SFG3101 V2 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra DEPARTMENT OF TOURISM GOVERNMENT OF UTTAR PRADESH NCB Contract Package NO. 02/Agr/Pro-Poor/UPT/W/2016 ENVIRONMENTAL ASSESSMENT REPORT FOR REVITALIZATION OF KACHHPURA AND MEHTAB BAGH AREA, AGRA Project : Uttar Pradesh Pro-Poor Tourism Development Project Owner : DIRECTOR GENERAL TOURISM, Department of Tourism, GoUP 4th Floor, Paryatan Bhawan, C-13, Vipin Khand, Gomti Nagar, Lucknow, UP 226010 1 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra LIST OF ABBREVIATIONS ADA Agra Development Authority ARAP Abbreviated Resettlement Action Plan ASI Archaeological Survey of India CPCB Central Pollution Control Board DoT Department of Tourism DPR Detailed Project Report EIA Environment Impact Assessment EMP Environment Management Plan ESMF Environment and Social Management Framework ESMP Environment and Social Management Plan ESS Environmental and Social Safeguards GoI Government of India GRC Grievance Redress Cell ICSC International Center for Sustainable Cities ICT Information, Communication and Technology INR Indian Rupee NGO Non-Government Organization OBC Other Backward Castes OP Operational Policy PAP Project Affected Persons RAP Resettlement Action Plan SC Scheduled Caste SPCU State Project Coordination Unit ST Scheduled Tribe STP Sewage Treatment Plant TSU Technical Support Units TVC Town Vending Committee UP Uttar Pradesh UPPCB Uttar Pradesh Pollution Control Board 2 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Table of Contents S.No Chapter & Contents Covered Page No A List of Abbreviation 2 B Table of Contents 3 C List of Tables 6 D List of Figures 7 Chapter -1 Introduction 1.0 Project Background 8 1.1 Scope of This Report 9 1.2 About Kachhpura and Mehtab Bagh Sub Project and Its Components 9 1.3 Methodology Adopted for Preparation of Environmental Impact 10 Assessment (EIA) Chapter-2 Project Description 2.0 About the Sub Project 12 2.1 Components Proposed under Sub Project 13 2.2 Construction Material and Sourcing 21 2.3 Sub Project Cost and Implementation Schedule 22 Chapter-3 Polices & Regulation Framework 3.0 Key Indian Policies & Regulations 23 3.1 World Bank Safeguard Policies 29 3.2 Screening & Categorization Of The Project 31 Chapter-4 Description of Environment 4.0 Background 37 4.1 Project Area Setting 37 3 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra S.No Chapter & Contents Covered Page No 4.2. Baseline Status of Project & Influence Area (Agra City) 38 4.2.1 Geographical Location 38 4.2.2 Geology And Soil 39 4.2.3 Drainage 39 4.2.4 Climatic Conditions 39 4.2.5 Demography 42 4.2.6 Water Environment 42 4.2.7 Air Quality 43 Chapter-5 Stakeholders Consultation 5.0 Stakeholder Consultation 45 5.1 45 Objective of Public Consultation 5.2 46 Tools of Public Consultation 5.3 52 Mechanism for Continued Consultations Chapter-6 Anticipated Environmental Impacts 6.0 Background 53 6.1 Impact Identification & Prediction: 57 6.2 Anticipated Environmental Impacts 55 6.3 Mitigation Measures 58 6.4 Anticipated Social Impacts & Mitigation Measures 58 Chapter-7 Environmental Management and Monitoring Plan 7.0 Background 60 4 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra S.No Chapter & Contents Covered Page No 7.1 Environmental Management Plan 60 7.2 Environmental Monitoring 74 7.3 75 Reporting Requirement 7.4 Institutional Arrangement for Safeguards Monitoring 75 7.5 Framework for Monitoring and Evaluation 76 7.6 Grievance Redressal Mechanism 77 7.7 78 Information Disclosure 7.8 78 Capacity Building and Technical Support EMP Budget 80 7.9 82 EMP- Budget for the Implementation of Safeguard Mitigation Measures Chapter-8 Conclusion 86 Annexure-I Guidelines for Construction and Demolition Waste 87 Management & Solid Waste Management (as per Demolition Waste Management Rules, 2016 & Solid Waste Management Rules 2015) 5 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra List of Tables Table No. Title of the Table Page No. Table 3.1 Important National Rules and Regulations that may apply to this 24 Project Table 3.2 Proposed activities require permission prior to implementation of 29 Project Table 3.3 Relevant World Bank Safeguard Policies 31 Table 4.1 Station wise annual Average Air Quality Data of 4 Locations at 43 Agra (Year 2002-2015) Table 5.1 Summary of Stakeholder consultations 46 Table 5.2 Key issues and actions designed 52 Table 6.1 Activity Impact Identification Matrix & Inter-action of Project 54 Activities & Environmental components Table 7.1 Generic Environmental Management Plan: Common to all sub- 59 components of the project Table 7.2 Specific Impacts and Mitigation Measures for the sub-components 65 of the Project Table 7.3 Environmental Monitoring Program 74 Table 7.4 Roles and responsibilities of implementing team 75 Table 7.5 Framework for Monitoring 77 Table 7.6 Capacity Strengthening Plan 79 Table 1 Budget for ESMP implementation 80 6 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra List of Figures Figure No. Title of the Figures Page No. Figure 1.1 Flowchart Describing the Steps Adopted for Preparation of EIA/EMP 11 Figure 2.1 Arial View of Kachhapura, Mehtab Bagh & Taj Mahal 12 Figure 2.2 Location of Kachhapura and Mehtab Bag Area in ASI Protected Zone 12 Figure 2.3 Map showing the different components of the DPR 13 Figure 4.1 Land use of Kachhpura village 37 Figure 4.2 Access to water supply 38 Figure 4.3 Access to toilets in Kachhpura 38 Figure 4.4 Variation in Average Temperature & Precipitation of Agra 40 Figure 4.5 Variation in Average Cloudy Sunny and Precipitation Days of Agra 40 Figure 4.6 Variation in Maximum Temperature of Agra 41 Figure 4.7 Variation in Precipitation Amount of Agra 41 Figure 4.8 Wind Rose Diagram of Agra City 42 Figure 4.9 Air Quality Status at Taj Mahal in April 2016 44 7 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter-1 Introduction 1.0 PROJECT BACKGROUND: Uttar Pradesh – India’s biggest tourist draw, containing some of the country’s most iconic heritage and annually attracting millions of devotees and visitors – remains one of India’s most lagging states. UP is the fourth largest and most populous state with over 199 million inhabitants, and is home to the emblematic Taj Mahal, to the second ancient living city in the world – Varanasi – located on the banks of the sacred Ganges, and two of the world’s four most sacred Buddhist sites Sarnath and Kushinagar, to mention a few of its heritage assets visited and worshipped by millions annually. In 2011, the state attracted 155 million domestic and 1.8 million international visitors out of 748 million domestic and 6.2 million international tourists visiting India, who contributed a total of USD 6 billion to Uttar Pradesh’s economy in the same year. Despite this unique endowment, Uttar Pradesh remains India’s third most lagging state, with a 37.7 poverty rate. Currently, over 50 million people live below the poverty line. The state has one of the lowest per-capita incomes compared to the national average. It also lags behind most Indian states across a number of human development indicators, such as literacy and infant mortality. Specifically in terms of tourism, despite its staggering numbers, the majority of earnings have been captured by airlines, travel agencies and tour operators but poor people in touristic cities often gain very few direct benefits from tourism while bearing many of the costs. UP Pro Poor Tourism Development Project: The envisioned Uttar Pradesh Pro Poor Tourism Development Project with the financial support of World Bank is one of the stepping stone in restructuring its tourism sector in a pro-poor manner with a view to increasing benefits to local communities and improving the management of its tourism destinations. The pro-poor approach adopted by the project also aims at catalyzing the impact of key sectors in a given area, such as accessibility/connectivity, environmental preservation, asset management and business development on local communities. The project will do so by promoting an integrated area-based approach in which tourist destinations and their iconic heritage assets are planned, promoted, served, stewarded and linked geographically. Uttar Pradesh Pro- Poor Development Project focuses on two main regions- Braj-Agra Corridor and the Buddhist Circuit; covering in all 11 destinations of high heritage and tourism significance. Among these, the subproject sites for 1st year has been identified along Braj – Agra corridor namely Agra and Vrindavan (Mathura); as these cities depend heavily on tourism but it has had minimal positive economic impact on the lives of the local communities, especially the poor. Almost half of the city’s population are living in slums and low-income settlements, without access to adequate basic urban and social services or decent housing. Most of these slums/low income settlements are located in the neighbourhood of protected and unprotected monuments and heritage sites. The presence of heritage assets in some of these neighbourhoods within which heritage regulations apply leads to restricted infrastructure development or income gains and services. Poor households within these areas therefore stay disconnected about these heritage assets and do not feel a sense of ownership towards them. The “Revitalization of Kachhpura and Mehtab Bagh, Agra” is one of identified subproject under this project. This report focuses on Environmental Impact Assessment (EIA) associated with this sub project. 8 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra 1.1 SCOPE OF THIS REPORT: Detailed Project Report and Social Management Plan for “Revitalization of Kachhpura and Mehtab Bagh Area, Agra,” has been prepared and approved by the Department of Tourism, GoUP. Therefore, scope of this report is limited to assess environmental impacts of the components proposed under the said project and to determine the specific measures to reduce, mitigate and/or offset potential adverse impacts during pre-construction, construction and operation phases of the project. 1.2 ABOUT SUB PROJECT AREA AND ITS COMPONENT Kachhpura and Mehtab bagh area covered under this sub project are located in the historic city of Agra. Agra is one of the largest cities of Uttar Pradesh State and about 378 kilometres away from the State capital, Lucknow and approx. 206 kilometres from the National Capital New Delhi, India. Kachhpura is geographically located at 27010’N and 78002’E in ward number 17 in Trans Yamuna Area of Agra City and Mehtab Bagh is located near Kachhpura. The sub project sites are well connected with the main city through the Ambedkar bridge. Kachhpura is a historic settlement, about 300-year-old but was listed a slum when it came inside the city boundaries. Because of its location at the city periphery, the area is disconnected from city’s infrastructure and service networks hence inadequate amenities and services exist for residents of Kachhpura and visitors. However, these project sites occupy a strategic location historically as it formed part of the cultural landscape of the Mughal Riverfront in Agra. There are 3 Archaeological Survey of India (ASI) protected Monuments in the sub-project area - Gyarah Sidi, Mehtab Bagh, and Humayun Mosque; surrounded by agricultural fields; partially retaining the historic land use. The proposed sub-project includes revitalization of Kachhpura and approach road to Mehtab Bagh from Ambedkar Bridge; its linkage to the adjoining low-income settlement- Kachhpura. Components Proposed Under The Project: In the Detailed Project Report (DPR) of Revitalization of Kachhpura and Mehtab Bagh Area, following components are proposed: S No. Components Proposed under DPR 1 Mehtab Bagh Visitor Parking Facilities 2 Approach road and side walk to Mehtab Bagh 3 Paving of Pedestrian Access to Kachchpura Through Fields 4 Rehabilitation of 4 Community Chowks 5 Basic Services, Sanitation, Drainage and SWM 6 Consolidation of Village Well 7 Urban Design Guidelines and Signage 9 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra 1.3 METHODOLOGY ADOPTED FOR PREPARATION OF ENVIRONMENTAL IMPACT ASSESSMENT (EIA) Based on the project understanding and in compliance to the Environmental and Social Management Framework of the UP Pro-poor tourism development project, following steps were taken while preparing environmental management plan for Revitalization Of Kachhpura And Mehtab Bagh Area, Agra: I- Reconnaissance survey: Reconnaissance survey was conducted at the project sites of proposed components by the experts to assess the field situation and key issues which need to be addressed in EIA & EMP. II- Project Screening: Screening has been done in the initial stages of project development. The purpose of screening was to screen out “no significant impacts” from those with significant impacts and to get a broad picture of the nature, scale and magnitude of the issues. Screening was done on the basis of Environment and Social Management Framework of the current pro-poor tourism project. III- Review of World Bank Safeguard Policies & Indian Regulations: During preparation of EIA and EMPs World Bank Safeguard Policies and Indian Regulations were taken into consideration to fulfill the regulatory requirements. IV- Data Collection & Analysis: All the available information and data (quantitative, qualitative) regarding the proposed project was collected mainly from the old Project Reports, consultation with stake-holders and other secondary sources including the water/air/noise monitoring reports of Pollution Control Board, City Development Plan, CGWB reports and many others. Based on secondary information, a description and analysis of the sub-project activities along with baseline environmental profile of the project influence has been established. V- Stakeholders Consultation: Stakeholder consultation has been carried out while preparing of EIA and EMP report. As per the procedure, local people and stakeholders were interviewed in groups in formal and informal discussions. The interviewees were asked about their awareness of the project and their response to it and how the project will affect them (during construction phase and after completion phases). The mitigation and rehabilitation plans were discussed, and suggestions for improvement and public grievances if any were asked for. All the associated government departments were also visited to collect the relevant data and to obtain their feedback on the project activities. VI- Identification and Assessment of the Environmental Impacts of sub project activities: Based on the analysis of the data gathered from field survey, stakeholder consultations and secondary sources, issues related to the environmental sectors of the activities were identified. The identified impacts have been compared with the existing baseline environmental condition of the project area. VII- Preparation of Environment Management Plan: Based on the identified environmental issues, the measures suggested in the EMP is to help prevent, minimize, mitigate, or compensate for 10 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra the impacts and improve environmental performance. The EMP provides information on agencies responsible for management measures to be taken at different stages (construction and operational phase) along with an outline of the cost involved for implementation of Environmental Management Plan. The flowchart below (Figure 1.1) describes the steps adopted for preparation of EMP: Reconnaissance Survey & Investigation Collection & Analysis of Data Detailed environmental Profile Brief description & analysis of the sub- Discussion with local population of Project Area project activities and key stakeholders Project Screening Identification and assessment of environmental impacts Development of EIA/EMP Figure 1.1: Flowchart describing the steps adopted for Preparation of EIA/EMP 11 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter - 2 Project Description 2.0 ABOUT THE SUB PROJECT The sub-project covers the historic area around Kachhpura and Mehtab Bagh in the city of Agra. Kachhpura is geographically located at 27010’56”N and 78002’21”E in ward number 17 of Trans Yamuna Area of city of Agra and Mehtab Bagh is situated in its vicinity across the Taj Mahal and River Yamuna. As shown in Fig. 2.1, project sites occupy a strategic location historically as it formed part of the cultural landscape of the Mughal Riverfront in Agra. Revitalization of Kachhpura is a focal point considering the importance of heritage monuments in its vicinity, Humayun Mosque, Mehtab Bagh and Gyarah Sidi and has been included as a major intervention area in the development plan. The site development is centered around the benefits for the community of Kachhpura and the environment. The buffer zones as determined by the regulations of the Archaeological Survey of India for the three protected monuments is summarized and depicted in Fig. 2.2. Fig. 2.1 Arial View of Kachhapura, Mehtab Bagh & Mehtab Bagh and the settlement of Taj Mahal Kachhpura are both intricately connected with the Mughal history of the city of Agra. The cityscape of Mughal Agra was defined by 44 gardens built along the bank of river Yamuna with Mehtab Bagh being part of the larger riverfront scheme. Gardens were the preferred type of residence for Mughals and it was part of their culture (Islamic culture) to lay gardens with water channels running along as it symbolized “Paradise on Earth”. The Mughal gardens were symmetrically designed oasis in hot and dusty environment. In 1526, Babur started remodeling the 12 Figure 2.2: Location of Kachhapura and Mehtab Bag Area in ASI Protected Zone Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra landscape of the city by laying garden on the west bank of river Yamuna, which was carried forward by his successors. His son Humayun is believed to have lived around this area and built the Humayun Mosque in Kachhpura. The villagers of Kachhpura were also closely associated with the construction of the Taj Mahal. Just over a century ago, it was a small cluster outside the city with small huts owned by farmers surrounded by their fields, which now numbers 565 houses; counted physically in the absence of specific census data. These houses and the ancient Humayun Mosque is located approximately 120m away from Mehtab Bagh. Highlighted below is the main scope of work in this sub project:  Revitalization of Kachhpura’s living environment through provision of basic services and enhancement of open and green area and leisure spaces including heritage walk as a traditional village walk.  Enhancing the historic character of the village through guidelines for improvement in housing and modifications in the built environment  Establishment of physical, cultural and social linkages between Kachhpura and the surrounding heritage. Such linkage includes improving the approach road to Mehtab Bagh from Gyarah Sidi and between Mehtab Bagh and Kachhpura  Providing improved tourist services and facilities to the visitors 2.1 COMPONENTS PROPOSED UNDER SUB-PROJECT Following components (as shown in fig 2.3) are proposed under the sub project of Revitalization of Kachhpura and Mehtab Bagh Area, Agra. Figure 2.3: Map showing the different components of the DPR 13 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Components of the Sub Project SUBPROJECT 1: KACHCHPURA AND LINKAGE TO MEHTAB BAGH COMPONENTS COMPONENT 2.1 Visitor Parking and facilities: Integrated parking is proposed on land, which is under possession of ADA. (The land currently has no development and is being used for small farming activities by some villagers). However proposed land is under possession of ADA, and resettlement assistance is considered and will be given (as per mutually agreed measures highlighted in approved ARAP plan).  