Page 1 Procurement Plan-Goods Country/Organisation: Nigeria//Katsina State Procurement Plan Goods 2008 Project/Programme: Katsina State HIV/AIDS Prog. Dev. Project If Post-Review, No-objection Dates are not needed Loan #: 3556 UNI Spec Proc Notice Advert Contract Implementation Description* Package Number Lot Number Estimated Amount in US $ Procurement Method Pre-or Post Qualification Prior or Post Review Plan vs. Actual Prep & Submission by Ex Agency No-objection Date On-line UNDB Gateway Nat Press Bid Invitation Date Bid Closing- Opening Submission Bid Eval Rpt No-objection Date Plan vs. Actual Contract Amount in US$'000 Date Contract Award Date Contract Advert Date Contract Signature Opening of Let of Credit Arrival of Goods Inspection Final Acceptance If Prequalification Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks 1 - 1.5 wks Plan 1 wk 1.5-3 wks add 7-13 wks Actual Actual List of Contracts KT/HIV/NS/01/08 02 41,026.00 N/S N/A Post Plan N/A N/A N/A 17/03/08 31/03/08 N/A N/A Plan 41,026.00 10/04/08 N/A 15/04/08 N/A 13/05/08 15/05/08 Actual Actual KT/HIV/NS/02/08 01 7,265.00 N/S N/A Post Plan N/A N/A N/A 17/03/08 31/03/08 N/A N/A Plan 7,265.00 10/04/08 N/A 15/04/08 N/A 13/05/08 15/05/08 Actual Actual KT/HIV/NS/03/08 04 4,111.00 N/S N/A Post Plan N/A N/A N/A 17/03/08 31/03/08 N/A N/A Plan 4,111.00 10/04/08 N/A 15/04/08 N/A 13/05/08 15/05/08 Actual Actual KT/HIV/NS/05/08 01 32,479.00 N/S N/A Post Plan N/A N/A N/A 24/03/08 07/04/08 N/A N/A Plan 32,479.00 14/04/08 N/A 18/04/08 N/A 09/05/08 12/05/08 Actual Actual KT/HIV/NS/07/08 01 5,983.00 N/S N/A Post Plan N/A N/A N/A 31/03/08 14/04/08 N/A N/A Plan 5,983.00 21/04/08 N/A 23/04/08 N/A 21/04/08 23/04/08 Actual Actual KT/HIV/NS/08/08 01 5,385.00 N/S N/A Post Plan N/A N/A N/A 08/04/08 22/04/08 N/A N/A Plan 5,385.00 29/05/08 N/A 02/05/08 N/A 30/05/08 02/06/08 Actual Actual KT/HIV/NS/09/08 01 7,692.00 N/S N/A Post Plan N/A N/A N/A 05/04/08 05/05/08 N/A N/A Plan 7,692.00 26/05/08 N/A 28/05/08 N/A 25/06/08 27/06/08 Actual Actual KT/HIV/NS/10/08 01 11,966.00 N/S N/A Post Plan N/A N/A N/A 05/05/08 19/05/08 N/A N/A Plan 11,966.00 04/06/08 N/A 06/06/08 N/A 04/07/08 07/07/08 Actual Actual KT/HIV/NS/11/08 05 22,936.00 N/S N/A Post Plan N/A N/A N/A 07/05/08 21/05/08 N/A N/A Plan 22,936.00 04/06/08 N/A 06/06/08 N/A 04/07/08 07/07/08 Actual Actual KT/HIV/NS/11/08 01 1,709.00 N/S N/A Post Plan N/A N/A N/A 07/05/08 21/05/08 N/A N/A Plan 1,709.00 06/06/08 N/A 09/06/08 N/A 01/07/08 03/07/08 Actual Actual Printing of 500 copies of M & E Management Tools KT/HIV/NS/13/08 01 5,128.00 N/S N/A Post Plan N/A N/A N/A 09/05/08 23/05/08 N/A N/A Plan 5,128.00 06/06/08 N/A 09/06/08 N/A 01/07/08 03/07/08 Actual Actual M & E Materials for ART/HCT Sites KTH/IV//NS/14/08 01 8,547.00 N/S N/A Post Plan N/A N/A N/A 09/05/08 23/05/08 N/A N/A Plan 8,547.00 09/06/08 N/A 12/06/08 N/A 10/07/08 14/07/08 Actual Actual Production of NNRIMS/DHIS Quaterly update KT/HIV/NS/15/08 01 15,385.00 N/S N/A Post Plan N/A N/A N/A 12/05/08 26/05/08 N/A N/A Plan 15,385.00 23/06/08 N/A 26/06/08 N/A 24/07/08 28/07/08 Actual Actual Production of Annual Reports KT/HIV/NS/16/08 01 17,094.00 N/S N/A Post Plan N/A N/A N/A 26/05/08 09/06/08 N/A N/A Plan 17,094.00 23/06/08 N/A 26/06/08 N/A 24/07/08 28/07/08 Actual Actual Printing of 500 copies of National HIV Policies Copies KT/HIV/NS/17/08 01 4,273.00 N/S N/A Post Plan N/A N/A N/A 26/05/08 09/06/08 N/A N/A Plan 4,273.00 23/06/08 N/A 26/06/08 N/A 24/07/08 28/07/08 Actual Actual Total Cost 208,073.00 Plan Plan 208,073.00 Actual Actual Printing of Mapping Exercise Reports Norm Duration of Proc Steps Printing of 500 copies of National BCC Guidelines BCC Advocacy Kits 1No. Desktop Computer for SDP Data Base, Printer, UPS, Stabilizer. STI Drugs for ART/HCT Centres ART/HCT Laboratory Reagents. Blood Storage Facility Contract Finalization Bidding Period Draft Bid Documents, including specs and quantities, draft SPN ART/HCT laboratory consumerbers: Hand Gloves 2000, Syringes 2000, Spirit 2000, Distilled Water 1000, e.t.c. Health