Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: September 2014]: Revision 4 of Updated Procurement Plan, March 2017. 2. Date of General Procurement Notice: 3. Period covered by this procurement plan: The procurement period of project covered from year December 2016 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,000 ,000 All 2. NCB (Goods) Above US$ 1,000,000 First contract 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Below US$ 1,000,000 First contract 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [Refer to Procurement Plan] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 4. Single Source (Individual) All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 4. Consultancy Assignments with Selection Methods and Time Schedule [Refer to Procurement Plan] PROCUREMENT Tunisia : Tunisia Northern Tunis Wastewater Project PLAN General Information Country: Tunisia Bank’s Approval Date of the Original Procurement Plan: 2017-03-27 2021-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P117082 GPN Date: Project Name: Tunisia Northern Tunis Wastewater Project Loan / Credit No: IBRD / 79170, IBRD / 86440 Office National de l'Assainissement Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 20 / Projet pilote d'assistance Part C: monitoring and Single Stage - One 2016-02- IBRD / 79170 A posteriori Appel d'offres Open - International 710,000.00 470,181.64 Signé 2014-11-07 2014-11-14 2015-01-06 2015-01-06 2015-03-31 2015-04-30 2015-04-30 technique au GDA Sidi Amor capacity strengthening Envelope 24 50 / L'équipement du centre des opérations de contrôle permettant de centraliser Part C: monitoring and Single Stage - One En attente 2015-12- toutes les demandes et IBRD / 79170 A posteriori Demande de prix Limited 88,000.00 0.00 2015-11-13 2015-11-13 2015-11-26 capacity strengthening Envelope d'exécution 31 doléances des abonnés de l'ONAS pour faire face aux exigences du PGES: génie civil 28 / lot2 : Travaux de pose Part A: transfer of treated de la conduite terrestre, génie Single Stage - One 2,466,711.8 2015-11- IBRD / 79170 wastewater (TWW) to increase A priori Appel d'offres Open - International 4,100,000.00 Signé 2013-03-13 2013-03-16 2013-05-07 2014-02-13 2017-06-21 2014-03-28 2014-03-28 civil et équipements de la Envelope 0 18 its reuse in agriculture station de pompage 5 / Aménagement d'une cloture (bassins du pilote) et Part C: monitoring and Single Stage - One En attente 2018-04- IBRD / 79170 A posteriori Demande de prix Limited 75,000.00 0.00 2017-10-16 2018-02-13 acquisition de pièces de capacity strengthening Envelope d'exécution 14 rechange 29 / Fourniture, transport et Part B: improvement of the Single Stage - One 24,668,551.0 32,365,870. 2017-08- pose des conduites DN 1600 IBRD / 79170 discharge of the remaining A priori Appel d'offres Open - International Signé 2013-10-08 2014-05-20 2014-06-05 2013-10-12 2014-09-09 2014-09-09 2015-09-08 2017-11-08 2016-05-20 2016-05-20 Envelope 0 15 13 (EMISSAIRE EN MER) TWW in the Mediterranean Sea 51 / Mise à niveau du réseau informatique du parc Charguia (travaux de GC de Part C: monitoring and Single Stage - One En attente 2018-05- IBRD / 79170 A posteriori Demande de prix Open - National 40,000.00 0.00 2017-12-15 2018-02-15 mise en place d'un cablage en capacity strengthening Envelope d'exécution 16 fibre optique au complexe charguia) 53 / Aménagement de la salle de commande et Part C: monitoring and Single Stage - One 2017-02- IBRD / 79170 A posteriori Demande de prix Limited 3,000.00 2,950.78 Signé 2016-09-14 2017-02-20 2017-02-20 contrôle El Jisr et fourniture capacity strengthening Envelope 27 d'une solution de commande 65 / Aménagement du site de stockage des boues des Part C: monitoring and Single Stage - One En attente 2019-10- IBRD / 86440 A posteriori Appel d'offres