IN: NATIONLA CYCLONE RISK MITIGATION PROJECT II (P144726) I. General 1. Bank’s approval Date of the procurement Plan: Original: May 21, 2015 2. Date of General Procurement Notice: May 5, 2015 3. Period covered by this procurement plan: The procurement period of project covered from Year May 5, 2015 to October 2016 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$ 2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. Services (non-consultant) Above US$ 2 million All 6. LIB Above US$ 30,000 Procurement Methods and Threshold Category Method of Procurement Threshold (US$ Equivalent) Goods and Non-consultant ICB >3,000,000 services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per Para 3.7 of the Bank Guidelines Force Account As per Para 3.9 of Guidelines Framework Agreements As per Para 3.6 of Guidelines Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 200,000 Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines Community Participation As per Para 3.19 of Guidelines Page 1 of 4 Prior Review by the Bank. The Bank will prior review the following contracts: • Works: All contracts more than US$ 10.0 million equivalent; • Goods: All contracts more than US$ 2.0 million equivalent; • Non-Consulting Services: All contracts more than US$ 2.0 million equivalent; The PMU shall prior review the first contract issued by each implementing agency, if the estimate of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contract whose estimate falls in prior review threshold value. In addition, the justifications for all contracts to be issued on LIB, single-source (>US$ 30,000) or direct contracting (>US$ 30,000) basis will be subject to Banks prior review. These thresholds are for the initial 18 months period and are based on the procurement performance of the project, these thresholds will be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). For the avoidance of doubts, the Bank shall be entitled to conduct, at any time, independent procurement reviews of all the contracts financed under the Credit. The IA shall prepare a list of contract and submit it to the Bank for conducting PPR. The PPR will be conducted on annual basis. All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank. 2. Pre-qualification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable 4. Reference to Project Operational/Procurement Manual: The Project Operations/Procurement Manual was prepared and agreed by the Bank to be used as guidance note while conducting project procurement. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014, In case of any inconsistency between the Project Operation/Procurement Manual, the Bank Guidelines shall prevail. 5. Any Other Special Procurement Arrangements: Procurement of goods, works and non- consulting services shall be conducted through e-procurement portal in all the participating states using Bank’s standard bidding documents. International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services. However, it is unlikely that there will be any ICB contract. All National Competitive Bidding (NCB) shall be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines. In addition, following additional provisions as agreed with GOI task force (as amended form time to time) shall apply: Page 2 of 4 • Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; • Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); • For prior review contracts , re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; • The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; • Rates contract entered into by Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however, for any procurement under the Shopping procedure; • Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: Available in STEP. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$ 1 million All contract 2. Single Source (Firms) Above US$ 1 million All contract Page 3 of 4 3. Individual Above US$ 300,000 All contracts 4. CQS/LCS Up to US$ 300,000 All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The implementation of component 1 (designating of Early Warning Development System) is foreseen as challenge as there are limited consulting firms in the market. M/s Telecommunications Consultant India Ltd. (TCIL) a government owned public sector has been designing EWDS system for Andhra Pradesh and Odisha under NCRMP I project. Many participating states have requested to single source designing of EWDS to TCIL as they do not have capacity to conduct selection process for such firm. NDMA suggested that while it will be an advantage to use TCIL in all the states, an option will be given to the respective states to either single source TCIL or choose competitive selection procedure to select such firms as reflected in the procurement plan in STEP. 4. Consultancy Assignments with Selection Methods and Time Schedule Available on STEP. Page 4 of 4 PROCUREMENT India : National Cyclone Risk Mitigation Project-II PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-08-08 2019-04-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P144726 GPN Date: Project Name: National Cyclone Risk Mitigation Project-II Loan / Credit No: IDA / 56930 Executing Agency(ies): Department of Revenue Management (Karnataka) WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DRM-KAR-1388-CW-RFB / Package 1: Construction of Multipurpose Cyclone Shelter Single Stage - Two near Govt. Higher Primary IDA / 56930 Post Request for Bids Open - National 380,858.70 Signed 2016-10-30 2016-11-04 2016-12-16 2017-02-28 2017-04-04 2019-10-04 Envelope School and PU college in Padu Kapu village, Udupi taluk, Udupi district IN-DRM-KAR-1947-CW-RFB / Package 5:Construction all weather road from Herikudru temple to NH Single Stage - Two IDA / 56930 Post Request for Bids Open - National 323,710.10 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 (2.12 km) and road from Envelope Herikudru school to NH (0.82 km), Anagalli in Kundapura taluk, Udupi IN-DRM-KAR-1948-CW-RFB / Package 3: Construction and improvements of Hejamadi-Kodi Fisheries Single Stage - Two IDA / 56930 Post Request for Bids Open - National 180,859.27 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Road and Construction and Envelope improvements of Tenka Yermal Fisheries Road in Udupi taluk IN-DRM-KAR-1950-CW-RFB / Package 6:Construction and improvement of Thekkatte to Kome fisheries road Single Stage - Two IDA / 56930 Post Request for Bids Open - National 449,075.60 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 (2.10 Km); Beejadi fisheries Envelope road (2.15 Km) Kundapura Taluk, Udupi Total Length- 4.25 km IN-DRM-KAR-1951-CW-RFB / Package 7: Construction and improvements Road from Gangolli light house to Trasi Gangolli Main road; Single Stage - Two Bengeri Naga temple to IDA / 56930 Post Request for Bids Open - National 444,502.66 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope Trasi Gangolli Main road; Uppunda Madical Alvekodi fisheries road; Koderi fisheries road, Kundapura taluk, Udupi District Page 1 IN-DRM-KAR-1952-CW-RFB / Package 8:Construction and improvements Road from Yedthare Paduvari customs Single Stage - Two to NH 66; Road from IDA / 56930 Post Request for Bids Open - National 523,024.09 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope Yedthare Market road; Road from NH 66 to Shirur under bridge approach road, Kundapura, Udupi District IN-DRM-KAR-1953-CW-RFB / Package 9: Construction and improvements Shirur Single Stage - Two IDA / 56930 Post Request for Bids Open - National 601,095.91 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Alvegadde fisheries road ; Envelope Yedthare to Paduvari Someshwara road IN-DRM-KAR-1992-CW-RFB / Package 12:Construction of Multipurpose cyclone shelter Under Single Stage - Two near Zilla Panchayath IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Envelope Higher Primary School, on Hosabettu in Mangalore Taluk IN-DRM-KAR-1996-CW-RFB / Package 13: Construction and improvements to Mukka- Single Stage - Two Sashihithlu road from Km. IDA / 56930 Post Request for Bids Open - National 669,363.80 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope 0.00 to 5.50 Km. in Mangalore Taluk, Dakshina Kannada District IN-DRM-KAR-1998-CW-RFB / Package 14:Improvements to road from Chitrapura Under Single Stage - Two River side towards East IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope Upto NH, Mulki Town in on Mangalore Taluk, Dakshina Kannada