at Sarali Cluster Diversification ion Distt. Kullu (WUA Community Procurement) IN-PIU HORTICULTURE- 185111-CW-RFQ / Construction of Tank No. 3 Component A: Horticulture Pending Request for Single Stage - One &4 (50,000 Ltr Capacity IDA / 58380 Production and Post Limited 11,111.00 0.00 Implementat 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope each)at Sarali Cluster Distt. Diversification ion Kullu (WUA Community Procurement) Page 5 IN-PIU HORTICULTURE- 186737-CW-RFQ / Excavation in foundation trenches for G.I Pipes from water source to main tank`and Providing Component A: Horticulture Pending Request for Single Stage - One ,laying , jointing and IDA / 58380 Production and Post Limited 16,246.00 0.00 Implementat 2020-09-08 2020-11-04 2021-05-03 Quotations Envelope commisioning of G.I pipes( Diversification ion Including all fitting) for Procurement at Kuhant Distt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186739-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 1 &2 (50000 Lts ) 2 Nos IDA / 58380 Production and Post Limited 10,341.00 0.00 Implementat 2020-09-08 2020-11-04 2021-05-03 Quotations Envelope for Procurement at Kuhant Diversification ion Dostt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186740-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 100000Litres-01 Nos IDA / 58380 Production and Post Limited 10,983.00 0.00 Implementat 2020-09-25 2020-11-21 2021-05-20 Quotations Envelope for Procurement at Chhogtoli Diversification ion Distt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186742-CW-RFQ / Providing Laying, jointing and commissioning of GI Pipes - Fittings And Excavation in Component A: Horticulture Pending Request for Single Stage - One foundation trenches for GI IDA / 58380 Production and Post Limited 45,915.00 0.00 Implementat 2020-09-25 2020-11-21 2021-05-20 Quotations Envelope Pipes from water source to Diversification ion main tank for Procurement at Chhogtoli Distt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186747-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 100000Litres-01 Nos IDA / 58380 Production and Post Limited 10,983.00 0.00 Implementat 2020-12-19 2021-02-14 2021-08-13 Quotations Envelope for Procurement at Chhogtoli Diversification ion Distt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186749-CW-RFQ / Providing Laying, jointing and commissioning of HDPE pipes & Fittings and Component A: Horticulture Pending Excavation in foundation Request for Single Stage - One IDA / 58380 Production and Post Limited 22,016.00 0.00 Implementat 2020-12-19 2021-02-14 2021-08-13 trenches for HDPE Pipes Quotations Envelope Diversification ion from water source to main tank for Procurement at Chhogtoli Distt. Sirmour ( WUA Community Procurement IN-PIU HORTICULTURE- 186750-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 100000 Litres-01 Nos IDA / 58380 Production and Post Limited 11,572.00 0.00 Implementat 2020-09-25 2020-11-21 2021-05-20 Quotations Envelope for Procurement at Kanda Diversification ion Distt. Sirmour ( WUA Community Procurement ) Page 6 IN-PIU HORTICULTURE- 186754-CW-RFQ / Providing Laying, jointing and commissioning of GI Pipes - Fittings And Excavation in Component A: Horticulture Pending Request for Single Stage - One foundation trenches for GI IDA / 58380 Production and Post Limited 43,979.00 0.00 Implementat 2020-09-25 2020-11-21 2021-05-20 Quotations Envelope Pipes from water source to Diversification ion main tank for Procurement at Kanda Distt. Sirmour ( WUA Community Procurement) IN-PIU HORTICULTURE- 186756-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres-02 Nos for IDA / 58380 Production and Post Limited 12,038.00 0.00 Implementat 2020-12-19 2021-02-14 2021-08-13 Quotations Envelope Procurement at Kanda Distt. Diversification ion Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186757-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 100000Litres-01 