The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Ethiopia Urban Institutional and Infrastructure Development Program (P163452) AFRICA | Ethiopia | Urban, Resilience and Land Global Practice | Requesting Unit: AFCE3 | Responsible Unit: SAFU2 IBRD/IDA | Program-for-Results Financing | FY 2018 | Team Leader(s): Gyongshim An, Berhanu Legesse Ayane, Dinkneh Tefera Seq No: 5 | ARCHIVED on 13-Feb-2020 | ISR40380 | Created by: Dinkneh Tefera on 21-Jan-2020 | Modified by: Gyongshim An on 04-Feb-2020 Program Development Objectives Program Development Objective (from Program Appraisal Document) The Program Development Objective (PDO) is to enhance the institutional performance of participating Urban Local Government (ULGs)to develop and sustain urban infrastructure, services, and local economic development. Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Implementation Status and Key Decisions Overall Program implementation is on track. The first annual performance assessment and quality assurance review were completed successfully. The second annual performance assessment is ongoing. The Program is relatively at early stage of implementation with procurement activities ongoing at the MUDCo and city levels for various types of consultancy and civil works contracts. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P163452 IDA-61960 Effective USD 127.00 127.00 0.00 28.94 94.14 24% P163452 IDA-61970 Effective USD 200.00 200.00 0.00 30.71 169.29 15% P163452 IDA-D2770 Effective USD 273.00 273.00 0.00 113.02 152.92 42% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P163452 IDA-61960 Effective 14-Mar-2018 20-Mar-2018 08-Jun-2018 07-Jul-2023 07-Jul-2023 2/13/2020 Page 1 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) P163452 IDA-61970 Effective 14-Mar-2018 20-Mar-2018 08-Jun-2018 07-Jul-2023 07-Jul-2023 P163452 IDA-D2770 Effective 14-Mar-2018 20-Mar-2018 08-Jun-2018 07-Jul-2023 07-Jul-2023 DLI Disbursement Achievement Disbursed amount in Disbursement % for DLI ID DLI Type Description Coc DLI Amount Status Coc DLI Loan: IDA61960-001 Elig. ULG strengthened Partially 2 Regular XDR 50,900,000.00 14,126,540.89 28 % Inst. Performance Achieved Elig. ULG implemented Partially 3 Regular XDR 24,120,000.00 6,848,896.08 28 % quality infra. & m Achieved Elig. ULG strengthened 4 Regular XDR 14,180,000.00 Not Achieved 0.00 perf. on LED Loan: IDA61970-001 Elig. ULG hv strengthened Partially 2 Regular USD 113,841,015.00 20,491,383.00 18 % inst'l perform Achieved Elig. ULG hv implemented Partially 3 Regular USD 53,952,180.00 9,721,186.00 18 % quality infra Achieved Elig. ULG hv strengthened 4 Regular USD 31,706,805.00 Not Achieved 0.00 perf. on LED Program Action Plan To ensure sufficient capacity in MUDCo to manage the UIIDP, the UIIDP Unit will be further Action Description enhanced to 32 staff. MUDCo will fill its vacant positions and engage additional staff to fulfill the 32 staff positions Source DLI# Responsibility Timing Timing Value Status Ministry of Urban Other Development and Due Date 08-Jun-2018 Completed Constr Completion Measurement --- Comments All positions filled except 7 To ensure that the independent APA is completed on time, MUDCo will initiate the Action Description procurement process for selection and assignment of independent consultants for the APA through multi-year contract Source DLI# Responsibility Timing Timing Value Status Ministry of Urban Other Development and Due Date 31-Aug-2018 Completed Constr Completion Measurement --- Comments Completed 2/13/2020 Page 2 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) To enable the supply-side capacity building activities for ULGs, MUDCo will sign agreement(s) (memorandum of Action Description understanding) with relevant federal, and regional training institutions for course design and administration for new ULGs. Source DLI# Responsibility Timing Timing Value Status Other MUDCo Due Date 08-Jun-2018 Delayed Completion Measurement --- Comments To be followed up by FMT Capacity Building Specialist To ensure sufficient capacity in regional governments to support the up-scaled UIIDP, the regional governments will Action Description fill staffing gaps and procure and deploy RMTs. Source DLI# Responsibility Timing Timing Value Status Regional Other Due Date 08-Jun-2018 Completed governments Completion Measurement --- Comments Completed except for a few positions Annual performance review and audit on environment and social management: Produce the Performance Action Description Assessment Manual, as part of the Program Operation Manual and share with 117 ULGs Source DLI# Responsibility Timing Timing Value Status Other MUDCo Due Date 28-Sep-2018 Completed Completion Measurement --- Comments Produced as part of the POM and APA Guidelines and shared with the 117 ULGs Establish Program technical subcommittee comprising key technical staff of MUDCo and MoFEC including Action Description environmental and social management. Source DLI# Responsibility Timing Timing Value Status Other MUDCo Due Date 08-Jun-2018 Completed Completion Measurement Briefing note on established Program technical subcommittee Comments This was revised by MUDCo to avoid running parallel structures/committees for both ULGDP II & UIIDP. Revision of the program’s Employment / Job Creation Guideline to better clarify ways in which the program Action Description contributes to temporary versus permanent employment Source DLI# Responsibility Timing Timing Value Status 2/13/2020 Page 3 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Other MUDCo Due Date 28-Jun-2019 