Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: last approved PP on 2. Date of General Procurement Notice: June 07, 2017 3. Period covered by this procurement plan: The procurement period of project covered from year May 2016 until December 2013 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: To be updated accordingly Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) 2. NCB (Goods) 3. ICB (Works) 4. NCB (Works) 5. (Non-Consultant Services) [Add other methods if necessary] PROCUREMENT Brazil : BAHIA ROAD REHABILITATION AND MAINTENANCE PROJECT - 2ND PHASE PLAN General Information Country: Brazil Bank’s Approval Date of the Original Procurement Plan: 2017-01-19 2019-09-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147272 GPN Date: 2017-06-07 Project Name: BAHIA ROAD REHABILITATION AND MAINTENANCE PROJECT - 2ND PHASE Loan / Credit No: IBRD / 85800 Executing Agency(ies): Secretariat of Infrastructure of the State of Bahia WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-18665-CW- Component 2: Performance- RFB / Obras de Restauracao based State Highway Solicitação de Open - Single Stage - One IBRD / 85800 Prévia 23,746,003.28 Assinado 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 e Manutencao de Rodovias Rehabilitation and Propostas International Envelope Grupo I Lotes 1 e 2 Maintenance BR-SEINFRA-BA-18669-CW- Component 2: Performance- RFB / Obras de Restauracao based State Highway Solicitação de Open - Single Stage - One IBRD / 85800 Prévia 19,228,370.28 Assinado 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 e Manutencao de Rodovias Rehabilitation and Propostas International Envelope Grupo II Lotes 1 e 2 Maintenance BR-SEINFRA-BA-18670-CW- Component 2: Performance- RFB / Obras de Restauracao based State Highway Solicitação de Open - Single Stage - One IBRD / 85800 Prévia 24,922,606.76 Assinado 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 e Manutencao de Rodovias Rehabilitation and Propostas International Envelope Grupo III Lotes 1 e 2 Maintenance BR-SEINFRA-BA-18672-CW- Component 2: Performance- RFB / Obras de Restauracao based State Highway Solicitação de Open - Single Stage - One IBRD / 85800 Prévia 27,214,572.61 Assinado 2017-06-20 2017-06-25 2017-08-06 2017-09-05 2017-10-10 2018-04-08 e Manutencao de Rodovias Rehabilitation and Propostas International Envelope Grupo IV Lotes 1 e 2 Maintenance BR-SEINFRA-BA-109160-CW- Component 2: Performance- RFP / Obras de Restauração based State Highway Solicitação de Open - Single Stage - One e Manutenção de Rodovias IBRD / 85800 Prévia 0.00 Em Análise 2019-04-17 2019-04-22 2019-06-03 2019-07-03 2019-08-07 2024-08-05 Rehabilitation and Propostas International Envelope Lote 1-Grupo VI Maintenance Lote 2 - Grupo VII GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-54600-GO- RFB / Aquisição e Solicitação de Single Stage - One Implementaçã IBRD / 85800 Component 4: Road Safety Posterior Open - National 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2020-12-25 Manutencao de Etilômetros Propostas Envelope o Pendente Ativos e Passivos BR-SEINFRA-BA-55182-GO- RFB / Instalações e Solicitação de Single Stage - One Implementaçã Equipamentos de Escritório IBRD / 85800 Component 4: Road Safety Posterior Open - National 0.00 2018-03-21 2018-03-26 2018-05-07 2018-06-06 2018-07-11 2019-07-06 Propostas Envelope o Pendente para Agência-Líder em Segurança Viária Page 1 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-18633-NC- RFB / NCB Nº 001/2017 - Prestação de serviços de Levantamento de Condições de Superfície, Medições de Component 1: : Institutional Solicitação de Single Stage - One IBRD / 85800 Posterior Open - National 0.00 Cancelado 2017-06-19 2017-06-19 2017-07-18 