Rajasthan Agriculture competitiveness Project Government of Rajasthan Procurement Plan 18 months (From May 2016 to December 2017 ) I. General 1. Project information Country : India Borrower : Government of India Project Name : Rajasthan Agriculture competitiveness Project Project Identification No (ID) : P124614 -- Applicable Bank Guideline : a) For Goods ,Works and Non-consulting Services :"Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Procurement Guidelines) and revised July 2014; and b) For Consultancy Services :"Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Consultant Guidelines) and revised July 2014; II. Goods, Works and Non-Consulting Services Category Method of Threshold (US$ Equivalent)* Prior review Procurement threshold Goods and International Contracts more than the equivalent of US$ 3 million per Non- competitive contract All ICB,LIB consulting Bidding and services Limited As per para 3.2 of the Guideline .All Contracts more than Framework International the equivalent of US $ 100,000 per contract Contracts . Bidding National Contracts more than the equivalent of US$ 100,000 but less All other competitive than the equivalent of US$ 3 million per contract (with contracts Bidding NCB conditions) equal to or greater than Shopping ** Contracts equivalent of US$ 100,000 or less per contract. US 2 million equivalent; Direct Contracting Proprietary software; educational journals and other procurement justified as per para 3.7 of Guidelines and estimated to cost equivalent of US$ 10,000 or less per contract Force Account As per para 3.9 of Guidelines Community As per guideline para 3.19 of the guideline participation# Framework As per para 3.6 of Guidelines Agreements@ Works International Civil works more or equivalent of US$40,000,000 per all contracts Competitive contract equal to or Bidding greater than National Civil works more than $10000 and Up to $40,000,000 US$10 competitive per contract (with NCB conditions) million Bidding equivalent Shopping** Civil works Up to $100,000 per contract Direct contracting As per para 3.7 of Guidelines. All Civil Works estimated to cost equivalent of US$ 10,000 or less Community As per guideline para 3.19 of the guideline participation# Force Account As per para 3.9 of Guidelines Consultant Consultant Contracts Up to $300,000 or less per contract All contracts s’ Services Qualification equal to or /Least cost greater than selection US$1 Million Category Method of Threshold (US$ Equivalent)* Prior review Procurement threshold Single source As per para 3.9-3.11 of Guidelines and less than or equivalent for selection equal to $10000 firms; and Individual As per Section V of Guidelines equal to or Contracts greater than Quality and cost for All other Contracts US$300,000 Based selection equivalent for /Quality Based individuals Selection /Fixed Based Selection (i) International >800,000 shortlist (ii) Shortlist may Up to 800,000 comprise national consultants only * If a transaction comprises several contracts, lots or slices, the aggregate estimated value of all contracts, lots or slices will determine the applicable threshold amount# *State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. However DGS&D rate contracts are acceptable under any procurement under the Shopping procedure .#Community Procurement would be applicable to activities under learning/training pilots It would be based on World Bank “Guidance Note For Management of Procurement Responsibilities In Community-Driven Development Projects dated December 2009 and as included in the Procurement manual. @Use of DGS&D rate contracts under Framework Agreement (FA) method can be used, provided that: • Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. • Before issuing the purchasing order, the borrower carries-out a price analysis on the specific good that is intended to be purchased. If after this due diligence the borrower concludes (and Bank agrees) that the DGS&D rate contract is not suitable, then the borrower will have to proceed using NCB or shopping depending on the value. • To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. 2. Pre-qualification: Not Applicable 3. Reference to Project Procurement Manual: A Procurement Manual based on World Bank Guidelines “Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, January 2011,Revised July 2014”and “Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” has been prepared. All procurements in the project will be governed by the procedures described in the Manual. In case of any inconsistency between the Procurement Manual and the World Bank Guidelines 2011, Revised July 2014, the provisions of the Guidelines shall prevail. 4. Any Other Special Procurement Arrangements (Goods & Works) : A. Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided they are procured in accordance with agreed processes and procedures for the project and have been cleared as part of procurement plan. B. National Competitive Bidding (NCB) method for procurement of goods, works and non-consulting services as per the above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World Bank Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; (ii) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access ) along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. (iv) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) Extension of bid validity shall not be allowed with reference to contracts subject to prior review without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for prior approved packages, all subsequent requests for extension irrespective of the period. (Such concurrence will be considered by the Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); (vi) Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank. (vii) The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project. (viii) Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures. (ix) Two or three envelop system will not be used (except when using e-Procurement system assessed and agreed by the Bank). (x) As per 1.1(e) of World Bank Procurement Guidelines, the Association’s right to inspect accounts and records of the bidders, suppliers and contractors will be included in the bidding document. III) Selection of Consultants 1. Methods and Value thresholds for Consultancy Services Consulting Methods Value Review Arrangements Services Threshold* Consulting i) Quality and Cost Based All contracts valued above US$ 1 Services Selection (QCBS) Million will be subject to Prior (Firms) ii) Quality Based Selection Review by the World Bank. All (QBS) other contracts will be subject to iii) Selection based on a Fixed post review. Budget (FBS) iv) Selection Based on Least Cost Basis (LCS) v) (Selection based on Contracts Consultant’s Qualification estimated to cost (CQS) equivalent of US$ 300,000 or less per contract. vi) Single Source Selection (SSS)# provided the conditions stipulated in Procurement is in accordance paragraph 3.8 to 3.11 of with para 3.9-3.11 of the Bank Consultant Guidelines are guidelines. met Individual i) Competitive Selection All other contracts subject to post Consultants review provided procurement is in accordance with Section V of the Bank guidelines. ii) Single Source Selection All contracts equal to or above (SSS)# US$ 300,000 shall be subject to prior review. All procurement to be in accordance with Section V of the Bank guidelines. * If a transaction comprises several packages, lots or slices, the aggregate estimated value of contracts will determine the applicable threshold amount. # Irrespective of contract value any hiring of Government or Research Institutes of unique and exceptional nature requires prior no objection of the World Bank on case to case basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Para 2.7 the World Bank Consultant Guidelines. 3. Any Other Special Selection Arrangements (Consulting Services) : (a) Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided procurement is in accordance with agreed processes and procedures for the project. (b) Requests for Expression of Interest (REOI) for assignments expected to cost more than US$ 300,000 shall be advertised in UNDB online in accordance with Para 2.5 of the Consultant Guidelines. PROCUREMENT India : Rajasthan Agricultural Competitiveness Project PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2016-09-20 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-11 Project ID: P124614 GPN Date: Project Name: Rajasthan Agricultural Competitiveness Project Loan / Credit No: IDA / 50850 Executing Agency(ies): Watershed Development & Soil Conservation Department, Project Management Unit - RACP, Horticulture Department - RACP, Ground Water Department - RACP, Agriculture Department - RACP, Water Resources Department - RACP, Rajasthan University of Veterinary and Animal Sciences - RACP, District Project Management Unit - RACP, Animal Husbandry Department - R WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMU-RACP-4309-CW-RFQ / Request for Single Stage - One Fabrication of Emergency Mobile IDA / 50850 Climate Resilient Agriculture Post Limited 55,000.00 48,663.76 Signed 2017-01-16 2017-01-02 2017-03-13 2017-02-07 2017-09-09 Quotations Envelope Vehicles IN-WDSCD-4590-CW-RFQ / Implementation of NRM activities in micro watershed no 10 of Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 86,045.00 86,539.08 Signed 2017-01-01 2017-02-17 2017-01-31 2017-06-13 2017-03-30 macro watershed 10 in Quotations Envelope Kushalgarh cluster district Banswara IN-WDSCD-4593-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 2 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 52,940.00 44,587.87 Signed 2017-01-01 2017-02-01 2017-01-31 2017-03-20 2017-03-30 Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4596-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 4 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 28,358.00 24,182.63 