Procurement Plan for P151318 (Higher Education Support Project) I. General 2. Bank’s approval Date of the procurement Plan: (Original February 2015) Revisions: September 25, 2016; May 6, 2016; June 30, 2017 3. Date of General Procurement Notice: March 25, 2017 4. Period covered by this procurement plan: Year 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Mandatory threshold to Prior Review Procurement Type of procurement use Thresholds in methods Procurement USD method in USD Works (including ≥ All contract ICB turnkey, supply & 15.000.000 with estimated installation of plant NCB < 15.000.000 cost equal or and equipment, Shopping < 200.000 above 10 and PPP) Direct contracting No threshold million ≥ All contract Goods, information ICB 3.000.000 with estimated technology and NCB < 3.000.000 cost equal or non-consulting Shopping < 100.000 above 2 services Direct contracting No threshold million 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P151318 (Higher Education Support Project) 4. Any Other Special Procurement Arrangements: Not applicable 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: This Project is implementing since 2015. This Procurement plan is only for the year 2018. 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ million Prefere (Prior / Post) nce (yes/no) 1 Summary of 3,200,000 2 No Post the NCB (Works) 2 Summary of 2,214,000 4 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Mandatory threshold to Prior Review Procurement Type of procurement use Thresholds in methods Procurement USD method in USD QCBS; QBS; FBS; All contract No threshold LCS; SSS with estimated Consultants: firms cost equal or CQS < 300.000 above 1million All contract with estimated Consultants: Competitive and No threshold cost equal or individuals SSS above 0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of number of 580,000 2 Post contracts that will be let under QCBS 2 Summary of number of 268,000 29 Post INDV contracts that will be let under other methods PROCUREMENT Mali : MALI - Higher Education Support Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-03-03 2020-01-08 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151318 GPN Date: Project Name: MALI - Higher Education Support Project Loan / Credit No: IDA / 56060, IDA / D0430 Executing Agency(ies): Higher Education Support Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CW-REF-640 / Construction Component 1: Support to de la faculté d'élevage et de Selected Public Higher Single Stage - One En cours IDA / D0430 A posteriori Appel d'offres Open - National 0.00 2018-03-12 2018-03-17 2018-04-28 2018-05-13 2018-06-17 2019-12-09 santé animale de l'Université Education Institutions Envelope d'exécution de Ségou (HEIs) CW-REF-630 / Construction Component 2: Higher Single Stage - One En cours IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2018-04-16 2018-04-21 2018-06-02 2018-07-02 2018-08-15 2019-12-08 de la DGESRS et l'AMAQ, Education System Support Envelope d'exécution GO-REF-2006 / Component 2: Higher Single Stage - One En attente Aménagement des locaux IDA / 56060 A posteriori Demande de prix Open - National 0.00 2019-03-02 2019-04-18 2019-06-17 Education System Support Envelope d'exécution pour l'équipe Maliren CW-REF-4 / Amenagement Component 1: Support to de 12 salles informatiques Selected Public Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2020-01-18 2020-03-14 2020-09-10 (IUG, FSEG, FHG) et une Education Institutions Envelope d'exécution salle de formation ISA (HEIs) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-200 / Acquisition 06 vehicules Pick up double Component 2: Higher Single Stage - One En cours IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2018-01-30 2018-02-04 2018-03-18 2018-04-02 2018-05-07 2018-08-05 cabines 4X4 pour la Education System Support Envelope d'exécution DGESRS/AMAQ et UPP, GO-REF-280 / Acquisition et installation Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 2018-08-05 d'équipements pour la Education System Support Envelope d'exécution migration du PGI au Mali GO-REF-300 / Acquisition du NOC et Operationnalisation de Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2018-01-15 2018-01-20 2018-03-03 2018-03-18 2018-04-22 2018-06-21 MALIREN et équipement Education System Support Envelope d'exécution d'interconnexion CIRN- MALIREN Component 3: Project GO-REF-10 / Mobiliers de Single Stage - One En attente IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2018-02-10 2018-03-13 2018-03-28 bureau pour le PADES Envelope d'exécution Assistance Component 3: