Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descriptio Estimate Packages Dome Review Commen No. n d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million (yes/n o) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contract (Works) for Prior Review Summary 1.86 4 No Post 1st of the NCB contract (Goods) for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimate Packages Review Comments of d by Bank Assignment Cost (Prior / US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Bangladesh : Bangladesh NATP-2: National Agricultural Technology Program - Phase II Project PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2017-03-09 2020-11-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149553 GPN Date: Project Name: Bangladesh NATP-2: National Agricultural Technology Program - Phase II Project Loan / Credit No: IDA / 56650 Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WD/PMU-01 / Refurbishment Request for Single Stage - One 2019-01- of Kitchen, Office Space and IDA / 56650 Project Management Post Limited 12,903.00 34,832.30 Signed 2018-05-19 2018-05-20 2018-07-14 2018-06-06 Quotations Envelope 10 building of baths WD/PMU-02 / Refurbishment Request for Single Stage - One 2019-11- of PMU Office Space-Account IDA / 56650 Project Management Post Open - National 6,450.00 0.00 Canceled 2019-03-25 2019-05-20 Quotations Envelope 16 Building BARC GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD/PMU/09A / Office Request for Single Stage - One supplies and Consumables, IDA / 56650 Project Management Post Limited 6,450.00 0.00 Canceled 2017-03-17 2017-04-06 2017-04-20 Quotations Envelope PMU Request for Single Stage - One GD/PMU-6 / Furniture, PMU IDA / 56650 Project Management Post Open - National 2,970.00 2,306.33 Signed 2017-03-22 2017-04-27 2017-06-21 2017-05-27 Quotations Envelope GD/PMU-07 / Electrical Goods: Television- 01 No, Request for Single Stage - One IDA / 56650 Project Management Post Limited 2,580.00 2,329.98 Signed 2017-05-15 2018-04-24 2017-07-24 2017-06-15 2017-08-21 Refrigerator- No, Micro Oven- Quotations Envelope 01 No, Electric Kettle- 01 No. NATP-2/PP/GD-2 / Laptop Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 363,871.00 1,321,511.48 Signed 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-01-25 2017-12-04 2018-04-30 2018-01-15 2018-05-28 2018-02-26 Computer Envelope Under NATP-2/PP/GD-3 / Mobile Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 1,508,387.00 0.00 Implementati 2017-10-09 2017-12-19 2017-10-16 2017-11-13 2018-02-13 2017-11-27 2018-04-30 2018-01-08 2018-02-05 Tablets Envelope on NATP-2/PP/GD-7 / Furniture Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 1,640,000.00 1,726,271.96 Signed 2017-11-06 2018-05-06 2017-11-13 2017-12-11 2018-02-15 2018-01-08 2018-04-30 2018-02-19 2018-05-09 2018-03-19 for FIAC centers Envelope GD/PMU-10 / Stationery and Request for Single Stage - One IDA / 56650 Project Management Post Limited 6,452.00 4,673.51 Completed 2018-05-19 2018-05-21 2018-07-14 2018-06-05 2019-01-10 2018-06-24 Consumables Quotations Envelope GD/PMU-11 / Computer and Request for Single Stage - One IDA / 56650 Project Management Post Limited 3,871.00 3,537.18 Completed 2018-05-19 2018-05-28 2018-07-14 2018-06-05 2019-01-10 2018-06-12 Consumables Quotations Envelope NATP-2/PP/GD-8 / Furniture Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 1,141,936.00 0.00 Canceled 2017-11-06 2018-05-06 2017-11-13 2017-12-11 2018-02-19 2018-01-08 2018-04-30 