2017-08-07 2017-09-07 2018-03-06 Deflexões Recuperáveis e Strengthening Propostas Envelope Irregularidade Longitudinal da Superfície dos pavimentos da malha rodoviária estadual pavimentada da Bahia. BR-SEINFRA-BA-54596-NC- RFP / Operacionalização do Sistema de Gestão de Pavimentos(SGP): Medição de Irregularidade (IRI), de Deflexão Recuperável (FWD) Component 1: : Institutional Solicitação de Single Stage - One Implementaçã e das Condições do IBRD / 85800 Prévia Open - National 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2023-06-13 Strengthening Propostas Envelope o Pendente Pavimento através Levantamento Visual Contínuo (LVC-DNIT PRO08/2004) ou Índice de Gravidade Global (IGG - DNIT) BR-SEINFRA-BA-55181-NC- RFP / Implantação de Component 1: : Institutional Solicitação de Single Stage - One IBRD / 85800 Posterior Open - National 693,820.49 Assinado 2018-03-21 2018-03-26 2018-05-07 2018-06-06 2018-07-11 2019-07-06 Marcos Quilométricos em Strengthening Propostas Envelope Toda Rede Pavimentada BR-SEINFRA-BA-72268-NC- Em fase de RFP / Projeto de Engenharia Component 3: Feeder Road Solicitação de Single Stage - One IBRD / 85800 Posterior Open - National 623,288.29 Implementaçã 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-08-05 para Estradas Vicinais, Improvement Propostas Envelope o Grupos 1 a 4. BR-SEINFRA-BA-54598-NC- Solicitação de Single Stage - One Implementaçã IBRD / 85800 Component 4: Road Safety Posterior Open - National 0.00 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2021-06-23 RFP / para apagar. Propostas Envelope o Pendente BR-SEINFRA-BA-133558-NC- RFB / *Georreferenciamento do ativo da faixa de domínio das rodovias, bem como Solicitação de Single Stage - One Implementaçã realização de inventário das IBRD / 85800 Component 4: Road Safety Posterior Open - National 0.00 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2023-01-04 Propostas Envelope o Pendente ocupações, estudos e inspeções em campo para assessorar sua gestão, monitoramento e fiscalização. BR-SEINFRA-BA-133688-NC- RFB / Pesquisa Domiciliar Component 1: : Institutional Solicitação de Single Stage - One Implementaçã de Campo em Trechos de IBRD / 85800 Posterior Open - National 0.00 2019-09-23 2019-09-28 2019-11-09 2019-12-09 2020-01-13 2022-12-28 Strengthening Propostas Envelope o Pendente Estradas Vicinais – Coleta de Dados BR-SEINFRA-BA-134219-NC- RFB / Disponibilização, Instalação, Operação e Solicitação de Single Stage - One Implementaçã IBRD / 85800 Component 4: Road Safety Posterior Open - National 0.00 2019-09-12 2019-09-17 2019-10-29 2019-11-28 2020-01-02 2020-06-30 Manutenção de Propostas Envelope o Pendente Equipamentos Eletrônicos de Controle de Tráfego. CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 7.179/2014 / Engineering Seleção Baseada Design and Supervision of Component 1: : Institutional Open - IBRD / 85800 Prévia na Qualidade e 1,512,085.26 Assinado Road Rehabilitation and Strengthening International Custo Maintenance Works MI - 001/2017 / Manutencao do Plano Diretor de Logistica de Transportes, Seleção Baseada visando a atualizacao do Component 1: : Institutional Open - IBRD / 85800 Prévia na Qualidade e 0.00 Cancelado 2017-06-07 2017-06-30 2017-08-13 2017-09-10 2017-10-10 2017-11-14 2017-12-19 2018-12-19 conjunto de investimentos Strengthening International Custo em infraestrutura de logistica de transportes apresentado no PDLT. BR-SEINFRA-BA-18582-CS- Component 2: Performance- QCBS / Execucao de Projeto Seleção Baseada based State Highway Open - de Engenharia e Supervisao IBRD / 85800 Prévia na Qualidade e 2,355,627.43 Assinado 2017-07-13 2017-08-03 2017-09-16 2017-10-14 2017-11-13 2017-12-18 2018-01-22 2019-01-22 Rehabilitation and