District. IN-DRM-KAR-2000-CW-RFB / Package 15:Construction and improvements of KFDC Hoige Bazaar 3rd stage to Under Fisheries Jetty road and Single Stage - Two IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 road from Hoige Bazaar to Envelope on Railway gate to Marigudi Temple, Bolar Leewel Feery Road in Mangalore Taluk, Dakshina Kannada District IN-DRM-KAR-2001-CW-RFB / Package 16: Construction and improvements to road Under Single Stage - Two from Someshwara Temple IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope sea shore to Thokkottu in on Mangalore Taluk, Dakshina Kannada District. (3 km) IN-DRM-KAR-2019-CW-RFB / Package 17: Construction and improvements to road Under Single Stage - Two from Ullala Beach, Ullal IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope Dargha via to Thokkottu in on Mangalore Taluk, Dakshina Kannada District. Page 2 IN-DRM-KAR-2020-CW-RFB / Package 18:Construction of Multipurpose Cyclone Shelter Single Stage - Two IDA / 56930 Post Request for Bids Open - National 447,036.42 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 at Chittakula village, Envelope Chittakula GP Karwar Taluk, Uttara Kannada IN-DRM-KAR-2092-CW-RFB / Package 19: Construction of Multipurpose Cyclone Single Stage - Two IDA / 56930 Post Request for Bids Open - National 498,579.73 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shelter at Amadalli Village, Envelope Amadalli GP, Karwar Taluk, Uttara Kannada IN-DRM-KAR-2093-CW-RFB / Package 20: Construction of Multipurpose Cyclone Single Stage - Two IDA / 56930 Post Request for Bids Open - National 363,131.39 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shelter at Pujgeri Gram Envelope Panchyat Shetgeri, Ankola, Uttara Kannada IN-DRM-KAR-2094-CW-RFB / Package 21: Construction of Multipurpose Cyclone Single Stage - Two IDA / 56930 Post Request for Bids Open - National 348,640.48 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shelter at Govt. HPS, Envelope Kharviwada Belekeri GP, Ankola, Uttara Kannada IN-DRM-KAR-2095-CW-RFB / Package 22: Construction Single Stage - Two of Multipurpose Cyclone IDA / 56930 Post Request for Bids Open - National 362,216.55 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Envelope Shelter at Manaki, Kumta, Uttara Kannada District IN-DRM-KAR-2096-CW-RFB / Package 23: Construction of Multipurpose Cyclone Single Stage - Two IDA / 56930 Post Request for Bids Open - National 390,288.89 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shelter at Manki High Envelope School, Honnavar, Uttara Kannada District IN-DRM-KAR-2097-CW-RFB / Package 24: Construction of Multipurpose Cyclone Single Stage - Two IDA / 56930 Post Request for Bids Open - National 355,130.93 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2019-10-02 Shelter at Shirali Village Envelope (Tattlihakkal), Shirali GP, Bhatkal, Uttara Kannada IN-DRM-KAR-2099-CW-RFB / Package 25: Improvements to Manki Banasale to Single Stage - Two IDA / 56930 Post Request for Bids Open - National 316,588.01 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Halemath Fisheries Link Envelope Road in Honavar Taluka of UK Dist. IN-DRM-KAR-2100-CW-RFB / Package 26: Improvements to Manki Banasale Hosahitlu Single Stage - Two IDA / 56930 Post Request for Bids Open - National 396,486.34 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Doddagunda Talmakki Envelope Fisheries Link Road in Honavar Taluka of UK Dist. IN-DRM-KAR-2101-CW-RFB / Package 27: Improvement Single Stage - Two to Murudeshwar-Tudalli IDA / 56930 Post Request for Bids Open - National 456,768.31 Signed 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Envelope fisheries link road, Bhatkal Taluk Page 3 IN-DRM-KAR-1390-CW-RFB / Package 2: Construction of Multipurpose Cyclone Shelter Single Stage - Two at Govt. Higher Primary IDA / 56930 Post Request for Bids Open - National 370,182.63 Signed 2016-10-30 2016-11-04 2016-12-16 2017-02-28 2017-04-04 2019-10-04 Envelope Kuvempu School, Thekkatte, Kundapura Taluk, Udupi District INDRMKAR6088CWRFB / Package 29: Construction and improvements to road Under Single Stage - Two from Adamkudru School to IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2017-03-31 2017-04-05 2017-05-17 