PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2019-02-12 2021-08-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / D2890, TF / A7132 P Executing Agency(ies): roject Fiduciary and Administrative Agency WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 20/STP/COMP2/W/WACA/201 Component 2: Strengthening Request for Single Stage - One 2019-11- 9 / Réparation et entretien IDA / D2890 the Policy and Institutional Post Limited 25,000.00 21,815.20 Signed 2019-03-16 2019-05-14 2019-05-11 2019-07-22 Quotations Envelope 07 des phares. Framework 01/STP/COMP3/W/WACA/201 9 / Construction des routes Component 3: Strengthening Single Stage - One 2020-10- d'accès,d'égouts et d'autres IDA / D2890 National Physical and Social Post Request for Bids Open - National 450,000.00 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 Envelope 31 infrastructures dans les zones Investments d'expansion sécurisées. 02/STP/COMP3/W/WACA720 Component 3: Strengthening 19 / Infrastructures sociales Single Stage - One 2021-01- IDA / D2890 National Physical and Social Post Request for Bids Open - National 240,000.00 0.00 Canceled 2020-04-01 2020-04-06 2020-05-18 2020-06-17 2020-07-22 pour Malanza, Santa catarina Envelope 18 Investments et Praia Burra. 03/STP/COMP3/W/WACA/201 9 / Construtions de maisons Component 3: Strengthening Request for Single Stage - One 2021-01- pour les plus vulnérables au IDA / D2890 National Physical and Social Post Limited 190,000.00 0.00 Canceled 2020-06-06 2020-08-01 Quotations Envelope 28 Malanza, Santa Catarina et Investments Praia Burra. 26/STP/COMP3/W/WACA/201 9 / Reabilitação dos Component 3: Strengthening 2020-07- dispositivos de protecção do IDA / D2890 National Physical and Social Post Direct Selection Direct 30,110.00 33,182.29 Signed 2019-12-09 2019-12-13 2019-12-14 2019-12-12 2020-01-18 2019-12-26 16 Rio de Ribeira Afonso contra Investments inundações 32/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de murro de Single Stage - One 2021-01- IDA / D2890 National Physical and Social Post Request for Bids Open - National 400,000.00 506,252.93 Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-06-25 2020-06-02 2020-06-26 2020-07-07 2020-08-17 proteção e ordenamento Envelope 03 Investments urbanístico de Santa Catarina 33/STP/COMP3/W/WACA/202 Component 3: Strengthening 0 / Obras de ordenamento Single Stage - One 1,073,025.3 2021-01- IDA / D2890 National Physical and Social Post Request for Bids Open - National 350,000.00 Signed 2020-03-17 2020-03-31 2020-03-22 2020-04-06 2020-05-03 2020-08-14 2020-06-02 2020-10-01 2020-07-07 2020-10-07 urbanístico de Malanza e Praia Envelope 6 03 Investments Burra 37/STP/COMP3/W/WACA/202 0 / Obras de construção de Component 3: Strengthening Single Stage - One 2021-05- infraestruturas sociais em IDA / D2890 National Physical and Social Post Request for Bids Open - National 190,000.00 0.00 Canceled 2020-08-03 2020-08-08 2020-09-19 2020-10-19 2020-11-23 Envelope 22 Malanza, Praia Burra e Santa Investments Catarina 46/STP/COMP3/W/WACA/202 0 / Appui à la construction des maisons (Coût de l'appui, Component 3: Strengthening Single Stage - One 2021-05- du materiel et de IDA / D2890 National Physical and Social Post Request for Bids Open - International 375,000.00 0.00 Canceled 2020-08-10 2020-08-15 2020-09-26 2020-10-26 2020-11-30 Envelope 29 l'accompagnement technique) Investments à Malanza, à Praia Burra et à Santa Catarina. 