INTEGRTED FOREST ECOSYSTEM MANAGEMENT PROJECT General Procurement Thresholds and Methods of Procurement: The following methods of procurement shall be used for procurement under the project. It has been agreed that if a invitation for a bid is comprised of several packages, lots or slices, and invited in the same invitation for bid, then the aggregate value of the whole package determines the applicable threshold amount for procurement and also for the review by the Bank. The national competitive bidding (NCB) conditions will be part of the Financing Agreement. Expenditur Contract Procurement Bank Prior Review e Category Value Method (USD) >= 5, 000 ICB All ICB contracts 000 < 5, NCB NA Civil Works 000,000 <50 000 Shopping NA NA DC >= 5, 000 000 >= 1, 000 ICB All ICB contracts 000 <1, 000 NCB NA Goods 000 <100 000 Shopping NA NA DC >= 1, 500 000 NA QCBS, QBS, FBS, All contracts >= USD Consultant LCS and CQS* 500,000 for firms; all Services NA SSS contracts >= USD NA IC 200,000 for individuals; Notes: ICB – International Competitive Bidding All TORs NCB – National Competitive Bidding DC – Direct Contracting QCBS – Quality and Cost Based Selection QBS – Quality Based Selection FBS – Fixed Budget Selection LCS – Least Cost Selection *CQS – Selection Based on Consultants’ Qualification below $300,000 depending on the nature of assignment SSS – Single (or Sole) Source Selection IC – Individual Consultant selection procedure NA – Not Applicable July 9, 2010 Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1. PROCUREMENT PLAN (July 2015) Date WB of Proc. Revie Item Contra Contract Description Metho w № ct d (Prior/ Signin Post) g GOODS Component 1. Forest Sector Institutional Reform No goods Component 2. Strategic Investments and Piloting of Sustainable Management Approaches NCB/S 1 Financing the implementation of INRMPs Prior/Post H Investments like afforestation of short NCB/S 2 rotation tree species, natural Prior/Post H regeneration through thinning etc. Component 3. Information and Monitoring and Evaluation National Forest Inventory (NFI) and the 9/1/20 3 Management Forest Inventory (MFI) ICB Prior 16 (Non-consulting services) 6/1/20 4 Office equipment for FMIS NCB Prior 17 Component 4. Project Management, Monitoring and Evaluation 3/1/20 5 Computers for PCU SH Prior 16 3/1/20 6 Furniture for PCU SH Post 16 3/1/20 7 Car for PCU SH Post 16 3/1/20 8 Accounting software for PCU SH Post 16 CONSULTANCY LARGE Date WB Select of Revie Item . Contra Contract Description w № Metho ct (Prior/ d Signin Post) g July 9, 2010 Component 1. Forest Sector Institutional Reform Support of introduction of new principles 9/1/20 1 QCBS Prior of planning, budgeting and monitoring /a 16 Component 2. Strategic Investments and Piloting of Sustainable Management Approaches Preparation of the Integrated Natural 9/1/20 2 QCBS Prior Resource Management Plans (INRMPs) 16 Component 3. Information and Monitoring and Evaluation The Forest Management Information 1/1/20 3 QCBS Prior System (FMIS) 17 Component 4. Project Management, Monitoring and Evaluation 9/1/20 4 Project Audit LCS Prior 16 July 9, 2010 PROCUREMENT Kyrgyz Republic : Integrated Forest Ecosystem Management PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2018-04-04 2021-09-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151102 GPN Date: 2020-09-11 Project Name: Integrated Forest Ecosystem Management Loan / Credit No: IDA / D0950, IDA / 57430 S Executing Agency(ies): tate Agency on Environment Protection and Forestry WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IFEMP-INVEST-W-SH-10- Strategic Investments and Request for Single Stage - One 2019-08- 2019 / Fencing in Aksu IDA / D0950 Piloting of Sustainable Post Open - National 11,912.00 0.00 Canceled 2019-06-05 2019-07-05 Quotations Envelope 05 leskhoz 8 hectare Management Approaches IFEMP-INVEST-W-SH-1-2019 / Installation of fencing and soil preparation for planting Strategic Investments and Request for Single Stage - One 2019-11- forest crops, fast-growing IDA / D0950 Piloting of Sustainable Post Open - National 27,696.00 27,058.67 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 plantations and orchards in Management Approaches Uch-Korgon LH for the current and next years. IFEMP-INVEST-W-SH-2-2019 / Installation of fencing and soil preparation for planting Strategic Investments and Request for Single Stage - One 2019-11- forest crops, fast-growing IDA / D0950 Piloting of Sustainable Post Open - National 290,772.00 168,911.54 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 plantations and orchards in Management Approaches Naryn LH in the current and next years. IFEMP-INVEST-W-SH -3- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 80,655.00 70,213.58 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Batken LH for the current and next years. IFEMP-INVEST-W-SH -4- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 109,980.00 82,803.43 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Toktogul LH for the current and next years. IFEMP-INVEST-W-SH-5-2019 / Installation of fencing and soil preparation for planting Strategic Investments and Request for Single Stage - One 2019-11- forest crops, fast-growing IDA / D0950 Piloting of Sustainable Post Open - National 136,138.00 93,094.05 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 plantations and orchards in Management Approaches Talas LH for the current and next years. IFEMP-INVEST-W-SH -6- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 67,031.00 46,563.62 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Aksy LH for the current and next years. IFEMP-INVEST-W-SH -7- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 202,650.00 141,188.34 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Kara-Kuldzha LH for the current and next years. IFEMP-INVEST-W-SH -8- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast- Request for Single Stage - One 2019-11- IDA / D0950 Piloting of Sustainable Post Open - National 128,234.00 78,687.27 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 growing plantations and Quotations Envelope 29 Management Approaches orchards in Toskol-Ata (Kochkor-Ata) LH for the current and next years. IFEMP-INVEST-W-SH-9-2019 / Installation of fencing and soil preparation for planting Strategic Investments and Request for Single Stage - One 2019-11- forest crops, fast-growing IDA / D0950 Piloting of Sustainable Post Open - National 194,000.00 145,193.60 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 plantations and orchards in Management Approaches Karakol (Aksuu) LH for the current and next years. IFEMP-INVEST-W-SH-11- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 113,259.00 80,647.33 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in At-Bashy LH for the current and next years. IFEMP-INVEST-W-SH-12- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 64,191.00 47,463.04 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Chui LH for the current and next years. Page 1 IFEMP-INVEST-W-SH-13- 2019 / Installation of fencing and soil preparation for Strategic Investments and Request for Single Stage - One 2019-11- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Open - National 72,780.00 37,256.77 Completed 2019-08-14 2019-08-30 2019-09-09 2019-09-18 Quotations Envelope 29 growing plantations and Management Approaches orchards in Frunze LH for the current and next years. IFEMP-INVEST-W-SH-1/1- 2019 / Installation of fencing and soil preparation for Strategic Investments and planting forest crops, fast - 2020-01- IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 27,696.00 36,983.00 Completed 2019-10-30 2019-10-31 2019-10-31 2019-11-01 2019-11-01 2019-11-04 growing plantations and 30 Management Approaches orchards in Uch-Korgon LH for the courrent and next years IFEMP-INVEST-W-SH-12/1- 2019 / Installation of fencing and soil preparation for Strategic Investments and 2020-01- planting forest crops, fast - IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 64,191.00 53,197.61 Completed 2019-10-30 2019-10-31 2019-10-31 2019-11-01 2019-11-01 2019-11-04 30 growing plantations and Management Approaches orchards in Chui LH for the courrent and next years IFEMP-INVEST-W-SH-5/1 - 2019 / Installation of fencing and soil preparation for Strategic Investments and 2020-01- planting forest crops, fast- IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 136,138.00 110,482.26 Completed 2019-10-30 2019-11-01 2019-10-31 2019-11-01 2019-11-01 2019-11-04 30 growing plantations and Management Approaches orchards in Talas LH for the courent and next years IFEMP/INVEST/W/NCB-1- 2020 / Installation of fences and soil preparation for Strategic Investments and Single Stage - One 2020-07- planting forest crops in Chui, IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 290,714.00 246,772.90 Signed 2020-02-17 2020-02-21 2020-02-19 2020-02-20 2020-03-11 2020-03-13 2020-03-20 2020-04-30 2020-04-20 2020-06-05 Envelope 19 Toktogul, Uch-Korgon, Management Approaches Batken, Karakol, Naryn, At- Bashy leskhozes IFEMP/INVEST/W/NCB-4- 2020 / Construction of 10 green houses and 2 concrete Strategic Investments and pits in pilot leskhozes Single Stage - One 2021-03- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 479,145.00 289,218.32 Signed 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-10 2020-07-22 2020-07-10 2020-08-21 2020-09-25 (Karakol, At-Bashy, Naryn, Envelope 31 Management Approaches Chuy, Talas, Toktogul,Aksy, Toskool-Ata,Uch-Korgon,Kara- Kuldzha) IFEMP/INVEST/W/NCB-2- 2020 / Construction of 21 Strategic Investments and cordon-houses of the Single Stage - One 1,028,634.5 2021-06- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 1,272,770.00 Signed 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-10 2020-07-22 2020-07-17 2020-08-21 2020-09-02 northern pilot leskhozes Envelope 6 30 Management Approaches (Talas, Karakol, Naryn, At- Bashy, Ton, Chui, Frunze) IFEMP/INVEST/W/NCB-3- 2020 / Construction of 21 cordon - houses of the Strategic Investments and Single Stage - One 2021-06- southern pilot leskhozes IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 1,023,280.00 881,799.16 Signed 2020-06-12 2020-06-17 2020-06-17 2020-06-19 2020-07-08 2020-07-10 2020-07-22 2020-08-06 2020-08-21 2020-09-18 Envelope 30 (Toktogul,Uch Korgon, Management Approaches Batken, Aksy, Kara-Kuldzha, Toskool-Ata) IFEMP/INVEST/W/NCB-7- 2020 / Construction of 4 Strategic Investments and Single Stage - One 2021-06- bridges in pilot leskhozes ( IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 198,866.00 156,900.67 Signed 2020-06-23 2020-07-14 2020-07-08 2020-07-15 2020-07-29 2020-08-05 2020-08-10 2020-08-24 2020-08-28 2020-09-07 Envelope 28 Karakol 1, Toskool Ata 1, Management Approaches Toktogul 1, Batken 1) IFEMP/INVEST/W/NCB-8- 2020 / Construction of Strategic Investments and irrigation facilities in pilot Single Stage - One 2021-06- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 556,957.00 330,368.99 Signed 2020-06-23 2020-08-26 2020-07-08 2020-08-28 2020-07-29 2020-09-18 2020-08-10 2020-11-02 2020-08-28 2020-12-10 leskhozes (Karakol, Frunze, Envelope 28 Management Approaches Uch-Korgon, Kara-Kulzha, Toktogul) IFEMP/INVEST/W/NCB-9- 2020 / Construction of power Strategic Investments and Single Stage - One 2021-06- lines and installation of TS in IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 194,893.00 164,614.28 Signed 2020-06-23 2020-08-20 2020-07-08 2020-08-21 2020-07-29 2020-09-11 2020-08-11 2020-09-25 2020-08-28 2020-10-28 Envelope 28 pilot leskhozes (Karakol, Kara- Management Approaches Kulzha) IFEMP/INVEST/W/NCB-5- Strategic Investments and 2020 / Сonstruction of Single Stage - One 2021-06- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 359,488.00 0.00 Canceled 2020-06-23 2020-08-06 2020-07-08 2020-08-06 2020-07-29 2020-08-10 2020-08-28 irrigation canals from trays in Envelope 28 Management Approaches pilot leshozes (Chui, Ton) IFEMP/INVEST/W/NCB- Strategic Investments and 5/2020 / Сonstruction of Single Stage - One 2021-07- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 420,671.00 334,399.12 Signed 2020-09-09 2020-09-22 2020-09-11 2020-09-23 2020-10-02 2020-10-14 2020-10-16 2020-10-26 2020-11-02 2020-12-01 irrigation canals from trays in Envelope 02 Management Approaches pilot leshozes (Chui, Ton) IFEMP/INVEST/W/NCB-6- 2020 / Drilling and Strategic Investments and Single Stage - One 2021-06- rehabilitation of 6 wells in IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 297,199.00 268,113.50 Signed 2020-06-23 2021-03-02 2020-06-29 2021-03-02 2020-07-08 2021-03-23 2020-07-29 2021-04-14 2020-08-28 2021-05-17 Envelope 28 pilot leskhozes (Karakol 2, Management Approaches Balykchi 4) IDA/IFEMP/W/NCB/2021/3 / Strategic Investments and Single Stage - One 2022-05- Overhaul of "Dugoba" tuoristic IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 467,282.00 406,157.36 Signed 2021-03-26 2021-03-31 2021-03-30 2021-04-02 2021-04-20 2021-04-23 2021-04-30 2021-04-29 2021-05-31 2021-05-21 Envelope 30 house Management Approaches IFEMP/INVEST/W/NCB-7/1- 2021 / R/c cattle run bridge Strategic