PROCUREMENT PLAN PERU INTEGRATED WATER RESOURCES MANAGEMENT IN TEN BASINS PROJECT P151851 I. General 1. Bank’s approval Date of the procurement Plan: Original, February 23, 2017 2. Date of General Procurement Notice: February 23, 2017 3. Period covered by this procurement plan: all the procurement process planned II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Below US$ 2 million None 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Below US$ 10 million None 2. Project Operational/Procurement Manual: Procurement implementation details activities will be outlined in the Project Operational Manual (POM) 3. Any Other Special Procurement Arrangements: None 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 Description Estimated Package Domestic Review Comments Cost s Preferenc by Bank US$ e (Prior / Post) million (yes/no) Summary of the ICB (Goods) 25.2 5 No Prior Summary of the NCB (Works) 9.28 5 No Post Summary of the NCB (Goods) 3.16 4 No Post III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 350,000 All 2. Single Source (Firms) All 3. Individual Key personnel All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 350,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Description of Assignment Estimated Packages Review Comments Cost by Bank US$ million (Prior / Post) Summary of number of 15.95 10 Prior contracts that will be let under QCBS > US$ 350 mil Summary of number of 1.20 5 Post contracts that will be let under QCBS < US$ 350 mil PROCUREMEN Peru : Integrated Water Resources Management in Ten Basins T PLAN General Information Country: Peru Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 2020-10-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151851 GPN Date: Project Name: Integrated Water Resources Management in Ten Basins Loan / Credit No: IBRD / 87400 Executing Agency(ies): National Water Authority of the Ministry of Agriculture - Autoridad Nacional del Agua (ANA) WORKS Estimate Bid Evaluation Activity Reference No. High Procurement Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio d Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method SEA/SH Document Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) Amount Status Evaluation Report as Issued Recommendation Completion Risk Type (US$) Documents Justification / Invitation Opening / Minutes (US$) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planne d LPN 003 2018 ANA PGIRH BM / PERFORACIÓN E Component 1: INSTALACIÓN DE 58 Solicitud de Single Stage - 2,205,593.0 En 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2019-01- IBRD / 87400 Consolidating IWRM at Posterior Open - National 0.00 PIEZÓMETROS EN LOS ofertas One Envelope 0 ejecución 26 08 29 28 25 07 27 26 23 the National Level ACUÍFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA LPN 007-2018-ANA- PGIRH-BM / PERFORACION E INSTALACION DE 58 PIEZOMETROS EN LOS Component 1: Solicitud de Single Stage - 1,664,437.0 2,141,562. 2018-10- 2018-10- 2018-10- 2018-10- 2018-11- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- 2019-04- ACUIFEROS DE ICA Y IBRD / 87400 Consolidating IWRM at Posterior Open - National Firmado ofertas One Envelope 0 01 04 12 07 12 06 21 16 28 05 05 03 TACNA lote 1 ICA 28 the National Level perfotaciones metodo diamantina, lote 2 TACNA 8 perforaciones metodo diamantina, lote 3 TACNA 22 perforaciones metodo RC CP 001 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA Component 1: Solicitud de Single Stage - 2018-10- 2018-11- 2018-12- EJECUCIÒN DE IBRD / 87400 Consolidating IWRM at Posterior Limited 21,870.00 0.00 Cancelado cotizaciones One Envelope 21 15 30 PERFORACIÒN E the National Level INSTALACION DE 28 PIEZOMETROS EN LOS ACUIFEROS DE ICA CP 002 2018 ANA PGIRH BM / OBRAS PRELIMINARES Y DE CIERRE PARA LA Component 1: Solicitud de Single Stage - Ejecución 2018-10- 2018-11- 2018-12- EJECUCION DE IBRD / 87400 Consolidating IWRM at Posterior Limited 13,587.00 0.00 cotizaciones One Envelope pendiente 21 15 30 PERFORACION E the National Level INSTALACION DE 30 PIEZOMETROS EN LOS ACUIFEROS DE TACNA CP 003 2018 ANA PGIRH BM / Component 1: CONSTRUCCION DE Solicitud de Single Stage - 2019-04- 2019-05- 2019-06- IBRD / 87400 Consolidating IWRM at Posterior Limited 55,239.00 0.00 Cancelado CASETAS DE cotizaciones One Envelope 07 02 16 the National Level PROTECCION DE 30 PIEZOMETROS EN LOS ACUIFEROS DE TACNA LPN 008 2018 ANA PGIRH / Contratación para la Construcción - Obras Civiles para la Implementación de la Component 1: Infraestructura del Centro Solicitud de Single Stage - 2019-06- 2019-06- 2019-07- 2019-07- 2019-08- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 238,806.00 0.00 Cancelado de Datos, Laboratorio de ofertas One Envelope 24 26 26 31 17 13 the National Level Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-126672-CW-RFQ / Perforación y habilitación Component 1: Solicitud de Single Stage - Ejecución 2019-09- 2019-10- 2019-12- de 18 piezómetros en los IBRD / 87400 Consolidating IWRM at Posterior Open - National 180,000.00 0.00 cotizaciones One Envelope pendiente 21 31 15 acuiferos de Ica, Villacurí the National Level y Lanchas PE-ANA-126678-CW-RFQ / CONSTRUCCIÓN DE 30 ESTRUCTURAS DE Component 1: Solicitud de Single Stage - Ejecución 2019-09- 2019-10- 2019-12- PROTECCIÓN EN IBRD / 87400 Consolidating IWRM at Posterior Open - National 45,000.00 0.00 cotizaciones One Envelope pendiente 21 31 15 PIEZOMETROS the National Level UBICADOS EN EL ACUIFERO CAPLINA PE-ANA-121004-CW-RFQ / Obras Civiles para la Implementación del Centro de Datos, Laboratorio de Component 1: Solicitud de Single Stage - 2019-09- 2019-10- 2020-04- Instrumentación, Centro de IBRD / 87400 Consolidating IWRM at Posterior Open - National 238,806.00 0.00 Cancelado cotizaciones One Envelope 18 26 23 Monitoreo y Modelamiento the National Level de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-139769-CW-RFB / Obras Civiles para la Implementación del Centro de Datos, Laboratorio de Component 1: Solicitud de Single Stage - 392,098.5 2019-10- 2019-10- 2019-10- 2020-02- 2019-12- 2019-11- 2019-12- 2019-12- 2019-12- 2020-02- 2020-03- Instrumentación, Centro de IBRD / 87400 Consolidating IWRM at Posterior Open - National 410,326.94 Firmado ofertas One Envelope 0 21 25 26 18 07 29 17 20 27 14 26 Monitoreo y Modelamiento the National Level de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-145138-CW-RFQ / Construcción de Component 1: subestación y red de Solicitud de Single Stage - Ejecución 2019-11- 2019-12- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 58,541.00 0.00 media tensión para la cotizaciones One Envelope pendiente 22 06 04 the National Level electrificación del Centro de Procesamiento de Datos Secundarios ICA PE-ANA-145139-CW-RFQ Component 1: / CONSTRUCCIÓN DE Solicitud de Single Stage - Ejecución 2019-11- 2019-12- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 30,434.00 0.00 RED MATRIZ DE AGUA cotizaciones One Envelope pendiente 22 06 20 the National Level Y DESAGUE PE-ANA-165869-NC-RFB / CONSTRUCCIÓN DE 22 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-07- 2020-09- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 117,848.00 0.00 cotizaciones One Envelope pendiente 06 01 29 MEDICIÓN DE AGUA EN the National Level LA REGIÓN TUMBES PE-ANA-165872-NC-RFB / CONSTRUCCIÓN DE 11 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-07- 2020-08- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 58,924.00 0.00 cotizaciones One Envelope pendiente 06 01 30 MEDICIÓN DE AGUA EN the National Level LA REGIÓN MOQUEGUA PE-ANA-165873-NC-RFB / CONSTRUCCIÓN DE 15 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-07- 2020-08- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 80,351.00 0.00 cotizaciones One Envelope pendiente 06 01 30 MEDICIÓN DE AGUA EN the National Level LA REGIÓN TACNA PE-ANA-165981-CW-RFB / CONSTRUCCIÓN DE Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-10- 131 ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 701,729.85 0.00 ofertas One Envelope pendiente 15 12 MEDICIÓN DE AGUA EN the National Level LA REGIÓN PIURA PE-ANA-166005-CW-RFB / CONSTRUCCIÓN DE 95 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 508,889.00 0.00 ofertas One Envelope pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN LAMBAYEQUE PE-ANA-166006-CW-RFB / CONSTRUCCIÓN DE 80 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 428,537.31 0.00 ofertas One Envelope pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN LA LIBERTAD PE-ANA-166008-CW-RFB / CONSTRUCCIÓN DE 73 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 391,041.00 0.00 ofertas One Envelope pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN ANCASH PE-ANA-166009-CW-RFB / CONSTRUCCIÓN DE 87 Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 466,035.00 0.00 ofertas One Envelope pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN LIMA PE-ANA-166011-CW-RFB / CONSTRUCCIÓN DE Component 1: Solicitud de Single Stage - Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- 107 ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 573,168.66 0.00 ofertas One Envelope pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN ICA PE-ANA-166012-CW-RFB / CONSTRUCCIÓN DE Component 1: Solicitud de Single Stage - 1,017,777.0 Ejecución 2020-05- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- 190 ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 0.00 ofertas One Envelope 0 pendiente 01 06 17 17 21 18 MEDICIÓN DE AGUA EN the National Level LA REGIÓN AREQUIPA GOODS Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 LPI 003 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: Solicitud de Open - Single Stage - 2018-07- 2019-05- 2018-07- 2019-06- 2018-09- 2019-09- 2018-09- 2019-10- 2018-10- 2019-11- 2019-01- CAPACITACIÓN DEL IBRD / 87400 Consolidating IWRM at Previa 5,786,425.49 7,338,345.74 Firmado ofertas International One Envelope 06 30 11 03 13 30 23 28 25 13 03 EQUIPAMIENTO PARA the National Level EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 004 2018 ANA PGIRH / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: Solicitud de Open - Single Stage - 2018-07- 2018-07- 2018-09- 2018-09- 2018-10- 2019-01- CAPACITACIÓN DE LOS IBRD / 87400 Consolidating IWRM at Posterior 1,418,283.54 0.00 Cancelado ofertas International One Envelope 09 14 16 26 28 11 SUBSISTEMAS PARA EL the National Level SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2018 ANA PGIRH / SUMINISTRO, INSTALACIÓN PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE EQUIPAMIENTO PARA LA PLATAFORMA Component 1: Solicitud de Single Stage - En 2018-07- 2018-08- 2018-07- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2022-08- 2022-10- TECNOLÓGICA PARA LA IBRD / 87400 Consolidating IWRM at Posterior Open - National 100,250.00 0.00 ofertas One Envelope ejecución 09 05 14 11 16 05 26 31 25 24 ADQUISICIÓN, the National Level DECODIFICACIÓN, INTEGRACIÓN Y DISTRIBUCIÓN DE DATOS DE LAS ESTACIONES AUTOMATICAS CON TELEMETRIA LPN 002 2018 ANA PGIRH BM / ADQUISICIÓN DE Component 1: CATORCE (14) Solicitud de Single Stage - En 2018-07- 2018-08- 2018-07- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- IBRD / 87400 Consolidating IWRM at Posterior Open - National 592,732.00 0.00 VEHÍCULOS PARA LA ofertas One Envelope ejecución 26 22 31 31 17 05 25 20 20 the National Level SUPERVISIÓN, SEDE CENTRAL Y ADMINISTRACIÓN DE LAS CUENCAS DEL PGIRH LPN 004 2018 ANA PGIRH BM / SUMINISTRO, INSTALACIÓN, PUESTA Component 1: Solicitud de Single Stage - 2018-07- 2018-08- 2018-09- 2018-09- 2018-10- 2019-01- EN FUNCIONAMIENTO Y IBRD / 87400 Consolidating IWRM at Posterior Open - National 564,000.00 0.00 Cancelado ofertas One Envelope 31 06 05 17 04 02 CAPACITACIÓN DE 141 the National Level SENSORES CON SISTEMA DE TELEMETRÍA PARA PIEZÓMETROS EN ICA Y TACNA LPI 005 2018 ANA PGIRH BM / SUMINISTRO, Component 1: Solicitud de Open - Single Stage - En 2018-07- 2018-09- 2018-07- 2018-09- 2018-09- 2018-11- 2018-09- 2018-12- 2018-10- 2018-12- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Previa 3,200,000.00 0.00 ofertas International One Envelope ejecución 26 07 31 07 14 22 19 14 04 28 EN FUNCIONAMIENTO Y the National Level CAPACITACIÓN DE INSTRUMENTACIÓN DE PRESAS LPN 006 2018 ANA PGIRH BM / SUMINISTRO, Component 1: Solicitud de Single Stage - 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-12- 2018-10- 2019-01- 2018-11- 2019-03- 2019-02- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Posterior Open - National 645,577.00 0.30 Firmado ofertas One Envelope 13 12 18 12 18 03 21 03 13 25 11 EN FUNCIONAMIENTO Y the National Level CAPACITACIÓN DE INSTRUMENTACIÓN DE PIEZOMETROS CP 010 2018 ANA PGIRH BM / ADQUISICION DE Component 3: General Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2018-11- 2018-12- 2018-12- EQUIPOS IBRD / 87400 Posterior Limited 45,151.52 6,737.05 Finalizado Project Adminstration cotizaciones One Envelope 21 16 06 19 21 13 INFORMATICOS Y ACCESORIOS PERIFERICOS PARA LAS COORDINACIONES TECNICAS DE CUENCA CP 011 2018 ANA PGIRH BM / Component 3: General Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- IBRD / 87400 Posterior Limited 14,470.00 16,425.03 Finalizado ADQUISICION DE LAP Project Adminstration cotizaciones One Envelope 21 23 06 06 21 28 TOP PARA LA SEDE CENTRAL LPN 002 2019 ANA Component 1: PGIRH BM2 / Solicitud de Single Stage - 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- IBRD / 87400 Consolidating