PROCUREMENT PLAN (Textual Part) Project information: Pakistan Sindh Enhancing Response to Stunting and Malnutrition (P161624) Project Implementation agency: Provincial Task Force Secretariat for AAP Date of the Procurement Plan: April 18, 2017 Period covered by this Procurement Plan: August 2, 2017- February 28 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. In order to ensure that the national market approach is aligned with NPF, assessment has been undertaken and following will be included in legal agreements Bank’s Anti-Corruption To be incorporated 1 Guidelines in legal agreements Rights for the Bank to review To be incorporated in 2 procurement documentation and legal agreements activities Request for Quotation method To be incorporated in 3 upto $ 100,000 legal agreements When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Procuremen Activity Category Estimated cost t Procurement arrangemen t for Quotation Request of IT Goods 100,000 (National) Equipment Procurement Request for Quotations Goods 50,000 of Furniture (National) Procurement Request for Quotations of Office Goods 100,000 (National) Equipment Procurement & Contract Services 100,000 Competitive Management Specialist Financial Management Services 100,000 Competitive Specialist CCT Institutional Services 100,000 Competitive Specialist PROCUREMENT Pakistan : Sindh Enhancing Response to Reduce Stunting PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2018-03-16 2021-09-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161624 GPN Date: 2017-08-17 Project Name: Sindh Enhancing Response to Reduce Stunting Loan / Credit No: IDA / 60470 S Executing Agency(ies): ocial Protection Unit WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SPU-55373-GO-RFQ / Component 2: Strengthening Office furniture and fixture for Under Key Cross-cutting Nutrition- Request for Single Stage - One CCT-health facilities in pilot IDA / 60470 Post Limited 112,382.00 0.00 Implementati 2021-02-15 2021-03-01 2021-04-18 2021-10-15 related Interventions and Quotations Envelope districts, Tharpakar and on Project Management Umarkot PK-SPU-54635-GO-RFQ / Component 2: Strengthening Under Procurement and Installation Key Cross-cutting Nutrition- Request for Single Stage - One IDA / 60470 Post Limited 76,315.00 0.00 Implementati 2020-12-25 2021-02-15 2021-02-25 2021-06-25 of Furniture & Fixture in SPSU related Interventions and Quotations Envelope on office Project Management PK-SPU-55366-GO-RFQ / Component 2: Strengthening Pending Installation of office Key Cross-cutting Nutrition- Request for Single Stage - One IDA / 60470 Post Limited 23,877.00 0.00 Implementati 2020-12-25 2021-02-19 2021-08-18 communication system for related Interventions and Quotations Envelope on SPSU Project Management PK-SPU-55374-GO-RFQ / I.T Component 2: Strengthening Under equipment for CCT- Health Key Cross-cutting Nutrition- Request for Single Stage - One IDA / 60470 Post Limited 178,861.00 0.00 Implementati 2021-02-15 2021-03-01 2021-04-18 2021-10-15 facilities in pilot districts, related Interventions and Quotations Envelope on Tharpakar & Umarkot Project Management Component 2: Strengthening PK-SPU-53539-GO-RFQ / Under Key Cross-cutting Nutrition- Request for Single Stage - One Office equipment for CCT- IDA / 60470 Post Limited 20,433.00 0.00 Implementati 2021-02-15 2021-03-01 2021-04-18 2021-10-15 related Interventions and Quotations Envelope Health facilities on Project Management Component 2: Strengthening PK-SPU-55370-GO-RFQ / Pending Key Cross-cutting Nutrition- Request for Single Stage - One Office appliances and IDA / 60470 Post Limited 25,566.00 0.00 Implementati 2021-04-20 2021-06-21 2021-12-18 related Interventions and Quotations Envelope machinery for SPSU on Project Management Component 2: Strengthening Pending PK-SPU-53516-GO-RFQ / I.T Key Cross-cutting Nutrition- Request for Single Stage - One