Total area for parking is 5168.2 sqmt including area of 387 sqmt for landscaping.  Provision for 07 buses  Provision for 62 cars  Provision to park / dock bicycles: and 2 wheelers which includes 16 bicycle and 33 two wheelers  Utility block proposed to accommodate- Guard Room, Male and female toilets, Inquiry / information room, Administration / multipurpose area, Drinking water facility and provision of 3 kiosks (4*3*3 m each) for 3 rehabilitated shops (the three shops which are at the entrance of Mehtab Bagh), two of which will act as small cafeterias (area: 362 sqmt) and 1 as a souvenir shop (the existing livelihood activity)  Total 35 Nos. of Street Lights are required for appropriate lighting in the parking area. 14 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.2 Approach Road and Sidewalk to Mehtab Bagh: A pedestrian walkway on one side of the road starting from proposed parking all the way till Mehtab Bagh is proposed for smooth movement of visitors and traffic as well. One side walkway has been proposed to avoid disruption in current vehicular movement because existing road width varies between 7 to 9 meters. A slightly elevated pathway is proposed (above the existing road) to be made of sandstone with appropriate curbing Pathway is naturally shaded by existing trees in the vicinity and provision for street lights at 30m regular interval is proposed. There are 2 vendors having food stalls on the approach road to Mehtab bagh. These shops will be shifted from Mehtab Bagh to parking premise as per the R&R plan highlighted in approved ARAP. 15 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.3 Paving of Pedestrian access to Kachhpura through fields Proposed DPR intervention aims to revitalize existing streets of Kachhpura with appropriate street surfacing and redevelopment for smooth access to Kachhpura. Access through farm: Access is defined by paving the street with rubber molded paver blocks with adequate lighting. Access route is 5 meter wide and ? meter long with no provision for drains up to the chowk (entrance to the village)  Internal Streets: CC block paving was observed in some of the streets of Kachhpura, however most of the drains are exposed and street edges are broken. Therefore street resurfacing, drain cover and lighting have been proposed considering the situation. Average width of these internal streets is between 2 to 3.5 meters. Internal streets that fall on the route of heritage walk has slight variation in paving pattern where small indicative “arrow shaped pattern” is designed to orient people to walk through Kachhpura 16 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.4 Rehabilitation of 3 community chowks: DPR proposes redevelopment of chowks keeping in mind its current use and connections and dependency of villagers with it. There are total 4 main chowks in Kachhpura, out of which 3 have been undertaken for redevelopment based on their existing use, contextual details and needs. Three chowks are proposed for redevelopment in Kachhpura. All of them are village community chowks and the central space where major village activities take place, depicting the rural and traditional character of the Kachhpura village. These chowks are inclusive of the new Heritage Walk route and depict varied character, as can be observed in the table below. Following components have been proposed for the development of these chowks:  Repaving of chowks with same paving material used for heritage walk route, to integrate with the walk.  Provision of street furniture which is inclusive of both, permanent elements like street light, signage, dustbin, tree seating and temporary elements like swings, keeping in mind the specific character of each chowk (as listed in the table below).  In order to have a visual integration with the chowks another proposed component is coloring of façades of buildings facing the chowks, which will be decided mutually with the household owners. Length Width Area Proposed No. (Meter) (Meter) (sq m) Character 1 13 13 166 Kids play area 20 13 254 Street play (Nukkad 2 Natak) Performance 4 14.4 14.8 196 Mixed activities 17 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.5 Basic services (toilets, sanitation, drainage and SWM): Access to toilet is one of the most critical and prevailing issue of Kachhpura. There are about 565 houses in Kachhpura out of which 378 houses do not have toilet facility. Typical HH toilets for the entire Kachhpura has been proposed in the DPR along with a proposed drainage and sewerage system. Sewerage Treatment Plant (STP) of 350 KL capacity (to be awarded for construction of work to a construction agency, subsequently) is proposed for treatment of sewage to be collected through sewerage system 18 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.6 Consolidation of Village Well and the Surrounding Area Development  Removal of wild vegetation  Leveling of ground around the well  Development of paved open area and grassing  Paving of the area surrounding the well  Installation of benches around the well Well Restoration and Cleaning  An apron of brick on edge to be laid around the well while renovating it (above ground). The restoration will be done using lime mortar and traditional Mughal (Kakaiya) bricks.  Desilting and cleaning is proposed to take out debris and garbage filled in the well.  After restoration, the opening of the well shall be grilled with a lid to prevent any accidents.  The well will act as a natural catchment for rain water harvesting. A wheel (Pulley) has been proposed for easy extraction of water from well. 19 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra COMPONENT 2.7 Urban Design Guidelines for façades, Street furniture, Signage and public spaces in the village and Kachhpura Village Walk Brochure Urban design guidelines are provided to develop a more harmonious development of the village, building upon its existing character. It focuses on the following major aspects mentioned below:  Public spaces  Street Drains  New Development  Façade control 20 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra 2.2 CONSTRUCTION MATERIAL AND SOURCING General construction activities proposed under the sub project require sand and fine aggregates, coarse aggregates, bricks and blocks, ready mix concrete (grade M10, 20, 30), TMT steel, binding wires and cement. Most of the construction material shall be purchased from local sources. However, material such as sand, fine aggregate, bricks and concrete will only be purchased from government approved authorized dealers and vendors. 21 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra 2.3 SUB PROJECT COST & IMPLEMENTATION PERIOD Summary of cost estimates are summarized below: S No. Particulars Amount (Rs.) 1 Mehtab Baug Visitor Parking Facilities 29,272,441.96 2 Approach road and side walk to Mehtab Bagh 16,926,548.01 3 Paving of Pedestrain Access to Kachchpura Through Fields 88,757,795.85 4 Rehabilitation of 4 Community Chowks 7,778,343.09 5 Basic Services, Sanitation, Drainage and SWM 43,064,979.93 6 Consolidation of Village Well 752,764.04 7 Urban Design Guidelines and Signage 2,691,149.53 8 EMP (LS) 3,266,000.00 Taxes and Contingency 36,576,904.26 Total (Rs.) 229,086,926.66 IMPLEMENTATION PERIOD Implementation of the Environmental Management Plan would require three years considering 24 months of project implementation period. The time line is tentative based on the present project conditions 22 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter- 3 Policy and Regulation Framework 3.0 KEY INDIAN POLICIES & REGULATIONS The Government of India procedures on externally aided projects entail that all projects must be prepared and implemented in full compliance with the national legislation, regulations and standards governing protection and management of the cultural and natural heritage of the country, social development, and environmental management frameworks. In line with that, the Environment and Social Management Framework prepared for UP pro poor tourism development project includes the national and state level environmental laws and the operational policies of the World Bank. Specific state and local level standards and regulations also apply to the projects based on their location and nature of the proposed investments and activities. The key environment related legislations that apply to this sub project are summarized below in Table 3.1: 23 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Table 3.1: Important National Rules and Regulations that may apply to this Project Act/ Policy Year Objective Main stipulations Applicability to Responsible the project Agency Cultural Heritage – Government of India Ancient 1958 Declares certain Monuments are “protected” area. Some of the Ministry of Monuments and monuments/sites as being of proposed Culture; Archaeological “national importance”. 100m radius is “prohibited” area – no components of the NMA with Sites and construction or reconstruction can be done. sub project are ASI Stipulates conservation of Remains Repairs and renovation allowed. located within the cultural and historical regulated zones of Act remains found in India. the three ASI 2010 200m radius is “regulated” area (structures protected Amended can be constructed/reconstructed with due monuments and sanctions from the competent authority). would require permission from Protection, maintenance and conservation of National monuments is done by Archaeological Survey Monuments of India (ASI) Authority The Antiquities 1972 To ensure registration of Registration of antiquities/remains/art is Possibly, if any Directorate of and Art antiquarian remains in mandatory. subproject Culture, Govt. of Treasures Act personal possession of involves chance UP. individuals and institutions. find. Tourism 24 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra National Tourism 2002 To increase the number of To focus on welcoming, information provision, Yes. The policy Ministry of Policy domestic and international facilitation, safety, cooperation, infrastructure objectives are in Tourism, Govt. of tourists. To diversify the development, and cleanliness. sync with project India Indian tourism product and objectives. substantially improve the quality of (tourism) infrastructure, marketing, visa arrangements and air- travel. Tourism Policy of 1998 To leverage a diversified Projects must improve and diversify the Yes. The objectives Department of Uttar Pradesh tourism sector for economic tourism product base with a focus on of the policy are in Tourism, Govt. of benefit of local populations. adventure, religion and monument-based sync with project Uttar Pradesh travelers, while economically objectives. benefiting local populations and increasing employment opportunities Environmental Environmental 1986 To protect and improve the Prevention, control, and abatement of Environment MoEF. Govt. of (Protection) Act overall environment. environmental pollution. Gives central (Protection) Act, India; Central government rights to monitor and test for popularly known Pollution Control environmental pollution, and if necessary as EP Act, is an Board; UP State umbrella Pollution Control penalize for infringements. legislation that Board; Central supplements and existing Regional Ground environmental regulations. Water Boards 25 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra The Forest 1927 To check deforestation by If any forest land is proposed to be used for The project doesn’t Forest Conservation Act restricting conversion of nonforest purposes, the user agency needs to pass through any Department, Govt. & Its Amendment forested areas into non- get the clearances under the Forest kind of reserve of UP (for land forested areas. (Conservation) Rules, 1981 forest and doesn’t conversion below The Forest 5 hectare & 40% 1981 involve any (Conservation) density), MoEF, diversion of Rules & Its Regional reserve forest area. Amendment Office and MoEF. Additionally, no protected forest area diversion is involved. Wild Life 1972 To protect wildlife through The Act provides for protection of wild The project does Chief Conservator. (Protection) Act certain of National Parks and animals, birds and plants and related matters. not pass through Wildlife, Wildlife Sanctuaries. The Act contains specific provisions and any wildlife Wing, Forest sanctuary, or falls Department, Govt. chapters on protection of specified plants, within 10km from of UP and sanctuaries and national parks, etc. either side of the National project road from Board For any wild life Wildlife, sanctuary/National Park/ Biosphere Govt. of India Reserve etc. Therefore, no such clearance is required for this project. Water 1974 To control water pollution Provides for the prevention and control of Implementing UPPCB (Prevention and by controlling discharge of water pollution and the maintaining or agency need to Control of pollutants as per the restoring of wholesomeness of water; creates ensure that construction Pollution) Act prescribed standards. Boards and assigns functions and powers for activities do not the prevention and control of water pollution. deteriorate the 26 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra water quality. Air (Prevention 1981 To control air pollution by Act provides for prevention, control and Implementing UPPCB; Transport and Control of controlling emission of air abatement of air pollution and establishment agency need to Department. Pollution) Act pollutants as per the of Boards for planning a comprehensive ensure that construction prescribed standards. program for this task. Collect and disseminate activities do not information relating to air pollution, lay down deteriorate the standards for emission of air pollutants into ambient air quality. the atmosphere from industrial plants, automobiles or other sources. The Noise 2000 To control noise pollution by Rules provides statutory norms to regulate and Implementing UPPCB; Transport Pollution controlling noise at sources. control noise levels to prevent their adverse agency need to Department. (Regulation And effects on human health and psychological ensure that construction Control) Rules wellbeing of the people. Statutory norms to activities do not regulate and control noise levels to prevent deteriorate their adverse effects on human health and ambient noise level psychological wellbeing of the people Solid Waste 2016 To control and management Waste generator shall segregate and store the This act will be Municipal Management of Solid Waste waste generated by them in three separate applicable for the Corporation/body Rules streams namely bio-degradable, non- proposed project. biodegradable and domestic hazardous wastes Applicable in suitable bins and handover segregated provisions of this wastes to authorised waste pickers or waste act are collectors as per the direction or notification summarized in by the local authorities from time to time. Annexure-I. No waste generator shall throw, burn or bury the solid waste generated by him, on streets, open public spaces outside his premises or in the drain or water bodies. All waste generators shall pay such user fee for solid waste management, as specified in the 27 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra bye-laws of the local bodies. Construction 2016 The rules shall apply to Every waste generator shall prima-facie be This act will be Municipal And Demolition every waste resulting from responsible for collection, segregation of applicable for the Corporation/body Waste construction, re-modeling, concrete, soil and others and storage of proposed project. Management repair and demolition of any construction and demolition waste generated, Applicable Rules civil structure of individual as directed or notified by the concerned local provisions of this or organization or authority authority in consonance with these rules. act are who generates construction (b) The generator shall ensure that other waste summarized in and demolition waste such (such as solid waste) does not get mixed with Annexure-I. as building materials, debris, this waste and is stored and disposed rubble. separately. Central Motor 1988 To check vehicular air and Vehicles to be used for construction and other Yes. All vehicles Motor Vehicle Vehicle Act noise pollution. purposes need to meet the standards and used at project Department certificates prescribed as per the Rules, 1989 road should have Central Motor to control noise, pollution, etc. valid ‘Pollution Vehicle Rules and under Control’ 1989 (Amendment) (PUC) Certificates issued as per Central Motor Vehicle Act 28 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab Ba Applicable Legislations and Permission Required: As per the Government of India procedure on externally added projects, its subprojects must also be prepared and implemented in full compliance with national legislation, regulation and standards governing protection and management of cultural and natural heritage of the country, social development and environmental management. Specific state and local level standards and regulations also apply based on the project location and nature of proposed interventions. Pertaining to current subproject, some of the key national legislations and regulations related to environment that may apply for this project are summarized above in Table 3.1 while proposed activities that require permission and authorization prior to implementation of project are summarized in Table 3.2. Table 3.2: Proposed activities require permission prior to implementation of Project Applicable Rules & Responsibility Technical Granting Activity/Permission Regulations Support Authority/Executing Authority Permission for Ancient Monuments State Project Supervision National Monuments renovation/ and Archaeological Coordination Unit Consultant Authority/ construction/ repair Sites and Remains (SPCU) UP Pro- Archaeological in Archaeologically Act, 1958 & as Poor Tourism Survey of India. Protected areas and amended Act 2010. Development its 300 m regulated Project/ Agra zone. Development Authority (ADA). Consent to Establish Water Pollution SPCU / ADA Supervision UP State Pollution and Consent to Prevention & Control Consultant Control Board Operate for Sewage Act 1974. Treatment Plant. Permission under TTZ Notification. SPCU / ADA Supervision TTZ Authority Taj Trapezium Zone Consultant (TTZ). Permission for Traffic Rules & SPCU / ADA Supervision Department of junction Guidelines. Consultant Transport, Agra improvements. 