International das Obras do CREMA Custo Maintenance GRUPO V BR-SEINFRA-BA-24799-CS- Component 2: Performance- QCBS / Execucao de Projeto Seleção Baseada based State Highway Open - de Engenharia e Supervisao IBRD / 85800 Prévia na Qualidade e 1,562,872.77 Assinado 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2021-02-07 Rehabilitation and International das obras do CREMA Custo Maintenance Grupo VI BR-SEINFRA-BA-24801-CS- Component 2: Performance- LCS / Execucao de Projeto based State Highway Seleção Baseada Open - de Engenharia e Supervisao IBRD / 85800 Posterior 1,352,485.88 Assinado 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2021-02-08 Rehabilitation and no Menor Custo International das Obras do CREMA Maintenance GRUPO VII BR-SEINFRA-BA-24802-CS- Component 2: Performance- LCS / Execucao de Projeto based State Highway Seleção Baseada Open - de Engenharia e Supervisao IBRD / 85800 Posterior 490,313.16 Assinado 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2018-08-23 Rehabilitation and no Menor Custo International das Obras do CREMA - Maintenance Grupo VIII BR-SEINFRA-BA-24803-CS- Seleção Baseada QCBS / Implantacao de um Component 1: : Institutional Open - Implementação IBRD / 85800 Posterior na Qualidade e 0.00 2017-09-02 2017-09-23 2017-11-06 2017-12-04 2018-01-03 2018-02-07 2018-03-14 2019-03-14 Sistema de Base de Dados Strengthening International Pendente Custo de Jazidas BR-SEINFRA-BA-24805-CS- QCBS / Suporte para Implantacao de Seleção Baseada Component 1: : Institutional Open - Implementação Reorganizacao Funcional da IBRD / 85800 Posterior na Qualidade e 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-12-08 Strengthening International Pendente Superintendencia de Custo Infraestrutura de Transportes BR-SEINFRA-BA-24809-CS- QCBS / Operacionalizacao do Seleção Baseada Sistema de Gestao de Component 1: : Institutional Open - Implementação IBRD / 85800 Posterior na Qualidade e 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-02 2018-02-01 2018-03-08 2018-04-12 2024-03-11 Pavimentos (SGP) - Suporte Strengthening International Pendente Custo para a Gestao/Atualizacao do Sistema Informatizado BR-SEINFRA-BA-24812-CS- Seleção Baseada QCBS / Estudo para Component 1: : Institutional Open - Em fase de IBRD / 85800 Posterior na Qualidade e 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Readequacao da Malha Strengthening International Implementação Custo Ferroviaria Estadual Page 3 BR-SEINFRA-BA-24819-CS- QCBS / Estudo para Seleção Baseada Component 1: : Institutional Open - Implementação Potencializacao da Ferrovia IBRD / 85800 Posterior na Qualidade e 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Strengthening International Pendente de Integracao Oeste-Leste Custo (FIOL) BR-SEINFRA-BA-24823-CS- Seleção Baseada QCBS / Estudo para Component 1: : Institutional Open - Implementação IBRD / 85800 Posterior na Qualidade e 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Potencializacao de Novos Strengthening International Pendente Custo Terminais BR-SEINFRA-BA-24831-CS- Seleção Baseada Component 1: : Institutional Open - Implementação QCBS / Estudo sobre IBRD / 85800 Posterior na Qualidade e 0.00 2017-10-01 2017-10-22 2017-12-05 2018-01-02 2018-02-01 2018-03-08 2018-04-12 2019-04-07 Strengthening International Pendente Biomassa Custo BR-SEINFRA-BA-24859-CS- Seleção Baseada QCBS / Estudo de Component 1: : Institutional Open - Implementação IBRD / 85800 Posterior na Qualidade e 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2018-12-20 Potencialidades da Faixa de Strengthening International Pendente Custo Dominio BR-SEINFRA-BA-24881-CS- QCBS / Pesquisa de Satisfacaoo dos Usuarios das Seleção Baseada Component 1: : Institutional