Investments and Single Stage - One 2022-01- construction through the Kara- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 39,646.00 40,047.35 Signed 2021-03-26 2021-03-31 2021-03-30 2021-04-08 2021-04-20 2021-04-23 2021-04-30 2021-04-28 2021-05-31 2021-05-28 Envelope 01 Kol River on the territory of Management Approaches Kochkor-Ata LH (Toskool-Ata) IDA/IFEMP/LSGB/W/NCB/202 Strategic Investments and 1/5 / Consrtuction of pipeline Single Stage - One 2022-01- IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 123,954.00 117,972.75 Signed 2021-03-29 2021-03-31 2021-04-02 2021-04-02 2021-04-23 2021-04-23 2021-04-30 2021-04-28 2021-05-31 2021-05-17 and storage tanks in Dostuk Envelope 31 Management Approaches LSGB Page 2 IDA/IFEMP/W/NCB/2021/4 / Overhaul of the administrative Strategic Investments and building of Toktogul LH and Single Stage - One 2022-05- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 89,695.00 78,153.14 Signed 2021-03-26 2021-03-31 2021-03-30 2021-04-02 2021-04-20 2021-04-23 2021-04-30 2021-04-28 2021-05-31 2021-05-28 construction of a canopy box Envelope 30 Management Approaches for equipment in Kara- Kuldzha LH IDA/IFEMP/W/NCB/2021/2 / Strategic Investments and Single Stage - One 2022-05- Construction of administrative IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 251,600.00 198,424.12 Signed 2021-03-26 2021-03-31 2021-03-30 2021-04-02 2021-04-20 2021-04-23 2021-04-30 2021-04-28 2021-05-31 2021-05-28 Envelope 30 building of Chuy leskhoze Management Approaches IDA/IFEMP/W/NCB/2021/1 / Strategic Investments and Construction of refrigerating Single Stage - One 2022-02- IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 964,336.00 939,074.07 Signed 2021-03-05 2021-03-31 2021-03-12 2021-04-02 2021-04-02 2021-04-23 2021-04-12 2021-04-28 2021-04-27 2021-05-28 chambers and processing Envelope 28 Management Approaches shops GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP-SH-COMPS-005- 2018 / Procurement of Computers and office equipment as a support of Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Limited 22,000.00 20,997.94 Completed 2018-03-19 2018-04-30 2018-05-08 2018-05-30 2018-05-28 Joint Forest Management Reform Quotations Envelope Council (JFMC) and Consultative and Coordination Council (CCC) KG-IFEMP-SH-FURNITURE- 003-2018 / Office furniture as a support of Joint Forest Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Limited 4,000.00 0.00 Canceled 2018-03-19 2018-04-23 2018-05-23 Management Council (JFMC) Reform Quotations Envelope and Consultative Coordination Council (CCC) IFMP-SH-PRINT-004-2018 / Forest Sector Institutional Request for Single Stage - One Information Board in pilot IDA / D0950 Post Open - National 8,500.00 2,804.09 Completed 2018-08-03 2018-09-12 2018-08-28 2018-10-08 2018-09-24 Reform Quotations Envelope leskhozes IFMP-SH-FURNITURE-005/1- Forest Sector Institutional Request for Single Stage - One 2018 / Support CCC and JFMC IDA / D0950 Post Open - National 10,080.00 4,024.56 Completed 2018-08-08 2018-08-28 2018-08-28 2018-09-28 2018-09-24 Reform Quotations Envelope (office furniture) IFMP-SH-PRINT-005-2018 / Forest Sector Institutional Request for Single Stage - One Information poster in pilot IDA / D0950 Post Open - National 5,000.00 3,708.51 Completed 2018-08-17 2018-09-21 2018-09-10 2018-10-21 2018-10-31 Reform Quotations Envelope leskhozes IFEMP-SH-COMPS-001-2017 Project Management, Request for Single Stage - One IDA / D0950 Post Limited 7,200.00 8,071.60 Completed 2017-06-05 2017-06-15 2017-07-02 2017-07-06 2017-07-27 2017-11-30 / Computers for PCU Monitoring and Evaluation Quotations Envelope IFEMP-SH-VEHICLE-004- Project Management, Request for Single Stage - One IDA / D0950 Post Limited 80,000.00 80,790.33 Completed 2017-06-26 2017-06-30 2017-07-31 2017-08-07 2017-08-30 2017-08-28 2017 / Car for PCU Monitoring and Evaluation Quotations Envelope KG-IFEMP-SH-MNE-005- 2018 / Server for the Project Management, Request for Single Stage - One development of IFEMP IDA / D0950 Post Open - National 2,000.00 3,684.59 Completed 2018-09-24 2018-10-18 2018-09-10 2018-11-18 2018-10-25 Monitoring and Evaluation Quotations Envelope database for MnE and office equipment KG-IFEMP- SH-COMPS -007- Project Management, Request for Single Stage - One IDA / D0950 Post Open - National 10,000.00 5,317.87 Completed 2018-11-23 2018-11-30 2018-12-17 2019-01-11 2019-02-07 2018-12-31 2018 / Computers for PIU Monitoring and Evaluation Quotations Envelope IFEMP-INVEST-G-SH-5-2019 Strategic Investments and Request for Single Stage - One / Purchase of motor cultivato IDA / 57430 Piloting of Sustainable Post Open - National 18,859.00 33,012.91 Completed 2019-06-05 2019-07-08 2019-07-05 2019-08-29 2019-08-05 2019-10-08 Quotations Envelope rwith a plow and tree shovels Management Approaches IFEMP-INVEST-G-NCB-2- Strategic Investments and 2019 / Purchase of a car with Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 471,486.00 389,071.31 Completed 2019-06-13 2019-06-28 2019-06-18 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-05 2019-09-11 2019-10-07 2019-11-05 fie-fighting equipment (MLPK) Envelope Management Approaches for pilot leskozes IFEMP-INVEST-G-NCB-3- Strategic Investments and 2019 / Purchase of wheeled Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 537,003.00 523,344.13 Completed 2019-06-11 2019-06-28 2019-06-11 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-01 2019-09-11 2019-10-07 2019-11-05 tractors with mounted Envelope Management Approaches equipment IFEMP-INVEST-G-NCB-4- Strategic Investments and 2019 / Purchase of wheeled Single Stage - One IDA / 57430 Piloting of Sustainable Post Request for Bids Open - National 124,348.00 87,142.83 Completed 2019-06-13 2019-07-05 2019-06-18 2019-07-08 2019-06-27 2019-07-24 2019-07-03 2019-08-01 2019-08-01 2019-09-11 2019-10-07 2019-11-05 mini tractors with mounted Envelope Management Approaches equipment IFEMP-SH-PRINT-010-2019 / Development and replication Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Open - National 1,500.00 616.63 Completed 2019-09-06 2019-08-30 2019-09-13 2019-09-18 2019-09-27 2019-10-01 of booklets on municipal Reform Quotations Envelope forests IFEMP-INVEST-G-SH-6-2019 Strategic Investments and / Purchase of materials for Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 21,540.00 0.00 Canceled 2019-06-05 2019-07-08 2019-08-07 fencing of 4 km in Naryn Quotations Envelope Management Approaches leskhoz KG-IFEMP-SH-02-2020 / Project Management, Request for Single Stage - One IDA / D0950 Post Open - National 4,091.00 