Procurement Plan Mekong Delta Integrated Climate Resilience and Sustainable Livelihoods Project I. General 1. Bank’s approval Date of the procurement Plan: MARD: 17 March 2016; MONRE: April 2, 2016; MPI: May 18, 2016 2. Date of General Procurement Notice: Nov. 3, 2016 3. Period covered by this procurement plan: 1st year of the project, from December 2016 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Prior Review Threshold (US$ millions): Substantial Type of Procurement Risk Works (including Turnkey, Supply & Installation of Plant and Equipment, and 10 PPP Goods, Information Technology and Non- 2 Consulting Services 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: CDD method is applied for Livelihoods component. CDD POM will be prepared and agreed with the Bank 4. Reference to (if any) Project Operational/Procurement Manual: Project Operation Manual dated April 2016 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] Not applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] Summary of Estimated Bank Number Ref. group of cost in Domestic Review Procuring of No contracts/scopes US$ Preference entity packages to be procured (million) Construction of Prior and Provincial sluice gates, dikes Post PMUs, 1 74.7 8 No and dredging ICMB 10 - canals MARD Construction of No Post water/coastal/river bank monitoring stations and Mekong Delta Center; Supply and PMU- 2 21.6 8 installation of MONRE equipment for monitoring systems, stations and Mekong Delta Center. Supply and No Post PMU- Installation of MONRE Surface Water 3 1.1 1 Monitoring and Transmission Equipment Provision of No Prior PMU- Images during MONRE 4 3.5 1 Receiving Station Upgrades Upgrade satellite No Post PMU- 5 0.6 1 MONRE receiving station Supply and No Prior PMU- Installation of SW MONRE 6 Monitoring and 6.8 1 Transmission Equipment Supply and No Post PMU- Installation of MONRE 7 Well Monitoring 0.85 1 and Transmission Equipment Post PMU- MONRE, 8 Other goods/works 0.27 5 No PMU-MPI, CPMU- MARD III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review Threshold (US$ millions): Substantial Type of Procurement Risk Consultants: Firms 1 Consultants: Individual 0.3 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule Summary of Estimated Bank Number Ref. group of cost in Domestic Review Procuring of No contracts/scopes US$ Preference entity packages to be procured (million) No Post Provincial PMUs, Monitoring ICMB 10 - 3 implementation of 0.62 7 MARD, safeguard policies CPMU – MARD No Prior PMU- Project MONRE, 4 implementation 5.74 13 PMU-MPI, support consultants CPMU- MARD No Prior and Provincial Post PMUs, PMU- 5 Detailed design 3.58 4 MONRE, CPMU- MARD No Post CPMU- 6 Audit 0.38 2 MARD Other research, No Prior and PMU- study consultancy Post MONRE, 7 1.83 1 services relating to coastal zone PROCUREMENT Vietnam : Mekong Delta Integrated Climate Resilience and Sustainable Livelihoods Project PLAN General Information Country: Vietnam Banks Approval Date of the Original Procurement Plan: 2016-11-23 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-10-16 Project ID: P153544 GPN Date: 2016-11-03 Project Name: Mekong Delta Integrated Climate Resilience and Sustainable Livelihoods Project Loan / Credit No: IDA / 58450 Executing Agency(ies): MONRE Construction Investment Project Management Unit, Ministry of Planning and Investment PMU for M-ICRSL, Central Project Management Unit for M-ICRSL, Ben Tre Provincial PMU for Agriculture and Rural Development, Irrigation Construction and Management Board No.10 WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Project CPMU-CW-01 / Office renovation Request for Single Stage - One Pending IDA / 58450 Management and Post Open - National 30,000.00 0.00 2017-09-06 2017-11-13 2018-03-13 for CPO in Ha NÍi Quotations Envelope Implementation Implementation Support BT-CW-01 / Construction of 5 Component 3: Adapting to Sluice gates: Duong Khai, Tràng Single Stage - One Pending IDA / 58450 Salinity Transitions in the Delta Post Request for Bids Open - National 7,390,000.00 0.00 2018-04-02 2018-04-07 2018-05-19 2018-06-18 2018-07-23 2021-07-07 Û , N°c Duong Tac, Cay Keo, An Envelope Implementation Estuary Thanh Component 3: Adapting to Single Stage - One Pending BT-CW-02 / Dredging 14 canals IDA / 58450 Salinity Transitions in the Delta Post Request for Bids Open - National 999,000.00 0.00 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2021-08-05 Envelope Implementation Estuary PMU10-CW-03 / Vung Liem Component 3: Adapting to Single Stage - One Pending sluice construction and gate IDA / 58450 Salinity Transitions in the Delta Post Request for Bids Open - National 9,859,000.00 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2019-10-11 Envelope Implementation manufacture and installation Estuary PMU10-CW-01 / Bong Bot Component 3: Adapting to Single Stage - One Pending sluice construction and gate IDA / 58450 Salinity Transitions in the Delta Post Request for Bids Open - National 8,355,000.00 0.00 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2019-11-10 Envelope Implementation manufacture and installation Estuary PMU10-CW-02 / Tan Dinh sluice Component 3: Adapting to Single Stage - One Pending construction and gate IDA / 58450 Salinity Transitions in the Delta Post Request for Bids Open - National 5,626,000.00 0.00 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2019-10-25 Envelope Implementation manufacture and installation Estuary Component 1: Enhancing SP1 - CW01 / Upgrade and Single Stage - One Pending IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 2,158,855.00 0.00 2017-08-18 2017-09-06 2017-10-07 2017-10-31 2017-11-13 2019-05-13 construct 20 monitoring stations Envelope Implementation Information Systems SP2 - CW01 / Upgrade and Component 1: Enhancing construct new wells in GW CC- Single Stage - One IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 4,617,215.00 0.00 Canceled 2017-09-04 2017-09-20 2017-10-20 2017-11-14 2017-11-28 2019-11-28 effected & GW trans-boundary Envelope Information Systems area SP2-CW1 / Upgrade and Component 1: Enhancing construct new wells in GW CC- Pending IDA / 58450 Monitoring, Analytics, and Prior Force Account Direct 4,214,158.00 0.00 2017-10-10 2017-10-25 2017-12-21 2019-12-20 effected & GW trans-boundary Implementation Information Systems area Component 1: Enhancing SP2-CW2 / Construction of the Single Stage - One Pending IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 367,601.00 0.00 2018-01-02 2018-01-16 2018-02-26 2018-03-12 2018-04-05 2020-04-04 wall surrounding the borehole Envelope Implementation Information Systems GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Project MPI-PMU-SC05-G01 / Office Request for Single Stage - One IDA / 58450 Management and Post Open - National 50,000.00 45,198.66 Signed 2016-12-21 2017-02-14 2017-06-30 2017-04-19 equipment & funiture Quotations Envelope Implementation Support Component 5: Project CPMU-GO-01 / Office equipment Request for Single Stage - One Pending IDA / 58450 Management and Post Open - National 50,000.00 0.00 2017-05-06 2017-07-15 2017-09-13 & funiture CPO/CPMU Quotations Envelope Implementation Implementation Support Component 1: Enhancing PMU MONRE - G01 / Request for Single Stage - One Pending IDA / 58450 Monitoring, Analytics, and Post Open - National 50,000.00 0.00 2017-07-30 2017-09-24 2018-03-23 Equipment for PMU MONRE Quotations Envelope Implementation Information Systems SP3 - G02 / Upgrading the VietNam ground receiving station Component 1: Enhancing Single Stage - One Pending for receiving and processing IDA / 58450 Monitoring, Analytics, and Prior Request for Bids Open - International 8,107,184.00 0.00 2017-07-21 