In Progress Completion Measurement --- Comments A consultant is recruited and commences on Nov 15, 2019. Action Description Identify needs and develop local DRM and emergency plan (building on woreda risk profile) Source DLI# Responsibility Timing Timing Value Status MUDCo and Technical Due Date 30-Jun-2020 Not Yet Due NDRMC Completion Measurement --- The task team secured a TF from GFDRR and mobilized technical experts to support the Government of Ethiopia’s Comments efforts in building resilience against select natural hazards at the local level by providing technical assistance to 2 disaster-prone ULGs With NDRMC, carry out detailed risk assessment to develop national urban DRM plan; establish information and Action Description warning system; and develop training program and guidance notes Source DLI# Responsibility Timing Timing Value Status MUDCo and Technical Due Date 30-Jun-2020 Not Yet Due NDRMC Completion Measurement --- Comments Development and adaptation of (a) code of conduct in employment and sub-project contract documents for women’s Action Description rights in workplace and (b) potential procedures for addressing complaints Source DLI# Responsibility Timing Timing Value Status Technical MUDCo Due Date 28-Jun-2019 Delayed Completion Measurement UIIDP Code of conduct document and protocol/procedure document Comments To be followed up by newly appointed FMT Gender Specialist Action Description Conduct FM Trainings for cities in 6 agreed priority areas to build capacities and reduce risks Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Yearly Not Yet Due Completion Measurement • Training's conducted Comments • MoF to prepare TOR 2/13/2020 Page 4 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Prepare detailed annual training report and submit to the WB on the conduct of the FM trainings noted above (By Action Description August 30 of each year for past year trainings) Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Yearly In Progress Completion Measurement Training report submitted Comments To be followed up by FMT Capacity Building Specialist Action Description Program funds need to be transferred in the agreed time to cities Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MoF and BOFED Recurrent Yearly Completed Completion Measurement Funds transfer data reported on IFRs Comments Funds transfer is reported in IFRs Ensure correct recording of budget figures in accounts/IBEX. Close follow up is required by stakeholders on low Action Description budget utilization Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MoFEC and MUDCo Recurrent Yearly Completed Completion Measurement Reported on APA and IFRs Comments Reflected in APA and IFRs Transparency -MUDCo should disclose on its website the program annual budget, in year budget executions, and Action Description program financial and VfM external audit reports. Cities should also disclose annual budget, in year budget executions, and external audits Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo and ULGs Recurrent Yearly In Progress Completion Measurement APA Comments • ULGs are disclosing budget information as reported in the APA. Follow up to be done on MUDCo website. For VFM audit findings -Prepare time bounded action plan for rectifying audit findings, follow up with Cities. Prepare Action Description regular follow up status report on rectified audit findings Source DLI# Responsibility Timing Timing Value Status 2/13/2020 Page 5 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Fiduciary Systems MUDCo Recurrent Yearly Completed Completion Measurement Reports submitted by MUDCo Comments Done and reported in APA. FMT Financial Management Specialist to obtain the rectification plans Provide intensive procurement and contracts management training to staff of the ULGs. The training Action Description shall include ULGs Procurement staff, and staff involved in the implementation of procurement (within 6 months of effectiveness and continuous) Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Continuous In Progress Completion Measurement Training Reports and contract management guidelines/manuals Intensive training provided by both MUDCo and WB to procurement staff and Ministry Tender Award Committee Comments members. The ToRs of RPPPAAs and APA should include adequate provisions to closely examine any potential loopholes in Action Description the procurement process which might be source of complaints (each annual audit / assessment and continuous) Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Continuous In Progress Completion Measurement Approved ToRs Comments Done and reported in APA The POM to state that ICB contracts should also be published in the international media such as UNDB online (by Action Description program effectiveness and continuous) Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Continuous In Progress Completion Measurement POM Comments Done As part of the POM, MUDCo to prepare and agree with the WB on the procedures of use of SOEs and MSEs. Non- Action Description MSE actors will not be excluded from bidding with MSEs of similar capacity. Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Due Date 08-Jun-2018 In Progress Completion Measurement POM Comments Consultants being procured to prepare the guidelines. RFP issued and closing this week. 2/13/2020 Page 6 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Include a provision in the POM for the ULGs to state in the bidding documents to exclude award to WB debarred and Action Description suspended firms Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Due Date 08-Jun-2018 Completed Completion Measurement POM Comments Done Provide Regional Public Procurement and Property Administration Agencies and Internal Audit units of ULGs with Action Description Procurement Audit Training (within four months of effectiveness and continuous) Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems MUDCo Recurrent Continuous Delayed Completion Measurement Training reports Comments FPPPAA to prepare TOR FEACC will share the data with the WB Semi-annually on Fraud and Corruption, public grievances, procurement Action Description complaints in regard to program activities at the ULG level. Source DLI# Responsibility Timing Timing Value Status FEACC / REACCs, Fiduciary Systems Recurrent Semi-Annually Completed ULGs Completion Measurement Semi annual report Comments Done Assign complaint handling focal person for recording processing and reporting F&C, grievances and procumbent Action Description complaints at ULGs Source DLI# Responsibility Timing Timing Value Status Fiduciary Systems ULGs / MUDCo Due Date 28-Jun-2019 Completed Completion Measurement APA Comments Done Allocate sufficient TA resource and assign coordinating mobile team focal person/ Ethics and Anticorruption officer in Action Description MUDCo and RMT for supporting/ building accountability and monitoring fiduciary personnel at ULGs Source DLI# Responsibility Timing Timing Value Status 2/13/2020 Page 7 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Fiduciary Systems MUDCo / BUD Due Date 28-Jun-2019 Completed Completion Measurement APA Comments Done Develop a prototype template and provide cascaded training to streamline the F & C, public grievance and Action Description procurement function, recording and reporting arrangements in those ULGs where public grievance office also follow up F & C cases. Source DLI# Responsibility Timing Timing Value Status FEACC / REACCs, Fiduciary Systems Due Date 28-Jun-2019 In Progress MUDHo Completion Measurement --- Comments TOR prepared by FEACC Provide cascaded training on the functional roles, process of tracking, recording, data organization, reporting and Action Description related methods, approaches. Source DLI# Responsibility Timing Timing Value Status FEACC / REACCs, Fiduciary Systems Due Date 30-Jun-2020 Not Yet Due MUDHo Completion Measurement -- Comments TOR to be prepared by FEACC Use public media for disclosure and information sharing related to program activities, providing awareness to the Action Description public and enhancing the transparency of the procedures of grievance/complaint handling system. Source DLI# Responsibility Timing Timing Value Status FEACC / REACCs, Fiduciary Systems Recurrent Continuous In Progress MUDHo Completion Measurement -- Comments Initiated by FEACC Establishing the Environmental and Social Management System at new 73 UIIDP cities and strengthen at MUDCo, Action Description BoU and previous ULGDP II 44 cities Source DLI# Responsibility Timing Timing Value Status Environmental and Social MUDCo and BUDs Due Date 08-Jun-2018 Completed Systems Completion Measurement Established and strengthened ESMS Updated ESMG and RSG Staffs in place Screening reports 2/13/2020 Page 8 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Safeguards instruments are prepared, as required ESMSG and RSG updated and already in use by ULGs. Staff on place and screening reports done as reported in Comments APA Ensure that the federal and RMTs are adequately staffed with environment gender and social management Action Description specialists having appropriate skills Source DLI# Responsibility Timing Timing Value Status Environmental and Social MUDCos and BUDs Due Date 08-Jun-2018 In Progress Systems Completion Measurement The mentioned staffing in place, Program Reports Comments Done as reported in other sections of this report Procure and ensure implementation of standard ULG environment and social management training program from Action Description designated centres of excellence. Availing the required facilities for environmental and social management activities at all levels Source DLI# Responsibility Timing Timing Value Status Environmental and Social MUDCo, BUDs and Recurrent Continuous In Progress Systems ULGs Prepared Capacity building and Training plans Training reports Procurement reports on resources and facilities Completion Measurement TORs for training being prepared by FMT Environment and Social Management Specialists with assistance of FMT Comments Capacity Building Specialist Increase stakeholders’ awareness on social and environmental impacts of UIIDP sub-projects by Action Description developing a guideline for setting service delivery standards, and citizen charters including vulnerable groups and organize awareness raising sessions Source DLI# Responsibility Timing Timing Value Status MUDCo, BUDs, Environmental and Social ULGs, MoEFCC and Recurrent Continuous In Progress Systems REFA Developed service delivery standards, and citizen charters Briefing note on conducted awareness and sensitization program Completion Measurement Environment and Social Management Implementation Reports Training reports Comments To be followed up by FMT Environment and Social Management Specialists 2/13/2020 Page 9 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Broaden stakeholders’ involvement by including and working closely with the offices in charge of environmental Action Description protection, Labour and Social Affairs and WCOs to improve planning and implementation of