IWRM at Posterior Open - National 55,000.00 46,967.58 Firmado ADQUISICIÓN DE ofertas One Envelope 08 25 13 26 15 28 25 03 29 24 13 the National Level CORRENTOMETROS LPI 001 2019 ANA PGIRH BM / SUMINISTRO, Component 1: INSTALACIÓN, PUESTA Solicitud de Open - Single Stage - 2019-02- 2019-03- 2019-03- 2019-03- 2019-04- 2019-04- 2019-04- 2019-06- 2019-06- 2019-07- 2020-06- IBRD / 87400 Consolidating IWRM at Previa 3,200,000.00 2,709,756.00 Firmado EN FUNCIONAMIENTO Y ofertas International One Envelope 24 01 01 01 17 29 24 06 06 12 05 the National Level CAPACITACIÓN DE LA INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS CP 010 B 2018 ANA PGRIH BM / Equipos Component 2: Improving Informaticos y Accesorios Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- 2018-12- 2018-12- 2019-01- IBRD / 87400 WRM in Selected Pilot Posterior Limited 20,121.00 19,216.27 Finalizado Perifericos para las cotizaciones One Envelope 16 16 04 04 24 15 River Basins Coordinaciones Tecnicas de Cuenca. LPN 009 2018 ANA PGIRH / ADQUISICION E INSTALACION DE EQUIPOS DE TELEMETRIA PARA Component 1: ESTRUCTURAS DE Solicitud de Single Stage - 2019-02- 2019-03- 2019-02- 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- IBRD / 87400 Consolidating IWRM at Posterior Open - National 147,962.00 0.00 Cancelado MEDICION DE AGUA ofertas One Envelope 22 08 26 12 28 02 20 20 the National Level CON SENSORES PARA LAS ADMINISTRACIONES DE LOCAL DE AGUA DE TUMBES, PIURA, LAMBAYEQUE, AREQUIPA PE-ANA-116125-GO-RFB / SUMINISTRO , INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: Solicitud de Open - Single Stage - 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-08- 2019-08- 2019-09- 2019-09- 2019-09- 2020-01- CAPACITACIÓN DE LOS IBRD / 87400 Consolidating IWRM at Previa 2,000,000.00 2,473,511.86 Firmado ofertas International One Envelope 27 30 01 03 13 26 12 20 16 27 14 SUBSISTEMAS PARA EL the National Level SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPI 006 2018 ANA PGIRH BM / ADQUISICIÓN, INSTALACIÓN, CAPACITACIÓN Y Component 1: PUESTA EN MARCHA Solicitud de Open - Single Stage - 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-11- 2020-08- IBRD / 87400 Consolidating IWRM at Previa 3,480,149.89 0.00 Cancelado DE EQUIPOS DE ofertas International One Envelope 10 15 15 17 25 19 10 the National Level MEDICIÓN DE AGUA Y TRANSMISIÓN DE DATOS EN LAS CAPTACIONES Y BLOQUES DE RIEGO SELECCIONADOS EN LA COSTA DEL PERU PE-ANA-116523-GO-RFB / SUMINISTRO, INSTALACIÓN, PUESTA Component 1: EN FUNCIONAMIENTO Y Solicitud de Open - Single Stage - Bajo 2019-10- 2020-06- 2019-10- 2020-06- 2019-11- 2020-10- 2019-12- 2020-01- 2022-01- IBRD / 87400 Consolidating IWRM at Previa 7,874,768.00 0.00 CAPACITACIÓN DE 153 ofertas International One Envelope Revision 10 26 19 26 23 05 08 04 03 the National Level ESTACIONES HIDROLÓGICAS CON 33 EHCA LPI 001 ANA PGIRH / SUMINISTRO, INSTALACIÓN, PUESTA Component 1: EN FUNCIONAMIENTO Y Solicitud de Open - Single Stage - 2019-04- 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- IBRD / 87400 Consolidating IWRM at Previa 7,874,768.00 0.00 Cancelado CAPACITACIÓN DE 153 ofertas International One Envelope 05 14 16 07 31 30 the National Level ESTACIONES HIDROLÓGICAS CON 33 EHCA PE-ANA-121041-GO-RFP / Component 1: ADQUISICIÓN DE Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Open - National 36,882.35 0.00 PLOTTERS E cotizaciones One Envelope pendiente 06 18 18 the National Level IMPRESORAS LPN 005 2018 ANA PGIRH BM / SUMINISTRO , INSTALACIÓN, PUESTA Component 1: Solicitud de Single Stage - 2019-03- 2019-03- 2019-04- 2019-04- 2019-05- 2019-07- EN FUNCIONAMIENTO Y IBRD / 87400 Consolidating IWRM at Posterior Open - National 1,418,283.54 0.00 Cancelado ofertas One Envelope 01 02 02 13 03 02 CAPACITACIÓN DE LOS the National Level SUBSISTEMAS PARA EL SISTEMA DE SEGURIDAD Y RESPALDO DE LA INFORMACIÓN LPN 001 2019 ANA PGIRH BM / EQUIPAMIENTO PARA LA IMPLEMENTACIÓN DE LAS SALAS DE Component 2: Improving Solicitud de Single Stage - En 2019-10- 2020-07- 2019-10- 2019-11- 2020-09- 2019-12- 2020-01- 2020-03- MONITOREO HÍDRICO IBRD / 87400 WRM in Selected Pilot Posterior Open - National 850,000.00 0.00 ofertas One Envelope ejecución 01 24 09 25 04 05 06 06 EN LOS COORDINACIÓN River Basins DE RECURSOS HÍDRICOS DE LAS CUENCAS DE LA VERTIENTE DEL ATLÁNTICO PE-ANA-134184-GO-RFQ / ADQUISICION DE Component 1: Solicitud de Single Stage - 2019-09- 2019-11- 2019-10- 2019-12- 2019-10- SOFTWARE (INC. IBRD / 87400 Consolidating IWRM at Posterior Limited 32,613.00 37,219.02 Firmado cotizaciones One Envelope 18 25 07 20 22 LICENCIA) DISEÑO DE the National Level PROCESOS PE-ANA-155600-GO-RFQ / ADQUISICIÓN DE EQUIPOS Component 1: Solicitud de Single Stage - Ejecución 2020-01- 2020-02- 2020-03- DEMOSTRATIVOS: IBRD / 87400 Consolidating IWRM at Posterior Open - National 13,134.00 0.00 cotizaciones One Envelope pendiente 28 04 05 CUATRO DE MEDICIÓN the National Level DE AGUA Y CUATRO DE TRANSMISIÓN DE DATOS. Page 2 PE-ANA-158249-GO-RFB / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y Component 1: CAPACITACIÓN DE Solicitud de Open - Single Stage - En 2020-03- 2020-10- 2020-03- 2020-05- 2020-05- 2020-06- 2021-10- IBRD / 87400 Consolidating IWRM at Previa 3,822,975.00 0.00 INSTRUMENTACIÓN ofertas International One Envelope ejecución 17 20 22 06 26 30 23 the National Level PARA LA MEDICIÓN DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO EN LA COSTA DEL PERÚ PE-ANA-155601-GO-RFQ / ADQUISICIÓN DE ACCESORIOS PARA Component 1: Solicitud de Single Stage - En 2020-01- 2020-03- 2020-02- 2020-04- CORRENTOMETROS IBRD / 87400 Consolidating IWRM at Posterior Open - National 5,970.00 0.00 cotizaciones One Envelope ejecución 28 12 04 06 ELECTROMAGNÉTICOS the National Level (BARRA CONCENTRICA HERES) LPI 002 ANA PGIRH / SUMINISTRO INSTALACION PUESTA Component 1: Solicitud de Open - Single Stage - 2019-04- 2019-04- 2019-06- 2019-07- 2019-07- 2020-07- EN FUNCIONAMIENTO Y IBRD / 87400 Consolidating IWRM at Previa 3,190,000.00 0.00 Cancelado ofertas International One Envelope 05 19 20 06 21 20 CAPACITACION DE 110 the National Level SISTEMA MECANIZADOS DE AFOROS PE-ANA-161081-GO-RFQ / SUMINISTRO, INSTALACIÓN, PUESTA EN FUNCIONAMIENTO Y CAPACITACIÓN DE 121 SISTEMAS MECANIZADOS DE Component 1: AFOROS, 05 PASARELAS Solicitud de Open - Single Stage - Bajo 2020-03- 2020-07- 2020-03- 2020-07- 2020-05- 2020-10- 2020-06- 2020-07- 2021-12- IBRD / 87400 Consolidating IWRM at Previa 3,500,000.00 0.00 METÁLICAS PARA ofertas International One Envelope Revision 16 15 21 16 02 23 01 06 28 the National Level AFOROS Y WINCHES PARA AFOROS EN SECCIONES DE CONTROL DE ESTACIONES HIDROLÓGICAS PARA FINES DE GESTIÓN DE RECURSOS HÍDRICOS PE-ANA-161126-GO-RFQ / SUMINISTRO, INSTALACIÓN Y Component 1: CAPACITACIÓN DE 90 Solicitud de Single Stage - Ejecución 2020-03- 2020-03- 2020-04- 2020-05- 2020-07- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Open - National 456,716.00 0.00 CAUDALIMETROS Y ofertas One Envelope pendiente 12 17 28 28 02 29 the National Level SISTEMA DE TELEMETRIA EN EL ACUÍFERO CAPLINA PE-ANA-164500-GO-RFQ / Component 1: Solicitud de Single Stage - Ejecución 2020-03- 2020-04- 2020-06- compra de flujometros IBRD / 87400 Consolidating IWRM at Posterior Open - National 26,000.00 0.00 cotizaciones One Envelope pendiente 27 03 04 ultrasonicos portátiles the National Level PE-ANA-164501-GO-RFB / ADQUISICIÓN DE UNA Component 1: Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-05- COMPRESORA PARA IBRD / 87400 Consolidating IWRM at Posterior Open - National 35,000.00 0.00 cotizaciones One Envelope pendiente 06 20 30 MONITOREO DE AGUAS the National Level SUBTERRANEAS PE-ANA-165163-GO-RFQ / ADQUISICIÓN DE Component 3: General Solicitud de Single Stage - Ejecución 2020-04- 2020-05- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 0.00 MOBILIARIO PARA LAS Project Adminstration cotizaciones One Envelope pendiente 19 14 29 OFICINAS DEL PGIRH PE-ANA-165181-GO-RFQ / ADQUISICION DE Component 1: EQUIPAMIENTO PARA Solicitud de Single Stage - Ejecución 2020-06- 2020-08- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 23,000.00 0.00 ANALISIS cotizaciones One Envelope pendiente 19 14 10 the National Level HIDROBIOLOGICO EN LAS CUATRO CUENCAS PE-ANA-165894-GO-RFQ / Component 1: ADQUISICIÓN DE 03 Solicitud de Single Stage - Ejecución 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at Posterior Limited 2,687.00 0.00 NIVELES DE cotizaciones One Envelope pendiente 22 08 07 the National Level INGENIERO, INCLUIDO ACCESORIOS PE-ANA-161084-GO-RFQ / SUMINISTRO Y Component 1: CAPACITACIÓN DE Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-06- 2020-06- 2020-07- 2020-11- IBRD / 87400 Consolidating IWRM at Posterior Open - National 1,200,000.00 0.00 EQUIPOS E ofertas One Envelope pendiente 17 22 03 23 28 05 the National Level INSTRUMENTACIÓN HIDROLÓGICA PE-ANA-186823-GO-RFQ / ADQUISICIÓN E Component 1: INSTALACIÓN DE BASES Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 18,000.00 0.00 ANTI SÍSMICAS PARA cotizaciones One Envelope pendiente 18 06 05 the National Level EL SISTEMA ELÉCTRICO DEL CENTRO DE DATOS PE-ANA-116126-GO-RFB / ADQUISICIÓN DE EQUIPOS DE MEDICIÓN Component 1: Y TRANSMISIÓN DE Solicitud de Open - Single Stage - 2019-05- 2019-06- 2019-07- 2019-08- 2019-09- 2020-06- IBRD / 87400 Consolidating IWRM at Previa 3,822,971.00 0.00 Cancelado DATOS PARA EL ofertas International One Envelope 27 01 13 12 16 12 the National Level CONTROL DEL AGUA EN LAS CAPTACIONES Y BLOQUES DE RIEGO PE-ANA-164478-GO-RFB / Component 1: ADQUISICIÓN DE Solicitud de Single Stage - 2020-04- 2020-04- 2020-06- 2020-07- 2020-08- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 247,100.00 0.00 Cancelado EQUIPOS DE MEDICIÓN ofertas One Envelope 20 25 06 06 10 06 the National Level DE CAUDAL - TIPO ADCP PE-ANA-167427-GO-RFQ / Adquisición de equipos de Component 1: Solicitud de Single Stage - Ejecución 2020-04- 2020-05- 2020-06- medición de caudal y IBRD / 87400 Consolidating IWRM at Posterior Limited 37,500.00 0.00 cotizaciones One Envelope pendiente 15 05 19 medición de calidad de the National Level agua en campo PE-ANA-163933-GO-RFB / ADQUISICIÓN DE EQUIPOS Component 1: MULTIPARÁMETROS Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-05- 2020-06- 2020-07- 2020-09- IBRD / 87400 Consolidating IWRM at Posterior Open - National 755,000.00 0.00 PORTÁTILES PARA ofertas One Envelope pendiente 01 06 18 17 22 20 the National Level MEDICIÓN DE CALIDAD DE AGUA SUPERFICIAL PE-ANA-190562-GO-RFQ / ADQUISICION DE EQUIPOS DE MUESTREO Component 1: Solicitud de Single Stage - Ejecución 2020-10- 2020-10- 2020-12- Y EQUIPOS IBRD / 87400 Consolidating IWRM at Posterior Limited 38,000.00 0.00 cotizaciones One Envelope pendiente 02 26 25 MULTIPARAMETROS the National Level PARA AGUAS SUBTERRANEAS PE-ANA-190602-GO-RFQ / Component 1: ADQUISICION DE Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 43,000.00 0.00 EQUIPOS DE cotizaciones One Envelope pendiente 29 29 28 the National Level PROSPECCION GEOFISICA PE-ANA-190604-GO-RFQ / Component 1: ADQUISICION DE Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Open - National 43,000.00 0.00 SONDA DE RESONANCIA cotizaciones One Envelope pendiente 30 26 25 the National Level MAGNETICA NUCLEAR PE-ANA-190605-GO-RFQ / ADQUISICION DE Component 1: Solicitud de Single Stage - Ejecución 2020-09- 2020-11- 2021-01- EQUIPOS DE PERFILAJE IBRD / 87400 Consolidating IWRM at Posterior Limited 30,000.00 0.00 cotizaciones One Envelope pendiente 30 04 03 GEOFISICO Y DE the National Level CAUDAL DE POZOS PE-ANA-190607-GO-RFQ / ADQUISICION DE Component 1: Solicitud de Single Stage - Ejecución 2020-10- 2020-11- 2021-01- SOFTWARE DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 20,000.00 0.00 cotizaciones One Envelope pendiente 02 10 09 MODELAMIENTO the National Level HIDROGEOLOGICO PE-ANA-190610-GO-RFQ / Component 1: ADQUISICION DE Solicitud de Single Stage - Ejecución 2020-09- 2020-11- 2021-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 40,000.00 0.00 EQUIPOS SISTEMA CMT cotizaciones One Envelope pendiente 29 03 02 the National Level PARA SEIS PIEZOMETROS PE-ANA-194534-GO-RFB / ADQUISICIÓN DE Component 1: CAMIONETAS PARA LA Solicitud de Single Stage - Ejecución 2020-10- 2020-10- 2020-11- 2020-12- 2021-01- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 183,000.00 0.00 SUPERVISION - EQUIPO ofertas One Envelope pendiente 12 17 28 08 05 04 the National Level TECNICO COORDINADO DE EHA- SMA PE-ANA-199721-GO-RFQ / Impresoras Multifuncional Monocromática para la Component 2: Improving Implementación de las Solicitud de Single Stage - Ejecución 2020-10- 2020-10- 2021-02- IBRD / 87400 WRM in Selected Pilot Posterior Limited 50,000.00 0.00 Salas de Monitoreo Hídrico cotizaciones One Envelope pendiente 18 28 25 River Basins en las Coordinaciones de Recursos Hídricos de las Cuencas de la Vertiente NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Actual Draft Pre- Draft Bidding Specific Proposal Loan / Market Procurement Prequalificatio Process Prequalification Bidding Documents Report and Contract / Description Component Review Type Method Amount Amount qualification Document / Procurement Notice Submission / Signed Contract Credit No. Approach Process n (Y/N) Status Evaluation Report as Issued Recommendation Completion (US$) (US$) Documents Justification / Invitation Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CP 