PROCUREMENT PLAN Project information: Angola Commercial Agriculture Development Project P159052 Project Implementation Agency: Ministry of Agriculture (MINAGRI) – Office of Studies, Planning and Statistics (GEPE) Date of the Procurement Plan: March 22, 2017 Period covered by this Procurement Plan: March 22, 2017 to March 22, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “National procurement legislation and applicable conditions under review by the Bank” When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. 1 Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works), Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. “Not Applicable” 2 PROCUREMENT Angola : Angola: Commercial Agriculture Development Project PLAN General Information Country: Angola Bank’s Approval Date of the Original Procurement Plan: 2017-03-06 2021-10-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159052 GPN Date: 2021-09-15 Project Name: Angola: Commercial Agriculture Development Project Loan / Credit No: IBRD / P4860, / , IBRD / 88660, COFN / C1580 M Executing Agency(ies): inistry of Agriculture WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 002/W/CADP/18 / Infrastructure for Production Single Stage - One 2022-05- Maintenance of rural roads COFN / C1580 Post Request for Bids Open - National 956,655.00 0.00 Canceled 2021-07-18 2021-07-23 2021-09-03 2021-10-03 2021-11-07 and Marketing Envelope 06 (1st and 2nd yr) 006/W/CADP/20 / Works of electrical connections, Pending Infrastructure for Production Single Stage - One 15,000,000.0 2022-08- including Design - Kwanza IBRD / 88660 Prior Request for Bids Open - International 0.00 Implementat 2021-11-11 2021-11-16 2021-12-28 2022-01-27 2022-03-03 and Marketing Envelope 0 30 Norte, Kwanza Sul and ion Malange Request for Bids - Works (without 007/W/CADP/20 / Pending Infrastructure for Production Single Stage - One prequalification) 2023-06- Rehabilitation of Irrigation COFN / C1580 Post Request for Bids Open - National 6,500,000.00 0.00 Implementat 2022-02-21 2022-03-07 2022-04-11 2022-05-11 2022-06-15 and Marketing Envelope SPD - Applying 15 infrastructure (Lot 2) ion contractor disqualificiation Request for Bids - 004/W/CADP/20 / Works (without Rehabilitation and Pending Infrastructure for Production Single Stage - One prequalification) 2023-02- Maintenance rural roads - COFN / C1580 Post Request for Bids Open - National 9,000,000.00 0.00 Implementat 2022-02-02 2022-02-16 2022-03-23 2022-04-27 2022-05-28 and Marketing Envelope SPD - Applying 22 (Works Phase 1 - Lot 3) ion contractor Kuanza Sul - 50 km disqualificiation Request for Bids - 001/W/CADP/18 / Works (without Rehabilitation and Pending Infrastructure for Production Single Stage - One prequalification) 10,000,000.0 2026-04- Maintenance rural roads - COFN / C1580 Prior Request for Bids Open - International 0.00 Implementat 2022-04-05 2022-04-19 2022-05-17 2022-06-21 2022-07-26 and Marketing Envelope SPD - Applying 0 21 (Works Phase 1- Lot 2) ion contractor Kuanza Norte (50 km) disqualificiation Request for Bids - Works (without 008/W/CADP/20 / Pending Infrastructure for Production Single Stage - One prequalification) 2023-07- Rehabilitation of Irrigation COFN / C1580 Post Request for Bids Open - National 7,000,000.00 0.00 Implementat 2022-03-31 2022-04-14 2022-05-19 2022-06-23 2022-07-28 and Marketing Envelope SPD - Applying 28 infrastructure (Lot 3) ion contractor disqualificiation Request for Bids - 005/W/CADP/20 / Works (without Rehabilitation and Pending Infrastructure for Production Single Stage - One prequalification) 2023-07- Maintenance rural roads - COFN / C1580 Post Request for Bids Open - National 9,500,000.00 0.00 Implementat 2022-07-10 2022-07-24 2022-08-28 2022-10-02 2022-11-02 and Marketing Envelope SPD - Applying 30 (Works Phase 1- Lot1) ion contractor Malange - 50 km disqualificiation Request for Bids - 003/W/CADP/18 / Works (without Pending Rehabilitation of Irrigation Infrastructure for Production Single Stage - One prequalification) 2023-07- COFN / C1580 Post Request for Bids Open - National 5,000,000.00 0.00 Implementat 2022-03-22 2022-04-05 2022-05-10 2022-06-14 2022-07-15 infrastructure Kwanza Norte and Marketing Envelope SPD - Applying 15 ion (Lot 1) contractor disqualificiation GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 001/GD/ACDP/17 / Supply Project Management, Request for Single Stage - One / Post Open - National 180,000.00 0.00 Canceled 2017-03-18 2017-04-22 2017-07-21 of Vehicles (3) Monitoring and Evaluation Quotations Envelope 007/GD/ACDP/17 / Supply Project Management, UN Agencies of vehicles for the Project IBRD / P4860 Prior Direct 180,000.00 102,941.35 Completed 2017-10-16 2017-10-13 2017-10-21 2017-11-02 2017-11-25 2017-11-14 2018-05-24 2018-03-29 Monitoring and Evaluation (Direct) Implementation Unit 002/GD/ACDP/17 / Supply Project Management, Request for Single Stage - One of IT equipment for PIU Office IBRD / P4860 Post Limited 50,000.00 22,626.49 Completed 2017-11-27 2017-12-07 2018-01-01 2018-03-06 2018-01-08 2018-09-20 Monitoring and Evaluation Quotations Envelope in Luanda 005/GD/ACDP/17 / Project Management, Request for Single Stage - One IBRD / P4860 