IDA / 60470 Post Limited 36,536.00 0.00 Implementati 2021-04-20 2021-06-21 2021-12-18 equipment for SPSU office related Interventions and Quotations Envelope on Project Management Component 2: Strengthening PK-SPU-53530-GO-RFQ / Pending Key Cross-cutting Nutrition- Request for Single Stage - One Office equipment for SPSU IDA / 60470 Post Limited 61,051.00 0.00 Implementati 2021-04-20 2021-06-21 2021-12-18 related Interventions and Quotations Envelope office on Project Management Component 2: Strengthening PK-SPU-208095-GO-RFQ / Pending Key Cross-cutting Nutrition- Request for Single Stage - One Procurement of Office vehicles IDA / 60470 Post Limited 50,006.00 0.00 Implementati 2020-12-30 2021-03-02 2021-08-29 related Interventions and Quotations Envelope for SPSU on Project Management PK-SPU-247839-GO-RFB / Component 2: Strengthening Hardware & Miscellaneous Pending Key Cross-cutting Nutrition- Single Stage - One Items, Installation & IDA / 60470 Post Request for Bids Open - National 340,000.00 0.00 Implementati 2021-09-01 2021-09-05 2021-09-21 2021-09-28 2021-10-04 2021-10-18 related Interventions and Envelope Commissioning for DATA on Project Management Center NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SPU-53582-NC-RFB / Component 2: Strengthening Pending Communication material and Key Cross-cutting Nutrition- Single Stage - One IDA / 60470 Post Request for Bids Open - National 286,177.00 0.00 Implementati 2018-05-21 2018-05-26 2018-07-07 2018-08-06 2018-09-10 2019-03-09 Public Information campaign related Interventions and Envelope on (PIC) for CCT-SPU Project Management PK-SPU-211111-NC-RFB / Component 2: Strengthening Payment Service Provider for Key Cross-cutting Nutrition- Single Stage - One IDA / 60470 Post Request for Bids Open - National 187,301.00 0.01 Signed 2021-01-08 2021-03-03 2021-01-13 2021-01-29 2021-02-24 2021-03-10 2021-03-26 2021-04-26 2021-04-30 2021-06-08 2022-04-30 Health & Nutrition Conditional related Interventions and Envelope Cash Transfer (H&N CCT) Project Management PK-SPU-227873-NC-RFB / Component 2: Strengthening Payment Service Provider for Pending Key Cross-cutting Nutrition- Single Stage - One Health and Nutrition IDA / 60470 Post Request for Bids Open - National 187,301.00 0.00 Implementati 2021-04-05 2021-04-10 2021-05-22 2021-06-21 2021-07-26 2022-01-22 related Interventions and Envelope Conditional Cash Transfer (H on Project Management & N CCT) PK-SPU-251598-NC-RFQ / Component 2: Strengthening Under Baseline Survey for Impact Key Cross-cutting Nutrition- Request for Single Stage - One IDA / 60470 Post Open - National 75,000.00 0.00 Implementati 2021-09-03 2021-09-15 2021-09-17 2021-12-30 Evaluation of Pilot Health and related Interventions and Quotations Envelope on Nutrition CCT – SPSU Project Management CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Strengthening PK-SPU-53746-CS-CQS / Consultant Key Cross-cutting Nutrition- Communication and Social IDA / 60470 Post Qualification Open - National 295,716.00 0.00 Canceled 2018-04-02 2018-04-23 2018-06-06 2018-07-06 2018-08-10 2019-02-06 related Interventions and Mobilization for CCT-SPU Selection Project Management PK-SPU-59985-CS-CQS / Component 2: Strengthening Consultant Communication Strategy and Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - National 134,300.00 0.00 Canceled 2018-05-07 2018-05-14 2018-06-08 2018-07-23 2018-08-08 2020-01-30 beneficiary outreach design related Interventions and Selection for CCT-SPU Project Management PK-SPU-53760-CS-CQS / Management Information Component 2: Strengthening Consultant System for design, Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - National 372,495.00 0.00 Canceled 2018-06-20 2018-07-11 2018-08-24 2018-09-23 2018-10-28 2019-04-26 development, implementation related Interventions and Selection and grievances redressal Project Management mechanism for CCT-SPU