Project GO-REF-60 / Achat de Single Stage - One En attente IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2018-01-20 2018-01-31 2018-02-15 carburant Envelope d'exécution Assistance Page 1 Component 3: Project GO-REF-70 / Réfrigérateur Single Stage - One En attente IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2018-04-28 2018-05-06 2018-05-21 Grand format Envelope d'exécution Assistance GO-REF-610 / Fourniture Component 3: Project Single Stage - One En attente et pose de climatiseurs au IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2018-03-19 2018-04-19 2018-05-04 Envelope d'exécution PADES Assistance GO-REF-2001 / Ordinateurs Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2019-07-23 2019-08-08 2019-10-07 portables et accessoires Education System Support Envelope d'exécution GO-REF-2007 / Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2019-02-28 2019-03-05 2019-04-04 2019-05-04 2019-06-17 2019-10-15 Equipements d'interconnexion Education System Support Envelope d'exécution ML-PADES-96018-GO-RFQ / Component 2: Higher Single Stage - One En attente Mobiliers de bureau pour la IDA / 56060 A posteriori Demande de prix Open - National 0.00 2019-02-11 2019-03-15 2019-03-30 Education System Support Envelope d'exécution FSEG GO-REF-50 / Acquisition de Component 1: Support to matériels divers (carte Selected Public Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2020-01-27 2020-02-28 2020-04-28 Trutzshler, Bauer, Simoreg) Education Institutions Envelope d'exécution CERFITEX (HEIs) GO-REF-51 / Acquisition d’équipements pour la Component 2: Higher Single Stage - One En attente formation en ligne + Serveur IDA / 56060 A posteriori Appel d'offres Limited 0.00 2020-01-15 2020-01-20 2020-03-02 2020-03-17 2020-04-21 2020-06-20 Education System Support Envelope d'exécution Backup PGI (serveurs, switchs, accessoires) GO-REF-52 / Acquisition d'équipements pour l'interconnexion avec Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2020-01-15 2020-01-20 2020-02-14 2020-02-29 2020-04-04 2020-06-03 MALIREN (Switch + Education System Support Envelope d'exécution onduleur+mise en place du NOC GO-REF-59 / Acquisition de matériels informatiques Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2020-01-13 2020-01-18 2020-02-22 2020-03-23 2020-04-27 2020-06-26 (ENSUP-ISA-ULSHB-USSGB- Education System Support Envelope d'exécution CERFITEX-UGP) Component 1: Support to GO-REF-55 / Achat de Selected Public Higher Single Stage - One En attente mobiliers de bureau IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2020-01-21 2020-01-26 2020-03-01 2020-04-15 2020-05-20 2020-07-19 Education Institutions Envelope d'exécution (DGESRS/AMAQ-SUP; DESA) (HEIs) Component 1: Support to GO-REF-57 / Achat Selected Public Higher Single Stage - One En attente d'équipements de laboratoire IDA / D0430 A posteriori Appel d'offres Open - National 0.00 2020-03-09 2020-03-24 2020-05-05 2020-06-04 2020-07-09 2020-10-07 Education Institutions Envelope d'exécution pour le DESA-FAMA-US (HEIs) Component 1: Support to GO-REF-58 / Acquisition Selected Public Higher Single Stage - One En attente IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2020-01-15 2020-01-20 2020-02-09 2020-02-24 2020-03-15 2020-04-29 d'un minicar (ULSHB) Education Institutions Envelope d'exécution (HEIs) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 Component 1: Support to NC-REF-140 / Location de Selected Public Higher Single Stage - One En attente véhicules pour la mobilité IDA / D0430 A posteriori Demande de prix Open - National 0.00 2018-05-06 2018-06-09 2018-06-24 Education Institutions Envelope d'exécution des consultants (HEIs) NC-REF-150 / Restauration Component 1: Support to pour l'atelier de partage des Selected Public Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-14 2018-07-23 2018-07-24 conclusions de l'évaluation Education Institutions Envelope d'exécution des indicateurs (HEIs) NC-REF-180 / Restauration de l'atelier de mise à jour Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-01-28 2018-02-16 2018-03-03 des Plan Developpmt Inst Education System Support Envelope d'exécution des IES NC-REF-210 / Restauration de l'atelier de traitement des Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-05 2018-07-28 2018-08-27 données pour la production Education System Support Envelope d'exécution de l’annuaire statistique NC-REF-240 / Restauration dans le cadre de l'atélier de Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-23 2018-08-05 2018-08-20 restitution des rapports Education System Support Envelope d'exécution