Nos IDA / 58380 Production and Post Limited 11,572.00 0.00 Implementat 2020-12-19 2021-02-14 2021-08-13 Quotations Envelope for Procurement at Kanda Diversification ion Distt. Sirmour ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186760-CW-RFQ / "Construction of Water Tank 50,000 Ltr Capacity- (3 No) Construction of Retaining Component A: Horticulture Pending Request for Single Stage - One Walls. For Water Tank- IDA / 58380 Production and Post Limited 21,398.00 0.00 Implementat 2020-08-25 2020-10-21 2021-04-19 Quotations Envelope 50000L capacity-3 Nos Diversification ion Package-01" for Procurement at Mihana Distt. Shimla ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186764-CW-RFQ / "Construction of Water Tank 50,000 Ltr Capacity- (3 No) Construction of Retaining Component A: Horticulture Pending Request for Single Stage - One Walls. For Water Tank- IDA / 58380 Production and Post Limited 21,398.00 0.00 Implementat 2020-09-14 2020-11-10 2021-05-09 Quotations Envelope 50000L capacity-3 Nos Diversification ion Package-02"for Procurement at Mihana Distt. Shimla ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186767-CW-RFQ / "Construction of Water Tank 50,000 Ltr Capacity- (2 No) Construction of Retaining Component A: Horticulture Pending Request for Single Stage - One Walls. For Water Tank- IDA / 58380 Production and Post Limited 14,266.00 0.00 Implementat 2020-10-24 2020-12-20 2021-06-18 Quotations Envelope 50000L capacity-2 Nos Diversification ion Package-03" for Procurement at Mihana Distt. Shimla ( WUA Community Procurement ) IN-PIU HORTICULTURE- 186778-CW-RFQ / Construction of Tank ( Component A: Horticulture Pending Request for Single Stage - One 141000 Lts ) 1 Nos for IDA / 58380 Production and Post Limited 11,713.00 0.00 Implementat 2020-09-14 2020-11-10 2021-05-09 Quotations Envelope Procurement at Shilli Distt. Diversification ion Solan ( WUA Community Procurement ) Page 7 IN-PIU HORTICULTURE- 186789-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres-02 Nos for IDA / 58380 Production and Post Limited 10,217.00 0.00 Implementat 2020-09-14 2020-11-10 2021-05-09 Quotations Envelope Procurement at Shilli Distt. Diversification ion Solan ( WUA Community Procurement) IN-PIU HORTICULTURE- 186790-CW-RFQ / Construction Of Water Component A: Horticulture Pending Request for Single Stage - One Tank 50000Litres-02 Nos for IDA / 58380 Production and Post Limited 15,325.00 0.00 Implementat 2020-12-22 2021-02-17 2021-08-16 Quotations Envelope Procurement at Shilli Distt. Diversification ion Solan ( WUA Community Procurement) IN-PIU HORTICULTURE- 187335-CW-RFQ / Laying & Jointing of HDPE Pipe 7 GI Pipe in gravity main Component A: Horticulture Pending Request for Single Stage - One Including accessories & IDA / 58380 Production and Post Limited 27,870.00 0.00 Implementat 2020-09-10 2020-11-13 2021-05-12 Quotations Envelope Valves for procurement at Diversification ion Janjehli (Bhekhali) Distt. Mandi (WUA Community procurement) IN-PIU HORTICULTURE- 187381-CW-RFQ / Procurement of pipe , Component A: Horticulture Pending accessories, flanges and Request for IDA / 58380 Production and Post 29,795.00 0.00 Implementat 2020-09-22 2020-11-25 2021-05-24 valves (GI pipe) at Quotations Diversification ion Mashogal DB Gohar Distt. Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 187383-CW-RFQ / Cost of pipe , accessories, flanges Component A: Horticulture Pending Request for Single Stage - One and valves (HDPE Pipe) for IDA / 58380 Production and Post Limited 10,621.00 0.00 Implementat 2020-09-22 2020-11-25 2021-05-24 Quotations Envelope procurement at Mashogal DB Diversification ion Gohar Distt. Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 187384-CW-RFQ / Cost of pipe , accessories, flanges Component A: Horticulture Pending Request for Single Stage - One and valves for procurement IDA / 58380 Production and Post Limited 34,150.00 0.00 Implementat 2020-09-22 2020-11-25 2021-05-24 Quotations Envelope at Bandhi DB Sadar Distt. Diversification ion Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 187386-CW-RFQ / HDPE Pipe & GI Pipe in gravity main and distribution. Component A: Horticulture Pending Request for Single Stage - One Including accessories & IDA / 58380 Production and Post Limited 21,713.00 0.00 Implementat 2020-09-17 2020-11-20 2021-05-19 Quotations Envelope Valves for procurement at Diversification ion Bhatkidhar in DB Seraj Distt. Mandi (WUA Community Procurement) IN-PIU HORTICULTURE- 189097-CW-RFQ / Procurement of crate wall Component A: Horticulture Pending Request for Single Stage - One and Starting Chamber at IDA / 58380 Production and Post Limited 10,806.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Quotations Envelope Devamanal Distt. Sirmour Diversification ion (WUA Community Procurement) Page 8 IN-PIU HORTICULTURE- 189106-CW-RFQ / Construction of Tank ( Component A: Horticulture Pending 100000 Lts ) 1 Nos and Request for Single Stage - One IDA / 58380 Production and Post Limited 18,018.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Tank 50000 Lts for Quotations Envelope Diversification ion procurement at Devamanal Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189111-CW-RFQ / Construction of Tank ( Component A: Horticulture Pending 100000 Lts ) 1 Nos and Request for Single Stage - One IDA / 58380 Production and Post Limited 18,018.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Tank 50000 Lts for Quotations Envelope Diversification ion Procurement at Devamanal at Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189114-CW-RFQ / Excavation in foundation trenches for G.I Pipes from water source to main tank`and Providing Component A: Horticulture Pending Request for Single Stage - One ,laying , jointing and IDA / 58380 Production and Post Limited 27,002.00 0.00 Implementat 2020-10-12 2020-12-15 2021-06-13 Quotations Envelope commisioning of G.I pipes( Diversification ion Including all fitting) for procurement at Devamanal Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189119-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One 100000 Lts (1 No.) for IDA / 58380 Production and Post Limited 11,815.00 0.00 Implementat 2020-12-23 2021-02-25 2021-08-24 Quotations Envelope Procurement at Devamanal Diversification ion Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189121-CW-RFQ / Excavation in foundation trenches for HDPE Pipes from water source to main tank and Component A: Horticulture Pending Providing ,laying , jointing Request for Single Stage - One IDA / 58380 Production and Post Limited 36,665.00 0.00 Implementat 2020-12-23 2021-02-25 2021-08-24 and commisioning of HDPE Quotations Envelope Diversification ion pipes( Including all fitting) for Procurement at Devamanal Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189128-CW-RFQ / Construction of Water Tank Component A: Horticulture Pending Request for Single Stage - One (50000 Lts ) Nos 1 for IDA / 58380 Production and Post Limited 12,406.00 0.00 Implementat 2021-01-11 2021-03-16 2021-09-12 Quotations Envelope Procurement at Devamanal Diversification ion Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189132-CW-RFQ / Procurement of crate wall (2 Component A: Horticulture Pending Request for Single Stage - One Nos ) and intake chamber( IDA / 58380 Production and Post Limited 15,150.00 0.00 Implementat 2020-09-12 2020-11-15 2021-05-14 Quotations Envelope 3 Nos) at Kinnu Ponog Diversification ion Distt Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189245-CW-RFQ / Procurement of Main Water Component A: Horticulture Pending Request for Single Stage - One Tank ( 141000 Lts ) at IDA / 58380 Production and Post Limited 14,222.00 0.00 Implementat 2020-09-12 2020-11-15 2021-05-14 Quotations Envelope Kinnu Panog Distt. Sirmour Diversification ion (WUA Community Procurement) Page 9 IN-PIU