47/STP/COMP3/W/WACA/202 0 / Preparation zone Component 3: Strengthening Request for Single Stage - One 2021-09- expansion: urbanisation et IDA / D2890 National Physical and Social Post Limited 200,000.00 0.00 Canceled 2021-02-03 2021-03-31 Quotations Envelope 27 infraestrutures sociales à Praia Investments Abade. 53/STP/COMP3/W/WACA/202 0 / Constructions de maisons Component 3: Strengthening Single Stage - One 2021-07- et infraestructures sociales en IDA / D2890 National Physical and Social Post Request for Bids Open - International 500,000.00 0.00 Canceled 2020-09-22 2020-10-16 2020-09-27 2020-10-21 2020-11-08 2020-12-08 2021-01-12 Envelope 11 Santa Catarina, Malanza et Investments Praia Burra 65/STP/COMP3/W/WACA/202 Component 3: Strengthening Request for Under 1 / Construction de Request for Single Stage - One 2022-02- IDA / D2890 National Physical and Social Post Limited Quotations (Non 160,000.00 0.00 Implementat 2021-07-07 2021-07-05 2021-09-01 infrastructures sociales à Quotations Envelope 28 Investments Bank-SPD) ion Santa Catarina et à Malanza. 56/STP/COMP3/W/WACA/202 1 / Drainage des eaux pluviales et mur de protection Request for Bids - Component 3: Strengthening Pending contre l'inondation marine à Single Stage - One Small Works SPD 2022-06- IDA / D2890 National Physical and Social Post Request for Bids Open - National 1,680,000.00 0.00 Implementat 2021-08-25 2021-08-30 2021-10-11 2021-11-10 2021-12-15 IÔ Grande, Micoló et Praia Envelope (1 envelope 13 Investments ion Abade et Préparation de zone process) d'expansion sécurité à IÔ Grande, Micoló et Praia Abade GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/STP/COMP2/G/WACA/201 Component 2: Strengthening 9 / Kit d'equipements de Single Stage - One IDA / D2890 the Policy and Institutional Post Request for Bids Open - International 200,000.00 267,258.69 Signed 2019-06-24 2019-09-17 2019-06-29 2019-09-20 2019-08-10 2019-10-21 2019-09-09 2019-10-21 2019-10-14 2020-10-22 2020-04-11 sécurite en mer pour les Envelope Framework pêcheurs. Page 1 03/STP/COMP2/G/WACA/201 9 / Acquisition de matériel informatique et de logiciels Component 2: Strengthening Request for Single Stage - One dans le domaine de la TF / A7132 the Policy and Institutional Post Open - National 10,000.00 57,751.70 Completed 2019-03-30 2019-05-25 2019-07-16 2019-11-21 2019-09-23 Quotations Envelope surveillance pour Framework l'observatoire de l'environnement 04/STP/COMP4/G/WACA/201 9 / Acquisition de biens et de Component 4: National Request for Single Stage - One IDA / D2890 Post Open - National 22,000.00 0.00 Canceled 2019-04-06 2019-06-01 2019-11-28 matériaux aux propriétaires Coordination Quotations Envelope pour la cession de terres. 21/STP/COMP4/G/WACA/201 9 / Acquisition de biens aux Component 4: National IDA / D2890 Post Direct Selection Direct 4,700.00 4,700.00 Completed 2019-05-23 2019-05-27 2019-05-28 2019-06-05 2019-07-02 2019-06-11 2019-12-29 2019-06-12 proprietaires pour la cession Coordination des terres. 