Implementação Rodovias Estaduais com os IBRD / 85800 Posterior na Qualidade e Open - National 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2019-02-18 Strengthening Pendente Resultados a Serem Custo Publicados no Site da SEINFRA/SIT BR-SEINFRA-BA-24888-CS- QCBS / Banco de Dados Seleção Baseada sobre Seguranca Viaria e Open - Implementação IBRD / 85800 Component 4: Road Safety Prévia na Qualidade e 0.00 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2019-08-17 Sistema de Policiamento - International Pendente Custo Re-Desenvolvimento e Treinamento BR-SEINFRA-BA-24997-CS- QCBS / Estabelecimento de Planos e Documentação para Criar Agencia Lider em Segurança Viaria / Seleção Baseada Desenvolvimento de Open - Implementação IBRD / 85800 Component 4: Road Safety Posterior na Qualidade e 0.00 2018-06-05 2018-06-26 2018-08-09 2018-09-06 2018-10-06 2018-11-10 2018-12-15 2019-12-10 Estrategia de Longo Prazo International Pendente Custo para Seguranca Viaria / Monitoramento e Auditoria dos Resultados dos Programas de Segurança Viaria BR-SEINFRA-BA-25004-CS- QCBS / Treinamento em Seleção Baseada Implementação Seguranca Viaria do Pessoal IBRD / 85800 Component 4: Road Safety Posterior na Qualidade e Open - National 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-19 Pendente da SIT, Policia Rodoviaria e Custo dos Municipios BR-SEINFRA-BA-25007-CS- QCBS / Execucao Projeto para Obras Corredores-Piloto Seguranca Viaria Lote 1: BA502 (Feira de Seleção Baseada Santana a BR101) Component 5: Project Open - Implementação IBRD / 85800 Posterior na Qualidade e 0.00 2017-09-02 2017-09-23 2017-11-06 2017-12-04 2018-01-03 2018-02-07 2018-03-14 2018-07-12 Lote 2: BR420 (BR324 a Management International Pendente Custo Sao Felix) Lote 3 - BA262 (Vitoria da Conquista a Brumado) Lote 4 - BA-263(Conquista a Itambe) BR-SEINFRA-BA-25012-CS- Seleção Baseada QCBS / Programa de Component 1: : Institutional Implementação IBRD / 85800 Posterior na Qualidade e Open - National 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2021-02-08 Capacitacao da Consultoria Strengthening Pendente Custo do Pessoal da SEINFRA Page 4 BR-SEINFRA-BA-25018-CS- Seleção Baseada Component 1: : Institutional Open - Em fase de QCBS / Pesquisa Origem- IBRD / 85800 Posterior na Qualidade e 551,452.26 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2019-01-07 Strengthening International Implementação Destino Ilhéus-Itabuna Custo BR-SEINFRA-BA-25019-CS- Seleção Baseada Component 1: : Institutional Open - Implementação QCBS / Logistica Urbana IBRD / 85800 Posterior na Qualidade e 0.00 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-09 Strengthening International Pendente Ilheus-Itabuna Custo BR-SEINFRA-BA-24212-CS- Seleção Baseada QCBS / PDLT Manutencao Component 1: : Institutional Implementação IBRD / 85800 Posterior na Qualidade e Open - National 0.00 2017-08-07 2017-08-28 2017-10-11 2017-11-08 2017-12-08 2018-01-12 2018-02-16 2019-02-16 do Plano Diretor de Strengthening Pendente Custo Logistica de Transportes BR-SEINFRA-BA-24995-CS- FBS / Operacionalizacao e Seleção Baseada Component 1: : Institutional Open - Implementação Desenvolvimento do Sistema IBRD / 85800 Posterior em Orçamento 0.00 2017-08-15 2017-09-05 2017-10-19 2017-11-16 2017-12-16 2018-01-20 2018-02-24 2019-02-19 Strengthening International Pendente de Gestao de Obras de Arte Fixo Especiais BR-SEINFRA-BA-25000-CS- CQS / Auditoria / Seleção Baseada Open - Implementação Fiscalizacao para Obras dos IBRD / 85800 Component 4: Road Safety Posterior nas Qualificações 0.00 2017-11-02 2017-11-23 2018-01-06 2018-02-05 2018-03-12 2020-08-28 International Pendente Corredores-Piloto de dos Consultores Segurança Viaria BR-SEINFRA-BA-24211-CS- Seleção