Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non-consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Shopping Up to USD 100,000 (INR 6.5 m) Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from any given state. (d) Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g) Two or three envelope system will not be used (except when using the e-procurement system assessed and agreed by the Bank). (h) No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget (FBS) Must meet the requirements as per Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis (LCS) Must meet the requirements as per Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Qualification Estimated not to exceed USD 300,000, and (CQ) must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for 1. Executive, Assistant Engineers who are responsible for 2 weeks Continuous Procurement – multiple trainings 2. Contract management training – multiple trainings 2 weeks Continuous Customized training on Procurement Procedures arranged for 3. Executive, Assistant Engineers who are responsible for 1 week Continuous Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-08-10 2020-09-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Executing Agency(ies): Central Water Commission - NHP WORKS Bid Evaluation Activity Reference No. / Procurement Estimated Actual Draft Bidding Loan / Credit Market Procurement Prequalification High SEA/SH Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Contract Description Component Review Type Method Document Amount Amount Document / Signed Contract No. Approach Process (Y/N) Risk Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Completion Type (US$) (US$) Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-CWC-NHP-10546-GO-DIR Water Resources Information / Extension/Up-gradation of IBRD / 87250 Prior Direct Selection Direct 452,941.00 0.00 Canceled 2017-12-21 2017-12-21 2018-01-25 2018-07-24 Systems eSWIS NHP-2018-2019-CWC-271725 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Very High IBRD / 87250 Post Open - National 25,646.15 0.00 Implementati 2018-02-03 2018-03-31 2018-09-27 System Quotations Envelope End workstation on NHP-2018-2019-CWC-899489 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of High End IBRD / 87250 Post Open - National 8,784.62 0.00 Implementati 2018-02-12 2018-04-09 2018-10-06 System Quotations Envelope Workstation on NHP-2018-2019-CWC-339996 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Low End IBRD / 87250 Post Open - National 21,590.37 0.00 Implementati 2018-02-10 2018-04-07 2018-10-04 System Quotations Envelope Workstation on NHP-2018-2019-CWC-505631 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Low End IBRD / 87250 Post Open - National 42,000.00 0.00 Implementati 2018-07-25 2018-09-19 2019-03-18 System Quotations Envelope Workstation on NHP-2018-2019-CWC-311885 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Low End IBRD / 87250 Post Open - National 16,153.85 0.00 Implementati 2018-07-29 2018-09-23 2019-03-22 System Quotations Envelope Workstation on NHP-2018-2019-CWC-792477 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Audio Visual IBRD / 87250 Post Open - National 15,384.62 0.00 Implementati 2018-08-05 2018-09-30 2019-03-29 System Quotations Envelope Equipments on Under NHP-2018-2019-CWC-257334 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 23,076.92 0.00 Implementati 2018-04-02 2018-05-28 2018-11-24 / Purchase of Computers System Quotations Envelope on Pending NHP-2018-2019-CWC-849131 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 6,461.54 0.00 Implementati 2018-09-06 2018-11-01 2019-04-30 / Purchase of Laptop System Quotations Envelope on NHP-2018-2019-CWC-950004 Pending Institutional Capacity Request for Single Stage - One / Purchase of IBRD / 87250 Post Limited 6,153.85 0.00 Implementati 2018-09-10 2018-11-05 2019-05-04 Enhancement Quotations Envelope Networking/Internet Facility on Page 1 Pending NHP-2018-2019-CWC-758674 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 14,646.15 0.00 Implementati 2018-02-14 2018-04-11 2018-10-08 / Purchase of Plotter System Quotations Envelope on NHP-2018-2019-CWC-727479 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 