PK-SPU-77564-CS-LCS / Management Information System for Design Component 2: Strengthening Development Implementation Key Cross-cutting Nutrition- Least Cost IDA / 60470 Post Open - National 185,154.00 0.00 Canceled 2018-09-18 2018-09-24 2018-09-27 2018-11-05 2018-11-26 2018-12-07 2019-01-09 2019-02-13 2020-08-11 and Grievances Redressal related Interventions and Selection Mechanism for Conditional Project Management Cash Transfer - Social Protection Unit PK-SPU-74539-CS-CQS / Component 2: Strengthening Consultant Communication Strategy and Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - National 143,000.00 0.00 Canceled 2018-08-27 2018-09-04 2018-09-25 2018-10-09 2018-11-23 2018-12-13 2020-05-31 beneficiary outreach design related Interventions and Selection for CCT-SPU Project Management PK-SPU-53749-CS-CQS / Component 2: Strengthening Consultant Monitoring and Evaluation, Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - National 143,088.00 0.00 Canceled 2018-12-11 2019-01-01 2019-03-22 2019-02-14 2019-03-16 2019-04-20 2019-10-17 spot checks and process related Interventions and Selection evaluation for CCT-SPU Project Management PK-SPU-207893-CS-LCS / Management Information Component 2: Strengthening System for design, Key Cross-cutting Nutrition- Least Cost IDA / 60470 Prior Open - National 502,908.00 0.00 Canceled 2020-12-10 2020-12-24 2020-12-16 2021-02-03 2021-03-10 2021-03-25 2021-04-29 2021-06-03 2022-12-02 development, implementation related Interventions and Selection and grievances redressal Project Management mechanism for CCT-SPSU PK-SPU-207914-CS-CQS / Component 2: Strengthening Consultant Communication Strategy and Key Cross-cutting Nutrition- Under IDA / 60470 Post Qualification Open - National 143,000.00 0.00 2020-12-16 2021-01-13 2020-12-23 2021-01-15 2021-02-10 2021-03-12 2021-04-10 2022-10-09 beneficiary outreach design related Interventions and Implementation Selection for CCT-SPSU Project Management Component 2: Strengthening PK-SPU-59986-CS-CQS / Consultant Key Cross-cutting Nutrition- Pending Social Mobilization, Behavioral IDA / 60470 Post Qualification Open - National 161,415.00 0.00 2018-11-12 2018-11-19 2018-12-14 2019-01-28 2019-02-14 2020-02-09 related Interventions and Implementation Change and outreach Selection Project Management PK-SPU-215298-CS-LCS / Management Information Component 2: Strengthening System for design, Key Cross-cutting Nutrition- Least Cost IDA / 60470 Post Open - National 502,908.00 0.00 Canceled 2021-01-22 2021-01-22 2021-01-25 2021-01-25 2021-03-06 2021-04-05 2021-04-20 2021-05-20 2021-06-24 2022-12-23 development, implementation related Interventions and Selection and grievances redressal Project Management mechanism for CCT-SPSU PK-SPU-54077-CS-CQS / Component 2: Strengthening Consultant Monitoring and Evaluation for Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - International 171,706.00 0.00 Canceled 2018-04-19 2018-05-10 2019-03-17 2018-06-23 2018-07-23 2018-08-27 2019-02-23 impact assessment for CCT- related Interventions and Selection SPU Project Management PK-SPU-215561-CS-LCS / Baseline Survey, Monitoring Component 2: Strengthening Consultant and Evaluation for Impact Key Cross-cutting Nutrition- Under IDA / 60470 Post Qualification Open - National 171,706.00 0.00 2021-01-28 2021-01-26 2021-01-31 2021-03-27 2021-04-16 2021-05-21 2023-12-31 Assessment for intervention related Interventions and Implementation Selection of Pilot Health & Nutrition CCT- Project Management SPSU PK-SPU-221728-CS-CQS / Management Information Component 2: Strengthening Consultant System for design, Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Limited 295,000.00 232,182.82 Signed 2021-02-27 2021-03-02 2021-03-03 2021-05-16 2021-03-23 2021-07-15 2021-04-27 2021-07-12 2022-10-26 development, implementation related Interventions and Selection and grievances redressal Project