Open - National 536,000.00 0.00 2018-11-15 2018-11-30 2019-01-02 2019-03-01 2019-04-01 stations d'épuration de capacity strengthening Envelope d'exécution 28 Choutrana 1 et 2 62 / Travaux de Part C: monitoring and Single Stage - One 10,000,000.0 11,154,188. En cours 2019-08- réhabilitation du système IBRD / 86440 A priori Appel d'offres Open - International 2018-10-30 2020-04-27 2018-11-04 2018-12-16 2017-01-31 2019-01-15 2020-05-21 2019-02-19 2018-09-27 capacity strengthening Envelope 0 66 d'examen 18 canal el khalij lot n°2 pose 68 / Réhabilitation des équipements électromécaniques de trois Part C: monitoring and Single Stage - One En attente 2021-06- IBRD / 86440 A posteriori Appel d'offres Open - National 1,800,000.00 0.00 2020-04-28 2020-05-04 2020-06-18 2020-07-30 2020-08-28 (03) stations de pompage des capacity strengthening Envelope d'exécution 24 eaux usées: , Montplaisir, Chatt Ghaba et côtière Nord GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 27 / Fournitures et transport Part B: improvement of the Single Stage - One de conduites en PEHD 1600 IBRD / 79170 discharge of the remaining A priori Appel d'offres Open - International 3,483,785.00 2,816,559.67 Signé 2013-03-11 2013-03-19 2013-05-07 2013-10-15 2017-10-06 2014-04-07 2014-04-07 2014-12-03 Envelope mm et accessoires TWW in the Mediterranean Sea Part C: monitoring and Single Stage - One En attente 36 / Lot 1,1: 110 scanners IBRD / 79170 A posteriori Appel d'offres Open - National 54,044.00 0.00 2016-02-15 2016-02-19 2016-03-23 2016-03-23 2016-09-23 2016-11-22 capacity strengthening Envelope d'exécution 37 / Lot 1,2: 100 lecteurs Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Appel d'offres Open - National 51,000.00 0.00 2015-06-19 2015-06-25 2015-07-30 2015-07-30 2016-03-17 2016-07-30 code à barre capacity strengthening Envelope d'exécution 38 / Lot 1,3: PC + Part C: monitoring and Single Stage - One En cours IBRD / 79170 A posteriori Appel d'offres Open - National 128,950.00 0.00 2015-06-19 2015-06-25 2015-07-30 2016-03-23 2015-07-30 2016-03-09 2016-07-22 Imprimantes + Onduleurs capacity strengthening Envelope d'exécution 41 / Equipement al Jesrou 1 Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Demande de prix Limited 681.00 0.00 2016-06-01 2016-06-03 2016-06-10 2016-06-13 (porte coupe feu) capacity strengthening Envelope d'exécution Part C: monitoring and Single Stage - One En cours 42 / Equipement al Jesrou 2 IBRD / 79170 A posteriori Demande de prix Limited 28,742.00 0.00 2016-04-18 2016-06-10 2016-06-17 capacity strengthening Envelope d'exécution 44 / Equipement Al jesrou 3 Part C: monitoring and Single Stage - One En attente (services et fournitures IBRD / 79170 A posteriori Demande de prix Limited 1,568.00 0.00 2016-05-24 2016-05-31 2016-06-23 2016-07-13 capacity strengthening Envelope d'exécution soft+hard du centre d'appel) 47 / Salle des opérations et Part C: monitoring and Single Stage - One En attente de contrôle (panneaux IBRD / 79170 A posteriori Demande de prix Limited 3,321.00 0.00 2016-05-15 2016-06-27 2016-08-11 capacity strengthening Envelope d'exécution publicitaires sponsoring) 3 / Acquisition des Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Appel d'offres Open - National 225,000.00 0.00 2017-06-15 2018-01-15 2018-02-15 2018-04-16 2018-05-16 2018-08-14 équipements centraux capacity strengthening Envelope d'exécution Page 1 52 / mise à niveau du réseau informatique, acquisition et Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Appel d'offres Open - National 80,000.00 0.00 2018-01-12 2018-01-15 2018-02-15 2018-04-15 2018-05-16 2018-08-14 montage du système du video capacity strengthening Envelope d'exécution surveillance 54 / Acquisition de tablettes Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Demande de prix Limited 