PROCUREMENT PLAN FOR WORKS Country/Borrower: Government of Sri Lanka Project Name: Emergency Northern Recovery Project Credit/Grant #: 4676 Implementing Agency: ENREP PMU GPN # and Date Published : Original Plan Approved Date(at Appraisal/Negotiations): November 30, 2009 Update as of: January 4, 2010 Update as of: May 7, 2010 Update as of: September 24, 2010 Update as of: May 31, 2011 Update as of: September 30, 2011 Update as of: December 31, 2011 Update as of : 30th April, 2012 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O C1. Irrigation Schemes Rehabilitation of Kanagambigai Tank, Planned 1/29/2010 3/5/2010 - 4/19/2010 Rohan 10/16/2010 1 ENREP/W/2 Kilinochchi Karachchi NCB 25.4 0.23 Post LKR 21.56 12.09 Karachchi, Kilinochchi Actual 6/26/2010 7/16/2010 - 7/28/2010 Enterprises 8/11/2011 On Progress Restoration of Kalmadu tank, Planned 1/29/2010 3/5/2010 - 4/19/2010 Kanthi 4/19/2011 2 ENREP/W/4 Kilinochchi Kandavalai NCB 171.62 1.55 Prior LKR 128.51 114.29 Kandawalai, Kilinochchi Construction Actual 6/26/2010 7/16/2010 - 7/23/2010 8/6/2011 On Progress Rehabilitation of Kariyalainagapaduwan Planned 1/29/2010 3/5/2010 - 4/19/2010 Shyaam 1/14/2011 3 ENREP/W/6 Kilinochchi Pooneryn NCB 51.8 0.47 Post LKR 44.99 13.33 Tank in Pooneriyn Kilinochchi. Actual 6/26/2010 7/16/2010 - 7/9/2010 Builders 7/18/2011 On Progress Rehabilation of Dri aru tank in Planned 7/19/2010 8/23/2010 - 9/23/2010 Jathur 3/23/2011 4 ENREP/W/258 Kilinochchi Karachchi NCB 30.8 0.28 Post LKR 23.09 12.86 Kilinochchi Actual 2/8/2011 3/8/2011 - 4/7/2011 Enterprise 12/17/2011 On Progress Rehabilitaion of Sampukulam, Planned - - - 10/8/2010 1/6/2011 Completed FO, 5 ENREP/W/3-h Villukulam, Kuruppikulam in Kilinochchi Karachchi DC 4.00 0.04 Post LKR 3.98 3.06 Actual - - - 11/9/2010 Kalmadunagar 3/16/2011 6/16/2011 Ramanathapuram ASC Rehabilitaion of Ramanathankulam, Eraddaipanikulam, Mamilkulam, Planned - - - 10/8/2010 FO, 1/6/2011 Completed 6 ENREP/W/3-i Kilinochchi Karachchi DC 5.00 0.05 Post LKR 4.48 3.46 Kunchumeesankulam in Actual - - - 11/9/2010 Vaddakachchi 3/16/2011 16/6/2011 Ramanathapuram ASC Rehabilitaion of Puthukulam in Planned - - - 10/8/2010 FO, 1/6/2011 Completed 7 ENREP/W/3-p Kilinochchi Karachchi DC 1.27 0.01 Post LKR 1.27 1.25 Kilinochchi ASC Actual - - - 10/4/2010 Kandawalai 3/15/2011 12/10/2010 Planned 7/19/2010 8/23/2010 - 9/23/2010 Leading 3/23/2011 8 ENREP/W/5-a Rehabilitation of Rasanayakulam Kilinochchi Kandavalai NCB 8.58 0.08 Post LKR 6.19 2.92 Actual 2/8/2011 3/8/2011 - 4/11/2011 Crusher Works 9/22/2011 On Progress Planned - - - 9/23/2010 FO, 3/23/2011 9 ENREP/W/5-b Rehabilitation of Thatchadampan kulam Kilinochchi Kandavalai DC 2.67 0.02 Post LKR 2.67 Nagenthirapura 1.17 Actual - - - 10/28/2010 m 3/3/2011 On Progress Planned - - - 9/23/2010 Fo, 3/23/2011 Completed 10 ENREP/W/5-c Rehabilitation of Periyakulam Kilinochchi Kandavalai DC 5.28 0.05 Post LKR 5.28 5.16 Actual - - - 9/20/2010 Periyakulam 1/28/2011 6/6/2011 Rehabilitation of Thadduvankoddikulam Planned 8/27/2010 10/1/2010 - 10/8/2010 1/6/2011 11 ENREP/W/5-f Kilinochchi Kandavalai NCB 11.53 0.10 Post LKR 11.53 Abdul Azeez 1.03 and Uriyankulam Actual 2/8/2011 3/8/2011 - 4/25/2011 10/6/2011 On Progress Planned - - - 10/8/2010 FO, 1/6/2011 Rehabilitaion of Pullukulam in 12 ENREP/W/5-g Kilinochchi Kandavalai DC 0.77 0.01 Post LKR 0.77 Tharmapuram 0.39 Puliyampokkanai ASC Actual - - - 10/5/2010 2/9/2011 On Progress West Rehabilitaion of Karukkaikulam in Planned - - - 10/8/2010 FO, 1/6/2011 13 ENREP/W/5-h Kilinochchi Kandavalai DC 0.73 0.01 Post LKR 0.73 0.33 Puliyampokkanai ASC Actual - - - 10/5/2010 Karukkaikulam 2/9/2011 On Progress Rehabilitaion of Kallattukulam in Planned - - - 10/8/2010 FO, 1/6/2011 14 ENREP/W/5-i Kilinochchi Kandavalai DC 0.35 0.00 Post LKR 0.35 0.35 Puliyampokkanai ASC Piramanthanaru Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehabilitaion of Kallattukulam in FO, 14 ENREP/W/5-i Kilinochchi Kandavalai DC 0.35 0.00 Post LKR 0.35 0.35 Puliyampokkanai ASC Actual - - - 10/5/2010 Piramanthanaru 2/9/2011 On Progress Rehabilitaion of Kanthankulam in Planned - - - 10/8/2010 FO, 1/6/2011 15 ENREP/W/5-j Kilinochchi Kandavalai DC 1.04 0.01 Post LKR 1.04 0.82 Puliyampokkanai ASC Actual - - - 10/5/2010 Kandawalai 2/9/2011 On Progress Rehabilitaion of konankulam in Planned - - - 10/8/2010 FO, 1/6/2011 Completed 16 ENREP/W/5-k Kilinochchi Kandavalai DC 1.47 0.01 Post LKR 1.47 1.03 Puliyampokkanai ASC Actual - - - 10/4/2010 Kandawalai 3/15/2011 12/10/2011 Rehabilitation of Thumpuruvil - Planned - - - 2/9/2010 FO, Jeyapuram 6/9/2010 Terminated 17 ENREP/W/7-a Kilinochchi Pooneryn DC 2.17 0.02 Post LKR 2.17 - Mathamoodaikulam at Mulankavil ASC Actual - - - 10/7/2010 North 2/11/2011 5/30/2011 Rehabilitation of Puthiyarmoodaikulam Planned - - - 2/9/2010 FO, Nallur, 6/9/2010 Terminated 18 ENREP/W/7-b Kilinochchi Pooneryn DC 1.99 0.02 Post LKR 1.99 - in Poonagary Asc Actual - - - 10/7/2010 Poonakari 2/11/2011 5/30/2011 Planned - - - 2/9/2010 RDS 6/9/2010 19 ENREP/W/7-d Rehabilation of Neradampan kulam. Kilinochchi Pooneryn DC 4.18 0.04 Post LKR 3.76 3.62 Actual - - - 7/19/2010 Neradampan 12/29/2010 On Progress Rehabilation of Mudkompan kulam Planned - - - 2/9/2010 FO, 6/9/2010 20 ENREP/W/7-f Kilinochchi Pooneryn DC 4.10 0.04 Post LKR 3.68 3.71 Pooneryn, Actual - - - 10/10/2010 Mudkompan 3/15/2011 On Progress Construction of 3 Bay Regulator at Planned - - - 10/8/2010 FO, 1/6/2011 Completed 21 ENREP/W/7-j Kilinochchi Poonakary DC 0.83 0.01 Post LKR 0.83 0.78 Gnanimadam in Kilinochchi Actual - - - 10/29/2010 Gnanimadam 1/3/2011 11/24/2010 Construction of 3 Bay Regulator at Planned - - - 10/8/2010 FO, 1/6/2011 Completed 22 ENREP/W/7-k Kilinochchi Poonakary DC 0.65 0.01 Post LKR 0.65 0.59 Pavoodai in Kilinochchi Actual - - - 10/29/2010 Gnanimadam 1/3/2011 11/24/2011 Planned - - - 7/17/2010 Rural 4/13/2011 Rehabilitaion of Uppulavan Kalappu 23 ENREP/W/9 Kilinochchi Pooneryn DC 3.58 0.03 post LKR 3.22 Development 2.41 SWE Scheme - 4km Actual - - - 7/19/2010 12/29/2010 On Progress society Planned - - - 7/18/2010 Rural 4/14/2011 Completed Rehabilitation of Ramankalappu SWE 24 ENREP/W/10 Kilinochchi Pooneryn DC 3.93 0.04 post LKR 3.53 Development 2.71 Scheme 4.5km, Poonakary Actual - - - 7/21/2010 12/29/2010 4/25/2011 society Rehabilitation of Planned - - - 2/9/2010 FO, 6/9/2010 25 ENREP/W/11-a Mannar Manthai West DC 5.22 0.05 Post LKR 4.71 1.96 Illupaikadaviperiyakulam Actual - - - 8/12/2010 Illupaikadavai 1/13/2011 On Progress Planned 1/10/2010 1/10/2010 - 2/9/2010 Santhiyapillai 6/9/2010 26 ENREP/W/11-b Rehabilitation of Soolamandakulam Mannar Manthai West NCB 8.21 0.07 Post LKR 5.79 - Actual 10/30/2010 12/3/2010 - 12/28/2010 &Son's 6/10/2010 On Progress Planned - - - 2/9/2010 FO, St. 6/9/2010 27 ENREP/W/11-d Rehabilitation of Veddiyamurippu Mannar Manthai West DC 2.22 0.02 Post LKR 2.00 0.86 Actual - - - 9/14/2010 Anthony's 1/19/2011 On Progress Planned - - - 2/9/2010 6/9/2010 28 ENREP/W/11-e Rehabilitation of Annaipappankulam Mannar Manthai West DC 2.09 0.02 Post LKR 1.88 FO, Chalampan 0.94 Actual - - - 8/13/2010 1/13/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 29 ENREP/W/11-f Rehabilitation of Kovilkulam Mannar Manthai West DC 3.18 0.03 Post LKR 3.18 0.99 Actual - - - 10/1/2010 Kovilkulam 1/5/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 30 ENREP/W/11-g Rehabilitation of Periyavillankulam Mannar Manthai West DC 2.94 0.03 Post LKR 2.94 1.67 Actual - - - 9/17/2010 Vellankulam 1/22/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 31 ENREP/W/11-h Rehabilitation of Ahathikulam Mannar Manthai West DC 3.66 0.03 Post LKR 3.30 - Actual - - - 8/13/2010 Arunothaya 1/13/2011 On Progress Planned - - - 10/8/2010 1/6/2011 32 ENREP/W/11-i Rehabilitation of Uyilankulam Mannar Manthai West DC 3.06 0.03 Post LKR 3.06 FO,Vellankula 1.75 Actual - - - 9/17/2010 m 1/22/2011 On Progress Rehabilitation of Mullikulam- Planned - - - 10/8/2010 1/6/2011 33 ENREP/W/11-j Mannar Manthai West DC 2.27 0.02 Post LKR 2.27 FO,Vellankula 1.19 Vellankulam Actual - - - 9/17/2010 1/22/2011 On Progress m Planned - - - 10/8/2010 FO, 1/6/2011 34 ENREP/W/11-m Rehabilitation of Villiyankulam Mannar Madhu DC 4.43 0.04 Post LKR 4.43 0.64 Actual - - - 9/10/2010 Uthaiyasooriyan 1/19/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned - - - 10/8/2010 FO, 1/6/2011 35 ENREP/W/11-n Rehabilitation of Viravappuliyankulam Mannar Madhu DC 2.50 0.02 Post LKR 2.50 1.11 Uthaiyasooriyan Actual - - - 9/14/2010 1/19/2011 On Progress Planned - - - 10/8/2010 1/6/2011 36 ENREP/W/11-o Rehabilitation of Vinayakarkulam Mannar Madhu DC 3.47 0.03 Post LKR 3.47 FO, Vinayagar - Actual - - - 9/14/2010 1/19/2011 On Progress Planned - - - 10/8/2010 1/6/2011 37 ENREP/W/11-p Rehabilitation of Palampiddikulam Mannar Madhu DC 3.75 0.03 Post LKR 3.75 FO, Vinayagar 0.58 Actual - - - 9/10/2010 1/19/2011 On Progress Planned - - - 10/8/2010 1/6/2011 38 ENREP/W/11-t Rehabilitation of Kallikulam Mannar Musali DC 1.97 0.02 Post LKR 1.97 FO, Methanveli 0.74 Actual - - - 9/17/2010 1/22/2011 On Progress Planned 1/29/2010 3/5/2010 - 4/19/2010 SMA 1/14/2011 Rehabilitation of Periyapandivirichchan, 39 ENREP/W/12 Mannar Madhu NCB 117.98 1.06 post LKR 97.59 Construction, 27.87 Madhu Actual 2/1/2011 3/8/2011 - 4/7/2011 4/20/2012 On Progress thalawatugoda Planned 2/13/2011 3/20/2011 - 4/19/2011 SMA 4/18/2012 40 ENREP/W/409 Rehabilitation of Mullikulam Tank Mannar Madu NCB 64.20 0.58 Post LKR 60.64 Construction, 13.85 Actual 3/8/2011 4/8/2011 - 4/25/2011 thalawatugoda 5/8/2012 On Progress Planned 4/30/2010 6/4/2010 - 7/19/2010 Rajarata 4/15/2011 41 ENREP/W/13 Rehabilitation of Adampankulam, Mannar Manthai west NCB 50.32 0.45 post LKR 41.80 13.25 Actual 9/27/2010 11/4/2010 - 12/30/2010 Construction 1/13/2012 On Progress Planned 5/1/2010 6/5/2010 - 7/20/2010 Padminie 4/16/2011 42 ENREP/W/14 Rehabilitation of Periyamadu Mannar Manthai west NCB 92.74 0.84 post LKR 86.49 27.10 Actual 9/27/2010 11/4/2010 - 12/3/2010 Construction 12/17/2011 On Progress Planned 7/12/2012 - 7/25/2012 Zanu 11/14/2012 43 ENREP/W/15 Rehabilitation of Sinnathimoddai Tank Mannar Nanaddan NS 14.08 0.84 post LKR 13.34 Actual 7/30/2012 - 8/15/2012 Construction On Progress Improvements to Vilathikulam in Planned 44 ENREP/W/16 Mannar Mannar NS 14.40 post Mannar Actual On Progress Planned - - - 2/9/2010 FO, 6/9/2010 45 ENREP/W/17-c Rehabilitation of Kankanarkulam Mullaitivu Manthai East DC 5.04 0.05 Post LKR 5.04 1.57 Actual - - - 8/19/2010 Naddankandal 12/21/2010 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 46 ENREP/W/17-d Rehabilitation of Thevikulam Mullaitivu Manthai East DC 5.29 0.05 Post LKR 5.29 1.23 Actual - - - 8/13/2010 Vinayagapuram 12/21/2010 On Progress Planned - - - 8/8/2010 12/6/2010 47 ENREP/W/17-e Rehabilitation of Palaipanikulam Mullaitivu Manthai East DC 3.83 0.03 Post LKR 3.83 FO, Palaipani 1.97 Actual - - - 10/4/2010 2/8/2011 On Progress Rehabilitation of Thanukankulam and Planned 12/6/2009 1/10/2010 - 8/8/2010 puvithara Civil 12/6/2010 48 ENREP/W/17-f Mullaitivu Manthai East NCB 5.26 0.05 Post LKR 4.46 - Periyathihilankulam Actual 11/29/2010 1/4/2011 - 1/25/2011 Engineering 7/8/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 49 ENREP/W/17-g Rehabilitation of Kompuvaithakulam Mullaitivu Manthai East DC 4.60 0.04 Post LKR 4.60 Vavnnivilankul 1.66 Actual - - - 10/4/2010 am 2/11/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 50 ENREP/W/17-h Rehabilitation of Moonrumuripukulam Mullaitivu Manthai East DC 4.42 0.04 Post LKR 4.42 2.60 Actual - - - 10/4/2010 Moonrumurippu 2/8/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 51 ENREP/W/17-i Rehabilitation of Siradikulam Mullaitivu Manthai East DC 3.53 0.03 Post LKR 3.53 1.01 Actual - - - 10/4/2010 Siraddikulam 2/8/2011 On Progress Planned - - - 9/19/2010 FO, 1/17/2011 52 ENReP/W/17-k Rehabilitation of Vandilkaddukulam Mullaitivu Manthai East DC 5.22 0.05 Post LKR 5.22 2.92 Actual - - - 10/4/2010 Ampalpuram 2/8/2011 On Progress Planned - - - 12/5/2010 FO, 4/4/2011 53 ENReP/W/30-a Rehabilitation of Salampankulam Mullaitivu Manthai East DC 4.00 0.04 Post LKR 4.07 Poovarasankula 1.54 Actual - - - 11/9/2010 m 3/16/2011 On Progress Planned 1/11/2010 2/15/2010 - 3/17/2010 Shyaam 3/17/2011 54 ENREP/W/18 Rehabilation of Mallavi, Thunukai Mullaitivu Thunukai NCB 36.9 0.33 Post LKR 28.94 19.02 Builders Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Shyaam 54 ENREP/W/18 Rehabilation of Mallavi, Thunukai Mullaitivu Thunukai NCB 36.9 0.33 Post LKR 28.94 19.02 Actual 6/26/2010 7/16/2010 - 7/28/2010 Builders 8/11/2011 On Progress Rehabilitation of Therankandal, Planned 1/11/2010 2/15/2010 - 3/17/2010 Edward & 3/17/2011 55 ENREP/W/20 Mullaitivu Thunukai NCB 24.7 0.22 Post LKR 20.90 5.52 Thunukai Actual 6/26/2010 7/16/2010 - 7/28/2010 Christe 8/23/2011 On Progress Planned 1/29/2010 3/5/2010 - 4/19/2010 Padmini 4/19/2011 56 ENREP/W/21 Rehabilitation of Iyankulam, Thunukai Mullaitivu Thunukai NCB 74.78 0.67 Post LKR 65.80 17.93 Actual 3/9/2011 7/9/2010 - 7/23/2010 Construction 8/6/2011 On Progress Planned 1/11/2010 2/15/2010 - 3/17/2011 Jathur 3/16/2012 57 ENREP/W/23 Rehabilation of Koddaikaddiyakulam Mullaitivu Thunukai NCB 34.94 0.31 Post LKR 39.11 1.23 Actual 03/09/2011 4/8/2011 - 4/18/2011 Enterprise 5/2/2012 On Progress Planned 1/11/2010 2/15/2010 - 3/17/2010 Shyaam 3/17/2011 58 ENREP/W/24 Rehabilation of Palayamurukandi Mullaitivu Thunukai NCB 41.00 0.37 Post LKR 32.57 5.12 Actual 9/3/2011 7/16/2010 - 8/9/2010 Builders 8/23/2011 On Progress Planned 1/29/2010 3/5/2010 - 4/19/2011 WMB 4/18/2012 59 ENREP/W/25 Rehabilation of Ampalaperumal Mullaitivu Thunukai NCB 72.08 0.65 Post LKR 68.49 Contractors & 10.54 Actual 3/9/2011 4/8/2011 - 4/25/2011 Transporters 6/9/2012 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 60 ENREP/W/26-a Rehabilitation of Vattaiadappukulam Mullaitivu Thunukai DC 4.70 0.04 Post LKR 4.83 Yogapuram - Actual - - - 8/19/2010 West 12/21/2010 On Progress Rehabilitation of Paddankadikulam and Planned 12/6/2009 1/10/2010 - 2/9/2010 SMS 6/9/2010 Terminated 61 ENREP/W/26-b Mullaitivu Thunukai NCB 8.71 0.08 Post LKR 6.57 - Asaipillai Kulam Actual 11/29/2010 1/4/2011 - 1/25/2011 Construction 6/8/2011 7/11/2011 Planned - - - 2/9/2010 6/9/2010 62 ENREP/W/26-c Rehabilitation of Murukankulam Mullaitivu Thunukai DC 4.77 0.04 Post LKR 4.77 FO, Thunukkai 2.60 Actual - - - 10/4/2010 2/8/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 63 ENREP/W/26-d Rehabilitation of Karampaikulam Mullaitivu Thunukai DC 4.25 0.04 Post LKR 4.25 3.22 Actual - - - 10/4/2010 Therankandal 2/8/2011 On Progress Karunya Civil Planned 7/16/2010 8/20/2010 - 9/19/2010 3/18/2011 64 ENReP/W/29-a Rehabilitation of Ampakamamkulam Mullaitivu Oddusuddan NCB 10.17 0.09 Post LKR 7.80 Engineering - Actual 11/29/2010 1/4/2011 - 1/25/2011 Contractors 7/8/2011 On Progress Planned - - - 12/5/2010 4/4/2011 65 ENReP/W/29-b Rehabilitation of Kodalikalukulam Mullaitivu Oddusuddan DC 4.95 0.04 Post LKR 4.95 Fo, Kodalikallu 2.13 Actual - - - 2/28/2011 6/5/2011 On Progress Rehabilitation of Olumadukulam and Oddusuddan, Planned 7/16/2010 8/20/2010 - 9/19/2010 SMA 3/18/2011 66 ENReP/W/29-c Mullaitivu NCB 9.97 0.09 Post LKR 9.85 2.32 Periyapuliyankulam Maritimepattu Actual 11/29/2010 1/4/2011 - 1/25/2011 Construction 7/8/2011 On Progress Planned - - - 9/19/2010 1/17/2011 67 ENReP/W/29-d Rehabilitation of Thavasikulam Mullaitivu Oddusuddan DC 2.95 0.03 Post LKR 3.00 F.O, Palampasi - Actual - - - 11/9/2010 3/15/2011 On Progress Planned - - - 9/19/2010 FO, 1/17/2011 68 ENReP/W/29-e Rehabilitation of Periyakulam Mullaitivu Oddusuddan DC 4.45 0.04 Post LKR 4.53 2.07 Actual - - - 11/9/2010 Periyakulam 3/16/2011 On Progress Planned - - - 9/19/2010 FO, 7th Mile 1/17/2011 69 ENReP/W/29-f Rehabilitation of Palampasikulam Mullaitivu Oddusuddan DC 3.91 0.04 Post LKR 3.91 post 0.54 Actual - - - 11/9/2010 Karadipallavu 3/16/2011 On Progress Rehabilitation of Kuruvichchai Anicut Planned 7/16/2010 8/20/2010 - 9/19/2010 1/17/2011 70 ENReP/W/29-j Mullaitivu Oddusuddan NCB 12.00 0.11 Post LKR 10.15 Abdul Azeez 2.45 and Kakkaipanikkankulam Actual 11/29/2010 1/4/2011 - 1/25/2011 7/8/2011 On Progress Planned - - - 12/5/2010 4/4/2011 71 ENReP/W/29-k Rehabilitation of Puthirirruppukulam Mullaitivu Oddusuddan DC 2.00 0.02 Post LKR 2.01 FO, Mankulam 0.80 Actual - - - 11/9/2010 2/14/2011 On Progress Rehabilitation of Periyakulam in Planned - - - 2/9/2010 FO, 7/9/2010 72 ENREP/W/28-a Vavuniya Vavuniya North DC 3.78 0.03 Post LKR 3.41 1.74 Kanagarayankulam ASC Actual - - - 6/14/2010 Periyakulam 11/20/2010 On Progress Planned - - - 2/9/2010 FO, 7/9/2010 Rehabilitation of kurisuddakulam in 73 ENREP/W/28-b Vavuniya Vavuniya North DC 2.41 0.02 Post LKR 2.18 Kanakarayankul 1.29 Kanagarayankulam ASC Actual - - - 5/12/2010 10/12/2010 On Progress am South Planned - - - 2/9/2010 FO, 6/9/2010 Rehabilitation of Kunriddamadukulam 74 ENREP/W/28-c Vavuniya Vavuniya North DC 3.27 0.03 Post LKR 2.95 Puliyankulam 0.98 in Kanagarayankulam ASC Actual - - - 6/18/2010 10/12/2010 On Progress North Planned - - - 2/9/2010 FO, 6/9/2010 Rehabilitation of Aanaipooddiyakulam 75 ENREP/W/28-d Vavuniya Vavuniya North DC 2.23 0.02 Post LKR 2.01 Puliyankulam 0.91 in Kanagarayankulam ASC Actual - - - 6/18/2010 10/26/2010 On Progress North Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehabilitation of Karappukuththi kulam Planned - - - 2/9/2010 FO, 6/9/2010 76 ENREP/W/28-e Vavuniya Vavuniya North DC 4.99 0.04 Post LKR 4.49 1.66 in Kanagarayankulam ASC Actual - - - 6/4/2010 Sinnadampan 11/11/2010 On Progress Rehabilitation of Nedunkerneykulam in Planned - - - 2/9/2010 7/9/2010 77 ENREP/W/28-f Vavuniya Vavuniya North DC 5.32 0.05 Post LKR 4.79 FO, Olumadu 1.00 Nedunkerney ASC Actual - - - 6/14/2010 11/13/2010 On Progress Rehabilitation of Mamadukkulam in Planned - - - 2/9/2010 FO, 8/9/2010 Completed 78 ENREP/W/28-g Vavuniya Vavuniya North DC 3.65 0.03 Post LKR 3.29 1.75 Nedunkerney ASC Actual - - - 6/18/2010 Mamadukulam 12/2/2010 7/30/2011 Planned - - - 2/9/2010 FO, 6/9/2010 Rehabilitation of Maruthankulam in 79 ENREP/W/28-h Vavuniya Vavuniya North DC 2.35 0.02 Post LKR 2.12 Nedunkerny 0.49 Nedunkerney ASC Actual - - - 6/18/2010 10/26/2010 On Progress South Planned - - - 2/9/2010 FO, 6/9/2010 Rehabilitation of Rambaikulam in 80 ENREP/W/28-i Vavuniya Vavuniya North DC 2.39 0.02 Post LKR 2.15 Nedunkerny 0.72 Nedunkerney ASC Actual - - - 6/18/2010 10/26/2010 On Progress South Rehabilitation of Kulavisuddan Planned - - - 2/9/2010 FO, 7/9/2010 81 ENREP/W/28-j Vavuniya Vavuniya North DC 3.20 0.03 Post LKR 2.88 0.21 Periyakulam in Nedunkerney ASC Actual - - - 7/19/2010 Kulavisuddan 12/30/2010 On Progress Planned - - - 2/9/2010 FO, 7/9/2010 82 ENREP/W/28-l Rehabilitation of Puthuvilankulam Vavuniya Vavuniya North DC 3.58 0.03 Post LKR 3.23 0.79 Actual - - - 9/24/2010 Mannakulam 2/1/2011 On Progress Planned - - - 2/9/2010 FO, 6/9/2010 83 ENREP/W/28-n Rehabilitation of Sadavankulam Vavuniya Vavuniya North DC 2.02 0.02 Post LKR 1.82 0.44 Actual - - - 9/6/2010 Sinnadampan 1/19/2011 On Progress Planned 12/6/2009 1/10/2010 - 2/9/2010 Ajith 8/9/2010 84 ENREP/W/28-o Rehabilitation of Palaiyavadikulam Vavuniya Vavuniya North NCB 6.70 0.06 Post LKR 5.42 1.15 Actual 9/27/2010 11/4/2010 - 12/3/2010 Construction 6/15/2011 On Progress Planned - - - 2/9/2010 FO, Mara 6/9/2010 85 ENREP/W/28-p Rehabilitation of Koththankulam Vavuniya Vavuniya North DC 5.50 0.05 Post LKR 4.95 3.27 Actual - - - 9/9/2010 Eluppai 1/19/2011 On Progress Planned - - - 2/9/2010 7/9/2010 86 ENREP/W/28-s Rehabilitation of Theevukadupankulam Vavuniya Vavuniya North DC 2.20 0.02 Post LKR 1.98 FO,Olumadhu 0.54 Actual - - - 9/1/2010 2/10/2011 On Progress Planned - - - 2/9/2010 6/9/2010 87 ENREP/W/28-t Rehabilitation of Ariyamadukulam Vavuniya Vavuniya North DC 4.60 0.04 Post LKR 4.14 F.O,Nochcikula 0.45 Actual - - - 8/9/2010 m 12/16/2010 On Progress Planned - - - 9/19/2010 FO, 3/18/2011 ENREP/W/28- 88 Rehabilitation of Nochchikulam Vavuniya Vavuniya North DC 3.55 0.03 Post LKR 3.2 Anantharpuliya 0.54 ad Actual - - - 10/21/2010 3/3/2011 On Progress nkulam ENREP/W/28- Planned - - - 10/1/2010 FO, 3/30/2011 89 Rehabilitation of Thuvarankulam Vavuniya Vavuniya North DC 2.15 0.02 Post LKR 2.15 1.15 ak Actual - - - 10/19/2010 Thuvarankulam 2/10/2011 On Progress Planned - - - 10/1/2010 FO, 2/1/2011 Completed ENREP/W/28- 90 Rehabilitation of Puthukulam Vavuniya Vavuniya North DC 1.53 0.01 Post LKR 1.53 Muththumari 1.23 an Actual - - - 10/8/2010 2/15/2011 6/15/2011 Amman ENREP/W/28- Planned - - - 10/1/2010 2/1/2011 Completed 91 Rehabilitation of Sinnaparanthankulam Vavuniya Vavuniya North DC 2.76 0.02 Post LKR 2.76 FO, Paranthan 2.33 ap Actual - - - 10/19/2010 2/25/2011 7/10/2011 ENREP/W/28- Planned - - - 10/1/2010 FO, 2/1/2011 Completed 92 Rehabilitation of Moonrumurippu Vavuniya Vavuniya North DC 3.53 0.03 Post LKR 3.53 3.28 aq Actual - - - 10/5/2010 Mathiyamadu 2/9/2011 3/28/2011 Planned - - - 10/7/2010 FO, 2/5/2011 93 ENREP/W/28-ar Rehabilitation of Mathiyamadu Vavuniya Vavuniya North DC 4.18 0.04 Post LKR 4.18 3.60 Actual - - - 10/16/2010 Mathiyamadu 2/22/2011 On Progress Planned 8/3/2010 9/7/2010 - 10/7/2010 Ajani 4/5/2011 94 ENREP/W/28-at Rehabilitation of Anantharpuliyankulam Vavuniya Vavuniya North NCB 3.97 0.04 Post LKR 3.19 1.10 Actual 10/30/2010 12/3/2010 - 12/22/2010 Construction 6/4/2010 On Progress ENREP/W/28- Planned - - - 10/7/2010 FO, 3/5/2011 95 Rehabilitation of Karadijankulam Vavuniya Vavuniya North DC 2.54 0.02 Post LKR 2.54 1.18 au Nainamadu Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O ENREP/W/28- FO, 95 Rehabilitation of Karadijankulam Vavuniya Vavuniya North DC 2.54 0.02 Post LKR 2.54 1.18 au Actual - - - 10/21/2010 Nainamadu 3/11/2011 On Progress ENREP/W/28- Planned - - - 10/7/2010 FO, 4/5/2011 96 Rehabilitation of Periyamadukulam Vavuniya Vavuniya North DC 1.25 0.01 Post LKR 1.12 0.75 av Actual - - - 10/26/2010 Periyamadu 3/1/2011 On Progress ENREP/W/28- Planned - - - 12/5/2010 6/3/2011 Completed 97 Rehabilitation of Sannasiparanthan Vavuniya Vavuniya North DC 3.19 0.03 Post LKR 3.19 FO, Paranthan 2.90 bg Actual - - - 10/19/2010 2/25/2011 7/10/2011 Planned - - - 9/19/2010 3/18/2011 98 ENREP/W/28-w Rehabilitation of Arasankulam Vavuniya Vavuniya DC 5.14 0.05 Post LKR 5.14 F.O,Asikulam 0.21 Actual - - - 9/27/2010 2/3/2011 On Progress Planned - - - 9/19/2010 3/18/2011 99 ENREP/W/28-y Rehabilitation of Sinnalankulam Vavuniya Vavuniya DC 4.56 0.04 Post LKR 4.65 F.O,Mamadhu 2.21 Actual - - - 8/19/2010 12/23/2010 On Progress Planned - - - 9/19/2010 FO, 3/18/2011 100 ENREP/W/28-z Rehabilitation of Vairavarsinnakulam Vavuniya Vavuniya DC 2.09 0.02 Post LKR 2.13 0.89 Actual - - - 8/18/2010 Veemankallu 12/21/2010 On Progress Planned - - - 9/19/2010 FO, 3/18/2011 ENREP/W/28- 101 Rehabilitation of Aththikulam Vavuniya Vavuniya DC 2.62 0.02 Post LKR 2.62 Periyavilaththik 1.26 ab Actual - - - 10/21/2010 2/3/2011 On Progress ulam ENREP/W/28- Rehabilitation of Kothandar Planned - - - 10/7/2010 FO, 4/5/2011 Completed 102 Vavuniya Vavuniya DC 4.59 0.04 Post LKR 4.67 2.69 ax Nochchikulam Actual - - - 9/9/2010 Suriyothayam 1/14/2011 6/20/2011 ENREP/W/28- Planned - - - 10/7/2010 FO, 4/5/2011 Completed 103 Rehabilitation of Kallikulam Vavuniya Vavuniya DC 2.19 0.02 Post LKR 2.19 1.42 ay Actual - - - 9/14/2010 Echchankulam 1/22/2011 6/25/2011 ENREP/W/28- Planned - - - 10/7/2010 4/5/2011 104 Rehabilitation of Ariyan Kurisudakulam Vavuniya Vavuniya DC 3.87 0.03 Post LKR 3.87 FO, Kalmadu 3.70 az Actual - - - 9/17/2010 1/25/2011 On Progress Planned - - - 10/1/2010 FO, 3/30/2011 Completed 105 ENREP/W/28-aj Rehabilitation of Peyadikulankulam Vavuniya Vavuniya DC 2.89 0.03 Post LKR 2.89 1.50 Actual - - - 11/9/2010 Nochchimoddai 3/16/2011 7/14/2011 Planned - - - 12/5/2010 FO, 6/3/2011 ENREP/W/28- 106 Rehabilitation of Kovilmoddaikulam Vavuniya Vavuniya DC 3.98 0.04 Post LKR 3.98 Poovarasankula 2.75 be Actual - - - 10/20/2010 3/2/2011 On Progress m Planned - - - 12/5/2010 FO, 6/3/2011 Completed 107 ENREP/W/28-bf Rehabilitation of Nelvelikkulam Vavuniya Vavuniya DC 3.64 0.03 Post LKR 3.64 Kompuvaithaku 2.55 Actual - - - 10/1/2010 lam 2/18/2011 7/18/2011 ENREP/W/28- Planned - - - 10/7/2010 4/5/2011 108 Rehabilitation of Kelebogaswewa tank Vavuniya Vavuniya South DC 4.22 0.04 Post LKR 4.32 FO,Eropothana 1.15 ba Actual - - - 8/30/2010 2/3/2011 On Progress ENREP/W/28- Planned - - - 12/5/2010 Fo, 6/3/2011 Completed 109 Rehabilitation of Kalayanoorkulam Vavuniya Vavuniya South DC 4.31 0.04 Post LKR 3.89 2.26 bc Actual - - - 9/27/2010 Rangethkama 2/1/2011 5/31/2011 Planned - - - 9/19/2010 Fo, 3/18/2011 Completed ENREP/W/28- 110 Rehabilitation of Puliyankulama Vavuniya Vavuniya South DC 4.23 0.04 Post LKR 4.23 Mahakachchiko 1.86 ac Actual - - - 10/11/2010 2/15/2011 5/18/2011 diya Planned 1/29/2010 3/5/2010 - 4/19/2010 Mega 1/14/2011 111 ENREP/W/37 Rehabilitation of Kanagarayankulam, Vavuniya Vavuniya North NCB 34.74 0.31 Post LKR 32.11 14.47 Actual 6/26/2010 7/16/2010 - 7/23/2010 Construction 8/6/2011 On Progress Rehabilitation of Kalmadu Tank in Planned 1/1/2011 2/5/2011 - 3/22/2011 WMB 12/17/2011 112 ENREP/W/410 Vavuniya Vavuniya NCB 64.15 0.58 Post LKR 60.91 11.62 vavuniya Actual 3/8/2011 3/8/2011 - 5/20/2011 Construction 6/2/2012 On Progress Planned 1/1/2011 2/5/2011 - 3/22/2011 SSK 12/17/2011 113 ENREP/W/412 Rehabilitation of Rasenthirakulam Vavuniya Cheddikulam NCB 46.3 0.42 Post LKR 43.02 - Actual 6/30/2011 7/29/2011 - 5/8/2011 Construction 5/7/2012 On Progress Rehabilitation of MahaKachchakodiya Planned 10/31/2010 12/5/2010 - 1/19/2011 Ajani 10/16/2011 Terminated 114 ENREP/W/411 Vavuniya Vavuniya South NCB 34.35 0.31 Post LKR 29.29 2.54 Tank, Actual 11/29/2010 1/4/2011 - 2/10/2011 Construction 2/24/2012 11/11/2011 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned 1/1/2011 2/5/2011 - 3/22/2011 Rajarata 12/17/2011 115 ENREP/W/413 Rehabilitation of Iraipothana tank Vavuniya Vavuniya South NCB 32.67 0.29 Post LKR 26.95 12.03 Actual 3/8/2011 4/8/2011 - 4/25/2011 Construction 5/8/2012 On Progress Rehabilitation of Mahakachakodiya Planned 5/10/2012 - 4/24/2012 Jathur 10/16/2011 On Progress 116 ENREP/W/400 Vavuniya Vavuniya South NS 21.5 0.19 Post LKR 20.87 Tank balance work at Vavuniya Actual 6/1/2012 - 5/23/2012 Enterprises 10/15/2012 Planned 9/2/2012 - SMA 117 ENREP/W/401 Rehab.of Kalabogaswewa Tank Pack - II Vavuniya Vavuniya South NS 19.9 0.18 Post LKR 24.87 Actual 9/5/2012 - Construction Planned 9/2/2012 - SMA 118 ENREP/W/402 Rehab.of Kalabogaswewa Tank Pack - I Vavuniya Vavuniya South NS 16.0 0.14 Post LKR 23.45 Actual 9/5/2012 - Construction Construction of Emergency need of Planned - 119 ENREP/W/403 Water in the bed of tank at Vavuniya Vavuniya Vavuniya South DC 1.05 0.01 Post South Actual - Construction of Arugampuleliya Anicut Planned - - - 120 ENREP/W/404 Vavuniya Vavuniya South 10 0.09 Post - in Vavuniya South Actual - - C2 Rural Access Roads Rehabilitation of Roads in Planned 12/6/2009 1/10/2010 - 2/9/2010 Master 8/8/2010 122 ENREP/W/38 Jaffna Maruthankerni NCB 26.50 0.24 Post LKR 22.63 12.75 Maruthankerny Package-01 Actual 5/10/2010 7/9/2010 - 7/23/2010 Builders 2/2/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehabilitation of Roads in Planned 12/6/2009 1/10/2010 - 2/9/2010 Jathur 8/8/2010 123 ENREP/W/39 Jaffna Maruthankerni NCB 40.20 0.36 Post LKR 33.46 19.42 Maruthankerny Package-02 Actual 7/8/2010 8/10/2010 - 9/9/2010 Enterprises 3/22/2011 On Progress Reconstruction of Roads in Planned 12/6/2009 1/10/2010 - 2/9/2010 Master 8/8/2010 124 ENREP/W/40 Jaffna Maruthankerni NCB 39.00 0.35 Post LKR 26.53 4.51 Maruthankerny Jaffna Package 3 Actual 9/27/2010 11/4/2010 - 12/3/2010 Builders 6/15/2011 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 A Group 6/3/2011 125 ENREP/W/261 Jaffna Maruthankerni NCB 52.83 0.48 Post LKR 44.31 7.36 Mathurankerny Package 4, Jaffna Actual 10/30/2010 12/3/2010 - 12/28/2010 Construction 7/10/2010 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 SMA 6/3/2011 Terminated 126 ENREP/W/262 Jaffna Maruthankerni NCB 50.87 0.46 Post LKR 35.28 5.69 Maruthankerney, Jaffna- Package 5 Actual 2/8/2011 3/8/2011 - 4/7/2011 Construction 10/18/2011 Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 Shakthi Civil 6/3/2011 127 ENREP/W/263 Jaffna Maruthankerni NCB 43.41 0.39 Post LKR 33.98 7.31 Maruthankerney, Jaffna- Package 6 Actual 2/8/2011 3/8/2011 - 4/7/2011 Construction 10/18/2011 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 SMA 6/3/2011 128 ENREP/W/264 Jaffna Maruthankerni NCB 39.86 0.36 Post LKR 33.09 18.92 Maruthankerney, Jaffna- Package 7 Actual 2/8/2011 3/8/2011 - 4/11/2011 Construction 10/22/2011 On Progress Planned 10/1/2010 11/5/2010 - 12/5/2010 Eurivile 6/3/2011 Rehabilitation of Internal Roads in 129 ENREP/W/414 Jaffna Jaffna Town NCB 23.43 0.21 Post LKR 20.47 Engineers And 9.40 Jaffna MC Area, Jaffna Actual 11/29/2010 1/4/2011 - 2/1/2011 8/14/2011 On Progress Contractors Hospital Repair of Interior Roads within the Planned - - - 2/3/2011 Development 6/3/2011 130 ENREP/W/415 Jaffna Jaffna Town DC 3.02 0.03 Post LKR 3.02 - Jaffna Teaching Hospital Actual - - - 12/22/2011 Society, 3/3/2011 On Progress Teaching Rehabilitation of Internal Road in Planned 10/1/2010 11/5/2010 - 12/5/2010 Master 6/3/2011 131 ENREP/W/415 Jaffna Vali North NCB 37.69 0.34 Post LKR 30.24 9.23 Valikamam North, Jaffna Actual 10/30/2010 12/3/2010 - 12/22/2010 Builders 7/4/2010 On Progress Rehabilitation of Internal Roads in Planned 9/25/2010 10/30/2010 - 1/28/2011 Leading 7/27/2011 132 ENREP/W/32 Jaffna Vali North NCB 33.12 0.30 Post LKR 24.75 19.89 Valikamam North, Jaffna- Package 2 Actual 2/8/2011 3/8/2011 - 4/7/2011 Crusher Works 10/18/2011 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 Leading 6/3/2011 133 ENREP/W/265 Jaffna Vali North NCB 27.93 0.25 Post LKR 21.03 1.63 Valikamam North, Jaffna- Package 3 Actual 3/8/2011 3/8/2011 - 4/25/2011 Crusher Works 11/5/2011 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 Koneswaran 6/3/2011 134 ENREP/W/267 Jaffna Kopay NCB 45.41 0.41 Post LKR 37.84 27.88 Valimamam East, Jaffna Actual 10/30/2010 12/3/2010 - 12/28/2010 Engineering 7/10/2010 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 Benaal 6/3/2011 135 ENREP/W/416 Jaffna Uduvil NCB 56.98 0.51 Post LKR 45.52 22.92 Valikamam South, Jaffna Actual 10/30/2010 12/3/2010 - 12/28/2010 Constryction 7/10/2010 On Progress Rehabilitation of Internal Roads in Planned 10/1/2010 11/5/2010 - 12/5/2010 Benaal 6/3/2011 136 ENREP/W/417 Jaffna Chavakachcheri NCB 63.09 0.57 Post LKR 51.18 11.72 Chavakachcheri, Jaffna Actual 11/29/2010 1/4/2011 - 2/1/2011 construction 10/13/2011 On Progress Rehabilation of Metaling u Sampalodai Planned - - 7/15/2012 - 7/30/2012 Sairam 11/20/2012 137 ENREP/W/418 Jaffna Maruthankerny NS 17.7 0.18 Post LKR 16.69 - Veethy at Karainagar Actual - - 8/6/2012 - 8/9/2012 Contractor Rehabilitation of Thanippanai Veethy Planned - - 7/10/2012 - 7/25/2012 Sairam 11/20/2012 138 ENREP/W/419 Jaffna Maruthankerny NS 10.7 0.11 Post LKR 10.01 - Metling and Tarring Actual - - 8/6/2012 - 8/9/2012 Contractor Rehabilitation of Arasady veethy Planned - - 139 ENREP/W/420 Jaffna Maruthankerny NS Post - vathrajan in Maruthankerny in Jaffna Actual - - Rehab.of Mudipillaiyar Road in Velanai Planned - - 140 ENREP/W/421 Jaffna Velanai NS 20.8 Post - at Jaffna Actual - - Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehab.of Sudaaliveethy in Allaipiddy Planned - - 141 ENREP/W/422 Jaffna NS 10.3 Post - Jaffna Actual - - Planned - - 142 ENREP/W/423 Rehab.of Karainagar Package -I Jaffna Karainagar NS 20 Post - Actual - - Rehabilitation of Roads in Karachchi, Planned 12/6/2009 1/10/2010 - 2/9/2010 A Group (Pvt) 9/7/2010 143 ENREP/W/41 Kilinochchi Karachchi NCB 6.10 0.05 Post LKR 4.11 3.56 Kilinochchi- Pacakge-01 Actual 7/8/2010 8/10/2010 - 9/9/2010 Ltd. 3/22/2011 On Progress Planned 12/6/2009 1/10/2010 - 2/9/2010 D.S 9/7/2010 Terminated Rehabilitation of Roads in Karachchi, 144 ENREP/W/42 Kilinochchi Karachchi NCB 23.40 0.21 Post LKR 15.30 Construction & 1.96 Kilinochchi- Pacakge-02 Actual 7/8/2010 8/10/2010 - 9/9/2010 2/26/2011 6/13/2011 Earth Movers Rehabilitation of Roads in Karachchi, Planned 12/6/2009 1/10/2010 - 2/9/2010 C&C 9/7/2010 145 ENREP/W/43 Kilinochchi Karachchi NCB 19.30 0.17 Post LKR 14.48 9.00 Kilinochchi- Pacakge-03 Actual 7/8/2010 8/10/2010 - 9/9/2010 Engineering 3/22/2011 On Progress Rehabilitation of Elephant Pass - Planned - - - 5/15/2011 Karachchi 9/12/2011 146 ENREP/W/578 Kilinochchi Karachchi DC 1.93 0.02 Post LKR 1.93 0.55 Thadduvankoddi Road, Kilinochchi Actual - - - 5/30/2011 South MPCS 10/1/2011 On Progress Rehabilitation of Roads in Kandawalai, Planned 12/6/2009 1/10/2010 - 2/9/2010 9/7/2010 147 ENREP/W/44 Kilinochchi Kandavalai NCB 18.40 0.17 Post LKR 13.82 C&C Eng. 6.83 Kilinochchi- Package-01 Actual 7/8/2010 8/10/2010 - 9/9/2010 3/22/2011 On Progress Planned 12/6/2009 1/10/2010 - 2/9/2010 D.S 9/7/2010 Terminated Rehabilitation of Roads in Kandawalai, 148 ENREP/W/45 Kilinochchi Kandavalai NCB 19.60 0.18 Post LKR 12.80 Construction & 0.78 Kilinochchi- Pacakge-02 Actual 7/8/2010 8/10/2010 - 9/9/2010 3/22/2011 6/13/2011 Earth Movers Rehabilitation of Roads in Kandawalai, Planned 12/6/2009 1/10/2010 - 2/9/2010 AMM Welding 9/7/2010 149 ENREP/W/46 Kilinochchi Kandavalai NCB 11.40 0.10 Post LKR 9.74 9.31 Kilinochchi – Package 03 Actual 7/8/2010 8/10/2010 - 9/24/2010 Workshop 4/6/2011 On Progress Rehabilitation of Roads in Kandawalai, Planned 12/6/2009 1/10/2010 - 2/9/2010 Vanaja 9/7/2010 150 ENREP/W/47 Kilinochchi Kandavalai NCB 11.90 0.11 Post LKR 10.49 9.31 Kilinochchi – Package 04 Actual 7/8/2010 8/10/2010 - 9/24/2010 Construction 4/6/2011 On Progress Rehabilitation of Roads in Poonery, Planned 12/6/2009 1/10/2010 - 2/9/2010 Edward & 9/7/2010 151 ENREP/W/48 Kilinochchi Pooneryn NCB 15.00 0.14 Post LKR 10.48 8.51 Package 01 Christe Actual 6/26/2010 7/16/2010 - 7/28/2010 2/7/2011 On Progress Rehabilitation of Road in Poonaryan Planned 12/6/2009 1/10/2010 - 2/9/2010 Land Mark 9/7/2010 Terminated 152 ENREP/W/49 Kilinochchi Pooneryn NCB 10.80 0.10 Post LKR 8.49 0.02 Package 02 Eng. Actual 6/26/2010 7/16/2010 - 8/9/2010 2/19/2011 7/19/2011 Planned 12/6/2009 1/10/2010 - 2/9/2010 Subramaniam 9/7/2010 Terminated Rehabilitation of Road in Poonaryan 153 ENREP/W/50 Kilinochchi Pooneryn NCB 12.90 0.12 Post LKR 9.57 Civil 0.03 Package 03 Actual 6/26/2010 7/16/2010 - 8/25/2010 Engineering 3/7/2011 7/19/2011 Rehabilitation of Road in Poonaryan Planned 12/6/2009 1/10/2010 - 2/9/2010 Ragal 9/7/2010 154 ENREP/W/51 Kilinochchi Pooneryn NCB 15.20 0.14 Post LKR 12.37 9.39 Package 04 Construction Actual 6/26/2010 7/16/2010 - 8/25/2010 3/7/2011 On Progress Kilinochchi Planned - - - 2/9/1900 9/7/2010 Improvement of Approach Road to Co- District Women 155 ENREP/W/52 Kilinochchi Pooneryn DC 2.98 0.03 Post LKR 40.91 - operative Council in Kilinochchi. Development Actual - - - 12/26/2011 4/27/2012 On Progress Federation. Rehabilitation of Roads in Karachchi, Planned 7/10/2012 12/21/2012 156 ENREP/W/42 Kilinochchi Karachchi NS 12.50 0.12 Post LKR 9.30 K.P.K.Construc Kilinochchi- Pacakge-02 Balance work Actual 8/3/2012 tion Rehabilitation of Roads in Kandawalai, Planned 7/12//2012 S.R.M. 12/12/2012 157 ENREP/W/45 Kilinochchi Kandavalai NS 11.58 0.11 Post LKR 11.96 - Kilinochchi- Pacakge-02 balance work Actual 8/3/2012 Construction Rehabilitation of Road in Poonaryan Planned 7/5/2012 5/3/2009 12/21/2012 158 ENREP/W/50 Kilinochchi Pooneryn NS Post LKR - Cancelled Package 03 Actual 8/3/2012 9/21/2009 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Metaling & Tarring of Ponthor Planned 7/12/2012 - 7/25/2012 Jathur 11/15/2012 - 159 ENREP/W/51 Kilinochchi Pachilaipalli NS 19.08 0.17 Post LKR 18.03 - Kudiyiruppu Road (Package-1) Enterprises Actual 7/30/2012 - 8/8/2012 - Metaling & Tarring of Malayankanthan Planned 7/10/2012 - 7/25/2012 11/15/2012 - Road, Graveling ross Roads, Jungle Jathur 160 ENREP/W/51 Kilinochchi Pachilaipalli NS 17.79 0.16 Post LKR 17.21 - Clearing & Security Bund Clearing at Enterprises Actual 7/30/2012 - 8/8/2012 - Muhamalai Construction of Box culvert at Planned - - 161 ENREP/W/52 Krishnapuram focal village in Kilinochchi NS Post LKR - Kilinonchchi Actual - - Planned - - Skanthapuram Maniyankulam link road 162 ENREP/W/53 Kilinochchi NS Post LKR - 1.4Km Actual - - Planned - - Ramanathapuram Kalmadunagar road 163 ENREP/W/54 Kilinochchi NS Post LKR - 0.8Km Actual - - Ananthapuram Thurkkaiamman road Planned - - 164 ENREP/W/55 Uthayanagar east and west cross road Kilinochchi NS Post LKR - 1.8Km Actual - - Planned - - Metaling and Taring of Ponthor 165 ENREP/W/56 Kilinochchi NS Post LKR - Kudiyiruppu road, Package 1 Actual - - Metaling and Taring of Malayankanthan Planned - - 166 ENREP/W/57 road, cross road, Bund clearing Package Kilinochchi NS Post LKR - 2 Actual - - Rehabilitation of Approach road to dri 167 ENREP/W/417 Kilinochchi Karachchi DC 2.07 - - aru tank in kilinochchi Rehabilitation of Roads in Manthai Planned 12/6/2009 1/10/2010 - 2/9/2010 A Group (Pvt) 9/7/2010 Completed 168 ENREP/W/52 Mannar Manthai West NCB 10.00 0.09 Post LKR 7.05 6.69 West- Package 1 Actual 4/20/2010 5/25/2010 - 6/30/2010 Ltd. 1/10/2011 1/15/2011 Rehabilitation of Roads in Manthai Planned 12/6/2009 1/10/2010 - 2/9/2010 Sanjeeve 9/7/2010 Completed 169 ENREP/W/53 Mannar Manthai West NCB 9.20 0.08 Post LKR 7.29 7.04 West- Package 2 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction. 1/10/2011 12/3/2010 Rehabilitation of Roads in Manthai Planned 12/6/2009 1/10/2010 - 2/9/2010 Mahadevan 9/7/2010 Completed 170 ENREP/W/54 Mannar Manthai West NCB 10.00 0.09 Post LKR 7.37 7.17 West- Package 3 Actual 4/20/2010 5/25/2010 - 6/30/2010 Contractors. 1/10/2011 4/24/2011 Planned 12/6/2009 1/10/2010 - 2/9/2010 R&S 9/7/2010 Completed Rehabilitation of Roads in Manthai 171 ENREP/W/55 Mannar Manthai West NCB 11.00 0.10 Post LKR 8.16 Eng.Constructio 7.05 West- Package 4 Actual 4/20/2010 5/25/2010 - 6/30/2010 1/10/2011 4/20/2011 n. Rehabilitation of Internal Roads in Planned 12/6/2010 1/10/2011 - 2/9/2011 Edward & 9/7/2011 172 ENREP/W/421 Mannar Manthai West NCB 34.64 0.31 Post LKR 21.21 3.38 Manthai West, Mannar- Package 5 Actual 1/20/2011 3/8/2011 - 4/7/2011 Christie 10/18/2011 On Progress Rehabilitation of Roads in Madhu- Planned 12/6/2009 1/10/2010 - 2/9/2010 Santhiyapillai 9/7/2010 Completed 173 ENREP/W/56 Mannar Madhu NCB 9.00 0.08 Post LKR 6.44 5.90 Package 1 Actual 4/20/2010 5/25/2010 - 6/30/2010 &Sons 1/10/2011 12/20/2010 Rehabilitation of Roads in Madhu- Planned 12/6/2009 1/10/2010 - 2/9/2010 Sri Arans Civil 9/7/2010 174 ENREP/W/57 Mannar Madhu NCB 14.00 0.13 Post LKR 7.61 - Package 2 Actual 3/8/2011 4/8/2011 - 4/25/2011 Contractors 11/5/2011 On Progress Rehabilitation of Roads in Madhu- Planned 12/6/2009 1/10/2010 - 2/9/2010 Jana Civil 9/7/2010 Completed 175 ENREP/W/58 Mannar Madhu NCB 11.00 0.10 Post LKR 7.70 7.30 Package 3 Actual 4/20/2010 5/25/2010 - 6/30/2010 Works. 1/10/2011 4/20/2011 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehabilitation of Roads in Madhu- Planned 12/6/2009 1/10/2010 - 2/9/2010 Jana Civil 9/7/2010 Completed 176 ENREP/W/59 Mannar Madhu NCB 6.00 0.05 Post LKR 3.62 3.50 Package 4 Actual 4/20/2010 5/25/2010 - 6/30/2010 Works. 1/10/2011 4/20/2011 Rehabilitation of Internal Roads in Planned 12/6/2010 1/10/2011 - 2/9/2011 Leading 9/7/2011 177 ENREP/W/422 Mannar Madhu NCB 22.46 0.20 Post LKR 15.95 2.61 Madhu, Mannar- Package 5 Actual 1/20/2011 3/8/2011 - 4/7/2011 Crusher Works 10/18/2011 On Progress Rehabilitation of Periyapandiviruchchan Planned 7/12/2012 - 7/28/2012 11/14/2012 Agriculture Road including Mataling tar Priyanka 178 ENREP/W/423a Mannar Madhu NS 16.05 0.14 Post LKR 15.25 and Gravel Road at Madu AGA Conionstruct Actual 7/30/2012 - 8/15/2012 Division Planned 7/5/2012 - 7/25/2012 Pastini 11/14/2012 179 ENREP/W/424b Rehabilitation of Variveli Tank Road Mannar Musali NS 10.01 0.09 Post LKR 9.67 Construction Actual 7/30/2012 - 8/15/2012 Rehabilitation of Sinnathmoddai Tank Planned - 180 ENREP/W/425c Mannar Mannar NS Post LKR road Actual - Rehabilitation of Agriculture road at Planned 181 ENREP/W/428 Thetaveli including metaling tar gravel Mannar Mannar NS Post road Actual Rehabilitation of Internal Roads in Planned 12/6/2010 1/10/2011 - 2/9/2011 Edward & 9/7/2011 182 ENREP/W/423 Mannar Musali NCB 23.73 0.21 Post LKR 18.23 2.95 Musali, Mannar Actual 1/20/2011 3/8/2011 - 4/7/2011 Christie 10/18/2011 On Progress Rehabilitation of Narikkadu Housing Planned Priyanka 183 ENReP/W/510 Mannar Nanaddan NS Post Scheme road in Nanaddan Actual Conionstruct Rehabilitation of Internal Roads in Planned 12/6/2009 1/10/2010 - 2/9/2010 Lanka Machine 9/7/2010 184 ENREP/W/60 Mullaitivu Thunukai NCB 22.33 0.20 Post LKR 19.04 3.10 Thunukkai, Mullaitivu- Package 1 Actual 2/1/2011 3/8/2011 - 4/7/2011 Leasers 10/18/2011 On Progress Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 Mega 9/7/2010 185 ENREP/W/61 Mullaitivu Thunukai NCB 18.00 0.16 Post LKR 15.07 5.80 Package 2 Actual 4/20/2010 5/25/2010 - 7/12/2010 Construction 1/22/2011 On Progress Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 SMS 9/7/2010 186 ENREP/W/62 Mullaitivu Thunukai NCB 11.20 0.10 Post LKR 9.53 2.39 Package 3 Actual 4/20/2010 5/25/2010 - 7/12/2010 Construction 1/22/2011 On Progress Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 9/7/2010 187 ENREP/W/63 Mullaitivu Thunukai NCB 15.00 0.14 Post LKR 13.08 K.P.K.Construc 7.31 Package 4 Actual 4/20/2010 5/25/2010 - 7/12/2010 tion 1/22/2011 On Progress Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 Theepan 9/7/2010 188 ENREP/W/64 Mullaitivu Thunukai NCB 11.20 0.10 Post LKR 9.79 5.61 Package 5 Actual 4/20/2010 5/25/2010 - 7/12/2010 Engneering. 1/22/2011 On Progress Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 9/7/2010 189 ENREP/W/65 Mullaitivu Thunukai NCB 11.90 0.11 Post LKR 10.2 K.P.K.Construc 7.79 Package 6 Actual 4/20/2010 5/25/2010 - 7/12/2010 1/22/2011 On Progress tion Rehabilitation of Roads in Thunukkai- Planned 12/6/2009 1/10/2010 - 2/9/2010 9/7/2010 190 ENREP/W/66 Mullaitivu Thunukai NCB 18.40 0.17 Post LKR 15.59 Jana Agency. 10.59 Package 7 Actual 4/20/2010 5/25/2010 - 7/12/2010 1/22/2011 On Progress Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 SMA 9/7/2010 191 ENREP/W/67 Mullaitivu Manthai East NCB 13.40 0.12 Post LKR 12.13 7.43 Package 1 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 On Progress Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 Leading 9/7/2010 192 ENREP/W/68 Mullaitivu Manthai East NCB 16.00 0.14 Post LKR 13.99 12.09 Package 2 Actual 4/20/2010 5/25/2010 - 6/30/2010 Crusher Works. 1/10/2011 On Progress Rehabilitation of Roads in Mantha East- Planned 12/6/2009 1/10/2010 - 2/9/2010 Pupethira Civil 9/7/2010 Completed 193 ENREP/W/69 Mullaitivu Manthai East NCB 11.00 0.10 Post LKR 9.37 6.77 Package 3 Actual 4/20/2010 5/25/2010 - 7/12/2010 Engineering. 1/22/2011 3/18/2011 Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 D&D 9/7/2010 194 ENREP/W/70 Mullaitivu Manthai East NCB 12.20 0.11 Post LKR 10.3 9.19 Package 4 Construction Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Rehabilitation of Roads in Manthai East- D&D 194 ENREP/W/70 Mullaitivu Manthai East NCB 12.20 0.11 Post LKR 10.3 9.19 Package 4 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 On Progress Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 SMA 9/7/2010 Completed 195 ENREP/W/71 Mullaitivu Manthai East NCB 15.10 0.14 Post LKR 13.15 8.68 Package 5 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 3/20/2011 Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 SMA 9/7/2010 Completed 196 ENREP/W/72 Mullaitivu Manthai East NCB 15.40 0.14 Post LKR 13.58 8.23 Package 6 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 3/30/2011 Rehabilitation of Roads in Manthai East- Planned 12/6/2009 1/10/2010 - 2/9/2010 Mega 9/7/2010 197 ENREP/W/73 Mullaitivu Manthai East NCB 21.50 0.19 Post LKR 19.09 5.60 Package 7 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 On Progress Rehabilitation of Roads in Manthai East- Planned 6/15/2011 7/15/2011 - 6/1/2011 Koneswaran 12/1/2011 198 ENREP/W/74 Mullaitivu Manthai East NCB 30.32 0.27 Post LKR 24.17 - Package 8 Actual 6/30/2011 7/29/2011 - 8/4/2011 Engineering 2/14/2012 On Progress Construction of Bridge across the left Planned - - - 10/10/2010 RDS, 5/8/2011 199 ENREP/W/270 Mullaitivu Manthai East DC 1.50 0.01 Post LKR 1.5 0.77 bank main channel at Vavunikkulam Actual - - - 11/3/2010 Selvapuram 1/19/2011 On Progress Rehabilitation of Roads in Oddusuddan- Planned 12/6/2009 1/10/2010 - 2/9/2010 K.R.Lanka 9/7/2010 200 ENREP/W/74 Mullaitivu Oddusuddan NCB 16.00 0.14 Post LKR 12.49 10.58 Package 1 Actual 4/20/2010 5/25/2010 - 6/30/2010 (pvt) Ltd 1/10/2011 On Progress Rehabilitation of Roads in Oddusuddan- Planned 12/6/2009 1/10/2010 - 2/9/2010 S.Subramaniam 9/7/2010 201 ENREP/W/75 Mullaitivu Oddusuddan NCB 20.60 0.19 Post LKR 17.02 9.89 Package 2 Actual 4/20/2010 5/25/2010 - 7/12/2010 Civil Eng. 1/22/2011 On Progress Rehabilitation of Roads in Oddusuddan- Planned 12/6/2009 1/10/2010 - 2/9/2010 A Group 9/7/2010 202 ENREP/W/76 Mullaitivu Oddusuddan NCB 20.00 0.18 Post LKR 15.95 13.79 Package 3 Actual 4/20/2010 5/25/2010 - 6/30/2010 Constructions 1/10/2011 On Progress Rehabilitation of Roads in Oddusuddan- Planned 12/6/2009 1/10/2010 - 2/9/2010 9/7/2010 203 ENREP/W/77 Mullaitivu Oddusuddan NCB 15.50 0.14 Post LKR 11.26 J.K.Constructio 5.59 Package 4 Actual 4/20/2010 5/25/2010 - 6/30/2010 1/10/2011 On Progress n Rehabilitation of Roads in Oddusuddan- Planned 12/6/2009 1/10/2010 - 2/9/2010 Thurai 9/7/2010 204 ENREP/W/78 Mullaitivu Oddusuddan NCB 16.00 0.14 Post LKR 12.91 10.91 Package 5 Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 1/10/2011 On Progress Planned 12/6/2009 1/10/2010 - 2/9/2010 S. 9/7/2010 Rehabilitation of Roads in Oddusuddan- 205 ENREP/W/79 Mullaitivu Oddusuddan NCB 16.00 0.14 Post LKR 12.97 Subramaniam 8.96 Package 6 Actual 4/20/2010 5/25/2010 - 6/30/2010 1/10/2011 On Progress Civil Engineers Rehabilitation of internal roads in Planned 7/11/2010 8/15/2010 - 9/14/2010 K.R.Lanka 4/12/2011 206 ENREP/W/35 Mullaitivu Maritimepattu NCB 23.00 0.21 Post LKR 15.65 0.09 Maratimepattu, Mullaitivu Package 1 Actual 10/30/2010 12/3/2010 - 12/28/2010 PVT(LTD) 6/27/2011 On Progress Rehabilitation of internal roads in Planned 7/11/2010 8/15/2010 - 9/14/2010 K.R.Lanka 4/12/2011 207 ENREP/W/36 Mullaitivu Maritimepattu NCB 22.23 0.20 Post LKR 15.21 0.07 Maratimepattu, Mullaitivu Package 2 Actual 10/30/2010 12/3/2010 - 12/28/2010 PVT(LTD) 6/27/2011 On Progress Renovation of internal roads in Planned 7/11/2010 8/15/2010 - 9/14/2010 Master 4/12/2011 208 ENREP/W/197 Mullaitivu Maritimepattu NCB 22.32 0.20 Post LKR 17.56 2.84 Maratimepattu, Mullaitivu Package 3 Actual 10/30/2010 12/3/2010 - 12/28/2010 Construction 7/19/2011 On Progress Rehabilitation of internal roads in Planned 7/11/2010 8/15/2010 - 9/14/2010 Babithan 4/12/2011 209 ENREP/W/198 Mullaitivu Maritimepattu NCB 21.07 0.19 Post LKR 14.45 4.64 Maratimepattu, Mullaitivu Package 4 Actual 10/30/2010 12/3/2010 - 12/28/2010 Construction 7/31/2011 On Progress Rehabilitation of Internal Roads in Planned 7/11/2010 8/15/2010 - 2/1/2010 Yansika 8/30/2010 210 ENREP/W/425 Mullaitivu Maritimepattu NCB 8.18 0.07 Post LKR 6.14 0.09 Maritimepattu, Mullaitivu- Package 5 Actual 2/1/2011 3/8/2011 - 4/7/2011 Construction 8/19/2011 On Progress Renovation of Rural Road at Planned 7/20/2012 - 8/5/2012 11/25/2012 Babithan 211 ENREP/W/426a Kumulamunai in Marritimepattu Mullaitivu Maritimepattu NS 11.73 0.11 Post LKR 11.10 Construction Division, Actual 8/9/2012 - 8/15/2012 Renovation of Rural Road at Planned 7/15/2012 - 7/20/2012 11/25/2012 Babithan 212 ENREP/W/426b Mulliyavalai East in Marritimepattu Mullaitivu Maritimepattu NS 18.25 0.16 Post LKR 17.16 Construction Division, Actual 8/9/2012 - 8/15/2012 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Community Infrastructure II Meddukudi Planned - 213 ENREP/W/426c Mullaitivu Meddukudi NS Post LKR Road Visvamadhu Actual - Rehabilitation of Suthan suthana Play 214 ENREP/W/414 Mullaitivu Mamoolai 19.60 ground front concrete road 1.1 Km Rehabilitation of Thoondal North 215 ENREP/W/415 Mullaitivu Upumaveli 19.75 Upumaveli joint road 1.5 Km V.V. Rehabilitation of Roads in Vavuniya Planned 12/6/2009 1/10/2010 - 2/9/2010 Ramanthan 9/7/2010 216 ENREP/W/80 Vavuniya Vav North NCB 16.80 0.15 