environment and social management instruments Source DLI# Responsibility Timing Timing Value Status MUDCo, BUD, Environmental and Social ULGs, MoEFCC, Recurrent Continuous In Progress Systems REFA, MoLSA Briefing note on coordination mechanism of the various relevant parties Annual Plans, and progress reports Completion Measurement Joint monitoring reports Comments To be followed up by FMT Environment and Social Management Specialists Develop a harmonized and standardized Environment and Social Audit ToRs; and ensure quarterly performance Action Description review and annual environmental and social audit. Source DLI# Responsibility Timing Timing Value Status Environmental and Social REFA, MUDCo Recurrent Quarterly Completed Systems Developed TOR Quarterly performance review report Completion Measurement Annual audit report Comments Done and audit reports submitted to MUDCo and WB. Ensure management of community and worker’s health and safety risk and develop SMP as required, make available Action Description safety protection materials, tools and Personal Protective Equipment over the program implementation period Source DLI# Responsibility Timing Timing Value Status Environmental and Social MUDCo, BoUD and Recurrent Continuous In Progress Systems ULGs Developed SMP Included EHS code of practice on contract document Completion Measurement Progress report and incident notification checklist Comments To be followed up by FMT Environment and Social Management Specialists Conduct adequate consultations where land (communal or private) is acquired and/or vulnerable person is involved Action Description and ensure proper documentation of the same 2/13/2020 Page 10 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Source DLI# Responsibility Timing Timing Value Status Environmental and Social MUDCo, BUD, ULGs Recurrent Continuous In Progress Systems Minutes of Consultations Completion Measurement Implementation Reports Comments Done as reported in APA Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Substantial Substantial Substantial Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Substantial Substantial Substantial Stakeholders Moderate Moderate Moderate Other Moderate Moderate Moderate Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Enhance institutional performance of ULGs to develop and sustain infrastructure, services, and LED IN00797480 ►People provided with improved urban living conditions (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6,600,000.00 Date 14-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments 2/13/2020 Page 11 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) IN00797486 People provided with improved urban living conditions - Female (RMS requirement) (Number, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 15-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 IN00797487 ►Cities with improved livability, sustainability, and/or management (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 117.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797488 ►Composite institutional performance of participating ULGs, averaged across all cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 83.00 83.00 85.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797489 ►Composite performance for achievement urban infrastructure and service targets, maintenance performance and VFM in investments by ULGs, averaged across all cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 84.00 84.00 85.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797490 ►Composite perfomance for achievement of LED, urban resilience, and gender targets by ULGs, averaged across all cities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments Intermediate Results Indicators by Results Areas Institutional performance IN00797491 ►ULGs that achieve an increase of own source municipal revenue of at least 10 percent over the previous year under UIIDP (Number, Custom) 2/13/2020 Page 12 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797495 ►ULGs with timely audits (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 44.00 111.00 111.00 117.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797499 ►ULGs with clean (unqualified) audit (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 13.00 25.00 25.00 35.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments Infrastructure and Maintenance IN00797492 ►Urban cobblestone roads built or rehabilitated under UIIDP (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797496 ►Urban gravel roads built or rehabilitated under UIIDP (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 900.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797500 ►Serviced land for industry, MSE sheds, and housing under UIIDP (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target 2/13/2020 Page 13 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Value 0.00 0.00 0.00 15,500.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797503 ►Drains built or rehabilitated under UIIDP (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,000.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797506 ►Public parks and greenery built or rehabilitated under UIIDP (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 400.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797509 ►ULGs that execute at least 80 percent of their O&M budget under UIIDP (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments Urban resilience, local economic development, job creation and gender mainstreaming IN00797493 ►Temporary jobs created under UIIDP-supported infrastructure works (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600,000.