2018-02-19 2018-03-19 for Training Centers Envelope NATP-2/PP/GD-6 / Air Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 456,774.00 0.00 Canceled 2017-11-15 2017-12-19 2017-11-22 2017-12-13 2018-02-12 2017-12-27 2018-04-30 2018-02-07 2018-03-07 Cooler Envelope NATP-2/PP/GD-1 / Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 936,774.00 0.00 Canceled 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-01-30 2017-12-04 2018-04-30 2018-01-15 2018-02-26 Computer and Accessories Envelope NATP-2/PP/GD-5 / Video Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 1,003,871.00 0.00 Canceled 2017-10-23 2017-12-19 2017-10-30 2017-11-20 2018-02-06 2017-12-18 2018-04-30 2018-01-29 2018-02-26 and Digital Camera Envelope NATP-2/PP/GD-4 / Pico Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 123,871.00 0.00 Canceled 2017-10-02 2017-12-19 2017-10-09 2017-11-06 2018-02-06 2017-11-20 2018-04-30 2018-01-01 2018-01-29 Projector Envelope NATP-2/PP/E-GP/GD-04 / Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 123,871.00 114,387.84 Signed 2018-07-11 2018-07-10 2018-07-16 2018-08-27 2018-08-01 2018-09-26 2018-10-23 2018-10-31 2018-11-22 2019-04-29 Pico Projector Envelope NATP-2/PP/E-GP/GD-08 / Pooled Procurement of Single Stage - One Furniture for Training Centers IDA / 56650 Project Management Post Request for Bids Open - National 994,998.00 909,558.49 Signed 2018-08-27 2019-02-07 2018-09-01 2018-09-30 2018-12-11 2018-10-30 2018-12-22 2018-12-11 2019-03-07 2019-03-26 Envelope for PIU-BARC, PIU-DAE, PIU- DoF and PIU-DLS NATP-2/PP/E-GP/GD-01 LOT- 01 / Pooled Procurement of Single Stage - One Desktop Computers, Offline IDA / 56650 Project Management Post Request for Bids Open - National 851,335.00 786,166.18 Signed 2018-08-27 2018-09-12 2018-09-01 2018-10-13 2018-10-25 2018-11-12 2018-11-28 2018-12-17 2019-01-08 2019-03-17 Envelope UPS, Printers, Scanners and Server NATP-2/PP/E-GP/GD-05 LOT- 02 / Pooled Procurement of Single Stage - One IDA / 56650 Project Management Post Request for Bids Open - National 761,548.00 703,959.87 Signed 2018-08-19 2018-09-06 2018-08-24 2018-10-05 2018-10-08 2018-11-04 2018-12-03 2018-12-09 2019-01-20 2019-03-10 Multimedia Projector with Envelope Screen NATP-2/PP/E-GP/GD-05 LOT- Single Stage - One 03 / Photocopier Normal & IDA / 56650 Project Management Post Request for Bids Open - National 49,212.00 44,728.05 Signed 2018-08-20 2018-09-25 2018-08-25 2018-10-06 2018-10-29 2018-11-05 2018-11-13 2018-12-10 2019-01-20 2019-03-11 Envelope Heavy Duty and Fax Machine NATP-2/PP/E-GP/GD-06 / Single Stage - One Pooled Procurement Air IDA / 56650 Project Management Post Request for Bids Open - National 456,774.00 421,805.16 Signed 2018-08-09 2018-08-27 2018-08-14 2018-09-13 2018-09-24 2018-10-13 2018-12-18 2018-11-17 2019-01-17 2021-09-30 Envelope Coolers Page 1 NATP-2/PP/E-GP/GD-05 LOT- Single Stage - One 01 / Digital Camera and Video IDA / 56650 Project Management Post Request for Bids Open - National 170,839.00 0.00 Canceled 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 2019-03-07 Envelope Camera Handycam NATP-2/PP/E-GP/SD-05A Request for Single Stage - One LOT 1 / Digital Camera and IDA / 56650 Project Management Post Open - National 170,839.00 0.00 Canceled 2019-04-01 2019-05-27 2019-11-23 Quotations Envelope Video Camera Handycam NATP-2/PP/GD-5A / Pooled Enhancing Agricultural Single Stage - One Procurement of Digital IDA / 56650 Post Request for Bids Open - National 173,000.00 0.00 Canceled 2019-09-09 