Signed 2017-01-01 2017-02-01 2017-01-31 2017-03-06 2017-03-30 Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4597-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 5 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 15,940.00 12,958.55 Signed 2017-01-01 2017-02-01 2017-01-31 2017-05-11 2017-03-30 Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4598-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 7 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 77,985.00 64,043.38 Signed 2017-01-01 2017-02-01 2017-01-31 2017-03-20 2017-03-30 Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4599-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 10 of IDA / 50850 Climate Resilient Agriculture Post Limited 36,642.00 30,860.79 Signed 2017-01-01 2017-02-01 2017-01-31 2017-03-20 2017-03-30 Quotations Envelope macro watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4600-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 3 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 14,284.00 14,419.67 Signed 2017-01-01 2017-05-15 2017-01-31 2017-06-06 2017-03-30 Quotations Envelope watershed no 36 in Orai Bassi cluster district Chittorgarh IN-WDSCD-4601-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 4 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 71,985.00 68,870.31 Signed 2017-01-01 2017-02-23 2017-01-31 2017-03-28 2017-03-30 Quotations Envelope watershed no 36 in Orai Bassi Cluster district Chittorgarh IN-WDSCD-4602-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 5 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 58,836.00 59,338.05 Signed 2017-01-01 2017-04-25 2017-01-31 2017-05-31 2017-03-30 Quotations Envelope watershed no 2 in Bari cluster district Dholpur IN-WDSCD-4604-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 6 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 93,925.00 94,733.33 Signed 2017-01-01 2017-04-25 2017-01-31 2017-05-31 2017-03-30 Quotations Envelope watershed no 2 in Bari cluster district Dholpur IN-WDSCD-4607-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 9 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 26,687.00 26,830.04 Signed 2017-01-01 2017-03-10 2017-01-31 2017-03-23 2017-03-30 Quotations Envelope watershed no 34 in Manohar Thana cluster district Jhalawar IN-WDSCD-4617-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 9 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 64,731.00 65,043.26 Signed 2017-01-01 2017-03-10 2017-01-31 2017-03-23 2017-03-30 Quotations Envelope watershed no 40 in Manohar Thana cluster district Jhalawar IN-WDSCD-4633-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 19 of IDA / 50850 Climate Resilient Agriculture Post Limited 61,343.00 50,236.96 Signed 2017-01-01 2017-01-11 2017-01-31 2017-02-08 2017-03-30 Quotations Envelope macro watershed no 6 in Jakham Catchment District Pratapgarh IN-WDSCD-4634-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 20 of IDA / 50850 Climate Resilient Agriculture Post Limited 37,254.00 29,439.86 Signed 2017-01-01 2017-02-04 2017-01-31 2017-03-28 2017-03-30 Quotations Envelope macro watershed no 6 in Jakham Catchment District Pratapgarh IN-WDSCD-4635-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 21 of IDA / 50850 Climate Resilient Agriculture Post Limited 84,821.00 72,268.80 Signed 2017-01-01 2017-01-11 2017-01-31 2017-02-08 2017-03-30 Quotations Envelope macro watershed no 6 in Jakham Catchment District Pratapgarh Page 1 IN-WDSCD-4636-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 5 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 84,119.00 76,054.80 Signed 2017-01-01 2017-01-24 2017-01-31 2017-02-21 2017-03-30 Quotations Envelope watershed no 15 in Deoli Dooni Cluster District Tonk IN-WDSCD-4637-CW-RFQ / Implementation of NRM activities Request for Single Stage - One for Watershed Development in IDA / 50850 Climate Resilient Agriculture Post Limited 12,284.00 11,546.70 Signed 2017-01-01 2017-01-25 2017-01-31 2017-02-15 2017-03-30 Quotations Envelope Village Bharnawa Ladnu Cluster District Nagour IN-WDSCD-4638-CW-RFQ / Implementation of NRM activities Request for Single Stage - One for Watershed Development in IDA / 50850 Climate Resilient Agriculture Post Limited 14,627.00 13,613.58 Signed 2017-01-01 2017-01-25 2017-01-31 2017-02-15 2017-03-30 Quotations Envelope Village Toki Ladnu Cluster District Nagour IN-WDSCD-4639-CW-RFQ / Implementation of NRM activities Request for Single Stage - One for Watershed Development in IDA / 50850 Climate Resilient Agriculture Post Limited 77,239.00 74,046.68 Signed 2017-01-01 2017-01-25 2017-01-31 2017-02-15 2017-03-30 Quotations Envelope Village Lukhash Ladnu Cluster District Nagour IN-AD - RACP-5596-CW-RFQ / Minor repairs in existing Krishi Request for Single Stage - One Seva Kendra and Agriculture IDA / 50850 Climate Resilient Agriculture Post Limited 58,000.00 324.66 Signed 2017-02-20 2017-03-10 2017-04-17 2017-03-17 2017-10-14 Quotations Envelope Research Centers in16 clusters of RACP IN-WRD - RACP-5663-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One IDA / 50850 Post Limited 38,000.00 7,642.25 Signed 2017-01-25 2016-08-05 2017-03-22 2016-08-31 2017-09-18 of Water User Association Capacity Building Quotations Envelope Buildings in Orai- Bassi Cluster IN-WRD - RACP-5665-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One of Water User Association IDA / 50850 Post Limited 30,300.00 7,327.04 Signed 2017-03-05 2016-03-12 2017-04-30 2016-04-04 2017-10-27 Capacity Building Quotations Envelope Buildings in Z Distributary Cluster in Sri Gangangar IN-WRD - RACP-5666-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One of Water User Association IDA / 50850 Post Limited 60,600.00 830,391.71 Signed 2017-03-05 2017-03-01 2017-04-30 2017-04-17 2017-10-27 Capacity Building Quotations Envelope Building in Phoolasar Cluster in Bikaner District IN-WRD - RACP-5668-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One of Water User Association IDA / 50850 Post Limited 53,000.00 70,672.82 Signed 2017-03-05 2017-03-01 2017-04-30 2017-04-17 2017-10-27 Capacity Building Quotations Envelope Building in Kheruwala Cluster in Jaisalmer District IN-RAJUVAS - RACP-5785-CW- Request for Single Stage - One Pending RFQ / Renovation works of goat IDA / 50850 Climate Resilient Agriculture Post Limited 45,455.00 0.00 2017-02-11 2017-04-08 2017-10-05 Quotations Envelope Implementation sheds at goat farm Chittorgarh IN-RAJUVAS - RACP-5786-CW- Request for Single Stage - One Pending RFQ / Construction of Tubewell IDA / 50850 Climate Resilient Agriculture Post Limited 1,516.00 0.00 2017-03-06 2017-05-01 2017-10-28 Quotations Envelope Implementation for Goat Farm at Chittogarh IN-RAJUVAS - RACP-5788-CW- RFQ / JCB Work for Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 13,637.00 0.00 2017-03-04 2017-04-29 2017-10-26 Development of Goat Farm at Quotations Envelope Implementation Chittogarh IN-RAJUVAS - RACP-5784-CW- RFB / Construction of Goat Shed , Buck Shed ,Kidding Shed, Single Stage - One Pending Feed & Fodder Store, Isolation IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 436,364.00 0.00 2017-09-13 2017-09-18 2017-10-30 2017-11-29 2018-01-03 2018-07-02 Envelope Implementation Shed, Kid Shed and Protection of Pasture Land at Goat Farm Chittorgarh IN-PMU-RACP-4276-CW-RFB / Civil Construction of Rural Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,670,000.00 0.00 2017-10-20 2017-10-25 2017-12-06 2018-01-05 2018-02-09 2018-08-08 Technology Centre in Project Envelope Implementation Clusters IN-PMU-RACP-4278-CW-RFB / Single Stage - One Pending Civil Works of Rural Haat in 7 IDA / 50850 Markets and Value Chains Post Request for Bids Open - National 1,600,000.00 0.00 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Envelope Implementation Project Clusters IN-WRD - RACP-5664-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One Pending of Water User Association IDA / 50850 Post Limited 90,900.00 0.00 2017-07-22 2017-09-16 2018-03-15 Capacity Building Quotations Envelope Implementation Building in Palaitha Cluster of Baran District IN-WDSCD-6544-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.6 of IDA / 50850 Climate Resilient Agriculture Post Limited 58,866.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Quotations Envelope Macro Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7619-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One in Micro Watershed no. 8 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 151,269.00 0.00 Canceled 2017-03-01 2017-03-06 2017-04-17 2017-04-27 2017-05-09 2018-02-27 Envelope Macro Watershed no. 6 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-6617-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.1 of IDA / 50850 Climate Resilient Agriculture Post Limited 65,910.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Quotations Envelope Macro Watershed no.8 in Bansur Cluster District Alwar for F. Y. 2017-18 Page 2 IN-WDSCD-6620-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.2 of IDA / 50850 Climate Resilient Agriculture Post Limited 46,746.