Post Open - National 15,000.00 13,214.11 Completed 2017-11-06 2017-12-08 2017-12-18 2018-01-17 2017-12-25 2018-03-21 Renovation of PIU office Monitoring and Evaluation Quotations Envelope 003/GD/ACDP/17 / Supply Project Management, Request for Single Stage - One of Office Furniture for PIU IBRD / P4860 Post Open - National 70,000.00 26,780.96 Completed 2017-11-25 2017-12-08 2018-01-20 2018-03-06 2018-02-10 2018-09-12 Monitoring and Evaluation Quotations Envelope Office in Luanda 004/GD/ACDP/17 / Supply Project Management, Request for Single Stage - One of Accountant Software for the IBRD / P4860 Post Open - National 15,000.00 19,462.35 Completed 2018-05-11 2018-06-15 2019-01-11 2018-06-22 2019-07-22 Monitoring and Evaluation Quotations Envelope Project 006/GD/CADP/18 / Supply Project Management, UN Agencies IBRD / 88660 Post Direct 80,000.00 0.00 Canceled 2019-02-04 2019-09-11 2019-02-09 2019-09-11 2019-03-16 2019-09-12 of Vehicles (3) Monitoring and Evaluation (Direct) 002/GD/ACDP/18 / Supply Project Management, Request for Single Stage - One IBRD / P4860 Post Open - National 5,000.00 0.00 Canceled 2017-11-25 2017-12-30 2018-01-06 of TC equipment for PIU Monitoring and Evaluation Quotations Envelope 007/GD/CADP/18 / Supply Project Management, Request for Single Stage - One IBRD / 88660 Post Limited 65,000.00 29,221.33 Completed 2019-02-09 2019-03-20 2019-04-06 2019-06-17 2019-10-03 2019-07-26 of IT equipment for PIU Monitoring and Evaluation Quotations Envelope 009/GD/CADP/18 / Supply Project Management, Request for Single Stage - One IBRD / 88660 Post Limited 75,000.00 17,250.93 Completed 2019-01-30 2019-03-20 2019-03-27 2019-05-06 2019-09-23 2019-07-29 of Office Furniture for PIU Monitoring and Evaluation Quotations Envelope Office 074/CS/CADP/19 / Portable Institutional Strengthening IT Equipment for field Single Stage - One COFN / C1580 and Improved Business Post Request for Bids Open - National 800,000.00 611,543.73 Completed 2019-09-13 2019-10-29 2019-09-18 2019-10-29 2019-10-30 2019-11-29 2019-11-29 2020-04-08 2020-01-03 2020-06-15 2020-07-01 2020-10-01 collection of primary Envelope Environment information (Tablets) Page 1 013/GD/CADP/20 / Office Project Management, IBRD / 88660 Post Direct Selection Direct 25,000.00 14,597.54 Completed 2020-04-30 2020-04-03 2020-05-05 2020-04-07 2020-06-03 2020-05-06 2020-08-02 2020-05-19 Equipment for PIU/GEPE Monitoring and Evaluation 012/GD/CADP/20 / Supply Project Management, Request for Single Stage - One IBRD / 88660 Post Limited 100,000.00 131,409.57 Completed 2020-05-05 2020-04-08 2020-06-30 2020-06-02 2020-10-28 2020-06-30 of Vehicles (3) Monitoring and Evaluation Quotations Envelope 084/CS/CADP/20 / Institutional Strengthening Rehabilitation of the Single Stage - One COFN / C1580 and Improved Business Post Request for Bids Open - National 537,000.00 0.00 Canceled 2020-02-21 2020-02-26 2020-04-08 2020-05-08 2020-06-12 2020-12-09 communication network for Envelope Environment Business intelligence GEPE 008/GD/CADP/18 / Supply Project Management, Request for Single Stage - One IBRD / 88660 Post Limited 10,000.00 0.00 Canceled 2021-07-14 2021-09-08 2022-03-07 of TC equipment for PIU Monitoring and Evaluation Quotations Envelope 105/G/CADP/21 / Vehicles Institutional Strengthening Request for Single Stage - One to support GEPE on Statistic COFN / C1580 and Improved Business Post Limited 105,000.00 120,849.03 Completed 2021-05-31 2021-05-24 2021-07-14 2021-08-19 2021-09-12 2021-09-29 Quotations Envelope Data collection Environment 116/G/CADP/21 / Purchase Pending of Two Vehicles (truck 4x4) to Project Management, Request for Single Stage - One COFN / C1580 Post Limited 130,000.00 0.00 Implementati 2021-10-29 2021-12-20 2022-04-19 support FGC with Business Monitoring and Evaluation Quotations Envelope on Plan implementation 117/G/CADP/21 / Laptops Pending and related IT equipment to Project Management, Request for Single Stage - One COFN / C1580 Post Limited 50,000.00 0.00 Implementati 2021-10-27 2021-12-14 2022-04-13 support CADP and FGC with Monitoring and Evaluation Quotations Envelope on Business Plan implementation NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 090/CS/CADP/20 / Business Institutional Strengthening Intelligence and rehabilitation Single Stage - One COFN / C1580 and Improved Business Post Request for Bids Open - International 1,200,000.00 1,498,136.00 Signed 2020-05-04 2020-10-29 2020-05-09 2021-01-19 2020-06-20 2021-02-03 2020-07-20 2021-05-11 2020-08-24 2021-06-22 2021-08-24 of the communication Envelope Environment network for GEPE CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 010/CS/ACDP/16 / Consultancy to support value chain analysis/development for Poultry & Eggs, Corn and Promotion and Support for Quality And Cost- Soy, and Coffee VCs. This IBRD / P4860 Prior Open - International 500,000.00 159,585.00 Completed 2017-03-13 2017-04-03 2017-08-22 2017-04-19 2017-12-08 2017-04-24 2017-12-08 2017-05-15 2018-01-12 2017-06-03 2018-03-07 2017-06-13 2018-03-09 2017-12-20 2018-12-10 Agribusiness Development Based Selection would include studies, strategy development, stakeohlder mobilization, build capacity at MINAGRI. 