HORTICULTURE- 189248-CW-RFQ / Providing ,laying , jointing and commisioning of G.I pipes( Including all fitting) and Component A: Horticulture Pending Request for Single Stage - One Excavation in foundation IDA / 58380 Production and Post Limited 19,895.00 0.00 Implementat 2020-09-12 2020-11-15 2021-05-14 Quotations Envelope trenches for G.I Pipes from Diversification ion water source to main tank for Procurement at Kinnu Panog Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189249-CW-RFQ / Procurement of Main Water Component A: Horticulture Pending Request for Single Stage - One Tank ( 141000 Lts ) at IDA / 58380 Production and Post Limited 14,222.00 0.00 Implementat 2020-09-12 2020-11-15 2021-05-14 Quotations Envelope Kinnu Panog Distt. Sirmour Diversification ion (WUA Community Procurement ) IN-PIU HORTICULTURE- 189251-CW-RFQ / Component A: Horticulture Pending Procurement of Water Tank Request for Single Stage - One IDA / 58380 Production and Post Limited 14,175.00 0.00 Implementat 2020-11-10 2021-01-13 2021-07-12 2&3 (50000 Lts ) at Kinnu Quotations Envelope Diversification ion Panog Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189253-CW-RFQ / Component A: Horticulture Pending Procurement of Water Tank Request for Single Stage - One IDA / 58380 Production and Post Limited 14,175.00 0.00 Implementat 2021-01-08 2021-03-13 2021-09-09 5&6 (50000 Lts ) at Kinnu Quotations Envelope Diversification ion Panog Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 189255-CW-RFQ / Laying, Jointing and Commissioning Component A: Horticulture Pending of HDPE pipes Except Tank Request for Single Stage - One IDA / 58380 Production and Post Limited 34,694.00 0.00 Implementat 2020-11-25 2021-01-28 2021-07-27 01 to junction N for Quotations Envelope Diversification ion Procurement at Guwadi Distt. Chamba (WUA Community Procurement) IN-PIU HORTICULTURE- 189257-CW-RFQ / Excavation of foundation trenches. Component A: Horticulture Pending Except Tank 01 to junction Request for Single Stage - One IDA / 58380 Production and Post Limited 13,157.00 0.00 Implementat 2020-11-25 2021-01-28 2021-07-27 N for Procurement at Quotations Envelope Diversification ion Guwadi Distt. Chamba (WUA Community Procurement) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PIU HORTICULTURE- 95346-GO-RFB / Purchase of Secateurs & Pruning saw for Component A: Horticulture Single Stage - Two on farm demo of Scientific IDA / 58380 Production and Post Request for Bids Open - National 19,285.00 0.00 Canceled 2019-02-23 2019-02-28 2019-04-11 2019-06-24 2019-07-29 2020-01-25 Envelope Management Practices/ Diversification Canopy Management at Panchyat Level Page 10 IN-PIU HORTICULTURE- 95379-GO-RFB / Purchase of HDP - Pipes for clusters (Re-modelling improvement Component A: Horticulture Single Stage - Two and strengthening of IDA / 58380 Production and Post Request for Bids Open - National 342,857.00 0.00 Canceled 2019-03-25 2019-03-30 2019-05-11 2019-07-24 2019-08-28 2020-02-24 Envelope community irrigation systems Diversification and Identifications of the Schemes in Collaboration with IPH and Community) IN-PIU HORTICULTURE- 99196-GO-RFQ / Purchase of HDP - Pipes for cluster Sunah Batahar Janjheli Block Distt.-Mandi (Re- Component A: Horticulture Request for Single Stage - One modelling improvement and IDA / 58380 Production and Post Limited 92,857.14 0.00 Canceled 2019-03-06 2019-02-27 2019-05-01 2019-10-28 Quotations Envelope strengthening of community Diversification irrigation systems and Identifications of the Schemes in Collaboration with IPH and Community) IN-PIU HORTICULTURE- 151603-GO-DIR / Purchase of Secateurs & Pruning saw Component A: Horticulture for on farm demo of IDA / 58380 Production and Post Direct Selection Direct 19,718.00 9,101.67 Signed 2020-01-01 2020-01-02 2020-01-06 2020-05-29 2020-02-10 2020-06-23 2020-08-08 Scientific Management Diversification Practices/ Canopy Management at