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Will be updated after the submission of the annual report in August 2020. Comments IN00797498 of which female (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 2/13/2020 Page 14 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 IN00797501 ►People employed in firms provided with serviced land and in MSE sheds under UIIDP (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 151,875.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797504 Of which female (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 40.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 IN00797507 ►ULGs that have established emergency response unit, and prepared emergency response plan (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797510 ►ULGs for which citizen fora (between government, residents and private sector, including on plans and budgets) have been held at least twice a year, with at least 50 percent women participation (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 117.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797511 ►ULGs that implement 80 percent of the budget presented in the annual gender development plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 90.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments Capacity Building IN00797494 ►ULGs that implement at least 80 percent of the budget presented in the annual capacity building plans (Number, Custom) 2/13/2020 Page 15 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 41.00 41.00 90.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797497 ►Regions that implement at least 80 percent of the budget presented in the annual capacity building plans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4.00 4.00 8.00 Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797502 ►Urban development program updated and financing strategy a. developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments IN00797505 b. approved (Yes/No, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes IN00797508 ►MUDCo procures and conducts APA in a timely fashion (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Yes Yes Yes Yes Date 08-Jun-2018 22-Nov-2019 22-Nov-2019 30-Jun-2023 Comments Disbursement Linked Indicators DLI_IND_TABLE ►DLI 1 Eligible ULGs have achieved Program minimum conditions (Output, 109,320,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 27,332,200.00 27,332,200.00 109,320,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- 2/13/2020 Page 16 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) This will be updated after the quality assurance review in June 2020. Comments ►DLI 2 Eligible ULGs have strengthened institutional performance (Intermediate Outcome, 190,090,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 40,682,269.00 40,682,269.00 190,090,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 3 Eligible ULGs have implemented quality infrastructure and maintenance activities and ensured value for money (Intermediate Outcome, 90,090,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 19,503,138.00 19,503,138.00 90,090,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 4 Eligible ULGs have strengthened performance on LED, urban resilience, and gender mainstreaming (Intermediate Outcome, 52,950,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 0.00 0.00 52,950,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 5 Regional support teams have delivered effective capacity building services to Eligible ULGs in urban institutional and infrastructure development (Output, 27,880,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 6,970,000.00 6,970,000.00 2,788,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 6 Regional Government Audit Agencies (ORAGs) have carried out timely audits of Eligible ULGs' financial reports (Output, 14,960,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 2/13/2020 Page 17 of 18 The World Bank Implementation Status & Results Report Ethiopia Urban Institutional and Infrastructure Development Program (P163452) Value 0.00 3,512,000.00 3,512,000.00 14,960,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 7 Regional environment protection, forest and climate change authorities (REFAs) have completed timely review of Eligible ULGs environmental and social safeguards compliance (Output, 13,120,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 3,220,000.00 3,220,000.00 13,120,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 8 Regional Revenue Bureaus (RRBs) have supported Eligible ULG revenue mobilization (Output, 7,040,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 1,151,250.00 1,151,250.00 7,040,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 9 Regional Public Procurement and Property Administration Agencies (RPPPAA) conduct timely and quality procurement audit of Eligible ULGs accounts and performance (Output, 7,040,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 1,755,000.00 1,755,000.00 7,040,000.00 Date -- 22-Nov-2019 21-Jan-2020 -- This will be updated after the quality assurance review in June 2020. Comments ►DLI 10 Strengthening institutional performance, infrastructure and service delivery, maintenance and job creation for 44 ULGs (prior results) (Outcome, 63,740,000.00, 0%) Baseline Actual (Previous) Actual (Current) End of Year 5 Value 0.00 63,740,000.00 63,740,000.00 63,740,000.00 Date -- 22-Nov-2019 22-Nov-2019 -- Comments 2/13/2020 Page 18 of 18