Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Community 5.48 60 No Post procured by infrastructur Communes/Sa es ngkats individually for the whole life of the project June 12, 2017 Procureme 0.92 8 No Post will be nt of procured vehicles, centrally at the office beginning of project equipment, implementation office (shopping furniture, method) motorcycle s, etc. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Consultant Above US$ 400,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimated Pack Review Comments No. Cost ages by Bank US$ million (Prior / Post) Producer Group 0.34 1 Post QCBS method Mobilization for Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact June 12, 2017 survey, and External financial auditing Individual consultants 2.93 126 Post Selection of for supporting the individual national level and sub- consultant. national level project entities (finance, procurement, infrastructure, community development, micro- finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2020-09-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Executing Agency(ies): Ministry of Interior WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Contract Description Component Review Type Method Document Amount Amount qualification Document / Signed Contract No. Approach Process (Y/N) Risk Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Completion Type (US$) (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KH-MOI-99874-CW-RFQ / Pending Component 3: Project Request for Single Stage - One Office Renovation at PCO- IDA / 59600 Post Open - National 30,000.00 0.00 Implementa 2019-03-06 2019-04-17 2019-05-17 Management Quotations Envelope MOI tion KH-MOI-99875-CW-CDD / The rehabilitation laterite road (Length 2400m, Width Component 1: Improving Community Pending 4.00m, 0.15m thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 28,341.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Single Pipe Culvert Ø 1.0m and Vulnerable Households Development tion (2 units) for Anlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / The rehabilitation laterite road ( Length 1500m, Width Component 1: Improving Community Pending 4.00m, 0.15m Thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,208.00 0.00 Implementa 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 2019-08-19 Construction of Box Culver and Vulnerable Households Development tion heigth 2m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (Length 2419m, Width IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 25,921.00 0.00 Implementa 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 3.50m, 0.15m thick) for Chi and Vulnerable Households Development tion Kraeng, Chi Kraeng. KH-MOI-99880-CW-CDD / The rehabilitation laterite road (Length 2090m, Width 4.00m, 0.15m thick) and Component 1: Improving Community Pending Construction of Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,721.00 0.00 Implementa 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 Culvert Ø 0.6m (1 unit), and Vulnerable Households Development tion Single Pipe Culvert Ø 0.8m (1 unit) and Single Pipe Culvert Ø 1.0m (1unit) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / The rehabilitation laterite road (Length 1550m, Width 4.00m, 0.15m thick), Single Component 1: Improving Community Pending Pipe Culvert Ø 1.0m (1unit) IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,965.00 0.00 Implementa 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-09-19 and Construction of Double and Vulnerable Households Development tion Pipe Culvert Ø 0.8m (5units), for Ballangk, Prasat Bakong. KH-MOI-99887-CW-CDD / Construction of Box Culvert heigth 2m with stop Log (1unit), Box Culvert heigth Component 1: Improving Community Pending 1.5m with stop Log (1unit) IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,896.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culver Ø 0.8m with and Vulnerable Households Development tion Stop Log (1unit) and Single Pipe Culvert Ø 0.8m (4 unit) for Sasar Sdam, Puok. KH-MOI-99888-CW-CDD / Construction of Reinforced Component 1: Improving Community Pending Concrete Road (Lengh 260m, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,417.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 width 5.00m, 0.15m thick) and Vulnerable Households Development tion for Kampong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / The rehabilitation ponds size (60mx30mx5m), Component 1: Improving Community Pending (30mx25mx5m), IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,949.00 0.00 Implementa 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 (40mx20mx5m), and Vulnerable Households Development tion (50mx50mx5m) for Slaeng Spean, Srei Snam. Total:4 Places Page 1 KH-MOI-99891-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (1.450km) and Single IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 32,660.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culvert Ø 1.0m (3 and Vulnerable Households Development tion units) for Svay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / The rehabilitation laterite road ( Length 2520m, Width Component 1: Improving Community Pending 4.00m, 0.15 Thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 34,064.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Construction of Single Pipe and Vulnerable Households Development tion Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / The rehabilitation laterite road (Length 1080m, Width 4.00m, 0.15m thick) and Component 1: Improving Community Pending Construction of Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 27,869.20 0.00 Implementa 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 2019-08-05 Culvert Ø 0.8m (1 unit) and and Vulnerable Households Development tion Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Construction of Reinforced Component 1: Improving Community Pending Concrete Road (Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 48,510.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 445m, Width 3.50m, 0.15m and Vulnerable Households Development tion thick) for khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (Length 2600m, Width IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,932.