Public Disclosure Copy The World Bank Implementation Status & Results Report ELECTRICITY ACCESS EXPANSION PROJECT (P151618) ELECTRICITY ACCESS EXPANSION PROJECT (P151618) EAST ASIA AND PACIFIC | Solomon Islands | Energy & Extractives Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2017 | Seq No: 2 | ARCHIVED on 17-May-2017 | ISR27929 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:20-Jul-2016 Effectiveness Date:02-Nov-2016 Original Closing Date:30-Jun-2018 Revised Closing Date:30-Jun-2018 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to increase access to electricity services in low-income areas of Solomon Islands. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Satisfactory  Moderately Satisfactory Implementation Status and Key Decisions The project was approved in July 20, 2016. It was declared effective and implementation formally commenced on November 2, 2016. The first connections were completed in January 2017 and project implementation is expected to accelerate over the next few months. 5/17/2017 Page 1 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report ELECTRICITY ACCESS EXPANSION PROJECT (P151618) Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall  --  Moderate  Substantial Comments There is substantial risk linked to the institutional capacity for implementation. SP has been advised to recruit a project manager asap. Results Project Development Objective Indicators PHINDPDOTBL Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 91.00 14,620.00 Date 05-Apr-2016 30-Nov-2016 09-May-2017 30-Jun-2018 PHINDPDOTBL Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 44.00 7,050.00 PHINDPDOTBL People in urban and peri urban areas of Honiara provided with access to electricity by household connection -Grid (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 91.00 12,113.00 Date 30-Apr-2016 30-Nov-2016 09-May-2017 30-Jun-2018 5/17/2017 Page 2 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report ELECTRICITY ACCESS EXPANSION PROJECT (P151618) PHINDPDOTBL Peopleprovided with access to electricity from minigrid connections by household connection - Other renewable sources (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,507.00 Date 30-Apr-2016 30-Nov-2016 09-May-2017 30-Jun-2018 Overall Comments Intermediate Results Indicators PHINDIRITBL Community contribution in the total project costs (percentage) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 400.00 234,500.00 Date 04-May-2016 30-Nov-2016 09-May-2017 30-Jun-2018 PHINDIRITBL Total community contribution (US$) (Amount(USD), Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 400.00 234,500.00 5/17/2017 Page 3 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report ELECTRICITY ACCESS EXPANSION PROJECT (P151618) PHINDIRITBL Number of LED bulbs distributed and installed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4,250.00 Date 04-May-2016 30-Nov-2016 09-May-2017 30-Jun-2018 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P151618 TF-A2923 Effective USD 2.23 2.23 0.00 0.01 2.21 1% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P151618 TF-A2923 Effective 20-Jul-2016 15-Aug-2016 02-Nov-2016 30-Jun-2018 30-Jun-2018 Cumulative Disbursements 5/17/2017 Page 4 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report ELECTRICITY ACCESS EXPANSION PROJECT (P151618) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/17/2017 Page 5 of 5 Public Disclosure Copy