PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic of Congo, Transport and Connectivity Support Project(P161877) Project Implementation agency: Cellule Infrastructures Date of the Procurement Plan: January 10, 2020 Period covered by this Procurement Plan: January 2020 – June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Congo, Democratic Republic of : TRANSPORT AND CONNECTIVITY SUPPORT PROJECT PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2020-01-12 2021-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161877 GPN Date: Project Name: TRANSPORT AND CONNECTIVITY SUPPORT PROJECT Loan / Credit No: / , IDA / V2970 Cellule Infrastructures Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151794-NC-DIR / Passation de En attente Mise à jour du logiciel / Monitoring and evaluation A posteriori marché de gré à Direct 50,000.00 0.00 2020-10-01 2020-10-06 2020-11-10 2020-11-25 d'exécution TOMPRO par TOMATE gré CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-152090-CS-CQS / Etudes techniques et Sélection fondée économiqes et préparation du Transport infrastructure sur les En attente / A posteriori Open - International 100,000.00 0.00 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 DAO pour le bitumage de la works qualifications des d'exécution RN2, tronçon Bukavu - consultants Walungu (38 km) ZR-CI-152092-CS-QCBS / Etudes techniques et Sélection fondée économiqes et préparation du Transport infrastructure / A posteriori sur la qualité et le Open - International 425,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-02-07 DAO pour le bitumage de la works coût RN2, tronçon Mbuji Mayi - Kabinda (159 km) ZR-CI-152088-CS-CQS / Etudes techniques et Sélection fondée économiqes ainsi que la Transport infrastructure sur les préparation du DAO pour la / A posteriori Open - International 120,000.00 0.00 Annulé 2020-01-30 2020-02-20 2020-04-04 2020-05-04 2020-06-08 2020-11-07 works qualifications des réhabilitation et l'entretien de consultants la RN2, tronçon Walungu- Kamituga (142 km) ZR-CI-152139-CS-CQS / Etudes techniques et Sélection fondée économiqes et préparation du Transport infrastructure sur les / A posteriori Open - International 125,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 DAO pour le bitumage de la works qualifications des RN2, tronçon Butembo - Beni consultants (55 km) ZR-CI-152097-CS-QCBS / Etudes techniques et économiques ainsi que la Sélection fondée Transport infrastructure En cours préparation du DAO pour la IDA / V2970 A posteriori sur la qualité et le Open - International 300,000.00 0.00 2020-03-27 2020-04-24 2020-04-17 2020-05-20 2020-05-31 2020-07-24 2020-06-28 2020-11-03 2020-07-28 2020-11-03 2020-09-01 2020-11-03 2020-10-06 2021-03-07 works d'exécution réhabilitation de la RN2, coût tronçon Beni-Butembo- Rutshuru (306 km) ZR-CI-152087-CS-QCBS / Etudes de sauvegardes (EIES, Sélection fondée Environmental, social, and PAR et PPA) des travaux de IDA / V2970 A posteriori sur la qualité et le Open - International 450,000.00 0.00 Annulé 2020-03-27 2020-07-27 2020-04-17 2020-05-31 2020-06-28 2020-07-28 2020-09-01 2020-10-06 2021-03-07 GBV mitigations program réhabilitation du tronçon Beni- coût Butembo-Rutshuru ZR-CI-151795-CS-CQS / Evaluation des risques VBG Sélection fondée liés aux travaux de Environmental, social, and sur les IDA / V2970 A posteriori Limited 200,000.00 149,160.00 Signé 2020-04-12 2020-05-29 2020-04-26 2020-08-07 2020-05-26 2020-09-04 2020-06-30 2020-09-28 2020-09-29 réhabilitation de la RN2, GBV mitigations program qualifications des tronçon Mbuji Mayi-Kabinda- consultants Lubao ZR-CI-164527-CS-QCBS / Elaboration des cadres de Sélection fondée sauvegardes (CGES y compris Environmental, social, and En attente IDA / V2970 A posteriori sur la qualité et le Open - International 300,000.00 0.00 2020-04-06 2020-04-27 2020-06-10 2020-07-08 2020-08-07 2020-09-11 2020-10-16 2021-03-17 les risques VBG, CPR et CPPA) GBV mitigations program d'exécution coût des travaux des routes prioritaires ZR-CI-164534-CS-QCBS / Sélection fondée Préparation des documents de Environmental, social, and En attente IDA / V2970 A posteriori sur la qualité et le Open - International 200,000.00 0.00 2020-04-10 2020-05-01 2020-06-14 2020-07-12 2020-08-11 2020-09-15 2020-10-20 2021-03-21 sauvegardes (EIES et PAR) des GBV mitigations program d'exécution coût travaux aéroportuaires de Beni Page 1 ZR-CI-164532-CS-CQS / Analyse technique et Sélection fondée économique pour Transport infrastructure sur les En cours IDA / V2970 A posteriori Open - International 100,000.00 0.00 2020-04-30 2020-05-13 2020-05-21 2020-06-23 2020-07-04 2020-08-03 2020-09-07 2021-01-06 l'aménagement de la RP works qualifications des d'exécution 1029 Sake-Masisi-Walikale consultants (287 km) ZR-CI-164603-CS-QCBS / Etudes techniques et Sélection fondée Transport infrastructure En attente préparation du DAO des IDA / V2970 A posteriori sur la qualité et le Open - International 350,000.00 0.00 2020-03-30 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-03-10 works d'exécution travaux aéroportuaires (Goma coût et Beni) ZR-CI-164588-CS-CQS / Etude de faisabilité et Sélection fondée assistance technique sur Transport infrastructure sur les En attente IDA / V2970 A posteriori Limited 200,000.00 0.00 2020-04-13 2020-04-27 2020-05-27 2020-07-01 2020-12-28 l'intégration et la gestion de la works qualifications des d'exécution fibre optique dans les routes consultants du projet Sélection fondée ZR-CI-173044-CS-QCBS / En cours IDA / V2970 Monitoring and evaluation A posteriori sur la qualité et le Open - International 45,000.00 0.00 2020-08-03 2020-09-10 2020-08-24 2020-10-09 2020-10-07 2021-01-13 2020-11-04 2020-12-04 2021-01-08 2021-02-12 2022-02-12 Audit externe des comptes d'exécution coût ZR-CI-152089-CS-CQS / Sélection fondée Capacity building, reforms, Audit organisationnel et sur les IDA / V2970 and private sector A posteriori Open - International 90,000.00 0.00 En cours d'examen 2020-10-05 2020-11-13 2020-10-26 2020-12-09 2021-01-08 2021-02-12 2021-04-14 technique du Fonds National qualifications des participation d'Entretien Routier (FONER) consultants ZR-CI-190167-CS-QCBS / Elaboration des cadres de Sélection fondée Environmental, social, and sauvegardes (CGES y compris IDA / V2970 A posteriori sur la qualité et le Open - International 350,000.00 0.00 En cours d'examen 2020-09-11 2020-11-09 2020-10-02 2020-11-15 2020-12-13 2021-01-12 2021-02-16 2021-03-23 2021-07-23 GBV mitigations program les risques VBG, CPR et CPPA) coût du PACT (routes et aéroports) ZR-CI-190169-CS-LCS / Capacity building, reforms, Sélection au En cours Audit financier de la RVA, IDA / V2970 and private sector A posteriori Open - International 60,000.00 0.00 2020-09-04 2020-08-27 2020-09-25 2020-10-07 2020-11-08 2021-03-09 2020-12-06 2021-01-05 2021-02-09 2021-03-16 2021-08-13 moindre coût d'exécution exercices 2019 et 2020 participation ZR-CI-190170-CS-LCS / Capacity building, reforms, Sélection au En cours audit financier du FONER, IDA / V2970 and private sector A posteriori Open - International 60,000.00 0.00 2020-09-04 2020-09-01 2020-09-25 2020-10-07 2020-11-08 2021-01-20 2020-12-06 2021-03-09 2021-01-05 2021-02-09 2021-03-16 2021-08-13 moindre coût d'exécution exercices 2019 et 2020 participation ZR-CI-190171-CS-CQS / Etude d'impact Sélection fondée environnemental et social Environmental, social, and sur les En cours (EIES) des travaux de IDA / V2970 A posteriori Open - International 150,000.00 0.00 2020-09-04 2021-05-07 2020-09-25 2020-11-08 2020-12-08 2021-01-12 2021-03-14 GBV mitigations program qualifications des d'exécution réhabilitation du tronçon consultants routier Beni-Butembo- Rutshuru ZR-CI-205399-CS-CQS / Elaboration du Plan d'Action Sélection fondée de Réinstallation (PAR) et du Environmental, social, and sur les Plan en faveur des Populations IDA / V2970 A posteriori Open - International 183,000.00 0.00 En cours d'examen 2020-11-27 2020-12-21 2020-12-18 2021-01-31 2021-03-02 2021-04-06 2021-08-04 GBV mitigations program