Post LKR 12.58 9.87 District – Package 1 Actual 3/26/2010 4/29/2010 - 5/21/2010 &Company(pvt) 12/1/2010 On Progress Ltd V.V. Rehabilitation of Roads in Vavuniya Planned 12/6/2009 1/10/2010 - 2/9/2010 Ramanthan 9/7/2010 Completed 217 ENREP/W/81 Vavuniya Vav North NCB 17.80 0.16 Post LKR 13.96 7.14 District – Package 2 Actual 3/26/2010 4/29/2010 - 5/21/2010 &Company(pvt) 12/1/2010 6/30/2011 Ltd V.V. Rehabilitation of Roads in Vavuniya Planned 12/6/2009 1/10/2010 - 2/9/2010 Ramanthan 9/7/2010 218 ENREP/W/82 Vavuniya Vav North NCB 17.60 0.16 Post LKR 13.44 3.30 District – Package 3 Actual 3/26/2010 4/29/2010 - 5/21/2010 &Company(pvt) 12/1/2010 On Progress Ltd Formation & Gravelling of Resettlement Planned - - - 11/12/2010 6/10/2011 Vavuniya 219 ENREP/W/271 area Roads at Karappukuththi Vavuniya Vavuniya North DC 4.66 0.04 Post LKR 4.66 - Actual - - - 10/1/2010 North MPCS 2/8/2011 On Progress Periyamadu road in Vavuniya Formation & Gravelling of Resettlement Planned - - - 11/12/2010 6/10/2011 Vavuniya 220 ENREP/W/273 area Roads at Keerisuddankiramam in Vavuniya Vavuniya North DC 2.56 0.02 Post LKR 2.56 0.01 North MPCS Vavuniya North Actual - - - 10/1/2010 2/8/2011 On Progress Formation & Gravelling of Resettlement Planned - - - 11/12/2010 6/10/2011 Completed area Roads at Kurisuddakulam Ampal Vavuniya 221 ENREP/W/272 Vavuniya Vavuniya North DC 4.53 0.04 Post LKR 4.53 3.87 nagar and Panaininran kulam roads in North MPCS Actual - - - 10/1/2010 2/8/2011 6/24/2011 Vavuniya North Cleaning & Reformation of VNPS area Planned - - - 11/12/2010 Vavuniya 6/10/2011 Completed 222 ENREP/W/284 Vavuniya Vavuniya North DC 3.78 0.03 Post LKR 3.78 2.78 Roads Vavuniya North North MPCS Actual - - - 10/20/2010 3/4/2011 6/22/2011 Planned 12/15/2010 2/15/2011 - 11/12/2010 6/10/2011 Rehabilitation of Roads in Vavuniya Edward & 223 ENREP/W/437 Vavuniya Vavuniya NCB 24.54 0.22 Post LKR 18.79 3.18 North package 4 christie Actual 1/24/2011 3/8/2011 - 4/7/2011 10/18/2011 On Progress Formation and gravelling of resettlement Planned - - - 11/12/2010 Vavuniya 6/10/2011 224 ENREP/W/274 Vavuniya vavuniya DC 3.81 0.03 Post LKR 3.81 1.20 area road at Salampaikulam Roads Actual - - - 10/20/2010 MPCS 2/25/2011 On Progress Formation and Gravelling of Planned - - - 11/12/2010 6/10/2011 Vevakanantha Resettlement area road at 225 ENREP/W/275 Vavuniya Vavuniya DC 5.63 0.05 Post LKR 5.08 Community 0.79 Nochchimoddai & Veemankal in Actual - - - 10/4/2010 2/11/2011 On Progress Center Vavuniya Planned - - - 11/12/2010 Vevakanantha 6/10/2011 Completed Formation & gravelling of resettlement 226 ENREP/W/276 Vavuniya Vavuniya DC 3.15 0.03 Post LKR 3.15 Community 2.76 area road at Paranaddakal Roads Actual - - - 10/4/2010 2/11/2011 5/24/2011 Center Formation and gravelling of resettlement Planned - - - 11/12/2010 Vavuniya 6/10/2011 227 ENREP/W/277 Vavuniya vavuniya DC 2.77 0.02 Post LKR 2.77 2.51 area at omanthai Roads Actual - - - 10/18/2010 MPCS 2/25/2011 On Progress Urgent clearing and reformation of Planned - - - 11/12/2010 6/10/2011 Completed VSTPS area in vavuniya(illamaruthankulam internal Vavuniya 228 ENREP/W/283 Vavuniya Vavuniya DC 4.15 0.04 Post LKR 4.15 1.62 roads, Nochchikulam roads, Kothanda Actual - - - 10/20/2010 MPCS 2/25/2011 6/22/2011 Nochchikulam Approach & Internal road) Formation and Gravelling of Planned - - - 11/12/2010 6/10/2011 Completed resettlement area roads at Cheddikulam 229 ENREP/W/278 Vavuniya Vavuniya DC 4.56 0.04 Post LKR 4.56 4.28 Periyathampanai & Piramanalankulam MPCS Roads Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Formation and Gravelling of resettlement area roads at Cheddikulam 229 ENREP/W/278 Vavuniya Vavuniya DC 4.56 0.04 Post LKR 4.56 4.28 Periyathampanai & Piramanalankulam Actual - - - 10/4/2010 MPCS 2/9/2011 5/31/2011 Roads Formation and Gravelling of Planned - - - 11/12/2010 6/10/2011 Completed Cheddikulam 230 ENREP/W/279 Resettlement area road at Vavuniya Cheddikulam DC 3.87 0.03 Post LKR 3.87 3.61 Actual - - - 10/4/2010 MPCS 2/8/2011 4/4/2011 Kanthasamynagar in VCK Formation and Gravelling of Planned - - - 11/12/2010 6/10/2011 231 ENREP/W/280 Resettlement area road at Palairuva & Vavuniya Vavuniya South DC 4.57 0.04 Post LKR 4.57 RDS, Palaruwa 1.41 Track 07 Roads Actual - - - 10/25/2010 1/27/2011 On Progress Formation and Gravelling of Planned - - - 11/12/2010 6/10/2011 WRDS, 232 ENREP/W/281 Resettlement area road at Vavuniya Vavuniya South DC 2.38 0.02 Post LKR 2.38 0.55 Actual - - - 11/15/2010 Awaranthulawa 2/20/2011 On Progress Awaranthulawa Roads Rehabilitation of roads in Planned 9/20/2010 10/25/2010 - 2/1/2010 WMB 6/10/2011 233 ENREP/W/427 Vavuniya Vavuniya South NCB 27.45 0.25 Post LKR 19.14 4.32 Galabogaswewa Road Actual 10/30/2010 12/3/2010 - 12/28/2010 Contractors 6/10/2010 On Progress Renovation of Kallikulam Internal Road Planned - - - 5/25/2011 9/25/2011 234 ENREP/W/428 Vavuniya Vavuniya South DC 3.17 0.03 Post LKR 3.17 FO Kallikulam - in Vavuniya Actual - - - 7/15/2011 11/17/2011 On Progress Rehabilitation and reconstruction of Planned - - - 6/10/2012 SMA 235 ENREP/W/401 Galabogeswewa Bridge Across Kiwoya Vavuniya Vavuniya South NCB 26.31 0.24 Post LKR - Actual - - - 7/5/2012 Construction On Progress at Galabogeswewa Rehabilitation of Kalabogeswewa Road Planned - - - 5/10/2012 8/20/2012 SMA 236 ENREP/W/402 16 Km + 365 m to 17 Km + 165 m in Vavuniya Vavuniya South NS 12.87 0.12 Post LKR - Actual - - - 6/15/2012 Construction 9/20/2012 On Progress Vavuniya Construction of Achchipuram Main road Planned - - - 8/8/2012 A.J.S 8/20/2012 237 ENREP/W/403 Vavuniya Vavuniya South NS 14.30 0.13 Post LKR 14.4 - in Vavuniya district Actual - - - 8/14/2012 Contractors 11/26/2012 On Progress Construction of Salmmalankulam Planned - - - 8/8/2012 8/20/2012 Pastini 238 ENREP/W/404 Achchipuram Main road in Vavuniya Vavuniya Vavuniya South NS 19.90 0.18 Post LKR 19.74 - Actual - - - 8/14/2012 Construction 11/26/2012 On Progress district Concreting and gravelling road at Planned - - - 239 ENREP/W/407 Vavuniya Vavuniya South NS Post LKR Atabagasksda in vavuniya Actual - - - Const.of Rural roads (Pack I) at 40 acre Planned - - - 240 ENREP/W/408 Vavuniya Vavuniya South NS 9.20 Post LKR Division at Vavuniya Actual - - - Const.of Rural roads (Pack II) at 40 acre Planned - - - 241 ENREP/W/409 Vavuniya Vavuniya South NS 15.20 Post LKR Division at Vavuniya Actual - - - Const.of Rural roads at Kokweliya in Planned - - - Panditharatne 242 ENREP/W/410 Vavuniya Vavuniya South NS Post LKR Vavuniya South Construction Actual - - - Rehabilitation and Reconstruction of Y Planned - - - 243 ENREP/W/411 junction to Kiri- ibban wewa and y Vavuniya Vavuniya NS Post LKR junction to Monarawewa Actual - - - Rehabilitation of Reconstruction of Planned - - - 244 ENREP/W/412 Vavuniya Mamaduwa NS Post LKR Mamaduwa Internal road 3Km Actual - - - Rehabilitation & Reconst.of Peranamadu Planned - - - 245 ENREP/W/413 Vavuniya Vavuniya NS Post LKR main road 3 km Actual - - - Const.of Metaling & tarring of Allakalla Planned - - - Yansika 246 ENREP/W/414 Vavuniya Vavuniya NS Post LKR Aluthgama Road - 2 km Construction Actual - - - Metaling & Tarring Annanagar Internal Planned - - - Gnanam 247 ENREP/W/415 Vavuniya Vavuniya NS 11.80 Post LKR Road Builders Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Metaling & Tarring Annanagar Internal Gnanam 247 ENREP/W/415 Vavuniya Vavuniya NS 11.80 Post LKR Road Builders Actual - - - Metaling & Tarring Annanagar School Planned - - - 248 ENREP/W/416 Vavuniya Vavuniya NS 9.20 Post LKR Vijeya Buildres Road Actual - - - C3 Drinking Water Planned - - - - - 249 ENREP/W/285 Maruthankerny Community WSS Jaffna Maruthankerny NCB 25.00 0.23 Post LKR 0 - - Actual - - - - - On Progress ENREP/W/285- Planned - - - 6/1/2010 6/1/2011 Civil Works NCB 10.00 1.23 Post LKR - a Actual - - - - - ENREP/W/285- Planned - - - 12/1/2010 12/1/2011 Pipe Laying NCB 10.00 2.23 Post LKR - b Actual - - - - - ENREP/W/285- Planned - - - 6/1/2011 6/1/2012 M & E Works NCB 5.00 3.23 Post LKR - c Actual - - - - - Planned - - - - - 250 ENREP/W/83 ValvettithuraiWSS, Point Pedro Jaffna Point pedro NCB 348.57 2.24 Post - - - 68.65 Actual - - - - - On Progress Planned - - - 6/1/2010 Squir Mech 6/1/2011 - ENREP/W/83-a Civil Works NCB 75.00 3.24 Post LKR 63.63 Engineering(Pvt Actual - - - 4/8/2011 ) Ltd 4/20/2012 - Planned - - - 12/1/2010 12/1/2011 - ENREP/W/83-b Pipe Laying NCB 200.00 4.24 Post LKR Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O ENREP/W/83-b Pipe Laying NCB 200.00 4.24 Post LKR Actual - - - - - - Planned - - - 6/1/2011 6/1/2012 - ENREP/W/83-c M & E Works NCB 73.57 5.24 Post LKR Actual - - - - - - - - - - - 251 ENREP/W/84 Vidathalthivu WSS, Manthai W Mannar Manthai West NCB 204.07 - - - 20.00 - - - - - On Progress Planned - - - 6/1/2010 Squir Mech 6/1/2010 - ENREP/W/84-a Civil Works NCB 60.00 2.84 Post LKR 56.50 Engineering(Pvt Actual - - - 2/23/2011 ) Ltd 5/7/2012 - Planned - - - 12/1/2010 12/1/20111 - ENREP/W/84-a Pipe Laying NCB 100.00 3.84 Post LKR Actual - - - - - - Planned - - - 6/1/2011 6/1/2012 - ENREP/W/84-a M & E Works NCB 44.07 4.84 Post LKR Actual - - - - - - Planned - - - - - 252 ENREP/W/85 Thevanpiddy, Manthai W Mannar Manthai West NCB 168.04 1.51 Post - - - 90.38 Actual - - - - - On Progress Planned - - - 6/1/2010 Finite Lanka 6/1/2011 - ENREP/W/85-a Civil Works NCB 50.00 2.51 Post LKR 48.03 Actual - - - 4/7/2011 (Pvt) Ltd 4/19/2012 - Planned - - - 12/1/2010 Richmo 12/1/2011 - ENREP/W/85-b Pipe Laying NCB 80.00 3.51 Post LKR 101.22 Construction Actual - - - 8/5/2011 Engineers 4/14/2012 - Planned - - - 6/1/2011 6/1/2012 - ENREP/W/85-c M & E Works NCB 38.04 4.51 Post LKR Actual - - - - - - - - - - 253 ENREP/W/90 Adampan WSS, Manthai W Mannar Manthai West NCB 296.00 2.51 - - 20.00 - - - - Planned - - - 6/1/2010 Finite Lanka 6/1/2011 - ENREP/W/90-a Civil Works NCB 75.00 3.51 Post LKR 45.62 (Pvt) Ltd Actual - - - 12/92010 12/21/2011 - On Progress Planned - - - 12/1/2010 12/1/2011 - ENREP/W/90-b Pipe Laying NCB 125.00 4.51 Post LKR 115.85 Isuru Builders Actual - - - 13/5/2011 2/21/2012 - On Progress Planned - - - 6/1/2011 6/1/2012 - ENREP/W/90-c M & E Works NCB 96.00 5.51 Post LKR Actual - - - - - - Planned - - - - - 254 ENREP/W/87 Mallavi Town WSS, Thunikai Mullaitivu Thunukkai NCB 294.26 1.75 Post - - - 50.00 Actual - - - - - On Progress Planned - - - 6/1/2010 Squir Mech 6/1/2011 - ENREP/W/87-a Civil Works NCB 75.00 2.75 Post LKR 51.25 Engineering(Pvt Actual - - - 5/3/2011 ) Ltd 5/15/2012 - Planned - - - 12/1/2010 12/1/2011 - ENREP/W/87-b Pipe Laying NCB 150.00 3.75 Post LKR Actual - - - - - - Planned - - - 6/1/2011 6/1/2012 - ENREP/W/87-c M & E Works NCB 69.26 4.75 Post LKR Actual - - - - - - Planned - - - - - 255 ENREP/W/88 Pandiyankulam, Manthai E Mullaitivu Manthai East NCB 298.53 1.79 Post LKR 0 - 37.12 Actual - - - - - On Progress Planned - - - 6/1/2010 Lohitha 6/1/2011 - ENREP/W/88-a Civil Works NCB 75.00 2.79 Post LKR 32.4 Actual - - - 4/22/2011 Construction - - Planned - - - 12/1/2010 12/1/2011 - ENREP/W/88-b Pipe Laying NCB 150.00 3.79 Post LKR Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O ENREP/W/88-b Pipe Laying NCB 150.00 3.79 Post LKR Actual - - - - - - Planned - - - 6/1/2011 6/1/2012 - ENREP/W/88-c M & E Works NCB 73.53 4.79 Post LKR Actual - - - - - - Planned - - - - - 256 ENREP/W/86 Oddusuddan Town WSS, Oddusuddan Mullaitivu Oddusuddan NCB 92.21 0.83 Post LKR 0 - 80.00 Actual - - - - - On Progress Planned - - - 6/1/2010 Squir Mech - - ENREP/W/86-a Civil Works NCB 92.21 1.83 Post LKR 65.33 Engineering(Pvt Actual - - - 2/23/2011 ) Ltd - - Planned - - - - 3/22/2011 257 ENREP/W/89 Nedunkerny WSS, Vav North Vavuniya Vav North NCB 175.62 1.58 Post LKR 0 - 116.27 Actual - - - - - On Progress Planned - - - 6/1/2010 Squir Mech - - 6/1/2011 ENREP/W/89-a Civil Works NCB 50.00 2.58 Post LKR 37.92 Engineering(Pvt - Actual - - - 2/23/2011 ) Ltd - - 11/3/2012 Planned - - - 12/1/2010 - - 12/1/2011 - ENREP/W/89-b Pipe Laying NCB 100.00 3.58 Post LKR - - Actual - - - - - - - - Planned - - - 6/1/2011 - - 6/1/2012 - ENREP/W/89-c M & E Works NCB 25.62 4.58 Post LKR - - Actual - - - - - - - - C4 Public Buildings and Facilities Planned 11/2/2010 12/7/2010 - 3/17/2010 Dharmadasa 11/12/2010 Reconstruction of DS Office at 258 ENREP/W/91 Jaffna Maruthankerny NCB 49.17 0.44 Post LKR 43.73 Construction & 12.35 Maruthankerny, Jaffna Actual 11/29/2010 1/4/2011 - 2/1/2011 10/13/2011 On Progress Enterprises Reconstruction of Kudaththanai Planned 1/11/2010 2/15/2010 - 3/7/2010 Krishna 8/4/2010 259 ENREP/W/92 Jaffna Maruthankerny NCB 5.50 0.05 Post LKR 4.82 - Pradeshiya Sabha Sub Officer, Jaffna Actual 9/27/2010 11/4/2010 - 12/10/2010 Contractor 5/23/2011 On Progress Reconstruction of Vadamarachchi East Planned 1/11/2010 2/15/2010 - 3/7/2010 Jathur 9/3/2010 260 ENREP/W/93 Jaffna Maruthankerny NCB 4.50 0.04 Post LKR 4.24 2.98 MPCS Builidng, Maruthankerny, Jaffna Actual 9/27/2010 11/4/2010 - 12/10/2010 Enterprose 5/23/2011 On Progress Reconstruction of Agrarian Service Planned 1/11/2010 2/15/2010 - 3/7/2010 Chandra 8/4/2010 Completed 261 ENREP/W/95 Jaffna Maruthankerny NCB 7.60 0.07 Post LKR 7.23 6.02 Centre, Ampan, Jaffna Actual 9/27/2010 11/4/2010 - 12/3/2010 Construction 5/16/2011 6/30/2011 Planned 1/11/2010 2/15/2010 - 3/7/2010 Ratna 8/4/2010 reconstruction of Vetinerary surgeon's 262 ENREP/W/95 Jaffna Maruthankerny NCB 7.70 0.07 Post LKR 8.51 Engineering and 1.01 office at Maruthankerny Actual 11/29/2010 1/4/2011 - 2/10/2011 7/24/2011 On Progress Constractors Planned 1/11/2010 2/15/2010 - 3/7/2010 Shanth 8/4/2010 Construction of Nagarkovil Market, 263 ENREP/W/96 Jaffna Maruthankerny NCB 5.58 0.05 Post LKR 5.65 Engineering 0.03 jaffna. Actual 7/8/2010 8/10/2010 - 9/9/2010 2/20/2011 On Progress Contractor Yaso Reconstruction of Post Office at Planned 1/11/2010 2/15/2010 - 3/7/2010 Construction & 8/4/2010 264 ENREP/W/97 Jaffna Maruthankerny NCB 6.43 0.06 Post LKR 5.78 0.76 Thalaiyadi, Jaffna Actual 11/29/2010 1/4/2011 - 2/1/2011 Civil Contract 7/15/2011 On Progress Works Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Renovation of Class room building at Planned - - - 10/8/2010 12/7/2010 Completed 265 ENREP/W/292 Jaffna Maruthankerny DC 5.31 0.05 Post LKR 5.31 SDS 4.73 J/Uduthurai MV Actual - - - 9/27/2010 12/5/2010 3/4/2011 Renovation of Class room building at Planned - - - 10/8/2010 1/6/2011 Completed 266 ENREP/W/293 Jaffna Maruthankerny DC 1.49 0.01 Post LKR 1.49 SDS 1.37 J/Aliyawalai CCTMS Actual - - - 9/27/2010 12/5/2010 12/5/2011 Renovation of Class room building at Planned - - - 10/8/2010 1/6/2011 Completed 267 ENREP/W/294 Jaffna Maruthankerny DC 0.43 0.00 Post LKR 0.43 SDS 0.38 J/Chempijanpattu GTMS Actual - - - 9/27/2010 12/5/2010 2/4/2011 Renovation of Class room building at Planned - - - 10/8/2010 1/6/2011 Completed 268 ENREP/W/296 Jaffna Maruthankerny DC 5.00 0.05 Post LKR 5 SDS 4.14 J/Maruthankerny HTMS, Jaffna Actual - - - 9/27/2010 12/5/2010 4/4/2011 Renovation of Class room building at Planned - - - 10/8/2010 1/6/2011 269 ENREP/W/302 Jaffna Maruthankerny DC 1.82 0.02 Post LKR 1.82 SDS 1.42 J/Chempijanpattu RCTMS Actual - - - 9/27/2010 12/5/2010 On Progress Planned - - - 10/8/2010 SDS, 2/5/2011 Rehabilitation of roof works of 270 ENREP/W/295 Jaffna Maruthankerny DC 2.52 0.02 Post LKR 2.52 J/Thalayadi 1.18 J/Thalayadi RCTMS Actual - - - 3/17/2011 RCTMS 7/19/2011 On Progress Planned - - - 1/1/2011 SDS, 5/1/2011 Reconstruction of CR building in 271 ENREP/W/300 Jaffna Maruthankerny DC 3.65 0.03 Post LKR 3.56 J/Mamunai 1.99 J/Mamunai GTMS Actual - - - 3/18/2011 GTMS 7/19/2011 On Progress Planned 12/11/2010 1/15/2011 - 2/5/2011 10/3/2011 Reconstruction of Ward Blocks in Nimovil Civil 272 ENREP/W/428 Jaffna Maruthankerny NCB 33.87 0.31 Post LKR 27.64 1.37 Divisional Hospital, Maruthankerny Engineering Actual 2/8/2011 3/8/2011 - 4/25/2011 1/4/2012 On Progress Vadamarachchi Reconstruction of Vadamarachchi East Planned - - - 2/6/2011 6/6/2011 east Palm 273 ENREP/W/429 Palm Development Co-op Society Ltd, Jaffna Maruthankerny DC 4.91 0.04 Post LKR 4.91 1.55 Actual - - - 3/9/2011 Development 7/9/2011 On Progress Maruthankerny, Jaffna Co-op Society Reconstruction of 4 Nos. of MPCS Planned 8/31/2010 10/5/2010 - 10/12/2010 Mathankan 2/9/2011 274 ENREP/W/305 Jaffna Maruthankerny NCB 12.34 0.11 Post LKR 10.12 3.50 Outlet Branches at Maruthankerny Actual 2/8/2011 3/8/2011 - 5/12/2011 Construction 9/18/2011 On Progress Planned - - - 10/12/2010 Vadamarachchi 2/9/2011 Reconstruction of GHC Uduthurai, 275 ENREP/W/541 Jaffna Maruthankerny DC 3.66 0.03 Post LKR 3.66 East MPCS - Maruthankerny Actual - - - 5/23/2011 9/22/2011 On Progress Maruthankerny Planned - - - 10/12/2010 2/9/2011 Vadamarachchi Renovation of Fisherman Co-op Society 276 ENREP/W/542 Jaffna Maruthankerny DC 4.15 0.04 Post LKR 4.15 East Fisherman 0.20 Building at Maruthankerny Actual - - - 5/23/2011 9/22/2011 On Progress Co-op Society Reconstruction of Primary Medical Care Planned - - - 6/15/2011 Maruthankerny 10/13/2011 277 ENREP/W/543 Jaffna Maruthankerny DC 5.50 0.05 Post LKR 5.5 - Unit at Mullian Stage-1, Jaffna Actual - - - 7/27/2011 MPCS Ltd 11/29/2011 On Progress Reconstruction of School Building Planned - - - 6/15/2011 SDS 10/13/2011 278 ENREP/W/544 (120’x25’) J/Kaddaikadu Jaffna Maruthankerny DC 4.57 0.04 Post LKR 4.57 /Kaddaikadu - RCTMS,Jaffna. Actual - - - 7/25/2011 RCTMS,Jaffna 11/25/2011 On Progress SDS Repairs to Class Room Building Planned - - - 6/20/2011 10/18/2011 Vettilaikerney 279 ENREP/W/98 J/Vettilaikerney Parameswara Jaffna Maruthankerny NCB 2.67 0.02 Post LKR 2.67 - Actual - - - 7/25/2011 Parameswara 11/25/2011 On Progress Vidiyalayam. Vidiyalayam. Reconstruction of School Building Planned - - - 6/25/2011 SDS Kervil 10/23/2011 280 ENREP/W/431 Jaffna Maruthankerny NCB 3.95 0.04 Post LKR 3.95 - J/Kervil GTMS, Jaffna. Actual - - - 7/25/2011 GTMS, 11/25/2011 On Progress Hospital Renovation Works of DMO’s Qrs at DC Planned - - - 6/26/2011 Development 10/24/2011 281 ENREP/W/547 Jaffna Maruthankerny 4.46 0.04 Post LKR 4.46 - Maruthankerney, Jaffna. Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Pointpedro Hospital Reconstruction of Female Ward of 12 DC Planned - - - 6/27/2011 10/25/2011 Development 282 ENREP/W/548 Beds & Canteen at R.H Jaffna Maruthankerny 5.46 0.05 Post LKR 5.46 - Society, Maruthankerney, Jaffna Pointpedro Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Hospital Reconstruction of Female Ward of 12 Development 282 ENREP/W/548 Beds & Canteen at R.H Jaffna Maruthankerny 5.46 0.05 Post LKR 5.46 - Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Maruthankerney, Jaffna Pointpedro Hospital Reconstruction of Male Ward of 12 DC Planned - - - 6/28/2011 10/26/2011 Development 283 ENREP/W/549 Beds, Ambulance Garage & Kitchen at Jaffna Maruthankerny 5.02 0.05 Post LKR 5.02 - Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Maruthankerney, Jaffna. Pointpedro Hospital Reconstruction of Maternity Ward at DC Planned - - - 6/29/2011 Development 10/27/2011 284 ENREP/W/550 Jaffna Maruthankerny 5.34 0.05 Post LKR 5.34 - R.H Maruthankerney, Jaffna. Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Pointpedro Hospital Renovation Works of MID Wife Qrs at DC Planned - - - 6/30/2011 Development 10/28/2011 285 ENREP/W/551 Jaffna Maruthankerny 5.23 0.05 Post LKR 5.23 - Maruthankerney, Jaffna. Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Pointpedro Hospital Renovation of OPD Block, Water Tank DC Planned - - - 7/1/2011 10/29/2011 Development 286 ENREP/W/552 & Generator Room at Maruthankerney, Jaffna Maruthankerny 5.45 0.05 Post LKR 5.45 - Actual - - - 11/28/2011 Society, 3/30/2012 On Progress Jaffna. Pointpedro Reconstruction of Two Storey Class DC Planned - - - 7/2/2011 SDS, J/ 10/30/2011 287 ENREP/W/553 Room Building With Stage(Ground Jaffna Jaffna Town 4.57 0.04 Post LKR 4.57 Kaddaikadu - Floor) J/Kaddaikadu RCTMS,Jaffna. Actual - - - 12/30/2011 RCTMS 4/29/2012 On Progress Reconstruction of Unit Office Cum Planned 4/27/2010 6/1/2010 - 6/21/2010 Nimovi Civil 12/18/2010 288 ENREP/W/98 Jaffna Jaffna Town NCB 15.60 0.14 Post LKR 13.38 10.20 Quality Control Laboratory at Pannai Actual 3/26/2010 4/29/2010 - 6/11/2010 Engineers 12/22/2010 On Progress Improvements of Chief Engineer's & Planned - - - 6/21/2010 WRDS 12/18/2010 289 ENReP/W/197 Jaffna Jaffna Town DC 4.13 0.04 Post LKR 3.73 1.38 Executive Engineer's office, Jaffna Actual - - - 8/16/2010 Eachamopddai 1/13/2011 On Progress Reconstruction of Market at Moor street, Planned 4/27/2010 6/1/2010 - 6/21/2010 Sairam 12/18/2010 290 ENREP/W/431 Jaffna Jaffna Town NCB 8.23 0.07 Post LKR 6.98 2.84 Jaffna. Actual 11/29/2010 1/4/2011 - 2/1/2011 Contractors 7/15/2011 On Progress Yaso Repairs to Osmanya College Buildings 11/2/2010 12/7/2010 - 12/31/2010 Construction & 6/29/2011 291 ENREP/W/432 Jaffna Jaffna Town NCB 8.42 0.08 Post LKR 7.51 2.72 at Jaffna. 11/29/2010 1/4/2011 - 1/25/2011 Civil Contract 7/8/2011 On Progress Works Koddai Renovation and Improvements of Planned - - - 10/12/2010 Meenadchi 2/9/2011 292 ENREP/W/539 Building of Nurses Traning School Jaffna Jaffna Town DC 3.53 0.03 Post LKR 3.53 Women Rural 3.04 Jaffna Teaching hospital, Jaffna Actual - - - 3/8/2011 Development 7/7/2011 On Progress Society. Reconstruction of Lab for Chief Planned - - - 10/12/2010 2/9/2011 293 ENREP/W/547 Engineer Office at Dept of Building , Jaffna Jaffna Town DC 5.50 0.05 Post LKR 5.5 Nallur MPCS 0.01 Jaffna Actual - - - 6/24/2011 10/27/2011 On Progress Planned - - - 10/12/2010 SDS J/St. John 2/9/2011 Reconstruction of 63x25 class room 294 ENREP/W/548 Jaffna Jaffna Town DC 3.47 0.03 Post LKR 3.47 Bosco's 0.01 Building J/St. John Bosco's Vidylalayam Actual - - - 5/20/2011 9/22/2011 On Progress Vidylalayam Reconstruction of MPCS outlet and Sub Planned - - - 1/1/2011 5/1/2011 295 ENREP/W/549 Jaffna Nallur DC 2.63 0.02 Post LKR 2.63 Nallur MPCS 0.71 post office at poompugar, Ariyalai East Actual - - - 5/20/2011 9/22/2011 On Progress Refurbishment of CE Office & Planned - - - 10/12/2010 2/9/2011 Nallur MPCS 296 ENREP/W/433 Ancillary Items at Depet of Building Jaffna Jaffna Town DC 4.59 0.04 Post LKR 4.59 1.00 Actual - - - 3/30/2011 Ltd 8/2/2011 On Progress Jaffna Reconstruction of Two Storey Class Planned - - - 2/2/2011 SDS 6/2/2011 297 ENREP/W/550 Room Building J/Koddaikaddu GTMS, Jaffna Jaffna Town DC 5.22 0.05 Post LKR 5.22 J/Koddaikaddu 1.00 Jaffna. Actual - - - 7/4/2011 GTMS, Jaffna. 