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Quotations Envelope Macro Watershed no.8 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7611-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One in Micro Watershed no. 4 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 259,731.00 0.00 Canceled 2017-03-01 2017-03-06 2017-04-17 2017-04-27 2017-05-09 2018-02-27 Envelope Macro Watershed no. 8 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WRD - RACP-5669-CW-RFQ / Construction of New / repairing Farmers Organizations and Request for Single Stage - One Pending of Water User Association IDA / 50850 Post Limited 92,500.00 0.00 2017-07-25 2017-09-19 2018-03-18 Capacity Building Quotations Envelope Implementation Building in Jakham Cluster of Pratapgarh District IN-PMU-RACP-1850-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 4,507,611.94 0.00 Canceled 2016-10-14 2016-10-19 2016-11-30 2016-12-30 2017-02-03 2019-02-04 works of Orai Irrigation Project Envelope Canal system IN-WRD - RACP-20051-CW- RFB / Rehabilitation and Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 4,095,261.00 0.00 2017-08-14 2017-09-20 2017-08-19 2017-10-13 2017-09-30 2017-12-07 2017-10-30 2017-12-04 2019-01-30 modernization works of Gudha Envelope Implementation Irrigation Project Canal system IN-WRD - RACP-20052-CW- RFB / Rehabilitation and Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 3,525,061.00 0.00 2017-09-11 2017-10-24 2017-09-16 2017-12-28 2017-10-28 2017-11-27 2018-01-01 2019-02-27 modernization works of Orai Envelope Implementation Irrigation Project Canal system IN-WRD - RACP-20053-CW- RFB / Rehabilitation and Single Stage - One Under modernization works of Jakham IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,473,461.00 0.00 2017-09-04 2017-10-24 2017-09-09 2018-01-01 2017-10-21 2017-11-20 2017-12-25 2019-01-30 Envelope Implementation (LMC) Irrigation Project Canal system IN-WRD - RACP-20054-CW- RFB / Rehabilitation and Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,107,461.00 0.00 2017-09-04 2017-10-24 2017-09-09 2017-10-24 2017-10-21 2017-11-20 2017-12-25 2019-01-15 modernization works of Bassi Envelope Implementation Irrigation Project Canal system IN-WRD - RACP-20055-CW- RFB / Rehabilitation and Single Stage - One Under modernization works of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,557,492.00 0.00 2017-08-21 2017-12-20 2017-08-26 2017-12-20 2017-10-07 2017-11-06 2017-12-11 2019-01-30 Envelope Implementation Kheruwala Distributary Canal system IN-WRD - RACP-20056-CW- RFB / Rehabilitation and Single Stage - One Under modernization works of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,816,692.00 0.00 2017-09-12 2017-12-20 2017-09-17 2017-12-20 2017-10-29 2017-11-28 2018-01-02 2019-02-21 Envelope Implementation Phoolasar Distributary Canal system IN-WRD - RACP-20057-CW- RFB / Rehabilitation and Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 298,107.00 0.00 2017-09-26 2017-11-01 2017-10-01 2017-12-27 2017-11-12 2017-12-12 2018-01-16 2018-10-31 modernization works of Z- Envelope Implementation Distributary Canal system IN-WRD - RACP-20058-CW- RFB / Rehabilitation and modernization works of direct off- Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,908,400.00 0.00 2017-09-19 2017-10-09 2017-09-24 2017-12-27 2017-11-05 2017-12-05 2018-01-09 2019-02-28 taking minors of Palaitha sub Envelope Implementation branch from KM 12.30 to KM 25.75 IN-PMU-RACP-1854-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,557,500.00 0.00 Canceled 2018-01-25 2018-01-30 2018-03-13 2018-04-12 2018-05-17 2020-05-17 works of Kheruwala Distributry Envelope canal system IN-PMU-RACP-1856-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,666,400.00 0.00 Canceled 2018-01-24 2018-01-29 2018-03-12 2018-04-11 2018-05-16 2020-01-10 works of Bassi Irrigation System Envelope canal system IN-PMU-RACP-1853-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,816,700.00 0.00 Canceled 2018-01-10 2018-01-15 2018-02-26 2018-03-28 2018-05-02 2020-05-02 works of Phoolasar Distributry Envelope canal system IN-PMU-RACP-1855-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 4,786,900.00 0.00 Canceled 2018-01-29 2018-02-03 2018-03-17 2018-04-16 2018-05-21 2020-05-20 works in canal system of Gudha Envelope Irrigation Project IN-PMU-RACP-1857-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 298,100.00 0.00 Canceled 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2020-01-28 works of Z-distributry canal Envelope system IN-PMU-RACP-1852-CW-RFB / Rehabilitation and modernization Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 1,822,500.00 0.00 Canceled 2018-01-22 2018-01-27 2018-03-10 2018-04-09 2018-05-14 2020-05-14 works of LMC of Jakham Envelope Irrigation Project canal system IN-PMU-RACP-1851-CW-RFB / Rehabilitation and modernization Single Stage - One works of direct off-taking minors IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,207,575.00 0.00 Canceled 2016-10-14 2016-10-19 2016-11-30 2016-12-30 2017-02-03 2019-02-04 Envelope of Palaitha Sub Branch from KM 12.30 to KM 25.75 Page 3 IN-WDSCD-7617-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One in Micro Watershed no. 5 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 114,000.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Envelope Macro Watershed no. 6 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-7574-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One in Micro Watershed no. 2 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 180,567.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Envelope Macro Watershed no. 7 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-6577-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.5 of IDA / 50850 Climate Resilient Agriculture Post Limited 93,194.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Quotations Envelope Macro Watershed no.7 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6473-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.4 of IDA / 50850 Climate Resilient Agriculture Post Limited 61,567.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Quotations Envelope Macro Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6548-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.7 of IDA / 50850 Climate Resilient Agriculture Post Limited 23,388.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Quotations Envelope Macro Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-4588-CW-RFQ / Implementation of NRM activities Request for Single Stage - One in micro watershed no 9 of macro IDA / 50850 Climate Resilient Agriculture Post Limited 60,100.00 0.00 Canceled 2017-07-15 2017-08-14 2017-10-11 Quotations Envelope watershed 6 in Bansur cluster district Alwar IN-WDSCD-6576-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.10 of IDA / 50850 Climate Resilient Agriculture Post Limited 25,597.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Quotations Envelope Macro Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6579-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One in Micro Watershed no.6 of IDA / 50850 Climate Resilient Agriculture Post Limited 70,373.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Quotations Envelope Macro Watershed no.7 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7606-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One in Micro Watershed no. 3 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 188,955.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Envelope Macro Watershed no. 7 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-22460-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro watershed No. 5 of IDA / 50850 Climate Resilient Agriculture Post Limited 90,255.00 0.00 2017-08-23 2017-09-04 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro Watershed no. 7 in Bansur Cluster District Alwar for FY 2017-18 IN-WDSCD-22553-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 6 of IDA / 50850 Climate Resilient Agriculture Post Limited 68,070.00 0.00 2017-08-23 2017-09-04 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22563-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 5 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 103,896.00 0.00 2017-08-18 2017-09-01 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-AD - RACP-5504-CW-CDD / Construction of Water Storage Community Driven Pending Structure/ Diggies by Individual IDA / 50850 Climate Resilient Agriculture Post Direct 454,500.00 0.00 2017-01-25 2017-01-30 2017-03-06 2017-09-02 Development Implementation Beneficiaries in Canal Command Areas In Z-Distributary (Grant) IN-AD - RACP-5498-CW-CDD / Construction of Water Storage Structure / Diggies by individual Community Driven Pending IDA / 50850 Climate Resilient Agriculture Post Direct 2,727,000.00 0.00 2017-01-14 2017-01-19 2017-02-23 2017-08-22 beneficiaries in Canal Command Development Implementation Area in Phoolasar Cluaster (Grant) IN-AD - RACP-5501-CW-CDD / Construction of Water Storage Structure / Diggies by Individual Community Driven Pending IDA / 50850 Climate Resilient Agriculture Post Direct 2,727,000.00 0.00 2017-01-20 2017-01-25 2017-03-01 2017-08-28 Beneficiaries in Canal Command Development Implementation Area in Kheruwala Cluster (Grant) Page 4 IN-WDSCD-22599-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 1 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 173,959.00 0.00 2017-08-18 2017-09-01 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22602-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 3 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 182,156.00 0.00 2017-08-18 2017-09-01 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22609-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 12 of IDA / 50850 Climate Resilient Agriculture Post Limited 75,110.00 0.00 2017-08-23 2017-09-06 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22610-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 09 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 340,037.00 0.00 2017-08-18 2017-09-06 2017-08-23 2017-09-11 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22614-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 11 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 110,874.00 0.00 2017-08-18 2017-09-06 2017-08-23 2017-09-11 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22615-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 13 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 161,707.00 0.00 2017-08-18 2017-09-06 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22618-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 1 of IDA / 50850 Climate Resilient Agriculture Post Limited 55,355.