004 2018 ANA Component 1: PGIRH BM / SERVICIO Solicitud de Single Stage - Ejecución 2018-12- 2019-01- 2019-03- IBRD / 87400 Consolidating IWRM at Posterior Limited 38,044.00 0.00 DE NIVELACION Y cotizaciones One Envelope pendiente 23 17 03 the National Level MONUMENTACION ICA CP 005 2018 ANA Component 1: PGIRH BM / SERVICIO Solicitud de Single Stage - Ejecución 2018-12- 2019-01- 2019-03- IBRD / 87400 Consolidating IWRM at Posterior Limited 40,760.00 0.00 DE NIVELACION Y cotizaciones One Envelope pendiente 22 16 02 the National Level MONUMENTACION TACNA CP 008 2018 ANA Component 1: PGIRH BM / Solicitud de Single Stage - Ejecución 2018-10- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 29,892.00 0.00 ADQUISICION DE DOS cotizaciones One Envelope pendiente 21 06 21 the National Level CAUDALIMETROS ULTRASONICOS Page 3 CP 009 2018 ANA Component 1: PGIRH BM / Solicitud de Single Stage - Ejecución 2018-10- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 29,629.00 0.00 ADQUISICION DE UNA cotizaciones One Envelope pendiente 21 06 21 the National Level CAMARA DE INSPECCION DE POZOS CP 014 2018 ANA PGIRH BM / ADECUACION DE ESTRUCTURA DE MEDICION DE NIVEL Component 1: DE AGUA EN BLOQUES Solicitud de Single Stage - En 2018-10- 2018-11- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 28,528.00 129,635.34 DE RIEGO DE LOS cotizaciones One Envelope ejecución 28 19 20 14 the National Level VALLES DE ALGARROBO - VALLE HERMOSO - HUALTACO I - II - IV - SOMATE ALTO - SOMATE BAJO - VALLE LOS INCAS - CHIPILLICO BAJO -M - CP 015 2018 ANA MALINGAS PGIRH BM / ADECUACION DE ESTRUCTURA DE Component 1: MEDICION DE NIVEL Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 25,934.00 207,452.42 Firmado DE AGUA EN BLOQUES cotizaciones One Envelope 28 19 20 16 13 the National Level DE RIEGO DE LOS VALLES DE QUIROZ PAMPAS-SAN ISIDRO I-II- TEJEDORES-TG- MALINGAS-YUSCAY- TABLAZO ALTO CP 016 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE Solicitud de Single Stage - 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 12,550.00 57,574.33 Firmado MEDICION DE NIVEL cotizaciones One Envelope 02 21 25 16 07 the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE PRAXADES- SANTA MARCELA CP 017 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 28,485.00 26,918.23 Firmado cotizaciones One Envelope 02 12 25 16 18 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE CASCAJAL-ANITAS- ILLIMO CP 018 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 25,990.00 131,662.63 Firmado cotizaciones One Envelope 28 12 20 16 10 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE MARGEN DERECHA CP 019 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - Ejecución 2018-10- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 23,103.00 0.00 cotizaciones One Envelope pendiente 28 20 08 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE MIGUEL CHECA CP 020 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 25,636.00 20,942.09 Firmado cotizaciones One Envelope 28 12 20 16 10 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE CASARANA CP 021 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-10- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 19,167.00 14,735.72 Firmado cotizaciones One Envelope 28 13 20 17 03 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN ANDRES CP 022 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE Solicitud de Single Stage - En 2018-11- 2019-01- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 42,727.00 0.00 MEDICION DE NIVEL cotizaciones One Envelope ejecución 02 09 25 28 the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE CAPOTE-LA RAMADA-CHONGOYAOPE- PITIPO CP 023 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE Solicitud de Single Stage - En 2018-11- 2019-01- 2018-11- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 28,485.00 85,114.40 MEDICION DE NIVEL cotizaciones One Envelope ejecución 02 09 25 18 the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE PUCALA TUMAN-POMALCA CP 024 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2019-01- 2018-11- 2019-02- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 19,939.00 66,347.73 Firmado cotizaciones One Envelope 02 15 25 01 10 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE LAMBAYEQUE CP 025 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - Ejecución 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 37,030.00 0.00 cotizaciones One Envelope pendiente 02 25 19 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE TALAMBO CP 013 2018 ANA PGIRH BM / Component 1: ADECUACION DE Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 39,879.00 20,893.44 Firmado ESTRUCTURA DE cotizaciones One Envelope 28 23 20 16 20 the National Level MEDICION DE NIVEL DE AGUA EN BLOQUES DE RIEGO DEL VALLE CP 026 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - En 2018-11- 2019-01- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 42,342.00 0.00 cotizaciones One Envelope ejecución 02 07 25 28 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN PEDRO CP 027 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - En 2018-11- 2019-01- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 36,697.00 0.00 cotizaciones One Envelope ejecución 02 07 25 19 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN JOSÉ CP 028 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 14,243.00 0.00 Cancelado cotizaciones One Envelope 02 25 07 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAN MIGUEL CP 029 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - Ejecución 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 19,940.00 0.00 cotizaciones One Envelope pendiente 02 25 10 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE SAYAN CP 030 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-12- 2018-11- 2019-01- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 28,485.00 83,611.18 Firmado cotizaciones One Envelope 02 05 25 16 18 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE LLAMACHUPAN CP 031 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 25,636.00 0.00 Cancelado cotizaciones One Envelope 02 25 15 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE HUARICANGA CP 032 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 22,788.00 0.00 Cancelado cotizaciones One Envelope 02 25 13 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE NARANJAL CP 033 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - Ejecución 2018-11- 2018-12- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 28,485.00 0.00 cotizaciones One Envelope pendiente 02 05 28 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE MACASH- POCOS CP 034 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 8,546.00 0.00 Cancelado cotizaciones One Envelope 02 25 04 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE RINCONADA CP 035 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 17,091.00 0.00 Cancelado cotizaciones One Envelope 02 25 08 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE LATERAL 4, 5 Y 6 Page 4 CP 036 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - Ejecución 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 37,030.00 0.00 cotizaciones One Envelope pendiente 02 25 19 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DEL VALLE DE EL CHOLOQUE CP 038 2018 ANA PGIRH BM / ADECUACION DE Component 1: ESTRUCTURA DE Solicitud de Single Stage - 2018-10- 2018-11- 2018-11- 2019-01- 2018-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 22,788.00 38,281.31 Firmado MEDICION DE NIVEL cotizaciones One Envelope 28 23 20 16 08 the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE MALA MUERTE-CHICAMITA CP 006 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Solicitud de Single Stage - 2019-04- 2019-05- 2019-06- MONUMENTACION ICA IBRD / 87400 Consolidating IWRM at Posterior Limited 43,479.00 0.00 Cancelado cotizaciones One Envelope 07 02 16 (POZOS RED CONTROL the National Level GLOBAL ALA, AAA, DCERH) CP 007 2018 ANA PGIRH BM / SERVICIO DE NIVELACION Y Component 1: Solicitud de Single Stage - 2019-04- 2019-05- 2019-06- MONUMENTACION IBRD / 87400 Consolidating IWRM at Posterior Limited 24,457.00 0.00 Cancelado cotizaciones One Envelope 07 02 16 TACNA (POZOS RED the National Level CONTROL GLOBAL ALA, AAA, DCERH) CP 012 2018 ANA PGIRH BM / Component 3: General Solicitud de Single Stage - 2019-04- 2019-04- 2019-06- CONTRATACION DE IBRD / 87400 Posterior Limited 25,000.00 0.00 Cancelado Project Adminstration cotizaciones One Envelope 07 21 14 AGENCIA PARA PUBLICACION DE AVISOS EN DIARIOS CP 037 2018 ANA PGIRH BM / ADECUACION DE Component 1: Solicitud de Single Stage - 2018-11- 2018-11- 2018-12- ESTRUCTURA DE IBRD / 87400 Consolidating IWRM at Posterior Limited 17,091.00 0.00 Cancelado cotizaciones One Envelope 02 25 08 MEDICION DE NIVEL the National Level DE AGUA EN BLOQUES DE RIEGO DE LOS VALLES DE MORO- VICHANZAO PE-ANA-126675-NC-RFQ / SERVICIO DE EJECUCIÓN DE SIETE Component 1: Solicitud de Single Stage - Ejecución 2019-09- 2019-10- 2019-11- PRUEBAS DE BOMBEO IBRD / 87400 Consolidating IWRM at Posterior Open - National 45,000.00 0.00 cotizaciones One Envelope pendiente 21 31 30 EN PIEZÓMETROS the National Level UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-130327-NC-RFQ / SERVICIO DE ELABORACIÓN DEL PLAN DE MONITOREO Component 1: ARQUEOLÓGICO PARA Solicitud de Single Stage - Ejecución 2019-09- 2019-10- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 32,915.00 0.00 ADECUACIÓN DE cotizaciones One Envelope pendiente 20 07 04 the National Level MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LA ZONA SUR DE LA COSTA PE-ANA-133579-NC-RFB / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2019-12- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Limited 8,000.00 0.00 cotizaciones One Envelope pendiente 03 14 13 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 10 SECTORES HIDRÁULICOS CASMA, HUARMEY PE-ANA-133581-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-01- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Limited 12,000.00 0.00 cotizaciones One Envelope pendiente 03 14 12 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 3 SECTORES HIDRÁULICOS MyBP, SECHURA PE-ANA-133582-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 12,000.00 0.00 TÉCNICOS DE cotizaciones One Envelope pendiente 03 14 12 the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 5 SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-133583-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 12,000.00 0.00 TÉCNICOS DE cotizaciones One Envelope pendiente 03 14 10 the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 8 SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-133584-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: EXPEDIENTES Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 16,000.00 0.00 TÉCNICOS DE cotizaciones One Envelope pendiente 03 14 09 the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 12 SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-133585-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-01- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Limited 12,000.00 0.00 cotizaciones One Envelope pendiente 03 14 12 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 13 SECTORES HIDRÁULICOS SAN JUAN, PISCO PE-ANA-133586-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2019-12- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Limited 8,000.00 0.00 cotizaciones One Envelope pendiente 03 14 13 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN GRUPO 14 SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-133587-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2020-01- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Limited 12,000.00 0.00 cotizaciones One Envelope pendiente 03 14 12 ESTRUCTURAS DE the National Level MEDICIÓN GRUPO 18 SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR YURA PE-ANA-133588-NC-RFQ / ALQUILER DE VEHÍCULO PARA ELABORACIÓN DE LOS EXPEDIENTES TÉCNICOS DE Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-10- 2019-12- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Limited 8,000.00 0.00 cotizaciones One Envelope pendiente 03 14 13 MEDICIÓN GRUPO 20 the National Level SECTORES HIDRÁULICOS IRRIG. EMM, PTA DE BOMBOM, MOQUEGUA, TORATA, LOCUMBA, SAMA, UCHUSUMA, BAJO CAPLINA PE-ANA-136558-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 32,740.00 0.00 DE AGUA EN BLOQUES cotizaciones One Envelope pendiente 19 17 16 the National Level DE RIEGO EN EL SECTOR HIDRÁULICO MENOR CAÑETE PE-ANA-136561-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 35,680.00 0.00 DE AGUA EN BLOQUES cotizaciones One Envelope pendiente 19 17 03 the National Level DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO I PE-ANA-137039-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Limited 28,312.00 0.00 DE AGUA EN BLOQUES cotizaciones One Envelope pendiente 19 17 27 the National Level DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO II PE-ANA-137046-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: DE AGUA EN BLOQUES Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 23,452.00 0.00 DE RIEGO EN LOS cotizaciones One Envelope pendiente 19 17 16 the National Level SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN Page 5 PE-ANA-137047-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: DE AGUA EN