qualifications des Autochtones (PPA) liés aux consultants travaux de bitumage de la RN2, tronçon Beni-Butembo ZR-CI-230037-CS-CQS / Elaboration du Plan en faveur Sélection fondée des Populations Autochtones Environmental, social, and sur les En attente IDA / V2970 A posteriori Open - International 130,340.00 0.00 2021-05-21 2021-06-11 2021-07-25 2021-08-24 2021-09-28 2022-02-25 (PPA) lié aux travaux de GBV mitigations program qualifications des d'exécution bitumage de la RN2, tronçon consultants Beni-Butembo ZR-CI-230401-CS-CQS / Sélection fondée Elaboration du Plan d'Action Environmental, social, and sur les En attente de Réinstallation (PAR) lié aux IDA / V2970 A posteriori Limited 103,448.00 0.00 2021-05-14 2021-05-28 2021-06-27 2021-08-01 2021-11-29 GBV mitigations program qualifications des d'exécution travaux de bitumage de la consultants RN2, tronçon Beni-Butembo ZR-CI-230619-CS-CQS / Sélection fondée Actualisation du PAR des Environmental, social, and sur les En cours travaux de réhabilitation de la IDA / V2970 A posteriori Limited 110,000.00 0.00 2021-05-14 2021-06-27 2021-05-28 2021-06-27 2021-08-01 2021-08-11 GBV mitigations program qualifications des d'exécution RN2, tronçon Mbuji Mayi- consultants Kabinda Sélection fondée ZR-CI-230067-CS-CQS / Environmental, social, and sur les En attente Elaboration du CPR du PACT IDA / V2970 A posteriori Open - International 285,110.00 0.00 2021-07-12 2021-08-02 2021-09-15 2021-10-15 2021-11-19 2022-04-03 GBV mitigations program qualifications des d'exécution (routes et aéroports) consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151569-CS-INDV / Mise à jour du manuel de Capacity building, reforms, En attente procédures administratives, / and private sector A posteriori Individuel Limited 35,000.00 0.00 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2020-10-28 d'exécution comptables, financières, et participation de passation des marchés ZR-CI-152128-CS-INDV / En cours Mise à jour du manuel / Monitoring and evaluation A posteriori Individuel Limited 35,000.00 0.00 2020-04-01 2020-11-23 2020-04-06 2020-04-27 2020-06-01 2020-08-31 d'exécution d'exécution du projet ZR-CI-164594-CS-CDS / Actualisation des études techniques et économiques Sélection de ainsi que du DAO pour la Transport infrastructure IDA / V2970 A posteriori consultants par Direct 200,000.00 349,200.00 Signé 2020-03-30 2020-05-20 2020-04-09 2020-07-29 2020-06-13 2020-09-10 2020-09-13 réhabilitation de la RN2, works entente directe tronçon Mbuji Mayi - Kabinda - Lubao (332 km) par AIC PROGETTI ZR-CI-164593-CS-INDV / Analyse sécuritaire du projet Environmental, social, and En attente IDA / V2970 A posteriori Individuel Open 200,000.00 0.00 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2021-02-06 et élaboration du plan de GBV mitigations program d'exécution gestion de la sécurité Page 2 ZR-CI-164587-CS-INDV / Etudes économiques des Transport infrastructure En attente IDA / V2970 A posteriori Individuel Limited 40,000.00 0.00 2020-04-06 2020-04-11 2020-05-02 2020-06-06 2020-12-03 activités aéroportuaires (Goma works d'exécution et Beni) ZR-CI-164590-CS-INDV / Actualisation du PPA des travaux de rehabilitation de la Environmental, social, and En cours IDA / V2970 A posteriori Individuel Direct 50,000.00 0.00 2020-05-26 2020-06-18 2020-06-05 2020-06-26 2020-07-31 2020-10-29 RN2, tronçon Mbuji Mayi- GBV mitigations program d'exécution Kabinda-Lubao par Bruno BOLEKYMO ZR-CI-164605-CS-INDV / Actualisation du PAR des travaux de réhabilitation de la Environmental, social, and En cours IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 2020-05-26 2020-08-10 2020-06-05 2020-06-26 2020-07-31 2020-10-29 RN2, tronçon Mbuji Mayi- GBV mitigations program d'exécution Kabinda-Lubao par Mamadou DIEDHIOU ZR-CI-164586-CS-INDV / Actualisation et préparation des documents de Environmental, social, and En attente IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 2020-05-28 2020-06-07 2020-06-28 2020-08-02 2020-10-31 sauvegardes (EIES et PAR) des GBV mitigations