013/CS/ACDP/17 / Consultant Consultant to develop Promotion and Support for IBRD / P4860 Post Qualification Open - International 150,000.00 156,310.00 Completed 2017-03-20 2017-05-15 2017-04-03 2017-05-01 2017-06-19 2017-05-08 2017-07-03 2017-05-29 2017-07-24 2017-07-28 2018-05-11 environmental studies and Agribusiness Development Selection related safeguard instruments 009/CS/ACDP/17 / Consultant Consultant to develop Social Promotion and Support for / Post Qualification Open - International 120,000.00 0.00 Canceled 2017-03-20 2017-05-15 2017-04-03 2017-05-01 2017-06-19 2017-05-08 2017-07-03 2017-05-29 2017-07-28 Safeguard studies and related Agribusiness Development Selection Instruments 060/CS/CADP/18 / External Project Management, Least Cost IBRD / 88660 Prior Open - International 200,000.00 87,865.50 Signed 2018-09-24 2018-09-26 2018-10-15 2018-10-07 2018-11-19 2019-03-05 2018-12-17 2019-06-21 2019-01-16 2019-09-23 2019-02-13 2019-10-15 2019-03-13 2019-11-13 2019-09-09 Audit for PIU (first 3 years) Monitoring and Evaluation Selection 061/CS/CADP/18 / Survey of Infrastructure for Production Quality And Cost- supporting infrastructure IBRD / 88660 Post Open - International 350,000.00 249,434.61 Signed 2018-10-29 2018-12-27 2018-11-19 2019-02-06 2019-01-02 2019-04-24 2019-01-30 2019-07-31 2019-03-01 2019-07-02 2019-04-05 2019-08-05 2019-05-10 2019-09-13 2020-05-09 and Marketing Based Selection Phase 2 052/CS/CADP/18 / TECHNICAL SERVICES PROVIDERS TO SUPPORT Promotion and Support for Quality And Cost- IBRD / 88660 Prior Open - International 1,000,000.00 8,915,275.57 Under Review 2019-01-31 2019-07-23 2019-02-21 2019-08-13 2019-04-06 2019-11-21 2019-05-04 2020-01-17 2019-06-03 2020-02-12 2019-07-08 2021-08-27 2019-08-12 2020-06-22 2020-08-11 PROJECT INTERVENTIONS FOR Agribusiness Development Based Selection BUSINESS PLANS IMPLEMENTATION (TSP 1.1) 072/CS/CADP/19 / TECHNICAL SERVICES Institutional Strengthening PROVIDERS TO SUPPORT THE Quality And Cost- IBRD / 88660 and Improved Business Post Open - International 120,000.00 0.00 Canceled 2019-07-26 2019-07-14 2019-08-16 2019-09-29 2019-10-27 2019-11-26 2019-12-31 2020-02-04 2021-02-03 SUB-COMPONENT OF VALUE Based Selection Environment CHAIN STRATEGY DEVELOPMENT 070/CS/CADP/19 / Participatory process for Infrastructure for Production Quality And Cost- IBRD / 88660 Post Open - International 120,000.00 0.00 Canceled 2019-07-23 2019-07-15 2019-08-13 2019-09-26 2019-10-24 2019-11-23 2019-12-28 2020-02-01 2021-01-31 identification of irrigation and Marketing Based Selection schemes 071/CS/CADP/19 / Feasibility study on Infrastructure for Production Quality And Cost- rehabilitation of small and IBRD / 88660 Prior Open - International 120,000.00 550,032.08 Signed 2019-07-23 2019-10-29 2019-08-13 2019-10-29 2019-09-26 2020-02-18 2019-10-24 2020-04-30 2019-11-23 2020-06-08 2019-12-28 2020-08-04 2020-02-01 2020-10-07 2021-01-31 and Marketing Based Selection medium-sized irrigated perimeters 073/CS/CADP/19 / Technical Feasibility Study (TFS) Preparatory Assistance for the Institutional Strengthening UN Agencies design of a strategy to COFN / C1580 and Improved Business Prior Direct 494,000.00 493,810.00 Signed 2019-11-16 2020-09-23 2020-07-13 (Direct) develop and implement a Environment unique system for international trade in Angola Page 2 077/CS/CADP/19 / Technical Studies including Infrastructure for Production Quality And Cost- environmental and social COFN / C1580 Post Open - International 300,000.00 0.00 Canceled 2020-03-15 2020-04-05 2020-05-19 2020-06-16 2020-07-16 2020-08-20 2020-09-24 2021-09-24 and Marketing Based Selection impact assessment for rural roads 064/CS/CADP/18 / TA on geospatial mapping, Infrastructure for Production Quality And Cost- feasibility, demand and cost IBRD / 88660 Prior Open - International 900,000.00 0.00 Canceled 2019-01-31 2019-04-22 2019-02-21 2019-05-01 2019-04-06 2019-09-07 2019-05-04 2019-10-11 2019-06-03 2019-11-14 2019-07-08 2019-08-12 2020-08-11 and Marketing Based Selection studies for rural electrifications 087/CS/CADP/20 / Technical Services Providers to support Promotion and Support for Quality Based COFN / C1580 Prior Open - International 400,000.00 1,022,684.00 Signed 2020-04-15 2020-04-11 2020-05-06 2020-04-14 2020-06-19 2020-07-24 2020-07-17 2020-10-08 2020-08-16 2020-11-30 2020-09-15 2021-03-03 2020-10-20 2021-03-22 2022-10-20 Financial Sector intervention Agribusiness Development Selection for partial credit guarantees 069/CS/CADP/19 / Technical Services Providers to support Promotion and Support for Quality And Cost- Financial Sector intervention IBRD / 88660 Post Open - International 200,000.00 0.00 Canceled 2019-07-14 2019-07-15 2019-08-04 2019-09-17 2019-10-15 2019-11-14 2019-12-19 2020-01-23 2021-01-22 Agribusiness Development Based Selection for partial credit guarantees (TSP 1.2) 093/CS/CADP/20 / Priorization Studies and Infrastructure for Production Quality And Cost- Under COFN / C1580 Prior Open - International 837,000.00 0.00 2020-09-18 2020-09-21 2020-10-09 2020-10-26 2020-11-22 2021-03-05 2020-12-20 2021-05-13 2021-01-19 2021-09-23 2021-02-23 2021-03-30 2021-09-26 Design for Malanje, Cuanza and Marketing