Waste Disposal Materials and Equipments Production of Syndromic Management of STI Copies Basic Data Bid Evaluation 426480PROP0P071n0200801020090LATEST.xls 1 of 4 02/25/2008 1:30 AM Page 2 Procurement Plan-Works Country/Organisation: Nigeria//Katsina State Procurement Plan Works 2008 Project/Programme: Katsina State HIV/AIDS Prog. Dev. Project If Post-Review, No-objection Dates are not needed Loan #: 3556 UNI Spec Proc Notice Advert Description* Package Number Lot Number Lumpsum or Bill of Quantities Procurement Method Estimated Amount in US $ Pre-or Post Qualification Prior or Post Review Plan vs. Actual Prep & Submission by Ex Agency No-objection Date On-line UNDB Gateway Nat Press Bid Invitation Date Bid Closing- Opening Submission Bid Eval Rpt No-objection Date Plan vs. Actual Contract Amount in US$ '000 Date Contract Award Date Contract Advert Date Contract Signature Mobilization Advance Payment Substantial Completion Final Acceptance Final Cost If Prequalification Plan 4 - 7 wks 1 - 1.5 wks 1.5 - 2 wks 1.5 - 2 wks 6 to 12 wks 1.5 - 3 wks Plan 1 wk 1.5-3 wks add 7-13 wks Actual Actual List of Contracts Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Plan Plan Actual Actual Total Cost 0.00 Plan Plan 0.00 0.00 0.00 Actual Actual 0.00 0.00 Fill gray cells only! Bid Evaluation Contract Finalization Basic Data Bidding Period Draft Bid Documents, including specs and quantities, draft SPN Contract Implementation Norm Duration of Proc Steps 426480PROP0P071n0200801020090LATEST.xls 2 of 4 02/25/2008 1:30 AM Page 3 Procurement Plan-Consultants 2 Country/Organisation: Nigeria//Katsina State Procurement Plan Consultancy 2008 Project/Programme: Katsina State HIV/AIDS Prog. Dev. Project Loan #: 3556 UNI Description* Selection Method Lumpsum or Time-Based Estimated Amount in US$ '000 Prior/Post Review Plan vs. Actual Prep & Submission by Ex Ag No-objection Date On-line UNDB Gateway Nat Press Lead-time before shortlist Submission Date No-objection Date Plan vs. Actual Invitation Date Submission/ Opening Date Submission Evaluation Report (T) No-objection Evaluation Report (T) Opening Financial Proposals Preparation Eval Report (T) (F) Negotiations (N) Plan vs. Actual Submission Date No-objection Date Contract Amount in US$ '000 Contract Award Date Contract Advert Contract Signature Plan vs. Actual Mobilization Advance Payment Draft Report Final Report Final Cost Plan 3 - 6 wks 1 - 2 wks 1 - 1.5 wks 2 wks 1 - 2 wks Plan 4 to 12 wks 2 - 3 wks 0.5 - 2 wks 2 wks 1 - 2 wks 2 wks Plan 1 - 2 wks 1 - 2 wks 1 wk 1 - 3 wks Plan Actual Actual Actual Actual List of Contracts QCBS LUMPSUM 301.70 Prior Plan 04/03/08 18/03/08 25/03/08 08/04/08 22/04/08 06/05/08 Plan 03/06/08 01/07/08 N/A N/A N/A 02/09/08 02/09/08 Plan 09/09/08 23/09/08 301.70 30/09/08 30/09/08 07/10/08 Plan 14/10/08 11/11/08 19/12/08 301.70 Actual Actual Actual Actual Leasr cost Lumpsum 12.56 Prior Plan 02/05/08 N/A N/A N/A 10/05/08 N/A Plan 8/06/08 08/07/08 N/A N/A 14/09/08 N/A 28/09/08 Plan 4/10/08 N/A 12.56 11/09/08 15/09/08 16/09/08 Plan N/A N/A N/A 12.56 Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Plan Plan Plan Plan Actual Actual Actual Actual Total Cost 314.26 Plan Plan Plan 314.26 Plan 314.26 0.00 Actual Actual Actual 0.00 Actual 0.00 Fill gray cells only! * NOTE: HAF 2: HAF Proposal are submitted together. HAF 1: Final trench & evaluation 31% RRF final trench & evaluation 2% Norm Duration of Proc Steps * Financial support to NGOs/Csos - RRF/HAF II Basic Data Draft Contract Request for EOI (where required) Short List Consultant Proposals Contract Implementation Contract Finalization Proposal Evaluation and Negotiation for Projects after May 2002 Technical (T) & Financial (F) and Negotions (N) Hire Consultant to conduct Mapping of SDPS 426480PROP0P071n0200801020090LATEST.xls 3 of 4 02/25/2008 1:30 AM Page 4 Procurement Plan-Approvals-Consultants 2 Initial Approval Update Dates of Bank Approval of Procurement Plan For Consultants 2 426480PROP0P071n0200801020090LATEST.xls 4 of 4 02/25/2008 1:30 AM