27/STP/COMP4/G/WACA/201 9 / Aquisição de bens para os Component 4: National Request for Single Stage - One IDA / D2890 Post Limited 7,000.00 6,969.30 Signed 2019-11-20 2019-12-23 2020-01-15 2020-02-18 2020-07-13 2020-02-26 proprietários pela concepção Coordination Quotations Envelope de terras em Praia Abade 29/STP/COMP4/G/WACA/201 Under 9 / Aquisição e instalação de Component 4: National IDA / D2890 Post Direct Selection Direct 5,000.00 0.00 Implementati 2019-12-09 2019-12-16 2019-12-14 2019-12-23 2020-01-18 2020-07-16 sistema de contabilidade e Coordination on gestão financeira 38/STP/COMP4/G/WACA/202 Component 4: National Request for Single Stage - One IDA / D2890 Post Limited 15,000.00 14,343.87 Signed 2020-03-28 2020-04-06 2020-05-23 2020-06-08 2020-11-19 0 / Equipamentos para a UGP Coordination Quotations Envelope 39/STP/COMP4/G/WACA/202 Component 4: National 0 / Aquisição de software de IDA / D2890 Post Direct Selection Direct 11,000.00 8,880.00 Signed 2020-04-08 2020-04-10 2020-04-13 2020-04-15 2020-05-18 2020-04-30 2020-11-14 Coordination monitoria e avaliação RUCHE 52/STP/COMP3/G/WACA/202 Component 3: Strengthening 0 / Aquisição de uma moto IDA / D2890 National Physical and Social Post Direct Selection Direct 4,000.00 3,018.79 Completed 2020-06-15 2020-06-22 2020-06-20 2020-07-07 2020-07-25 2020-07-01 2021-01-21 2020-07-02 carrinha Investments NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/S/WACA/201 Component 2: Strengthening Request for Single Stage - One 9 / Aquisition peinture pour IDA / D2890 the Policy and Institutional Post Open - National 9,000.00 0.00 Canceled 2019-05-20 2019-07-15 2020-01-11 Quotations Envelope Marquage des pirogues. Framework CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/STP/COMP3/C/WACA/201 Component 3: Strengthening Consultant 9 / Dessins techniques pour IDA / D2890 National Physical and Social Post Qualification Open - National 30,000.00 65,815.47 Signed 2019-02-08 2019-04-24 2019-03-01 2019-06-12 2019-04-14 2019-10-10 2019-05-14 2019-10-17 2019-06-18 2019-10-17 2019-12-15 la planification spatiale de Investments Selection zones d'expansion sûres 34/STP/COMP3/C/WACA/202 0 / Fiscalização das obras de Component 3: Strengthening Consultant ordenamento urbanístico em IDA / D2890 National Physical and Social Post Qualification Open - National 20,000.00 75,805.36 Signed 2020-03-17 2020-03-31 2020-04-07 2020-04-27 2020-05-21 2020-07-08 2020-06-20 2020-09-28 2020-07-25 2020-08-24 2021-01-21 S.Tomé e Príncipe (Santa Investments Selection Catarina, Malanza e Praia Burra) 45/STP/COMP3/C/WACA/202 Component 3: Strengthening Consultant 0 / Supervision des travaux IDA / D2890 National Physical and Social Post Qualification Open - National 20,000.00 0.00 Canceled 2020-05-11 2020-04-08 2020-06-01 2020-07-15 2020-08-14 2020-09-18 2021-03-17 construction des oeuvres Investments Selection sociaux à S.Tomé et à RAP. 44/STP/COMP3/C/WACA/202 0 / Design d'oeuvres pour les Component 3: Strengthening Consultant travaux des communités IDA / D2890 National Physical and Social Post Qualification Open - National 140,000.00 196,330.00 Signed 2020-04-23 2020-04-25 2020-05-14 2020-07-12 2020-06-27 2020-09-22 2020-07-27 2020-12-18 2020-08-31 2020-12-18 2021-02-27 (Pantufo,Praia Melão, Praia Investments Selection Gamboa-Lochinga-Cruz) 48/STP/COMP3/C/WACA/202 0 / Etude d'impact Component 3: Strengthening Consultant environnementale et sociale IDA / D2890 National Physical and Social Post Qualification Open - International 40,000.00 88,393.37 Signed 2020-05-15 2020-12-16 2020-06-05 2021-01-07 2020-07-19 2021-04-06 2020-08-18 2021-05-05 2020-09-22 2021-04-19 2021-03-21 au Pantufo, Praia Melão et Investments Selection Praia Gamboa-Lochinga-Cruz 57/STP/COMP3/C/WACA/202 1 / Supervision des travaux