Based Selection Implementation Norte and Cuanza Sul 094/CS/CADP/20 / Innovative Management Infrastructure for Production Quality And Cost- COFN / C1580 Post Open - International 200,000.00 157,225.00 Signed 2020-10-11 2020-09-20 2020-11-01 2020-10-05 2020-12-15 2020-11-27 2021-01-12 2021-01-19 2021-02-11 2021-02-26 2021-03-18 2021-05-31 2021-04-22 2021-06-21 2021-08-20 Systems for Irrigated and Marketing Based Selection Perimeters 085/CS/CADP/20 / Environmental and social assessment studies for Infrastructure for Production Quality And Cost- IBRD / 88660 Post Open - National 80,000.00 0.00 Canceled 2020-05-22 2020-06-12 2020-07-26 2020-08-23 2020-09-22 2020-10-27 2020-12-01 2021-12-01 electrical connection works - and Marketing Based Selection Kwanza Norte, Kwanza Sul, Malange 075/CS/CADP/19-2 / Participatory process for Infrastructure for Production Quality And Cost- COFN / C1580 Post Open - International 120,000.00 0.00 Canceled 2020-02-28 2019-11-06 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-09-08 identification of irrigation and Marketing Based Selection schemes 035/CS/CADP/18 / Consultancy Design Review Infrastructure for Production Quality And Cost- and Works Supervision COFN / C1580 Post Open - International 350,000.00 0.00 Canceled 2020-03-30 2020-03-13 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-10-09 and Marketing Based Selection including E&S Safeguards, PHASE 1 Kwanza Norte 076/CS/CADP/20 / Consultancy Design Review Infrastructure for Production Quality And Cost- and Works Supervision, COFN / C1580 Post Open - International 350,000.00 0.00 Canceled 2020-03-27 2020-03-13 2020-04-17 2020-05-31 2020-06-28 2020-07-28 2020-09-01 2020-10-06 2021-10-06 and Marketing Based Selection including E&S Safeguards, PHASE 1 Kwanza Sul 078/CS/CADP/19 / Consultancy Design Review Infrastructure for Production Quality And Cost- and Works Supervision, COFN / C1580 Post Open - International 350,000.00 0.00 Canceled 2020-03-30 2020-03-11 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-10-09 and Marketing Based Selection including E&S Safeguards, PHASE 1 Malange Institutional Strengthening 051/CS/CADP/18 / Business Quality And Cost- COFN / C1580 and Improved Business Prior Open - International 850,000.00 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-09-08 Intelligence for GEPE Based Selection Environment 101/CS/CADP/20 / Consultancy Services for Project Management, Quality And Cost- Under IBRD / 88660 Prior Open - International 800,000.00 0.00 2021-01-29 2021-01-27 2021-02-19 2021-02-03 2021-04-04 2021-09-03 2021-05-02 2021-10-13 2021-06-01 2021-07-06 2021-08-10 2025-08-09 Monitoring and Evaluation of Monitoring and Evaluation Based Selection Implementation the CADP 050/CS/CADP/21 / Technical Institutional Strengthening Assistance for the completion Quality And Cost- Under COFN / C1580 and Improved Business Prior Open - International 1,000,000.00 0.00 2021-05-14 2021-08-13 2021-05-29 2021-08-23 2021-06-29 2021-07-27 2021-08-17 2021-09-17 2021-10-18 2023-10-18 and implementation of Based Selection Implementation Environment PLANIRRIGA 080/CS/CADP/20 / Technical Institutional Strengthening Service Provider (TSP) Quality And Cost- Pending COFN / C1580 and Improved Business Post Open - National 250,000.00 0.00 2022-04-29 2022-05-14 2022-06-14 2022-07-12 2022-08-02 2022-09-02 2022-09-22 2023-03-21 Weather index-based crop Based Selection Implementation Environment insurance studies 017/CS/ACDP/16 / Project Project Management, Quality And Cost- COFN / C1580 Post Open - International 300,000.00 0.00 Canceled 2020-03-06 2020-09-10 2020-03-27 2020-04-24 2020-04-29 2020-05-14 2020-06-03 2020-06-13 2020-09-11 Baseline Survey Monitoring and Evaluation Based Selection 110/CS/CADP/21 / Technical Assistance for review and Institutional Strengthening Quality And Cost- Under update of the Mid-Term Plan COFN / C1580 and Improved Business Post Open - National 210,000.00 0.00 2021-04-11 2021-10-12 2021-04-26 2021-05-27 2021-06-24 2021-07-15 2021-08-15 2021-09-04 2022-09-04 Based Selection Implementation of the Agrarian Sector (year Environment 2022 -2027) 088/CS/CADP/20 / TECHNICAL SERVICES PROVIDERS TO SUPPORT THE Institutional Strengthening Quality And Cost- Under SUB-COMPONENT ON PUBLIC- COFN / C1580 and Improved Business Post Open - International 500,000.00 0.00 2021-04-16 2021-04-19 2021-05-01 2021-04-29 2021-06-01 2021-08-31 2021-06-29 2021-07-20 2021-08-20 2021-09-09 2023-08-30 Based Selection Implementation PRIVATE DIALOGUE ON VALUE Environment CHAIN STRATEGY DEVELOPMENT 053/CS/CADP/18 / Technical assistance for capacity Institutional Strengthening Quality And Cost- Pending building in research and COFN / C1580 and Improved Business Prior Open - International 500,000.00 0.00 2022-03-31 2022-04-15 2022-05-16 2022-06-13 2022-07-04 2022-08-04 2022-08-24 2023-08-24 Based Selection Implementation development (to support the 3 Environment inst: INCA, IIA, IIV) 095/CS/CADP/20 / Supervision for rehabilitation Infrastructure for Production Quality And Cost- Pending COFN / C1580 Post Open - International 800,000.00 0.00 2022-01-12 2022-01-27 2022-02-27 2022-03-27 2022-04-17 2022-05-18 2022-06-07 