Panchyat Level IN-PIU HORTICULTURE- 99201-GO-RFQ / Purchase of Secateurs & Pruning saw for Component A: Horticulture Request for Single Stage - One on farm demo of Scientific IDA / 58380 Production and Post Limited 19,285.71 0.00 Canceled 2019-07-25 2019-09-19 2020-03-17 Quotations Envelope Management Practices/ Diversification Canopy Management at Panchyat Level IN-PIU HORTICULTURE- Component A: Horticulture 155691-GO-DIR / IDA / 58380 Production and Post Direct Selection Direct 171,500.00 162,966.94 Signed 2020-01-30 2020-01-23 2020-02-04 2020-02-04 2020-03-10 2020-02-06 2020-09-06 Procurement of Total Station Diversification with GNSS IN-PIU HORTICULTURE- 185013-GO-RFQ / Supplying of HDPE (High Density Component A: Horticulture Pending Polyethylene) pipes along Request for Single Stage - One IDA / 58380 Production and Post Limited 42,846.00 0.00 Implementati 2020-08-05 2020-10-08 2021-04-06 with fitting and accessories Quotations Envelope Diversification on for Majhewali cluster Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185022-GO-RFQ / Supplying of HDPE (High Density Component A: Horticulture Pending Polyethylene) pipes along Request for Single Stage - One IDA / 58380 Production and Post Limited 27,636.00 0.00 Implementati 2020-08-12 2020-10-07 2021-04-05 with fitting and accessories Quotations Envelope Diversification on for peja cluster Distt. Shimla (WUA - Community Procurement) IN-PIU HORTICULTURE- 185031-GO-RFQ / HDPE PIPES of different pressure Component A: Horticulture Pending ratings & Fitting (Flanged Request for Single Stage - One IDA / 58380 Production and Post Limited 16,439.00 0.00 Implementati 2020-08-05 2020-09-30 2021-03-29 Connection) and Accessories Quotations Envelope Diversification on for HDPE Pipe for Seema cluster Distt. Shimla (WUA - Community Procurement) Page 11 IN-PIU HORTICULTURE- 185051-GO-RFQ / GI pipes 65 mmMedium Grade ;IS Component A: Horticulture Pending 6392-1971(Providing, laying, Request for Single Stage - One IDA / 58380 Production and Post Limited 25,217.00 0.00 Implementati 2020-08-15 2020-10-18 2021-04-16 jointing and commisning of Quotations Envelope Diversification on GI pipe line) for Ghanduri Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185054-GO-RFQ / HDPE pipes 110mm PN10 PE 100 and 50 mm PN 10 PE 100 Component A: Horticulture Pending ;IS 4984 (Providing, laying, Request for Single Stage - One IDA / 58380 Production and Post Limited 15,443.00 0.00 Implementati 2020-10-28 2020-12-31 2021-06-29 jointing and commisning of Quotations Envelope Diversification on HDPE pipe line) for Ghanduri Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185056-GO-RFQ / HDPE pipes 110mm PN10 PE 100 and 50 mm PN 10 PE 100 Component A: Horticulture Pending ;IS 4984 (Providing, laying, Request for Single Stage - One IDA / 58380 Production and Post Limited 23,015.00 0.00 Implementati 2020-08-15 2020-10-18 2021-04-16 jointing and commisning of Quotations Envelope Diversification on HDPE pipe line) for Sanohat Kotali Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185057-GO-RFQ / Providing ,laying , jointing and Component A: Horticulture Pending commisioning of G.I pipes( Request for Single Stage - One IDA / 58380 Production and Post Limited 13,333.00 0.00 Implementati 2020-08-15 2020-10-18 2021-04-16 Including all fitting) for Quotations Envelope Diversification on Nawna Batwar Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185058-GO-RFQ / Providing ,laying , jointing and commisioning of HDPE pipes( Including all fittin Component A: Horticulture Pending Request for Single Stage - One 50MMPN10PE100 63MM IDA / 58380 Production and Post Limited 19,631.00 0.00 Implementati 2020-11-23 2021-01-26 2021-07-25 Quotations Envelope PN10 PE100 75MM Diversification on PN10PE100 for Nawna Batwar Cluster Distt. Sirmour (WUA Community Procurement) IN-PIU HORTICULTURE- 185077-GO-RFQ / Providing, HDPE Pipe Including Component A: Horticulture Pending Request for Single Stage - One FITTINGS & accessories for IDA / 58380 Production and Post Limited 25,203.00 0.00 Implementati 2020-08-16 2020-10-19 2021-04-17 Quotations Envelope Leh Naktera Cluster Distt Diversification on Mandi (WUA Comunity Procurement) IN-PIU HORTICULTURE- 185081-GO-RFQ / Providing, HDPE Pipe Including Component A: Horticulture Pending Request for Single Stage - One FITTINGS & accessories for IDA / 58380 Production and Post Limited 17,082.00 0.00 Implementati 2020-08-17 2020-10-20 2021-04-18 Quotations Envelope Kheldhar Cluster Distt Diversification on Mandi (WUA Comunity Procurement) Page 12 IN-PIU HORTICULTURE- 185085-GO-RFQ / Providing Laying, Jointing and testing Component A: Horticulture Pending of HDPE Pipe Including Request for Single Stage - One IDA / 58380 Production and Post Limited 17,654.00 0.00 Implementati 2020-08-13 2020-10-16 2021-04-14 accessories & Valves for Quotations Envelope Diversification on Riyada-1 Cluster Distt Mandi (WUA Comunity Procurement) IN-PIU HORTICULTURE- 185089-GO-RFQ / Providing Laying, Jointing and testing Component A: Horticulture Pending of HDPE Pipe Including Request for Single Stage - One IDA / 58380 Production and Post Limited 20,453.00 0.00 Implementati 2020-08-13 2020-10-16 2021-04-14 accessories & Valves for Quotations Envelope Diversification on Riyada-2 Cluster Distt Mandi (WUA Comunity Procurement) IN-PIU HORTICULTURE- 185090-GO-RFQ / Providing ,laying , jointing and commisioning of G.I pipes Component A: Horticulture Pending Request for Single Stage - One 65mm Medium Grade( IDA / 58380 Production and Post Limited 17,165.00 0.00 Implementati 2020-08-15 2020-10-18 2021-04-16 Quotations Envelope Including all fitting) for Diversification on Kurgal Cluster Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185100-GO-RFQ / Providing ,laying , jointing and Component A: Horticulture Pending commisioning of G.I pipes( Request for Single Stage - One IDA / 58380 Production and Post Limited 10,326.00 0.00 Implementati 2020-08-20 2020-10-23 2021-04-21 Including all fitting) for Quotations Envelope Diversification on Dharon ki Dhar Cluster Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185102-GO-RFQ / Providing ,laying , jointing and commisioning of HDPE Component A: Horticulture Pending Request for Single Stage - One pipes( Including all fitting) IDA / 58380 Production and Post Limited 14,989.00 0.00 Implementati 2021-05-17 2021-07-20 2022-01-16 Quotations Envelope 63MM PN10, PE100 for Diversification on Dharon ki Dhar Cluster Distt. Solan (WUA Community Procurement) IN-PIU HORTICULTURE- 185107-GO-RFQ / GMS Tubes/ G.I Pipes 80 mm Component A: Horticulture Pending Medium class GMS Tubes/ Request for Single Stage - One IDA / 58380 Production and Post Limited 25,269.00 0.00 Implementati 2020-10-17 2020-12-20 2021-06-18 G.I Pipes 80 mm Medium Quotations Envelope Diversification on class for Sarali Cluster Distt. Kullu (WUA Community Procurement) IN-PIU HORTICULTURE- 186771-GO-RFQ / Supplying of GMS pipe (Quality Medium/ B Type) screwed & Component A: Horticulture Pending socketed i/c all type of Request for Single Stage - One IDA / 58380 Production and Post Limited 12,381.00 0.00 Implementati 2020-10-16 2020-12-19 2021-06-17 fitting such as bends Quotations Envelope Diversification on confirming to IS:1239-2004 for procurement at Mihana Distt. Shimla ( WUA Community Procurement) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 13 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PIU HORTICULTURE- 184892-CS-QCBS / Hiring of Component A: Horticulture Quality And Cost- Internal Auditors (CA) for IDA / 58380 Production and Post Open - National 200,000.00 0.00 Under Review 2020-08-05 2020-07-31 2020-08-26 2020-10-09 2020-11-06 2020-12-06 2021-01-10 2021-02-14 2022-02-14 Based Selection Water User Association Diversification (WUA) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 14