2017-08-16 2017-10-06 2017-11-20 2017-12-25 2019-12-25 Envelope Implementation imagery and remotely sensed Information Systems data management. SP2 - G01 / Supply and Component 1: Enhancing Single Stage - One Pending Installation of Well Monitoring IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 1,697,004.00 0.00 2017-09-22 2017-10-06 2017-11-06 2017-11-24 2017-12-12 2019-06-12 Envelope Implementation and Transmission Equipment Information Systems SP1 - G01 / Supply, Installation of SW Monitoring and Component 1: Enhancing Single Stage - One Pending Transmission Equipment and IDA / 58450 Monitoring, Analytics, and Prior Request for Bids Open - International 6,628,438.00 0.00 2017-08-30 2017-09-29 2017-11-13 2017-12-25 2018-02-05 2019-08-05 Envelope Implementation surveying, building and correcting Information Systems relationship graph Component 1: Enhancing SP3 - G03 / Auxiliary equipment Single Stage - One Pending IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 166,543.00 0.00 2017-09-15 2017-10-06 2017-11-07 2017-12-04 2017-12-18 2018-12-18 for Remote Sensing laboratory Envelope Implementation Information Systems NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Component 5: Project CPMU-GO-02 / Office renting for Request for Single Stage - One Pending IDA / 58450 Management and Post Open - National 95,000.00 0.00 2017-02-25 2017-05-02 2022-12-31 CPMU in Can Tho Quotations Envelope Implementation Implementation Support Component 1: Enhancing SP3 - NCS01 / 01 year signal Single Stage - One Pending IDA / 58450 Monitoring, Analytics, and Post Request for Bids Open - National 1,452,974.00 0.00 2018-06-22 2018-07-06 2018-08-20 2018-10-02 2018-10-25 2019-10-25 reception Envelope Implementation Information Systems CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Project CPMU-CS-QCBS-05 / Project Quality And Cost- Under IDA / 58450 Management and Post Open - International 700,000.00 0.00 2017-01-15 2017-02-15 2017-02-19 2017-04-12 2017-05-17 2017-06-21 2017-07-20 2017-08-13 2022-12-31 Monitoring and Evaluation Based Selection Implementation Implementation Support CPMU-CS-QCBS-06 / Consultant firm for research wave Component 5: Project Quality And Cost- Pending breaker for mudflat creating to IDA / 58450 Management and Post Open - International 800,000.00 0.00 2017-06-01 2017-06-22 2017-08-26 2017-09-30 2017-11-06 2017-12-11 2018-01-08 2019-01-08 Based Selection Implementation protect coastal dikes in Kien Implementation Support Giang province MPI-PMU-SC01-CQS-01 / TOR Component 1: Enhancing Consultant preparation, procurement support IDA / 58450 Monitoring, Analytics, and Post Qualification Open - International 350,000.00 342,718.34 Signed 2017-01-02 2017-03-20 2017-01-23 2017-03-27 2017-02-20 2017-05-22 2017-03-20 2017-06-22 2017-04-03 2017-06-26 2018-12-31 and technical assistance for the Information Systems Selection Scheme implementation CPMU-CS-CQS-02 / Component 5: Project Consultant Environmental management plan Pending IDA / 58450 Management and Post Qualification Open - National 150,000.00 0.00 2017-02-20 2017-03-13 2017-04-26 2017-06-09 2017-07-14 2022-07-14 (EMP) monitoring for 4 first Implementation Implementation Support Selection subprojects Component 5: Project Consultant CPMU-CS-CQS-03 / Internal Pending IDA / 58450 Management and Post Qualification Open - National 200,000.00 0.00 2017-04-01 2017-04-22 2017-06-05 2017-07-19 2017-08-23 2022-12-31 audit supporting firm Implementation Implementation Support Selection Component 5: Project Consultant CPMU-CS-CQS-04 / External Pending IDA / 58450 Management and Post Qualification Open - National 180,000.00 0.00 2017-07-01 2017-07-22 2017-09-04 2017-10-18 2017-11-22 2020-06-30 Audit - Phase 1 Implementation Implementation Support Selection CPMU-CS-CQS-01 / RAP and Component 5: Project Consultant Under EMDP