Management mechanism for CCT-SPSU PK-SPU-222329-CS-CQS / Component 2: Strengthening Consultant Monitoring and Evaluation, Key Cross-cutting Nutrition- Under IDA / 60470 Post Qualification Limited 143,088.00 0.00 2021-03-04 2021-03-08 2021-03-08 2021-03-28 2021-05-02 2022-05-02 spot checks and process related Interventions and Implementation Selection evaluation for CCT-SPSU Project Management PK-SPU-207916-CS-CQS / Component 2: Strengthening Consultant Monitoring and Evaluation, Key Cross-cutting Nutrition- IDA / 60470 Post Qualification Open - National 143,088.00 0.00 Canceled 2021-01-20 2021-01-27 2021-03-12 2021-04-11 2021-05-16 2021-11-12 spot checks and process related Interventions and Selection evaluation for CCT-SPSU Project Management PK-SPU-254415-CS-CQS / Component 2: Strengthening Hiring of a Law Firm for Consultant Key Cross-cutting Nutrition- Pending Developing the Legal IDA / 60470 Post Qualification Open - National 65,000.00 0.00 2021-09-24 2021-10-10 2021-10-20 2021-10-22 2021-10-26 2021-12-31 related Interventions and Implementation Framework for a Sindh Social Selection Project Management Protection Authority INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SPU-53590-CS-INDV / Component 2: Strengthening Individual Hiring of Sr. CCT Operations Key Cross-cutting Nutrition- IDA / 60470 Post Consultant Open 148,812.36 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 Specialist for implementation related Interventions and Selection of CCT-SPU under SERRSP Project Management Page 2 PK-SPU-55272-CS-INDV / Component 2: Strengthening Hiring of Sr. M&E, Research Individual Key Cross-cutting Nutrition- and MIS Specialist for IDA / 60470 Post Consultant Open 148,812.36 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 related Interventions and implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-55275-CS-INDV / Hiring of Social Mobilization, Component 2: Strengthening Individual Beneficiary Services and Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Open 114,471.05 0.00 2018-03-30 2018-05-18 2018-06-08 2018-09-25 2018-07-13 2019-06-30 Communication Specialist for related Interventions and Implementation Selection implementation of CCT-SPU Project Management under SERRSP PK-SPU-55293-CS-INDV / Component 2: Strengthening Individual Hiring of Payments Specialist Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Open 114,471.05 0.00 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 for implementation of CCT- related Interventions and Implementation Selection SPU under SERRSP Project Management PK-SPU-55308-CS-INDV / Component 2: Strengthening Hiring of Monitoring, Individual Key Cross-cutting Nutrition- Evaluation, Research and MIS IDA / 60470 Post Consultant Open 114,471.05 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 related Interventions and Specialist for implementation Selection Project Management of CCT-SPU under SERRSP PK-SPU-55316-CS-INDV / Component 2: Strengthening Hiring of Enrolment & Individual Key Cross-cutting Nutrition- Under Compliance Specialist for IDA / 60470 Post Consultant Open 114,471.05 0.00 2018-03-30 2018-05-18 2018-06-08 2018-10-04 2018-07-13 2019-06-30 related Interventions and Implementation implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-55319-CS-INDV / Component 2: Strengthening Hiring of Assistant Grievances Individual Key Cross-cutting Nutrition- Under Redressal Mechanism IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-03-30 2018-05-18 2018-10-04 2018-06-08 2018-10-15 2018-07-13 2019-06-30 related Interventions and Implementation Specialist for implementation Selection Project Management of CCT-SPU under SERRSP PK-SPU-55322-CS-INDV / Hiring of Assistant Component 2: Strengthening Individual Monitoring, Evaluation & Key Cross-cutting Nutrition- IDA / 60470 Post Consultant Open 64,103.79 0.00 Canceled 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 