program d'exécution travaux aéroportuaires de Goma par André TURCOTTE ZR-CI-164585-CS-INDV / Actualisation des EIES des travaux de réhabilitation de Environmental, social, and IDA / V2970 A posteriori Individuel Direct 120,000.00 143,236.00 Signé 2020-05-26 2020-06-18 2020-06-05 2020-07-29 2020-06-26 2020-08-20 2020-07-31 2020-09-10 2020-10-29 la RN2, tronçon Mbuji Mayi- GBV mitigations program Kabinda-Lubao par Adama ZARE ZR-CI-173049-CS-INDV / Chef de Section Routes au En cours IDA / V2970 Monitoring and evaluation A posteriori Individuel Open 60,000.00 0.00 2020-05-26 2020-05-27 2020-07-14 2020-08-04 2020-09-08 2021-09-08 sein de la Cellule d'exécution Infrastructures ZR-CI-181740-CS-INDV / Prestations de service au poste de Coordonnateur de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 55,825.00 87,725.00 Signé 2020-06-26 2020-07-14 2020-06-28 2020-07-14 2020-06-29 2020-09-30 2020-07-01 2020-12-02 2021-01-31 Cellule Infrastructures par Théophile NTELA LUNGUMBA ZR-CI-181736-CS-INDV / Prestations de service au poste de Chef de Section Administration et Finances au IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 35,000.00 55,000.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-29 2020-07-01 2020-11-05 2021-01-31 sein de la Cellule Infrastructures par Pierre BUNDOKI NDONGALA ZR-CI-181744-CS-INDV / Prestations de service au poste de Comptable au sein IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 18,900.00 18,900.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 de la Cellule Infrastructures par Jean-Jacques MAKUNZA ZR-CI-181742-CS-INDV / Prestations de service au poste de Gestionnaire de Projet Transport au sein de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,920.00 39,160.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Cellule Infrastructures par Théodore NGAMBILA VAN MAZIREL ZR-CI-181732-CS-INDV / Prestations de service au poste de Responsable de Passation des Marchés de la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 31,990.00 50,270.00 Signé 2020-06-26 2020-07-30 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Cellule Infrastructures par Damien MANYAMALA MAKANDAKELE ZR-CI-181739-CS-INDV / Prestations de service au poste de Chargé de Passation IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,570.00 38,610.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-10-30 2020-07-01 2020-11-05 2021-01-31 des Marchés au sein de la Cellule Infrastructures par Godefroid KASENDE MESO ZR-CI-181735-CS-INDV / Prestations de service au poste de Spécialiste en Environmental, social, and sauvegardes IDA / V2970 A posteriori Individuel Direct 28,560.00 47,040.00 Signé 2020-06-26 2020-08-03 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 GBV mitigations program environnementales au sein de la Cellule Infrastructures par Aimé KABAMBA ZR-CI-181731-CS-INDV / Prestations de service au poste de Spécialiste en Environmental, social, and IDA / V2970 A posteriori Individuel Direct 23,450.00 36,850.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 sauvegardes sociales au sein GBV mitigations program de la Cellule Infrastructures par Félix TSHIABA ZR-CI-181737-CS-INDV / Prestations de service au poste d'Expert Senior SIG au IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 28,560.00 44,880.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 sein de la Cellule Infrastructures par Patrick MBUY'A SAKAFUKU ZR-CI-181734-CS-INDV / Prestations de service au poste d'Assistante à la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 15,120.00 23,760.