BLOQUES Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Limited 43,598.00 0.00 DE RIEGO EN EL cotizaciones One Envelope pendiente 19 17 27 the National Level SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-137048-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: Solicitud de Single Stage - En 2019-10- 2019-11- 2020-02- DE AGUA EN BLOQUES IBRD / 87400 Consolidating IWRM at Posterior Limited 40,110.00 0.00 cotizaciones One Envelope ejecución 19 17 03 DE RIEGO EN EL the National Level SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-137049-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: DE AGUA EN BLOQUES Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 22,399.00 0.00 DE RIEGO EN EL cotizaciones One Envelope pendiente 19 17 03 the National Level SECTOR HIDRÁULICO MENOR IRRIGACIÓN ENSENADA-MEJIA- MOLLENDO Y PUNTA DE BOMBOM PE-ANA-137051-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: DE AGUA EN BLOQUES Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 44,793.00 0.00 DE RIEGO EN LOS cotizaciones One Envelope pendiente 19 17 03 the National Level SECTORES HIDRÁULICOS MENOR MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-137052-NC-RFQ / ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE AGUA EN Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 36,795.00 0.00 BLOQUES DE RIEGO EN cotizaciones One Envelope pendiente 19 17 03 the National Level EL SECTOR HIDRÁULICO MENOR MOTUPE-OLMOS-LA LECHE PE-ANA-139771-NC-RFQ / Component 1: SERVICIO PARA Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Open - National 26,268.66 0.00 EJECUTAR 11 cotizaciones One Envelope pendiente 26 24 02 the National Level PERFILAJES GEOFISICOS PE-ANA-139772-NC-RFQ / SERVICIO PARA LA Component 1: INSTALACIÓN Y Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Open - National 35,820.90 0.00 CONSTRUCCIÓN DE cotizaciones One Envelope pendiente 26 24 23 the National Level CASETAS PRE FABRICADAS TACNA PE-ANA-139773-NC-RFQ / SERVICIO PARA LA Component 1: INSTALACIÓN Y Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Open - National 33,433.00 0.00 CONSTRUCCIÓN DE cotizaciones One Envelope pendiente 26 24 23 the National Level CASETAS PRE FABRICADAS ICA PE-ANA-139774-NC-RFQ / SERVICIO DE ADAPTACIÓN, SEGURIDAD PARA LA INSTRUMENTACIÓN DE Component 1: Solicitud de Single Stage - Ejecución 2019-10- 2019-11- 2020-01- 27 POZOS Y IBRD / 87400 Consolidating IWRM at Posterior Open - National 29,553.00 0.00 cotizaciones One Envelope pendiente 26 24 23 PIEZOMETROS EN the National Level ESTADO UTILIZABLE Y 15 EN ESTADO UTILIZADO EN EL ACUIFERO DE ICA, VILLACURI Y LANCHAS PE-ANA-152835-NC-RFQ / SERVICIO DE Component 1: ALOJAMIENTO DE Solicitud de Single Stage - En 2020-01- 2020-01- 2020-02- 2020-07- IBRD / 87400 Consolidating IWRM at Posterior Limited 30,000.00 0.00 INFRAESTRUCTURA cotizaciones One Envelope ejecución 25 13 21 20 the National Level TECNOLÓGICA DE DATA CENTER PE-ANA-154274-NC-RFQ / SERVICIO DE ALOJAMIENTO Y ALIMENTACIÓN PARA Component 1: LOS PARTICIPANTES Solicitud de Single Stage - Ejecución 2020-01- 2020-01- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Limited 50,000.00 0.00 DEL TALLER DE cotizaciones One Envelope pendiente 18 26 02 the National Level CAPACITACIÓN PARA ESPECIALISTAS DE CALIDAD DE RECURSOS HIDRICOS PE-ANA-155598-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES Component 1: TÉCNICOS PARA LA Solicitud de Single Stage - En 2020-02- 2020-02- 2020-04- IBRD / 87400 Consolidating IWRM at Posterior Open - National 8,597.00 0.00 CONSTRUCCIÓN DE cotizaciones One Envelope ejecución 09 19 04 the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS VALLE DE MAJES Y VALLE SIGUAS QUILCA. PE-ANA-155595-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: EXPEDIENTES Solicitud de Single Stage - En 2020-02- 2020-02- 2020-04- IBRD / 87400 Consolidating IWRM at Posterior Open - National 6,179.00 0.00 TÉCNICOS PARA LA cotizaciones One Envelope ejecución 09 19 04 the National Level CONSTRUCCIÓN DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR ALTO PIURA. PE-ANA-155594-NC-RFQ / SERVICIO DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE Component 1: EXPEDIENTES Solicitud de Single Stage - En 2020-02- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at Posterior Open - National 9,134.00 0.00 TÉCNICOS PARA LA cotizaciones One Envelope ejecución 09 19 20 the National Level CONSTRUCCIÓN DE ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN EL SECTOR HIDRÁULICO MENOR CHIRA. PE-ANA-155596-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES Component 1: Solicitud de Single Stage - En 2020-02- 2020-02- 2020-03- TÉCNICOS PARA LA IBRD / 87400 Consolidating IWRM at Posterior Open - National 8,597.00 0.00 cotizaciones One Envelope ejecución 09 19 30 CONSTRUCCIÓN DE the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS MENOR ZAÑA Y JEQUETEPEQUE PE-ANA-155599-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES Component 1: TÉCNICOS PARA LA Solicitud de Single Stage - Ejecución 2020-02- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at Posterior Open - National 5,373.00 0.00 CONSTRUCCIÓN DE cotizaciones One Envelope pendiente 09 19 20 the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-155597-NC-RFQ / SERVICIOS DE ESTUDIOS BÁSICOS DE MECÁNICA DE SUELOS PARA ELABORACIÓN DE EXPEDIENTES TÉCNICOS PARA LA Component 1: Solicitud de Single Stage - En 2020-02- 2020-02- 2020-03- CONSTRUCCIÓN DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 9,134.00 0.00 cotizaciones One Envelope ejecución 09 19 25 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN LOS SECTORES HIDRÁULICOS PALPA, NASCA, ACARI, BELLA UNIÓN, CHAPARRA, Y YAUCA. PE-ANA-158210-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Solicitud de Single Stage - Ejecución 2020-02- 2020-02- 2020-06- funcionamiento y IBRD / 87400 Consolidating IWRM at Posterior Limited 38,500.00 0.00 cotizaciones One Envelope pendiente 20 29 13 Capacitación de la the National Level Instrumentación para la Seguridad de las presas Poechos, San Lorenzo, Tinajones y Gallito Ciego. PE-ANA-158215-NC-RFQ / Alquiler de camionetas 4x4 para las actividades de Supervisión del Suministro, Instalación, Puesta en Component 1: Solicitud de Single Stage - Ejecución 2020-02- 2020-03- 2020-06- funcionamiento y IBRD / 87400 Consolidating IWRM at Posterior Limited 23,500.00 0.00 cotizaciones One Envelope pendiente 21 01 19 Capacitación de la the National Level Instrumentación para la Seguridad de las presas del Sur Condoroma, El Frayle, Sutunta y Pasto Grande. Page 6 PE-ANA-159315-NC-RFQ / SERVICIO DE LIMPIEZA, Component 1: TALA Y DESBROCE, Y Solicitud de Single Stage - Ejecución 2020-02- 2020-02- 2020-03- IBRD / 87400 Consolidating IWRM at Posterior Limited 23,000.00 0.00 TRASLADO DE cotizaciones One Envelope pendiente 21 28 30 the National Level MATERIAL ELIMINADO EN LA PRESA POECHOS PE-ANA-161087-NC-RFQ / SERVICIO DE ALOJAMIENTO, ALIMENTACIÓN Y SALAS EQUIPADAS Component 1: Solicitud de Single Stage - En 2020-03- 2020-01- 2020-03- 2020-03- PARA EL TALLER IBRD / 87400 Consolidating IWRM at Posterior Limited 50,000.00 0.00 cotizaciones One Envelope ejecución 02 13 05 07 NACIONAL: the National Level FORTALECIMIENTO DE LAS JUNTAS USUARIAS Y SU ROL EN EL DESARROLLO PRODUCTIVO AGRARIO PE-ANA-161131-NC-RFQ / SERVICIOS DE Component 1: LIMPIEZA Y Solicitud de Single Stage - Ejecución 2020-03- 2020-04- 2020-07- IBRD / 87400 Consolidating IWRM at Posterior Limited 14,925.00 0.00 ADAPTACIÓN DE 15 cotizaciones One Envelope pendiente 18 04 03 the National Level POZOS UBICADO EN LOS ACUÍFEROS DE ICA, VILLACURI Y LANCHAS. PE-ANA-161129-NC-RFQ / SERVICIO DE ADAPTACIÓN DE Component 1: Solicitud de Single Stage - Ejecución 2020-03- 2020-03- 2020-04- 2020-05- 2020-07- 2020-12- ESTRUCTURAS IBRD / 87400 Consolidating IWRM at Posterior Open - National 94,030.00 0.00 ofertas One Envelope pendiente 11 16 27 27 01 28 HIDRÁULICAS EN 90 the National Level POZOS UBICADOS EN EL ACUÍFERO CAPLINA PE-ANA-164268-NC-DIR / SERVICIO DE ARRENDAMIENTO DE INMUEBLE 2 PARA EL Component 3: General Adquisición Ejecución 2020-03- 2020-03- 2020-04- 2022-12- IBRD / 87400 Posterior Direct 84,500.00 0.00 PROYECTO GESTIÓN Project Adminstration directa pendiente 23 30 01 31 INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS PE-ANA-164313-NC-RFQ / SERVICIO DE Component 1: Solicitud de Single Stage - Ejecución 2020-03- 2020-05- 2020-11- ELABORACIÓN DE IBRD / 87400 Consolidating IWRM at Posterior Open - National 10,448.00 0.00 cotizaciones One Envelope pendiente 31 26 22 CARTELES DE the National Level IDENTIFICACIÓN POZOS PE-ANA-164550-NC-RFQ / SERVICIO DE Component 1: AGENCIAMIENTO DE Solicitud de Single Stage - Ejecución 2020-04- 2020-05- 2021-01- IBRD / 87400 Consolidating IWRM at Posterior Open - National 29,851.00 0.00 PASAJES AÉREOS cotizaciones One Envelope pendiente 13 04 12 the National Level NACIONALES Y INTERNACIONALES PE-ANA-164552-NC-RFQ / SERVICIO DE Component 1: PUBLICIDAD DE AVISOS Solicitud de Single Stage - Ejecución 2020-04- 2020-05- 2021-01- IBRD / 87400 Consolidating IWRM at Posterior Open - National 17,910.00 0.00 RELACIONADOS A LAS cotizaciones One Envelope pendiente 13 04 12 the National Level CONVOCATORIAS DEL PROYECTO PE-ANA-164985-NC-DIR / SERVICIO DE ARRENDAMIENTO DE INMUEBLE PARA LA SEDE PRINCIPAL DEL Component 3: General Adquisición En 2020-03- 2020-03- 2020-03- 2020-04- 2022-12- IBRD / 87400 Posterior Direct 239,415.00 0.00 PGIRH DE LA UNIDAD Project Adminstration directa ejecución 18 27 25 05 31 EJECUTORA N°002 MODERNIZACION DE LA GESTION DE LOS RECURSOS HIDRICOS PE-ANA-165161-NC-RFQ / SERVICIO DE Component 3: General Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-05- IBRD / 87400 Posterior Open - National 30,000.00 0.00 CABLEADO DE VOZ Y Project Adminstration cotizaciones One Envelope pendiente 16 26 11 DATA PARA LOCAL DEL PGIRH PE-ANA-165867-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: Solicitud de Single Stage - Ejecución 2020-04- 2020-06- 2020-09- MEDICIÓN DE AGUA EN IBRD / 87400 Consolidating IWRM at Posterior Limited 42,728.00 0.00 cotizaciones One Envelope pendiente 25 20 18 LOS SECTORES the National Level HIDRÁULICOS MENORES COMPRENDIDOS DESDE CHICAMA HASTA SANTA PE-ANA-165868-NC-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE AGUA EN Solicitud de Single Stage - Ejecución 2020-04- 2020-06- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Limited 26,192.00 0.00 LOS SECTORES cotizaciones One Envelope pendiente 25 20 19 the National Level HIDRÁULICOS MENORES COMPRENDIDOS DESDE FORTALEZA HASTA LURÍN PE-ANA-165877-NC-RFQ / ALQUILER DE Component 1: CAMIONETA PARA Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-06- IBRD / 87400 Consolidating IWRM at Posterior Limited 9,242.00 0.00 VERIFICACIÓN DE cotizaciones One Envelope pendiente 21 30 29 the National Level COBERTURA DE TRANSMISIÓN PE-ANA-165652-GO-RFB / CULMINACIÓN DE LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE AGUA EN Solicitud de Single Stage - Ejecución 2020-06- 2020-06- 2020-08- 2020-08- 2020-09- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Open - National 130,401.14 0.00 LOS SECTORES ofertas One Envelope pendiente 15 20 01 21 25 24 the National Level HIDRÁULICOS MENORES COMPRENDIDOS DESDE TUMBES HASTA JEQUETEPEQUE PE-ANA-187094-NC-RFQ / SERVICIO DE TELEFONIA MOVIL PARA EL PERSONAL Component 3: General Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2021-10- IBRD / 87400 Posterior Limited 20,000.00 0.00 DEL PROYECTO DE Project Adminstration cotizaciones One Envelope pendiente 17 01 01 GESTION INTEGRADA DE RECURSOS HIDRICOS EN DIEZ CUENCAS PE-ANA-187470-NC-RFQ / ELABORACION E Component 1: Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2021-03- IMPLEMENTACION DE IBRD / 87400 Consolidating IWRM at Posterior Limited 50,000.00 0.00 cotizaciones One Envelope pendiente 17 08 07 PLANES DE MONITOREO the National Level ARQUEOLÓGICO - PMA. PE-ANA-164575-NC-RFB / SERVICIO DE ANÁLISIS Component 1: Solicitud de Single Stage - Ejecución 2020-04- 2020-04- 2020-05- 2020-06- 2020-07- 2020-12- DE LABORATORIO PARA IBRD / 87400 Consolidating IWRM at Posterior Open - National 477,650.00 0.00 ofertas One Envelope pendiente 06 11 23 22 27 24 MUESTRAS DE AGUA the National Level NATURAL PE-ANA-165874-NC-RFB / ELABORAR E Component 1: Solicitud de Single Stage - 2020-04- 2020-05- 2020-06- 2020-07- 2020-08- 2021-01- IMPLEMENTAR ONCE IBRD / 87400 Consolidating IWRM at Posterior Open - National 59,702.00 0.00 Cancelado ofertas One Envelope 30 05 16 16 20 17 (11) PLANES DE the National Level MONITOREO ARQUEOLÓGICO-PMA PE-ANA-191481-NC-RFQ / SERVICIO DE INTERNET PARA EL CENTRO DE Component 1: Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2021-01- PROCESAMIENTO DE IBRD / 87400 Consolidating IWRM at Posterior Limited 40,000.00 0.00 cotizaciones One Envelope pendiente 17 01 29 DATOS SECUNDARIO DE the National Level LA AUTORIDAD NACIONAL DEL AGUA PE-ANA-187303-NC-RFQ / SERVICIO DE INFRAESTRUCTURA Y Component 3: General Solicitud de Single Stage - Ejecución 2020-09- 2020-10- 2021-10- IBRD / 87400 Posterior Limited 32,500.00 0.00 PLATAFORMA EN LA Project Adminstration cotizaciones One Envelope pendiente 27 22 22 NUBE PARA EL PROYECTO PGIRH CONSULTING FIRMS Activity Reference No. Estimated Actual Short List and Opening of Combined Loan / Market Contract Type Process Expression of Request for Evaluation of Contract / Description Component Review Type Method