PROCUREMENT PLAN (Textual Part) Project information: Eastern Recovery Project (P145196) Project Implementation agency: FSRDC Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC Eastern Recovery Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-02-12 2021-06-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145196 GPN Date: Project Name: DRC Eastern Recovery Project Loan / Credit No: IDA / 57510, IDA / 66650 Fonds Social de la République Démocratique du Congo Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification High SEA/SH nt Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Contract Description Component Review Type Method Amount qualification Document / and Recommendation Signed Contract No. Approach Process (Y/N) Risk Document Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Completion (US$) Documents Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-49337-CW-RFB / Single Stage - One 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-12- Construction du bâtiment IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 0.00 Annulé Envelope 01 06 17 17 21 18 annexe du bureau de la CG Request for ZR-FSRDC-232720-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 NDAWELE/NU SPD) Request for ZR-FSRDC-232735-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 YAKOKI/NU SPD) Request for ZR-FSRDC-232736-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 DIANGENDA/NU SPD) Request for ZR-FSRDC-232740-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 WOLO/NU SPD) Request for ZR-FSRDC-232743-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Ouelé/Yakoma SPD) Request for ZR-FSRDC-232748-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Zabo/Yakoma SPD) Request for ZR-FSRDC-232751-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Nzewe/Yakoma SPD) Request for ZR-FSRDC-232753-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Ubangi/Yakoma SPD) Request for ZR-FSRDC-232757-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP Sorozo IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 1/Yakoma SPD) Request for ZR-FSRDC-232759-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP Sorozo IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 2/Yakoma SPD) Request for ZR-FSRDC-232762-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP Ya IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Mbongo/Yakoma SPD) Request for ZR-FSRDC-232765-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Yakoma/Yakoma SPD) Request for ZR-FSRDC-232766-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 04 30 28 Wakwa/Yakoma SPD) Request for ZR-FSRDC-232777-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-09- 2021-10- 2022-04- / Travaux de Forage à Kawele, IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 31 29 Tudu et Nganza SPD) Request for ZR-FSRDC-232886-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Demande de prix Limited 0.00 / Construction de l’EP Lubala Resilience Envelope (Non Bank- d'exécution 05 30 26 SPD) Request for ZR-FSRDC-232887-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 MITENGU SPD) Request for ZR-FSRDC-232888-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Demande de prix Limited 0.00 / Construction de l’EP NSELE Resilience Envelope (Non Bank- d'exécution 05 30 26 SPD) Request for ZR-FSRDC-232889-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 TSHIBALA SPD) Request for ZR-FSRDC-232890-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 THSIMAYI SPD) Request for ZR-FSRDC-232891-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 KABUAYI SPD) Request for ZR-FSRDC-232892-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 CENTRAL SPD) Request for ZR-FSRDC-232893-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP LUABA IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 NTONDO SPD) Request for ZR-FSRDC-232894-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP MBULU IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 MIKONGO SPD) Request for ZR-FSRDC-232895-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 05 30 26 MPANDA SPD) Request for ZR-FSRDC-232897-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Demande de prix Limited 0.00 / Construction de l’EP TUBADI Resilience Envelope (Non Bank- d'exécution 05 30 26 SPD) ZR-FSRDC-236098-CW-RFQ Request for / Construction de l’E.P Lengi, 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Limited 0.00 Quartier/KAYA/ Commune de Resilience Envelope (Non Bank- d'exécution 14 09 06 GBADOLITE/NU SPD) ZR-FSRDC-236353-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 Hingaso, Quartier/LITE / Resilience Envelope (Non Bank- d'exécution 16 11 08 Commune de GBADOLITE/NU SPD) ZR-FSRDC-236333-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- GBADOLITE, Quartier/MBANZA IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 14 09 06 / Commune de SPD) GBADOLITE/NU ZR-FSRDC-236537-CW-RFQ Request for / Construction de l’E. 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- ZANGBINGO, IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 11 06 03 Quartier/PANGOMA / SPD) Commune de GBADOLITE/NU Page 1 ZR-FSRDC-236405-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- MOANDA, Quartier/MOANDA IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 10 05 02 / Commune de SPD) GBADOLITE/NU ZR-FSRDC-236390-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 MWANDA CECU / Commune Resilience Envelope (Non Bank- d'exécution 10 05 02 de MOLEGBE/NU SPD) ZR-FSRDC-236149-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 MOLOMBE/ Commune de Resilience Envelope (Non Bank- d'exécution 21 16 13 MOLEGBE/NU SPD) Request for ZR-FSRDC-236038-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- / Construction de l’E.P FIWA/ IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 21 16 13 Commune de MOLEGBE/NU SPD) ZR-FSRDC-236406-CW-RFQ Request for / Construction de l’E.P MBAYA 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 SOKORO / Commune de Resilience Envelope (Non Bank- d'exécution 21 16 13 MOLEGBE/NU SPD) ZR-FSRDC-236407-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 MATONDI / Commune de Resilience Envelope (Non Bank- d'exécution 21 16 13 MOLEGBE/NU SPD) Request for ZR-FSRDC-236341-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- / Construction du CS FADU / IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 25 20 17 Commune de MOLEGBE/NU SPD) ZR-FSRDC-236339-CW-RFQ Request for / Travaux de 5 forages au 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 village Kawele et 1 forage à Resilience Envelope (Non Bank- d'exécution 25 20 17 Tudu, 1 à Fadu/NU SPD) ZR-FSRDC-236167-CW-RFQ Request for / Construction de l’E.P 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Open - National 0.00 NGANZA, Quartier/NGANZA / Resilience Envelope (Non Bank- d'exécution 25 20 17 Commune de NGANZA/NU SPD) ZR-FSRDC-236039-CW-RFQ Request for / Construction de l’E.P BOYI, 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Limited 0.00 Quartier/BAMBU / Commune Resilience Envelope (Non Bank- d'exécution 24 19 16 de NGANZA/NU SPD) Request for ZR-FSRDC-236150-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-04- 2021-06- 2021-12- / Construction de l’EP IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 24 19 16 MOGORO/NU SPD) ZR-FSRDC-236160-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP 2 LUNGANDU/KANANGA Resilience Envelope (Non Bank- d'exécution 17 11 10 (001) SPD) ZR-FSRDC-236049-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Limited 0.00 l'EP NGIDILAYI/KANANGA Resilience Envelope (Non Bank- d'exécution 20 14 13 (002) SPD) ZR-FSRDC-236413-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP ARC-EN-CIEL/KANANGA Resilience Envelope (Non Bank- d'exécution 22 16 15 (003) SPD) ZR-FSRDC-236358-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'E.P 1 LUMUMBA/KANANGA Resilience Envelope (Non Bank- d'exécution 15 09 08 (004) SPD) ZR-FSRDC-236162-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP MUINDIDI/KANANGA Resilience Envelope (Non Bank- d'exécution 19 13 12 (005) SPD) ZR-FSRDC-236343-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP 2 MUKOLESHI/KANANGA Resilience Envelope (Non Bank- d'exécution 11 05 04 (006) SPD) Request for ZR-FSRDC-236054-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 13 07 06 l'EP KAPAJIKA/KANANGA (007) SPD) ZR-FSRDC-236394-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'E.P KANDIKU/KANANGA Resilience Envelope (Non Bank- d'exécution 13 07 06 (008) SPD) ZR-FSRDC-236360-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP MUFIMISHI/KANANGA Resilience Envelope (Non Bank- d'exécution 24 18 17 (009) SPD) ZR-FSRDC-236163-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP MUDIDIKE/KANANGA Resilience Envelope (Non Bank- d'exécution 22 16 15 (010) SPD) Request for ZR-FSRDC-236084-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 21 15 14 l'EP NGANZA/KANANGA (011) SPD) ZR-FSRDC-236410-CW-RFQ Request for / Travaux de construction de 2. Livelihoods and Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP TSHINSAMBI/KANANGA Employment Generation Envelope (Non Bank- d'exécution 26 20 19 (012) SPD) Request for ZR-FSRDC-236395-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 22 16 15 l'E.P DIKU/KANANGA (013) SPD) ZR-FSRDC-236542-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP TOSALISANAI/KANANGA Resilience Envelope (Non Bank- d'exécution 23 17 16 (014) SPD) Request for ZR-FSRDC-236396-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 18 12 11 l'EP DISANKA/KANANGA (015) SPD) ZR-FSRDC-236141-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP Mgr BAKAFUA/KANANGA Resilience Envelope (Non Bank- d'exécution 26 20 19 (016) SPD) ZR-FSRDC-236283-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'E.P