11/4/2011 On Progress Reconstruction of Generator House of Planned - - - 2/3/2011 2/28/2011 298 ENREP/W/551 Jaffna Jaffna Town DC 0.16 0.00 Post LKR 0.16 Nallur MPCS. - Conference Hall at Public Library Jaffna. Actual - - - 12/22/2011 3/30/2012 On Progress Planned - - - 2/5/2011 Ariyalai Center 6/5/2011 Reconstruction of Primary Health Center 299 ENREP/W/434 Jaffna Nallur DC 3.27 0.03 Post LKR 3.27 South Samurthi 2.67 Ariyalai Actual - - - 1/10/2011 Task Force 5/17/2011 On Progress Women Rural Planned - - - 10/8/2010 1/6/2011 Development 300 ENREP/W/435 Reconstruction of J/Poompukar GTMS Jaffna Nallur DC 3.47 0.03 Post LKR 3.47 1.36 Society, Actual - - - 3/17/2010 Navaladi 7/19/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned - - - 2/5/2011 SDS, 7/5/2011 Reconstruction of Class room building 301 ENREP/W/436 Jaffna Nallur DC 5.16 0.05 Post LKR 5.16 Muthuthamby 2.53 J/Muthuthamby MV Actual - - - 3/18/2011 7/19/2011 On Progress MV Planned - - - 7/5/2011 Lingam 1/1/2012 Reconstruction of Two Storey Class 302 ENREP/W/437 Jaffna Nallur NCB 10.37 0.09 Post LKR 8.72 Building - Building at J/Ariyalai GTMS, Jaffna Actual - - - 11/3/2011 2/15/2011 - Construction Planned 11/5/2010 12/10/2010 - 2/11/2011 V.T. 2/11/2012 Reconstruction of Public Market 303 ENREP/W/286 Jaffna Point pedro NCB 65.36 0.59 Post LKR 54.55 Construction 18.73 Building at Point pedro Phase II Actual 11/29/2010 1/4/2011 - 1/18/2011 9/29/2011 On Progress (pvt) Ltd. Reconstruction & Improvements to Planned 8/27/2010 10/1/2010 - 10/8/2010 1/6/2011 Mathankan 304 ENREP/W/438 Assembly Hall & Library Building in Jaffna Point pedro NCB 20.88 0.19 Post LKR 17.45 6.58 Actual 2/8/2011 3/8/2011 - 3/11/2011 Construction 9/21/2011 On Progress J/hartley College Reconstruction of two storey Class room Planned 8/27/2010 10/1/2010 - 10/8/2010 Lingam 1/6/2011 305 ENREP/W/439 Building at J/Methodist Girls High Jaffna Point pedro NCB 23.90 0.22 Post LKR 19.75 Buildeing 1.53 School Actual 3/8/2011 4/8/2011 - 4/11/2011 Construction 11/21/2011 On Progress Reconstruction of Libarary Building in Planned 8/27/2010 10/1/2010 - 10/8/2010 Sai Ram 1/6/2011 306 ENREP/W/440 Jaffna Point pedro NCB 11.40 0.10 Post LKR 9.88 1.86 J/Point pedro Sithivinayagar Vidylayam Actual 2/8/2011 3/8/2011 - 3/11/2011 Construction 8/22/2011 On Progress Reconstruction of Ward Block at base Planned - - - 1/15/2011 RDS Puloiy 5/15/2011 Completed 307 ENREP/W/441 Jaffna Point pedro DC 5.46 0.05 Post LKR 5.46 4.74 Hospital Point pedro Actual - - - 2/7/2011 North West 6/10/2011 7/9/2011 Reconstrution of Zonal Education Office Planned 6/15/2011 7/15/2011 - 8/15/2011 Jana Civil 2/11/2012 308 ENREP/W/578 Jaffna Point pedro NCB 27.06 0.24 Post LKR 24.54 4.00 at Vadamarachi, Jaffna(22.2Mn) Actual 6/30/2011 7/29/2011 - 8/15/2011 Works 2/25/2012 On Progress Planned 6/15/2011 7/15/2011 - 2/5/2011 VV 11/2/2011 309 ENREP/W/442 Reconstruction of UC Point pedro Jaffna Point pedro NCB 52.47 0.47 Post LKR 49.65 Ramanathan & 7.61 Actual 6/30/2011 7/29/2011 - 8/5/2011 Co 5/15/2012 On Progress Completion of UC Building at Planned - - - 12/5/2011 Sairam 11/3/2011 310 ENREP/W/443 Jaffna Point pedro NS 13.92 0.13 Post LKR 11.77 - Valveddithurai, Jaffna Actual - - - 12/27/2011 Contractors 6/29/2012 1/0/1900 Planned - - - 2/7/2011 Lingam 11/4/2011 Reconstruction of Library Urban 311 ENREP/W/444 Jaffna Point pedro DC 9.66 0.09 Post LKR 9.66 Buildeing - Council, Pointpedro, Jaffna. Actual - - - 12/30/2011 7/11/2012 1/0/1900 Construction Rehabilitation of 2 MPCS Branches Planned 8/31/2010 10/5/2010 - 12/12/2010 Star 5/11/2011 312 ENREP/W/287 and 2 no of Food Stores at Thellipalai, Jaffna Vali North NCB 9.63 0.09 Post LKR 7.14 Engineering 5.72 Jaffna. Actual 11/29/2010 1/4/2011 - 2/10/2011 Construction 7/24/2011 On Progress Planned - - - 10/8/2010 12/7/2010 Completed 313 ENREP/W/445 Repairs to J/ Vasavillan M.M.V Jaffna Vali North DC 6.03 0.05 Post LKR 5.44 SDS 5.14 Actual - - - 10/5/2010 12/13/2010 12/3/2010 Planned - - - 2/8/2011 SDS, 6/8/2011 Completed Rehabilitation of a J/Pannalai Sri J/Pannalai Sri 314 ENREP/W/446 Jaffna Vali North DC 1.50 0.01 Post LKR 1.35 1.29 Kanagasabai Vid Kanagasabai Actual - - - 3/18/2011 Vidiyalayam 7/19/2011 8/30/2011 Planned - - - 5/5/2011 SDS 9/5/2011 Reconstruction of Two Storey Class J/Veemankama 315 ENREP/W/551 Room J/Veemankamam M.V, Jaffna Vali North DC 4.71 0.04 Post LKR 4.71 0.20 m M.V, Thellipalai. Actual - - - 6/9/2011 10/12/2011 On Progress Thellipalai SDS Planned - - - 5/5/2011 9/5/2011 Reconstruction of J/Veemankamam J/Veemankama 316 ENREP/W/552 Jaffna Vali North DC 4.69 0.04 Post LKR 4.69 0.23 M.V, Thellipalai m M.V, Actual - - - 6/9/2011 10/12/2011 On Progress Thellipalai SDS Planned - - - 5/5/2011 9/5/2011 Reconstruction of J/Maaviddapuram J/Thellipalai 317 ENREP/W/553 Jaffna Vali North DC 4.30 0.04 Post LKR 4.3 0.01 South AMTMS, Thellipalai. Ssivapiragasa Actual - - - 6/9/2011 10/12/2011 On Progress Vid Planned - - - 5/5/2011 SDS 9/5/2011 Repairs to Class Room Building at J/Alaveddy 318 ENREP/W/554 J/Kolankaladdy Saiva Vidyalayam, Jaffna Vali North NCB 4.53 0.04 Post LKR 4.53 0.21 Arunachchalam Thellipalai. Actual - - - 6/9/2011 10/12/2011 On Progress Vidyalayam Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned - - - 5/5/2011 SDS Illavalai 9/5/2011 Reconstruction of J/Valithundal 319 ENREP/W/555 Jaffna Vali North DC 4.19 0.04 Post LKR 4.19 Meihandan 0.01 RCTMS, Jaffna. Actual - - - 6/14/2011 10/20/2011 On Progress Maha Vid SDS J/ Planned - - - 5/5/2011 9/5/2011 Reconstruction of J/Maaviddapuram Kadduvanpulam 320 ENREP/W/556 Jaffna Vali North DC 4.30 0.04 Post LKR 4.3 0.21 North AMTMS, Thellipalai. Maha Actual - - - 6/9/2011 10/12/2011 On Progress Vidyalayam Planned - - - 1/15/2011 Java Civil 6/14/2011 Repairs & Improvements to Thellipalai 321 ENREP/W/447 Jaffna Vali North DC 10.53 0.09 Post LKR 9.12 Engineering 1.49 DS office Actual - - - 5/20/2011 10/31/2011 On Progress Construction SDS, J/ Keerimalai Reconstruction of Two Storey Class Planned - - - 1/16/2011 6/15/2011 Naguleswara Room Building with Stage (Ground 322 ENREP/W/578 Jaffna Vali North DC 5.48 0.05 Post LKR 5.48 Maha - Floor) J/Keerimalai Naguleswara Actual - - - 12/22/2011 Vidyalayam. 4/29/2012 On Progress Vidyalayam, Jaffna. Reconstruction of Naguleswaram Planned 11/20/2010 12/25/2010 - 1/15/2011 K.S Arumugam 5/15/2011 323 ENREP/W/448 Jaffna Vali North NCB 10.06 0.09 Post LKR 8.83 0.98 Vidiyalayam Actual 3/8/2011 4/8/2011 - 5/20/2011 & Sons 10/31/2011 On Progress Reconstruction of Primary Health Center Planned - - - 2/5/2011 RDS, Ilavalai 6/5/2011 Completed 324 ENREP/W/449 Jaffna Vali North DC 5.50 0.05 Post LKR 5.5 3.74 Vithagapuram in Thellipalai Actual - - - 2/1/2011 North 7/7/2011 8/24/2011 Planned - - - 3/10/2011 Piam De.Co-op 7/10/2011 Renovation works at Palmara Production 325 ENREP/W/557 Jaffna Vali North DC 4.13 0.04 Post LKR 4.13 Society 0.82 Center at Vithagapuram Actual - - - 5/20/2011 9/22/2011 On Progress Thellipalai Planned - - - 3/10/2011 Piam De.Co-op 7/10/2011 Renovation works at Palmara Production 326 ENREP/W/558 Jaffna Vali North DC 4.13 0.04 Post LKR 4.13 Society 0.65 Center at Vasanthapuram Actual - - - 5/25/2011 9/29/2011 On Progress Thellipalai Hospital Planned - - - 3/10/2011 7/10/2011 Renovation Works of OPD Block at Development 327 ENREP/W/559 Jaffna Vali North DC 5.50 0.05 Post LKR 5.5 1.93 Base hospital Thellipalai Society Actual - - - 6/10/2011 10/12/2011 On Progress Thellipalai Hospital Planned - - - 3/10/2011 7/10/2011 Renovation and Balance works at Base Development 328 ENREP/W/560 Jaffna Vali North DC 5.50 0.05 Post LKR 5.5 0.01 hospital Thellipalai Society Actual - - - 6/10/2011 Thellipalai 10/12/2011 On Progress Hospital Planned - - - 3/10/2011 7/10/2011 Renovation of Ward no 1, ward no 2 and Development 329 ENREP/W/561 Jaffna Vali North DC 5.50 0.05 Post LKR 5.5 1.62 Kitchen at base hospital Thellipalai Society Actual - - - 6/10/2011 10/12/2011 On Progress Thellipalai Planned - - - 3/10/2011 RDS 7/10/2011 Reconstruction of Village Secretariat 330 ENREP/W/562 Jaffna Vali North DC 1.85 0.02 Post LKR 1.85 Kurumbasiddy 0.03 Kurumbasiddy East (J/243) Jaffna Actual - - - 8/12/2011 12/14/2011 On Progress East Reconstruction of Village Secretariat Planned - - - 3/10/2011 7/10/2011 331 ENREP/W/563 Pannalai(J/224),Thurkkapuram (J/229) Jaffna Vali North DC 3.70 0.03 Post LKR 3.7 RDS Pannalai 0.94 Jaffna. Actual - - - 10/1/2010 4/13/2011 On Progress Reconstruction of Village Planned - - - 3/10/2011 RDS 7/10/2011 332 ENREP/W/564 SecretariatNaguleswaram(J/226), Jaffna Vali North DC 3.70 0.03 Post LKR 3.7 Thanthaiselvapu 0.03 Thanthaiselvapuram (J/230)Jaffn Actual - - - 1/31/2011 ram 6/10/2011 On Progress Reconstruction of Village Secretariat Planned - - - 3/10/2011 RDS 7/10/2011 333 ENREP/W/565 Maviddapuram (J/231), Maviddapuram Jaffna Vali North DC 3.70 0.03 Post LKR 3.7 Maviddapuram 0.03 South(J/232), Jaffna Actual - - - 5/20/2011 South 9/22/2011 On Progress Reconstruction of Village Secretariat Planned - - - 3/10/2011 7/10/2011 RDS 334 ENREP/W/566 Illavalai North Jaffna Vali North DC 3.70 0.03 Post LKR 3.7 2.89 Actual - - - 6/24/2011 Viththagapuram 10/27/2011 On Progress (J/221)Viththagapuram(J/223), Jaffna. Reconstruction of PS Office, Bus Stand Planned 5/15/2011 6/25/2011 - 3/10/2011 Java Civil 11/12/2011 335 ENREP/W/567 & Market Building at Thellipalai, Jaffna Vali North NCB 32.35 0.29 Post LKR 28.13 Engineering 0.02 Jaffna(18.9 Mn) Actual 6/29/2011 7/29/2011 - 8/5/2011 Construction 12/14/2011 On Progress Planned 5/15/2011 6/25/2011 - 6/22/2011 MCT Cvil 12/19/2010 Reconstruction of ASC Building at 336 ENREP/W/568 Jaffna Vali North NCB 10.90 0.10 Post LKR 9.39 Engineering 1.53 Keerimalai, Jaffna(9.06Mn) Contractor Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O MCT Cvil Reconstruction of ASC Building at 336 ENREP/W/568 Jaffna Vali North NCB 10.90 0.10 Post LKR 9.39 Engineering 1.53 Keerimalai, Jaffna(9.06Mn) Actual 6/29/2011 7/29/2011 - 8/12/2011 12/14/2011 On Progress Contractor Improvement of Divisional Secretariat, Planned - - - 6/22/2011 RDS 12/19/2011 337 ENREP/W/569 Jaffna Vali North DC 2.41 0.02 Post LKR 2.41 - Thellipalai, Jaffna. Actual - - - 9/2/2011 Viththagapuram 1/12/2012 On Progress Planned 4/28/2010 6/2/2010 - 6/22/2010 Visvakarma 12/19/2010 338 ENREP/W/99 Reconstruction of IE's Office at valalai Jaffna Kopai NCB 15.50 0.14 Post LKR 15.72 4.07 Actual 3/26/2010 4/29/2010 - 10/1/2010 Pvt Ltd. 4/13/2011 On Progress Rehabilitation of Public Market at Planned - - - 10/12/2010 Women RDS 12/11/2010 Terminated 339 ENREP/W/289 Jaffna Kopai DC 4.96 0.04 Post LKR 4.96 0.01 Valalai Actual - - - 3/18/2011 Valalai 7/19/2011 5/30/2011 Vali-East Reconstruction of Food packing Centers Planned - - - 2/5/2011 6/5/2011 Sourthern 340 ENREP/W/308 7 Agriculture Product Storange Centre Jaffna Kopai DC 4.69 0.04 Post LKR 4.69 3.88 Division MPCS Neervely Actual - - - 1/31/2011 6/10/2011 On Progress Ltd. Vali- East Renovation of Food Packing Center & Planned - - - 2/6/2011 6/6/2011 Sourthern 341 ENREP/W/309 Agriculture Product Storage Centre Jaffna Kopay DC 3.52 0.03 Post LKR 3.52 - Division MPCS Stage II Neervely, Jaffna Actual - - - 12/22/2011 4/28/2012 On Progress Ltd. SDS, Planned - - - 2/2/2011 6/3/2011 Ramakrishnan 342 ENREP/W/291 Reconstruction of J/Kondavil R.M.V Jaffna Kopay DC 5.17 0.05 Post LKR 5.17 0.21 mahavidiyalaya Actual - - - 3/18/2011 m, Kondavil 7/19/2011 On Progress SDS Planned - - - 2/2/2011 6/3/2011 Reconstruction of Main hall J/Aththiyar J/Aththiyar 343 ENREP/W/569 Jaffna Kopay DC 3.21 0.03 Post LKR 3.21 - Hindu College Neervely Hindu College Actual - - - 5/20/2011 Neervely 9/22/2011 On Progress Vali-East Planned - - - 2/2/2011 6/3/2011 Reconstruction of Store for MPCS Northern 344 ENREP/W/616 Jaffna Kopay DC 5.50 0.05 Post LKR 5.5 - Iddaikkadu, Jaffna Division MPCS Actual - - - 7/29/2011 12/1/2011 On Progress Ltd. Vali-East Planned - - - 2/2/2011 6/3/2011 Reconstruction of Store for MPCS Northern 345 ENREP/W/570 Jaffna Kopay DC 5.50 0.05 Post LKR 5.5 - (J/281) at Paththameny Division MPCS Actual - - - 6/24/2011 Ltd. 10/27/2011 On Progress SDS Reconstruction of Two Storey Class Planned - - - 4/2/2011 6/3/2011 J/Achuvelly St 346 ENREP/W/571 Room Building J/Achuvelly St Thiresha Jaffna Kopay DC 4.31 0.04 Post LKR 4.32 - Thiresha Vidyalayam Actual - - - 6/9/2011 10/12/2011 On Progress Vidyalayam Planned - - - 3/8/2011 Pandaterippu 7/3/2011 Reconstruction of MPCS Branch- 347 ENREP/W/572 Jaffna Vali South West DC 1.90 0.02 Post LKR 1.9 parish MPCS 0.21 Sitharamoli, Sandilipai Actual - - - 5/25/2011 9/22/2011 On Progress ltd Planned - - - 5/25/2011 Pandaterippu 8/24/2011 Renovation of Main Store Pandaterippu 348 ENREP/W/573 Jaffna Vali South West DC 2.42 0.02 Post LKR 2.42 parish MPCS 0.21 parish MPCS ltd. Sandilipai Actual - - - 6/7/2011 9/23/2011 On Progress ltd Mareesankudal Planned - - - 5/26/2011 Kusumanthurai 8/25/2011 Reconstruction of Fish Stall & Rest Hall Fisherman 349 ENREP/W/288 Jaffna Vali South West DC 5.38 0.05 Post LKR 5.38 - Mathagal East in Sandillipay, Jaffna. Cooperative Actual - - - 12/22/2011 Society Ltd. 4/29/2012 On Progress SDS Reconstruction of Two Story Class Planned - - - 5/5/2011 9/6/2011 Uyarapulam 350 ENREP/W/574 Room Building J/Uyarapulam M.M.T.M Jaffna Vali South West DC 5.39 0.05 Post LKR 5.39 1.05 M.M.T.M School, Anaikoddai, Jaffna Actual - - - 6/7/2011 10/11/2011 On Progress School Planned 8/31/2010 10/5/2010 - 10/12/2010 Ratna 4/10/2011 351 ENREP/W/288 Reconstruction of ASC at Punkuduthivu Jaffna Velanai NCB 11.73 0.11 Post LKR 10.13 5.37 Actual 11/29/2010 1/4/2011 - 2/1/2011 Engineers 8/14/2011 On Progress Reconstruction of Velanai Central Planned - - - 2/10/2011 6/10/2011 352 ENREP/W/454 Jaffna Velanai DC 2.06 0.02 Post LKR 2.06 SDS 1.05 College Actual - - - 3/18/2010 7/30/2010 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Renovation of Roof for J/Mandaithivu Planned - - - 2/10/2011 6/10/2011 353 ENREP/W/455 Jaffna Velanai DC 1.71 0.02 Post LKR 1.71 SDS 0.20 MV Actual - - - 3/21/2011 7/21/2011 On Progress Renovation of Roof for J/Naranthanai Planned - - - 2/10/2011 6/10/2011 354 ENREP/W/456 Jaffna Velanai DC 1.59 0.01 Post LKR 1.59 SDS 1.46 RC Vid. Actual - - - 3/21/2011 7/21/2011 On Progress Renovation of Roof for J/Punguduteevu Planned - - - 2/10/2011 6/10/2011 Completed 355 ENREP/W/457 Jaffna Velanai DC 3.15 0.03 Post LKR 3.15 SDS 1.06 Sri thuraiswami Vid. Actual - - - 3/21/2011 7/21/2011 8/23/2011 Improvement of Self Study Center at Planned - - - 1/5/2011 5/5/2011 356 ENREP/W/575 Jaffna Velanai DC 4.74 0.04 Post LKR 4.74 Delft MPCS - Delft in Jaffna Actual - - - 8/3/2011 12/6/2011 On Progress Planned - - - 4/18/2011 J/Kayts 8/16/2011 Renovation of Main Hall Enterance Roof 357 ENREP/W/576 Jaffna Kayts DC 0.85 0.01 Post LKR 0.85 St.Anthony's 0.09 at J/Kayts St.Anthony's College jaffna Actual - - - 5/20/2011 9/22/2011 On Progress College SDS Consortium of Planned - - - 4/19/2011 8/17/2011 Organizations Reconstruction of Self Study Center at 358 ENREP/W/580 Jaffna Velanai DC 5.40 0.05 Post LKR 5.4 for Rural - Kayts, Jaffna. Empowerment, Actual - - - 30/12/2011 Kayts. 1/5/2012 Rehabilitation of Maravanpulo Branches Planned 10/25/2010 11/25/2010 - 1/6/2011 K.S Arumugam 5/6/2011 359 ENREP/W/290 Jaffna Chavakachcheri NCB 2.33 0.02 Post LKR 2.11 1.57 at Thenmaracchi. Actual 11/29/2010 1/4/2011 - 2/1/2011 & Sons. 7/15/2011 On Progress Maravanpulo Reconstruction of Primary Health Center Planned - - - 11/11/2010 West 3/11/2011 360 ENREP/W/458 Jaffna Chavakachcheri DC 2.18 0.02 Post LKR 2.18 0.66 Maravanpullo Community Actual - - - 12/23/2010 Center 4/26/2011 On Progress Planned - - - 11/12/2010 Thenmarachchi 3/12/2011 Reconstruction of Market at 361 ENReP/W/540 Jaffna Chavakachcheri DC 4.79 0.04 Post LKR 4.79 MPCS, - Eluthumadduval Stage I, Jaffna. Actual - - - 12/22/2011 Kodikamam 4/29/2012 On Progress Planned 1/25/2011 3/1/2011 - 3/24/2011 Tharani 7/22/2011 Rehabilitation of J/Meesalai 362 ENReP/W/540 Jaffna Chavakachcheri NCB 10.95 0.10 Post LKR 10.27 Building - Veerasingam MV Actual 6/29/2011 7/29/2011 - 8/12/2011 2/22/2012 On Progress Enterprises Vali-East Reconstruction ofPrimary Health Center Planned - - - 2/15/2011 Northern 6/15/2011 363 ENReP/W/617 Jaffna Karaveddy DC 5.49 0.05 Post LKR 5.49 4.03 at Thondamanaru Actual - - - 3/30/2011 Division MPCS 8/2/2011 On Progress Ltd Reconstruction of Two Storey Class Planned - - - 2/16/2011 6/16/2011 SDS, J/ Araly 364 ENREP/W/541 Room Building with Stage J/Araly Jaffna Chankanai DC 5.20 0.05 Post LKR 5.2 - Actual - - - 12/22/2011 Hindu College 4/27/2012 On Progress Hindu College, Jaffna Reconstruction of Two Storey Class Planned - - - 7/22/2011 SDS /Araly 11/19/2011 365 ENREP/W/542 Room Building J/Araly Murugamoorthy Jaffna Chankanai DC 5.50 0.05 Post LKR 5.5 Murugamoorthy 0.26 Vidyalayam. Actual - - - 7/22/2011 Vidyalayam. 11/25/2011 On Progress Additional works of self study centre at Planned - - - 366 ENREP/W/543 Jaffna Delft DC Post LKR Delft Actual - - - Supplying & Fixing steel truss for Planned - - - 367 ENREP/W/544 Jaffna Palai DC Post LKR proposed Market Eluthumadduval Actual - - - Extension work of Govt Audit office, Planned 368 ENREP/W/413 Jaffna to provide the office for the Asst Jaffna Jaffna DC 5.00 Post Auditor General, Northern Province Actual Reconstruction of PCMU, Mulliyan in Planned 369 ENREP/W/418 Jaffna Mulliyan DC Post Jaffna District Actual Improvement to Ministry of Economic Planned 370 ENREP/W/419 Jaffna Jaffna DC Post Development Building at Jaffna Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Improvement to Ministry of Economic 370 ENREP/W/419 Jaffna Jaffna DC Post Development Building at Jaffna Actual Planned 1/16/2010 2/20/2010 - 4/6/2010 Eastern 10/3/2010 Reconstruction of Mail Hub Office at 371 ENREP/W/100 Kilinochchi Karachi NCB 46.00 0.41 Post LKR 39.61 Building 9.96 Karachchi Actual 9/27/2010 11/4/2010 - 12/22/2010 9/2/2010 On Progress Construction Renovation of Laboratory building and Additional infrastructure facilities to Planned 1/11/2010 2/15/2010 - 3/7/2010 Visvakarma 6/5/2010 Completed 372 ENREP/W/101 Kilinochchi Karachi NCB 8.60 0.08 Post LKR 7.72 7.85 Regional Agriculture Research Center at Actual 3/26/2010 4/29/2010 - 5/12/2010 (Pvt)Ltd 11/22/2010 4/15/2011 Iranaimadhu Govt Seed Production Farm at Vadakachchi - Phase 1 (District Planned 1/16/2010 2/20/2010 - 4/6/2010 Master 10/3/2010 373 ENREP/W/103 Kilinochchi Karachi NCB 15.03 0.14 Post LKR 13.24 13.34 agriculture training centre and Actual 6/26/2010 7/16/2010 - 7/23/2010 Building 1/3/2011 On Progress Vaddakachchi farm rehabilitation) Re-construction of Karachi Office & Planned 1/11/2010 2/15/2010 - 3/7/2010 KPK 6/5/2010 374 ENREP/W/104 Kilinochchi Karachi NCB 19.00 0.17 Post LKR 16.44 8.92 Library Building in Kilinochchi Actual 5/10/2010 6/9/2010 - 8/9/2010 Construction 1/20/2011 On Progress Planned 12/28/2009 2/1/2010 - 2/21/2010 5/22/2010 Terminated Construction of MPCS Branch offices Dharmadasa 375 ENREP/W/105 Kilinochchi Karachi NCB 10.00 0.09 Post LKR 8.36 4.92 & MPCS building at Karachchi Actual 5/10/2010 6/9/2010 - 7/12/2010 Construction 12/23/2010 12/17/2011 Planned 12/28/2009 2/1/2010 - 2/21/2010 5/22/2010 Re-Construction of ACCD Office at 376 ENREP/W/107 Kilinochchi Karachi NCB 8.73 0.08 Post LKR 6.39 Land mark 3.02 Kilinochchi (Stage 1) Actual 3/26/2010 4/29/2010 - 5/21/2010 11/1/2010 On Progress Re-construction of ACLG Office Planned 12/28/2009 2/1/2010 - 2/21/2010 GISO 5/22/2010 377 ENREP/W/108 Kilinochchi Karachi NCB 9.20 0.08 Post LKR 8.15 0.96 Building at Kilinochchi Actual 5/10/2010 6/9/2010 - 8/25/2010 Construction 2/5/2011 On Progress Re-construction of Market Building Planned 12/16/2009 1/20/2010 - 2/9/2010 Kawsi 5/10/2010 Terminated 378 ENREP/W/110 Kilinochchi Karachi NCB 5.50 0.05 Post LKR 4.99 1.29 Complex at Ampalkulam Actual 5/10/2010 6/9/2010 - 7/23/2010 Construction 12/4/2010 3/16/2011 Renovation &Improvements to a Planned 12/28/2009 2/1/2010 - 2/21/2010 Premium 5/22/2010 379 ENREP/W/111 Building of Dept. of Buildings- Kilinochchi Karachi NCB 10.20 0.09 Post LKR 8.96 International.(p 4.54 Kilinochchi Actual 6/26/2010 7/16/2010 - 7/23/2010 vt) Ltd 12/4/2010 On Progress Planned 12/28/2009 2/1/2010 - 2/21/2010 Ahnanth 5/22/2010 380 ENREP/W/113 Repairs to Kilinochchi ASC Building Kilinochchi Karachi NCB 12.10 0.11 Post LKR 10.65 2.88 Actual 7/8/2010 8/10/2010 - 9/24/2010 Builders 3/7/2011 On Progress Re-construction of government seed farm Planned 12/28/2009 2/1/2010 - 2/21/2010 V.V.Ramanatha 6/21/2010 381 ENREP/W/114 Kilinochchi Karachi NCB 20.08 0.18 Post LKR 15.91 7.22 at Paranthan Actual 3/26/2010 4/29/2010 - 5/21/2010 n & Co (Pvt) 12/1/2010 On Progress Ltd Re-construction of Office Building for Planned 12/28/2009 2/1/2010 - 2/21/2010 5/22/2010 382 ENREP/W/115 Kilinochchi Karachi NCB 6.98 0.06 Post LKR 5.91 Turbo Group 3.25 Asst. Director of Fisheres Office Actual 4/20/2010 5/25/2010 - 6/30/2010 12/11/2010 On Progress Re-construction of Chief Engineer's Planned 12/28/2009 2/1/2010 - 2/21/2010 Hema 5/22/2010 Completed 383 ENREP/W/117 Kilinochchi Karachi NCB 10.04 0.09 Post LKR 8.47 8.13 office RDD Actual 4/20/2010 5/25/2010 - 6/30/2010 Engineering 11/11/2010 1/7/2011 Construction of PIC Building of Planned - - - 9/5/2010 Karachchi 1/3/2011 Completed 384 ENREP/W/117 Kilinochchi Karachi DC 5.25 0.05 Post LKR 5.25 5.17 ENRePat Kilinochchi Actual - - - 10/14/2010 South MPCS 2/9/2011 11/15/2010 Urgent Repairs to Agriculture Ministry Planned 5/1/2010 6/5/2010 - 6/25/2010 Mapil Civil 12/22/2010 Completed 385 ENREP/W/118 Kilinochchi Karachi NCB 2.09 0.02 Post LKR 1.90 1.62 Building Actual 3/26/2010 4/29/2010 - 6/11/2010 Eng. 12/1/2010 8/30/2010 Planned 5/2/2010 6/6/2010 - 6/26/2010 Premium 12/23/2010 Re-construction of Two Storey Senior 386 ENREP/W/119 Kilinochchi Karachi NCB 31.00 0.28 Post LKR 26.37 International.(p 11.49 Staff Quarters at Kilinochchi Actual 4/20/2010 5/25/2010 - 6/30/2010 12/11/2010 On Progress vt) Ltd Urgent repairs & Rehabilitation works to Planned - - - 4/25/2010 10/22/2010 Completed Karachchi 387 ENREP/W/120 Chief Engineers office Dept. of Kilinochchi Karachi DC 2.10 0.02 Post LKR 1.89 1.70 Actual - - - 5/11/2010 North MPCS 7/16/2010 8/10/2010 Buildings, Kilinochchi Renovation and Repairs to vetinary Planned 4/1/2010 5/6/2010 - 6/6/2010 JK 10/6/2010 Completed 388 ENREP/W/121 Kilinochchi Karachi NCB 6.28 0.06 Post LKR 6.61 5.91 Office and Quarters at Karachi Actual 5/10/2010 6/9/2010 - 7/12/2010 Construction 11/23/2010 11/23/2010 Reconstruction of Food Store Building Planned 4/1/2010 5/6/2010 - 6/6/2010 Ahnanth 10/6/2010 389 ENReP/W/198 Kilinochchi Karachi NCB 7.65 0.07 Post LKR 6.70 3.22 in Karachi Actual 7/8/2010 8/10/2010 - 9/9/2010 Builders 2/20/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Reconstruction of Paddy Store at Planned - - - 6/6/2010 Karachchi 10/6/2010 Completed 390 ENReP/W/199 Kilinochchi Karachi DC 5.61 0.05 Post LKR 5.04 4.26 Kilinochchi Actual - - - 8/27/2010 North MPCS 1/29/2011 4/15/2011 Construction of the Fertilizer store at Planned - - - 6/6/2010 FO, D5 Right 10/6/2010 Completed 391 ENReP/W/200 Kilinochchi Karachi DC 3.60 0.03 Post LKR 3.24 2.86 Kilinochchi ASC Actual - - - 8/12/2010 Bank 1/13/2011 2/28/2011 Construction of the Fertilizer store at Planned - - - 6/6/2010 10/6/2010 Completed 392 ENReP/W/201 Kilinochchi Karachi DC 3.60 0.03 Post LKR 3.24 FO, Pillayar 2.90 Akkarayankulam ASC Actual - - - 8/12/2010 1/13/2011 2/28/2011 Reconstruction of Kn/Kilinochchi Maha Planned - - - 2/20/2011 6/22/2011 Completed 393 ENReP/W/202 Kilinochchi Karachi DC 5.24 0.05 0 LKR 5.24 SDS 4.68 Vidyalayam Actual - - - 3/21/2011 7/26/2011 6/23/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 394 ENReP/W/311 Kilinochchi Karachi DC 0.61 0.01 Post LKR 0.61 SDS 0.43 perair to Kn/Uruthirapuram MV Actual - - - 10/9/2010 1/2/2011 4/5/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 395 ENReP/W/312 Kilinochchi Karachi DC 0.89 0.01 Post LKR 0.89 SDS 3.36 perair to Kn/Thiruvairu MV Actual - - - 9/20/2010 12/8/2010 2/23/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 396 ENReP/W/313 perair to Kn/Kanagambigaikulam Kilinochchi Karachi DC 1.65 0.01 Post LKR 1.65 SDS 1.54 GTMS Actual - - - 8/20/2010 12/8/2010 2/21/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 397 ENReP/W/314 Kilinochchi Karachi DC 1.29 0.01 Post LKR 1.29 SDS 0.98 perair to Kn/Pannakandy GTMS Actual - - - 9/20/2010 12/8/2010 2/25/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 398 ENReP/W/315 Kilinochchi Karachi DC 0.21 0.00 Post LKR 0.21 SDS 1.51 perair to Kn/Skanthapuram No.2 GTMS Actual - - - 10/12/2010 1/2/2011 3/20/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 399 ENReP/W/316 Kilinochchi Karachi DC 0.32 0.00 Post LKR 0.32 SDS 0.30 perair to Kn/Vaddakachchi South GTMS Actual - - - 10/13/2010 1/2/2011 2/18/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 400 ENReP/W/317 Kilinochchi Karachi DC 1.17 0.01 Post LKR 1.17 SDS 0.97 perair to Kn/Sivapathakalaiagam GTMS Actual - - - 9/20/2010 12/8/2010 2/15/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 401 ENReP/W/318 Kilinochchi Karachi DC 1.43 0.01 Post LKR 1.43 SDS 1.22 perair to Kn/Unionkulam GTMS Actual - - - 9/20/2010 12/8/2010 2/23/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 402 ENReP/W/319 perair to Kn/Kilinochchi Hindu Primary Kilinochchi Karachi DC 0.93 0.01 Post LKR 0.93 SDS 0.84 Vid Actual - - - 10/15/2010 1/2/2011 2/26/2011 Renovation and Reconstruction in Planned - - - 2/10/2011 7/10/2011 Completed 403 ENReP/W/461 K/Vivekananda Vidylayam, Kilinochchi Karachi DC 5.24 0.05 Post LKR 5.24 SDS 2.76 Ampalkulam Actual - - - 3/21/2011 7/26/2010 7/25/2011 Renovation of School building in Planned - - - 2/10/2011 7/10/2011 404 ENReP/W/462 Kilinochchi Karachi DC 1.97 0.02 Post LKR 1.97 SDS 0.30 Kn/Sivanagar GTMS Actual - - - 3/21/2011 7/26/2010 On Progress Renovation of School building in Planned - - - 2/10/2011 7/10/2011 Completed 405 ENReP/W/463 Kilinochchi Karachi DC 3.36 0.03 Post LKR 3.36 SDS 4.52 Kn/Puthumurippu vigneswara vidylayam Actual - - - 3/21/2011 7/26/2011 5/28/2011 Repairs of School Building at Planned - - - 6/5/2011 10/3/2011 406 ENReP/W/579 Kilinochchi Karachi DC 4.71 0.04 Post LKR 4.71 SDS 3.58 Kilinochchi Central College. Actual - - - 7/4/2011 11/1/2011 On Progress Construction of Class Room Building Planned - - - 5/15/2011 9/12/2011 407 ENReP/W/580 with Principal office at Kn/Ampalkulam Kilinochchi Karachi DC 5.45 0.05 Post LKR 5.45 SDS 1.31 Vivekanada Vidyalayam. Actual - - - 6/28/2011 11/1/2011 On Progress Construction of Class Room Building Planned - - - 5/15/2011 9/12/2011 408 ENReP/W/618 with Principal office at Kilinochchi Kandavalai DC 5.45 0.05 Post LKR 5.45 SDS 4.94 Kn/Ramanathapuram East GTMS Actual - - - 6/28/2011 11/1/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Construction of Class Room Building Planned - - - 5/15/2011 9/12/2011 409 ENReP/W/581 with Principal office at Kn/Poonakay Kilinochchi Pooneryn DC 5.45 0.05 Post LKR 5.45 SDS 4.93 Jeyapuram M.V Actual - - - 6/28/2011 11/1/2011 On Progress Renovation of School building at Kn/ St. Planned - - - 3/28/2011 11/23/2011 410 ENReP/W/582 Kilinochchi Karachi DC 3.71 0.03 Post LKR 3.71 SDS 2.19 Thiresa Girls College at Kilinochchi. Actual - - - 4/7/2011 10/18/2011 On Progress Construction of Class Room Building Planned - - - 1/15/2011 6/14/2011 411 ENReP/W/583 with Principal office at Kn/Iyakkachchi Kilinochchi Palai DC 5.45 0.05 Post LKR 5.45 SDS 1.46 GTMS Actual - - - 1/25/2011 7/8/2011 On Progress Construction of Class Room Building Planned - - - 2/6/2011 6/6/2011 412 ENReP/W/584 with Principal office at Kilinochchi Karachi DC 5.45 0.05 Post LKR 5.45 SDS 2.98 Kn/Uruthirapuram MV Actual - - - 2/8/2011 6/15/2011 On Progress Reconstruction of Class Room Building with Principal Office at Kn/Kilinochchi DC Planned - - - 2/7/2011 6/7/2011 413 ENReP/W/585 Kilinochchi Karachi 5.50 0.05 Post LKR 5.50 SDS - Central Primary Vidyalayam, Actual - - - 29/12/2011 4/28/2012 On Progress Kilinochchi. Repairs to Aesthetic College Building at DC Planned - - - 2/8/2011 SDS, 6/8/2011 Jeyanthinagar, Kilinochchi. 