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22623-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 3 of IDA / 50850 Climate Resilient Agriculture Post Limited 88,268.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22627-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 4 of IDA / 50850 Climate Resilient Agriculture Post Limited 75,388.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22628-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 5 of IDA / 50850 Climate Resilient Agriculture Post Limited 48,206.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22631-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 2 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 125,940.00 0.00 2017-08-18 2017-09-05 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22633-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 1 of IDA / 50850 Climate Resilient Agriculture Post Limited 81,009.00 0.00 2017-08-23 2017-09-15 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017-18 IN-WDSCD-22635-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 2 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 104,258.00 0.00 2017-08-18 2017-09-11 2017-08-23 2017-09-15 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017-18 IN-WDSCD-22637-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 6 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 392,458.00 0.00 2017-08-18 2017-09-11 2017-08-23 2017-09-15 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017-18 Page 5 IN-WDSCD-22638-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 4 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 241,556.00 0.00 2017-08-18 2017-09-05 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2017-18 IN-WDSCD-22639-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 8 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 134,829.00 0.00 2017-08-18 2017-09-05 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2017-18 IN-WDSCD-22640-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 2 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 220,791.00 0.00 2017-08-18 2017-09-05 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 3 in Bari Cluster District Dholpur for F.Y. 2017-18 IN-WDSCD-22642-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 3 of IDA / 50850 Climate Resilient Agriculture Post Limited 25,062.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 23 in Manoharthana Cluster District Jhalawar for F.Y. 2017-18 IN-WDSCD-22647-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 3 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 409,984.00 0.00 2017-08-18 2017-09-06 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 32 in Manohar thana Cluster District Jhalawar for F.Y. 2017-18 IN-WDSCD-22651-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 277,800.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed Development in Envelope Implementation Village Manu Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22656-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 126,046.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed Development in Envelope Implementation Village Jhardiya Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22658-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 122,400.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed Development in Envelope Implementation Village Sunari Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22663-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 16 of IDA / 50850 Climate Resilient Agriculture Post Limited 74,369.00 0.00 2017-08-23 2017-09-06 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22668-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 15 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 126,169.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22671-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 17 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 186,723.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22673-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 18 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 167,222.00 0.00 2017-08-18 2017-08-30 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22676-CW-RFB / Implementation of Natural Resource Management activities Single Stage - One Under in Micro Watershed No. 1 of IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 903,323.00 0.00 2017-08-18 2017-09-01 2017-08-23 2017-09-13 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Envelope Implementation Macro watershed No. 17 in Duni Deoli Cluster District Tonk for F.Y. 2017-18 IN-PMU-RACP-22606-CW-FCA / Construction of Piezometers and Obsevation Wells including civil IDA / 50850 Climate Resilient Agriculture Post Force Account Direct 153,847.00 185,143.75 Signed 2017-09-21 2017-10-13 2017-09-26 2017-10-25 2017-10-31 2017-12-19 2018-04-29 works at different locations in Pisangan, Bonli and Sangod Ground water clusters IN-WDSCD-22643-CW-RFQ / Implementation of Natural Resource Management activities Request for Single Stage - One Under in Micro Watershed No. 4 of IDA / 50850 Climate Resilient Agriculture Post Limited 58,995.00 0.00 2017-08-23 2017-09-08 2017-10-18 2018-12-31 Quotations Envelope Implementation Macro watershed No. 32 in Manohar thana Cluster District Jhalawar for F.Y. 2017-18 Page 6 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMU-RACP-1672-GO-RFB / Supply and Installation of Geo Single Stage - One Under Membrane as a Pond Liner on IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 750,000.00 400,578.27 2016-09-19 2016-11-04 2016-09-19 2016-09-19 2017-01-06 2016-09-30 2017-01-21 2016-10-15 2016-11-07 2017-10-14 Envelope Implementation Farm Pond (Framework Agreement) IN-PMU-RACP-1679-GO-RFB / Supply and Commissioning of Single Stage - One IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,690,606.00 2,408,393.99 Signed 2016-09-19 2016-10-13 2016-09-19 2016-10-13 2016-09-19 2016-10-14 2016-09-19 2017-01-21 2016-09-30 2016-10-04 2017-09-29 Micro Irrigation Equipment's Envelope (Drip/Mini Sprinkler/Automation) IN-PMU-RACP-1685-GO-RFB / Single Stage - One Supply of Plastic Mulch Sheet on IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 351,515.00 213,743.74 Signed 2016-09-19 2016-10-04 2016-09-19 2016-09-19 2017-01-11 2016-10-05 2017-01-12 2016-10-25 2016-11-23 2017-10-24 Envelope Farmers Field IN-PMU-RACP-1693-GO-RFB / Procurement of Vegetable Seeds Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 351,515.00 86,469.20 Signed 2016-09-19 2016-09-20 2016-09-19 2016-09-19 2016-09-20 2016-09-25 2016-09-20 2016-10-10 2016-11-30 2017-10-09 for Open Cultivation and Envelope Protected Cultivation IN-PMU-RACP-1696-GO-RFB / Single Stage - One Procurement of Water Soluble IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 960,500.00 544,188.93 Signed 2016-10-10 2017-01-12 2016-10-15 2016-11-26 2017-01-12 2016-12-26 2017-01-12 2017-01-30 2017-02-07 2018-01-29 Envelope Fertilizer Kit IN-PMU-RACP-1698-GO-RFB / Supply and commissioning of Single Stage - One IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,439,394.00 1,904,484.63 Signed 2016-09-19 2016-12-14 2016-10-09 2016-12-16 2016-11-20 2017-01-25 2016-12-20 2017-02-17 2017-01-24 2017-03-08 2018-01-23 solar photovoltaic (SPV) water Envelope pumping system IN-PMU-RACP-1703-GO-RFB / Single Stage - One Procurement of Feeding and IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 241,667.00 238,270.53 Signed 2016-10-15 2016-10-26 2016-10-20 2017-06-01 2016-12-01 2016-11-28 2016-12-31 2017-01-11 2017-02-04 2017-01-24 2018-02-03 Envelope Water Trough IN-PMU-RACP-1704-GO-RFB / Procurement of Multiutility Vehicles ( Mobile Veterinary Single Stage - One Vans for 12 Clusters and Mobile IDA / 50850 Project Management and M&E Post Request for Bids Open - National 169,697.00 118,815.89 Signed 2016-09-19 2016-10-04 2016-09-19 2017-06-01 2016-09-19 2016-06-08 2016-09-19 2016-07-21 2016-10-10 2016-11-29 2017-10-09 Envelope Diognostic and Demonstration Vehicles in 2 Center of Excellence IN-PMU-RACP-1709-GO-RFB / Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 345,455.00 297,296.29 2016-09-19 2016-06-22 2016-09-19 2016-09-19 2016-07-27 2016-09-25 2016-09-22 2016-10-30 2016-10-10 2017-10-29 Procurement of Chaff Cutter Envelope Implementation IN-PMU-RACP-1719-GO-RFQ / Request for Single Stage - One Procurement of Almirah and IDA / 50850 Project Management and M&E Post Limited 22,727.00 2,388.13 Signed 2016-09-19 2017-03-16 2016-10-31 2017-04-03 2017-04-29 Quotations Envelope Furniture IN-PMU-RACP-1722-GO-RFQ / Request for Single Stage - One IDA / 50850 Project Management and M&E Post Limited 27,273.00 15,622.75 Signed 2016-11-19 2017-03-24 2017-01-14 2017-04-17 2017-07-13 Multi-functional Photocopier Quotations Envelope IN-PMU-RACP-1724-GO-RFQ / Request for Single Stage - One Procurement of Desktop IDA / 50850 Project Management and M&E Post Limited 20,000.00 26,796.92 Signed 2016-11-14 2016-03-11 2017-01-09 2016-04-05 2017-07-08 Quotations Envelope Computers IN-PMU-RACP-1725-GO-RFQ / Request for Single Stage - One Procurement of Multi-functional IDA / 50850 Project Management and M&E Post Limited 10,000.00 26,796.92 Signed 2016-11-20 2016-03-11 2017-01-15 2016-04-05 2017-07-14 Quotations Envelope Printer IN-PMU-RACP-1727-GO-RFQ / Request for Single Stage - One IDA / 50850 Project Management and M&E Post Limited 20,000.00 26,796.92 Signed 2016-11-20 2016-03-11 2017-01-15 2016-04-05 2017-07-14 Procurement of Laptops Quotations Envelope IN-PMU-RACP-1676-GO-RFB / Installation of Green House and Single Stage - One IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,401,515.00 0.00 Canceled 2016-09-19 2016-09-19 2016-09-19 2016-09-20 2016-09-19 2016-09-30 2017-09-29 Shade Net House with Irrigation Envelope System IN-PMU-RACP-1860-GO-RFB / Supply and Installation of Green Single Stage - One IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,401,515.00 