Textual Procurement Plan (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2015]: Revision of decentralized PP by provinces, starting from Jan.2016 until now] 2. Date of General Procurement Notice: July 2016 3. Period covered by this procurement plan: from July 2017 to June 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Risk Rating - High Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 3 million All 2. NCB (Goods) Above US$ 1.5 million All above threshold 3. ICB (Works) Above US$ 20 million All 4. NCB (Works) Above US$ 5 million All above threshold 5. Shopping for Works (below US$ None 200,000) 6. Shopping for Goods (below US$ None 100,000) 7. Non-consulting services Above US$ 1.5 million 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan issued by the CPMU for VN-DRaSIP 5. 6. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 02 NCB works packages may be subject to advance procurement 7. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0 0 No Prior No ICB the ICB Works (Works) contracts expected Summary of 0 0 No N/A the ICB (Goods) Summary of To be No Prior – In the NCB counted on Only for accordan (Works) annual PP Works ce with contracts Bank at High- Procedur risk e for estimated Prior above US$ review 5 million threshold (risk- based) Summary of 0 0 No N/A the NCB (Goods) Summary of 0 0 No N/A the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 0.5 million QCBS, FBS, LCS packages above US$ 500,000 2. Single Source (Firms) Above US$ 0.5 million SSS 3. Individual Above US$ 200,000 IC 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable]: 06 QCBS packages may be subject to advance procurement and retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 8.000 4 Prior Prior review number of of QCBS contracts that contracts will be let above 0.5 under QCBS million per each Summary of 0.715 3 Post CQS number of contracts that will be let under other methods for firms Summary of 1.732 9 Prior/Po Prior review number of st of IC contracts contracts with above 0.2 Individual million per Consultants each PROCUREMENT Vietnam : Vietnam Dam Rehabilitation and Safety Improvement Project PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2017-01-09 2018-11-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152309 GPN Date: Project Name: Vietnam Dam Rehabilitation and Safety Improvement Project Loan / Credit No: IDA / 57490 Executing Agency(ies): Central Project Management Unit for DRSIP, Quang Ngai Province Project Management Unit for DRSIP, Khanh Hoa Province Project Management Unit for DRSIP, Binh Thuan Province Project Management Unit for DRSIP, Binh Dinh Province Project Management Unit of Construction Investment Works for Agriculture and Rural Development, Dak Lak Province Project Management U WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-QN-DL-W1 / The first NCB Works contract for Single Stage - One Dap Lang Reservoir IDA / 57490 Prior Request for Bids Open - National 778,841.23 Signed 2017-01-16 2017-01-23 2017-02-28 2017-04-27 2017-05-18 2018-11-09 Envelope Rehabilitation and Safety Improvement C1-BT-SQ-W-01 / This CW package comprises 03 lots, including: Lot 1: Spillway 2, estimated at USD 3,843,875; Lot 2: Main dam, auxiliary Under Single Stage - One dam, construction road, IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2017-07-31 2017-08-14 2017-09-25 2017-11-24 2017-12-29 2019-12-29 Envelope management house, on estimated at USD 2,937,848; Lot 3: Dan Sach Dam headworks; estimated at USD 986,456. C1-BT-SQ-W-03 / Dan Sach Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Canceled 2017-07-24 2017-08-07 2017-09-18 2017-11-17 2017-12-22 2019-12-22 dam headworks Envelope C1-BD-TB-W1 / Thach Ban Single Stage - One reservoir rehabilitation and IDA / 57490 Prior Request for Bids Open - National 871,955.05 Signed 2017-05-24 2017-06-03 2017-07-18 2017-09-06 2017-10-11 2019-10-01 Envelope safety improvement. C1-LD-DT-W1 / Da Teh Dam Rehabilition and Safety Under Single Stage - One improverment (The first IDA / 57490 Prior Request for Bids Open - National 3,027,071.09 Implementati 2017-05-22 2017-06-07 2017-07-16 2017-09-14 2017-10-05 2019-10-05 Envelope NCB package in Lam Dong on - the first-year province) C1-TQ-NL2-W1 / Ngoi La 2 Single Stage - One reservoir Rehabilitation and IDA / 57490 Prior Request for Bids Open - National 1,518,551.66 Signed 2017-03-15 2017-03-28 2017-05-05 2017-06-23 2017-07-14 2019-01-05 Envelope Safety improvement C1-HB-DT-W1 / Dai Thang Reservoir Rehabilitation and Under Single Stage - One Safety Improvement (This is IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2017-02-13 2017-02-20 2017-03-22 2017-05-04 2017-05-25 2019-05-25 Envelope first NCB of the year-1 on subproject) C1-QB-PV-W1 / Rehabilitation and Safely Single Stage - One Improvement of Phu Vinh IDA / 57490 Prior Request for Bids Open - National 0.00 Canceled 2017-02-05 2017-02-10 2017-03-24 2017-05-03 2017-06-07 2019-05-28 Envelope (This is first NCB of the year-1 subproject) C1-QB-GD1-W1 / Rehabilitation and Safely Improvement of Phu Vinh (Include: Build, insurance Single Stage - One IDA / 57490 Prior Request for Bids Open - National 2,876,323.72 Signed 2017-04-20 2017-05-10 2017-06-21 2017-07-31 2017-09-04 2019-08-25 works and Supply and Envelope installation of SCADA) - This is first NCB of the year-1 subproject C1-QB-GD2-W2 / Rehabilitation and Safely Pending Single Stage - One Improvement of Thanh Son IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Envelope and Vung Mo and Dap on Lang (Phase 2) C1-QB-GD2-W3 / Pending Rehabilitation and Safely Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Improvement of Long Dai Envelope on and Dong Suon (Phase 2) C1-QB-GD2-W4 / Rehabilitation and Safely Pending Improvement of Thach Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-08-10 2018-08-25 2018-10-06 2018-11-15 2018-12-20 2020-12-09 Truong and Dong Vat and Envelope on Cay Bom and Buoi Roi (Phase 2) Page 1 C2-MONRE-CW1 / Construction of water Pending resources, hydro and Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-01 2018-04-11 2018-05-11 2018-07-08 2018-07-22 2019-06-30 meteorology monitoring Envelope on stations in the Ca and Vu Gia - Thu Bon river basin C1-DAKNONG-W2 / Civil works: Repair 9 lakes, inclu ding 2 lots: Lot 1: 2 lakes i Pending n Đắk R'lấp and Tuy Đức d Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-30 2018-05-15 2018-06-25 2018-08-20 2018-09-10 2020-03-03 istricts, estimated amount U Envelope on S$ 1,089,000. Lot 2: 7 lakes in Đắk Glong district, estim ated amount US$ 3,267,000. C1-QN-KC-W1 / Khe Che Pending Single Stage - One reservoir rehabilitation and IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-02-27 2018-03-16 2018-04-20 2018-06-22 2018-07-13 2019-05-09 Envelope safety improvement on C1-TH-DB-W1 / The first n cb work contract for Rehabil Single Stage - One IDA / 57490 Post Request for Bids Open - National 1,456,677.47 Signed 2017-09-25 2017-09-30 2017-10-30 2017-11-19 2017-12-15 2019-06-08 itation and Safety Improvem Envelope ent of Đồng Bể Dam. C1-PT-B-W1 / Repairs and safety upgrades reservoirs Ban and Insurance of Single Stage - One Under IDA / 57490 Prior Request for Bids Open - National 483,496.90 2017-06-08 2017-06-18 2017-08-17 2017-10-26 2017-11-23 2019-05-02 works. (The first NCB Envelope Review package in Phu Tho - the first-year province). C1-DAKNONG-W1 / Civil works: Repair 9 lakes, Inclu ding 2 plots: Lot 1: 6 lakes in Đắk Mil district, estimate Pending d amount US$ 2,719,200, Lo Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-04-27 2018-05-11 2018-06-15 2018-08-14 2018-09-04 2020-02-26 t 2: 3 lakes in Đắk Song di Envelope on strict, estimated amount US $ 1,812,800 (the first NCB c ontract of first-year subproje ct) C1-GL-W2 / Repair 3 reser voirs, including 03 lots: Lot 1: Buôn Lưới Reservoir, esti mated cost US$ 493,000, Lot Pending Single Stage - One 2: Plei Tô Kôn Reservoir, e IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-31 2019-05-05 2019-07-04 2019-07-25 2020-07-19 Envelope stimated cost US$ 309,000, on Lot 3: Ia Năng and Làng M e Reservoir, estimated cost US$ 635,000 C1-GL-W1 / Repair 4 reser voirs, including 04 lots:Lot 1 :Iaring,estimated cost US$1,3 70,000,Lot 2:Ayun Hạ,estima Pending ted cost US$ 850,000,Lot 3: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-31 2019-05-05 2019-07-04 2019-07-25 2020-07-19 Ea Dreh,estimated cost US$ Envelope on 210,000,Lot 4:Hà Tam, estim ated cost US$ 449,000 (The first NCB contract of first-ye ar subproject) C1-NA-KG-W1 / The package includes 02 lots: Lot 1: Rehabilitation and upgrading Khe Gang Under Single Stage - One Reservoir. Lot 2: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2017-12-26 2017-12-30 2018-01-30 2018-03-01 2018-03-22 2019-09-13 Envelope Rehabilitation and upgrading on Khe San Reservoir. The lots include work, equipment, insurance and general items. C1-LANGSON-W2 / Construction of 5 reservoirs: Pending Single Stage - One Bo Chuong, Tham Sinh, IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2020-03-18 2020-03-30 2020-05-04 2020-07-03 2020-08-06 2022-01-28 Envelope Khau Pieu, Khuoi Man, Coc on Lung C1-LANGSON-W1 / Pending Construction of 5 reservoirs: Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-22 2019-04-03 2019-05-08 2019-07-10 2019-08-15 2021-02-05 Ban Cuom, Ba Son, Ky Na, Envelope on Khuon Pinh, Phai Luong C1-SONLA-W1 / Civil work package - Rehabilitation and Under safety improvement of Bản Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2018-09-25 2018-10-10 2018-11-14 2019-01-03 2019-02-07 2020-06-01 Ỏ, Noong Chạy, Huổi Nhả - Envelope on Khơ Mú, Xa Căn, Xum Lo, Bản Củ, Nà Bó Reservoirs Page 2 C1-LAMDONG-W1 / Constr uction of 8 reservoirs: inter Pending -reservoir Suối Đỉa - Cây X Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2019-08-20 2019-09-03 2019-10-08 2019-12-10 2020-01-15 2022-01-14 oài, Đạ Sa, R'Lôm, Ma Poh, Envelope on Thanh Bạch, Hồ Số 4, Lộc Thắng, Đạ Bo B C1-QN-GD1-W3 / Repair and improve the safety of Pending 04 water reservoirs. Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-20 2019-01-25 2019-02-24 2019-03-21 2019-04-02 2020-09-23 Including 02 lots: Lot 1: Envelope on Hoc Khe, Ho Hieu. Lot 2: An Phong, Hoc Co C1-QN-GD1-W2 / Repair Pending and improve the safety of Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-11-12 2018-11-17 2018-12-17 2019-01-11 2019-01-23 2020-07-16 02 water reservoirs: Liet Envelope on Son, Cay Khe C1-QN-GD1-W1 / Repair and improve the safety of Pending 04 water reservoirs. Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-09 2018-10-14 2018-11-13 2018-12-08 2018-12-20 2020-06-12 Including 02 lots: Lot 1: Go Envelope on Lang, Hoc Bua. Lot 2: Lien Tri, Ho Da C1-QN-W1 / Rehabilitation and safety improvement of 0 6 reservoirs, divided into 03 Pending lots, including: Lot 1: Đập Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-05 2018-11-05 2018-12-17 2018-12-28 2020-12-27 Đá and Hố Lau reservoirs, Envelope on Lot 2: Hóc Két and Hóc Bầ u reservoirs, Lot 3: Đồng N hơn and Hố Mây reservoirs. C1-QUANGTRI-W1 / Pending Rehabilitation and Safely Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-14 2019-01-29 2019-03-11 2019-05-10 2019-05-31 2020-11-21 Improvement of Kinh Mon Envelope on and Dap Hoi Reservoirs C1-QUANGTRI-W3 / Rehabilitation and Safely Pending Improvement of Khe Muong Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-11-11 2019-11-26 2019-12-31 2020-02-24 2020-03-16 2021-09-07 and Km6 and Da Cua and Envelope on Khom 7 and Tan Vinh Reservoirs C1-QUANGTRI-W2 / Rehabilitation and Safely Pending Improvement of Duc Duc Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-14 2019-05-23 2019-06-27 2019-08-21 2019-09-11 2021-03-04 and Khe Na and Khom 2 Envelope on and Co Kieng 2 and Tram Reservoirs C1-BT-TDA2-W-01 / Rehabil itation and Safety Improvem ent for 06 reservoirs, includi Pending ng 03 lots: Lot 1: Đá Bạc, Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2020-03-05 2020-03-10 2020-04-16 2020-06-12 2020-07-17 2021-07-17 Cẩm Hang and Hộc Tám Envelope on Reservoirs, Lot 2: Tà Mon a nd Tân Lập Reservoirs, Lot 3: Trà Tân Reservoir C1-KHANH HOA-W1 / Reh abilitation and Safety Impro vement for 04 reservoirs, div Pending Single Stage - One ided into 02 lots, icluding: L IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-12-14 2018-12-19 2019-01-23 2019-03-20 2019-04-03 2020-09-24 Envelope ot 1: Láng Nhớt and Cây s on ung reservoirs, Lot 2: Đồng Bò and Đá Mài reservoirs C1-HB-GD2-W1 / Rehabilita tion and safety improvement of 5 reservoirs, divided into Pending Single Stage - One 2 lots, including: Lot 1: Đồn IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-26 2018-10-29 2018-11-28 2018-12-12 2018-12-18 2020-08-19 Envelope g Bến, Rả and Rộc Kháo on reservoirs, Lot 2: Mền 1, M ền 2 reservoirs. C1-VINHPHUC-W1 / Rehab ilitation and safety improve ment of 8 reservoirs, divided into 3 lot, including: Lot 1: Pending Single Stage - One Bò Lạc reservoir, Lot 2: Su IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-07-13 2018-07-16 2018-08-20 2018-09-19 2018-10-10 2020-04-10 Envelope ối Sải, Đá Ngang and Khuô on n reservoirs, Lot 3: Rừng V àu, Đá Bạc 2, Đồng Mồ an d Đa Mang reservoirs. Page 3 C1-VINHPHUC-W2 / Rehab ilitation and safety improve ment of 3 reservoirs, divided into 3 lots, including: Lot 1: Pending Single Stage - One Vĩnh Thành reservoir, Lot 2: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-07-13 2018-07-16 2018-08-20 2018-09-19 2018-10-10 2020-04-10 Envelope Tân Bình and Trại Trâu res on ervoirs, Lot 3: Treatment of termite for reservoirs under subproject. C1-TTH-W1 / Rehabilitation and safety improvement of Pending 03 reservoirs Including 02 Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-11-14 2018-11-21 2018-12-21 2019-01-28 2019-02-18 2020-08-11 lots: Lot 1: Phu Bai 2 Envelope on reservoir-Lot 2: Phu Nu and Cay Coi reservoir C1-TTH-W2 / Rehabilitation and safety improvement of 06 reservoirs Including 03 Pending lots: Lot 1: Cua and Khe Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-15 2019-05-27 2019-07-01 2019-08-19 2019-09-09 2021-03-02 Rung reservoir-Lot 2: Ka Tu Envelope on and Ta Rinh reservoir-Lot 3: Nam Lang and Ba Cua reservoir C1-YB-W1 / Construction 5 of reservoirs, divided into 2 Pending lots, including: Lot 01: Tu Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-23 2018-10-26 2018-11-26 2018-12-21 2018-12-27 2020-06-27 Do, Chop Du reservoirs - Envelope on Lot 02: Goc Nhoi, Khe Hoai, Hang Luon reservoirs C1-YB-W2 / Construction 5 of reservoirs, divided into 2 lots, including: Lot 01: Nong Pending Single Stage - One truong nghia lo, thon 26-3 IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-04 2019-01-22 2019-02-22 2019-03-29 2019-04-04 2020-10-03 Envelope reservoirs - Lot 02: Lang on At, Khe Hop, Khe Ngang reservoirs C1-YB-W3 / Construction 6 of reservoirs, divided into 3 lots, including: Lot 01: Khe Pending Dua, Khe Vai reservoirs - Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-02-22 2019-03-11 2019-04-11 2019-05-21 2019-05-31 2020-11-29 Lot 02: Khe Chinh, Phu Envelope on Nham reservoir - Lot 03: Tang An, Roong Đen reservoirs C1-BD-GD2-W1 / Under Construction of 03 reservoirs Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-21 2018-12-10 2019-02-08 2019-03-15 2021-03-04 Cu Le, Lo Mon and Ho Envelope on Cung C1-BD-GD2-W2 / Construction of 05 reservoirs Pending (Including 2 lot: Lot 01: Hoc Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-01-03 2019-01-23 2019-03-14 2019-05-13 2019-06-17 2021-06-06 Tranh, Kim Son and My Envelope on Duc, lot 02: Da Ban, Giao Hoi) C1-BD-GD2-W3 / Construction of 05 reservoirs (Including 2 lot: Lot 01: An Pending Single Stage - One Tuong, Nui Mieu and IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-09-27 2019-10-17 2019-12-06 2020-02-04 2020-03-10 2022-02-28 Envelope monitoring equipment, lot on 02: Trinh Van, Suoi Run and Hung Long) C1-LC-W1 / Rehabilitation and safety improvement of 6 reservoirs, divided into 2 Pending lots, including: Lot 1: Ta Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-18 2018-10-23 2018-11-22 2018-12-06 2018-12-14 2019-12-09 Xin, Phong Niên and Pho Envelope on rang reservoirs, Lot 2: Phu Nhuan, Sung Lang and Tan An reservoirs. C1-KONTUM-W1 / Rehabili tation and safety improveme Pending nt of 04 reservoirs including Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-03-29 2019-04-08 2019-05-13 2019-07-02 2019-07-23 2021-12-29 Lot 1: Đăk Hơ Niêng, Đăk Envelope on Tin reservoir- Lot 2: Kon T u Zốp, Thôn 9 reservoir. C1-KONTUM-W2 / Rehabili tation and safety improveme nt of 04 reservoirs and cons truction of new 04 managem Pending Single Stage - One ent house including Lot 1: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-04-29 2019-05-13 2019-06-17 2019-08-12 2019-09-16 2021-09-15 Envelope Ya Xăng, Đăk Ngót reservoi on r- Lot 2: Đội 5, Cà Sâm re servoir- Lot 3: 04 Manageme nt house Page 4 C1-KHANH HOA-W2 / Reh abilitation and Safety Impro vement for 04 reservoirs, div Pending ided into 02 lots, icluding: L Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2019-02-21 2019-02-26 2019-04-02 2019-05-28 2019-06-11 2020-12-02 ot 1: Suối Trầu and Bến G Envelope on he reservoirs, Lot 2: Suối L uồng and Suối Lớn reservoi rs C1-KONTUM-W3 / Rehabili tation and safety improveme nt of 06 reservoirs including Pending Single Stage - One Lot 1: C2, A1 đội 4 reservoi IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-20 2019-06-03 2019-07-08 2019-09-06 2019-10-11 2021-10-15 Envelope r- Lot 2: C3, C4 reservoir- on Lot 3: C3 (704), Ia Bang Th ượng reservoir. C1-QN-TDAGD2-W1 / Repair and improve the Pending safety of 03 water Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2020-04-11 2020-04-16 2020-05-16 2020-06-10 2020-06-22 2021-12-14 reservoirs. Including 02 lots: Envelope on Lot 1: Ong Tho, Hoc Cay. Lot 2: Son Rai C1-QN-TDAGD2-W2 / Repair and improve the safety of 05 water Pending Single Stage - One reservoirs. Including 02 lots: IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2020-04-26 2020-05-01 2020-05-31 2020-06-25 2020-07-07 2021-12-29 Envelope Lot 1: Hoc Mua, Pho Tinh, on Tuyen Tung. Lot 2: Gia Hoi, Ho Vang. C1-QN-TDA2-W2 / Construction of 8 reservoirs: Pending Sau Lang, Roc Cung, Da Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2018-11-15 2018-11-26 2018-12-26 2019-01-11 2019-01-31 2020-06-14 Trang, Roc Chay, Dong Do Envelope on 1, Quat Dong, Chuc Bai Son, Khe Tau C1-DL-TDAI-W1 / Rehabilit ation and safety improvemen t of 03 reservoirs in sub-pro Pending Single Stage - One ject 1 including Lot 1: Ea U IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-14 2019-05-24 2019-07-02 2019-08-27 2019-09-30 2021-03-23 Envelope y thượng reservoir- Lô 2: Đ on ội 11, Buôn Dung II reservo ir. C1-DL-TDAI-W2 / Rehabilit ation and safety improvemen t of 07 reservoirs in sub-pro ject 1 including lot1: 725 , Pending Single Stage - One C19 reservoir - Lot 2: Ea B IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-05-31 2019-06-10 2019-07-15 2019-09-09 2019-10-14 2021-04-06 Envelope long Thượng, Ea Kmiên 3 r on eservoir -Lot 3: Ea Nao Dar , Ea Ngách, Ea Brơ 2 reser voir C1-THAINGUYEN-W1 / C1- THAINGUYEN-W1 Construction of 06 reservoirs - Lot 1: Suoi Lanh, Ghenh Pending Che (Estimate: 786,667 US$) Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-08-01 2019-08-06 2019-09-10 2019-10-30 2019-11-13 2020-11-12 - Lot 2: Na Tac, Khuon Envelope on Nanh (Estimate: 1,137,778 US$) - Lot 3: Ho Chuoi, Na Khao (Estimate: 1,142,222 US$) C2-THAINGUYEN-W2 / Construction of 04 reservoirs - Lot 1: Dam Chieu, Ben Pending Single Stage - One Dong (Estimate: 404,444 IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2019-11-14 2019-11-19 2019-12-24 2020-01-23 2020-02-06 2021-02-05 Envelope US$) on - Lot 2: Nui Che, Ho Coc (Estimate: 564,445 US$) C1-DL-TDAI-W3 / Pending Treatment of termite for Request for Single Stage - One IDA / 57490 Post Open - National 0.00 Implementati 2019-04-30 2019-07-29 2019-10-27 