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 5.00m, 0.15m thick) for and Vulnerable Households Development tion Klang Hay, Srei Snam. Total: 2.600 km KH-MOI-110153-CW-CDD / Construction:1- Reinforcement concrete road:(L353m, W 4m, T0.15m) Component 1: Improving Community Pending and drainage system IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 89,712.00 0.00 Implementa 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 (L353m, 0.6m ) and 2- and Vulnerable Households Development tion Reinforcement concrete road (L357m, W 4m, T 0.15m) in Sangkat Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / Construction of Reinforcement concrete road and Drainage System: 1- Component 1: Improving Community Pending Road (100m) , 2-Road IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 98,080.00 0.00 Implementa 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 (171m ), 3-Road (52m), 4- and Vulnerable Households Development tion Road(88m) ,5- Road (90m), 6- Road (93m) and 7-Road (L128m) in Sangkat Prey Veaeng, Khan Dangkao KH-MOI-110159-CW-CDD / Construction of reinforcement concrete road:(466m, width 5m, thickness 0.15m ), 2- Component 1: Improving Community Pending Road:(312m, width 4m, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 105,204.00 0.00 Implementa 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 thickness 0.15m ) and and Vulnerable Households Development tion drainage system:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110165-CW-CDD / Construction of reinforcement concrete road and and drainage system in Prey Spueu & Prey Component 1: Improving Community Pending Sandaek, Sangkat Chaom IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 84,579.00 0.00 Implementa 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 Chau 2, Khan Por Sen and Vulnerable Households Development tion Chey (663m) and drainage system (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / Construction of reinforcement concrete: 1- Road(124m), 2- Road (137m). Component 1: Improving Community Pending 3- Road (117m ). 4- IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,250.00 0.00 Implementa 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 Installation of Sola street and Vulnerable Households Development tion lighting and poles (117m), and (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Ampov Page 2 KH-MOI-110155-CW-CDD / Construction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3-Drainage Component 1: Improving Community Pending system:(9m), 4-Installation of IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 28,703.49 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 Sola street lighting and and Vulnerable Households Development tion poles (120m),(439m),(439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,Khan Russey Keo KH-MOI-110151-CW-CDD / Construction: 1- Reinforcement concrete road (340m) and drainage system:(448m), 2-Road (L130m) and drainage Component 1: Improving Community Pending system (130m), 3-Road IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 171,670.08 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 (120m) and drainage and Vulnerable Households Development tion system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Trapeang Krasang, Khan Por Sen Chey KH-MOI-110147-CW-CDD / Construction:1-Reinforcement concrete road, Drainage (L171m),Installation of Sola street lighting and Component 1: Improving Community Pending poles(171m), 2-Reinforcement IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 43,476.23 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 concrete and Vulnerable Households Development tion road(147m),drainage(48m), Installation of Sola street lighting and poles (147m) in Sangkat Khmuonh, Khan Saen Sokh KH-MOI-110144-CW-CDD / Construction: 1- Reinforcement concrete road:(L262m, w 2.6m, T 0.12m) ,Drainage Component 1: Improving Community Pending system:(262m,0.6m), 2- IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 71,818.97 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 Installation:(18 Sola street and Vulnerable Households Development tion lighting and poles for 262m) and 3-Concrete bridge: (L206m, width1.50m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / Construction of reinforcement concrete:1- road:(L102m, width 2.5m, thickness 0.12m) and Component 1: Improving Community Pending drainage system:(114m).2- IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 37,878.83 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 road:(169m, width 3.5m, and Vulnerable Households Development tion thickness 0.15m) and drainage system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork KH-MOI-110173-CW-CDD / Construction of reinforcement concrete: 1- Road(110m, width 4m, Component 1: Improving Community Pending thickness 0.15m), 2- IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,281.06 0.00 Implementa 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 Road(100m),2-Installation of and Vulnerable Households Development tion Sola street lighting and poles (250m) in Khtor,Sangkat Preak Leap, Khan Chroy Changvar KH-MOI-110168-CW-CDD / Construction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and drainage Component 1: Improving Community Pending system (77m),3- road(261m) IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 73,334.73 0.00 Implementa 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 and drainage (207m),4- and Vulnerable Households Development tion Installation of Sola street lighting and poles(158m), (77m)and (261m) in Sangkat Chak Angrae Leu, Khan Mean Chey KH-MOI-140916-CW-CDD / Repair Dike 78 for Sangkat Component 1: Improving Community Pending Krabei Riel, Siem Reap IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,005.00 0.00 Implementa 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 2020-02-27 Municipality ( Size 2.95Km and Vulnerable Households Development tion length, 4.00m width, 2.00m height) Page 3 KH-MOI-140917-CW-CDD / Construction of Reinforced Concrete Road for Kampong Component 1: Improving Community Pending Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,248.00 0.00 Implementa 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 2020-02-27 Nikom District ( Size and Vulnerable Households Development tion 0.25Km length, 5.00m width, 0.15m thick) KH-MOI-140918-CW-CDD / Upgrade Earth Road to Laterite Pavement for Sangkat Chong Khneas, Component 1: Improving Community Pending Siem Reap Municipality ( IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 27,191.00 0.00 Implementa 2019-10-18 2019-10-25 2019-11-08 2019-11-15 2019-11-29 2020-02-27 Size 0.80Km length, 4.00m and Vulnerable Households Development tion width, 0.15m thick), including 1 unit of culvert construction, 0.60m Diameter, 16.00m length. KH-MOI-146743-CW-CDD / Digging Community Pond one place (size 100mx75mx6.00m) including fence construction and Earth Component 1: Improving Community Pending Dam with laterite pavement IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 45,730.00 0.00 Implementa 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 2020-04-16 4.00 meter width, 2.00 and Vulnerable Households Development tion meter heigh surrounding the pond and 2 reinforced concrete stairs, access laterite road 170m length, 4.00m wid KH-MOI-146745-CW-CDD / Unlined Earth Canal Rehabilitation with 1500m Length, 2m bed, 1.60m Depth including the Component 1: Improving Community Pending Construction of Cented IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 41,288.00 0.00 Implementa 2019-12-06 2019-12-13 2019-12-27 2020-01-03 2020-01-17 2020-04-16 Causeway with pipe 0.80m and Vulnerable Households Development tion diameter, 8m length, 4m width 5 places and Construction of Trapezoidal Section Lined Concrete canal with 16m length, 2 KH-MOI-162028-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Sangkat Svay Dangkum, Siem Reap Municipality (For Component 1: Improving Community Pending line 1: 0.87 Km length, 4.00 IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 22,511.