Page 1 Project Procurement Plan Namibian Coast Conservation and Management Project (Grant No. TF 055983) Simplified Procurement Plan I. General 1. Project information: Namibia, Namibian Coast Conservation and Management Project, P070885. Project Implementing Agencies: Ministry of Environment and Tourism (MET) and Ministry of Regional and Local Government, Housing and Rural Development (MRLGHRD) 2. Bank’s approval Date of the procurement Plan: June 2005 3. Date of General Procurement Notice: June, 2005 4. Period covered by this procurement plan: February 2009 to September 2010 II. Goods and non-consulting services. 1. Prior Review Threshold : Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments 1. ICB and LIB (Goods) > = US$ 100,000.00 All contract are Subject to Prior Review 2. NCB (Goods) < US$ 100,000.00 First contract is Subject to Prior Review 3. Shopping < US$ 50,000.00 No contract is subject to prior review 4. Direct contracting All values All contract are Subject to Prior Review 5. IAPSO All values All contract are Subject to Prior Review 2. Pre-qualification . There will be no prequalification of bidders. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: The procurement procedures and Standard Bidding Documents (SBD) to be used for each procurement method, as well as model contracts for works and goods procured, are presented in the 47817 Page 2 Project Implementation Manual which has been approved prior to Grant Agreement signing. Page 3 5 . A n y O t h e r S p e c i a l P r o c u r e m e n t A r r a n g e m e n t s : N O N E 6 . P r o c u r e m e n t P a c k a g e s w i t h M e t h o d s a n d T i m e S c h e d u l e f o r G o o d s a n d N o n – C o n s u l t i n g S e r v i c e s ( G N C S ) 1 2 3 4 5 6 7 8 9 R e f . N o . C o n t r a c t ( D e s c r i p t i o n ) E s t i m a t e d C o s t P r o c u r e m e n t M e t h o d P r e q u a l i f i c a t i o n ( y e s / n o ) D o m e s t i c P r e f e r e n c e ( y e s / n o ) R e v i e w b y B a n k ( P r i o r / P o s t ) E x p e c t e d B i d - O p e n i n g D a t e A c t i v i t y n o 1 D e s i g n a n d l a y o u t o f t h e I C Z M B i l l 2 , 5 0 0 S h o p p i n g N o Y e s P o s t S e p t 2 0 1 0 I . 1 . 5 . a 2 . E d i t i n g o f t h e I C Z M B i l l 2 , 5 0 0 S h o p p i n g N o Y e s P o s t S e p t 2 0 1 0 I . 1 . 5 . a 3 P r i n t i n g o f t h e I C Z M B i l l 5 , 0 0 0 S h o p p i n g N o Y e s P o s t S e p t 2 0 1 0 I . 1 . 5 . a 4 P r i n t i n g o f t h e G r e e n P a p e r D o c u m e n t 2 5 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 0 9 I . 3 . 1 5 D e s i g n a n d L a y o u t o f t h e G r e e n P a p e r 1 5 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 0 9 I . 3 . 1 6 P r i n t i n g o f t h e N A C O W P d o c u m e n t 1 0 , 0 0 0 S h o p p i n g N o Y e s P o s t S e p t 2 0 1 0 I . 3 . 5 7 D e s i g n a n d L a y o u t o f t h e N A C O W P d o c u m e n t 3 0 , 0 0 0 S h o p p i n g N o Y e s P o s t S e p t 2 0 1 0 I . 3 . 5 8 P u r c h a s e o f C o m p u t e r f o r M E T c o a s t a l o f f i c e s 1 5 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 0 9 I I . 2 . 2 9 P r i n t i n g o f t h e C o a s t a l B i o d i v e r s i t y S t a t u s R e p o r t 1 2 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 1 0 I I . 2 . 3 1 0 P r i n t i n g o f C o a s t a l A w a r e n e s s B o o k l e t s 7 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 0 9 I I . 3 . 2 . d 1 1 D e s i g n a n d L a y o u t o f t h e C o a s t a l A w a r e n e s s B o o k l e t s 3 , 0 0 0 S h o p p i n g N o Y e s P o s t M a r c h 2 0 0 9 I I . 3 . 