3.1 WORLD BANK SAFEGUARD POLICIES: Safeguard policies are cornerstone of the support to sustainable growth, environment conservation, poverty reduction and shared prosperity. The core objective of these policies is to prevent and mitigate undue harm to people, their environment and cultural assets in the development process. Safeguard policies have often not only increased the effectiveness and development impact of projects and programs supported by the World Bank, but also provided a platform for the participation of stakeholders in project design, and thus have been an important instrument for building ownership among local populations, government agencies and partner organizations. To achieve these ends, client (in this project- UP Tourism Dept.) are required to develop two overarching documents during a given project preparation. These include: | 29 29 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra • An Environmental and Social Management Framework (ESMF), which establishes the overarching standards that the client is to meet throughout the life of the project. • An Environmental and Social Impact Assessment (ESIA), which establishes the specific procedures, management and mitigation measures that the client is to meet for the implementation of each identified subproject and activity to be financed under a project supported by a World Bank loan or credit. The ESIAs and ESMF provide a practical tool for the State Department of Tourism, its partners and associated implementing entities to identify measures to reduce, mitigate and/or offset potential adverse impacts while enhancing positive impacts during the project design and implementation. They also make provisions for the State Department of Tourism, its partners and associated implementing entities to estimate and budget the costs of such measures, as well as providing information on the agencies responsible for addressing such impacts during the project implementation. Finally, given the pro-poor tourism development nature of the project as well as the distinctive features of its target areas, the ESMF and ESIAs will pay specific attention to and provide the State Tourism Department, its partners and associated implementing entities with the principles and guidelines for culturally sensitive and ecologically sound subprojects in the project target areas. Environmental and Social Management Framework: This Environmental and Social Management Framework (ESMF) is a project-level document for the Uttar Pradesh Pro-Poor Tourism Development Project. It is a technical day-to-day guide for the State Department of Tourism and its partners at government, private, civil society and expert levels to identify and address the potential environmental and social and cultural concerns or adverse impacts of the project from the preparation stage to its implementation and post-implementation operation and maintenance. It provides guidance on cultural properties, environmental and social management aspects for the adequate planning, design, execution and operation of the works and investments to be financed under the project, ultimately enhancing the expected positive impacts of the project. The main objectives of the ESMF are to:  Establish clear principles and outline all relevant legislation/regulations for the cultural, environmental and social planning, review, approval, implementation and monitoring of subprojects to be financed under the project  Outline the procedures to be followed in order to comply with the principles, laws and regulations relevant to the project  Specify appropriate roles and responsibilities, and outline the necessary reporting procedures, for managing and monitoring cultural, environmental and social concerns related to subprojects to be financed under the project  Determine the training, capacity building and technical assistance needed to successfully implement the provisions of the ESMF  Establish the project funding required to implement the ESMF requirements Provide practical information resources for implementing the ESMF 30 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Out of the several World Bank safeguard policies which were discussed in the ESMF of UP Pro-poor tourism project, following policies as highlighted in Table 3.3 will be applicable for the implementation of sub-project on Revitalization of Kachhpura and Mehtab Bagh Area, Agra Project: Table 3.3: Relevant World Bank Safeguard Policies World Bank Objective Applicability Safeguard Safeguard Requirements Policies OP 4.01 The objective of this policy The environmental issues will be EIA and/or EMP Environmental is to ensure that Bank addressed adequately in advance. required. Assessment financed projects are An integrated Environmental environmentally sound Screening and Environmental and sustainable. Assessment (EA) with Environmental Management Plan (EMP) will be developed to manage environmental risks and maximize environmental and social benefits wherever it is applicable OP/BP 4.11 This policy aims at This policy may be triggered by Appropriate cultural Physical assisting in the sub-projects where cultural properties Cultural reservation of cultural property, historical, religious and management plan Resources property, historical, unique natural value-this includes shall be prepared as religious and unique remains left by previous human part the EA for the natural value-this includes inhabitants and unique sub-project. In remains left by previous environment features may be addition clearance human inhabitants and affected due to project. from unique Archaeological environment features, as Department as per well as in the protection the regulations of and enhancement of GoI. cultural properties encountered in WB financed project 3.2 SCREENING & CATEGORIZATION OF THE PROJECT oj Screening was carried out to understand the nature, scale and magnitude of environmental and social issues and impacts associated with the proposed sub-project. The screening activity was conducted as per the standard guidelines and format defined in Environment and Social Management Framework (ESMF) of UP Pro Poor Tourism Development Project. Before doing the project screening, review of project components proposed under the DPR, site visit and stakeholder consultations were completed. The detail of screening is summarized below in Form 1 Screening Form-1 Revitalization of Kachhpura and Mehtab Bagh Area, Agra 31 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Uttar Pradesh Pro-Poor Tourism Development Project Screening Note no. 1 Subproject Title: Revitalization of Kachhpura And Mehtab Bagh Area, Agra, India Subproject location (area/district/site): The subproject is located in Ward 17-Kachhpura in the Trans Yamuna Area, on the eastern bank of river Yamuna, in the city of Agra, District Agra. Sub-project scope of work: 1. Mehtab Bagh Visitor Parking and facilities 2. Approach Road and sidewalk to Mehtab Bagh 3. Paving of Pedestrian access to Kachchpura through fields 4. Rehabilitation of 3 community chowks 5. Basic services (toilets, sanitation, drainage and SWM) 6. Consolidation of Village Well 7. Urban design Guidelines for façades, Street furniture, signage etc. 8. Provisional Items Subproject cost: Rs. 22.91 cr Implementing Agency: Agra Development Authority Date of screening: 30th June 2015; Revised 7th November 2016 Responsible agency: ICSC, Ahmedabad & Environmental Consultant, State UP Tourism Dept. S/n. Screening Criteria Assessment of Explanation category ENVIRONMENT 1 Is the subproject in an eco- Yes Sub project is located within the Taj Trapezium sensitive area or adjoining Zone (TTZ) which is a large trapezoid shaped, an eco-sensitive area or defined area of 10,400 Sq. Km around the Taj monument? (Yes/No) If Yes, Mahal. It is a buffer zone designed to protect the which is the area? Elaborate historic monument from pollution. Within the impact accordingly. TTZ, there are over 40 protected monuments. Near the present project site, there are 3 ASI protected monuments- Mehtab Bagh, Humayun Mosque and Gyarah Sidi. As far as distance from the site of construction related activity from protected boundary of the monuments is concerned; proposed parking is 218 meter away from Gyarah Sidhi while proposed households toilets from Humayun Mosque are located in between 100 to 400 meter distance but considering the nature of the project and proposed interventions, it is expected that proposed activities will have very limited impact on environment and no adverse impact on ASI protected monuments. 2 Will the subproject create Limited impact significant/limited/no environmental impacts during the construction stage? 32 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  Clearance of vegetation/ No Only small hedges, shrubs will be cleared to tree-cover/other make way for pathways  Direct discharge of At the time of construction activities, there is construction run-off, limited possibility of temporary flushing away improper storage and Limited of un-managed spoils and construction wastes disposal of excavation during rainfall via storm water drains because spoils, wastes and other project activities are within project area only. construction materials However, all necessary measures will be adversely affecting ensured by implementing agency to avoid any water quality and flow such situation. regimes.  Flooding of adjacent No As there is no disturbance in drainage pattern areas. but to strengthen the drainage and sewerage under proposed project components  Improper storage and Temporary storage of construction and handling of substances Limited masonry materials will not create severe leading to impacts on soil and water. However, during contamination of soil rain materials such as cement, oil, fluids and and water. greases will be required to manage properly to avoid any accident at project site  Elevated noise and dust Limited During construction dust and noise levels may emission. increase temporarily.  Disruption to traffic and Limited During construction activity and supply of raw visitors movements. materials to the construction site, traffic movement may slow down but this will happen occasionally. During construction activities there may be some disruption in visitors movement also.  Damage to existing No damage expected as there is limited infrastructure, public infrastructure existing at site. Proposed project utilities, amenities. will create infrastructure for betterment of tourism and sanitation improvement & livelihood.  Failure to restore May be Construction activities proposed under project temporary construction are confined in defined and limited area. sites. However, SPCU will ensure that contractor will restore temporary construction sites.  Possible conflicts with Limited Some inconvenience to the visitors is expected and/or disruption to at the time of construction activities. However, local community and/or it will be temporary and will be managed visitors. through giving proper access, putting signage and demarcation and zoning of construction activities.  Health risks due to If hygienic conditions are not maintained at unhygienic conditions at may be small labour camp at site, there may be workers’ camps. temporary impacts on health of workers. 33 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  Safety hazards during Limited Possibility of temporary hazards such as construction. injuries and damage to property during the construction phase in case of lack of proper preventive measures  Other, specify. - - 3 Will the subproject create Limited significant/limited/no environmental impacts during the operational stage? (Significant / limited / no impacts)  Flooding of adjacent No There is no disturbance in drainage pattern by areas the project activities  Impacts to water quality Limited In the absence of proper sewerage system, due to effluent discharge presently most of the sewage is directly going into River Yamuna or disposed off on land without any treatment. A STP is proposed to treat the waste-water before discharging on ground or river to avoid water pollution and to improve sanitation conditions in project area. However, proper maintenance and monitoring is required for quality performance of STP.  Gas emissions No -  Safety hazards No - Other, specify- Impact No - on ground water table 4 Does the subproject involve No No such permission is required. any prior clearance from the MOEF or State Forest Department for either the conversion of forest land or for tree-cutting? (Yes/ No). If yes, which? CULTURAL HERITAGE 5 Will the subproject create No significant/limited/no cultural properties impacts?  Involve significant excavations, demolition, movement of earth, flooding or other No There are 3 ASI protected monuments- Mehtab major Bagh, Humayun Mosque and Gyarah Sidi that environmental exist near the project site, but considering the 34 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra damages. Yes nature of the project and proposed  Is located within or interventions, it is expected that proposed in the vicinity of a activities will not have any adverse impact on recognized cultural ASI protected monuments. property conservation area or heritage site. Yes  Is designed to support the management or conservation of a cultural property. Other, specify. 6 Does the subproject involve Yes Grant of permission/ NOC will be required from any prior clearance from the National Monuments Authority/ASI for MoC or State Archeology construction of parking and proposed Department for either the households toilets. conservation or Application and project details have already management of heritage been submitted to concerned agency for NOC sites or vicinities? (Yes/ No). and grant of permission. If yes, which? SOCIAL 7 Will the subproject create Limited significant/limited/no social As per social impact assessment 7 impacts? households (49 project affected  Involuntary land taking persons) will be affected by the resulting in loss of project. These families shall be income; livelihood; Yes rehabilitated and resettled as per sources of livelihood; measures highlighted in the approved loss of access to ARAP common property resources and / or private residential and/or commercial property. No  Land acquisition resulting in relocation of households. No  Any loss / reduction of access to traditional dependent communities (to areas where they No earn for their primary or substantial livelihood).  Adverse impacts to women, including economic and safety 35 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra concerns.  Other, specify. OVERALL ASSESSMENT □ Subproject is declined NA □ Subproject is accepted Yes □ Subproject is classified as environmental Category A and NA requires an in-depth Environmental and Social Impact Assessment and an Environmental Management Plan. □ Subproject is classified as environmental Category B and Yes. Environment & Social requires an Environmental Management Plan. Management Plan will be prepared. □ Subproject is classified as environmental Category C and NA does not require an Environmental Management Plan. Outcome of Screening & Project Categorization: Project screening was carried out as per the screening form described in Environment and Social Management Framework of UP pro-poor tourism development project. As per the outcome of the screening form for the project Revitalization of Kachhpura and Mehtab Bagh Area, Agra, it is classified as a Category B Project as it would have only limited impact on the environment. As per World Bank safeguard policies , Category B project needs to prepare an Environment Management Plan to minimize and mitigate the impacts on the environment. 36 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter - 4 Description of Environment 4.0 BACKGROUND The baseline environmental data has been collected to determine the existing status of various environmental attributes viz., climate and atmospheric conditions, air, water, noise, soil, hydro geological, ecological and socio-economic environment, prior to proposing the sub project. This study would help to undertake corrective mitigation measures for protection of the environment on account of any change of attributes due to activities of the proposed project. The baseline data of environment includes inventorization of physical, chemical, and biological parameters. This section deals with the description of existing environmental setting in the project area. A. Project Area B. Influence Area 4.1 PROJECT AREA SETTING Kachhpura and Mehtab Bagh area is situated in the historic city of Agra in Uttar Pradesh. The settlement of Kachhpura is historic and about 300 year-old. Kachhpura was listed as a slum when it became part of the city municipal area. The area is disconnected from city’s service networks because of its location at the periphery resulting in lack of infrastructure and services for visitors and residents. Therefore, focus of this sub project ‘Revitalization of Kachhpura And Mehtab Bagh Area, Agra’ is to provide basic amenities, services and connectivity in the project area to enhance the tourist footfall, conserve social and cultural heritage and improve the quality of life of the residents of Kachhpura. Physical Settings & Land Use around the project site included in the sub project 4.1.1 Land use of Kachhpura The figure 4.1 represents the existing land use of the village. Majority of the land use in the area is under residential. Some of the households are involved in the shoe making businesses. Open spaces are very limited, wherein the children play and there is lack of basic services in the village area. 37 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Figure 4.1: Land use of Kachhpura village 4.1.2 Infrastructure of Kachhpura A- Water Supply 70% of the households are supplied with municipal water supply in the Kachhpura village as shown in fig. 4.2. Remaining 30% of the households depend on other sources like hand pumps and community stand posts, of which 23% of the households depend on the hand pumps for daily water needs. B- Solid waste management Figure 4.2: Access to water supply Solid waste collection is not regularly done for Kachhpura. The corporation collects the waste every 15-20 days from major dumping areas in the villages. Most of the time the waste is burnt in the open showing the poor solid waste management systems in Kachhpura. C-Access to toilets In Kacchpura, access to toilets is a major issue for residents, as almost 61% of the households do not have toilets. Only 28% of the community has access to toilets, and the existing sewage treatment is in the form of septic tanks and soaks pits. 5% of the toilets are infact without septic tanks. Existing situation of toilets in Kachhpura is shown in Fig. 4.3. Figure 4.3: Access to toilets in Kachhpura 4.2 BASELINE STATUS OF PROJECT & INFLUENCE AREA (Agra City): Agra city is of historic importance and was the capital seat of Mughals in ancient times. The primary heritage of the city is linked with the Mughal dynasty but other rulers also contributed in its development. Agra was founded by Sikandar Lodi in the 16th century. Emperor Babur was the one who introduced the concept of square Persian-styled gardens in India; Emperor Akbar built the Agra Fort while Emperor Jehangir developed some of the beautiful gardens and palaces. The city is in proud possession of “Taj Mahal” considered widely as one of the Seven Wonders of the World, and which has been declared as a World Heritage Site. The post- Mughal era of Agra saw the 38 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra rule of Jats, Marathas and finally the British taking over the city. In addition to its historic importance, Agra is a center of political, economic, commercial and cultural activities in the state of UP. 4.2.1 GEOGRAPHICAL LOCATION: Agra city is situated on the western bank of river Yamuna in the state of Uttar Pradesh and can be accessed by the National Highway (NH- 2) and is about 200 Kms from Delhi. Agra is geographically located at 27°12' North latitude and 78°12' East longitude. It has an extremely strategic location at the confluence of three distinct geo-physical regions namely the plains of Uttar Pradesh, the plateau of Madhya Pradesh and the desert of Rajasthan. The city also falls within the center of the four- culture rich areas - Braj, Bundelkhand, Rajputana and western UP. 4.2.2 GEOLOGY AND SOIL: The soil of Agra is loose, sandy and calcareous. The river Yamuna flows through the metropolitan city of Agra. The river enters the city on its northern boundary and takes a U-shape while crossing through the heart of the city. The area is characterized by alluvium, which is an admixture of gravel, sand, silt and clay in various proportions, deposited during the Quaternary period. The study area is a part of Indo-Gangetic alluvium of quaternary age and is made up of recent unconsolidated fluviatile formations comprising sand, silt, clay and grit (kankar) with occasional beds of gravel. There are some underground rocks of quartzite and sand stone of Vindhyan-series in the west and south west of Agra. The topsoil is coarse and angular sand with small clay fraction. The sub-soil is sandy throughout. The stabilized topsoil is reddish brown with sand and clay mixed. Minimum depth of topsoil layer is 60 cm. Sand and silt is slightly alkaline to saline in nature. The topography of the area is flat. Saline soils are generally brown. Alkaline soils are grey and get sticky on wetting and hard on drying, acquiring a clotted structure. 