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 m width, 0.15m thick and Vulnerable Households Development tion including 1 unit of single culvert construction, 1.00m Diameter, 7.00m length ( For line 2: 0.60 Km le KH-MOI-162399-CW-CDD / Reinforced Concrete Road for Component 1: Improving Community Pending Kampong Thkov Commune, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,950.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 Kralanh District ( 0.26 Km and Vulnerable Households Development tion length,4.50m Width, 0.15 thick). KH-MOI-162400-CW-CDD / Earth Road Repair and Laterite Pavement for Svay Leu Commune, Svay Leu Component 1: Improving Community Pending District ( 3.70 Km length, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 55,881.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 4.00 m width, 0.15m thick), and Vulnerable Households Development tion including 2 units of double culvert construction, 1.00 m Diameter, 6.00 m length. KH-MOI-162401-CW-CDD / Earth Road Repair and Laterite Pavement for Ta Siem Commune, Svay Leu Component 1: Improving Community Pending District ( 2.335 Km length, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 35,980.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 4.50 m width, 0.15m thick), and Vulnerable Households Development tion including 1 unit of single culvert construction, 1.00m Diameter, 6.00 m length. KH-MOI-162402-CW-CDD / Earth Road Repair and Laterite Pavement for Boeng Mealea Commune, Svay Leu Component 1: Improving Community Pending District ( 2.80 Km length, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 44,027.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 5.00 m width, 0.15m thick), and Vulnerable Households Development tion including 2 units of single culvert construction, 0.60m&0.80 Diameter, 6.00 m length. Page 4 KH-MOI-162403-CW-CDD / Earth Road Repair and Laterite Pavement 3 lines for Peak Snaeng Commune, Angkor Thom District ( For Component 1: Improving Community Pending Line1: 1.95 Km length, 4.00 IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 54,983.00 0.00 Implementa 2020-03-10 2020-03-17 2020-03-31 2020-04-07 2020-04-21 2020-07-20 m width, 0.15m thick and Vulnerable Households Development tion including 2 units of single culvert construction, 1.00 m Diameter, 5.00 m length & 1 unit of single culver KH-MOI-162406-CW-CDD / Earth Road Repair and Laterite Pavement 5 lines for Kampong Kdei Component 1: Improving Community Pending Commune, Chi kraeng IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 59,812.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 District, ( Total length and Vulnerable Households Development tion 3190m, 4.00m width, 0.15 thick including 1 unit of Double box culvert 2.00m heigh, 6.00m length) KH-MOI-162407-CW-CDD / Earth Road Repair and Literate Pavement 3 lines for Chi kraeng Commune, Chi kraeng District, ( Total Component 1: Improving Community Pending length 1680m, 4.00m, 0.15 IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 39,802.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 thick width including 2 and Vulnerable Households Development tion units of single pipe culvert 0.60m diameter, 6.00m length and 3 units of single pipe culvert 1.00m diam KH-MOI-162408-CW-CDD / Reinforced Concrete Bridge Component 1: Improving Community Pending Construction for Tram Sasar IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,100.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 Commune, Srei Snam and Vulnerable Households Development tion District ( 4.00m Heigh, 11.00m length, 4.00m width). KH-MOI-162409-CW-CDD / Earth Road Repair and Laterite Pavement for Mean Chey Commune, Brasat Component 1: Improving Community Pending Bakong District ( Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 31,649.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 1800m, 4.00m width, 0.15 and Vulnerable Households Development tion thick and 1 unit of single box culvert with water gate, 2.50m heigh, 5.90m length ) KH-MOI-162410-CW-CDD / Earth Road Repair and Laterite Pavement for Roluos Commune, Brasat Bakong District, ( Length Component 1: Improving Community Pending 4625m, 4.00m width, 0.15 IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 49,078.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 thick including 1 units of and Vulnerable Households Development tion single pipe culvert 0.60m diameter, 6.00m length and 2 units of single pipe culvert 0.80m diameter, 6.00m len KH-MOI-162412-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Kantreang Commune, Component 1: Improving Community Pending Brasat Bakong District, ( IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 19,225.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 Total length 1500m, 4.00m and Vulnerable Households Development tion width, 0.15 thick including 1 unit of single pipe culvert 0.80m diameter, 5.00m length) KH-MOI-162414-CW-CDD / Earth Road Repair and Laterite Pavement for Ballangk Commune, Brasat Component 1: Improving Community Pending Bakong District, ( Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 20,670.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 985m, 4.00m width, 0.15 and Vulnerable Households Development tion thick including 3 units of single pipe culvert 0.60m diameter, 5.00m length) KH-MOI-162415-CW-CDD / Earth Road Repair and Component 1: Improving Community Pending Laterite Pavement for Dan IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 26,913.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 Run Commune, Sotr Nikom and Vulnerable Households Development tion District, ( Length 2600m, 4.00m width, 0.15m thick ) Page 5 KH-MOI-162416-CW-CDD / Laterite Road Construction for Prey Chruk Commune, Pouk District ( 3614 m length, 4.00m width, 0.15 Component 1: Improving Community Pending thick including 5 units of IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 62,129.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 single pipe culvert, 0.60m and Vulnerable Households Development tion Diameter, length 6.00m and 1 unit of single pipe culvert 0.80m diameter, length 6.00m ) KH-MOI-162417-CW-CDD / Laterite Road Construction for Doun Kaev Commune, Pouk District ( 2500 m length, 4.00m width, 0.15 Component 1: Improving Community Pending thick including 1 unit of IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 49,293.