d'évaluation CNH NC-REF-290 / Restauration de l'atélier de formation pour le Transfert de Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-30 2018-08-10 2018-08-25 compétences pour la prise en Education System Support Envelope d'exécution main de code source de CockTail+ (le PGI) NC-REF-30 / Abonnement à Component 2: Higher Single Stage - One En attente des revues numériques pour IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-06-16 2018-07-22 2018-08-21 Education System Support Envelope d'exécution le CIRN NC-REF-40 / Ouvrages Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-17 2018-09-11 2018-10-11 numériques pour le CIRN Education System Support Envelope d'exécution NC-REF-320 / Service Component 3: Project Single Stage - One En cours d'entretien et sécurité du IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2017-12-23 2018-01-19 2019-01-14 Envelope d'exécution siège du Projet PADES Assistance NC-REF-600 / Restauration Component 2: Higher Single Stage - One En attente de l'atelier sur la IDA / 56060 A posteriori Demande de prix Open - National 0.00 2018-07-29 2018-08-27 2018-09-11 Education System Support Envelope d'exécution methodologie de recherche NC-REF-623 / Hebergement Component 3: Project des consultants chargés de Single Stage - One En attente IDA / 56060 Management and Technical A posteriori Demande de prix Open - National 0.00 2018-02-10 2018-02-17 2018-03-04 l'évaluation à mi-parcours du Envelope d'exécution Assistance projet, ML-PADES-52123-NC-RFQ / Component 1: Support to Confection du rapport Selected Public Higher Single Stage - One En attente IDA / D0430 A posteriori Demande de prix Limited 0.00 2018-07-13 2018-08-07 2018-09-06 d'évaluation des indicateurs Education Institutions Envelope d'exécution de la 3ème année des IES (HEIs) ML-PADES-52124-NC-RFQ / Confection et Impression des Component 2: Higher Single Stage - One En attente annuaires des étudiants de l' IDA / 56060 A posteriori Demande de prix Limited 0.00 2018-07-28 2018-09-22 2018-10-22 Education System Support Envelope d'exécution Enseignement Superieur Public ML-PADES-96159-NC-RFQ / Impression de l’annuaire Component 2: Higher Single Stage - One En attente IDA / 56060 A posteriori Demande de prix Open - National 0.00 2019-10-06 2019-11-01 2019-11-17 statistique et du Rapport Education System Support Envelope d'exécution d'évaluation des indicateurs Page 3 ML-PADES-96011-NC-RFB / Component 2: Higher Single Stage - One En attente Interconnexion des réseaux IDA / 56060 A posteriori Appel d'offres Open - National 0.00 2019-02-10 2019-02-15 2019-03-17 2019-04-01 2019-05-02 2019-07-01 Education System Support Envelope d'exécution Mali-REN ML-PADES-148183-NC-RFQ / Archivage électronique des Component 3: Project Single Stage - One En attente documents financiers et des IDA / D0430 Management and Technical A posteriori Demande de prix Open - National 0.00 2020-02-02 2020-02-27 2020-05-27 Envelope d'exécution dossiers de marchés de 2015 Assistance à 2020 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-160 / Bureau Component 1: Support to Sélection fondée d'Architecture pour la Selected Public Higher Open - En cours IDA / 56060 A posteriori sur la qualité et 0.00 2018-02-15 2018-03-02 2018-03-24 2018-04-21 2018-04-28 2018-06-02 2018-07-07 2018-11-04 réalisation des etudes Education Institutions International d'exécution le coût architecturales EAM (HEIs) CS-REF-170 / Etude sur le Sélection fondée financement de l' Component 2: Higher Open - En cours IDA / 56060 A posteriori sur la qualité et 0.00 2018-01-22 2018-02-12 2018-03-13 2018-04-10 2018-04-25 2018-05-24 2018-06-28 2018-09-26 Enseignement Superieur du Education System Support International d'exécution le coût Mali CS-REF-1631 / Recrutement Component 1: Support to Sélection fondée d'un bureau pour élaborer le Selected Public Higher En cours IDA / 56060 A posteriori sur la qualité et Open - National 0.00 2019-01-23 2019-02-07 2019-03-09 2019-04-08 2019-04-28 2019-05-28 2019-06-30 2019-11-27 cursus académique de Education Institutions d'exécution le coût l'EAM (HEIs) ML-PADES-96003-CS-CQS / Sélection fondée Enquête sur le marché de Component 2: Higher sur les En cours IDA / 56060 A posteriori Open - National 0.00 2019-04-08 2019-04-23 2019-05-13 2019-05-23 2019-07-02 2019-09-30 l'emploi et la satisfaction des Education System Support qualifications des d'exécution employeurs consultants CS-REF-1661 / Recrutement Sélection fondée d'un bureau pour le contrôle Component 2: Higher sur les En attente IDA / 56060 A posteriori Open - National 0.00 2019-01-22 