4.2.3 DRAINAGE: River Yamuna forms the major drainage of the city and it flows from North to South-East of the city. There are about 13 unlined and 6 lined drains flowing across the city area. These drains were formerly natural water drainage. Now they serve as sewage disposal drains falling into river Yamuna. 4.2.4 CLIMATIC CONDITIONS: The study area is characterized by semi-arid area bounded by Thar Desert on its southwest, west and northwest peripheries. The maximum temperature goes upto 47°C in summer months (May to June) and minimum temperature falls to a low of 3°C in winters. The average rainfall in the region is 685 mm. The city experiences extreme hot summers and extreme cold winter. The climate of the city experiences a typical extreme climate as of the plains of Uttar Pradesh. All seasonal climatic changes e.g. temperature; rainfall, wind-pattern etc. are observed throughout the year, particularly high temperature during the summer, cold weather during winters and sufficient rains in the monsoon. Apart from above climate data, detailed climatic condition of Agra City has been presented in the form of figures that are produced from a weather model Meteoblue which has compiled global historical weather data from 1985 onwards and generated a continuous 30-year global history with hourly weather data. 39 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra In Figure 4.4 "mean daily maximum" (solid red line) shows the maximum temperature of an average day for every month in Agra. Likewise, "mean daily minimum" (solid blue line) shows the average minimum temperature. Hot days and cold nights (dashed red and blue lines) show the average of the hottest day and coldest night of each month of the last 30 years. Figure 4.4: Variation in Average Temperature & Precipitation of Agra Figure 4.5: Variation in Average Cloudy Sunny and Precipitation Days of Agra 40 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Figure 4.5 shows the monthly number of sunny, partly cloudy, overcast and precipitation days. Days with less than 20% cloud cover are considered as sunny, with 20-80% cloud cover as partly cloudy and with more than 80% as overcast. Figure 4.6: Variation in Maximum Temperature of Agra Figure 4.6 shows; the maximum temperature diagram for Agra which displays how many days per month reach certain temperature while Figure 4.7 shows the variation in precipitation amount in Agra City. Figure 4.7: Variation in Precipitation Amount of Agra 41 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Figure 4.8: Wind Rose Diagram of Agra City A "wind rose" diagram is the most common way of displaying wind data, and can be measured in a “speed distribution” or a “frequency distribution. Figure 4.8 represents the wind rose diagram of Agra city that indicates wind blows from NW and NE direction of Agra City. 4.2.5 DEMOGRAPHY: According to the 2011 India census, Agra city has a population of 1,585,704, while the population of Agra cantonment is 53,053. The urban agglomeration of Agra has a population of 1,760,285. Males constitute 53% of the population and females 47%. Agra city has an average literacy rate of 73.11%, lower than the national average of 74%. Literacy rate of males is considerably higher than that of women. The sex ratio in the city was 875 females per thousand males while child sex ratio stood at 857. Agra district literacy rate is 62.56%. 4.2.6 WATER ENVIRONMENT: Groundwater The groundwater in unconfined conditions rests at 1 m below ground level to a maximum of 29.4 m below ground level. In general deeper water level remains within 19.20 m below ground level. Groundwater through boreholes can be accessed at depths of 4.57 to 27.60 m below ground level. In pre-monsoon the water level ranges from 4.89 to 12.3 m below ground level. While in the post- monsoon depth of water level varies between 2.24 m to 17.82 m below ground level. Most of the wells in Agra have saline water except immediately after the monsoon. According to the Agra Jal 42 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Sansthan, 4298 hand pumps are in operation in the town. As per the studies carried out by the University of Roorkee under the Agra Heritage Project, the Agra Heritage area has large groundwater potential. (Source: CGWB , CPCB,2007) Ground Water Quality Issue: High concentration of nitrate, fluoride, total hardness, chloride, TDS, calcium, sulphate, potassium, magnesium, conductivity and Coliform organisms, whereas concentration of micro-pollutants such as toxic (heavy) metals Fe, Mn, and Cu were exceeding the permissible limit for drinking water during pre and post-monsoon seasons and also pesticides such as α-BHC, Endosulphan and Methoxychlor were detected in some of the observations of Central Pollution Control Board. 4.2.7 AIR QUALITY: Air quality data monitored Table 4.1: Station wise Annual Average Air Quality Data of 4 Locations at Agra (Year 2002-2015) by CPCB, Agra Office from (Source: CPCB 2015) 2002 to 2015 indicates that annual average concentration levels of different pollutants at Taj Mahal Site which is nearest to the project location are in the range as, SO2: 4-9 μg/m3, NO2: 15-23 μg/m3, PM: 133- 178 μg/m3 and SPM: 276- 376 μg/m3. SO2 and NO2 levels are below the applicable annual average CPCB Standard value of 20 μg/m3 and 30 μg/m3 for the sensitive area category. However, PM and SPM concentration are always found beyond the standard limits. Station wise annual Average Air Quality Data of 4 Locations at Agra (Year 2002-2015) are summarized in Table 4.1. 43 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Air Quality Status at Taj Mahal in April 2016 Air Quality Status at Taj Mahal Site (monitored by Central Pollution Control Board) in April 2016 indicates that RSPM and SPM concentration varied in between 183-236 μg/m3 and 373-487 μg/m3 respectively which were recorded higher to the National Ambient Air Quality standards for sensitive area. Project sites are located at down wind direction as wind rose data indicates that mostly, wind blows from North West and North East direction hence dispersion of Air Pollutants if any, generated during construction and operational phase will not be in the direction of Taj Mahal located at North East direction of the city. 35 600 Air Quality Status at Taj Mahal in April 2016 30 29 28 500 487 467 25 403 400 373 microgram/m3 19 microgram/m3 20 300 15 12 236 236 218 200 10 183 4 4 4 100 5 BDL 0 0 02.04.16 09.04.16 21.04.16 28.04.16 Avg. Concentration (microgram/m3) SO2 Avg. Concentration (microgram/m3) NO2 Avg. Concentration (microgram/m3) RSPM Avg. Concentration (microgram/m3) SPM (Source: CPCB 2016) 44 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter – 5 Stakeholders Consultation 5.0 STAKEHOLDER CONSULTATION Consultation is a process in the project cycle in which an attempt is made to involve the public as stakeholders in project preparation through consultations and focus group discussion meetings. Stakeholder’s participation and consultation have been viewed as a continual course of action, which promote public understanding and help eradicate hurdles in the way of the project. Consultation during project preparation is an integral part of the environmental and social assessment process that not only minimizes the risks but also removes the gap between the community and the project formulators, which leads to timely completion of the project and making it people friendly. Public consultations and community participation was an integral part of this project preparation. Consultation sessions were carried out with different stakeholder groups at the local, regional and district levels, so as to incorporate their concerns and needs To ensure the effectiveness of the consultations and the full participation of all stakeholders in the project, all relevant information was shared with stakeholders in a timely manner prior to the consultation and in a form and language that could be understood and accessed by all groups. Consultations with these groups were carried out on two occasions: a. Shortly after environmental and social screening; and b. Once after draft ESMP was prepared. Such groups were also consulted throughout project implementation as necessary to address ESMP related issues relevant to them, allowing relevant stakeholders the opportunity to share their concerns during both the implementation phases of the project. 5.1 OBJECTIVE OF PUBLIC CONSULTATIONS Keeping in mind the objective of minimizing adverse impact and the need of the stakeholders’ participation for the smooth implementation of the project, consultation with the members of different sections of society and local communities of the project area were carried out. The consultation with people was done with the aim of building awareness among them. The type of consultations undertaken are individual interviews, field level observations, community consultations and meetings. The main objectives of undertaking these consultations are as stated below:  Dissemination of information to build awareness among stakeholders and inform them about the objective of the project  To inform stakeholders about the adverse and positive impacts of the project  To inform stakeholders about the design aspects  Discuss about the training requirements to enhance their skills & livelihood options The primary and secondary stakeholders included (i) community having their shops & residence in the project area, (ii) Street vendors, (iii) visitors, and (iv)project officials. These consultations 45 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra provided inputs on environmental and social issues and in identification of the needs of the communities. In deciding the target groups for consultation, all sections of stakeholders viz. visitors, govt. officials, vendors, residents, private tourist agents, parking contractor and NGOs etc. were considered. These consultations provided inputs on social issues and in identification of the felt needs of the communities. Consultations were conducted with two major objectives: a. Identifying specific issues related to the project b. Ensuring participation of people in project activities 5.2 TOOLS APPLIED OF PUBLIC CONSULTATION & ITS OUTCOMES Different tools were employed in interviews conducted and discussions ranged from informal and undirected to formal and directed. Focus Group Discussions, Interviews and Public Consultations were the three tools largely used; the latter being the most important of them. The entire process of public consultation was completed through a series of actions starting from giving out a public information notice in the newspapers and culminating in acquiring feedback from the participants. Focus Group Discussion Public consultation is a continual process. In order to document the issues raised by the people potentially affected, Focus Group Discussions were conducted with the identified groups. This gave an opportunity for some of the affected people to express their views about the proposed project. Interviews A series of questionnaire-based interviews were also conducted to elicit public response to some specific questions regarding the perception of the public about the project as well as their willingness for partnership in the implementation of the same. Simultaneously with the filling of the interview schedules, people were engaged in informal, unstructured discussion about the general objective and design of the project. At every consultation meeting, women were encouraged to participate and their views and opinions were heard. Table 5.1 below presents the discussions held during the consultations with all stakeholder groups: Table 5.1: Summary of Stakeholder consultations S.No STAKEHOLDERS KEY DISCUSSION POINTS 1  He is a young boy from Kachhpura who earns his living by taking tourist on camel ride along road from Mehtab Bagh to the riverfront. He charges Rs. 200 for a round  He has learnt English on his own picking up while talking to tourist. Camel Cart Rider, Mehtab  As the riverfront is barbed now, there is not much scope of camel ride left. Bagh  He gets tourist mostly in winters, but there are not much 46 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra livelihood opportunities so he waits if he can get some client for ride during all season.  The camel cart owner thinks that if the area is developed he would get more tourists and the project would indirectly improve his income. 2 Vendors selling souvenirs  Sell small souvenirs like key chains, magnets etc. They belong to at Mehtab Bagh Kachhpura and keep roaming around Mehtab Bagh to get some buyers.  Earn more in winter when it’s the tourist season; though the escorts/guides that come with the group of tourist do-not let the tourist buy from them. They take them to shops which give them commission  Feel there are no good livelihood opportunities for them linked to tourism in the area.  They are also hopeful that if the area is developed there would be more opportunities for them to link with the project and improve their livelihood opportunities. 3  2 women from Kachhpura work as laborer in the Mehtab Bagh, earning Rs. 5000 per month working from 9am - 5pm.  They do not have toilets in their houses and go in the field for open defecation early morning or late night.  They strongly feel that the infrastructure should be improved in the village.  They feel positive about the project. They feel it would improve the quality of life for them by providing access to toilets.  They feel it is also important for their safety and confidence. Women Gardeners in Mehtab Bagh 4 Skill based group-  About 80% of the households in Kachhpura are involved in Shoemakers in making shoes; they are the people who belong to the Jatav Kachhpura community.  They work on piece-meal rate and make shoe uppers. All the raw material is provided by the contractor. They earn Rs. 24 per pair of uppers and make about 20-22 pairs daily.  They do not get any benefit from the tourism in the area. The tourist who come to see the village as part of the Heritage walk, sometime interact with them but they do not get benefited from it in anyway.  They would be keen that visitors come to their house, see and understand the overall process of making shoe in Agra and also buy shoe at a very reasonable price if they like. Chandan Singh one of the shoe makers in Kachhpura showed the shoe making process in his house and is willing to open his house to visitors.  The villagers are very positive of the project and they think through the project they would have increase in tourist footfalls and the shoe making process can become part of the package of tourist experience. 47 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra 5  They have been farming in the lands adjoining Mehtab Bagh since several years. They say that it is their land on which they do farming, though they do-not have any documents to prove the ownership of the land.  They use the water from the Kachhpura Drain for farming.  As they do not have household toilets they use their agriculture fields for defecation.  The farmers mentioned that there is a road that is coming up connecting Chowk (Garhi Chandni) settlement to Kachhpura and the entire agricultural field would be taken up by the government. The government would not give any compensation Farmers In Kachhpura to people who do not have any documents showing the ownership of land.  The farmers also said that their land might be taken up as a part of this project. But given a fair compensation they do not mind giving the land. However, none of the farmers have documents of land ownership. 6  Consultation with kids of Kachhpura highlighted that the community does not have any park or green space in the vicinity where kids can play and visit at any given time.  Gyarah Sidi area is one of the meeting points where several community activities, gatherings and festival celebrations take place. Kids from Kachhpura 7 Heritage Walk Animator The team of MHWE comprises of two walk animators and 6 committee members. The heritage walk was developed by an NGO- Center for Urban and Regional Excellence as a community based tourism product with the aim to highlight the lesser known monuments of Agra; improve the living environment of Kachhpura and provide sustainable livelihood opportunities for youth and women of Kachhpura. The walk is 1.5 km long, which takes about 1-1.5 hrs, starting from Gyara Sidi. It includes 3 ASI monuments, walk through Kachhpura settlement, and visit to the tea terrace along with a box of souvenir. The Walk is managed by 2 youth from Kachhpura- trained as Walk animators along with the support of CURE. The animators are employees of CURE and other associated with the walk are paid per walk basis. There is a separate account of the Heritage Walk, where all the money gets deposited of which the signing authority is one of the animator and one employee from CURE. The money which gets collected from the walk is used in running cost incurred in the walk, maintenance of DEWATS in Kachhpura, rent of the resource centre, etc. The financial control of the walk money lies with CURE.  