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 single pipe culvert,0.80m and Vulnerable Households Development tion Diameter length 6.00m and 1 unit of single pipe culvert 1.00m diameter, length 6.00m ) KH-MOI-162418-CW-CDD / Digging Community Pond 2 places for Kdei Run Commune, Pouk District Component 1: Improving Community Pending including fence construction IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 34,396.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 surrounding the pond and 2 and Vulnerable Households Development tion doors ( Size: 60mx33mx5m and 60mx24mx5m) KH-MOI-162419-CW-CDD / Reinforced Concrete Road Construction for Khnat Commune, Pouk District ( Component 1: Improving Community Pending 400m length, 5.00m width, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 57,625.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 0.15m thick including 1 unit and Vulnerable Households Development tion of single pipe culvert 0.60 diameter, 6.00m length and 1 unit of single pipe culvert 0.80 diameter, 6.00m length KH-MOI-162420-CW-CDD / Laterite Road Construction for Sasar Sdam Commune, Component 1: Improving Community Pending Pouk District ( 1500m IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 39,060.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 length, 5.00m width, 0.15 and Vulnerable Households Development tion thick including 2 units of single pipe culvert,0.80m Diameter length 6.00m) KH-MOI-162421-CW-CDD / Laterite Road Construction for Lvea Commune, Pouk Component 1: Improving Community Pending District ( 2200m length, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 38,419.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 4.00m width, 0.15 thick and Vulnerable Households Development tion including 3 units of single pipe culvert,0.60m Diameter length 6.00m) KH-MOI-162422-CW-CDD / Unlined Earth Canal Rehabilitation for Spean Tnoat Commune, Chi Component 1: Improving Community Pending Kraeng District ( 2100m IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 33,487.00 0.00 Implementa 2020-03-20 2020-03-27 2020-04-10 2020-04-17 2020-05-01 2020-07-30 length, 1.20m bed, 1.20 and Vulnerable Households Development tion Depth including of 6 units of single pipe culvert with water gate) KH-MOI-162423-CW-CDD / Reinforced Concrete Bridge upgrade in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Total length Component 2: Improving Community Pending 73m, 1.20m width, 1.50 IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 65,309.00 0.00 Implementa 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 2020-08-09 heigh, 0.07m thickness), and Vulnerable Households Development tion Reinforced Concrete Road in Phum 20, Sangkat Srah Chak, Khan Daun Penh ( Total length 60m, 2.40m widt, 0.15m thi KH-MOI-162424-CW-CDD / Reinforced Concrete Road in Phum 3, Sangkat Boeung Kak 1, Khan Toul Kork( Total length 46m, 2m width, Component 2: Improving Community Pending 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 9,333.00 0.00 Implementa 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 2020-08-09 Drainage system (Total and Vulnerable Households Development tion length 34m, 0.6m diameter). Reinforced concrete road in Phum 4, Sangkat Boeung Kak 1, Khan Toul kork(Total le Page 6 KH-MOI-162425-CW-CDD / Reinforced Concrete Road in Talei Village, Sangkat Dangkao, Khan Dangkao( Total length 149m, 3.5m Component 2: Improving Community Pending width, 0.15m thickness) and IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 50,729.00 0.00 Implementa 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 2020-08-16 Drainage system (Total and Vulnerable Households Development tion length 67m, 0.6m diameter). Reinforced concrete road in Khva Village, Sangkat Dangkao, Khan Dangkao(Total KH-MOI-162426-CW-CDD / Reinforced Concrete Road in Component 2: Improving Community Pending Toap Boss Village, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 40,542.00 0.00 Implementa 2020-04-06 2020-04-13 2020-04-27 2020-05-04 2020-05-18 2020-08-16 Prey Veang, Khan Dangkao( and Vulnerable Households Development tion Total length 310m, 4m width, 0.15m thickness) KH-MOI-162428-CW-CDD / Reinforced Concrete Road in Preak Leap Village, Sangkat Preak Leap, Khan Chroy Component 2: Improving Community Pending Changvar( Total length IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 55,323.00 0.00 Implementa 2020-03-30 2020-04-06 2020-04-20 2020-04-27 2020-05-11 2020-08-09 287m, 3.5m width, 0.15m and Vulnerable Households Development tion thickness) and drainage system (Total length 287m, 0.6m diameter) KH-MOI-162429-CW-CDD / Reinforced Concrete Road in Sen Sok Ty Mouy Village, Component 2: Improving Community Pending Sangkat Khmounh, Khan IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 111,552.00 0.00 Implementa 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 2020-08-13 Sen Sok( Total length 547m, and Vulnerable Households Development tion 4m width, 0.15m thickness) and drainage system (Total length 550m, 0.6m diameter) KH-MOI-162430-CW-CDD / Reinforced Concrete Road in Samaki 5 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length Component 2: Improving Community Pending 196m, 6m width, 0.15m IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 64,039.00 0.00 Implementa 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 2020-08-13 thickness) Reinforced and Vulnerable Households Development tion Concrete Road in Samaki 6 Village, Sangkat Trapeang Krasang, Khan Pou Sen Chey( Total length 121m, 4m & 5m KH-MOI-162432-CW-CDD / Reinforced Concrete Road in Chrey Koang Village, Sangkat Choam Chau 2, Khan Pou Sen Chey( Total Component 2: Improving Community Pending length 287m, 5m width, IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 177,610.00 0.00 Implementa 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 2020-08-13 0.15m thickness) and and Vulnerable Households Development tion Drainage System(Total Length 287, 0.6m diameter) , Reinforced Concrete Road in Prey Lvea Village, Sangkat Choam Ch KH-MOI-162433-CW-CDD / Reinforced Concrete Road in Andong 1 & Andong 2 Villages, Sangkat Kork Component 2: Improving Community Pending Roka, Khan Peeak Phnov( IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 42,245.00 0.00 Implementa 2020-04-03 2020-04-10 2020-04-24 2020-05-01 2020-05-15 2020-08-13 Total length 211m, 4m and Vulnerable Households Development tion width, 0.15m thickness) and Drainage System(Total Length 211m, 0.6m diameter) KH-MOI-162435-CW-CDD / Reinforced Concrete Road in Daeum Sleng Village, Component 2: Improving Community Pending Sangkat Chbar Ampov 2, IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 28,928.00 0.00 Implementa 2020-04-10 2020-04-17 2020-05-01 2020-05-08 2020-05-22 2020-08-20 Khan Chbar Ampov ( Total and Vulnerable Households Development tion length 234m, 3.4m width, 0.15m thickness) KH-MOI-169345-CW-CDD / Solar LED Power Street lighting in Phum 2, Sangkat Srah Chak, Khan Daun Pend ( Total sets 22 Component 2: Improving Community Pending sets), Solar LED Power IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 13,469.00 0.00 Implementa 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 2020-09-14 Street lighting in Phum 22, and Vulnerable Households Development tion Sangkat Srah Chak, Khan Daun Pend ( Total sets 11 sets), Solar LED Power Street lighting in Phum 24, Sangkat Page 7 KH-MOI-169346-CW-CDD / Solar LED Power street Component 2: Improving Community Pending lighting in Phum 8, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 3,613.00 0.00 Implementa 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 2020-09-14 Boeung Kak 1, Khan Toul and Vulnerable Households Development tion Kork( Total sets 11 sets) KH-MOI-169347-CW-CDD / Solar LED Power street lighting in Khva Village, Sangkat Dangkao, Khan Component 2: Improving Community Pending Dangkao( Total sets 26 IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 15,774.00 0.00 Implementa 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 2020-09-14 sets), Solar LED Power and Vulnerable Households Development tion street lighting in Mol Village, Sangkat Dangkao, Khan Dangkao(Total sets 23 sets) KH-MOI-169348-CW-CDD / Solar LED Power street Component 2: Improving Community Pending lighting in Phum 3, Sangkat IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 5,495.00 0.00 Implementa 2020-05-05 2020-05-12 2020-05-26 2020-06-02 2020-06-16 2020-09-14 Chrang Chamreas Ty Mouy, and Vulnerable Households Development tion Khan Russei Kao( Total sets 17 sets) KH-MOI-169349-CW-CDD / Solar LED Power street Component 2: Improving Community Pending lighting in Khtor Village, IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 9,674.00 0.00 Implementa 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 2020-09-15 Sangkat Preak Leap, Khan and Vulnerable Households Development tion Chroy Chang Var( Total sets 30 sets) KH-MOI-169350-CW-CDD / Solar LED Power street lighting in Svay Ckek Component 2: Improving Community Pending Thmei Village, Dandong 1&2 IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 15,064.00 0.00 Implementa 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 2020-09-15 Villages, Sangkat Kork and Vulnerable Households Development tion Roka, Khan Preak Phnov( Total sets 47 sets) KH-MOI-169351-CW-CDD / Solar LED Power street lighting in Daeum Sleng, Component 2: Improving Community Pending Daeum Sleng I, Daeum IDA / 59600 Livelihoods for Urban Poor Post Driven Open - National 21,978.00 0.00 Implementa 2020-05-06 2020-05-13 2020-05-27 2020-06-03 2020-06-17 2020-09-15 Chan I Villages, Sangkat and Vulnerable Households Development tion Chbar Ampov 2, Khan Chbar Ampov( Total sets 69 sets) KH-MOI-191856-CW-CDD / Earth Road Repair and Laterite Pavement for Anlong Samnar, Siem Reap Component 1: Improving Community Pending Province ( Length 1.80 Km, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 27,338.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 Width 4.00 m, 0.15m thick and Vulnerable Households Development tion including 2 units of single culvert construction, Ø0.80m, length 6.00m) KH-MOI-191857-CW-CDD / Earth Road Repair and Laterite Pavement two lines for Sangkat Krabei Riel, Siem Reap Municipality, Component 1: Improving Community Pending Siem Reap Province ( For IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 45,396.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 line1: Length: 1.868 Km, and Vulnerable Households Development tion Width 5.00m, 0.15 thick including 2 units of single culverts, Ø 0.80m, length 7.00m and Ø1.00m, length 7.0 KH-MOI-191859-CW-CDD / Earth Road Repair and Laterite Pavement for Sangkat Tuek Vil ,Siem Reap Municipality, Siem Component 1: Improving Community Pending Reap Province ( Length: IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 64,903.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 2.325 Km , Width: 5.00 m, and Vulnerable Households Development tion 0.15m thick), including 5 units of single culvert construction, 1 Unit Ø1.00 m, length 6.00 m, 4 units Ø1.00 m, l KH-MOI-191860-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Community Pending Khleang Commune, Sotr IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 33,774.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2020-12-26 Nikom District, Siem Reap and Vulnerable Households Development tion Province ( Length 0.25 Km, Width 5.00 m, 0.15m thick) Page 8 KH-MOI-191861-CW-CDD / Reinforced Concrete Road Construction for Kampong Component 1: Improving Community Pending Phluk Commune, Brasat IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 39,635.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2020-12-26 Bakong District, Siem Reap and Vulnerable Households Development tion Province ( Length 0.23 Km, Width 6.00 m, 0.15m thick) KH-MOI-191862-CW-CDD / Earth Road Repair and Laterite Pavement 2 lines for Trapeang Thum Commune ,Brasat Bakong Component 1: Improving Community Pending District, Siem Reap Province IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 36,380.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 ( For line1: Length 0.50 and Vulnerable Households Development tion Km, Width 4.00m, 0.15 thick , For line 2: Length 3.05 Km, Width 4.00m, 0.15 thick) KH-MOI-191863-CW-CDD / Laterite Road Construction 2 lines for Reul Commune ,Pouk District, Siem Reap Component 1: Improving Community Pending Province (For line Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 31,787.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 2.09 Km, Width 4.00m, 0.15 and Vulnerable Households Development tion thick , For line 2: Length 0.75 Km, Width 4.00m, 0.15 thick) KH-MOI-191864-CW-CDD / Laterite Road Construction 2 lines for Trei Nhoar Commune ,Pouk District, Siem Reap Province ( For Component 1: Improving Community Pending line 1: Length 1.20 Km, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 35,805.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 Width 4.00m, 0.15 thick , and Vulnerable Households Development tion For line 2: Length 1.45 Km, Width 4.00m, 0.15 thick including 1 unit of double culvert Ø0.60m, length 6.0 KH-MOI-191865-CW-CDD / Drilled wells Construction Component 1: Improving Community Pending with Afridev Pump for IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 11,429.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2020-12-26 Yeang Commune ,Pouk and Vulnerable Households Development tion District, Siem Reap Province for 5 places KH-MOI-191866-CW-CDD / Drilled wells with solar Pump and Water Distributed Component 1: Improving Community Pending Connection 4 places for IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 47,530.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 Chrouy Neang and Vulnerable Households Development tion NguonCommune ,Srei Snam District, Siem Reap Province KH-MOI-191867-CW-CDD / Reinforced Concrete Road Construction for Khnang Component 1: Improving Community Pending Phnum Commune,Svay Leu IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 20,181.