2,989.97 Completed 2020-02-07 2020-02-06 2020-02-28 2020-03-11 2020-03-29 2020-05-21 Computer equipment for PIU Monitoring and Evaluation Quotations Envelope IFEMP-SH-03-2020 / Development and replication Forest Sector Institutional Request for Single Stage - One IDA / D0950 Post Open - National 1,000.00 0.00 Canceled 2020-03-06 2020-02-06 2020-04-01 2020-04-24 of booklets and barcodes of Reform Quotations Envelope PIU IFEMP-/INVEST/G/SH-1- Strategic Investments and Request for Single Stage - One 2020 / Beekeeping equipment IDA / D0950 Piloting of Sustainable Post Open - National 40,383.00 35,084.76 Completed 2020-03-04 2020-02-20 2020-04-06 2020-03-16 2020-05-06 2020-06-04 Quotations Envelope for At-Bashi leskhozes Management Approaches Page 3 IFEMP/INVEST/G/NCB-1- Strategic Investments and Single Stage - One 2020 / Beekeeping equipment IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 141,345.00 96,904.37 Completed 2020-02-19 2020-02-21 2020-03-04 2020-02-21 2020-03-25 2020-03-13 2020-03-31 2020-04-20 2020-04-29 2020-05-21 2020-05-29 2020-07-10 Envelope for Kara-Kuldzhinsky leskhoz Management Approaches IFEMP-/INVEST/G/SH-2- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 26,140.00 7,746.63 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2020-03-24 Quotations Envelope materials for Chuy leskhoz Management Approaches IFEMP-/INVEST/G/SH-3- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 45,810.00 21,945.12 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2021-03-16 Quotations Envelope materials for Ton leskhoz Management Approaches IFEMP-/INVEST/G/SH-4- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 6,650.00 1,912.52 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2020-03-25 Quotations Envelope materials for Karakol leskhoz Management Approaches IFEMP-/INVEST/G/SH-5- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 30,410.00 19,421.43 Signed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 Quotations Envelope materials for Naryn leskhoz Management Approaches IFEMP-/INVEST/G/SH-6- Strategic Investments and Request for Single Stage - One 2020 / Purchase of planting IDA / D0950 Piloting of Sustainable Post Open - National 7,730.00 4,937.65 Completed 2020-02-21 2020-02-21 2020-03-16 2020-03-16 2020-04-15 2021-04-26 Quotations Envelope materials for At-Bashi leskhoz Management Approaches IFEMP-/INVEST/G/SH-7- Strategic Investments and Under 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 34,210.00 10,565.21 Implementati 2020-02-21 2020-02-21 2020-03-16 2020-03-27 2020-04-15 2020-11-23 materials for Toktogul Quotations Envelope Management Approaches on leskhoz IFEMP/INVEST/LSGB/G/NCB/- Strategic Investments and Single Stage - One 1-2020 / Special technique IDA / D0950 Piloting of Sustainable Post Request for Bids Open - National 226,274.00 188,632.49 Completed 2020-05-01 2020-05-12 2020-05-08 2020-05-15 2020-05-29 2020-06-05 2020-06-05 2020-06-26 2020-07-01 2020-07-24 2020-09-01 2020-09-14 Envelope for 6 LSGB Management Approaches IFEMP-COVID-SH-1-2020 / Strategic Investments and Under Request for Single Stage - One Purchase of calcium IDA / 57430 Piloting of Sustainable Post Open - National 15,000.00 13,158.04 Implementati 2020-04-27 2020-04-30 2020-05-08 2020-05-18 2020-05-22 2020-05-18 Quotations Envelope hypochlorite (chlorine) Management Approaches on IFEMP-COVID-SH-2-2020 / Strategic Investments and Request for Single Stage - One Purchase of individual IDA / 57430 Piloting of Sustainable Post Open - National 85,000.00 66,869.52 Completed 2020-05-06 2020-05-15 2020-05-27 2020-05-26 2020-06-27 2020-07-17 Quotations Envelope protective means Management Approaches IFEMP/INVEST/M/G/SH/-1- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 55,384.00 0.00 Canceled 2020-03-27 2020-04-21 2020-05-11 materials for Cholpon Ata Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/M/G/SH/-2- Strategic Investments and 2020 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 12,637.00 0.00 Canceled 2020-03-27 2020-04-21 2020-05-11 materials for Bel Aldy Ail Quotations Envelope Management Approaches Aimak IFEMP-/INVEST/G/SH-8- Strategic Investments and 2020 / Materials and Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 29,200.00 26,462.72 Completed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 2020-10-09 equipment for drip irrigation Quotations Envelope Management Approaches system of Karakol leskhoz IFEMP-/INVEST/G/SH-9- 2020 / Materials and Strategic Investments and Request for Single Stage - One equipment for drip irrigation IDA / 57430 Piloting of Sustainable Post Open - National 96,600.00 80,652.76 Completed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 2020-09-22 Quotations Envelope system of Kara - Kuldzha Management Approaches leskhoz IFEMP-/INVEST/G/SH-10- Strategic Investments and 2020 / Materials and Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 12,250.00 11,105.48 Completed 2020-08-07 2020-08-14 2020-09-01 2020-09-04 2020-10-01 2020-10-19 equipment for drip irrigation Quotations Envelope Management Approaches system of Aksy leskhoz IFEMP/INVEST/LSGB/G/SH-1- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots of forest and IDA / D0950 Piloting of Sustainable Post Open - National 56,920.00 45,891.13 Completed 2020-08-14 2020-08-21 2020-09-10 2020-09-09 2020-10-05 2020-11-12 Quotations Envelope fruit plantations for Cholpon Management Approaches Ata Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-2- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots of forest and IDA / D0950 Piloting of Sustainable Post Open - National 27,240.00 23,898.84 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-11-17 Quotations Envelope fruit plantations for Zhany Management Approaches Zhol Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-3- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots of forest and IDA / D0950 Piloting of Sustainable Post Open - National 28,870.00 26,557.67 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-12-04 Quotations Envelope fruit plantations for Onbir Management Approaches Zhylga Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-4- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots of forest and IDA / D0950 Piloting of Sustainable Post Open - National 36,142.00 25,729.36 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-07 2020-10-05 2020-10-14 Quotations Envelope fruit plantations for Bel Aldy Management Approaches Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-5- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots for forest IDA / D0950 Piloting of Sustainable Post Open - National 41,247.00 31,688.34 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-11-17 Quotations Envelope and fruit plantations for Management Approaches Nichke Sai Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-6- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One for fencing plots for forest IDA / D0950 Piloting of Sustainable Post Open - National 37,705.00 29,518.64 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2021-02-22 Quotations Envelope and fruit plantations for Management Approaches Dostuk Aiyl Aymak IFEMP/INVEST/LSGB/G/SH-7- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One and equipment for drip IDA / D0950 Piloting of Sustainable Post Open - National 86,468.00 64,203.82 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-09-29 Quotations Envelope irrigation system for Zhany - Management Approaches Zhol ayil aimak Page 4 IFEMP/INVEST/LSGB/G/SH-9- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One and equipment for a drip IDA / D0950 Piloting of Sustainable Post Open - National 47,930.00 38,263.85 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-11-12 Quotations Envelope irrigation system for Cholpon- Management Approaches Ata aiyl aimak IFEMP/INVEST/LSGB/G/SH-10- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One and equipment for drip IDA / D0950 Piloting of Sustainable Post Open - National 52,954.00 42,411.86 Completed 2020-08-14 2020-08-21 2020-09-11 2020-09-09 2020-10-05 2020-09-29 Quotations Envelope irrigation system for Nichke - Management Approaches Sai aiyl aimak IFEMP/INVEST/LSGB/G/SH-8- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One and equipment for drip IDA / D0950 Piloting of Sustainable Post Open - National 68,958.00 52,133.85 Completed 2020-08-14 2020-08-28 2020-09-11 2020-09-21 2020-10-05 2020-11-12 Quotations Envelope irrigation system for Onbir - Management Approaches Zhilga ayil aimak IFEMP/INVEST/LSGB/G/SH-11- 2020 / Purchase of materials Strategic Investments and Request for Single Stage - One and equipment for a drip IDA / D0950 Piloting of Sustainable Post Open - National 79,258.00 51,417.57 Completed 2020-09-04 2020-09-09 2020-09-18 2020-10-01 2020-10-08 2020-11-12 Quotations Envelope irrigation system for Bel-Aldy Management Approaches aiyl aimak IFEMP/INVEST/LSGB/G/SH- 1/1/2021 / Purchase of Strategic Investments and materials for fencing plots for Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 1,720.00 1,607.98 Completed 2021-01-13 2021-01-22 2021-01-26 2021-03-12 2021-02-15 2021-03-19 forest and fruit plantations for Quotations Envelope Management Approaches Cholpon Ata Aiyl Aymak (Imerilish Plot) IFEMP/INVEST/LSGB/G/SH- 5/2/2021 / Purchase of Strategic Investments and materials for fencing plots for Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 4,700.00 4,465.98 Completed 2021-01-13 2021-01-21 2021-01-26 2021-03-12 2021-02-15 2021-03-19 forest and fruit plantations for Quotations Envelope Management Approaches Nichke Sai Aiyl Aymak (Chylpakai plot) IFEMP/INVEST/LSGB/G/SH/-1- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 32,807.00 19,214.61 Signed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 materials for Cholpon Ata Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/LSGB/G/SH/-2- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 64,748.00 36,229.27 Completed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 2021-03-19 materials for Bel Aldy Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/LSGB/G/SH/-3- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 14,150.00 5,005.47 Completed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 2021-03-30 materials for Zhany Zhol Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/LSGB/G/SH/-5- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 37,875.00 37,594.10 Signed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 materials for Dostuk Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/LSGB/G/SH/-6- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 34,016.00 18,873.41 Completed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 2021-03-19 materials for Nichke Sai Ail Quotations Envelope Management Approaches Aimak IFEMP/INVEST/LSGB/G/SH/-4- Strategic Investments and 2021 / Purchase of planting Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 50,475.00 21,337.51 Signed 2021-02-19 2021-02-15 2021-03-05 2021-03-09 2021-03-22 materials for Onbir Zhylga Ail Quotations Envelope Management Approaches Aimak IDA/IFEMP/G/SH/COVID/5/20 Strategic Investments and 21 / Purchase of planting Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 18,840.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 material for vulnerable layers Quotations Envelope Management Approaches in pilot zone of Chui leskhoz IDA/IFEMP/G/SH/COVID/6/20 21 / Purchase of planting Strategic Investments and Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 22,647.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of Frunze Management Approaches leskhoz IDA/IFEMP/G/SH/COVID/7/20 21 / Purchase of planting Strategic Investments and Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 11,469.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of Balykchy Management Approaches leskhoz IDA/IFEMP/G/SH/COVID/8/20 21 / Purchase of planting Strategic Investments and Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 34,407.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of Kara-Kuldzha Management Approaches leskhoz IDA/IFEMP/G/SH/COVID/9/20 21 / Purchase of planting Strategic Investments and Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 26,761.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 Quotations Envelope in pilot zone of Toktogul Management Approaches leskhoz IDA/IFEMP/G/SH/COVID/13/2 Strategic Investments and 021 / Purchase of planting Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 15,292.00 0.00 Canceled 2021-02-20 2021-03-02 2021-03-12 2021-03-29 material for vulnerable layers Quotations Envelope Management Approaches in pilot zone of Aksy leskhoz IDA/IFEMP/G/SH/2021/1 / Strategic Investments and Purchase of planting materials Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Open - National 13,894.00 8,030.57 Completed 2021-03-05 2021-03-10 2021-03-16 2021-03-29 2021-04-19 2021-04-15 to promote natural forest Quotations Envelope Management Approaches regeneration (At-Bashi, Naryn) IDA/IFEMP/MP/SH/2021/1 / Fencing forest crops (2 ha) on Strategic Investments and Pending Request for Single Stage - One the site of Kapchygai, of Kara- IDA / D0950 Piloting of Sustainable Post Limited 3,220.