monitoring for 4 first IDA / 58450 Management and Post Qualification Open - National 200,000.00 0.00 2017-02-13 2017-03-06 2017-04-19 2017-06-02 2017-07-07 2022-07-07 Implementation subprojects Implementation Support Selection Component 3: Adapting to Consultant BT-CS-CQS-02 / Enviromental Pending IDA / 58450 Salinity Transitions in the Delta Post Qualification Open - National 32,000.00 0.00 2018-03-01 2018-03-11 2018-05-04 2018-06-03 2018-07-08 2021-06-22 Management consultant Implementation Estuary Selection BT-CS-CQS-01 / Consultant for Component 3: Adapting to Consultant Survey, detailed design and Pending IDA / 58450 Salinity Transitions in the Delta Post Qualification Open - National 296,000.00 0.00 2017-05-01 2017-05-21 2017-07-15 2017-08-24 2017-09-13 2018-03-12 preparation of Dreding Material Implementation Estuary Selection Disposal Plan CPMU-CS-QCBS-04 / Project Component 5: Project Quality And Cost- implementation support IDA / 58450 Management and Prior Open - International 3,500,000.00 0.00 Canceled 2016-12-23 2016-12-30 2017-01-16 2017-01-09 2017-03-24 2017-05-05 2017-06-05 2017-07-04 2017-07-28 2022-12-31 Based Selection consultant Implementation Support Component 5: Project CPMU-CS-QCBS- 04 / Project Quality And Cost- Under IDA / 58450 Management and Prior Open - International 2,679,000.00 0.00 2016-12-23 2017-02-09 2017-04-13 2017-07-10 2017-05-11 2017-06-20 2017-07-18 2017-08-22 2022-12-31 Management Consultant Support Based Selection Implementation Implementation Support PMU10-CS-CQS-01 / Component 3: Adapting to Consultant Pending Emviroment management IDA / 58450 Salinity Transitions in the Delta Post Qualification Open - National 55,000.00 0.00 2017-07-01 2017-07-10 2017-08-25 2017-09-20 2017-10-15 2019-12-04 Implementation consultant (EMC) Estuary Selection Component 1: Enhancing SP2 - CS1 / Ground water Quality And Cost- Under IDA / 58450 Monitoring, Analytics, and Prior Open - International 1,311,967.00 0.00 2017-07-07 2017-07-28 2017-09-29 2017-11-20 2017-12-20 2018-01-29 2018-03-20 2020-03-20 survey/study Based Selection Implementation Information Systems SP3 - CS1 / Monitoring of Component 1: Enhancing Quality And Cost- Pending riverbank and coastal zone IDA / 58450 Monitoring, Analytics, and Prior Open - International 1,264,901.00 0.00 2017-07-28 2017-08-18 2017-10-24 2017-12-14 2018-01-12 2018-02-20 2018-04-10 2020-04-10 Based Selection Implementation erosions Information Systems SP4 - CS1 / History data survey, preparation of detail design - cost Component 1: Enhancing Quality And Cost- Pending estimation for construction items, IDA / 58450 Monitoring, Analytics, and Post Open - International 664,946.00 0.00 2017-07-28 2017-08-18 2017-10-11 2017-12-14 2018-01-12 2018-02-20 2018-04-10 2019-10-11 Based Selection Implementation IT infrastructure and data base Information Systems software PMU MONRE - CS1 / Project Component 5: Project Quality And Cost- Under Implementation and Management IDA / 58450 Management and Post Open - International 650,900.00 0.00 2017-07-14 2017-08-04 2017-09-22 2017-11-28 2017-12-28 2018-02-01 2018-03-20 2022-03-20 Based Selection Implementation support Implementation Support INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 5: Project PMU MONRE - CS02 / Project Individual Consultant IDA / 58450 Management and Post Open 24,000.00 2,902.88 Terminated 2016-11-22 2016-12-02 2017-01-16 2016-12-16 2017-01-16 2016-12-30 2017-12-31 Coordinator Selection Implementation Support PMU MONRE - CS04 / Component 5: Project Individual Consultant Under Technical Specialist (Remote IDA / 58450 Management and Post Open 24,000.00 0.00 2016-11-22 2016-12-02 2016-12-16 2016-12-30 2017-12-31 Selection Implementation sensing) Implementation Support Component 5: Project PMU MONRE - CS05 / Financial Individual Consultant Under IDA / 58450 Management and