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2020-12-26 District, Siem Reap Province and Vulnerable Households Development tion ( Length: 0.18 Km, Width 5.00 m, 0.15m thick) KH-MOI-162413-CW-CDD / Earth Road Repair and Laterite Pavement for Bakong Commune, Brasat Component 1: Improving Community Pending Bakong District, ( Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 42,032.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2021-01-25 1.60 Km, 4.00m width, 0.15 and Vulnerable Households Development tion thick including 3 units of double pipe culvert 1.00m diameter, 5.00m length) KH-MOI-162411-CW-CDD / Construction of Community Shelter for Ampil Commune, Brasat Bakong District ( Size: 8mx12m, with steel Component 1: Improving Community Pending frame, reinforced concrete IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 14,645.00 0.00 Implementa 2020-09-15 2020-09-22 2020-10-06 2020-10-13 2020-10-27 2020-12-26 slab 0.10m thick and zinc and Vulnerable Households Development tion roof ) including one latrine construction with 4 separated rooms and installation of one unit of wa GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 KH-MOI-14029-GO-RFQ / Pending Office Furniture for National Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 27,380.00 0.00 Implementati 2017-07-14 2017-09-03 2017-10-18 Level and Sub National Management Quotations Envelope on Level KH-MOI-14017-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Softwares ( Accounting) for IDA / 59600 Post Open - National 10,000.00 0.00 Implementati 2017-07-31 2017-09-20 2017-11-19 Management Quotations Envelope PCO-MOI 1 unit on KH-MOI-26199-GO-RFB / Component 1: Improving Pending Motorcycles plus helmets for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 226,100.00 0.00 Implementati 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 National level and Sub- Envelope and Vulnerable Households on National (Total 133 Units) KH-MOI-26827-GO-RFB / Lot1: Develop Management Information System (MIS) Pending System Lot2: Component 3: Project Single Stage - One IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 Implementati 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 Server, Network, Tablet, Management Envelope on website, etc.) Lot 3:MIS webside maintenance for PCO-MOI KH-MOI-33988-GO-RFQ / 4 Pending Component 3: Project Request for Single Stage - One Laptop Computers for IDA / 59600 Post Open - National 9,200.00 0.00 Implementati 2017-11-05 2017-12-05 2017-12-20 Management Quotations Envelope Management on KH-MOI-34259-GO-RFB / Under Office Equipment for Component 3: Project Single Stage - One IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 Implementati 2017-11-08 2019-01-10 2017-11-13 2017-12-15 2019-02-15 2018-01-14 2018-02-18 2018-04-19 National and Sub National Management Envelope on Leve KH-MOI-36613-GO-UN / Lot1:Vehicles (Station Wagon) 3 units for -PCO- MOI and 1 units for MEF, Component 1: Improving Pending UN Agencies Lot2:Vehicles (Pick up Cars) IDA / 59600 Livelihoods for Rural Poor Post Direct 330,000.00 0.00 Implementati 2017-11-17 2017-11-22 2017-12-25 2018-02-23 (Direct) for 1units for GDA-MAFF, 3 and Vulnerable Households on units for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehicles (Station Wagon) 3 Component 1: Improving UN Agencies units for -PCO-MOI and 1 IDA / 59600 Livelihoods for Rural Poor Post Direct 132,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 (Direct) units for MEF, Total and Vulnerable Households Vehicles: 4 Units KH-MOI-11051-GO-RFB / Vehicles (Pick up Cars) for Component 1: Improving 1units for GDA-MAFF, 3 Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 198,000.00 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 units for Siem Reap and 2 Envelope and Vulnerable Households units for PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Total 7 Air Conditioners for IDA / 59600 Post Open - National 4,900.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-17 Management Quotations Envelope PCO and MAFF on KH-MOI-99860-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Office Furniture for MOI- IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Management Quotations Envelope PCO on KH-MOI-99861-GO-RFQ / Printing Material and Component 1: Improving Pending Thumbprint pad for Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,644.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 SHG/producer Quotations Envelope and Vulnerable Households on group/commune federation for 2019 KH-MOI-99863-GO-RFQ / Material for SHG/producer Component 1: Improving Pending Request for Single Stage - One group/commune federation IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,250.00 0.00 Implementati 2019-03-06 2019-04-24 2019-05-24 Quotations Envelope (Boxes for keeping and Vulnerable Households on documents and cash) KH-MOI-99865-GO-RFQ / Equipment for Component 1: Improving Pending Request for Single Stage - One Commune/Sangkat IDA / 59600 Livelihoods for Rural Poor Post Open - National 10,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-18 Quotations Envelope Investment Projects (SRP and Vulnerable Households on and PPCH) KH-MOI-99868-GO-RFQ / 72 Tablets for MIS (3 MoI, Component 1: Improving Pending Request for Single Stage - One 3 GDA, 3 PPCH, 3 Pro. IDA / 59600 Livelihoods for Rural Poor Post Open - National 24,840.00 0.00 Implementati 2019-04-06 2019-05-04 2019-06-03 Quotations Envelope S_Reap, 47 commune, 13 and Vulnerable Households on Sangkat) Page 10 KH-MOI-99869-GO-RFQ / Printing Materials (Logos, Component 1: Improving Pending Request for Single Stage - One Printed Folder, Factsheets, IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,250.00 0.00 Implementati 2019-05-06 2019-06-03 2019-06-24 Quotations Envelope Newsletters, Brochures, and Vulnerable Households on Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Printing Materials for Component 1: Improving Pending Request for Single Stage - One SHG/producer IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,145.00 0.00 Implementati 2019-12-06 2020-01-04 2020-02-03 Quotations Envelope group/commune federation and Vulnerable Households on for 2020 KH-MOI-26829-GO-RFB / Material for SHG/Poducer group/commune Component 1: Improving federation(books keeping, Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 126,250.70 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 cash book, pay and loan Envelope and Vulnerable Households record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pending Procurement of supply Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-07-10 2019-08-04 2019-09-03 Server and network for Management Quotations Envelope on LEAP Project KH-MOI-136652-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Office Furniture for Skill IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,400.