Baseada QCBS / PDLT Atualizacao Component 1: : Institutional Open - Em fase de IBRD / 85800 Posterior na Qualidade e 0.00 2017-08-07 2017-08-28 2017-10-11 2017-11-08 2017-12-08 2018-01-12 2018-02-16 2019-02-16 do Plano Diretor de Strengthening International Implementação Custo Logistica de Transportes BR-SEINFRA-BA-24213-CS- LCS / iRAP Levantamento, Seleção Baseada Open - Implementação IBRD / 85800 Component 4: Road Safety Posterior 0.00 2017-08-07 2017-08-28 2017-10-11 2017-11-08 2017-12-08 2018-01-12 2018-02-16 2018-08-15 Codificacao e Analise de no Menor Custo International Pendente 4200 km BR-SEINFRA-BA-32915-CS- QCBS / Supervisão Component 2: Performance- Seleção Baseada Ambiental: apoio à based State Highway Open - IBRD / 85800 Prévia na Qualidade e 1,782,839.70 Assinado 2017-10-19 2017-11-09 2017-12-23 2018-01-20 2018-02-19 2018-03-26 2018-04-30 2019-04-30 Coordenação de Meio Rehabilitation and International Custo Ambiente nas Obras de Maintenance CREMA e em Vicinais BR-SEINFRA-BA-24873-CS- CDS / Metodologia de Seleção Baseada Avaliação do Impacto Component 1: : Institutional Em fase de IBRD / 85800 Posterior na Qualidade e Open - National 0.00 2018-03-16 2018-04-06 2018-05-20 2018-06-17 2018-07-17 2018-08-21 2018-09-25 2019-09-25 Socioeconômico Provocado Strengthening Implementação Custo pelas Intervenções nas Estradas Vicinais BR-SEINFRA-BA-24854-CS- QCBS / Consultoria para Seleção Baseada Component 1: : Institutional Open - Manuais Técnicos da IBRD / 85800 Posterior na Qualidade e 0.00 Cancelado 2017-08-14 2017-09-04 2017-10-18 2017-11-15 2017-12-15 2018-01-19 2018-02-23 2024-01-23 Strengthening International Coordenacao de Meio Custo Ambiente (CMAM) BR-SEINFRA-BA-100839-CS- QCBS / Elaboração de Modelo Inter-regional de Insumo-Produto e Modelo Seleção Baseada Inter-Regional de Equilíbrio Component 1: : Institutional Em fase de IBRD / 85800 Posterior na Qualidade e Open - National 0.00 2019-02-14 2019-03-07 2019-04-20 2019-05-18 2019-06-17 2019-07-22 2019-08-26 2020-08-25 Geral Computável (IEGC) Strengthening Implementação Custo para Avaliação dos Impactos em Investimentos em Transportes no Estado da Bahia BR-SEINFRA-BA-107102-CS- Component 2: Performance- QCBS / Execução de Projeto Seleção Baseada based State Highway Open - Implementação de Engenharia e Supervisão IBRD / 85800 Prévia na Qualidade e 0.00 2019-03-31 2019-04-21 2019-06-04 2019-07-02 2019-08-01 2019-09-05 2019-10-10 2020-10-09 Rehabilitation and International Pendente das Obras do CREMA, Custo Maintenance GRUPO IV Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BR-SEINFRA-BA-25022-CS- INDV / Reforço da Diretoria Component 3: Feeder Road de Construcoes e IBRD / 85800 Posterior Individual Limited 0.00 Cancelado 2017-10-02 2017-10-07 2017-10-28 2017-12-02 2019-11-22 Improvement Manutencao - Apoio as Obras Vicinais BR-SEINFRA-BA-25023-CS- INDV / Estabelecimento do Component 1: : Institutional Implementação IBRD / 85800 Posterior Individual Open 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-06-13 Regimento do Fundo Strengthening Pendente Rodoviario BR-SEINFRA-BA-25024-CS- INDV / Reforço da Diretoria Component 3: Feeder Road IBRD / 85800 Posterior Individual Open 0.00 Cancelado 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2019-12-06 de Construcoes e Improvement Manutencao - Apoio Vicinais BR-SEINFRA-BA-25025-CS- Component 2: Performance- INDV / Biologo para Reforco based State Highway IBRD / 85800 Posterior Individual Open 73,388.15 Assinado 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2019-02-09 da Coordenacao de Meio Rehabilitation and Ambiente Maintenance BR-SEINFRA-BA-25026-CS- INDV / Estatistico para IBRD / 85800 Component 4: Road Safety Posterior Individual Open 