Amount Amount Terms of Reference Draft Request for Technical Proposals Evaluation Report Signed Contract Credit No. Approach Status Interest Notice Proposals as Issued Technical Proposal Completion (US$) (US$) Proposals / Minutes and Draft Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Negotiated Contract Actual Planned Actual Planned Actual SBCC 002 ANA MGRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TECNICOS PARA Component 1: Selección 2018-06- 2018-06- 2018-06- 2018-06- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2018-07- 2018-07- 2018-10- CONSTRUCCION DE 200 IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 125,000.00 0.00 Cancelado 2018-06-01 13 08 18 23 10 08 12 11 26 13 31 14 ESTRUCTURAS DE the National Level calidad y costo CONTROL Y MEDICION DE AGUA EN BLOQUES DE RIEGO EN DIECIOCHO SECTORES HIDRAULICO DE LA ZONA CENTRO DE LA COSTA DEL PERU SBCC 003 2018 ANA PGIRH / CONSULTORÍA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA Component 1: Selección 2018-06- 2018-06- 2018-07- 2018-08- 2018-08- 2018-10- 2018-11- 2019-02- CONSTRUCCIÓN DE 274 IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 148,931.00 0.00 Cancelado 2018-06-15 25 20 23 07 16 29 16 14 ESTRUCTURAS DE the National Level calidad y costo MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN DOCE (12) SECTORES HIDRÁULICOS DE LA ZONA NORTE DE LA COSTA DEL PERÚ SBCC 001 ANA PGIRH / FORMULACIÓN DE LOS Component 2: Improving Selección Open - 2018-08- 2018-06- 2018-07- 2018-10- 2018-10- 2018-10- 2018-11- 2020-11- PLANES DE GESTIÓN IBRD / 87400 WRM in Selected Pilot Previa basada en 5,955,217.00 0.00 Cancelado 2018-06-01 International 08 06 11 08 19 26 27 26 DE RECURSOS HDRICOS River Basins calidad y costo EN CUATRO CUENCAS Page 7 SBCC 004 2018 ANA PGIRH / CONSULTORIA PARA LA ELABORACIÓN DE UN PAQUETE DE EXPEDIENTES TÉCNICOS PARA Component 1: Selección 2018-07- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2019-01- CONSTRUCCIÓN DE 337 IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 155,680.00 0.00 Cancelado 2018-07-05 17 11 08 15 12 19 27 05 03 ESTRUCTURAS DE the National Level calidad y costo MEDICIÓN DE AGUA EN BLOQUES DE RIEGO EN TREINTA (30) SECTORES HIDRÁULICOS DE LA ZONA SUR DE LA COSTA DEL PERÚ SBC 001 2018 ANA PGIRH BM / ESTUDIO Selección DE LÍNEA BASE DEL Component 3: General 2018-08- 2018-07- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-12- IBRD / 87400 Posterior basada en Open - National 88,459.00 0.00 En ejecución 2018-07-23 PIP 302961 GESTIÓN Project Adminstration 08 25 12 22 11 24 14 05 17 18 28 27 calidad INTEGRADA DE LOS RECURSOS HÍDRICOS EN DIEZ CUENCAS SBCC 005 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN Component 2: Improving Selección DE RECURSOS HÍ Open - 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2019-07- 2020-11- IBRD / 87400 WRM in Selected Pilot Previa basada en 1,809,400.00 2,537,766.50 Firmado 2018-08-22 DRICOS EN DOS International 03 06 11 16 06 16 08 21 09 24 24 13 26 02 River Basins calidad y costo CUENCAS PILOTO DE LA VERTIENTE DEL ATLÁNTICO: MAYO Y MANTARO SBCC 006 2018 ANA PGIRH BM / FORMULACIÓN DE LOS PLANES DE GESTIÓN Component 2: Improving Selección DE RECURSOS Open - 2018-10- 2018-09- 2018-10- 2018-09- 2019-03- 2018-10- 2019-04- 2018-10- 2019-05- 2018-10- 2019-07- 2018-11- 2020-05- IBRD / 87400 WRM in Selected Pilot Previa basada en 2,151,920.00 0.00 En ejecución 2018-08-22 HIDRICOS EN DOS International 03 06 11 16 06 16 08 21 09 24 24 13 06 River Basins calidad y costo CUENCAS PILOTO DE LA VERTIENTE DEL ATLÁNTICO: PAMPAS- APURIMAC Y URUBAMBA-VILCANOTA SBCC 007 2018 ANA PGIRH BM / SUPERVISIÓN DE LA Component 1: Selección PERFORACIÓN E 2018-09- 2018-10- 2018-09- 2018-10- 2018-10- 2018-10- 2018-11- 2019-03- IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 236,142.00 0.00 Cancelado 2018-09-07 INSTALACIÓN DE 58 08 12 25 23 26 30 15 14 the National Level calidad y costo PIEZOMETROS EN LOS ACUIFEROS DE ICA Y TACNA: LOTE 01 ICA Y LOTE 02 TACNA SCC 001 2018 ANA PGIRH BM / SERVICIO Selección Component 1: DE ASESORÍA EN LA basada en 2019-01- 2019-02- 2019-03- 2019-05- IBRD / 87400 Consolidating IWRM at Posterior Limited 190,000.00 0.00 Cancelado 2019-01-04 EJECUCIÓN DE LAS calificaciones de 18 17 24 08 the National Level PERFORACIONES EN LA consultores REGIÓN DE ICA Y TACNA SBCC 001 2019 ANA PGIRH BM / SUPERVISION PARA EL SUMINISTRO, Component 1: Selección 2019-04- 2019-02- 2019-04- 2019-03- 2019-07- 2019-04- 2019-08- 2019-05- 2019-08- 2019-05- 2019-08- 2019-06- 2020-01- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 326,071.00 0.00 En ejecución 2019-02-11 05 16 05 31 03 28 02 08 09 18 19 13 09 EN FUNCIONAMIENTO Y the National Level calidad y costo CAPACITACIÓN DE LA INSTRUMENTACIÓN PARA LA SEGURIDAD DE OCHO PRESAS SBCC 002 2019 ANA PGIRH BM / SUPERVISIÓN PARA EL SUMINISTRO, Component 1: Selección Ejecución 2019-02- 2019-04- 2019-05- 2019-05- 2019-06- 2019-07- 2021-01- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Previa basada en Open - National 629,981.44 0.00 2019-02-22 pendiente 27 08 08 13 05 06 03 EN FUNCIONAMIENTO Y the National Level calidad y costo CAPACITACIÓN DE 153 ESTACIONES HIDROLÓGICAS CON 33 EHCA SCC 001 2019 ANA PGIRH BM / SERVICIO Selección Component 2: Improving DE CONSULTORIA PARA basada en Ejecución 2019-04- 2019-06- 2019-07- 2019-08- 2020-08- IBRD / 87400 WRM in Selected Pilot Posterior Open - National 164,180.00 0.00 2019-04-05 LA IMPLEMENTACIÓN calificaciones de pendiente 26 09 09 13 12 River Basins DEL PLAN DE consultores DESARROLLO DE CAPACIDADES SBCC 003 2019 ANA PGIRH BM / SERVICIO Component 1: Selección DE CONSULTORIA PARA 2019-04- 2019-04- 2019-05- 2019-05- 2019-06- 2019-06- 2019-07- 2019-11- IBRD / 87400 Consolidating IWRM at Posterior basada en Open - National 126,453.73 0.00 En ejecución 2019-04-01 LA IMPLEMENTACION 17 15 06 27 11 25 17 14 the National Level calidad y costo DE LA FASE 0 - GOBIERNO DE DATOS PE-ANA-121030-CS-QCBS / SERVICIO DE CONSULTORÍA PARA LA PROMOCIÓN E IMPLEMENTACIÓN DE MECANISMOS DE Component 2: Improving Selección 2019-09- 2019-09- 2019-10- 2019-11- 2019-11- 2019-12- 2019-12- 2022-03- FINANCIAMIENTO DE IBRD / 87400 WRM in Selected Pilot Posterior basada en Open - National 1,399,406.25 0.00 En ejecución 2019-09-19 20 24 21 20 29 13 23 12 PROGRAMAS Y River Basins calidad y costo PROYECTOS DE LOS PLANES DE GESTIÓN INTEGRADA DE RECURSOS HÍDRICOS DE CUENCA PE-ANA-161088-CS-QCBS / SUPERVISION DEL SUMINISTRO, INSTALACIÓN PUESTA Component 1: Selección EN FUNCIONAMIENTO Y Open - Ejecución 2020-05- 2020-06- 2020-07- 2020-08- 2020-09- 2020-10- 2021-10- IBRD / 87400 Consolidating IWRM at Posterior basada en 500,000.00 0.00 2020-04-12 CAPACITACIÓN DE International pendiente 03 16 14 13 17 22 22 the National Level calidad y costo SISTEMAS MECANIZADOS DE AFOROS, PASARELAS DE AFOROS Y WINCHAS DE AFOROS PE-ANA-165654-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 131 basada en Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- IBRD / 87400 Consolidating IWRM at Posterior Open - National 80,600.00 0.00 2020-11-02 ESTRUCTURAS DE calificaciones de pendiente 23 06 05 12 09 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN PIURA PE-ANA-165655-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 95 basada en Ejecución 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Consolidating IWRM at Posterior Open - National 58,449.43 0.00 2020-06-01 ESTRUCTURAS DE calificaciones de pendiente 22 05 04 09 08 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN LAMBAYEQUE PE-ANA-165656-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 80 basada en Ejecución 2020-06- 2020-08- 2020-09- 2020-10- 2021-03- IBRD / 87400 Consolidating IWRM at Posterior Open - National 49,220.57 0.00 2020-06-01 ESTRUCTURAS DE calificaciones de pendiente 22 05 04 09 08 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN LA LIBERTAD PE-ANA-165657-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 73 basada en Ejecución 2020-05- 2020-07- 2020-08- 2020-09- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 44,913.77 0.00 2020-05-01 ESTRUCTURAS DE calificaciones de pendiente 22 05 04 08 05 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN ANCASH PE-ANA-165658-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 73 basada en Ejecución 2020-05- 2020-07- 2020-08- 2020-09- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 44,913.77 0.00 2020-05-01 ESTRUCTURAS DE calificaciones de pendiente 22 05 04 08 05 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN ANCASH PE-ANA-165659-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 87 basada en Ejecución 2020-05- 2020-07- 2020-08- 2020-09- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Open - National 53,527.37 0.00 2020-05-01 ESTRUCTURAS DE calificaciones de pendiente 22 05 04 08 05 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN LIMA PE-ANA-165660-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 107 basada en Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-08- IBRD / 87400 Consolidating IWRM at Posterior Open - National 65,832.51 0.00 2020-11-02 ESTRUCTURAS DE calificaciones de pendiente 23 06 05 12 09 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN ICA PE-ANA-165661-CS-CQS / SUPERVISIÓN DE LA Selección Component 1: CONSTRUCCIÓN DE 190 basada en Ejecución 2020-11- 2021-01- 2021-02- 2021-03- 2021-09- IBRD / 87400 Consolidating IWRM at Posterior Open - National 116,898.86 0.00 2020-11-02 ESTRUCTURAS DE calificaciones de pendiente 23 06 05 12 08 the National Level MEDICIÓN DE AGUA EN consultores LA REGIÓN AREQUIPA INDIVIDUAL CONSULTANTS Activity Reference No. Estimated Actual Invitation to Loan / Market Contract Type Process Draft Negotiated Contract / Description Component Review Type Method Amount Amount Terms of Reference Identified/Selected Signed Contract Credit No. Approach Status Contract Completion (US$) (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCI-001 / III Administración General del Component 3: General 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- 2018-04- 2018-10- IBRD / 87400 Previa Individual Open 360,000.00 324,000.00 Firmado 2017-12-28 Proyecto Project Adminstration 31 12 12 15 24 18 06 15 III.a Director Ejecutivo SCI 003 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2022-11- IBRD / 87400 Previa Individual Limited 202,500.00 0.00 Cancelado 2018-05-22 Especialista en Project Adminstration 30 23 29 31 06 Adquisiciones SCI 004 ANA PGIRH / ESPECIALISTA EN ADMINISTRACIÓN DE Component 3: General 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 Previa Individual Limited 192,000.00 0.00 Cancelado 2018-05-25 RECURSOS HÍDRICOS - Project Adminstration 01 08 12 22 COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 005 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-05- ESPECIALISTA EN AGUA IBRD / 87400 Posterior Individual Limited 192,000.00 0.00 En ejecución 2018-05-28 Project Adminstration 04 11 13 23 SUBTERRÁNEAS SCI 009 ANA PGIRH / Component 3: General 2018-08- 2018-06- 2018-06- 2018-06- 2021-05- IBRD / 87400 Posterior Individual Limited 72,000.00 0.00 En ejecución 2018-05-28 GEOGRAFO - SIG Project Adminstration 09 04 11 13 28 Page 8 SCI 010 ANA PGIRH / Component 3: General 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- ASISTENTE TECNICO IBRD / 87400 Posterior Individual Limited 71,460.00 5,955.00 Firmado 2018-05-25 Project Adminstration 01 26 08 01 12 01 27 TALLERES SCI 011 ANA PGIRH / Component 2: Improving COORDINADOR TECNICO 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 184,140.00 19,664.33 Firmado 2018-05-28 CUENCA PILOTO 15 04 18 11 06 13 06 23 River Basins URUBAMBA SCI 012 ANA PGIRH / Component 2: Improving 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2022-05- 2018-10- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 184,140.00 19,664.33 Finalizado 2018-05-28 15 04 18 11 06 13 06 23 04 CUENCA PILOTO MAYO River Basins SCI 013 ANA PGIRH / Component 2: Improving 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2022-11- COORDINADOR TECNICO IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 184,140.00 0.00 En ejecución 2018-05-28 04 18 11 30 13 19 CUENCA PILOTO River Basins PAMPAS SCI 014 ANA PGIRH / Component 2: Improving COORDINADOR TECNICO 2018-06- 2018-06- 2018-06- 2022-05- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 184,140.00 0.00 En ejecución 2018-05-28 CUENCA PILOTO 04 11 13 23 River Basins MANTARO SCI 017 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE Ejecución 2018-06- 2018-06- 2018-06- 2022-06- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 2018-06-04 RECURSOS HIDRICOS pendiente 11 19 22 01 River Basins CUENCA PILOTO MAYO SCI 016 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO DE 2018-02- 2018-06- 2018-06- 2018-06- 2022-06- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 En ejecución 2018-06-04 RECURSOS HIDRICOS 16 11 19 22 01 River Basins CUENCA PILOTO PAMPAS SCI 018 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving Ejecución 2018-06- 2018-06- 2018-06- 2022-06- RECURSOS HIDRICOS IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 2018-06-04 pendiente 11 19 22 01 CUENCA PILOTO River Basins MANTARO SCI 024 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL Ejecución 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-06-04 AMBIENTAL CUENCA pendiente 11 19 22 28 River Basins PILOTO MAYO SCI 025 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL Ejecución 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-06-04 AMBIENTAL CUENCA pendiente 11 19 22 28 River Basins PILOTO PAMPAS SCI 026 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL Ejecución 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-06-04 AMBIENTAL CUENCA pendiente 11 19 22 28 River Basins PILOTO MANTARO SCI 027 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-11- ASESOR EN GESTIÓN IBRD / 87400 Posterior Individual Limited 286,200.00 0.00 Cancelado 2018-05-25 Project Adminstration 01 08 12 18 DE RECURSOS HÍDRICOS SCI 029 ANA PGIRH / Component 3: General 2018-07- 2018-06- 2018-06- 2018-06- 2022-11- SECRETARIA DE LA IBRD / 87400 Posterior Individual Limited 64,800.00 0.00 En ejecución 2018-05-29 Project Adminstration 29 06 13 15 21 JEFATURA SCI 031 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 Posterior Individual Limited 54,000.00 0.00 2018-05-29 CHOFER DE JEFATURA Project Adminstration pendiente 06 13 15 21 SCI 035 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2021-05- ASISTENTE SOPORTE IBRD / 87400 Posterior Individual Limited 36,000.00 0.00 2018-05-29 Project Adminstration pendiente 06 13 15 30 TECNICO SCI 036 ANA PGIRH / SECRETARIA DE Component 3: General 2018-09- 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 Posterior Individual Limited 54,000.00 0.00 En ejecución 2018-05-29 ADMINISTRACION Y Project Adminstration 20 06 13 15 21 FINANZAS SCI 037 ANA PGIRH / CHOFER DE Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2022-11- IBRD / 87400 Posterior Individual Limited 48,600.00 0.00 2018-05-29 ADMINISTRACIÓN Y Project Adminstration pendiente 06 13 15 21 FINANZAS SCI 038 ANA PGIRH / Component 3: General 2018-05- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2021-05- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 103,500.00 8,625.00 Firmado 2018-05-29 Project Adminstration 29 06 26 13 01 15 01 30 ADQUISICIONES 1 SCI 040 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2022-11- CHOFER DE IBRD / 87400 Posterior Individual Limited 48,600.00 0.00 2018-05-29 Project Adminstration pendiente 06 13 15 21 ADQUISICIONES SCI 041 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 194,076.00 0.00 En ejecución 2018-05-28 Project Adminstration 04 11 13 19 CONTABILIDAD SCI 042 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2021-05- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 67,500.00 0.00 2018-05-28 Project Adminstration pendiente 04 11 13 28 CONTABILIDAD SCI 043 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA IBRD / 87400 Posterior Individual Limited 155,250.00 0.00 2018-05-28 Project Adminstration pendiente 04 11 13 19 FINANCIERO SCI 044 ANA PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 194,076.00 0.00 En ejecución 2018-05-28 Project Adminstration 04 11 13 19 TESORERIA SCI 045 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2021-05- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 67,500.00 0.00 2018-05-29 Project Adminstration pendiente 06 13 15 30 TESORERIA SCI 033 ANA PGIRH / Component 3: General Ejecución 2018-06- 2018-06- 2018-06- 2022-11- ESPECIALISTA EN IBRD / 87400 Posterior Individual Limited 155,250.00 0.00 2018-06-04 Project Adminstration pendiente 11 18 22 28 PRESUPUESTO SCI 002 ANA PGIRH / Component 3: General 2018-05- 2018-05- 2018-05- 2018-05- 2018-11- Especialista en IBRD / 87400 Previa Individual Limited 243,000.00 0.00 Cancelado 2018-05-22 Project Adminstration 29 23 29 31 09 Administración y Finanzas SCI 053 ANA PGIRH / ESPECIALISTA EN Component 3: General 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 Previa Individual Open 243,000.00 13,500.00 Firmado 2018-06-14 ADMINISTRACIÓN Y Project Adminstration 21 02 22 02 09 03 10 30 FINANZAS SCI 054 2018 ANA Component 3: General 2018-06- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- PGIRH / ESPECIALISTA IBRD / 87400 Previa Individual Open 202,500.00 9,125.00 Firmado 2018-06-14 Project Adminstration 21 02 03 02 22 03 22 30 EN ADQUISICIONES SCI 007-ANA-PGIRH / Component 3: General 2018-06- 2018-06- 2018-06- 2022-05- ESPECIALISTA IBRD / 87400 Posterior Individual Direct 192,000.00 0.00 Cancelado 2018-05-25 Project Adminstration 04 06 08 18 AMBIENTAL SCI 028 2018 ANA Component 3: General Ejecución 2018-07- 2018-07- 2018-07- 2022-12- PGIRH BM / IBRD / 87400 Posterior Individual Limited 192,000.00 0.00 2018-07-19 Project Adminstration pendiente 20 30 31 30 ESPECIALISTA AMBIENTAL SCI 030 2018 ANA PGIRH BM / ESPECIALISTA EN Component 3: General 2018-07- 2018-09- 2018-07- 2018-10- 2018-07- 2018-10- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 12,000.00 Firmado 2018-07-19 ADMINISTRACIÓN DE Project Adminstration 20 25 30 01 31 01 30 RECURSOS HÍDRICOS - COORDINADOR DE LA SUPERVISIÓN TÉCNICA SCI 006 2018 ANA PGIRH BM / ASESOR EN Component 3: General 2018-08- 2018-07- 2018-08- 2018-07- 2018-10- 2018-07- 2022-12- IBRD / 87400 Previa Individual Limited 286,200.00 0.00 En ejecución 2018-07-19 GESTIÓN DE RECURSOS Project Adminstration 02 20 07 30 03 31 30 HÍDRICOS SCI 008 2018 ANA PGIRH BM / Component 3: General Ejecución 2018-07- 2018-07- 2018-07- 2022-12- IBRD / 87400 Posterior Individual Limited 192,000.00 0.00 2018-07-19 ESPECIALISTA EN Project Adminstration pendiente 20 30 31 30 GESTIÓN DE RECURSOS HÍDRICOS SCI 060 2018 ANA PGIRH / ESPECIALISTA Component 2: Improving Ejecución 2018-07- 2018-07- 2018-07- 2022-12- EN SISTEMAS DE IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-07-19 pendiente 20 30 31 30 INFORMACIÓN CUENCA River Basins PILOTO MANTARO SCI 061 2018 ANA PGIRH BM / Component 2: Improving Ejecución 2018-07- 2018-07- 2018-07- 2022-12- ESPECIALISTA EN IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-07-19 pendiente 20 30 31 30 SISTEMAS DE River Basins INFORMACIÓN CUENCA PILOTO PAMPAS SCI 062 2018 ANA PGIRH BM / Component 2: Improving Ejecución 2018-07- 2018-07- 2018-07- 2022-12- ESPECIALISTA EN IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 151,200.00 0.00 2018-07-19 pendiente 20 30 31 30 SISTEMAS DE River Basins INFORMACIÓN CUENCA PILOTO MAYO SCI 063 2018 ANA PGIRH BM / ASISTENTE Component 2: Improving TÉCNICO EN SISTEMAS 2020-02- 2018-07- 2020-02- 2018-07- 2020-02- 2018-07- 2022-12- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 En ejecución 2018-07-19 DE INFORMACIÓN 18 20 25 30 27 31 30 River Basins CUENCA PILOTO URUBAMBA SCI 064 2018 ANA PGIRH BM / ASISTENTE Component 2: Improving TÉCNICO EN SISTEMAS Ejecución 2018-07- 2018-07- 2018-07- 2022-12- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 2018-07-19 DE INFORMACIÓN pendiente 20 30 31 30 River Basins CUENCA PILOTO MANTARO SCI 065 2018 ANA PGIRH BM / ASISTENTE Component 2: Improving Ejecución 2018-07- 2018-07- 2018-07- 2022-12- TÉCNICO EN SISTEMAS IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 2018-07-19 pendiente 20 30 31 30 DE INFORMACIÓN River Basins CUENCA PILOTO MAYO Page 9 SCI 034 2018 ANA PGIRH BM / ASISTENTE Component 2: Improving Ejecución 2018-07- 2018-07- 2018-07- 2022-12- TÉCNICO EN SISTEMAS IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 96,000.00 0.00 2018-07-19 pendiente 20 30 31 30 DE INFORMACIÓN River Basins CUENCA PILOTO PAMPAS SBCC 066 2018 ANA Component 1: PGIRH 2018 / 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-09- 2022-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 192,000.00 12,000.00 Bajo Revision 2018-08-28 ESPECIALISTA EN 28 30 07 01 28 05 28 30 the National Level HIDROMETRIA SCI 015 ANA PGIRH / ASISTENTE TECNICO DE Component 2: Improving 2020-02- 2019-02- 2020-02- 2019-02- 2019-02- 2020-02- RECURSOS HIDRICOS IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 16,119.48 0.00 En ejecución 2019-02-08 20 15 24 20 28 28 CUENCA PILOTO River Basins URUBAMBA SCI 039 ANA PGIRH / Component 3: General Ejecución 2019-02- 2019-02- 2019-02- 2020-02- ASISTENTE DE IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-02-08 Project Adminstration pendiente 15 20 28 28 ADQUISICIONES 2 SCI 056 2018 ANA Component 2: Improving PGIRH BM / Ejecución 2019-02- 2019-02- 2019-02- 2020-02- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 40,920.00 0.00 2019-02-08 COORDINADOR TECNICO pendiente 15 20 28 28 River Basins CUENCA URUBAMBA SCI 057 2018 ANA Component 2: Improving Ejecución 2019-02- 2019-02- 2019-02- 2020-02- PGIRH BM / IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 40,920.00 0.00 2019-02-08 pendiente 15 20 28 28 COORDINADOR TÉCNICO River Basins CUENCA MAYO SCI 023 ANA PGIRH / Component 2: Improving ESPECIALISTA SOCIAL 2020-02- 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 33,600.00 0.00 En ejecución 2019-04-05 AMBIENTAL CUENCA 18 15 20 30 29 River Basins PILOTO URUBAMBA SCI 032 ANA PGIRH / ESPECIALISTA EN Component 3: General Ejecución 2019-04- 2019-04- 2019-04- 2020-04- PLANIFICACION, IBRD / 87400 Posterior Individual Limited 48,000.00 0.00 2019-04-05 Project Adminstration pendiente 15 20 30 29 PRESUPUESTO Y EVALUACIÓN SCI 046 ANA PGIRH / ESPECIALISTA EN Component 3: General Ejecución 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-04-05 CONTROL PATRIMONIAL Project Adminstration pendiente 15 20 30 29 Y ALMACEN SCI 055 2018 ANA PGIRH BM / Component 3: General 2019-09- 2019-05- 2019-05- 2019-05- 2020-05- IBRD / 87400 Previa Individual Open 54,000.00 0.00 Bajo Revision 2019-04-05 ESPECIALISTA EN Project Adminstration 20 15 20 31 24 ADMINISTRACIÓN Y FINANZAS SCI 068 2018 ANA Component 3: General Ejecución 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 30,000.00 0.00 2019-04-05 PGIRH BM / ASESOR Project Adminstration pendiente 15 20 30 29 LEGAL SCI 071 2018 ANA Component 3: General 2019-09- 2019-05- 2019-05- 2019-06- 2020-06- IBRD / 87400 Previa Individual Open 55,880.63 0.00 Bajo Revision 2019-04-05 PGIRH BM / JEFE DE Project Adminstration 20 20 25 09 08 PROYECTO SCI 059 2018 ANA PGIRH / ESPECIALISTA Component 2: Improving 2020-02- 2019-04- 2019-04- 2019-05- 2020-05- EN SISTEMAS DE IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 33,600.00 0.00 En ejecución 2019-04-05 17 20 25 05 04 INFORMACIÓN CUENCA River Basins PILOTO URUBAMBA SCI 058 2018 ANA PGIRH BM / Component 1: 2019-04- 2019-04- 2019-04- 2019-05- CONSULTOR EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 6,000.00 0.00 Cancelado 2019-04-05 15 20 30 30 SEGURIDAD DE PRESAS the National Level -SALVAGUARDAS BANCO MUNDIAL PE-ANA-116127-CS-INDV / ESTUDIO DE INGENIERÍA DE DETALLE DE Component 1: Ejecución 2019-07- 2019-08- 2019-09- 2019-12- TELECOMUNICACIONES IBRD / 87400 Consolidating IWRM at Posterior Individual Open 13,433.00 0.00 2019-05-31 pendiente 19 09 13 12 PARA LA TRANSMISIÓN the National Level DE DATOS DE 396 PUNTOS DE MEDICIÓN DE NIVEL EN BLOQUES DE RIEGO PE-ANA-121010-CS-INDV / SUPERVISIÓN DE LA CONTRATACIÓN - OBRAS CIVILES PARA LA IMPLEMENTACIÓN DEL CENTRO DE Component 1: 2020-02- 2019-11- 2019-11- 2019-12- 2020-06- DATOS, LABORATORIO IBRD / 87400 Consolidating IWRM at Posterior Individual Open 23,880.00 0.00 En ejecución 2019-10-01 04 20 25 05 02 DE INSTRUMENTACIÓN, the National Level CENTRO DE MONITOREO Y MODELAMIENTO DE RECURSOS HÍDRICOS DE LA AUTORIDAD NACIONAL DEL AGUA PE-ANA-122155-CS-INDV Component 2: Improving / ASISTENTE DE 2020-02- 2019-10- 2020-02- 2019-10- 2020-02- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 En ejecución 2019-10-01 COMUNICACIONES 17 06 20 21 27 31 30 River Basins CUENCA URUBAMBA PE-ANA-122156-CS-INDV Component 2: Improving / ASISTENTE DE 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 En ejecución 2019-10-01 COMUNICACIONES 18 06 21 31 30 River Basins CUENCA MAYO PE-ANA-122157-CS-INDV Component 2: Improving / ESPECIALISTA SOCIAL 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 33,600.00 0.00 Bajo Revision 2019-10-01 AMBIENTAL CUENCA 18 06 21 31 30 River Basins MAYO PE-ANA-122158-CS-INDV Component 2: Improving / ESPECIALISTA 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 33,600.00 0.00 En ejecución 2019-10-01 SISTEMA DE 18 06 21 31 30 River Basins INFORMACIÓN CUENCA MAYO PE-ANA-122159-CS-INDV Component 2: Improving / ASISTENTE DE 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 En ejecución 2019-10-01 COMUNICACIÓN 18 06 21 31 30 River Basins CUENCA PAMPAS PE-ANA-122160-CS-INDV Component 2: Improving 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- / COORDINADOR IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 134,220.00 0.00 En ejecución 2019-10-01 18 06 21 31 30 TÉCNICO CUENCA River Basins MANTARO PE-ANA-122161-CS-INDV Component 2: Improving / ASISTENTE DE 2020-02- 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 En ejecución 2019-10-01 COMUNICACIÓN 18 06 21 31 30 River Basins CUENCA MANTARO PE-ANA-122162-CS-INDV / ASISTENTE DE Component 3: General Ejecución 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 Posterior Individual Limited 28,656.00 0.00 2019-10-01 MONITOREO Y Project Adminstration pendiente 06 21 31 30 EVALUACIÓN PE-ANA-122163-CS-INDV Component 3: General Ejecución 2019-10- 2019-10- 2019-10- 2020-10- / ASISTENTE DE IBRD / 87400 Posterior Individual Limited 23,280.00 0.00 2019-10-01 Project Adminstration pendiente 16 21 31 30 CONTABILIDAD SCI 047 ANA PGIRH / Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 TECNICO DE ARCHIVO Project Adminstration 15 20 30 29 SCI 048 ANA PGIRH / ASISTENTE EN Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 13,500.00 0.00 Cancelado 2019-04-05 SERVICIOS GENERALES Project Adminstration 15 20 30 29 Y