d'aménagement des zones Component 3: Strengthening Consultant Pending d'expansion à Iô Grande et IDA / D2890 National Physical and Social Post Qualification Limited 50,000.00 0.00 2021-08-27 2021-09-10 2021-10-10 2021-11-14 2022-05-13 Implementation Micoló et des travaux de Investments Selection drainage et mur de protection à Iô Grande et Micoló INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/STP/COMP2/C/WACA/201 9 / Diagnostic de la situation Component 2: Strengthening Individual de la météorologie maritime TF / A7132 the Policy and Institutional Post Consultant Open 10,000.00 48,973.00 Completed 2019-02-08 2019-04-18 2019-03-29 2019-09-05 2019-04-19 2019-09-05 2019-05-24 2019-08-28 2019-11-20 2019-12-30 pour la création d'un centre Framework Selection de prévision maritime Page 2 04/STP/COMP2/C/WACA/201 9 / Assistance technique à Component 2: Strengthening Individual l'INM pour la préparation et la TF / A7132 the Policy and Institutional Post Consultant Open 4,000.00 0.00 Canceled 2019-05-27 2019-05-12 2019-07-15 2019-08-05 2019-09-09 2020-03-07 transmission d'informations Framework Selection météorologiques sur TVS 05/STP/COMP2/C/WACA/201 9 / Conseil en techniques de Component 2: Strengthening Individual suivi et de traitement de TF / A7132 the Policy and Institutional Post Consultant Limited 20,000.00 20,000.00 Completed 2019-05-24 2019-08-21 2019-05-29 2019-10-03 2019-06-19 2019-10-17 2019-07-24 2019-10-18 2020-01-20 2019-11-15 données pour les indicateurs Framework Selection de projet 07/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual 9 / Appui à la loi de gestion TF / A7132 the Policy and Institutional Prior Consultant Open 15,000.00 0.00 Canceled 2019-04-24 2019-06-24 2019-06-12 2019-07-03 2019-08-07 2020-02-03 des risques et catastrophes Framework Selection 09/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual 9 / Appui au cadre juridique TF / A7132 the Policy and Institutional Prior Consultant Open 15,000.00 0.00 Canceled 2019-04-25 2019-06-13 2019-07-04 2019-08-08 2020-02-04 pour le littoral Framework Selection 10/STP/COMP4/C/WACA/STA Individual Component 4: National FF/2019 / Spécialiste en suivi TF / A7132 Post Consultant Open 18,000.00 18,000.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-05 2019-11-12 Coordination et évaluation Selection 11/STP/COMP4/C/WACA/STA Individual FF/2019 / Spécialiste en Component 4: National IDA / D2890 Post Consultant Limited 2,400.00 2,400.00 Signed 2019-01-31 2019-02-21 2019-02-05 2019-05-27 2019-02-26 2019-06-14 2019-04-02 2019-06-11 2019-09-29 communication à temps Coordination Selection partiel 12/STP/COMP4/C/WACA/STA Individual Component 4: National FF/2019 / Hiring a civil IDA / D2890 Post Consultant Open 21,600.00 21,600.00 Signed 2019-01-31 2019-02-13 2019-03-21 2019-04-16 2019-04-11 2019-04-17 2019-05-16 2019-04-05 2019-11-12 Coordination engineer Selection 06/STP/COMP2/C/WACA/201 Component 2: Strengthening Individual 9 / Amélioration de la TF / A7132 the Policy and Institutional Post Consultant Open 10,000.00 11,327.50 Signed 2019-03-20 2019-04-18 2019-05-08 2019-07-10 2019-05-29 2019-07-22 2019-07-03 2019-06-28 2019-12-30 diffusion de messages. Framework Selection 03/STP/COMP2/C/WACA/201 9 / Réalisation du diagnostic Component 2: Strengthening Individual de la situation du studio de TF / A7132 the Policy and Institutional Post Consultant Open 10,000.00 0.00 Canceled 