2019-09-14 2019-10-09 2019-11-20 2020-01-01 2020-06-29 Technology Generation Envelope Camera and Video Camera Under GD/PMU-20 / Procurement Request for Single Stage - One IDA / 56650 Project Management Post Limited 6,415.00 0.00 Implementati 2019-10-24 2019-11-10 2019-11-28 of Photocopy Machine Quotations Envelope on GD/PMU-15 / Supply and Request for Single Stage - One IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-09-11 2018-10-14 2018-11-04 Installation of IP Phone Quotations Envelope GD/PMU-14 / Printing of Request for Single Stage - One Annual Report of NATP-2 IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-08-27 2018-09-23 2018-11-22 Quotations Envelope Project GD/PMU-16 / Office Request for Single Stage - One IDA / 56650 Project Management Post Open - National 4,968.00 0.00 Canceled 2019-03-25 2019-05-20 2019-11-16 Stationery and Consumables Quotations Envelope GD/PMU-13 / Office Request for Single Stage - One Equipment and Computer IDA / 56650 Project Management Post Limited 6,452.00 0.00 Canceled 2018-12-21 2019-01-24 2019-02-21 Quotations Envelope Consumables for PMU Office NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD/PMU-12 / Non- Request for Single Stage - One consulting Service for IDA / 56650 Project Management Post Limited 3,871.00 2,217.16 Completed 2018-05-19 2018-05-14 2018-07-14 2018-05-21 2019-01-10 2018-06-20 Quotations Envelope Computer repair CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD/PMU/F1 / Firm Hire for Base Line Survey, Monitoring Quality And Cost- IDA / 56650 Project Management Prior Open - National 1,637,419.00 0.00 Canceled 2017-10-11 2018-01-15 2017-10-18 2017-12-06 2018-07-30 2018-01-17 2018-11-28 2018-02-15 2018-03-15 2018-04-26 2021-09-30 & Evaluation and Impact Based Selection Assessments. SD/PMU/F2 / Consulting Firm Quality And Cost- Under IDA / 56650 Project Management Post Open - National 677,419.00 0.00 2017-10-18 2017-12-19 2017-11-01 2017-12-13 2018-12-18 2018-01-10 2018-12-18 2018-02-07 2018-11-28 2018-03-07 2019-03-04 2018-04-18 2021-09-30 for Internal Audit. Based Selection Implementation SD/PMU/F-3 / Consulting Firm Hire for Developing of Consultant Computerized/Web Based IDA / 56650 Project Management Post Qualification Open - National 82,580.00 82,644.66 Signed 2018-08-20 2018-09-10 2018-09-10 2018-10-24 2019-05-05 2018-11-23 2019-10-21 2018-12-28 2019-11-04 2021-09-30 Accounting and Reporting Selection Software SD/PMU/F-4 / Consulting Quality And Cost- Firm Hire for AudioVideo/Film IDA / 56650 Project Management Post Open - National 200,000.00 0.00 Canceled 2019-09-22 2019-10-13 2019-12-12 2020-01-09 2020-02-27 2020-03-24 2020-05-05 2021-11-02 Based Selection Production SD/PMU/F-5 / Consulting Firm Hire for Information and Quality And Cost- Under IDA / 56650 Project Management Post Open - National 464,516.00 0.00 2019-09-19 2020-04-19 2019-10-10 2020-06-29 2019-12-19 2020-01-16 2020-03-12 2020-04-16 2020-05-21 2021-09-30 Communication Technologies Based Selection Implementation for PMU SD/PMU/F-6 / Pooled Procurement of Consulting Supporting Agricultural Firm for design and Quality And Cost- Under IDA / 56650 Technology for Crops Post Open - National 335,484.00 0.00 2019-09-15 2019-11-20 2019-10-06 2019-12-10 2019-12-08 2020-03-03 2020-01-05 2020-06-10 2020-02-27 2020-08-27 2020-04-02 2020-09-17 2020-05-07 2021-05-07 development of agricultural Based Selection Implementation Development extension MIS for PIU-DAE, PIU-DOF and PIU-DLS SD/PMU/F-7 / Pooled Procurement of Consulting Firm for Design and Supporting Agricultural Quality And Cost- Under Development of Agricultural IDA / 56650 Technology for Crops Post Open - National 174,193.00 0.00 2019-09-24 2019-04-21 2019-10-15 2020-06-17 2019-12-12 2020-01-09 2020-02-27 2020-04-02 2020-05-07 2021-05-07 Based Selection Implementation Knowledge and Learning Development Platform for PIU-DAE, PIU- DLS and PIU-DOF SD/PMU/F-8 / Procurement Quality And Cost- Pending of Consulting Firm for Impact IDA / 56650 Project Management Prior Open - International 580,645.00 0.00 2019-12-15 2020-01-05 2020-03-08 2020-04-05 2020-05-05 2020-06-09 2020-07-14 2021-09-30 Based Selection Implementation Assessment of NATP-2 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SD/PMU/IC-10 / Training Individual and Communication IDA / 56650 Project Management Post Consultant Open 267,100.00 180,701.10 Signed 2017-03-02 2017-10-17 2017-05-15 2017-10-22 2017-05-29 2017-10-26 2017-06-26 2017-10-31 2021-09-30 Specialist, PMU Selection Individual SD/PMU/IC-09 / Monitoring IDA / 56650 Project Management Post Consultant Open 267,100.00 180,777.30 Signed 2017-03-02 2017-10-17 2017-05-15 2017-10-22 2017-05-29 2017-10-26 2017-06-26 2017-11-02 2021-09-30 and Evaluation Specialist, PMU Selection Page 2 Individual SD/PMU/IC-13 / Assistant IDA / 56650 Project Management Prior Consultant Open 222,580.00 108,466.38 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-30 2017-06-26 2017-11-06 2021-09-30 Manager (Procurement), PMU Selection Individual SD/PMU/IC-07 / ICT IDA / 56650 Project Management Post Consultant Open 267,100.00 407,246.00 Signed 2017-03-02 2017-05-15 2017-12-18 2017-05-29 2017-12-21 2017-06-26 2018-05-10 2021-09-30 Specialist, PMU Selection SD/PMU/IC-12 / Assistant Individual Manager (Accounts), PMU, 2 IDA / 56650 Project Management Prior Consultant Open 445,160.00 216,411.12 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-30 2017-06-26 2017-11-01 2021-09-30 Position Selection SD/PMU/IC-3 / Procurement Individual Enhancing Agricultural Specialist (PMU, BARC, DAE, IDA / 56650 Prior Consultant Open 1,112,910.00 678,107.78 Signed 2017-02-23 2017-08-20 2017-10-22 2017-08-24 2017-11-05 2017-08-31 2017-11-26 2021-12-28 Technology Generation DoF and DLS)- 5 Positions Selection SD/PIU-BARC-5 / Individual Procurement Specialist (PIU- IDA / 56650 Project Management Prior Consultant Open 222,580.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 BARC) Selection Individual SD DOF/IC-02 / Procurement IDA / 56650 Project Management Prior Consultant Open 244,840.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 Specialist (PIU-DOF) Selection Individual PS/LS-4 / Procurement IDA / 56650 Project Management Prior Consultant Open 133,550.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 Specialist (PIU-DLS) Selection SD/PMU/IC-14 / Individual Procurement Support IDA / 56650 Project Management Post Consultant Open 89,030.00 90,198.45 Signed 2017-03-02 2017-05-15 2017-10-05 2017-05-29 2017-10-10 2017-06-26 2017-10-24 2019-07-31 Specialist, PMU Selection PP/SD/PIU-DAE/IC-02 / Individual Procurement Specialist, PIU- IDA / 56650 Project Management Prior Consultant Open 244,840.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 DAE Selection PP/SD/PIU-DAE/IC-01 / Individual Manager (Financial IDA / 56650 Project Management Post Consultant Open 244,840.