They have been conducting the heritage walk since 2007 and initially not many people used to come but in last few years it has picked up. In the last year about 850 visitors became part of the walk. The walk costs Rs. 750 for non-Indian and Rs. 500 for Indian citizens. 48 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  System of booking: About 20-22 local tour operators are associated with the walk, they project heritage walk as one of the products to their guests and put it in their itinerary, if they want and would be staying for 2-3 days in Agra. The bookings are made through mail/phone to the tour animator or to one of the employees of CURE. Components to upgrade Kachhpura:  Education of children of Kachhpura is an important component. Other important things are individual household toilets. About 50% of Kachhpura does not have toilet and defecate in the open. As the household size is quite large in Kachhpura (8-10 persons), even for the houses which have toilets, the residents go out in the fields to defecate in the morning as one toilet is not sufficient to cater to all people in the household. Enhancement of the walk:  The walk can be enhanced by adding more activities to the walk which will attract tourists - farm visits, camel safari, live shoe making experience etc. The girls of Kachhpura could be further trained for making souvenirs. More community members should be linked with the walk, this will enhance the walk as well and will help more community members to improve their livelihood options while being linked to it. There should be a booking counter for the walk in Kachhpura, so a lot of tourist who come to Mehtab Bagh can experience the walk. There should be a toilet facility for tourists who come for the walk. Kachhpura has become a settlement for movie/TV program shooting and has lot of potential for photo opportunity. 8 Vendors at Mehtab Bagh-  There are 3 vendors with temporary shops selling beverages, Sabid Ali Abbas, Manjoo foodstuff and souvenir catering to the tourist. All the 3 shops Ali Abbas, Said Ali Abbas are of the same family who owns the adjoining agriculture land.  These shops are their main source of livelihood, and all the family members support in this work, they earn sufficient to live from these shacks. Farming is secondary occupation, whatever they produce (wheat, bajra, some vegetables) is only sufficient for the family itself. They do not sell it in the market.  ASI does not allow them to build any temporary kiosks like the ticket counter at Mehtab Bagh, so they have temporary shacks made of bamboo and thatch. They spend Rs. 10,000 yearly on the roof and canvas sheet of the shack. They have the insecurity of being moved from the location any time, if any development happens.  There is no provision of water for the vendors; they get it from their house in Kachhpura. Neither is there any public toilet facility or power supply. For SWM, they have individually kept a small dustbin in their shacks, which the ANN sweeper collects it on a daily basis.  The area is safe at night due to PAC and Patrolling.  They are willing to move, out of 100 mts of Mehtab Bagh if they get permanent kiosks and they do not want others to get kiosks as that will affect their livelihood/income. 9 Travel Agency Operators  Kachhpura offers great views of Taj and therefore many visitors like to take the heritage walk  There is a need to develop more activities for tourist attraction 49 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra that can engage domestic and foreign visitors to Kachhpura  Poor infrastructure and Visitor Amenities is a major drawback of Kachhpura  Provision of infrastructure in Kacchpura would help improve the tourist visitation at the site. 10 Women of the village  Lack of Livelihood opportunities  Limited opportunity linked with the Heritage Walk  Immediate need of individual toilets / even community toilets  Need for skill development programs for youth (men and women)  The women’s group strongly wants access to toilets and they are happy that the overall infrastructure of Kacchpura would be improved as a result of the project. 11 Self -Help Group:  Primary activities carried out by the SHG- maternity benefits, Women, girls and youth generating awareness regarding vaccination, sanitation, use of of Kachhpura dustbins.  Savings of Rs 100 per month. With rate of interest @2% loans are given for education, maternity needs etc. (Not for marriage).  Toilets: 50% of the houses are having toilet facility with septic tank. However remaining need to construct toilets  The remaining households use the fields for open defecation. There are big problems of lack of privacy, insects and infections. They are keen to receive some government schemes as support for toilet construction. ASI has not given permission to build household toilets to some of the residents.  Water supply: drinking water is accessed via bottled commercial RO water from Gautam Nagar. Very expensive at Rs 5 or 10 per bottle. There is a hand pump, and some of the houses have Municipal water supply connections. Involvement in tourism activities-  There was a women group (11 members), which was formed under Cross-cutting Agra Programme making bags to be supplied to few hotels in Agra. It used to provide some employment to the women but in the last one year the group has not been functional and there has been no orders.  There is a girls group (5 members), which is part of the Heritage walk. They welcome the guest of heritage walk and show souvenir at the Centre in the courtyard during the walks. They are paid per walk basis- Rs. 25.The girls and women feel that they have the skills but do not have the market to sell the products.  The women and the girls group feel very positive about the project. They feel that the infrastructure would improve their quality of life. Especially access to toilets would improve their privacy and will have positive impacts on health. 12 Kachhpura Panchayat Kachhpura has a village panchayat, which is a social governing body 50 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Head- Kishan Singh and for the village. There are 5 main members in the committee, which his son- Hari Babu has been there since long. Though the panchayat does not have funds and the power to sort out social issues in the village but they provide help through contributions for small community works through collection of funds from residents-eg. Repairs of hand pumps, support in marriages etc.  The main problem of Kachhpura is open defecation; household toilets should be built. About 50% toilets were built with partial support of CURE and ANN under its programme- Cross-cutting Agra programme but now there are remaining households that need to build toilets. Also the toilets were mostly built in new aabadi; most houses in old aabadi do not have toilets.  About 20-25 families are farmers and have land, which was given on lease to them for farming. They are dependent on these lands for food for their families- whatever they cultivate is consumed by their families. The administration is keen to get them vacated. They are willing to give their land if they get compensation of the land based on the circle rate and one member from the family gets a government job.  Kachhpura is safe for tourist and the people behave nicely with tourist who come to see their settlement. Holi is celebrated in the chowk  The panchayat is keen about the project. They feel that public spaces and infrastructure which are part of the project will improve the living conditions in the village. 13 Men group in Kachhpura-  Water supply- a government submersible with an overhead Lakhan Singh, Dharam tank should be installed in the courtyard for the people. The Singh, Chandan, Praveen, municipal water is unfit for drinking. Most houses are Ajay, Maharaj Singh, Raju, dependent on the hand pump for cooking and drinking AshokSagar. purposes. Only 10% houses use RO water for drinking.  Household toilets need to be built in Kachhpura, otherwise the road connecting Kachhpura to MehtabBagh is being used for open defecation. The community toilet is non-functional now which can be renovated enabling for use by some residents also. They are willing to maintain it and pay a monthly fee too for using it.  The toilet in the school which was built under the Crosscutting Agra Programme remains locked; as a result the children go out to defecate.  The access road to Kachhpura from the other side (Nagla Devjeet side) should be constructed. The road connecting Kachhpura to Mehtab Bagh is actually a rear entry to the village, so nobody uses that route and is longer too. SUMMARY OF ISSUES RAISED AND ACTIONS DESIGNED Table 5.2 below presents the summary of key issues raised and the actions designed in this ESMP and the plan to mitigate any social impact as a result of the implementation of the proposed interventions. 51 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Table 2.2: Key issues and actions designed Sr. No. Key Issues Actions Designed 1 Provision of Basic Services in Basic Service Provision is an integral part of the Kachhpura intervention. The villagers would be important stakeholders in the implementation and monitoring of the interventions. 2 Involvement of Women and Capacity Building and training of youth and women Youth in Tourism Sector groups for heritage walks, souvenir making etc. 3 Loss of livelihood for some Compensation for loss of livelihood has been covered farmers as a part of this ARAP. The loss of livelihood would be compensated and rehabilitated. They would also have a representation in the monitoring of the interventions. 4 Loss of livelihood and shops of The vendors losing livelihood are covered in the three vendors at Mehtab Bagh ARAP. The vendors would be compensated and kiosks would be given to each of these vendors in the ADA parking. 5.3 MECHANISM FOR CONTINUED CONSULTATIONS The consultation will be continued in the implementation stage. Several additional rounds of consultations with the stakeholders will be done through Local Representatives involvement during project implementation. The following set of activities will be pursued for effective implementation of project:  Involvement of women and other vulnerable groups during the project implementation process to ensure their participation and addressal of their needs.  The Local Representatives involved in the implementation of project will organize Public meetings, and appraise the communities about the progress in the implementation of project works.  Involve community in project progress monitoring. 52 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter -6 Anticipated Environmental Impacts 6.0 BACKGROUND This section of the chapter will identify and discuss both positive and negative impacts associated with the proposed project components. The assessment would be done for nature, type and magnitude of the potential impacts likely to be caused by various project activities which may affect various environmental components. A wide variety of direct and indirect positive and negative impacts have been identified. It is found that the project will improve the bio-physical and socio- economic environment components, if proper mitigation measures are adopted in the design, construction and operation phases of proposed Project. 6.1 IMPACT IDENTIFICATION & PREDICTION: The general impacts will be assessed from base line information and primary data collected during survey and investigation. The possible impacts at various stages of the project such as prior initiation, during implementation and post project period will be assessed and mitigation measures will be suggested. The following elements are proposed to be analyzed:  Natural Environment - Topography (Soil, forests & Land-use/Landscape) - Geological - Hydrological - Water Quality- Surface/Ground water - Air Quality (Noise & Meteorology) - Biodiversity- (Flora/fauna)  Social Environment - Resettlement & Land acquisition issues (if any) - Livelihood and local economy - Public health IMPACTS: Environmental impacts of proposed components are analyzed and predicted for construction and operation phases. The assessment results confirm that negative impacts are temporary and short term in nature. Table 6.1 represents activity impact identification matrix and interaction of project activities and environmental components. 53 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab Bagh Area, Agra 2017 Table 6.1: Activity Impact identification Matrix & Inter-action of Project Activities & Environmental components Potential Impacts on Environmental Components by Project Activities Water Social & Aesthetic Air Biodiversity Project Components Any Ground Land Health damage to Surface Water Traffic Livelihood Resettlement and Public & Water Air Quality Noise Flora Fauna / Safety sensitive Displacement property Mehtab Bagh Visitor    X X       X Parking & Facilities Approach road and side   X  X X      X walk to Mehtab Bagh Paving of Pedestrian  Access to Kachchpura  X  X X      X Through Fields Rehabilitation of 4  X  X X     X  X Community Chowks Basic Services, Sanitation,          X  X Drainage and SWM Consolidation of Village  X X X X X X X X X  X Well Urban Design Guidelines X X X X X X X X X X X X and Signage | 54 54 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab Ba 6.2 ANTICIPATED ENVIRONMENTAL IMPACTS: The qualitative /quantitative impacts have been taken into consideration based on following parameters: - Types: Positive (+) or Negative (-) - Magnitude: Long term and Short Term - Duration: Permanent impacts, Temporary impacts - Reversibility: Reversible, Irreversible The environmental impacts caused due to the development of the project can be categorized as primary (direct) and secondary (indirect) impacts. Primary impacts are those which are induced directly by the project whereas the secondary impacts are those which are indirectly induced and typically include the associated investment and changing patterns of social and economic activities due to the proposed action. Interaction of the project activities with environmental attributes is presented as Activity-Impact matrix in Table. 6.1 Environmental impacts due to the proposed project have been taken into account based on the project activities:  impact identification during construction  Impact identification during operation Impacts Due To Project Location: Impact on Physical Cultural Property/ Protected Monuments and Mitigation Measures Sub project is located within the Taj Trapezium Zone (TTZ) which is a trapezoid shaped, defined area of 10,400 Sq. Km around the Taj Mahal. Considering the nature of the project and proposed interventions, it is expected that proposed activities will have very limited impact on environment and no adverse impact on ASI protected monuments. Mitigation Measures: Though no specific mitigation measures are required, however, permission as required under the Ancient Monuments and Archaeological Sites and Remains Validation Act, 2010, to undertake construction/reconstruction/repair/renovation activities shall be obtained. Precautionary measures as will be mentioned in the permission document shall be followed. Impact Identification during Construction The impact during construction will be localized and short term with reversible changes in use of surrounding land as compared to the current condition. Impact will be primarily related to the civil works and less intensive impact is expected during erection of the equipment and operation. The construction phase, in general, has adverse influence on all the components of environment. Construction works generally may involve site clearance, excavation, filling of earth materials, dumping of unusable debris material, transportation of materials from production site to construction site, and other construction activities and associated works like mobilization of construction equipment, setting up of different construction plants, setting up of workforce camp, quarrying, transportation of material, material storage etc. These activities can have some impacts | 55 55 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra of varying magnitude on different components of environment. Proper care is essential to minimize the adverse impacts to the extent possible to facilitate the restoration of the environment and is discussed under following sub-heads: Impact on Land and Soil Environment:  Clearing and excavation of the land  Generation, storage and disposal of spoils and debris due to construction activities  Loss of aesthetics  Contamination of project land due to leakage or spillage of fuel and lubricants, waste water discharge from labor camps Impact on Air Environment I- Dust Emissions During the construction phase, dust emissions in populated areas will be emitted and deposited on the leaves of trees and other vegetation which may affect the growth of the trees and other vegetation. Certain amount of dust and gaseous emissions will be generated during the construction phase from excavation machine and construction machines. Pollutants of primary concern include respirable particulate matters. However, suspended dust particles matter may be coarse and will be settled within a short distance of construction area. Therefore, impact will be temporary and restricted within the closed vicinity of the construction activities only. Generation of Exhaust Gases Generation of exhaust gases is likely due to movement and operation of machinery for construction. Toxic gases are released through the heating process during bitumen production. Although the impact will be more localized, it can spread downwind direction depending upon the wind speeds. Increase in air pollution level from mobile and stationary sources during construction phase will be a short term impact on the air quality which is not expected to be significant as the commissioning phase will be staggered and intermittent in activity. Impact of Noise During the construction phase, the major sources of noise pollution are vehicles transporting the construction material to the construction yard and the noise generating activities at the yard itself. Mixing, casting and material movement are primary noise generating activities in the yard and will be uniformly distributed over the entire construction period. Construction activities are anticipated to produce noise levels in the range of 80 - 95 dB(A). The construction equipment will have high noise levels, which can affect the personnel operating the machines. Use of proper Personal Protective Equipment (PPE) such as earmuffs will mitigate any adverse impact of the noise generated by such equipment. The noise likely to be generated during excavation, loading and transportation of material will be in the range of 90 to 105 dB(A) and this will occur only when all the equipment operate together and simultaneously, however, is a remote possibility. The workers in general are likely to be exposed to an equivalent noise level of 80 to 90 dB (A) in an 8-hour shift, for which all statutory precautions should be taken into consideration. However, careful planning of machinery selection (not to operate more than 15 year old), operations and scheduling of operations can reduce these levels. 