TSHIBASHI/KANANGA Resilience Envelope (Non Bank- d'exécution 26 20 19 (017) SPD) ZR-FSRDC-236354-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP BUSHALA Resilience Envelope (Non Bank- d'exécution 26 20 19 BUAMBA/KANANGA (018) SPD) ZR-FSRDC-236521-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP NDESHA Resilience Envelope (Non Bank- d'exécution 23 17 16 LUSAMBO/KANANGA (019) SPD) ZR-FSRDC-236284-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'E.P BAOLONGO/KANANGA Resilience Envelope (Non Bank- d'exécution 23 17 16 (020) SPD) Page 2 ZR-FSRDC-236507-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'EP TSHISUMBU/KANANGA Resilience Envelope (Non Bank- d'exécution 23 17 16 (021) SPD) ZR-FSRDC-236085-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Limited 0.00 l'EP DIKU DIETU/KANANGA Resilience Envelope (Non Bank- d'exécution 26 20 19 (022) SPD) Request for ZR-FSRDC-236508-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 27 21 20 l'EP DIAKAJA/KANANGA (023) SPD) ZR-FSRDC-236286-CW-RFQ Request for / Travaux de construction de 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- IDA / 66650 A posteriori Demande de prix Open - National 0.00 l'E.P TUYA Resilience Envelope (Non Bank- d'exécution 22 16 15 KUMPALA/KANANGA (024) SPD) Request for ZR-FSRDC-236156-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2020-12- 2021-02- 2021-08- / Travaux de construction de IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 23 17 16 l'EP SANKAYI/KANANGA (025) SPD) Request for ZR-FSRDC-236361-CW-RFQ 1. Support to Community Single Stage - One Quotations En attente 2021-01- 2021-03- 2021-08- / Travaux de construction EP IDA / 66650 A posteriori Demande de prix Open - National 0.00 Resilience Envelope (Non Bank- d'exécution 05 02 29 Dikongayi 2/Kananga SPD) ZR-FSRDC-239808-CW-RFQ / Construction de l'EP Request for BISHIYA/Village KALUMBA 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 MANDE/Groupement BENA Resilience Envelope (Non Bank- d'exécution 14 08 07 NGOYI/KALUMBA/Secteur SPD) DIBANDA_KC ZR-FSRDC-239813-CW-RFQ / Construction de l'EP Request for MUAKAJI/Village TSHIMANGA 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 NFUMA/Groupement BENA Resilience Envelope (Non Bank- d'exécution 17 11 10 KABIYE/ TSHIKELE/Secteur SPD) DIBANDA_KC ZR-FSRDC-239818-CW-RFQ / Construction de l'EP1 Request for DIBANDA/Village 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 BUNKONDE/Groupement BENE Resilience Envelope (Non Bank- d'exécution 19 13 12 KALUBI/ BAKUA SPD) NDOLO/Secteur DIBANDA_KC ZR-FSRDC-239821-CW-RFQ / Construction de l'EP EP Request for NDIBU KALAMBA/Village 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 TSHILOLO/Groupement Resilience Envelope (Non Bank- d'exécution 20 14 13 BAKUA NDAYE/Secteur SPD) KASANGIDI_KC ZR-FSRDC-239825-CW-RFQ / Construction de l'EP Request for LUAJA/Village BENA 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 NGANA/Groupement BENA Resilience Envelope (Non Bank- d'exécution 18 12 11 NGALA/Secteur SPD) KASANGIDI_KC ZR-FSRDC-239830-CW-RFQ / Construction de l'EP3 Request for LUKULA/Village BENA 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 NKENU/Groupement BENA Resilience Envelope (Non Bank- d'exécution 24 18 17 NKENU/Secteur SPD) KASANGIDI_KC ZR-FSRDC-239832-CW-RFQ / Construction de l'EP1 Request for BASANGA/Village 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 KAULU/Groupement KAULU Resilience Envelope (Non Bank- d'exécution 25 19 18 MIKELE/Secteur SPD) KASANGIDI_KC ZR-FSRDC-239833-CW-RFQ / Construction de l'EP NTUADIJILU/Village BAKUA Request for TSHILUNDU 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 /NFUAMBA/Groupement Resilience Envelope (Non Bank- d'exécution 25 19 18 BAKUA TSHILUNDU/ SPD) NFUAMBA/Secteur KASANGIDI_KC ZR-FSRDC-239835-CW-RFQ / Construction de l'EP Request for MAMBASAKO/Village 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- TSHINEMA BENA IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope (Non Bank- d'exécution 26 20 19 MUABA/Groupement BENA SPD) MUAMBA/Secteur KASANGIDI_KC ZR-FSRDC-239837-CW-RFQ / Construction de l'EP Request for TSHIMAKAKA/Village 1. Support to Community Single Stage - One Quotations En attente 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 MUPOYI/Groupement BAKUA Resilience Envelope (Non Bank- d'exécution 27 21 20 NKATE (MUPOYI)/Secteur SPD) KASANGIDI_KC Request for ZR-FSRDC-239867-CW-RFQ Single Stage - One Quotations En attente 2021-07- 2021-08- 2022-02- / Extension Bureaux de IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope (Non Bank- d'exécution 05 30 26 l'Antenne_Kananga SPD) GOODS Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-49334-GO-RFQ / Acquisition de 4 tracteurs et remorques matériel - Brigade Single Stage - One 2018-03- 2018-06- 2018-04- 2018-07- 2018-10- d'entretien - OVD IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 258,572.05 Signé Envelope 05 22 30 26 27 1) Lot 1Nord Kivu (2), 2) Lot 2 Ituri (1), 3) Lot 3: Tanganyika (1) ZR-FSRDC-51041-GO-RFQ / Single Stage - One 2018-12- 2019-01- 2019-07- Acquisition LABOSEM IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Envelope 01 26 25 phytosanitaire du Sud Kivu ZR-FSRDC-51046-GO-RFB / Single Stage - One 2018-11- 2019-01- 2019-07- Acsuisition des équipements IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Envelope 28 23 22 pour LABO INERA ZR-FSRDC-49370-GO-RFQ / Acquisition des équipements Single Stage - One 2018-06- 2018-08- 2019-01- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé du nouveau bureau de la CG à Envelope 06 01 28 construire. ZR-FSRDC-232724-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- de mise en œuvre des IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 31 29 chantiers Thimo/cash for work à Kananga (Kit d’urgence) ZR-FSRDC-232729-GO-RFQ Single Stage - One En attente 2021-07- 2021-09- 2022-03- / Fourniture de 15 véhicules IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 20 14 13 4x4 pour le STEP 2 ZR-FSRDC-232732-GO-RFQ / Acquisition des équipements de protection 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- individuelle (EPI) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 31 29 de mise en œuvre des chantiers Thimo/cash for work à Kananga (vague 1) Page 3 ZR-FSRDC-232737-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- de mise en œuvre des IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 31 29 chantiers Thimo/cash for work à Kananga (vague 1) en 9 lots ZR-FSRDC-232746-GO-RFQ / Fourniture des matériels informatiques pour les Single Stage - One En cours 2021-06- 2021-05- 2021-08- 2022-02- antennes provinciales IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 20 14 15 11 (Kinshasa, Nord Kivu, Sud Kivu, Kasaï Central, Nord Ubangi) du STEP 2 ZR-FSRDC-232758-GO-RFQ / Acquisition et Installation de Single Stage - One En attente 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 2 Générateurs pour Kasaï Envelope d'exécution 13 08 04 Central et Nord Ubangi ZR-FSRDC-232763-GO-RFQ / Acquisition et Installation de Single Stage - One En attente 2021-06- 2021-08- 2022-02- 3 VSAT pour la connexion IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 13 08 04 Internet/Nord Ubangi/Kasaï Central et Ituri ZR-FSRDC-232770-GO-RFQ / Fourniture des mobiliers pour les EP Lengi, Hingaso, 1. Support to Community Single Stage - One En attente 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 Gbadolite, Zangbino et Resilience Envelope d'exécution 04 29 28 Moanda toutes/commune de Gbadolite ZR-FSRDC-232772-GO-RFQ / Fourniture de la connexion Single Stage - One En attente 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Internet et Interphones en Envelope d'exécution 13 08 04 faveur du projet STEP II ZR-FSRDC-232774-GO-RFQ / Fourniture des mobiliers pour les EP Mwanda Cecu, 1. Support to Community Single Stage - One En attente 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 Molombe, Fiwa, Mbaya Resilience Envelope d'exécution 04 29 28 Sokoro, Matondi et le CS Fadu tous/commune de Molegbe ZR-FSRDC-232775-GO-RFQ / Achat 11 Tablettes Single Stage - One En cours 2021-06- 2021-05- 2021-08- 2022-01- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 1,760.00 enquêteurs TSHIMBULU ET Envelope d'exécution 06 26 01 28 DIBAYA CENTRE ZR-FSRDC-232780-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Demande de prix Limited 0.00 de mise en œuvre des Employment Generation Envelope d'exécution 05 30 29 chantiers Thimo/cash for work à TSHIMBULU ZR-FSRDC-232781-GO-RFQ / Acquisition des équipements de protection 2. Livelihoods and Single Stage - One En attente 2021-10- 2021-11- 2022-05- individuelle (EPI) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 30 29 de mise en œuvre des chantiers Thimo/cash for work à TSHIMBULU ZR-FSRDC-232782-GO-RFQ Single Stage - One En attente 2021-07- 2021-09- 2022-03- / Acquisition d’un mini bus IDA / 66650 5. CERC A posteriori Demande de prix Limited 0.00 Envelope d'exécution 13 07 06 pour le CERC ZR-FSRDC-232783-GO-RFQ / Fourniture des mobiliers 1. Support to Community Single Stage - One En attente 2021-09- 2021-10- 2022-04- pour les EP Nganza, Boyi, IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope d'exécution 05 31 29 Mogoro et le CS Tudu/Commune de Nganza ZR-FSRDC-232786-GO-RFQ / Fourniture des mobiliers 1. Support to Community Single Stage - One En attente 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Demande de prix Limited 0.00 pour les EP Ndawele, Yakoki , Resilience Envelope d'exécution 05 30 29 Diangenda et Wolo ZR-FSRDC-232794-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Demande de prix Limited 0.00 de mise en œuvre des Employment Generation Envelope d'exécution 05 30 29 chantiers Thimo/cash for work à DIBAYA ZR-FSRDC-232805-GO-RFQ / Acquisition des équipements de protection 2. Livelihoods and Single Stage - One En attente 2021-10- 2021-11- 2022-05- individuelle (EPI) dans le cadre IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 30 29 de mise en œuvre des chantiers Thimo/cash for work à DIBAYA ZR-FSRDC-232804-GO-DIR / Passation de Acquisition, mise à jour et En attente 2021-06- 2021-06- 2021-07- 2022-01- IDA / 66650 4. Project Management A posteriori marché de gré à Direct 0.00 formation sur le logiciel d'exécution 15 20 25 21 gré TOM2PRO ZR-FSRDC-232809-GO-RFQ Single Stage - One En attente 2021-06- 2021-08- 2022-02- / Aménagement des IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 13 08 04 containers ZR-FSRDC-232820-GO-RFQ / Acquisition des motos de 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Demande de prix Limited 0.00 terrain, lot 1: 4 pour le NU et Employment Generation Envelope d'exécution 05 31 29 lot 2: 6 pour Kananga ZR-FSRDC-220575-GO-RFQ / Acquisition de trois Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 véhicules automobile 4x4 Envelope d'exécution 24 21 18 pour le projet STEP II ZR-FSRDC-232898-GO-RFQ / Fourniture des mobiliers 1. Support to Community Single Stage - One En attente 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 pour les 5 EP de Tshibulu ( 5 Resilience Envelope d'exécution 04 29 28 lots) ZR-FSRDC-232899-GO-RFQ / Fourniture des mobiliers 1. Support to Community Single Stage - One En attente 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Demande de prix Limited 0.00 pour les 6 EP de DIBAYA ( 6 Resilience Envelope d'exécution 04 29 28 lots) ZR-FSRDC-233086-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-07- 2021-08- 2022-02- de mise en œuvre des IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 30 26 chantiers Thimo/cash for work à Yakoma pour 9 quartiers ZR-FSRDC-233089-GO-RFQ / Acquisition des équipements de protection individuelle (EPI) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Demande de prix Limited 0.00 de mise en œuvre des Employment Generation Envelope d'exécution 05 30 26 chantiers Thimo/cash for work à Yakoma pour les 9 quartiers ZR-FSRDC-232764-GO-RFQ / Acquisition des outillages (Petits matériels) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- de mise en œuvre des IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 05 31 29 chantiers Thimo/cash for work à Kananga (vague 3) en 9 lots Page 4 ZR-FSRDC-232755-GO-RFQ / Acquisition des équipements de protection individuelle (EPI) dans le cadre 2. Livelihoods and Single Stage - One En attente 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Demande de prix Limited 0.00 de mise en œuvre des Employment Generation Envelope d'exécution 05 31 29 chantiers Thimo/cash for work à Kananga (vague 3) en 9 lots ZR-FSRDC-236168-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scolaire l'EP 2 Employment Generation Envelope d'exécution 05 02 29 LUNGANDU/KANANGA (001) ZR-FSRDC-236139-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Employment Generation Envelope d'exécution 05 02 29 NGIDILAYI/KANANGA (002) ZR-FSRDC-236101-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP ARC-EN- Employment Generation Envelope d'exécution 05 02 29 CIEL/KANANGA (003) ZR-FSRDC-236158-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'E.P 1 Employment Generation Envelope d'exécution 05 02 29 LUMUMBA/KANANGA (004) ZR-FSRDC-236105-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Employment Generation Envelope d'exécution 05 02 29 MUINDIDI/KANANGA (005) ZR-FSRDC-236043-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP 2 Resilience Envelope d'exécution 05 02 29 MUKOLESHI/KANANGA (006) ZR-FSRDC-236387-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scolaire l'EP Resilience Envelope d'exécution 05 02 29 KAPAJIKA/KANANGA (007) ZR-FSRDC-236042-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scolaire l'E.P Resilience Envelope d'exécution 05 02 29 KANDIKU/KANANGA (008) ZR-FSRDC-236151-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scolaire l'EP Employment Generation Envelope d'exécution 05 02 29 MUFIMISHI/KANANGA (009) ZR-FSRDC-236408-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Resilience Envelope d'exécution 05 02 29 MUDIDIKE/KANANGA (010) ZR-FSRDC-236051-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Resilience Envelope d'exécution 05 02 29 NGANZA/KANANGA (011) ZR-FSRDC-236170-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Employment Generation Envelope d'exécution 05 02 29 TSHINSAMBI/KANANGA (012) ZR-FSRDC-236276-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'E.P Employment Generation Envelope d'exécution 05 02 29 DIKU/KANANGA (013) ZR-FSRDC-236140-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Employment Generation Envelope d'exécution 05 02 29 TOSALISANAI/KANANGA (014) ZR-FSRDC-236107-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Employment Generation Envelope d'exécution 05 02 29 DISANKA/KANANGA (015) ZR-FSRDC-236281-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Mgr Employment Generation Envelope d'exécution 05 02 29 BAKAFUA/KANANGA (016) ZR-FSRDC-236391-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'E.P Resilience Envelope d'exécution 05 02 29 TSHIBASHI/KANANGA (017) ZR-FSRDC-236503-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- /mobilier scoalire l'EP IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope d'exécution 05 02 29 BUSHALA BUAMBA/KANANGA (018) ZR-FSRDC-236050-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP NDESHA Resilience Envelope d'exécution 05 02 29 LUSAMBO/KANANGA (019) ZR-FSRDC-236501-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'E.P Resilience Envelope d'exécution 05 02 29 BAOLONGO/KANANGA (020) ZR-FSRDC-236047-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Resilience Envelope d'exécution 05 02 29 TSHISUMBU/KANANGA (021) ZR-FSRDC-236389-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP DIKU Resilience Envelope d'exécution 05 02 29 DIETU/KANANGA (022) ZR-FSRDC-236048-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Resilience Envelope d'exécution 05 02 29 DIAKAJA/KANANGA (023) ZR-FSRDC-236058-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'E.P TUYA Resilience Envelope d'exécution 05 02 29 KUMPALA/KANANGA (024) ZR-FSRDC-236393-GO-RFQ / Fourniture d'équipements 1. Support to Community Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scoalire l'EP Resilience Envelope d'exécution 05 02 29 SANKAYI/KANANGA (025) ZR-FSRDC-236153-GO-RFQ / Fourniture d'équipements 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-09- IDA / 66650 A posteriori Demande de prix Limited 0.00 /mobilier scolaire EP Employment Generation Envelope d'exécution 05 02 29 Dikongayi 2/KANANGA ZR-FSRDC-236077-GO-RFQ / Fourniture des kits de lavage des mains dans le 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 cadre de la mise en œuvre de Employment Generation Envelope d'exécution 30 25 21 chantiers de THIMO à Gbadolite et à Mbayi Mbongo/NU Page 5 ZR-FSRDC-236142-GO-RFQ / Fourniture des kits médicaux dans le cadre de la mise en œuvre de chantiers 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 de THIMO / « CASH FOR Employment Generation Envelope d'exécution 30 25 21 WORK » à Gbadolite (quartiers Lite, Kaya, Pangoma, Mowanda et Mbanza)/NU ZR-FSRDC-236362-GO-RFQ / Fourniture des panneaux de mécanismes de gestion des plaintes dans le cadre de la mise en œuvre des activités 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 de la composante 1 Employment Generation Envelope d'exécution 27 22 18 (infrastructures) et de composante 2 (THIMO) dans la ville de Gbadolite et territoire de Mobayi Mbongo_ NU ZR-FSRDC-236322-GO-RFQ / Acquisition des outillages complémentaires dans le cadre de la mise en œuvre de 2. Livelihoods and Single Stage - One En attente 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 chantiers de THIMO / « CASH Employment Generation Envelope d'exécution 03 29 25 FOR WORK » à Gbadolite (quartiers Lite, Kaya, Pangoma, Mowanda et Mbanza)/NU ZR-FSRDC-236318-GO-RFQ / Acquisition des outillages complémentaires dans le cadre de la mise en œuvre de 2. Livelihoods and Single Stage - One En attente 2021-04- 2021-05- 2021-11- chantiers de THIMO / « CASH IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 03 29 25 FOR WORK » à Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa)/NU ZR-FSRDC-236145-GO-RFQ / Fourniture des masques faciaux en tissus réutilisable dans le cadre de la mise en 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- œuvre de chantiers de travaux IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 30 25 21 à haute intensité de main d’œuvre (THIMO) / « CASH FOR WORK » à Gbadolite et Mobayi Mbongo. ZR-FSRDC-236081-GO-RFQ / Fourniture de la limonite 2. Livelihoods and Single Stage - One En attente 2021-04- 2021-06- 2021-12- dans les 27 Sous projets de la IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 18 13 10 ville de Kananga en Lot unique /KNGA MOF-REF-75 / Acquisition des EPI complémentaires dans le cadre de la mise en œuvre 2. Livelihoods and Single Stage - One En attente 2021-04- 2021-06- 2021-12- IDA / 66650 A posteriori Demande de prix Limited 0.00 de 5 chantiers de THIMO « Employment Generation Envelope d'exécution 18 13 10 cash for work » à Kananga / KNGA ZR-FSRDC-236147-GO-RFQ / Acquisition des EPI complémentaires dans le 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 cadre de la mise en œuvre de Employment Generation Envelope d'exécution 16 11 07 6 chantiers de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236320-GO-RFQ / Acquisition des EPI complémentaires dans le 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 cadre de la mise en œuvre de Employment Generation Envelope d'exécution 16 11 07 6 chantiers