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Quotations Envelope Zhygach Ayil Aimak, of Management Approaches on AksyLH Page 5 IDA/IFEMP/MP/SH/2021/2 / Strategic Investments and Pending Fencing of forest crops (2 ha) Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 3,305.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 on Ak-Tiken site of , of Ak- Quotations Envelope Management Approaches on Zhol Ayil Aimak of Aksy LH IDA/IFEMP/MP/SH/2021/3 / Strategic Investments and Pending Development of beekeeping in Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 3,965.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Zhany-Zhol village of Zhany- Quotations Envelope Management Approaches on Zhol Ayil Aimak of Aksy LH IDA/IFEMP/MP/SH/2021/4 / Strategic Investments and Pending Development of beekeeping in Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 3,205.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Kosh-Dobo village of Kosh- Quotations Envelope Management Approaches on Dobo Ayil Aimak of Aksy LH IDA/IFEMP/MP/SH/2021/5 / Strategic Investments and Pending Restoration of apple orchards Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 12,165.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 of subsidiary farm of Bel-Aldy Quotations Envelope Management Approaches on Ayil Aimak of Toktogul LH IDA/IFEMP/MP/SH/2021/6 / Strategic Investments and Pending Creation of an orchard in Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 16,282.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Dostuk Ayil Aimak of Kochkor- Quotations Envelope Management Approaches on Ata LH IDA/IFEMP/MP/SH/2021/7 / Strategic Investments and Pending Development of beekeeping in Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 4,250.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Tunuk-Say village of Dari Ayil Quotations Envelope Management Approaches on Aimak of Batken LH IDA/IFEMP/MP/SH/2021/8 / Organizing of intensive Strategic Investments and Pending Request for Single Stage - One garden in Buzhum village of IDA / D0950 Piloting of Sustainable Post Limited 8,225.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Quotations Envelope Kara-Bulak Aiyl Aimak of Management Approaches on Batken LH IDA/IFEMP/MP/SH/2021/9 / Fencing of 2.65 ha land to Strategic Investments and Pending Request for Single Stage - One create a fruit-bearing orchard IDA / D0950 Piloting of Sustainable Post Limited 2,910.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Quotations Envelope on the territory of the Kur-Sai Management Approaches on site of Kara-Kulzha AO IDA/IFEMP/MP/SH/2021/10 / Planting of coniferous trees Strategic Investments and Pending and currants on the square of Request for Single Stage - One IDA / D0950 Piloting of Sustainable Post Limited 4,180.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 2 ha on the site of Konur- Quotations Envelope Management Approaches on Dobo, village Chet-Nur, Naryn LH IDA/IFEMP/MP/SH/2021/11 / Strategic Investments and Under Request for Single Stage - One Barbed wire fencing of the IDA / D0950 Piloting of Sustainable Post Limited 7,590.00 0.00 Implementati 2021-08-10 2021-09-01 2021-09-20 Quotations Envelope orchard (35 ha.) Balykchy LH Management Approaches on IDA/IFEMP/G/SH/COVID/2021 /3 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 30,408.00 0.00 Implementati 2021-09-29 2021-10-18 2021-11-18 Quotations Envelope in pilot zone of Kara-Kuldzha Management Approaches on leskhoz IDA/IFEMP/G/SH/COVID/2021 /4 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 14,725.00 0.00 Implementati 2021-09-29 2021-10-18 2021-11-18 Quotations Envelope in pilot zone of Toktogul Management Approaches on leskhoz IDA/IFEMP/G/SH/COVID/2021 Strategic Investments and Pending /5 / Purchase of planting Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 6,683.00 0.00 Implementati 2021-09-29 2021-10-18 2021-11-18 material for vulnerable layers Quotations Envelope Management Approaches on in pilot zone of Aksy leskhoz IDA/IFEMP/G/SH/COVID/2021 /6 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 7,216.00 0.00 Implementati 2021-09-29 2021-10-18 2021-11-18 Quotations Envelope in pilot zone of Kochkor-Ata Management Approaches on leskhoz IDA/IFEMP/G/SH/COVID/2021 Strategic Investments and Pending /7 / Purchase of planting Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 34,216.00 0.00 Implementati 2021-09-27 2022-03-07 2022-04-07 material for vulnerable layers Quotations Envelope Management Approaches on in pilot zone of Talas leskhoz IDA/IFEMP/G/SH/COVID/2021 /8 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 41,969.00 0.00 Implementati 2021-09-27 2022-03-07 2022-04-07 Quotations Envelope in pilot zone of At-Bashy Management Approaches on leskhoz IDA/IFEMP/G/SH/COVID/2021 Strategic Investments and Pending /9 / Purchase of planting Request for Single Stage - One IDA / 57430 Piloting of Sustainable Post Open - National 26,228.00 0.00 Implementati 2021-09-27 2022-03-07 2022-04-07 material for vulnerable layers Quotations Envelope Management Approaches on in pilot zone of Naryn leskhoz IDA/IFEMP/G/SH/COVID/2021 /10 / Purchase of planting Strategic Investments and Pending Request for Single Stage - One material for vulnerable layers IDA / 57430 Piloting of Sustainable Post Open - National 10,704.00 0.00 Implementati 2021-09-27 2022-03-07 2022-04-07 Quotations Envelope in pilot zone of Karakol Management Approaches on leskhoz NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Page 6 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP- CQS-DESIGN ESTIMATES -05-2019 / Company for the development Strategic Investments and Consultant of design estimates IDA / D0950 Piloting of Sustainable Post Qualification Open - National 280,000.00 226,378.64 Completed 2019-06-19 2019-06-21 2019-07-10 2019-06-27 2019-07-12 2019-09-16 2019-08-19 2019-10-25 2019-08-23 2019-10-28 2019-11-25 2020-06-19 documetation for Management Approaches Selection bridges,greenhouses, irrigation systems KG-IFEMP- CQS-DESIGN ESTIMATES -04-2019 / Strategic Investments and Consultant Company for the development IDA / D0950 Piloting of Sustainable Post Qualification Open - National 280,000.00 210,962.72 Completed 2019-06-10 2019-06-28 2019-07-01 2019-07-15 2019-07-12 2019-09-16 2019-08-19 2019-10-25 2019-08-23 2019-10-28 2019-12-23 2020-06-19 of design estimates Management Approaches Selection documentation for cordons, drying shops and refrigerators KG-IFEMP-CQS- DES.ESTIMATES-06-2019 / Strategic Investments and Consultant