2,122.62 1,936.28 Signed 2018-04-02 2018-05-28 2018-03-28 2018-11-24 / Purchase of Printer (Color) System Quotations Envelope Pending NHP-2018-2019-CWC-284992 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 2,286.28 0.00 Implementati 2018-08-07 2018-10-02 2019-03-31 / Purchase of Printer (Color) System Quotations Envelope on NHP-2018-2019-CWC-677124 Water Resources Monitoring Request for Single Stage - One / Purchase of Scanner (A4 IBRD / 87250 Post Open - National 1,784.62 1,680.82 Signed 2018-04-01 2018-05-27 2018-03-28 2018-11-23 System Quotations Envelope size) NHP-2018-2019-CWC-603110 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Scanner (A3 IBRD / 87250 Post Open - National 2,307.69 0.00 Implementati 2018-08-10 2018-10-05 2019-04-03 System Quotations Envelope size) on NHP-2018-2019-CWC-707424 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 4,560.00 4,294.78 Signed 2018-04-02 2018-05-28 2018-03-28 2018-11-24 / Purchase of UPS (7.5 KV) System Quotations Envelope Pending NHP-2018-2019-CWC-411639 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 861.54 0.00 Implementati 2018-08-18 2018-10-13 2019-04-11 / Purchase of UPS (1 KV) System Quotations Envelope on NHP-2018-2019-CWC-393223 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Video IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-08-25 2018-10-20 2019-04-18 System Quotations Envelope Conferencing equipments on NHP-2018-2019-CWC-400691 Water Resources Monitoring Request for Single Stage - One / Purchase of Video IBRD / 87250 Post Open - National 2,846.15 2,597.75 Signed 2018-04-02 2018-05-28 2018-03-28 2018-11-24 System Quotations Envelope wall/LED Display NHP-2018-2019-CWC-373476 Water Resources Monitoring Request for Single Stage - One / Purchase of Video IBRD / 87250 Post Open - National 999.23 911.06 Signed 2018-04-02 2018-05-28 2018-03-28 2018-11-24 System Quotations Envelope wall/LED Display NHP-2018-2019-CWC-566260 / Purchase of Photocopier Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 4,586.15 4,294.78 Signed 2018-04-01 2018-05-27 2018-03-27 2018-11-23 multi-functional Machine A3 System Quotations Envelope (Color) NHP-2018-2019-CWC-755564 / Purchase of Photocopier Water Resources Monitoring Request for Single Stage - One Digital multifunctional IBRD / 87250 Post Open - National 4,496.14 4,103.73 Signed 2018-04-01 2018-05-27 2018-03-27 2018-11-23 System Quotations Envelope Machine office Machine (Color) NHP-2018-2019-CWC-944587 Under Water Resources Monitoring Request for Single Stage - One / Purchase of Photocopier IBRD / 87250 Post Open - National 1,439.92 0.00 Implementati 2018-04-01 2018-05-27 2018-11-23 System Quotations Envelope Multifunctional (B&W) on Pending NHP-2018-2019-CWC-325815 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 18,461.54 0.00 Implementati 2018-12-11 2019-02-05 2019-08-04 / Purchase of photocopier System Quotations Envelope on NHP-2018-2019-CWC-921128 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of office IBRD / 87250 Post Open - National 33,846.15 0.00 Implementati 2018-12-11 2019-02-05 2019-08-04 System Quotations Envelope Furniture on NHP-2018-2019-CWC-720626 Water Resources Information IBRD / 87250 Post Direct Selection Direct 120,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-10 2019-03-09 / Purchase of Arc GIS Systems Page 2 NHP-2018-2019-CWC-393150 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of Image IBRD / 87250 Post Limited 41,538.46 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope processing software on NHP-2018-2019-CWC-315559 / Purchase of RTDAS ( Water Resources Monitoring Open - Single Stage - Two IBRD / 87250 Prior Request for Bids 5,692,307.69 0.00 Canceled 2018-10-18 2018-12-03 2018-10-23 2019-02-06 2018-12-04 2019-05-21 2019-02-16 2019-03-23 2019-09-19 AWLR, ARG, AWS & V- System International Envelope SAT) IN-CWC-NHP-105252-GO- Pending DIR / Purchase & Up- Institutional Capacity IBRD / 87250 Post Direct Selection Direct 367,143.00 0.00 Implementati 2019-03-12 2019-03-17 2019-04-21 2019-10-18 gradation of ARC GIS Enhancement on Softwares NHP-2018-2019-CWC-315559- 2 / SUPPLY, INSTALLATION, TESTING, COMMISSIONING AND MAINTENANCE OF REAL Under TIME DATA ACQUISITION Water