0.00 Cancelado 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 Reforco da Diretoria de Operacoes e Trafego BR-SEINFRA-BA-25027-CS- Component 2: Performance- INDV / Auditoria Tecnica da based State Highway PPP-CREMA, apoio a IBRD / 85800 Posterior Individual Open 0.00 Cancelado 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2019-12-05 Rehabilitation and AGERBA e SEINFRA na Maintenance execucao do contrato BR-SEINFRA-BA-25028-CS- INDV / Especialista em Procedimentos e Controles Component 5: Project Internos para Reforco do IBRD / 85800 Posterior Individual Open 0.00 Cancelado 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 Management Gabinete da Superinetencia de Infraestrutura de Transportes BR-SEINFRA-BA-25029-CS- INDV / Estudo de Longo Component 1: : Institutional Implementação IBRD / 85800 Posterior Individual Open 0.00 2017-09-01 2017-10-20 2017-11-10 2017-12-15 2018-12-10 Prazo para Estruturacao do Strengthening Pendente Fundo Rodoviario BR-SEINFRA-BA-24800-CS- CDS / iRAP - Controle e Auditoria dos Processos de Seleção Direta de Implementação IBRD / 85800 Component 4: Road Safety Posterior Direct 0.00 2017-08-14 2017-08-24 2017-10-28 2018-10-23 Levantamento, Analise e Consultores Pendente Codificacao de Seguranca Viaria BR-SEINFRA-BA-54437-CS- INDV / Reforço da Component 1: : Institutional Coordenação de Meio IBRD / 85800 Posterior Individual Open 0.00 Cancelado 2018-05-07 2018-06-25 2018-07-16 2018-08-20 2019-02-16 Strengthening Ambiente (CMAM) - Manuais Técnicos Page 6 BR-SEINFRA-BA-72579-CS- INDV / Especialista em Component 2: Performance- Pavimentação para Apoio à based State Highway IBRD / 85800 Posterior Individual Open 193,329.39 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Diretoria de Projetos e Rehabilitation and Programas Especiais Maintenance (DPPE)* BR-SEINFRA-BA-72588-CS- INDV / Especialista em Component 2: Performance- Terraplanagem para Apoio à based State Highway IBRD / 85800 Posterior Individual Open 64,756.90 Concluído 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Diretoria de Projetos e Rehabilitation and Programas Especiais Maintenance (DPPE)* Component 2: Performance- BR-SEINFRA-BA-72589-CS- based State Highway INDV / Especialista em IBRD / 85800 Posterior Individual Open 54,119.12 Concluído 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Rehabilitation and Orçamento* Maintenance BR-SEINFRA-BA-72590-CS- INDV / Técnico em Apoio Component 5: Project Financeiro para a Unidade IBRD / 85800 Posterior Individual Open 25,047.53 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Management de Coordenação do Projeto (UCP)* BR-SEINFRA-BA-72594-CS- Component 2: Performance- INDV / Reforço para based State Highway Diretoria de Construção e IBRD / 85800 Posterior Individual Open 90,503.20 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2020-11-14 Rehabilitation and Manutenção (DCM) e Apoio Maintenance às Obras CREMA* BR-SEINFRA-BA-72597-CS- INDV / Apoio à Unidade de Component 3: Feeder Road Implementação Coordenação do Projeto IBRD / 85800 Posterior Individual Open 0.00 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2020-11-14 Improvement Pendente (UCP) na Gestão do Componente Vicinais* BR-SEINFRA-BA-72601-CS- INDV / Reforço da Diretoria de Construções e Component 3: Feeder Road IBRD / 85800 Posterior Individual Open 64,445.74 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Manutenção (DCM) e Apoio Improvement Obras nas Vicinais, consultor 01* BR-SEINFRA-BA-72603-CS- INDV / Reforço da Diretoria de Construções e Component 3: Feeder Road IBRD / 85800 Posterior Individual Open 58,478.54 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Manutenção e Apoio às Improvement Obras em Vicinais, Consultor 