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Coordination de la Cellule Infrastructures par Marianne IKOBO ZR-CI-181743-CS-INDV / Prestations de service au poste de Chauffeur à la IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,540.00 13,420.00 Signé 2020-06-26 2020-09-29 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 Coordination de la Cellule Infrastructures par Noël MATUNGULU Page 3 ZR-CI-181741-CS-INDV / Prestations de service au poste d'Assistante au projet IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 12,390.00 19,470.00 Signé 2020-06-26 2020-07-10 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 au sein de la Cellule Infrastructures par Mélanie KAYIBA ZR-CI-181738-CS-INDV / Prestations de service au poste de Chauffeur au sein de IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,260.00 12,980.00 Signé 2020-06-26 2020-08-20 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-05 2021-01-31 la Cellule Infrastructures par Jean-Pierre KILONGOKELE ZR-CI-182253-CS-INDV / Prestations de service au poste d'Ingénieur Assistant 1 IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-05 2021-01-31 à la Section Routes de la Cellule Infrastructures par Cyrille KIBULU ZR-CI-182250-CS-INDV / Prestations de service au poste d'Ingénieur Assistant 2 IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-05 2021-01-31 à la Section Routes de la Cellule Infrastructures par Ange MUSHIGO ZR-CI-186421-CS-INDV / Appuis ponctuels à En cours l'évaluation des offres des IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 42,000.00 0.00 2020-08-14 2020-09-01 2020-08-19 2020-09-09 2020-10-14 2021-04-12 d'exécution marchés prévus au PPA du PACT ZR-CI-152119-CS-INDV / Etude de marchés du projet et IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 75,000.00 0.00 Annulé 2020-06-15 2020-06-20 2020-07-11 2020-08-15 2020-10-15 préparation de la stratégie de passation de marchés ZR-CI-151728-CS-INDV / Environmental, social, and Elaboration des procédures de IDA / V2970 A posteriori Individuel Open 150,000.00 0.00 Annulé 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2020-11-08 GBV mitigations program gestion de la main d'oeuvre ZR-CI-215461-CS-INDV / Prestations de services de Transport infrastructure En cours Comptable du projet PACT au IDA / V2970 A posteriori Individuel Open 42,000.00 0.00 2021-01-29 2021-02-15 2021-03-22 2021-03-26 2021-04-12 2022-04-12 works d'exécution sein de la Cellule Infrastructures ZR-CI-215454-CS-CDS / Réalisation des études diachroniques, durant la période de 10 dernières Sélection de années, de l’évolution Environmental, social, and En attente IDA / V2970 A posteriori consultants par Direct 54,000.00 0.00 2021-01-29 2021-02-01 2021-02-26 2021-05-17 environnementale et sociale GBV mitigations program d'exécution entente directe par télédétection dans la bande de 10 km centrée sur les axes routiers Mbuji-Mayi – Lubao et Goma – Beni ZR-CI-230075-CS-INDV / Expert en fibre optique et Transport infrastructure En attente développement numérique au IDA / V2970 A posteriori Individuel Open 48,000.00 0.00 2021-05-07 2021-06-25 2021-07-16 2021-08-20 2022-08-20 works d'exécution sein de la Cellule Infrastructures ZR-CI-230031-CS-CDS / Actualisation des EIES des Sélection de travaux de réhabilitation de la Environmental, social, and En attente IDA / V2970 A posteriori consultants par Direct 227,490.00 0.00 2021-05-07 2021-05-17 2021-07-21 2021-11-18 RN2, tronçon Mbuji Mayi- GBV mitigations program d'exécution entente directe Kabinda-Lubao par la firme SERF BURKINA ZR-CI-241053-CS-INDV / Elaboration du Cadre de Environmental, social, and En attente IDA / V2970 A priori Individuel Limited 304,250.00 0.00 2021-07-12 2021-07-17 2021-08-07 2021-09-11 2022-02-08 gestion environnementale et GBV mitigations program d'exécution sociale (CGES) du Projet ZR-CI-241060-CS-INDV / Prestations de services au poste d'Expert Violences Environmental, social, and En attente Basées sur le Genre au sein de IDA / V2970 A posteriori Individuel Direct 38,500.00 0.00 2021-06-28 2021-07-04 2021-07-07 2021-07-31 2022-05-31 GBV mitigations program d'exécution la Cellule Infrastructures par Madame Liliane MUSAU KAZADI ZR-CI-241107-CS-INDV / Elaboration du Cadre de Environmental, social, and En attente planification en faveur des IDA / V2970 A posteriori Individuel Limited 195,241.00 0.00 2021-07-14 2021-07-19 2021-08-09 2021-09-13 2022-01-26 GBV mitigations program d'exécution Populations Autochtones (CPPA) du Projet Page 4