5,000.00 0.00 2016-10-31 2016-11-04 2016-11-04 pour el Jisrou capacity strengthening Envelope d'exécution 55 / Mise en place d'un nouveau réseau informatique Part C: monitoring and Single Stage - Two En attente IBRD / 79170 A posteriori Appel d'offres Open - National 170,000.00 0.00 2018-03-01 2018-03-15 2018-04-30 2018-10-10 2018-11-12 2019-03-12 et du système de sécurité du capacity strengthening Envelope d'exécution siège sociale 57 / Fourniture et transport Part B: improvement of the Single Stage - One En attente de deux piquages bridés en IBRD / 79170 discharge of the remaining A posteriori Demande de prix Limited 10,000.00 0.00 2017-07-10 2017-08-15 2017-08-25 Envelope d'exécution PEHD DN 1600 TWW in the Mediterranean Sea 58 / Alimentation électrique Part A: transfer of treated Passation de En attente de la station de pompage SPEE IBRD / 79170 wastewater (TWW) to increase A posteriori marché de gré à Direct 28,249.00 0.00 2017-01-10 2017-01-27 2017-08-18 2018-02-14 d'exécution de Raoued its reuse in agriculture gré 61 / Travaux de Part C: monitoring and Single Stage - One En cours réhabilitation du système IBRD / 86440 A priori Appel d'offres Open - International 3,257,000.00 0.00 2016-06-27 2016-07-02 2016-08-13 2016-09-12 2016-10-17 2017-04-15 capacity strengthening Envelope d'exécution canal el khalij lot n°1 fournitures 71 / Acquisition et installation de débimetres dans la STEP de choutrana, de Part C: monitoring and Single Stage - One En attente matériel de contrôle de la IBRD / 86440 A posteriori Appel d'offres Open - National 200,000.00 0.00 2019-01-01 2019-06-03 2019-07-01 2019-09-02 2019-10-01 2020-03-29 capacity strengthening Envelope d'exécution qualité des eaux épurées et de matériel de laboratoires pour la station d'épuration 69 / Acquisition de 15 voitures tourismes pour Part C: monitoring and Single Stage - One En attente IBRD / 86440 A posteriori Appel d'offres Open - National 500,000.00 0.00 2020-05-01 2020-05-11 2020-06-10 2020-08-25 2020-09-25 2021-01-25 réalisation, suivi et capacity strengthening Envelope d'exécution exploitation 73 / Acquisition de 4 aéroéjecteurs de capacité 30 Part C: monitoring and Single Stage - One En attente IBRD / 86440 A posteriori Appel d'offres Open - National 320,000.00 0.00 2020-05-01 2020-05-15 2020-06-15 2020-08-31 2020-09-30 2021-01-29 Kg O2/h et 5 de capacité 50 capacity strengthening Envelope d'exécution kg O2/h 74 / Acquisition de matériel Part C: monitoring and Single Stage - One En attente informatique (ordinateurs, IBRD / 86440 A posteriori Appel d'offres Open - National 280,000.00 0.00 2020-05-04 2020-05-11 2020-06-22 2020-08-21 2020-09-21 2020-12-21 capacity strengthening Envelope d'exécution imprimantes, scanners,…etc) 72 / Travaux de Part C: monitoring and Single Stage - One En cours réhabilitation du système de IBRD / 86440 A priori Appel d'offres Open - International 8,000,000.00 7,989,440.75 2016-07-02 2020-04-24 2016-07-02 2016-08-13 2015-05-19 2016-09-12 2020-05-21 2016-10-17 2016-05-17 2017-04-15 capacity strengthening Envelope d'examen transfert canal Khèlij lot n°1 fourniture 90 / Acquisition de materiel Part C: monitoring and Single Stage - One En attente informatique (ordinateur, IBRD / 86440 A posteriori Demande de prix Open - National 37,000.00 0.00 2021-03-03 2021-05-10 2021-06-09 capacity strengthening Envelope d'exécution imprimantes,...) NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 32 / Compagne Part C: monitoring and Single Stage - One En attente d’échantillonnage et d’analyse IBRD / 79170 A posteriori Appel d'offres Open - International 62,000.00 0.00 2012-08-01 2012-11-12 2013-01-22 2013-01-22 2013-11-22 2015-11-12 capacity strengthening Envelope d'exécution de laboratoire 39 / Lot n°4 (Acquisition des licenses des outils ORACLE/ Part C: monitoring