de THIMO « cash for work » à Kananga / KNGA ZR-FSRDC-236516-GO-RFQ / Acquisition des EPI dans le 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- cadre de la mise en œuvre de IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 16 11 07 9 chantiers de THIMO « cash for work » 0 Kanaga/KNGA ZR-FSRDC-236323-GO-RFQ / Acquisition outillage 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 suplementaire ( Nganza sud, Employment Generation Envelope d'exécution 10 07 04 sukisa) ZR-FSRDC-236547-GO-RFQ / Acquisition outillage 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 suplementaire ( Employment Generation Envelope d'exécution 10 07 04 Mabondo,Itabayi) ZR-FSRDC-236539-GO-RFQ / Acquisition outillage 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 suplementaire ( Kamilabi, Employment Generation Envelope d'exécution 10 07 04 malanji) ZR-FSRDC-236540-GO-RFQ / Acquisition outillage 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 suplementaire ( Mpokolo, Employment Generation Envelope d'exécution 10 07 04 tukombe) ZR-FSRDC-236326-GO-RFQ 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- / Acquisition Panneaux de IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 10 07 04 signalisation ( Nganza, sukisa) ZR-FSRDC-236328-GO-RFQ / Acquisition Panneaux de 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 signalisation ( Employment Generation Envelope d'exécution 10 07 04 Kamilabi,malanji) ZR-FSRDC-236397-GO-RFQ / Acquisition Panneaux de 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 signalisation ( Mabondo, Employment Generation Envelope d'exécution 10 07 04 itabayi) ZR-FSRDC-236329-GO-RFQ / Acquisition Panneaux de 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 A posteriori Demande de prix Limited 0.00 signalisation ( Mpokolo, Employment Generation Envelope d'exécution 10 07 04 tukombe) ZR-FSRDC-236551-GO-RFQ / Acquisition de trois Single Stage - One En attente 2021-03- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 véhicules automobiles 4x4 Envelope d'exécution 02 27 24 pour le projet STEP II ZR-FSRDC-236847-GO-RFQ Single Stage - One En attente 2021-07- 2021-07- 2021-09- 2021-10- 2021-11- 2022-11- / Fourniture de bureau et IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 26 31 11 11 15 15 consommable informatique ZR-FSRDC-220580-GO-RFQ / Acquisition de matériels Single Stage - One En attente 2021-02- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 informatiques pour le staff du Envelope d'exécution 24 21 18 projet STEP II ZR-FSRDC-223099-GO-RFQ / Acquisition d’équipements de protection individuelle dans le cadre de la mise en œuvre de chantiers de travaux 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 à haute intensité de main Employment Generation Envelope d'exécution 13 08 04 d’œuvre (Thimo) « cash for work » à Mobayi mbongo (quartiers Ngonda, Mune, Nziamba, et Kumbu) ZR-FSRDC-223086-GO-RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en œuvre de chantiers de travaux à haute 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 intensité de main d’œuvre Employment Generation Envelope d'exécution 13 08 04 (Thimo) « cash for work » a Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa). Page 6 ZR-FSRDC-223095-GO-RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en œuvre de 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- chantiers de travaux à haute IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 13 08 04 intensité de main d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Nganza, Kambo, Tudu, et Bambu) ZR-FSRDC-49338-GO-RFQ / Acquisition de 50 tablettes 1. Support to Community Single Stage - One En attente 2018-02- 2018-04- 2018-10- IDA / 57510 A posteriori Demande de prix Limited 0.00 pour MIS de Kalemie et filières Resilience Envelope d'exécution 10 07 04 agricoles ZR-FSRDC-223080-GO-RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en œuvre de chantiers de travaux à haute 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 intensité de main d’œuvre Employment Generation Envelope d'exécution 13 08 04 (Thimo) « cash for work » à Gbadolite (quartiers Kaya, Pangoma, Mbanza, Mowanda et Lite) ZR-FSRDC-223071-GO-RFQ / Acquisition d’équipements de protection individuelle dans le cadre de la mise en œuvre de chantiers de travaux 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 à Haute Intensité de Main Employment Generation Envelope d'exécution 13 08 04 d’Œuvre (THIMO) / « Cash For Work » à Gbadolite (Quartiers Kaya, Pangoma, Mbanza, Mowanda et Lite). ZR-FSRDC-223082-GO-RFQ / Acquisition d’équipements de protection individuelle dans le cadre de la mise en œuvre de chantiers de travaux 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 à haute intensité de main Employment Generation Envelope d'exécution 13 08 04 d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Molegbe, Fadu, Gobele, Gbau, Bakpa, Kawele et Fiwa). ZR-FSRDC-49609-GO-RFQ / Acquisition de 7 groupes motopompes pour Brigade d'entretien -THIMO Single Stage - One En attente 2018-03- 2018-05- 2018-11- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 1) Lot 1: Nord Kivu (2), 2) Envelope d'exécution 12 07 03 Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (1), 4)Lot 4: Haut Uele (1), 5) Lot 5: Tanganyika (1) ZR-FSRDC-120255-GO-RFQ / Acquisition de 8 motos pour Single Stage - One En attente 2019-06- 2019-08- 2020-02- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 IPAPEL et SENASEM pour la Envelope d'exécution 26 21 17 province de Tanganyika ZR-FSRDC-223091-GO-RFQ / Acquisition d’équipements de protection individuelle dans le cadre de la mise en œuvre de chantiers de travaux 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 à haute intensité de main Employment Generation Envelope d'exécution 13 08 04 d’œuvre (Thimo) « cash for work » à Gbadolite (quartiers Nganza, Kambo, Tudu, et Bambu) ZR-FSRDC-228078-GO-RFQ / Acquisition de deux générateurs de 20 KVA pour Single Stage - One En cours 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 les bâtiments du Envelope d'exécution 17 13 12 09 FSRDC/Antennes du Nord Ubangi et Kasaï Central ZR-FSRDC-223142-GO-RFQ / Acquisition des outillages (petits matériels) dans le cadre de la mise en œuvre de chantiers de travaux à haute 2. Livelihoods and Single Stage - One En attente 2021-03- 2021-05- 2021-11- IDA / 66650 A posteriori Demande de prix Limited 0.00 intensité de main d’œuvre Employment Generation Envelope d'exécution 13 08 04 (Thimo) « cash for work » à Mobayi mbongo (quartiers Ngonda, Mune, Nziamba, et Kumbu) ZR-FSRDC-120248-GO-RFQ / Acquisition de 2 Véhicules 4 Single Stage - One En attente 2019-06- 2019-08- 2020-02- X 4 cinq portes pour IPAPEL et IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Envelope d'exécution 27 22 18 SENASEM pour la province de Tanganyika ZR-FSRDC-121711-GO-RFQ / Acquisition de trois (3) appareils Topographique Single Stage - One En attente 2019-07- 2019-09- 2020-03- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Station Totale pour OVD dans Envelope d'exécution 18 12 10 les provinces de Tshopo, Ituri et Tanganyika ZR-FSRDC-49229-GO-RFQ / Acquisition de 5 vehicules additionnelles pour les Single Stage - One 2018-03- 2018-04- 2018-10- partenaires institutionnelles IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Envelope 05 30 27 (OVD Bunia 1,OVD Kisangani 1, OVD Bukavu 1 OVD Kalemie 1 et OVD Nord Kivu) ZR-FSRDC-49623-GO-RFQ / Acquisition de 36 motos - pour OVD (10) et Carg (26) 1) Lot 1: Nord Kivu (9), 2) Single Stage - One 2018-03- 2018-05- 2018-11- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Lot 2: Sud Kivu (9), 3) Lot 3: Envelope 10 05 01 Ituri (9), 4)Lot 4: Haut Uele (5), 5) Lot 5: Tanganyika (2) et 6) Lot 6: Tshopo (2) ZR-FSRDC-51040-GO-RFB / Acquisition de 6 Kits pour Single Stage - One 2018-03- 2018-03- 2018-04- 2018-05- 2018-06- 2018-12- IDA / 57510 3. Capacity Building A posteriori Appel d'offres Open - National 0.00 Annulé Mini-LABOSEM physique dans Envelope 07 12 23 23 27 24 un corridor ZR-FSRDC-49377-GO-RFQ / Acquisition de 14 tronçonneuses pour Brigade d'entretien -THIMO: 1) Lot 1: Single Stage - One 2018-03- 2018-05- 2018-10- IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Nord Kivu (4); 2) Lot 2: Sud Envelope 06 01 28 Kivu (4); 3) Lot 3; Ituri (2); 4)Lot 4: Haut Uele (2)); 5) Lot 5: Tanganyika (2) ZR-FSRDC-49335-GO-RFQ / Acquisition de 10 compacteurs manuels pour Brigade d'entretien -THIMO - Single Stage - One 2018-03- 2018-05- 2018-04- 2018-10- OVD IDA / 57510 3. Capacity Building A posteriori Demande de prix Limited 0.00 Annulé Envelope 05 03 30 27 1) Lot 1: Nord Kivu (2), 2) Lot 2: Sud Kivu (2), 3) Lot 3: Ituri (2), 4)Lot 4: Tshopo (2), 5) Lot 5: Tanganyika (2) ZR-FSRDC-239840-GO-RFQ / Fourniture d'équipements/mobiliers 1. Support to Community Single Stage - One En attente 2021-09- 2021-11- 2022-04- IDA / 66650 A posteriori Demande de prix Limited 0.00 scolaires pour l'EP BISHIYA, Resilience Envelope d'exécution 06 01 30 l'EP MUAKAJI et l'EP1 DIBANDA du secteur de DIBANDA_KC ZR-FSRDC-239842-GO-RFQ / Fourniture d'équipements/mobiliers 1. Support to Community Single Stage - One En attente 2021-09- 2021-10- 2022-04- scolaires pour l'EP NDIBU IDA / 66650 A posteriori Demande de prix Limited 0.00 Resilience Envelope d'exécution 05 31 29 KALAMBA, l'EP LUAJA et l'EP LUKULA du secteur de KASANGIDI_KC Page 7 ZR-FSRDC-239843-GO-RFQ / Fourniture d'équipements/mobiliers scolaires pour l'EP1 BASANGA, 1. Support to Community Single Stage - One En attente 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Demande de prix Limited 0.00 l'EP NTUADIJILU, l'EP Resilience Envelope d'exécution 05 31 29 MAMBASAKO et l'EP TSHIMAKAKA du secteur KASANGIDI_KC NON CONSULTING SERVICES Activity Reference No. / Draft Pre- Draft Bidding