2,016,322.83 Signed 2016-09-22 2016-10-13 2016-09-22 2016-10-19 2016-09-22 2016-12-28 2016-09-22 2017-01-02 2016-09-30 2017-01-06 2017-09-29 House and Shade Net House Envelope with Micro Irrigation Facilities IN-HD - RACP-3555-GO-RFQ / Request for Single Stage - One Up-gradation of Irrigation System IDA / 50850 Climate Resilient Agriculture Post Limited 30,770.00 23,569.41 Signed 2017-01-15 2017-01-04 2017-03-12 2017-01-24 2017-09-08 Quotations Envelope with Automation at COE, Kota IN-HD - RACP-3558-GO-RFQ / Tractor and tractor mounted Request for Single Stage - One equipment including hydraulic IDA / 50850 Climate Resilient Agriculture Post Limited 15,400.00 5,499.81 Signed 2017-01-17 2016-11-23 2017-03-14 2016-12-20 2017-09-10 Quotations Envelope trolly, rotavator, lift harrow and cultivator for COE, Kota IN-HD - RACP-3559-GO-RFQ / Request for Single Stage - One Post Harvest Management IDA / 50850 Climate Resilient Agriculture Post Limited 37,000.00 6,093.33 Signed 2017-01-21 2017-02-22 2017-03-18 2017-02-22 2017-09-14 Quotations Envelope Equipment for COE, Kota IN-HD - RACP-3560-GO-RFQ / Request for Single Stage - One Installation of Weather Station at IDA / 50850 Climate Resilient Agriculture Post Limited 4,700.00 5,029.13 Signed 2016-12-25 2017-02-14 2017-02-19 2017-02-28 2017-08-18 Quotations Envelope COE, Kota IN-HD - RACP-3563-GO-RFQ / Request for Single Stage - One Power Operated Equipment's for IDA / 50850 Climate Resilient Agriculture Post Limited 7,700.00 1,142.81 Signed 2017-01-14 2016-09-02 2017-03-11 2016-09-20 2017-09-07 Quotations Envelope COE, Bassi, Jaipur IN-PMU-RACP-4272-GO-RFQ / Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 90,000.00 77,818.04 Signed 2016-12-06 2016-12-27 2017-01-26 2016-12-22 2017-07-25 Travis for Animal Restrain Quotations Envelope IN-PMU-RACP-4273-GO-RFQ / Request for Single Stage - One Animal Tag for Identification of IDA / 50850 Climate Resilient Agriculture Post Limited 12,000.00 2,874.74 Signed 2017-01-14 2017-03-02 2017-03-11 2017-03-21 2017-09-07 Quotations Envelope Animals Page 7 IN-HD - RACP-5267-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in IDA / 50850 Climate Resilient Agriculture Post Limited 4,700.00 4,235.84 Signed 2017-01-30 2017-03-23 2017-03-27 2017-03-14 2017-09-23 Quotations Envelope Pisangan Cluster of Ajmer IN-HD - RACP-5271-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in IDA / 50850 Climate Resilient Agriculture Post Limited 6,700.00 5,714.06 Signed 2017-01-30 2017-03-09 2017-03-27 2017-03-24 2017-09-23 Quotations Envelope Manoharthan -Jhalawar Cluster IN-HD - RACP-5272-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in Z IDA / 50850 Climate Resilient Agriculture Post Limited 3,400.00 3,107.82 Signed 2017-01-30 2017-03-08 2017-03-27 2017-03-28 2017-09-23 Quotations Envelope Distributery Ganganagar Cluster IN-HD - RACP-5274-GO-RFQ / Request for Single Stage - One Supply of Plastic crates in Bonil IDA / 50850 Climate Resilient Agriculture Post Limited 6,700.00 3,878.98 Signed 2017-01-30 2017-02-28 2017-03-27 2017-03-14 2017-09-23 Quotations Envelope Sawai Madhopur District IN-HD - RACP-5275-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in IDA / 50850 Climate Resilient Agriculture Post Limited 3,400.00 3,025.60 Signed 2017-01-30 2017-03-20 2017-03-27 2017-03-27 2017-09-23 Quotations Envelope Kushalgarh Banswara cluster IN-HD - RACP-5276-GO-RFQ / Supply of Plastic Crates in Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 3,400.00 3,025.60 Signed 2017-01-25 2017-03-22 2017-03-10 2017-09-18 Jakham Cluster in Pratapgarh Quotations Envelope District IN-HD - RACP-5277-GO-RFQ / Request for Single Stage - One Supply of plastic Crates in Bari IDA / 50850 Climate Resilient Agriculture Post Limited 1,400.00 1,212.78 Signed 2017-01-30 2017-02-23 2017-03-27 2017-03-30 2017-09-23 Quotations Envelope Dholpur Cluster IN-HD - RACP-5278-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in Dooni- IDA / 50850 Climate Resilient Agriculture Post Limited 3,400.00 3,034.31 Signed 2017-01-30 2017-02-22 2017-03-27 2017-03-11 2017-09-23 Quotations Envelope Deoli Cluster of Tonk District IN-HD - RACP-5279-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in Guda IDA / 50850 Climate Resilient Agriculture Post Limited 2,000.00 1,817.48 Signed 2017-01-30 2017-03-06 2017-03-27 2017-03-20 2017-09-23 Quotations Envelope Bundi Cluster IN-GWD - RACP-5285-GO-RFQ / Supply of Electronic Water Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,470.00 851.59 Signed 2017-01-30 2017-03-10 2017-03-27 2017-03-23 2017-09-23 Level Sounder in Bonli cluster, Quotations Envelope District Sawai Madhopur. IN-GWD - RACP-5289-GO-RFQ / Supply of Electronic Water Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,100.00 449.91 Signed 2017-01-30 2017-02-27 2017-03-27 2017-03-14 2017-09-23 Level Sounder in Pisangan Quotations Envelope cluster, District Ajmer. IN-PMU-RACP-5392-GO-RFQ / Request for Single Stage - One Procurement of Tractor Mounted IDA / 50850 Climate Resilient Agriculture Post Limited 11,400.00 22,340.30 Signed 2017-01-25 2017-02-14 2017-03-22 2017-03-02 2017-09-18 Quotations Envelope Straw Reaper IN-PMU-RACP-5393-GO-RFQ / Request for Single Stage - One Procurement of Multi Crop IDA / 50850 Climate Resilient Agriculture Post Limited 72,000.00 94,468.61 Signed 2017-01-30 2017-02-14 2017-03-27 2017-03-02 2017-09-23 Quotations Envelope Thresher IN-PMU-RACP-5394-GO-RFQ / Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 95,500.00 50,901.18 Signed 2017-02-04 2017-03-03 2017-04-01 2017-03-19 2017-09-28 Procurement of Rotavator Quotations Envelope IN-PMU-RACP-5395-GO-RFQ / Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 10,600.00 11,637.66 Signed 2017-02-01 2017-02-16 2017-03-29 2017-03-10 2017-09-25 Procurement of Groundnut Digger Quotations Envelope IN-PMU-RACP-5396-GO-RFB / Single Stage - One Procurement of Plastic /HDPE IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 403,000.00 124,527.96 Signed 2017-01-25 2017-02-13 2017-01-30 2017-03-13 2017-03-15 2017-04-12 2017-04-05 2017-05-17 2017-04-19 2017-11-13 Envelope Movable Threshing Floor IN-GWD - RACP-5437-GO-RFQ Request for Single Stage - One / Supply of Handled GPS in IDA / 50850 Climate Resilient Agriculture Post Limited 1,470.00 1,368.24 Signed 2017-01-30 2017-03-17 2017-03-27 2017-03-23 2017-09-23 Quotations Envelope Pisangan cluster, District Ajmer IN-AD - RACP-5505-GO-RFQ / Procurement of Photocopier cum Request for Single Stage - One IDA / 50850 Project Management and M&E Post Limited 1,900.00 750.80 Signed 2017-02-01 2017-02-13 2017-03-29 2017-02-20 2017-09-25 Printer Machine for Bari Cluster Quotations Envelope of Dholpur District IN-AD - RACP-5523-GO-RFQ / Procurement of Computer, Request for Single Stage - One Printer and Scanner for IDA / 50850 Project Management and M&E Post Limited 1,500.00 1,239.61 Signed 2017-02-01 2017-02-01 2017-03-29 2017-02-15 2017-09-25 Quotations Envelope Kheruwala Cluster of Jaisalmer District IN-AD - RACP-5599-GO-RFQ / Furniture and fixture in existing Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 19,400.00 644.75 Signed 2017-02-25 2017-03-03 2017-04-22 2017-03-14 2017-10-19 Krishi Seva Kendra in RACP 16 Quotations Envelope clusters IN-RAJUVAS - RACP-5768-GO- Request for Single Stage - One RFQ / Procurement of Grinder for IDA / 50850 Climate Resilient Agriculture Post Limited 758.00 768.93 Signed 2017-02-11 2017-02-14 2017-04-08 2017-03-18 2017-10-05 Quotations Envelope Grinding of Feed Ingradient IN-RAJUVAS - RACP-5770-GO- Request for Single Stage - One RFQ / Procurement of Feeding IDA / 50850 Climate Resilient Agriculture Post Limited 7,576.00 7,689.32 Signed 2017-02-11 2017-02-14 2017-04-08 2017-03-18 2017-10-05 Quotations Envelope Trough IN-RAJUVAS - RACP-5771-GO- Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 379.00 0.00 2017-02-11 2017-04-08 2017-10-05 RFQ / Procurement of Milk Cans Quotations Envelope Implementation IN-RAJUVAS - RACP-5772-GO- RFQ / Procurement of Clinical Request for Single Stage - One Pending Equipment's like Weighing IDA / 50850 Climate Resilient Agriculture Post Limited 3,030.00 0.00 2017-02-11 2017-04-08 2017-10-05 Quotations Envelope Implementation Balance ,Refrigerator etc. for Goat Farm IN-RAJUVAS - RACP-5773-GO- RFQ / Procurement of Request for Single Stage - One Computer, Printer, Photocopier IDA / 50850 Project Management and M&E Post Limited 4,546.00 4,637.67 Signed 2017-02-13 2017-02-14 2017-04-10 2017-03-18 2017-10-07 Quotations Envelope and Digital Camera for Goat Farm Page 8 IN-RAJUVAS - RACP-5774-GO- RFQ / Procurement of furniture Request for Single Stage - One Pending IDA / 50850 Project Management and M&E Post Limited 1,894.00 0.00 2017-02-13 2017-04-10 2017-10-07 and fixture for Sirohi Goat Farm Quotations Envelope Implementation at Chittogarh IN-RAJUVAS - RACP-5775-GO- Request for Single Stage - One Pending RFQ / Procurement of Water IDA / 50850 Climate Resilient Agriculture Post Limited 2,273.00 0.00 2017-02-13 2017-04-10 2017-10-07 Quotations Envelope Implementation Pump for Sirohi Goat Farm IN-RAJUVAS - RACP-5776-GO- RFQ / Procurement of Tractor Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 12,122.00 0.00 2017-02-15 2017-04-12 2017-10-09 with Trolly and other implements Quotations Envelope Implementation for Sirohi Goat Farm IN-RAJUVAS - RACP-5777-GO- RFQ / Procurement of Irrgation Request for Single Stage - One Pending Pipes to Develop Irrigation IDA / 50850 Climate Resilient Agriculture Post Limited 7,576.00 0.00 2017-02-15 2017-04-12 2017-10-09 Quotations Envelope Implementation Facility at Sirohi Goat Farm Chittorgarh IN-RAJUVAS - RACP-5779-GO- Request for Single Stage - One Pending RFQ / Procurement of Feed for IDA / 50850 Climate Resilient Agriculture Post Limited 90,910.00 0.00 2017-02-20 2017-04-17 2017-10-14 Quotations Envelope Implementation Sirohi Goat Farm at Chittogarh IN-HD - RACP-5365-GO-RFQ / Supply of Garlic Sowing Machine Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 14,000.00 621.36 Signed 2017-01-23 2017-04-21 2017-03-20 2017-05-05 2017-09-16 in Palyatha Cluster of Baran Quotations Envelope District IN-HD - RACP-5356-GO-RFQ / Procurement of Mini Tractor (up Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 5,900.00 3,211.79 Signed 2017-02-15 2017-03-08 2017-04-12 2017-03-14 2017-10-09 to 20 HP) in Bonil Cluster of Quotations Envelope Sawai Madhopur District IN-HD - RACP-5357-GO-RFQ / Procurement of Mini Tractor (up Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 59,000.00 5,446.20 Signed 2017-02-15 2017-02-08 2017-04-12 2017-03-01 2017-10-09 to 20 HP) Z Distributry Cluster of Quotations Envelope Shri Ganganagar District IN-HD - RACP-5358-GO-RFQ / Procuremetn of Mini Tractor (up Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 17,500.00 5,685.44 Signed 2017-02-15 2017-02-15 2017-04-12 2017-03-30 2017-10-09 to 20 HP) in Manoharthana Quotations Envelope Cluater of Jhalawar District IN-HD - RACP-5363-GO-RFQ / Supply of Power Tiller in Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 5,000.00 4,754.07 Signed 2017-01-23 2017-03-10 2017-03-20 2017-03-14 2017-09-16 Pisangan Cluster of Ajmer Quotations Envelope District IN-HD - RACP-5366-GO-RFQ / Supply of Garlic Sowing Machine Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 6,700.00 660.81 Signed 2017-01-23 2017-03-09 2017-03-20 2017-03-23 2017-09-16 in Manoharthan Cluster of Quotations Envelope Jhalawar District IN-HD - RACP-5367-GO-RFQ / Request for Single Stage - One Supply of Garlic Sowing Machine IDA / 50850 Climate Resilient Agriculture Post Limited 14,000.00 68,621.36 Signed 2017-01-23 2017-04-25 2017-03-20 2017-05-15 2017-09-16 Quotations Envelope in Sangod Cluster of Kota District IN-PMU-RACP-4269-GO-RFQ / Community Driven Pending Community Procurement of Buck IDA / 50850 Climate Resilient Agriculture Post Limited - National 541,000.00 0.00 2017-09-18 2017-09-23 2017-11-04 2017-12-04 2018-01-08 2018-07-07 Development Implementation and Goat IN-DPMU - RACP-7291-GO-RFQ / Portable Diesel Pump set 5 HP for Pumping of Rain Water Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 17,650.00 0.00 2017-02-25 2017-04-22 2017-10-19 Harvested in Farm Pound Quotations Envelope Implementation Excavated on Farmers Fields in Mokhampura Cluster. IN-RAJUVAS - RACP-5780-GO- Request for Single Stage - One Pending RFQ / Procurement of Fodder for IDA / 50850 Climate Resilient Agriculture Post Limited 75,758.00 0.00 2017-10-09 2017-12-04 2018-06-02 Quotations Envelope Implementation Sirohi Goat Farm at Chittogarh IN-RAJUVAS - RACP-5782-GO- RFQ / Procurement of Medicine Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 22,728.00 0.00 2017-10-30 2017-12-25 2018-06-23 for Sirohi Goat Farm at Quotations Envelope Implementation Chittorgarh IN-GWD - RACP-5436-GO-RFQ Request for Single Stage - One / Supply of Handheld GPS in IDA / 50850 Climate Resilient Agriculture Post Limited 1,470.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Quotations Envelope Sangod cluster, District Kota. IN-GWD - RACP-5435-GO-RFQ / Supply of Handheld GPS in Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,470.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Bonli cluster, District Sawai Quotations Envelope Madhopur. IN-GWD - RACP-5288-GO-RFQ / Supply of Electronic Water Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,100.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Level Sounder in Sangod cluster, Quotations Envelope District Kota. IN-GWD - RACP-5295-GO-RFQ / Supply of Water sample bottles Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 660.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 in Pisangan cluster, District Quotations Envelope Ajmer. IN-GWD - RACP-5294-GO-RFQ Request for Single Stage - One / Supply of Water sample bottles IDA / 50850 Climate Resilient Agriculture Post Limited 660.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Quotations Envelope in sangod cluster, District Kota IN-GWD - RACP-5293-GO-RFQ / Supply of Water sample bottles Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 660.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 in Bonli cluster, District Sawai Quotations Envelope Madhopur. Page 9 IN-GWD - RACP-5291-GO-RFQ / Supply of Chemicals and Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,840.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Glassware's in Sangod cluster, Quotations Envelope District Kota. IN-GWD - RACP-5292-GO-RFQ / Supply of Chemicals and Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 1,840.00 0.00 Canceled 2017-01-30 2017-03-27 2017-09-23 Glassware's in Pisangan cluster, Quotations Envelope District Ajmer. IN-PMU-RACP-4310-GO-RFQ / Request for Single Stage - One Azolla cultivation for MTG goat IDA / 50850 Climate Resilient Agriculture Post Limited 38,000.00 0.00 Canceled 2017-01-15 2017-03-12 2017-09-08 Quotations Envelope members IN-PMU-RACP-5391-GO-RFQ / Request for Single Stage - One Procurement of Reaper (Self IDA / 50850 Climate Resilient Agriculture Post Limited 30,300.00 0.00 Canceled 2017-01-21 2017-03-18 2017-09-14 Quotations Envelope Propelled) IN-PMU-RACP-1700-GO-RFB / Single Stage - One Under Procurement of DWLR IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 540,909.00 0.00 2018-01-22 2018-01-03 2018-01-27 2018-01-04 2018-03-10 2018-04-09 2018-05-14 2019-05-13 Envelope Implementation Telemetric IN-WRD - RACP-5670-GO-RFQ / Procurement of Computers and Farmers Organizations and Request for Single Stage - One Pending Printers for Water User IDA / 50850 Post Limited 80,900.00 0.00 2018-03-26 2018-05-21 2018-11-17 Capacity Building Quotations Envelope Implementation Association of Surface Water Clusters of RACP IN-WRD - RACP-5671-GO-RFQ / Procurement of Furniture for Farmers Organizations and Request for Single Stage - One Pending IDA / 50850 Post Limited 40,500.00 0.00 2018-03-27 2018-05-22 2018-11-18 Water User Associations of Capacity Building Quotations Envelope Implementation Surface Water Clusters of RACP IN-PMU-RACP-1720-GO-RFQ / Request for Single Stage - One IDA / 50850 Project Management and M&E Post Limited 5,455.00 2,297.60 Signed 2017-12-24 2017-11-01 2018-02-18 2017-11-23 2018-08-17 Procurement of LED TV Quotations Envelope IN-HD - RACP-5355-GO-RFQ / Procurement of Mini Tractor (up Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 5,900.00 0.00 Canceled 2017-02-15 2017-04-12 2017-10-09 to 20 HP) Sangod Cluster of Kota Quotations Envelope District IN-HD - RACP-5360-GO-RFQ / Request for Single Stage - One Supply of Power Weeder in IDA / 50850 Climate Resilient Agriculture Post Limited 2,500.00 2,026.50 Signed 2017-09-09 2017-02-20 2018-03-08 2017-06-27 2018-09-04 Quotations Envelope Bansur Cluster of Alwar District IN-HD - RACP-5269-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in IDA / 50850 Climate Resilient Agriculture Post Limited 6,700.00 6,079.50 Signed 2017-08-26 2017-02-20 2018-02-13 2017-06-27 2018-08-12 Quotations Envelope Bansur Cluster of Alwar District IN-HD - RACP-5287-GO-RFQ / Community Procurement of Pack Request for Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Limited 100,000.00 0.00 2017-07-29 2017-03-23 2018-03-12 2018-09-08 House in Manoharthan Cluster of Quotations Envelope Implementation Jhalawar District IN-HD - RACP-5353-GO-RFQ / Community Procurement of Pack Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 14,000.00 0.00 2017-09-02 2018-03-27 2018-09-23 House in Sangod Cluster of Kota Quotations Envelope Implementation District IN-HD - RACP-5354-GO-RFQ / Community Procurement of Request for Single Stage - One Pending Pack House in Z Distributery IDA / 50850 Climate Resilient Agriculture Post Limited 14,000.00 0.00 2017-08-26 2018-03-12 2018-09-08 Quotations Envelope Implementation Cluster of Sri Ganganagar District IN-HD - RACP-5286-GO-RFQ / Community Procurement of Pack Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 47,000.00 0.00 2017-08-29 2018-04-11 2018-10-08 House in Orai-Bassi Cluster in Quotations Envelope Implementation Chittorgarh District IN-HD - RACP-5281-GO-RFQ / Request for Single Stage - One Procurement of Pack House in IDA / 50850 Climate Resilient Agriculture Post Limited 6,700.00 0.00 Canceled 2017-02-01 2017-03-29 2017-09-25 Quotations Envelope Bansur Cluster of Alwar District IN-HD - RACP-5270-GO-RFQ / Request for Single Stage - One Pending Supply of Plastic Crates in Orai- IDA / 50850 Climate Resilient Agriculture Post Limited 3,400.00 0.00 2017-07-22 2017-09-16 2018-03-15 Quotations Envelope Implementation Bassi Cluster of Chittorgarh IN-GWD - RACP-5290-GO-RFQ / Supply of Chemicals/Lab Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 7,500.00 0.00 Canceled 2017-07-01 2017-08-26 2018-02-22 equipment's under PIU, GWD, Quotations Envelope JAIPUR IN-PMU-RACP-21528-GO-RFQ / Request for Single Stage - One Supply of Plastic Crates in IDA / 50850 Climate Resilient Agriculture Post Limited 88,000.00 37,742.27 Signed 2017-09-20 2017-09-11 2017-11-15 2017-11-13 2018-05-14 Quotations Envelope Horticulture Clusters IN-PMU-RACP-21530-GO-RFQ / Request for Single Stage - One Supply of Power Weeder in IDA / 50850 Climate Resilient Agriculture Post Limited 9,230.00 12,202.48 Signed 2017-10-16 2017-09-11 2017-12-11 2017-11-13 2018-06-09 Quotations Envelope Horticulture Clusters IN-PMU-RACP-21531-GO-RFQ / Request for Single Stage - One Supply of Power Tiller in IDA / 50850 Climate Resilient Agriculture Post Limited 37,000.00 16,249.85 Signed 2017-10-16 2017-09-11 2017-12-11 2017-11-13 2018-06-09 Quotations Envelope Horticulture Clusters IN-PMU-RACP-21532-GO-RFQ / Request for Single Stage - One Supply of Tractor Mounted Power IDA / 50850 Climate Resilient Agriculture Post Limited 17,800.00 15,306.12 Signed 2017-09-03 2017-09-11 2017-10-29 2017-11-13 2018-04-27 Quotations Envelope Sprayer in Horticulture Clusters