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Quotations Envelope Development Activities and Vulnerable Households on KH-MOI-136666-GO-RFQ / Component 1: Improving Pending Motorcycles for Skill Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 17,500.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Development Activities (10 Quotations Envelope and Vulnerable Households on Units) KH-MOI-168855-GO-RFQ / Component 1: Improving Pending Vehicles (VAN) 1 units for - Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open 30,000.00 0.00 Implementati 2020-04-29 2020-06-05 2020-07-05 PCO-MOI ( Import tax will Quotations Envelope and Vulnerable Households on be exempted) KH-MOI-168856-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Office Furniture for Sub IDA / 59600 Livelihoods for Rural Poor Post Open - National 16,915.00 0.00 Implementati 2020-05-02 2020-05-28 2020-06-27 Quotations Envelope National Level (PCO, SRP ) and Vulnerable Households on KH-MOI-168859-GO-RFQ / Study Equipment (Hummer Component 1: Improving Pending Test, DCP Test, Autormatic Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 11,000.00 0.00 Implementati 2020-05-06 2020-05-29 2020-06-13 Level, GPS…2sets) for Quotations Envelope and Vulnerable Households on Commnune/Sangkat Investment Projects (SRP) KH-MOI-168860-GO-RFQ / Printing Communication Component 1: Improving Pending Materials (LEAP Newsletters Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 12,000.00 0.00 Implementati 2020-06-20 2020-07-18 2020-08-08 semi-annual (2time/years) in Quotations Envelope and Vulnerable Households on Khmer and English 2time/year) KH-MOI-168861-GO-RFQ / Component 1: Improving Pending Printing Communication Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,000.00 0.00 Implementati 2020-09-06 2020-10-04 2020-10-25 Materials ( Success Story 4 Quotations Envelope and Vulnerable Households on time/year) KH-MOI-168862-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Video Production of project IDA / 59600 Livelihoods for Rural Poor Post Open - National 7,000.00 0.00 Implementati 2020-09-06 2020-09-29 2020-10-29 Quotations Envelope achievement (15 Minute) and Vulnerable Households on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99864-NC-RFQ / Pending Component 3: Project Request for Single Stage - One Develop Website for LEAP IDA / 59600 Post Open - National 5,600.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Management Quotations Envelope Projec on Component 1: Improving Pending KH-MOI-99870-NC-RFQ / Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,000.00 0.00 Implementati 2019-07-06 2019-08-17 2019-10-16 Four (4) Video Spots Quotations Envelope and Vulnerable Households on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 11 KH-MOI-39863-CS-CQS / Consultant Impact Survey (3nd year of Component 3: Project Pending IDA / 59600 Post Qualification Open - National 30,000.00 0.00 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 the project/Mid-term review) Management Implementation Selection (Local Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Final Impact Survey ( (5th Consultant Component 3: Project Pending year of Project evaluation IDA / 59600 Post Qualification Open - National 40,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 Management Implementation and completion report) Selection (Local Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for Under IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 280,000.00 0.00 2018-10-22 2019-01-18 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 4 Districts​​  (Angkor Thum, Implementation and Vulnerable Households Selection Kralanh, Pouk and Srei Snam District) KH-MOI-82083-CS-CQS / Development of Community Institutions of the Poor for Component 1: Improving Consultant Under 5 Districts ( Chi Kraeng, IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 290,000.00 0.00 2018-10-22 2018-12-21 2018-11-12 2019-01-11 2019-03-22 2019-02-10 2019-03-17 2022-12-05 Implementation Prasat Bakong, Siem Reap, and Vulnerable Households Selection Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Human Resource Component 1: Improving Quality And Cost- Open - Development Service IDA / 59600 Livelihoods for Rural Poor Prior 784,000.00 0.00 Canceled 2018-12-14 2019-01-13 2019-01-16 2019-02-26 2019-05-10 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Based Selection International Provider (HRDSP) for SRP and Vulnerable Households and PPCH KH-MOI-39858-CS-QCBS / Human Resources Component 2: Improving Quality And Cost- Open - Development Services IDA / 59600 Livelihoods for Urban Poor Post 367,932.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for PPM and Vulnerable Households (NGO/Firm) KH-MOI-39860-CS-CQS / Consultant Baseline Survey (1st Component 3: Project IDA / 59600 Post Qualification Open - National 30,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 year)(Local Firm) at PCO- Management Selection MOI KH-MOI-39857-CS-QCBS / Human Resources Component 1: Improving Quality And Cost- Open - Development Services IDA / 59600 Livelihoods for Rural Poor Post 545,936.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for SRP and Vulnerable Households (NGO/Firm) KH-MOI-187154-CS-CQS / Tracer Study Consultant for Component 1: Improving Consultant Under 24 months (one firm IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 45,000.00 0.00 2020-08-10 2020-08-07 2020-08-31 2020-08-23 2020-10-14 2020-11-13 2020-12-18 2022-12-08 Implementation consultant will be hired for and Vulnerable Households Selection both SRP and PPCH) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Component 1: Improving Individual Provincial Operation and Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 120,000.00 0.00 2017-06-26 2017-12-07 2017-08-23 2018-04-30 2017-09-06 2018-04-30 2017-10-11 2022-10-10 M&E Specialist for SRP (60 Implementation and Vulnerable Households Selection Months) KH-MOI-13901-CS-INDV / Individual Component 3: Project Pending Project Assistant for PCO- IDA / 59600 Post Consultant Open 18,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2020-10-24 Management Implementation MOI (60 Months) Selection KH-MOI-13903-CS-INDV / Component 2: Improving Individual National Operation and Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 150,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 M&E Specialist for PPM (60 Implementation and Vulnerable Households Selection Months) KH-MOI-13905-CS-INDV / Component 1: Improving Individual Provincial Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2020-10-10 Management Specialist for Implementation and Vulnerable Households Selection SRP (36 Months) KH-MOI-13907-CS-INDV / Component 1: Improving Individual Pending Project Assistant for SRP IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation (60 Months) and Vulnerable Households Selection