construction work under sub- Quotations Envelope on project I C3-THAINGUYEN-W3 / Termite treatment (Dam Pending Request for Single Stage - One Chieu, Ben Dong, Nui Che, IDA / 57490 Post Open - National 0.00 Implementati 2019-07-15 2019-09-12 2019-11-11 Quotations Envelope Ho Coc, Suoi Lanh, Ghenh on Che, Khuon Nanh reservoir) C1-HAGIANG-W2 / Rehabilitation and safety Pending improvement of 4 reservoirs Single Stage - One IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2020-01-02 2020-01-16 2020-02-20 2020-04-23 2020-05-19 2021-11-15 - Lot 1: Khuoi Pha, Tan Envelope on Bang - Lot 2: Coc Bo, Na Pong Page 5 C1-HAGIANG-W1 / Rehabili tation and safety improveme nt of 10 reservoirs - Lot 1: Nam Vac, Thom L Pending uong, Thon Thia reservoirs Single Stage - One IDA / 57490 Prior Request for Bids Open - National 0.00 Implementati 2019-09-11 2019-09-24 2019-10-29 2019-12-31 2020-01-24 2022-01-28 - Lot 2: Na Tam, Thon Lai Envelope on , Thong Nhat, Thom Ta res ervoirs - Lot 3: Đội 1, Đoi 2, Trun g reservoir GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-QB-PV-G2 / Supply and Request for Single Stage - One IDA / 57490 Post Open - National 0.00 Canceled 2018-05-20 2018-07-15 2019-07-10 Installation of SCADA Quotations Envelope C2-MONRE-GO2 / Procurement of equipments Pending Single Stage - One for monitoring rainfall in IDA / 57490 Post Request for Bids Open - National 0.00 Implementati 2018-10-01 2018-10-11 2018-11-10 2018-12-31 2019-01-14 2019-12-31 Envelope the Ca and Vu Gia - Thu on Bon river basin C2-MONRE-GO1 / Procurement of equipments Pending for monitoring water level, Open - Single Stage - One IDA / 57490 Prior Request for Bids 0.00 Implementati 2018-10-01 2018-10-11 2018-11-25 2019-01-15 2019-01-29 2020-01-15 water discharge and water International Envelope on quality in the Ca and Vu Gia - Thu Bon river basin NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Consultant C2-MARD-CS1 / Support Pending IDA / 57490 Post Qualification Open - National 0.00 2017-03-01 2017-03-22 2017-05-18 2017-08-03 2017-08-24 2018-06-24 for database development Implementation Selection C2-MARD-CS2 / Improving Consultant Pending the legal framework for dam IDA / 57490 Post Qualification Open - National 0.00 2017-03-01 2017-03-22 2017-05-18 2017-08-03 2017-08-24 2018-06-24 Implementation safety management Selection C3-CPMU-CS1 / Project Quality And Cost- Open - Implementation Consultant IDA / 57490 Prior 0.00 Under Review 2016-10-30 2016-11-13 2016-12-11 2017-01-08 2017-02-14 2017-03-23 2017-04-13 2022-06-30 Based Selection International (PIC) C1-QN-DL-CS1 / Consultant construction supervision IDA / 57490 Post Qualification Open - National 13,838.40 Signed 2016-12-27 2017-01-16 2017-03-16 2017-04-27 2017-05-18 2018-11-09 consultants Selection C1-KHANH HOA-CS1 / Consultant Environmental and Social IDA / 57490 Prior Qualification Open - National 96,113.19 Signed 2016-12-14 2016-12-29 2017-04-04 2017-06-01 2017-06-16 2017-08-30 Safeguard Reports Preparing Selection Consutant. C1-BT-SQ-CS-01 / Consulting services for Consultant Under investigations, construction IDA / 57490 Post Qualification Open - National 0.00 2016-12-14 2016-12-28 2017-03-16 2017-05-05 2017-05-26 2017-08-14 Implementation drawing design and cost Selection estimate C3-CPMU-CS3 / Audit of Consultant Under financial statements for the IDA / 57490 Post Qualification Open - National 0.00 2017-02-20 2017-03-13 2017-05-29 2017-07-25 2017-08-15 2022-06-30 Implementation first 3 years Selection C1-CPMU-CS1 / Quality And Cost- Open - International Monitoring and IDA / 57490 Prior 1,313,712.92 Signed 2016-12-30 2017-01-13 2017-02-10 2017-04-07 2017-05-29 2017-07-05 2017-07-26 2022-06-30 Based Selection International Evaluation (M&E) consultant Page 6 C3-CPMU-CS2 / Third party Independent Quality And Cost- Open - IDA / 57490 Prior 1,366,673.00 Signed 2016-12-23 2017-01-06 2017-02-03 2017-03-03 2017-04-17 2017-05-24 2017-06-14 2022-06-30 Supervision and Internal Based Selection International audit Consultant (ISC) C1-DL-TDA1-CS1 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 0.00 Canceled 2016-12-19 2017-01-03 2017-03-22 2017-05-09 2017-05-30 2017-11-26 Safeguard Reports Preparing Selection Consultant C1-BD-GD2-CS1 / Consultant feasibility study report and dam safety Quality And Cost- report year - 2 of Binh IDA / 57490 Post Open - National 289,509.05 Completed 2017-01-16 2017-03-07 2017-05-16 2017-06-20 2017-07-25 2017-09-06 2017-10-26 2018-04-24 Based Selection Dinh province Dam rehabilitation and safety improvement project C1-LD-DT-CS1 / Consultant Construction Supervision and Under IDA / 57490 Post Qualification Open - National 0.00 2017-04-28 2017-05-12 2017-08-10 2017-09-11 2017-10-02 2019-10-05 Preparation of Emergency Implementation Selection Preparedness Plan (EPP) C1-QN-GD1-CS1 / Consultant Consultancy service for IDA / 57490 Post Qualification Open - National 263,745.09 Signed 2017-02-15 2017-03-08 2017-05-05 2017-06-16 2017-07-07 2018-01-03 preparation of feasibility Selection study and dam safety report C1-QN-GD1-CS3 / Report on environmental Iimpact Consultant assessment, environmental IDA / 57490 Post Qualification Open - National 111,443.87 Signed 2017-02-15 2017-03-08 2017-05-03 2017-06-02 2017-06-23 2017-11-20 and social impact Selection assessment, resettlement action plan C1-GL-CS1 / Consultant for Consultant Under developing feasibility study IDA / 57490 Post Qualification Open - National 0.00 2017-07-13 2017-07-27 2017-10-25 2017-11-24 2017-12-22 2018-03-22 Implementation and dam safety report Selection C1-GL-CS2 / Consultant for Consultant developing social and Under IDA / 57490 Post Qualification Open - National 0.00 2017-07-13 2017-07-27 2017-10-25 2017-11-24 2017-12-22 2018-03-22 environmental safeguards Implementation Selection reports C1-QN-CS1 / Consultant Consultant for developing feasibility IDA / 57490 Post Qualification Open - National 278,369.28 Signed 2017-02-28 2017-03-14 2017-06-12 2017-07-14 2017-08-04 2017-12-02 study and dam safety report Selection C1-QN-CS2 / Consultant Consultant for developing social and IDA / 57490 Post Qualification Open - National 85,685.42 Signed 2017-02-28 2017-03-14 2017-06-12 2017-07-14 2017-08-04 2017-12-02 environmental safeguards Selection C1-LC-CS1 / Consultant for Consultant developing feasibility study IDA / 57490 Post Qualification Open - National 112,895.02 Signed 2017-02-21 2017-03-01 2017-05-29 2017-06-30 2017-07-21 2017-09-20 and dam safety report Selection C1-LC-CS2 / Consultant for Consultant developing safeguards IDA / 57490 Post Qualification Open - National 51,513.93 Signed 2017-02-21 2017-03-01 2017-05-29 2017-06-30 