Bid Evaluation Report Loan / Credit Market Procurement Prequalification Actual Amount Process Prequalification Specific Procurement Bidding Documents as Proposal Submission Description Component Review Type Method qualification Document / and Recommendation Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Evaluation Report Notice / Invitation Issued / Opening / Minutes Documents Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-139684-NC-RFQ / Recrutement d'un Consultant firme/individuel pour la traduction de 1. Support to Community Single Stage - One 2019-10- 2019-10- 2020-04- IDA / 57510 A posteriori Demande de prix Limited 0.00 Annulé documents de travail du Resilience Envelope 11 22 19 Fonds Social de la RDC du Français en Anglais et de l'Anglais en Français. ZR-FSRDC-232738-NC-RFQ / Souscription d’une Single Stage - One En attente 2021-06- 2021-08- 2022-02- assurance maladie en faveur IDA / 66650 4. Project Management A posteriori Demande de prix Limited 0.00 Envelope d'exécution 20 15 11 du personnel du STEP2 et leurs ayants droits ZR-FSRDC-236411-NC-RFQ / Impression et fourniture des Single Stage - One En attente 2021-03- 2021-04- 2021-10- supports de visibilité pour la IDA / 66650 5. CERC A posteriori Demande de prix Limited 0.00 Envelope d'exécution 01 26 23 distribution du cash à Kinshasa ZR-FSRDC-236346-NC-RFQ / Impression et fourniture de Single Stage - One En attente 2021-02- 2021-04- 2021-10- 100 000 flyers et 1 000 IDA / 66650 5. CERC A posteriori Demande de prix Limited 0.00 Envelope d'exécution 23 20 17 affiches pour la distribution du Cash à Kinshasa ZR-FSRDC-236549-NC-RFQ / Mise en place et suivi d’une Single Stage - One En attente 2021-01- 2021-03- 2021-09- collecte de données par IDA / 66650 5. CERC A posteriori Demande de prix Open - National 0.00 Envelope d'exécution 10 07 03 téléphone mobile dans la ville de Kinshasa ZR-FSRDC-232792-NC-RFQ / Services de Paiements Single Stage - One En attente 2021-07- 2021-09- 2022-03- IDA / 66650 5. CERC A posteriori Demande de prix Limited 0.00 Digitaux des Bénéficiaires Envelope d'exécution 20 14 13 STEP-KANANGA ZR-FSRDC-220606-NC-RFQ / Transport des équipements et matériels dans le cadre de 2. Livelihoods and Single Stage - One En attente 2021-02- 2021-04- 2021-10- la mise en œuvre de chantiers IDA / 66650 A posteriori Demande de prix Limited 0.00 Employment Generation Envelope d'exécution 24 21 18 de travaux à haute intensité de main d'œuvre (THIM) "cash work" vers Gbadolite ZR-FSRDC-190923-NC-RFB / Recrutement des prestataire Single Stage - One 2020-08- 2020-09- 2020-09- 2020-09- 2020-10- 2020-10- 2020-11- 2020-11- de Services de Paiements IDA / 66650 5. CERC A priori Appel d'offres Limited 0.00 Annulé Envelope 28 02 01 06 01 16 09 18 Digitaux des Bénéficiaires STEP-Kinshasa ZR-FSRDC-236334-NC-RFQ / Selection d'une entreprise Single Stage - One En attente 2021-02- 2021-03- 2021-09- pour assurer les Services de IDA / 66650 5. CERC A posteriori Demande de prix Limited 0.00 Envelope d'exécution 02 30 26 Paiements Digitaux des Bénéficiaires STEP-Kinshasa CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-46218-CS-UN / Recrutement de FAO pour la mise en œuvre des filières Passation de agricoles dans le corridor 2. Livelihoods and marchés auprès 2018-02- 2018-06- 2018-08- IDA / 57510 A priori Direct 1,508,910.79 Signé Kalemie-Nyunzu - bassins de Employment Generation des agences de 10 21 09 Kyoko, Kasanga-Nyemba et l'ONU Kisunkulu, Province de Tanganyika ZR-FSRDC-46235-CS-FBS / Recrutement d'une ONG partenaire de la mise en Sélection dans le 2. Livelihoods and 2018-01- 2018-01- 2018-01- 2018-02- 2018-03- 2018-03- 2020-07- œuvre des filières agricoles IDA / 57510 A posteriori cadre d'un budget Open - National 0.00 Annulé 2018-01-26 Employment Generation 26 29 29 09 10 18 05 dans le bassin de Panda, déterminé corridor de Kalemie- Nyunzu, Province de Tanganyika ZR-FSRDC-232808-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-09- 2021-11- 2021-12- 2022-01- 2022-07- IDA / 66650 A posteriori Open - National 0.00 2021-08-31 contrôle pour la Construction Resilience qualifications des d'exécution 21 04 04 08 07 de l’EP Ouelé/ Zabo / consultants ZR-FSRDC-232815-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la Construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Nzewe/ Ubangi/ consultants ZR-FSRDC-232819-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la Construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Sorozo1/ Sorozo 2 consultants ZR-FSRDC-232823-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la Construction Resilience qualifications des d'exécution 28 11 10 15 13 des EP Mbongo/ Yakoma consultants ZR-FSRDC-232824-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Ouelé/Yakoma consultants ZR-FSRDC-232827-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Zabo/Yakoma consultants ZR-FSRDC-232829-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Ubangi/Yakoma consultants ZR-FSRDC-232831-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Sorozo 1/Yakoma consultants ZR-FSRDC-232832-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Yakoma/Yakoma consultants ZR-FSRDC-232838-CS-CQS Sélection fondée / Recrutement d’un bureau de 1. Support to Community sur les En attente 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 A posteriori Open - National 0.00 2021-06-07 contrôle pour la construction Resilience qualifications des d'exécution 28 11 10 15 13 de l’EP Wakwa/Yakoma consultants ZR-FSRDC-232862-CS-CQS Sélection fondée / Agence de communication 2. Livelihoods and sur les En attente 2021-08- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 0.00 2021-07-12 pour l’élaboration du plan de Employment Generation qualifications des d'exécution 02 15 15 19 18 communication de STEP-CERC consultants Page 8 Sélection fondée ZR-FSRDC-232901-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Bureau de contrôle pour l'EP IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 à KABUAYI consultants Sélection fondée ZR-FSRDC-232902-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutrement d'un bureau IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 de contrôle pour l'EP à Central consultants ZR-FSRDC-232903-CS-CQS Sélection fondée / Recrutement d'un bureau de 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 0.00 2021-06-30 contrôle pour l'EP à LUABA Resilience qualifications des d'exécution 15 21 03 03 07 06 NTONDO consultants ZR-FSRDC-232905-CS-CQS Sélection fondée / Recrutement d'un bureau de 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 0.00 2021-06-30 contrôle pour l'EP à MBULU- Resilience qualifications des d'exécution 15 21 03 03 07 06 MIKONGO consultants Sélection fondée ZR-FSRDC-232906-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à MPANDA consultants Sélection fondée ZR-FSRDC-232907-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à TUBADI consultants Sélection fondée ZR-FSRDC-232908-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à LUBALA consultants Sélection fondée ZR-FSRDC-232909-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à MITENGU consultants Sélection fondée ZR-FSRDC-232910-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à NSELE consultants Sélection fondée ZR-FSRDC-232911-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à THSIBALA consultants Sélection fondée ZR-FSRDC-232912-CS-CQS 1. Support to Community sur les En cours 2021-06- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- / Recrutement d'un bureau de IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Resilience qualifications des d'exécution 15 21 03 03 07 06 contrôle pour l'EP à TSHIMAYI consultants ZR-FSRDC-233375-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée Capacités des Bénéficiaires 2. Livelihoods and sur les En cours 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 0.00 2021-06-30 THIMO de 1 350 bénéficiaires Employment Generation qualifications des d'exécution 06 21 03 03 07 06 pour les ( Malandi, kamayi, consultants thsinsambi, Platea, Mpemba) de la ville de Kananga ZR-FSRDC-233377-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée Capacités des Bénéficiaires 2. Livelihoods and sur les En cours 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- THIMO de 1 350 bénéficiaires IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Employment Generation qualifications des d'exécution 06 21 03 03 07 06 pour les ( Nsele Nganza - consultants Nord, Nganza- Sud, Saloneo- Muimba- lubi-A-Mpata- Sukisa) de la ville de Kananga ZR-FSRDC-233378-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée Capacités des Bénéficiaires 2. Livelihoods and sur les En cours 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- IDA / 66650 A posteriori Open - National 0.00 2021-06-30 THIMO de 1 350 bénéficiaires Employment Generation qualifications des d'exécution 06 21 03 03 07 06 pour les ( katokaz- Mpokolo- consultants kelekele- Kapanda- Tukombe) de la ville de Kananga ZR-FSRDC-233379-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée Capacités des Bénéficiaires 2. Livelihoods and sur les En cours 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- THIMO de 1 350 bénéficiaires IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Employment Generation qualifications des d'exécution 06 21 03 03 07 06 pour les ( Ndesma- Thibanda consultants Banda- Kamilabi- Lubuwa- Kamu pongo) de la ville de Kananga ZR-FSRDC-233381-CS-CQS / Recrutement d’une Structure chargée du Renforcement de Sélection fondée Capacités des Bénéficiaires 2. Livelihoods and sur les En cours 2021-05- 2021-07- 2021-09- 2021-10- 2021-11- 2022-05- THIMO de 1 350 bénéficiaires IDA / 66650 A posteriori Open - National 0.00 2021-06-30 Employment Generation qualifications des d'exécution 06 21 03 03 07 06 pour les ( Mabondo- Itabayi- consultants Lumumba-dikongayi- Mulunda- Tshibashi) de la ville de Kananga ZR-FSRDC-236086-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Lungandu/KC consultants Sélection fondée MOF-REF-95 / Bureau pour 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- contrôle et Surveillance des IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Resilience qualifications des d'exécution 20 05 04 09 05 travaux de l'EP Ngindalalyi/KC consultants ZR-FSRDC-236398-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EPArc En Ciel/KC consultants ZR-FSRDC-236344-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Lumumba 1/KC consultants ZR-FSRDC-236029-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Muindindi/KC consultants ZR-FSRDC-236034-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Mukoleshi/KC consultants ZR-FSRDC-236143-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Kandiku/KC consultants ZR-FSRDC-236399-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EPA Mufumishi/KC consultants ZR-FSRDC-236345-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Mudidike/KC consultants ZR-FSRDC-236500-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Nganza/KC consultants Page 9 ZR-FSRDC-236059-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Tshisambi/KC consultants ZR-FSRDC-236517-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Diku/KC consultants MOF-REF-107 / Bureau pour Sélection fondée contrôle et Surveillance des 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 travaux de l'EP Resilience qualifications des d'exécution 20 05 04 09 05 TOSALISANA/KC consultants ZR-FSRDC-236412-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Disanka/KC consultants ZR-FSRDC-236543-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Mgr Bakafua/KC consultants ZR-FSRDC-236374-CS-CQS Sélection fondée / Bureau pour contrôle et 2. Livelihoods and sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Employment Generation qualifications des d'exécution 20 05 04 09 05 l'EP Bushala Muamba/KC consultants ZR-FSRDC-236365-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Ndesha/KC consultants ZR-FSRDC-236523-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Baolongo/KC consultants ZR-FSRDC-236082-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP TSHISUMBU/KC consultants ZR-FSRDC-236091-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP Tuya Kumpala/KC consultants ZR-FSRDC-236109-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP SANKAYI/KC consultants ZR-FSRDC-236512-CS-CQS Sélection fondée / Bureau pour contrôle et 1. Support to Community sur les En attente 2021-01- 2021-03- 2021-04- 2021-05- 2021-11- IDA / 66650 A posteriori Open - National 0.00 2020-12-30 Surveillance des travaux de Resilience qualifications des d'exécution 20 05 04 09 05 l'EP DIKONGAYI/KC consultants ZR-FSRDC-191902-CS-CQS / Recrutement d'un consultant Sélection fondée pour la mise en place et suivi sur les En attente 2020-09- 2020-11- 2020-12- 2021-01- 2021-07- de l’auto-enregistrement par IDA / 66650 5. CERC A posteriori Open - National 0.00 2020-09-07 qualifications des d'exécution 28 11 11 15 14 téléphone mobile des consultants personnes éligibles sur le registre des bénéficiaires. ZR-FSRDC-121707-CS-QCBS / Recruitment d'un consultant pour la réalisation d' Audit Sélection fondée technique externe du Projet 1. Support to Community Open - En attente 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2020-07- IDA / 57510 A posteriori sur la qualité et le 0.00 2019-07-08 pour la Stabilisation de l'Est Resilience International d'exécution 10 13 14 16 18 21 20 coût de la RDC pour la Paix "STEP" pour les exercices 2017, 2018 et 2019, ZR-FSRDC-46241-CS-QCBS / Recruitement d'un consultant Sélection fondée 1. Support to Community Open - 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- 2019-03- pour la réalisation de audit IDA / 57510 A posteriori sur la qualité et le 0.00 Annulé 2018-02-01 Resilience International 02 04 05 15 25 09 09 financier et comptable des coût exercices 2017, 2018 et 2019 ZR-FSRDC-87769-CS-CQS / Recrutement d'un Consultant- Sélection fondée firme pour mener l'enquête 2. Livelihoods and sur les 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-03- IDA / 57510 A posteriori Open - National 0.00 Annulé 2018-11-23 finale d'évaluation d'impact de Employment Generation qualifications des 07 26 10 14 31 29 la composante THIMO urbain consultants du Projet STEP. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-FSRDC-110894-CS-CDS / Recrutement de l'Institut National de Préparation Sélection de 1. Support to Community 2020-02- 2019-04- 2019-07- 2019-12- Professionnel « INPP » pour la IDA / 57510 A priori consultants par Direct 0.00 Annulé 2019-04-19 Resilience 16 29 03 30 formation des bénéficiaires « entente directe THIMO sociaux », deuxième phase ZR-FSRDC-232841-CS-CQS / Recrutement d'un consultant 1. Support to Community En attente 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Individuel Limited 0.00 2021-06-07 en appui au CTIC/ Nord Resilience d'exécution 12 03 07 03 Ubangi (consultant 1) ZR-FSRDC-232840-CS-INDV / Recrutement d'un En cours 2021-05- 2021-08- 2021-08- 2021-09- 2022-03- IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-06-15 Spécialiste, Expert en MEDAC d'exécution 19 03 24 28 27 du Projet STEP 2 ZR-FSRDC-232847-CS-INDV / Recrutement d'un consultant 1. Support to Community En attente 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 A posteriori Individuel Limited 0.00 2021-06-07 en appui au CTIC/Nord Resilience d'exécution 12 03 07 03 Ubangi (consultant 2) ZR-FSRDC-232849-CS-INDV En attente 2021-08- 2021-08- 2021-09- 2022-03- / Recrutement d'un Assistant IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-06-15 d'exécution 03 24 28 27 Comptable pour le Projet STEP ZR-FSRDC-232851-CS-INDV / Contractualisation par entente directe de Monsieur En attente 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-06-15 Guy BUKALANGI comme d'exécution 25 16 20 16 Assistant du Chargé des Opérations du Projet STEP 2 ZR-FSRDC-232855-CS-INDV En cours 2021-06- 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-06-30 / Chargé des MESDAC/KC d'exécution 01 18 08 13 11 ZR-FSRDC-232854-CS-INDV / Recrutement d'un En attente 2021-06- 2021-07- 2021-08- 2022-02- Consultant Secrétaire IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 d'exécution 20 11 15 11 Réceptionniste du Projet STEP 2 ZR-FSRDC-232859-CS-INDV En attente 2021-09- 2021-10- 2021-11- 2022-05- / Chargé du Transfert IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-07-30 d'exécution 17 08 12 11 Monétaire/KC ZR-FSRDC-232860-CS-INDV En cours 2021-06- 2021-10- 2021-11- 2021-12- 2022-06- / Assistant Administratif et IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-08-31 d'exécution 01 19 09 14 12 Financier/KC ZR-FSRDC-232861-CS-INDV En cours 2021-06- 2021-07- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-30 / Caissier/KC d'exécution 21 05 26 30 26 Page 10 ZR-FSRDC-232863-CS-INDV En attente 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-09-30 / Chauffeur 1 des courses/KC d'exécution 05 26 30 29 ZR-FSRDC-232864-CS-INDV En attente 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-09-30 / Chauffeur 2 des courses/KC d'exécution 05 26 30 29 ZR-FSRDC-232865-CS-INDV En attente 2021-10- 2021-10- 2021-11- 2022-05- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-09-30 / Chauffeur 3 des courses/KC d'exécution 05 26 30 29 ZR-FSRDC-232867-CS-INDV En attente 2021-12- 2022-01- 2022-02- 2022-08- IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-10-29 / Chargé de MGP/KC d'exécution 17 07 11 10 ZR-FSRDC-232866-CS-INDV / Recrutement d'un Assistant En attente 2021-08- 2021-08- 2021-09- 2022-03- en Base de Données (gestion IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-06-15 d'exécution 03 24 28 27 du système intégré/MIS) du Projet STEP 2 ZR-FSRDC-232868-CS-INDV / Recrutement d'un En attente 2021-08- 2021-08- 2021-09- 2022-03- Consultant Chargé de IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-06-15 d'exécution 03 24 28 27 Transfert Monétaire à l'antenne du Nord Ubangi ZR-FSRDC-232870-CS-INDV / Consultant chargé de la comptabilité pour le En attente 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 5. CERC A posteriori Individuel Open 0.00 2021-07-12 Contingent Emergency d'exécution 30 20 25 23 Response Component ‘CERC- COVID19’ KINSHASA ZR-FSRDC-232871-CS-INDV / Recrutement d'un Assistant En attente 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 Administratif et Financier du d'exécution 20 11 15 11 Projet STEP 2 ZR-FSRDC-232872-CS-INDV En cours 2021-06- 2021-06- 2021-07- 2021-08- 2022-02- / Recrutement d'un Caissier IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 d'exécution 21 20 11 15 11 pour l'antenne du Nord Ubangi ZR-FSRDC-232873-CS-INDV / Recrutement d'un Chauffeur En attente 2021-06- 2021-07- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 n° 1 de Course du Projet STEP d'exécution 20 11 15 11 2 ZR-FSRDC-232874-CS-INDV En attente 2021-06- 2021-07- 2021-08- 2022-02- / Recrutement d'un Chauffeur IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 d'exécution 20 11 15 11 n° 2 du Projet STEP 2 ZR-FSRDC-232876-CS-INDV En attente 2021-06- 2021-07- 2021-08- 2022-02- / Recrutement d'un Chauffeur IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-06-15 d'exécution 20 11 15 11 N) 3 du Projet STEP 2 ZR-FSRDC-191751-CS-INDV / Recrutement du Chargé des En attente 2020-09- 2020-09- 2020-09- 2020-10- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-09-07 Opérations du STEP 2 d'exécution 11 13 17 23 (François Kabemba) ZR-FSRDC-232836-CS-INDV / Recrutement d'un chargé de En attente 2021-08- 2021-08- 2021-09- 