PROCUREMENT PLAN (Textual Part) Project information: Mauritania Basic Education Support Project – Phase 2 P163143 Project Implementation agency: Direction des Projets Education et Formation Date of the Procurement Plan: February 17, 2020 Period covered by this Procurement Plan: February 19, 2020 – October 30, 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Mauritania : Basic Education Sector Support Project - Phase 2 PLAN General Information Country: Mauritania Bank’s Approval Date of the Original Procurement Plan: 2020-02-19 2020-11-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163143 GPN Date: Project Name: Basic Education Sector Support Project - Phase 2 Loan / Credit No: / , IDA / V3120 Mauritania Basic Education Sector Support Project Executing Agency(ies): WORKS Procureme Activity Reference No. / Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH nt Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) Justification for Award Type Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-161843-GO-RFQ Component 1: Transforming / Un onduleur pour la teacher management using Single Stage - One En attente plateforme du SIGE à la / A posteriori Demande de prix Limited 0.00 2020-03-20 2020-05-15 2020-11-11 accountability frameworks Envelope d'exécution DIGTEC, Un logiciel Backup et and new technology point d'accès wifi MR-BESSP-159785-GO-RFB / Component 2: Improving Equipement SIGE pour Single Stage - One En attente / education service delivery in A posteriori Appel d'offres Open - National 0.00 2020-03-12 2020-03-14 2020-04-13 2020-04-28 2020-05-18 2020-06-17 Administration centrale , Envelope d'exécution selected regions DRENs et IDENs à Nouakchott. MR-BESSP-159784-GO-DIR / Connexion internet et accès WIFI, pour DREN et IDEN à Component 3: Strengthening Passation de En attente Nouakchott, et administration / management of the A posteriori marché de gré à Direct 0.00 2020-03-24 2020-03-29 2020-04-16 2020-04-19 d'exécution du SIGE, et Installation de la education sector gré connexion aux DREN et IDEN et formation. Component 3: Strengthening MR-BESSP-175882-GO-RFQ Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 0.00 2020-06-17 2020-07-13 2020-08-12 / Location de voitures Envelope d'exécution education sector MR-BESSP-175893-GO-RFQ Component 3: Strengthening / Duplication des items de Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 0.00 2020-06-13 2020-06-30 2020-07-30 l'évaluation des enseignants Envelope d'exécution education sector du fondamental. MR-BESSP-175899-GO-RFQ Component 3: Strengthening / Matériel de passation des Single Stage - One En attente IDA / V3120 management of the A posteriori Demande de prix Limited 0.00 2020-06-20 2020-07-11 2020-07-26 épreuves de l'évaluation des Envelope d'exécution education sector enseignants du fondamental MR-BESSP-204844-GO-RFB / Component 3: Strengthening Single Stage - One En attente Acquisition de 18 véhicules IDA / V3120 management of the A posteriori Appel d'offres Open - National 0.00 2020-12-05 2021-02-17 2021-08-16 Envelope d'exécution pour 6 régions education sector MR-BESSP-205324-GO-RFB / Acquisition de tablettes au Component 1: Transforming profit de 4000 responsables teacher management using Single Stage - One En attente IDA / V3120 A posteriori Appel d'offres Open - National 0.00 2020-12-07 2020-12-12 2021-01-11 2021-01-26 2021-02-19 2021-02-25 de l'Enseignement accountability frameworks Envelope d'exécution Fondamental and new technology (Opérationnalisation du SIGE) MR-BESSP-205597-GO-RFQ / Location de véhicules pour Component 3: Strengthening Single Stage - One En attente l'évaluation des acquis des IDA / V3120 management of the A posteriori Demande de prix Limited 0.00 2020-11-29 2020-12-29 2020-12-30 Envelope d'exécution élèves de la 1ère AF et 1ère education sector AS par la CNE MR-BESSP-205598-GO-RFQ / Fournitures et duplicata des Component 3: Strengthening Single Stage - One En attente instruments pour l'évaluation IDA / V3120 management of the A posteriori Demande de prix Limited 0.00 2020-11-29 2020-12-10 2020-12-12 Envelope d'exécution des acquis des élèves de 1ère education sector AF et 1ère AS par la CNE NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-159797-NC-RFP / Component 3: Strengthening Sélection fondée En attente Formulation du plan sectoriel / management of the A posteriori sur la qualité et le Open - International 0.00 2020-04-20 2020-05-11 2020-06-24 2020-07-22 2020-08-21 2020-09-25 2020-10-30 2021-10-30 d'exécution et réformes éducatives education sector coût MR-BESSP-166467-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les En attente IDA / V3120 management of the A posteriori Open - National 0.00 2020-04-06 2020-04-21 2020-05-20 2020-06-19 2020-07-24 