2023-06-07 of Irrigation infrastructure (Lot and Marketing Based Selection Implementation 2) Page 3 096/CS/CADP/20 / Supervision for rehabilitation Infrastructure for Production Quality And Cost- Pending COFN / C1580 Post Open - International 800,000.00 0.00 2022-02-20 2022-03-07 2022-04-07 2022-05-05 2022-05-26 2022-06-26 2022-07-16 2023-07-16 of Irrigation infrastructure (Lot and Marketing Based Selection Implementation 3) 099/CS/CADP/20 / Infrastructure for Production Quality And Cost- Pending Supervision for Works PHASE COFN / C1580 Post Open - International 850,000.00 0.00 2021-10-15 2021-10-30 2021-11-30 2021-12-28 2022-01-18 2022-02-18 2022-03-10 2023-03-10 and Marketing Based Selection Implementation 1 Malange (Lot 1) 098/CS/CADP/20 / Infrastructure for Production Quality And Cost- Pending Supervision for Works PHASE COFN / C1580 Post Open - International 850,000.00 0.00 2022-04-18 2022-05-03 2022-06-03 2022-07-01 2022-07-22 2022-08-22 2022-09-11 2023-06-08 and Marketing Based Selection Implementation 1 Kwanza Sul (Lot 3) 097/CS/CADP/20 / Infrastructure for Production Quality And Cost- Under Supervision for Works PHASE COFN / C1580 Post Open - International 850,000.00 0.00 2022-04-22 2021-09-13 2022-05-07 2022-06-07 2022-07-05 2022-07-26 2022-08-26 2022-09-15 2023-06-12 and Marketing Based Selection Implementation 1 Kwanza Norte (Lot 2) 103/CS/CADP/21 / Technical Assistance on revision of the Institutional Strengthening Quality And Cost- Basic Law of Agrarian COFN / C1580 and Improved Business Post Open - International 400,000.00 0.00 Under Review 2021-10-15 2021-10-12 2021-10-30 2021-11-30 2021-12-28 2022-01-27 2022-03-08 2022-03-28 2023-03-28 Based Selection Development (Law No. 15/05 Environment of 7 December) 054/CS/CADP/18 / Technical Project Management, Quality And Cost- Pending assistance for the investment COFN / C1580 Post Open - International 500,000.00 0.00 2021-12-10 2021-12-31 2022-02-13 2022-03-13 2022-04-12 2022-05-17 2022-06-21 2023-06-21 Monitoring and Evaluation Based Selection Implementation committee 036/CS/CADP/19 / Supervision of Works for Infrastructure for Production Quality And Cost- Under Rehabilitation of Small and COFN / C1580 Post Open - International 800,000.00 0.00 2021-10-22 2021-10-05 2021-11-05 2021-11-22 2021-12-22 2022-01-06 2022-01-31 2022-02-20 2023-02-20 and Marketing Based Selection Implementation Medium Irrigated Perimeters Kwanza Norte ( Lot 1) 079/CS/CADP/20 / Supervision for Works of electrical connections, Infrastructure for Production Quality And Cost- Pending IBRD / 88660 Prior Open - International 1,250,000.00 0.00 2022-01-10 2022-01-25 2022-02-25 2022-03-25 2022-04-15 2022-05-16 2022-06-05 2023-06-05 including design revision in and Marketing Based Selection Implementation Kwanza Norte, Kwanza Sul and Malange INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual 002/CS/ACDP/16 / Project Management, IBRD / P4860 Prior Consultant Open 130,000.00 817,829.44 Signed 2017-03-06 2017-08-29 2017-04-04 2017-09-08 2017-04-05 2017-09-28 2017-04-20 2017-09-29 2018-04-20 Procurement specialist Monitoring and Evaluation Selection 014/CS/ACDP/16 / Consultant to undertake analysis of infrastructure Promotion and Support for IBRD / P4860 Post Direct Selection Direct 100,000.00 299,133.85 Completed 2017-03-13 2017-03-23 2017-05-20 2017-09-12 2017-06-19 2018-05-07 current status as well as other Agribusiness Development services for the betterment of the value chains 003/CS/ACDP/16 / Individual Project Management, Agribusiness and Value Chain IBRD / P4860 Prior Consultant Open 150,000.00 278,174.02 Terminated 2017-11-13 2018-05-17 2017-12-16 2017-12-23 2018-10-01 2018-01-13 2018-11-01 2019-01-13 Monitoring and Evaluation Analysis Specialist Selection 016/CS/ACDP/16 / Individual Project Management, Consultant to develop the IBRD / P4860 Post Consultant Open 70,000.00 45,200.00 Completed 2017-12-18 2018-04-13 2018-02-05 2018-04-16 2018-02-26 2018-05-02 2018-03-08 2018-05-17 2018-06-06 2019-08-13 Monitoring and Evaluation project's manual Selection Individual 004/CS/ACDP/16 / Finance Project Management, IBRD / P4860 Prior Consultant Open 130,000.00 343,662.13 Signed 2017-10-30 2017-10-04 2017-11-28 2017-12-12 2018-01-31 2018-01-09 2018-02-20 2019-01-09 management specialist Monitoring and Evaluation Selection 023/CS/ACDP/17 / Individual Contracting of an Project Management, IBRD / P4860 Prior Consultant Open 70,000.00 389,271.24 Signed 2018-01-15 2017-11-30 2018-03-05 2018-05-08 2018-03-26 2018-05-08 2018-04-30 2018-07-06 2019-04-30 Environmental Safeguards Monitoring and Evaluation Selection Specialist Individual 007/CS/ACDP/16 / Project Project Management, IBRD / P4860 Post Consultant Open 90,000.00 0.00 Canceled 2018-01-15 2017-11-07 2018-03-05 2018-03-19 2018-04-07 2019-04-07 accountant Monitoring and Evaluation Selection 025/CS/ACDP/18 / Consultancy services for the Individual Promotion and Support for elaboration of a Diagnosis of IBRD / P4860 Post Consultant Open 90,000.00 0.00 Canceled 2017-06-25 2017-06-05 2017-07-19 2017-08-28 2017-07-24 2017-08-03 2018-01-30 Agribusiness Development Land Uses and Rights in the Selection Project Implementation Area 025/CS/CADP/17 / Individual DIAGNOSTIC REVIEW OF LAND Promotion and Support for IBRD / P4860 Prior Consultant Open 90,000.00 80,000.00 Completed 2017-11-20 2017-11-22 2017-12-12 2017-12-04 2017-12-15 2018-01-24 2018-01-10 2018-02-08 2018-07-09 2018-12-26 RIGHTS AND LAND USES IN Agribusiness Development Selection THE PROJECT AREA Individual 005/CS/ACDP/16 / Junior Project Management, IBRD / P4860 Prior Consultant Open 70,000.00 243,044.75 Signed 2018-05-07 2018-05-29 2018-06-05 2018-09-10 2018-06-19 2018-09-27 2018-07-10 2018-10-02 2019-07-10 Procurement Officer 1 Monitoring and Evaluation Selection 026/CS/CADP/17 / Individual Project Management, Consultancy to prepare the IBRD / P4860 Post Consultant Open 30,000.00 0.00 Canceled 2018-01-29 2018-03-19 2018-04-09 2018-05-14 2018-11-10 Monitoring and Evaluation project manuals Selection Individual 034/CS/CADP/18 / Project Project Management, IBRD / P4860 Post Consultant Open 70,000.00 165,897.79 Terminated 2018-06-04 2018-05-17 2018-07-03 2018-07-12 2018-07-13 2018-07-17 2018-08-12 2018-08-13 2019-02-08 Accountant Monitoring and Evaluation Selection Individual 006/CS/ACDP/16 / Assistant Project Management, IBRD / P4860 Post Consultant Open 75,000.00 0.00 Canceled 2017-03-06 2017-04-04 2017-04-18 2017-05-16 2018-05-16 Financial Management Monitoring and Evaluation Selection Individual 028/CS/CADP/18 / Matching Project Management, IBRD / 88660 Prior Consultant Open 150,000.00 385,664.22 Signed 2019-01-15 2019-01-23 2019-03-05 2019-07-15 2019-03-26 2019-07-25 2019-04-30 2019-08-05 2019-10-27 Grant Manager Monitoring and Evaluation Selection Page 4 Individual 032/CS/CADP/18 / Matching Project Management, IBRD / 88660 Post Consultant Open 70,000.00 82,308.45 Signed 2019-01-15 2019-02-11 2019-03-05 2019-11-05 2019-03-26 2019-11-13 2019-04-30 2019-11-18 2019-10-27 Grant Specialist Monitoring and Evaluation Selection Individual 033/CS/CADP/18 / Junior Project Management, IBRD / 88660 Post Consultant Open 70,000.00 233,811.58 Signed 2019-01-15 2018-12-06 2019-03-05 2019-04-25 2019-03-26 2019-05-07 2019-04-30 2019-05-20 2019-10-27 Financial Management officer Monitoring and Evaluation Selection Individual 031/CS/CADP/18 / Matching Project Management, IBRD / 88660 Post Consultant Open 70,000.00 230,661.87 Signed 2019-01-18 2018-11-29 2019-03-08 2019-07-15 2019-03-29 2019-07-26 2019-05-03 2019-09-18 2019-10-30 grant accountant Monitoring and Evaluation Selection 058/CS/CADP/18 / Individual Project Management, Monitoring and Evaluation IBRD / 88660 Post Consultant Open 70,000.00 132,150.00 Terminated 2018-12-28 2019-02-11 2019-02-15 2019-10-28 2019-03-08 2019-11-08 2019-04-12 2019-11-25 2019-10-09 Monitoring and Evaluation specialist Selection Individual 057/CS/CADP/18 / Provincial Project Management, IBRD / 88660 Post Consultant Open 40,000.00 73,335.82 Signed 2019-01-09 2019-04-22 2019-02-27 2019-12-24 2019-03-20 2020-01-23 2019-04-24 2020-01-17 2019-10-21 Representative 3 Monitoring and Evaluation Selection Individual 056/CS/CADP/18 / Provincial Project Management, IBRD / 88660 Post Consultant Open 40,000.00 73,335.10 Signed 2019-01-09 2019-04-22 2019-02-27 2019-11-13 2019-03-20 2019-11-15 2019-04-24 2019-11-04 2019-10-21 Representative 2 Monitoring and Evaluation Selection Individual 055/CS/CADP/18 / Provincial Project Management, IBRD / 88660 Post Consultant Open 40,000.00 73,335.82 Signed 2019-01-09 2019-04-15 2019-02-27 2019-11-13 2019-03-20 2019-11-14 2019-04-24 2019-11-04 2019-10-21 Representative 1 Monitoring and Evaluation Selection Individual 043/CS/CADP/18 / Project Management, IBRD / 88660 Prior Consultant Open 70,000.00 291,821.33 Signed 2019-01-11 2019-02-26 2019-03-01 2019-04-30 2019-03-22 2019-05-29 2019-04-26 2019-06-11 2019-10-23 Communication specialist Monitoring and Evaluation Selection Individual 044/CS/CADP/18 / Senior Project Management, IBRD / 88660 Prior Consultant Open 150,000.00 309,372.24 Signed 2018-12-28 2019-02-11 2019-02-15 2019-04-22 2019-03-08 2019-06-24 2019-04-12 2019-06-17 2019-10-09 Infrastructure specialist Monitoring and Evaluation Selection Individual 045/CS/CADP/18 / Project Project Management, IBRD / 88660 Post Consultant Open 18,000.00 17,934.06 Terminated 2019-01-24 2019-05-16 2019-03-14 2020-01-09 2019-04-04 2020-01-20 2019-05-09 2020-01-31 2019-11-05 Coordinator's Assistant Monitoring and Evaluation Selection 063/CS/CADP/18 / Expert Institutional Strengthening Individual for Data collection and IBRD / 88660 and Improved Business Post Consultant Open 90,000.00 198,668.14 Signed 2019-01-31 2019-11-08 2019-03-21 2020-02-18 2019-04-11 2020-02-21 2019-05-16 2020-03-09 2019-11-12 analysis to support GEPE Environment Selection 066/CS/CADP/18 / Individual Project Management, Administrative/Office IBRD / 88660 Post Consultant Open 30,000.00 101,014.54 Signed 2019-02-08 2019-02-11 2019-03-29 2019-06-18 2019-04-19 2019-06-21 2019-05-24 2019-07-01 2019-11-20 Monitoring and Evaluation Assistant Selection Individual 062/CS/CADP/18 / Internal Project Management, IBRD / 88660 Post Consultant Open 90,000.00 61,754.00 Terminated 2018-12-14 2018-11-29 2019-02-01 2019-04-30 2019-02-22 2019-06-07 2019-03-29 2019-06-21 2019-09-25 Audit for PIU