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 Management), PIU-DAE Selection SD/PIU-BARC-4 / Manager Individual (Financial Management), PIU- IDA / 56650 Project Management Post Consultant Open 267,100.00 0.00 Canceled 2017-02-28 2017-05-13 2017-05-27 2017-06-24 2021-09-30 BARC Selection SD DOF/IC-01 / Manager Individual (Financial Management), PIU- IDA / 56650 Project Management Post Consultant Open 244,840.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 DOF Selection Individual PS/LS-3 / Manager (Financial IDA / 56650 Project Management Post Consultant Open 267,100.00 0.00 Canceled 2017-03-01 2017-05-14 2017-05-28 2017-06-25 2021-09-30 Management), PIU-DLS Selection SD/PMU/IC-16 / Consultant Individual (Office Management and IDA / 56650 Project Management Prior Consultant Direct 13,355.00 0.00 Canceled 2017-03-12 2017-03-18 2017-03-23 2017-04-01 2017-06-30 Coordination), PMU Selection SD/PMU/IC-15 / Consultant Individual (Human Resource IDA / 56650 Project Management Prior Consultant Direct 13,355.00 0.00 Canceled 2017-03-12 2017-03-18 2017-03-23 2017-04-01 2017-06-30 Development), PMU Selection Individual SD/PMU/IC-2 / Manager IDA / 56650 Project Management Post Consultant Open 267,100.00 0.00 Canceled 2017-02-23 2017-05-08 2017-05-22 2017-06-19 2021-09-30 (Financial Management), PMU Selection SD/PMU/IC-02 / Manager Individual Enhancing Agricultural (Financial Management) for IDA / 56650 Prior Consultant Open 1,290,980.00 723,362.10 Signed 2017-09-19 2017-11-07 2017-10-09 2017-11-28 2017-10-30 2018-01-02 2017-11-30 2018-07-01 Technology Generation PMU and four PIUs Selection SD/PMU/IC-01 / Sector Individual Coordinator, Extension IDA / 56650 Project Management Post Consultant Open 267,097.00 440,229.03 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 Specialist Selection Individual SD/PMU/IC-04 / Project IDA / 56650 Project Management Post Consultant Open 267,097.00 440,229.03 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 Management Specialist Selection Individual SD/PMU/IC-05 / Research- IDA / 56650 Project Management Post Consultant Open 267,097.00 440,229.03 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 Extension Linkage Specialist Selection SD/PMU/IC-06 / Producer Individual Organization Mobilization IDA / 56650 Project Management Post Consultant Open 267,097.00 440,229.03 Signed 2017-12-04 2017-12-03 2018-01-22 2018-06-11 2018-02-12 2018-06-20 2018-03-19 2018-06-28 2018-09-15 Specialist Selection SD/PIUS/PP/IC-1 / Environmental and Social Individual Under Safeguard Specialist, PIU- IDA / 56650 Project Management Prior Consultant Open 390,968.00 0.00 2017-12-04 2018-01-22 2018-08-08 2018-02-12 2018-11-01 2018-03-19 2018-09-15 Implementation BARC, PIU-DAE, PIU-DoF, PIU- Selection DLS SD/PMU/IC-02A / Manager ( Individual Financial Management), PIU- IDA / 56650 Project Management Prior Consultant Open 267,100.00 0.00 Canceled 2018-02-01 2018-03-22 2018-04-12 2018-02-25 2018-05-17 2018-11-13 DLS Selection SD/PMU/IC-3A / Individual Procurement Specialist, PIU- IDA / 56650 Project Management Prior Consultant Open 244,840.00 147,405.63 Signed 2018-02-01 2018-03-22 2018-04-12 2018-05-15 2018-05-17 2018-05-24 2018-11-13 DAE Selection Individual SD/PMU/IC-08 / Gender IDA / 56650 Project Management Post Consultant Open 267,097.00 0.00 Canceled 2017-12-04 2017-12-03 2018-01-22 2018-02-12 2018-03-19 2018-09-15 Specialist Selection SD/PMU/IC-11 / Assistant Individual Manager (Administration), IDA / 56650 Project Management Post Consultant Open 222,580.00 0.00 Canceled 2017-03-02 2017-11-30 2017-05-15 