2022-03- IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-07-30 communication du Projet STEP d'exécution 04 25 29 28 2 ZR-FSRDC-236277-CS-INDV 1. Support to Community En attente 2020-12- 2021-01- 2021-02- 2021-08- / Consultant en appui IDA / 66650 A posteriori Individuel Limited 0.00 2020-12-18 Resilience d'exécution 23 13 17 16 STIC/KC ZR-FSRDC-236355-CS-INDV 1. Support to Community En attente 2021-02- 2021-02- 2021-04- 2021-09- / Consultant en appui IDA / 66650 A posteriori Individuel Open 0.00 2020-12-18 Resilience d'exécution 05 26 02 29 STIC/KC ZR-FSRDC-236035-CS-INDV / CI pour contrôle et 1. Support to Community En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 0.00 2020-12-30 Surveillance des travaux de Resilience d'exécution 17 10 14 11 l'EP Kapajika/KC ZR-FSRDC-236161-CS-INDV / CI pour contrôle et 1. Support to Community En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 0.00 2020-12-30 Surveillance des travaux de Resilience d'exécution 17 10 14 11 l'EP Tshibashi/KC ZR-FSRDC-236401-CS-INDV / Consultant Individuel pour 1. Support to Community En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 0.00 2020-12-30 contrôle et Surveillance des Resilience d'exécution 17 10 14 11 travaux de l'EP Diku Dietu/KC ZR-FSRDC-236400-CS-INDV / Consultant Individuel pour 1. Support to Community En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 0.00 2020-12-30 le contrôle et Surveillance des Resilience d'exécution 17 10 14 11 travaux de l'EP DJAKAJA/KC ZR-FSRDC-236366-CS-INDV / Sélection de Consultants 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 0.00 2021-03-01 formateurs des Chefs de Resilience d'exécution 19 10 14 11 Chantiers/NU ZR-FSRDC-236368-CS-INDV / Sélection de Consultants 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 0.00 2021-03-01 formateurs des Chefs de Resilience d'exécution 19 10 14 11 Chantiers/NU ZR-FSRDC-236347-CS-INDV / Consultant pour réaliser le suivi environnemental et social des chantiers Ecoles 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Open 0.00 2021-03-01 dans la ville de Gbadolite et la Resilience d'exécution 19 10 14 11 cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236372-CS-INDV / Consultant pour réaliser les screening environnementaux et sociaux des chantiers 1. Support to Community En attente 2021-05- 2021-06- 2021-07- 2022-01- THIMO dans la ville de IDA / 66650 A posteriori Individuel Open 0.00 2021-03-31 Resilience d'exécution 19 09 14 10 Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236089-CS-INDV / Consultant pour appuyer le suivi des appels à travers les numéros verts du MGP des 2. Livelihoods and En attente 2021-05- 2021-06- 2021-07- 2022-01- chantiers THIMO et Ecoles IDA / 66650 A posteriori Individuel Open 0.00 2021-03-31 Employment Generation d'exécution 19 09 14 10 dans la ville de Gbadolite et la cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236350-CS-INDV / Consultant pour réaliser le suivi environnemental et social des chantiers THIMO 2. Livelihoods and En attente 2021-05- 2021-06- 2021-07- 2022-01- IDA / 66650 A posteriori Individuel Open 0.00 2021-03-31 dans la ville de Gbadolite et la Employment Generation d'exécution 19 09 14 10 cité de Mobayi Mbongo dans le cadre du lancement du STEP II au Nord Ubangi ZR-FSRDC-236092-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-02- 2021-03- 2021-04- 2021-10- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Open 0.00 2020-12-25 Employment Generation d'exécution 12 05 09 06 des chantiers THIMO à Kananga ZR-FSRDC-236094-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-02- 2021-03- 2021-04- 2021-10- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Open 0.00 2020-12-25 Employment Generation d'exécution 12 05 09 06 des chantiers THIMO à Kananga Page 11 ZR-FSRDC-236514-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-02- 2021-03- 2021-04- 2021-10- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Open 0.00 2020-12-25 Employment Generation d'exécution 12 05 09 06 des chantiers THIMO à Kananga ZR-FSRDC-236044-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236371-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236103-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236422-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236096-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236351-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236110-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236045-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236403-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236369-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236087-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236376-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236515-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236370-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236352-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236278-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236146-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236112-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236528-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236409-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236402-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236135-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236382-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236530-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236046-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236154-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236532-CS-INDV 2. Livelihoods and En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 A posteriori Individuel Open 0.00 2020-11-24 / Consultants Enquêteurs/KC Employment Generation d'exécution 12 02 09 05 ZR-FSRDC-236279-CS-INDV 2. Livelihoods and En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 A posteriori Individuel Open 0.00 2020-12-21 / Consultant en appui SSS/KC Employment Generation d'exécution 08 01 05 02 ZR-FSRDC-236137-CS-INDV En attente 2021-05- 2021-06- 2021-07- 2022-01- / Spécialiste en Sauvegardes IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-04-05 d'exécution 24 14 19 15 Environnementales ZR-FSRDC-236357-CS-INDV En attente 2021-02- 2021-03- 2021-04- 2021-10- / Spécialiste en Suivi et IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-01-10 d'exécution 28 21 25 22 Evaluation STEP 2 ZR-FSRDC-236506-CS-INDV / Contractualisation avec le En attente 2021-04- 2021-05- 2021-06- 2021-12- Consultant Yves MISSIATU IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-04-01 d'exécution 11 02 06 03 comme Assistant en Passation des Marches du Projet STEP 2 ZR-FSRDC-236138-CS-INDV / Contractualisation avec le Consultant Danny KALEMBU RUTAMU comme Chargé du En attente 2021-02- 2021-03- 2021-04- 2021-10- Développement IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-02-15 d'exécution 25 18 22 19 Communautaire et Gestion des Conflits à l'antenne du Nord-Ubangi dans le cadre du Projet STEP 2 ZR-FSRDC-235770-CS-INDV / Contractualisation avec le En attente 2020-09- 2020-09- 2020-10- 2021-04- Consultant Francois KABEMBA IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-08-24 d'exécution 03 24 29 27 comme Chargé des Opérations du Projet STEP 2 ZR-FSRDC-235768-CS-INDV / Contractualisation avec le Consultant Claude OGOU En attente 2021-04- 2021-04- 2021-05- 2021-11- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-03-22 comme Assistant Technique d'exécution 01 22 27 23 en Passation des Marchés du Projet STEP 2 ZR-FSRDC-236005-CS-INDV / Contractualisation avec le Consultant Magnant En attente 2020-10- 2020-11- 2020-12- 2021-06- MUBONGE MUKULUMANYA IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-10-14 d'exécution 24 14 19 17 comme Spécialiste en Sauvegardes Sociales du Projet STEP 2 ZR-FSRDC-236006-CS-INDV / Contractualisation avec la Consultante Sylvie LUZALA En attente 2020-10- 2020-11- 2020-12- 2021-06- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-10-19 comme Assistant du Chargé d'exécution 29 19 24 22 des Opérations du Projet STEP 2 (Administration-RH) Page 12 ZR-FSRDC-236534-CS-INDV / Contractualisation avec le Consultant Ademar NAMUISI En attente 2021-01- 2021-02- 2021-03- 2021-09- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-01-06 KINABUNA comme Chauffeur d'exécution 16 06 13 09 du Chargé des Opérations du Projet STEP 2 ZR-FSRDC-236164-CS-INDV / Contractualisation avec le En attente 2021-01- 2021-02- 2021-03- 2021-09- Consultant D'Acquin NZAU IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-01-06 d'exécution 16 06 13 09 DIMAVINGA comme Chauffeur du Projet STEP 2 ZR-FSRDC-235773-CS-INDV / Contractualisation avec le En attente 2020-10- 2020-11- 2020-12- 2021-06- Consultant Adeline M'BUY IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-10-16 d'exécution 26 16 21 19 MANDEAK comme Caissière du Projet STEP 2 ZR-FSRDC-236525-CS-INDV / Contractualisation avec le Consultant Bernard TSHISHIKU En attente 2020-12- 2020-12- 2021-01- 2021-07- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-11-23 BULULU comme Chargé de la d'exécution 03 24 28 27 Comptabilité à l'antenne du Kasai Central ZR-FSRDC-236053-CS-INDV / Contractualisation avec le Consultant Raymond BWANAHERI MAPISANO comme Chargé de En attente 2021-02- 2021-03- 2021-04- 2021-10- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-02-15 Développement d'exécution 25 18 22 19 Communautaire et Gestion des Conflits à l'antenne du Kasai Central dans la le cadre du Projet STEP 2 ZR-FSRDC-236057-CS-INDV / Contractualisation avec le Consultant Joslin KAMADILU En attente 2021-03- 2021-04- 2021-05- 2021-11- TSHIPAMBULA comme Chargé IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-03-02 d'exécution 