414 ENReP/W/586 Kilinochchi Karachi 5.50 0.05 Post LKR 5.50 Kn/Vivekananth - Actual - - - 12/15/2010 a Vidyalayam 4/18/2012 On Progress Reconstruction of Hostal Building for DC Planned - - - 2/9/2011 6/9/2011 415 ENReP/W/587 Kilinochchi Karachi 5.50 1.05 Post LKR 5.50 SDS - Kilnochchi Central College Actual - - - 30/12/2011 29/4/202 On Progress Renovation & Improvements to Co-op Planned 9/10/2010 10/15/2010 - 11/5/2010 Premium 3/5/2011 416 ENReP/W/320 Society's Rice mill & Stores at Kilinochchi Karachi NCB 12.03 0.11 Post LKR 10.13 International 2.25 Kilinochchi. Actual 11/29/2010 1/4/2011 - 2/1/2011 Pvt Ltd 7/15/2011 On Progress Renovation & Improvements to Co- Planned 8/31/2010 10/5/2010 - 10/26/2010 Kawsi 2/23/2011 417 ENReP/W/321 Kilinochchi Karachi NCB 9.51 0.09 Post LKR 8.40 5.04 operaty Building at Kilinochchi. Actual 11/30/2010 3/8/2011 - 4/7/2011 Construction 10/18/2011 On Progress Renovation & Improvements to Planned 8/31/2010 10/5/2010 - 10/26/2010 2/23/2011 Sadhu 418 ENReP/W/322 Karachchi East MPCS mills and Stores Kilinochchi Karachi NCB 6.08 0.05 Post LKR 4.97 3.44 Actual 11/29/2010 1/4/2011 - 1/25/2011 Construction 10/6/2011 On Progress at Kilinochchi. Reconstruction of 03 Nos. MPCS Planned 8/31/2010 10/5/2010 - 10/26/2010 Premium 2/23/2011 419 ENReP/W/323 Branches of Karachi East MPCS at Kilinochchi Karachi NCB 7.20 0.06 Post LKR 6.53 International 1.45 Vaddakachchi, Kilinochchi. Actual 11/29/2010 1/4/2011 - 1/25/2011 Pvt Ltd 7/8/2011 On Progress Karachi South MPCS Outlet at Planned - - - 10/26/2010 Karachi South 2/23/2011 420 ENReP/W/324 Kilinochchi Karachi DC 2.15 0.02 Post LKR 2.15 1.85 Selvanagar Actual - - - 2/8/2011 MPCS 6/15/2011 On Progress Karachi South MPCS Outlet at Planned - - - 10/26/2010 Karachi South 2/23/2011 Completed 421 ENReP/W/464 Kilinochchi Karachi DC 2.15 0.02 Post LKR 2.15 1.81 Uruthirapuram Actual - - - 2/8/2011 MPCS 6/15/2011 7/13/2011 Reconstruction of Stores at Planned - - - 10/26/2010 Akkarayan 2/23/2011 422 ENReP/W/465 Kilinochchi Karachi DC 2.24 0.02 Post LKR 2.24 1.80 Skanthapuram for Akkarayan MPCS Actual - - - 2/21/2011 MPCS Ltd 6/23/2011 On Progress Planned - - - 10/26/2010 Thiruvairu 2/23/2011 Reconstruction of 01 MPCS Branch of 423 ENReP/W/325 Kilinochchi Karachi DC 2.15 0.02 Post LKR 2.15 Youth Project 1.08 Thiruvaiyaru MPCS(thiruvaiyaru West) Actual - - - 2/21/2011 6/23/2011 On Progress Agriculture Co- Reconstruction of Outlets for Karachchi Planned - - - 10/26/2010 Karachi South 2/23/2011 424 ENReP/W/326 Kilinochchi Karachi DC 3.17 0.03 Post LKR 3.17 3.17 South MPCS Actual - - - 12/15/2010 MPCS Ltd. 4/23/2011 On Progress Reconstruction of 01 stores building for Planned - - - 10/26/2010 Karachi South 2/23/2011 425 ENReP/W/327 Kilinochchi Karachi DC 2.26 0.02 Post LKR 2.26 1.61 Karachi South MPCS Actual - - - 12/15/2010 MPCS Ltd. 4/23/2011 On Progress Rehabilitation of Hostal building in Planned - - - 2/10/2010 Karachi South 7/10/2010 426 ENReP/W/466 Kilinochchi Karachi DC 4.96 0.04 Post LKR 4.96 1.84 Mahadeva Siva Siruvar Illam Actual - - - 3/25/2011 MPCS Ltd. 7/28/2011 On Progress Rehabilitation of External Supply in Planned - - - 2/10/2010 Karachi South 7/10/2010 427 ENReP/W/467 Kilinochchi Karachi DC 1.47 0.01 Post LKR 1.47 0.61 Mahadeva Siva Siruvar Illam Actual - - - 3/25/2011 MPCS Ltd. 7/28/2011 On Progress Renovation and Improvement of Prayer Planned - - - 2/10/2010 7/10/2010 hall, Study Room & Store with external Karachi South 428 ENReP/W/468 Kilinochchi Karachi DC 5.50 0.05 Post LKR 5.50 0.97 Toilet building complex in Mahadeva Actual - - - 3/25/2011 MPCS 7/28/2011 On Progress Siva Siruvar Illam Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Repairs and Reconstruction of Planned - - - 2/14/2011 Karachi South 6/14/2011 Completed 429 ENReP/W/585 Kilinochchi Karachi DC 5.20 0.05 Post LKR 5.20 4.76 Kanagapuram Training Center Actual - - - 3/28/2011 MPCS 7/28/2011 5/6/2011 Reconstruction of Field Officer's Office Planned - - - 4/15/2011 8/15/2011 Karachi South 430 ENReP/W/587 Building District Secretariat, Kilinochchi Karachi DC 5.43 0.05 Post LKR 5.43 - Actual - - - 5/20/2011 MPCS 9/22/2011 On Progress Kilinochchi. Confederation Reconstruction of Office Building for Planned - - - 4/20/2011 8/20/2011 of Co-operative 431 ENReP/W/539 Confederation of Co-op Society, Kilinochchi Karachi DC 5.03 0.05 Post LKR 5.03 2.30 Actual - - - 5/27/2011 Society, 9/30/2011 On Progress Kilinochchi. Kilinochchi Reconstruction of ACCD Office Balance Planned - - - 4/21/2011 Karachchi 8/21/2011 432 ENReP/W/590 Kilinochchi Karachi DC 3.65 0.03 Post LKR 3.65 - Work at Kilinochchi. Actual - - - 12/29/2011 North MPCS 4/28/2012 On Progress Reconstruction of Laboratory Building Planned - - - 6/15/2011 Karachchi 10/15/2011 433 ENReP/W/588 Kilinochchi Karachi DC 4.51 0.04 Post LKR 4.51 1.08 for Dept. of Building, Kilinochchi. Actual - - - 6/23/2011 North MPCS 10/27/2011 On Progress Reconstruction of MPCS Outlet Planned - - - 6/10/2011 10/10/2011 Karachchi 434 ENReP/W/589 BuildingUmaiyalpuram Branch, Kilinochchi Kandavalai DC 4.35 0.04 Post LKR 4.35 - Actual - - - 6/23/2011 North MPCS 10/27/2011 On Progress Kilinochchi. Reconstruction of Paddy Stor to Planned - - - 6/10/2011 Akkarayan 10/10/2011 435 ENReP/W/619 Kilinochchi Karachi DC 4.35 0.04 Post LKR 4.35 - Akkarayan MPCS at Konavil Actual - - - 9/27/2011 MPCS Ltd 1/26/2012 On Progress Reconstruction of Office for Department Planned 4/5/2011 5/5/2011 - 6/2/2011 Premier 1/28/2012 436 ENReP/W/469 Kilinochchi Karachi NCB 24.16 0.22 Post LKR 22.40 3.60 of Survey at Kilinochchi Actual 7/7/2011 7/29/2011 - 8/12/2011 Enterprises 2/22/2012 On Progress Reconstruction of Study Hall Building at Planned - - - 6/2/2011 RDS 1/28/2012 437 ENReP/W/470 Kilinochchi Karachi DC 3.60 0.03 Post LKR 3.60 - Shanthapuram, Kilinochchi Actual - - - 12/26/2011 Santhapuram 4/27/2012 On Progress Kilinochchi Planned - - - 8/15/2011 Palm 4/11/2012 438 ENReP/W/470 Reconstruction of Market Vadakachchi Kilinochchi Karachi DC 4.79 0.04 Post LKR 4.79 1.25 Actual - - - 8/17/2011 Development 12/20/2011 On Progress Co-op Society Northern Planned - - - 8/15/2011 Region Lorry 4/11/2012 439 ENReP/W/471 Reconstruction of Market Skanthapuram Kilinochchi Karachi DC 4.79 0.04 Post LKR 4.79 - Actual - - - 8/17/2011 Owners' co-op 12/31/2011 On Progress Society Ltd Planned - - - 5/5/2011 Thiruvaiyaru 10/2/2011 440 ENReP/W/473 Reconstruction of GHC at Santhapuram Kilinochchi Karachi DC 5.20 0.05 Post LKR 5.20 1.81 Actual - - - 5/27/2011 MPCS 10/1/2011 On Progress Construction of 03 Nos of Production Planned - - - 10/6/2011 Karachi South 10/3/2011 Completed 441 ENReP/W/474 Kilinochchi Karachi DC 2.00 0.03 Post LKR 1.74 - well and Clean a Dug well Actual - - - 12/26/2011 MPCS 26/11/2011 . Planned - - - 4/15/2011 Karachchi 8/15/2011 442 ENReP/W/590 Renovation of GHC at Malaiyalpuram Kilinochchi Karachi DC 5.28 0.05 Post LKR 5.28 - Actual - - - 5/27/2011 South MPCS 10/1/2011 On Progress Reconstruction of Karachchi South Planned - - - 4/28/2011 8/30/2011 Karachchi 443 ENReP/W/591 MPCS Mill at Uruthirapuram, Kilinochchi Karachi DC 5.47 0.05 Post LKR 5.47 - Actual - - - 5/30/2011 South MPCS 10/1/2011 On Progress Kilinochchi Renovation of MPCS Outlet for Planned - - - 5/5/2011 9/10/2011 Karachchi 444 ENReP/W/592 Karachchi South MPCS Kilinochchi Karachi DC 1.89 0.02 Post LKR 1.89 0.45 Actual - - - 6/10/2011 South MPCS 10/15/2011 On Progress Uruththirapuram, Kilinochchi. Reconstruction of MPCS Outlet Planned - - - 6/15/2011 10/12/2011 Karachchi East 445 ENReP/W/593 Building Ramanathapuram East, Kilinochchi Karachi DC 2.05 0.02 Post LKR 2.05 - Actual - - - 6/23/2011 MPCS 10/27/2011 On Progress Kilinochchi. Thiruvaiyaru Reconstruction of Store (7.2m x 9m) Planned - - - 5/25/2011 Youth Project 9/25/2011 446 ENReP/W/594 Kilinochchi Karachi DC 2.24 0.02 Post LKR 2.24 1.58 Thiruvaiyaru MPCS at Kilinochchi. Actual - - - 6/10/2011 Cooperative 10/15/2011 On Progress Society. NS Planned 7/15/2011 7/28/2011 - 8/1/2011 Chandra 12/1/2011 Reconstruction of a Building for Audit 447 ENReP/W620 Kilinochchi Karachi 7.28 0.07 Post LKR 6.23 Construction - Sub Office in Kilinochchi Actual 7/19/2011 8/2/2011 - 8/12/2011 12/24/2011 On Progress Works Reconstruction of Field Officer’s Office 5.41 0.05 Planned - - - 8/2/2011 5.41 12/2/2011 Karachchi 448 ENReP/W/622 & 1 No Vehicle Park (Stage-II), Kilinochchi Karachi DC Post LKR - South MPCS Kilinochchi. Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Reconstruction of Field Officer’s Office Karachchi 448 ENReP/W/622 & 1 No Vehicle Park (Stage-II), Kilinochchi Karachi DC Post LKR - Actual - - - 10/31/2011 South MPCS 3/2/2012 On Progress Kilinochchi. 5.42 0.05 Planned - - - 8/3/2011 5.42 Karachchi 12/3/2011 Repairs of Building for Open University 449 ENReP/W/623 Kilinochchi Karachi DC Post LKR South MPCS - Study Center, Kilinochchi. Actual - - - 11/23/2011 3/27/2012 On Progress Ltd Repairs to Study Hall Building at 1.65 0.01 Planned - - - 8/4/2011 1.65 RDS 12/4/2011 450 ENReP/W/624 Kilinochchi Karachi DC Post LKR - Uthayanagar East, Kilinochchi. Actual - - - 12/26/2011 Uthayanagar 4/27/2012 On Progress Rehabilitation & Resumption of 4.26 0.04 Planned - - - 8/5/2011 4.26 RDS 12/5/2011 451 ENReP/W/625 Elephantpass & Kurunjathivu Salterns, Kilinochchi Pachilaipalai DC Post LKR Thadduvankodd - Kilinochchi. Actual - - - 12/26/2011 i 4/27/2012 On Progress Balance Work in Co-operative Council 5.50 0.05 Planned - - - 8/6/2011 5.50 Karachchi 12/6/2011 452 ENReP/W/626 Kilinochchi Pachilaipalai DC Post LKR - Buildings at Kilinochchi. Actual - - - 12/26/2011 North MPCS 4/27/2012 On Progress NS Planned 7/15/2011 7/28/2011 - 8/1/2011 Sarukaya 12/1/2011 453 ENReP/W622 Reconstruction of DS Office at Palai Kilinochchi Pachilaipalai 22.77 0.21 Post LKR 20.78 5.10 Actual 6/28/2011 7/29/2011 - 8/12/2011 Construction 3/10/2012 On Progress Planned 4/1/2010 5/6/2010 - 5/27/2010 Lion Asian 10/6/2010 Terminated 454 ENREP/W/122 Reconstruction of Post office at Palai Kilinochchi Pachilaipalai NCB 11.20 0.10 Post LKR 10.80 2.55 Actual 9/27/2010 11/14/2010 - 12/22/2010 Construction 6/4/2010 11/18/2011 Planned 5/7/2012 - Chandra 25/11/2012 Reconstruction of Post office balance 455 ENREP/W/123 Kilinochchi Pachilaipalai NS 8.70 0.08 Post LKR 8.28 Construction work at Palai Actual 3/8/2012 - 21/12/2012 works Re-construction of pachchipalai MPCS Planned 4/1/2010 5/6/2010 - 5/27/2010 Ahnanth 10/6/2010 456 ENReP/W/202 Kilinochchi Pachilaipalai NCB 11.40 0.10 Post LKR 9.30 2.15 office at Palai. Actual 7/8/2010 8/10/2010 - 9/24/2010 Builders 3/7/2011 On Progress Reconstructionof Bus Stand at Palai for Planned - - - 5/27/2010 9/27/2011 457 ENReP/W/595 Kilinochchi Pachilaipalai DC 4.68 0.04 Post LKR 4.68 Palai MPCS 1.17 Pachchilaipalai PS office Stage-I Actual - - - 8/5/2011 12/9/2011 On Progress Reconstruction of MPCS Store (7.2m x Planned - - - 5/27/2010 9/27/2011 458 ENReP/W/596 Kilinochchi Pachilaipalai DC 2.20 0.02 Post LKR 2.26 Palai MPCS 0.50 9m) Palai Kilinochchi. Actual - - - 6/23/2011 10/27/2011 On Progress Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 459 ENReP/W/339 Kilinochchi Pachilaipalai DC 1.12 0.01 Post LKR 1.14 SDS 1.08 perair to Kn/Soranpattru CCTMS Actual - - - 10/15/2010 1/3/2011 4/20/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 460 ENReP/W/340 Kilinochchi Pachilaipalai DC 2.08 0.02 Post LKR 2.08 SDS 2.01 perair to Kn/Soranpattru Ganesh Vid Actual - - - 8/20/2010 12/8/2010 2/21/2011 Planned - - - 10/8/2010 11/22/2010 Completed Providing roof with necessary structural 461 ENReP/W/341 Kilinochchi Pachilaipalai DC 1.44 0.01 Post LKR 1.44 SDS 1.37 perair to Kn/Tharmakerny GTMS Actual - - - 9/15/2010 12/8/2010 2/24/2011 Planned - - - 4/10/2011 8/10/2011 Repairs to School Building at Kn/ Palai 462 ENReP/W/597 Kilinochchi Pachilaipalai DC 5.48 0.05 Post LKR 5.48 SDS 5.09 RCTMS, Kilinochchi Actual - - - 5/11/2011 9/13/2011 On Progress Reconstruction of (120’x27’) Classroom 5.50 0.05 Planned - - - 4/11/2011 5.50 SDS 8/11/2011 463 ENReP/W/598 Building With (20’x20’) Principal Kilinochchi Pachilaipalai DC Post LKR Tharmakkerney - Office at Kn/Kilaly RCTMS, Actual - - - 11/28/2011 GTMS 3/30/2012 On Progress Palm Reconstruction of Palm Development Co- 4.82 0.04 Planned - - - 4/12/2011 4.82 Development 8/12/2011 464 ENReP/W/599 Kilinochchi Pachilaipalai DC Post LKR - op Society Ltd at Palai, Kilinochchi. Actual - - - 12/26/2011 Co-op Society, 4/27/2012 On Progress Palai Reconstruction of Proposed MPCS 4.31 0.04 Planned - - - 4/13/2011 4.31 Palai MPCS 8/13/2011 465 ENReP/W/600 Outlet at Vannankerni & Kilinochchi Pachilaipalai DC Post LKR - Actual - - - 12/29/2011 Ltd. 4/28/2012 On Progress Sinnathalayady, Kilinochchi Reconstruction of Proposed MPCS 4.31 0.04 Planned - - - 4/14/2011 4.31 8/14/2011 Palai MPCS 466 ENReP/W/601 Outlet at Soranpattu & Kilali, Kilinochchi Pachilaipalai DC Post LKR - Actual - - - 12/29/2011 Ltd. 4/28/2012 On Progress Kilinochchi. Sooranpattu Reconstruction of Vegetable Market at Planned - - - 3/11/2011 sarasvathy 7/11/2011 Completed 467 ENReP/W/476 Kilinochchi Pachilaipalai DC 0.98 0.01 Post LKR 0.98 0.89 Pithukaddu Junction Palai Actual - - - 3/21/2011 Community 7/26/2011 6/16/2011 Center Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned - - - 4/15/2011 Pachcilipalli 8/16/2011 468 ENReP/W/479 Reconstruction of GHC at Iyakachchi Kilinochchi Pachilaipalai DC 3.04 0.03 Post LKR 3.04 1.76 Actual - - - 5/30/2011 MPCS 10/1/2011 On Progress Re-Estabilishment of Herbal Harden at Planned - - - 2/21/2010 Akkarayan 6/1/2010 469 ENREP/W/124 Kilinochchi Kandavalai DC 4.47 0.04 Post LKR 4.47 1.46 Kalmadunagar Actual - - - 1/10/2011 MPCS ltd. 5/10/2011 On Progress Re-Estabilishment of Herbal Harden Planned - - - 10/8/2010 11/22/2010 Karachchi East 470 ENReP/W/480 office & over head tank at Kilinochchi Kandavalai DC 5.40 0.05 Post LKR 5.15 4.74 MPCS Kanmadunagar Actual - - - 1/10/2011 5/10/2011 On Progress Planned - - - 2/21/2010 GM, Karachchi 5/7/2010 Completed Construction of MPCS Building for 471 ENREP/W/125 Kilinochchi Kandavalai DC 5.25 0.05 Post LKR 5.49 North MPCS 4.07 Karachi North MPCS Ltd Actual - - - 5/5/2010 Ltd 8/10/2010 3/12/2011 Construction of Veterinary Surgeon's Planned 12/28/2009 2/1/2010 - 2/21/2010 SY 5/7/2010 472 ENREP/W/126 Kilinochchi Kandavalai NCB 8.85 0.08 Post LKR 7.82 4.59 Office at Kandawalai Construction Actual 5/10/2010 7/16/2010 - 7/23/2010 12/4/2010 On Progress Turbo Group Re-construction of Market Building Planned 12/28/2009 2/1/2010 - 2/21/2010 Civil 5/7/2010 473 ENREP/W/127 Kilinochchi Kandavalai NCB 5.50 0.05 Post LKR 4.79 2.76 Complex at Paranthan Engineering Actual 5/10/2010 6/9/2010 - 8/9/2010 12/21/2010 On Progress Consultant Reconstruction of Post Office at Planned 12/28/2009 2/1/2010 - 2/21/2010 Dharmadasa 5/7/2010 Terminated 474 ENREP/W/128 Kilinochchi Kandavalai NCB 11.60 0.10 Post LKR 9.68 4.26 Paranthan Actual 5/10/2010 5/25/2010 - 7/12/2010 Construction 12/23/2010 15/03/2012 Planned - - - 2/21/2010 FO, 5/7/2010 Repairs of the Fertilizer store at 475 ENREP/W/203 Kilinochchi Kandavalai DC 1.20 0.01 Post LKR 1.20 Nagenthirapura 1.04 Puliyampokanai ASC Actual - - - 8/15/2010 1/13/2011 On Progress m Repairs of the Fertilizer store at Planned - - - 2/22/2010 FO, 5/8/2010 Completed 476 ENREP/W/204 Kilinochchi Kandavalai DC 0.69 0.01 Post LKR 0.69 0.55 Ramanathapuram ASC Actual - - - 8/15/2010 Vaddakachchi 1/13/2011 3/2/2011 Construction of proposed Building for Planned - - - 2/22/2010 5/8/2010 Completed Karachchi 477 ENREP/W/205 Karachchi North MPCS Ltd. Paranthan Kilinochchi Kandavalai DC 2.24 0.02 Post LKR 2.02 1.78 Actual - - - 8/26/2010 North MPCS 1/29/2011 3/15/2011 Branch Renovation & Improvements to Planned - - - 2/22/2010 5/8/2010 Completed Karachchi 478 ENReP/W/481 Karachchi North MPC Food Store at Kilinochchi Kandavalai DC 6.06 0.05 Post LKR 5.46 4.78 Actual - - - 9/6/2010 North MPCS 1/7/2011 4/15/2011 Paranthan Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 479 ENREP/W/343 Kilinochchi Kandavalai DC 1.45 0.01 Post LKR 1.45 SDS 1.32 perair to Kn/Muruganantha MV Actual - - - 10/13/2010 1/2/2011 2/20/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 480 ENREP/W/344 perair to Kn/Paranthan Hindu MV (120 Kilinochchi Kandavalai DC 2.00 0.02 Post LKR 2.00 SDS 1.72 x 27) Actual - - - 9/20/2010 12/8/2010 2/21/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 481 ENREP/W/345 Kilinochchi Kandavalai DC 0.55 0.00 Post LKR 0.55 SDS 0.42 perair to Kn/Kandawalai MV Actual - - - 10/12/2010 1/2/2011 On Progress Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 482 ENREP/W/346 Kilinochchi Kandavalai DC 0.10 0.00 Post LKR 0.10 SDS 0.91 perair to Kn/Paranthan GTMS Actual - - - 10/10/2010 1/2/2011 3/20/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 483 ENREP/W/347 Kilinochchi Kandavalai DC 0.89 0.01 Post LKR 0.89 SDS 0.85 perair to Kn/Kaddaikadu GTMS Actual - - - 9/20/2010 12/8/2010 2/23/2011 Reconstruction of (120'x27') Classroom Building with Principal office Planned - - - 7/15/2011 11/15/2011 484 ENREP/W/598 Kilinochchi Kandavalai DC 5.48 0.05 Post LKR 5.48 SDS - Kn/Mylvaganapuram GTMS, Actual - - - 8/3/2011 12/6/2011 On Progress Kilinochchi. Reconstruction of (120'x27') Classroom Planned - - - 7/15/2011 11/15/2011 485 ENREP/W/599 Building with Principal office Kilinochchi Kandavalai DC 5.48 0.05 Post LKR 5.48 SDS - Kn/Kovilvayal GTMS, Kilinochchi. Actual - - - 8/3/2011 12/6/2011 On Progress Reconstruction of (120'x27') Classroom Planned - - - 7/15/2011 11/15/2011 486 ENREP/W/600 Building with Principal office Kn/ Kilinochchi Kandavalai DC 5.48 0.05 Post LKR 5.48 SDS 4.82 Malaiyalapuram GTMS, Kilinochchi. Actual - - - 8/3/2011 12/6/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Reconstruction of (120'x27') Classroom Planned - - - 7/15/2011 11/15/2011 487 ENREP/W/601 Building with Principal office Kilinochchi Kandavalai DC 5.48 0.05 Post LKR 5.48 SDS - Kn/Mayavanoor GTMS, Kilinochchi. Actual - - - 8/3/2011 12/6/2011 On Progress Renovation of Classroom at Kn/ St Planned - - - 7/15/2011 11/15/2011 488 ENREP/W/602 Kilinochchi Kandavalai DC 0.29 0.00 Post LKR 0.29 SDS - Fatima RCTMS, Kilinochchi Actual - - - 8/3/2011 12/6/2011 On Progress Reconstruction of GHC at Planned - - - 5/15/2011 Karachchi 9/15/2011 489 ENReP/W/484 Kilinochchi Kandavalai DC 3.49 0.03 Post LKR 3.49 2.26 Puliyampokkanai Actual - - - 5/27/2011 North MPCS 9/30/2011 On Progress Planned - - - 5/15/2011 Karachchi 9/15/2011 490 ENReP/W/486 Reconstruction of GHC at Kalaru Kilinochchi Kandavalai DC 1.58 0.01 Post LKR 1.58 - Actual - - - 7/22/2011 North MPCS 11/26/2011 On Progress Reconstruction of GHC at Umayal Planned - - - 5/15/2011 Jeka 9/15/2011 491 ENReP/W/487 Kilinochchi Kandavalai DC 8.66 0.08 Post LKR 7.62 1.82 Puram Actual - - - 8/12/2011 Construction 1/23/2012 On Progress Rural Reconstruction of Primary Health Center Planned - - - 5/16/2011 Development 9/16/2011 492 ENReP/W/488 Kilinochchi Kandavalai DC 5.50 0.05 Post LKR 5.50 - at Kalmadhunagar, Kilinochchi. Actual - - - 12/26/2011 Society, 4/27/2012 On Progress Kalmadhunagar. Planned - - - 5/15/2011 Lanka Trading 9/15/2011 7/5/2012 493 ENREP/W/129 Construction of DS office at poonakary Kilinochchi Poonakary DC 52.02 0.47 Post LKR 45.38 8.93 Actual - - - 12/22/2010 & Construction 9/2/2011 Terminated Construction of District Fisheries Planned 12/28/2009 2/1/2010 - 2/21/2010 Rohan 5/7/2010 494 ENREP/W/130 Kilinochchi Poonakary NCB 5.09 0.05 Post LKR 4.26 4.09 Inspector Office at Jayapuram Actual 4/20/2010 5/25/2010 - 6/30/2010 Enterprises 12/11/2010 On Progress Planned 12/28/2009 2/1/2010 - 2/21/2010 5/7/2010 Reconstruction of Pradesheiya sabha 495 ENREP/W/131 Kilinochchi Poonakary NCB 6.00 0.05 Post LKR 5.11 Jeya Builders 1.55 office building pooneryn Actual 5/10/2010 6/9/2010 - 8/9/2010 1/20/2011 On Progress Re-construction of MPCS Office Planned 12/28/2009 2/1/2010 - 2/21/2010 Dharmadasa 5/7/2010 496 ENREP/W/132 Kilinochchi Poonakary NCB 5.81 0.05 Post LKR 4.40 5.76 Building at Poonakery Actual 3/26/2010 4/29/2010 - 6/11/2010 Construction 11/22/2010 On Progress Construction of Veterinary Surgeon's Planned 12/28/2009 2/1/2010 - 2/21/2010 5/7/2010 497 ENREP/W/133 Kilinochchi Poonakary NCB 8.02 0.07 Post LKR 6.93 Jeya Building 3.63 office at Poonakary Actual 5/10/2010 6/9/2010 - 8/9/2010 12/21/2010 On Progress Construction of market Complex at Planned - - - 2/21/2010 5/7/2010 498 ENREP/W/134 Kilinochchi Poonakary DC 5.22 0.05 Post LKR 4.71 Poonery MPCS 1.78 poonagary Actual - - - 917/2010 1/22/2011 On Progress Reconstruction of Post Office at Planned 12/28/2009 2/1/2010 - 2/21/2010 Eastern 5/7/2010 499 ENREP/W/135 Kilinochchi Poonakary NCB 11.10 0.10 Post LKR 9.99 2.97 Poonakary Actual 5/10/2010 6/9/2010 - 8/9/2010 Building 1/20/2011 On Progress Planned - - - 10/8/2010 FO, 11/22/2010 Terminated Construction of the Fertilizer store at 500 ENREP/W/207 Kilinochchi Poonakary DC 3.60 0.03 Post LKR 3.24 Kariyalainagapa - Mulankavil ASC Actual - - - 10/15/2010 1/13/2011 5/30/2011 duvan Construction of the Fertilizer store at Planned - - - 10/8/2010 11/22/2010 Completed 501 ENREP/W/208 Kilinochchi Poonakary DC 3.60 0.03 Post LKR 3.24 FO, Vadiyady 2.85 Poonakery ASC Actual - - - 10/15/2010 1/13/2011 3/25/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 502 ENREP/W/348 perair to Kn/Kariyalainagapaduvan No.2 Kilinochchi Poonakary DC 0.60 0.01 Post LKR 0.60 SDS 0.45 School Actual - - - 8/20/2010 12/8/2010 2/23/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 503 ENREP/W/349 Kilinochchi Poonakary DC 0.88 0.01 Post LKR 0.88 SDS 0.70 perair to Kn/Valaipadu RCTMS Actual - - - 10/15/2010 1/2/2011 2/24/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 504 ENREP/W/350 Kilinochchi Poonakary DC 0.74 0.01 Post LKR 0.74 SDS 0.68 perair to Kn/Gnanimadam GTMS Actual - - - 10/13/2010 12/8/2010 2/21/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 505 ENREP/W/351 perair to Kn/Poonakary Nallur Kilinochchi Poonakary DC 1.39 0.01 Post LKR 1.39 SDS 1.33 MV(100x20) Actual - - - 10/21/2010 1/11/2011 2/25/2011 Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 506 ENReP/W/488 perair to Kn/Poonakary Nallur Kilinochchi