2019-02-06 2019-02-25 2019-03-07 2019-04-02 2020-06-25 technique de la DGESRS et Education System Support qualifications des d'exécution le DESA de l'US consultants Sélection fondée CS-REF-1611 / Evaluation Component 2: Higher sur les En attente de l’insertion professionnelle IDA / 56060 A posteriori Open - National 0.00 2019-01-22 2019-02-06 2019-02-21 2019-02-26 2019-03-16 2019-06-14 Education System Support qualifications des d'exécution des diplômés consultants CS-REF-1641 / Recrutement Component 1: Support to Sélection dans le d'un bureau pour faire les Selected Public Higher En attente IDA / 56060 A posteriori cadre d'un budget Open - National 0.00 2019-07-08 2019-07-29 2019-09-11 2019-10-09 2019-11-08 2019-12-13 2020-01-17 2020-04-16 spécifications des Education Institutions d'exécution déterminé équipements EAM (HEIs) ML-PADES-117422-CS-LCS / Recrutement d'un bureau Component 3: Project Sélection au En attente pour la réalisation de l'audit IDA / 56060 Management and Technical A posteriori Open - National 0.00 2019-06-17 2019-07-08 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-02-25 moindre coût d'exécution des états financiers 2019- Assistance 2020 et la cloture du projet. CS-REF / Evaluation finale de l'insertion professionnelle Sélection fondée des diplômés et Enquête Component 2: Higher sur les En attente IDA / 56060 A posteriori Open - National 0.00 2020-08-03 2020-08-17 2020-09-14 2020-10-14 2020-11-03 2021-02-01 finale sur le marché de Education System Support qualifications des d'exécution l'emploi et la satisfaction des consultants employeurs Page 4 CS-REF-16 / Recrutement d'un bureau pour la Component 2: Higher Sélection au En attente IDA / 56060 A posteriori Open - National 0.00 2020-07-03 2020-07-24 2020-08-12 2020-08-17 2020-08-22 2020-09-26 2020-10-31 2020-11-10 formation en audit des Education System Support moindre coût d'exécution Systèmes d'information INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-90 / Consultant Component 1: Support to pour l'évaluation des Selected Public Higher En attente IDA / 56060 A posteriori Individuel Limited 0.00 2018-03-27 2018-04-01 2018-04-06 2018-04-16 2018-05-01 indicateurs de la 3ème Education Institutions d'exécution année de l'US (HEIs) CS-REF-120 / Consultant Component 1: Support to pour faire la coordination de Selected Public Higher En attente IDA / 56060 A posteriori Individuel Limited 0.00 2018-03-27 2018-04-01 2018-04-06 2018-04-10 2018-04-25 l'évaluation des indicateurs Education Institutions d'exécution de la 3ème année des IES (HEIs) CS-REF-230 / Consultants Component 2: Higher En attente pour appuyer la Commission IDA / 56060 A posteriori Individuel Limited 0.00 2018-06-10 2018-06-15 2018-06-20 2018-07-09 2018-07-24 Education System Support d'exécution National Habilitation CS-REF-260 / Consultant Component 3: Project En attente pour opperationnaliser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-02-12 2018-02-17 2018-02-22 2018-02-26 2018-03-13 d'exécution GED Assistance CS-REF-340 / Consultant Component 3: Project En attente pour dispenser la littérature IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-01-15 2018-01-20 2018-01-25 2018-02-01 2018-02-16 d'exécution Africaine à l'ULSHB Assistance CS-REF-370 / Consultant Component 3: Project pour dispenser la En attente IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-01-05 2018-01-10 2018-01-15 2018-01-25 2018-02-09 Littérature Americaine à d'exécution Assistance l'ULSHB CS-REF-410 / Consultant Component 3: Project En attente pour dispenser la Sociologie IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-03-05 2018-03-10 2018-03-15 2018-03-22 2018-04-06 d'exécution lingustique à l'ULSHB Assistance CS-REF-420 / Consultant Component 3: Project En attente pour dispenser les finances IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-02-12 2018-02-17 2018-02-22 2018-03-04 2018-03-19 d'exécution Publiques à l'USJPB Assistance CS-REF-440 / Consultant Component 3: Project En attente pour dispenser les Droits IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-02-19 2018-02-24 2018-03-01 2018-03-11 2018-03-26 d'exécution des Affaires à l'USJPB Assistance CS-REF-460 / Consultant Component 3: Project En attente pour dispenser la Recherche IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-03-05 2018-03-10 2018-03-15 2018-03-23 2018-04-07 d'exécution Opérationnelle à l'USSGB Assistance CS-REF-530 / Consultant Component 3: Project pour dispenser En attente IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2018-06-19 2018-06-24 2018-06-29 