ARCHIVO SCI 069 2018 ANA PGIRH BM / TECNICO Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 Posterior Individual Limited 8,400.00 0.00 Cancelado 2019-04-05 ADMINISTRATIVO DE Project Adminstration 15 20 30 29 JEFATURA SCI 049 ANA PGIRH / ASISTENTE Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- ADMINISTRATIVO IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO River Basins URUBAMBA SCI 050 ANA PGIRH / Component 2: Improving ASISTENTE 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 ADMINISTRATIVO 15 20 30 29 River Basins CUENCA PILOTO MAYO SCI 051 ANA PGIRH / Component 2: Improving ASISTENTE 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 ADMINISTRATIVO 15 20 30 29 River Basins CUENCA PILOTO PAMPAS SCI 052 ANA PGIRH / ASISTENTE Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- ADMINISTRATIVO IBRD / 87400 Posterior Individual Limited 16,119.48 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 CUENCA PILOTO MANTARO SCI 020 ANA PGIRH / Component 2: Improving ASISTENTE TECNICO 2019-04- 2019-04- 2019-04- 2020-04- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 CULTURA DEL AGUA 15 20 30 29 River Basins CUENCA PILOTO MAYO SCI 021 ANA PGIRH / ASISTENTE TÉCNICO Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- CULTURA DEL AGUA IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO River Basins PAMPAS SCI 019 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- CULTURA DEL AGUA IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO River Basins URUBAMBA SCI 022 ANA PGIRH / ASISTENTE TECNICO Component 2: Improving 2019-04- 2019-04- 2019-04- 2020-04- CULTURA DEL AGUA IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 24,000.00 0.00 Cancelado 2019-04-05 15 20 30 29 CUENCA PILOTO River Basins MANTARO Page 10 SCI 070 2018 ANA Component 3: General 2019-04- 2019-04- 2019-04- 2020-04- PGIRH BM / IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 Cancelado 2019-04-05 Project Adminstration 15 20 30 29 ESPECIALISTA EN INFORMATICA PE-ANA-122164-CS-INDV / ESPECIALISTA EN Component 3: General Ejecución 2019-10- 2019-10- 2019-10- 2020-10- IBRD / 87400 Posterior Individual Limited 34,500.00 0.00 2019-10-01 SISTEMAS DE Project Adminstration pendiente 16 21 31 30 INFORMACIÓN SCI 067 2018 ANA PGIRH BM / Supervision de la Contratación - Obras Civiles para la Implementación de la Component 1: Infraestructura del Centro 2019-04- 2019-04- 2019-04- 2019-10- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 19,387.61 0.00 Cancelado 2019-04-05 de Datos, Laboratorio de 15 20 30 27 the National Level Instrumentación, Centro de Monitoreo Y Modelamiento de Recursos Hídricos de la Autoridad Nacional del Agua PE-ANA-130323-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE EXPEDIENTES Component 1: 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,330.00 0.00 En ejecución 2019-09-18 23 23 26 30 28 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130324-CS-INDV / SUPERVISOR 02 DE LA ELABORACIÓN DE EXPEDIENTES Component 1: 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,330.00 0.00 En ejecución 2019-09-18 23 23 26 30 28 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130325-CS-INDV / SUPERVISOR 03 DE LA ELABORACIÓN DE EXPEDIENTES Component 1: 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,330.00 0.00 En ejecución 2019-09-18 23 23 26 30 28 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130326-CS-INDV / SUPERVISOR 04 DE LA ELABORACIÓN DE EXPEDIENTES Component 1: 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,330.00 0.00 En ejecución 2019-09-18 23 23 26 30 28 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERÚ PE-ANA-130328-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 01 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 38,059.71 0.00 Bajo Revision 2019-09-05 EXPEDIENTES 22 10 11 13 12 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS TUMBES, SAN LORENZO PE-ANA-130329-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 03 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2019-09- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 46,567.17 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 14 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTOR HIDRÁULICOS MyBP, SECHURA PE-ANA-130330-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 05 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 46,567.17 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 11 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OLMOS, MOTUPE, LA LECHE PE-ANA-130331-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 06 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 50,746.27 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 11 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CHANCAY- LAMBAYEQUE, CHICAMA PE-ANA-130334-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 10 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 34,925.38 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 12 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS CASMA HUARMEY PE-ANA-130335-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 11 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 38,059.71 0.00 En ejecución 2019-09-05 TÉCNICOS DE 22 10 11 13 12 the National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS FORTALEZA, PATIVILCA, SUPE, HUAURA, CH- HUARAL PE-ANA-130336-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 12 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2020-02- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 11,641.80 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 10 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS CHILLÓN, RIMAC, LURIN, CAÑETE PE-ANA-130337-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 13 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 46,567.17 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 11 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRAULICOS SAN JUAN, PISCO PE-ANA-130338-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 14 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-10- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 34,925.38 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 15 01 30 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS ICA, LA ACHIRANA PE-ANA-130339-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 16 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 38,059.71 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 12 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS OCOÑA, CAMANÁ PE-ANA-132925-CS-INDV / CONSULTORES INDIVIDUALES GRUPO 20 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 34,925.38 0.00 En ejecución 2019-09-09 TÉCNICOS DE 22 14 15 17 16 the National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS Irrig. EMM, Pta de Bombón, Moquegua, Torata, Locumba, Sama, Uchusuma, Bajo Caplina PE-ANA-132943-CS-INDV Component 1: / ESPECIALISTA EN 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 44,118.00 0.00 En ejecución 2019-09-18 SENSIBILIZACIÓN Y 23 23 26 30 28 the National Level CAPACITACIÓN 01 PE-ANA-132945-CS-INDV Component 1: / ESPECIALISTA EN 2019-09- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 44,118.00 0.00 En ejecución 2019-09-18 SENSIBILIZACIÓN Y 23 23 26 30 28 the National Level CAPACITACIÓN 02 PE-ANA-120995-CS-INDV Component 1: / ESPECIALISTA EN 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 SENSIBILIZACIÓN Y 20 25 05 04 the National Level CAPACITACIÓN 01 PE-ANA-120996-CS-INDV Component 1: / ESPECIALISTA EN 2019-11- 2019-11- 2019-12- 2020-03- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 44,118.00 0.00 Cancelado 2019-10-01 SENSIBILIZACION Y 20 25 05 04 the National Level CAPACITACIÓN 02 Page 11 PE-ANA-130340-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 18 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES 2019-07- 2019-09- 2019-09- 2019-09- 2020-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 46,567.17 0.00 En ejecución 2019-09-05 TÉCNICOS DE 22 10 11 13 11 the National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS IRRIG. MAJES, STA RITA DE SIGUAS, LA JOYA, VITOR, YURA PE-ANA-130332-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 08 PARA LA ELABORACIÓN DE LOS Component 1: 2019-07- 2019-09- 2019-09- 2019-09- 2020-01- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Individual Open 46,567.17 0.00 En ejecución 2019-09-05 22 10 11 13 11 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS MOCHE, VIRU, CHAO, GUADALUPITO PE-ANA-130333-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 09 PARA LA Component 1: ELABORACIÓN DE LOS 2019-07- 2019-09- 2019-09- 2019-09- 2019-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Open 38,059.71 0.00 En ejecución 2019-09-05 EXPEDIENTES 22 10 11 13 12 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN SECTORES HIDRÁULICOS SANTA, NEPEÑA, IRCHIM PE-ANA-135207-CS-INDV Component 3: General 2019-10- 2019-10- 2019-10- 2020-10- / ESPECIALISTA EN IBRD / 87400 Previa Individual Open 45,000.00 0.00 Bajo Revision 2019-09-20 Project Adminstration 06 11 14 13 ADQUISICIONES PE-ANA-139763-CS-INDV / Contratación de Component 1: Consultor Internacional 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-11- 2019-10- 2019-11- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 11,842.00 11,842.00 Firmado 2019-10-21 para apoyo técnico al 21 28 23 02 23 09 29 27 the National Level Taller Análisis de Modos de fallo potenciales de la presa Poechos PE-ANA-152038-CS-INDV / CONSULTORES INDIVIDUALES - GRUPO 17 PARA LA ELABORACIÓN DE LOS Component 1: EXPEDIENTES 2020-01- 2020-01- 2020-01- 2020-01- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 50,000.00 0.00 Bajo Revision 2020-01-02 TÉCNICOS DE 10 12 17 27 26 the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS MENOR VALLE DE MAJES Y VALLE SIGUAS QUILCA PE-ANA-157004-CS-INDV / Contratación de un Especialista Internacional Component 1: para el diagnóstico de 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 66,823.00 66,382.18 En ejecución 2020-01-31 situación y análisis de la 03 02 03 02 04 02 17 the National Level seguridad de la presa Poechos recrecida, durante el llenado del embalse PE-ANA-155010-CS-INDV / SUPERVISOR 01 DE LA ELABORACIÓN DE EXPEDIENTES Component 1: 2020-02- 2020-02- 2020-02- 2020-02- 2020-04- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 7,165.00 0.00 Bajo Revision 2020-02-06 04 08 09 13 13 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS DE LA COSTA DEL PERU PE-ANA-155004-CS-INDV / GRUPO 19 PARA LA ELABORACIÓN DE LOS EXPEDIENTES Component 1: TÉCNICOS DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 34,925.00 0.00 Bajo Revision 2020-02-06 ESTRUCTURAS DE 04 08 09 13 13 the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO. PE-ANA-154991-CS-INDV / GRUPO 07 PARA LA ELABORACIÓN DE LOS EXPEDIENTES Component 1: 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- TÉCNICOS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 33,134.00 0.00 Bajo Revision 2020-02-06 04 08 09 14 15 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-155862-CS-INDV / GRUPO 02 - PARA Component 1: ELABORACIÓN DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 38,059.00 0.00 Bajo Revision 2020-02-06 EXPEDIENTES 04 08 09 13 13 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN DE AGUA. PE-ANA-155863-CS-INDV / GRUPO 15 PARA Component 1: ELABORACIÓN DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-06- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 46,566.00 0.00 Bajo Revision 2020-02-06 EXPEDIENTES 04 08 09 13 12 the National Level TÉCNICOS DE ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-154996-CS-INDV / GRUPO 04 PARA LA ELABORACIÓN DE LOS EXPEDIENTES Component 1: TÉCNICOS DE 2020-02- 2020-02- 2020-02- 2020-02- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 38,060.00 0.00 Bajo Revision 2020-02-06 ESTRUCTURAS DE 04 08 09 13 13 the National Level MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS CHILI NO REGULADO Y CHILI REGULADO PE-ANA-160683-CS-INDV / CONSULTORES ADICIONALES AL GRUPO 07 PARA LA ELABORACIÓN DE LOS Component 1: 2020-03- 2020-03- 2020-03- 2020-03- 2020-06- EXPEDIENTES IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 18,400.00 0.00 Bajo Revision 2020-03-16 03 18 19 24 08 TÉCNICOS DE the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA EN LOS SECTORES HIDRÁULICOS ZAÑA Y JEQUETEPEQUE PE-ANA-161048-CS-INDV Component 2: Improving / ESPECIALISTA SOCIAL 2020-02- 2020-03- 2020-03- 2020-03- 2023-01- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 93,170.00 0.00 Bajo Revision 2020-03-02 AMBIENTAL CUENCA 17 09 16 27 01 River Basins PAMPAS PE-ANA-161050-CS-INDV Component 2: Improving / ASISTENTE DE Ejecución 2020-03- 2020-03- 2020-03- 2022-12- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 93,170.00 0.00 2020-03-02 RECURSOS HIDRICOS pendiente 09 16 27 30 River Basins CUENCA PAMPAS PE-ANA-161052-CS-INDV Component 2: Improving Ejecución 2020-03- 2020-03- 2020-03- 2022-12- / COORDINADOR IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 113,469.00 0.00 2020-03-02 pendiente 09 16 24 30 TÉCNICO CUENCA River Basins URUBAMBA PE-ANA-163778-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: Ejecución 2020-03- 2020-03- 2020-03- 2020-05- DE AGUA EN BLOQUES IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,776.00 0.00 2020-03-16 pendiente 17 24 25 25 DE RIEGO EN LOS the National Level SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN. PE-ANA-163779-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: 2020-08- 2020-03- 2020-03- 2020-03- 2020-06- DE AGUA EN BLOQUES IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,970.00 0.00 En ejecución 2020-03-16 10 17 24 25 08 DE RIEGO EN EL the National Level SECTOR HIDRÁULICO MENOR IRRIGACION MAJES, VALLE DE MAJES, CAMANA PE-ANA-164551-CS-INDV / APOYO AL ANÁLISIS DE LA SEGURIDAD DE Component 1: Ejecución 2020-04- 2020-04- 2020-04- 2020-05- LA PRESA POECHOS IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 6,500.00 0.00 2020-04-01 pendiente 08 13 20 08 RECRECIDA, DURANTE the National Level EL LLENADO DEL EMBALSE PE-ANA-164570-CS-INDV / SERVICIO DE Component 1: Ejecución 2020-04- 2020-05- 2020-06- 2020-12- COORDINADOR DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 30,600.00 0.00 2020-04-19 pendiente 24 15 19 31 CALIDAD DE RECURSOS the National Level HIDRICOS PGIRH PE-ANA-164571-CS-INDV / SERVICIO DE Component 1: ESPECIALISTA DE 2020-04- 2020-04- 2020-04- 2020-05- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 19,600.00 0.00 Bajo Revision 2020-03-29 CALIDAD DE AGUA 30 03 18 03 31 the National Level SUPERFICIAL CUENCA URUBAMBA PE-ANA-164572-CS-INDV / SERVICIO DE Component 1: ESPECIALISTA DE 2020-03- 2020-04- 2020-04- 2020-05- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 19,600.00 0.00 Bajo Revision 2020-03-29 CALIDAD DE AGUA 30 03 18 03 31 the National Level SUPERFICIAL CUENCA PAMPAS Page 12 PE-ANA-164573-CS-INDV / SERVICIO DE Component 1: ESPECIALISTA DE 2020-04- 2020-04- 2020-04- 2020-05- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 19,600.00 0.00 Bajo Revision 2020-03-29 CALIDAD DE AGUA 30 03 18 03 31 the National Level SUPERFICIAL CUENCA MAYO PE-ANA-164574-CS-INDV / SERVICIO DE Component 1: ESPECIALISTA EN 2020-04- 2020-04- 2020-04- 2020-05- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 19,600.00 0.00 Bajo Revision 2020-03-29 GESTION DE CALIDAD 13 03 18 03 31 the National Level DE RECURSOS HIDRICOS CUENCA MANTARO PE-ANA-164991-CS-INDV / SERVICIO DE APOYO EN PROCESAMIENTO DE INFORMACION DE Component 1: Ejecución 2020-04- 2020-04- 2020-05- 2020-12- ACTIVIDADES DEL IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 16,000.00 0.00 2020-04-01 pendiente 06 21 06 31 COMPONENTE DE the National Level CALIDAD DE RECURSOS HIDRICOS EN LA CUENCA MANTARO PE-ANA-164992-CS-INDV / SERVICIO DE APOYO EN GESTIONES Y MONITOREO DE EJECUCION DE Component 1: 2020-04- 2020-04- 2020-04- 2020-04- 2020-12- ACTIVIDADES DEL IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 11,000.00 0.00 En ejecución 2020-04-01 06 06 11 21 31 COMPONENTE DE the National Level MONITOREO DE LA CALIDAD DE LOS RECURSOS HIDRICOS PGIRH PE-ANA-165879-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: 2020-08- 2020-05- 2020-05- 2020-05- 2020-07- DE AGUA EN BLOQUES IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,672.00 0.00 En ejecución 2020-05-20 10 21 28 29 27 DE RIEGO EN LOS the National Level SECTORES HIDRÁULICOS MENOR ICA, PALPA, NAZCA, ACARY Y BELLA UNIÓN PE-ANA-165880-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL Component 1: Ejecución 2020-05- 2020-05- 2020-05- 2020-08- DE AGUA EN BLOQUES IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 7,090.00 0.00 2020-05-20 pendiente 21 28 29 12 DE RIEGO EN EL the National Level SECTOR HIDRÁULICO MENOR IRRIGACIÓN MAJES , VALLE DE MAJES, CAMANÁ PE-ANA-165881-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: MEDICIÓN DE NIVEL 2020-08- 2020-06- 2020-06- 2020-06- 2020-09- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 7,090.00 0.00 En ejecución 2020-06-19 DE AGUA EN BLOQUES 10 22 29 30 14 the National Level DE RIEGO EN EL SECTOR HIDRÁULICO MENOR LA JOYA, CHILI REGULADO Y CHILI NO REGULADO PE-ANA-165883-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE MEDICIÓN DE NIVEL DE AGUA EN BLOQUES Component 1: Ejecución 2020-06- 2020-06- 2020-06- 2020-08- DE RIEGO EN EL IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,672.00 0.00 2020-06-19 pendiente 22 29 30 28 SECTOR HIDRÁULICO the National Level MENOR IRRIGACIÓN ENSENADA-MEJIA- MOLLENDO, PUNTA DE BOMBOM, MOQUEGUA, LOCUMBA, SAMA Y BAJO UCHUSUMA PE-ANA-165885-CS-INDV / DESARROLLO E IMPLEMENTACIÓN DE Component 1: Ejecución 2020-06- 2020-07- 2020-08- 2020-11- CURSO VIRTUAL: IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 9,851.00 0.00 2020-06-22 pendiente 29 20 24 24 MEDICIÓN DEL AGUA the National Level EN SISTEMAS HIDRÁULICOS COMUNES PE-ANA-165889-CS-INDV / BACHILLER 01 PARA TRABAJOS DE Component 1: Ejecución 2020-04- 2020-05- 2020-06- 2022-11- HIDROMETRÍA EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 38,955.00 0.00 2020-04-20 pendiente 27 18 22 09 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165890-CS-INDV / BACHILLER 02 PARA TRABAJOS DE Component 1: Ejecución 2020-04- 2020-05- 2020-06- 2022-11- HIDROMETRÍA EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 38,955.00 0.00 2020-04-20 pendiente 27 18 22 09 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165891-CS-INDV / PROFESIONAL Component 1: ESPECIALISTA PARA 2020-03- 2020-04- 2020-05- 2020-06- 2021-02- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 26,269.00 0.00 Bajo Revision 2020-04-20 ADECUACIÓN DE 30 27 18 22 17 the National Level ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165964-CS-INDV / TÉCNICO 01: Component 1: SENSIBILIZACIÓN Y Ejecución 2020-04- 2020-04- 2020-05- 2021-03- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,300.00 0.00 2020-04-19 CAPACITACIÓN EN pendiente 24 29 14 10 the National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165971-CS-INDV / TÉCNICO 02: Component 1: SENSIBILIZACIÓN Y Ejecución 2020-04- 2020-04- 2020-05- 2021-03- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,300.00 0.00 2020-04-19 CAPACITACIÓN EN pendiente 24 29 14 10 the National Level SISTEMAS HIDRÁULICOS COMUNES DE LA COSTA PE-ANA-165979-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y Component 1: 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- PRESUPUESTOS 01 IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,030.00 0.00 En ejecución 2020-04-20 20 25 30 15 13 PARA the National Level ESTANDARIZACIÓN E INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165984-CS-INDV / TÉCNICO EN METRADOS, COSTOS Y Component 1: 2020-04- 2020-04- 2020-04- 2020-05- 2020-08- PRESUPUESTOS 02 IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,030.00 0.00 En ejecución 2020-04-20 20 25 30 06 04 PARA the National Level ESTANDARIZACIÓN E INTEGRACIÓN DE EXPEDIENTTES TÉCNICOS PE-ANA-165985-CS-INDV / PROFESIONAL Component 1: ESPECIALISTA EN 2020-03- 2020-04- 2020-04- 2020-05- 2022-01- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 81,493.00 0.00 En ejecución 2020-04-20 EJECUCIÓN DE OBRAS 30 25 30 06 26 the National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165987-CS-INDV / PROFESIONAL Component 1: 2020-03- 2020-04- 2020-04- 2020-05- 2022-01- ASISTENTE EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 59,553.00 0.00 En ejecución 2020-04-20 30 25 30 06 26 EJECUCIÓN DE OBRAS the National Level DE ESTRUCTURAS DE MEDICIÓN DE AGUA PE-ANA-165989-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 22 2020-09- 2020-04- 2020-04- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 14,142.00 0.00 En ejecución 2020-04-20 ESTRUCTURAS DE 16 25 30 15 13 the National Level MEDICIÓN DE AGUA EN LA REGIÓN TUMBES PE-ANA-165990-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 11 2020-09- 2020-04- 2020-04- 2020-05- 2020-05- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 7,071.00 0.00 En ejecución 2020-04-20 ESTRUCTURAS DE 16 25 30 15 21 the National Level MEDICIÓN DE AGUA EN LA REGIÓN MOQUEGUA PE-ANA-165991-CS-INDV / SUPERVISIÓN DE LA Component 1: CONSTRUCCIÓN DE 15 2020-09- 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 9,643.00 0.00 En ejecución 2020-04-20 ESTRUCTURAS DE 16 25 30 15 14 the National Level MEDICIÓN DE AGUA EN LA REGIÓN TACNA PE-ANA-165993-CS-INDV / SUPERVISOR PARA LA ADECUACIÓN DE ESTRUCTURAS DE Component 1: 2020-07- 2020-04- 2020-04- 2020-05- 2020-07- MEDICIÓN DE NIVEL IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,672.00 0.00 En ejecución 2020-04-20 10 25 30 15 14 DE AGUA EN BLOQUES the National Level DE RIEGO EN EL SECTOR HIDRÁULICO MENOR PISCO PE-ANA-165994-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Ejecución 2020-04- 2020-04- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 8,508.00 0.00 2020-04-20 MEDICIÓN DE AGUA EN pendiente 25 30 15 13 the National Level LOS SECTORES HIDRÁULICOS DESDE TUMBES HASTA JEQUETEPEQUE Page 13 PE-ANA-165998-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: Ejecución 2020-04- 2020-04- 2020-05- 2020-07- ESTRUCTURAS DE IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,672.00 0.00 2020-04-20 pendiente 25 30 15 14 MEDICIÓN DE AGUA EN the National Level LOS SECTORES HIDRÁULICOS DESDE CHICAMA HASTA SANTA PE-ANA-165999-CS-INDV / SUPERVISIÓN PARA LA CULMINACIÓN DE LA ADECUACIÓN DE Component 1: ESTRUCTURAS DE Ejecución 2020-04- 2020-04- 2020-05- 2020-07- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 5,672.00 0.00 2020-04-20 MEDICIÓN DE AGUA EN pendiente 25 30 15 14 the National Level LOS SECTORES HIDRÁULICOS DESDE FORTALEZA HASTA LURÍN PE-ANA-166000-CS-INDV / TÉCNICO 01 PARA SUPERVISIÓN DEL SUMINISTRO, Component 1: Ejecución 2020-04- 2020-04- 2020-05- 2021-05- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 25,075.00 0.00 2020-04-20 pendiente 25 30 15 10 EN MARCHA Y the National Level CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-166002-CS-INDV / TÉCNICO 02 PARA SUPERVISIÓN DEL SUMINISTRO, Component 1: Ejecución 2020-04- 2020-04- 2020-05- 2021-05- INSTALACIÓN, PUESTA IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 25,075.00 0.00 2020-04-20 pendiente 25 30 15 10 EN MARCHA Y the National Level CAPACITACIÓN DE INSTRUMENTACIÓN PARA LA MEDICIÓN PE-ANA-171096-CS-INDV / TECNICO EN Component 1: AUTOCAD 01 PARA 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,030.00 0.00 En ejecución 2020-04-27 ESTANDARIZACION E 20 29 04 05 03 the National Level INTEGRACION DE PLANOS PE-ANA-171097-CS-INDV / TECNICO EN Component 1: AUTOCAD 02 PARA 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,030.00 0.00 En ejecución 2020-04-27 ESTANDARIZACION E 20 29 04 05 03 the National Level INTEGRACION DE PLANOS PE-ANA-171099-CS-INDV / TECNICO EN Component 1: AUTOCAD 03 PARA 2020-04- 2020-04- 2020-05- 2020-05- 2020-08- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 4,030.00 0.00 En ejecución 2020-04-27 ESTANDARIZACION E 20 29 04 05 03 the National Level INTEGRACION DE PLANOS PE-ANA-165886-CS-INDV / PROFESIONAL 01 PARA TRABAJOS DE Component 1: Ejecución 2020-05- 2020-06- 2020-07- 2022-11- HIDROMETRÍA EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 51,940.00 0.00 2020-05-08 pendiente 15 05 10 27 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-165888-CS-INDV / PROFESIONAL 02 PARA TRABAJOS DE Component 1: Ejecución 2020-05- 2020-06- 2020-07- 2022-11- HIDROMETRÍA EN IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 51,940.00 0.00 2020-05-08 pendiente 15 05 10 27 ESTRUCTURAS DE the National Level MEDICIÓN DE AGUA, EN LA COSTA DEL PERÚ PE-ANA-171926-CS-INDV / PROFESIONAL 01 PARA Component 1: Ejecución 2020-05- 2020-05- 2020-05- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 8,400.00 0.00 2020-05-03 pendiente 13 16 20 18 INTEGRACIÓN DE the National Level EXPEDIENTES TÉCNICOS PE-ANA-171929-CS-INDV / PROFESIONAL 02 PARA Component 1: Ejecución 2020-05- 2020-05- 2020-05- 2020-08- ESTANDARIZACIÓN E IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 8,400.00 0.00 2020-05-03 pendiente 08 11 14 12 INTEGRACIÓN DE the National Level EXPEDIENTES TÉCNICOS PE-ANA-182711-CS-INDV / PROFESIONAL SENIOR Component 1: PARA ACTUALIZAR LA 2020-06- 2020-07- 2020-07- 2020-07- 2020-11- IBRD / 87400 Consolidating IWRM at Posterior Individual Direct 21,000.00 0.00 En ejecución 2020-06-30 POLITICA Y 30 02 07 13 10 the National Level ESTRATEGIA NACIONAL DE RECURSOS HÍDRICOS. PE-ANA-187092-CS-INDV Component 2: Improving / ESPECIALISTA SOCIAL 2020-09- 2020-09- 2020-09- 2020-10- 2022-12- IBRD / 87400 WRM in Selected Pilot Posterior Individual Limited 73,500.00 0.00 En ejecución 2020-09-21 AMBIENTAL CUENCA 23 26 28 01 31 River Basins MAYO - PGIRH PE-ANA-190830-NC-RFQ / Component 1: Ejecución 2020-10- 2020-10- 2020-11- 2020-12- Estudio Geológico del IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 35,000.00 0.00 2020-09-28 pendiente 03 13 08 08 acuífero Caplina the National Level PE-ANA-190831-NC-RFQ / Component 1: Estudio de prospección Ejecución 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 13,000.00 0.00 2020-09-28 geofísica reubicación pendiente 03 13 08 08 the National Level piezómetros PE-ANA-190616-NC-RFQ / Component 1: Estudio Geológico de los Ejecución 2020-10- 2020-10- 2020-11- 2020-12- IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 35,000.00 0.00 2020-09-28 acuíferos de Ica, Villacurí pendiente 03 13 08 08 the National Level y Lanchas PE-ANA-199722-CS-INDV / Profesional especialista Component 1: Ejecución 2020-10- 2020-10- 2020-10- 2022-12- para la instrumentación de IBRD / 87400 Consolidating IWRM at Posterior Individual Limited 72,500.00 0.00 2020-10-20 pendiente 22 27 31 31 las estructuras de the National Level Medición de agua en bloques de riego Page 14