Research Specialist for related Interventions and Selection implementation of CCT-SPU Project Management under SERRSP PK-SPU-55324-CS-INDV / Component 2: Strengthening Hiring of Assistant MIS, IT & Individual Key Cross-cutting Nutrition- Under Systems Specialist for IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 related Interventions and Implementation implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-55329-CS-INDV / Component 2: Strengthening Hiring of Assistant Field Individual Key Cross-cutting Nutrition- Under Operations Specialist for IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-03-30 2018-05-18 2018-09-25 2018-06-08 2018-10-08 2018-07-13 2019-06-30 related Interventions and Implementation implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-55356-CS-INDV / Component 2: Strengthening Hiring of Assistant Field Individual Key Cross-cutting Nutrition- Under Coordinator Specialist for IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2019-06-30 related Interventions and Implementation implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-55358-CS-INDV / Component 2: Strengthening Hiring of Assistant Field Individual Key Cross-cutting Nutrition- Under Coordinator Specialist for IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-03-30 2018-05-18 2018-06-08 2018-10-08 2018-07-13 2019-06-30 related Interventions and Implementation implementation of CCT-SPU Selection Project Management under SERRSP PK-SPU-74551-CS-INDV / Sr. Component 2: Strengthening Individual CCT Operations Specialist for Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Open 148,812.36 0.00 2018-08-28 2018-10-02 2018-10-17 2018-11-21 2019-11-30 implementation of CCT-SPU related Interventions and Implementation Selection under SERRSP Project Management PK-SPU-74555-CS-INDV / Sr. Component 2: Strengthening Individual MIS Specialist for Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Open 148,812.36 0.00 2018-08-28 2018-10-02 2018-10-07 2018-11-21 2019-11-30 implementation of CCT-SPU related Interventions and Implementation Selection under SERRSP Project Management PK-SPU-84447-CS-INDV / Component 2: Strengthening Hiring of Individual Individual Key Cross-cutting Nutrition- Under Consultant for the position of IDA / 60470 Post Consultant Open 64,103.79 0.00 2018-11-02 2018-12-10 2018-12-17 2019-01-10 2020-01-09 related Interventions and Implementation Monitoring and Evaluation Selection Project Management Officer. PK-SPU-84455-CS-INDV / Component 2: Strengthening Hiring of Individual Individual Key Cross-cutting Nutrition- Under Consultant for the position of IDA / 60470 Post Consultant Open 114,471.05 0.00 2018-11-02 2018-12-17 2018-12-24 2019-01-09 2020-01-08 related Interventions and Implementation Monitoring & Evaluation Selection Project Management Specialist Component 2: Strengthening PK-SPSU-188430-CS-INDV / Individual Key Cross-cutting Nutrition- Under Research Management IDA / 60470 Post Consultant Limited 48,375.22 0.00 2020-08-28 2020-09-18 2020-09-02 2020-10-07 2020-09-23 2020-12-21 2020-10-28 2021-10-28 related Interventions and Implementation Specialist Selection Project Management Component 2: Strengthening Individual PK-SPSU-188431-CS-INDV / Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 48,375.22 26,999.11 2020-08-28 2020-09-24 2020-09-02 2020-10-15 2020-09-23 2021-01-08 2020-10-28 2021-10-28 Economic Analysis Specialist related Interventions and Implementation Selection Project Management Component 2: Strengthening Individual PK-SPSU-188432-CS-INDV / Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 48,375.22 0.00 2020-08-28 2020-09-24 2020-09-02 2020-09-23 2020-10-28 2021-10-28 Survey and Process Specialist related Interventions and Implementation Selection Project Management Component 2: Strengthening Individual PK-SPSU-188436-CS-INDV / Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 