and Single Stage - One IBRD / 79170 A posteriori Appel d'offres Open - National 78,500.00 74,817.00 Signé 2016-04-26 2016-04-29 2016-06-02 2016-06-02 2016-06-02 2016-09-12 2016-10-11 2016-10-11 2016-12-25 Base des donnees et capacity strengthening Envelope OAS/Service d'application): 1 / Alimentation Elèctrique Part A: transfer of treated Passation de En attente de la Station de Pompage IBRD / 79170 wastewater (TWW) to increase A posteriori marché de gré à Direct 25,000.00 0.00 2017-09-01 2017-10-01 2017-11-30 2018-05-29 d'exécution (STEG) its reuse in agriculture gré 2 / Alimentation en eau Part A: transfer of treated Passation de En attente potable de la Station de IBRD / 79170 wastewater (TWW) to increase A posteriori marché de gré à Direct 75,000.00 0.00 2017-09-01 2017-09-08 2017-12-07 2018-06-05 d'exécution Pompage (SONEDE) its reuse in agriculture gré 4 / Mise à niveau de la salle centrale d'informatique et Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Appel d'offres Open - National 175,000.00 0.00 2017-06-15 2017-08-15 2017-09-15 2017-11-14 2017-12-14 2018-03-14 renforcement de réseau de capacity strengthening Envelope d'exécution messagerie interne 6 / Mise à niveau du réseau informatique du parc Part C: monitoring and Single Stage - One Charguia (mise à niveau du IBRD / 79170 A posteriori Appel d'offres Open - National 150,000.00 0.00 Annulé 2017-09-11 2017-09-15 2017-10-15 2017-12-14 2018-01-13 2018-04-13 capacity strengthening Envelope cablage et acquisition et montage du système de vidéo surveilance) 56 / Acquisition d'un système Part C: monitoring and Single Stage - One En attente IBRD / 79170 A posteriori Demande de prix Open - National 40,000.00 0.00 2018-06-15 2018-07-15 2018-10-13 de messagerie interne capacity strengthening Envelope d'exécution CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sélection fondée 11 / Outil financier d'aide à la Part C: monitoring and En attente IBRD / 79170 A priori sur la qualité et le Open - International 500,000.00 0.00 2017-10-01 2017-10-04 2018-03-18 2018-03-19 2018-07-17 2018-09-16 2018-10-16 2019-10-16 prise de décision capacity strengthening d'exécution coût Page 2 18 / Renforcement des mécanismes de suivi pour Sélection fondée Part C: monitoring and En attente permettre la mise en œuvre IBRD / 79170 A priori sur la qualité et le Open - International 424,417.00 0.00 2012-10-23 2012-10-25 2013-04-01 2013-10-08 2013-10-08 2014-12-01 2014-12-30 2017-12-14 capacity strengthening d'exécution du PGE dans la zone coût d'influence du projet (partie maritime ) 21 / Assistance technique à Sélection fondée Part C: monitoring and En cours la mise en oeuvre du projet IBRD / 79170 A priori sur la qualité et le Open - International 198,834.00 0.00 2012-04-30 2012-05-07 2013-10-02 2013-11-12 2013-12-30 2014-08-24 2014-09-23 2015-12-17 capacity strengthening d'exécution Partie terrestre coût 30 / Supervision des travaux Sélection fondée Part C: monitoring and d'installation de l'émissaire en IBRD / 79170 A posteriori sur la qualité et le Open - International 400,000.00 479,418.16 Signé 2013-04-09 2013-04-12 2014-01-04 2014-07-15 2014-07-15 2015-03-12 2016-10-17 2016-10-17 2020-09-26 capacity strengthening mer coût 31 / Etude d'exécution d'une Sélection fondée Part C: monitoring and nouvelle STEP au Nord de IBRD / 79170 A priori sur la qualité et le Open - International 1,045,198.00 373,032.19 En cours d'examen 2010-08-06 2010-08-09 2013-06-26 2013-08-20 2014-08-29 2014-09-09 2018-05-01 2015-09-21 2015-09-21 2016-12-14 capacity strengthening Tunis coût Sélection fondée Part C: monitoring and En attente 33 / Etude de danger et ATEX IBRD / 79170 A priori sur la qualité et le Open - International 200,000.00 0.00 2012-06-01 2012-06-06 2013-05-21 2013-07-30 2014-07-02 2014-07-14 2015-06-29 2016-03-25 