KH-MOI-13910-CS-INDV / Component 2: Improving Individual Pending Project Assistant for PPM IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation (60 Months) and Vulnerable Households Selection Page 12 KH-MOI-13913-CS-INDV / Component 2: Improving Individual 01 PPM Infrastructure Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 72,000.00 0.00 2017-07-17 2017-09-13 2017-09-27 2017-11-01 2020-10-31 Specialist at PPM (36 Implementation and Vulnerable Households Selection Months) KH-MOI-11055-CS-INDV / Individual National Project Component 3: Project Pending IDA / 59600 Post Consultant Open 180,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2022-11-30 Management and M&E Management Implementation Selection consultant at PCO-MOI KH-MOI-11263-CS-INDV / Component 1: Improving Individual National Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Management Specialist for Implementation and Vulnerable Households Selection MOI/PPM(36 Months) KH-MOI-13886-CS-INDV / Component 2: Improving Individual Pending National procurement IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Implementation Specialist based at PCO and Vulnerable Households Selection KH-MOI-30826-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (P M & E IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Engineer) at SRP (36 and Vulnerable Households Selection Months) KH-MOI-30834-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Building IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at and Vulnerable Households Selection SRP (36 Months) KH-MOI-30840-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Rural Road IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at and Vulnerable Households Selection SRP (36 Months) KH-MOI-39794-CS-INDV / Individual Component 3: Project Pending International Micro-Finance IDA / 59600 Post Consultant Open 60,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-07-16 Management Implementation Expert at PCO-MOI(60 days) Selection KH-MOI-39797-CS-INDV / Individual National Communication Component 3: Project Pending IDA / 59600 Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Specialist at PCO-MOI (36 Management Implementation Selection Months) KH-MOI-39798-CS-INDV / Individual Component 3: Project Pending National MIS Specialist at IDA / 59600 Post Consultant Open 60,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Management Implementation PCO-MOI (24 Months) Selection KH-MOI-39800-CS-INDV / Component 1: Improving Individual National Agriculture Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Likelihood Specialist for Implementation and Vulnerable Households Selection GDA-MAFF (36 Months) KH-MOI-39817-CS-INDV / Component 1: Improving Individual National HR Development Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 48,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Specialist for SRP (24 Implementation and Vulnerable Households Selection Months) KH-MOI-39821-CS-INDV / Component 2: Improving Individual National HR Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 48,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2020-05-06 Specialist for PPM ( 24 Implementation and Vulnerable Households Selection Months) KH-MOI-39888-CS-INDV / Component 1: Improving Individual Pending 7 District Facilitators (7 DF IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 336,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation x 55 Months) at Siem Reap and Vulnerable Households Selection KH-MOI-40438-CS-INDV / Component 1: Improving Individual Provincial Micro-Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 Specialist for SRP ( 36 Implementation and Vulnerable Households Selection Months) KH-MOI-40440-CS-INDV / Component 1: Improving Individual Senior Livelihood/business Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 development Specialist for Implementation and Vulnerable Households Selection SRP (36 Months) KH-MOI-40447-CS-INDV / Component 1: Improving Individual Pending 47 Commune Facilitators IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 564,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation (47CFs x55 Months) for SRP and Vulnerable Households Selection KH-MOI-40449-CS-INDV / 47 Commune Animal Health Component 1: Improving Individual Pending & Extension Workers (47 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 338,400.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation CAHEW x 55 Months) for and Vulnerable Households Selection SRP Page 13 KH-MOI-40453-CS-INDV / Component 2: Improving Individual 4 Local Coordinator for Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 96,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 urban poor(4CLUPs x 55 Implementation and Vulnerable Households Selection Months) for PPM Individual KH-MOI-99872-CS-INDV / Component 3: Project Pending IDA / 59600 Post Consultant Open 15,000.00 0.00 2019-03-01 2019-04-21 2019-05-05 2019-06-09 2022-06-08 Project Assistant for MAFF Management Implementation Selection KH-MOI-99873-CS-INDV / Component 1: Improving Individual Tracer Study Consultant (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 18,000.00 0.00 Canceled 2019-06-03 2019-07-22 2019-07-29 2019-08-12 2019-10-11 Working Days) and Vulnerable Households Selection KH-MOI-136635-CS-INDV / International Skill Component 1: Improving Individual Development Advisor (120 Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 112,800.00 0.00 2019-10-04 2019-10-18 2019-11-10 2019-11-15 2019-11-28 2020-03-27 days x 1 pax) for (20day- Implementation and Vulnerable Households Selection 2019, 80 days-2020 and 20 days-2021) KH-MOI-136641-CS-INDV / Component 2: Improving Individual National Skills Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 85,000.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Specialist (34 monthsx1pax) Implementation and Vulnerable Households Selection for PCO-LEAP KH-MOI-136643-CS-INDV / Component 2: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 190,400.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection SRP (34month x 7 paxes) KH-MOI-136648-CS-INDV / Component 1: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 81,600.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection PPCH (34month x 3 paxes) KH-MOI-168864-CS-INDV / National Consultant for Component 1: Improving Individual Pending Market Linkage Study IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 56,000.00 0.00 2020-05-24 2020-07-12 2020-08-02 2020-09-06 2022-09-06 Implementation (Intermittent) for 3 year and Vulnerable Households Selection (2020-2022) KH-MOI-168866-CS-INDV / National Consultant for Component 1: Improving Individual Sturdy research promote Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 31,200.00 0.00 2020-05-01 2020-06-19 2020-07-10 2020-08-14 2022-08-14 Linkage with formal Implementation and Vulnerable Households Selection Financial sector for 3 year (2020-20220) Page 14