2020-10-22 l'Enseignement Fondamental qualifications des d'exécution education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 2 Page 1 MR-BESSP-166468-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les En attente IDA / V3120 management of the A posteriori Open - National 0.00 2020-04-13 2020-04-28 2020-05-27 2020-06-26 2020-07-31 2020-10-29 l'Enseignement Fondamental qualifications des d'exécution education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 3 Sélection fondée MR-BESSP-175876-CS-CQS / Component 3: Strengthening sur les En attente Recrutement d'un expert IDA / V3120 management of the A posteriori Open - International 0.00 2020-06-10 2020-06-25 2020-07-12 2020-07-16 2020-07-23 2021-07-23 qualifications des d'exécution économiste/planificateur education sector consultants MR-BESSP-166466-CS-CQS / Recrutement d'un cabinet Sélection fondée Component 3: Strengthening pour un appui au Ministère de sur les En attente IDA / V3120 management of the A posteriori Open - National 0.00 2020-03-30 2020-04-14 2020-05-13 2020-06-12 2020-07-17 2020-08-31 l'Enseignement Fondamental qualifications des d'exécution education sector et de la réforme du Secteur de consultants l'éducation Nationale zone 1 MR-BESSP-205407-CS-CQS / Sélection fondée Component 2: Improving Elaboration d'un manuel de sur les En attente IDA / V3120 education service delivery in A posteriori Open - National 0.00 2020-12-01 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2021-06-09 procédures pour les COGES et qualifications des d'exécution selected regions les subventions aux écoles consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-BESSP-159783-CS-INDV Component 1: Transforming / Appui au processus de teacher management using En cours / A posteriori Individuel Limited 0.00 2020-03-09 2020-03-14 2020-04-04 2020-05-09 2020-11-05 restructuration des ENIS et de accountability frameworks d'exécution l'ENS and new technology MR-BESSP-159791-CS-INDV Component 3: Strengthening En attente / Manuel de procédure du / management of the A posteriori Individuel Limited 0.00 2020-02-24 2020-02-29 2020-03-21 2020-04-25 2020-10-22 d'exécution Projet education sector MR-BESSP-159793-CS-INDV / Finalisation études Component 2: Improving En attente environnementales et sociales / education service delivery in A posteriori Individuel Limited 0.00 2020-03-12 2020-03-17 2020-04-07 2020-05-12 2020-11-08 d'exécution et Mécanisme de Gestion des selected regions Plaintes (trois consultants) MR-BESSP-159795-CS-INDV Component 3: Strengthening En attente / Manuel d'exécution du / management of the A posteriori Individuel Limited 0.00 2020-02-29 2020-03-05 2020-03-26 2020-04-30 2020-10-27 d'exécution projet education sector Component 1: Transforming MR-BESSP-160153-CS-INDV teacher management using En attente / Appui à la restructuration / A posteriori Individuel Open 0.00 2020-03-09 2020-04-27 2020-05-18 2020-06-22 2020-12-19 accountability frameworks d'exécution des ENIs et ENS II and new technology MR-BESSP-159786-CS-INDV Component 2: Improving / Appui à l'élaboration du En attente / education service delivery in A posteriori Individuel Limited 0.00 2020-04-13 2020-04-18 2020-05-09 2020-06-13 2020-12-10 nouveau modèle des cartes d'exécution selected regions scolaires (central et régional) MR-BESSP-175841-CS-QCBS Component 3: Strengthening En attente / Recrutement d'un Expert en IDA / V3120 management of the A posteriori Individuel Open 0.00 2020-06-09 2020-07-08 2020-07-13 2020-08-03 2021-01-30 d'exécution suivi-évaluation education sector MR-BESSP-175878-CS-CQS / Component 3: Strengthening En attente recrutement d'un expert en IDA / V3120 management of the A posteriori Individuel Open 0.00 2020-06-08 2020-07-07 2020-07-14 2020-07-26 2021-01-22 d'exécution Education/Formation education sector MR-BESSP-205334-CS-INDV Component 2: Improving / Manuel de procédures pour En attente IDA / V3120 education service delivery in A posteriori Individuel Open 0.00 2020-12-02 2020-12-28 2021-01-02 2021-01-10 2021-02-09 les plans de développement d'exécution selected regions régionnaux MR-BESSP-159788-CS-INDV Component 2: Improving / Elaboration d'un manuel de / education service delivery in A posteriori Individuel Limited 0.00 Annulé 2020-02-25 2020-03-01 2020-03-22 2020-04-26 2020-10-23 procédures pour COGES et selected regions subventions aux écoles MR-BESSP-205542-CS-INDV / Accompagnement pour un Component 1: Transforming appui à la conception , la mise teacher management using En attente IDA / V3120 A posteriori Individuel Open 0.00 2020-12-14 2021-02-01 2021-02-22 2021-03-29 2025-03-28 en œuvre et au suivi des accountability frameworks d'exécution Projets d'Etablissement des and new technology ENI. Page 2