Design of construction, repair IDA / D0950 Piloting of Sustainable Post Qualification Open - National 78,427.00 56,237.29 Completed 2019-11-08 2019-11-14 2019-11-29 2019-11-14 2019-12-13 2019-12-20 2019-12-20 2020-01-27 2019-12-27 2020-01-27 2020-03-06 2021-01-21 and reconstruction of pilot Management Approaches Selection leshoz facilities KG-IFEMP-CQS- DES.ESTIMATES-07-2020 / Development of design Strategic Investments and Consultant estimate documentation for IDA / D0950 Piloting of Sustainable Post Qualification Open - National 216,000.00 102,105.18 Completed 2020-02-07 2020-02-05 2020-02-28 2020-02-06 2020-03-12 2020-05-17 2020-04-09 2020-05-14 2020-04-15 2020-05-18 2020-07-22 2020-12-04 construction, repair and Management Approaches Selection reconstruction of processing shops and cold storage facilities in pilot leskhozes IFEMP-CQS-SUPERVISION-09- Strategic Investments and Consultant 2020 / Company for IDA / D0950 Piloting of Sustainable Post Qualification Open - National 150,000.00 140,943.69 Signed 2020-05-08 2020-06-23 2020-05-15 2020-07-15 2020-06-16 2020-08-17 2020-06-29 2020-09-08 2020-07-01 2020-09-10 2021-07-01 providing technical Management Approaches Selection supervision INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-IFEMP-CS-INT-FA- 01/2018 / Selection of Forest Sector Institutional individual consultant for IDA / D0950 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-05-23 2018-05-23 2018-05-24 2018-05-27 2018-12-02 Reform functional and institutional review of Kyrgyz Forestry KG-SAEPF-CS-ENV- SAFEGUARD-INDV / Selection Individual of Individual consultant Information and Monitoring IDA / 57430 Post Consultant Limited 10,000.00 44,636.68 Signed 2018-05-23 2018-05-31 2018-05-28 2018-06-01 2018-06-18 2018-06-05 2018-07-23 2018-07-06 2019-01-19 (national) for providing of and Evaluation Selection consulting services on Environmental Safeguard KG-SAEPF-CS- SOCIALSAFEGUARD-INDV / Individual Selection of Individual Information and Monitoring IDA / 57430 Post Consultant Limited 10,000.00 26,498.92 Signed 2018-05-24 2018-05-31 2018-05-29 2018-06-01 2018-06-19 2018-06-15 2018-07-24 2018-07-23 2019-01-20 consultant (national) for and Evaluation Selection providing of consulting services on Social Safeguard CS-NAT-FA-01-2018 / Selection of national Individual Forest Sector Institutional consultant for Functional IDA / D0950 Post Consultant Limited 10,000.00 5,448.81 Completed 2018-05-25 2018-05-29 2018-05-28 2018-05-30 2018-05-29 2018-06-06 2018-05-31 2018-06-14 2018-11-27 2019-01-30 Reform analyzing of Kyrgyz Forest Selection Sector KG-SAEPF-64439-CS-INDV / Selection of individual Individual consultant for functional and Forest Sector Institutional IDA / D0950 Post Consultant Limited 50,000.00 33,224.00 Completed 2018-05-29 2018-05-31 2018-06-01 2018-04-17 2018-06-04 2018-06-07 2018-06-08 2018-06-12 2018-10-16 2019-01-30 institutional review of the Reform Selection forestry sector of the Kyrgyz Republic SSS-PIUDATABASE-009/2018 / IT specialist on development of database for the Integrated Project Management, IDA / D0950 Post Direct Selection Direct 8,000.00 8,137.84 Completed 2018-07-31 2018-07-26 2018-08-03 2018-08-05 2018-08-24 2019-01-06 2019-04-30 Forest Ecosystem Monitoring and Evaluation Management Project of the Kyrgyz Republic Individual CS- CCC/JFMC-02-1/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 6,750.00 6,589.93 Completed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-2/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 6,750.00 11,748.93 Completed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 2019-10-18 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-3/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,100.00 19,413.24 Signed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-4/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,150.00 21,500.02 Signed 2018-02-12 2018-01-31 2018-03-17 2018-02-23 2018-04-09 2018-04-20 2018-05-23 2018-05-08 2019-05-08 PIU Local Focal Point Reform Selection Individual CS- CCC/JFMC-02-5/2018 / Forest Sector Institutional IDA / D0950 Post Consultant Limited 7,250.00 18,951.32 Signed 2018-02-12 2018-01-31 2018-02-17 2018-05-18 2018-04-09 2018-07-06 2018-05-23 2018-07-13 2019-05-08 PIU Local Focal Point Reform Selection SSS-RTK-03-1/2018 / Development of metodology Forest Sector Institutional IDA / D0950 Post Direct Selection Direct 10,000.00 4,985.34 Completed 2018-04-03 2018-04-04 2018-04-13 2018-04-13 2018-04-25 2018-04-25 2018-10-27 2019-06-15 of Calculation the Cost of Reform foresty works SSS-RTK-03-2/2018 / Development of metodology Forest Sector Institutional IDA / D0950 Post Direct Selection Direct 10,000.00 4,569.65 Completed 2018-04-03 2018-04-04 2018-04-13 2018-04-13 2018-04-25 2018-04-25 2018-10-27 2019-06-28 of Calculation the Cost of Reform foresty works Page 7 IC-MF-REGULATORY-012- Strategic Investments and Individual 2018 / Expert on regulatory IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 6,466.45 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-04-30 2019-12-25 status of orphan forests Management Approaches Selection IC-MF-INVENTORY-014- 2018 / Expert on forest Strategic Investments and Individual management inventory IDA / D0950 Piloting of Sustainable Post Consultant Open 3,000.00 2,873.98 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-01-31 2019-10-30 guidelines for municipal Management Approaches Selection forest IC-MF-FACILITATION-013/1- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 6,825.69 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-MF-FACILITATION-013/2- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 8,057.07 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-MF-FACILITATION-013/3- Strategic Investments and Individual 2018 / Consultants for IDA / D0950 Piloting of Sustainable Post Consultant Open 9,000.00 9,069.78 Completed 2018-09-11 2018-09-25 2018-10-12 2018-10-26 2018-10-17 2018-10-26 2018-10-31 2018-10-29 2019-03-31 2019-10-31 facilitation in municipal Management Approaches Selection forests (3 positoins) IC-FOREST CULTURES- 017/2018 / Consultant on Strategic Investments and Individual devolopment forest IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 8,836.59 Completed 2018-10-05 2018-10-10 2018-11-01 2018-11-16 2018-11-02 2018-11-16 2018-11-09 2018-11-20 2019-03-09 2019-10-10 management investment Management Approaches Selection projects IC-TECHNICAL ENGENEER- Strategic Investments and Individual 015/2018 / Technical IDA / D0950 Piloting of Sustainable Post Consultant Open 