56 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Impact on Water Environment Demand of water may increase as it will be required primarily at the construction activities and for domestic purpose in the labour camps. The contamination of ground water due to leakage or spillage of fuel and lubricants from machineries and waste water discharge from labor camps may also be possible impact on water environment. Impact on Flora and Fauna: There are no ecologically sensitive areas like national parks or wildlife sanctuaries and reserved forests within the 10 km radius of proposed site. However following impacts may affect the flora and fauna found near the project site:  Loss of small shrubs & herbs at the time of dumping of debris and construction waste  Noise & vibration disturbance of fauna and local population Impact on Public and Sensitive Monuments Project is located near the ASI protection zones (prohibited and regulated zones of 3 protected monuments) therefore, special attention is required during construction activities as heavy construction, noise and vibration etc. may affect the ASI monuments. Impact of Traffic Congestion At the time of raw material transportation and by proposing project components which to improve traffic and pedestrian movement, it may cause some congestion that may cause inconvenience to the road users. Impact on Public health and Safety  Dust, gaseous pollutant and noise generation within the congested area during the construction works may affect the health of people residing in close proximity  Stagnancy of water in borrow pits located near settlements during rains may enhance the possibility of spreading the vector borne diseases  Unhygienic conditions and health hazards due to discharge of wastewater from labour camps  Poor sanitation and accumulated garbage/ waste generated from labor camp may cause increase in communicable diseases  Safety risks to construction workers Impact Identification during Operation During operation stage, major impacts anticipated may be highlighted as follows: Impact on Air Quality and Ambient Noise 57 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  Slight increase in PM10, PM2.5 and gaseous pollutant levels and gaseous project in ambient air during congestion (if any) and if entry allowed of vehicles in village  Increase in noise level due to movement of vehicles Impact on Water Environment  The proposed project may increase the water demand of the area because some public facilities viz. toilets, drinking water taps, will be developed to facilitate the commuters as well as staff.  In the absence of proper sewerage system, presently most of the sewage is directly going into River Yamuna or disposed off on land without any treatment. Therefore, a STP of capacity (to be awarded for construction of work to a construction agency, subsequently) of 350 KLD has been proposed to combat present situation and to improve sanitation condition in project area. Capacity of the STP covers sewage load from current population and expected growth of population in the next 10 years. However, there may be some chance to substandard treatment from STP, if not maintained properly. Impact of Refuse Disposal and Sanitation  Generation of Municipal solid waste could create odor and pollution if not managed properly  Aesthetic problem and nuisance to commuters  Un-hygienic condition in surroundings may trigger diseases Impact on Public Safety  Unhygienic condition due to unsafe disposal of waste 6.3 MITIGATION MEASURES: Environmental impacts of proposed components are analyzed and predicted for construction and operation phases. The assessment results confirm that negative impacts are temporary and short term in nature. However, mitigation measures for all above identified impacts are summarized in Chapter 7, Table 7.1. 6.4 ANTICIPATED SOCIAL IMPACTS & MITIGATION MEASURES The project report of the proposed project for Revitalization of Kachhpura and Mehtab Bagh Area, Agra after social impact assessment concludes that the project falls in ‘low impact’ category and has overall positive impacts on the life and environment of the people. There will be no private land acquisition and the project will be constructed on government land. A total of 7 households (49 project affected persons) are affected by the sub-project. Out of total PAPs, 23 are male and 17 are women members and remaining are children. Primarily there are three categories of PAPs: the Farmers (3 households), the Tenant Farmers (1 household), and the Shop owners (3 households) near Mehtab Bagh. 
 Out of the seven project affected families three are shop owners near Mehtab Bagh. To restore their income apart from training, shop owners will be relocated to new shops in parking area. The other four farmers affected will be given training as 58 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra per their choice for restoration of their income and all will be given preference in employment during construction stage of the project. The executing agency (Agra Development Authority) either on its own (given that only 7 households are affected) or with support of local NGO will conduct a training need assessment in consultations with the PAPs so as to develop appropriate income restoration schemes. The project will facilitate PAPs access to Government schemes that could help them to restore income and livelihood. In addition, the entitlement matrix provides for short-term income restoration activities intended to restore the income of the displaced person in the period immediately before and after relocation focusing on relocation, and providing short-term allowances such as: (i) transitional allowance; and (ii) shifting assistance. The details are available in the Generic Environmental and Social Management Plan and the Abbreviated Resettlement Action Plan. 59 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab Ba Chapter-7 Environmental Management and Monitoring Plan 7.0 Background: Font Environmental Assessment study was carried out for the proposed revitalization of Kachhpura and Mehtab Bagh and as an outcome of the study Environmental Management Plan (EMP) to minimize and mitigate the impact of activities proposed under this sub project. The Environment Management Plan (EMP) outlines the environmental management system that will be implemented during construction and operational stage of the project. The proposed management plan comprises following components: 1. Environmental Management Plan (EMP) 2. Environmental Monitoring plan 3. Reporting Requirement 4. Institutional Arrangement 5. Framework for Monitoring and Evaluation 6. Grievance Redress Mechanism 7. Information Disclosure 8. Capacity Building and Technical support 9. EMP Budget 7.1 ENVIRONMENTAL MANAGEMENT PLAN Environmental Management Plan (EMP) is prepared considering the activities proposed under this sub project. Table 7.1 summarizes the Generic Environmental Management Plan, which is common to all sub-components of the project while Table 7.2 indicates specific impacts and mitigation measures for the sub-components of the Project. Table 7.1: Generic Environmental Management Plan: Common to all sub-components of the Project Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency I. Air Environment 1. Emissions from  All vehicles used for the 240 Contractor Supervision Construction Equipment and project should have valid Consultant movement of vehicles. ‘Pollution under Control’ ADA/SPCU (PUC) Certificates.  All construction Equipment should be operated only through | 60 60 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency CNG.  All construction material shall be covered during transportation. 2. Dust Generation during Dust Suppression measures 240 Contractor Supervision earthwork operations. such as sprinkling of water Consultant (to wet the dust prone ADA/SPCU area/construction site) should be done at regular intervals to control fugitive dust emissions during construction activities. 3. Fugitive dust generation  Stock piling of 240 Contractor Supervision due to wind from stock piling construction material Consultant of earth/sand or other loose shall be done at ADA/SPCU construction material. designated and approved places away from habitation and water bodies/ drains.  Regular sprinkling of water and covering stack piles should be done to prevent wind-blown dust.  Temporary barriers (berms, silt fence or sandbag) shall be erected to prevent spreading of construction material. 4. Disruption of traffic due to  Specific Traffic 240 Contractor Supervision construction activities, management and Consultant movement of vehicles leading diversion plans shall be ADA/SPCU to congestion and air prepared by the pollution. Contractor and approved by the Engineer–in- charge prior to commencement of works on any section of the street / road.  The plan shall contain details of temporary diversions, traffic safety arrangements, safety signs, temporary barriers and flagmen around the exposed construction site to warn the public and ensure smooth traffic 61 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency flow. II. Water Environment 5. Depletion of water  Authorization for use of 240 Contractor Supervision resources due to use of water ground water or other Consultant for construction. sources of water should ADA/SPCU be obtained.  In case tanker water is used, the source of water shall have necessary authorizations.  All efforts shall be made to reuse/ recycle water during construction. 6. Contamination of  No cleaning, washing or 240 Contractor Supervision surrounding areas and maintenance activity Consultant stagnation of water due to shall be undertaken in the ADA/SPCU construction waste, vehicle influence area of the washing, cleaning, other project and near any activities. water body. All equipment and vehicle shall be serviced /washed only in vehicle workshops.  Adequate water supply and sanitation (toilets with adequate collection and treatment) facilities shall be provided to the construction labor at construction sites and at other project facilities.  All waste generated by the project shall be managed complying with Construction and Demolition Waste Management Rules, 2016 & Solid Waste Management Rules 2016 and guidelines annexed to this EMP.  All waste shall be reused for the project activities to the extent feasible.  Waste and construction activities shall be managed to avoid spillage in the nearby 62 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency drains water bodies. III. Noise Pollution 7. Vehicles and Construction  All plant and equipment 240 Contractor Supervision machinery movement & used in construction shall Consultant operation. strictly conform to the ADA/SPCU prescribed noise standards of Central Pollution Control Board.  No construction should be carried out during the night.  Construction near habitation/ education institutes/ hospitals (health centers) should be carried out with proper barricades.  All construction personal should be provided with ear plugs and other personal protective equipments. IV. Land Pollution 8. Soil contamination from  No fuel / lubricants 240 Contractor Supervision spillage of fuel, oils / should be stored at Consultant lubricants from construction project site. All ADA/SPCU equipment and storage areas. oils/lubricants storage shall be procured from authorized agencies / suppliers.  Construction vehicles should be well maintained with periodic inspection to avoid leakages / spillage.  Bitumen waste / scrap (if any) should be disposed in authorized disposal sites with approval from the engineer in-charge. 9. Soil contamination due to  Adequate facilities for the 240 Contractor Supervision discharge of untreated/ treatment of wastewater Consultant partially treated wastewater on shall be provided and no ADA/SPCU ground. water shall be discharged without meeting discharge standards of UPPCB. 63 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency 10. Damage to vegetation  No construction material 240 Contractor Supervision due to Temporary use of should be stored outside Consultant land for construction and the project area, on the ADA/SPCU material storage. streets, near habitation and sensitive locations.  Temporary storage of construction material shall be done with the consent of the neighboring population, concerned land owner/authority and with adequate barricading and protection. 11. Land pollution due to  All Construction and 240 Contractor Supervision Disposal of Construction and demolition waste should Consultant Demolition Waste. be disposed as per the ADA/SPCU Construction and Demolition Waste Management Rules, 2016 of Government of India.  Efforts should be made to reuse the waste generated during excavation of the road. Some measures include, (i) the sub-grade of the existing pavement may be used as embankment filling material. (ii) The existing sub base material may be recycled as sub base of any haul road or access road. (iii) existing bitumen surface may be utilized for paving of access roads and paving construction sites and campus, temporary traffic diversions, haulage routes etc.  All arrangements for transportation during 64 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency construction including provision, maintenance, dismantling and clearing debris shall be considered incidental to the works and shall be planned and implemented by Contactor.  Debris / waste generated from other construction activities shall be disposed such that it does not spill into surface water bodies or drains.  Debris/ waste shall not be stored in the project area for more than 24 hours. 12. Occupational health and  Shall comply with the 240 Contractor Supervision safety hazards to construction safety protocols, Building Consultant personnel. and Other Construction ADA/SPCU Workers Regulations of GoI & Environment, Health and Safety (EHS) Guidelines of World Bank Group.  Shall provide suitable safety barricading at all construction sites.  Shall provide and ensure use of PPEs (Personal Protective Equipment) such as Helmets, Mask, gumboots, gloves, ear plugs etc.  All vehicles and equipment shall have safety gear such as safety belt, reverse horn, etc.  All electrical connections shall be provided earth link circuit breaker (ELCB) and earthing.  Shall provide appropriate and adequate safety signage in local language (Hindi) and English at all project areas.  Shall deploy Health & 65 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Environmental Mitigation Measures BOQ Implementing Supervision Component/ Issue Reference Agency agency Safety Officers at the construction sites.  Shall provide facilities for first aid and medical support on call at project sites.  All safety incidents/accidents shall be monitored and appropriate preventive/ mitigation actions shall be taken. 13. “Chance Find” of items /  Report to relevant 240 Contractor Supervision materials of cultural and / or authorities, comply with Consultant/ archaeological importance World Bank’s safeguard ADA/SPCU during construction or policy on Physical and execution of the project. Cultural Resources and Ancient Monuments and Archaeological Sites and Remains Act, 1958 & as amended Act 2010 of GoI.  Prepare cultural properties management plan (if needed). Table 7.2 Specific Impacts and Mitigation Measures for the sub-components of the Project Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce Component 1: Visitors Parking and Facilities During construction phase 1. Safety Hazards, dust  Provide metal cover / 240 Contractor Supervision pollution and construction curtain of 4 meter height Consultant/ nuisance to the residents of for dust control around the ADA/SPCU Kachhpura and Mehtab Bagh area of construction around visitors. the construction site to avoid hazards, construction nuisance and dust pollution to neighbouring areas.  Specific Traffic management plans shall be prepared and approved by the Engineer–in-charge prior to the commencement of works. The plan shall 66 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce contain details of temporary diversions, traffic safety arrangements, safety signs, and flagmen around exposed construction sites to warn the public and ensure smooth traffic flow. 2. Blockage of storm water  All Construction and Contractor Supervision drains due to the disposal of demolition waste shall be Consultant/ excavated material during disposed as per the ADA/SPCU construction. Construction and Demolition Waste Management Rules, 2016 of Government of India. (Refer annex ?).  Efforts should be made to reuse the waste generated. During Operational Phase 1. Water logging during rainy  Adequate drainage - O&M ADA season due to loss of natural channels and slope shall be agency/ADA recharge of surface/ground provided at parking area to water collect rain water to avoid water logging and water losses due to paved ground. During Construction phase Component 2: Approach Road and Side Walk to Mehtab Bagh 1. Impacts to the adjoining  No construction activity, 240 Contractor Supervision forest land and damage to material storage, dumping / Consultant/ vegetation due to construction disposal of waste shall be ADA/SPCU activities, temporary use of carried out in the adjoining area for construction material forest land. storage  Adequate information and guidance shall be provided to the workforce including warning signs to prevent impacts on the forest land. 2. Site Clearance and  Preserve fertile top soil for 240 Contractor Supervision Preparation for the upgradation reuse of agricultural Consultant/ of the existing road purposes. ADA/SPCU  Only mechanical means shall be adopted and no herbicides and chemicals shall be used for clearance.  Dispose waste material in the disposal site identified 67 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce in point I (2) above.  Dust Suppression measures such as sprinkling of water (to wet the dust prone area/construction site) shall be done at regular intervals to control fugitive dust emissions. 3. Earth work excavation and  Provide complete 240 Contractor Supervision preparation of sub-base and barricading along the area Consultant/ base for the road of excavation with ADA/SPCU adequate safety warnings to prevent safety hazards and dust emissions.  Prepare specific traffic management plans with the approval of local authorities and the Engineer–in-charge prior to the commencement of works. The plan shall contain details of temporary diversions, traffic safety arrangements (including safety lighting at night), safety signs, and flagmen around construction site to warn the public and ensure smooth traffic flow.  Excavated soil shall be covered and stored within the site and shall be used for embankment, refilling, other construction and landscaping purposes.  All vehicles including earth moving equipment (excavator, JCB, etc.) should have Pollution Under Control (PUC) certificates.  All vehicles and equipment shall be operated by certified and trained operators.  No construction activity 68 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce should be done at night and during monsoon season.  “Chance Find” of items / materials of cultural and / or archaeological importance during earthwork excavation, all works should be stopped and reported to State/ Central Archaeological Agencies immediately. 