52,297.54 0.00 2020-08-28 2020-09-21 2020-09-02 2020-09-23 2020-10-28 2021-10-28 Senior MIS SPECIALIST related Interventions and Implementation Selection Project Management Component 2: Strengthening PK-SPSU-188445-CS-INDV / Individual Key Cross-cutting Nutrition- Pending Financial Management IDA / 60470 Post Consultant Limited 32,685.96 0.00 2020-08-28 2020-09-02 2020-09-23 2020-10-28 2021-10-28 related Interventions and Implementation Specialist Selection Project Management Page 3 Component 2: Strengthening Individual PK-SPSU-189053-CS-INDV / Key Cross-cutting Nutrition- IDA / 60470 Post Consultant Limited 45,760.35 19,797.62 Signed 2020-08-28 2020-09-03 2020-09-02 2020-10-09 2020-09-23 2021-02-23 2020-10-28 2021-03-19 2021-10-28 Procurement Specialist related Interventions and Selection Project Management PK-SPSU-188428-CS-INDV / Component 2: Strengthening Individual Intervention Design and Key Cross-cutting Nutrition- IDA / 60470 Post Consultant Limited 71,909.11 20,069.94 Signed 2020-09-03 2020-09-03 2020-09-08 2020-10-27 2020-09-29 2020-12-21 2020-11-03 2021-07-01 2021-11-03 Evaluation Senior Specialist – related Interventions and Selection Research Team Lead (RTL) Project Management Component 2: Strengthening Individual PK-SPU-197464-CS-INDV / Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 54,663.06 0.00 2020-10-08 2020-10-12 2020-10-23 2020-11-13 2020-12-18 2021-12-18 Social Inclusion Specialist related Interventions and Implementation Selection Project Management Component 2: Strengthening Individual PK-SPU-197470-CS-INDV / Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 54,663.06 0.00 2020-10-08 2020-10-12 2020-10-23 2020-10-09 2020-11-13 2021-01-05 2020-12-18 2021-12-18 Public Health Specialist related Interventions and Implementation Selection Project Management Component 2: Strengthening PK-SPU-200077-CS-INDV / Individual Key Cross-cutting Nutrition- Senior Specialist-Field IDA / 60470 Post Consultant Limited 67,588.46 56,864.83 Terminated 2020-11-10 2020-10-29 2020-11-15 2020-11-25 2020-12-06 2021-02-01 2021-01-10 2021-02-01 2022-01-10 related Interventions and Operation Team Lead Selection Project Management Component 2: Strengthening PK-SPU-201935-CS-INDV / Individual Key Cross-cutting Nutrition- Nutrition Programme IDA / 60470 Post Consultant Limited 45,905.71 24,756.71 Terminated 2020-11-10 2020-10-29 2020-11-15 2020-11-11 2020-12-06 2021-01-05 2021-01-10 2021-01-25 2022-01-10 related Interventions and Specialist Selection Project Management Component 2: Strengthening PK-SPU-222674-CS-INDV / Individual Key Cross-cutting Nutrition- Under Field Coordination Officer @ IDA / 60470 Post Consultant Limited 13,842.04 0.00 2021-03-05 2021-03-05 2021-03-10 2021-03-20 2021-04-09 2021-12-31 related Interventions and Implementation Umarkot for H&N CCT - SPSU Selection Project Management PK-SPU-222676-CS-INDV / Component 2: Strengthening Individual Field Coordination Officer Key Cross-cutting Nutrition- Under IDA / 60470 Post Consultant Limited 13,824.04 0.00 2021-03-05 2021-03-05 2021-03-10 2021-03-20 2021-04-09 2021-12-31 @Tharparkar for H&N CCT - related Interventions and Implementation Selection SPSU Project Management Component 2: Strengthening PK-SPU-226426-CS-INDV / Individual Key Cross-cutting Nutrition- Under Monitoring & Evaluation IDA / 60470 Post Consultant Limited 28,610.00 0.00 2021-03-26 2021-04-06 2021-03-31 2021-04-15 2021-05-20 2021-12-31 related Interventions and Implementation Specialist Selection Project Management PK-SPU-249668-CS-INDV / Component 2: Strengthening Communications and Social Individual Key Cross-cutting Nutrition- Under Mobilization Strategy for Pilot IDA / 60470 Post Consultant Limited 15,000.00 0.00 2021-09-02 2021-09-09 2021-09-07 2021-09-13 2021-09-14 2021-09-26 2021-12-30 related Interventions and Implementation Health and Nutrition CCT – Selection Project Management SPSU Page 4