Poonakary DC 0.88 0.01 Post LKR 0.88 SDS 0.84 MV(72x21) Actual - - - 10/15/2010 1/9/2011 2/25/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 507 ENReP/W/489 perair to 60'x20', 20'x20' Kn/Chelliyar Kilinochchi Poonakary DC 1.02 0.01 Post LKR 1.02 SDS 0.76 thivu GTMS Actual - - - 10/12/2010 1/2/2011 2/18/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 508 ENREP/W/352 Kilinochchi Poonakary DC 2.34 0.02 Post LKR 2.34 SDS 2.10 perair to Kn/Chelliyar thivu GTMS Actual - - - 10/12/2010 1/3/2011 3/15/2011 Providing roof with necessary structural Planned - - - 10/8/2010 11/22/2010 Completed 509 ENREP/W/353 Kilinochchi Poonakary DC 3.26 0.03 Post LKR 3.26 SDS 2.88 perair to Kn/Karukkaithivu MV Actual - - - 10/13/2010 1/3/2011 2/25/2011 SDS, Planned - - - 2/10/2011 7/10/2011 Completed Renovation of Kn/Kariyalai Kn/Kariyalai 510 ENReP/W/490 Kilinochchi Poonakary DC 2.11 0.02 Post LKR 2.11 2.06 Nagapaduwan No II Actual - - - 3/21/2011 Nagapaduvan 7/26/2011 6/15/2011 No Ii GTMS Planned - - - 4/10/2011 8/12/2011 Repaits to 100'x20' School Building at 511 ENReP/W/603 Kilinochchi Poonakary DC 1.17 0.01 Post LKR 1.17 SDS 1.03 Kn/Poonakary Nallur M.V Kilinochchi. Actual - - - 5/20/2011 9/22/2011 On Progress Reconstruction of Gramodaya Health Planned - - - 4/10/2011 8/12/2011 Cancelled Karachchi 512 ENReP/W/604 Centre at 4thMile Post Poonagari, Kilinochchi Poonakary DC 1.68 0.02 Post LKR 1.68 - South MPCS Kilinochchi. Actual - - - 5/30/2011 10/1/2011 5/12/2011 Improvement of Class Room Building Planned - - - 4/10/2011 8/12/2011 513 ENReP/W/605 with Principal Office Kn/Thiruvaiaru Kilinochchi Karachi DC 5.48 0.05 Post LKR 5.48 SDS - Maha Vidyalayam, Kilinochchi. Actual - - - 8/3/2011 12/6/2011 On Progress 5.18 0.05 Planned - - - 4/11/2011 SDS 8/13/2011 Repairs to school Building at Kn/ 514 ENReP/W/606 Kilinochchi Akkarayan DC Post LKR 5.18 - Akkarayan M.V Kilinochchi Actual - - - 5/11/2011 9/13/2011 On Progress Reconstruction of Class Room Building 5.48 0.05 Planned - - - 4/12/2011 SDS 8/14/2011 515 ENReP/W/607 with Principal Office at Kn/Mudkomban Kilinochchi Akkarayan DC Post LKR 5.48 - GTMS, Kilinochchi. Actual - - - 12/16/2011 4/18/2012 On Progress Reconstruction of Class Room Building 5.48 0.05 Planned - - - 4/13/2011 SDS 8/15/2011 516 ENReP/W/608 with Principal Office at Kn/Oottupulam Kilinochchi Karachi DC Post LKR 5.48 - GTMS, Kilinochchi. Actual - - - 12/16/2011 4/18/2012 On Progress Repairs to school Building at Kn/ Planned - - - 4/10/2011 8/12/2011 517 ENReP/W/606 Kilinochchi Akkarayan DC 5.18 0.05 Post LKR 5.18 SDS 2.85 Akkarayan GTMS, Kilinochchi Actual - - - 5/11/2011 9/13/2011 On Progress Reconstruction of Store (7.2m x 9m) at Planned - - - 4/10/2011 Poonagary 8/12/2011 518 ENReP/W/607 Kilinochchi Poonakary DC 2.24 0.02 Post LKR 2.24 0.18 Poonagary MPCS Actual - - - 6/23/2011 MPCS 10/27/2011 On Progress Reconstruction of Akkaraayan MPCS Planned - - - 4/10/2011 Akkarayan 8/12/2011 519 ENReP/W/608 Kilinochchi Karachi DC 5.47 0.05 Post LKR 5.47 1.05 Head office, Kilinochchi. Actual - - - 6/10/2011 MPCS 10/15/2011 On Progress Reconstruction of Palm Development Co- Planned - - - 4/11/2011 8/13/2011 Akkarayan 520 ENReP/W/609 op Society Ltd at Poonakary, Kilinochchi Poonakary DC 4.35 0.04 Post LKR 4.35 - Actual - - - 16/12/2011 MPCS 1/31/2012 On Progress Kilinochchi. Reconstruction of GHC Planned - - - 4/10/2011 Karachchi 8/12/2011 521 ENReP/W/491 Kilinochchi Poonakary DC 3.78 0.03 Post LKR 3.78 - Kanakambikaikulam at Thampirai Actual - - - 7/22/2011 South MPCS 11/26/2011 On Progress Livestock Reconstruction of Building for Dept.of Planned - - - 8/1/2011 11/31/2011 Breeders 522 ENReP/W/623 Animal Production & Health at Kilinochchi Poonakary DC 3.11 0.03 Post LKR 3.11 0.99 Actual - - - 8/5/2011 cooperative 12/20/2011 On Progress Pooneryn Society Ltd Renovation & Improvements to Study Planned - - - 8/1/2011 11/31/2011 Karachi South 523 ENReP/W/624 Hall & Office Buildings at Children Kilinochchi Poonakary DC 3.59 0.03 Post LKR 3.59 - MPCS Home in Kilinochchi Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Renovation & Improvements to Study Karachi South 523 ENReP/W/624 Hall & Office Buildings at Children Kilinochchi Poonakary DC 3.59 0.03 Post LKR 3.59 - MPCS Home in Kilinochchi Actual - - - 9/27/2011 1/27/2012 On Progress Construction of Two Storey Building for Planned 12/28/2009 2/1/2010 - 2/21/2010 5/7/2010 Completed Zanu 524 ENREP/W/137 Manthai West Pradeshiya Shaba Sub Mannar Manthai West NCB 8.50 0.08 Post LKR 7.32 7.47 Construction. Office at Vidathalthivu Actual 4/20/2010 5/25/2010 - 6/30/2010 11/11/2010 4/15/2011 Re-Construction of 2 MPCS Branch Planned 12/28/2009 2/1/2010 - 2/21/2010 5/7/2010 Completed Sumanasekara 525 ENREP/W/138 Office and Repairs one Building in Mannar Manthai West NCB 6.00 0.05 Post LKR 6.89 4.96 Construction Manthai West Actual 3/26/2010 4/29/2010 - 6/1/2010 11/12/2010 12/7/2010 Planned 12/28/2009 2/1/2010 - 2/21/2010 Nilantha 5/22/2010 Completed Re-construction of Manthai AKN 526 ENREP/W/139 Mannar Manthai West NCB 9.55 0.09 Post LKR 8.79 Traders&Contra 7.48 Building at Manthai west Actual 3/26/2010 4/29/2010 - 6/11/2010 ctors. 11/22/2010 8/2/2011 Planned 12/28/2009 2/1/2010 - 2/21/2010 Barberyn 5/22/2010 Construction of Veterinary Surgeon's 527 ENREP/W/140 Mannar Manthai West NCB 8.15 0.07 Post LKR 8.05 Engineering 6.34 Office at Adampan Actual 5/10/2010 7/17/2010 - 7/23/2010 Construction 12/4/2010 On Progress Construction of 120'-0" x 120'-0" Planned 12/28/2009 2/1/2010 - 2/21/2010 Pushpamal 5/22/2010 528 ENREP/W/141 Mannar Manthai West NCB 5.02 0.05 Post LKR 4.07 1.92 Market Building at Adampan Construction Actual 4/20/2010 5/25/2010 - 6/30/2010 11/11/2010 On Progress Planned 12/28/2009 2/1/2010 - 2/21/2010 Nilantha 5/22/2010 Reconstruction of post office at 529 ENREP/W/143 Mannar Manthai West NCB 6.76 0.06 Post LKR 6.59 Traders&Contra 1.84 Adampan Actual 9/27/2010 11/4/2010 - 12/3/2010 ctors. 5/16/2011 On Progress Construction of Fertilizer store in Planned - - - 1/24/2011 FO, 5/24/2011 Completed 530 ENREP/W/209 Mannar Manthai West DC 3.71 0.03 Post LKR 3.34 2.79 Velankulam Vellankulam Actual - - - 8/26/2010 12/24/2010 3/29/2011 Construction of Fertilizer store at Planned - - - 1/24/2011 5/24/2011 Completed 531 ENREP/W/210 Mannar Manthai West DC 3.34 0.03 Post LKR 3.34 FO, Chalampan 2.84 Manthai Actual - - - 8/27/2010 12/30/2010 3/27/2011 Planned - - - 10/8/2010 Agriculture 11/22/2010 Repair works of Kathankulam Paddy 532 ENREP/W/211 Mannar Manthai West DC 5.48 0.05 Post LKR 5.48 Society, 3.83 store 01 at manthai west Actual - - - 8/25/2010 12/24/2010 On Progress Manthai West Repair works of Kathankulam Paddy Planned 8/27/2010 10/1/2010 - 10/8/2010 Zanu 11/22/2010 Completed 533 ENREP/W/212 Mannar Manthai West NCB 6.80 0.06 Post LKR 6.07 5.73 store 02 at manthai west Actual 9/27/2010 11/4/2010 - 12/3/2010 Construction 3/25/2011 3/25/2011 Planned - - - 10/8/2010 Agriculture 11/22/2010 Repair works of Kathankulam Paddy 534 ENREP/W/213 Mannar Manthai West DC 5.03 0.05 Post LKR 5.03 Society, 4.05 store 03 at manthai west Actual - - - 8/24/2010 12/24/2010 On Progress Manthai West Planned - - - 10/8/2010 11/22/2010 Completed 535 ENREP/W/357 Mn/Thevanpitty RCTMS Mannar Manthai west DC 2.18 0.02 Post LKR 2.18 SDS 1.93 Actual - - - 9/30/2010 12/6/2010 2/22/2011 Planned - - - 10/8/2010 11/22/2010 Completed 536 ENREP/W/358 Mn/Monrampiddy GTMS Mannar Manthai west DC 1.55 0.01 Post LKR 1.55 SDS 1.31 Actual - - - 9/30/2010 12/6/2010 12/6/2010 Planned - - - 10/8/2010 11/22/2010 Completed 537 ENREP/W/359 Mn/Kovilkulam GTMS Mannar Manthai west DC 1.31 0.01 Post LKR 1.31 SDS 1.16 Actual - - - 9/30/2010 9/8/2010 12/10/2010 Planned - - - 10/8/2010 11/22/2010 Completed 538 ENReP/W/498 Mn/Karakuli GMMS Mannar Manthai west DC 1.81 0.02 Post LKR 1.81 RDS 1.62 Actual - - - 10/6/2010 12/12/2010 5/30/2011 Construction of fertilizer store in Planned - - - 5/21/2010 8/19/2010 539 ENREP/W/219 Mannar Manthai west DC 3.67 0.03 Post LKR 3.31 St. Anthony's 1.82 Uylankulam ASC Actual - - - 8/26/2010 12/24/2010 On Progress Construction of Fertilizer Store at Planned - - - 5/21/2010 8/19/2010 Completed 540 ENReP/W/499 Mannar Manthai west DC 3.05 0.03 Post LKR 3.05 FO, Chalampan 2.87 Adampan Actual - - - 9/1/2010 1/11/2011 1/25/2011 Reconstruction of Primary Medical Care Planned 9/27/2010 11/1/2010 - 11/21/2010 Rucksika 2/19/2011 541 ENReP/W/500 Mannar Manthai west NCB 5.54 0.05 Post LKR 4.72 1.19 Unit Periyamadu. Actual 11/29/2010 1/4/2011 - 2/1/2011 Builders 7/15/2011 On Progress K Vemake Repairs to 2 no of Co-op Branches at Planned 9/27/2010 11/1/2010 - 11/21/2010 Civil 2/19/2011 Terminated 542 ENReP/W/501 Mannar Manthai west NCB 3.58 0.03 Post LKR 3.14 0.58 Kandal & Kovilkulam. Construction Works Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O K Vemake Repairs to 2 no of Co-op Branches at Civil 542 ENReP/W/501 Mannar Manthai west NCB 3.58 0.03 Post LKR 3.14 0.58 Kandal & Kovilkulam. Actual 11/29/2010 1/4/2011 - 2/10/2011 Construction 6/24/2011 11/17/2011 Works Reconstruction of Fertilizer Store at Planned - - - 11/22/2010 FO 2/20/2011 543 ENReP/W/503 Mannar Manthai west DC 3.83 0.03 Post LKR 3.83 - Illupaikadvai, Mannar Actual - - - 12/8/2011 Illupaikadvai 4/10/2012 On Progress Planned - - - 11/23/2010 Manthai West 2/21/2011 544 ENReP/W/504 p Mannar Manthai west DC 3.09 0.03 Post LKR 3.83 Division Famers - Actual - - - 12/8/2011 Organization 4/10/2012 On Progress Reconstruction of Fertilizer Store at Planned - - - 11/24/2010 2/22/2011 545 ENReP/W/617 Mannar Manthai west DC 3.81 0.03 Post LKR 3.81 FO Salampan - Vidathalteevu, Mannar Actual - - - 11/15/2011 3/20/2012 On Progress Reconstruction of Primary Medical Care Planned 9/27/2010 11/1/2010 - 11/21/2010 Rucksika 2/19/2011 546 ENReP/W/502 Mannar Musali NCB 11.09 0.10 Post LKR 9.19 2.17 Unit and OPD Block at Martchchukaddi. Actual 11/29/2010 1/4/2011 - 2/10/2011 Builders 6/24/2011 On Progress Planned 6/15/2011 7/15/2011 - 8/1/2011 Mega 1/28/2012 Reconstruction of PS Office at Musali, 547 ENReP/W/617 Mannar Musali NCB 27.59 0.25 Post LKR 25.93 Constructions & - Mannar Actual 6/30/2011 7/29/2011 - 8/12/2011 2/22/2012 On Progress Suppliers Reconstruction of Fertilizer Store at Planned - - - 11/2/2011 FO 4/30/2012 548 ENReP/W/618 Mannar Madhu DC 3.81 0.03 Post LKR 3.81 - Chalavathurai, Mannar Actual - - - 11/15/2011 Meththavelly 3/20/2012 1/0/1900 Construction of Two Storey Building for Planned 12/28/2009 2/1/2010 - 2/21/2010 5/22/2010 Completed Prasanth 549 ENREP/W/144 Manthai West Pradeshiya Shaba Sub Mannar Madhu NCB 8.50 0.08 Post LKR 7.01 6.55 Actual 4/20/2010 5/25/2010 - 6/30/2010 Builders. 11/10/2010 5/20/2011 Office at Madhu Reconstruction of 3 MPCS Branch Planned 12/28/2009 2/1/2010 - 2/21/2010 T.V.V.Building 6/11/2010 550 ENREP/W/145 Mannar Madhu NCB 8.95 0.08 Post LKR 8.14 6.76 Offices at Madhu Actual 5/10/2010 6/9/2010 - 8/25/2010 Contractors 2/5/2011 On Progress Construction of Veterinary Surgeon's Planned 12/28/2009 2/1/2010 - 2/21/2010 Arul Selvi 5/22/2010 Completed 551 ENREP/W/146 Mannar Madhu NCB 8.15 0.07 Post LKR 6.51 4.68 Office at Madhu Actual 5/10/2010 6/9/2010 - 9/8/2010 Construction 12/21/2010 5/3/2011 Construction of 120'-0" x 120'-0" Planned 12/28/2009 2/1/2010 - 2/21/2010 SLP Transport 5/22/2010 Completed 552 ENREP/W/147 Mannar Madhu NCB 5.02 0.05 Post LKR 4.19 3.43 Market Building at Madhu Actual 4/20/2010 5/25/2010 - 7/12/2010 & Construction 11/23/2010 4/22/2011 Reconstruction of Irranillpaikulam AKN Planned 3/27/2010 5/1/2010 - 5/21/2010 Samadhi 8/19/2010 Completed 553 ENREP/W/214 Mannar Madhu NCB 8.20 0.07 Post LKR 7.17 6.77 Building Actual 9/27/2010 11/4/2010 - 12/17/2010 Construction 5/30/2011 7/29/2011 Construction of Irranillpaikulam Planned - - - 5/21/2010 FO, 8/19/2010 554 ENREP/W/215 Mannar Madhu DC 2.88 0.03 Post LKR 2.88 1.90 Fertilizer Store at Irranillpaikulam ASC Actual - - - 8/13/2010 Uthayasooriyan 10/29/2010 On Progress Construction of Palampiddy Fertilizer Planned - - - 5/21/2010 8/19/2010 Completed 555 ENREP/W/216 Mannar Madhu DC 3.19 0.03 Post LKR 2.88 FO, Vinayagar 2.72 Store at Irranillpaikulam ASC Actual - - - 8/12/2010 1/13/2011 4/3/2011 Planned - - - 10/8/2010 11/22/2010 Completed 556 ENREP/W/364 Mn/Periyapandivirichan MV Mannar Madhu DC 2.19 0.02 Post LKR 2.19 SDS 1.77 Actual - - - 9/30/2010 12/6/2010 2/7/2011 Planned - - - 10/8/2010 11/22/2010 Completed 557 ENREP/W/365 Mn/Keerisuddan GTMS Mannar Madhu DC 2.59 0.02 Post LKR 2.59 SDS 1.83 Actual - - - 9/30/2010 12/6/2010 3/1/2011 Planned - - - 10/8/2010 11/22/2010 Completed 558 ENReP/W/503 Mn/Palampiddi GTMS Mannar Madhu DC 1.61 0.01 Post LKR 1.61 SDS 1.41 Actual - - - 10/4/2010 12/10/2010 12/10/2011 Planned - - - 10/8/2010 11/22/2010 Completed 559 ENReP/W/504 Mn/Thachchanamaruthamadu GTMS Mannar Madhu DC 1.44 0.01 Post LKR 1.44 SDS 1.24 Actual - - - 10/4/2010 12/10/2010 2/7/2011 repairs to school building at Planned - - - 10/8/2010 11/22/2010 Completed 560 ENReP/W/505 Mannar Madhu DC 0.73 0.01 Post LKR 0.73 SDS 0.84 Mn/Ilanthaimoddai GMMS Actual - - - 10/5/2010 12/11/2010 1/9/2011 Repair works of Palampiddy AKN Planned - - - 10/8/2010 11/22/2010 561 ENREP/W/217 Mannar Madhu DC 5.37 0.05 Post LKR 5.37 FO, Vinayagar 4.23 Building Actual - - - 8/27/2010 12/30/2010 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Reconstruction of Primary Medical Care Planned 10/11/2010 11/15/2010 - 12/15/2010 5/14/2011 Rucksika 562 ENReP/W/506 Unit and OPD Block at Mannar Madhu NCB 11.09 0.10 0 LKR 9.20 1.02 Actual 11/29/2010 1/4/2011 - 2/10/2011 Builders 7/24/2011 On Progress Iranalluppaikulam Planned - - - 6/6/2010 RDS, 9/4/2010 Completed Urgent repairs to CE office, Buildings, 563 ENREP/W/148 Mannar Mannar DC 2.19 0.02 post LKR 1.97 Pallimunai 1.82 Mannar Actual - - - 5/28/2010 8/21/2010 10/31/2010 West Construction of Technical Unit 34x32 Planned - - - 6/6/2010 FO, St. 9/4/2010 Completed 564 ENREP/W/218 Mannar Mannar DC 4.83 0.04 post LKR 4.83 4.37 Ground floor stage 1 for district office Actual - - - 8/27/2010 Anthiony's 12/30/2010 4/20/2011 Planned - - - 7/30/2010 RDS, 12/27/2010 Construction of ENReP PIC Building 565 ENReP/W/507 Mannar Mannar DC 4.92 0.04 post LKR 4.92 Panankaddikodd 5.02 Mannar Actual - - - 11/24/2010 3/31/2011 On Progress u Reconstruction of Technical Unit 1st Planned - - - 7/30/2010 FO, St. 12/27/2010 566 ENReP/W/616 Mannar Mannar DC 2.26 0.02 post LKR 2.26 - Floor (Stage II) Actual - - - 5/27/2011 Anthiony's 9/30/2011 On Progress Reconstruction of EE's Office Building Planned 6/15/2011 7/15/2011 - 7/30/2010 Mahadevn 12/29/2010 567 ENReP/W/508 Mannar Mannar DC 28.38 0.26 post LKR 26.90 - of Dept of Buidings, Mannar Actual 6/30/2011 7/29/2011 - 8/11/2011 Contractor 4/7/2012 On Progress Planned - - - 7/30/2010 RDS, 12/27/2010 Construction of PIC Building, Mannar 568 ENReP/W/617 Mannar Mannar DC 5.37 0.05 post LKR 5.37 Panankaddikodd - Stage II Actual - - - 8/26/2011 12/27/2011 On Progress u Reconstruction of General Audit Office Planned - 9/25/2011 - 10/1/2011 Arulselvi 2/28/2011 569 ENReP/W/618 Mannar Mannar NS 8.50 0.08 post LKR 8.54 - Building, Mannar Actual - 10/3/2011 - 10/7/2011 construction 3/5/2012 On Progress Reconstruction of ACAD Office Planned - - - 7/30/2011 11/30/2011 St. Anthony's 570 ENReP/W/625 Building (34'x48') Ground Floor Stage-I Mannar Manthai West DC 5.50 0.05 post LKR 5.50 - Actual - - - 7/18/2011 FO 11/19/2011 On Progress in Mannar Manthai West Reconstruction of Fertilizer Store at Planned - - - 7/30/2011 11/30/2011 Division 571 ENReP/W/626 Alkaddiveli ASC Manthai West in Mannar Manthai West DC 3.60 0.03 post LKR 3.60 - Actual - - - 7/19/2011 Agriculture 11/19/2011 On Progress Mannar Society Planned - - - 7/30/2011 RDS, 11/30/2011 Reconstruction of Garage Building & 572 ENReP/W/621 Mannar Manthai West DC 5.47 0.05 post LKR 5.47 Panankaddikodd - Drivers Rest Room Kachcheri, Mannar Actual - - - 12/26/2011 4/27/2012 1/0/1900 u West Repairs to 2 no of Co-op Branches at Planned - - - 6/6/2012 SLP Transport 8/15/2012 573 ENReP/W/501 Mannar Manthai west NS 2.42 0.03 Post LKR 3.14 Kandal & Kovilkulam. Actual - - - 7/5/2012 & Construction 9/21/2012 Planned - - - 574 ENReP/W/502 Construction of PIC Building stage 3 Mannar Mannar DC Post LKR Actual - - - Construction of (30*20) community Planned - - - 575 ENReP/W/503 Mannar Mannar DC Post LKR building at Mannar Actual - - - Renovation of building (59*20) of paddy Planned - - - 576 ENReP/W/504 store at Pallikuli & Construction of Mannar Pallikuli DC Post LKR (50*20) community building at Kannady Actual - - - Const.of 30'*20' Community Bldg. at Planned - - - 577 ENReP/W/505 Mannar Karunkandal DC Post LKR Karunkandal Actual - - - Const.of Fertilizer store at Planned - - - Pastini 578 ENReP/W/506 Mannar Musali NS Post LKR Marichukaddy at Musali Actual - - - Construction Const.of Marichukaddy AKN Bldg. at Planned - - - Pastini 579 ENReP/W/507 Mannar Musali NS Post LKR Musali Actual - - - Construction Construction of 2 Nos Dug Well at Planned - - - - CheddiyarMaha - 580 ENReP/W/508 Mannar Narikkadu DC Post LKR - 50.00 Narikkadu Village, Mannar Actual - - - - n - On Progress Kaddayadampa Relocation surveying at Narikkadu Planned 581 ENReP/W/509 Mannar Narikkadu DC 4.76 0.04 Post LKR Scheme at Mannar Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Relocation surveying at Narikkadu 581 ENReP/W/509 Mannar Narikkadu DC 4.76 0.04 Post LKR Scheme at Mannar Actual Reconstruction of Staulter house Planned 582 ENReP/W/510 Mannar Mannar NS Post LKR building at Mannar Actual Completion of Divisional Secretariat Planned 12/28/2009 2/1/2010 - 11/4/2010 Lion Asian 2/22/2011 Terminated 583 ENREP/W/149 Mullaitivu Thunukai NCB 35.73 0.32 Post LKR 31.17 6.53 Office Thunukkai DS (Phase 2) Actual 10/30/2010 12/3/2010 - 12/22/2010 Construction 9/2/2010 8/10/2011 Planned 12/28/2009 2/1/2010 - 2/21/2010 Supreme 5/22/2010 584 ENREP/W/150 Re construction of Thunukkai PS office Mullaitivu Thunukai NCB 11.23 0.10 Post LKR 9.81 1.98 Actual 7/8/2010 8/10/2010 - 9/24/2010 Builders 3/7/2011 On Progress Construction of Office Building for Planned - - - 2/21/2010 5/22/2010 Completed Thunukkai 585 ENREP/W/151 Multi- Purpose Co-op Society at Mullaitivu Thunukai DC 5.55 0.05 Post LKR 5 4.87 Actual - - - 3/24/2010 MPCS Ltd. 7/30/2010 12/24/2010 Thunukkai Sewa Economic Planned 12/28/2009 2/1/2010 - 2/21/2010 Development 6/11/2010 586 ENREP/W/153 District Herbal Garden at Mallavi Mullaitivu Thunukai NCB 10.21 0.09 Post LKR 8.9 1.39 Actual - 3/8/2011 - 4/7/2011 Company 9/18/2011 On Progress (PVT) LTD Construction of Veterinary Surgeon's Planned 12/28/2009 2/1/2010 - 2/21/2010 SY 5/22/2010 Completed 587 ENREP/W/154 Mullaitivu Thunukai NCB 8.85 0.08 Post LKR 7.9 3.06 Office at Thunukkai Actual 5/10/2010 7/16/2010 - 8/9/2010 Construction 12/21/2010 12/24/2010 Construction of Bus Stand & Market Planned 12/28/2009 2/1/2010 - 2/21/2010 Mary 6/21/2010 588 ENREP/W/155 Mullaitivu Thunukai NCB 16.18 0.15 Post LKR 15.75 12.34 Building at Thunukkai Actual 6/26/2010 7/16/2010 - 8/9/2010 Construction 2/19/2011 On Progress Construction of Sub Post Office at Planned 12/28/2009 2/1/2010 - 2/21/2010 Island 5/22/2010 Completed 589 ENREP/W/157 Mullaitivu Thunukai NCB 6.72 0.06 Post LKR 5.8 4.69 Yogapuram Actual 3/26/2010 4/29/2010 - 5/12/2010 Engineers 11/22/2010 5/31/2011 Planned 7/28/2010 9/1/2010 - 9/22/2010 Asiri 2/19/2011 590 ENREP/W/220 Reconstruction of ASC Thunukkai Mullaitivu Thunukai NCB 10.80 0.10 Post LKR 9.52 5.39 Actual 9/27/2010 11/4/2010 - 12/10/2010 Contractor 6/22/2011 On Progress Planned - - - 9/22/2010 Thunukkai 2/19/2011 Construction of Fertilizer store at 591 ENREP/W/221 Mullaitivu Thunukai DC 3.60 0.03 Post LKR 3.24 Cultivators 2.31 Thunukkai Actual - - - 8/20/2010 12/21/2010 On Progress Society Urgent Repairsto Office Building, Planned - - - 9/22/2010 2/19/2011 SDS, 592 ENREP/W/627 Qurters at Zonal Education Office Mullaitivu Oddusuddan DC 4.89 0.04 Post LKR 4.89 - Actual - - - - Mankulam M.V 12/6/2011 On Progress ,Thunukkai Planned 12/28/2009 2/1/2010 - 3/18/2010 Lion Asian 7/16/2010 Terminated Construction of Divisional Sedretariat 593 ENREP/W/160 Mullaitivu Manthai East NCB 52.40 0.47 Post LKR 44.98 Construction 8.39 office Building ofr Manthai East DS Actual 10/30/2010 12/3/2010 - 1/25/2011 10/6/2011 11/17/2011 (Pvt) Ltd. Reconstruction of PS office Building at Planned 12/28/2009 2/1/2010 - 2/21/2010 Pupethira 5/22/2010 594 ENReP/W/509 Mullaitivu Manthai East NCB 5.50 0.05 Post LKR 4.78 2.89 Manthai East Actual 6/26/2010 7/16/2010 - 7/23/2010 Construction 2/2/2011 On Progress Construction of Office Building for Planned - - - 2/21/2010 Panankamam 5/22/2010 595 ENReP/W/510 Multi- Purpose Co-op Society at Mullaitivu Manthai East DC 5.55 0.05 Post LKR 5 Pattu MPCS 4.44 Palinagar Actual - - - 4/3/2010 Ltd. 8/3/2010 On Progress Construction of Vaterinary Surgeon's Planned 12/28/2009 2/1/2010 - 2/21/2010 AJ 5/22/2010 596 ENReP/W/511 Mullaitivu Manthai East NCB 8.83 0.08 Post LKR 8.09 3.15 Office at Pandiyankulam Actual 5/10/2010 6/9/2010 - 8/9/2010 Construction 12/21/2010 On Progress Construction of Market Building at Planned 12/28/2009 2/1/2010 - 2/21/2010 Prashanth 5/22/2010 597 ENREP/W/164 Mullaitivu Manthai East NCB 6.50 0.06 Post LKR 5.7 4.74 Manthai East Actual 6/26/2010 7/16/2010 - 7/23/2010 Builders 2/2/2011 On Progress Reconstruction of Vavunikulam Planned 12/28/2009 2/1/2010 - 2/21/2010 SY 6/21/2010 598 ENREP/W/165 Irrigation Engineers office at Mullaitivu Manthai East NCB 19.40 0.17 Post LKR 16.16 Construction 3.90 Vavunikulam Actual 4/20/2010 5/25/2010 - 7/12/2010 &Contractors 12/23/2010 On Progress Construction of Sub Post Office at Planned 12/28/2009 2/1/2010 - 2/21/2010 Karunya Civil 5/22/2010 Completed 599 ENREP/W/166 Mullaitivu Manthai East NCB 6.72 0.06 Post LKR 5.55 4.44 Naddankandal Actual 3/26/2010 4/29/2010 - 5/19/2010 Eng. 11/29/2010 3/25/2011 Construction of Fertilizer store at Planned - - - 9/22/2010 FO, 2/19/2011 600 ENREP/W/222 Mullaitivu Manthai East DC 3.60 0.03 Post LKR 3.24 2.59 Pandiyankulam Actual - - - 7/16/2010 Pandiyankulam 12/30/2010 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Providing roof with necessary structural Planned - - - 10/7/2010 11/6/2010 601 ENREP/W/231 Mullaitivu Manthai East DC 0.94 0.01 Post LKR 0.94 SDS 0.84 repair to Mu/Vavunikulam Central Slusu Actual - - - 9/23/2010 12/14/2010 On Progress Repairs of DA Quarters, Staff Quarters Planned - - - 9/22/2010 2/19/2011 Pandiyankulam/ 602 ENReP/W/512 & Store Irrigation Engineer's office at Mullaitivu Manthai East DC 5.40 0.05 Post LKR 5.4 4.16 Thunukkai Palm Vavunikulam Actual - - - 1/6/2011 4/13/2011 On Progress Development Construction of District Office Building Planned 12/29/2009 2/2/2010 - 9/21/2010 Sewa Economic 1/19/2011 Completed 603 ENREP/W/167 Mullaitivu Oddusuddan NCB 12.20 0.11 Post LKR 10.79 8.84 for Housing Department at Mullaitivu Actual 3/20/2010 4/20/2010 - 5/12/2010 Development 11/22/2010 11/22/2010 Re construction of Oddusuddan PS Planned 12/28/2009 2/1/2010 - 2/22/2010 Inthiran 5/23/2010 604 ENREP/W/168 Mullaitivu Oddusuddan NCB 6.11 0.06 Post LKR 5.55 1.82 office -Puthukudiyiruppu Actual 7/8/2010 8/10/2010 - 9/9/2010 Builder 2/20/2011 On Progress Construction of Office Building for Planned - - - 2/21/2010 5/22/2010 Completed MPCS, 605 ENREP/W/169 Multi- Purpose Co-op Society at Mullaitivu Oddusuddan DC 5.55 0.05 Post LKR 5 4.58 Actual - - - 4/7/2010 Muthayankaddu 8/13/2010 4/30/2011 Muthuiyankaddu Planned 12/28/2009 2/1/2010 - 2/21/2010 Lanka 6/21/2010 7/5/2012 606 ENREP/W/173 Construction of Mail hub at Mankulam Mullaitivu Oddusuddan NCB 58.79 0.53 Post LKR 50.44 Trading&Constr 10.92 Actual 9/27/2010 11/4/2010 - 12/22/2010 uction 9/2/2010 Terminated Planned 12/28/2009 2/1/2010 - 2/21/2010 Jeshani 6/21/2010 Reconstruction of Post office at 607 ENREP/W/174 Mullaitivu Oddusuddan NCB 11.70 0.11 Post LKR 9.86 Buildings 4.06 Oddusuddan Actual 9/27/2010 11/4/2010 - 12/10/2010 6/22/2011 On Progress Contruction Reconstruction of District Agriculture Planned 12/28/2009 2/1/2010 - 2/21/2010 Premium 6/21/2010 608 ENREP/W/175 Mullaitivu Oddusuddan NCB 20.79 0.19 Post LKR 17.8 2.87 Training centre Actual 11/29/2010 1/4/2011 - 2/1/2011 International 8/14/2011 On Progress Urgent Repairs