2017-07-21 2017-09-20 reports Selection C1-KONTUM-CS1 / Consultant Feasibility Study and Dam IDA / 57490 Post Qualification Open - National 228,754.84 Signed 2017-02-14 2017-02-28 2017-05-19 2017-06-19 2017-07-10 2017-11-07 Safety Report Preparing Selection Consultant C1-HB-GD2-CS1 / Consultant Consultant for developing Under IDA / 57490 Post Qualification Open - National 0.00 2017-05-18 2017-06-02 2017-09-08 2017-10-13 2017-11-03 2018-04-05 feasibility Study and Dam Implementation Selection Safety Reports - Phase 2 C1-HB-GD2-CS2 / Consultant Consultant for developing Pending IDA / 57490 Post Qualification Open - National 0.00 2017-05-18 2017-06-02 2017-09-08 2017-10-13 2017-11-03 2018-04-05 environmental and Social Implementation Selection Safeguard Report - Phase 2 C1-BG-CS1 / Consultant for Consultant Pending developing feasibility study IDA / 57490 Post Qualification Open - National 0.00 2017-11-30 2017-12-30 2018-03-15 2018-04-16 2018-05-09 2018-08-07 Implementation and dam safety report Selection C1-BG-CS2 / Consultant for Consultant developing social and Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-30 2017-12-30 2018-03-15 2018-04-16 2018-05-09 2018-08-07 environmental safeguards Implementation Selection reports Page 7 C1-QB-PV-CS4 / Consultant for developing feasibility Consultant study and dam safety report IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-27 2017-03-20 2017-05-03 2017-06-02 2017-07-07 2017-10-05 of subproject: Improvement Selection of Dam safety in Quang Binh Province (Phase 2) C1-QB-PV-CS03 / Consultant Consultant for Emergency IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-04-15 2017-05-06 2017-06-19 2017-07-19 2017-08-23 2018-02-19 Preparedness Plan of Phu Selection Vinh (EPP) C1-QB-GD2-CS1 / Consultant services for Feasible Study report Consultant establishment on Dam safety IDA / 57490 Post Qualification Open - National 224,988.94 Signed 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2017-12-16 of subproject: Improvement Selection of Dam safety in Quang Binh province (Phase 2) C1-QB-GD2-CS2 / Environmental and Social Safeguard Reports Preparing Consultant Consultant of subproject: IDA / 57490 Post Qualification Open - National 96,508.20 Signed 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2017-12-16 Improvement of Dam safety Selection in Quang Binh province (Phase 2) C2-MONRE-CS4 / Development of real-time Consultant Pending multi-reservoir operation IDA / 57490 Post Qualification Open - National 0.00 2018-07-01 2018-07-29 2018-09-02 2018-09-09 2018-09-23 2020-12-31 Implementation scenarios in the Ca and Vu Selection Gia - Thu Bon river basin Consultant C2-MONRE-CS1 / Survey Under IDA / 57490 Post Qualification Open - National 0.00 2017-05-25 2017-06-08 2017-07-13 2017-08-03 2017-08-17 2018-03-31 and design for construction Implementation Selection C2-MONRE-CS3 / Development of database, hydrology and hydraulic models to serve for the Quality And Cost- Pending IDA / 57490 Post Open - National 0.00 2018-10-01 2018-10-15 2018-11-26 2018-12-03 2018-12-17 2019-01-07 2019-01-21 2020-12-31 management of the multi- Based Selection Implementation reservoir operation in the Ca and Vu Gia- Thu Bon river basin C2-MONRE-CS2 / Development of maps on Quality And Cost- Pending river bed topography in the IDA / 57490 Prior Open - National 0.00 2017-06-15 2017-06-29 2017-08-10 2017-08-17 2017-08-31 2017-09-21 2017-10-05 2020-12-31 Based Selection Implementation Ca and Vu Gia - Thu Bon river basin C1-PT-CS3 / Consultant services for Feasible Study report establishment on Consultant Under Dam safety of subproject: IDA / 57490 Post Qualification Open - National 0.00 2017-05-25 2017-06-08 2017-09-26 2017-10-26 2017-11-23 2018-02-21 Implementation Improvement of Dam safety Selection in Phu Tho Province (Phase 2) C1-PT-CS2 / Consultant services on report establishment on social Consultant environmental safety IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-20 2017-03-06 2017-06-24 2017-07-24 2017-08-21 2017-11-19 policies of subproject: Selection Improvement of Dam safety in Phu Tho Province (Phase 2) C1-QUANGTRI-CS2 / Consultant Preparation of environmental IDA / 57490 Post Qualification Open - National 168,701.91 Completed 2017-04-10 2017-06-06 2017-08-23 2017-10-03 2017-10-17 2018-01-25 and social safeguards Selection instruments. C1-QB-CS3 / Consultant engineering design (phase 2) and Planning for Emergency Quality And Cost- Preparedness (EPP) of the IDA / 57490 Post Open - National 0.00 Canceled 2018-01-25 2018-02-15 2018-03-31 2018-04-28 2018-05-28 2018-07-02 2018-08-06 2018-11-04 Based Selection subproject: Improving Dam Safety in Quang Binh Province C1-DAKNONG-CS1 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 85,726.96 Signed 2017-05-31 2017-06-14 2017-09-13 2017-10-13 2017-11-10 2018-02-08 Safeguard Reports Preparing Selection Consutant C1-DAKNONG-CS2 / Consultant Consulting services for IDA / 57490 Post Qualification Open - National 234,291.49 Signed 2017-05-30 2017-06-13 2017-09-15 2017-10-17 2017-11-14 2018-02-12 survey, construction drawing Selection design and cost estimate Page 8 C1-TTH-CS1 / Consultant Consultant for developing feasibility IDA / 57490 Post Qualification Open - National 158,736.46 Signed 2017-05-04 2017-05-18 2017-08-17 2017-09-18 2017-10-23 2018-01-31 study and dam safety report Selection C1-TTH-CS2 / Consultant Consultant for developing social and IDA / 57490 Post Qualification Open - National 69,889.60 Signed 2017-05-30 2017-06-13 2017-09-12 2017-10-13 2017-11-17 2018-02-15 environmental safeguards Selection C1-PHUYEN-CS1 / Consultant Feasibility Study and Dam Under IDA / 57490 Post Qualification Open - National 0.00 2017-04-28 2017-05-25 2017-07-31 2017-08-28 2017-09-12 2017-12-13 Safety Reports Preparing Implementation Selection Consultant C1-QUANGTRI-CS1 / Consultant Preparation of feasibility IDA / 57490 Post Qualification Open - National 224,309.78 Completed 2017-05-08 2017-06-02 2017-08-19 2017-09-29 2017-10-13 2018-01-21 study and dam safety Selection reports for phase-2 dams. Consultant C1-BD-GD2-CS2 / Tu van IDA / 57490 Post Qualification Open - National 122,666.86 Signed 2017-06-12 2017-07-03 2017-08-16 2017-09-15 2017-10-20 2018-03-19 cac chinh sach an toan Selection C1-PT-B-CS1 / Consulting Consultant supervision for construction IDA / 57490 Post Qualification Open - National 12,785.44 Signed 2017-06-02 2017-06-16 2017-09-29 2017-10-29 2017-11-19 2019-04-15 works and installation of Selection equiment C1-DAKNONG-CS3 / Consultant Under Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2018-03-22 2018-04-05 2018-07-06 2018-08-06 2018-09-03 