The World Bank Implementation Status & Results Report Tanzania Renewable Energy CDM Program of Activities (P127585) Tanzania Renewable Energy CDM Program of Activities (P127585) AFRICA EAST | Tanzania | Energy & Extractives Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2014 | Seq No: 2 | ARCHIVED on 27-May-2021 | ISR46698 | Implementing Agencies: Rural Energy Agency, REPUBLIC OF TANZANIA Key Dates Key Project Dates Bank Approval Date: 25-Apr-2014 Effectiveness Date: 31-Mar-2014 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 31-Dec-2023 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the CDM-PoA project is to increase the capacity of renewable energies installed - including hydro, solar, wind and/or biomass technologies for electricity generation. The subprojects can be: isolated mini-grids, connected to the national grid or connected to one of the national utility’s isolated grids. Over the long term, this will lead to increased access to modern energy services in Tanzania. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Clean Development Mechanism (CDM) Program of Activities (PoA) was registered in May 8, 2014. Nine CDM Component Project Activities (sub-projects) were included in the CDM PoA by the UNFCCC. The first verification of the five operating sub-projects for the period of 2015-2016 yielded 16,834 Certified Emission Reductions (CERs). The second verification for the 2017yielded 19,871 CERs. The third verification for 2018 yielded 23,149 CERs. All payments related to the verified CERs have been disbursed to REA. The verification of Emission Reductions generated in the 2019-2020 period is ongoing. Risks 5/27/2021 Page 1 of 4 The World Bank Implementation Status & Results Report Tanzania Renewable Energy CDM Program of Activities (P127585) Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Moderate Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Substantial Substantial Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and -- Substantial Substantial Sustainability Fiduciary -- Moderate Low Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Substantial Substantial Results PDO Indicators by Objectives / Outcomes Greenhouse gas emission reduction achieved IN00992742 ►Reduce greenhouse gas emissions by 116,268 tCO2e from 2015 to 2020 from the displacement of fossil fuel electricity generation through the generation of small hydropower in Tanzania. (Metric ton, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 36,705.00 59,854.00 116,268.00 Date 01-Dec-2015 10-Feb-2020 17-May-2021 31-Dec-2022 Intermediate Results Indicators by Components Renewable energy generation capacity IN00992743 ►Installed renewable energy generation capacity (Megawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.00 12.00 12.00 Date 01-Jan-2014 17-Nov-2020 17-May-2021 31-Dec-2022 Performance-Based Conditions 5/27/2021 Page 2 of 4 The World Bank Implementation Status & Results Report Tanzania Renewable Energy CDM Program of Activities (P127585) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P127585 TF-16921 Effective USD 4.53 1.01 3.52 0.32 0.33 31% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P127585 TF-16921 Effective 31-Mar-2014 31-Mar-2014 31-Mar-2014 31-Dec-2023 31-Dec-2023 Cumulative Disbursements PBC Disbursement Achievement Disbursed amount in Disbursement % PBC ID PBC Type Description Coc PBC Amount Status Coc for PBC 5/27/2021 Page 3 of 4 The World Bank Implementation Status & Results Report Tanzania Renewable Energy CDM Program of Activities (P127585) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/27/2021 Page 4 of 4