to Agriculture Ministry Planned 12/28/2009 2/1/2010 - 2/21/2010 Gnanam 6/21/2010 Completed 609 ENREP/W/158 Mullaitivu Oddusuddan NCB 4.30 0.04 Post LKR 4.25 3.49 Building Actual 3/26/2010 4/29/2010 - 5/21/2010 Builders 11/1/2010 10/21/2010 Reconstruction of Fertilizer store at Planned - - - 9/22/2010 2/19/2011 610 ENREP/W/223 Mullaitivu Oddusuddan DC 3.60 0.03 Post LKR 3.24 FO, Mankulam 2.87 Olumadu Actual - - - 7/26/2010 12/30/2010 On Progress Reconstruction of Fertilizer store at Planned - - - 9/22/2010 FO, 2/19/2011 611 ENREP/W/224 Mullaitivu Oddusuddan DC 3.60 0.03 Post LKR 3.24 1.48 Oddusudan Actual - - - 8/16/2010 Puliyakulam 12/16/2010 On Progress Repairs of Fertilizer store at Planned - - - 9/22/2010 FO, Track one 2/19/2011 Completed 612 ENREP/W/225 Mullaitivu Oddusuddan DC 0.94 0.01 Post LKR 0.96 0.83 Muthuiyankaddu Actual - - - 11/25/2010 Right Bank 3/2/2011 3/17/2011 Reconstruction of Agriculture Ministry Planned - - - 9/22/2010 2/19/2011 Completed 613 ENREP/W/226 Mullaitivu Oddusuddan DC 2.25 0.02 Post LKR 2.25 Muthaiyankadd 2.07 building Vithyapuram Actual - - - 11/1/2010 3/4/2011 3/1/2011 u MPCS Repair work to fertilizer stores at Planned - - - 7/30/2010 12/27/2010 614 ENREP/W/229 Mullaitivu Oddusuddan DC 1.61 0.01 Post LKR 1.61 FO, Palampasi 0.75 Thanduwan ASC Actual - - - 11/9/2010 2/14/2011 On Progress Providing roof with necessary structural Planned - - - 7/30/2010 12/27/2010 615 ENREP/W/232 Mullaitivu Oddusuddan DC 0.96 0.01 Post LKR 0.96 SDS 0.87 repair to Mu/Periyaeththimadu GTMS Actual - - - 9/3/2010 1/11/2011 On Progress Planned - - - 7/30/2010 12/27/2010 616 ENREP/W/233 Repairs of ASC at Olumadu Mullaitivu Oddusuddan DC 1.88 0.02 Post LKR 1.7 FO, Olumadu 0.94 Actual - - - 11/9/2010 3/16/2011 On Progress Renovation of Outlets (MPCS branch) Planned - - - 7/30/2010 12/27/2010 617 ENREP/W/234 at Vithiyapuram & Kaneshapuram in Mullaitivu Oddusuddan DC 4.07 0.04 Post LKR 4.07 Muthaiyankadd 0.54 Oddusuddan DS Division Actual - - - 9/9/2010 u MPCS 1/14/2011 On Progress Renovation of Outlets (MPCS branch) Planned - - - 7/30/2010 12/27/2010 618 ENREP/W/366 at Thirumurukandy in Oddusuddan DS Mullaitivu Oddusuddan DC 2.04 0.02 Post LKR 2.04 Muthaiyankadd 0.18 Division Actual - - - 9/9/2010 u MPCS 1/14/2011 On Progress Planned - - - 7/30/2010 Thift Credit 12/27/2010 Completed Renovation & Repair of Building for 619 ENREP/W/367 Mullaitivu Oddusuddan DC 1.03 0.01 Post LKR 1.05 Co_op Societies 0.98 TCCS Union at Vithiyapuram. Actual - - - 11/25/2010 3/2/2011 4/13/2011 Union Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Completion of Divisional Secretariat Planned 6/10/2010 7/15/2010 - 7/30/2010 Lion Asian 12/27/2010 Terminated 620 ENREP/W/259 Mullaitivu Oddusuddan NCB 22.52 0.20 Post LKR 18.45 3.10 Office Oddusuddan DS (Phase 2) Actual 9/27/2010 11/4/2010 - 12/10/2010 Construction 6/22/2011 8/10/2011 Planned 6/10/2010 7/15/2010 - 7/30/2010 Hema 12/27/2010 Renovation & Reconstruction of RDD 621 ENReP/W/513 Mullaitivu Oddusuddan NCB 23.36 0.21 Post LKR 20.2 EngineeringCon - Building Complex Actual 1/20/2011 3/8/2011 - 4/7/2011 10/18/2011 On Progress struction SDS, Urgent Roof Repairs to Thunukkai Planned - - - 3/15/2011 7/13/2011 Mankulam 622 ENReP/W/628 Zonal Education Office Buildings & Mullaitivu Oddusuddan DC 5.00 0.05 Post LKR 5 4.58 Actual - - - 4/26/2011 Maha 8/25/2011 On Progress Quarters, Mullaitivu. Vidyalayam Repairs of Oddusuddan ASC at Planned - - - 3/16/2011 F.O, 7/14/2011 623 ENReP/W/629 Mullaitivu Oddusuddan DC 0.89 0.01 Post LKR 0.89 - Mullaitivu Actual - - - 12/23/2011 Puliyankulam 4/24/2012 1/0/1900 Oddusuddan Renovation of Palm Development Office Planned - - - 3/17/2011 Palm 7/15/2011 624 ENReP/W/514 Mullaitivu Oddusuddan DC 2.77 0.02 Post LKR 2.77 - at Oddusuddan Actual - - - 12/23/2011 Development 4/24/2012 1/0/1900 Co-op Society Construction of Divisional Sedretariat Planned 6/10/2010 7/15/2010 - 7/30/2010 Wahid 12/27/2010 625 ENREP/W/232 Mullaitivu Maritimepattu NCB 52.40 0.47 Post LKR 44.58 10.18 office Building ofr maritime pattu DS Actual 9/27/2010 11/14/2010 - 12/22/2010 Construction 9/2/2010 On Progress Reconstruction of PS office building at Planned 6/10/2010 7/15/2010 - 7/30/2010 SMA 12/27/2010 626 ENREP/W/236 Mullaitivu Maritimepattu NCB 14.30 0.13 Post LKR 14.61 7.08 Maritime pattu -Phase 1 Actual 10/30/2010 12/3/2010 - 12/22/2010 Construction 7/4/2010 On Progress Repair works to food store no 1 at Planned - - - 7/30/2010 12/27/2010 Completed 627 ENREP/W/233 Mullaitivu Maritimepattu DC 2.63 0.02 Post LKR 2.63 Puthukudiyirup 2.05 mullaiwalai Actual - - - 9/13/2010 1/18/2011 10/6/2010 pu MPCS Repair works to Food & paddy store no Planned 6/10/2010 7/15/2010 - 7/30/2010 Tharani 12/27/2010 628 ENREP/W/238 Mullaitivu Maritimepattu NCB 5.94 0.05 Post LKR 5.15 3.04 2 at mulliyawalai Actual 11/29/2010 1/4/2011 - 2/1/2011 Construction 6/15/2011 On Progress Planned - - - 7/30/2010 FO, 12/27/2010 629 ENREP/W/239 Repairs to ASC Mulliyawalai Mullaitivu Maritimepattu DC 4.90 0.04 Post LKR 4.9 Mulliyawalai 1.41 Actual - - - 11/9/2010 North 3/16/2011 On Progress Planned - - - 7/30/2010 FO, 12/27/2010 Construction of Fertilizer store at 630 ENREP/W/240 Mullaitivu Maritimepattu DC 3.60 0.03 Post LKR 3.24 Thanneerutu 2.69 Mulliyawalai ASC Actual - - - 7/26/2010 12/30/2010 On Progress West Planned - - - 7/30/2010 FO, 12/27/2010 631 ENREP/W/241 Reconstruction of ASC Kumulamunai Mullaitivu Maritimepattu DC 3.20 0.03 Post LKR 3.2 Kumulamunai - Actual - - - 11/9/2010 East 3/16/2011 On Progress Construction of Fertilizer store at Planned - - - 7/30/2010 FO, 12/27/2010 632 ENREP/W/242 Mullaitivu Maritimepattu DC 3.24 0.03 Post LKR 3.24 1.56 Kumulamunai ASC Actual - - - 7/19/2010 Kumulamunai 12/30/2010 On Progress Planned 6/10/2010 7/15/2010 - 7/30/2010 Subramaniam 12/27/2010 633 ENREP/W/243 Reconstruction of ASC Alampil Mullaitivu Maritimepattu NCB 10.31 0.09 Post LKR 9.53 2.89 Actual 10/30/2010 12/3/2010 - 12/22/2010 Civil Eng. 7/4/2010 On Progress Planned - - - 7/30/2010 WRDS, 12/27/2010 Renovation & Repairs to DRRS & DPS 634 ENREP/W/244 Mullaitivu Maritimepattu DC 3.00 0.03 Post LKR 2.7 Vattapallai 2.54 at Kachcheri Actual - - - 8/4/2010 8/25/2010 On Progress North Repairing of proposed office space of Planned - - - 7/30/2010 MPCS 12/27/2010 635 ENREP/W/245 Mullaitivu Maritimepattu DC 5.28 0.05 Post LKR 5.28 4.73 ENReP office & Kachcheri Building Actual - - - 8/20/2010 Maritimepattu 12/28/2010 On Progress Improvements of maritimepattu Planned - - - 11/17/2010 Chemalai cente, 1/16/2011 Completed 636 ENREP/W/368 Praseshiya saba Chemalai sub office Mullaitivu Maritimepattu DC 2.00 0.02 Post LKR 2 Community 1.86 building Actual - - - 10/21/2010 center 1/10/2011 6/17/2011 Renovation of outlets (MPCS branch) at Planned - - - 7/30/2010 12/27/2010 MPCS 637 ENREP/W/370 Udappukulam & Chemmalai in Mullaitivu Maritimepattu DC 4.07 0.04 Post LKR 4.07 3.21 Actual - - - 8/23/2010 Maritimepattu 11/29/2010 On Progress Marritimepattu DS Division Renovation of outlets (MPCS branch) at Planned - - - 7/30/2010 12/27/2010 Completed MPCS 638 ENREP/W/371 Silawathai & Mulliyawalai west in Mullaitivu Maritimepattu DC 4.07 0.04 Post LKR 4.07 4.61 Actual - - - 8/23/2010 Maritimepattu 11/29/2010 3/27/2011 Marritimepattu DS Division Renovation of outlets (MPCS branch) at Planned - - - 7/30/2010 12/27/2010 MPCS 639 ENREP/W/372 Kallappadu & Karachcheikudiyiruppu in Mullaitivu Maritimepattu DC 4.07 0.04 Post LKR 4.07 1.74 Maritimepattu Marritimepattu DS Division Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Renovation of outlets (MPCS branch) at MPCS 639 ENREP/W/372 Kallappadu & Karachcheikudiyiruppu in Mullaitivu Maritimepattu DC 4.07 0.04 Post LKR 4.07 1.74 Actual - - - 8/23/2010 Maritimepattu 11/29/2010 On Progress Marritimepattu DS Division Repair of outlets (MPCS branch) at Planned - - - 7/30/2010 12/27/2010 MPCS 640 ENREP/W/373 Neeravipity, Mulliyawalai center & Mullaitivu Maritimepattu DC 3.00 0.03 Post LKR 3.06 1.48 Actual - - - 10/14/2010 Maritimepattu 12/5/2010 On Progress Alampil in Marritimepattu DS Division Planned - - - 7/30/2010 SDS, 12/27/2010 Completed Repairs to Maritimepattu DE office at 641 ENReP/W/515 Mullaitivu Maritimepattu DC 1.03 0.01 Post LKR 1.07 Mullaitivu 1.03 Zonal Education office Actual - - - 10/14/2010 12/5/2010 11/3/2011 HBTMS Providing roof with necessary structure Planned - - - 10/7/2010 11/6/2010 Completed 642 ENREP/W/374 Mullaitivu Maritimepattu DC 1.03 0.01 Post LKR 1.06 SDS 1.01 repair to Mu/Chellawattai TV Actual - - - 10/4/2010 11/27/2010 12/8/2010 Providing roof with necessary structure Planned - - - 10/7/2010 11/6/2010 Completed 643 ENREP/W/375 Mullaitivu Maritimepattu DC 1.27 0.01 Post LKR 1.32 SDS 1.22 repair to Mu/Thannirootu HBTMS Actual - - - 10/12/2010 12/5/2010 12/5/2011 Providing roof with necessary structure Planned - - - 7/30/2010 12/27/2010 Completed 644 ENReP/W/516 Mullaitivu Maritimepattu DC 0.37 0.00 Post LKR 0.39 SDS 0.32 repair to Mu/Mullaitivu RCTMS Actual - - - 10/11/2010 11/27/2010 10/26/2010 Providing roof with necessary structure Planned - - - 10/7/2010 8/21/2010 Completed 645 ENREP/W/379 Mullaitivu Maritimepattu DC 2.23 0.02 Post LKR 2.32 SDS 2.07 repair to Mu/Mulliyawalai TV Actual - - - 10/14/2010 12/5/2010 4/15/2011 Providing roof with necessary structure Planned - - - 10/7/2010 11/6/2010 Completed 646 ENREP/W/380 Mullaitivu Maritimepattu DC 0.45 0.00 Post LKR 0.46 SDS 0.44 repair to Mu/Mullaitivu HBTMS Actual - - - 10/18/2010 11/27/2010 11/3/2011 Providing roof with necessary structure Planned - - - 10/7/2010 11/6/2010 Completed 647 ENREP/W/382 Mullaitivu Maritimepattu DC 2.26 0.02 Post LKR 2.36 SDS 1.86 repair to Mu/Kumulamunai MV Actual - - - 10/14/2010 12/5/2010 10/28/2010 Providing roof with necessary structure Planned - - - 2/6/2011 3/8/2011 Completed 648 ENREP/W/384 Mullaitivu Maritimepattu DC 1.20 0.01 Post LKR 1.25 SDS 1.18 repair to Mu/Vidyannanda College Actual - - - 10/6/2010 2/15/2011 10/28/2011 Planned - - - 7/30/2010 FO, 12/27/2010 Reconstruction of Paddy Stores CUM 649 ENREP/W/385 Mullaitivu Maritimepattu DC 5.40 0.05 Post LKR 5.4 Mulliyawalai 4.56 Seles center at Mullaiwalai ASC Actual - - - 10/25/2010 3/8/2011 On Progress East Construction of fertilizer Stores at Planned - - - 7/30/2010 FO, Alampil 12/27/2010 650 ENREP/W/386 Mullaitivu Maritimepattu DC 3.60 0.03 Post LKR 3.24 1.79 Alampil ASC in Mullaitivu Actual - - - 9/8/2010 South 1/15/2011 On Progress Planned - - - 10/7/2010 SDS, 12/6/2010 651 ENReP/W/517 Impeovements to DEO at Maritiempattu Mullaitivu Maritimepattu DC 2.48 0.02 Post LKR 2.48 Mullaitivu 0.69 Actual - - - 2/28/2011 HBTMS 5/6/2011 On Progress improvements of a Block at Mu/ Planned 8/26/2010 9/30/2010 - 10/7/2010 Lanka Machile 12/6/2010 652 ENReP/W/518 Mullaitivu Maritimepattu NCB 6.82 0.06 Post LKR 5.25 1.24 Mullaitivu RCTMS Actual 1/20/2011 3/8/2011 - 4/7/2011 Leasers 9/18/2011 On Progress Improvements to Market Vatapallai, Planned - - - 2/6/2011 4/7/2011 653 ENReP/W/521 Kumulamunai & Chemmalai Market Mullaitivu Maritimepattu DC 5.00 0.05 Post LKR 5.12 MPCS,maritime 0.01 Maritimepatu PS, Actual - 3/8/2011 - 4/25/2011 pattu 8/29/2011 On Progress improvements of a Block at Mu/ Planned 1/5/2011 2/28/2011 - 10/7/2010 Prasanth 12/6/2010 654 ENReP/W/519 Mullaitivu Maritimepattu NCB 6.80 0.06 Post LKR 5.95 1.91 Chilawaththai shool Actual 1/20/2011 3/8/2011 - 4/25/2011 Builders 21/11/2011 On Progress Renovation of 10 Rooms Summary Planned - - - 7/1/2011 10/29/2011 655 ENReP/W/610 Quarters kachcheri staff at Mullaitivu Maritimepattu DC 5.30 0.05 Post LKR 5.3 Muththiyankadd 0.38 Maritimepattu Actual - - - 7/7/2011 u MPCS 11/4/2011 On Progress Planned - - - 6/14/2011 SDS, Alampil 10/18/2011 Reconstruction of Class Room Building 656 ENReP/W/610 Mullaitivu Maritimepattu DC 5.47 0.05 Post LKR 5.47 RC - at Karunadukerney GTMS Actual - - - 6/20/2011 10/18/2011 On Progress Vidiyalayam Reconstruction of Class Room Building Planned - - - 6/1/2011 SDS, Kokkulai 9/29/2011 657 ENReP/W/612 Mullaitivu Maritimepattu DC 5.47 0.05 Post LKR 5.22 4.14 at Kokulai GTMS Actual - - - 6/21/2011 GTMS 10/18/2011 On Progress Planned - - - 6/14/2011 SDS, 10/12/2011 Reconstruction of Class Room Building 658 ENReP/W/612 Mullaitivu Maritimepattu DC 5.47 0.05 Post LKR 5.47 Vadduvakal - at Muslim Vidyalayam Actual - - - 6/20/2011 10/18/2011 On Progress GTMS Repairs of Statistical branch, DRDO branch, Audit branch, Vehicle Garage & Planned - - - 10/7/2010 Maretimepattu 12/6/2010 Completed 659 ENREP/W/387 Mullaitivu Maritimepattu DC 2.30 0.02 Post LKR 2.39 2.15 Ladies & gents toilets buildings in the MPCS Kachcheri Premieses Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Repairs of Statistical branch, DRDO branch, Audit branch, Vehicle Garage & Maretimepattu 659 ENREP/W/387 Mullaitivu Maritimepattu DC 2.30 0.02 Post LKR 2.39 2.15 Ladies & gents toilets buildings in the Actual - - - 11/9/2010 MPCS 1/25/2011 12/10/2010 Kachcheri Premieses Reconstruction of ACLG Office at Planned - - - 6/1/2011 Latha 11/28/2011 660 ENReP/W/525 Mullaitivu Maritimepattu NCB 30.23 0.27 Post LKR 27.23 - Mullaitivu Actual - - - 8/12/2011 Construction 2/22/2012 On Progress Reconstruction of ACAD Office at Planned - - - 6/1/2011 Premier 11/28/2011 661 ENReP/W/526 Mullaitivu Maritimepattu NCB 28.24 0.25 Post LKR 25.85 - Mullaitivu Actual - - - 8/12/2011 Enterprises 2/22/2012 On Progress Reconstruction of PIC Building of Planned - - - 3/1/2011 MPCS, 8/28/2011 662 ENReP/W/629 Mullaitivu Maritimepattu DC 5.43 0.05 Post LKR 5.43 1.31 ENReP at Mullaitivu Actual - - - 8/11/2011 Maritimepattu 12/9/2011 On Progress Reconstruction of 60 x 20 Quarters at Planned - - - 12/1/2011 SDS, Alapmil 8/29/2011 663 ENReP/W/630 Mullaitivu Maritimepattu DC 4.04 0.04 Post LKR 4.04 - Karunaddaikerney GTMS at Mullaitivu Actual - - - 23/12/2011 RC Vid 4/24/2012 On Progress Reconstruction of 60 x 20 Quarters at Planned - - - 12/5/2011 SDS, Kokulai 8/30/2011 664 ENReP/W/631 Mullaitivu Maritimepattu DC 4.04 0.04 Post LKR 4.04 - Kokulai GTMS at Mullaitivu Actual - - - 23/12/2011 GTMS 4/24/2012 On Progress Completion of PIC Building Stage II at Planned - - - 12/1/2011 MPCS 8/29/2011 665 ENReP/W/632 Mullaitivu Maritimepattu DC 5.49 0.05 Post LKR 5.49 - Kachcheri Mullaitivu Actual - - - 23/12/2011 Maritimepattu 4/24/2012 On Progress Reconstruction of DS Office at Puthukkudiyirup Planned - - - 6/1/2011 Anchaneya 11/28/2011 666 ENReP/W/526 Mullaitivu NCB 52.59 0.47 Post LKR 49.31 - Puthukudiyiruppu, Mullaitivu pu Actual - - - 8/5/2011 Constructioin 4/15/2012 On Progress Reconstruction of PS Office at Planned - - - 6/1/2011 Sewa Economic 11/28/2011 667 ENReP/W/527 Mullaitivu Maritimepattu NCB 24.17 0.22 Post LKR 21.65 - Puthukudiyiruppu, Mullaitivu Actual - - - 8/5/2011 Development 2/15/2012 On Progress Reconstruction of Audit Sub Office in Planned 7/10/2011 7/25/2011 - 2/6/2011 Prasanth 4/7/2011 668 ENReP/W/630 Mullaitivu Maritimepattu NS 7.28 0.07 Post LKR 6.15 - Mullaitivu Actual 7/19/2011 8/2/2011 - 8/12/2011 Builders 12/14/2011 On Progress Completion of Divisional Secretariat Planned 7/12/2012 12/21/2012 Mary 669 ENREP/W/259 Office Oddusuddan DS Balance work Mullaitivu Oddusuddan NS 22.91 0.22 Post LKR 20.45 Construction (Phase 2) Actual 8/3/2012 Construction of Divisional Sedretariat Planned 7/10/2012 12/21/2012 Premier 670 ENREP/W/160 office Building of Manthai East DS Mullaitivu Manthai East NS 24.40 0.24 Post LKR 25.3 Enterprises Balance work Actual 8/3/2012 Completion of Divisional Secretariat Planned 7/15/2012 12/21/2012 Mary 671 ENREP/W/149 Office Thunukkai DS (Phase 2) Balance Mullaitivu Thunukai NS 24.30 0.24 Post LKR 23.79 Construction work Actual 8/3/2012 Planned Construction of Pre school building for 672 ENREP/W/150 Mullaitivu DC Post LKR Naddankandal Actual Planned Improv.to the office of the M/Economic 673 ENREP/W/151 Mullaitivu DC Post LKR Development in Mullaitivu Actual Planned 674 ENREP/W/416 Renovation of Ms Quarters at Mullaitivu Mullaitivu DC 1.30 0.01 Post Actual Planned Const.of Courts Registar's Quarters in 675 ENREP/W/417 Mullaitivu DC 2.30 0.02 Post Mullaitivu Actual Planned - - - 2/21/2010 6/21/2010 Completed Construction of Co-operative Retail Vavuniya Shop Building at Nainamadu, Vavuniya 675 ENREP/W/177 Vavuniya Vavuniya North DC 5.00 0.05 Post LKR 4.51 North MPCS 2.62 and Repair Works for Co-operative Ltd. Branch Shops at Nedunkerny, Vavuniya. Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Construction of Co-operative Retail Vavuniya Shop Building at Nainamadu, Vavuniya 675 ENREP/W/177 Vavuniya Vavuniya North DC 5.00 0.05 Post LKR 4.51 North MPCS 2.62 and Repair Works for Co-operative Actual - - - 5/18/2010 6/20/2010 10/21/2011 Ltd. Branch Shops at Nedunkerny, Vavuniya. Construction and Repairs of Rice mill Planned 12/26/2010 1/30/2011 - 2/6/2011 A.J 4/7/2011 Completed 676 ENREP/W/178 Vavuniya Vavuniya North NCB 9.98 0.09 Post LKR 8.78 7.63 and Stores at Nedunkerny Actual 4/20/2010 5/25/2010 - 6/30/2010 Construction 11/11/2010 2/24/2011 Re - Construction of DO's Quarters, Planned 12/28/2009 2/1/2010 - 2/21/2010 6/21/2010 Completed 677 ENREP/W/179 Seed Paddy Stores, Sales Center at Vavuniya Vavuniya North NCB 9.00 0.08 Post LKR 7.76 Vijeya Builders 5.09 Nedunkerny. Actual 3/26/2010 4/29/2010 - 5/12/2010 10/23/2010 12/14/2010 Construction of Bus stand and market Planned 12/28/2009 2/1/2010 - 3/18/2010 7/16/2010 678 ENREP/W/180 Vavuniya Vavuniya North NCB 41.84 0.38 Post LKR 30.91 Sisira Builders 25.20 Building at Nedunkerny Actual 6/26/2010 7/16/2010 - 7/30/2010 4/10/2011 On Progress Construction of Veterinary Surgeons Planned 12/29/2009 2/2/2010 - 2/22/2010 Karuniya Civil 5/23/2010 Completed 679 ENREP/W/181 Vavuniya Vavuniya North NCB 8.13 0.07 Post LKR 6.81 6.19 Office at Kanagarayankulam. Actual 3/20/2010 4/20/2010 - 5/12/2010 Contractors 11/22/2010 2/12/2010 Construction of Training center Building Planned 12/28/2009 2/1/2010 - 3/18/2010 Wahid 7/16/2010 680 ENREP/W/183 Vavuniya Vavuniya North NCB 33.00 0.30 Prior LKR 28.54 27.12 in Kanagarayankulam Actual 3/8/2010 3/23/2010 - 4/24/2010 Construction 11/4/2010 On Progress Construction of Community Store at Planned 12/29/2009 2/2/2010 - 2/22/2010 Inthiran 5/23/2010 Completed 681 ENREP/W/184 Vavuniya Vavuniya North NCB 2.50 0.02 Post LKR 2.11 1.82 Nedunkerny, Vavuniya Actual 3/20/2010 4/20/2010 - 5/12/2010 Contractors 11/22/2010 11/24/2010 Planned 12/28/2009 2/1/2010 - 2/21/2010 Vinayaga Civil 5/22/2010 Completed Construction of Post Office at 682 ENREP/W/185 Vavuniya Vavuniya North NCB 10.17 0.09 Post LKR 8.68 Eng. 7.65 Nedunkerny Actual 4/20/2010 5/25/2010 - 7/12/2010 12/23/2010 2/3/2011 Construction Planned - - - 6/24/2010 FO, 12/21/2010 Completed Repairs to A.I. Quarters Cum Office for 683 ENREP/W/186 Vavuniya Vavuniya North DC 2.28 0.02 Post LKR 2.05 Kanagarayankul 1.90 Agriculture Department Actual - - - 5/13/2010 10/12/2010 10/8/2010 am Repairs to Farmers Traing centre and Planned - - - 8/25/2010 1/22/2011 Vavuniya 684 ENREP/W/243 construction of tractor Garage at Vavuniya Vavuniya North DC 3.16 0.03 Post LKR 2.85 2.83 Actual - - - 8/27/2010 North MPCS 2/6/2011 On Progress nedunkerny Reconstructionof Co-Op Retail Shops at Planned 6/30/2010 8/4/2010 - 8/25/2010 CSN 1/22/2011 Terminated 685 ENReP/W/526 Vavuniya Vavuniya North NCB 10.09 0.09 Post LKR 9.52 1.20 Vavuniya Package-2 Actual 10/30/2010 12/3/2010 - 12/22/2010 Engineering 9/2/2010 10/2/2012 Planned - - - 7/30/2010 12/27/2010 Completed 686 ENREP/W/252 Renovation of V/Periyakulam GTMS Vavuniya Vavuniya North DC 2.90 0.03 Post LKR 2.61 SDS 2.34 Actual - - - 9/2/2010 12/8/2010 11/12/2010 Planned - - - 9/27/2010 11/11/2010 Completed 687 ENREP/W/391 Renovation of V/Marailluppai GTMS Vavuniya Vavuniya North DC 3.55 0.03 Post LKR 3.55 SDS 3.09 Actual - - - 9/22/2010 12/14/2010 12/27/2010 Planned - - - 9/27/2010 11/11/2010 Completed 688 ENREP/W/392 Renovation of V/Mannakulam GTMS Vavuniya Vavuniya North DC 1.91 0.02 Post LKR 1.91 SDS 1.71 Actual - - - 9/22/2010 12/14/2010 3/29/2011 Construction of Paddy store at Planned - - - 9/27/2010 MPCS, 12/26/2010 Completed 689 ENREP/W/400 Vavuniya Vavuniya North DC 4.86 0.04 Post LKR 4.86 2.67 Nedunkerny Actual - - - 10/4/2010 Vavuniya North 2/8/2011 4/29/2011 Reconstruction of fertilizer store at Planned - - - 9/27/2010 FO, 12/26/2010 Completed 690 ENREP/W/407 Vavuniya Vavuniya North DC 2.85 0.03 Post LKR 2.57 2.29 Kanakarayankulam Actual - - - 9/27/2010 Madiyamadu 2/1/2011 6/30/2011 Repairs of the Nedunkerny ASC Planned - - - 8/25/2010 1/22/2011 Completed 691 ENREP/W/242 Vavuniya Vavuniya North DC 5.16 0.05 Post LKR 4.66 FO, Katkulam 1.99 Building Actual - - - 9/3/2010 1/11/2011 6/30/2011 Improvements to Existing Building of Planned - - - 2/20/2010 MPCS, 3/30/2010 692 ENREP/W/187 Vavuniya Vavuniya DC 5.79 0.05 Post LKR 5.2 5.02 for PMU of ENReP Actual - - - 2/9/2010 Vavuniya 4/17/2010 On Progress Construction of Conference Hall and Planned - - - 8/25/2010 1/22/2011 Completed Vavuniya 693 ENREP/W/188 Improvements to PMU, ENReP at Vavuniya Vavuniya DC 5.43 0.05 Post LKR 5.43 5.10 Actual - - - 12/1/2010 MPCS 2/2/2011 3/28/2011 Vavuniya Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Repairs to College of Education Hostel Planned - - - 8/25/2010 1/22/2011 Completed 694 ENReP/W/527 Vavuniya Vavuniya DC 4.84 0.04 Post LKR 4.84 SDS 4.65 Blocks in Vavuniya Actual - - - 10/20/2010 3/31/2011 3/23/2011 Planned - - - 7/22/2010 9/13/2010 Completed 695 ENREP/W/253 Renovation of V/Kovilkunchukulam Vid Vavuniya Vavuniya DC 1.61 0.01 Post LKR 1.61 SDS 1.39 Actual - - - 9/22/2010 12/14/2010 12/9/2010 Renovation of Planned - - - 9/27/2010 9/5/2010 Completed 696 ENREP/W/388 Vavuniya Vavuniya DC 0.54 0.00 Post LKR 0.54 SDS 0.42 V/Arumugathanputhukulam GTMS Actual - - - 9/22/2010 12/14/2010 12/14/2010 Renovation of V/Nochchimoddai No 1 Planned - - - 9/27/2010 11/11/2010 Completed 697 ENREP/W/389 Vavuniya Vavuniya DC 0.91 0.01 Post LKR 0.91 SDS 0.86 JSV Actual - - - 9/23/2010 12/14/2010 12/31/2010 Renovation of V/Semamadu Planned - - - 9/27/2010 11/11/2010 Completed 698 ENREP/W/390 Vavuniya Vavuniya DC 1.00 0.01 Post LKR 1 SDS 0.83 Sanmuganantha vid Actual - - - 9/22/2010 12/14/2010 12/10/2010 Renovation of V/Semamadu Unit 2 Planned - - - 9/27/2010 11/11/2010 699 ENREP/W/254 Vavuniya Vavuniya DC 0.91 0.01 Post LKR 0.91 SDS 0.71 GTMS Actual - - - 9/22/2010 12/14/2010 On Progress Renovation of V/Matharpanikar Planned - - - 9/27/2010 11/11/2010 700 ENREP/W/255 Vavuniya Vavuniya DC 1.63 0.01 Post LKR 1.63 SDS 1.44 Makilankulam GTMS Actual - - - 9/23/2010 12/14/2010 On Progress Reconstruction & Renovation of School Planned 2/25/2011 8/4/2010 - 8/25/2010 Edward & 1/22/2011 701 ENReP/W/528 Vavuniya Vavuniya NCB 15.19 0.14 Post LKR 13.49 3.61 Buildings at Vavuniya Actual 2/29/2011 3/8/2011 - 3/22/2011 Christie 9/18/2011 On Progress Urgent Repairs to School building at Planned 2/25/2011 8/4/2010 - 8/25/2010 1/22/2011 Completed 702 ENReP/W/631 Vavuniya Vavuniya DC 5.28 0.05 Post LKR 5.28 SDS 4.76 Omanthai Centarl College Actual 2/29/2011 11/4/2010 - 4/17/2011 8/15/2011 6/232011 Construction of rice Mill and Stores at Planned 8/16/2010 9/20/2010 - 11/22/2010 Jathur 4/21/2011 Completed 703 ENREP/W/394 Vavuniya Vavuniya NCB 11.10 0.10 Post LKR 10.51 9.79 Omanthai Actual 9/27/2010 11/4/2010 - 12/10/2010 Enterprises 5/23/2011 7/25/2011 Planned - - - 10/20/2010 Vavuniya 3/19/2011 Completed 704 ENREP/W/396 Construction of Paddy store at omanthai Vavuniya Vavuniya DC 4.86 0.04 Post LKR 4.86 4.41 Actual - - - 10/1/2010 MPCS 2/4/2011 6/30/2011 Construction of Paddy store at Planned - - - 9/27/2010 Vavuniya 2/24/2011 705 ENREP/W/397 Vavuniya Vavuniya DC 3.89 0.04 Post LKR 3.89 3.08 Palamoddai Actual - - - 10/1/2010 MPCS 2/4/2011 On Progress Construction of Paddy store at Planned - - - 9/27/2010 MPCS, 12/26/2010 Completed 706 ENREP/W/401 Vavuniya Vavuniya DC 4.86 0.04 Post LKR 4.86 4.54 Arumugaththanputhukkulam Actual - - - 10/1/2010 Vavuniya 2/4/2011 5/30/2011 Fertilizer store at Omanthai in Planned - - - 8/25/2010 FO, 1/22/2011 707 ENREP/W/246 Vavuniya Vavuniya DC 2.78 0.03 Post LKR 2.78 1.96 Palamoddai Palamoddai Actual - - - 10/1/2010 2/4/2011 On Progress Rural Planned - - - 12/23/2010 Development 5/22/2011 708 ENReP/W/529 Reconstruction