2020-03-03 Implementation consultant Selection C1-TQ-NL2-CS1 / Consultant Construction supervision and IDA / 57490 Post Qualification Open - National 0.00 Canceled 2017-02-22 2017-03-07 2017-06-05 2017-07-07 2017-07-28 2019-01-19 Preparation of Emergency Selection Preparedness Plan (EPP) C1-TQ-CS3 / Preparation of Emergency Preparedness Plan for 2 Projects (Subproject 1: Ngoi La 2 reservoir, Subproject 2: Consultant Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 194,141.79 Signed 2017-11-30 2017-12-15 2018-03-15 2018-04-16 2018-05-10 2021-03-09 Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) VN-DRSIP MOIT-16496-CS- Consultant LCS / Project audit annually Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 (2017, 2018, 2019, 2020, Implementation Selection 2021) C1-THAINGUYEN-CS1 / Consultant Feasibility Study and Dam Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-19 2017-10-03 2018-01-02 2018-02-06 2018-02-27 2018-04-28 Safety Reports preparing Implementation Selection consultant. C2-THAINGUYEN-CS2 / Consultant Environmental and social Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-19 2017-10-03 2018-01-02 2018-02-06 2018-02-27 2018-04-28 safeguard reports preparing Implementation Selection consultant. VN-DRSIP MOIT-12374-CS- CQS / Consultant service for assessment apply of Consultant standards and regulations IDA / 57490 Post Qualification Open - National 0.00 Canceled 2018-07-02 2018-07-23 2018-09-05 2018-10-05 2018-11-09 2019-05-08 system in design, Selection construction, operation and management of hydropower projects C1-GL-CS3 / Consultant to survey, prepare construction Consultant drawing design and cost Pending IDA / 57490 Post Qualification Open - National 0.00 2018-05-01 2018-05-25 2018-08-25 2018-09-24 2018-10-22 2019-01-20 estimates and Consultant to Implementation Selection prepare Emergency Preparedness Plan (EPP) VN-DRSIP MOIT-18007-CS- QCBS / Improve standards and regulations system for Quality And Cost- Pending IDA / 57490 Prior Open - National 0.00 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 hydropower dams in periods Based Selection Implementation of design, construction, operation and management C1-PHUYEN-CS2 / Consultant Environmental and Social Under IDA / 57490 Post Qualification Open - National 0.00 2017-09-21 2017-10-05 2017-12-23 2018-01-29 2018-02-05 2018-05-06 Safeguard Reports Preparing Implementation Selection Consultant Page 9 C1-TQ-NL2-CS2 / Consultant Supervision consultant for IDA / 57490 Post Qualification Open - National 30,561.12 Signed 2017-09-20 2017-10-05 2017-11-20 2017-11-30 2017-12-11 2019-06-11 Ngoi La 2 reservoir sub- Selection project C1-DL-TDAII-CS2 / Feasibility Study and Dam Consultant Under Safety Reports preparing IDA / 57490 Post Qualification Open - National 0.00 2017-11-15 2017-12-06 2018-01-19 2018-02-19 2018-03-26 2018-09-24 Implementation consultant, subproject phase Selection II VN-DRSIP MOIT-16468-CS- Consultant CQS / Consulting Company Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 for Project Monitoring and Implementation Selection Evaluation (M&E) C1-VINHPHUC-CS1 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-15 2017-12-29 2018-02-26 2018-03-29 2018-04-19 2018-06-29 Safeguard Reports Preparing Implementation Selection Consutant C1-VINHPHUC-CS2 / Consultant Survey, design construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-01-08 2018-01-22 2018-04-20 2018-05-20 2018-06-10 2018-08-29 drawing, cost estimates Implementation Selection consultant C1-HB-GD3-CS1 / Consultant Consultant for developing Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-20 2018-05-04 2018-07-06 2018-08-10 2018-08-24 2018-11-22 feasibility Study and Dam Implementation Selection Safety Reports - Phase 3 C1-HB-GD3-CS2 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-20 2018-05-04 2018-07-06 2018-08-10 2018-08-24 2018-11-22 Safeguard Reports Preparing Implementation Selection Consultant-Phase 3 C1-TQ-GD2-CS1 / Feasibility study and dam safety reports preparing consultant (Subproject 2: Consultant Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 218,883.23 Signed 2017-11-10 2017-11-24 2018-02-19 2018-03-23 2018-04-20 2018-08-20 Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) C1-TQ-GD2-CS2 / Environmental and Social Safeguard Reports Preparing Consultant (Subproject 2: Consultant Trung Long, Hai Mo, Khe IDA / 57490 Post Qualification Open - National 114,953.61 Signed 2017-10-31 2017-11-24 2018-02-22 2018-03-26 2018-04-16 2018-06-16 Thuyen, Cay Gao, Minh Selection Cam, Na Vang, Ao Buc, Khuoi Thung, Hoang Khai, Na Heng, O Ro, Cay Dau and Noong Mo reservoir) C1-BK-CS1 / Consulting Consultant Under package of Feasibility Study IDA / 57490 Post Qualification Open - National 0.00 2017-11-06 2017-11-28 2018-02-26 2018-03-30 2018-05-04 2018-08-03 Implementation and Dam Safety Report Selection C1-BK-CS2 / Consulting Consultant package of Social and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-06 2017-11-28 2018-02-26 2018-03-30 2018-05-04 2018-08-03 Environmental Safety Implementation Selection Reports C1-NT-CS04 / Consultant Environmental and social Pending IDA / 57490 Post Qualification Open - National 0.00 2017-11-16 2017-12-15 2018-03-16 2018-04-20 2018-05-11 2018-09-08 safeguard reports preparing Implementation Selection consultant C1-NT-CS05 / Construction Consultant Pending supervision consultancy IDA / 57490 Post Qualification Open - National 0.00 2018-08-01 2018-09-15 2018-11-30 2018-12-30 2019-01-20 2019-07-19 Implementation package Selection C1-LANGSON-CS1 / Consultation on preparation of safety policy reports including: Environmental Impact Assessment Report, Consultant Under Social Environment Impact IDA / 57490 Post Qualification Open - National 0.00 2018-02-02 2018-02-27 2018-05-29 2018-07-03 2018-07-25 2018-09-24 Implementation Assessment Report, Selection Resettlement Action Plan Report, Social Impact Assessment Report , ethnic minority development plan C1-LANGSON-CS2 / Consultant Consultancy of construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-06-11 2018-06-26 2018-09-27 2018-11-01 2018-11-23 2019-01-22 drawing design - total cost Implementation Selection estimate Page 10 C1-LANGSON-CS3 / Consultant Pending Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2019-08-15 2019-08-29 2019-12-18 2020-01-19 2020-02-13 2022-02-28 Implementation consultant Selection C1-SONLA-CS1 / Consultant Construction supervision, Pending IDA / 57490 Post Qualification Open - National 0.00 2018-09-03 2018-09-17 2018-12-17 2019-01-17 2019-02-07 2020-06-01 Emergency Preparedness Implementation Selection Plan (EPP) C1-KONTUM-CS2 / Consultant