Resources Monitoring Open - Single Stage - Two IBRD / 87250 Prior Request for Bids 5,243,000.00 0.00 Implementati 2019-09-19 2019-09-25 2019-09-24 2019-10-20 2019-11-05 2020-01-24 2020-02-02 2020-06-10 2020-03-08 2020-09-04 SYSTEM (RTDAS) OF System International Envelope on NORTH EASTERN STATE (EXCEPT ASSAM) OF INDIA UNDER NATIONAL HYDROLOGY PROJECT (NHP) IN-CWC-NHP-135413-GO- RFB / Supply, installation, Pending testing, commissioning and Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 1,258,742.00 0.00 Implementati 2019-09-29 2019-10-09 2019-11-20 2020-02-02 2020-03-08 2020-09-04 maintenance of RTDAS in System Envelope on Narmada Basin for NCA under NHP NHP-2018-2019-CWC-119701 Pending / Procurement of WQ lab Water Resources Information Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 1,126,761.00 0.00 Implementati 2018-09-10 2018-09-15 2018-10-27 2019-01-09 2019-02-13 2019-08-12 equipment and other Systems Envelope on accessories IN-CWC-NHP-164044-GO- Pending Water Resources Monitoring Single Stage - Two RFB / Procurement of ADCP IBRD / 87250 Post Request for Bids Open - National 557,432.43 0.00 Implementati 2020-03-11 2020-03-11 2020-04-01 2020-06-09 2020-07-14 2021-01-10 System Envelope for the field offices of CWC on NHP-2020-2021-CWC-162936 Pending Institutional Capacity Request for Single Stage - One / Purchase of Erdas Imgine IBRD / 87250 Post Open - National 62,123.08 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 Enhancement Quotations Envelope software on Pending NHP-2020-2021-CWC-258184 Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 46,153.85 0.00 Implementati 2020-10-01 2020-10-06 2020-11-17 2021-01-30 2021-03-06 2021-09-02 / Purchase of VC equipment System Envelope on Pending NHP-2020-2021-CWC-329009 Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 139,846.15 0.00 Implementati 2019-10-18 2019-10-23 2019-12-04 2020-02-16 2020-03-22 2020-09-18 / RTDAS for Narmada System Envelope on NHP-2020-2021-CWC-350462 Pending Water Resources Monitoring Request for Single Stage - One / Networking internet IBRD / 87250 Post Open - National 35,461.54 0.00 Implementati 2021-01-05 2021-03-02 2021-08-29 System Quotations Envelope facilities on NHP-2020-2021-CWC-353216 Pending Water Resources Monitoring Request for Single Stage - One / Purchase of LED wall IBRD / 87250 Post Limited 2,307.69 0.00 Implementati 2020-11-06 2021-01-01 2021-06-30 System Quotations Envelope display on Pending NHP-2020-2021-CWC-408747 Institutional Capacity Single Stage - One IBRD / 87250 Post Request for Bids Open - National 86,153.85 0.00 Implementati 2020-10-10 2020-10-15 2020-11-26 2020-12-26 2021-01-30 2021-07-29 / Purchase of workstations Enhancement Envelope on Page 3 Pending NHP-2020-2021-CWC-516015 Water Resources Monitoring Single Stage - One IBRD / 87250 Post Request for Bids Open - National 123,076.92 0.00 Implementati 2020-06-01 2020-06-06 2020-07-18 2020-08-17 2020-09-21 2021-03-20 / Purchase of GIS software System Envelope on Pending NHP-2020-2021-CWC-532201 Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 15,384.62 0.00 Implementati 2020-09-06 2020-11-01 2021-04-30 / Purchase of computer System Quotations Envelope on Pending NHP-2020-2021-CWC-675759 Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Limited 15,384.62 0.00 Implementati 2020-10-06 2020-12-01 2021-05-30 / Purchase of printer plotter Enhancement Quotations Envelope on Pending NHP-2020-2021-CWC-776583 Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Open - National 738.46 0.00 Implementati 2020-10-19 2020-12-14 2021-06-12 / Purchase of antivirus Enhancement Quotations Envelope on Pending NHP-2020-2021-CWC-960338 Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Open - National 2,461.54 0.00 Implementati 2020-09-15 2020-11-10 2021-05-09 / Purchase of MS office Enhancement Quotations Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2020-2021-CWC-817913 Under Water Resources Information Single Stage - Two / Upgradation of eSWIS, IBRD / 87250 Prior Request for Bids Open - National 3,000,000.00 0.00 Implementati 2020-08-01 2020-08-06 2020-09-17 2020-11-30 2021-01-04 2021-07-03 Systems Envelope AMC of WIMS on IN-CWC-NHP-191716-NC- RFB / CONDUCTING RESERVOIR Pending