Monitoring and Evaluation Selection 067/CS/CADP/19 / External Project Management, IBRD / 88660 Post Direct Selection Direct 40,000.00 30,000.00 Completed 2019-04-30 2019-04-29 2019-05-10 2019-05-08 2019-06-13 2019-05-17 2019-09-11 2019-09-10 Audit for PIU (First Year) Monitoring and Evaluation 068/CS/CADP/19 / Technical Institutional Strengthening Individual support for agriculture policy IBRD / 88660 and Improved Business Post Consultant Open 80,000.00 132,780.67 Signed 2019-05-10 2019-05-31 2019-06-28 2020-01-23 2019-07-19 2020-02-19 2019-08-23 2020-08-10 2020-08-17 set up and analysis for Environment Selection GEPE/MINAGRIF Individual 082/CS/CADP/19 / Internal Project Management, COFN / C1580 Post Consultant Limited 90,000.00 175,939.80 Signed 2019-12-27 2020-01-09 2020-01-03 2020-01-08 2020-01-24 2020-02-28 2020-02-28 2020-03-03 2020-03-02 Audit for PIU Monitoring and Evaluation Selection Individual 042/CS/CADP/18 / IT Project Management, IBRD / 88660 Post Consultant Open 70,000.00 0.00 Canceled 2019-07-25 2019-09-12 2019-10-03 2019-11-07 2020-05-05 Specialist Monitoring and Evaluation Selection 065/CS/CADP/18 / Expert to Institutional Strengthening Individual provide TA on commissioning IBRD / 88660 and Improved Business Post Consultant Open 97,500.00 0.00 Canceled 2019-02-11 2019-04-01 2019-04-22 2019-05-27 2020-05-26 studies related to institutional Environment Selection support 020/CS/ACDP/17 / Individual Project Management, Contracting of a Land IBRD / 88660 Post Consultant Open 30,000.00 0.00 Canceled 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-07-09 Monitoring and Evaluation governance/social Assistant Selection Individual 081/CS/CADP/20 / M&E Project Management, COFN / C1580 Post Consultant Limited 90,000.00 102,673.80 Terminated 2020-02-17 2020-02-17 2020-02-22 2020-03-03 2020-03-14 2020-07-28 2020-04-18 2020-08-07 2021-04-13 Specialist Monitoring and Evaluation Selection 030/CS/CADP/18 / Junior Individual Project Management, Agribusiness and Value Chain COFN / C1580 Post Consultant Open 70,000.00 54,936.90 Signed 2020-04-24 2020-06-22 2020-06-12 2020-10-07 2020-07-03 2020-10-14 2020-08-07 2020-11-03 2021-08-02 Monitoring and Evaluation Analysis Specialist Selection Individual 048/CS/CADP/18 / Impact Project Management, COFN / C1580 Post Consultant Open 50,000.00 0.00 Canceled 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 evaluation specialist Monitoring and Evaluation Selection 021/CS/ACDP/17 / Individual Contracting of a Value chain Project Management, COFN / C1580 Post Consultant Open 70,000.00 0.00 Canceled 2020-02-28 2020-04-17 2020-05-08 2020-06-12 2021-06-12 development/competitiveness Monitoring and Evaluation Selection expert Individual 089/CS/CADP/20 / Project Project Management, IBRD / 88660 Post Consultant Limited 90,000.00 149,718.94 Signed 2020-04-15 2020-04-09 2020-04-20 2020-05-05 2020-05-11 2020-06-09 2020-06-15 2020-06-15 2021-06-10 Accountant Monitoring and Evaluation Selection 024/CS/ACDP/17 / Individual Project Management, Contracting of a Social COFN / C1580 Post Consultant Open 70,000.00 57,754.01 Signed 2020-10-08 2020-08-07 2020-11-26 2020-11-09 2020-12-17 2020-11-17 2021-01-21 2020-11-23 2022-01-21 Monitoring and Evaluation Safeguards Specialist Selection 091/CS/CADP/20 / Technical Service Provider (TSP) Institutional Strengthening Developing a risk financing COFN / C1580 and Improved Business Post Direct Selection Direct 300,000.00 298,962.00 Signed 2020-07-07 2020-06-11 2020-07-17 2020-07-03 2020-09-20 2020-09-10 2021-09-15 tool for agriculture and food Environment security Page 5 092/CS/CADP/20 / LEAST- COST GEOSPATIAL ELECTRIFICATION OPTIONS Infrastructure for Production IBRD / 88660 Post Direct Selection Direct 300,000.00 293,274.00 Signed 2020-07-01 2020-06-15 2020-07-22 2020-06-21 2020-08-15 2020-08-03 2021-02-11 ANALYSIS FOR LAST-MILE and Marketing EXTENSION OF GRID IN THE PROJECT AREA (Partial Study) 086/CS/CADP/20 / Technical Individual Studies for environmental and Infrastructure for Production COFN / C1580 Post Consultant Open 90,000.00 0.00 Canceled 2020-03-23 2020-03-11 2020-05-11 2020-06-01 2020-07-06 2020-11-03 social impact assessment for and Marketing Selection rural roads 083/CS/CADP/20 / Individual Project Management, Assistant/Junior M&E COFN / C1580 Post Consultant Open 70,000.00 74,859.48 Signed 2020-10-16 2021-03-04 2020-12-04 2021-06-01 2020-12-25 2021-06-03 2021-01-29 2021-06-21 2022-01-24 Monitoring and Evaluation Specialist Selection 100/CS/CADP/21 / Project Project Management, COFN / C1580 Prior Direct Selection Direct 191,700.00 192,513.37 Signed 2021-02-26 2021-02-26 2021-03-13 2021-03-04 2021-04-01 2021-02-12 2022-03-27 Coordinator Monitoring and Evaluation Individual 106/CS/CADP/21 / Assistant Project Management, COFN / C1580 Post Consultant Limited 32,117.00 30,000.00 Signed 2021-04-09 2021-04-14 2021-04-19 2021-05-06 2021-05-04 2021-08-02 2021-05-24 2021-08-17 2022-05-24 for the Project Coordinator Monitoring and Evaluation Selection Individual 107/CS/CADP/21 / Matching Project Management, COFN / C1580 Post Consultant Limited 90,000.00 90,000.00 Signed 2021-04-16 2021-04-30 2021-04-26 2021-05-06 2021-05-11 2021-06-21 