12 02 07 03 de Suivi et Evaluation à l'angtenne du Kasai Central dans le cadre du Projet STEP 2 ZR-FSRDC-235697-CS-INDV / Contractualisation avec le Consultant Zacharie MASIALA LELI-VAKANDA comme En attente 2021-02- 2021-03- 2021-04- 2021-10- Spécialiste en Travaux IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-02-15 d'exécution 25 18 22 19 d'Infrastructures Communautaires à l'antenne du Kasai Central dans le cadre du Projet STEP 2 ZR-FSRDC-236148-CS-INDV / Contractualisation avec le Consultant Titien LIKONDJI En attente 2020-10- 2020-11- 2020-12- 2021-06- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-10-14 BAATA comme Spécialiste en d'exécution 24 14 19 17 Infrastructure au sein du Projet STEP 2 ZR-FSRDC-236330-CS-INDV / Contractualisation avec le Consultant Serge MUFENGI En attente 2020-10- 2020-11- 2020-12- 2021-06- NZOFU comme Spécialiste en IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2020-10-20 d'exécution 30 20 25 23 Travaux à Haute Intensité de Main d’œuvre au sein du Projet STEP 2 ZR-FSRDC-236076-CS-INDV En attente 2021-05- 2021-06- 2021-07- 2022-01- / Chargé en Travaux à Haute IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-04-06 d'exécution 25 15 20 16 Intensité de Main d’œuvre ZR-FSRDC-236166-CS-INDV En attente 2021-05- 2021-06- 2021-07- 2022-01- / Chargé des Sauvegardes IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2021-04-06 d'exécution 25 15 20 16 Environnementales et Sociales ZR-FSRDC-235776-CS-INDV / Contractualisation avec le En attente 2021-04- 2021-05- 2021-06- 2021-12- Consultant Serge ZOLA KIAMA IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-04-19 d'exécution 29 20 24 21 comme Chauffeur du Projet STEP 2 ZR-FSRDC-236078-CS-INDV En attente 2021-05- 2021-06- 2021-07- 2022-01- / Spécialiste en Base de IDA / 66650 5. CERC A posteriori Individuel Open 0.00 2021-04-01 d'exécution 20 10 15 11 Données du CERC-STEP2 ZR-FSRDC-236009-CS-INDV En attente 2021-04- 2021-04- 2021-05- 2021-11- / Assistant en Mécanisme de IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-03-29 d'exécution 03 24 29 25 Gestion des Plaintes CERC Kin ZR-FSRDC-236332-CS-INDV / Chargé du suivi des activités En attente 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-02 de transfert monétaire dans le d'exécution 07 28 02 29 cadre du STEP-Kin ZR-FSRDC-236083-CS-INDV / Chargé du suivi des activités En attente 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-02 de transfert monétaire dans le d'exécution 07 28 02 29 cadre du STEP-Kin ZR-FSRDC-236027-CS-INDV / Chargé du suivi des activités En attente 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-02 de transfert monétaire dans le d'exécution 07 28 02 29 cadre du STEP-Kin ZR-FSRDC-236036-CS-INDV / Chargé du suivi des activités En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-05 de transfert monétaire dans le d'exécution 10 01 05 02 cadre du STEP-Kin ZR-FSRDC-236404-CS-INDV / Chargé du suivi des activités En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-07 de transfert monétaire dans le d'exécution 12 03 07 04 cadre du STEP-Kin ZR-FSRDC-236388-CS-INDV En attente 2020-11- 2020-12- 2021-01- 2021-07- / Expert en Transfert IDA / 66650 5. CERC A posteriori Individuel Open 0.00 2020-10-05 d'exécution 23 14 18 17 Monétaire du CERC ZR-FSRDC-236040-CS-INDV / Chargé du suivi des En attente 2021-04- 2021-04- 2021-06- 2021-11- IDA / 66650 5. CERC A posteriori Individuel Limited 0.00 2021-04-01 mécanismes de gestion des d'exécution 06 27 01 28 plaintes du STEP2 ZR-FSRDC-237038-CS-INDV 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- / Consultant en appui IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 Resilience d'exécution 17 08 12 09 STIC/KC ZR-FSRDC-237039-CS-INDV 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- / Consultant en appui IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 Resilience d'exécution 17 08 12 09 STIC/KC ZR-FSRDC-237034-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-04- 2021-05- 2021-06- 2021-12- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 Employment Generation d'exécution 17 08 12 09 des chantiers THIMO à Kananga ZR-FSRDC-237040-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-04- 2021-05- 2021-06- 2021-12- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 Employment Generation d'exécution 17 08 12 09 des chantiers THIMO à Kananga ZR-FSRDC-237037-CS-INDV / Consultants en appui au 2. Livelihoods and En attente 2021-04- 2021-05- 2021-06- 2021-12- STHIMO pour la supervision IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 Employment Generation d'exécution 17 08 12 09 des chantiers THIMO à Kananga Page 13 ZR-FSRDC-237035-CS-INDV / Consultants en appui pour 1. Support to Community En attente 2021-04- 2021-05- 2021-06- 2021-12- IDA / 66650 A posteriori Individuel Limited 0.00 2021-04-12 le suivi environnemental et Resilience d'exécution 17 08 12 09 social de kananga ZR-FSRDC-237048-CS-INDV / Contractualisation au poste En cours 2021-06- 2021-07- 2021-07- 2021-09- 2022-03- IDA / 66650 4. Project Management A posteriori Individuel Direct 0.00 2021-06-30 de MEDAC avec Adolphe d'exécution 15 10 31 04 03 NAKAKULA ZR-FSRDC-237050-CS-INDV En attente 2021-08- 2021-08- 2021-09- 2022-03- / Recrutement d'un MGP Kasaï IDA / 66650 4. Project Management A posteriori Individuel Limited 0.00 2021-07-30 d'exécution 04 25 29 28 Central ZR-FSRDC-220633-CS-CDS / Recrutement du Coordonnateur de la Sélection de convention de partenariat En attente 2021-06- 2021-08- 2022-02- IDA / 66650 4. Project Management A posteriori consultants par Direct 0.00 2021-05-31 FSRDC-MINAS pour le Projet d'exécution 10 14 10 entente directe STEP II par entente directe avec Mr Jules BISILWALA MUSUKU ZR-FSRDC-191792-CS-INDV / Recrutement du En attente 2020-09- 2020-10- 2020-11- 2021-05- IDA / 66650 4. Project Management A posteriori Individuel Open 0.00 2020-09-07 Responsable Administratif et d'exécution 21 12 16 15 Financier du STEP 2 ZR-FSRDC-191764-CS-INDV / Recrutement du Spécialiste En attente 2020-09- 2020-10- 2020-10- 2021-10- IDA / 57510 4. Project Management A posteriori Individuel Open 0.00 2020-09-07 en Passation des Marchés du d'exécution 24 01 22 17 Projet STEP 2 ZR-FSRDC-141795-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser la mission d’élaborer 1. Support to Community En attente 2019-10- 2019-10- 2019-10- 2019-11- le Cadre de Politique de IDA / 57510 A posteriori Individuel Limited 0.00 2019-10-22 Resilience d'exécution 24 25 28 12 Réinstallation (CPR) du Projet de STEP - FA dans les provinces de Kasai, Kasai Oriental et Kasai Central ZR-FSRDC-141821-CS-INDV / Recrutement d'un Consultant Individuel pour réaliser la mission d’élaborer 1. Support to Community En attente 2019-10- 2019-10- 2019-10- 2019-11- le Cadre de Gestion IDA / 57510 A posteriori Individuel Limited 0.00 2019-10-22 Resilience d'exécution 25 26 29 13 Environnementale et Sociale (CGES) du Projet de STEP - FA dans les provinces de Kasai, Kasai Oriental et Kasai Central ZR-FSRDC-120259-CS-INDV / Recrutement de consultants 1. Support to Community En attente 2019-07- 2019-07- 2019-07- 2019-07- individuels/panels pour IDA / 57510 A posteriori Individuel Limited 0.00 2019-06-30 Resilience d'exécution 02 07 17 23 appuyer le FSRDC dans les évaluations des offres. ZR-FSRDC-236830-CS-CDS / recrutement du consultant Sélection de GiveDirectly, pour la mise en 1. Support to Community En cours 2021-06- 2021-07- 2021-09- 2022-03- IDA / 66650 A posteriori consultants par Direct 0.00 2021-06-30 œuvre du Pilote MobileAid Resilience d'exécution 17 10 13 12 entente directe dans le cadre du programme STEP KIN ZR-FSRDC-239849-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-21 surveillance de l'EP BISHIYA Resilience d'exécution 26 16 20 19 dans le secteur de DIBANDA_KC ZR-FSRDC-239851-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-20 surveillance de l'EP MUAKAJI Resilience d'exécution 25 15 19 18 dans le secteur de DIBANDA_KC ZR-FSRDC-239852-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-20 surveillance de l'EP1 DIBANDA Resilience d'exécution 25 15 19 18 dans le secteur de DIBANDA_KC ZR-FSRDC-239853-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-20 surveillance de l'EP NDIBU Resilience d'exécution 25 15 19 18 KALAMBA dans le secteur de KASANGIDI_KC ZR-FSRDC-239856-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-21 surveillance de l'EP LUAJA Resilience d'exécution 26 16 20 19 dans le secteur de KASANGIDI_KC ZR-FSRDC-239857-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-22 surveillance de l'EP3 LUKULA Resilience d'exécution 27 17 21 20 dans le secteur de KASANGIDI_KC ZR-FSRDC-239858-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-22 surveillance de l'EP1 BASANGA Resilience d'exécution 27 17 21 20 dans le secteur de KASANGIDI_KC ZR-FSRDC-239859-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-23 surveillance de l'EP Resilience d'exécution 28 18 22 21 NTUADIJILU dans le secteur de KASANGIDI_KC ZR-FSRDC-239860-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-07- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-26 surveillance de l'EP Resilience d'exécution 31 21 25 24 MAMBASAKO dans le secteur de KASANGIDI_KC ZR-FSRDC-239861-CS-INDV / Recrutement d'un consultant individuel pour le contrôle et 1. Support to Community En attente 2021-08- 2021-08- 2021-09- 2022-03- IDA / 66650 A posteriori Individuel Limited 0.00 2021-07-27 surveillance de l'EP Resilience d'exécution 01 22 26 25 TSHIMAKAKA dans le secteur de KASANGIDI_KC ZR-FSRDC-240661-CS-INDV / Recrutement d'un Assistant En attente 2021-08- 2021-09- 2021-10- 2022-04- IDA / 66650 5. CERC A posteriori Individuel Open 0.00 2021-06-30 Technique International en d'exécution 18 08 13 11 transferts monétaires Page 14