Water Resources Operations Single Stage - Two SEDIMENTATION STUDIES IBRD / 87250 Post Request for Bids Open - National 887,692.31 0.00 Implementati 2020-09-14 2020-09-19 2020-10-31 2021-01-13 2021-02-17 2021-08-16 and Planning System Envelope USING HYDROGRAPHIC on SURVEY OF RESERVOIRS IN INDIA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-CWC-NHP-12586-CS- QCBS / To equip MoWR, RD&GR, CWC, CGWB and states with rational water- related assessment and Water Resources Operations Quality And Cost- Open - planning at basin level, IBRD / 87250 Prior 7,253,731.00 0.00 Canceled 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2018-01-18 2018-02-17 2018-03-24 2018-04-28 2019-04-28 and Planning System Based Selection International through the development and application for 3 basins in India (Godavari Basin, Krishna Basin and Mahanadi Basin). NHP-2018-2019-CWC-750657 / Physical Based Mathematical modeling for Water Resources Operations Least Cost Open - Under IBRD / 87250 Prior 2,076,923.08 0.00 2018-09-28 2019-01-23 2018-10-19 2019-05-10 2018-12-02 2019-08-30 2018-12-30 2020-01-27 2019-01-29 2020-04-27 2019-03-05 2020-08-27 2019-04-09 2019-10-06 sediment rate estimation and and Planning System Selection International Implementation sediment transport in the river basin NHP-2018-2019-CWC-841056 Water Resources Operations Least Cost Open - Pending / Development of Regional IBRD / 87250 Post 384,615.38 0.00 2018-10-29 2018-11-19 2019-01-02 2019-01-30 2019-03-01 2019-04-05 2019-05-10 2019-11-06 and Planning System Selection International Implementation models for water availability Page 4 NHP-2018-2019-CWC-218376 / Basin wise EHP Model for Water Resources Operations Least Cost Open - Under IBRD / 87250 Prior 3,076,923.08 0.00 2018-08-31 2018-11-23 2018-09-21 2019-01-15 2018-11-04 2019-05-01 2018-12-02 2019-08-02 2019-01-01 2019-10-24 2019-02-05 2020-02-28 2019-03-12 2019-09-08 medium & long term and Planning System Selection International Implementation forecasting NHP-2018-2019-CWC-266557 / 2D Stream-flow forecasting Water Resources Operations Least Cost Open - Under IBRD / 87250 Prior 2,307,692.31 0.00 2019-09-24 2019-07-12 2019-10-15 2019-12-27 2019-11-28 2020-07-06 2019-12-26 2020-01-25 2020-02-29 2020-04-04 2020-10-01 system including inundation and Planning System Selection International Implementation modelling IN-CWC-NHP-40711-CS- QCBS / Cost Estimate of IWRM Study of Krishna & Water Resources Operations Quality And Cost- Open - IBRD / 87250 Prior 6,000,000.00 0.00 Canceled 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2017-12-22 2018-01-13 2018-01-19 2018-04-05 2018-02-18 2018-07-12 2018-03-25 2018-04-29 2019-04-29 Godavari River Basin for and Planning System Based Selection International Package-I(Krishna & Godawari Basin) IN-CWC-NHP-40721-CS- QCBS / Cost Estimate of Water Resources Operations Quality And Cost- Open - IWRM Study of Krishna & IBRD / 87250 Prior 4,000,000.00 0.00 Canceled 2017-12-21 2017-12-21 2017-12-21 2017-12-21 2017-12-22 2018-01-13 2018-01-19 2018-04-05 2018-02-18 2018-07-12 2018-03-25 2018-04-29 2019-04-29 and Planning System Based Selection International Godavari River Basin for Package-II(Mahanadi Basin) NHP-2020-2021-CWC-668444 / STUDY ON THE ISSUE OF FLOOD AND SILTATION IN RIVER Water Resources Operations Least Cost Open - Pending IBRD / 87250 Post 307,692.31 0.00 2020-09-14 2020-10-05 2020-11-18 2020-12-16 2021-01-15 2021-02-19 2021-03-26 2021-09-22 GANGA AND ITS and Planning System Selection International Implementation TRIBUTARIES DUE TO FARAKKA BARRAGE IN THE STATE OF BIHAR NHP-2020-2021-CWC-697151 / DSS for Integrated Water Resources Operations Least Cost Open - Pending IBRD / 87250 Post 895,384.62 0.00 2020-09-14 2020-10-05 2020-11-18 2020-12-16 2021-01-15 2021-02-19 2021-03-26 2021-09-22 Reservoir Operations for and Planning System Selection International Implementation Ganaga Basin INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-CWC-NHP-123112-CS- Water Resources Operations Under CDS / Aquatic Habitat Atlas IBRD / 87250 Prior Direct Selection Direct 1,441,633.00 0.00 2019-08-01 2019-09-06 2019-08-31 2019-12-16 2019-11-04 2022-11-03 and Planning System Implementation in major rivers of India Page 5