2017-07-30 2017-09-03 2018-05-31 Envelope Adamkudru Church in on Mangaluru City South Constituency. IN-DRM-KAR-46477-CW- RFB / Construction of MPCS Under Single Stage - Two in Ombhathu Kare at Ullal, IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2018-02-06 2018-02-11 2018-03-25 2018-06-07 2018-07-12 2019-01-08 Envelope Managaluru, Dakshina on Kannada IN-DRM-KAR-1985-CW-RFB / Package 10: Construction Pending of bridge and approach road Single Stage - Two IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2018-07-16 2018-07-21 2018-09-01 2018-11-14 2018-12-19 2020-12-29 Manooru to Nadubettu Envelope on across Boodanagundi River in Udupi taluk IN-DRM-KAR-1986-CW-RFB / Package 11: Construction Pending Single Stage - Two of bridge and approach road IDA / 56930 Post Request for Bids Open - National 0.00 Implementati 2018-07-27 2018-08-01 2018-09-12 2018-11-25 2018-12-30 2020-12-24 Envelope @ Kelageri to Kodi Kanyana on Temple Udupi taluk. IN-DRM-KAR-1949-CW-RFB / Package 4:Construction and improvements to Malpe - Single Stage - Two IDA / 56930 Post Request for Bids Open - National 0.00 Canceled 2016-10-31 2016-11-05 2016-12-17 2017-03-01 2017-04-05 2018-03-05 Tottam - Gujjarabettu Envelope Fisheries Road in Udupi taluk, Udupi District. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DRM-KAR-1184-GO-DIR / Furnishing and renovation IDA / 56930 Post Direct Selection Direct 0.00 Canceled 2016-10-31 2016-11-05 2016-12-10 2017-06-08 of SPIU and Implementing agencies office IN-DRM-KAR-1190-GO-RFQ / Purchase of office Pending Request for Single Stage - One equipment and stationary, IDA / 56930 Post Open - National 0.00 Implementati 2018-07-30 2018-09-24 2019-03-29 Quotations Envelope computers, laptops, etc for on SPIU NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 IN-DRM-KAR-53851-NC- RFQ / Hiring of Vehicles for Pending Request for Single Stage - One Project Director, Project IDA / 56930 Post Open - National 0.00 Implementati 2018-03-21 2018-05-16 2018-11-12 Quotations Envelope Manager and Implementing on Staff IN-DRM-KAR-1196-NC-RFQ Pending Request for Single Stage - One / Hiring of vehicles on IDA / 56930 Post Open - National 0.00 Implementati 2018-07-30 2018-09-24 2019-12-27 Quotations Envelope contract for SPIU officers on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DRM-KAR-1067-CS-CQS / Hiring structural Consultant consultant to assist IDA / 56930 Post Qualification Open - National 0.00 Canceled 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 engineers in designing Selection MPCS IN-DRM-KAR-1068-CS-CQS / Hiring of structural Consultant Under engineering to assist IDA / 56930 Post Qualification Open - National 0.00 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 Implementation engineering with bridge Selection design IN-DRM-KAR-1069-CS-CQS Consultant / Hiring services of Pending IDA / 56930 Post Qualification Open - National 0.00 2016-09-30 2016-10-21 2016-12-04 2017-01-03 2017-02-07 2017-08-06 consultant for assisting Implementation Selection engineers in road design IN-DRM-KAR-274-CS-QCBS / Selection of Consultant for conducting Environmental Quality And Cost- IDA / 56930 Post Open - National 70,760.30 Signed 2016-09-15 2016-10-06 2016-11-19 2016-12-17 2017-01-16 2017-02-20 2017-03-27 2018-03-27 Impact Assessment (EIA) for Based Selection construction of Saline Embankment IN-DRMKAR-343-CS-QCBS / Hiring of THIRD PARTY Quality And Cost- Open - IDA / 56930 Post 378,365.55 Signed 2016-09-29 2016-10-20 2016-12-03 2016-12-31 2017-01-30 2017-03-06 2017-04-10 2018-04-10 QUALITY AUDITOR FOR Based Selection International NCRMP-II in Karnataka IN-DRM-KAR-2594-CS- QCBS / Hiring of internal Quality And Cost- Under auditor to audit finances of IDA / 56930 Post Open - National 0.00 2016-12-31 2017-01-21 2017-03-06 2017-04-03 2017-05-03 2017-06-07 2017-07-12 2019-12-31 Based Selection Implementation SPIU and District implementation unit IN-DRM-KAR-2593-CS- QCBS / Hiring of Consultant Quality And Cost- to assist KSNDMC in IDA / 56930 Post Open - National 0.00 Canceled 2016-11-30 2016-12-21 2017-02-03 2017-03-03 2017-04-02 2017-05-07 2017-06-11 2019-12-11 Based Selection implementing EWDS in three coastal districts INDIVIDUAL CONSULTANTS Page 5