17,518.00 24,314.08 Signed 2018-10-01 2018-10-11 2018-10-26 2018-11-16 2018-10-29 2018-11-22 2018-11-05 2018-11-26 2019-11-05 engeneer for PIU Management Approaches Selection IC-FOREST CULTURES- 017/1/2018 / Short-term Strategic Investments and Individual consultant on development of IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 9,231.94 Completed 2018-10-10 2018-10-11 2018-11-01 2018-11-16 2018-11-02 2018-11-16 2018-11-09 2018-11-20 2019-02-01 2019-10-10 forest management Management Approaches Selection investments IC-FOOD-SAFETY-016-2019 Strategic Investments and Individual / Short-term consultant on IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 4,842.75 Completed 2019-07-03 2019-06-28 2019-07-25 2019-07-24 2019-07-26 2019-07-25 2019-07-31 2019-07-26 2019-11-30 2019-12-19 the organization of Management Approaches Selection processing production IC-CFTI FRUNZE -028/2019 / Short-term consultant on organizing the logistics of Strategic Investments and Individual "Center for Forest IDA / D0950 Piloting of Sustainable Post Consultant Open 3,000.00 2,143.49 Completed 2019-08-30 2019-08-27 2019-09-27 2019-10-29 2019-09-30 2019-10-29 2019-10-01 2019-10-30 2019-10-31 2019-12-25 Technologies and Management Approaches Selection Information" on the basis of the Frunze LH IC-FS.TOURISM-027/2019 / Short-term consultant on the Strategic Investments and Individual development of feasibility IDA / D0950 Piloting of Sustainable Post Consultant Open 10,000.00 5,174.09 Completed 2019-09-06 2019-09-10 2019-10-25 2019-11-01 2019-10-25 2019-11-04 2019-10-31 2019-11-06 2020-02-29 2020-04-27 studies, logistics and Management Approaches Selection organization of tourist facilities IC(NAT)-02-6-2019 / PIU Individual Forest Sector Institutional Local Focal Point in Ysyk-Kul IDA / D0950 Post Consultant Open 9,000.00 13,831.43 Signed 2019-10-25 2019-10-30 2019-11-22 2019-11-26 2019-11-25 2019-11-29 2019-12-01 2019-12-02 2020-12-01 Reform and Naryn oblast Selection IC-LSGB-029/2019 / Short- Strategic Investments and Individual term Consultant 1 for IDA / D0950 Piloting of Sustainable Post Consultant Open 4,000.00 3,650.19 Completed 2019-11-06 2019-10-29 2019-11-29 2019-11-27 2019-12-02 2019-11-29 2019-12-09 2019-12-02 2020-03-09 2020-03-02 development of projects on Management Approaches Selection restoration of LSGB IC-LSGB-030/2019 / Short- term Consultant 2 for Strategic Investments and Individual development of projects on IDA / D0950 Piloting of Sustainable Post Consultant Open 4,000.00 3,470.99 Completed 2019-11-06 2019-10-29 2019-11-29 2019-11-27 2019-12-02 2019-11-29 2019-12-09 2019-12-02 2020-03-09 2020-03-02 restoration of degraded Management Approaches Selection municipal forests IC-MAPPING-01/2020 / Strategic Investments and Individual Consultant on municipal IDA / D0950 Piloting of Sustainable Post Consultant Open 6,000.00 4,800.50 Terminated 2020-01-31 2020-02-05 2020-02-26 2020-03-04 2020-02-28 2020-03-10 2020-03-05 2020-03-11 2020-07-05 forests mapping Management Approaches Selection IC-CONST.SUPERVISION-05- Strategic Investments and Individual 2020 / Construction IDA / D0950 Piloting of Sustainable Post Consultant Open 18,000.00 13,792.24 Signed 2020-04-22 2020-04-24 2020-05-12 2020-05-21 2020-05-14 2020-06-01 2020-05-21 2020-06-01 2021-05-21 supervision consultant Management Approaches Selection IC(SSS)-EVAL.SPECIAL Strategic Investments and EQUIP.06-2020 / Technical IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 500.00 777.01 Completed 2020-04-22 2020-05-07 2020-04-30 2020-05-12 2020-05-06 2020-05-15 2020-09-06 2021-01-26 expert on special equipment Management Approaches evaluation IC(SSS)-MF-07-2020 / Strategic Investments and Consultant under sub- IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 7,000.00 5,685.86 Signed 2020-06-10 2020-06-17 2020-06-12 2020-06-26 2020-06-15 2020-07-01 2021-06-15 component 2.3 Management Approaches IC-DIS-09-2020 / Technical Supervision Consultant on the Strategic Investments and Individual installation of a drip irrigation IDA / D0950 Piloting of Sustainable Post Consultant Open 7,500.00 3,237.79 Terminated 2020-08-28 2020-09-01 2020-09-24 2020-09-30 2020-09-25 2020-10-19 2020-09-29 2020-10-21 2021-01-29 system, fencing, and other Management Approaches Selection projects of the municipality and pilot leskhozes IFEMP-COMPANY-SSS-1- 2020 / Author's supervision Strategic Investments and over the construction of IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 20,000.00 9,821.94 Signed 2020-09-22 2020-09-18 2020-09-25 2020-12-15 2020-10-03 2020-12-30 2021-06-30 cordon houses and Management Approaches greenhouses IFEMP-COMPANY-SSS-2- 2020 / Author's supervision Strategic Investments and over the construction of IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 20,000.00 8,127.26 Signed 2020-09-22 2020-10-14 2020-09-25 2020-10-22 2020-10-03 2020-12-24 2021-06-30 bridges, irrigation systems, Management Approaches power transmission lines Page 8 IC-CONST.SUPERVISION-06- Strategic Investments and Individual 2020 / Construction IDA / D0950 Piloting of Sustainable Post Consultant Open 15,000.00 11,756.15 Signed 2020-09-23 2020-09-29 2020-10-13 2020-11-05 2020-10-13 2020-11-13 2020-10-15 2020-11-16 2021-09-15 Supervision Consultant Management Approaches Selection IDA/IFEMP/CS/SSS/2021/1 / Author's supervision over the Strategic Investments and construction of processing IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 10,000.00 6,196.09 Signed 2021-04-27 2021-06-18 2021-05-14 2021-06-29 2021-06-03 2021-08-10 2022-06-03 shops and cold storage Management Approaches facilities in pilot leshozes IDA/IFEMP/CS/SSS/2021/2 / Author's supervision over the Strategic Investments and construction of facilities IDA / D0950 Piloting of Sustainable Post Direct Selection Direct 10,000.00 2,341.16 Signed 2021-06-09 2021-06-29 2021-06-29 2021-07-08 2021-07-01 2021-08-06 2022-07-01 (admimistrative offices) in Management Approaches pilot leskhozes Strategic Investments and Individual IDA/IFEMP/CS/IC/2021/1 / IDA / D0950 Piloting of Sustainable Post Consultant Open 17,000.00 11,554.02 Signed 2021-06-21 2021-06-29 2021-07-20 2021-07-29 2021-08-02 2021-08-18 2021-08-08 2021-08-20 2022-08-08 Technical Engineer Management Approaches Selection Strategic Investments and Individual IDA/IFEMP/CS/IC/2021/2 / IDA / D0950 Piloting of Sustainable Post Consultant Open 16,000.00 8,838.61 Signed 2021-06-30 2021-07-08 2021-07-22 2021-08-16 2021-07-29 2021-08-18 2021-08-02 2021-08-20 2022-08-02 Civil Engineer Management Approaches Selection Page 9