Post Open 24,000.00 0.00 2016-11-22 2016-12-02 2016-12-16 2016-12-30 2017-12-31 Management Selection Implementation Implementation Support Page 2 Component 5: Project MPI-PMU-SC05-IC-08 / Individual Consultant Pending IDA / 58450 Management and Post Open 20,100.00 0.00 2016-12-08 2017-01-12 2017-01-19 2017-02-02 2019-12-31 Safeguards Specialist Selection Implementation Implementation Support Component 5: Project MPI-PMU-SC05-IC-02 / Project Individual Consultant IDA / 58450 Management and Post Open 66,230.00 57,743.63 Signed 2016-12-08 2017-01-12 2017-03-29 2017-01-19 2017-03-30 2017-02-01 2017-03-31 2019-12-31 coordinator Selection Implementation Support Component 5: Project MPI-PMU-SC05-IC-01 / Individual Consultant IDA / 58450 Management and Prior Open 40,000.00 37,634.61 Signed 2016-12-08 2016-12-21 2017-01-17 2017-01-31 2017-03-15 2017-02-14 2017-03-31 2019-12-31 Procurement Specialist Selection Implementation Support Component 5: Project MPI-PMU-SC05-IC-03 / Project Individual Consultant IDA / 58450 Management and Post Open 59,200.00 44,632.25 Signed 2016-12-08 2017-03-14 2017-01-12 2017-08-07 2017-01-19 2017-08-08 2017-02-02 2017-08-15 2019-12-31 Technical Officer Selection Implementation Support Component 5: Project MPI-PMU-SC05-IC-04 / Individual Consultant IDA / 58450 Management and Post Open 62,050.00 55,672.88 Signed 2016-12-08 2017-02-02 2017-01-19 2017-03-09 2017-01-26 2017-03-10 2017-02-09 2017-03-15 2019-12-31 Financial Management Specialist Selection Implementation Support Component 5: Project MPI-PMU-SC05-IC-05 / Individual Consultant IDA / 58450 Management and Post Open 59,200.00 52,441.01 Signed 2016-12-08 2016-12-21 2017-01-19 2017-03-09 2017-01-26 2017-03-10 2017-02-09 2017-03-15 2019-12-31 Accountant Selection Implementation Support Component 5: Project MPI-PMU-SC05-IC-06 / Individual Consultant IDA / 58450 Management and Post Open 37,000.00 32,701.98 Signed 2016-12-08 2017-01-12 2017-03-06 2017-01-19 2017-03-07 2017-02-02 2017-03-15 2019-12-31 Secretary cum Translator Selection Implementation Support MPI-PMU-SC05-IC-07 / Component 5: Project Individual Consultant Pending Monitoring and Evaluation IDA / 58450 Management and Post Open 20,100.00 0.00 2016-12-08 2017-01-12 2017-01-19 2017-02-02 2019-12-31 Selection Implementation Consultant Implementation Support CPMU-CS-IC-01 / International Component 5: Project Individual Consultant Pending consultant for safeguards IDA / 58450 Management and Post Open 100,000.00 0.00 2017-07-01 2017-08-19 2017-09-09 2017-10-14 2019-10-14 Selection Implementation implementation support Implementation Support Component 5: Project PMU MONRE - CS03 / Individual Consultant IDA / 58450 Management and Prior Open 24,000.00 0.00 Canceled 2016-11-22 2016-12-02 2016-12-16 2016-12-30 2017-12-31 Procurement Specialist Selection Implementation Support Component 5: Project PMU MONRE - CS3 / Individual Consultant Under IDA / 58450 Management and Post Open 72,000.00 0.00 2016-12-02 2016-12-05 2017-04-18 2017-04-18 2017-04-21 2021-04-21 Procurement Specialist Selection Implementation Implementation Support Component 5: Project PMU MONRE - CS2 / Project Individual Consultant Under IDA / 58450 Management and Post Open 87,000.00 0.00 2017-05-05 2017-05-08 2017-06-09 2017-06-12 2022-04-12 Coordinator Selection Implementation Implementation Support PMU MONRE-CS6 / Social and Component 5: Project Individual Consultant Pending Environmental Safeguards IDA / 58450 Management and Post Open 54,000.00 0.00 2017-10-20 2017-11-22 2017-11-27 2017-11-30 2021-11-29 Selection Implementation Consultant Implementation Support Component 5: Project PMU MONRE - CS06 / Social Individual Consultant IDA / 58450 Management and Post Open 18,000.00 0.00 Canceled 2017-06-30 2017-07-27 2017-08-16 2017-08-23 2018-08-23 and Safeguard Consultant Selection Implementation Support Page 3