IN-PMU-RACP-21534-GO-RFQ / Request for Single Stage - One Supply of Battery operated IDA / 50850 Climate Resilient Agriculture Post Limited 15,400.00 9,671.06 Signed 2017-09-03 2017-09-11 2017-10-29 2017-11-13 2018-04-27 Quotations Envelope Sprayer in Horticulture Clusters IN-PMU-RACP-21536-GO-RFB / Single Stage - One Supply of Chaff cutters for Animal IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 350,780.00 153,431.41 Signed 2017-08-01 2017-09-11 2017-08-06 2017-09-08 2017-09-17 2017-10-11 2017-10-17 2017-11-13 2017-11-21 2017-11-22 2018-05-20 Envelope Husbandry Clusters Page 10 IN-PMU-RACP-21540-GO-RFB / Supply and Commissioning of Micro Irrigation Equipment's (Drip/ Sprinkler/Mini-Sprinkler/ Single Stage - One Pipe line/ Automation) at IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 3,872,307.00 0.00 Under Review 2017-08-08 2017-10-06 2017-08-13 2017-10-08 2017-09-24 2017-11-15 2017-10-24 2017-11-28 2018-11-28 Envelope Farmers Field in RACP Clusters Under Closed Framework Agreement(Single Stage, Multi- Supplier). IN-PMU-RACP-21570-GO-RFB / Supply of feed Supplement for Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 209,616.00 0.00 2017-10-03 2017-11-24 2017-10-08 2017-11-24 2017-11-19 2017-12-19 2018-01-23 2018-07-22 Buck & Goats for Animal Envelope Implementation Husbandry Clusters . IN-PMU-RACP-21571-GO-RFB / Supply of Clean Milk Production Single Stage - One Under Kit for Milking Goats & Dairy IDA / 50850 Markets and Value Chains Post Request for Bids Open - National 184,616.00 0.00 2017-10-11 2017-12-12 2017-10-16 2017-12-19 2017-11-27 2017-12-27 2018-01-31 2018-07-30 Envelope Implementation Animals of Animal Husbandry Clusters. IN-PMU-RACP-21580-GO-RFB / Supply and installation of Azolla Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 410,769.00 367,383.99 Signed 2017-09-06 2017-09-11 2017-09-11 2017-09-11 2017-10-23 2017-10-13 2017-11-22 2017-11-15 2017-12-27 2017-11-17 2018-06-25 Unit for Animal Husbandry Envelope Clusters . IN-PMU-RACP-21742-GO-RFB / Single Stage - One Supply of Mini Tractor (up to 20 IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 246,154.00 177,147.65 Signed 2017-11-22 2017-09-25 2017-11-27 2017-09-25 2018-01-08 2017-11-13 2018-02-07 2017-11-22 2018-03-14 2017-12-11 2018-09-10 Envelope HP) for 14 Horticulture clusters IN-HD - RACP-21743-GO-RFQ / Supply of Garlic Showing Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 6,154.00 0.00 2017-09-25 2017-11-20 2018-05-19 Machine in Sangod Cluster of Quotations Envelope Implementation Kota District IN-HD - RACP-21744-GO-RFQ / Supply of Garlic Showing Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 6,154.00 0.00 2017-09-25 2017-11-20 2018-05-19 Machine in Manoharthana Quotations Envelope Implementation Cluster of Jhalawar District IN-HD - RACP-21745-GO-RFQ / Supply of Garlic Showing Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 6,154.00 0.00 2017-09-27 2017-11-22 2018-05-21 Machine in Palyatha Cluster of Quotations Envelope Implementation Baran District IN-HD - RACP-21746-GO-RFQ / Supply of Garlic Showing Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 3,077.00 0.00 2017-09-27 2017-11-22 2018-05-21 Machine in Jakham Cluster of Quotations Envelope Implementation Pratapgarh District IN-PMU-RACP-21747-GO-RFB / Construction of green house and shade net house along with micro irrigation and other related Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,286,154.00 0.00 2017-08-17 2017-10-07 2017-08-22 2017-10-08 2017-10-03 2017-11-14 2017-11-02 2017-12-07 2018-12-07 facilities at Farmers Fields in Envelope Implementation RACP Clusters under Closed Single Stage Multi-Supplier Framework Agreement . IN-PMU-RACP-21748-GO-RFB / Supply and Commissioning of Solar Photovoltaic (SPV) Water Single Stage - One Under Pumping System at Farmer IDA / 50850 Climate Resilient Agriculture Prior Request for Bids Open - National 2,810,770.00 0.00 2017-10-25 2017-09-04 2017-10-30 2017-09-11 2017-12-11 2017-10-23 2018-01-10 2018-02-14 2019-02-14 Envelope Implementation Fields in RACP Clusters under Closed Single Stage Multi- Supplier Framework Agreement IN-HD - RACP-5364-GO-RFQ / Supply of Power Tiller and Power Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 18,400.00 0.00 Canceled 2017-08-22 2017-10-17 2018-04-15 Weeder in Orai-Bassi Cluster of Quotations Envelope Chittorgarh District IN-HD - RACP-5362-GO-RFQ / Request for Single Stage - One Supply of Power Tiller in Gudha IDA / 50850 Climate Resilient Agriculture Post Limited 5,000.00 0.00 Canceled 2017-08-28 2017-10-23 2018-04-21 Quotations Envelope Cluster of Bundi District IN-PMU-RACP-22541-GO-RFB / Farm Mechanization and PHM Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 606,061.00 0.00 2017-09-06 2017-09-14 2017-09-11 2017-09-14 2017-10-23 2017-10-16 2017-11-22 2017-12-27 2018-06-25 Implements for framework Envelope Implementation Agreement . IN-PMU-RACP-22566-GO-RFQ / Request for Single Stage - One Pending Micro nutrient foliar Spray / INM IDA / 50850 Climate Resilient Agriculture Post Limited 48,485.00 0.00 2017-09-04 2017-10-30 2018-04-28 Quotations Envelope Implementation Kits IN-PMU-RACP-22573-GO-RFQ / Request for Single Stage - One Pending Solar Roof top system for Krishi IDA / 50850 Climate Resilient Agriculture Post Limited 45,455.00 0.00 2017-09-25 2017-11-20 2018-05-19 Quotations Envelope Implementation Seva Kendra (KSK) IN-AD - RACP-22608-GO-RFQ / Procurement of Drip cum Water Request for Single Stage - One Pending Storage Tank to Encourage Local IDA / 50850 Climate Resilient Agriculture Post Limited 24,242.00 0.00 2017-09-27 2017-11-22 2018-05-21 Quotations Envelope Implementation Method of Micro Irrigation in Kushalgarh Cluster IN-AD - RACP-5600-GO-RFQ / Technical literature in existing Request for Single Stage - One Pending Krishi Seva Kendra and IDA / 50850 Climate Resilient Agriculture Post Limited 19,300.00 0.00 2017-09-20 2017-11-15 2018-05-14 Quotations Envelope Implementation Agriculture Research Centres in RACP 16 clusters IN-AD - RACP-5598-GO-RFQ / Electronic devices for existing Request for Single Stage - One Pending Krishi Sewa Kendra and IDA / 50850 Climate Resilient Agriculture Post Limited 48,500.00 0.00 2017-08-23 2017-10-18 2018-04-16 Quotations Envelope Implementation Agriculture Research Centres of RACP Clusters IN-AD - RACP-5514-GO-RFQ / Request for Single Stage - One Pending Procurement of Laptop for Dooni- IDA / 50850 Project Management and M&E Post Limited 800.00 0.00 2017-09-17 2017-11-12 2018-05-11 Quotations Envelope Implementation Deoli Cluster of Tonk District Page 11 IN-PMU-RACP-1723-GO-RFQ / Request for Single Stage - One Pending Procurement of Air Conditioners IDA / 50850 Project Management and M&E Post Limited 18,182.00 0.00 2017-07-25 2017-09-19 2018-03-18 Quotations Envelope Implementation for PMU IN-GWD - RACP-22634-GO- RFQ / Supply, Installation, Testing and Commissioning of Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 18,462.00 0.00 2017-09-23 2017-11-18 2018-05-17 Digital complete Weather station Quotations Envelope Implementation at different locations in Pisangan, Bonli & Sangod Clusters. IN-GWD - RACP-22641-GO- RFQ / Supply, Installation and Commissioning of LCD Projector Request for Single Stage - One IDA / 50850 Project Management and M&E Post Limited 1,540.00 691.99 Signed 2017-08-28 2017-10-06 2017-10-23 2017-10-17 2018-04-21 for Conference Hall at SHG & Quotations Envelope Nodal Officer, PIU-RACP, GWD, Jaipur IN-GWD - RACP-22645-GO- Request for Single Stage - One Under RFQ / Supply & Installation of IDA / 50850 Climate Resilient Agriculture Post Limited 1,850.00 0.00 2017-08-28 2017-08-11 2017-10-23 2018-04-21 Quotations Envelope Implementation UV-Visible Spectrophotometer IN-GWD - RACP-22650-GO- Request for Single Stage - One RFQ / Supply & Installation of IDA / 50850 Climate Resilient Agriculture Post Limited 1,540.00 620.40 Signed 2017-08-28 2017-08-11 2017-10-23 2017-09-14 2018-04-21 Quotations Envelope Flame Photometer IN-GWD - RACP-22652-GO- Request for Single Stage - One Pending RFQ / Supply & Installation of Ion IDA / 50850 Climate Resilient Agriculture Post Limited 1,540.00 0.00 2017-08-28 2017-10-23 2018-04-21 Quotations Envelope Implementation Meter IN-GWD - RACP-22655-GO- RFQ / Supply & Installation of Request for Single Stage - One IDA / 50850 Climate Resilient Agriculture Post Limited 615.00 82.77 Signed 2017-08-28 2017-08-11 2017-10-23 2017-09-14 2018-04-21 Digital Electrical Conductivity Quotations Envelope Meter IN-GWD - RACP-22659-GO- Request for Single Stage - One RFQ / Supply & Installation of IDA / 50850 Climate Resilient Agriculture Post Limited 770.00 163.01 Signed 2017-08-28 2017-08-11 2017-10-23 2017-09-14 2018-04-21 Quotations Envelope Digital pH Meter IN-GWD - RACP-22662-GO- Request for Single Stage - One RFQ / Supply & Installation of IDA / 50850 Climate Resilient Agriculture Post Limited 465.00 170.40 Signed 2017-08-28 2017-08-11 2017-10-23 2017-09-14 2018-04-21 Quotations Envelope Nephlometer IN-GWD - RACP-22667-GO- Request for Single Stage - One RFQ / Supply & Installation of IDA / 50850 Climate Resilient Agriculture Post Limited 615.00 524.80 Signed 2017-08-28 2017-10-25 2017-10-23 2017-11-17 2018-04-21 Quotations Envelope Refrigerator IN-RAJUVAS - RACP-5778-GO- DIR / Spot Purchase of Goat and Buck for Sirohi Goat Farm at Chittorgarh. Purchase of 1000 Pending she goats @ Rs. 8000.00 per IDA / 50850 Climate Resilient Agriculture Post Direct Selection Direct 126,517.00 0.00 2017-10-11 2017-10-16 2017-11-20 2018-05-19 Implementation goat and purchase of 35 bucks @Rs. 10000.00 per buck duration purchase is within 12 months. IN-PMU-RACP-22612-GO-RFB / Supply, Installation, Testing and Commissioning of Water Meter Single Stage - One Under IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 461,538.00 0.00 2017-09-26 2017-12-18 2017-10-01 2017-12-19 2017-11-12 2017-12-12 2018-01-16 2018-07-15 