2017-05-29 2017-06-26 2021-09-30 PMU Selection Page 3 SD/PMU/IC-11A / Assistant Individual Pending Manager (Administration), IDA / 56650 Project Management Post Consultant Open 63,870.00 0.00 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Implementation PMU Selection Individual SD/PMU/IC-3B / Procurement IDA / 56650 Project Management Prior Consultant Open 278,581.00 169,416.56 Signed 2019-03-21 2019-07-21 2019-05-09 2019-10-07 2019-05-30 2019-10-29 2019-07-04 2019-11-20 2019-12-31 Specialist, PIU-BARC, PIU-DoF Selection Individual SD/PMU/IC-13A / Assistant Under IDA / 56650 Project Management Prior Consultant Open 83,575.00 53,084.84 2019-03-21 2019-07-22 2019-05-09 2019-09-25 2019-05-30 2019-09-30 2019-07-04 2019-12-31 Manager (Procurement), PMU Implementation Selection SD/PMU/IC-2B / Pooled Individual Procurement of Manager Pending IDA / 56650 Project Management Post Consultant Limited 435,484.00 0.00 2018-08-16 2018-09-10 2018-10-01 2018-11-05 2021-09-30 (Financial Management) for Implementation Selection PIU-DAE , PIU-DLS, PIU-DOF SD/PMU/IC-13B / Assistant Individual Manager ( Procurement ) for IDA / 56650 Project Management Post Consultant Open 49,000.00 48,655.32 Signed 2019-11-11 2019-07-22 2019-11-11 2019-10-29 2019-11-11 2019-10-31 2019-11-24 2019-11-17 2021-09-30 PMU Selection SD/PMU/IC-STC2 / DPP Individual Revision and Procurement IDA / 56650 Project Management Post Consultant Direct 24,194.00 0.00 Canceled 2019-12-15 2020-03-02 2019-12-25 2019-12-30 2020-01-13 2021-01-12 Support Consultant Selection Individual SD/PMU/IC-12A / Assistant Under IDA / 56650 Project Management Post Consultant Open 41,000.00 0.00 2020-01-27 2020-01-29 2020-03-16 2020-03-23 2020-04-06 2021-08-26 Manager ( Accounts) of PMU Implementation Selection SD/PMU/IC-07A / Individual Under Procurement of ICT Specialist IDA / 56650 Project Management Post Consultant Open 67,000.00 0.00 2020-01-28 2020-03-09 2020-03-17 2020-09-17 2020-03-23 2020-04-07 2021-09-30 Implementation for PMU Selection SD/PMU-IC -STC 01 / Individual Communication Consultant Pending IDA / 56650 Project Management Post Consultant Limited 29,032.00 0.00 2018-09-16 2018-09-21 2018-10-12 2018-11-16 2019-05-15 for PMU Implementation Selection Duration = 6 months Individual SD/PMU/IC-08A / Gender Pending IDA / 56650 Project Management Post Consultant Open 106,451.00 0.00 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2021-09-30 Specialist, PMU Implementation Selection SD/PMU/IC-STC2A / Individual Individual Short Term Under IDA / 56650 Project Management Post Consultant Open 29,500.00 0.00 2020-03-15 2020-03-11 2020-05-03 2020-05-24 2020-06-28 2020-12-25 Consultant for DPP Revision Implementation Selection and Procurement Support SD/PMU/IC-04A / Project Individual Under Management Specialist ( PMS) IDA / 56650 Project Management Post Consultant Open 38,709.67 0.00 2020-11-09 2020-11-22 2020-12-28 2021-01-18 2021-02-22 2021-09-30 Implementation of PMU Selection SD/PMU/IC- STC-03 / Short Individual Term Consultant for Gender Under IDA / 56650 Project Management Post Consultant Limited 12,903.22 0.00 2020-11-08 2020-11-17 2020-11-25 2020-12-08 2021-03-08 and Value Chain Study for Implementation Selection PMU SD/PMU/IC-03C / Supporting Agricultural Individual Pending Procurement Specialist of PIU- IDA / 56650 Technology for Fisheries Post Consultant Open 38,709.67 0.00 2020-11-22 2021-01-10 2021-01-31 2021-03-07 2021-09-30 Implementation DOF Development Selection Page 4