2021-05-31 2021-07-06 2022-05-31 Grant Manager Monitoring and Evaluation Selection 108/CS/CADP/21 / Individual Monitoring and Evaluation Project Management, COFN / C1580 Post Consultant Limited 77,000.00 77,005.31 Signed 2021-04-13 2021-04-19 2021-04-23 2021-04-28 2021-05-08 2021-06-11 2021-05-28 2021-06-29 2022-05-28 Specialist for the Project and Monitoring and Evaluation Selection is closing. Individual 109/CS/CADP/21 / IT Project Management, Under COFN / C1580 Post Consultant Open 64,500.00 0.00 2021-04-18 2021-08-10 2021-06-02 2021-06-17 2021-07-07 2022-07-07 Specialist for the project Monitoring and Evaluation Implementation Selection 022/CS/ACDP/17 / Individual Project Management, Pending Contracting of a Junior COFN / C1580 Post Consultant Open 50,000.00 0.00 2022-04-22 2022-06-10 2022-07-01 2022-08-05 2023-08-05 Monitoring and Evaluation Implementation Agribusiness Expert Selection 112/CS/CADP/21 / Junior Individual Agribusiness and Value Chain Project Management, COFN / C1580 Post Consultant Limited 38,500.00 38,503.20 Signed 2021-04-13 2021-05-05 2021-04-18 2021-05-31 2021-05-09 2021-07-20 2021-06-13 2021-08-13 2022-06-13 Analysis Specialist (new Monitoring and Evaluation Selection strategy) 111/CS/CADP/21 / Institutional Strengthening Individual Agronomist Researcher COFN / C1580 and Improved Business Post Consultant Limited 40,000.00 40,000.00 Signed 2021-04-21 2021-04-27 2021-04-26 2021-07-14 2021-05-17 2021-08-18 2021-06-21 2021-08-18 2021-09-19 (Specialist in agricultural Environment Selection research) 102/CS/CADP/21 / Individual Project Management, Agribusiness and Value Chain IBRD / 88660 Post Consultant Direct 16,000.00 0.00 Canceled 2021-04-23 2021-04-21 2021-05-10 2021-05-17 2021-05-31 2022-05-31 Monitoring and Evaluation Analysis Specialist Selection 113/CS/CADP/21 / Individual Project Management, Under Environmental Safeguards COFN / C1580 Post Consultant Open 70,000.00 0.00 2021-07-21 2021-07-23 2021-08-25 2021-09-21 2021-09-09 2021-09-29 2022-09-29 Monitoring and Evaluation Implementation Specialist Selection 114/CS/CADP/21 / Individual Project Management, Under Agribusiness and Value Chain COFN / C1580 Post Consultant Direct 64,000.00 0.00 2021-07-13 2021-07-23 2021-07-30 2021-07-28 2021-08-02 2021-07-28 2021-08-15 2022-08-15 Monitoring and Evaluation Implementation Analysis Specialist Selection Individual 047/CS/CADP/18 / Junior Project Management, COFN / C1580 Prior Consultant Open 70,000.00 0.00 Under Review 2021-07-18 2021-08-05 2021-08-26 2021-09-05 2021-09-25 2022-09-25 Procurement Officer 2 Monitoring and Evaluation Selection Individual 115/CS/CADP/21 / Junior Project Management, Under COFN / C1580 Prior Consultant Open 70,000.00 0.00 2021-09-07 2021-09-13 2021-10-16 2021-10-26 2021-11-19 2022-11-14 Procurement Officer Monitoring and Evaluation Implementation Selection 019/CS/ACDP/17 / Individual Project Management, Under Contracting of a Land COFN / C1580 Post Consultant Open 50,000.00 0.00 2021-09-13 2021-10-12 2021-10-22 2021-10-27 2021-11-13 2022-11-13 Monitoring and Evaluation Implementation Administration specialist Selection 104/CS/CADP/21 / Consultancy to support the Institutional Strengthening Individual registration and legalization COFN / C1580 and Improved Business Post Consultant Open 150,000.00 0.00 Canceled 2021-07-30 2021-09-07 2021-09-17 2021-10-07 2022-04-05 of land of potential Environment Selection beneficiaries 118/CS/CADP/21 / Individual Contracting of new Project Management, Pending COFN / C1580 Post Consultant Direct 70,000.00 0.00 2021-10-25 2021-11-06 2021-11-16 2021-12-06 2022-12-01 Environmental Safeguards Monitoring and Evaluation Implementation Selection Specialist 119/CS/CADP/21 / Junior Individual Consultant to support the Project Management, Pending COFN / C1580 Post Consultant Open 18,000.00 0.00 2021-11-03 2021-12-13 2021-12-27 2022-01-20 2023-01-15 Provincial Representative of Monitoring and Evaluation Implementation Selection Cuanza Norte 120/CS/CADP/21 / Junior Individual Consultant to support the Project Management, Pending COFN / C1580 Post Consultant Open 18,000.00 0.00 2021-11-03 2021-12-13 2021-12-27 2022-01-20 2023-01-15 Provincial Representative of Monitoring and Evaluation Implementation Selection Cuanza Sul 121/CS/CADP/21 / Junior Individual Consultant to support the Project Management, Pending COFN / C1580 Post Consultant Open 18,000.00 0.00 2021-11-03 2021-12-13 2021-12-27 2022-01-20 2023-01-15 Provincial Representative of Monitoring and Evaluation Implementation Selection Malange 122/CS/CADP/21 / Individual Individual Consultant to conduct the Mid- Project Management, Pending COFN / C1580 Post Consultant Direct 75,000.00 0.00 2021-10-25 2021-11-04 2021-11-09 2021-11-19 2022-02-17 Term Evaluation of the Project Monitoring and Evaluation Implementation Selection CADP Page 6 123/CS/CADP/21 / Agronomist Researcher to Institutional Strengthening Individual support the PIU to monitor the Pending COFN / C1580 and Improved Business Post Consultant Direct 90,000.00 0.00 2021-10-26 2021-11-05 2021-11-15 2021-11-27 2022-11-22 implementation of the Implementation Environment Selection Harmonized Strategy under SubComponent 3.2 Page 7