capacity strengthening d'exécution coût Sélection fondée 34 / Assistance technique de Part C: monitoring and En attente IBRD / 79170 A priori sur la qualité et le Open - International 250,000.00 0.00 2012-06-01 2012-06-06 2013-05-21 2013-07-30 2014-07-02 2014-11-14 2015-07-31 2016-04-26 l'étude de danger et ATEX capacity strengthening d'exécution coût 35 / Mise en place d'un Sélection fondée Part C: monitoring and En cours système de gestion IBRD / 79170 A priori sur la qualité et le Open - International 1,007,562.00 0.00 2011-02-02 2013-01-22 capacity strengthening d'exécution commerciale coût 49 / Réalisation d’un programme d’analyses Part B: improvement of the complémentaires des discharge of the remaining Sélection au En attente IBRD / 79170 A posteriori Open - National 25,000.00 0.00 2016-02-05 2016-02-06 2016-04-20 2016-07-04 sédiments de dragage dans la TWW in the Mediterranean moindre coût d'exécution zone maritime de l’émissaire Sea en mer  8 / Etude d'exécution pour la réalisation de l'émissaire en Sélection fondée Part C: monitoring and En cours mer pour l'éloignement des IBRD / 79170 A priori sur la qualité et le Open - International 1,045,198.00 0.00 2014-10-03 2014-10-06 2016-02-02 2016-04-05 2017-01-19 2017-07-17 2017-08-16 2019-05-08 capacity strengthening d'exécution eaux usées épurées du pôle coût d'épuration Sud Mèliane 7 / Etude d'impact Sélection fondée environnementale et sociale Part C: monitoring and En attente IBRD / 79170 A posteriori sur la qualité et le Open - International 200.00 0.00 2017-04-16 2017-05-10 2017-12-21 2018-01-27 2018-03-13 2018-07-11 2018-08-10 2019-02-06 de la nouvelle STEP au Nord capacity strengthening d'exécution coût de Tunis 9 / Etude d'impact Sélection fondée environnementale et sociale Part C: monitoring and En attente IBRD / 79170 A posteriori sur la qualité et le Open - International 60,000.00 0.00 2016-09-06 2016-09-07 2017-08-15 2017-10-14 2017-12-13 2018-05-12 2018-06-11 2018-12-08 du projet de réalisation de capacity strengthening d'exécution coût l'émissaire en mer Tunis Sud 59 / Contrôle et suivi des Part C: monitoring and Sélection au En attente travaux de réalisation du IBRD / 79170 A posteriori Open - National 5,360.00 0.00 2018-08-15 2018-09-05 2018-10-19 2018-11-16 2018-12-16 2019-01-20 2019-02-24 2019-08-23 capacity strengthening moindre coût d'exécution nouveau Datacenter 60 / Travaux géotechniques du nouveau site proposée à El Part C: monitoring and Sélection au En attente IBRD / 79170 A posteriori Open - National 17,860.00 0.00 2018-11-15 2018-12-06 2019-01-19 2019-02-16 2019-03-18 2019-04-22 2019-05-27 2019-11-23 Hessiyene pour la nouvelle capacity strengthening moindre coût d'exécution STEP au Nord de Tunis INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 19 / Renforcement des mécanismes de suivi pour Part C: monitoring and En attente permettre la mise en œuvre IBRD / 79170 A priori Individuel Open 21,840.00 0.00 2013-09-25 2013-12-26 2014-02-11 2014-03-04 2016-08-20 capacity strengthening d'exécution du PGE dans la zone d'influence du projet ( partie terrestre) 10 / Mise en place d'un PGES lors de la phase travaux du Part C: monitoring and En cours projet financé par la BEI IBRD / 79170 A posteriori Individuel Limited 22,500.00 0.00 2017-04-20 2017-10-05 2017-07-03 2017-08-02 2017-08-16 2019-08-16 capacity strengthening d'exécution (Transfert des EE de Choutrana tronçon n°1) 75 / Sélection d'un consultant pour la mission de vérification de probité des Part C: monitoring and négociations entre l'ONAS et IBRD / 86440 A priori Individuel Limited 10,000.00 15,593.42 Signé 2020-12-30 2021-01-04 2021-01-06 2021-01-06 2021-01-19 2021-02-02 2021-02-05 2021-02-05 2021-02-26 capacity strengthening le groupement dirigé par SUEZ pour le lot 2 du projet de concession Page 3