2 . d 1 2 P r i n t i n g o f t h e N a t i o n a l C o a s t a l P r o f i l e s 2 0 , 0 0 0 S h o p p i n g N o Y e s P o s t N o v 2 0 0 9 I I . 3 . 3 1 3 P r i n t i n g o f t h e P A ’ s a n d r e l a t e d r e g u l a t i o n s r e p o r t 3 0 , 0 0 0 S h o p p i n g N o Y e s P o s t A u g u s t 2 0 0 9 I I I . 1 . 2 1 4 Page 4 III. Selection of Consultants 1. Prior Review Threshold : Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Gu idelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments QCBS >=US$ 100,000.00 All contract are Subject to Prior Review Consultant Qualification Selection (CQS) < US$ 100,000.00 No contract is subject to prior review 1. Firm’s Least Cost Selection (LC) < US$ 100,000.00 No contract is subject to prior review Individual Consultant (IC) >= US$ 50,000.00 All contract are Subject to Prior Review Individual Consultant (IC) < US$ 50,000.00 No contract is subject to prior review 2. Individuals Single Source Methods All values All contract are Subject to Prior Review 2. Short list comprising entirely of national consultants : Short list of consultants for services, estimated to cost less than US$ 100,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. No. Description of Assignment Estimated Cost Selection Method Review by Bank (Prior / Post) Expected Proposals Submission Date Activit y no. 15 Development of an income/revenue strategy for the coastal Protected areas 30,000 IC Post 30 July 2009 I.1.4 16 Development of the ICZM Bill 72,000 CQS Post 31 January 2010 I.1.5 17 Organise the High Level workshop 20,000 IC Post 31 March 2009 I.2.2 18 Development of the institutional arrangements report form the implementation of the coastal policy 30,000. CQS Post 28 February 2010 I.4.1 19 Assess the implementation of the training strategy and recommendation provide further training 20,000 CQS Post 31 July 2010 II.1.9 20 Organisation of a Study Tour 10,000 IC Post 31 June 2009 II.1.10 Page 5 21 Develop a study to define the future ICZM roles and functions 15,000 IC Post 31 June 2009 II.1.11 22 Identify a cost effective collection of coastal and Marine Biodiversity data. 27,000 CQS Post 31June 2009 II.2.1 23 Implement the agreed cost effective collection and sharing mechanism of coastal and Marine Biodiversity data. 40,000 CQS Post 31 Dec 2009 II.2.2 24 Compile a coastal and Marine Biodiversity data status report and develop M&E tool for assessing of status 32,000 CQS Post 31 June 2009 II.2.3 25 Maintenance of the NACOMA webpage 10,000 IC Post 13 July 2008 II.3.2.c 26 Identify and develop Coastodians awareness campaign activities and coordinates its implementation 10,000 IC Post 29 April 2009 II.3.2.e 27 Develop a user friendly DVD compiling of all NACOMA products and other relevant coastal and marine data. 20,000 CQS Post 29 February 2010 II.3.4 28 Support Coastal local authority to develop an environmental policy and management plans 30,000 CQS Post 30 June 2009 III.1.1 2 29 Support the development of regulation of policies on ICZM implementation. 40,000 CQS Post 30 Sept 2009 III.2.4 Page 6 IV. Training and Workshops Activities with Time Schedule 1. In this section the agreed Training and Workshops Activities are listed with time schedule No. Expected outcome / Activity Description Estimated Cost Start Date End Date Activity no. 30 Workshops to support the Government to formally agree on the institutional mechanism and arrange for the implementation of the coastal policy 25,000 01 June 2009 31 Nov. 2009 I.2.2 31 Workshop to identify and agree on an cost- effective mechanism to operationalise, integrated and improve accessibility and usage of data for coastal and marine biodiversity information 5,000 01 Sept 2009 31 Dec 2009 II.2.1