4. Sourcing of Construction  Identification and 240 Contractor Supervision Material procurement of Consultant/ construction material (sand, ADA/SPCU gravel and stone) from authorized mines/quarries  Contractor should submit the copy of the clearance of source of materials. 5. Laying BT Layer and  Bitumen mix should not be 240 Contractor Supervision associated activities prepared at the site either Consultant/ through pot boiling or other ADA/SPCU means.  Ready mix bitumen shall be procured only from authorized hot mix plants. During Operational Phase 1. Water logging during rainy  Adequate drainage - O&M ADA season due to loss of natural channels and slope shall be agency/ADA recharge of surface/ground provided at parking area to water collect rain water to avoid water logging and water losses due to paved ground. Component 3& 4: Paving of Pedestrian Access Road to Kachchpura through fields During Construction Phase 1. Specific impacts 1 to 5 of  Implement all the 240 Contractor Supervision Component 2 above mitigation measures listed Consultant/ above for specific impacts ADA/SPCU 1 to 5 of Component 2. 2. Hindrance to storm water  Provide adequate cross 240 Contractor Supervision drainage due to the upgradation drainage structures based Consultant/ of pedestrian road. on the natural flow pattern ADA/SPCU and as per IRC specifications, to ensure 69 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce free flow of storm water. 3. Hindrance to storm water  Stock piling of construction 240 Contractor Supervision flow due to disposal of material shall be done at Consultant/ construction material / waste in designated and approved ADA/SPCU the drainage path places away from habitation and water bodies/ drains.  All Construction and demolition waste shall be disposed as per the Construction and Demolition Waste Management Rules, 2016 of Government of India. (Refer annexure 1).  Efforts should be made to reuse the waste generated. During Operational Phase 1. Water logging during rainy  Adequate drainage - O&M ADA season due to loss of natural channels and slope shall be agency/ADA recharge of surface/ground provided at parking area to water collect rain water to avoid water logging and water losses due to paved ground. Component 5: Rehabilitation of 4 community chowks During Construction Phase 1. Safety hazards and possible  Temporary diversion of 240 Contractor Supervision accidents - tourists, visitors and routes and alternate routes Consultant/ local residents during to be developed to avoid ADA/SPCU rehabilitation of community inconvenience to visitors chowks and local residents.  Proper and adequate diversion signs shall be provided at all working areas.  Proper safety signs, barriers, warning tapes and flagmen around the construction area shall be provided to ensure safety and to avoid accidents.  Work shall be carried out in phases to avoid inconvenience of local residents. 70 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce 2. Blockage of storm water  Adequate alternate 240 Contractor Supervision drains during rehabilitation drainage arrangements Consultant/ shall be made during ADA/SPCU rehabilitation work.  Redevelopment work for street and drains should not be carried out during rainy season to avoid flooding. 3. Risk of electrocution and  Earth link circuit breaker 240 Contractor Supervision electrical safety to local (ELCB) shall be provided Consultant/ communities due to electrical for all electrical ADA/SPCU works. connections.  Proper signage (danger sign) at street lights will be provided to avoid electric shock/electrocution. During Operational Phase Crowding & Congestion at Performance area and sitting - O&M ADA Chowks during small cultural arrangement shall be ensured agency/ADA performance/show and demarcated to avoid crowd & congestion at village chowks Component 6: Basic Services (Sanitation, Drainage and Solid Waste Management) During Construction Phase & Operational Phase Sewerage and Sanitation 240 Contractor Supervision Facilities  Design sewers with Consultant/  Bursting / leakage / adequate capacity and flow ADA/SPCU breakdown of sewers, velocity. leading to flooding of nearby  Conduct regular inspection areas, Backlogging due to and maintenance of the unexpected heavy flow sewers.  Prepare safety and Emergency Preparedness plan, prior to commissioning.  Damage to underground  Identify underground utility utilities like water, electricity lines in consultation with and telephone conduits, etc local authorities and plan due to construction activities. construction activities to minimize damage to utilities.  Incorporate appropriate budget for protection,  Accidents/ damages due to repair, replacement and erosion/ sliding of vertical restoration of underground 71 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce sides of excavated trenches utilities. while placing the sewers  Excavation shall be done by shoring trench sides by placing sheeting, timber shores, trench jacks, bracing, piles, or other material  Generation of substantial  All exposed surface shall debris, top soil and muck be resurfaced and during construction stabilized, by making sloping sides of trench to the angle of repose at which slope will remain safely.  Top soil shall be preserved and shall be used for agricultural purposes.  Spillage of fuel and oil  Debris shall be suitably stored to filling back the excavated areas after placing the trunk sewer lines.  All excess waste shall be disposed as per the Construction and Demolition Waste Management Rules, 2016 of Government of India. (Refer annexure 1)  Fuel and oil shall be stored at places away from any drainage channel/nalla, in drums mounted on a concrete paved platform with slope draining to small spill collection pit. Sewage Treatment Plant 240 Contractor Supervision  Pollution of receiving water  Treated water shall comply Consultant/ body (river) or land due to with prescribed standards ADA/SPCU inefficient treatment or non- of UPPCB/CPCB and the operation of STP conditions of consent to establish issued by UPPCB.  Treatment technology shall be selected that can handle quantity and characteristics of influent sewage and that 72 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce ensures achievement of  Flooding of STP site due to treated wastewater rain / storm water. standards.  STP site shall be located outside the flood plain / flooding area.  Disposal of sludge leading to  Drainage arrangements contamination of land and such as peripheral garland water. drain to collect /divert rain water shall be provided.  Efficient Sludge collection and disposal facilities meeting UPPCB/CPCB standards shall be provided.  Noise/Odour/fly nuisance  Treated and digested sludge hazards to neighbouring shall be disposed at a site areas. located away from habitation, and water bodies and shall be approved by UPPCB.  Provide appropriate acoustic control systems at the STP.  Implement suitable odour control measures at the STP. No herbicides shall be used for odour control. Component 7: Consolidation of Village Well During Construction Phase 1. Inconvenience and safety  Barricading/curtain/sheets 240 Contractor Supervision hazards to local residents during shall be provided at Consultant/ improvement works. working site to avoid ADA/SPCU accidents.  Proper signs, temporary barriers, danger tape and flagmen around the exposed construction work shall be provided to avoid accidents 2. Littering of excavated  Debris due to excavation 240 Contractor Supervision soil/waste on street may block and construction material Consultant/ the passage to village left over shall be disposed ADA/SPCU as per C& D Management Rules 2016 (Refer Appendix) 73 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Potential Environmental Mitigation Measures BOQ Responsible Supervision Impacts Refere Agency nce During Operational Phase Risk of accident during visit  Proper safety wall and - O&M ADA cover around the well shall agency/ADA be provided to avoid accident during site visit. Component 8: Urban design Guidelines for façades, Street furniture, Signage and public spaces in the village and Kachhpura Village Walk Brochure During Construction Phase 1. Contamination of soil and Empty cans of paints/colour 240 Contractor Supervision water due to improper storage, materials shall be stored in Consultant/ handling, transportation and covered shed and handed over ADA/SPCU disposal of paints/colour to authorized vendor or materials and empty cans disposed off at hazardous during implementation. waste disposal facility During Operational Phase - O&M ADA Modality for painting and agency/ADA Maintenance of Urban Design façade maintenance to be Guidelines discussed and decided by ADA and residents mutually 7.2 ENVIRONMENTAL MONITORING Monitoring is an important tool in establishing the success or failure of a project with regard to compliance of environmental safeguards. The purpose of the monitoring programme is to ensure that the intended environmental measures are achieved and result in desired benefits to the target population. To ensure proper implementation of the Environment Monitoring Plan it is essential that an effective monitoring programme is designed and carried out. The broad objectives of the environment monitoring program are:  To monitor impacts on the surrounding environment and the effectiveness of mitigation measures during the construction and operation phases.  To ensure that the environmental control systems are installed at the plant and are operating satisfactorily.  To suggest ongoing improvements in management plan, if required, for subsequent effective monitoring  To satisfy the requirements of environmental regulatory framework and community obligations The environmental monitoring program and cost associated with this monitoring is summarized in Table 7.3. Considering the length of implementation period (18 months) and existing 74 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra environmental scenario of the proposed project, environmental monitoring cost of Rs.3, 86,000/- has been allocated for construction and operation stages of project. Table 7.3: Environmental Monitoring Program Project Stage Location/frequency No. Unit Total Cost Env. Component Rate (INR) (INR) A-Air Quality Monitoring Construction Quarterly Monitoring 18 6000 1,08,000.00 (parameters-PM2.5, PM at 3 stations, all 10, SO2, NO2, CO) through during construction Operational once at 2 sites after 3 6000 18,000 project completion B-Water Quality Monitoring- Construction Monthly 36 4500 Monthly monitoring of raw 1,62,000 water & discharge water (construction)/ STP outfall (operation)- Parameters Operational Monthly STP inlet and 12 4500 54,000 -pH, turbidity, chemical oxygen outlet sample Testing demand (COD), Biological oxygen till 6 months after STP demand(BOD), dissolved oxygen construction (DO), conductivity, total dissolved solid (TDS), total suspended solid (TSS), Total Hardness, Residual Chlorine, Calcium, Magnesium, sulphate, nitrate, phosphate, copper, Chromium, iron, manganese, nickel cadmium, lead, Total Coliform & Fecal Coliform) C-Noise Monitoring- Construction Monthly monitoring 36 1000 36,000 Monthly monitoring at 2 at 2 sites, all through sites, all through during during construction construction Operational 4 times at 2 sites 8 1000 8,000 Cost of Environmental Monitoring (INR) Rs.3, 86,000/- 7.3 REPORTING REQUIREMENT Monthly compliance report of the above environmental management plan and monitoring plan shall be submitted by the contractor to DSC / TSU. On the basis of monthly compliance report from contractor and supervision on site, DSC will prepare quarterly progress report and submit to SPCU/TSU. 7.4 INSTITUTIONAL ARRANGEMENTS FOR SAFEGUARDS MONITORING The State Project Coordination Unit (SPCU) in Lucknow is located in the Department of Tourism and is supported by existing agencies (the Development Authorities in each core target area) and competitively selected decentralized teams (Technical Support Units – TSUs) based in each of the project core target areas, in principle in Agra, Mathura, Sarnath and Kushinagar. The TSUs will support the respective Development Authorities, the project implementing entities, in the day-to- day execution of respective subprojects. Social, heritage management and environment specialists are hired by the SPCU to coordinate, review, support and monitor all respective safeguards aspects of the project. The specialists will 75 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra also train and strengthen the capacities of specialists in the TSUs and in the implementing entities. The project may hire qualified civil society organizations for the implementation of the ESMP. The SPCU and the decentralized TSUs may also be supported by competitively recruited experts in highly specialized areas, as needed. Agra Development Authority will be primarily responsible for implementation of the project ESMP. ADA will be assisted by SPCU through its Environment Specialist and Social specialist and TSU in implementation. ADA will designate one of its official as Environmental Officer. The implementing team will comprise of the following:  Social Officer of ADA,  Environmental Officer at ADA  Social Specialist of SPCU,  Environment Specialist of SPCU  Representative of local NGO  Local people representatives The roles and responsibility of these officials are given in Table 7.4: Table 7.4: Roles and responsibilities of implementing team Players ROLES and RESPONSIBILITIES SPCU  Provide guidance to Social Officer of ADA; Social Specialist  Monitoring implementation activities and make budgetary provisions  Participate in meetings;  Monitor physical and financial progress during implementation. SPCU  Dedicated Environment Safeguard Specialist shall be deployed at SPCU for regular Environment monitoring of environmental management plan Specialist  Provide guidance to environmental officer of ADA;  Monitoring implementation of EMP activities through regular visits to the sub- project sites  Participate in meetings;  Monitor progress on EMP implementation. IE/TSU  Co-ordinate with district administration for implementation Officer  Translation of ESMP in local language and ensure dissemination at community level – prepare pamphlets on policy for information dissemination;  Provide training for skill enhancement  Liaison with district administration for dovetailing of government schemes for provision of basic services.  Report on physical, financial and EMP progress during implementation  Participate in the project level meetings;  Report progress, highlight issues not addressed and suggest mid-term correction; Contractor  Designate Environment Safeguard Specialist shall be deployed for Environmental Management during implementation of project.  Monthly compliance report to the above environmental management plan and monitoring plan shall be submitted by the contractor to DSC / TSU. NGO  Represent interest of stakeholders during the implementation of ESMP and gender Representative actions.  Provide information to stakeholders and local community and conduct awareness programs 76 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  Be part of grievance mechanism 7.5 FRAMEWORK FOR MONITORING AND EVALUATION The project authority will be responsible for carrying out M&E. Internal monitoring will be carried out by the Environmental and Social Officers of ADA with assistance from Social Specialist and Environment Specialist of SPCU and local representatives. This will help monitor project activities closely. Regular monitoring by undertaking site visits will help identify potential difficulties and problems faced in the project implementation and subsequently help take timely corrective measures including deviations, if needed. Monitoring will start as soon as the project implementation begins and Environmental Officer and local representatives are appointed / nominated at site for implementation of ESMP. Components of monitoring will include performance monitoring i.e., physical progress of the work and impact monitoring and external evaluation. Indicators that would be monitored related to performance are provided in the following sections. However, if during the project implementation some other indicators are found relevant those shall be included. NGO with appropriate expertise will be hired for external evaluation of ESMP implementation or DPR components. A quarterly report of internal monitoring will be prepared by Environmental Officer of ADA. The monitoring will also provide feedback on community concerns, grievances and requests. Monitoring will focus and ensure the following:  Verification that there are no outstanding or unresolved issues with respect to the project  Information campaign, discrimination and consultation with affected persons,  Effective operation of the Grievance Redress Committees detailing out number of complaints received and those resolved; reasons for not being able to resolve the grievance and status of unresolved grievances. Framework of monitoring is summarized in Table 7.5 below: Table 7.5: Framework for Monitoring Type Indicators Issues Procedure Timing Responsibility Project/ ESMP Employment of Site observation, Monthly ADA / NGO Implementatio local labor attendance record, n including women interaction with laborers and contractors Process level monitoring\ Campsite Site observation, Monthly ADA /SPCU/ management interaction with Local including lodging laborers, Representatives/ arrangement and contractors NGO campsite facilities EMP As prescribed in the At All times Contractor/SPCU Implementation ESA Report during /ADA construction Use of health and Site observation, Quarterly ADA / SPCU/ safety measures interaction with Local laborers, Representatives/ contractors NGO 77 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Temporary leasing Site observation, Monthly ADA / Local of land and house, contractors, check Representatives/ if any contract agreement NGO Discrimination of Interaction with Monthly ADA / SPCU. wage rate between laborers, labor male and female survey, record of workers wage payment Incidence of Discuss with local Annually ADA / SPCU/NGO communicable people, health diseases workers/ health post/ center records Change in Changes in Consultation with Annually ADA / SPCU Forest Cover/ vegetation forest department/ Impact Level Vegetation local Types if any representatives Social safety State of social Police records, Annually ADA / SPCU harmony and social consultation with security stakeholders. Note:-No Change in forest cover /vegetation is proposed under this Sub Project 7.6 GRIEVANCE REDRESSAL MECHANISM An Integrated Grievance Redressal Mechanism (IGRM) based on use of ICT shall be established, with necessary officials and systems, at the state as well as subproject levels. Grievances if any, may be submitted through various mediums, including in person, in written form to a noted address, through a toll free phone line or through direct calls to concerned officials, and online. All local contact information and options for complaint submission will be available on site on local information boards. Moreover, they will be in addition to the Public Information Officers to be appointed under the Right to Information (RTI) Act. A half yearly report on Grievance Redressal by the project will be prepared. The project will abide by the RTI Act of 2005; it will commit itself for proactive disclosure and sharing of information with the key stakeholders, including the communities/beneficiaries. The project will have a communication strategy focusing on efficient and effective usage of print and electronic media, bill boards, posters, wall writing, and adoption of any other method suiting local context, logistics, human and financial resources. The project however will have a project level Grievance Redressal Mechanism (GRM) to address the grievances of the stakeholders related to project implementation and project impacts if any. Members of Grievance Redressal Mechanism (GRM): The GRM will be constituted under the chairmanship of District Magistrate (DM), Agra. The GRM will have local representatives and other opinion leaders who will look into the grievance of the people. It will be chaired by a retired officer, who served as principal/judge/ DM/Additional DM, etc. The suitability of the Chairperson will be decided by the DM in consultation with ADA. Apart from the nominated persons, the cell will have a representative from ADA as convener. GRM will have representatives of the village resident’s including, farmers, youth groups and women self-help groups together with representatives of city administration. Total of 12 – 15 members will be part of the GRM. 78 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Functions of the Grievance Redressal Mechanism: The GRM will conduct a meeting in the first week of every month to hear the grievances from the stakeholders. All the complaints will be forwarded to the concerned department/officials within 15 days from the date of receiving the complaints. The issues are to be resolved/addressed by concerned officials within 45 days from the receipt of the complaints. All the grievances received shall be discussed by the Chairperson of the cell with DM for the necessary action. The compliance to all the petitions shall be reviewed in each of the meeting by the chairman and the DM. In case of the grievances not addressed by the GRM, it will be escalated to the office of District Magistrate by the Chairperson / ADA. The stakeholders can also approach judiciary if their grievances are not addressed at any of these levels. The grievance call shall submit a monthly report to the ADA for reference regarding the issues received and the cases disposed and forwarded to higher level. 