2019-04-01 2019-09-26 2019-05-20 2019-06-10 2019-07-15 2020-01-11 télévision pour la diffusion Framework Selection d'informations météorologiques 22/C/AFAP/STAFF/2019 / Component 4: National Spécialiste en sauvegardes IDA / D2890 Post Direct Selection Direct 32,181.60 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 Coordination environnemental et sociales 23/C/AFAP/STAFF/2019 / Component 4: National IDA / D2890 Post Direct Selection Direct 32,181.60 32,181.60 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 Assistente de operações Coordination 24/C/AFAP/STAFF/2019 / Component 4: National Spécialiste en passation de IDA / D2890 Prior Direct Selection Direct 33,000.00 33,000.00 Signed 2019-08-09 2019-09-19 2019-08-19 2019-09-25 2019-10-23 2019-01-01 2020-04-20 Coordination marchés 25/C/AFAP/STAFF/2019 / Component 4: National IDA / D2890 Post Direct Selection Direct 33,000.00 33,000.00 Signed 2019-08-09 2019-08-08 2019-08-19 2019-08-20 2019-10-23 2019-01-01 2020-04-20 Gestor financeiro adjunto Coordination 08/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual 9 / Soutien à la mise en TF / A7132 National Physical and Social Post Consultant Open 10,000.00 0.00 Canceled 2020-02-10 2020-03-30 2020-04-20 2020-05-25 2020-11-21 œuvre de solutions Investments Selection végétatives 28/STP/COMP4/C/WACA/201 Component 4: National Under 9 / Auditoria as contas do ano IDA / D2890 Post Direct Selection Direct 17,440.00 0.00 2019-12-20 2019-12-19 2019-12-30 2019-12-23 2020-03-04 2020-08-31 Coordination Implementation de 2018 do Projecto WACA . 30/STP/COMP3/C/WACA/201 Component 3: Strengthening Individual 9 / Levantamento topográfico IDA / D2890 National Physical and Social Post Consultant Limited 2,600.00 2,600.00 Signed 2019-12-30 2020-01-13 2020-01-04 2020-03-06 2020-01-25 2020-03-11 2020-02-29 2020-03-11 2020-08-27 da zona de expansão segura Investments Selection de Micoló 36/STP/COMP3/C/WACA/202 Component 3: Strengthening Individual 0 / Desenhos técnicos das IDA / D2890 National Physical and Social Post Consultant Limited 10,000.00 13,200.00 Signed 2020-03-20 2020-04-06 2020-03-25 2020-05-04 2020-04-15 2020-06-26 2020-05-20 2020-06-29 2020-11-16 casas e infraestruturas sociais Investments Selection 35/STP/COMP3/C/WACA/202 0 / Estudos técnicos de Component 3: Strengthening ordenamento urbanístico em IDA / D2890 National Physical and Social Post Direct Selection Direct 140,000.00 137,960.00 Signed 2020-03-20 2020-04-06 2020-03-30 2020-04-13 2020-06-03 2020-04-23 2020-11-30 Iô Grande, Micoló e Praia Investments Abade 31/STP/COMP4/C/WACA/202 Component 4: National IDA / D2890 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-03-23 2019-12-30 2020-04-02 2020-01-02 2020-06-06 2020-01-03 2020-12-03 0 / Assistente de Direcção Coordination 40/STP/COMP2/C/WACA/202 0 / Diagnostic des Component 2: Strengthening Individual réglementations et des cadres IDA / D2890 the Policy and Institutional Post Consultant Open 30,000.00 88,108.10 Signed 2020-04-16 2020-04-17 2020-06-04 2021-05-05 2020-06-25 2021-06-22 2020-07-30 2021-06-29 2021-01-26 politiques côtières, et les Framework Selection textes d'application. 