02* BR-SEINFRA-BA-72605-CS- INDV / Reforço da Diretoria de Construções e Component 3: Feeder Road IBRD / 85800 Posterior Individual Open 60,961.62 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-10 Manutenção e Apoio às Improvement Obras em Vicinais, Consultor 03* BR-SEINFRA-BA-72608-CS- INDV / Especialista em IBRD / 85800 Component 4: Road Safety Posterior Individual Open 157,016.60 Assinado 2018-08-02 2018-09-20 2018-10-11 2018-11-15 2019-11-15 Segurança Viária* BR-SEINFRA-BA-72733-CS- Component 5: Project IBRD / 85800 Posterior Individual Open 30,815.12 Concluído 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2019-11-16 INDV / Tradutor* Management Page 7 BR-SEINFRA-BA-72736-CS- INDV / Especialista em Aquisições para Reforço à Component 5: Project Unidade de Coordenação do IBRD / 85800 Posterior Individual Open 31,644.60 Rescindido 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2021-11-15 Management Projeto (UCP) e Comissão Permanente de Licitação(CPL)* BR-SEINFRA-BA-72737-CS- INDV / Especialista em Component 5: Project Implementação Procedimentos e Controles IBRD / 85800 Posterior Individual Open 0.00 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2020-11-15 Management Pendente Internos para Reforço do Gabinete da SIT* BR-SEINFRA-BA-72739-CS- INDV / Especialista em Controles de Projetos Component 5: Project Implementação Técnicos de IBRD / 85800 Posterior Individual Open 0.00 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2019-11-11 Management Pendente Engenharia(contratações e pagamentos) pra Reforço do Gabinete da SIT* BR-SEINFRA-BA-72740-CS- INDV / Especialista em Component 3: Feeder Road Implementação IBRD / 85800 Posterior Individual Open 0.00 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2019-11-11 Drenagem, para Reforço da Improvement Pendente DPPE* BR-SEINFRA-BA-72741-CS- INDV / Consultor em IBRD / 85800 Component 4: Road Safety Posterior Individual Open 36,553.78 Concluído 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2019-11-11 Segurança Viária / Gestão e Operação de Tráfego BR-SEINFRA-BA-73490-CS- Component 2: Performance- INDV / Especialista Social based State Highway IBRD / 85800 Posterior Individual Open 41,115.19 Assinado 2018-08-09 2018-09-27 2018-10-18 2018-11-22 2019-11-22 para reforço da Coordenação Rehabilitation and de Meio Ambiente (CMAM)* Maintenance BR-SEINFRA-BA-109141-CS- CDS / Reforço Técnico da Component 5: Project Seleção Direta de Em fase de IBRD / 85800 Prévia Direct 0.00 2019-04-04 2019-04-14 2019-06-18 2021-06-17 Unidade de Coordenação do Management Consultores Implementação Projeto (UCP)* BR-SEINFRA-BA-72731-CS- INDV / Reforço Técnico da Component 5: Project IBRD / 85800 Prévia Individual Open 0.00 Cancelado 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2022-11-15 Unidade de Coordenação do Management Projeto (UCP)* BR-SEINFRA-BA-86332-CS- Component 2: Performance- INDV / Auditoria Técnica da based State Highway Em fase de PPP-CREMA e apoio à IBRD / 85800 Posterior Individual Open 0.00 2018-11-08 2018-12-27 2019-01-17 2019-02-21 2021-02-10 Rehabilitation and Implementação AGERBA e SEINFRA na Maintenance Execução do Contrato BR-SEINFRA-BA-72738-CS- INDV / Elaboração de Component 1: : Institutional Manuais Técnicos em Reforço IBRD / 85800 Posterior Individual Open 0.00 Cancelado 2018-08-03 2018-09-21 2018-10-12 2018-11-16 2019-11-11 Strengthening para a Coordenação de Meio Ambiente (CMAM)* BR-SEINFRA-BA-134216-CS- INDV / Consultor para Apoio à Unidade de Component 3: Feeder Road Implementação IBRD / 85800 Posterior Individual Open 0.00 2019-09-11 2019-10-30 2019-11-20 2019-12-25 2020-12-19 Coordenação do Programa Improvement Pendente (UCP) na Gestão do Componente Vicinais Page 8