2018-07-06 2018-07-21 l'Ecotourisme et Ecologie à d'exécution Assistance l'USSGB CS-REF-350 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-01-08 2018-01-13 2018-01-18 2018-01-22 2018-02-06 littérature Britanique à Assistance l'ULSHB Page 5 CS-REF-470 / Consultant Component 3: Project pour dispenser IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-04 2018-06-09 2018-06-14 2018-06-24 2018-07-09 l'Econometrie à l'USSGB Assistance CS-REF-360 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Open 0.00 Annulé 2018-02-05 2018-03-06 2018-03-27 2018-04-25 2018-05-05 lingustique Africaine à Assistance l'ULSHB CS-REF-270 / Consultant Component 2: Higher pour élaborer le referentiel IDA / 56060 A posteriori Individuel Limited 0.00 Annulé 2018-01-15 2018-01-20 2018-01-25 2018-02-03 2018-02-18 Education System Support de l'Assurance Qualité CS-REF-450 / Consultant Component 3: Project pour dispenser les Sciences IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-02-05 2018-02-10 2018-02-15 2018-02-25 2018-03-12 politiques à l'USJPB Assistance CS-REF-100 / Consultant Component 1: Support to pour l'évaluation des Selected Public Higher IDA / 56060 A posteriori Individuel Limited 0.00 Annulé 2018-03-27 2018-04-01 2018-04-04 2018-05-09 2018-05-24 indicateurs de la 3ème Education Institutions année de l'USTTB (HEIs) CS-REF-480 / Consultant Component 3: Project pour dispenser la micro- IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-11 2018-06-16 2018-06-21 2018-07-01 2018-07-16 economie à l'USSGB Assistance CS-REF-110 / Consultant Component 3: Project pour l'évaluation des IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-03-27 2018-04-01 2018-04-06 2018-04-16 2018-05-01 indicateurs de la 3ème Assistance année de l'IPR/IFRA CS-REF-550 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-02-15 2018-02-20 2018-02-25 2018-03-07 2018-03-22 géographie urbaine à Assistance l'USSGB CS-REF-380 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-01-15 2018-01-20 2018-01-25 2018-02-04 2018-02-19 Didactique à l'ULSHB Assistance CS-REF-400 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-02-05 2018-02-10 2018-02-15 2018-02-25 2018-03-12 Civilisation Africaine à Assistance l'ULSHB CS-REF-430 / Consultant Component 3: Project pour dispenser le Droit IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-01-08 2018-01-13 2018-01-18 2018-02-13 2018-02-28 Civil et obligations à Assistance l'USJPB CS-REF-510 / Consultant Component 3: Project pour dispenser le contrôle IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-26 2018-07-01 2018-07-06 2018-07-13 2018-08-02 de Gestion et Audit à Assistance l'USSGB CS-REF-390 / Consultant Component 3: Project pour dispenser la IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-03-05 2018-03-10 2018-03-15 2018-03-25 2018-04-09 Communication à l'ULSHB Assistance CS-REF-490 / Consultant Component 3: Project pour dispenser la macro- IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-14 2018-06-19 2018-06-24 2018-07-04 2018-07-19 économie à l'USSGB Assistance CS-REF-540 / Consultant Component 3: Project pour dispenser l'histoire IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-02-14 2018-02-19 2018-02-21 2018-02-28 2018-03-15 ancienne de l'Afrique et sur Assistance l'égyptologie à l'USSGB Page 6 CS-REF-520 / Consultant Component 3: Project pour dispenser la stratégie IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-06 2018-06-11 2018-06-16 2018-06-23 2018-07-08 d'Entreprise à l'USSGB Assistance CS-REF-500 / Consultant Component 3: Project pour dispenser le IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 Annulé 2018-06-20 2018-06-25 2018-06-30 2018-07-10 2018-07-25 Marketing à l'USSGB Assistance CS-REF-1651 / Etude sur les défis et contraintes du Component 2: Higher En attente IDA / 56060 A posteriori Individuel Limited 0.00 2019-01-25 2019-01-30 2019-02-14 2019-03-17 2019-07-15 secteur privé de Education System Support d'exécution l’enseignement supérieur CS-REF-15 / Consultant Component 3: Project En attente pour l'évaluation finale du IDA / 56060 Management and Technical A posteriori Individuel Limited 0.00 2020-09-07 2020-09-12 2020-10-03 2020-10-09 2020-10-24 d'exécution projet Assistance CS-REF-17 / Consultant pour faire le diagnostic institutionnel et Component 2: Higher En attente organisationnel du secteur de IDA / 56060 A posteriori Individuel Limited 0.00 2020-02-10 2020-02-15 2020-03-07 2020-04-11 2020-05-11 Education System Support d'exécution l'Enseignement Supérieur ainsi que la relecture des textes du sous-secteur, Page 7