of Self learning center Vavuniya Vavuniya DC 4.99 0.04 Post LKR 5.08 2.42 Actual - - - 3/21/2011 Society, 8/21/2011 On Progress Ukkulankulam Addition & Improvements to Quality Planned - - - 1/27/2011 6/26/2010 MPCS, 709 ENReP/W/530 Control Laboratory at thandikulam & Vavuniya Vavuniya DC 4.48 0.04 Post LKR 4.48 4.15 Vavuniya Vehicle Park for EE office, vavuniya Actual - - - 3/11/2011 8/13/2011 On Progress Additional &Improvement to CE's & Planned - - - 8/25/2010 Vavuniya 1/22/2011 Completed 710 ENREP/W/251 Vavuniya Vavuniya DC 3.58 0.03 Post LKR 3.23 2.70 EE's office to Dept. of Building MPCS Actual - - - 8/27/2010 2/3/2011 1/12/2011 Planned - - - 7/30/2010 RDS, 12/27/2010 Completed 711 ENREP/W/256 Construction of PIC Building of ENReP Vavuniya Vavuniya DC 5.49 0.05 Post LKR 4.93 Vairavapuliyank 4.63 Actual - - - 10/21/2010 ulam 1/20/2011 11/30/2010 Improvement of wards No-03 &04 in Planned - - - 7/30/2010 Hospital 12/27/2010 712 ENREP/W/632 Vavuniya Vavuniya DC 4.86 0.04 Post LKR 4.86 2.37 General Hospital Actual - - - 5/2/2011 welfare Society 9/1/2011 On Progress Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Planned 8/16/2010 9/20/2010 - 9/27/2010 VV 12/26/2010 Reconstruction of RDI's , IE's © of 713 ENReP/W/531 Vavuniya Vavuniya NCB 42.17 0.38 Post LKR 36.19 Ramanathan & 5.79 Dept of Irrigation, Vavuniya Actual 6/29/2011 7/29/2011 - 8/15/2011 4/11/2012 On Progress Company Planned - - - 7/15/2011 Hospital 12/27/2010 Repairs & Iprovements of Ward , 714 ENReP/W/611 Vavuniya Vavuniya DC 4.57 0.04 Post LKR 4.57 Welfare Society, - Quarters General Hospital, Vavuniay Actual - - - 8/3/2011 12/6/2011 On Progress Vavuniay Renovation & repairs to Technical ollege Planned - - - 6/22/2011 RDS, 12/27/2010 715 ENReP/W/612 Vavuniya Vavuniya DC 5.50 0.05 Post LKR 5.50 1.22 Building Vavuniya Actual - - - 7/11/2011 Maravankulam 12/1/2011 On Progress Repairs & Iprovements of Ward No-05, Planned - - - 6/22/2011 Hospital 12/27/2010 716 ENReP/W/613 No-07 &No-14 in General Hospital, Vavuniya Vavuniya DC 4.24 0.04 Post LKR 4.24 Welfare Society, - Vavuniay Actual - - - 7/18/2011 Vavuniay 11/19/2011 On Progress Palmyra & Reconstruction of Palmyra & Coconut Planned - - - 6/22/2011 12/27/2010 Coconut 717 ENReP/W/614 Development Co-op Society Building at Vavuniya Vavuniya DC 4.51 0.04 Post LKR 4.51 0.77 Actual - - - 7/11/2011 Development 11/12/2011 On Progress Puliyankulam, Vavuniya Co-op Society Reconstrution fo Co-op Retail shop Planned - - - 6/22/2011 Vavuniya 12/27/2010 718 ENReP/W/615 Vavuniya Vavuniya DC 3.48 0.03 Post LKR 3.48 - building at Kanakarayankualm Actual - - - 6/23/2011 North MPCS 10/24/2011 On Progress Planned - - - 11/10/2011 RDS 12/28/2010 719 ENReP/W/616 Reconstruction of DPD office Stage II Vavuniya Vavuniya DC 4.98 0.04 Post LKR 4.98 - Actual - - - 26/12/2011 Ukkulankualam 4/27/2012 On Progress Planned - - - 12/5/2011 Procurement Preparation and Improvements of store 6/12/2012 720 ENReP/W/617 Vavuniya VCK DC 5.50 0.05 Post LKR 5.50 - Process & Under at Cheddikulam IE's office Actual - - - Process Planned - - - 12/25/2011 Procurement Preparation and Improvements of store 721 ENReP/W/618 Vavuniya Vavuniya DC 5.50 0.05 Post LKR 5.50 - Process & Under at Vavuniya IE's office Actual - - - 6/22/2012 Process Reconstructionof Co-Op Retail Shops at Planned 6/30/2010 8/4/2010 - 8/25/2010 1/22/2011 722 ENReP/W/536 Vavuniya Vavuniya South NCB 9.87 0.09 Post LKR 9.68 Omega Steels 5.95 Vavuniya Package-1 Actual 10/30/2010 12/3/2010 - 12/28/2010 9/8/2011 On Progress Construction of Paddy store at Planned - - - 9/27/2010 Vavuniya 12/26/2010 723 ENREP/W/399 Vavuniya Vavuniya South DC 2.73 0.02 Post LKR 2.73 1.55 Kachchakody Actual - - - 10/4/2010 South MPCS 2/8/2011 On Progress Reconstruction of fertilizer store at Planned - - - 9/27/2010 FO, Acre 400 12/26/2010 724 ENREP/W/408 Vavuniya Vavuniya South DC 2.85 0.03 Post LKR 2.57 0.65 Ulukulam Actual - - - 10/1/2010 L.B 2/18/2011 On Progress Construction of Fertilizer store at Planned - - - 8/25/2010 FO, 1/22/2011 Completed 725 ENREP/W/245 Vavuniya Cheddikulam DC 3.34 0.03 Post LKR 3 2.57 Periyathampanai Actual - - - 8/10/2010 Ramaiyankal 1/13/2011 6/20/2011 Renovation of V/Periyathampanai Planned - - - 9/27/2010 11/11/2010 Completed 726 ENREP/W/393 Vavuniya Cheddikulam DC 1.53 0.01 Post LKR 1.53 SDS 1.33 GTMS Actual - - - 9/23/2010 12/29/2010 12/13/2010 Construction of rice Mill and Stores at Planned 6/30/2010 8/4/2010 - 8/25/2010 Asire 1/22/2011 727 ENREP/W/395 Vavuniya Cheddikulam NCB 11.10 0.10 Post LKR 10.12 6.13 Pavatkulam Contractor Actual 9/27/2010 11/4/2010 - 12/10/2010 5/23/2011 On Progress Construction of Paddy store at Planned - - - 9/27/2010 MPCS 12/26/2010 Completed 728 ENREP/W/398 Vavuniya Cheddikulam DC 4.86 0.04 Post LKR 4.86 4.58 Pavatkulam unit 6 Cheddykulam Actual - - - 9/28/2010 2/2/2011 4/29/2011 Improvement of Project Management Planned - - - 2/20/2012 6/21/2012 MPCS 729 ENREP/W/399 Unit, Emergency Northern Recovery Vavuniya Cheddikulam DC 0.70 0.01 Post LKR 0.68 On Progress Actual - - - 2/27/2012 Vavuniya Project, Vavuniya Reconstruction of Co - Operative Planned 4/20/2012 30/12/2012 Retailshop at MPCS 730 ENREP/W/403 Vavuniya Vavuniya South DC 1.87 0.02 Post LKR On Progress Arumukathanputhukkulam, stage 2, Actual 5/25/2012 Vavuniya 10/1/2012 Vavuniya Reconstruction of Co - Operative Planned 4/20/2012 Vavuniya Agreement Not 731 ENREP/W/404 Retailshop at Marilluppai, stage 2, Vavuniya Vavuniya South DC Post LKR North MPCS signed Vavuniya Submit DBD with IFB for Bank's Contract No./ Amount/ Name of Publish contract award notice in Submit Signed Contract copyto UNDB & National News Paper Expenditure incured to date Method of Procurement Prior/ Post Review by Bank * Bid Close/ Bid opening Submit BER for Bank's N/O Estimated Cost Package No. D.S.Division Signing of Contract Publish IFB in National Completion Description newspapers and UNDB (Million) Serial No District Status/ Remarks** the Contractor Currency Amount Date LKR USD Stage Bank N/O Reconstruction of Co - Operative Vavuniya Agreement Not 731 ENREP/W/404 Retailshop at Marilluppai, stage 2, Vavuniya Vavuniya South DC Post LKR Actual North MPCS signed Vavuniya Reconstruction of Co - Operative Planned 4/20/2012 MPCS Agreement Not 732 ENREP/W/405 Retailshop at Palamoddai, stage 2, Vavuniya Vavuniya South DC Post LKR Actual Vavuniya signed Vavuniya Retail of office building at V/Vavuniya Planned Jammy Sacntion is on 733 ENREP/W/406 Vavuniya Vavuniya NS Post LKR Gamini Maha Vidyalayam Actual Enterprises Progress Retail of Assembly Hall at V/Vavuniya Planned Jammy Sacntion is on 734 ENREP/W/407 Vavuniya Vavuniya NS Post LKR Gamini Maha Vidyalayam Actual Enterprises Progress Air condition facility to conference hall Planned 735 ENREP/W/408 of Divineguma Training Center at Vavuniya Vavuniya Post LKR Kanagarajankulam Actual Planned Improv. Of DPD Office stage II A & Re- 736 ENREP/W/409 Vavuniya Vavuniya Post LKR awakening PPMU- Vavuniya Actual Planned 737 ENREP/W/411 Improv.to DPD Office Stage II Vavuniya Vavuniya 4.50 0.04 Post LKR Actual Planned 738 ENREP/W/412 Renov.of Mamadhu Hospital VS Vavuniya Vavuniya South 2.30 0.02 Post LKR Actual Planned Construction of V/Arugampulaliya 739 ENREP/W/413 Vavuniya Vavuniya South 5.03 0.05 Post LKR School Vavuniya South DS Division Actual Planned Construction of rural water supply 740 ENREP/W/414 Vavuniya Mamaduwa 0.65 0.01 Post LKR scheme stage 1 at Mamaduwa Actual Public Drinking water wells close to 741 ENREP/W/415 Vavuniya Mamaduwa 1.65 0.01 Sivisuma Vidyalaya in Pradesiya sabha Mamaduwa Kalikulam Co- Operative 742 ENREP/W/416 Vavuniya Mamaduwa 1.65 0.01 shop's common well 743 ENREP/W/417 Public well in Mamaduwa Vavuniya Mamaduwa 1.00 0.01 Repairs for the Computer Trainning 744 ENREP/W/417 Vavuniya Vavuniya South 2.00 0.02 centre at Pradesiya sabha office Serial No Package No. Description District D.S.Division Method of Procurement LKR (Million) USD Estimated Cost Prior/ Post Review by Bank * Stage Submit DBD with IFB for Bank's N/O Publish IFB in National newspapers and UNDB Bid Close/ Bid opening Submit BER for Bank's N/O Date Currency Signing of Contract Amount Contract No./ Amount/ Name of the Contractor Submit Signed Contract copyto Bank Publish contract award notice in UNDB & National News Paper Completion Expenditure incured to date Status/ Remarks** PROCUREMENT PLAN FOR GOODS Country/Borrower: Government of Sri Lanka Project Name: Emergency Northern Recovery Project Credit/Grant #: 4676 Implementing Agency: ENREP PMU GPN # and Date Published : Original Plan Approved Date(at Appraisal/Negotiations): November 30, 2009 Update as of: January 4, 2010 Update as of: May 7, 2010 Update as of: September 24, 2010 Update as of: May 31, 2011 Update as of: September 30, 2011 Update as of: December 31, 2011 Update as of: January 31, 2012 Update as of: April 30, 2012 * For post review, fill in columns 1 to 8, 10, 12 & 13, 15, 17 to 20, and 22 to 25 ** Indicate extensions/modifications etc. Prior/ Post Review Status/Remarks** Estimate UNDB & National submission of bids Submit DBD with Publish contract Submit BER for contract copy to incurred to date newspapers and d Cost award notice in IFB for Bank's Publish IFB in (Number) Completion of Submit signed Quantity Procurement Expenditure (Million) Deadline for Package No. Contractor/ newspapers Bank's N/O Description nationality Method of Stage Signing of contract Serial No. by Bank* National Name of contract UNDB Bank N/O LKR USD Date Currency Amount 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 D1 Vehicles, Equipment & Office Facilities 1 NS 3 27.00 0.24 Prior Planned - - 31/12/2009 1/03/2010 1/03/2010 ENReP/G/1 Purchases of 3 nos. of Double cabs LKR 24.99 Associated Motorways PLC 29.98 Completed Actual 15/02/2010 - 27/04/2010 2 NS 4 30.00 0.27 Post Planned - - 31/01/2010 1/04/2010 1/04/2010 ENReP/G/2 Purchases of 4 nos. of Double cabs LKR 19.98 M/s Associted Motorways PLC 17.98 Completed Actual 29/07/2010 - 12/10/2010 3 NCB 9 70.00 0.63 Post Planned - - 30/01/2010 31/03/2010 31/03/2010 ENReP/G/3 Purchases of 9 nos. of Double cabs LKR 44.25 United Motors Lanka PLC 41.01 Completed Actual 9/07/2010 12/01/2010 2/5/2011 4 Purchases of 6Nos. Of Computers & 2 No. of NS 8 0.90 0.01 Post Planned - - 20/01/2010 20/01/2010 ENReP/G/4 LKR 0.64 PC House (Pvt)Ltd 1.04 Completed Laptop for PMU 28/01/2010 - 12/2/2010 Actual 5 NCB 25 5.00 0.05 Post Planned - - 31/01/2010 2/03/2010 - - 2/03/2010 ENReP/G/5 Purchases of 25 Nos. Of Computers LKR 3.80 Regional Head, Regional office, 3.80 Completed Actual 28/01/2010 6/11/2010 MicroPC Systems 6/7/2010 6 NCB 7 1.10 0.01 Post Planned - - 31/01/2010 2/03/2010 - - 2/03/2010 ENReP/G/6 Purchases of 7 No. of Laptop LKR 0.91 PC House (Pvt)Ltd 1.01 Completed Actual 21/04/2010 6/11/2010 15/09/2010 7 NCB 6 0.10 0.00 Post Planned - - 31/01/2010 2/03/2010 - - 2/03/2010 ENReP/G/7 Purchases of 6 Nos. Scanner for PMU & PIC LKR 0.05 Strangers Group (Pvt)Ltd 0.05 Completed Actual 21/04/2010 14/06/2010 8/7/2010 8 Purchases of 24 Nos. Of Computers and 1 no NCB 25 2.50 0.02 Post Planned - - 6/31/2010 31/08/2010 31/08/2010 ENReP/G/8 LKR 3.06 Metropolitan office (Pvt) ltd 3.07 Completed Laptop 9/07/2010 6/10/2010 29/10/10 Actual 9 NS 2 0.30 0.00 Post Planned - - 20/01/2010 20/01/2010 ENReP/G/9 Purchases of 2 nos. of Photo copier LKR 0.23 Multi Vision Printers 0.23 Completed Actual 1/02/2010 - 12/2/2010 10 NCB 6 1.00 0.01 Post Planned - - 6/31/2010 1/09/2010 - - 1/09/2010 ENReP/G/10 Purchases of 6 nos. of Photo copier LKR 0.51 PC House (Pvt) Ltd 0.57 Completed Actual 21/04/2010 6/11/2010 29/10/2010 11 NCB 6 1.00 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/11 Purchases of 6 nos. of Photo copier LKR 1.39 Metropolitan office (Pvt) ltd 1.56 Completed 7/09/2010 6/10/2010 29/10/2010 Actual 12 5 Post 4/20/20010 20/05/2010 - - 20/05/2010 NS 0.35 0.00 Planned - - ENReP/G/12 Purchases of 5 Nos. of Fax LKR 0.09 PC House (Pvt) Ltd 0.10 Completed 21/04/2010 8/02/2010 Actual 15/09/2010 13 5 Post 7/01/2010 7/01/2010 NS 0.09 0.00 Planned - - ENReP/G/13 5 Nos. of Mobile Phone LKR 0.08 Global Net 0.08 Completed 2/01/2010 - 12/2/2010 Actual 14 15 Post 15/05/2010 20/05/2010 20/05/2010 NS 0.35 0.00 Planned - - ENReP/G/14 15 Nos. of Mobile Phone LKR 0.20 Global Net 0.20 Completed 20/07/2010 - 24/07/2010 Actual Prior/ Post Review Status/Remarks** Estimate UNDB & National submission of bids Submit DBD with Publish contract Submit BER for contract copy to incurred to date newspapers and d Cost award notice in IFB for Bank's Publish IFB in (Number) Completion of Submit signed Quantity Procurement Expenditure (Million) Deadline for Package No. Contractor/ newspapers Bank's N/O Description nationality Method of Stage Signing of contract Serial No. by Bank* National Name of contract UNDB Bank N/O LKR USD Date Currency Amount 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 15 6 Post 31/01/2010 2/03/2010 2/03/2010 NCB 1.00 0.01 Planned - - ENReP/G/15 Purchases of 6 Nos. of Multi media LKR 0.46 Dynamic AV Technologies 0.55 Completed 9/07/2010 11/01/2010 10/11/2010 Actual 16 NS 2 0.06 0.00 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/16 Purchases of 2 Nos. of Digital Camara LKR 0.09 N.S.Rathnam&Bros 0.09 Completed 1/02/2010 - 12/2/2010 Actual 17 NS 10 0.30 0.00 Post Planned - - 2/20/20010 20/03/2010 20/03/2010 ENReP/G/17 Purchases of 10 Nos. of Digital Camara LKR 0.22 N.S.Rathnam&Bros 0.22 Completed Actual 3/05/2010 - 15/04/2010 18 NS 0.30 0.00 Post Planned - - 6/01/2010 20/01/2010 20/01/2010 ENReP/G/18 Set of Furniture for PMU(Package 1) LKR 0.76 Superking Furniture 0.76 Completed Actual 18/01/2010 - 6/4/2010 19 NS 0.90 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/19 Set of Furniture for PMU(Package 2) LKR 0.64 Superking Furniture 0.64 Completed 9/09/2010 - 27/09/2010 Actual 20 NS 0.30 0.00 Post Planned - - 10.06.2011 18/06/2011 18/07/2011 ENReP/G/20 Conference Table with Chair for PMU LKR 0.55 DR Industries 0.55 Completed 11/07/2011 19/7/2011 - Actual 21 Set of Furniture for RaP PPMU Mullaitivu & NS 0.50 0.00 Post Planned - - 31/12/2009 20/01/2010 20/01/2010 ENReP/G/21 LKR 0.13 Superking Furniture 0.13 Completed Kilinochchi office 18/01/2010 - - Actual 22 NS 0.80 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/22 Set of Furniture for PIC office in Vavuniya LKR 0.63 Richco Associates 0.70 Completed Actual 21/04/2010 8/02/2010 30.08.2010 23 NS 0.80 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/23 Set of Furniture for PIC office in Mannar LKR 0.63 Richco Associates 0.70 Completed Actual 21/04/2010 8/02/2010 6/10/2010 24 NS 0.80 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/24 Set of Furniture for PIC office in Mullaitivu LKR 0.66 Richco Associates 0.74 Completed 21/04/2010 8/02/2010 20/09/2010 Actual 25 NS 0.80 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/25 Set of Furniture for PIC office in Kilinochchi LKR 0.66 Richco Associates 0.74 Completed Actual 21/04/2010 8/02/2010 7/10/2010 26 NS 0.80 0.01 Post Planned - - 31/01/2010 2/03/2010 2/03/2010 ENReP/G/26 Set of Furniture for PIC office in Jaffna LKR 0.69 Richco Associates 0.77 Completed 21/04/2010 8/02/2010 7/10/2010 Actual 27 NS 40 5.00 0.05 Post Planned - - 31/12/2009 1/03/2010 1/03/2010 ENReP/G/27 Purchases of Motor Cycle (40 Nos) LKR 4.43 David Pieris Motor Company 4.96 Completed Actual 15/07/2010 - Limited 23/08/2010 28 NS 75 1.00 0.01 Post Planned - - 31/12/2009 1/03/2010 1/03/2010 ENReP/G/28 Purchases of Cycle(75 Nos) LKR 0.99 Ayisha Multi Complex 0.99 Completed Actual 28/01/2010 - 11.02.2010 29 NS 0.08 0.00 Post Planned - - 1/05/2010 31/05/2010 31/05/2010 ENReP/G/29 Executive Iron safe LKR 0.06 Alpha Center 0.06 Completed Actual 14/07/2010 - 29/07/2010 30 2 Nos Generator for PIC office in Kilinochchi & NS 2 0.21 0.00 Post Planned - - 25/03/2010 25/04/2010 25/04/2010 ENReP/G/30 LKR - Completed Mullaitivu office - - Actual 31 NS 1 0.16 0.00 Post Planned - - 2/04/2010 2/05/2010 Swedish trading Audio Visual 2/05/2010 ENReP/G/31 Purchase of 01 Nos Multimedia Projector PMU LKR 0.12 0.12 Completed 24/06/2010 - (Pvt).Ltd 13/07/2010 Actual 32 NS 1 5.00 0.05 Post Planned - - 30/08/2010 30/09/2010 30/09/2010 ENReP/G/32 Purchase of a Car LKR 3.46 United Motors Lanka 4.15 Completed Actual 19/10/2010 - (Pvt).Ltd 10/11/2011 33 NS 2 0.10 0.00 Post Planned - - 30/07/2010 30/09/2010 30/09/2010 ENReP/G/33 Purchase of 2 Nos Colour Printer LKR 0.13 Metropolitan office (Pvt) ltd 0.13 Completed Actual 13/10/2010 29/10/2010 22/11/2010 Prior/ Post Review Status/Remarks** Estimate UNDB & National submission of bids Submit DBD with Publish contract Submit BER for contract copy to incurred to date newspapers and d Cost award notice in IFB for Bank's Publish IFB in (Number) Completion of Submit signed Quantity Procurement Expenditure (Million) Deadline for Package No. Contractor/ newspapers Bank's N/O Description nationality Method of Stage Signing of contract Serial No. by Bank* National Name of contract UNDB Bank N/O LKR USD Date Currency Amount 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 34 NS 10 0.80 0.01 Post Planned - - 7/07/2011 14/07/2011 28/07/2011 ENReP/G/34 Purchase of 10 nos Testing hammer and anvil LKR 0.46 Spectro Scientific Enterprises 0.46 Completed Actual 26/5/2011 27/5/2011 17/6/2011 35 NS 10 0.90 0.01 Post Planned - - 15/07/2011 22/07/2011 30/7/2011 ENReP/G/35 Purchase of 10 Nos GPS LKR 0.83 Techinnovators (Pvt) Ltd 0.83 Completed Actual 19/8/2011 26/8/2011 9/05/2011 36 15 Post 1/08/2011 8/08/2011 Metropolitan Office ( Pvt ) Ltd & 7/10/2011 NS 1.80 0.02 Planned - - ENReP/G/36 Purchase of 15 Nos Computers with Printers LKR 1.21 Jahn Keels Office Automation (Pvt) 0.39 Completed Actual 8/02/2011 12/08/2011 Ltd 37 NS 1 0.05 0.00 Post Planned 9/09/2011 17/09/2011 18/10/2011 ENReP/G/37 Purchase of 01 No Mobile Phone LKR 0.05 T-Mobiles Tech 0.05 Completed Actual 20/9/2011 28/09/2011 30/9/2011 38 Quality Contral Equipment Set for Dept. of NS 5.00 0.05 Post Planned 10/10/2011 18/10/2011 30/12/2011 ENReP/G/38 LKR 6.02 A.T.A International (Pvt) Ltd Completed Buildings. 9/08/2011 6/09/2011 Actual 39 NS 5 1.00 0.01 Post Planned 9/09/2011 17/09/2011 30/10/2011 ENReP/G/37 Purchase 5 Nos Photocopiers LKR 1.23 Metro Politan Office(Pvt) Ltd 1.23 Completed Actual 21/7/2011 27/7/2011 9/09/2011 17/09/2011 40 ENReP/G/38 Purchase of 15 Numbers of Laptops NS 15 1.5 0.0135 Post Planned LKR 0.99 Metro Politan Office(Pvt) Ltd 30/11/2011 0.99 Completed 14/9/2011 20/9/2011 9/09/2011 12/09/2011 41 ENReP/G/39 Purchase of a Dot Matrix Printer NS 1 0.1 0.0009 Post Planned LKR 0.085 PC Technologies 26/9/2011 0.09 Completed 9/09/2011 12/09/2011 12/10/2011 30/10/2011 Survey & Laboratory 42 ENReP/G/39 Purchase of 6 Nos of Total Station Equipments NS 6 2.1 0.0189 Post Planned LKR 3.48 30/11/2011 3.48 Completed 7/10/2011 30/10/2012 Equipments(Pvt) Ltd Purchase and supply of 2Nos of 42 inch LCD 18/01/2012 25/01/2012 43 ENReP/G/40 NS 2 2 0.018 Post Planned LKR 2.2 Abans (PVT) Ltd 3/2/2012 2.2 Completed Television with Home theatre 18/01/2012 26/01/2012 Purchase and Supply of 01 No of Network 18/04/2012 23/04/2012 43 ENReP/G/40 Switch 08 Port, 01 No of UPS and 02 Nos of NS 4 0.7 0.0063 Post Planned LKR 0.05 Kuinston 4/5/2012 0.05 Completed External Hard Drive 21/04/2012 3/05/2012 44 ENReP/G/41 Purchase 5 Nos of Mobile Phones to DPDs NS 5 1.15 0.0104 Post Planned Procurement Plan for Consulting Services Country/Borrower: Government of Sri Lanka Project Name: Emergency Northern Recovery Project Credit/Grant #: 4676 W/285 Implementing Agency: ENREP PMU GPN # and Date Published : Original Plan Approved Date(at Appraisal/Negotiations): November 30, 2009 Update as of: January 4, 2010 Update as of: May 7, 2010 Update as of: September 24, 2010 Update as of: May 31, 2011 Update as of: September 30, 2011 Update as of: January 31, 2012 Update as of: April 30, 2012 * For post review, fill in columns 1 to 8, 10, 12 & 13, 15, 17 to 20, and 22 to 25 ** Indicate extensions/modifications etc. Prior/post review Name/nationality Publish Contract Award of the consultant shortlisted firms Lumpsum/Time Submit TER for Status/Remarks incurred to date Submit shortlist contract copy to Submit CER & for Bank's N/O and draft RFP Publish Notice Submit signed in UNDB & National initialed draft submission of Issue RFP to Expenditure Deadline for contract for Bank's N/O Completion Description Opening of negotiated Method of proposals proposals by Bank* Serial no. Contract Selection financial RFP No. Estimated Cost newspapers for EOI Based Stage Bank Signing of Contract (Million) ** Currenc LKR USD Date Value y 4.00 0.04 Post Appraisal 2/14/2010 3/7/2010 3/21/2010 SLBDC 9/21/2010 1 ENREP/W/191 Base Line NS LS Actual 2/10/2010 2/15/2010 5/3/2010 LKR 3.22 10/30/2010 1.34 12.00 0.11 Post Appraisal 2/7/2010 2/21/2010 3/14/2010 3/21/2010 Enerest & Yong 12/31/2012 2 ENREP/W/192 Financial Audit NS TB LKR 7.86 3.07 Actual 1/29/2010 2/24/2010 3/15/2010 4/5/2010 EIA Study to Kalmadu 1.50 0.01 Post Appraisal 3/21/2010 ECL 4/21/2010 3 ENREP/W/194 SSS LS LKR 1.13 0.66 tank Actual 4/7/2010 5/17/2010 Dam Safty study to 0.50 0.00 Post Appraisal 3/21/2010 Damsafty Pannel 4/21/2010 4 ENREP/W/195 SSS LS LKR 0.32 0.32 Kalmadu Actual 3/26/2010 50.00 0.45 Post Appraisal 4/10/2010 4/24/2010 5/15/2010 5/29/2010 6/15/2010 RDC 12/31/2012 5 ENREP/W/196 Technical Audit QCBS TB LKR 38.25 15.68 Actual 5/3/2010 8/2/2010 8/25/2010 9/14/2010 10/25/2010 Advanced GIS Training 3.20 0.03 Post Appraisal 20/01/2012 PGIS, University 6/2/2012 6 ENREP/W/197 with six packages of SSS LS LKR of Peredeniya Actual ArcGIS software 1.00 0.01 Post Appraisal All uneiversity Actual student 7 ENREP/W/198 Internal Task Team SSS LS LKR development association vavuniya 2.46 0.02 Post Appraisal Licensed Surveying land for ASB Actual Surveyor - K. 7 ENREP/W/198 SSS LS LKR housing scheme Shanmugalinga m PROCUREMENT PLAN FOR NON-CONSULTANT SERVICES Country/Borrower: Government of Sri Lanka Project Name: Emergency Northern Recovery Project Credit/Grant #: 4676 Implementing Agency: ENREP PMU GPN # and Date Published : Original Plan Approved Date(at Appraisal/Negotiations): November 30, 2009 Update as of: January 4, 2010 Update as of: May 7, 2010 Update as of: September 24, 2010 Update as of: May 31, 2011 Update as of: September 30, 2011 Update as of: December 31, 2011 Update as of: January 31, 2012 Update as of: April 30, 2012 * For post review, fill in columns 1 to 8, 10, 12 & 13, 15, 17 to 20, and 22 to 25 ** Indicate extensions/modifications etc. Signing of Publish contract award notice Expenditure incurred to date Submit BER for Bank's N/O Submit signed contract copy contract Prior/post review by Bank* Deadline for submission of Submit DBD with IFB for Method of Procurement Publish IFB in National newspapers and UNDB Completion of contract Name & Nationality of in UNDB & National Estimat ed Cost Status/Remarks (Millio Package No. n) newspapers Bank's N/O Description contractor Serial No. to Bank Stage bids LKR USD Date Currenc Value y 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1 ENREP/W/19 Providing security LCS 1.6 0.01 Planned 3/15/2010 LKR 46789.7 Asha Security 12/31/2012 0.8 Actual 3/29/2010 12/31/2012 S.No Sector District TEC in Mn Kilinochchi Mannar 1 Irrigation Mullaitivu Vavuniya Sub Total Jaffna Kilinochchi Rural 2 Mannar Roads Mullaitivu Vavuniya Sub Total Jaffna Kilinochc hi Drinking 3 Water Mannar Schemes Mullaitivu Vavuniya Sub Total Jaffna Kilinochchi Public Buildings 4 Mannar & Facilities Mullaitivu Vavuniya Sub Total Total 2/22/2012 120 6/21/2012 Sector Total S. No District Irrigation Road Drinking Water Public Buildings 1 Jaffna - 463.33 373.57 766.59 1603.49 277.74 164.49 - 801.07 1243.3 2 Kilinochchi 331.77 110.63 668.11 267.71 1378.22 3 Mannar 362.89 361.19 685 700.98 2110.06 4 Mullaitivu 319.7 130.95 175.62 331.96 958.23 5 Vavuniya Sub Total 1292.1 1230.59 1902.3 2868.31 7293.3 11/18/2011 14 210 6/29/2012 12/30/2011 14 180 7/11/2012 12/22/2011 120 4/20/2012 4/19/2011 120 8/17/2011 12/5/2011 180 6/2/2012 12/25/2011 180 6/22/2012 6/22/2012 90 9/20/2012 90 3/30/1900 6/23/2012 90 9/21/2012 7/5/2012 14 7/19/2012 180 1/15/2013 8/14/2012 104 11/26/2012 1/0/1900 1/0/1900 8/9/2012 104 11/21/2012