Environmental and Social IDA / 57490 Post Qualification Open - National 72,649.43 Signed 2018-01-18 2018-02-01 2018-04-23 2018-05-24 2018-06-28 2018-09-26 Safeguard Documents Selection Preparing Consutant C1-PT-CS2-2 / Consultant services on report establishment on social Consultant Pending environmental safety policies IDA / 57490 Post Qualification Open - National 0.00 2028-01-19 2028-02-28 2028-04-19 2028-05-24 2028-06-28 2028-09-26 Implementation of subproject: Improvement Selection of Dam safety in Phu Tho Province (Phase 2) C1-LAMDONG-CS1 / Consultant Environmental and Social Pending IDA / 57490 Post Qualification Open - National 0.00 2018-01-30 2018-02-13 2018-05-15 2018-06-19 2018-07-11 2019-01-07 Safeguard Reports Preparing Implementation Selection Consultant C1-LAMDONG-CS2 / Consultancy of construction Consultant drawing design - total cost Pending IDA / 57490 Post Qualification Open - National 0.00 2018-08-09 2018-08-23 2018-11-22 2018-12-27 2019-01-18 2019-07-17 estimate + Emergency Implementation Selection Preparedness Plan Preparation Consultant C1-LAMDONG-CS3 / Consultant Pending Construction supervision IDA / 57490 Post Qualification Open - National 0.00 2019-08-05 2019-08-19 2019-11-20 2019-12-25 2020-01-15 2022-01-14 Implementation consultant Selection C1-NB-CS1 / Consulting Consultant Pending services for Feasibility Study IDA / 57490 Post Qualification Open - National 0.00 2018-03-16 2018-03-30 2018-06-29 2018-08-03 2018-08-24 2018-10-23 Implementation and Dam Safety report Selection C1-NB-CS2 / Environmental Consultant and Social Safeguard Pending IDA / 57490 Post Qualification Open - National 0.00 2018-04-26 2018-05-15 2018-08-15 2018-09-19 2018-10-10 2018-12-09 Reports Preparing Implementation Selection Consultant C1-NB-CS3 / Consultancy Consultant Pending of construction drawing IDA / 57490 Post Qualification Open - National 0.00 2018-08-03 2018-08-17 2018-11-15 2018-12-20 2019-01-10 2019-03-11 Implementation design - total cost estimate Selection C1-DL-TDAI-CS4 / Consultant Pending construction supervision for IDA / 57490 Post Qualification Open - National 0.00 2019-03-29 2019-04-12 2019-07-12 2019-08-12 2019-09-02 2021-02-23 Implementation sub-project 1 Selection C1-KHANH HOA-CS2 / Consultant Consultant to survey, Under IDA / 57490 Post Qualification Open - National 0.00 2018-05-05 2018-05-19 2018-07-18 2018-08-02 2018-08-16 2018-12-14 prepare construction drawing Implementation Selection design and cost estimates C1-KHANH HOA-CS3 / Consultant Consultant to prepare Pending IDA / 57490 Post Qualification Open - National 0.00 2018-08-15 2018-08-29 2018-11-27 2018-12-29 2019-01-19 2019-07-18 Emergency Preparedness Implementation Selection Plan (EPP) C1-BT-TDA2-CS-01 / Consultant for developing Consultant Pending feasibility study and dam IDA / 57490 Post Qualification Open - National 0.00 2018-04-27 2018-05-11 2018-08-09 2018-09-10 2018-10-01 2019-01-29 Implementation safety report for subproject Selection 2 C1-BT-TDA2-CS-02 / Consultant for developing Consultant Pending social and environmental IDA / 57490 Post Qualification Open - National 0.00 2018-05-21 2018-06-04 2018-09-02 2018-10-04 2018-10-25 2019-02-22 Implementation safeguards reports for Selection subproject 2 C1-BT-TDA2-CS-03 / Consultant to survey, Consultant Pending prepare construction drawing IDA / 57490 Post Qualification Open - National 0.00 2019-04-29 2019-05-13 2019-08-09 2019-09-10 2019-10-01 2019-12-30 Implementation design and cost estimates Selection for subproject 2 C1-BT-TDA2-CS-04 / Consultant Pending Consultant to construction IDA / 57490 Post Qualification Open - National 0.00 2020-03-02 2020-03-16 2020-06-14 2020-07-16 2020-08-07 2021-08-07 Implementation supervision for subproject 2 Selection Page 11 C1-QN-GD1-CS4 / Survey, Consultant design construction drawing IDA / 57490 Post Qualification Open - National 209,464.98 Signed 2018-05-15 2018-05-20 2018-07-14 2018-07-24 2018-08-05 2019-02-01 and emergency response Selection planning consultant C1-QN-GD1-CS5 / Consultant Construction, environment Under IDA / 57490 Post Qualification Open - National 0.00 2018-09-01 2018-09-11 2018-11-10 2018-11-20 2018-12-02 2020-05-25 and society supervision Implementation Selection consultant C1-QUANGTRI-CS3 / Consultancy on construction Consultant drawing design, Operational IDA / 57490 Post Qualification Open - National 237,866.21 Signed 2018-06-01 2018-06-15 2018-09-14 2018-10-19 2018-11-09 2019-11-04 and Maintenance Plan Selection (O&M), Emergency Preparedness Plan (EPP) C1-QN-CS3 / Consultancy f or survey, construction drawi ng design and cost estimates Consultant Pending for 06 reservoirs, including: IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-09-03 2018-09-10 2018-09-21 2018-12-20 Implementation Đập Đá, Hố Lau, Hóc Két, Selection Hóc Bầu, Đồng Nhơn and Hố Mây Reservoirs. C1-QUANGTRI-CS4 / Consultant Consultancy service for IDA / 57490 Post Qualification Open - National 108,240.45 Signed 2018-05-21 2018-06-04 2018-09-03 2018-10-08 2018-10-29 2021-06-25 construction supervision and Selection environmental monitoring C1-QN-CS4 / Consultancy f or prepare Emergency Prepa redness Plan (EPP) for 06 r Consultant Pending eservoirs, including: Đập Đá, IDA / 57490 Post Qualification Open - National 0.00 2018-12-26 2019-01-09 2019-03-20 2019-04-03 2019-04-17 2019-08-15 Implementation Hố Lau, Hóc Két, Hóc Bầu, Selection Đồng Nhơn, Hố Mây reserv oirs C1-KONTUM-CS5 / Constru ction supervision consultant of 14 reservoirs C3, C4, Đội 5, Cà Sâm, Ia Bang Thượng Consultant Pending ,Đăk Hơ Niêng,Kon Tu Zốp, IDA / 57490 Post Qualification Open - National 0.00 2019-03-29 2019-04-12 2019-05-31 2019-07-01 2019-07-23 2021-12-29 Implementation Đăk Tin, C2, A1 đội 4, Thô Selection n 9, Ya Xăng, C3(704), Đăk Ngót and 04 management h ouse C1-VINHPHUC-CS3 / Consultant Pending Consultant to construction IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-08-30 2018-10-01 2018-10-22 2020-04-22 Implementation supervision Selection C1-VINHPHUC-CS4 / Consultant Consultant to prepare Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-16 2018-07-30 2018-08-30 2018-10-01 2018-10-22 2019-04-22 Emergency Preparedness Implementation Selection Plan. C1-TTH-CS4 / Consulting service for investigation, Consultant Under design of construction IDA / 57490 Post Qualification Open - National 0.00 2018-07-02 2018-07-16 2018-08-14 2018-09-04 2018-09-14 2018-11-13 Implementation drawings, termite Selection investigation and EPP Consultant C1-TTH-CS5 / Supervision Pending IDA / 57490 Post Qualification Open - National 0.00 2018-11-29 2018-12-13 2019-01-14 2019-02-04 2019-02-18 2021-03-02 consultant