41/STP/COMP2/C/WACA/202 0 / Appui aux réformes Component 2: Strengthening Individual législatives visant à IDA / D2890 the Policy and Institutional Prior Consultant Open 10,000.00 8,740.00 Signed 2020-04-20 2020-07-07 2020-06-08 2021-01-27 2020-06-29 2021-02-11 2020-08-03 2021-02-12 2021-01-30 promouvoir la sécurité Framework Selection maritime (actualisation du decret) 43/STP/COMP2/C/WACA/202 0 / Appui à la préparation des bulletins météorologiques et Component 2: Strengthening Individual formation des cadres IDA / D2890 the Policy and Institutional Post Consultant Open 30,000.00 0.00 Canceled 2020-09-08 2020-10-27 2020-11-17 2020-12-22 2021-06-20 techniques de INM dans la Framework Selection préparation de prévisions météorologiques. Page 3 42/STP/COMP2/C/WACA/202 0 / Assistance technique pour Component 2: Strengthening Individual un système de partage IDA / D2890 the Policy and Institutional Post Consultant Open 30,000.00 0.00 Canceled 2020-09-01 2020-10-20 2020-11-10 2020-12-15 2021-06-13 d'informations climatolgiques Framework Selection (à combiner avec le studio COROBOR) 49/STP/COMP2/C/WACA/202 0 / Recrutement du juriste Component 2: Strengthening Individual national pour l’analyse du TF / A7132 the Policy and Institutional Post Consultant Limited 15,000.00 9,500.00 Signed 2021-05-14 2021-05-14 2021-05-19 2021-06-28 2021-06-09 2021-07-06 2021-07-14 2021-07-07 2022-01-10 cadre legal et institutionnel Framework Selection pour la gestion des zones côtières 50/STP/COMP2/C/WACA/202 Component 2: Strengthening Individual Under 0 / Elaboração da Lei de TF / A7132 the Policy and Institutional Post Consultant Open 60,000.00 0.00 2021-05-17 2021-05-17 2021-07-05 2021-07-26 2021-07-26 2021-08-16 2021-08-30 2022-02-26 Implementation gestão de riscos e catástrofes Framework Selection 64/STP/COMP2/C/WACA/202 1 / Recrutement du juriste Component 2: Strengthening Individual Under national pour l’appui a l' TF / A7132 the Policy and Institutional Post Consultant Limited 15,000.00 0.00 2021-05-26 2021-05-27 2021-05-31 2021-06-11 2021-06-21 2021-08-16 2021-07-26 2022-01-22 Implementation elaboration de loi de gestion Framework Selection des risques et catastrophes 61/STP/COMP2/C/WACA/202 1 / Recrutement d'un expert Component 2: Strengthening Individual Pending international pour TF / A7132 the Policy and Institutional Post Consultant Open 60,000.00 0.00 2021-07-16 2021-09-03 2021-09-24 2021-10-29 2022-04-27 Implementation l'élaboration du plan spatial Framework Selection maritime. 67/STP/COMP4/C/WACA/202 Individual Component 4: National Under 1 / Revisão a meio percurso IDA / D2890 Post Consultant Limited 20,000.00 0.00 2021-07-14 2021-07-15 2021-07-19 2021-08-09 2021-09-13 2022-03-12 Coordination Implementation do projecto Selection 66/STP/COMP3/C/WACA/202 1 / Supervision des Component 3: Strengthening Individual Under construction des IDA / D2890 National Physical and Social Post Consultant Limited 15,000.00 0.00 2021-08-09 2021-07-15 2021-08-14 2021-08-09 2021-09-04 2021-10-09 2022-04-07 Implementation infrastructures sociaux à Investments Selection Santa Catarina et Malanza Individual 68/STP/COMP4/C/WACA/202 Component 4: National IDA / D2890 Post Consultant Limited 10,000.00 0.00 Canceled 2021-07-21 2021-07-26 2021-08-16 2021-09-20 2022-03-19 1 / Revisão a meio percurso Coordination Selection 69/STP/COMP2/C/WACA/202 1 / Elaboração dos Component 2: Strengthening Individual Pending regulamentos da lei de IDA / D2890 the Policy and Institutional Post Consultant Open 30,000.00 0.00 2021-08-30 2021-10-18 2021-11-08 2021-12-13 2022-06-11 Implementation exploração e extração de Framework Selection inertes Page 4