7.8 INFORMATION DISCLOSURE: The ESMP will be translated into local language and will be shared with the affected community. The English and translated version of ESMP will be disclosed on the website of Department of Tourism. Hard copies in English and Hindi will be placed at following offices:  Agra Development Authority  Office of District Magistrate, Agra Through public meetings, attempt would be made to ensure that vulnerable groups such as SC households understand the process of project preparation and their needs are addressed in the best manner possible. 7.9 CAPACITY BUILDING AND TECHNICAL SUPPORT Given that Department of Tourism is implementing a World Bank-financed project for the first time, the capacity to address social, cultural and environmental issues as per the World Bank safeguards policies is limited. The Department of Tourism project staff will require training in the management of safeguards issues. The training program is to be coordinated and anchored by the Department of Tourism with support from agencies/individuals experienced in safeguard aspects for developing courses on conducting training programs. The course contents will focus on this ESMF, concept, regulatory requirements, environment and social priority issues, project cycle of investments, outline of the ESIAs, management plans and report formats. It will also focus on the resettlement and rehabilitation and heritage policies and procedures, land acquisition process, identification of project affected people, social entitlement frameworks, social assessment, risk assessment and management skills. As part of the capacity building program, the Department of Tourism would also aim to develop decentralized local capacity on managing environmental, social and cultural properties issues associated with various investments. In order to achieve this objective, the specialists will develop a network of technical man power resources such as staff from universities/research institutions, civil society organizations, etc. These persons will be trained during the course of the project, so that they can provide support to the project agencies in conducting the required impact assessments and later in implementing all applicable management plans (including Resettlement Action Plan, Gender Action Plan, as relevant) and also offer support on an on-going basis. 79 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra The capacity building at the local level for ESMP implementation agency as well as for the monitoring and redressal committee would be done through the tourism department. In addition to the above, DoT program will continue to mainstream the environmental, cultural and social issues within the training programs of State Project Coordination unit and the implementing entities. The program will be structured in such a way that it clearly brings out the value addition and enhancement benefits of proper management of environmental and social issues. Proposed capacity building plan is given in Table No. 7.6. Table 7.6: Capacity Strengthening Plan MODULES CONTENT DURATION ESMF  Project Concept Half a day  ESMF Concept To be repeated every  Regulatory Requirements alternative year  E&S Priority Issues  Subproject types  ESIA  Process Outline  Reporting Environmental  Environmental Laws & Regulations Full day class room Assessment Process  EIA process training.  Identification of Environmental Impacts Half a day field  Impact Identification Methods training.  Identification Mitigation Measures  Formulation of Environmental Management Plan  Implementation and Monitoring  Institutional Mechanism Social Assessment  Social Assessment process Half a day class room Process  Description of project; RPF, gender training. frameworks; and National regulatory frameworks Half a day field training.  LA process  Necessity for RAP/ ARAP, Gender plan and its preparation process  Implementation and Monitoring  Institutional Mechanism  Grievance Mechanism Cultural Properties  Cultural Properties Assessment Half a day class room Assessment Process process training.  Description of project and national regulatory frameworks Half a day field training.  Necessity for PCRMP and its preparation process  Implementation and Monitoring 80 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra  Institutional Mechanism 7.10 EMP- BUDGET FOR THE IMPLEMENTATION OF SAFEGUARD MITIGATION MEASURES The budget for the implementation (as highlighted in Table 7.7) of various mitigation measures is an important aspect of the safeguard management activities of the project. This section outlines the budget for implementation of the EMP provisions and has been based on the proposed actions. Table 7.7: Budget for EMP implementation Sr Particulars of EMP Cost Description No. Quantity Unit Rate (Rs.) Amount (Rs.) Remarks 1 Sprinkling of water for Dust Control A- Sprinkling of water For Dust 864.0 KL 500.00 4,32,000.00 Considering 6 Control at all the construction tanks (2KL points including sites of capacity) per material storage at every 2 hr week for 18 interval as dust suppression month’s measures during construction construction activities. Rate includes labour period cost, transportation, materials, equipment’s and works required to execute the job. 2 Development of Material Storage Sites - 2 in. No. Separate storage areas with three sides covered with temporary barricading of 2 m height is provided for course and fine aggregate material to minimize dust expansion. Land of material storage (base of storage sites) sites shall be protected with required thickness plastic sheets. Loose A 2.0 No. 100000.00 Market Rate course and fine aggregate 2,00,000.00 Material should also be covered by required thickness plastic sheets to prevent dust expansion. Rate includes labour cost, transportation, materials, equipment’s and works required to execute the job during entire construction period 81 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Sr Particulars of EMP Cost Description No. Quantity Unit Rate (Rs.) Amount (Rs.) Remarks Provision of Sanitation facilities at Labour camp 3 Considering 5 tanks (2KL A-Water Supply Considering 5 720.0 KL 500.00 capacity) per tanks (2KL capacity) per week 3,60,000.00 for 18 months week for 18 months B-Solid waste management by 10.0 No. 1500.00 providing bins of 100 Litre 15,000.00 Market Rate capacity at 10 points C-Mobile Toilet with anaerobic 18.0 Month 10000.00 treatment facility (10 seated) 1,80,000.00 Market Rate for 18 months on rental basis Traffic measures during construction 4 A- appointment of two traffic 36.0 Month 8000.00 - marshals for 18 months 2,88,000.00 B-Diversion of materials & safety signage cost LS - - 50,000.00 - 5 Noise Control Measures by providing barriers or sheets Noise Control Measures by providing acoustic barriers or sheets that are to be used at 100.0 Sheets 3000.00 300000 Market Rate high noise producing construction activities such as A- cutting of stones, drilling etc. Provision of PPEs (Personal Protective Equipment) i.e. Helmet, Mask, gum boots, gloves, Ear 6 plugs etc.), first-aid kits and safety signages A- Providing 30 Sets of PPEs (Personal Protective 25 No. 4000 Equipment) i.e. Helmet, Mask, 1,00,000.00 Market Rate gum boots, gloves, Ear plugs etc), 82 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Sr Particulars of EMP Cost Description No. Quantity Unit Rate (Rs.) Amount (Rs.) Remarks B- 2 Sets of First Aid Kits for 25 people that includes following items in the Kit: (10) Alcohol Wipes (1) Scissors (1) Tweezers (1) First Aid Guide (4) Nitrile Exam Gloves (1) Triangular Sling/Bandage, 40" x 40" x 56" (1) Cold Compress, 4" x 5" (1) Conforming Gauze Roll, 4" x 5 m (6) Gauze Dressing Pads, 4" x 4" 2 No. 10000 20,000.00 Market Rate (1) First Aid Tape, ½" x 5m (60) Plastic Bandages, 1" x 3" (2) Sunscreen Lotion Packets, SPF 30 (2) Trauma Pad, 5" x 9" (5) 2 Eyewash, 1oz, with 2 Eye Pads and 2 Strips (1) CPR Mask with One Way Valve (1) Burn Dressing, 4" x 4" (6) Hand Sanitizer Packets, 0.9g (4) Insect Sting Relief Wipes (10) First Aid/Burn Cream Packets, 0.9g (10) Triple Antibiotic Ointment Packets C- Safety Signage - 37 in No. to be used around construction sites, for diversions and other safety messages- Manufacturing, supplying and fixing retro reflective sign boards made of 2 mm thick aluminium sheet, face to be fully covered with high intensity encapsulated type heat activated retro reflective - sheeting conforming to type - IV of ASTM-D 4956-01 in blue and silver white or other colour combination including subject matter, message (bi-lingual), symbols and borders etc. as per IRC ; 67:2001, pasted on substrate by an adhesive backing which shall be 83 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Sr Particulars of EMP Cost Description No. Quantity Unit Rate (Rs.) Amount (Rs.) Remarks activated by applying heat and pressure conforming to class -2 of ASTM-D-4956-01 and fixing the same in following sizes at suitable sites or decided by the Engineer-in charge A- Small -3X2 Feet 25 No. 5000 Market Rate 1,25,000.00 B-Medium-5X3 Feet 10 No. 8000 Market Rate 80,000.00 c- Large-7X4 Feet 2 No. 15000 Market Rate 30,000.00 Environment Monitoring 7 A- Air Quality monitoring at 3 18 sites at bi-monthly interval till (Construction No. 6000 Phase) 1,08,000.00 Market Rate end of the construction period (parameters-PM2.5, PM 10, 3 SO2, NO2, CO) (Operational No. 6000 Phase) 18,00,0.00 B-Water Quality Monitoring - Monthly Monitoring of raw water & discharge water /STP 36 Market Rate outfall (Parameters -pH, turbidity, (Construction No. 4500 chemical oxygen demand (COD), Phase) Biological oxygen demand(BOD), dissolved oxygen (DO), 1,62,000.00 conductivity, total dissolved solid (TDS), total suspended solid (TSS), Total Hardness, Residual Chlorine, 12 Calcium, Magnesium, sulphate, No. 4500 Market Rate nitrate, phosphate, copper, (Operational 54,000.00 Chromium, iron, manganese, Phase nickel cadmium, lead, Total Coliform & Faecal Coliform) 36 (Operational No. 1000 Phase 36,000.00 Market Rate B- Noise Monitoring (24 Hr)-2 8 sites at bi-monthly till end of (Operational No. 1000 construction period Phase 8,000.00 8 Training & Capacity Building 84 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Sr Particulars of EMP Cost Description No. Quantity Unit Rate (Rs.) Amount (Rs.) Remarks Rs.100000/- considered for each year for two-year Training & Capacity Building on construction ESMP (as per capacity building A LS - - period that plan described in chapters & 2,00,000.00 includes trainer given in ESMF) cost and logistic arrangements cost 9 External Evaluation ToR for evaluation will be prepared by the subject expert. Cost of External Evaluation – ToR Evaluation needs to be done/ preparation is carried out by an independent considered Rs. agency - either a Design, 50000/-. Apart A Management and Review LS - - 500000/- from above agency or hired NGO who cost, Rs. 4.5 lacs would undertake the work. This will also be will be independent of DPR estimated for implementation agency evaluation of external evaluation of ESMP implementation Rs. 32,66,000.00 /- Grand Total of EMP Cost: Grand Total (in Words): Thirty Two Lacs Sixty Six Thousand Rupees Only 85 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Chapter-8 Conclusion The UP Government envisioned Uttar Pradesh Pro Poor Tourism Development Project with the financial support of World Bank is one of the stepping stone in restructuring its tourism sector in a pro-poor manner with a view to increasing benefits to local communities and improving the management of its tourism destinations. “Revitalization of Kachhpura and Mehtab Bagh Area, Agra” is one of the identified subproject proposed under UP Pro-Poor Tourism Development Project. Detailed Project Report for proposed sub project has been prepared and approved by the Department of UP Tourism, therefore, scope of this report is limited to assess environmental impacts of the components proposed under the said project and to determine the specific measures to reduce, mitigate and/or offset potential adverse impacts during pre-construction, construction and operation phases of the project. Project screening was carried out as per the screening criteria described in the Environment and Social Management Framework of UP pro-poor tourism development project that concludes that proposed sub project falls in ‘Category – B’ with minimal impact and has overall positive benefits on the life and environment of the people. There are no reported land acquisition or livelihood losses to be caused because of this sub project. As per environmental and social management framework guidelines of the Project; Environment impact Assessment was conducted for addressing possible issues/ concerns arising from proposed project. Impacts of activities were identified during the assessment under categories of Construction and Operation phase. Although no permanent negative or adverse environmental or social impacts were identified, there were certain temporary impacts, for which appropriate mitigation plans have been suggested. The environmental management plan ensures and suggests appropriate mitigation measures for the issues/ concerns identified during the environmental and social analysis studies. All the social and environmental issues have been appropriately studied and substantiated using appropriate evidence, to ascertain the magnitude of their impacts. Besides, the issues of public grievance and public notice have been taken care of in the report to ensure transparency during the project implementation. Report also ensures that well-defined institutional mechanism is in place to monitor and evaluate the progress of the project during construction, implementation and operation phases. 86 Environmental Assessment Report for Revitalization of Kachhpura And Mehtab 2017 Bagh Area, Agra Annexure-I Guidelines for Construction and Demolition Waste Management & Solid Waste Management (as per Demolition Waste Management Rules, 2016 & Solid Waste Management Rules 2015) (i) Every waste generator shall segregate construction and demolition waste and deposit at collection centre or hand it over to the authorized processing facilities (ii) Waste generator shall ensure that there is no littering or deposition of waste so as to prevent obstruction to the traffic or public or drains. (iii) Large generators (who generate more than 20 tons or more in one day or 300 tons per project in a month) shall submit waste management plan and get appropriate approvals from the local authority before starting construction or demolition or remodeling work, (iv) Large generators shall have environment management plan to address the likely environmental issues from construction, demolition, storage, transportation process and disposal / reuse of C & D Waste. (v) Large generators shall segregate the waste into four streams such as concrete, soil, steel, wood and plastics, bricks and mortar, (vi) Large generators shall pay relevant charges for collection, transportation, processing and disposal as notified by the concerned authorities; (vii) Segregate and store the waste generated in three separate streams namely bio-degradable, non- biodegradable and domestic hazardous wastes in suitable bins and handover segregated wastes to authorized waste pickers or waste collectors as per the direction or notification by the local authorities from time to time; (viii) Wrap securely the used sanitary waste like diapers, sanitary pads etc., in the pouches provided by the manufacturers or brand owners of these products or in a suitable wrapping material as instructed by the local authorities and shall place the same in the bin meant for dry waste or non- bio-degradable waste; (ix) Store separately construction and demolition waste, as and when generated, in his own premises and shall dispose off as per the Construction and Demolition Waste Management Rules, 2016; and (x) Store horticulture waste and garden waste generated from his premises separately at site and dispose of as per the directions of the local body from time to time. (xi) No waste generator shall throw, burn or bury the solid waste generated by him, on streets, open public spaces outside his premises or in the drain or water bodies. (xii) All waste generators shall pay such user fee for solid waste management, as specified in the bye- laws of the local bodies. (xiii) No person shall organize an event or gathering of more than one hundred persons at any unlicensed place without intimating the local body, at least three working days in advance and such person or the organizer of such event shall ensure segregation of waste at source and handing over of segregated waste to waste collector or agency as specified by the local body. 87