Implementation Selection C1-YB-CS6 / Survey, Consultant Preparation of termite Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-10 2018-07-26 2018-08-14 2018-09-03 2018-09-08 2019-01-06 treatment documents for all Implementation Selection dams under Subproject C1-YB-CS7 / Construction Consultant Pending Supervision Consultant for IDA / 57490 Post Qualification Open - National 0.00 2018-10-24 2018-11-09 2018-12-07 2018-12-21 2018-12-27 2020-11-28 Implementation all dams under Subproject Selection C1-BD-GD2-CS3 / Consultant for surveying, construction drawing design and cost estimation for 10 reservoirs (Kim Son, My Quality And Cost- Duc, Hoc Tranh, Hung IDA / 57490 Post Open - National 0.00 Canceled 2018-07-20 2018-09-08 2018-11-17 2018-12-22 2019-01-26 2019-03-10 2019-04-09 2019-12-05 Based Selection Long, Giao Hoi, Da Ban, Suoi Run, Trinh Van, An Tuong, Nui Mieu) and Emergency preparedness plan for 4 large reservoirs C1-BD-GD2-CS4 / Consultant Consultant for construction Pending IDA / 57490 Post Qualification Open - National 0.00 2018-07-30 2018-08-20 2018-10-19 2018-11-18 2018-12-23 2021-12-22 supervision and equipment Implementation Selection of 13 reservoirs Page 12 C1-LC-CS3 / Consultancy of construction drawing design Consultant - total cost estimate: Sung Under IDA / 57490 Post Qualification Open - National 0.00 2018-07-20 2018-07-27 2018-08-17 2018-09-07 2018-09-14 2018-10-29 Lang, Phu Nhuan, Tan An, Implementation Selection Pho Rang, Phong Nien, Ta Xin reservoirs. C1-YB-CS5 / Consultancy fo r survey, construction drawi ng design, cost estimates of 16 reservoirs: Tặng An, Ro ong Đen, Làng Át, Gốc Nhộ Consultant Pending i, Khe Hoài, Hang Luồn, K IDA / 57490 Post Qualification Open - National 0.00 2018-07-10 2018-07-26 2018-08-14 2018-09-03 2018-09-08 2019-01-06 Implementation he Vải, Khe dứa, Khe Hóp, Selection Khe Ngang, Khe Chinh, Tự Do, Chóp Dù, Phù Nham, N ông trường Nghĩa Lộ, Thôn 26 C1-KONTUM-CS3 / Consult ing services for design of co nstruction drawings of 14 re servoirs C3, C4, Đội 5, Cà Consultant Under Sâm, Ia Bang Thượng,Đăk IDA / 57490 Post Qualification Open - National 0.00 2018-08-24 2018-09-07 2018-11-01 2018-11-30 2018-12-21 2019-03-21 Implementation Hơ Niêng,Kon Tu Zốp,Đăk Selection Tin, C2, A1 đội 4, Thôn 9, Ya Xăng, C3(704), Đăk Ngót and 04 management house C1-KONTUM-CS4 / Consulting services for Consultant Pending Preparing of Emergency IDA / 57490 Post Qualification Open - National 0.00 2018-10-01 2018-10-15 2018-12-14 2019-01-09 2019-01-30 2019-04-01 Implementation Preparedness Plan (EPP) of Selection Ya Xăng reservoirs C1-DL-CS1 / Environmental Consultant and Social Safeguard Pending IDA / 57490 Post Qualification Open - National 0.00 2018-10-15 2018-10-29 2018-12-28 2019-01-28 2019-02-27 2019-08-26 Reports Preparing Implementation Selection Consultant C1-DL-TDAI-CS3 / Consulting services for Consultant Pending Construction Drawing IDA / 57490 Post Qualification Open - National 0.00 2018-08-24 2018-09-17 2018-12-17 2019-01-17 2019-02-07 2019-06-07 Implementation Designs and Cost Estimates Selection for sub-project 1 C1-BD-GD2- CS3 / Consultant for surveying, construction drawing design and cost estimation for 10 reservoirs (Kim Son, My Consultant Duc, Hoc Tranh, Hung IDA / 57490 Post Qualification Open - National 213,813.42 Signed 2018-08-21 2018-09-11 2018-10-05 2018-11-04 2018-12-05 2019-11-30 Long, Giao Hoi, Da Ban, Selection Suoi Run, Trinh Van, An Tuong, Nui Mieu) and Emergency preparedness plan for 4 large reservoirs C1-QN-GD2-CS1 / Consultant Consultancy service for Under IDA / 57490 Post Qualification Open - National 0.00 2018-10-01 2018-10-06 2018-11-30 2018-12-07 2018-12-19 2019-06-17 preparation of feasibility Implementation Selection study and Dam safety check C1-QN-GD2-CS2 / Report on environmental Iimpact Consultant assessment, environmental Under IDA / 57490 Post Qualification Open - National 0.00 2018-10-10 2018-10-15 2018-12-09 2018-12-16 2018-12-28 2019-06-26 and social impact Implementation Selection assessment, resettlement action plan C1-QN-GD2-CS3 / Survey, Consultant Pending design construction drawing, IDA / 57490 Post Qualification Open - National 0.00 2019-08-16 2019-08-21 2019-10-15 2019-10-22 2019-11-03 2020-02-01 Implementation cost estimates consultant Selection C1-QN-GD2-CS4 / Consultant Construction, environment Pending IDA / 57490 Post Qualification Open - National 0.00 2020-04-04 2020-04-09 2020-06-03 2020-06-10 2020-06-22 2021-12-14 and society supervision Implementation Selection consultant Consultant C1-QN-GD2-CS5 / Pending IDA / 57490 Post Qualification Open - National 0.00 2021-09-06 2021-09-11 2021-11-05 2021-11-12 2021-11-24 2022-02-07 Independent audit consultant Implementation Selection C1-HAGIANG-CS1 / Consul tant for construction drawin Consultant Pending g design - total cost estimat IDA / 57490 Post Qualification Open - National 0.00 2018-10-22 2018-11-06 2019-02-12 2019-03-19 2019-04-10 2019-09-10 Implementation e and Emergency Preparedn Selection ess Plan for Đội 2 reservoir Page 13 C1-NA-CS01 / Selection of consultants for construction drawing design and cost esti mation of subproject 03 (13 Consultant Pending reservoirs: Don Hung, Ke Sa IDA / 57490 Post Qualification Open - National 0.00 2018-10-22 2018-11-12 2018-12-26 2019-01-25 2019-03-01 2019-05-30 Implementation t, Hon Mat, Khe Dua, Khe Selection Du, Ho Tuan, Hoc Nghet, T hanh Thủy, Ho 271, Ho 3/9, La Nga, Khe Dung) C3-THAINGUYEN-CS3 / Consultant Consultant for survey and Pending IDA / 57490 Post Qualification Open - National 0.00 2018-10-22 2018-11-05 2019-02-04 2019-03-11 2019-04-01 2019-05-31 contruction drawing design - Implementation Selection total cost estimate C4-THAINGUYEN-CS4 / Consultant Consultant for preparation Pending IDA / 57490 Post Qualification Open - National 0.00 2018-10-22 2018-11-05 2019-02-04 2019-03-11 2019-04-01 2020-05-25 of Emergency Preparedness Implementation Selection Plan C1-HAGIANG-CS2 / Construction supervision consultant (14 reservoir: Nam Vac, Na Tam, Thon Consultant Pending Lai, Thong Nhat, Thom Ta, IDA / 57490 Post Qualification Open - National 0.00 2019-09-10 2019-09-25 2019-12-27 2020-02-03 2020-02-25 2021-12-28 Implementation Thom Luong, Thon Thia, Selection Đoi 1, Đoi 2, Trung, Khuoi Pha, Tan Bang, Coc Bo, Na Pong) C1-QB-GD2-CS3 / Consultant engineering design (phase 2) and Consultant Planning for Emergency Pending IDA / 57490 Post Qualification Open - National 0.00 2018-11-23 2018-12-14 2019-01-27 2019-02-26 2019-04-02 2019-08-30 Preparedness (EPP) of the Implementation Selection subproject: Improving DAm safety in Quang Binh province INDIVIDUAL CONSULTANTS Page 14