at different locations in Pisangan, Envelope Implementation Bonli and Sangod Ground clusters IN-HD - RACP-27392-GO-RFQ / Request for Single Stage - One Pending Supply of Garlic Seed in IDA / 50850 Climate Resilient Agriculture Post Limited 18,470.00 0.00 2017-10-14 2017-12-09 2018-06-07 Quotations Envelope Implementation Palyatha Cluster of Baran District IN-HD - RACP-27393-GO-RFQ / Supply of Garlic Seed in Request for Single Stage - One Pending IDA / 50850 Climate Resilient Agriculture Post Limited 18,470.00 0.00 2017-10-14 2017-12-09 2018-06-07 Manoharthana Cluster of Quotations Envelope Implementation Jhalawar District IN-HD - RACP-27390-GO-RFQ / Request for Single Stage - One Pending Supply of Potato Seed in Bari IDA / 50850 Climate Resilient Agriculture Post Limited 47,000.00 0.00 2017-10-14 2017-12-09 2018-06-07 Quotations Envelope Implementation Cluster of Dholpur District IN-HD - RACP-29469-GO-RFQ / Request for Single Stage - One Pending Procurement of Furniture for PIU IDA / 50850 Project Management and M&E Post Limited 1,550.00 0.00 2017-10-30 2017-12-25 2018-06-23 Quotations Envelope Implementation of Horticulture Department. IN-HD - RACP-30061-GO-RFQ / Request for Single Stage - One Pending Supply of Seed of Pea in Gudha IDA / 50850 Climate Resilient Agriculture Post Limited 8,500.00 0.00 2017-10-10 2017-12-05 2018-06-03 Quotations Envelope Implementation Cluster of Bundi District IN-PMU-RACP-34791-GO-RFQ / Request for Single Stage - One Procurement of Digital SLR IDA / 50850 Project Management and M&E Post Limited 6,200.00 5,781.22 Signed 2017-11-11 2017-11-01 2018-01-06 2017-11-23 2018-07-05 Quotations Envelope Camera and Still Camera. IN-PMU-RACP-21537-GO-RFB / Single Stage - One Supply of Weighing Balance for IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 200,000.00 0.00 Canceled 2017-08-30 2017-09-11 2017-09-04 2017-09-11 2017-10-16 2017-11-15 2017-12-20 2018-06-18 Envelope Animal husbandry Clusters IN-PMU-RACP-35693-GO-RFQ / IP Camera and Network Video Request for Single Stage - One Pending IDA / 50850 Project Management and M&E Post Limited 1,600.00 0.00 2017-11-18 2018-01-13 2018-07-12 Recorder (Closed circuit Quotations Envelope Implementation television CCTV system) IN-PMU-RACP-37167-GO-RFB / Single Stage - One Under Supply of Weighing Balance for IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 200,000.00 0.00 2017-11-30 2017-12-18 2017-12-05 2017-12-26 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Envelope Implementation Weighing of Animals IN-PMU-RACP-37168-GO-RFQ / Request for Single Stage - One Pending Supply of Self Propelled Power IDA / 50850 Climate Resilient Agriculture Post Limited 93,000.00 0.00 2017-11-27 2018-01-22 2018-07-21 Quotations Envelope Implementation Reaper IN-PMU-RACP-37171-GO-RFQ / Request for Single Stage - One Pending Supply of Tractor Mounted IDA / 50850 Climate Resilient Agriculture Post Limited 16,000.00 0.00 2017-11-28 2018-01-23 2018-07-22 Quotations Envelope Implementation Groundnut Digger Page 12 IN-WDSCD-37568-GO-RFQ / Shopping of Office Table Big Size- 1, Office Table Medium Size-2, Request for Single Stage - One Pending IDA / 50850 Project Management and M&E Post Limited 1,531.00 0.00 2017-11-27 2017-12-18 2018-01-17 Almirah-2, Revolving Officer Quotations Envelope Implementation Chairs-1, Visitors Chairs-8, Steel Office Rack-1 for F.Y. 2017-18 IN-AHD - RACP-22492-GO-RFQ Request for Single Stage - One Pending IDA / 50850 Project Management and M&E Post Limited 24,620.00 0.00 2017-10-07 2017-12-02 2018-05-31 / Tablet for LLW Quotations Envelope Implementation IN-DPMU - RACP-40120-GO- RFQ / SUPPLY AND INSTALLATION OF GEO- MEMBRANE SHEETS (AS Request for Single Stage - One Pending POND LINER) IN THE IDA / 50850 Climate Resilient Agriculture Post Limited 40,000.00 0.00 2017-12-30 2018-02-24 2018-08-23 Quotations Envelope Implementation EXCAVATED FARM PONDS ON THE FARMERS' FIELD IN MOKHAMPURA CLUSTER OF RACP IN-PMU-RACP-37166-GO-RFB / Single Stage - One Pending Supply of Power operated Chaff IDA / 50850 Climate Resilient Agriculture Post Request for Bids Open - National 500,000.00 0.00 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 Envelope Implementation Cutter NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-PMU-RACP-1671-CS-QCBS / Engaging Agri Business Quality And Cost- Promotion Facility (ABPF) IDA / 50850 Markets and Value Chains Prior Open - International 1,333,333.00 1,204,943.10 Signed 2016-09-19 2016-09-26 2016-09-19 2016-10-11 2016-09-19 2016-10-19 2016-09-23 2016-11-04 2016-10-05 2016-12-05 2016-10-31 2017-01-02 2016-12-05 2017-01-23 2017-12-05 Based Selection Consultancy firm by PMU under RACP IN-PMU-RACP-1675-CS-QCBS / Hiring of Services of Monitoring Quality And Cost- IDA / 50850 Project Management and M&E Post Open - National 434,167.00 284,965.19 Signed 2016-09-19 2016-06-27 2016-09-19 2016-09-30 2016-11-07 2016-10-30 2016-12-19 2016-11-10 2017-02-13 2016-11-30 2017-02-28 2017-01-04 2017-03-07 2019-03-19 and Evaluation Agency under Based Selection RACP IN-PMU-RACP-1681-CS-CQS / Engaging NGOs for Community Mobilization in RACP 2 Clusters Consultant Farmers Organizations and Under in 2 districts by Project IDA / 50850 Post Qualification Open - National 355,046.00 0.00 2016-09-19 2016-09-23 2016-09-19 2017-06-09 2016-09-19 2016-08-16 2016-09-30 2016-09-22 2016-10-06 2019-04-30 Capacity Building Implementation Management Unit (PMU) - Selection Phoolasar (Bikaner) & Kheruwala (Jaisalmer) IN-PMU-RACP-1694-CS-LCS / Under Hiring of consultancy for Internal IDA / 50850 Project Management and M&E Post Least Cost Selection Open - National 190,822.00 155,561.95 2016-09-19 2016-07-25 2016-09-19 2016-10-20 2016-11-07 2016-11-05 2016-12-05 2016-11-21 2016-12-23 2016-12-21 2017-01-09 2017-01-25 2017-01-27 2020-03-21 Implementation Audit IN-PMU-RACP-1678-CS-QCBS / Consultancy agency for planning and implementation of ground water sub plan in three clusters i.e. Pisangan (Ajmer), Bonli Quality And Cost- Under IDA / 50850 Climate Resilient Agriculture Post Open - National 569,645.91 0.00 2016-09-17 2016-10-13 2016-09-17 2016-09-17 2016-10-14 2016-09-17 2016-12-28 2016-09-17 2016-12-28 2016-09-28 2016-12-29 2016-10-24 2019-04-28 (Swaimadhopur) and Sangod Based Selection Implementation (Kota). Three contract will be signed from single EOI, the value of each contract comes under post review IN-PMU-RACP-1686-CS-CQS / Hiring Services of Market Consultant Resource Agency for IDA / 50850 Markets and Value Chains Post Qualification Open - National 151,515.00 0.00 Canceled 2016-10-30 2016-12-24 2016-11-20 2017-01-03 2017-06-06 2017-02-02 2017-03-09 2019-04-30 Management of Rural Haat Selection activities in clusters IN-PMU-RACP-4308-CS-CQS / Construction consultant for Consultant layout plan, BOQ preparation and IDA / 50850 Markets and Value Chains Post Qualification Open - National 150,000.00 0.00 Canceled 2016-12-30 2017-02-01 2017-01-20 2017-03-05 2017-04-28 2017-04-04 2017-06-13 2017-05-09 2017-11-05 construction monitoring of Rural Selection Haat and RTC IN-PMU-RACP-20570-CS-CQS / Consultant hired for Community Participation, Social Screening and Social Mobilization and Consultant Farmers Organizations and Pending Technical Support Required for IDA / 50850 Post Qualification Open - National 76,430.00 0.00 2017-08-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-12-13 Capacity Building Implementation the Implementation of Cluster Selection Agricultural Competitiveness Plan (CACP) In Sangod cluster of RACP IN-PMU-RACP-20572-CS-CQS / Consultant hired for Community Participation, Social Screening and Social Mobilization and Consultant Farmers Organizations and Pending Technical Support Required for IDA / 50850 Post Qualification Open - National 49,892.00 0.00 2017-08-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-12-13 Capacity Building Implementation the Implementation of Cluster Selection Agricultural Competitiveness Plan (CACP) In Ladnu cluster of RACP IN-PMU-RACP-20571-CS-CQS / Consultant hired for Community Participation, Social Screening and Social Mobilization and Consultant Farmers Organizations and Pending Technical Support Required for IDA / 50850 Post Qualification Open - National 117,184.00 0.00 2017-08-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-12-13 Capacity Building Implementation the Implementation of Cluster Selection Agricultural Competitiveness Plan (CACP) In Orai-Bassi cluster of RACP Page 13 IN-PMU-RACP-20388-CS-CQS / Consultant hired for Community Participation, Social Screening and Social Mobilization and Consultant Farmers Organizations and Pending Technical Support Required for IDA / 50850 Post Qualification Open - National 62,630.00 0.00 2017-08-05 2017-08-26 2017-10-09 2017-11-08 2017-12-13 2018-12-13 Capacity Building Implementation the Implementation of Cluster Selection Agricultural Competitiveness Plan (CACP) In Dooni-Deoli cluster of RACP IN-PMU-RACP-1684-CS-CQS / Consultant Hiring Services of Software IDA / 50850 Project Management and M&E Post Qualification Open - National 98,485.00 0.00 Canceled 2016-10-30 2017-08-01 2016-11-20 2017-01-03 2017-09-25 2017-02-02 2017-03-09 2019-04-30 Providers for Preparation of Selection Management Information System IN-PMU-RACP-20390-CS-QCBS / Selection of Consultant Firm to Quality And Cost- IDA / 50850 Project Management and M&E Post Open - National 799,384.00 0.00 Canceled 2017-07-20 2017-08-01 2017-08-10 2017-09-12 2017-09-23 2017-10-21 2017-11-20 2017-12-25 2018-01-29 2019-01-29 Provide Individual Experts for Based Selection Support Services in RACP INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Climate Resilient Agriculture TL/SSS / Preparation of various Project Management and M&E Thematic Layers of Watershed IDA / 50850 Farmers Organizations and Prior Direct Selection Direct N 0.00 83,462.48 Signed 2015-12-29 Projects Capacity Building Markets and Value Chains Page 14